Академический Документы
Профессиональный Документы
Культура Документы
through
better O&M Practices
S Bandyopadhyay
GM (CenPEEP), NTPC
Presentation
• Focus shift from Gross Heat Rate (GHR) & APC to Net Heat Rate
(NHR)
Accurate Gap
Assessment &
Analysis
Development
Skill & of
Awareness Action plans
Planning
R&M
&
Retrofits
Implementation
RCM of Prioritized
Re-visit of RCM Systems ( potential
Modify tasks, frequency, of benefit)
scope, additional task
Recommendations of
Living program frequency and scope
PM, PdM, OH
Identification of
equipment of
Concern Tracking of Performance
High BD, New failure
modes, repeat failures,
& Maint.
PM, BD, outages, losses, trips
high losses
• PAT Cycles-II
In any PAT cycle finalization of scheme, investment approval, Implementation &
planning of scheme takes at least two years before actual benefits are reaped after
implementation through out the year.
• Ageing of units
Study should be done to capture obsolescence of all C&I, Electrical & Mechanical
components. Ageing assessment based on RLA should be carried out and permanent
degradation may be taken into consideration.
Improvement through O&M Practices
• Proper & Optimum coal blending is a challenge for O&M . Some issues of
importance are :
• High Moisture
The moisture in the imported coal is of great concern and hence,
depending on the type of blending, the hot air temperature is
maintained.
• Safe operation / flame stability
Like the volatile matter yield, the heating value contained in the
volatiles influences flame stability and heat release profile in the
boiler
• Furnace slagging/ clinkering
Slagging/fouling characteristic of blended coal is an important factor.
The characteristics of ash are studied to arrive at the slagging
potential and correct blend ration
• Use of ground hopper, payloader, 30% capacity stack reclaimer
• Boiler, Turbine, pumps, mills & Air Heater & material upgrades
Gaps between baskets & • Action Plan & Restoration: Boiler &
diaphragms Air Pre heater
• Air ingress in Boiler casing/pent • Focus on OH preparedness
house/ducts/Expansion joints • Identification of engineering issues
• High boiler loading • Operational optimization
• Fouling / Soot blowing in- • Component upgrades - Air
effectiveness preheater & Pulverizer
• Engineering issues (design,
modifications)
Thrust area Turbine : Condenser
500 MW unit
1. Draft Power Consumption
Draft power 2. Milling Power consumption
6%
0% CEP Power
18%
CW Power
3. Pump power consumption
43%
Mill power
24% CT Power
9%
ESP
Source: Efficiency Improvement at State Utilities – Challenges and Opportunities, CII Power Plant Summit, 2013 21