7 CUSTOMER TARGETS FAI Samples 31.10.2019 Pre launch 15.12.2019 SOP 30.09.2019
9 LOGISTIC AGREEMENT Yes FOB Mumbai QUALITY TARGET AGREEMENT As per Quality Std.
18 OTHERS DANA will provide UPC codes as needed for each part number for any master pack labels
MARKETING CUSTOMER
Format FR-EG-051
UNDERSTANDING EAU
Diff Cage Assy 10113095 Minimum expected volumes / year Maximum expected volumes / year
S.No. Part Description Part No. Qty. Mat. Volumes 10097994 10100644 10096596 10097505 Hex Bolt Washer 10097994 10100644 10096596 10097505 Hex Bolt Washer
1 Plain Half 10097994 1 600/3 250-500 250 500
2 Flange Half 10100644 1 1000-1500 250 500
3 Hex Bolt M12x90 10111658 16 4000 8000
4 Flat Washer 10111661 16
5 Locktite 680 10111698 1
Sample number(s): Not Applicable 10100644, 10097994, 10097505, 10096596, 10111658 & 10111661
Does the Engg have the latest information about program timing (examples include Drawing release, Prototype, PPAP date, Build date, Material
1.1 Yes N No
required at plant date, Start of Production, Volumes)?
Program as per below table derived from development plan. DANA offer 120days for tooling development & 45 days for testing FAI
Explain: samples
Review Key Project Milestones with Engg:
Key Project Milestone Date Key Project Milestone Date Volumes Nos.
Drawing release 28.02.2019 PPAP date 15.12.2019 Per Annum 250-500 Sets
1.2 Y Yes No Does the Engg have and understand all the requirements listed in the Customer Input Requirements
1.3 Y Yes No Does the Engg understand the requirements of Customer marking & Packaging Specification?
Explain: Bulk packing & DANA will provide UPC codes (Bar Codes)
2.1 Y Yes No Does the Engg have and understand ALL of the latest drawings and specifications?
Explain: Yes
List them below:
Quantity Engg Promise Date Sample approval time
FAI Requirements
Not defined 31.10.2019 45 days
3.1 Y Yes No Are any new equipment, tooling, gages, special fixtures or test equipment needed to produce this part?
Explain: New Tooling required for Casting & Fixture required for machining, Snap Gauges required for grinding
Explain: Upper & Lower part Casting to procure, M12x90lg Bolt & Washer to procure
3.3 Enter lead time for tooling (days): 120
3.4 Enter date for first production run 45
3.5 Enter estimated PPAP Submission Date: 12/15/2019
Attendees: Marketing Manager Prod. Manager Quality Manager Design Manager Engineering Manager Plant Head
Sign off
EMMFORCE INC
CFT Members
PROJECT LOCKING HUB CUSTOMER: DORMAN 6.01.2019
5 Mr. JASDEEP QA
EMMFORCE INC
PLOT NO. 3 & 5, EPIP, JHARMAJRI, BADDI H.P
Part Name
Diff Case Assembly Sample No. Date
Requirements Status
Mr. Ramehar
Mr.Amrinder S
Format FR-EG-ASSY-052
EMMFORCE INC Ref. No. EMM/FSY/3095 EMMFORCE INC Ref. No. EMM/FSY/0511
Plot No. 3 & 5, EPIP Jharmajri Date 10.12.2018 Plot No. 3 & 5, EPIP Jharmajri Date 10.05.2018
RISK ANALYSIS RISK ANALYSIS Values Chapters Engineering Risk Element
Part Name Diff Case Assy Customer DANA Part Name Customer 1 1 - Low Risk 1 Requirements and Specifications A Technology
Part Number 10103095 Page 2 of 2 Part Number Page 1 of 2 2 2 - Low to Medium Ri 2 Engineering Risk Assessment B Environmental
Score Engineering Risk Elements Engineering Risk Elements High 3 3 - Medium Risk 3 Assembly Requirements C Vendor
Technology 2 - Low to Medium Risk 2 A #REF! A B C D E F G Risk Subtotal Assessment 4 4 - Medium to High R 4 System Design D Resource
