TABLE OF CONTENT
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
REVISION SHEET 1
TABLE OF CONTENT 2
1. GENERAL 3
1.1 Project Description 3
1.2 Objective 3
1.3 Definition 3
1.4 Codes & Standard 3
1.5 Abbreviation 4
2. RESPONSIBILITIES 4
3. GENERAL PRE-REQUISITES 6
3.1 Safety Preparedness 6
3.2 Mechanical Completion 7
3.3 Availability of Equipment, Tools, Consumables and Other Materials 7
4. DOCUMENT COMPLETION 7
5. COMMISSIONING PROCEDURE 8
5.1 Preparation for Gas in8
5.2 Commissioning Step 8
6. PROVIDE SPARE PART EQUIPMENT OR UTILITIY 12
7. ACCEPTANCE CRITERIA 12
8. ATTACHMENT 13
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
1. GENERAL
1.1 Project Description
PT Pertamina Gas intends to build new gas pipeline from Semare station,
which have two tie in point from Isargas Metering and Parnaraya Metering, to
Porong Grati Future Connection Station which has tie into existing pipe line Porong
Grati. The pipeline is about 8100 meter will be completed with piq launcher and piq
receiver.
1.2 Objective
The objective of this document is to guide the preparation and activity of
Commissioning for project "Pembangunan pipa gas diameter 16” sepanjang 8100
meter Semare – tie in pipeline Porong Grati” and ensure that all pipeline, valve and
accesories system are fully tested and commissioned.
1.3 Definition
ASME B31.8 Gas Transmission and Distribution Piping System (ed. 2010).
ASME B31.3 Process Piping.
ASME B16.5 Pipeline Flanges and Fittings.
ASME B16.9 Factory Made Wrought Steel Butt Welding Inductions Bends
for Transportation and Distribution System.
ASME VIII Div.1 Rules for Construction of Pressure Vessel
AGA- 8 Compressibility Factors of Natural Gas
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
1.5 Abbreviation
2. RESPONSIBILITIES
Project Manager Shall be responsible for all activities
Construction Manager Shall report to the Project Manager. Shall be responsible for
construction activities related to this procedure, and shall
coordinates with the QA/QC Manager, HSE Manager Supervisor
for implementation of this procedure.
QA/ QC Manager Shall report to the Project Manager. Shall be responsible for
overall quality matters described in this procedure
activities, conform to Procedure, Codes/ Standards.
HSE Manager Shall report to the Project Manager. Shall be responsible for
HSE performance and where QA necessary initiating
corrective action through line management.
HSE Coordinator Shall report to HSE Manager, Monitoring the safety of all
working practices. Coordinating with Employer supervisor for
all activities. Introduce implementation of HSE plan and
procedure to all personnels. Coordinating and monitoring all
activities accordingly in safety manners. Prepare emergency
response plans and mitigation of hazards equipment.
HSE Inspector Shall report to HSE Coordinator. Prepare Job Safety Analysis
(JSA). Perform safety briefing at site. Controlling and observing
of vehicle at work site. Perform routing check gas with gas
detector.
Supervisor Ensuring that the work permit are carried out. Familiarizing
himself and his operators, with the details of the overall
procedure including Welding Procedures, Tapping Procedures.
Coordinating with Employer supervisor for all activities.
Ensuring all personnel involved, understand of procedures and
scope of work and all materials comply with specification.
Supervise all activities of leakage test and gas in and make
sure working properly. Prepare equipment, worker and work
plan. Schedulling and controlling activities and ensuring on
time completion according to plan. Report all activities of
leakage test and gas in to Construction Manager.
3. GENERAL PRE-REQUISITES
Checklist for each pre-requisition item refer to Attachment-1 and detail of equipment,
tools and material refer to Attachment-2.
4. DOCUMENT COMPLETION
The following document items shall be submitted :
Design Basis.
Precommissioning check list.
Start up & Shutdown procedure (normal Operation) for each equipment.
Start up station Procedure.
Normal Operation (station) Procedure.
Shutdown station Procedure (normal & emergency condition).
Manual Instruction & Trouble Shooting Procedure for each equipment.
Emegency procedure.
Pra-Startup Safety Review.
