August 13, 2011

WORK METHODOLOGY FOR FIRE SYSTEM


DOLMEN SHOPPING MALL, CLIFTON, KARACHI

We have deployed 8-9 piping and 1 electric Teams since 13-07-11 for completion of fire
suppression system who will complete Mall Area by 21ST August & Basements by 31ST August
2011 as per following methodology:

S.# Work Team Bottlenecks Date


1 10” dia Valve (PRESENTLY) Hanif Team 1 Under clearance 12-14 / 08 / 11
2 ACV – 18 (check valves) Hanif Team 2 12-14 / 08 / 11
3 UEE Store Piping Hanif Team 3 12-18 / 08 / 11
4 ACV-11 (PRV) Hanif Team 1 16-17 / 08 / 11
5 Water Connection Hanif Team 1 15-16 / 08 / 11
6 Cooling Tower, Makeup Hanif Team 1 12-13 / 08 / 11
7 Fire Brigade Conn. (5 days) Iqbal Team 1 Core Cutting After Rains
8 Fire Hydrant Piping (15 days) Iqbal Team 2 - do - - do -
9 Sprinklers Hanif Team 4 13/07/11 – 24/8/11
Fire Pump Room
F.A. Ducting Zaheer Team 1 19-23 / 08 / 11
Silencer Piping 8” (50’) Hanif Team 2 15-18 / 08 / 11
Motor Connection + Tray Covers Sohail Team 1 13/07/11 – 14/08/11
Main Header Supports Hanif Team 1 17-18 / 08 / 11
Supply Header Supports Hanif Team 1 19-20 / 08 / 11
Gauges, Drain Valves Hanif Team 1 20-21 / 08 / 11
Genset Return Piping to Tank Hanif Team 2 19-20 / 08 / 11
10” Fire Valves (PRESENTLY) Hanif Team 1 On clearance 19-23 / 08 / 11
Landing Valves / Reels Faiz Team 1 18-30 / 08 / 11

Mall Area Completion Time 21-08-2011:

S.# Work Team Bottlenecks Date


Ground Floor / Mezz:
Landing Valves - - Completed
Sprinkler Piping - - Completed
Sprinklers - - Completed
Zone Valves / AHU Sprinklers Khalid Team 1 On clearance 19-20 / 08 /11
First Floor:
Landing Valves - - Completed
Sprinkler Piping - - Completed
Sprinklers - - Completed
Zone Valves / AHU Sprinklers Khalid Team 1 On clearance 20-21 / 08 /11
Second Floor:
Landing Valves Faiz Team 1 - 13-17 / 08 /11
Sprinkler Piping - - Completed
Sprinklers - - Completed
Zone Valves / AHU Sprinklers Khalid Team 2 On clearance 20-21 / 08 /11

Flushing & Water Filling By Mr. Nasim /


Guidelines FND
August 13, 2011

WORK METHODOLOGY FOR HVAC WORKS


DOLMEN SHOPPING MALL, CLIFTON, KARACHI

We have deployed 3 Ducting Teams, 2 Insulation, 2 Cladding, 3 Piping and 2 Grilles Fixing Teams
for completing the Mall by September 15, 2011 as per following methodology:

S.# Work Team Bottlenecks Date


AHU Rooms (2) Basement 5000
Condensate Drain Piping Mobin Team 1 12-15 / 08 / 11
Duct & Grilles Zaheer Team 1 Can be Grilles 16 / 08 / 11
Louvered Door Hi Tech Can be Supplier 14 / 09 /11
Piping / Teswting Khalid Team 1 13-17 / 08 /11
Pipe Insulation Asghar Team 1 18-20 / 08 /11
Cladding Naeem Team 1 23-25 / 08 /11

AHU Rooms (5) Basement 2000


Condensate Drain Piping Mobin Team 1 16-19 / 08 /11
Pipe Testing Khalid Team 1 12-13 / 08 /11
Pipe Insulation Asghar Team 1 14-17 / 08 /11
Cladding Naeem Team 1 19-22 / 08 /11

Ground Floor (Toilets Area)


