METHOD STATEMENT
FOR
BORED PILE WORK
CONTENT
1. Preliminary.
2. Technical data.
3. Mobilization of equipment and manpower.
4. Preparation work.
5. Preliminary work.
6. Surveying work.
7. Preparation for working platform.
8. Pre-drilling work.
9. Installation of top casing.
10. Drilling work.
11. Installation of rebar cage.
12. Installation of tremie pipe.
13. Installation of guide template.
14. Concreting Work.
15. Removing tremie pipe.
16. Removing top casing.
17. Installation of pipe support.
18. Installation of curve form and concreting.
19. Repairing area.
Appendix:
- Sketch / Drawing.
- List of equipment.
- Site Organization chart.
- Time schedule.
- Catalogue or Brochure.
FCRS AND POWER PLANT
LUMUT BALAI (Rev-01)
1. Preliminary.
In connection with bored pile work for FCRS and Power Plant - Lumut Balai,
Plant South Sumatera, herewith PT. Berdikari Pondasi Perkasa submits this
proposal as reference and guidance to execute the bored pile work for above
project.
2. Technical data.
Type of pile = Bored Pile.
Pile Ø = 600 mm, 700 mm.
Depth of pile = 4 m to 8 m (max).
Total length = Ø600mm = 4,550 m’ , Ø700mm = 4,918 m.
4. Preparation Work.
- Setup temporary site office, work shop, warehouse.
- Prepare the shop drawing.
- Prepare mess for accommodation and safety induction for personnel.
- Etc.
5. Preliminary Work.
a. Prepare the site access road including gradding and compacting.
b. Set up the equipment (excavator as drilling m/c, welding machine,
excavator as service, bar cutter / bar roller, welding m/c etc).
- Set up the drilling rig, install the rod and motor etc.
- Set up the service excavator for service.
FCRS AND POWER PLANT
LUMUT BALAI (Rev-01)
6. Surveying Work.
Before starting bored pile work, prior to surveying for bored pile position.
1. Surveyor will prepare the Total station and prism.
2. IKPT should prepare minimum two points as point reference or master
point (A and B) with value of coordinate and elevation.
3. Then surveyor will make auxiliary point (C) as near as possible with bored
pile location.
4. Set up the Total station on one of the master point (A).
5. Then measure the degree from AB to AC.
6. And measure the distance from A to C using prism or distomatch.
7. Then by calculating degree and distance surveyor will calculate coordinate
C.
8. Then move position of Total station to point C.
9. From point C (auxiliary point) surveyor will set the point coordinate of
bored pile (D) by calculating degree CB-CD and distance from C to D
point.
10. Repeat to measure for the next point by same method.
8. Pre-drilling Work.
- Prepare drilling machine including motor and auger.
- Move drilling machine to the platform.
- Check levelling of drilling machine.
- Then start to pre-drilling work by rotating the motor.
- During drilling work, the soil will move out from the hole.
- Continue to drilling work until 4m.
- Then release the lifting sling and the pipe will stand up by him self.