DQS393

MEASUREMENT OF
CIVIL ENGINEERING WORKS

EARTHWORK :
VOLUME
CALCULATION

A ‘PIECE OF WORK’ BY :
NUR’AIN BT. ISMAIL

DQS393_CLASS F :
1
EARTHWORK_NUR'AIN ISMAIL
LEARNING OUTCOMES

• Ability to prepare draft Bills of


Quantities based on Malaysian Civil
Engineering Standard Method of
Measurement for EARTHWORKS.

DQS393_CLASS F :
2
EARTHWORK_NUR'AIN ISMAIL
EARTHWORK

• General principle = to measure


excavation works.
• Shown in drawings or directed by the
engineer/S.O/PD.

• NOT COVERED = any excavation for


temporary works done by the
Contractor.

DQS393_CLASS F :
3
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

DQS393_CLASS F :
4
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

CLASS F : Excavation in CUT


MEASURED IN CUBIC METRE (m³).
1. Cut to fill
– The excavated material is used as
filling for the Work.
– EXCAVATION + FILLING (with
excavated material)
2. Cut and dispose
– The excavated material is to be
disposed of.
– EXCAVATION + DISPOSAL

DQS393_CLASS F :
5
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

Excavation in a LARGE VOLUME


involving CUT, DISPOSE and FILL.

CUT
PROPOSED
PLATFORM
LEVEL

FILL

DQS393_CLASS F :
6
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION
1. Volume of CUT > FILL

CUT

PROPOSED
PLATFORM
LEVEL

FILL

The items that shall be


measured :
BALANC
a. CUT TO FILL E
TO BE
b. CUT AND DISPOSE DISPOSE

DQS393_CLASS F :
7
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION
2. Volume of CUT < FILL

CUT
PROPOSED
PLATFORM
LEVEL

FILL

The items that shall be


measured :
a. CUT TO FILL FILLING
WITH
IMPORTED
b. FILLING MATERIAL

DQS393_CLASS F :
8
EARTHWORK_NUR'AIN ISMAIL
VOLUME CALCULATION
METHOD
There are various method of
calculation the volume that can be
used.

MOST USED and RELIABLE METHOD


of calculating the VOLUME of
excavation in cut :
• Average Depth Method (with or
without weightage)
• Simpsons’ Rules
• Prismodal Rules
• Conventional Method
DQS393_CLASS F :
9
EARTHWORK_NUR'AIN ISMAIL
VOLUME CALCULATION
METHOD
• Method used largely determined
by the shape and type of works.
• Accuracy, reasonableness and
speed of operation are the main
factors to consider when selecting
the method of calculating the
volume of excavation.
• Method used must be agreed at
an early stage before works starts.

DQS393_CLASS F :
10
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

Average Depth Method (with or


without weightage)

Suitable for preparation of platform


for domestic development such as
residential usually involves cutting
and filling

DQS393_CLASS F :
11
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD

DQS393_CLASS F :
12
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
Site Boundary
15.00

15.00
scale : 1:100

DQS393_CLASS F :
13
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
Site Boundary
15.00

15.00
scale : 1:100
create GRID
size 25 x 25

DQS393_CLASS F :
14
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
Site Boundary

A B C D E F G

1
C2 D2 E2

2
3
15.00

4
5
Labeled GRID POINT

6
7

15.00
scale : 1:100
create GRID
size 25 x 25

DQS393_CLASS F :
15
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
Site Boundary

A B C D E F G

1
CUT
C2 D2 E2
FILL

2
Platform Level =
80.00

3
15.00

4
5
Labeled GRID POINT

6
7

15.00
scale : 1:100
create GRID
size 25 x 25

DQS393_CLASS F :
16
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
Site Boundary

A B C D E F G

1
CUT
C2 D2 E2
FILL

2
Platform Level =
80.00

3
Identify LEVEL of
15.00

EACH grid point using

4
INTERPOLATION
METHOD

5
Labeled GRID POINT

6
7

15.00
scale : 1:100
create GRID
size 25 x 25

DQS393_CLASS F :
17
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
Identify LEVEL of EACH grid point using INTERPOLATION
METHOD

