Академический Документы
Профессиональный Документы
Культура Документы
an introduction
good building guide
Charles Stirling
BRE Scotland
Building all, or some components, of buildings off site in a factory has been
a feature of construction over many generations, and in some cases has
been adopted extensively (eg door and window sets). Many terms have
been used to describe this off-site construction (prefabrication, off-site
assembly, factory assembly, pre-assembly, off-site manufacture, etc.). In
this Guide the term ‘off-site construction’ will be used to refer to any part
of the construction process that is carried out in controlled conditions
away from the actual site where the building is or will be sited. In the post-
war period, prefabricated construction unfortunately acquired negative
connotations. However, with developments in lightweight, high strength
materials and modern production techniques, prefabrication has much to
offer today’s construction industry.
This Good Building Guide provides an introduction to the techniques and
methods of off-site construction and suggests how these might be
adopted within the modern construction process.
Photograph courtesy of Kingspan
Off-site construction is often perceived as highly where a large volume of prefabricated components
specialised and to many designers and specifiers is are being used then the individual production costs
only applicable to a limited number of and overall project cost can be reduced.
construction projects. There are, however, many To realise the full benefits of off-site
examples of off-site construction being construction, the project team needs to address the
incorporated within the mainstream construction specification and construction implications as
process [eg stairs, doors and window sets, early as possible in the design process. The
composite cladding panels, prefabricated integration of prefabricated components should
foundation systems (Figure 1) and insulated become an inherent part of the overall design,
walling panels (Figure 2)] and building services rather than simply offering an alternative to an
(air-conditioning or refrigeration packs). already determined design solution. As shown in
When properly integrated early in the design Figure 3, disproportionate costs and subsequent
process, off-site assembled components, waste can arise during the construction project or
assemblies and service runs can have a major during the life of a building from a failure to fully
impact on the construction process and can lead to understand the implications of the design.
improved performance by way of reduced times Figure 3 highlights the potential for cost
on site and improved quality. Prefabricated reduction and alternatively the resistance to the
assemblies may initially cost more but reduced on- cost of change during the project life. As the
site assembly times and increased control over site project progresses, the opportunities for
processes should reduce risks and in many cases implementing variation or change reduce and the
the overall project costs should be no more than consequent costs associated with these variations
those of conventionally constructed projects. rise substantially. Typically, around 80% of the
Where there is a repeat aspect to the project or construction costs are fixed within the first 20% of
2
Figure 1 Prefabricated beam installation in progress on piles. The beams can be omitted
and modular structures can be installed to span directly onto piles and pile caps
Cost
Cost Resistance Cost to
reduction to change change
potential
the design process and considerable cultural change is required to address issues
beyond the developmental design stage. Where off-site production techniques are
to be used these should be introduced early in the process.
Many of the developments in off-site construction are as a direct result of the
technical efforts involved in developing non-traditional, prefabricated mass
housing, schools and hospitals in the post-war period. In more recent times, skills
shortages on site, higher thermal requirements and increased client expectations
have resulted in off-site construction becoming a feature of hotel and office
developments. Systems are being developed by concrete panel and timber and steel
frame manufacturers for the private and social housing sectors (Figures 4 and 5).
The following sections provide a basic guide to the generic forms of off-site
construction. Off-site construction techniques require strict site tolerances in the
location of foundations, supporting ground structures and of incoming and
outgoing services.
Panels
Taking the framed approach one step further, pre-assembled floor, wall and roof
panels, which incorporate both a structural and infill element, are simply fitted
together on site. Panel systems rely heavily on the use of sealants between panels
and offer rapid erection times for buildings. At their simplest, panel systems can
form lightweight infill panels that are fixed to the structural frame. At their most
complex, prefabricated sandwich panels can provide the structural element and
internal and external finishes.
Figure 9 Volumetric units, fitted out in the factory, provide rapid assembly of completed
buildings
Figure 10 Modern boilers and controllers delivered to site completely assembled and
ready for connection; pipe runs can also be pre-assembled
5
Getting started
All projects require some point in time when the client makes the active decision to
construct. During this phase, the client, depending on their experience of
construction, may appoint a specialist advisor. It is the responsibility of this advisor
to determine whether the construction of a building is what is required, normally by
value management workshops. The client’s needs may well be satisfied by an
6
(a) (b)
Figure 12(a), (b) The project cycle requiring input by design, construct and supply teams