Академический Документы
Профессиональный Документы
Культура Документы
This dissertation has been submitted in partial fulfillment for the award of B.Arch.
degree from Shree Bankey Bihari Institute of Architecture, Meerut.
Date –
Place-
1|P ag e
DECLARATION
I hereby declare that this dissertation is my own work and effort and that it has not
been submitted anywhere for any award. Where other sources of information have
been used, they have been acknowledged.
This dissertation has been completed under the supervision of the guide assigned to
me by the Shree Bankey Bihari Institute of Architecture, Meerut.
ABHAY MALIK
Roll No.- 1372981001
Enrolment No:-137298161782
Batch: 2013 – 2018
2|P ag e
ACKNOWLEDGWMENT
The study has followed a long and winding path along which I meet many peoples,
this formal space to acknowledge their contribution is appreciated. Yet I would say
that the distribution of my gratitude to all these supporters from different places is
proportionate and equitable.
I would like to express sincere gratitude to all my teachers, friends, and colleagues at
Shree Bankey Bihari Institute of Architecture for their help to make this endeavor
possible.
First and foremost, I would like to thank my honorable guide ER. PIYUSH GUPTA &
AR. UMESH KUMAR for their guidance and encouragement throughout the
dissertation process.
ABHAY MALIK
Roll No. - 1372981001
Enrolment No:-137298161782
Batch: 2013 – 2018
3|P ag e
CONTENTS
1. SYNOPSIS
2. INTRODUCTION
2.1. DEFINING CONSTRUCTION MANAGEMENT
2.2. DEFINING CONSTRUCTION & MANAGEMENT
2.3. OBJECTIVES OF CONSTRUCTION MANAGEMENT
2.4. FUNCTIONS OF CONSTRUCTION MANAGEMENT
2.5. HISTORY OF CONSTRUCTION MANAGEMENT
7. ADVANTAGES
8. DISADVANTAGES
16. CONCLUSION
4|P ag e
1. SYNOPSIS -
INTRODUCTION -
It is important because:
HYPOTHESIS -
5|P ag e
AIM OF THE SUBJECT –
My aim is:
1. To expose the growth of management along with its applications for the
environment and human welfare.
2. To develop scientific attitude and temper and to create, inculcate and sustain
a general awareness amongst the people.
3. To promote and enhance public understanding of the culture of construction
management.
4. To stimulate interest in construction management activities among students
and enable them to carry out self-directed activities in areas of interest in
management of construction and project.
5. To provide opportunities for students and visitors to develop initiative and
creativity in the field of construction management.
6. Provide opportunity to the Indian and / or Global Private Sectors to involve in
this towards mutual benefits.
7. Provides an environment close interactions with a particular center of
knowledge creation for their mutual benefit.
8. To promote public understanding and awareness, especially with regard to
the importance of scientific studies and culture.
OBJECTIVES -
My objectives are:
1. To assess the current structure, status and direction of the Indian construction
management field.
2. To assess the competition in Indian construction management field.
3. To assess the financing of Indian construction management field.
4. To assess the opportunities and challenges of Indian construction
management field.
5. To develop strategies for competitors (domestic players) in Indian
construction management field.
6|P ag e
6. To assess the technology, managerial, operational, of the Indian construction
management field.
7. To create awareness about the importance of the construction management
in the Indian construction management field.
LIMITATION-
METHODOLOGY-
7|P ag e
2. INTRODUCTION -
2.1. DEFINING CONSTRUCTION MANAGEMENT: Construction project
management (CM) is a professional service that uses specialized, project
management techniques to oversee the planning, design, and construction
of a project, from its beginning to its end.
OR
OR
8|P ag e
Construction management is a building design which has made by the client itself in
a new building. Possible client has a wealth of experience in building design. If a
client has a new building and design was completed and the design of their own, for
the purpose of construction, the client will go to a consultant who is represented by
architects, civil engineers and quantity surveyors to evaluate the design. After that,
the consultant will assess the total cost of construction. The purpose of CM is to
control a project's time, cost and quality. CM is compatible with all project delivery
systems, including design-bid-build, design-build, CM At-Risk and Public Private
Partnerships. Every construction project features some amount of CM.
