INSTALLATION & MAINTENANCE MANUAL

MICROELETTRICA SCIENTIFICA BRAKING RESISTORS


M.S. RESISTANCES

Customer: GE Energy Power Conversion


P.O. Ref.: 4000088051 Internal Reference: O MC 12 04 012
Project: Cardiff ~ Hulls H2297, H2298, H2400 & H2401
Equipment Specification Braking Resistor (7.2kV Insulated) ~ 4BZM0230-A
Item Description: Item Designation Q’ty
1 8.2 (2x4.1) Ohms - 45MJ (3.3MW/27.3s) 8

Installation & Maintenance Manual


Braking Resistors

SECTION 1: GENERAL RECOMMENDATIONS ................................................................................2 


1.1. LOADING, UNLOADING, HANDLING .....................................................................................................2 
1.2. RECEIVING ...........................................................................................................................................2 
1.3. STORAGE .............................................................................................................................................2 
SECTION 2: INSPECTION & INSTALLATION ...................................................................................2 
2.1. VISUAL INSPECTION .............................................................................................................................2 
2.2. INSTALLATION .....................................................................................................................................2 
2.2.1. Foundation...................................................................................................................................2 
2.2.2. Units Preparation Before Installation .........................................................................................3 
2.2.3. Erection........................................................................................................................................3 
2.2.4. Electrical Connection ..................................................................................................................3 
SECTION 3: COMMISSIONING .............................................................................................................4 
SECTION 4: SERVICING & MAINTENANCE .....................................................................................4 
4.1. TYPES OF MAINTENANCE .....................................................................................................................4 
4.1.1. Preventive Maintenance ..............................................................................................................4 
4.1.2. Corrective maintenance...............................................................................................................4 
4.1.3. Cleaning resistors:.......................................................................................................................4 
4.2. PREVENTIVE MAINTENANCE SCHEDULE ..............................................................................................5 
4.2.1. Low And Medium Pollution Areas...............................................................................................5 
4.2.2. High And Severe Pollution Areas ................................................................................................5 
SECTION 5: TECHNICAL & ELECTRICAL ADDITIONAL INFORMATION’S...........................5 
5.1. MINIMUM CLEARANCES, PROTECTIVE BARRIER CLEARANCES AND WIDTHS OF GANGWAYS ............5 
5.2. POLLUTION SEVERITY LEVELS OR CLASSIFICATION ............................................................................7 
APPENDIX 1: HYDRO COOLER DISPOSAL .......................................................................................8 
APPENDIX 2: PT100 PROBE DISPOSAL ..............................................................................................9 
APPENDIX 3: RESISTOR BANK DISPOSAL......................................................................................10 

Page 1 of 10
0 24/04/2012 O Om 12 04 012 - 1 # 0 D. Jollans C. Millard B. Audouard
Rev. Date File Written Checked Approved
Template: Operation Manual (DA) # 1.Dot - rev. 1 dated 15/09/2003
INSTALLATION & MAINTENANCE MANUAL
BRAKING RESISTORS

