INSPECTION AND TEST PLAN
PROJECT NAME
EQUIPMENT DESCRIPTION: Customer Contract/PO No: Project No.: ITP/Document No. Revision Date Page No.
ZX2 500971894 1YHD000000A0678 B Aug-18-2014 2 of 11
Completely equipped as
SES-E08-S02 Approved
operating feeder, as specified Test Record W1 R R
Sec-7 Drawings
on the one line diagram
Similar to a ‘spare’ except that
SES-E08-S02
the main circuit breaker shall Drawings Test Record W1 R R
Sec-7
not be installed
SES-E08-S02
Drawings Test Record W1 R R
Sec-9
Aaccording to
IEC62271-200 Clause
5.32 earthing
SES-E08-S02 requirement, The
Check Ground Bus Drawings Test Record W1 R R
Sec-9 current density is not
exceed 200A/square.
Main earthing busbar
is 10*40mm.
3 poles, air break/vacuum The fixed Circuit
interrupter type, draw out, Approved Breaker, Vacuum
SES-E08-S02
Check Circuit Breakers electrically and manually Drawings Test Record W1 R R interrupter type for
Sec-8
operated, rated, manufactured &IEC-62271-100 GIS Switchgear
and tested to conform.
5 Final Inspection
No violation
Final inspection prior to Vendor
5.1 Final inspection Refer PEI drawings I I I observed during
packing & shipment Forms
inspection
Verify the rectification of punch Clearance of Sign off Inspection Release
5.2 Final Acceptance Refer PEI I H H
items & functional test punch items Punch items Report
Abbreviations: SES = PCQ-2 Engineering Standards, PEI=Project Execution Instructions, QVD=Quality Verifying Document
Legend:
(1) ‘Prepared by’ should be the name, signature and Company’s name for the Vendor’s (ABB Xiamen Switchgear Co., Ltd.)
(2) ‘Approved by’ should be the name, signature and Company’s name for the Contractor’s representative.
(3) ‘Location’, ‘Item Name’ and ‘Tag Number’ shall be used if applicable.
(4) ‘Characteristics Verified’ are the parameters checked during the inspection activity.
(5) ‘Reference Document’ is the Project Specification / Code / Standard / Drawing, Procedure, etc on the basis of which inspection shall be conducted.
(6) ‘Acceptance Criteria’ is the tolerance, reading, value or an outcome derived from reference documents.
(7) “Verifying Document’ is the record generated during inspection & Testing using approved forms / checklists. All forms and checklists shall be attached
to the ITP and submitted to the Company during Approval Stage.
(8) “Inspection Responsibility’ is the role of Vendor / Sub Contractor , Contractor and Company for each inspection step. Inspection responsibility shall be ‘I’ for
Inspection, ‘R’ for review, ‘A’ for approval, ‘S’ for Surveillance, “W1’ for 100% Witness, ‘W2’ for random witness and ‘H’ for hold. For the explanation of these
inspection responsibilities refer to the ‘definitions’ part of PEI section 4.7.1
(9) “ABB CNDMX” Xiamen Switchgear Co., Ltd.
NAME OF VENDOR:
INSPECTION WAIVED :
REQUISITION NO. :
EQUIPMENT/MATERIAL :
MATERIAL CONTROLLER
INSPECTION COORDINATOR CNCEC INSPECTOR
We hereby inform you of the following inspection schedule for OWNER's witness.
3) Date of Inspection:
4a) Inspection Activity: This part shall be linked to the Inspection & Test Plan
7) Vendor Details
a) Vendor Name
b) Address:
c) Person in charge:
d) tel: e) fax:
e) email
8) Place of Inspection:
The below fields shall be filled up if the manucturer is different than the vendor
9) Manufacturer Details
a) Manufacturer Name
b) Address:
c) Person in charge:
d) tel: e) fax:
e) email
10)
Remarks: _____________________________________________________________________________________