Академический Документы
Профессиональный Документы
Культура Документы
A. DELTA 14,949,000,000
B. GALAPHAGOS 7,727,000,000
Total 27,146,000,000
PPN 10%
Grand Total
Waktu Pelaksanaan ( Hari )
Summary Cost Bld 31B + Out Door AHU Room
A. CSA 7,727,281,903
1 CSA Building 31 B 5,655,076,067
1 Dismantle work 107,630,272
2 Earth Works 53,718,912
3 Shallow Foundation Works 189,949,276
4 Concrete Works 962,724,596
5 Wall & Partition 131,918,150
6 Steel work 1,957,115,264
7 Ceiling Works 454,149,600
8 Door Work 65,570,575
9 Wall Painting 163,564,674
10 Floor finishing work 1,420,378,504
11 Additional Item 148,356,244
B. MEP -
D. MEP (outdoor) -
E. Fire System -
1 Sprinkler
2 Fire Alarm
Total 7,727,281,903
Pembulatan 7,727,000,000
PPN 10% 772,700,000
Grand Total 8,499,700,000
Waktu Pelaksanaan ( Hari )
NO. DESCRIPTION
A PRELIMINARY WORK
1 SITE EXPENSE
2 TEMPORARY PROTECTION
3 TEMPORARY GATE
4 TEMPORARY ACCESS
5 TEMPORARY BRIDGE
6 TEMPORARY DRAINAGE
9 SCAFFOLDING
9 WORKSHOP
11 WATER SUPPLY
13 PROJECT SIGN
17 INSURANCE
SUB TOTAL
UNIT COST AMOUNT
QUANTITY UNIT
Rp. Rp.
1.00 Lot 0
1.00 Lot 0
1.00 Lot 0
645,000,000
180,000,000
8,000,000
6,500,000
5,000,000
30,000,000
20,000,000
20,000,000
10,000,000
60,000,000
30,000,000
7,000,000
45,000,000
24,000,000
27,000,000
17,500,000
490,000,000
Bill of Quantity
Pekerjaan renovasi Gedung Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
CSA
B. CSA 5,655,076,067
I Dismantle work 107,630,272
1 Dismantle office existing ( 3.5 mtr x 10 mtr ) 35.00 m2 - 561,200 19,642,000
3 Dismantle concrete slab existing u/ foundation ( 2.1 mtr x 4.5 mtr ) x 14 unit 132.30 m2 - 149,600 19,792,080
4 Dismantle Ramp existing GD 31A~31B ( 4 mtr x 6 mtr ) 24.00 m2 - 149,600 3,590,400
5 Dismantle window ( 3mtr x 4mtr ) x 8 unit 7.00 unit - 623,500 4,364,500
6 Dismantle window ( 1.2mtr x 2.4mtr ) x 10 Unit unit - - -
7 Dismantle window ( 2mtr x 4mtr ) x 8 unit 7.00 unit - 810,600 5,674,200
8 Dismantle existing wall u/ fire door 2.76 m2 - 187,100 516,396
9 Dismantle existing wall u/ Pedestrian door 2.76 m2 - 187,100 516,396
10 Dismantle Paving stone u/ Ramp 24.00 m2 - 74,800 1,795,200
11 Dismantle wire fence 1.00 lot - 4,676,300 4,676,300
12 Disposal material existing 1.00 lot - 8,468,300 8,468,300
14 Dismantle concrete slab existing u/ foundation ramp Tobacco feeder ~racking 24.00 m2 - 149,600 3,590,400
1 Strauss Ø 300mm - - -
-Steel bar 6 Ø10, Ø8-200 L=3mtr ( SNI HANIL STEEL ) 1,710.65 kg 11,100 2,000 22,409,534
-Concrete K-250 Readymix 17.80 m3 1,014,700 192,200 21,487,406
2 Lean concrete 1PC : 3 sand : 5 crush stone - - -
- bellow foundation 132.30 m2 50,300 18,700 9,128,700
3 Pile cap ( F6 ) Readymix K 250 + Hanil steel 39.71 m3 2,791,000 631,300 135,898,164
(pengkasaran permukaan kontruksi pedestal existing) 23.52 m2 - 43,600 1,025,472
4 Foundation beam Readymix K 250 + Hanil steel m3 - - -
- FB1 (300x200) - - -
7 Concrete ramp
- Concrete slab K300 Ex. SURYA BETON INDONESIA 3.60 m3 1,073,700 217,200 4,647,240
- Wiremesh M8 SBRC 24.00 m2 112,700 7,000 2,872,800
- Wiremesh M6 SBRC 24.00 m2 70,300 7,000 1,855,200
9 Shrinkage joint ( sealant 6 mm x 10 mm Sikaflex + dowel D13-300) 320.00 m' 93,500 18,700 35,904,000
10 Construction joint ( sealant 6mm x 10mm sikaflex + dowel D13-300) 343.00 m' 93,500 18,700 38,484,600
Bill of Quantity
Pekerjaan renovasi Gedung Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
CSA
1 Brick wall masonry Focon ; tebal +300mm 140.00 m2 254,100 109,100 50,848,000 sesuaikan tebal dinding + 30
2 Cement plaster (1PC : 6 sand) finish incl skim coat + linings Mortar Utama ; tebal 15mm 280.00 m2 64,500 56,100 33,768,000
3 Skim coat & linings exposed concrete Mortar Utama m2 - - -
4 Partition Gypsum 12 mm ( coulumn coulumn ) Jayaboard 150.50 m2 226,600 87,700 47,302,150
b Cat-walk
1 Cat Walk 3 Lajur dengan spesifikasi + penghubung antar calt-walk 49m x 3 nos + 30m = 177m'
Support CNP To Rafter (C150x50x20x2.3) 514.80 kg 20,000 4,400 12,561,120
Clamp Support CNP To Rafter (L70x70x7; L=150) 52.03 kg 20,000 4,400 1,269,508
Beam CNP(C150x65x20x2.3) 3,894.00 kg 20,000 4,400 95,013,600
Hollow 50x50x2; @L=600 47.35 kg 20,000 4,400 1,155,242
Expanded metal GM 30080 106.20 m2 404,700 24,900 45,623,520
2 Railling pipa Black Steel medium 354.00 m' 579,900 43,600 220,719,000
3 Bolt, turnbukle 1.00 lot 7,195,800 1,574,100 8,769,900