Section 1: GENERAL RECOMMENDATIONS


Section 2: INSPECTION & INSTALLATION
1.1. LOADING, UNLOADING, HANDLING 2.1. VISUAL INSPECTION
Resistors are placed in their mounting position Once at job site:
into wooden packing or on Palettes and securely 8 Remove all packing (wooden case) &
fastened to the bottom with bolts remove the bolts which fasten resistors units
Lifting lugs are provided to facilitate handling, to the palette or skid
loading or unloading
Warning: All packing should be removed within
It is the responsibility of carrier & client to
the enclosure before energizing. Failure to
provide proper care in shipping and handling
remove this material may result in fire hazard
Resistors are heavy & require proper equipment 8 Remove the rear & front panels using proper
& procedures for safe & reliable handling. Safety tools to unscrew the bolts
of personnel and properties is important. 8 Check the resistor banks to ensure that they
Handling, unloading, loading erection & are free from foreign bodies
remittance of electrical connections should be 8 Check porcelain indoor insulators. Broken
supervised by qualified person, experienced insulators must be replaced
tradesmen using proper lifting techniques & 8 If porcelain indoor insulators have been
crane of right capacity to unload the units and contaminated during transportation or
move them to their location storage, they have to be cleaned (refer to
Warning: when Handling, Loading, Unloading maintenance section)
or Erecting the Resistors, Rear And Front 8 Check the tightening of internal connections
Panels of Cubicles should be Securely Fastened and bolts (Bolts can be unscrewed during
1.2. RECEIVING transportation and shipping due to vibration)
Once received, the units should be unloaded and
2.2. INSTALLATION
moved using proper handling and lifting
equipment (Forklift or Crane). A preliminary 2.2.1. FOUNDATION
inspection should be made to ensure proper Foundations for electrical equipment such as
handling was practiced during shipment Damping Resistors are laid as simple concrete
Do not remove resistors units from their foundations or simply as a steel skid depending on
wooden palette or skid until they reach the job the size.
site Besides the static loading, they must also
withstand the stresses occurring in operation, such
1.3. STORAGE as short-circuit temperature rise, wind and ice load,
Resistors units should be stored as shipped using seismic vibration and loads
their wooden case or Palette The foundations are laid according to the layout of
NEVER store the cases Lying on the side, up- electrical equipment and steel structures.
side-down or stacked as this could damage The underside of the foundations must be free
bushings, indoor post insulators or resistor from frost, i.e. at a depth of 0,8 to 1,2m.
banks. Dimensions of Foundation Area should be
appropriate to ensure clearance purpose between
each equipment.
Please refer to attached table for minimum
clearances

Page 2 of 10
INSTALLATION & MAINTENANCE MANUAL
BRAKING RESISTORS

2.2.2. UNITS PREPARATION BEFORE 2.2.3. ERECTION


INSTALLATION Once foundations are made, clearances Distances
8 IN Bushings should be mounted, tightened have been checked, electrical verifications have
& secured been done & front & rear panels have been
8 Internal connections between bushings & mounted & secured, proceed with the erection of
resistor banks should be mounted tightened units.
& secured 8 If Resistor is to be installed on Steel
Care should be taken during the fixation of Structure (Pedestal), Install the Steel
connections with resistor banks Structure on flat concrete using appropriate
Warning: Terminals are for electrical purpose bolts (expansion type anchors for concrete
only. They should not be used as mechanical pad mounting)
supports Lifting lugs are provided on each unit for easy
ELECTRICAL VERIFICATION hoisting and placement of unit by carne
Once all electrical connections, bushings & CASE OF STACKED LIVE UNITS
components have been tightened & checked, 2.2.3.1 ERECTION OF BOTTOM UNITS
proceed with electrical verification 8 Install the bottom porcelain outdoor post
8 Insulation verification: please refer to insulators on the metallic structure or steel
Procedure N° PR-FA-06 bottom plate using appropriate bolts. Please
8 Measurement of resistance value: Refer to refer to components list for type of insulators
final routine test certificate for proper- for each unit
recorded resistance value for each unit. 8 Install & mount the unit on the bottom
Measured resistance value at site should porcelain outdoor insulators.
not exceed 2% of recorded resistance
Unit Should Not Be Earthed
value. Measurement should be done using
a 4-wires apparatus with appropriate 2.2.3.2 ERECTION OF MIDDLE / TOP UNITS
accuracy class. If ambient temperature is 8 Install the middle / Top porcelain outdoor
different from Test Ambient Temperature, insulators on insulators Support provided
following resistance value correction with each unit
formula should be used: 8 Install the middle / Top unit on the middle /
Rθ = Rθa.(1+α.(θ-θa)) Top Porcelain Outdoor Insulators
with CASE OF SIDE BY SIDE LIVE UNITS
Rθ: Measured resistance value at site 8 For each unit proceed as for bottom units
Rθa: Recorded resistance value
CASE OF GROUNDED UNITS
α: Temperature coefficient
8 Proceed as for Live units without Outdoor
θ: Ambient temperature at site post Station Insulator
θa: Recorded Ambient temperature Unit should always be securely grounded.
The dimensions of the foundations area must be
appropriate to ensure clearance purpose between 2.2.4. ELECTRICAL CONNECTION
the equipments (Please refer to enclosed table for Electrical Terminals Should Not Be Used As
minimum clearance) Mechanical Support
8 Proceed to the IN connection
8 Proceed to OUT connection
8 Proceed to Intermediate connections for
Multi-cubicle Systems
Check That All Connections Are Tightened
DO NOT TOUCH ACTIVE PART DURING ERECTION,
INSTALLATION OR MAINTENANCE
Page 3 of 10
INSTALLATION & MAINTENANCE MANUAL
BRAKING RESISTORS