View ON PLAN
C
B
y A
x 1. Identify distance
AB (x) & BC (y)

Level : 80.00

E
Grid point E5
D View by SECTION

Height :
1.00 m

Y : 1.60 m X : 2.30 m A
C B
Level : 79.00 Level : 79.00
DQS393_CLASS F :
18
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
Level : 80.00
E
Grid point E5
D

Height :
1.00 m

Y : 0.60 m B X : 2.30 m A
C
Level : 79.00 Level : 79.00

2. Insert in Formulae below :


AB DB
=
AC EC
DB AB
=
EC AC
AB X EC X (1.00)
DB = = = Z
AC
( X + Y)
2.30 (1.00)
= = 0.59
(2.30 + 1.60)

E5 = 79.00 + 0.59

= 79.59

DQSQSD393_CLASS F :
19
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD – CUT TABLE
POINT EXISTING LEVEL PLATFORM LEVEL DEPTH

A1 84.80 80.00 4.80


A2 83.67 80.00 3.67
A3 82.63 80.00 2.63
A4 81.62 80.00 1.62
A5 80.60 80.00 0.60
B1 83.80 80.00 3.80
B2 83.13 80.00 3.13
B3 82.27 80.00 2.27
B4 81.43 80.00 1.43
B5 80.44 80.00 0.44
C1 82.47 80.00 2.47
C2 82.21 80.00 2.21
C3 81.72 80.00 1.72
C4 81.09 80.00 1.09
C5 80.20 80.00 0.20
D1 81.55 80.00 1.55
D2 81.42 80.00 1.42
D3 80.90 80.00 0.90
D4 80.37 80.00 0.37
E1 80.50 80.00 0.50
E2 80.13 80.00 0.13

TOTAL 36.95

Average DEPTH : 36.95 m 1.76 m


=
21

DQS393_CLASS F :
20
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD – FILL TABLE
POINT EXISTING LEVEL PLATFORM LEVEL DEPTH

A6 78.29 80.00 1.71


A7 78.88 80.00 1.12
B6 78.94 80.00 1.06
B7 78.18 80.00 1.82
C6 79.00 80.00 1.00
C7 78.17 80.00 1.83
D5 79.71 80.00 0.29
D6 78.84 80.00 1.16
D7 78.10 80.00 1.90
E3 79.86 80.00 0.14
E4 79.59 80.00 0.41
E5 79.23 80.00 0.77
E6 78.60 80.00 1.40
E7 77.86 80.00 2.14
F1 79.62 80.00 0.38
F2 79.41 80.00 0.59
F3 79.21 80.00 0.79
F4 78.80 80.00 1.20
F5 78.59 80.00 1.41
F6 78.23 80.00 1.77
F7 77.52 80.00 2.48
G1 78.84 80.00 1.16
G2 78.63 80.00 1.37
G3 78.36 80.00 1.64
G4 78.07 80.00 1.93
G5 77.80 80.00 2.20
G6 77.36 80.00 2.64
G7 76.83 80.00 3.17

TOTAL 39.48

Average DEPTH : 39.48 m 1.41 m


=
28 DQS393_CLASS F :
21
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD

VOLUME OF CUT :

1
CUT = X Length X Width X Depth
2

= 1
X 150.00 m X 150.00 m X 1.76 m
2

= 19,800.00 m³

VOLUME OF FILL :

1
FILL = X Length X Width X Depth
2

= 1
X 150.00 m X 150.00 m X 1.41 m
2

= 15,862.50 m³

DQS393_CLASS F :
22
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork in Lot 1234, Seri EARTHWORK 1
Iskandar, Perak for UiTM (Perak)

Heading :

Description: Code : Unit : m³

Excavation ; cut to fill ; earth


F121 Qtty :
15,863

1
2 150.00 [ Fill
150.00
1.41

15,862.50

DQS393_CLASS F :
23
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork in Lot 1234, Seri EARTHWORK 2
Iskandar, Perak for UiTM (Perak)

Heading :

