Project
LINDE ENGINEERING
Unit(s): ASU
PCWBS: Z
QATAR SHELL GTL PROJECT (PEARL)
C2 AIR SEPARATION UNITS CONSTRUCTION
Document Title:
1.0 DOCUMENTATION
Contractor drawings, project TECHINICAL
1.1 100% - - - H R R
specifications, manuals, codes OFFICE
2.0 EQUIPMENT
Approved drawing,
Equipment identification and I S S
2.1 100% T-4.250.945 DEP 31.10.03.10; DEP STORE GAM-QCR-QAC-GTL-080
name plate verification
31.29.00.10 INCHARGE
3.0 INSTALLATION
Approved drawing,
Foundation complete and DEP 34.19.20.31; GAM-QCR-QAC-GTL-120;
3.1 100% T-4.250.945 QCI H I I
accepted T.13.376.358 DEP GAM-QCR-QAC-GTL-113
31.29.00.10
DEP34.19.20.31;
3.9 Grouting 100% T-4.234.545 T.13.376.358 ;Manufactures QCI GAM-QCR-QAC-GTL-025 I I I
Instruction
DEP 31.29.00.10 Vendor
3.10 Jack screw removal 100% T-4.250.945 specification, QCI GAM-QCR-QAC-GTL-120 I I S
Approved drawing,
3.11 Temporary earthing 100% T-4.250.945 QCI GAM-QCR-QAC-GTL-120 I I S
DEP 31.29.00.10,
Approved drawing,
T-4.250.945; T-4.250.936; GAM-QCR-QAC-GTL-120
3.13 Flanges parallelism (FSI) 100% DEP 31.29.00.10 DEP QCI H I I
T.13.377.360E GAM-QCR-QAC-GTL-058
31.38.01.11;T.13.376.815E
Approved drawing,
Mechanical seal/packing DEP 31.29.00.10, DEP
3.17 100% T-4.250.945; T.13.377.360E QCI GAM-QCR-QAC-GTL-120 I I I
installation check(FSI) 61.10.08.11; T.13.377.455E
Vendor specification
DEP 31.29.00.10, DEP
Cleaning, flushing and oil 70.10.80.11, DEP GAM-QCR-QAC-GTL-120
3.18 100% T-4.250.930;T.13.377.360E 61.10.08.11;T.13.377.455E QCI H H I
filling(FSI) GAM-QCR-QAC-GTL-070
Vendor specification,
Approved drawing,
DEP 31.29.00.10 DEP
3.19 Temporary suction strainers 100% T-4.250.936; T-4.250.945 QCI GAM-QCR-QAC-GTL-120 I I S
31.38.01.11;T.13.376.815E
installation check
DEP 61.10.08.11;
4.3 Shaft turning freely by hand 100% T-4.250.945 T.13.377.455EApproved QCI GAM-QCR-QAC-GTL-120 I I S
drawings, DEP 31.29.00.10
Vendor specifications
Cleanliness check for
DEP 61.10.08.11Approved GAM-QCR-QAC-GTL-120
4.4 equipment and associated 100% T-4.250.930;T.13.377.360E QCI H I I
drawings, DEP 31.29.00.10 GAM-QCR-QAC-GTL-070
system(FSI)
DEP 70.10.80.11
Vendor specifications
Verification of auxiliary system Approved drawings, DEP
4.5 100% T-4.250.945 31.29.00.10 QCI GAM-QCR-QAC-GTL-120 I I S
completion
DEP 61.10.08.11
Verification of piping pressure
T-4.250.945; T-4.250.908 Approved drawing DEP
4.6 test acceptance – Prior to final 100% QCI GAM-QCR-QAC-GTL-065 H H W
T.13.377.360E 31.38.01.11;T.13.376.815E
alignment(FSI)
Vendor specifications DEP
Installation of accessories & 61.10.08.11;T.13.377.455E
4.7 100% T-4.250.945 QCI GAM-QCR-QAC-GTL-120 I I S
coupling guard Approved drawings, DEP
31.29.00.10
4.8 General Punch List(Clearing) 100% T-4.250.945 - QCI GAM-QCR-QAC-GTL-128 H H R
Remarks:
Full Name/Signature/Date
GAMA QATAR CONTRACTOR COMPANY
C2 ASU PEARL GTL PROJECT
RASLAFFAN INDUSTRIAL CITY
BOLT TIGHTENING INSPECTION
REPORT
Subcontract Ref.: Report No.:
Item Description: Inspection Date:
Item Location /
Test Code No.:
Area:
Subsystem: ITP No.:
INSPECTIONS
Item No/Spool Mark No./Joint No Bolting Bolt Tightening Inspector’s
No Grade Size (Torque Value) Signature
GAMA REP.
LINDE REP.
GAM-QCR-QAC-GTL-041
C2 ASU PEARL GTL PROJECT
RASLAFFAN INDUSTRIAL CITY
FLANGE ALIGNMENT INSPECTION
REPORT
Subcontract Ref.: Report No.:
Item Description: Inspection Date:
Item Location /
Test Code No.:
Area:
Subsystem: ITP No.:
INSPECTIONS
Item No/Spool Mark No./Joint No Face Distance Face parallelism Centreline offset Inspector’s
No Signature
GAMA REP.
LINDE REP.
