Вы находитесь на странице: 1из 14

Electrical Switchgear Testing

The design of the insulation system for metal-enclosed switchgear is based


upon life expectancy of about 30 years. However, environmental conditions
such as dirt, moisture, and corrosive atmosphere can shorten the design life.

The Most Important Tests For Medium Voltage Metal-Enclosed Switchgear You
MUST Perform
Moisture combined with dirt is the greatest deteriorating factor for insulation
systems because of leakage and tracking, which will result in eventual failure.
Therefore, it is important to maintain the switchgear insulation and to chart the
condition of the primary insulation system by routine testing.

The electrical switchgear may be tested with AC or DC voltage to check the


condition of the insulation of switchgear and circuit breakers. Before
conducting any other tests, an insulation resistance test (by Megger) should
always be conducted first to determine if it is safe to conduct other HV tests.
Also when testing circuit breakers, it is important to check the condition of the
circuit breaker contacts and circuit breaker operating mechanism to
assure that the circuit breaker is opening and closing as designed.
These tests are listed and discussed as follows:

1. Insulation resistance test


2. DC or AC hi-pot test
3. Power factor or dielectric loss test
4. Circuit breaker contact resistance test
5. Circuit breaker time–travel analysis test

1. Insulation Resistance Measurement Test


The insulation resistance measurement test may be conducted on all types
of electrical switchgear using the insulation resistance
megohmmeter commonly known as the MEGGER.

The Megger S1-5010 is shown in Figure 1 that may be used to perform this
test.

Figure 1 –
Megger S1-5010 for making insulation resistance tests. (a) Megger S1-5010; (b) Megger S1-
5010 being used in the feld.
The insulation resistance test consists of applying voltage (600–10,000 V
DC) to the apparatus to determine the megohm value of resistance. This
test does not indicate the quality of primary insulation.
Several factors should be remembered when performing this test:

The first is that this test can indicate low values of insulation resistance because
of many parallel paths.

The other is that an insulation system having low dielectric strength may
indicate high resistance values. In view of this, the test results should only be
interpreted for comparative purposes. This does not indicate the quality of the
primary insulation system from the point of view of dielectric withstandability.
The connection diagram for making this test on a power circuit breaker is
shown in Figure 2.

When performing insulation testing, it is recommended that auxiliary equipment,


such as potential transformers and lightning arresters, be removed from the
stationary switchgear.

Figure 2
– Typical connection for insulation resistance test of circuit breaker in open position
Insulation resistance tests are made with the circuit breaker in open and closed
position, whereas the insulation test for the switchgear bus is made with one
phase to ground at a time, with the other two phases grounded.

The procedure for this test is as follows:

1. Circuit breaker open: Connect HV lead to pole 1. Ground all other


poles. Repeat for poles 2 through 6, in turn, with other poles grounded.
2. Circuit breaker closed: Connect HV lead to pole 1 or 2, as convenient, with
either pole of phase 2 and 3 grounded. Repeat for phases 2 and 3 with other
phases grounded.
3. Stationary gear (buses): Connect HV lead to phase 1 with phases 2 and 3
grounded. Repeat the same for phases 2 and 3 with other phases grounded.
Also, perform IR tests between phase 1 and 2 with phase 3 grounded, phase
2 and phase 3 with phase 1 grounded, and phase 3 and 1 with phase 2
grounded.

2. High-Potential (Hi-pot) Test


DC Hi-Pot Test
The DC hi-pot test is normally not made for AC electrical switchgear
and therefore may be considered only when AC hi-pot cannot be performed.

The hi-pot testing of switchgear involves testing of the circuit breakers and
switchgear buses separately. This is a major test and determines the condition
of the insulation of the switchgear assembly.

The DC hi-pot test is not preferred for testing AC switchgear because the
application of DC voltage does not produce similar stress in the insulation
system as is produced under operating conditions. Moreover, the DC hi-pot test
produces corona and tracking owing to concentration of stress at sharp edges
or end points of buses.
The corona and tracking are more pronounced in older equipment, and it is
therefore recommended that DC hi-pot testing be avoided on such
equipment. The test procedures for DC hi-pot testing are similar to those of AC
hi-pot testing.

If DC hi-pot testing is to be performed, the DC voltage test values shown in


Table 1 are recommended for various voltage-class equipment.

Table 1 – DC Hi-Pot Maintenance Test Values


Rated operating voltage 1 min. DC test voltage
240 1,600
480 2,100
600 2,300
2,400 15,900
4,160 20,100
7,200 27,600
13,800 38,200
23,000 63,600
34,500 84,800

The hi-pot test should be conducted under conditions similar to those


of commercial testing.

The switchgear should be wiped, cleaned, and restored to good condition


before the hi-pot test is conducted. Temperature and humidity readings
should be recorded and the test reading corrected when conducting DC tests.