Description: Code : Unit : m³

Excavation ; cut and dispose ; earth


F131 Qtty :
3,938

1
2 150.00 [ Cut
150.00
1.76

19,800.00

1
2 150.00 [ DDT Fill
150.00
1.41

15,862.50

3,937.50

DQS393_CLASS F :
24
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork in Lot 1234, Seri EARTHWORK 3
Iskandar, Perak for UiTM (Perak)

Heading :

Description: Code : Unit : m³

Filling ; general ; excavated material


F311 Qtty :
15,863

15,862.50 [ Fill
1.00 quantity taken
1.00 from slip no 1

15,862.50

DQS393_CLASS F :
25
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD
(WITH WEIGHTAGE)
Site Boundary

A B C D E F G

1
1 2 2 2 2 2 1

2
2 4 4 4 4 4 2

3
CUT
15.00

4
FILL

5
6

1 2
7

15.00
scale : 1:100

Platform Level = 80.00

DQS393_CLASS F :
26
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD (with
weightage) – CUT TABLE
CUT

POINT EXISTING PLATFORM DEPTH WEIGHTAGE WEIGHTAGE


LEVEL LEVEL DEPTH
A1 84.80 80.00 4.80 1 4.80
A2 83.67 80.00 3.67 2 7.34
A3 82.63 80.00 2.63 2 5.26
A4 81.62 80.00 1.62 2 3.24
A5 80.60 80.00 0.60 2 1.80
B1 83.80 80.00 3.80 2 7.60
B2 83.13 80.00 3.13 4 12.52
B3 82.27 80.00 2.27 4 9.08
B4 81.43 80.00 1.43 4 5.72
B5 80.44 80.00 0.44 4 1.76
C1 82.47 80.00 2.47 2 4.94
C2 82.21 80.00 2.21 4 8.84
C3 81.72 80.00 1.72 4 6.88
C4 81.09 80.00 1.09 4 4.36
C5 80.20 80.00 0.20 4 0.80
D1 81.55 80.00 1.55 2 3.10
D2 81.42 80.00 1.42 4 5.68
D3 80.90 80.00 0.90 4 3.60
D4 80.37 80.00 0.37 4 1.48
E1 80.50 80.00 0.50 2 1.00
E2 80.13 80.00 0.13 4 0.52

TOTAL 36.95 Y (65) X (100.32)

Average Total
WEIGHTAGE Weightage Zm
=
DEPTH : depth
(X)

Total
weightage
(Y) QSD393_CLASS F :
27
EARTHWORK_NUR'AIN ISMAIL
AVERAGE DEPTH METHOD (with
weightage) – FILL TABLE
FILL

POINT EXISTING PLATFORM DEPTH WEIGHTAGE WEIGHTAGE


LEVEL LEVEL DEPTH
A6 78.29 80.00 1.71 2 3.42
A7 78.88 80.00 1.12 1 1.12
B6 78.94 80.00 1.06 4 4.24
B7 78.18 80.00 1.82 2 3.64
C6 79.00 80.00 1.00 4 4.00
C7 78.17 80.00 1.83 2 3.66
D5 79.71 80.00 0.29 4 1.16
D6 78.84 80.00 1.16 4 4.64
D7 78.10 80.00 1.90 2 3.80
E3 79.86 80.00 0.14 4 0.56
E4 79.59 80.00 0.41 4 1.64
E5 79.23 80.00 0.77 4 3.08
E6 78.60 80.00 1.40 4 5.60
E7 77.86 80.00 2.14 2 4.28
F1 79.62 80.00 0.38 2 0.76
F2 79.41 80.00 0.59 4 2.36
F3 79.21 80.00 0.79 4 3.16
F4 78.80 80.00 1.20 4 4.80
F5 78.59 80.00 1.41 4 5.64
F6 78.23 80.00 1.77 4 7.08
F7 77.52 80.00 2.48 2 4.96
G1 78.84 80.00 1.16 1 1.16
G2 78.63 80.00 1.37 2 2.74
G3 78.36 80.00 1.64 2 3.28
G4 78.07 80.00 1.93 2 3.86
G5 77.80 80.00 2.20 2 4.40
G6 77.36 80.00 2.64 2 5.28
G7 76.83 80.00 3.17 1 3.17

