Вы находитесь на странице: 1из 41

THIS SUBMISSION IS DECLARED TO BE STRICTLY IN PROJECT DRAWING NUMBER

ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT PH10-1C-10-60-7001


CLIENT NAME

STAMP:

QATAR TRANSMISSION SYSTEM EXPANSION – PHASE 10


SUBSTATIONS PACKAGE S5 & S8
CONTRACT NO. GTC/371C/2010
CONSULTANT NAME

SUBSTATION NAME / CIRCUIT NAME

COMMON
220/66/11kV New Doha B Super Substation, 220/66/11kV Abu Hamur Super Substation
220/66/11kV Ain Khalid Super Substation, 220/66/11kV Lusail Development Super 3 Substation

0 07- 04- 12 ISSUED FOR COMMENTS Ramesh S.H.Baek W.B.Lee

REV. STAT. DATE DESCRIPTION DRAWN CHECK. APPRO.

CONTRACTOR NAME

MANUFACTURE NAME MANUFACTURE DRAWING NUMBER

DRAWING / DOCUMENT TITLE

LVDC STUDY OF SELECTIVITY AND SETTING OF PROTECTION

SCALE NTS SIZE A4 REV. PROJECT DRAWING NUMBER

SHEET 01 OF 41 SHEETS 0 PH10-1C-10-60-7001


1. PURPOSE
This document is intended to check a selectivity and setting of protection for 110V LV DC systems of
the 220/66/11kV New Doha B Super Substation, 220/66/11kV Abu Hamur Super Substation,
220/66/11kV Ain Khalid Super Substation, 220/66/11kV Lusail Development Super 3 Substation.

2. DESIGN INPUT
1) Technical Specification, Volume 3, Section 3.3.6 ‘LV Service Equipment’
2) Technical Schedule, (PH10-1C-10-60-T003)
3) LVDC Single Line Diagram, (PH10-1C-51-60-5001, PH10-1C-52-60-5001,
PH10-1C-81-60-5001, PH10-1C-82-60-5001)
4) LVDC DB Schematic Diagram, (PH10-1C-51-60-5003, PH10-1C-52-60-5003,
PH10-1C-81-60-5003, PH10-1C-82-60-5003)
5) LVDC Battery Charger Schematic Drawing, (PH10-1C-10-60-2002)

3. ASSUMPTION
1) Power Factor of 0.85 considered
2) Ambient Air Temperature is considered as 50°C

4. DESIGN CRITERIA
1) Low Voltage DC Basic Technical Values
- Nominal System Voltage: 110V
2) Study of selectivity and setting of protection is valid on four mode of operation as follows;
- Float Mode for trickle charging the batteries under normal DC loading condition.
- Equalizing Mode for periodic topping up of battery capacity and to correct the irregularities
of cell voltage and specific gravity. Selection shall be both auto and manual.
- Boost Mode for manual charging of batteries following a deep discharge or prolonged
absence of AC supply. This mode shall permit charging of the batteries only by manual mode
with auto – manual isolation of DC loads connected to the charger.
- Manual Charging Mode for commissioning of batteries.

2 OF 41 PH10-1C-10-60-7001_R0
5. SELECTIVIY PRINCIPAL

CHARGER 1 CHARGER 2

T4S320_320A

BATTERY 1 BATTERY 2
SBLE1600AH X 2: AHS, AKS, LDS-3 155.9kVA
SBLE1500AH X 2: NDBS

1000A

~ 110V ~
850A
BAT. CHAR.

1000A

1000A
NH4 800A gG

800A

K1 400A K2 400A
400A

K3
DIODE
A FUSE
PANEL
NH2 400A gG

DIODES
400A

DCDB
Total full load current (374.53A)
Note*
B INCOMING
T5N400_400A

BUS 1 630A 50°C (296.85A) BUS 2 630A 50°C (280.38A)

C COUPLER
T5N400_320A
D3 D2 D1 D4 D5
iC60L_32A iC60L_63A NS160DC iC60L_25A iC60L_10A
FEEDERS 160A

E
160A

1. BUS1 Max. Full Load Current: 296.85A


2. BUS2 Max. Full Load Current: 280.38A
3. BUS1 & BUS2 Max. Full Load Current: 374.53A
Note: (1) BUS1 load and BUS2 load is consist of a main and back-up power supply so that it was considered at the total load current calculation.
(2) Above full load current are based on 220/66/11kV Ain Khalid Super Substation loading data which is biggest substation.

