Академический Документы
Профессиональный Документы
Культура Документы
WEEK 1
WEEK 2
WEEK 3
WEEK 4
WEEK 5
WEEK 6
DAYS weeks CONTRACT
ITEMS % wt
(1W = (1W = COST
7D) 7D)
0.76%
0.76%
0.76%
0.76%
2. CONSTRUCTION 329 47 30,815,130.81 24.65% 0
0.85%
c. ELECTRICAL 287 41 13,814,128.93 11.05%
WEEKLY PROGRESS
0.76%
1.52%
2.28%
3.04%
3.04%
3.89%
CUMULATIVE PROGRESS
1,900,000.00
2,850,000.00
3,800,000.00
3,800,000.00
4,863,832.83
950,000.00
12-A Belvedere Tower
San Miguel Ave. Pasig
City 1605
Tel no.: 02 727 3351
WEEK 1
WEEK 2
WEEK 3
WEEK 4
WEEK 5
WEEK 6
DAYS weeks CONTRACT
ITEMS % wt
(1W = (1W = COST
7D) 7D)
18,750,053.59
Design and Build for the Construction of
Additional Jail Facilities (CONSTRUCTION
at Quezon City SCHEDULE, CASH FLOW, AND S-
Jail CURVE)
Annex
Quezon City Jail Annex, Camp Bagong Diwa, TOTAL PROJECT DURATION (365 DAYS)
Bicutan, Taguig City MONTH 2 MONTH 3 MONTH 4
TOTAL
WEEK 10
WEEK 11
WEEK 12
WEEK 13
WEEK 14
WEEK 15
WEEK 16
WEEK 7
WEEK 8
WEEK 9
DAYS
ITEMS (1W =
7D)
1. DESIGN WORKS 28
2. CONSTRUCTION 329 0 0 0 0 0 0 0 0 0 0
e. MECHANICAL 147
WEEKLY PROGRESS
13,095,372.02 10.48%
14,996,957.15 12.00%
16,898,542.28 13.52%
18,800,127.41 15.04%
20,701,712.55 16.56%
4.74%
5.59%
6.71%
7.83%
11,193,786.89 8.96%
CUMULATIVE PROGRESS
5,927,665.66
6,991,498.48
8,392,261.29
9,793,024.09
Design and Build for the Construction of
Additional Jail Facilities (CONSTRUCTION
at Quezon City SCHEDULE, CASH FLOW, AND S-
Jail CURVE)
Annex
Quezon City Jail Annex, Camp Bagong Diwa, TOTAL PROJECT DURATION (365 DAYS)
Bicutan, Taguig City MONTH 2 MONTH 3 MONTH 4
TOTAL
WEEK 10
WEEK 11
WEEK 12
WEEK 13
WEEK 14
WEEK 15
WEEK 16
WEEK 7
WEEK 8
WEEK 9
DAYS
ITEMS (1W =
7D)
14,996,957.15
Q1
Quezon City
c. AUXILLARY
TOTAL
c. ELECTRICAL
1. DESIGN WORKS
e. MECHANICAL
WEEKLY PROGRESS
2. CONSTRUCTION
Bicutan, Taguig City
ITEMS
CUMULATIVE PROGRESS
JailPROJECT
Jail
Annex
a. ARCHITECTURAL WORKS
28
Diwa,
147
287
140
287
329
245
329
7D)
DAYS
(1W =
TOTAL
Additional Jail Facilities at Quezon City
Design and Build for the Construction of
WEEK 17
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WEEK 20
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WEEK 24
0
0
0
0
0
WEEK 25
12-A Belvedere Tower
0
0
0
0
0
0
0
0
0
0
WEEK 28
0
0
0
0
0
WEEK 17
WEEK 18
WEEK 19
WEEK 20
WEEK 21
WEEK 22
WEEK 23
WEEK 24
WEEK 25
WEEK 26
WEEK 27
WEEK 28
WEEK 29
WEEK 30
WEEK 31
DAYS
ITEMS (1W =
7D)
29,668,526.81
Q2
c. AUXILLARY
c. ELECTRICAL
1. DESIGN WORKS
e. MECHANICAL
Additional Jail
WEEKLY PROGRESS
2. CONSTRUCTION
Bicutan, Taguig City
ITEMS
CUMULATIVE PROGRESS
Jail
Annex
a. ARCHITECTURAL WORKS
Quezon City Jail Annex, Camp
TOTAL
28
Diwa,
SCHEDULE,
147
287
140
287
329
245
329
7D)
DAYS
(1W =
TOTAL
City
Design and Build for the Construction of
MONTH 8