2.2. DEFINING THE TERM CONSTRUCTION & MANAGEMENT:
2.2.1. CONSTRUCTION- Construction is the process of constructing
a building or infrastructure. Construction differs from manufacturing in
that manufacturing typically involves mass production of similar items
without a designated purchaser, while construction typically takes place on
location for a known client. Construction as an industry comprises six to
nine percent of the gross domestic product of developed
countries. Construction starts with planning, design, and financing; and
continues until the project is built and ready for use. Construction is a
general term meaning the art and science to form objects, systems, or
organizations, and comes from Latin constructionem (from com-
"together" and struere "to pile up") and Old French construction.
Construction is a series of actions undertaken by construction companies
end consultants, which produces or alter buildings and infrastructure.
Construction actions can be described as a complex interplay of people,
tools, equipment and materials, coordinated by communication and paid
with money. Construction actions include:
design and management decisions;
direct physical production of the facility on site;
project close-out/final accounting; and
rehabilitation and maintenance of existing facilities.
9|P ag e
Building construction is usually further divided into residential and non-
residential (commercial/institutional).
Controlling a business/industry
10 | P a g e
making sure that everything is done correctly, safely
etc.
Resources Something that is required in order to do work. They
include: money equipment, people, materials,
information, skills, knowledge or any other item
likely to be in limited supply.
-- It is better; or
-- It is worse
11 | P a g e
Forecasting Looking into the future to try and assess the
possible trend of events, which are likely to
influence the conditions of the working situation,
so that steps may be taken to overcome any
difficulties before or soon as they arise.
them.
13 | P a g e
The Industrial Revolution (Circa 1750 to 1850)
The early days of management as a subject for study were related to the latter half
of the Industrial Revolution. This may be described as the period when mechanical
power was introduced and applied to the production of goods, and the earliest
efforts to improve management at this time were those concerned with technical
issues of production, because the social conscience of the day did not enforce
responsibility for personnel problems.
A) James Watt (1736–1819): whose main interest centered on the efficient use of
large variety of machinery. This entailed the elaboration of production
management processes such as:
the layout of plant;
the flow of operations;
the planning of work schedules; and
other technical matters as the standardization of parts and the pre-
fixing of dimensions.
B) Robert Owen (1771–1858): the pioneer of personnel management. Between
1800 and 1828, he successfully put into practice social reforms to remedy the
evils that contemporary industry accepted as inevitable. Evils such as length
of working day and lack of welfare scheme for workers.
C) Charles Babbage (1791–1871): was among the first to advocate in relation
to industrial problems, the fundamental thinking which preceded the
formulation of the principles of management. His writings told little of the
art of management as actually practiced in the early nineteenth century,
but suggested the scientific or analytical approach to the problems of
manufacturing.
Management Evolution (1850–date): Important as the technical problems created
by the introduction of machinery, were the social and organizational problems,
14 | P a g e
which it brought in its train. Particularly, problems that had to be managed
during this period arose out of the following prevailing conditions:
• The evolution of the Trade Union System and the means of
negotiation in collective bargaining raised questions on the
adequacy of wages and working conditions.
15 | P a g e
b) Henry Lawrence Gantt (1861–1919): His writings emphasized the
human interest. He is remembered chiefly as the inventor of the Gantt chart
for graphical planning. Gantt charts were employed on major infrastructure
projects, and continue to be an independent tool in project and construction
management.
16 | P a g e
ii. Workers develop group attitudes, norms and values, so that they react
his firm. The company’s organization structure was based upon functional
whilst monthly balance sheets and returns facilitated the preparation of the
annual stock-taking and yearly balance sheet within a few days. The
18 | P a g e
iii. commitment to objectives is a function of reward associated with
their achievement;
iv. the average human being learns under proper condition, not only to
accept, but to seek responsibility;
v. the capacity to exercise a relatively high degree of imagination,
ingenuity and creativity in the solution of organizational problems is
widely not narrowly distributed in the population; and
vi. under the condition of modern industrial life, the intellectual
potential of the average human being is partially utilized.
