By Neville Williamson
PC, Arakulam GP
Provide the size of Check Dam Check for stability at Foundation Level
Heigth of Check Dam 1.50 m When water is upto crest level and No tail water
Top Width of Checkdam 1.00 m
Bottom Width of Checkdam 1.70 m
Length of Checkdam 5.00 m
Offset of Foundation from Check Dam 0.15 m
Depth of Foundation 0.30 m
Concrete Mix used M20
Density of Concrete 24.00 Password to edit the fie
Density of Water 10.00
Density of Saturated soil 21.00
ural Water Supply & Sanitation Agency
st Level and there is no flow downsteam Enter more details for Estimate
Estimated Amount =
As per the PWD SO
ngs of Checkdam
Report of Checkdam
C
Click here to veiw the Estimate
0.10 m
A
Wing wall Wing wall
Upstream
2.85 m
tment wall
tment wall
Upstream
Abutment wall
Abutment wall
Checkdam foundation
2.00 m
1
2
4.85 m
Down Stream B 3 B
4
A
KERALA RURAL WATER SUPPLY & SANITATION AGENCY
Name of Work : JALANIDHI PHASE II - KERALA RURAL WATER SUPPLY & SANITATION SCHEME
Scheme : JAWAHAR WATER SUPPLY SCHEME
Beneficiary Groups : JAVAHAR SUDHAJALA VITHARANA SAMITHY
Support Organization : RAJAGIRI outREACH, Kalamassery
Quantity Estimate of Check Dam
Sl No. Description No. Length Breadth Depth Quantity Unit Remark
1 Putting up Ring bund for a
height of 2m width 2.5m at
bottom and 1m at top using
earth filled bags placing in
layer as headers and top layer as
stretchers …etc complete
30 x 1 - - - 30.00 days
Quantity 30.00 days
3 Earth work excavation in all
classes of soil and depositing on
bank with initial lead upto 50m
and lift including all labour
charges etc. complete.
Berm Cutting
R/S 1x1 10.00 1.50 3.00 45.00 m3
L/S 1x1 10.00 2.00 3.00 60.00 m3
River bed (dam, walls & apron) 1 x 1 7.70 9.70 0.10 7.47 m3
Wing walls on u/s side 2x1 1.50 1.50 0.75 3.38 m3
Wing walls on d/s side 2x1 1.50 1.50 0.50 2.25 m3
Quantity 118.10 m3
4 Chiscelling in hard rock
measured in solid and
depositing and stacking
materials for measurment within
initial lead and lift etc complete.
Front View
Section A - A
Section B - B
Stability Check
1 Maximum Flood Discharge Qa 1
3 River Width Rw 5
5 Average Bed Level ABL 99.500
6 Bottom Level of Weir/Check Dam WBL 99.000
8 Maximum Flood Level MFL 100.300
9 Height Of Check Dam Ht 1.5
10 Top Width Of Weir a 1
11 Offset of Foundation from Check Dam Ot 0.15
13 Density of Saturated soil ɤs 21.00
14 Density of Concrete ɤc 24.00
15 Density of Water ɤw 10.00
17 Afflux Afx 0.5
18 Retrogression Ret
19 Acceleration Due To Gravity g 9.81
20 Mix ratio of Concrete M20
21 Discharge Per Unit Width q = Qa/Rw 0.200
22 Average Depth of Flow d = MFL - ABL 0.800
23 Velocity of Flow v = q/d 0.250
24 Velocity Head hd = v²/2g 0.003
25 Crest Level CrL = WBL + Ht 100.500
26 Downstream Total Energy Line Ds TEL = MFL + hd 100.303
28 Upstream Total Energy Line Us TEL = Ds TEL + Afx 100.803
29 Upstream Water Level UWL = Us TEL - hd 100.800
30 Depth of Flow Over Weir H = UWL - CrL 0.300
33 Under maximum flow condition Depth of flow over the weir 0.3
34 Depth of water in the downstream H2 = H+Ht-Afx-Ret 1.300
35 Constant K = H/H2 0.231
36 Depth of flow over the crest when tail water is at crest level Htw = K Ht 0.347
1 Check for Stability at Bed Level (When the u/s water is at Crest Level and there is no flow downsteam)
a=1
3 Ht = 1.5 1
b = 1.7
Ht = 1.5
2 Bed Level
O
b = 1.7
5
3 Htw = 0.347
Ht = 1.5 1
2 5
WP Bed Level
O WP
b = 1.7
3 Check for Stability at Foundation Level (When water is upto crest level and No tail water)
Top width, a = 1.000 m
Bottom width, b = 1.700 m
Height of checkdam, Ht = 1.500 m
Density of Concrete, ɤc = 24.00 KN/m³
Density of Water, ɤw = 10.00 KN/m³
Density of Silt, ɤs = 21.000 KN/m³
Offset of Foundation, Ot = 0.150 m
Depth of Foundation, Df = 0.300 m
Rankies coeff. of Active Earth Pressure, Ka = 0.333
a=1
4 Crest Level
b + (2 x Ot) = 2
Ht = 1.5 7 1
Df = 0.3
Ot = 0.15
2 Ot = 0.15
6
5 Df = 0.3 3 O
b = 1.7
b + (2 x Ot) = 2