This defines the degree of technical complexity the Lead Engineer or engineering team will face in executing the project. B #REF! 2 1 3 1 2 2 2 ≥ 22 13 ### Standard Risk 5 5 - High Risk 5 Engineering Design Review E Quality
1 The project will use off-the-shelf technology. C #REF! 6 Procurement and Implementation F Safety
3 Engineers will purchase and modify off-the-shelf technology. D #REF! Assessment 7 Testing and Validation G Manufacturing
5 The project will require the development of new technology. E #REF! Standard Risk 8 Release to Operations
F #REF! High Risk 9 Final Documentation Project Risk Element
Environmental Impact 1 - Low Risk 1 G #REF! H Schedule
This defines the potential level of environmental impact. I Interfaces
1 There will be no environmental impact. J Experience / Capability
3 The project may have some environmental impact but will not require an environmental assessment K Regulatory Requirements
5 The project will require an environmental impact statement. L Project Funding
Project Risk Elements Project Risk Element High M Reporting Requirements
Vendor Issues 3 - Medium Risk 3 H Schedule H J K Risk Subtotal Assessment N Public Impact
This defines the degree of complexity to be expected with vendors. Complicating factors may include long-lead-time items
and issues with vendor qualification and reliability. J Experience / Capability 2 2 1 ≥ 10 5 ### Standard Risk
O Project Cost
1 Vendors could cause minor issues. K Regulatory Requirements
3 Vendors could cause manageable complications.
5 Vendor issues could result in significant schedule delays or cost overruns or could otherwise jeopardize the successful
completion of the project.
Format FR-EG-050
EMMFORCE INC.
PLOT NO. 3 & 5, EPIP, JHAR MAJRI, BADDI H.P
DEVELOPMENT PLAN
Diff Case assembly 10113095 Meritor DANA
Process Responsibility (Mr. ) Project Start Feb'19 Mar'19 April'19 May'19 Jun'19 Jul'19 Aug'19 Sep'19 Oct'19 Nov'19
Date
Plain Half (Upper) 10097994 01.02.19 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Plan
Design Drawing Amrinder S
Actual
Plan
Casting Drawing Amrinder S
Actual
Plan
RFQ to vendor Neeraj K
Actual
Plan
Quote approval Anil K
Actual
Tooling Neeraj K
Plan 90-120days
development Actual
Plan
T-0 Samples Neeraj K
Actual
Fixture design for Amrinder S
Plan
VMC Actual
Plan
Fixture for VMC Harmeet S
Actual
Plan
CNC Turning Ramehar
Actual
Plan
VMC Drilling Ramehar
Actual
Washer M12x2
Plan
Design Drawing Amrinder S
Actual
Plan
RFQ to vendor Neeraj K
Actual
Plan
Quote approval Anil K
Actual
Plan
Samples Neeraj K
Actual
CFT Mr.Amrinder S Mr. Ramehar Mr. Sondeep Mr. Jasdeep S Mr. Neeraj K Mr. S P Dhiman Mr. Anil K
SIGN OFF
Format
EG-047
Emmforce Inc.
Preliminary BOM
Plot No. 3 & 5, EPIP, Jharmajri, Baddi, H.P
Plot No. 3
MR. Ramehar
MR.AMRINDER SINGH
Mr. Sondeep
MR. JASDEEP
EMMFORCE INC
# 3 & 5 Phase -I EPIP, Jhar Majri - 173205 HP
ADVANCE PRODUCT QUALITY PLANING TIMING CHART
CFT MEMBERS
Dept Name Mr. Signature
APQP REVIEW RECORD
S P Dhiman Rev. Date
Engineering
Part Diff Case Meritor Amrinder Singh
Customer DANA
Quality Jasdeep Saini/Deepak Saini
Customer Part No. 10113095
Emmforce Part No.
Production Ramehar
Volume 250-500 Annual
Project Start Date 2/1/2019
Purchase Sondeep
Project End Date
SOP of Customer
Marketing Anil Chauhan
Project Owner S P Dhiman
Month Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20
APQP STAGE & PROGRAMME Resp.
