"MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO,
PROVINCIA DE CUTERVO- CAJAMARCA" (SEGUNDA ETAPA)
CO N C E P T O MONTO (S/.)
Amortizaciones : S/. -
. Del Adelanto Directo 0.00
. Del Adelanto de Materiales 0.00
Otros :
. Retencion por Retraso en la Obra S/. -
. Multas S/. -
"MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALAB
OBRA: ETAPA)
MUNICIPALIDAD PROVINCIAL DE
ENTIDAD: MODALIDAD:
CUTERVO
CONTRATISTA: CONSORCIO "SALABAMBA" PLAZO DE EJECUCION:
UBICACIÓN: C.P. SALABAMBA, DISTRITO Y PROVINCIA CUTERVO, REGION CAJAMARCA MONTO REF. INC. IGV:
FECHA: DICIEMBRE 2018 MONTO CONTRATADO:
RESIDENTE DE OBRA:
INSPECTOR:
REAJUSTES (R)
VALORIZACIÓN N° 01 S/. -
TOTAL REAJUSTES S/. -
AMORTIZACIONES (A)
AMORTIZACION ADELANTO DIRECTO S/. -
AMORTIZACION ADELANTO DE MATERIALES S/. -
TOTAL AMORTIZACIONES S/. -
"MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALAB
OBRA: ETAPA)
MUNICIPALIDAD PROVINCIAL DE
ENTIDAD: MODALIDAD:
CUTERVO
CONTRATISTA: CONSORCIO "SALABAMBA" PLAZO DE EJECUCION:
UBICACIÓN: C.P. SALABAMBA, DISTRITO Y PROVINCIA CUTERVO, REGION CAJAMARCA MONTO REF. INC. IGV:
FECHA: DICIEMBRE 2018 MONTO CONTRATADO:
RESIDENTE DE OBRA:
INSPECTOR:
NUMERO DE VALORIZACIONES 4
DE ACUERDO A LEY EL % DE GARANTIA POR FIEL CUMPLIMIENTO SE DEBE REALIZAR EN LAS DOS
PRIMERAS VALORIZACIONES (4/2)
% DE LA GARANTIA QUE LE CORRESPONDE A LA PRIMERA VALORIZACION 0.00%
RETENCIÓN DEL 10% POR GARANTÍA DE FIEL CUMPLIMIENTO: 0.00
RETENCIÓN POR GARANTÍA DE FIEL CUMPLIMIENTO (PRIMERA VALORIZACION): 0.00
A Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCIA DE CUTERVO- CAJAMARCA" (SEGUNDA
ETAPA)
DAD: SUMA ALZADA
E EJECUCION: 28 DIAS CALENDARIOS
REF. INC. IGV: S/. 75,428.14
S/. 75,428.14
Ing. LUIS A. VALLEJOS BURGA
OR: Ing. ANDRES A. ACOSTA CORONEL
ACUMULADO SALDO
ACUM. ACTUAL (%) MONTO %
A Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCIA DE CUTERVO- CAJAMARCA" (SEGUNDA
ETAPA)
DAD: SUMA ALZADA
E EJECUCION: 28 DIAS CALENDARIOS
REF. INC. IGV: S/. 75,428.14
S/. 75,428.14
Ing. LUIS A. VALLEJOS BURGA
OR: Ing. ANDRES A. ACOSTA CORONEL
ACUMULADO SALDO
3.3. RESUMEN DE METRADOS EJECUTADOS
"MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PRO
OBRA: (SEGUNDA ETAPA)
ENTIDAD: MUNICIPALIDAD PROVINCIAL DE CUTERVO MODALIDAD: SUMA ALZADA
CONTRATISTA:CONSORCIO "SALABAMBA" PLAZO DE EJECUCION: 28 DIAS CALENDARIOS
UBICACIÓN: C.P. SALABAMBA, DISTRITO Y PROVINCIA CUTERVO, REGION CAJAMARCA MONTO REF. INC. IGV: S/. 75,428.14
FECHA: DICIEMBRE 2018 MONTO CONTRATADO: S/. 75,428.14
RESIDENTE DE OBRA: Ing. LUIS A. VALLEJOS BURGA
INSPECTOR: Ing. ANDRES A. ACOSTA CORONEL
RESUMEN DE METRADOS
EJECUTADOS
TOTAL VAL. N°1 VAL. N°2