Section 3: COMMISSIONING Section 4: SERVICING & MAINTENANCE


Once all connection has been checked, foreign Users of electrical systems agree that servicing and
bodies & all packing material have been maintenance are obvious measures for ensuring
removed clearance has been checked, that products and installations operate over long
UNITS ARE READY TO OPERATE periods.
Before energizing please check that all safety
Maintenance activities may be divided into
instruction have been observed
8 Corrective maintenance
NOTE: During first energizing a smoke may 8 Preventive maintenance
exhaust from resistors, Smoke will not affect
the resistors 4.1. TYPES OF MAINTENANCE
4.1.1. PREVENTIVE MAINTENANCE
Means scheduled maintenance to prevent
breakdowns and to detect faults before damage is
caused.
8 Preventive maintenance may be divided into
direct and indirect maintenance.
8 Direct preventive maintenance includes
cleaning, scheduled replacement or
rehabilitation.
8 Indirect preventive maintenance includes
scheduled testing.
4.1.2. CORRECTIVE MAINTENANCE
Consists in repairing when material breaks down
4.1.3. CLEANING RESISTORS:
8 Check the cleanness of insulators, bushings.
8 They must be wiped off, using duster and a
rapidly evaporating thinner. (DO NOT USE
WATER)
8 Contamination must be removed.
8 Broken, Cracked insulators or Bushings must
be replaced.
8 Live parts or banks must be blown by air
(care must be taken in order not to destroy or
bend the live parts and the pressure or the
blower air speed).
8 Air inlet and outlet of the housing must be
cleaned.

Page 4 of 10
INSTALLATION & MAINTENANCE MANUAL
BRAKING RESISTORS

4.2. PREVENTIVE MAINTENANCE SCHEDULE Section 5: TECHNICAL & ELECTRICAL


Stainless steel resistors are designed to operate ADDITIONAL INFORMATION’S
with free maintenance, but minimum
5.1. MINIMUM CLEARANCES, PROTECTIVE
maintenance visits are required in accordance
BARRIER CLEARANCES AND WIDTHS OF
with pollution classification area.
GANGWAYS
4.2.1. LOW AND MEDIUM POLLUTION AREAS Key to symbols used:
8 First preventive maintenance visit: usually Um [kV] Maximum voltage for apparatus
after 6 months operation. Un [kV ] Nominal voltage
8 Scheduled preventive maintenance: One Urb [kV] Rated lightning impulse withstand voltage
visit every 18 months. Urs [kV] Rated switching impulse withstand voltage
N [mm] Minimum clearance, non-reduced values
4.2.2. HIGH AND SEVERE POLLUTION AREAS S [mm] Minimum clearance, reduced values
8 First preventive maintenance visit: after 3
months operation. Minimum clearances and protective barrier
8 Scheduled preventive maintenance: Once a clearances in power installations with rated
year. voltages above 1 kV:
IMPORTANT NOTICE The clearances between live parts of a system and
Before any maintenance operation, make sure earthed components must be at least equal to those
that resistors are not under voltage and that shown below. This table lists the minimum
they are disconnected. After disconnecting clearances for the maximum apparatus voltages
resistors, wait one hour before approaching and the respective insulation levels as per IEC 71.
resistors because housing is hot. Note: This table has been updated in order to
comply with the state of international European
standardization as of January 1993.

Minimum clearances between live parts of a


system and from earth as per IEC 71.
For Um between 1 kV and < 300 kV the criterion
is the rated lightning impulse withstand voltage.