4 Electrical wirebrush + meni Zinc Chromate + cat Emco 28 (spray system) 4,508.18 kg 2,000 700 12,172,073
2 List gypsum lebar 7 cm hanya di posisi Up Ceiling 48.00 m2 31,200 10,000 1,977,600
No Description
B. CSA
I Dismantle work
1 Demolish exusting Floor for anchor
2 disposal rubbish concrete
3
II Foundation work
1 Foundation for Mezzanin work
2 anchor work include welding
3 Formwork
4 Concrete grouting
1 Strauss Ø 300mm
-Steel bar 6 Ø10, Ø8-200
-Concrete K-250
2 Lean concrete 1PC : 3 sand : 5 crush stone
- bellow foundation
3 Pile cap ( F6 )
(pengkasaran permukaan kontruksi pedestal existing)
4 Foundation beam
- FB1 (300x200)
IV Concrete Works
Concrete min fc'=25 or K250
Reinforcement bar fy 240<Ø12mm , fy 390>D13mm
Wiremesh U49 ex. BRC / Lionmesh
Portland Cement SII 0013-18
Formwork use bataco / multipleks 12mm thickness
Chemical set Sikadur 31CF atau setara
1 Concrete Column pedestal ( SC1 )
- Column SC1
5 Concrete ramp
- Concrete slab K300
- Wiremesh M8
- Wiremesh M6
6 Foundation AHU
- Concrete slab K300 thicknees 150
- Wiremesh M8 x 2 layers
- Gutter
7 Finish trowelling
- Trowelling Manual
VI Steel work
- Mutu baja BJ 37 (SS-41)
- Mutu baut A.325
a Structure steel AHU Room
Structural Steel Works grid 6~9
1 SC 1 grid 6 s/d 9 WF 250 x 125
2 Rafter WF 200 x 100
3 Purlin CNP 125
4 Regel CNP 125
5 Siku Regel
6 Zag rod Ø10mm
7 Wind bracing Ø12mm
8 Frame Gutter & Fascia
9 Plate
10 Painting
11 Anchor & bolt
14 Grouting sika 215
VII Roofing
1 Roofing
2 Gutter
3 Ridge caping 0.4mm
4 Rain water vertical down pipe Ø4" ( main roof )
5 Roof Draine
6 Flasing
IX Wall Painting
Exterior wall painting ex. Dulux Weathershield
Interior wall painting ex.Dulux Eazy Clean
Including primer ex Alcaplast & Alcabond
The work condition could be started if the water content of the wall at least 18% and
Power of Hydrogen least 8
Ceiling paint ex. Dulux Eazy Clean
1 Exterior wall painting
2 Interior wall painting
1 Trowelling
180.00 m2 - 93,500
180.00 m2 - 31,200
60.00 m2 - 187,100
- -
15.60 m3 - 81,100
12.43 m3 - 43,600
Lokal 0.58 m3 311,800 31,200
2.59 m3 - 81,100
L-3000 48.00 m' - 87,300
25.20 m3 311,800 31,200
- -
L=3mtr ( SNI HANIL STEEL ) 325.84 kg 11,100 2,000
Readymix 3.39 m3 1,014,700 192,200
- -
5.76 m2 50,300 18,700
Readymix K 250 + Hanil steel 2.30 m3 2,791,000 631,300
- -
Readymix K 250 + Hanil steel 3.30 m3 2,791,000 631,300
- -
Readymix K 300 + Hanil steel 1.44 m3 3,599,200 631,300
- -
Sitemix 1:2:3 65.93 m' 84,800 21,200
Hanil steel
Sitemix 1:2:3 59.93 m' 84,800 21,200
Focon
Mortar Utama
Mortar Utama
Mortar Utama
Focon 179.76 m2 101,600 43,600
Mortar Utama 359.52 m2 64,500 56,100
Mortar Utama m2 - -
3.00 unit 226,600 87,700
1,427,205,835 1,143,851,940
63,769,949 51,132,000
16,830,000 75,000 13,500,000
5,616,000 25,000 4,500,000
11,226,000 150,000 9,000,000
- -
15,048,974 12,066,000
1,265,160 - 65,000 1,014,000
542,035 - 35,000 435,120
197,568 250,000 25,000 158,400
210,211 - 65,000 168,480
4,190,400 - 70,000 3,360,000
8,643,600 250,000 25,000 6,930,000
27,937,331 22,414,623
- -
4,268,483 8,936 1,600 3,433,115
4,092,839 813,750 154,167 3,282,399
-
397,440 40,370 15,000 318,931
7,884,979 2,238,207 506,293 6,323,328
- -
11,293,590 2,238,207 506,293 9,056,850
- -
158,336,901 126,973,923
6,091,920 2,886,307 506,293 4,885,344
- -
6,988,368 68,000 17,000 5,603,880
70,402,164 56,463,624
171,551,331 137,416,920
83,280,400 66,780,000
68,581,800 54,997,500
26,910,072 21,571,200
3,590,400 2,880,000
368,028,497 295,104,319
47,495,210 250,000 25,000 38,079,250
A. Pekerjaan MEP -
I PEKERJAAN INSTALASI DAN ARMATURE
Pengadaan dan pemasangan instalasi penerangan, stop kontak dan lampu lengkap
dengan bola lampu termasuk koneksi ke kabel instalasi,
gantungan dan semua alat bantu yang diperlukansesuai gambar dan spesifikasi
Busduct with Max. setting 800A completed with 4 Busduct ex. Schneider 800A / 4P / CU /
1
nos / line of Tap Off 160A ( 1 line ) IP.54 - jarak tap off point tiap 10 meter
Kabel feeder dari LVMDP to SDP-31B.2 NYY
2 ex. Supreme (prov sum)
4x3(1x300mm2)+E
MEP 1 Page 25
Bill of Quantity
Pekerjaan renovasi ruang Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
MEP & Fire System
V PEKERJAAN VACUUM
Pengadaan dan pemasangan Equipment lengkap dengan
accessories dan
alat bantu yang diperlukan sesuai gambar dan spesifikasi.
