PERT/CPM with Bar Chart

Beloy, Jeffrey H.
BSCE-4B

Dr. Danilo B. Pulma, dm


iNSTRUCTOR
Problem No. 2: Prepare an arrow diagram and a list of starts, finishes,
and floats for a project involving the listed activities.
Solution:

Activities w/c
STARTS FINISHES FLOATS
DURATION
ACTIVITY

immediately

PRECEDE FOLLOW ES LS EF LS TF FF

A 3 NONE C 0 6 3 9 6 0

B 5 NONE D, E 0 0 5 5 0 0

C 4 A F, G 3 9 7 13 6 6

D 8 B F, G 5 5 13 13 0 0

E 9 B H, I 5 6 14 15 1 0

F 6 C, D J, K, L, M 13 15 19 21 2 0

G 8 C, D K, L, M 13 13 21 21 0 0

H 6 E K, L, M 14 15 20 21 1 1

I 5 E P 14 27 19 32 13 9

J 4 F N 19 28 23 32 9 0

K 7 F, G, H O 21 21 28 28 0 0

L 6 F, G, H Q 21 25 27 31 4 0

M 7 F, G, H P 21 25 28 32 4 0

N 4 J R 23 32 27 36 9 9

O 8 K R 28 28 36 36 0 0

P 4 I, M R 28 32 32 36 4 4

Q 5 L R 27 31 32 36 4 4

R 3 N, O, P, Q NONE 36 36 39 39 0 0

PERT/CPM DIAGRAM:
GANTT CHART:
ACTIVITY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R