WEEK 32
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WEEK 35
0
0
0
0
0
0
0
WEEK 36
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WEEK 39
0
0
0
0
0
0
0
WEEK 40
0
0
0
0
0
0
0
WEEK 32
WEEK 33
WEEK 34
WEEK 35
WEEK 36
WEEK 37
WEEK 38
WEEK 39
WEEK 40
DAYS
ITEMS (1W =
7D)
39,625,906.05
Q3
c. AUXILLARY
c. ELECTRICAL
1. DESIGN WORKS
e. MECHANICAL
WEEKLY PROGRESS
2. CONSTRUCTION
Bicutan, Taguig City
ITEMS
CUMULATIVE PROGRESS
Jail
Annex
a. ARCHITECTURAL WORKS
28
Quezon City Jail Annex, Camp Bagong Diwa,
147
287
140
287
329
245
329
7D)
DAYS
(1W =
TOTAL
City
Design and Build for the Construction of
WEEK 41
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WEEK 43
0
0
0
0
0
0
0
WEEK 44
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WEEK 48
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WEEK 51
0
0
0
0
0
WEEK 52
0
0
0
0
0
WEEK 41
WEEK 42
WEEK 43
WEEK 44
WEEK 45
WEEK 46
WEEK 47
WEEK 48
WEEK 49
WEEK 50
WEEK 51
WEEK 52
DAYS
ITEMS (1W =
7D)
40,708,967.28
Q4
Design and Build for the Construction of
Additional Jail Facilities at Quezon City
Jail
Annex
Quezon City Jail Annex, Camp Bagong Diwa,
Bicutan, Taguig City
TOTAL
DAYS
ITEMS (1W =
7D)
President / C.E.O.
CUMULATIVE PROGRESS
Design and Build for the Construction of
Additional Jail Facilities at Quezon City
Jail
Annex
Quezon City Jail Annex, Camp Bagong Diwa,
Bicutan, Taguig City
TOTAL
DAYS
ITEMS (1W =
7D)
12-A Belvedere Tower
San Miguel Ave. Pasig
City 1605
Tel no.: 02 727 3351
WEEK 1
WEEK 2
WEEK 3
WEEK 4
WEEK 5
WEEK 6
DAYS weeks CONTRACT
ITEMS % wt
(1W = (1W = COST
7D) 7D)
0.76%
0.76%
0.76%
0.76%
2. CONSTRUCTION 329 47 30,815,130.81 24.65% 0
0.85%
c. ELECTRICAL 287 41 13,814,128.93 11.05%
WEEKLY PROGRESS
0.76%
1.52%
2.28%
3.04%
3.04%
3.89%
CUMULATIVE PROGRESS
Design and Build for the Construction of
Additional Jail Facilities (CONSTRUCTION
at Quezon City SCHEDULE, CASH FLOW, AND S-
Jail CURVE)
Annex
Quezon City Jail Annex, Camp Bagong Diwa, TOTAL PROJECT DURATION (365 DAYS)
Bicutan, Taguig City MONTH 2 MONTH 3 MONTH 4
TOTAL
WEEK 10
WEEK 11
WEEK 12
WEEK 13
WEEK 14
WEEK 15
WEEK 16
WEEK 7
WEEK 8
WEEK 9
DAYS
ITEMS (1W =
7D)
1. DESIGN WORKS 28
2. CONSTRUCTION 329 0 0 0 0 0 0 0 0 0 0
e. MECHANICAL 147
WEEKLY PROGRESS
10.48%
12.00%
13.52%
15.04%
16.56%
4.74%
5.59%
6.71%
7.83%
8.96%
CUMULATIVE PROGRESS
12-A Belvedere Tower
San Miguel Ave. Pasig City 1605
Tel no.: 02 727 3351
WEEK 17
WEEK 18
WEEK 19
WEEK 20
WEEK 21
WEEK 22
WEEK 23
WEEK 24
WEEK 25
WEEK 26
WEEK 27
WEEK 28
WEEK 29
WEEK 30
WEEK 31
DAYS
ITEMS (1W =
7D)
1. DESIGN WORKS 28
2. CONSTRUCTION 329 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
b. STRUCTURAL / CIVIL WORKS 329 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
c. ELECTRICAL 287 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
