JOB SAFETY ANALYSIS / RISK ASSESSMENT FORM HALLIBURTON MANAGEMENT REVISION NO:
DATE:
01 MARCH 2012
DOCUMENT NO: 001 SYSTEM A
Pages:
4
Job Title/Task: JSA/RA Document No: Revision Date: Risk Priority Code:
Offload cement 0 28-May- 2015
JSA-VN-HAL-CMT-1000 Allocated after Risk
Department: Plant/Location: Category: Prepared By: Approved By: Reduction Measures in place
Vung Tau Khanh Le PETER YATES RPC =
Cementing Viet Nam Cementing service Hai Pham
Dan Tran
Required and Recommended PPE Hard Hat, Safety Glasses, Coveralls, Safety Boots, Gloves, Hearing Protection; Dust Mask/Respirator
Before After
Sequence of Basic Risk Reduction Measures
Hazard Hazard Effect
Job Steps
SEVERI
SEVERI
PROBA
PROBA
BILITY
BILITY
RPC
RPC
TY
TY
Tool box meeting, Poor communication Injury people, damage EQ III C 2 Make sure everyone involved in the III D 3
review JSA operation understands their roles and
responsibilities.
III D 3
Check forklift extension Visible cracks Injury to personnel, dropped objects III C 2 Proceed if all is well III D 3
and forks
Using forklift(s) Driving backwards, Injury to personnel, property III C 2 Certified drivers only, seatbelts used, one III D 3
moving fast damage banksman used if multiple forklifts are
operating
Lifting operations Broken bags of III C 2 Insure only one bag at a time is lifted by III D 3
cement forklifts.
Injury to personnel,
damaged product
Visible damage on Injury to personnel III C 2 Reject damaged bags. III D
Received lifting straps. damaged product 3
product
Rain conditions Forklift slipping Property damage, injury to Suspend operations until rain stops. III D
personnel, water entering 3
product.
3 Note: RISK PRIORITY CODE OF LESS THAN 3 IS NOT ACCEPTABLE FOR HAZARDS THAT TARGET PERSONNEL
Page 3 of 4
INSTRUCTIONS FOR USING RISK ANALYSIS MATRIX
STEP1: After identifying a significant hazard, first consider the POTENTIAL CONSEQUENCES. For example, what happens if
the accident occurs?
STEP 2: After considering the POTENTIAL CONSEQUENCES, such as Sever Illness of Injury, identify the Hazard Severity Category (for
example, II).
STEP 3: Now consider the PROBABILITY RATING. If it is Reasonably Probable that the accident would occur, the rate would be “B”.
STEP 4: Follow the Hazard Severity Category (II) across the line until it dissects with the PROBABILITY RATE (B). This shows a RISK
PRIORITY CODE (RPC) of 1.
STEP 5: RPC 1 is unacceptable. STOP THE JOB! Institute controls to reduce the risk to an acceptable level with an RPC of 3.
Contact your manager if the risk cannot be reduced to RPC 3!
STEP 6: When the RPC is 2 and the hazard impacts people, this is still an unacceptable level of risk.
Page 4 of 4