COST SUMMARY - UNIFORMAT LEVELS 1 TO 2

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Rate Cost Per Cost Per
No. Section Individual Element Qty Unit $/Unit Cost $ Unit GFA Key Notes
MECHANICAL SERVICES
1 D20 Plumbing 2,280 FXT 2,120 4,834,060 80.2 8,057
2 D2010 Plumbing Fixtures 2,280 FXT 142.7 325,387 5.4 542.3
2 D2020 Domestic Water Distribution 2,280 FXT 653.8 1,490,645 24.7 2484.4
2 D2030 Sanitary Waste 2,280 FXT 423.5 965,691 16.0 1609.5
2 D2040 Rain Water Drainage 8,012 m2* 52.5 420,957 7.0 701.6 *Gross roof area
2 D2090 Other Plumbing Systems - - - 1,608,714 26.7 2681.2
Includes booster pump, piping and
2 G2050 Site Irrigation Systems 500 m 11.8 5,921 0.1 9.9 associated valves
2 G3010 Site Water Supply - - - 9,175 0.2 15.3
2 G3020 Site Sanitary Sewers 25 m 151.4 3,785 0.1 6.3
2 G3030 Site Storm Sewers 25 m 151.4 3,785 0.1 6.3
1 D30 HVAC 20,400 kW* 529.3 10,798,355 179.2 17,997 *Sum of sections D3020 & D3030
2 D3010 Energy Supply - - - 101,455 1.7 169.1
2 D3020 Heat Generation 11,772 kW 55.3 651,473 10.8 1085.8
2 D3030 Refrigeration 2,453 Ton 1,207 2,961,027 49.1 4935.0
2 D3040 HVAC Distribution 2,103 Ton 2,244 4,718,942 78.3 7864.9
2 D3050 Terminal and Packaged Units 676 Ton 1,001 676,868 11.2 1128.1
2 D3060 HVAC Instrumentation and Controls 20,400 kW 72 1,474,415 24.5 2457.4
2 D3070 Testing, Adjusting, and Balancing 2,103 Ton 102 214,175 3.6 357.0
1 D40 Fire Protection - - - 1,309,730 21.7 2,183
2 D4010 Sprinklers 5,854 HDS 185.5 1,085,899 18.0 1809.8
Cabinets only, piping cost included
2 D4020 Standpipes 100 CAB 1,356 135,569 2.2 225.9 in section D4010
2 D4030 Fire Protection Specialties - PA - 7,978 0.1 13.3 PA: protected area (m2)
2 D4090 Other Fire Protection Systems - - - 80,284 1.3 133.8
MECHANICAL SERVICES - COST 16,942,145

Data Date: Dec. 1997


Printed Date: 05/10/2019 Page 1 of 12
PLUMBING COST SUMMARY - UNIFORMAT LEVELS 1 TO 4

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Rate Cost Per Cost Per
No. Section Individual Element Qty Unit $/Unit Cost $ Unit GFA Key Notes
1 D20 Plumbing 2,280 FXT 2,120 4,834,060 80.2 8,057
2 D2010 Plumbing Fixtures 2,280 FXT 142.7 325,387 5.4 542.3
3 D2010.1 Water Closets 607 FXT 208.3 126,408
3 D2010.2 Urinals 42 FXT 221.2 9,291
3 D2010.3 Lavatories 149 FXT 179.8 26,788
3 D2010.4 Sinks 8 FXT 379.1 3,033
3 D2010.5 Showers 484 FXT 113.1 54,725
3 D2010.6 Bathtubs 479 FXT 56.8 27,187
3 D2010.7 Basins/Bidets 480 FXT 106.0 50,891
3 D2010.8 Other Plumbing Fixtures 31 FXT 873.0 27,064
2 D2020 Domestic Water Distribution 2,280 FXT 653.8 1,490,645 24.7 2484.4
3 D2020.1 Water Supply Piping Systems - - - 726,552
4 D2020.1.1 Pipes and Tubes 25,940 m 25.7 665,648 Cost is for copper pipes
4 D2020.1.2 Valves and Sundries 1,822 Nr 33.4 60,904
3 D2020.2 Water Supply Equipment - - - 654,006
4 D2020.2.1 Plumbing Pumps 10 Nr 20,719 207,190
4 D2020.2.2 Hot Water Storage Tanks 56,040 Liter 7.3 409,295
4 D2020.2.3 Heat Exchangers 1,479 kW 25.4 37,521
3 D2020.3 Water Supply Insulation 1,148 m2 95.9 110,087
4 D2020.3.1 Piping Insulation (25 and 50 thick) 1,148 m2 95.9 110,087
2 D2030 Sanitary Waste 2,280 FXT 423.5 965,691 16.0 1609.5
Galvanized steel for vent pipes;
3 D2030.1 Waste and Vent Piping 19,653 m 37.5 737,107 Cast iron for waste pipes
3 D2030.2 Waste Piping Specialties 529 Nr 351.6 185,979 Floor drains, cleanouts, cowls,...
3 D2030.3 Waste Piping Equipment 10 Nr 4,261 42,605
4 D2030.3.1 Interceptors 7 Nr 2,245 15,717
4 D2030.3.2 Pumps 3 Nr 8,963 26,888