c. AUXILLARY 140 0 0 0
0.25%
0.25%
0.25%
d. PLUMBING AND FIRE PROTECTION 287 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
0.40%
e. MECHANICAL 147
WEEKLY PROGRESS
18.08%
20.04%
22.00%
23.97%
25.93%
27.89%
29.85%
31.81%
33.77%
35.73%
37.69%
39.65%
41.86%
44.07%
46.28%
CUMULATIVE PROGRESS
Design and Build for the Construction of
Additional Jail Facilities at Quezon
(CONSTRUCTION City
SCHEDULE, CASH FLOW, AND S-CURVE)
Jail
Annex
TOTAL
Quezon City Jail Annex, Camp PROJECT
Bagong DURATION (365 DAYS)
Diwa,
Bicutan, Taguig City MONTH 8 MONTH 9 MONTH 10
TOTAL
WEEK 32
WEEK 33
WEEK 34
WEEK 35
WEEK 36
WEEK 37
WEEK 38
WEEK 39
WEEK 40
DAYS
ITEMS (1W =
7D)
1. DESIGN WORKS 28
2. CONSTRUCTION 329 0 0 0 0 0 0 0 0 0
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
b. STRUCTURAL / CIVIL WORKS 329 0 0 0 0 0 0 0 0 0
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
c. ELECTRICAL 287 0 0 0 0 0 0 0 0 0
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
c. AUXILLARY 140 0 0 0 0 0 0 0 0 0.27% 0
0.25%
0.25%
0.25%
0.25%
0.25%
0.25%
0.25%
0.25%
0.25%
e. MECHANICAL 147 0 0 0 0 0 0 0 0 0
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
WEEKLY PROGRESS
48.93%
51.57%
54.21%
56.86%
59.50%
62.15%
64.79%
67.43%
70.08%
CUMULATIVE PROGRESS
Design and Build for the Construction of
Additional Jail Facilities at Quezon City
(CONSTRUCTION SCHEDULE, CASH FLOW, AND S-CURVE)
Jail
Annex
Quezon City Jail Annex, Camp Bagong Diwa, TOTAL PROJECT DURATION (365 DAYS)
Bicutan, Taguig City MONTH 11 MONTH 12 MONTH 13
TOTAL
WEEK 41
WEEK 42
WEEK 43
WEEK 44
WEEK 45
WEEK 46
WEEK 47
WEEK 48
WEEK 49
WEEK 50
WEEK 51
WEEK 52
DAYS
ITEMS (1W =
7D)
1. DESIGN WORKS 28
2. CONSTRUCTION 329 0 0 0 0 0 0 0 0 0 0 0 0
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
0.44%
b. STRUCTURAL / CIVIL WORKS 329 0 0 0 0 0 0 0 0 0 0 0 0
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
0.85%
c. ELECTRICAL 287 0 0 0 0 0 0 0 0 0
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
0.27%
c. AUXILLARY 140 0 0 0 0 0 0 0 0 0.27%
0.25%
0.25%
0.25%
0.25%
0.25%
0.25%
0.25%
0.25%
e. MECHANICAL 147 0 0 0 0 0 0 0 0 0 0 0 0
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
0.43%
WEEKLY PROGRESS
72.72%
75.36%
78.01%
80.65%
83.30%
85.94%
88.58%
91.23%
93.62%
95.75%
97.87%
CUMULATIVE PROGRESS
Design and Build for the Construction of
Additional Jail Facilities at Quezon City
Jail
Annex
Quezon City Jail Annex, Camp Bagong Diwa,
Bicutan, Taguig City
TOTAL
DAYS
ITEMS (1W =
7D)
President / C.E.O.
CUMULATIVE PROGRESS
MOBILIZATION/DEMOBILIZATION
DEMOLITION WORKS
CONCRETE WORKS
STEEL WORKS
ROOFING WORKS
TILE WORKS
CARPENTRY WORKS
LOCKERS (WOODEN CABINETS)
PLUMBING
SEPTIC TANK
ELECTRICAL WORKS
PAINTING WORKS
APPURTENANCES