Вы находитесь на странице: 1из 5

SUMMARY OF BILL OF QUANTITIES

Item No. Description


Materials Cost Labor Cost Total Amount

I. General Requirements

Preliminaries(over head, Administrative Management) 10% of


1
total project cost communication & Transportation;Safety
Site Administration;
Facilities
Temporary Facilities; Support equipment rentals;permits &
licenses

2 Mobization / Demobilization

II. Structural Works


1 Site Works
2 Excavation Works
3 Concreting Works, 3000psi
4 Rebar Works / Grade 40
5 Formworks
total Structural Works

III. Architectural Works


1 Masonry Works
2 Floor Finishes
3 Wall Finishes
4 Ceiling Finishes
5 Doors
6 Windows
7 Tiles Work
8 Painting Works
9 Thermal & Moisture Protection
10 Window Grills
11 Floor Mounted Railing
12 Wall Mounted Railing
13 Steel Works
14 Other Miscellaneous Works
total Architectural Works

IV. Electrical Works


1 Roughin Roughing-In
PVC - moldex Brand
IMC - Panasonic Brand
Flexible Metallic Conduit
Boxes, Fumaco Brand
2 Wires, phelps dodge brand
3 Wiring Devices, Wide Series, Panasonic
4 Lighting Fixtures & Fans
5 Panelboards & Enclosed Circuit
6 HANGERS, SUPPORTS & ACCESSORIES
sub - total "A"
total "Electrical Works"

V. Plumbing and Sanitary Works


1 Plumbing Fixtures
2 Drainage Line System
A. Storm Drainage
B. Sewer Line System
C. Vent Line System
D. Water Line System
3 Miscellaneous Item to Complete the System.
total "Plumbing & Sanitary Works"

VI. Fire Protection Works


fire extinguisher
fire exit ladder rung and railings
sprinkler provision only (pipe line)
total "Plumbing & Sanitary Works"
TOTAL PROJECT COST
CONSTRUCTION OF PROPOSED 2 UNITS TWO (2) STOREY
Project :
RESIDENTIAL BUILDING Quantity Surveyor: MARK ROGER HUBERIT II
Nature of Project: TWO UNITS RESIDENTIAL HOUSE CIVIL ENGINEER
Location: MALOLOS, BULACAN
Client: JO ANNE GRACE OLORES
Project Early Start: TBA Approved by: Client
Project Duration: 185 Calendar Days
Subject: BILL OF QUANTITIES COST BREAKDOWN
Date: 28-Apr-2019
Total floor Area: 700 sq.m.

ITEM DESCRIPTION UNIT QTY %WT UNIT RATE SITE MATERIAL & LABOUR EQUIPMENT TOTAL AMOUNT
MANANGEMENT

CONSTRUCTION OF PROPOSED 2 UNITS TWO (2) STOREY RESIDENTIAL BUILDING

A. General Items
Preliminaries(over head, Administrative Management) 10% of total project cost 1 lot 479,790.47 479,790.47 479,790.47
Site Administration; communication & Transportation;Safety Facilities 1 lot #VALUE! #VALUE!
Temporary Facilities; Support equipment rentals;permits & licenses 1 lot #VALUE! #VALUE!
1 lot #VALUE! #VALUE!
Sub-Total = 8.83% #VALUE! 479,790.47
B. Construction of 2-Storey residential house
B.1 Ground floor
Foundation
Excavation works
FOOTINGS cu.m. 236.25 180.00 - 29,767.50 12,757.50 42,525.00
TIE BEAMS cu.m. 14.70 180.00 - 2,646.00 101.50 2,747.50
Gravel bedding
FOOTINGS cu.m. 23.63 1,200.00 466.09 28,350.00 1,087.54 29,903.63
TIE BEAMS cu.m. 1.47 1,200.00 29.00 1,764.00 67.67 1,860.67
Rebar works
FOOTINGS kgs 2,250.00 48.00 1,775.58 108,000.00 4,143.02 113,918.60
TIE BEAMS kgs 3,675.00 48.00 2,900.11 176,400.00 - 179,300.11
Formworks
FOOTINGS sq.m. 8.00 1,400.00 184.13 11,200.00 429.65 11,813.78
TIE BEAMS sq.m. 16.00 48,000.00 12,626.34 768,000.00 29,461.47 810,087.82
Concrete works
FOOTINGS cu.m. 9.00 4,800.00 710.23 43,200.00 1,657.21 45,567.44
TIE BEAMS cu.m. 14.70 4,800.00 1,160.05 70,560.00 2,706.77 74,426.82
Columns
Rebar works kgs 4,500.00 48.00 3,551.16 216,000.00 8,286.04 227,837.20
Formorks sq.m. 12.00 1,400.00 276.20 16,800.00 644.47 17,720.67
Concrete works cu.m. 25.00 4,800.00 1,972.87 120,000.00 4,603.35 126,576.22
Ground slab
Gravel bedding cu.m. 11.25 1,200.00 221.95 13,500.00 517.88 14,239.82
Rebar works kgs 6,750.00 48.00 5,326.74 324,000.00 12,429.06 341,755.80
CONSTRUCTION OF PROPOSED 2 UNITS TWO (2) STOREY
Project :
RESIDENTIAL BUILDING Quantity Surveyor: MARK ROGER HUBERIT II
Nature of Project: TWO UNITS RESIDENTIAL HOUSE CIVIL ENGINEER
Location: MALOLOS, BULACAN
Client: JO ANNE GRACE OLORES
Project Early Start: TBA Approved by: Client
Project Duration: 185 Calendar Days
Subject: BILL OF QUANTITIES COST BREAKDOWN
Date: 28-Apr-2019
Total floor Area: 700 sq.m.