RESUMEN DE METRADOS
EJECUTADOS
TOTAL VAL. N°1 VAL. N°2
RESUMEN DE METRADOS
EJECUTADOS
TOTAL VAL. N°1 VAL. N°2
RESUMEN DE METRADOS
EJECUTADOS
TOTAL VAL. N°1 VAL. N°2
ACUMULADO SALDO
METRADO METRADO
25.00 0.00
25.00 0.00
47.50 0.00
25.00 0.00
3.75 0.00
57.00 0.00
0.00 0.00
0.00 0.00
0.27 0.00
3.60 0.00
67.10 0.00
0.71 0.00
7.90 0.00
ETRADOS EJECUTADOS
A Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCIA DE CUTERVO- CAJAMARCA"
SEGUNDA ETAPA)
SUMA ALZADA
28 DIAS CALENDARIOS
S/. 75,428.14
S/. 75,428.14
Ing. LUIS A. VALLEJOS BURGA
Ing. ANDRES A. ACOSTA CORONEL
ACUMULADO SALDO
METRADO METRADO
121.49 0.00
0.00 0.00
28.10 0.00
11.88 0.00
1,871.24 0.00
5.00 0.00
0.00 0.00
20.70 0.00
0.00 0.00
3.00 0.00
5.25 0.00
0.00 0.00
0.00 0.00
10.35 0.00
0.00 0.00
0.00 0.00
ETRADOS EJECUTADOS
A Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCIA DE CUTERVO- CAJAMARCA"
SEGUNDA ETAPA)
SUMA ALZADA
28 DIAS CALENDARIOS
S/. 75,428.14
S/. 75,428.14
Ing. LUIS A. VALLEJOS BURGA
Ing. ANDRES A. ACOSTA CORONEL
ACUMULADO SALDO
METRADO METRADO
0.00 47.15
0.00 47.15
0.00 0.00
0.00 32.97
0.00 0.00
0.00 9.45
0.00 0.00
0.00 0.00
0.00 7.42
0.00 362.39
0.00 0.00
0.00 801.34
0.00 0.00
ETRADOS EJECUTADOS
A Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCIA DE CUTERVO- CAJAMARCA"
SEGUNDA ETAPA)
SUMA ALZADA
28 DIAS CALENDARIOS
S/. 75,428.14
S/. 75,428.14
Ing. LUIS A. VALLEJOS BURGA
Ing. ANDRES A. ACOSTA CORONEL
ACUMULADO SALDO
METRADO METRADO
0.00 66.78
0.00 1,193.66
0.00 0.00
0.00 67.20
0.00 8.40
0.00 66.78
0.00 42.50
0.00 0.00
0.00 0.00
6.25 0.00
64.06 0.00
798.55 0.00
3.4. VALORIZACION DE OBRA N° 01 DEL ADI
OBRA: "MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCI
UBICACIÓN: C.P. SALABAMBA, DISTRITO Y PROVINCIA CUTERVO, REGION CAJAMARCA MONTO REF. INC. IGV: S/. 75,428.14
VALORIZ. ANTERIOR
ITEM DESCRIPCION UND METRADO P.U PARCIAL
Metrado
03 CERCO PERIMETRICO
03.01 TRABAJOS PRELIMINARES
03.01.01 LIMPIEZA DE TERRENO MANUAL m2 25.00 0.95 S/. 23.75 0.00
03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 25.00 1.00 S/. 25.00 0.00
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS EN TERRENO NORMAL m3 47.50 11.60 S/. 551.00 0.00
03.02.02 NIVELACION Y COMPACTACION DE FONDO DE ZANJAS m2 25.00 0.77 S/. 19.25 0.00
03.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO (AFIRMADO) m3 3.75 65.40 S/. 245.25 0.00
03.02.05 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 57.00 4.77 S/. 271.89 0.00
03.04 OBRAS DE CONCRETO ARMADO
03.04.03 VIGAS
03.04.03.01 VIGAS DE CIMENT.- CONC. 175 kg/cm2 m3 0.27 266.10 S/. 71.85 0.00
03.04.03.02 VIGAS.- ENCOFRADO Y DESENCOFRADO m2 3.60 28.25 S/. 101.70 0.00