AC Hi-Pot Test
This test should be conducted separately for circuit breakers and
switchgear buses (stationary gear). It should be made only after the DC
insulation resistance measurement test has been passed
satisfactorily and all cleanup has been finished.

The AC test will stress the switchgear insulation similarly to the stresses found
during operating conditions. The maintenance test voltages should be 75% of
final factory test voltage.

These values are shown in Table 2.

Table 2 – Hi-Pot Test Values


Rated Operating AC Factory Proof Test AC Test Maintenance Values
Voltage (V) (V)
240 1,500 1,130

480 2,000 1,500

600 2,200 1,650

2,400 15,000 11,300

4,160 19,000 14,250

7,200 26,000 19,500


13,800 36,000 27,000

14,400 50,000 37,500

23,000 60,000 45,000

34,500 80,000 60,000

Hi-pot tests are made with the circuit breaker in both open and closed
positions. The hi-pot test should be the last test conducted after all repairs
have been made, cleanup is finished, and the insulation resistance test has
been successfully passed.

Figure 3 – Typical connection for hi-pot test for circuit breaker in closed position
Procedures for the hi-pot test of the circuit breaker are as follows:

1. The test connection for the hi-pot test is as shown in Figure 3.


2. Circuit breaker in open position:
Connect HV lead to pole 6. Ground all other poles. Repeat for poles 1
through 5, in turn, with all other poles grounded. Apply the desired high
voltage in each case in
accordance with Table 2.
3. Circuit breaker in closed position:
Connect HV lead to pole 1 or 2 or phase 1 as convenient with either pole of
phases 2 and 3 grounded. Repeat for test for phases 2 and 3 with other
phases grounded.
4. Stationary gear (buses):
Connect HV lead to phase 1 as convenient with phases 2 and 3 grounded.
Apply the recommended voltage. Repeat the test for phases 2 and 3 with
other phases grounded.

3. Power Factor Testing


The power factor testing of an insulation system is useful in finding signs
of insulation deterioration. The absolute values of power factor measured
have little significance.

However, comparative analysis of values from year to year may very well show
insulation deterioration. Therefore, when a power factor test is made, it should
be made under the same conditions of temperature and humidity. If
differences exist in the temperature and humidity from year to year, this
should be taken into consideration when evaluating the test data.

Generally, higher temperature and humidity result in higher power factor


values. As a general rule, only the air circuit breaker bushing should be power
factored, and the arc chutes, operating rods, and so on, should be disconnected
when conducting this test.
A significant change, especially an increase in watts loss or percent of power
factor indicates deterioration, which should be monitored.

As a general rule, a power factor below 1% indicates good insulation. Any value above 1%

warrants investigation.

4. Circuit Breaker Contact Resistance


Measurement Test
Stationary and moving contacts are built from alloys that are formulated
to endure the stresses of electrical arcing.

However, if contacts are not maintained on a regular basis, their electrical


resistance due to repeated arcing builds up, resulting in a significant decrease
in the contact’s ability to carry current. Excessive corrosion of contacts is
detrimental to the breaker performance.

One way to check contacts is to apply DC and measure the


contact resistance or voltage drop across the closed contacts.

The breaker contact resistance should be measured from bushing


terminal to bushing terminal with the breaker in closed position. It is
recommended that for MV and HV the resistance test be made with 100 A or
higher DC. The use of a higher current value gives more reliable results than
using lower current values.
The resistance value is usually measured in microohms (µΩ). The
average resistance value for 15 kV class circuit breakers is approximately
between 200 and 250µΩ. Several companies make good, reliable
microohmmeters to perform this testing.

One such instrument is the Megger DLRO 200. It can generate test
currents from 10 to 200 A and can measure resistances ranging from 0.1µΩ to
1 Ω.

The Megger DLRO 200 is shown in Figure 4.

Figure 4
– The Megger DLRO 200-115 High Current Digital Low Resistance Ohmmeter, 200 Amp is
designed to check and measure contact resistance in high voltage circuit breakers, disconnecting
switches (isolators), busbar joints, or for any low resistance measurement

5. Circuit Breaker Time-Travel Analysis


This test is usually performed on MV and HV circuit breakers, usually 34 kV and
above, to detect problems in the breaker operating mechanism.

This test can be conducted with a mechanical or electronic time–travel


analyzer.

Today, the electronic time-travel analyzers are replacing the old mechanical
time–travel analyzers. With either analyzer information on the breaker operating
mechanism is provided in form of charts or graphs which can be used to
assess the mechanical and electrical condition of the breaker.
There are eight tests that are usually conducted on the breaker with the circuit
breaker analyzer. These tests are:

1. Closing time and opening time,


2. Contact bounce,
3. Opening and closing synchronization,
4. Closing and opening speed (velocity and displacement),
5. Trip operation,
6. Trip-free operation,
7. Close operation, and
8. Trip-close operation.