Joint : Flange
MEP 1 Page 26
Bill of Quantity
Pekerjaan renovasi ruang Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
MEP & Fire System
VI PEKERJAAN HVAC
Pengadaan dan pemasangan Equipment lengkap dengan
accessories dan
alat bantu yang diperlukan sesuai gambar dan spesifikasi
MEP 1 Page 27
Bill of Quantity
Pekerjaan renovasi ruang Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
MEP AHU Room
A. Pekerjaan MEP -
I PEKERJAAN INSTALASI DAN ARMATURE
Pengadaan dan pemasangan instalasi penerangan, stop kontak dan lampu lengkap
dengan bola lampu termasuk koneksi ke kabel instalasi,
gantungan dan semua alat bantu yang diperlukansesuai gambar dan spesifikasi
D AHU Room
1 TCW 1X36W/865 ex. Philips
2 Double Switch ex. Schneider
3 Instalasi Penerangan ex. Supreme NYM 3 x 2.5 mm
4 Receptacle 1 phase termasuk socket ( male ) ex. Schneider
5 Instalasi Receptacle 1 Phase ex. Supreme NYM 3 x 2.5 mm
6 Bongkar Instalasi penerangan ex. Supreme NYM 3 x 2.5 mm
7 Bongkar lampu Spot high bay ex. Philips
1 Kabel feeder dari LVMDP? to PAC-AHU 31B NYY 4x150mm2 + E ex. Supreme
Kabel feeder dari PAC-AHU 31B to AHU-1 NYY 4x95mm2 + E
2 ex. Supreme
=> 2 Line (Start Delta )
Kabel feeder dari PAC-AHU 31B to AHU-2 NYY 4x95mm2 + E
3 ex. Supreme
=> 2 Line (Start Delta )
ex. Duta Listrik , Color : Orange, Finish :
4 Kabel ladder ukuran 300 x 100 mm
Powder Coating
5 Support & Accessories ( Scun Cable etc )
MEP 2 Page 28
Bill of Quantity
Pekerjaan renovasi ruang Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
MEP AHU Room
IV PEKERJAAN PLUMBING
Pengadaan dan pemasangan Equipment lengkap dengan
accessories dan
alat bantu yang diperlukan sesuai gambar dan spesifikasi.
1 Pipa GIP dia 25 mm2 ( 1" ) Pipa GIP class medium ex. Spindo
2 Pipa GIP dia 20 mm2 ( 3/4" ) Pipa GIP class medium ex. Spindo
3 Pipa GIP dia 15 mm2 ( 1/2" ) Pipa GIP class medium ex. Spindo
4 Gate Valve dia.1” class 10K ex.kitz
5 Faucet / Kran 15 mm ( 1/2 " ) ex.Toto
6 Water meter dia.1"
7 Fittings
8 Support dan material bantu
9 Testing dan comissioning
10 Tapping connection mainline Clean Water Pipe
V PEKERJAAN HVAC
Pengadaan dan pemasangan Equipment lengkap dengan
accessories dan
alat bantu yang diperlukan sesuai gambar dan spesifikasi
Ducting PU (pre-Insulated Aluminium duct Polyisocyanurate ex. Firstduct)
MEP 2 Page 29
Bill of Quantity
Pekerjaan renovasi ruang Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
MEP AHU Room
MEP 2 Page 30
Bill of Quantity
Pekerjaan renovasi ruang Produksi, Bentoel Malang
Location : Gedung 31B - Karanglo
Fire System
No Description
B FIRE SYSTEM
I Sprinkler
Instalasi sprinkler pendant
1 Pipa BS Sch 40 diameter 150 mm
2 Pipa BS Sch 40 diameter 100 mm
3 Pipa BS Sch 40 diameter 80 mm
4 Pipa BS Sch 40 diameter 65 mm
5 Pipa BS Sch 40 diameter 50 mm
6 Pipa BS Sch 40 diameter 40 mm
7 Pipa BS Sch 40 diameter 32 mm
8 Pipa BS Sch 40 diameter 25 mm
9 Sprinkler Head
10 MCV set
11 Gate Valve 150mm kitz
12 Flow Switch
13 Drain Inspection Test
14 Fitting and Accecories
15 Testing & commissioning
16 Bongkar pasang Indoor Hydrant Box
II Fire Alarm
Instalasi Fire Alarm
1 Instalasi Smoke Detector
### 2 Instalasi Manual break glass
3 Alarm bell