Watt, of the steam-engine fame, became one of the earliest pioneers of such
development in his Soho Foundry. The foundry was laid out in such a way
that the flow of materials through the various processes was logically and
thoughtfully arranged.
administration of which Robert Owen and Charles Babbage were by far the
19 | P a g e
c) Financial Accounting: The rapid expansion of industry meant that more
attention had to be paid to the means of providing capital. With the principle
need to assure those individuals providing the necessary capital that it was
d) Planning, Motivation and Efficiency: During the 1880s in the USA, the ‘Father
researches in the Midvale steel works, where he was a charge hand over
lathe operators. Soon, with his colleagues Lawrence Gantt and Frank Bunker
industry. He believed that both sides of industry were far too concerned with
how the surplus moneys of the business were divided, when they should be
more concerned with how to increase the extent of the surplus. As a means
to work with a proper and adequate use of incentive and bonus system. As
well as being concerned with proposals for a mental revolution, Taylor and
his associates Gantt and Gilbreth spent a considerable amount of time and
20 | P a g e
e) Processes of Management: The basis of his analysis was that a management
process consisted of five areas – planning, organizing, commanding,
coordinating and controlling. Fayol was the first person to advocate what at
that time was considered to be a somewhat revolutionary thought, namely
that management principles could and should be taught.
Construction management involves challenges that result from the unique nature of
21 | P a g e
II) Construction projects have features similar to the products and
production processes, which characterize manufacturing and those, which
characterize project-based industries.
III) The physical characteristics of construction projects are as a result of:
a) many different technologies – sometimes depending on global
networks of organizations;
b) local industries;
c) construction companies;
d) building regulations and standards available locally and internationally.
IV) Construction projects have:
a) individual locations (no two sites are the same);
b) complexity (a system with many parts);
c) uncertainties (lots of risks)
a) Scope Management
b) Schedule Management
c) Budget Management
d) Quality Management
e) Team Management
f) Stakeholder Management
g) Information Management
h) Risk management
i) Contract Management
22 | P a g e
Above management process have divided into two groups:
a) Enabling processes
b) Facilitating processes
1) Enabling Processes: In the construction management process enabling process
include with project scope, schedule, budget and quality. Hence these are should
enable to direct some specific objectives of the project and for project success
within on time, cost, quality.
2) Facilitating Processes: This process includes with some specific function such as,
Team, stakeholder, information, risk, and contract management, these are
facilitating for assist and make possible for the project to achieve its objectives.
a) Team Management: Team management is a techniques, processes and tools
for organizing and coordinating a group of individuals working towards a
common goal, there are few critical factors for success of the team
management process, identify the roles & responsibilities, reporting
relationships and getting the people that will be allocate to the project,
develop the team. As well as team evaluation is very important part to identify
the staff performance and their skill level and required improvement.
b) Stakeholder Management: Stakeholder management include stakeholder
identify, analysis, planning and communication. Project stakeholders are very
important people for the project success, hence project manager has to
manage them in proper way, because of all of them interest to the project
success. As example donors, beneficiaries, local government organizations,
partners or organizations are the stakeholders of construction project. As well
as managing them keeping good relationship between stakeholders and
project.
c) Risk Management: Identification of possible risks in advance is important and
major responsibility of the Construction manager. The project management
team will be able to take necessary actions to avoid or minimize the risks by
identifying them early. Safety of work, Economic matters, Weather conditions,
political matters etc. also includes in risk management. Hence it is important
to take insurances for the construction, material on site, employees; third
party etc.
8) The project manager must be flexible to accommodate any change that might
occur during the project.