Data Date: Dec. 1997


Printed Date: 05/10/2019 Page 2 of 12
PLUMBING COST SUMMARY - UNIFORMAT LEVELS 1 TO 4

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Rate Cost Per Cost Per
No. Section Individual Element Qty Unit $/Unit Cost $ Unit GFA Key Notes
2 D2040 Rain Water Drainage 8,012 m2* 52.5 420,957 7.0 701.6 *Gross roof area
3 D2040.1 Rain Water Drainage Piping Systems 3,155 m 108.6 342,738

3 D2040.2 Rain Water Drainage Specialties 291 Nr 211.2 61,454 Interceptors, balcony & roof drains
3 D2040.3 Rain Water Piping Equipment 2 Nr 8,382.5 16,765 Includes sump pumps
2 D2090 Other Plumbing Systems - - - 1,608,714 26.7 2681.2
3 D2090.1 Compressed Air Systems 180 m 51.1 9,191
3 D2090.2 Liquified Petroleum Gas Systems 638 m 237.9 151,775 2x12,000 liter gas tanks
3 D2090.3 Reverse Osmosis Systems 200 m /day
3
3,586 717,258 Cost is for copper pipes
4 D2090.3.1 Potable Water Pipes 3,890 m 29.0 112,984 Cost is for copper pipes
4 D2090.3.2 Pumps 1 Nr 1,961 1,961
4 D2090.3.3 Valves 105 Nr 27.5 2,887
4 D2090.3.4 Piping Insulation (25 and 50 thick) 171 m2 79.9 13,670
4 D2090.3.5 Water Softners 20 L/s 6,158 123,153
4 D2090.3.6 Reverse Osmosis Units 1 Nr 462,603 462,603
3 D2090.4 Electrical Works 60,269 m2 0.22 13,232
Includes booster pump, piping and
2 G2050 Site Irrigation Systems 500 m 11.8 5,921 0.1 9.9 associated valves
2 G3010 Site Water Supply - - - 9,175 0.2 15.3
3 G3010.1 Water Wells 1 Item 8,245 8,245
3 G3010.2 Site Domestic Water Distribution 30 m 31.0 930
2 G3020 Site Sanitary Sewers 25 m 151.4 3,785 0.1 6.3
2 G3030 Site Storm Sewers 25 m 151.4 3,785 0.1 6.3

Data Date: Dec. 1997


Printed Date: 05/10/2019 Page 3 of 12
PLUMBING COST SUMMARY - UNIFORMAT LEVELS 1 TO 2

