Process for finding

consumption of material
for a particular project
for a given period.
(1) Type Tcode – MB51 and Press Enter Key
(2) Enter Movement Type (281, 282) WBS Element No., Posting date (date
range of consumption of material) as shown in following example. And then
click on Execute icon (F8).
(3) click on Execute icon (F8).
(4) You will get a report for all material consumed on WBS Element No., during
specified period as shown in following example.
(5) You can also export the report to excel using menu bar LIST > Export >
Spreadsheet and save.