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
5. COMMISSIONING PROCEDURE
No Action Remark
1 Safety Equipment
1.1 Personal Protective Equipment:
Coverall/ Wearpack
Safety Helmet
Hand Glove
Safety Glasses
Ear Plug (If Necessary)
1.2 Baricade & Safety Sign
1.3 Gas Detector
1.4 Portable fire Extinguisher
1.5 Fire Truck & Fire Fighters tim (standby at Location)
1.6 Ambulance and medics (standby at Location)
2.1 Instrumentation:
Ensure all instrumentation ( Pressure Indicator) have been calibrated and ready to used.
Ensure Pig indicator is already checked and ready to be used
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
2.2 Electrical:
Electrical system has been checked and commissioned.
All electrical equipment has been loop check (Tested).
Electrical utilities preparation such as;
Solar Panel System/ electricl source temporary
2.3 Equipment:
Ensure all equipment installed are ready to used.
Ensure functionally of SDV has been tested and ready to used.
Ensure Temporary vent is installed.
All block valve is start up position.
2.4 Purging Procedure of Pipeline from Semare Station to Future Connection Porong-Grati
Station:
Ensure all future connection valves connected to blind flanges/caps on piping in both
station.
Put all valves on the position ready for commissioning as indicated at Attachment-3.
Step by steps N2 Purging for Pipeline :
Purging N2, Inject from valve 3/4”-BV-031 & 3/4”-BV-032 , with purity reach 99% and
dew point reach -200C until there is no O2 content in Piping system.
Step 1, make sure valve with tag number 16”-BV-002, 16”-BV-009, 16”-BV-004, 16”-BV-
007, 16”-BV-008, 12”-BV-045, 12”-BV-046, 10”-BV-011, 10”-BV-012, 10”-BV-043, 10”-
BV-044, 10”-BV-005, 8”-BV-013 & 8”-BV-014 are closed (another 16” valve are open).
Make sure gas indicator detected N2 from 3/4”-BV-028 (make tee connection before PI-
001) & 3/4”-BV-039. For monitoring pressure from PI-001 & PI-005 (another 3/4” valve
are closed). So SDV-001 is closed.
Start to purge pipeline.
When N2 is fully charged with 50 psig pressure then hold for 15 minutes then check with
gas detector with O2 indication.
Check O2 indication with gas detector, if more than 1 % it must be re-purged until the
O2 content is less than 1 %.
Check and make sure that the dew point content is less than -20 °C.
Ensure O2 content maximal 1% and nitrogen content minimum 99% and maintained the
minimum pressure at 2-3 barg until process gas in.
Step 2, inject N2 from ¾” BV-040.
When N2 is fully charged with 50 psig pressure then hold for 15 minutes then check with
gas detector with O2 indication from ¾” BV-027.
Re-check and make sure that the dew point content is less than -20 °C and O2 content
is less than 1 %.
SCHEMATIC PURGING N2 PIPELINE
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
Step 1, make sure valve with tag number 16”-BV-002, 16”-BV-009, 16”-BV-004, 16”-
BV-007, 16”-BV-008, 12”-BV-045, 12”-BV-046, 10”-BV-011, 10”-BV-012, 10”-BV-043,
10”-BV-044, 10”-BV-005, 8”-BV-013 & 8”-BV-014 are closed (another 16” valve are
open). For monitoring pressure from PI-001 & PI-005 (another 3/4” valve are closed).
realese N2 from valve with tag number 3/4”-BV-039
N2 & methane (CH4)content at temporary vent (3/4”-BV-039) by using gas indicator.
Parallel with this proses when raising pressure gradually, every step, check flange
connection and make sure no have leakage. If leakage happened, do the bolt
tightening until no leakage indication found.
Next, If N2 content get 1 % and methane (CH4) content get 99% and the gas indicator
has shown 100 % LEL means N2 inside pipeline has run out and the gas in process is
succed. closed temporary vent 3/4”-BV-039.
Install pressure indicator temporary at BV-039, and then setting opening percentage of
12”-BV-009 until temporary pressure indicator showing pressure 630 psi and less.
Piping and Pipeline system gas in is complete.