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Rate Cost Per Cost Per
No. Section Individual Element Qty Unit $/Unit Cost $ Unit GFA Key Notes
1 D20 Plumbing 2,280 FXT 2,120 4,834,060 80.2 8,057
2 D2010 Plumbing Fixtures 2,280 FXT 142.7 325,387 5.4 542.3
2 D2020 Domestic Water Distribution 2,280 FXT 653.8 1,490,645 24.7 2484.4
2 D2030 Sanitary Waste 2,280 FXT 423.5 965,691 16.0 1609.5
2 D2040 Rain Water Drainage 8,012 m2* 52.5 420,957 7.0 701.6 *Gross roof area
2 D2090 Other Plumbing Systems - - - 1,608,714 26.7 2681.2
Includes booster pump, piping and
2 G2050 Site Irrigation Systems 500 m 11.8 5,921 0.1 9.9 associated valves
2 G3010 Site Water Supply - - - 9,175 0.2 15.3
2 G3020 Site Sanitary Sewers 25 m 151.4 3,785 0.1 6.3
2 G3030 Site Storm Sewers 25 m 151.4 3,785 0.1 6.3

Data Date: Dec. 1997


Printed Date: 05/10/2019 Page 4 of 12
PLUMBING COST SUMMARY - UNIFORMAT LEVELS 1 & 3

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Rate Cost Per Cost Per
No. Section Individual Element Qty Unit $/Unit Cost $ Unit GFA Key Notes
1 D20 Plumbing 2,280 FXT 2,120 4,834,060 80.2 8,057
3 D2010.1 Water Closets 607 FXT 208.3 126,408
3 D2010.2 Urinals 42 FXT 221.2 9,291
3 D2010.3 Lavatories 149 FXT 179.8 26,788
3 D2010.4 Sinks 8 FXT 379.1 3,033
3 D2010.5 Showers 484 FXT 113.1 54,725
3 D2010.6 Bathtubs 479 FXT 56.8 27,187
3 D2010.7 Basins/Bidets 480 FXT 106.0 50,891
3 D2010.8 Other Plumbing Fixtures 31 FXT 873.0 27,064
3 D2020.1 Water Supply Piping Systems - - - 726,552
3 D2020.2 Water Supply Equipment - - - 654,006
3 D2020.3 Water Supply Insulation 1,148 m2 95.9 110,087
Galvanized steel for vent pipes;
3 D2030.1 Waste and Vent Piping 19,653 m 37.5 737,107 Cast iron for waste pipes
3 D2030.2 Waste Piping Specialties 529 Nr 351.6 185,979 Floor drains, cleanouts, cowls,...
3 D2030.3 Waste Piping Equipment 10 Nr 4,261 42,605
3 D2040.1 Rain Water Drainage Piping Systems 3,155 m 108.6 342,738
3 D2040.2 Rain Water Drainage Specialties 291 Nr 211.2 61,454 Interceptors, balcony & roof drains
3 D2040.3 Rain Water Piping Equipment 2 Nr 8,382.5 16,765 Includes sump pumps
3 D2090.1 Compressed Air Systems 180 m 51.1 9,191
3 D2090.2 Liquified Petroleum Gas Systems 638 m 237.9 151,775 2x12,000 liter gas tanks
3 D2090.3 Reverse Osmosis Systems 200 m3/day 3,586 717,258 Cost is for copper pipes
3 D2090.4 Electrical Works 60,269 m2 0.22 13,232
3 G3010.1 Water Wells 1 Item 8,245 8,245
3 G3010.2 Site Domestic Water Distribution 30 m 31.0 930

Data Date: Dec. 1997


Printed Date: 05/10/2019 Page 5 of 12
HVAC COST SUMMARY - UNIFORMAT LEVELS 1 TO 4