4 Indicator lamp
5 Reprogram MCFA existing
- Terminasi & Re-setting
6 Interlock System with Flow switch
7 Modifikasi JB - FA 31B c/w control module
8 Smoke Detector
9 Fixed temperatur detector
10 Manual break glass
11 Alarm bell
12 Indicator lamp
13 Chime strobe for Emergency door
14 Door contact + FRC 2x1,5 mm2
15 Support dan material bantu
16 Testing dan comissioning
17 Bongkar pasang accessories IHB
Unit Price (IDR)
Technical Spesification Qty Qty Unit
Material (IDR)
perubahan elevasi
NYA 2x1,5mm
Cable AWG18, ex. Belden
NYA 2x1,5mm
NYA 2x1,5mm
perubahan elevasi
Unit Price (IDR) Total Cost
Remarks
Labor (IDR) (IDR)
0.15 0.1
COST SUMMARY
Proyek : Bentoel - GALAPHAGOS Pj
Lokasi : Karanglo - Malang 25 Maret 2019
isi pancang
PC & PANCANG
bh
F1 ð 250X250
F2 ð 250X250
F3 ð 250X250
F4 ð 250X250
Tambahan Pancang ð 250X250
Slab on Pile ð 200X200
Slab on Pile ð 200X200
jumlah PC
TYPE PILE CAP
F1 31.00
F2
F3
F4
cek 31.00
F1 atas searah L
atas searah W
bawah searah L
bawah searah W
tulangan pinggang
F2 atas searah L
atas searah W
bawah searah L
bawah searah W
tulangan pinggang
F3 atas searah L
atas searah W
bawah searah L
bawah searah W
tulangan pinggang
F4 atas searah L
atas searah W
bawah searah L
bawah searah W
tulangan pinggang
level
SOIL WORKS PILE CAP
m
F1 (0.95)
F2 (0.95)
F3 (0.95)
F4 (0.95)
W B panjang
TYPE SLOOF
m m m
cek
W B panjang
SOIL WORKS SLOOF
m m m
W H L
GWT (Pump & Electrical Room)
m m m
W B L excavation
SOIL WORKS GWT
m m m
GWT
x y
GROUND SLAB
m m
- -
cek 2400
x y minus
m m m2
cek
W B panjang
Column
m m m
cek
W B panjang
BEAM - 2ND FLOOR
m m m
cek
0 - - -
0 - - -
0 - - -
0 - - -
m m m
RG1 200 x 400 as X1, X6, X7 & X12 0.20 0.40 48.00
m m m
x y minus
SLAB Roof
m m m2
cek
STEEL STRUCTURE
diagonal L 40
RG13 atas L 80
bawah L 80
diagonal L 40
pelat 12.50%
pengecatan
Cat Walk
CNP 150
pelat pelat %
pengecatan
AHU
IWF 200
pelat 12.50%
pengecatan
-minus gutter
insulasi
Flashing
52.40 4.00
52.40 4.00
1.25 2.00
drop gutter
factory
cek
inside office
cek
1st floor
2nd floor
toilet M
toilet F
2nd floor
toilet F
toilet M
1st floor
2nd floor
1st floor
2nd floor
toilet M 9.20 2.50 1.00
eksterior
elevation 1 as 1-6 as E
elevation 2 as 1-6 as E
elevation 3 as 6 as A-E
elevation 4 as 6 as A-E
CLADDING L H square
steel frame louver 4 nos & fixed windo SLW-1 3.50 4.10
cek 3,002.50
eksterior
interior - factory-processing
interior - office
1st floor
2nd floor
factory -
K1 159.92 159.92
K2 76.44 76.44
K3 85.60 85.60
481.96
1,471.60
SUMMARY eksterior
WALL 2,007.98
INTERIOR AEP
INTERIOR EP
TOUCH UP
CERAMIC WALL
VENTILATION BLOCK -
hardener
ceramic 30
ceramic 20
carpet
-
oil skirting
ceramic skirting
pvc skirting
gyptile
accoustic
expose
-
-
drop ceiling
door sill
concrete marble
ablution
W-1.8 x H-1.0 m
W-1.0 x H-1.0 m
Horisontal Blind
office AW-1(1),AW-2(1)
PD AW-3(2)
canteen AW-1(1),AW-2(1)
hand washing
TANGGA concrete
bordes-2 3.65
balok&kolom 2.09
13.19
gantungan ke purlin Ø 12 mm
pelat (10%)
PENGECATAN
5.76
H purlin
SUPPORT CEILING FACTORY L W
>1.5m
(9.00) 4.00
total pancang total pancang
bh bh
456.00
520.00
- 976.00
m3 m2 kg
- - -
- - -
- - -
koef
mm kg m m bh kg
total besi