TOTAL 39.48 79 97.49

Average 97.49 m 1.23 m


WEIGHTAGE =
DEPTH : 79

DQS393_CLASS F :
28
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork in Lot 1234, Seri EARTHWORK 1
Iskandar, Perak for UiTM (Perak)

Heading :

Description: Code : Unit : m³

Excavation ; cut to fill ; earth


F121 Qtty :
13,838

1
2 150.00 [ Fill
150.00
1.23

13,837.50

DQS393_CLASS F :
29
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork in Lot 1234, Seri EARTHWORK 2
Iskandar, Perak for UiTM (Perak)

Heading :

Description: Code : Unit : m³

Excavation ; cut and dispose ; earth


F131 Qtty :
3,488

1
2 150.00 [ Cut
150.00
1.54

17,325.00

1
2 150.00 [ DDT Fill
150.00
1.23

13,837.50

3,487.50

DQS393_CLASS F :
30
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork in Lot 1234, Seri EARTHWORK 3
Iskandar, Perak for UiTM (Perak)

Heading :

Description: Code : Unit : m³

Filling ; general ; excavated material


F311 Qtty :
13,838

13,837.50 [ Fill
1.00 quantity taken
1.00 from slip no 1

13,837.50

DQS393_CLASS F :
31
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

Simpsons’ Rules a.k.a


Cross Section Method

Suitable for preparation of platform


for road or railway track which
involve cutting and filling.

DQS393_CLASS F :
32
EARTHWORK_NUR'AIN ISMAIL
Simpsons’ Rules

DQS393_CLASS F :
33
EARTHWORK_NUR'AIN ISMAIL
QSD393_CLASS F :
34
EARTHWORK_NUR'AIN ISMAIL
SIMPSON’S RULES

Application of Simpson’s Rule


1
= X distance between X sum of all cross-
3 cross section section

Notes :

Cross-sections must be odd / even number of spaces


between cross-sections.

The areas of even cross section are multiplied by 4.

The areas of odd cross section are multiplied by 2.

The areas of end cross section are multiplied by 1.

DQS393_CLASS F :
35
EARTHWORK_NUR'AIN ISMAIL
SIMPSON’S RULES
X1 X4 X2 X4 X2 X4 X1
A
1 2 3 4 5 6 7

Identify the height by using 20.00 m


16.00 m 18.00 m
scale or interpolation
10.00 m 12.00 m
method

6.00 m
4.00 m

50.00 m

A
Divide length into same
400.00 m
distance of cross section

Slope ratio = 2:1


Cross section A-A
20.00 m
1 X = 10.00

Area = ½ X (a+b) X h 2 Y = 20.00


Area = ½ X (40+60) X 20

Area = 1000 m2 X 4
40.00 m

DQS393_CLASS F :
36
EARTHWORK_NUR'AIN ISMAIL
b

40.00 m
1

2
20.00 m

Slope

40.00 m

a
Slope ratio = 2:1

Area = ½ X (a+b) X h

DQS393_CLASS F :
2
EARTHWORK_NUR'AIN ISMAIL
Cross section area
Cross
section = 1
X (40.00m + 44.00m) X 4.00m
1 2

= 168.00m2 X 1

= 168.00m2

Cross
section = 1
X (40.00m + 50.00m) X 10.00m
2 2

= 450.00m2 X 4

= 1800.00m2

DQS393_CLASS F :
38
EARTHWORK_NUR'AIN ISMAIL
Cross section area

Cross
section = 1
X (40.00m + 56.00m) X 16.00m
3 2

= 768.00m2 X 2

= 1536.00m2

Cross
section = 1
X (40.00m + 58.00m) X 18.00m
5 2

= 882.00m2 X 2

= 1764.00m2

DQS393_CLASS F :
39
EARTHWORK_NUR'AIN ISMAIL
Cross section area

Cross
section = 1
X (40.00m + 52.00m) X 12.00m
6 2

= 184.00m2 X 4

= 736.00m2

Cross
section = 1
X (40.00m + 46.00m) X 6.00m
7 2

= 258.00m2 X 1

= 258.00m2

DQS393_CLASS F :
40
EARTHWORK_NUR'AIN ISMAIL
1
= X distance between X sum of all cross-
3 cross section section