1. Closing and opening time


In the example below, the closing time of the contacts is shown to be 31.4 ms
(phase A), 30.2 ms (phase B), and 31.8 ms (phase C).

Parameters Value Unit


001 Close time A 31.4 ms
060 Bounce time A 0.0 ms
001 Close time B 30.2 ms
060 Bounce time B 1.1 ms
001 Close time C 31.8 ms
060 Bounce time C 0.8 ms
010 Diff time A – B – C 1.6 ms
016 Cls speed 8.40 m/s
Also closing times of a breaker can be viewed in a graph form as displayed in
Figure 5.

Figure 5 – Graph showing closing time of contacts of a breaker


2. Contact bounce
If we expand the x-axis in Figure 5, we can actually view the contact bounce
associated with the above breaker operation as shown in Figure 6.

It is clear to see that there is 0.8 ms bounce associated with the


contact movement in phase C. These series of contact bounces can be
compared with future tests to see if there is any degradation to the actual
mechanism associated with breaker contacts.

3. Opening and closing synchronization


The breaker opening and synchronization can be viewed as a group, i.e., the
operation of all three phases together for breaker open and close cycle.

This information will indicate whether the breaker contacts open and close
together or how far apart the three-phase contacts are relative to each other
during the close and open cycle as shown in the example below.
The normal maximum time difference between all three phases should not be
more than 2 ms for most breakers.
Parameters Value Unit
010 Diff time A – B – C 1.6 ms

The synchronization of a breaker is defned as the time difference between the


fastest and slowest phase (contact make and break) during the breaker open
and close operation.

Figure 6 – Graph showing contact bounce of a breaker


4. Total opening and closing speed
All breakers have specific speed, opening and closing times. Therefore, it is
important that breakers operate within their opening and closing time.

For example, if a breaker is slow to open due to ageing or degradation, it may


compromise the protection and coordination scheme of the protective relays,
and thereby cause unwanted power interruption and equipment damage.

Further, all breakers have specified closing speed which is defined as the average speed

calculated between two defined points on the motion curve as indicated below.

Parameters Value Unit


016 Cls speed 8.40 m/s
These two points will be specified by the breaker manufacturer and
define where to set both points for accurate speed measurements.

For example, they will define the first point to be set to a distance above the
open position and a distance below the upper point where the contact motion
stops as indicated below.

Upper point Lower point


Distance above open position: 80.0 mm Distance below upper point: 20.0 mm
Distance below open position: 10.0 mm Distance below upper point: 10.0 mm
5. Trip operation
The trip operation of a breaker is another name for an
open operation. Most utility companies and plant owners want to perform a
trip (or open) operation to monitor the speed of the opening mechanism and
contacts to make sure there is enough energy in the spring mechanism to open
under a fault condition.

The graph for a trip is similar to the one for a close operation, except the motion
of the mechanism is going in the opposite direction, i.e., from closed contacts to
fully open position as seen in Figure 7

Figure 7 – Graph showing speed of the contacts opening for trip (or open) operation of a breaker
6. Trip-free operation
This operation simulates the condition when an open breaker is closed into a
fault and then it is tripped free by a protective relay.

Trip-free is an operation where the breaker contacts are in the open


position and the breaker is operated to perform a close–open sequence. In this
operation, the breaker is closed and then immediately sent a control
command to open.
This operation confirms whether a breaker, if closed into a fault, can clear it.

The graph for a trip-free operation is shown in Figure 8 below.


Figure 8 – Graph showing trip-free operation of a breaker
7. Close operation
This test is performed to verify a breaker’s closing mechanism. The graph for
close operation of a breaker is shown in Figure 9 which is similar to the graph of
Figure 5.

Figure 9 – Graph showing close operation of a breaker

8. Trip-reclose operation
In this test, the reclose operation of the breaker is checked to assure that the
breaker closing time is within specified limits after a trip operation. The
reclose time is measured either in milliseconds or cycles.

The trip-reclose operation of the breaker is shown in Figure 10.


Figure 10 – Graph showing trip-reclose operation of a breaker
The problems usually detected with this test are faulty dashpots,
faulty adjustments, weak accelerating springs, defective shock absorbers,
buffers and closing mechanisms, or broken parts.

This test should be performed during acceptance tests and then during
maintenance tests about every 3 years.

The breaker opening and closing parameters can easily be measured


with a Megger Programma EGIL breaker analyzer or its equivalent
manufactured by other vendors. The EGIL is designed to test MV breakers that
have a common operating mechanism and a single break per phase.
All three phases can be tested at the same time giving both individual phase
timing and combined measurements for all three phases. The EGIL analyzer is
shown in
video below.

Learn How to Conduct Circuit Breaker Testing

Вам также может понравиться