GAM-QCR-QAC-GTL-058
Q A T A R C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
Company Project No: Piping Test No:
PIPING FIELD
Project Title: Location Priority System No:
TEST REPORT
S/C Prepared By: Test Media:
Name: Signature Date: Description Of Test
LINDE Acceptance By: Reference Flow Sheets (List All applicable):
GAM-QCR-QAC-GTL-065
Piping Test No:
GAM-QCR-QAC-GTL-065
C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY
GAM-QCR-QAC-GTL-070
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Subsystem: Equipt.Tag No
Date of Inspection
PRESERVATION REQUIREMENTS
(ROTATIC EQUIPMENT)
GAMA REP.
LINDE REP.
QSGTL REP.
GAM-QCR-QAC-GTL-073
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Subsystem: Equipt.Tag No
8.Equipment low point drains shall be opened and checked for water
`
9. Check for “no welding permitted” signs stenciled at conspicuous location.
10. Check that test holes in reinforcement plates are open and greased.
12. Check surface for any transit damage and paint removal. Carry out touch up if required.
ORGANIZATIONS DATE NAME SIGNATURE
GAMA REP.
LINDE REP.
QSGTL REP.
GAM-QCR-QAC-GTL-074
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
1 Name Plate
3 Desiccant installed
4 Moisture present
8 Purge - pressure:
GAM-QCR-QAC-GTL-080
Report No:
FOUNDATION INSPECTION REPORT
Date:
ACTUAL
DEVIATION
TOLERANCE
REMARKS
FOUNDATION POCKET
POCKET DEPTH
NOTE:
THE ABOVE MENTIONED FOUNDATION IS ACCEPTED AND RELEASED FOR ERECTION ACTIVITIES
Date:
Equip. Description
GAM-QCR-QAC-GTL-115 PAGE 1 OF 2
REMARKS:
……………………………………………………………………………………………………..
……………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………
Name
Sign
Date
GAM-QCR-QAC-GTL-115 PAGE 2 OF 2
REPORT NO:
EQUIPMENT- SETTLEMENT MONITORING
DATE:
WEIGHT: NAME:
180°
270°
PLUMB: : _________________
ORIENTATION:_________________
GAM-QCR-QAC-GTL-116 PAGE 1 OF 2
THE SETTLEMENT OF THE ABOVE EQUIPMENT HAS BEEN SATISFACTORILY COMPLETED IN
ACCORDANCE WITH THE DRAWINGS AND SPECIFICATIONS (PAINTING AND INSTALLATION
EXCEPTION).
REMARKS:
----------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------------------------
GAMA
LINDE
GAM-QCR-QAC-GTL-116 PAGE 2 OF 2
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Q A T A R PUMP INSTALLATION PROCESS SHEET
The Installation of the above compressor has been satisfactorily completed in accordance with
the Drawings & Specifications
LINDE REP
QSGTL REP
GAM-QCR-QAC-GTL-120
REPORT NO.:
SITE INSPECTION REPORT
DATE:
Corrective Action:
NCR Required YES NO (Circle one) CTQ to Contractor Required YES NO (Circle one)
Remarks if any:
Discrepancy Corrected/Remarks:
Close-out of Corrective Action - Remarks: NCR No.: ___________________ CTQ No: ______________
GAM-QCR-QAC-GTL-127
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
PRIORITY/ COMPLETED(Date/Initials)
CATEGORY
ITEM NO ISO or DWG NUMBER DESCRIPTION OF WORK QSGTL or
(A,B,C,D,E) GAMA LINDE
its PMC
(X,Y,Z)
ALL PRIORITY A ITEMS SHOWN ABOVE HAVE BEEN VERIFIED AND ARE COMPLETED .INCOMPLETE PRIORITY B ITEMS
WILL BE TRANSFERRED TO THE MECHANICAL COMPLETION PUNCH LIST
GAMA REP
LINDE REP
GAM-QCR-QAC-GTL-128
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Q A T A R MECHANICAL EQUIPMENT ALIGNMENT REPORT
ITEM NO REPORT NO
COUPLING
DATE:
MANUFACTURER
COUPLING GAP
UNIT NO
PRELIMINARY ALIGNMENT (BEFORE PIPING CONNECTED):
DRIVER DRIVEN
SIGNED :
GAMA NAME DATE:
SIGNED :
LINDE NAME DATE:
SIGNED :
QSGTL or its PMC NAME DATE:
SIGNED :
GAMA NAME DATE:
SIGNED :
LINDE NAME DATE:
SIGNED :
QSGTL or its PMC NAME DATE:
GAM-QCR-QAC-GTL-132
C2 ASU PEARL GTL PROJECT Report No:
RAS LAFFAN INDUSTRIAL CITY
Date:
Q A T A R Equipment Box-Up Acceptance Sheet
Area:
It is hereby certified that the Equipment referenced has been mechanically completed in accordance with
Drawings, Specifications, Inspection and Test Records. The referenced Equipment is ready for box-up.
Equipment No
Equipment Designation
Vendor / Manufacturer
PID No
1 Name Plate,
CE-marking (if applicable)
2 Internals installed
3 Internal piping installed
4 Fillings completed
5 Refractory completed
6 Internal transport protection removed
7 Equipment internally clean and dry
8 Nozzles / manholes closed acc. drawing
9 Specified blind flanges installed
10 Specified nozzle gaskets installed
11 Specified bolts and nuts installed
12 Specified torques applied
13 Bolts lubricated (covers, manholes)
14
Remarks /
GAMA
VENDOR
LINDE
GAM-QCR-QAC-GTL-133