Ducting / Insulation - - Completed
Drain Piping - - Completed
Piping / Insulation - - Completed
Cladding Naeem Team 1 & 2 13-14 / 08 /11
Ground Floor (Hyperstar)
Ducting / Insulation Zaheer Team 2 16 / 08 /11
Drain Piping Mobin Team 2 12-15 / 08 /11
Piping / Insulation - - Completed
Cladding Naeem Team 1 14-18 / 08 /11

Mezzanine AHU-1
Condensate Drain - Floor Cutting ICPL to resolve
Ducting / Insulation - - Completed
Piping Insulation - - Completed
Cladding Naeem Team 2 - 14-17 / 08 /11

Mezzanine AHU-2
Condensate Drain - - Completed
Ducting / Insulation - - Completed
Piping Insulation - - Completed
Cladding Naeem Team 2 - 18-21 / 08 /11

Mezzanine AHU 4-5


Condensate Drain Mobeen Team 2 - 16-18 / 08 /11
Ducting / Insulation - - Completed
Piping Insulation - - Completed
Cladding Naeem Team 2 - 22-25 / 08 /11
S.# Work Team Bottlenecks Date
First Floor:
Condensate AHU Room C-6/7 - - Completed
Condensate AHU Room 5 & 6 Mobeen Team 3 - 12-13 / 08 / 11
Condensate AHU Room 7/8 Mobeen Team 3 - 13-14 / 08 / 11
Condensate AHU 4 Mobeen Team 3 - 14-15 / 08 / 11
Condensate AHU 3 Mobeen Team 3 - 15-16 / 08 / 11
Condensate AHU 2 Mobeen Team 3 - 16-17 / 08 / 11
Condensate AHU 1 Mobeen Team 3 - 17-18 / 08 / 11

Second Floor AHU 2, 7, 18, S1


Condensate Drain Mobeen Team 2 - 19-23 / 08 /11
Ducting / Insulation Zaheer Team 1 Dwg by FND 17-23 / 08 / 11
Piping Insulation Asghar Team 1 - 21-23 / 08 /11
Cladding Naeem Team 1 - 26-30 / 08 /11

Second Floor AHU 8,9,10,11,12


Condensate Drain Mobeen Team 1 - 20-23 / 08 /11
Louver opening
Ducting Zaheer Team 2 12-19 / 08 / 11
by ICPL
Duct Insulation Zaheer Team 3 - 20-31 / 08 / 11
Piping Insulation Asghar Team 1 - 24-27 / 08 /11
Cladding Naeem Team 2 - 26-30 / 08 /11

Second Floor AHU 13,14,15


Condensate Drain Mobeen Team 3 - 19-22 / 08 /11
Duct Insulation Zaheer Team 1 - 24-28 / 08 / 11
Piping Insulation Asghar Team 2 - 29-30 / 08 /11
Cladding Naeem Team 1 - 01-05 / 09 /11

Second Floor AHU 16 & 17


Condensate Drain Mobeen Team 2 - 24-26 / 08 /11
Duct Insulation Zaheer Team 1 - 29-30 / 08 / 11
Piping Insulation Asghar Team 1 - 28-30 / 08 /11
Cladding Naeem Team 2 - 01-05 / 09 /11

Second Floor AHU S-6, 7, 8


Condensate Drain Mobeen Team 1 - 24-27 / 08 /11
Piping Insulation Asghar Team 1 - 01-04 / 09 /11
Cladding Naeem Team 1 - 06-10 / 09 /11

Second Floor AHU S-19, 20


Condensate Drain Mobeen Team 2 - 27-30 / 08 /11
Ducting Zaheer Team 2 - 20-22 / 08 / 11
Pipe Insulation Asghar Team 2 - 01-04 / 09 /11
Cladding Naeem Team 2 - 06-10 / 09 /11

Third Floor AHU’s S-9, 10 Area N/A

SLOT DIFFUSERS Up to Sep 15, 2011


Shops Ground & First Floor:
PIPING 3 TEAMS 20/07/11 – 14/08/11
TESTING 3 TEAMS 15-16 / 08 /11
PIPE Insulation 2 TEAMS 16-20 / 08 /11
Cladding 2 TEAMS 17-16 / 08 /11

By Mr. Nasim /