03.04.03.03 VIGAS.- ACERO Fy=4200 kg/cm2 Kg 67.10 3.78 S/. 253.64 0.00
03.04.04 COLUMNAS
03.04.04.01 COLUMNAS.- CONCRETO 175 kg/cm² m3 0.71 288.71 S/. 204.98 0.00
03.04.04.02 COLUMNAS.- ENCOFRADO Y DESENCOFRADO m2 7.90 26.84 S/. 212.04 0.00
03.04.04.03 COLUMNAS.- ACERO Fy=4200 kg/cm2 Kg 121.49 3.78 S/. 459.23 0.00
03.04.05 MURO DE CONTENCION
03.04.05.01 MURO DE CONTENCION - CONCRETO f'c=210kg/cm2 m3 28.10 300.64 S/. 8,447.98 0.00
03.04.05.02 MURO DE CONTENCION - ENCOFRADO Y DESENCOFRADO (CARAVISTA) m2 11.88 31.99 S/. 380.04 0.00
03.04.05.03 MURO DE CONTENCION - ACERO f'y=4200kg/cm2 Kg 1,871.24 3.78 S/. 7,073.29 0.00
03.04.05.04 LLORADORES- TUBERIA DE DRENAJE PVC Ø2" m 5.00 15.46 S/. 77.30 0.00
3.4. VALORIZACION DE OBRA N° 01 DEL ADI
OBRA: "MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCI
UBICACIÓN: C.P. SALABAMBA, DISTRITO Y PROVINCIA CUTERVO, REGION CAJAMARCA MONTO REF. INC. IGV: S/. 75,428.14
VALORIZ. ANTERIOR
ITEM DESCRIPCION UND METRADO P.U PARCIAL
Metrado
03.05 ALBAÑILERIA
03.05.01 MURO DE LADRILLO KK SOGA 2 CARAVISTA M:1.1:4 e=1.5cm m2 20.70 97.54 S/. 2,019.08 0.00
03.06 REVOQUES Y REVESTIMIENTOS
03.06.02 TARRAJEO DE VIGAS MEZCLA C:A 1:4 1.5CM m2 3.00 30.71 S/. 92.13 0.00
03.06.03 TARRAJEO DE COLUMNAS MEZCLA C:A 1:4 1.5CM m2 5.25 19.41 S/. 101.90 0.00
03.07 PINTURA
03.07.01 PINTURA LATEX EN SOBRECIMIENTOS,VIGAS Y COLUMNAS m2 8.85 4.08 S/. 36.11 0.00
03.08 OTROS
03.08.01 JUNTA DE DILATACION CON TECNOPORT 1" m 10.35 1.26 S/. 13.04 0.00
06 GRADERIAS
06.01 TRABAJOS PRELIMINARES
06.01.01 LIMPIEZA DE TERRENO MANUAL m2 47.15 0.95 S/. 44.79 0.00
06.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 47.15 1.00 S/. 47.15 0.00
06.02 MOVIMIENTO DE TIERRAS
06.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS EN TERRENO NORMAL m3 27.48 11.60 S/. 318.77 0.00
06.02.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA m3 32.97 4.77 S/. 157.27 0.00
06.03 OBRAS DE CONCRETO SIMPLE
06.03.01 SOLADO PARA ZAPATAS e=2", 1:12 CEM/HORM m2 9.45 18.65 S/. 176.24 0.00
06.04 OBRAS DE CONCRETO ARMADO
06.04.01 ZAPATAS
06.04.01.01 ZAPATAS - CONCRETO F'c = 210 kg/cm2 m3 7.42 304.08 S/. 2,256.27 0.00
06.04.01.02 ZAPATAS - ACERO Fy=4200 kg/cm2 Kg 362.39 3.78 S/. 1,369.83 0.00
06.04.02 COLUMNAS
3.4. VALORIZACION DE OBRA N° 01 DEL ADI
OBRA: "MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE CUTERVO, PROVINCI
UBICACIÓN: C.P. SALABAMBA, DISTRITO Y PROVINCIA CUTERVO, REGION CAJAMARCA MONTO REF. INC. IGV: S/. 75,428.14
VALORIZ. ANTERIOR
ITEM DESCRIPCION UND METRADO P.U PARCIAL
Metrado
06.04.02.01 COLUMNAS - CONCRETO F'c = 210 kg/cm2 m3 7.14 363.15 S/. 2,592.89 0.00