m m3 m3 m3 m3 m2
1.10 - - - - -
1.10 - - - - -
1.10 - - - - -
kg/m3 m3 m2 kg
m m3 m3 m3 m3
12.00
2.00
kg/m3 m3 m2 kg m2
m m m3 m3 m3 m3
m2 m m3 m2 m2 m2
-
10,319.36 2,562.27 5,040.00 4,928.00 2,989.00
t=120 mm 2 layer
m2 m kg m2 m' m'
- - 1.00 - - -
- - 1.00 - - -
- - 1.99 - - -
kg/m3 m3 m2 kg m3
- - - -
- - - -
- - - -
kg/m3 m3 m2 kg m2
- - - -
- - - -
- - - -
- - - -
- - - - -
kg kg
-
-
kg/m3 m3 m2 kg m2
kg/m3 m3 m2 kg m2
- - - -
- - - -
- - -
- - -
- - - - -
t=120 mm 2 layer
m2 m kg m2 m' m'
- - 1.55 - - -
- - 1.55 - - -
5,725.48
51,529.35
UNIT
L (m) QTY (nos) VOLUME (kg)
(kg/m')
150 x 65 x 20 x 2.3 1.20 52.00 5.50 343.20
10% 450.82
4,958.99
495.15
-
4,456.32
- - m2 slope 3°
- - m2 slope 3°
378.00 m2 382.50
4.50 m2
210.00 m'
210.00 m'
209.60 m'
- m'
209.60 m'
2.50 m'
210.00 m'
2.50 m'
7.20 m'
132.00 m'
44.00 m'
11.00 nos
- - - - -
- ga ngurangi ga ngurangi ga ngurangi ga ngurangi
(368.42) (368.42) (368.42) (368.42) (368.42)
interior split
paint
plester paint interior
SQUARE add paint paint interior interior AEP
interior EP
h<1.8m
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
interior split
paint
paint paint interior
square interior AEP
interior EP
h<1.8m
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - - -
- -
square
-
-
- interior split
paint
paint paint interior
square interior AEP
interior EP
h<1.8m
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - - -
- -
interior split
ceramic paint paint interior paint
square
20x25 interior AEP h<1.8m interior EP
- - -
-
23.00 23.00 (23.00) (23.00)
350.98 (350.98)
square
minus to wall
- - - -
- - - -
- - - -
- - -
1,797.50 1,797.50
290.00 290.00
36.50 36.50
36.00 36.00
21.90 21.90
48.00 48.00
12.00 12.00
31.20 31.20
40.80 40.80
14.04 14.04
19.20 19.20
1.96 1.96
7.20 7.20
5.50 5.50
32.70 32.70
5.50 5.50
-
145.65 145.65
18.90 18.90
33.75 33.75
31.50 31.50
18.90 18.90
6.75 6.75
9.45 9.45
9.45 9.45
5.25 5.25
4.20 4.20
14.70 14.70
275.05 275.05
2.55 2.55
26.40
3,002.50
jumlah
-
interior total cek
1,348.09 3,356.07 m2
- - m2
4,302.57 4,302.57 m2
481.96 481.96 m2
1,471.60 m'
- - m2
- - m2
- - m2
350.98 350.98 m2
- m2
2,123.50 2,123.50 m2
578.75 578.75 m2
56.65 56.65 m2
217.20 217.20 m2
- - m2
294.25 294.25 m'
933.60 933.60 m2
217.20 217.20 m2
54.20 54.20 m2
- - m'
- - m2
m'
200.00 m'
24.00 nos
8.00 nos
16.80 m'
1.00 nos
2.00 nos
3.00 nos
1.00 nos
14.57 m2
3.00 m'
1.00 nos
2.00 m'
5.80 m'
6.00 m'
1.00 nos
1.00 nos
2.00 nos
38.50 m'
6.89
3.51
2.60
6.89
4.00 m'
4.00 nos
m2
- m'
ceramic ekspose
formwork rebar stepnosing grove line stair
stair stair
7.20 4.00 7.20 7.60
12.87
3.28
36.12
Koef total
6.27 3,778.60
6.27 (225.78)
3,552.82
Rate
bekisting besi
m2/m3 kg/m3
5.33 76.73
#DIV/0! #DIV/0!
#DIV/0! #DIV/0!
#DIV/0! #DIV/0!
1.05
total
kg
32.37
1,003.46
0.67
-
-
(9.00)
(15.95)
1,003.46
compaction
m2
48.44
48.44
m2 m2
288.00 403.20
210.00 294.00
498.00 697.20
41.68
82.27
41.13
m2 m2
116.64 123.75
116.64 123.75
m3 m3 m' m' m2
#DIV/0!
chamber
touch up grouting wood
column
m2 m2 m'
- - - 11.1111111111 0
- - -
- -
74.710204082
0.1225 130.0694
8.1632653061 1061.791
8.736
6.6666666667 5.1786
0.09 13.9146
11.1111111111 154.6067
#DIV/0!