3 OF 41 PH10-1C-10-60-7001_R0
Selectivity :

- Between A & B : a selectivity is not necessary because there is no differences on the system if it’s the first or
the second which is tripping.

- Between A & C : a selectivity is necessary because in the case of fault downstream a feeder, it should keep the
busbar supplied.

- Between A & D : a selectivity is necessary because in the case of fault downstream a feeder, it should keep the
busbar supplied.

- Between B & C : a selectivity is necessary because in the case of fault a bus zone, it should keep the other
busbar supplied.

- Between C & D : a selectivity is necessary because in the case of fault downstream a feeder, it should keep the
busbar supplied.

- Between C & E : a selectivity is necessary because in the case of fault downstream a feeder, it should keep the
busbar supplied.

- Between D1 & E : a selectivity is not necessary because there is no differences on the system if it’s the first or
the second which is tripping.

6. LIST OF FEEDERS

Protection Device
No. Feeder Description Type Setting
/ Trip Device
A FUSE 400A NH2 gG 400A Fuse

B LV DC BOARD INCOMER T5N 400 400A TMA

C LV DC BOARD COUPLER T5N 320 320A TMA

D1 NS160 DC 160A TM160DC

D2 iC60L 63A C curve

D3 LV DC BOARD FEEDERS iC60L 32A C curve

D4 iC60L 25A C curve

D5 iC60L 10A C curve

E FUSE 160A NH00 gG 160A Fuse

4 OF 41 PH10-1C-10-60-7001_R0
7. SELECTIVITY BETWEEN CHARGER FUSE & DCDB INCOMER
BREAKERS :

Discrimination Between : A-B

Selectivity between A & B

Supply side: Fuse – NH2 gG 400A (ABB)


Load side: MCCB – ABB_T5N400 400A (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)

There is not necessity to guarantee selectivity between A & B, however resetting of MCCB is much
easier, faster, cheaper and safe than replacement of fuses. Therefore it is better to guarantee selectivity
between the two.

Overload Zone
Please note that the maximum full load is 41,198 W.
Therefore, max. full load current = 41,198/110 = 374.53A (see below Table-1 on page 6)
The overload pickup of the incomer is 400A (400A x 1.0 setting). From the above curve, please note
the incomer breaker will trip first for the overload current starting from 400A up to 1023A. Therefore,
the breaker and fuse are well coordinated for the overload condition.

5 OF 41 PH10-1C-10-60-7001_R0
Short-circuit Zone
The through fault current of the battery is 21.82kA. This fault current is about 12.25kA in the LVDC
board after cable length between the battery and LVDC board. (Refer to attached short-circuit
calculation at DCDB on page 35-37) The overlapping between NH4-800A fuse and DC incomer
breaker occurs at over 20kA which is more than maximum fault current. Therefore 800A fuse is not
blown by the DCDB short-circuit fault, NH2-400A fuse or incomer breaker will trip first to block fault
current.

[Table-1]

6 OF 41 PH10-1C-10-60-7001_R0
8. SELECTIVITY BETWEEN CHARGER FUSE & DCDB COUPLER
BREAKER :

Discrimination Between : A-C

Selectivity between A & C

Supply side: Fuse – NH2 gG 400A (ABB)


Load side: MCCB – ABB_T5N400 320A (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)

Overload Zone
Please note that the maximum one DC bus load is 34,107 W.
Therefore, max. full load current = 32,653/110 = 296.85A (see above Table 1on page 6)
The overload pickup of the coupler is 320A. From the above curve, please note the coupler breaker
will trip first for the overload current starting from 320A up to 1357A. Therefore, the breaker and fuse
are well coordinated for the overload condition.