06.04.04.02 COLUMNAS - ENCOFRADO Y DESENCOFRADO m2 56.15 26.84 S/. 1,507.07 0.00
06.04.02.03 COLUMNAS - ACERO Fy=4200 kg/cm2 Kg 801.34 3.78 S/. 3,029.07 0.00
06.04.04 GRADERIAS
06.04.04.01 GRADERIAS - CONCRETO F'c = 175 kg/cm2 m3 13.49 284.68 S/. 3,840.33 0.00
06.04.04.02 GRADERIAS ENCOFRADO Y DESENCOFRADO m2 66.78 29.71 S/. 1,984.03 0.00
06.04.04.03 GRADERIAS, ACERO Fy=4200 kg/cm2 Kg 1,193.66 3.41 S/. 4,070.38 0.00
06.05 VARIOS
06.05.01 BARANDA DE METALICA m 42.95 97.28 S/. 4,178.18 0.00
06.05.02 CANTONERA DE FIERRO EN ESCALERA m 67.20 17.20 S/. 1,155.84 0.00
06.05.03 JUNTA DE DILATACION EN GRADERIO C/MORTERO ASFALTICO m 8.40 4.96 S/. 41.66 0.00
06.05.04 TARRAJEO SEMIPULIDO EN GRADERIOS E:1" m2 66.78 15.22 S/. 1,016.39 0.00
06.05.05 PINTURA ANTICORROSIVA ESMALTE 2 MANOS EN BARANDA METALICA m 42.50 2.15 S/. 91.38 0.00
07 MURO DE CONTENCION
7.05 SARDINEL REFORZADO (ADICIONAL)TRABAJOS PRELIMINARES
07.05.01 SARDINEL - CONCRETO Fc= 210 kg/cm2 m3 6.25 313.39 S/. 1,958.69 0.00
07.05.02 ENCOFRADO Y DESENCOFRADO EN SARDINEL SOBRE MURO DE CONTENCION m2 64.06 31.99 S/. 2,049.28 0.00
07.05.03 SARDINEL - ACERO f'y=4200kg/cm2 Kg 798.55 3.78 S/. 3,018.52 0.00
COSTO DIRECTO S/. 55,584.48
UBICACIÓN: C.P. SALABAMBA, DISTRITO Y PROVINCIA CUTERVO, REGION CAJAMARCA MONTO REF. INC. IGV: S/. 75,428.14
VALORIZ. ANTERIOR
ITEM DESCRIPCION UND METRADO P.U PARCIAL
Metrado
SUB TOTAL S/. 63,922.16
% MENSUAL
% ACUMULADO
DEL ADICONAL N° 01
O, PROVINCIA DE CUTERVO- CAJAMARCA" (SEGUNDA ETAPA)
S/. - 25.00 S/. 23.75 25.00 S/. 23.75 100.00% 0.00 S/. - 0.00%
S/. - 25.00 S/. 25.00 25.00 S/. 25.00 100.00% 0.00 S/. - 0.00%
S/. - 47.50 S/. 551.00 47.50 S/. 551.00 100.00% 0.00 S/. - 0.00%
S/. - 25.00 S/. 19.25 25.00 S/. 19.25 100.00% 0.00 S/. - 0.00%
S/. - 3.75 S/. 245.25 3.75 S/. 245.25 100.00% 0.00 S/. - 0.00%
S/. - 57.00 S/. 271.89 57.00 S/. 271.89 100.00% 0.00 S/. - 0.00%
S/. - 0.27 S/. 71.85 0.27 S/. 71.85 100.00% 0.00 S/. - 0.00%
S/. - 3.60 S/. 101.70 3.60 S/. 101.70 100.00% 0.00 S/. - 0.00%
S/. - 67.10 S/. 253.64 67.10 S/. 253.64 100.00% 0.00 S/. - 0.00%
S/. - 0.71 S/. 204.98 0.71 S/. 204.98 100.00% 0.00 S/. - 0.00%
S/. - 7.90 S/. 212.04 7.90 S/. 212.04 100.00% 0.00 S/. - 0.00%
S/. - 121.49 S/. 459.23 121.49 S/. 459.23 100.00% 0.00 S/. - 0.00%
S/. - 28.10 S/. 8,447.98 28.10 S/. 8,447.98 100.00% 0.00 S/. - 0.00%
S/. - 11.88 S/. 380.04 11.88 S/. 380.04 100.00% 0.00 S/. - 0.00%
S/. - 1,871.24 S/. 7,073.29 1,871.24 S/. 7,073.29 100.00% 0.00 S/. - 0.00%
S/. - 5.00 S/. 77.30 5.00 S/. 77.30 100.00% 0.00 S/. - 0.00%
DEL ADICONAL N° 01
O, PROVINCIA DE CUTERVO- CAJAMARCA" (SEGUNDA ETAPA)
S/. - 20.70 S/. 2,019.08 20.70 S/. 2,019.08 100.00% 0.00 S/. - 0.00%