17,180.29 (12,221.30)
interior split
paint interior paint interior
AEP h<1.8m EP
-
400.00
40.00
40.00
600.00
400.00
60.00
60.00
720.00
-
ga ngurangi ga ngurangi
(368.42)
- 1,951.58
1,951.58
nus to wall
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
ceramic
oil skirting pvc skirting gyptile accoustic expose
skirting
200.00
68.25 290.00
26.25 36.50
26.00 36.00
15.30 21.90
32.00 48.00
12.00
25.60 31.20
27.60 40.80
14.04
19.20
1.96
11.60 7.20
7.50 5.50
36.70 32.70
7.50 5.50
58.40 145.65
17.40 18.90
24.00 33.75
23.40 31.50
17.40 18.90
10.75 6.75
13.20 9.45
13.20 9.45
5.25
4.20
15.40 14.70
68.45 275.05
4.55 2.55
26.40
3,002.50
haindrailing
haindrailing
SS wall
SS
mounted
3.60
7.30
12.80 11.30
2.60
12.80 24.80
-
GAMBAR TIE BEAM /BALOK GAMBAR KOLOM
W W
B B
1.579
tulangan top 3 3 3
RG1 200 x tulangan bottom 3 3 3 8 0 0.64 8.00 normal 4 16
400 as X1, X6, begel 0.2 0.2 8 overlap 0.67 16
X7 & X12 dimension 0.2 0.4 ujung 0 16
1.579
tulangan top 3 3 3
tulangan bottom 3 3 3 8 0 0.60 6.80 normal 6 16
LG1 250 x
300
begel 0.2 0.2 8 overlap 0.67 16
dimension 0.25 0.3 ujung 0 16
1.579
tulangan top 4 2 4
tulangan bottom 2 4 2 5 0 0.50 6.00 normal 4 16
begel 0.15 0.2 5 overlap 0.42 16
dimension 0.2 0.5 ujung 0 16
tulangan top 3 2 3
tulangan bottom 2 3 2 6 0 0.48 6.00 normal 4 16
begel 0.15 0.2 6 overlap 0.50 16
dimension 0.2 0.4 ujung 0 16
tulangan top 3 2 3
tulangan bottom 2 3 2 6 0 0.48 6.00 normal 4 13
begel 0.15 0.2 6 overlap 0.50 13
dimension 0.2 0.4 ujung 0 13
8.00 - 0 13 2.00 - 0 13 2 - 0 13 4
0.52 0.36 1 13 0.26 0.27 1 13 0.26 0.27 1 13 0.52
0.33 - 0 13 0.33 - 0 13 0.33 -
1.04 1.042 1.042
Pembesian
utama + overlap Tump Kiri + overlap Tump Kanan + overlap Lapangan + overlap
L(m) kg n(bh) dia(mm) L(m) kg n(bh) dia(mm) L(m) kg n(bh) dia(mm) L(m)
Pembesian RATE
berat
ama + overlap Sengkang Sengkang Ikat total bekisting besi persen
besi
kg dia(mm) L(m) jlh kg L(m) jlh kg m2/m3 kg/m3
593.36 13 1.90 24.00 47.52 0.60 9.00 5.63 697.67 8.00 416.52 25.00 85.05%
23.00 45.54 7.00 5.63 13.00 14.95%
1.042 1.042
237.34 10 1.50 24.00 22.21 0.50 9.00 4.69 290.22 10.00 270.73 25.00 81.78%
23.00 21.29 7.00 4.69 10.00 18.22%
0.617 1.042
39.66 10 0.90 10.00 5.55 0.50 15.00 - 50.22 16.00 321.38 16.00 78.99%
9.00 5.00 7.00 - 10.00 21.01%
0.617
ian
gan + overlap Tulangan Pinggang + overlap Sengkang Sengkang Ikat Total Besi
kg n(bh) dia(mm) L(m) kg dia(mm) L(m) jlh kg L(m) jlh kg
ian
gan + overlap Tulangan Pinggang + overlap Sengkang Sengkang Ikat Total Besi
kg n(bh) dia(mm) L(m) kg dia(mm) L(m) jlh kg L(m) jlh kg
0.617
0.617
0.617
0.617
RATE
berat
bekisting besi persen
besi
m2/m3 kg/m3
Index
1 2 3 4 5 6
Wiremash
Type Spasi Sheet
Polos (mm) PxL Kg/Lbr Kg/m2
M4-150 150x150 5.4 x 2.1 15.45 1.36
M5-150 150x150 5.4 x 2.1 24.14 2.13
M6-150 150x150 5.4 x 2.1 34.76 3.07
M7-150 150x150 5.4 x 2.1 47.31 4.17
M8-150 150x150 5.4 x 2.1 61.79 5.45
M9-150 150x150 5.4 x 2.1 78.21 6.90
M10-150 150x150 5.4 x 2.1 96.55 8.51
IWF
CNP
Material Dimension Length Weight
(m) Weight (kg) (kg/m')
CNP 60 60 x 30 x 10 x 1.6 6 9.78 1.63
CNP 75.35 75 x 35 x 15 x 1.6 6 12.42 2.07
CNP 75.45 75 x 45 x 15 x 1.6 6 13.92 2.32
CNP 75.45 75 x 45 x 15 x 2.3 6 19.50 3.25
CNP 100.50.20.1,6 100 x 50 x 20 x 1.6 6 17.28 2.88
CNP 100.50.20.2,3 100 x 50 x 20 x 2.3 6 24.40 4.07
CNP 100.50.20.3,2 100 x 50 x 20 x 3.2 6 33.00 5.50
CNP 125.50.20.2,3 125 x 50 x 20 x 2.3 6 27.10 4.52
CNP 125.50.20.3,2 125 x 50 x 20 x 3.2 6 36.80 6.13
CNP 150.50.20.2,3 150 x 50 x 20 x 2.3 6 29.80 4.97
CNP 150.50.20.3,2 150 x 50 x 20 x 3.2 6 40.56 6.76