Short-circuit Zone
The through fault current of the battery is 21.82kA. This fault current is about 12.25kA in the LVDC
board after cable length between the battery and LVDC board. (Refer to attached short-circuit

7 OF 41 PH10-1C-10-60-7001_R0
calculation at DCDB on page 35-37) The overlapping between NH4-800A fuse and DC incomer
breaker occurs at over 20kA which is more than maximum fault current. Therefore 800A fuse is not
blown by the DCDB short-circuit fault, NH2-400A fuse or coupler breaker will trip first to block fault
current..

8 OF 41 PH10-1C-10-60-7001_R0
9. SELECTIVITY BETWEEN CHARGER FUSE & DCDB OUTGOING
FEEDERS :

Discrimination Between : A-D1, E

Selectivity between A & D1, E

Supply side: Fuse – NH2 gG 400A (ABB)


Load side: MCCB – Schneider_NS160 DC 160A (Thermal: 1.0, Magnetic: 8xIn) (Icu=100kA)

Overload Zone
In the overload zone, the load side breaker must trip more rapidly than the supply-side fuse because
there is no overlapping between two time-current curves.

Short-circuit Zone
In the short-circuit area, a selectivity is guaranteed by fuse E (160A). 160A fuse must trip rapidly more
than supply side 400A fuse. Therefore, selectivity is in order.

9 OF 41 PH10-1C-10-60-7001_R0
10. SELECTIVITY BETWEEN DCDB INCOMER BREAKERS & DCDB
COUPLER BREAKER :
Discrimination Between : B-C

Selectivity between B & C

Supply side: MCCB – ABB_T5N400 400A (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)
Load side: MCCB – ABB_T5N400 320A (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)

Overload Zone
Please note that the maximum one DC bus load is 34,107 W.
Therefore, max. full load current = 32,653/110 = 296.85A (see above Table 1on page 6)
The overload pickup of the coupler is 320A. From the above curve, please note the coupler breaker
will trip first for the overload current starting from 320A up to 400A, above which the incomer breaker
shall pick up in order to clear the fault. Therefore, the breakers are well coordinated for the overload
condition.

Short-circuit Zone
Short circuit discrimination is not possible between incomer and coupler breaker. These are only
guaranteed faults which occur up to 3.2kA by current discrimination.

10 OF 41 PH10-1C-10-60-7001_R0
11. SELECTIVITY BETWEEN DCDB COUPLER BREAKER & DCDB
OUTGOING FEEDERS :

1) Circuit Breaker 160A D1 (T3C160 TMD160)

Discrimination Between : C-D1

Selectivity between C & D1

Supply side: ABB_T5N400 320A (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)
Load side: Schneider_NS160 DC 160A (Thermal: 1.0, Magnetic: 8xIn) (Icu=100kA)

Overload Zone
Please note that the total UPS load is 18.6kVA. ie 18600 VA x 0.85 pf = 15810 W
Therefore, the max. full load current = 15810/110 = 143.73 A
The overload pickup of the UPS feeder is 160A. From the above curve, please note the UPS feeder
breaker will trip for the overload current starting from 160A up to 336.3A, above which the coupler
breaker shall pick up in order to clear the fault. Therefore, the breakers are well coordinated for the
overload condition.

11 OF 41 PH10-1C-10-60-7001_R0
Short-circuit Zone
In the short-circuit area, load side breaker will trip faster than coupler breaker however the gap of the
time is small to secure selectivity. So that a selectivity is guaranteed by load side 160A fuse. See the
below curve;

Coupler breaker trip time is 15ms in short-circuit condition, but 160A fuse is faster than 10ms.
Therefore 160A load side fuse must trip rapidly more than coupler breaker fuse.

12 OF 41 PH10-1C-10-60-7001_R0
2) Circuit Breaker 63A D2 (iC60L-C curve)

Discrimination Between : C-D2

Selectivity between C & D2

Supply side: ABB_T5N400 320A (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)
Load side: Schneider_iC60L In63 C curve (Thermal: Fixed, Magnetic: Fixed) (Icu=25kA)

Overload Zone
In the overload zone, the load side breaker must trip more rapidly than the supply-side breaker because
there is no overlapping between two time-current curves.