Page 5 of 10
INSTALLATION & MAINTENANCE MANUAL
BRAKING RESISTORS

For voltage range I: 1 kV < Um < 52 kV For voltage range I: 52 kV ≤ Um < 300 kV
Non-reduced values Reduced values Earth-fault factor Earth-fault factor

Maximum voltage for apparatus


Maximum voltage for apparatus

greater than 1.4 less than 1.4


Rated lightning impulse

Rated lightning impulse

withstand voltage UrB kV

withstand voltage UrB kV


Rated lightning impulse

Rated lightning impulse


Minimum clearances

Minimum clearances

phase-to-earth N mm
withstand voltage

withstand voltage

Minimum clearances

Minimum clearances
Nominal Voltage

phase-to-earth S mm
phase-to-phase

phase-to-phase
phase-to-earth

phase-to-earth

Nominal voltage

phase-to-phase

phase-to-phase
Indoor Outdoor Indoor Outdoor

Um kV
Un kV
Un Um UrB N N UrB S S
kV kV kV mm mm kV mm mm
3 3.6 40 60 120 20 60 120 45 52 250 480 _ _
6 7.2 60 90 120 40 60 120 60 72.5 325 630 _ _
10 12 75 120 150 60 90 150 110 123 550 1100 450 900
20 24 125 220 95 160 150 170 750 1500 650 1300
30 36 170 320 145 270 220 245 1050 2100 950 1900
850 1700

Page 6 of 10
INSTALLATION & MAINTENANCE MANUAL
BRAKING RESISTORS

5.2. POLLUTION SEVERITY LEVELS OR CLASSIFICATION

Minimum
creepage
Pollution level Examples of typical environments
distance
mm/kV
- Areas without industries and with low density of houses equipped
with heating plants
- Areas with low density of industries or houses but subjected to
frequent winds and/or rainfall
I Light 16
- Agricultural areas
- Mountainous areas
All these areas shall be situated at least 10 to 20 Km from the sea
and shall not be exposed to winds directly from the sea.
- Areas with industries not producing particularly polluting smoke
and/or with average density of houses equipped with heating plants.
- Areas with high density of houses and/or industries but subjected to
II Medium 20
frequent winds and/or rainfall.
- Areas exposed to wind from the sea but not too close to the coast
(at least several kilometres distant).
- Areas with high density of industries and suburbs of large cities
with high density of heating plants producing pollution.
III Heavy 25
- Areas close to the sea or in any case exposed to relatively strong
winds from the sea.
- Areas generally of moderate extent, subjected to conductive dusts
and to industrial smoke producing particularly thick conductive
deposits.
- Areas generally of moderate extent, very close to the coast and
IV Very Heavy exposed to sea-spray or to very strong and polluting winds from the 31
sea.
- Desert areas, characterized by no rain for long periods, exposed to
strong winds carrying sand and salt, and subjected to regular
condensation.
Applicable Standards: IEC 815, 71-2

Page 7 of 10
INSTALLATION & MAINTENANCE MANUAL

BRAKING RESISTOR

Appendix 1

Hydro cooler Disposal

1) Remove Pipes from Flanges

2) Remove Cables from Leak Detector

3) Remove Pipes from Air / Water Drain (if any)

4) Remove Holding screws between Hydro cooler & Resistor framing

5) Slide Hydro cooler out from Flanges Side


INSTALLATION & MAINTENANCE MANUAL

BRAKING RESISTOR

Appendix 2

PT100 Probe Disposal

1) Open Probe Head

2) Remove wiring

3) Open removable Panels on side where PT 100 Probe is to be removed

4) By holding nut inside enclosure between Frame & Thermal Shield, unscrew Probe

5) Slide Probe Out


INSTALLATION & MAINTENANCE MANUAL

BRAKING RESISTOR

Appendix 3

Resistor Bank Disposal

1) Open removable Panel on side where Resistor Block is to be removed

2) Dismantle Copper Bars linking Resistor Block to Terminals

3) Remove Bolds fixing Porcelain Insulators to Resistor Bloc Holding Frame

4) Slide Resistor Block Out.