9) There are factors of uncertainty such as the performance of individuals, how
their skills adapt to unfamiliar work, and other unknown external influences.
10) The total cost of construction project shall be defined and project shall be
completed within the given budget.
11) The project should provide unique opportunities to acquire new skills.
12) The project gives impetus to the project manager to adapt to working under
changing circumstances, as the nature of the project is change.
13) There are risks with each step of the project, and the project manager should
manage those risks to reach the project goal.
14) The Client and Architect have direct access to all the subcontractors, their
costs and contracts.
15) The Contract is directly between the Client and the subcontractor giving
greater control.
16) The subcontractors for each package specialize in the scope of work for which
they are appointed.
17) The specialist subcontractors give far better quality of finishes and less
snagging.
25 | P a g e
18) Because the Contract is directly with the subcontractor, the Client pays the
subcontractor directly and so all the money goes to him without an
intermediary taking a cut.
19) The Construction Manager is employed as the Client’s representative and is
‘on his side of the fence’, giving the Client better control and protection.
20) Each package is competitively tendered and therefore the Client knows that
the cost of the project is the sum of the tendered subcontracts which gives
considerable cost benefits to the Client.
1. Provides for the lowest possible project cost and construction management
fees based on selecting the lowest bidder from each of over 30 different bid
divisions.
2. Represents the best possible mechanism for securing local contractors.
3. Allows for Sales Tax savings on directly secured materials when allowed.
4. Provides an advocate exclusive to the Owner by placing a construction
manager and expert on-site during all phases of construction. This will
provide for early dispute resolution and aggressive and fair change order
negotiations.
5. Eliminates any conflict of interest since the Construction Manager does not
perform design or trade contracting through its own workforce (we are truly in
a position to act as your advocate).
6. Promotes building design feedback during plan creation. This includes design
and building material suggestions as well as early and accurate estimates.
(The greatest majority of cost savings realized during a construction project
occur during the design phase.)
7. Provides the opportunity to “fast-track” and phase the project to get the
project in the ground before it freezes, while maintaining continuity with your
building representative.
8. Eliminates the mark-up of subcontractor’s initial bids and on change
orders. The administrative fees of a General Contractor are simply
transferred to the Construction Management firm.
9. Allows the Owner to select their construction representative based on the
firm’s expertise and compatibility rather than simply on price. The
Construction Manager establishes a fee which is not dependent upon final
project cost, but rather is based on manpower needs.
26 | P a g e
10. Generates additional revenue for the Owner since any cost savings realized
through the bidding process and any leftover funds in contingency and
general condition accounts are returned to the Owner at the end of the
project.
1. Cost overhead can be more than many companies can afford. The hiring of
project managers and training a project management team can be difficult for
small companies and companies that are facing financial difficulties. Project
managers are rarely paid below $70,000 per year.
2. Communication overhead can be too much for a company to handle. With a
project management team, a new layer of communication has been added
into the fray. All information is generally funneled through the project
manager instead of information flowing directly between functional managers
and the team members.
3. Time overhead also is considered since there is no longer direct contact
between managers and team members. While all tasks are mapped out in
project management, a project manager can never accurately calculate the
time needed for each task. Delays are inevitable and then the project manager
is pushing the team to make up the time lost.
4. Obsession is becoming a problem among project managers and makes for a
stressful environment for all involved. Project managers can actually hinder a
project by becoming to rigid or precise in their project plans. The team
members no longer have a certain amount of flexibility.
5. Non-creativity can fall into two categories for project management: technical
and managerial. Technical non-creativity is when the project manager sets
strict deadlines on resources and forces the team members to work within
strict parameters. This hinders the creativity of the team members.
Managerial non-creativity is when the manager becomes lead by the
processes of management instead of being flexible. This causes their
managerial skills to weaken and they become stagnant in their position.
CPM and PERT in construction projects are the tools used for efficient
management of activities.
27 | P a g e
CPM is Critical Path Method and PERT is Program Evaluation and Review
Technique.