Short-circuit Zone
In the short-circuit zone, the load side breaker must trip more rapidly than the supply-side breaker
because there is no overlapping between two time-current curves.

Therefore C & D2 are total selectivity.

13 OF 41 PH10-1C-10-60-7001_R0
3) Circuit Breaker 32A D3 ((iC60L-C curve)

Discrimination Between : C-D3

Selectivity between C & D3

Supply side: ABB_T5N320 (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)


Load side: Schneider_iC60L In32 C curve (Thermal: Fixed, Magnetic: Fixed) (Icu=25kA)

Overload Zone
In the overload zone, the load side breaker must trip more rapidly than the supply-side breaker because
there is no overlapping between two time-current curves.

Short-circuit Zone
In the short-circuit zone, the load side breaker must trip more rapidly than the supply-side breaker
because there is no overlapping between two time-current curves.

Therefore C & D3 are total selectivity.

14 OF 41 PH10-1C-10-60-7001_R0
4) Circuit Breaker 25A D4 ((iC60L-C curve)

Discrimination Between : C-D4

Selectivity between C & D4

Supply side: ABB_T5N320 (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)


Load side: Schneider_iC60L In25 C curve (Thermal: Fixed, Magnetic: Fixed) (Icu=25kA)

Overload Zone
In the overload zone, the load side breaker must trip more rapidly than the supply-side breaker because
there is no overlapping between two time-current curves.

Short-circuit Zone
In the short-circuit zone, the load side breaker must trip more rapidly than the supply-side breaker
because there is no overlapping between two time-current curves.

Therefore C & D4 are total selectivity.

15 OF 41 PH10-1C-10-60-7001_R0
5) Circuit Breaker 10A D5 ((iC60L-C curve)

Discrimination Between : C-D5

Selectivity between C & D5

Supply side: ABB_T5N320 (Thermal: 1.0, Magnetic: 10x In) (Icu=36kA)


Load side: Schneider_iC60L In10 C curve (Thermal: Fixed, Magnetic: Fixed) (Icu=25kA)

Overload Zone
In the overload zone, the load side breaker must trip more rapidly than the supply-side breaker because
there is no overlapping between two time-current curves.

Short-circuit Zone
In the short-circuit zone, the load side breaker must trip more rapidly than the supply-side breaker
because there is no overlapping between two time-current curves.

Therefore C & D5 are total selectivity.

16 OF 41 PH10-1C-10-60-7001_R0
ANNEXURE

17 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline
Low Voltage Selectivity Theoretical Outline

18 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

19 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

20 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

21 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

22 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

23 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

24 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

25 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

26 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

27 OF 41 PH10-1C-10-60-7001_R0
ANNEX 1. LV Selectivity Theoretical Outline

28 OF 41 PH10-1C-10-60-7001_R0
ANNEX 2. Protection Discrimination

29 OF 41 PH10-1C-10-60-7001_R0
ANNEX 2. Protection Discrimination
Protection Descrimination

30 OF 41 PH10-1C-10-60-7001_R0
ANNEX 3. Fuse Time-Current Curves
Time-Current Trip Curve

31 OF 41 PH10-1C-10-60-7001_R0
ANNEX 3. ABB_T5N Time-Current Curves

32 OF 41 PH10-1C-10-60-7001_R0
ANNEX 3. Schneider_NS100DC to NS250DC Time-Current Curves

33 OF 41 PH10-1C-10-60-7001_R0
ANNEX 3. Schneider_iC60L Time-Current Curves

34 OF 41 PH10-1C-10-60-7001_R0
ANNEX 4. Short-Circuit Analysis

SHORT-CIRCUIT ANALYSIS

35 OF 41 PH10-1C-10-60-7001_R0
ANNEX 4. Short-Circuit Analysis

36 OF 41 PH10-1C-10-60-7001_R0
ANNEX 4. Short-Circuit Analysis

37 OF 41 PH10-1C-10-60-7001_R0

Вам также может понравиться