Академический Документы
Профессиональный Документы
Культура Документы
A Zone-2 timing of 0.35 seconds (considering LBB time of 200mSec, CB open time of
60ms, resetting time of 30ms and safety margin of 60ms) is recommended. However, if a
long line is followed by a short line, then a higher setting (typically 0.6second) may be
adopted on long line to avoid indiscriminate tripping through Zone-2 operation on both
lines.
For special cases, following shall be the guiding philosophy:
Since Zone-2 distance protection is set to overreach the circuit it is intended to protect, it
will also be responsive to faults within adjacent power system circuit. For this reason the
time delay for Zone–2 back-up protection must be set to coordinate with clearance of
adjacent circuit faults, within reach, by the intended main protection or by breaker fail
protection.
The following formula would be the basis for determining the minimum acceptable Zone-2
time setting:
t
Z2 >
t
MA +
t
CB +
t
Z2reset +
t
S
Where:
t
Z2
= Required Zone-2 time delay
t
MA
= Operating time of slowest adjacent circuit main protection or Circuit Local back-up
for faults within Zone-2 reach
t
CB
= Associated adjacent circuit breaker clearance time
t
Z2reset
= Resetting time of Zone-2 impedance element with load current present
t
S
= Safety margin for tolerance (e.g. 50 to 100ms)
Unequal lengths of transmission circuit can make it difficult to meet the Zone-2 secondary
reach setting criterion. In such cases it will be necessary to co-ordinate Zone-2 with longer
time delay. The time t
MA
in equation must be the adjacent circuit Zone-2 protection
operating time.
6. ZONE-3 TIMER SETTING
Zone-3 timer should be set so as to provide discrimination with the operating time of relays
provided in subsequent sections with which Zone-3 reach of relay being set, overlaps.
Typical recommended Zone-3 time is 0.8 to 1.0 second.
For Special cases, where co-ordination between long and short lines is required, following
formula would be the basis for determining the minimum acceptable Zone-3 time setting:
t
Z3 >
t
MA +
t
CB +
t
Z3reset +
t
S
Where:
tZ3 = Required Zone-3 time delay
tMA = Operating time of slowest adjacent circuit local back-up protection
tCB = Associated adjacent circuit breaker clearance time
tZ3reset = Resetting time of Zone-3 impedance element with load current present
tS = Safety margin for tolerance (e.g. 50 to 100milliseconds)
Report of the Task Force on Power System Analysis Under Contingencies
Appendix-9.1
(Page 4/7 of Appendix)
with bus bar main protection fault clearance and with Zone-1 fault clearance for
lines out of the same substation. For this reason this can be set according to the Zone-2
time setting guidelines.