S/. - 3.00 S/. 92.13 3.00 S/. 92.13 100.00% 0.00 S/. - 0.00%
S/. - 5.25 S/. 101.90 5.25 S/. 101.90 100.00% 0.00 S/. - 0.00%
S/. - 8.85 S/. 36.11 8.85 S/. 36.11 100.01% 0.00 S/. - 0.00%
S/. - 10.35 S/. 13.04 10.35 S/. 13.04 99.99% 0.00 S/. - 0.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 47.15 S/. 44.79 99.99%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 47.15 S/. 47.15 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 27.48 S/. 318.77 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 32.97 S/. 157.27 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 9.45 S/. 176.24 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 7.42 S/. 2,256.27 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 362.39 S/. 1,369.83 100.00%
DEL ADICONAL N° 01
O, PROVINCIA DE CUTERVO- CAJAMARCA" (SEGUNDA ETAPA)
S/. - 0.00 S/. - 0.00 S/. - 0.00% 13.49 S/. 3,840.33 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 66.78 S/. 1,984.03 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 1,193.66 S/. 4,070.38 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 42.95 S/. 4,178.18 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 67.20 S/. 1,155.84 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 8.40 S/. 41.66 99.99%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 66.78 S/. 1,016.39 100.00%
S/. - 0.00 S/. - 0.00 S/. - 0.00% 42.50 S/. 91.38 100.01%
S/. - 6.25 S/. 1,958.69 6.25 S/. 1,958.69 100.00% 0.00 S/. - 0.00%
S/. - 64.06 S/. 2,049.28 64.06 S/. 2,049.28 100.00% 0.00 S/. - 0.00%
S/. - 798.55 S/. 3,018.52 798.55 S/. 3,018.52 100.00% 0.00 S/. - 0.00%
S/. - S/. 27,706.93 S/. 27,706.93 S/. 27,877.54
49.85% 100.00%
3.5. CONTROL DE AVANCE DE LA OBRA
"MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505 DEL CENTRO POBLADO SALABAMBA, DISTRITO DE
OBRA:
CUTERVO, PROVINCIA DE CUTERVO- CAJAMARCA" (SEGUNDA ETAPA)
3.6. GRAFICOS
S/. 80,000.00
S/.75,428.14 100.00% 100.00%
S/. 70,000.00
S/. 60,000.00
75.00%
S/. 50,000.00
S/. 20,000.00
25.00%
S/.12,920.57
S/. 10,000.00 17.13%
S/. S/.-
0.00 S/. 0.00
27/12/18 31/12/18 23/01/19 0.00% 0.00%
27/12/18 31/12/18 23/01/19
CRONOGRAMA VALORIZADO DE OBRA
OBRA: "MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505, DEL CENTRO POBLADO SALABAMBA, DISTR
DE CUTERVO, PROVINCIA DE CUTERVO - CAJAMARCA" - SEGUNDA ETAPA
OBRA: "MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505, DEL CENTRO POBLADO SALABAMBA, DISTR
DE CUTERVO, PROVINCIA DE CUTERVO - CAJAMARCA" - SEGUNDA ETAPA
OBRA: "MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION INICIAL EN LA INSTITUCION EDUCATIVA Nº 505, DEL CENTRO POBLADO SALABAMBA, DISTR
