BRIDGE INSPECTION

Construction and maintenance of bridges along national roads


(replacement of permanent weak bridges)
Princesa bridge (B02425 LZ)
Along Lucena-Tayabas-Lucban-Sampaloc-Mauban Port Road

Abrihan, Mikaela Joyce Ann L.

Bongay, Amalia Zestinne

Booc, Reynalene O.

Cabesuelas, Giovanni A.

De Luna, Raphael L.

Epifanio, Tristan

Maaño, John Robert C.

Ong, Rodelo S.

Opis, John Carlo M.

Zabalerio, Kenneth John S.


NARRATIVE REPORT

The project entitled “Construction and maintenance of bridges along national roads
(replacement of permanent weak bridges) Princesa bridge (B02425 LZ)”, consisting of 2 lanes,
located along the Lucena-Tayabas-Lucban-Sampaloc-Mauban port road, the bridge having a
length of 41 meters and the total project having a length of 379 meters. The bridge has a starting
elevation of 134+614.45 and ends at 134+655.45. At least two of the remaining, Spanish-era
bridges in Tayabas, Quezon province, are in danger of being altered or altogether destroyed
because of a road-widening project by the Department of Public Works and Highways (DPWH).
The project will construct a new girder type bridge which will replace the old Princesa
bridge. This will widen modern bridges to over two lanes, affecting Puente de Gibanga and
Puente de Princesa, two of 12 surviving 19th- century bridges in Tayabas. These bridges were
collectively declared National Cultural Treasure by the National Museum in 2011.In the 2011
declaration, National Museum describe the Tayabas bridges as “testaments to ingenious
engineering and construction styles which pave the way for development [of several towns],
ideally without harmful consequences to the natural environment.”

Indicated in the contract is the completion date of the project which will be finished by
October 12, 2018, but due to a petition about the old Princesa bridge being one of the 12 bridges
that survived in the World War II, causing the completion date of the contract to become
uncertain and 2 of the lanes left unfinished. For this reason the completion of this project is not
definite.

The bridge was built due to the surveys executed indicating of heavy traffic experienced
in the parts of where the old bridge was erected, as a solution, the development of a new bridge
to lessen heavy traffic in the area was implemented this was the primary reason for the
construction of the bridge and to further economic development in the said areas.

The materials used are the following:


DESCRIPTION UNITS QUANTITY
BRIDGE CONSTRUCTION
Concrete piles cast in drilled holes, 1.50m dia M 318.00
Pile Integrity Testing (Low Strain) EA 4.00
High Strain Dynamic Load Testing (PDA) EA 10.00
Concrete Railing (Standard) M 80.20
Structural Steel, furnished and fabricated KG 7,799.13
Reinforcing Steel Bar, Grade 40 KG 3,749.00
Reinforcing Steel Bar, Grade 60 KG 61,911.00
Structural Concrete, Class A, 20.68MPa @28days CU. M. 479.10
Prestressed Structural Concrete Members (I-Girder type VI, EA 10.00
L=40.10 l.m)
Lean Concrete CU.M. 4.70
Elastomeric Bearing Pads EA 20.00
Preformed Sponge Rubber Joint Filler CU. M. 2.29
Drain Pipe, Galvanized 100mm dia I. M. 12.00
PROJECT DETAILS
Project Title: Construction and maintenance of bridges along national roads (replacement of
permanent weak bridges) Princesa bridge (B02425 LZ)
Location: Along Lucena-Tayabas-Lucban-Sampaloc-Mauban port road
Bridge length: 41m
Road Net Length: 379m
Date Started: April 10, 2017
Contract Completion Date: October 12, 2018
Contract Cost: Php 86,849,926.36
Implementing Office: DPWH Region IV- A

Hydraulic Parameters
Drainage Area A: 11.10 sq km
Design Discharge Q:
50 year return period. -358.00 cu.m/s
With Freeboard 100 year Return Period. 400 cu.m/s
Design Velocity: 4.25m/s average
Design Flood Level FDL: 75.40m
Ordinary water level OWL : 70.00m
Scour Depth: 1.00m
Analysis based on rational method using PAG-ASA Rainfall data at Tayabas Weather
Station.

SUMMARY OF QUANTITIES FOR BRIDGES


DESCRIPTION UNITS QUANTITY
EARTHWORKS
Removal of Structures and Obstructions (Concrete) CU. M. 130.73
Removal of Structures and Obstructions (Steel) KG 88,186.84
Bridge Excavation (Common Soil) CU. M. 167.44
BRIDGE CONSTRUCTION
Concrete piles cast in drilled holes, 1.50m dia M 318.00
Pile Integrity Testing (Low Strain) EA 4.00
High Strain Dynamic Load Testing (PDA) EA 10.00
Concrete Railing (Standard) M 80.20
Structural Steel, furnished and fabricated KG 7,799.13
Reinforcing Steel Bar, Grade 40 KG 3,749.00
Reinforcing Steel Bar, Grade 60 KG 61,911.00
Structural Concrete, Class A, 20.68MPa @28days CU. M. 479.10
Prestressed Structural Concrete Members (I-Girder type VI, EA 10.00
L=40.10 l.m)
Lean Concrete CU.M. 4.70
Elastomeric Bearing Pads EA 20.00
Preformed Sponge Rubber Joint Filler CU. M. 2.29
Drain Pipe, Galvanized 100mm dia I. M. 12.00

Road Plan and Profile


Beginning of Project 134+320.00
Beginning of Bridge 134+614.45
End of Bridge 134+655.45
End of Project 134+740.00
Wire Mesh Stone Masonry Retaining wall with geotextile
Gabion baskets 3.0x1.0x0.6 PVC Coated 3 Cell
Old Princesa Bridge