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Individual Cost Per Cost Per
No. Section Element Qty Unit Rate $/Unit Cost $ Unit GFA Key Notes
1 D30 HVAC 20,400 kW* 529.3 10,798,355 179.2 17,997 *Sum of sections D3020 & D3030
2 D3010 Energy Supply - - - 101,455 1.7 169.1
3 D3010.1 Oil Supply Systems - - - 101,455
4 D3010.1.1 Storage Equipment 120,000 Liter 1 87,298 4x30,000 liter fuel tanks
4 D3010.1.2 Transfer Equipment 2 Nr 2,834 5,667 Includes fuel pumps
4 D3010.1.3 Distribution Piping 330 m 25.7 8,490 Assume 1% of total piping cost
2 D3020 Heat Generation 11,772 kW 55.3 651,473 10.8 1085.8
High pressure Scotch steam boilers
for laundry, kitchens, heating and
3 D3020.1 Steam Boilers 11,772 kW 55.3 651,473 domestic demands
4 D3020.1.1 Heating Boilers and Accessories 11,772 kW 42.4 498,842
4 D3020.1.2 Feedwater Equipment 3 Nr 25,991 77,974
4 D3020.1.3 Breechings, Chimneys, and Stacks 65 m 534 34,712
Includes water chemical treatment
4 D3020.1.4 Water Treatment Equipment 1 Item 39,945 39,945 and water softeners
2 D3030 Refrigeration 2,453 Ton 1,207 2,961,027 49.1 4935.0
3 D3030.1 Absorption Water Chillers 2,100 Ton 1,073 2,254,133
4 D3030.1.1 Chillers 2,100 Ton 1,069 2,244,842
4 D3030.1.2 Water Treatment Equipment 1 Item 9,291 9,291
3 D3030.2 Centrifugal Water Chillers 350 Ton 592 207,293
4 D3030.2.1 Chillers 350 Ton 592 207,293
Both induced and forced draught
3 D3030.3 Cooling Towers 2,450 Ton 195.8 479,772 cooling towers
4 D3030.3.1 Mechanical-Draft Cooling Towers 4 Nr 103,554 414,217
Includes water chemical treatment
4 D3030.3.2 Water Treatment Equipment 1 Item 65,555 65,555 and water softeners
3 D3030.4 Compressors and Condensers 3.2 Ton 6,197 19,829
4 D3030.4.1 Refrigerant Condensing Units 3.2 Ton 6,197 19,829 Air-cooled units - computer room

Data Date: December 1997


Page 6 of 12
Printed Date: 05/10/2019
HVAC COST SUMMARY - UNIFORMAT LEVELS 1 TO 4

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Individual Cost Per Cost Per
No. Section Element Qty Unit Rate $/Unit Cost $ Unit GFA Key Notes
2 D3040 HVAC Distribution 2,103 Ton 2,244 4,718,942 78.3 7864.9
3 D3040.1 Air Distribution Systems 2,103 Ton 1,288 2,708,966
4 D3040.1.1 Air Handling Units 164,500 L/s 5.5 902,543
4 D3040.1.2 Fans 168,020 L/s 1.1 179,232
4 D3040.1.3 Ducts 206,000 kg 5.4 1,102,877 Includes 685 m of round duct
4 D3040.1.4 Duct Accessories 206,000 kg 0.2 45,619
4 D3040.1.5 Duct Insulation (25 and 50 thick) 22,200 m2 5.5 122,807
4 D3040.1.6 Duct Lining (12 mm thick) 500 m2 8.6 4,286
4 D3040.1.7 Air Terminal Units 206 Nr 548.7 113,037 CAV and VAV terminal boxes
4 D3040.1.8 Air Outlets and Inlets 2,103 Ton 113.4 238,565
3 D3040.2 Steam Distribution Systems 11,772 kW 4.2 49,855
4 D3040.2.1 Steam and Condensate Piping 1,830 m 17.8 32,515 Includes pipe insulation
4 D3040.2.2 Steam Condensate Pumps 11,772 kW 1.5 17,340
Includes piping, valves, pipe
insulation, pumps and expansion
3 D3040.3 Hydronic Distribution Systems 19,158 kW 96.1 1,841,853 tanks
Assume piping length = 45% of
4 D3040.3.1 Hot Water Distribution Systems 11,772 kW 60.1 707,928 total hydronic piping length
Assume piping length = 45% of
4 D3040.3.2 Chilled Water Distribution Systems 7,386 kW 117.0 864,170 total hydronic piping length
Assume piping length = 10% of
4 D3040.3.3 Condenser Water Distribution Systems 7,386 kW 36.5 269,755 total hydronic piping length
3 D3040.4 Special Exhaust Systems 53,005 L/s 0.9 48,198
4 D3040.4.1 Fans 53,005 L/s 0.7 38,239 Includes kitchen fans only
4 D3040.4.2 Ducts 2,300 kg 4.3 9,959 Black steel and stainless steel
3 D3040.5 Auxiliary Equipment 3,467 kW 20.2 70,070
4 D3040.5.1 Heat Exchangers 3,467 kW 20.2 70,070 For building heating only.
2 D3050 Terminal and Packaged Units 676 Ton 1,001 676,868 11.2 1128.1

