Item Description Units Item Rate Amount in INR
No. Quantity
a i Earth work excavation in soil (Depth Up to 3.00m) Cu.M 530 185.00 98,050
5 Cement concrete for plain CC for substructure M15 Cu.M 20 5762.00 1,15,240
grade
6 Cement Concrete for reinforced concrete for Cu.M 400 7685.00 30,74,000
foundation M40 grade
7 Cement concrete for reinforced concrete for Cu. M. 785 8772.00 68,86,020
substructure M40
8 Cement concrete for reinforced concrete for Cu. M. 405 9183.00 37,19,115
superstructure M40
11 PCC below approach slab and foot path PCC Cu.M 121 5770.00 6,98,170
S. Total
Item Description Units Item Rate Amount in INR
No. Quantity
19 Supplying, fitting and fixing in position true to line MT 10400 388.00 40,35,200
and level POT-PTFE bearing consisting of a metal
piston supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust
seals, PTFE surface sliding against stainless steel
mating surface, completre assembly to be of cast
steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of MoRTH
Specifications complete asper drawing and
approved technical specifications.
20 Providing and fixing strip seal type expansion joint RM 64 19315.00 12,36,160
24 Providing and fixing in position with clamps 100 mm RM 321 500.00 1,60,500
diameter PVC downtake and runner pipe
25 Providing and laying PVC 150mm dia service pipes RM 904 500.00 4,52,000
fixed on side of the crash barrier
26 Painting to Structure Sq.m 1503 157.00 2,35,971
Total 14,11,48,089
Bottom and top Flange Plate 4 63.400 0.73 0.025 7.84 36.285
Side Plates 4 63.400 0.95 0.025 7.84 47.220
Hanger (Section C-C)
U1-L1
Bottom plate 4 4.646 0.42 0.025 7.84 1.530
Top plate 4 4.646 0.40 0.025 7.84 1.457
Side Plates 8 4.646 0.75 0.025 7.84 5.464
U2-L2
Bottom plate 4 7.432 0.42 0.025 7.84 2.447
Top plate 4 7.432 0.4 0.025 7.84 2.331
Side Plates 8 7.432 0.75 0.025 7.84 8.740
U3-L3
Bottom plate 4 9.330 0.42 0.025 7.84 3.072
Top plate 4 9.330 0.4 0.025 7.84 2.926
Side Plates 8 9.330 0.75 0.025 7.84 10.972
U4-L4
Bottom plate 4 10.436 0.42 0.025 7.84 3.436
Top plate 4 10.436 0.4 0.025 7.84 3.273
Side Plates 8 10.436 0.75 0.025 7.84 12.273
U5-L5
Bottom plate 2 10.800 0.42 0.025 7.84 1.778
Top plate 2 10.800 0.4 0.025 7.84 1.693
Side Plates 4 10.800 0.75 0.025 7.84 6.350
Arc Long Beam (Section D-D)
S. Total
Item Description Units Item Rate Amount in INR
No. Quantity
1 Earthwork
a i Earth work excavation in soil (Depth Up to 3.00m) Cu.M 530 185.00 98,050
5 Cement concrete for plain CC for substructure M15 Cu.M 20 5762.00 1,15,240
grade
6 Cement Concrete for reinforced concrete for Cu.M 393 7685.00 30,20,205
foundation M40 grade
7 Cement concrete for reinforced concrete for Cu. M. 885 8772.00 77,63,220
substructure M40
8 Cement concrete for reinforced concrete for Cu. M. 405 9183.00 37,19,115
superstructure M40
11 PCC below approach slab and foot path PCC Cu.M 126 5770.00 7,27,020
S. Total
Item Description Units Item Rate Amount in INR
No. Quantity
19 Supplying, fitting and fixing in position true to line MT 12000 388.00 46,56,000
and level POT-PTFE bearing consisting of a metal
piston supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust
seals, PTFE surface sliding against stainless steel
mating surface, completre assembly to be of cast
steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of MoRTH
Specifications complete asper drawing and
approved technical specifications.
20 Providing and fixing strip seal type expansion joint RM 88 19315.00 16,99,720
24 Providing and fixing in position with clamps 100 mm RM 321 500.00 1,60,500
diameter PVC downtake and runner pipe
25 Providing and laying PVC 150mm dia service pipes RM 630 500.00 3,15,000
fixed on side of the crash barrier
27 Painting to Structure Sq.m 3000 157.00 4,71,000
28 High tensile steel wires/strands including all MT 21 99615.00 20,91,915
accessories for stressing, stressing operations and
grouting complete as per drawing and Technical
Specifications
Total 11,51,47,978
18.868
Sundries 1.132
Total 20 Cu.M
Top Splice Plate (Top Flange) 4 0.960 0.650 0.032 7.840 0.626
Top Inner Splice Plate (Top
8 0.280 0.960 0.032 7.840 0.539
Flange)
Bottom Splice Plate (Bottom
4 0.850 1.140 0.040 7.840 1.216
Flange)
Bottom Inner Splice Plate (Bottom
8 0.350 1.140 0.040 7.840 1.001
Flange)
Web Splice Plate 8 0.600 2.240 0.028 7.840 2.360
Stiffeners ISA 200 x 200 x 12 8 2.428 0.037 0.711
Packing Plate 16 0.200 0.094 0.028 7.840 0.066