CNP 150.65.20.2,3 150 x 65 x 20 x 2.3 6 33.00 5.50
CNP 150.65.20.3,2 150 x 65 x 20 x 3.2 6 45.10 7.52
CNP 200.75.20.2,3 200 x 75 x 20 x 2.3 6 45.10 7.52
CNP 200.75.20.3,2 200 x 75 x 20 x 3.2 6 55.62 9.27
UNP
117.6952
Baseplate JointPlate
0.10 0.10 0.05 WF 600 200 11 17 berat 0.0066
0.10 0.13 0.05 WF 450 200 9 14 berat 0.00405
0.15 0.15 0.10 WF 200 100 5.5 8 berat 0.0011
0.15 0.15 0.10 WF 350 175 7 11 berat 0.00245
0.15 0.20 0.10 WF 250 125 6 9 berat 0.0015
0.15 0.20 0.10 WF 500 200 10 16 berat 0.005
0.15 0.20 0.10 WF 588 300 10 16 berat 0.00588
0.15 0.20 0.10 WF 700 300 13 24 berat 0.0091
0.18 0.25 0.13 WF 800 300 14 26 berat 0.0112
0.18 0.25 0.13 WF 224 175 7 11 berat 0.001568
0.20 0.30 0.15 WF 440 300 11 18 berat 0.00484
0.20 0.30 0.15 WF 390 300 10 16 berat 0.0039
0.25 0.35 0.20 WF 294 200 8 12 berat 0.002352
0.25 0.35 0.20
0.25 0.40 0.20
0.25 0.40 0.20 UNP 50 38 5 5 berat 0.00025
0.25 0.45 0.20 100 50 5 5 berat 0.0005
0.25 0.45 0.20 140 60 7 7 berat 0.00098
0.25 0.50 0.20 80 45 5 5 berat 0.0004
0.35 0.60 0.30 berat 0
0.25 0.60 0.20 140 60 7 10 berat 0.00098
0.35 0.70 0.30 100 50 6 8.5 berat 0.0006
0.35 0.80 0.30 100 50 6.5 8 berat 0.00065
80 45 6 8 berat 0.00048
Baseplate Stiffener
0.13 0.15 0.08
0.18 0.20 0.13
0.18 0.20 0.13
0.23 0.25 0.18
0.23 0.25 0.18
0.23 0.30 0.18
0.23 0.30 0.18
0.28 0.35 0.23
0.28 0.35 0.23
0.28 0.40 0.23
0.28 0.40 0.23
0.28 0.45 0.23
0.28 0.50 0.23
0.28 0.60 0.23
0.40 0.60 0.35
0.40 0.70 0.35
0.40 0.80 0.35
Baseplate Stiffener
0.20 0.15 0.15
0.25 0.20 0.20
0.25 0.20 0.20
0.30 0.25 0.25
0.30 0.25 0.25
0.35 0.30 0.30
0.35 0.30 0.30
0.40 0.35 0.35
0.40 0.35 0.35
0.45 0.40 0.40
0.45 0.40 0.40
0.50 0.45 0.45
0.55 0.50 0.50
0.65 0.60 0.60
0.65 0.60 0.60
0.75 0.70 0.70
0.85 0.80 0.80
0.0068 105.19 106.00 1.01
0.0056 75.7525 76.00 1.003267
0.0016 21.195 21.33 1.006527
0.00385 49.455 49.60 1.002932
0.00225 29.4375 29.6 1.00552
0.0064 89.49 89.58 1.001043
0.0096 121.518 151.00 1.242614
0.0144 184.475 185.00 1.002846
0.0156 210.38 210.00 0.998194
0.00385 42.5313 44.1 1.036883
0.0108 122.774 124 1.009986
0.0096 105.975 107 1.009672
0.0048 56.1432 56.8 1.011699
11 1 M3 Pile Cap
Pek. Bekisting m2 1.68
Pek. Beton K-250 m3 1.00
Pembesian kg 136.76
12 1 M3 Column
Pek. Bekisting m2 4.32
Pek. Beton K-300 m3 1.00
Pembesian kg 141.73
15 1 M2 Acian
Bahan
MU 200 zak 0.05
Tenaga
Transport lot 1.00
Upah m2 1.00
- - -
62,400 62,400 50,000 50,000
Rp 306,100 Jumlah Rp 245,100
804,750 720,251,250
92,500,000 92,500,000
12,000,000 12,000,000
78,000 23,244,000
29,000 25,955,000
873,950,250
976,481
Rp 293,800
8900
21750
100
bawah 16-200 94.725 1.58 149.6655
tamb 16-200 66 1.58 104.28
atas 13-200 94.725 1.042 98.70345
387.9138
B CIVIL WORK
1 FACTORY BUILDING
SUB TOTAL
2 EARTH WORK
Land Clearance & Preparation
Excavation on foundation & slab
Leveling & Compaction
Sand gravel under foundation t=50 mm
Compacted Crushed Stone under Slab, t=100 mm
Backfill on foundation
Red soil Fill and Compaction under Ground Slab H
Soil Cut - Disposal - Spreading - Pay for disposal area
Plastic Sheet
CBR test
Mob Demob
SUB TOTAL
3 PILE WORK
PC Spun Pile Ø300, L= 20 m, , material only Ra = 40 T for foundation
PC Spun Pile SQP 250, L= 15 m, material only, Ra = 30 T for slab
Coordination Fee 3%
Pile Driving Hydraulic System
PC Spun Pile Ø 300, L 20 m, SQ Pile 250, L 15 m
Cutting pile
Pile Head Triming
Handling pile
Joint pile SP Ø300, & SQP 250
Mob - Demobilization Pilling Machine
PDA Test
Loading Test (use concrete block)
SUB TOTAL
4 CONCRETE WORK
Lean Concrete B-0
Foundation K-350, NFA, Slump 12±2