Data Date: December 1997


Page 7 of 12
Printed Date: 05/10/2019
HVAC COST SUMMARY - UNIFORMAT LEVELS 1 TO 4

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Individual Cost Per Cost Per
No. Section Element Qty Unit Rate $/Unit Cost $ Unit GFA Key Notes
3 D3050.1 Unitary Air Conditioning Equipment 9.2 Ton 4,287 39,440
4 D3050.1.1 Computer Room Air Conditioning Units 3.2 Ton 9,571 30,628
4 D3050.1.2 Unit Air Conditioners 6 Ton 1,469 8,812
3 D3050.2 Terminal Heat Transfer Units 667 Ton 955.7 637,428
4 D3050.2.1 Fan Coil Units 667 Ton 955.7 637,428
2 D3060 HVAC Instrumentation and Controls 20,400 kW 72 1,474,415 24.5 2457.4
Includes master and secondary
Energy Management & Conservation control stations c/w software
3 D3060.1 Systems 285 Points 499 142,256 packages
4 D3060.1.1 Building Automation System 285 Points 499 142,256
3 D3060.2 HVAC Instrumentation and Controls 20,400 kW 45.8 934,608 *Sum of sections D3020 & D3030
4 D3060.2.1 DDC's and FPU's 20,400 kW 20.9 425,760
4 D3060.2.2 Switches (Temperature, Pressure, etc.) 20,400 kW 12.1 246,985
4 D3060.2.3 Control Valves 20,400 kW 11.1 225,643
4 D3060.2.4 Control Dampers 20,400 kW 1.8 36,220
3 D3060.3 Other HVAC Instrumentation and Controls 20,400 kW 19.5 397,551
4 D3060.3.1 Motor Control Centers 3 Nr 95,217 285,651
4 D3060.3.2 Motor Control Panels 16 Nr 3,064 49,028
4 D3060.3.3 Other Electrical Works 1 Item 62,872 62,872
2 D3070 Testing, Adjusting, and Balancing 2,103 Ton 102 214,175 3.6 357.0

Data Date: December 1997


Page 8 of 12
Printed Date: 05/10/2019
HVAC COST SUMMARY - UNIFORMAT LEVELS 1 TO 2

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Individual Cost Per Cost Per
No. Section Element Qty Unit Rate $/Unit Cost $ Unit GFA Key Notes
1 D30 HVAC 20,400 kW* 529.3 10,798,355 179.2 17,997 *Sum of sections D3020 & D3030
2 D3010 Energy Supply - - - 101,455 1.7 169.1
2 D3020 Heat Generation 11,772 kW 55.3 651,473 10.8 1085.8
2 D3030 Refrigeration 2,453 Ton 1,207 2,961,027 49.1 4935.0
2 D3040 HVAC Distribution 2,103 Ton 2,244 4,718,942 78.3 7864.9
2 D3050 Terminal and Packaged Units 676 Ton 1,001 676,868 11.2 1128.1
2 D3060 HVAC Instrumentation and Controls 20,400 kW 72 1,474,415 24.5 2457.4
2 D3070 Testing, Adjusting, and Balancing 2,103 Ton 102 214,175 3.6 357.0