7. ACCEPTANCE CRITERIA
Commisioning is considered as completed if the following criteria are fulfilled:
1. Gas in :
a. CH4 contain in pipeline and metering system has reached minimum level
95%.
b. No leak is detected during gas delivery and pressurizing at 5%, 15%
25%, 50% and 100% of operating pressure.
2. Performance Verification :
a. Actual verification that the instrumentation has perform properly.
b. Actual verification that the gas filter has perform properly.
c. Actual verification that the valves have perform properly.
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
8. ATTACHMENT
Attachment – 1 Pre-Requisition Check List
Attachment – 2 Equipment and Tools List
Attachment – 3 Valve Initial Final Position List
Attachment – 4 Commissioning Committee & Communication Plan
Attachment – 5 P& ID (purging & gas in)
Attachment – 6 Prosedur Pertolongan Pertama
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning
COMMISSIONING PROCEDURE
Attachment – 1 PRE- REQUISITE CHECK LIST
No Description Status Remark
1 All piping are filled with nitrogen to a minimum 0.5 barg
2 All Instrumentation equipment has been calibrated and loop,
function, and sequential test have been performed.
3 All packing, media, and chemicals have been applied inside
equipment
4 All temporary equipment in the piping has been removed and has
been installed permanent equipment
5 All related documents: approved PFD/ P&ID, Commisioning
Procedures, Inspection Test Procedure, HSE procedures,proposed
commissioning team organization.
6 Check metering system are "Ready to Gas-in"
7 Area metering shall be considered as a hazard area. Safety signs,
barricade/fence, flash light, megaphone and displayed ERP, ERT,
shall be put around that area.
8 Area around venting point shall considered as a hazard area.
Methane gas detection shall be provided. Temporary barricade or
fence and safety sign around venting point shall be provided during
venting work.
9 Fire truck shall be provided at metering system.
10 Ambulances and paramedic shall be provided at metering system,
while emergency cars.
11 Portable fire extinguishers shall be provided for each metering
system
12 Mobile telephone and/or radio (handy talky) shall be provided for
communication. Mobile telephone shall be used at the outside of
metering fence.
13 Work permit shall be obtained from Area Authorizer.
14 Fire and evacuation drill shall be conducted prior of commissioning.
15 Ensure Basic Safety Training for all site personnel has been
conducted.
16 Joint safety patrol shall be performed daily by CONTRACTOR's
safety officer and the EMPLOYER safety office.
17 Regular tool box meeting shall be performed daily
COMMISSIONING PROCEDURE
Attachment – 2 Equipment & Tools List
No Parameter PIC Location Quantity Status Remark
1 PPE HSE&S
a. Wear Pack HSE&S
b. Safety Helmet
c. Safety Shoes
d. Hand Gloves
e. Raincoat
2 Portable Fire Extinguisher HSE&S
3 Display ERP HSE&S
4 ERT HSE&S
5 Emergency Contact List HSE&S
6 Warning Tapes HSE&S
7 Portable Gas Detector HSE&S
8 First Aid Kit HSE&S
9 Warning Sign Box: AWAS ADA GAS DILARANG HSE&S
MEROKOK & MENYALAKAN API DISINI
10 Flag HSE&S
11 Megaphone HSE&S
12 Medic HSE&S
a. SCBA HSE&S
b. Stretcher HSE&S
c. Ambulance HSE&S
d. Nurse HSE&S
General Tools
13 Spare part & Consumables Constrc
a. Grease Gun
b. Cotton Bag
c. Bubble fluid
d. Masking Tape
14 Tool Set Constrc
15 Anti Spark Hammer Constrc
16 Open- End Wrench (Kunci Pas) Constrc
17 N2 Bottle Constrc
18 Handy Talky HSE&S
19 Ladder Constrc
20 Digital Camera (Image & Video) HSE&S
21 Genset + LIghting Constrc
22 Pad Lock- Mater Key HSE&S
Attachment -3 Valve Piping & Pipeline Initial Final Position List (By PDC)
Initial Posistion
No Valve Tag Number From Before On Progress Final Position Remark
ISARGAS METERING Commissioning
PIER STATION
COMM. COORDINATOR
Name
Phone
RED ZONE
Date : Dec 04, 2017 Prosedur Gas-in dan Commissioning