ITEM DESCRIPTION UNIT QTY %WT UNIT RATE SITE MATERIAL & LABOUR EQUIPMENT TOTAL AMOUNT
MANANGEMENT

Formworks sq.m. 18.60 1,400.00 428.11 26,040.00 998.93 27,467.04


Concrete works cu.m. 67.50 4,800.00 5,326.74 324,000.00 12,429.06 341,755.80
Comfort rooms/Living room / kitchen
Doors no. 3.00 13,500.00 665.84 40,500.00 1,553.63 42,719.47
Windows no. 6.00 16,500.00 1,627.61 99,000.00 3,797.77 104,425.38
MEP(GF TO 2nd FLR) sq.m. 700.00 500.00 350,000.00 350,000.00
Tile works
Comfort rooms/Living room / kitchen sq.m. 175.00 260.00 748.05 45,500.00 1,745.44 47,993.48
Painting works sq.m. 412.25 240.00 1,626.61 98,939.10 3,795.43 104,361.15
Disposal cu.m. 250.95 150.00 618.86 37,642.50 1,444.01 39,705.38

Blockwall/Masonry CHB laying on side walls/plastering & finishes this includes facade sq.m. 180.00 850.00 2,515.40 153,000.00 5,869.28 161,384.68

Stair -
Rebar works kgs 393.75 48.00 310.73 18,900.00 725.03 19,935.75
Formworks sq.m. 10.50 1,400.00 241.68 14,700.00 563.91 15,505.59
Concrete works cu.m. 1.58 4,800.00 124.29 7,560.00 290.01 7,974.30
Sub-Total = 60.78% 45,434.38 3,145,969.10 112,105.63 3,303,509.12
CONSTRUCTION OF PROPOSED 2 UNITS TWO (2) STOREY
Project :
RESIDENTIAL BUILDING Quantity Surveyor: MARK ROGER HUBERIT II
Nature of Project: TWO UNITS RESIDENTIAL HOUSE CIVIL ENGINEER
Location: MALOLOS, BULACAN
Client: JO ANNE GRACE OLORES
Project Early Start: TBA Approved by: Client
Project Duration: 185 Calendar Days
Subject: BILL OF QUANTITIES COST BREAKDOWN
Date: 28-Apr-2019
Total floor Area: 700 sq.m.

ITEM DESCRIPTION UNIT QTY %WT UNIT RATE SITE MATERIAL & LABOUR EQUIPMENT TOTAL AMOUNT
MANANGEMENT

B.2 2nd floor


Beams -1
Rebar works kgs 1,837.50 48.00 - 88,200.00 - 88,200.00
Concrete works cu.m. 9.19 4,800.00 2,500.00 44,100.00 1,000.00 47,600.00
Suspended Slab
Rebar works kgs 6,750.00 48.00 310.73 324,000.00 725.03 325,035.75
Formworks sq.m. 18.60 1,400.00 241.68 26,040.00 563.91 26,845.59
Concrete works cu.m. 33.75 4,800.00 124.29 162,000.00 290.01 162,414.30
Reflected Ceiling
Ceiling board sq.m. 361.00 650.00 - 234,650.00 - 234,650.00

Blockwall/Masonry CHB laying on side walls/plastering & finishes this includes facade sq.m. 285.00 850.00 242,250.00 242,250.00
- -
Painting works sq.m. 570.00 240.00 6,840.00 136,800.00 - 143,640.00
Rent rooms + rest rooms
Doors no. 8.00 13,500.00 108,000.00 - 108,000.00
Windows no. 10.00 16,500.00 165,000.00 - 165,000.00
Strucutral works sq.m. 95.00 950.00 18,050.00 90,250.00 - 108,300.00

Sub-Total = 30.39% 43,786.00 28,066.69 1,621,290.00 2,578.95 1,651,935.64


Total Building Cost #VALUE! #VALUE! #VALUE! PHP 5,435,235.23
COST / AREA PHP 7,764.62

Вам также может понравиться