Data Date: December 1997


Page 9 of 12
Printed Date: 05/10/2019
HVAC COST SUMMARY - UNIFORMAT LEVELS 1 & 3

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Individual Cost Per Cost Per
No. Section Element Qty Unit Rate $/Unit Cost $ Unit GFA Key Notes
1 D30 HVAC 20,400 kW* 529.3 10,798,355 179.2 17,997 *Sum of sections D3020 & D3030
3 D3010.1 Oil Supply Systems - - - 101,455
High pressure Scotch steam boilers
for laundry, kitchens, heating and
3 D3020.1 Steam Boilers 11,772 kW 55.3 651,473 domestic demands
3 D3030.1 Absorption Water Chillers 2,100 Ton 1,073 2,254,133
3 D3030.2 Centrifugal Water Chillers 350 Ton 592 207,293
Both induced and forced draught
3 D3030.3 Cooling Towers 2,450 Ton 195.8 479,772 cooling towers
3 D3030.4 Compressors and Condensers 3.2 Ton 6,197 19,829
3 D3040.1 Air Distribution Systems 2,103 Ton 1,288 2,708,966
3 D3040.2 Steam Distribution Systems 11,772 kW 4.2 49,855
Includes piping, valves, pipe
insulation, pumps and expansion
3 D3040.3 Hydronic Distribution Systems 19,158 kW 96.1 1,841,853 tanks
3 D3040.4 Special Exhaust Systems 53,005 L/s 0.9 48,198
3 D3040.5 Auxiliary Equipment 3,467 kW 20.2 70,070
3 D3050.1 Unitary Air Conditioning Equipment 9.2 Ton 4,287 39,440
3 D3050.2 Terminal Heat Transfer Units 667 Ton 955.7 637,428
Includes master and secondary
Energy Management & Conservation control stations c/w software
3 D3060.1 Systems 285 Points 499 142,256 packages
3 D3060.2 HVAC Instrumentation and Controls 20,400 kW 45.8 934,608 *Sum of sections D3020 & D3030
3 D3060.3 Other HVAC Instrumentation and Controls 20,400 kW 19.5 397,551

Data Date: December 1997


Page 10 of 12
Printed Date: 05/10/2019
FIRE PROTECTION COST SUMMARY - UNIFORMAT LEVELS 1 TO 4

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Rate Cost Per Cost Per
No. Section Individual Element Qty Unit $/Unit Cost $ Unit GFA Key Notes
1 D40 Fire Protection - - - 1,309,730 21.7 2,183
2 D4010 Sprinklers 5,854 HDS 185.5 1,085,899 18.0 1809.8
3 D4010.1 Wet Pipe Fire Sprinkler Systems 5,854 HDS 185.5 1,085,899 Cost is for combined system

4 D4010.1.1 Piping and Valves 5,854 HDS 135.6 793,648 Average all pipe sizes 3.72 m/sprinkler
Two fire pumps and 1 jockey all @ 225
4 D4010.1.2 Equipment 225 kW 631 142,049 kW
4 D4010.1.3 Sprinklers 5,854 HDS 25.7 150,202 HDS: sprinkler heads
Cabinets only, piping cost included in
2 D4020 Standpipes 100 CAB 1,356 135,569 2.2 225.9 section D4010
3 D4020.1 Fire Protection Standpipe System 100 CAB 1,356 135,569
4 D4020.1.1 Hose Reels 100 CAB 1,356 135,569 CAB: fire cabinets (no.)
2 D4030 Fire Protection Specialties - PA - 7,978 0.1 13.3 PA: protected area (m2)
3 D4030.1 Fire Extinguishers 42 Nr 190.0 7,978
2 D4090 Other Fire Protection Systems - - - 80,284 1.3 133.8
3 D4090.1 CO2 Fire Extinguishing System 1 Item 80,284 80,284

Data Date: December 1997 Page 11 of 12


Printed Date: 05/10/2019
FIRE PROTECTION COST SUMMARY - UNIFORMAT LEVELS 1 TO 2

Project Name : PHOENICIA HOTEL Gross Floor Area : 60,269 (GFA, m2)
Job Number : L9799 Number of Keys : 600

Element
Level UniFormat Group Element Rate Cost Per Cost Per
No. Section Individual Element Qty Unit $/Unit Cost $ Unit GFA Key Notes
1 D40 Fire Protection - - - 1,309,730 21.7 2,183
2 D4010 Sprinklers 5,854 HDS 185.5 1,085,899 18.0 1809.8
Cabinets only, piping cost included in
2 D4020 Standpipes 100 CAB 1,356 135,569 2.2 225.9 section D4010
2 D4030 Fire Protection Specialties - PA - 7,978 0.1 13.3 PA: protected area (m2)
2 D4090 Other Fire Protection Systems - - - 80,284 1.3 133.8

Data Date: December 1997 Page 12 of 12