DE CUTERVO, PROVINCIA DE CUTERVO - CAJAMARCA" - SEGUNDA ETAPA
TOTAL
23.75
25.00
551.00
19.25
245.25
271.89
71.85
101.70
253.64
204.98
212.04
459.23
8,447.98
380.04
7,073.29
77.30
CRONOGRAMA VALORIZADO DE OBRA
TOTAL
2,019.08
92.13
101.90
36.11
13.04
44.79
47.15
318.77
157.27
176.24
2,256.27
1,369.83
2,592.89
1,507.07
3,029.07
CRONOGRAMA VALORIZADO DE OBRA
TOTAL
3,840.33
1,984.03
4,070.38
4,178.18
1,155.84
41.66
1,016.39
91.38
1,958.69
2,049.28
3,018.52
55,584.48
5,558.45
2,779.22
63,922.15
11,505.99
75,428.14
100.00%
CRONOGRAMA A
OBRA: "MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMAR
FINANCIA: MUNICIPALIDAD PROVINCIAL DE CUTERVO
EJECUTA: CONSORCIO LEAL
SUPERVISOR: ING. RAUL E. ESPEJO MONTESTRUQUE
RESIDENTE: ING. OSCAR O. REYES FLORES
MODALIDAD: CONTRATO A SUMA ALZADA
PLAZO: 90 DIAS CALENDARIO
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
60 S/. 402.97 S/. 24,178.20 100% S/. 24,178.20
61 S/. 31.01 S/. 1,891.61 100% S/. 1,891.61
5.25 S/. 364.49 S/. 1,913.57 100% S/. 1,913.57
600 S/. 2.84 S/. 1,704.00 100% S/. 1,704.00
260 S/. 8.15 S/. 2,119.00 50% S/. 1,059.50 50% S/. 1,059.50
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
6.3 S/. 287.71 S/. 1,812.57 100% S/. 1,812.57
184.04 S/. 3.06 S/. 563.16 100% S/. 563.16
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
156.11 S/. 1.35 S/. 210.75 100% S/. 210.75
156.11 S/. 1.87 S/. 291.93 100% S/. 291.93
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
20.32 S/. 19.89 S/. 404.16 100% S/. 404.16
0.38 S/. 345.08 S/. 131.13 100% S/. 131.13
78.71 S/. 25.74 S/. 2,026.00 100% S/. 2,026.00
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
1187 S/. 3.06 S/. 3,632.22 100% S/. 3,632.22
54 S/. 85.44 S/. 4,613.76 17% S/. 802.94 83% S/. 3,810.81
41.78 S/. 52.33 S/. 2,186.35 100% S/. 2,186.35
83.88 S/. 3.27 S/. 274.29 100% S/. 274.29
CRONOGRAMA ACTUALIZADO Y VALORIZADO DE OBRA
OS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERVO CAJAMARCA"
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
16.08 S/. 16.73 S/. 269.02 100% S/. 269.02
182.43 S/. 17.52 S/. 3,196.17 75% S/. 2,397.13 25% S/. 799.04
63.17 S/. 22.94 S/. 1,449.12 100% S/. 1,449.12
81.08 S/. 35.26 S/. 2,858.88 100% S/. 2,858.88
24.08 S/. 8.74 S/. 210.46 100% S/. 210.46
373.3 S/. 1.34 S/. 500.22 100% S/. 500.22
7.74 S/. 577.34 S/. 4,468.61 55% S/. 2,455.07 45% S/. 2,013.53
20.08 S/. 242.40 S/. 4,867.39 100% S/. 4,867.39
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
24 S/. 6.02 S/. 144.48 100% S/. 144.48
4 S/. 7.29 S/. 29.16 100% S/. 29.16
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
3.78 S/. 21.45 S/. 81.08 100% S/. 81.08
1 S/. 53.82 S/. 53.82 100% S/. 53.82