Week 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
CUSTOMER MILE STONE TESTING PPAP
COMPANY MILESTONE
Status
CFT Mr.
Amrinder S Deepak S/Jasdeep Ramehar Sondeep S P Dhiman
FR-EG-053
Plot No. 3 & 5, Phase I,
Part Name Manual Locking Hub
Cust. Part Number 600-220 14.06.2016
Bill of Materials (Final)
DORMAN
Free Wheel Hub (HFK0005) Manual
SR.NO PART NO. DESCRIPTION Qty.
1 1
2 1
3 1
4 1
5 1
6 1
7 1
8 1
9 1
10 1
11 1
CFT Members Sign off
K S BHOGAL
ANIL Kumar
AMRINDER SINGH
NEERAJ KUMAR
BALJEET
PROCESS FLOW DIAGRAM
Process Flow Diagram Category Process Flow Diagram Number Date (Orig.) Date (Rev.)
Prelimi
Final PFD - Diff C/ 7994 11.02.2019
nary
Customer Part Number Emm. Part no. Key Contact / Phone Organization / Plant
epip
10097994 S P Dhiman / 7986887591 Emmforce Inc., 3 & 5 Jharmajri, Baddi
Part Name / Description Engineering Change Level / Date Customer
Diff Case Upper Dana
PROCESS NAME/ KEY CHARACTERISTICS SYMBOL
PROCESS MACHINE / FACILITY SPECIAL
OPERATION VENDOR (V) REMARKS
NUMBER TYPE CHAR.
DESCRIPTION PRODUCT PROCESS
<SC>
Ø 186.2 -0.5
Dim. 58.8+0.1
Ø 71.65 +0.05
Dim. 21.1+0.2
Ø 98.35-0.1
Dim. 98
Ø 62.5+0.05
Dim. 146.16+0.5
Angle 17.5
Angle 18.33
position 0.25
PCD 165.1
Length 20
080 INSPECTION
090 Storage
NOTE: -
Mr. Ramehar
Mr. Neeraj
Mr. Parveen
Mr. Ashok
PROCESS FLOW DIAGRAM
Process Flow Diagram Category Process Flow Diagram Number Date (Orig.) Date (Rev.)
Prelimi
Final PFD - Diff C/ 0644 11.02.2019
nary
Customer Part Number Emm. Part no. Key Contact / Phone Organization / Plant
10100644 S P Dhiman / 7986887591 Emmforce Inc., 3 & 5 Jharmajri, Baddi
Part Name / Description Engineering Change Level / Date Customer
Diff Case Lower Dana
PROCESS NAME/ KEY CHARACTERISTICS SYMBOL
PROCESS MACHINE / FACILITY SPECIAL
OPERATION VENDOR (V) REMARKS
NUMBER TYPE PRODUCT PROCESS CHAR.
DESCRIPTION
<SC>
Dim.38+0.25
Dim. 58.8+0.1
Ø71.65 +0.05
Ø211.65+0.1
Dim. 80+0.2
Dim. 58.5+0.25
Ø62.5+0.05
Dim. 91.6±0.25
Depth 53
Angle 17.5
Angle 18.33
position 0.25
PCD 165.1
12 x Ø16.5
Thread M12x1.75
Depth 40
Spot face 12 x
060 Spot Facing VMC
Ø36
Dim. 18
070 Storage
NOTE: -
Mr. Ramehar
Mr. Neeraj
Mr. Parveen
Mr. Ashok
PROCESS FLOW DIAGRAM
Process Flow Diagram Category Process Flow Diagram Number Date (Orig.) Date (Rev.)
Prelimi
● Final PFD - Diff C assy/ 3095 11.02.2019
nary
Customer Part Number Emm. Part no. Key Contact / Phone Organization / Plant
Assemble
10100644,
010 10097994, Bolt Torque 5-6kgm
10111651 &
10111658
<SC>
4 X Ø27+0.025
Ø85.055+0.030
Ø211.20+0.05
040 INSPECTION
PACKING &
060
DISPATCH
NOTE: -
Mr. Ramehar
Mr. Neeraj
Mr. Parveen
Mr. Ashok