1
= X 50.00m X 168.00m2 + 1800.00m2
3
1536.00m2 + 4000.00m2
1764.00m2 + 736.00m2

+ 258.00m2

1
= X 50.00m X 10,262.00m2
3

= 156,033.33 m3

DQS393_CLASS F :
41
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork for Road in Lot EARTHWORK 1
1234, Seri Iskandar, Perak

Heading :

Description: Code : Unit : m³

Excavation ; cut and dispose ; earth


F131 Qtty :
156,033

1
3 50.00 [ Cut
9362.00
1.00

156,033.33

DQS393_CLASS F :
42
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

Primordial Rules

Simpler in calculation but accuracy


suspected.

DQS393_CLASS F :
43
EARTHWORK_NUR'AIN ISMAIL
PRIMORDIAL RULES
Application of Primodial Rule
First 4X Last
1
X Total length X cross + middle + cross
=
6 cross section
section
area section area
area

First Middle Last


cross cross cross
section section section
area area area
1 2 3 4 5 6 7

20.00 m
16.00 m 18.00 m
10.00 m 12.00 m

6.00 m
4.00 m

400.00 m

Total length

DQS393_CLASS F :
44
EARTHWORK_NUR'AIN ISMAIL
Cross section area
First
Cross = 1
X (40.00m + 44.00m) X 4.00m
section 2

= 168.00m2

Middle
Cross = 1
X (40.00m + 60.00m) X 20.00m
section 2

= 1000.00m2

Last
Cross = 1
X (40.00m + 46.00m) X 6.00m
section 2

= 258.00m2

DQS393_CLASS F :
45
EARTHWORK_NUR'AIN ISMAIL
Application of Primodial Rule
First 4X Last
1 + +
= X Total length X cross middle cross
6 cross section
section
area section area
area

168.00 4X 258.00
1
X 400.00m X m2 + 1000.00 + m2
=
6 m2

168.00 4,000.00 258.00


1 400.00m X + +
= X m2 m2 m2
6

1 400.00m X 4,426.00m2
= X
6

= 295,066.67m3

DQS393_CLASS F :
46
EARTHWORK_NUR'AIN ISMAIL
CLASS F : EARTHWORK
Job : Element : Slip No :
Proposed Earthwork for Road in Lot EARTHWORK 1
1234, Seri Iskandar, Perak

Heading :

Description: Code : Unit : m³

Excavation ; cut and dispose ; earth


F131 Qtty :
295,066

1
6 400.00 [ Cut
4426.00
1.00

295,066.67

DQS393_CLASS F :
47
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

Conventional Method

The volume measured by counting


the numbers of lorries (for other
means) used to remove material
from site or importing to site for
filling purposes.
This method may be not scientific
but it is easy to be agreed by both
parties, since it involve give and
take basis.

DQS393_CLASS F :
48
EARTHWORK_NUR'AIN ISMAIL
BULK EXCAVATION

Conventional Method
1. Multiplying the capacity of the
transport vehicle.
2. The number of loads dumped into
the Site.
3. Weighing the rock and convert into
volume by using density

DQS393_CLASS F :
49
EARTHWORK_NUR'AIN ISMAIL
the END
DQS393_CLASS F :
50
EARTHWORK_NUR'AIN ISMAIL
REFERENCES
• Construction Industry Development Board (2011).
Malaysian Civil Engineering Standard Method of
Measurement (CESMM). Malaysia: CIDB

• Construction Industry Development Board (2011). A


Guide to Malaysian Civil Engineering Standard Method
of Measurement (CESMM). Malaysia: CIDB.

QSD393_CLASS F :
51
EARTHWORK_NUR'AIN ISMAIL