Critical Path Method: Critical Path Method (CPM) was first used during the
overhauling of a chemical plant in United States in the year 1950 by Morgan R.
Walker of DuPont and James E. Kelley, Jr. of Remington Rand. By using this
technique of activity management, they substantially reduced the time of
overhauling of the chemical plant.
Technique (PERT) was first used in 1957 in United States for the design and
completion date for the project two years in advance of the earliest possible date
predicted by traditional planning methods the U.S. Naval dept. devised this new
technique.
28 | P a g e
CP
M
and
PER
T in
Con
struction Projects:
The difference between the CPM and PERT is that the PERT is mainly used where the
time required for completion of each of the activities involved cannot be accurately
defined nor are the resources to be used for the activity readily available. The events
could however be readily definable.
For example, for a construction project type, which have not been completed
anywhere in the past, when it is possible to say that with reasonable accuracy that an
activity “A” has to be completed before activity “B”, but the time required to complete
the activity “A” is not known or the completion time of activity “B” is uncertain, in that
case PERT technique is used.
This technique is based on the probabilities of completing each activity in time. The
time is not of much importance in this technique, and completion of each event is
taken care of. This technique is therefore most suited to projects like research and
development, investigation, design etc. Also PERT because of the large number of
calculations involved is essentially a computer-based system.
29 | P a g e
various activities during the execution of the project. Time required for each activity
is known and defined for the project.
Hierarchy of the construction project events are well defined and time of completion
of the same is also defined. The total time required for the given project can be
estimated based on this technique.
CPM is an activity oriented system as the times required for construction activities
are estimated more accurately. CPM is used where activities are definable and
measurable and minimum overall cost is of the utmost importance.
(b) The jobs must be such that they can be started or stopped independently of each
other within a given sequence, (e.g. certain continuous flow processes such as oil
refining, where jobs or operations must follow one after another with essentially no
time separation, are not amenable for analysis by PERT or CPM).
(c) The jobs are ordered i.e. they must be performed in Technological sequence (e.g.
the foundation of a wall must be completed before the wall can be built).
PERT and CPM are tools used for managing the construction project activities and if
followed thoroughly, the construction project can be completed within the time limit
and within the cost. But use of these tools does not guaranty the desired outcome
due to bad management problems, natural calamities, strikes by labors etc.
30 | P a g e
Howsoever good a tool may be, its success depends on how well the tool is used.
The CPM Network affords management with information for taking decisions and
focusing its attention to essential operations.
Step2: From event 1, strike off all outgoing activities. This would have made one or
more events as initial events (event which do not have incoming activities). Number
that event as 2.
Step3: Repeat step 2 for event 2, event 3 and till the end event. The end event must
have the highest number.
31 | P a g e
The activity B cannot start until activity A has been completed. Activities C and D
cannot begin until activity B has been completed, but they can be performed
simultaneously. Similarly, activities E and F can start only after completion of
activities C and D respectively. Both activities E and F finish at the end of event 6.
Example: Consider the project given in the following table and construct a
network diagram.
32 | P a g e
Example: Construct a network for a project whose activities and their predecessor
relationship are given in Table.
Solution: The network diagram for the given problem is shown in Figure with
activities A, B and C starting simultaneously.
Network Diagram
33 | P a g e
Example: Draw a network diagram for a project given in Table.
Project Activity Sequence
Solution: An activity network diagram describing the project is shown in figure below:
Network Diagram
34 | P a g e
5. NETWORK ANALYSIS OF CPM:
35 | P a g e
36 | P a g e
37 | P a g e
38 | P a g e
39 | P a g e
40 | P a g e
PERT Basics:
At the core, PERT is all about management probabilities. Therefore, PERT involves in
many simple statistical methods as well.
Sometimes, people categorize and put PERT and CPM together. Although CPM
(Critical Path Method) shares some characteristics with PERT, PERT has a different
focus.
Same as most of other estimation techniques, PERT also breaks down the tasks into
detailed activities.