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
9.55 S/. 9.34 S/. 89.20 100% S/. 89.20
1 S/. 388.33 S/. 388.33 100% S/. 388.33
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
8.75 S/. 1.87 S/. 16.36 100% S/. 16.36
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
0.96 S/. 403.52 S/. 387.38 100% S/. 387.38
17.28 S/. 42.93 S/. 741.83 100% S/. 741.83
133.5 S/. 3.06 S/. 408.51 100% S/. 408.51
CALENDARIO VALORIZADO
OCTUBRE NOVIEMBRE DICIEMBRE
DEL 5 AL 31 DEL 1 AL 30 DEL 1 AL 31
METRADO P.U PARCIAL % PARCIAL % PARCIAL % PARCIAL
S/. 7,738.68
S/. 859.16
S/. 525.00
S/. 2,682.25
S/. 1,864.39
S/. 1,059.32
S/. 810.00
S/. 1,122.00
S/. 32,683.86
S/. 58.71
S/. 1,278.00
S/. 8,538.00
S/. 4,494.00
S/. 15,720.45
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 24,178.20
S/. 1,891.61
S/. 1,913.57
S/. 1,704.00
S/. 2,119.00
S/. -
S/. 295.10
S/. 3,576.02
S/. 120.33
S/. 133.65
S/. 185.13
S/. 164.35
S/. 3,249.76
S/. 69.06
S/. 417.69
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 1,812.57
S/. 563.16
S/. 3,999.17
S/. 8,785.63
S/. 2,690.84
S/. 66.17
S/. 182.17
S/. 191.05
S/. 146.73
S/. 404.82
S/. 297.73
S/. 1,351.68
S/. 3,045.72
S/. -
S/. 604.03
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 210.75
S/. 291.93
S/. 19.58
S/. 7.86
S/. 221.17
S/. 441.20
S/. 99.46
S/. 177.66
S/. 1,489.58
S/. 58.43
S/. 794.90
S/. 1,079.87
S/. 345.80
S/. 169.20
S/. 729.49
S/. 280.59
S/. 460.95
S/. 1,595.31
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 404.16
S/. 131.13
S/. 2,026.00
S/. 3,581.30
S/. 752.21
S/. 2,117.14
S/. 1,695.31
S/. 1,825.29
S/. 1,327.21
S/. 1,252.35
S/. 423.81
S/. 3,361.32
S/. 3,529.28
S/. 4,677.73
S/. 4,206.55
S/. 4,987.95
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 3,632.22
S/. 4,135.79
S/. 4,336.25
S/. 2,151.49
S/. 2,215.95
S/. 3,161.50
S/. 57.24
S/. 2,271.00
S/. 7,982.35
S/. 1,001.22
S/. 2,039.07
S/. 1,124.00
S/. 3,323.23
S/. 4,613.76
S/. 2,186.35
S/. 274.29
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 269.02
S/. 3,196.17
S/. 1,449.12
S/. 2,858.88
S/. 210.46
S/. 500.22
S/. 133.56
S/. 347.96
S/. 1,658.47
S/. 2,310.81
S/. 718.13
S/. -
S/. 4,468.61
S/. 4,867.39
S/. 3,696.50
S/. 130.72
S/. 259.28
S/. 252.72
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 144.48
S/. 29.16
S/. 1,333.89
S/. 808.68
S/. 1,358.17
S/. 291.28
S/. 281.01
S/. 146.20
S/. 502.98
S/. 269.06
S/. 80.40
S/. 67.38
S/. 230.68
S/. 55.34
S/. 55.75
S/. 42.15
S/. 62.89
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 217.68
S/. 240.28
S/. 54.96
S/. 2.54
S/. 145.27
S/. 63.34
S/. 303.99
S/. 1,307.81
S/. 65.54
S/. 55.00
S/. 127.05
S/. 5.53
S/. 539.54
S/. 163.79
S/. 103.43
