Академический Документы
Профессиональный Документы
Культура Документы
METHOD STATEMENT
FOR
DEMOLITION OF RETAINING WALL &
INSTALLED PILES EXTRACTION WORK
Building No.(M1), 4th Floor, Upper Pansodan Road, Kandawgyi Housing Development,
Website: www.depawaddy.com
Sheet piles (Type‐III‐A, 12m Lengths) will be installed for portion‐1 at 3m away from
existing retaining wall at river side to prevent the soil collapse when excavation of
existing wall and demolition process.
3.3.2 Excavation and Demolition of R‐wall
Excavation will be done at both side of the R‐Wall up to ‐8 Ft Level for first step
demolition as
shown in below figure.
Bottom R‐Wall and Slab will be demolished with excavator mounted breaker and disposal
the debris out of the side.
3.3.3 Extraction of Piles
Installed piles below R‐wall slab will be extracted by vibro‐hammer which will be
attached at
50 ton crawler crane. (Assuming pile size is 8”x8” / 10”x10” / 12”x12” and penetration
not more than 6m). If the pile is more than 6m and can’t extract, confirm with engineers
and terminate the extraction work.
3.4. Backfill after pile extraction
After extraction of piles excavated area will be backfill with excavated soil and compact to get
working space for extraction of temporary sheet piles.