Then, a Gantt chart will be prepared illustrating the interdependencies among the
activities. Then, a network of activities and their interdependencies are drawn in an
illustrative manner.
In this map, a node represents each event. The activities are represented as arrows
and they are drawn from one event to another, based on the sequence.
41 | P a g e
Next, the Earliest Time (TE) and the Latest Time (TL) are figured for each activity and
identify the slack time for each activity.
When it comes to deriving the estimates, the PERT model takes a statistical route to
do that. We will cover more on this in the next two sections.
In PERT, these three estimate times are derived for each activity. This way, a range
of time is given for each activity with the most probable value, TLIKELY.
2. TLIKELY
Most of the times, project managers are asked only to submit one estimate. In that
case, this is the estimate that goes to the upper management.
3. TPESS
This is the maximum time required to complete an activity. In this case, it is
assumed that many things go wrong related to the activity. A lot of rework and
resource unavailability are assumed when this estimation is derived.
At the same time, the possible variance (V) of the estimate is calculated as below:
Then, the total of all Es are taken. This is the overall expected completion time
for the project.
Now, the corresponding V is added to each activity of the critical path. This is
the variance for the entire project. This is done only for the activities in the
critical path as only the critical path activities can accelerate or delay the
project duration.
43 | P a g e
Then, standard deviation of the project is calculated. This equals to the square
root of the variance (V).
Now, the normal probability distribution is used for calculating the project
completion time with the desired probability.
44 | P a g e
or tender software. Clear interfaces reduce unnecessary data collection and prevent
inconsistencies.
There is no completely comprehensive software tool available to deal with all the
tasks involved in project management, a suite of systems is usually needed:
Scheduling Software:
Construction scheduling software is used to plan, monitor and control project
progress. Buffers and the corresponding critical path can be calculated based on
process durations, deadlines and relationships and appropriate resources can
be assigned. The results are usually displayed in the form of a Gantt chart, network
plan or list. By entering current data, the user is able to automatically generate
appropriate target-performance comparisons.
Project Communication System:
Project communication systems support the coordination of a construction project
by providing a joint platform to all project members for collaboration
and information exchange. Usually, the platforms are internet-based and data
45 | P a g e
access can be governed by different user authorisations and privileges. The range of
functions varies greatly. Some platforms simply provide a common data store whilst
others provide comprehensive media and workflow support.
Digital Construction Diary:
Digital construction diaries range from simple templates for word processors, to
internet-based systems with complex data structures. By integrating media such as
photo documentation, the cogency of the construction diary can be increased.
Pictures can prove especially useful to remote project team members.
Cost Control Software:
Cost control software is based on capacity planning methods. Resources are
assessed according to cost information, such as the charge-out rates
for workers and equipment. By linking to the
project’s accounting software, budget figures can be compared with actual figures. In
addition, reports can be generated automatically presenting a visualisation of the
processed data.
The text in this article is based on an extract from COMPUTER METHODS IN
CONSTRUCTION, by Christoph Motzko, Florian Binder, Matthias Bergmann, Bogdan
Zieliski, Mariusz Zabielski and Robert Gajewski. Darmstadt, Warsaw 2011. The
original manual was developed within the scope of the LdV program, project
number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for
European Managers in Construction”. It is reproduced here in a slightly modified
form with the kind permission of the Chartered Institute of Building.
CONCLUSION:
Today's owner who adopts the project management approach to establish a new
facility, finds that he avoids becoming directly involved with the time-consuming
design and construction details. Instead, the approach enables him to continue to
concentrate on his primary on-going profit-making business.
46 | P a g e
With the exception of certain legally specified ecological resources,
such as endangered or threatened species and protected wetlands,
there is no social or scientific consensus on which ecological resources
affected by roads should be given priority attention. In addition, current
planning assessments that focus on transportation needs rarely
integrate other land-management objectives in their assessments.
47 | P a g e
DISSERTATION REPORT
CONSTRUCTION MANAGEMENT
48 | P a g e