S/. 51.09
S/. 1,466.32
S/. 1,108.58
S/. 559.31
S/. 406.39
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 81.08
S/. 53.82
S/. 159.93
S/. 57.63
S/. 751.87
S/. 266.33
S/. 201.67
S/. 122.80
S/. 48.04
S/. 622.40
S/. 41.04
S/. 10.76
S/. 420.42
S/. 568.20
S/. 250.27
S/. 578.20
S/. 538.60
S/. 250.46
S/. 90.20
S/. 1,565.95
34% S/. 24,744.44 S/. 73,864.00
100% S/. 439.83 S/. 439.83
100% S/. 508.47 S/. 508.47
S/. 11.81
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 16.36
S/. 108.80
S/. 13.20
S/. 15.48
S/. 31.87
S/. 51.71
S/. 412.30
S/. 458.24
S/. 110.86
S/. 165.17
S/. 131.57
S/. 179.96
S/. -
S/. 48.77
S/. 37.26
S/. 8.90
ADO
ENERO
1Y2
% PARCIAL TOTAL
S/. 387.38
S/. 741.83
S/. 408.51
S/. 131.32
S/. 198.71
S/. 96.30
S/. 593.81
S/. 243.53
S/. 346.85
S/. 132.23
S/. 181.22
S/. 3,401.58
S/. 7,474.47
S/. 330.51
S/. 34,521.52
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
OPERARIO H-H 13.85 2528.68 35022.22 228.68
OFICIAL H-H 12.05 1694.64 20420.41 694.64
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
ARENA FINA m3 80.51 15.95 1284.13
TIERRA CERNIDA m3 38.32 1.50 57.48
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
PEGAMENTO PARA CERAMICO (BOLSA DE 25KG) bl 11.86 3.97 47.08
FRAGUA Kg 3.81 0.86 3.28
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
PEGAMENTO PARA TUBERIA PVC gal 81.70 0.56 45.75
PEGAMENTO PARA TUBERIA PVC (ELECT.) gal 81.70 0.34 27.78
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
GUANTES DE CUERO par 6.78 25.00 169.50 25.00
RESPIRADOR CONTRA POLVO Und 16.87 25.00 421.75 25.00
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
PLATINA DE FIERRO 3/8" x 1" ml 5.38 30.40 163.55
PINTURA LATEX gal 23.73 22.90 543.42
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
UNION UNIVERSAL FºGº 3/4" Und 5.08 1.00 5.08
SUMIDERO DE BRONCE 2" Und 4.24 2.00 8.48
UNION SIMPLE PVC-SAP CLASE 10 1/2" ROSCADA Und 1.03 1.51 1.56
SOMBRERO PARA VENTILACION DE PVC DE 2" Und 2.54 1.00 2.54
CODO PVC-SAL 2" x 90 Und 1.27 4.00 5.08
CODO PVC-SAL 4" x 90 Und 3.39 10.42 35.32
YEE PVC-SAL 2" x 2" Und 1.27 1.00 1.27
YEE PVC-SAL 4" x 4" Und 4.23 2.40 10.15
TEE PVC SAL 4" PZA 3.81 2.00 7.62
HIPOCLORITO DE CALCIO 70% Kg 6.00 0.04 0.24
VALVULA DE COMPUERTA 1/2" Und 13.56 1.00 13.56
CRONOGRAMA DE ADQUISION DE MATERIALES
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.
REGISTRO BRONCE Ý 4" ROSCADO Und 8.48 18.00 152.64
PLANTON Und 12.75 112.00 1428.00
Proyecto: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. 10274 DE LA LOCALIDAD DE ANGURRA, DISTRITO CUTERVO, PROVINCIA DE CUTERV
Fecha: SEPTIEMBRE 2016
PRESUPUESTO MES 01
DESCRIPCION UND PRECIO S/.
CANT. PRESUP. CANT.