Академический Документы
Профессиональный Документы
Культура Документы
& Embankment
Construction
Presentation by
Sudhir Mathur
Head
Geotechnical Engineering Division
Central Road Research Institute, New Delhi
Major Road Construction
Programmes
• National Highway Development
Programme (NHDP)
• Pradhan Mantri Gram Sadak Yojna
(PMGSY)
Necessity of alternate
materials
• Large quantities of construction materials
required
Published in 2001
Guidelines for Use of Fly ash in
Road Embankments
These guidelines provide salient details regarding design
and construction of road embankments using fly ash
• Site investigations
• Characterization of materials
• Detailed design
• Clearing and grubbing
• Stripping and storing top soil
• Setting out
• Dewatering
• Compacting the ground supporting embankment
• Handling and transportation of fly ash
• Spreading and compaction
Fly Ash for Road Embankment
Earth
Earth
Cover
Cover
Bottom ash or
Pond ash
Granular Layer
0.5m
minimum
Selected FLYASH
Earth Cover
FLYASH 1-3m
FLYASH
Instrumentation
Installation of settlement
gauge under progress
Approach Embankment for Nizamuddin Bridge
0.15 m, M15
Weep holes at 1- Parameter Pond ash Earth cover Sub soil
concrete 2m c/c
Filter 0.2 m, thick bulk 1.56 kg/cm2 2.0 kg/cm2 1.8 kg/cm2
Stone pitching, 0.3 m thick
c 0 0.15 kg/cm2 0
AGENCIES INVOLVED
• Length of road - 60 km
• Height of embankment - 2 to 4 m
• Water logged conditions
• Soft sub-soil conditions
Four-laning work on NH-6, Dankuni to Kolaghat,
Existing
carriage
way
Granular sub-base
SPREADING OF GEOTEXTILE
OVER SOFT GROUND
Four-laning work on NH-6, Dankuni to Kolaghat,
SPREADING OF GEOTEXTILE
OVER SOFT GROUND
Four-laning work on NH-6, Dankuni to Kolaghat,
7.8 m
to 5.9 m
7.8 m
R einforced Foundation Mattress
of B ottom ash
Erection of facing panels
Laying of geogrids
Hanuman Setu Flyover Approach Embankment
Arrangement of friction
ties before laying pond
ash
Compaction of pond
ash using static and
vibratory rollers
Compaction using
plate vibrator near the
facing panels
Design of Reinforced Flyash
Embankment
• Height of Wall – 8m
• Reinforcing Material – Geogrid
• Back Fill – Soil and Flyash
• Design of Wall- BS 8006-1995
• Checks made- Internal and External Stability
- F.S. against Sliding
- F.S. against overturning
- F.S against bearing capacity
- F.S. against rupture
- F.S. against pullout
No of Layers = 16 No of Layers = 12
7.4
6.8 7
6.2 6.2
5.6
5.4
5
4.4 4.6
Soil 3.8
3.4 Fly Ash 3.8
3 3.2
2.6 2.6
2.2
1.8 2
1.4 1.4
1
0.6 0.8
0.2 0.2
0 2 4 6 8 0 2 4 6 8
Length of geogrid (m)
Length of geogrid (m)
• Failures observed
on both sides of
slope
•More pronounced on
d/s side
•Deep cavities were
observed exposing
fly ash at many
locations
• Undermining caused
caving in of road
pavement
Causes of
Failure
• Heavy flow of
water intersected
side slopes
inspite of grass
turfing
•Deep pits in slope
to provide
foundation for
crash barrier and
electric poles
•Pits were loosely
backfilled
Immediate Preventive
Measures
• Prevention of flow of
water in side slopes by
providing soil filled up
bags through out the
slope
•Filling of soil in erosion
gullies
•Filling of soil filled
bags in deep cavities
Long Term Remedial
Measures
• Compaction of Side Slopes
• Provision of Toe Walls
• Provision of Kerb Channel
• Provision of Chutes
• Provision of drains in Medians
• Provision of Stone Pitching along with Filter
(Granular/Geotextile)
Remedial Measures
IRC Guidelines / Specifications
Guidelines available on pavement construction
IRC 60 ‘Tentative guidelines for use of lime fly
ash concrete as pavement base or subbase’
IRC 68 ‘Tentative guidelines on cement fly
ash concrete for rigid pavement construction’
IRC 74 ‘Tentative guidelines for lean cement
concrete and lean cement fly ash concrete as
a pavement base or subbase’
IRC 88 ‘Recommended practice for lime fly
ash stabilised soil as base or subbase in
pavement construction’
Conclusions
• Ideally suited as back fill material for urban/
industrial areas and areas with weak sub soils
• Higher shear strength leads to greater stability
• Design is similar to earth embankments
• Intermediate soil layers for ease of construction
and to provide confinement
• Side slope erosion needs to be controlled by
providing soil cover
• Can be compacted under inclement weather
conditions
• Use of vibratory rollers is preferred
In road projects savings to the extent of 15-25 per
cent can be achieved. Savings depend on cost of
transportation of fly ash
Coarse ash is suitable as a fill material, finer part of
the ash (fly ash) collected in dry form can be used
to replace cement
Fly ash collection and handling techniques need to
be improved
Use of ash for all road projects in the vicinity of
thermal power plant should be made mandatory
Conservation of conventional construction
materials is possible by adopting fly ash for road
construction
Thank you