TRAINING PLAN

Qualification : Electrical Installation and Maintenance NC-II


Trainees’ Training Training Mode of Staff Facilities/Tools Venue Assessment Date and
Requirements Activity/ Training and Equipment Method Time
Tasks
1. Install 1.1 Plan OJT Mr. Bryan  Pencil with Work  Demonstration December
electrical and prepare Rodica- eraser Place  Oral 15, 2018/
protective devices work Student  Bond paper questioning 8:00-5:00
for distribution, Assistance  White Board pm 8hrs
power, lighting,  White Board
auxiliary, Marker
lightning  White Board
protection and Eraser
grounding Magnetic
systems  Pencil
Sharpener
 Spirit Level
1.2 Install OJT Mr. Bryan  Electrician Work  Demonstration December
electrical Rodica- Pliers Place  Oral 16-17,
protective Student  Phillips screw questioning 2018/
devices Assistance driver 8:00-5:00
 Flat Screw pm 16hrs
driver
 Wire splicer
 Wire stripper

document #:
CBLM on date developed: Issued by:
Trainers Methodology Level 1 November 2018 Subic Bay Colleges, Inc. page 1of2
EIM NC-II developed by:
E.D. PADULLON
date modified:
modified by: revision #:00
 Tools Holster
 1 Unit multi-
tester(Analog/
Digital)
 Long nose
 Side cutter
1.3 Install OJT Mr. Bryan  Electrician Work  Demonstration December
lighting Rodica- Pliers Place  Oral 18-19,
fixture and Student  Phillips screw questioning 2018/
auxiliary Assistance driver 8:00-5:00
outlet  Flat Screw pm 16hrs
driver
 Wire splicer
 Wire stripper
 Tools Holster
 1 Unit multi-
tester(Analog/
Digital)
 Long nose
Side cutter
1.4 Notify OJT Mr. Bryan Work December
completion Rodica- Place 20, 2018/
of work Student 8:00-12:00
Assistance pm 4hrs

document #:
CBLM on date developed: Issued by:
Trainers Methodology Level 1 November 2018 Subic Bay Colleges, Inc. page 2of2
EIM NC-II developed by:
E.D. PADULLON
date modified:
modified by: revision #:00