We have deployed 8-9 piping and 1 electric Teams since 13-07-11 for completion of fire
suppression system who will complete Mall Area by 21ST August & Basements by 31ST August
2011 as per following methodology:
We have deployed 3 Ducting Teams, 2 Insulation, 2 Cladding, 3 Piping and 2 Grilles Fixing Teams
for completing the Mall by September 15, 2011 as per following methodology:
Mezzanine AHU-1
Condensate Drain - Floor Cutting ICPL to resolve
Ducting / Insulation - - Completed
Piping Insulation - - Completed
Cladding Naeem Team 2 - 14-17 / 08 /11
Mezzanine AHU-2
Condensate Drain - - Completed
Ducting / Insulation - - Completed
Piping Insulation - - Completed
Cladding Naeem Team 2 - 18-21 / 08 /11
By Mr. Nasim /
Flushing & Water Filling Guidelines