SUB TOTAL
5 FORM WORK
Foundation
Tie Beam
Parapet Wall
Ramp
GWT (1,2,3,4) cap. 90 m3
Ground Slab (Pounching, G/Slab t=250 mm)
Column
Scaffolding
Beam
Scaffolding
Ring Beam
Scaffolding
Stair Entrance
Scaffolding
SUB TOTAL
6 REBAR WORK
Foundation
Tie Beam
Parapet Wall
Ramp
GWT (1,2,3,4) cap. 90 m3
Ground slab
Column
Ring Beam
Stair Entrance
Coordination fee 3%
Labour fee
SUB TOTAL
SUB TOTAL
8 MASONRY WORK
ALC wall t=100 mm
Wainscoat Louver Block t=100 mm, h=1200 mm
Concrete lintel & stiffener 100x120 mm
SUB TOTAL
9 WATERPROOFING WORK
Screeding Waterproofing at Toilet & Pantry floor
Waterproofing w/ Asphalt Membrane at Toilet, outside GWT wall
SUB TOTAL
10 TILE WORK
Floor Ceramic Tile 400 x 400 mm ex Roman
Floor Ceramic Tile 300 x 300 mm ex Roman
Floor Ceramic Tile 200 x 200 mm (Non Slip) ex Roman
Floor Ceramic Step Nosing at Stair
Skirting Ceramic Tile h=100 mm
Wall Ceramic Tile 200 x 400 mm at Toilet ex Roman
SUB TOTAL
End Closer
Eaves Closer
End Frame
Bird net w=800
Monitor Roof
Main Roof Galvalume Steel Sheet T=0.50mm, H=90mm
Insulation : Glasswool t=25mm, 16 kg/m2, w/ Al. Foil+roofmesh
Wall Light Duralite FRP t=1.2mm w=600 H=30 mm, Polycarbonate
Fascia : Duralite FRP t=1.2mm w=600 H=30 mm, Polycarbonate
Bird net w=1000
Canopy Roof
Canopy Roof Galvalume Steel Sheet TCT=0.50mm, H=90mm
Flashing Parapet Zinc Metal Sheet t=0.5mm W: 900
Flashing Gable Zinc Metal Sheet t=0.5mm W:900
Flashing Under Under Canopy Zinc Metal Sheet TCT 0.5mm W:450
Eaves Gutter, AlZn 0.5TCT W300
Eaver Rubber
Transportation & Rool on site
Coordination Fee 3%
SUB TOTAL
12 METAL WORK
Steel Ladder H=15.000mm; Hot Dip Galvanized
SUS Grill L=1500, w=300 mm at Ablution area
Galvanized Pipe Hand Rail Ø 2" & 3/4" with OP, H=1000mm at Entrance
SUB TOTAL
SUB TOTAL
14 PLASTERING WORK
Plaster ALC wall t=15 mm
Concrete Surface Treatment on Concrete Column
Concrete Surface Treatment on Concrete Beam
SUB TOTAL
15 PAINTING WORK
Painting Wall w/ EP (interior, inc. Column & Beam) ex Jotun or equal
SUB TOTAL
SUB TOTAL
12 MISCELLANEOUS WORK
Man Hole at GWT w/ Cast Iron Ø 600 mm
Insect Net on Louver Block h=1200 mm
Column Corner Guard w/ L-50x50 OP Finish
Corner Concrete w/ L-50x50x5 OP Finish at Dock Leveler pit
Corner Concrete w/ L-50x50x5 OP Finish at SS Door (Loading area)
Rubber Bumper at Loading area
Cable Pit at Electrical Room incl. Cover Chekered Plate t=45 mm
Marble Top Lining D=220, T=25 mm at Toilet & Urinoir
Skirting counter with Marble H=200mm, t=25 mm at Toilet
Concrete Counter Table for Washtafel w=600
Counter Marble for Toilet Washtafel, w=600
Mirror w=600 h=700 mm at Toilet M & F
Man Hote 600x600 mm at Ceiling
Dock Leveler cap. 2 Ton
Temporary Shoring For GWT
Logo/Company Name at Main Gate w/ SUS 304, H=400 mm
Logo at Building Wall w/ SUS 304, H=1000 mm
Sign Name Room w/ Acrylic t=2 mm
Support for M&E Work
SUB TOTAL
UNIT COST AMOUNT
QUANTITY UNIT
Rp. Rp.
1,288,000,000
4,214,739,000
4,454.00 m 150,000 668,100,000
41,100.00 m 140,000 5,754,000,000
1.00 lot 165,834,000 165,834,000
10,512,068,000
m³ 930,000 0
78.00 m³ 930,000 72,540,000
7.74 m³ 930,000 7,198,200
5,523.00 m 68,000 375,564,000
69.00 m 260,000 17,940,000
6,710,060,620
2,776,954,725
7,788,020,250
11,720,845,900
623,840,000
244,554,800
8,849,840,900
244,620,000
1,469,650,000
540,951,000
474,155,120
1,369,879,200
1,698,697,500
508.54
904.08
2,635.78
###
93,075.00
###
=((0,5*0,7*0,05*40)+(0,5*0,5*0,05*8)+(0,5*0,5*0,05*57))
77
8,592,078,900
60
16.8
4.2 #VALUE!
1.89
1.89
1.68
1.47
1.26
15
1.62
6.48
3.6
9.72
60,557,927,015