specification

April 19, 2019

1. Company name: AK INDIAI factory new construction

2. Outline of the Project: This project was carried out by Ackyeong Chemtech INDIA PVT.LtdI, a
subsidiary of AK Chemtech,

Is a paint factory that is newly built and built.

We will quote the specification, design book, and BOQ that we submitted today.

3. Quotation: e-mail tjkwon@aekyung.kr, pncleejh@aekyung.kr

Submit it by 17:00 (local time in India) on April 29, 2019.

4. Construction period 1) Date of installation: Within 5 days after contract

2) Working days: August 31, 2019

3) Other conditions: Production until January 2019 Production facilities and experiment

Equipment can be installed. Totok floor, exterior wall, roof construction should be
completed.

4) Completion criteria: Completion of all licenses related to the use of the factory, such as
construction, firefighting, etc.

When the condition is determined to be complete

5. Terms of payment (Rupee, GST separately)

1) Down payment 40%

2) Gross 50% (after completion of construction)

3) 5% after completion (after completing necessary licenses for construction, electricity, fire and
other factory operations)

4) After 12 months of completion, 5% (reserves related to warranty)

6. Uniqueness

1) The drawings and BOQ (mailed to us) submitted by the Company to the Quotation Presentation,
this specification,
Estimate that there are no parts. If there is an error in the quantity and quantity in the current
quantity calculation sheet,

If there is any content on the drawing, it should be done on site. (No additional settlement)

7. Major contract work contents

1) Key points of the construction work

A) Construction work

• On-site office - Install one container or equivalent of temporary container before construction

• Temporary Toilets

• Power and water for construction: Power supply and water required for construction are
provided by the contractor.

(User fee payment)

B) earthworks

• Residues and waste should be disposed of properly on site.

• The soil for backfilling is stored at the designated site in the site and stored.

Recovery should be restored

• Construction of other earthworks companies in accordance with the basic and standard
principles.

C) Construction, sanitation, sewage disposal, fire fighting, supply of water, steel frame, roof,
waterproof, plaster, exterior wall, window, painting, landscape

, Other construction work drawings, BOQ, general construction standards.

• External paint color to be selected later

• Inspection and approval of the supervisor must be obtained for major materials and processes.

• To prevent water leakage, it is important to waterproof the roof and waterproofing such as
eaves.

(Other than silicon finishing)

• Pottery for toilet is "rewarded"


D) HAVC: see drawing and BOQ

E) Production Dongklin Room: Glass Ool Panel 50T

Bar) AIR piping and others

2) Electric works

• Includes construction and licensing of water supply facilities.

• Construction shall be carried out in accordance with drawings and general electrical work
standards.

• Construction scope: Water distribution (750KVA three-phase four-wire 400 / 230V 50Hz),

Generator (450KVA, three phase four-wire type 400 / 230V 50Hz)

UPS 50KVA

Construction electric, fire fighting electric, telecommunication, internet, mechanical power facility
cable construction,

External buried pipeline construction, underground construction, etc.

• Basically, it includes all the 1st and 2nd power works.

• Electrical specialties specification

end. Building Construction Electric Works

A. The office shall be constructed by general electric works.

- Installation of power and light distribution panel for each floor

B. Factory lighting Electric construction is explosion-proof type.

- Factory light distribution panel panel, HAVC panel.

- Factory lighting fixtures are installed in explosion-proof type,

Explosion-proof flexible piping, sealing fitting, explosion-proof lighting equipment, etc.

C. Factory. office. laboratory. Electric panel, etc. All power, lighting,

Grounding shall be made to connect to the grounding specification.

I. Dissolver, Rimmel Electrical Works

A. Dissolver electrical work (see drawing)

- Primary Power in MCC Room Main Lt Panel, Dissolver Panel, CABLE Duct,

Conduit, explosion proof flexible, sealing fitting, (motor, LOP) are to be constructed in order.
- Dissolver (D-101, D-104) On-site facilities All power control circuits

It should be wired to one pipe.

(Agitator, Hydraulic Pump, Control, RPM Instrument - 2nd Installation Diesel for India)

- Two Dissolver 20HP units (D-102,103) are built into one panel.

Two primary power sources shall be installed.

- Dissolver 20HP 2 unit has 2 holes of 42ø hole in the terminal box.

Two power and control piping can be used.

- Dissolver 5 is designed to ground portable portable tank FCV 6SQ * 2M

Connect the cable to the 50A tongue to ground the portable tank by grounding to the dissolver.

(Tongue cord wire * 2m * 5EA manufacture and installation)

-. Place the cooling fan space (15 cm) on both sides of the dissolver (D-101, D-104) panel.

B. RingMill electrical work (see drawing)

- Primary power in MCC room Main Lt Panel, Rimmel panel, CABLE duct,

Conduit, explosion-proof flexible, sealing fitting, (3 motors, LOP).

- Since the ring box field terminal box is 54ø, 42ø * 2EA hole,

Power and control Three piping can be done.

- Installation of the same grounding cord as the dissolver.

All. Laboratory Power Construction

A. Laboratory test stand power outlet construction

New installation of panel after installing 16SQ * 4C cable in PDB panel SPARE (MCCB 4P

63A After main installation, branch MCCB 2P 20A 10EA, 7EA use, 3EA SPARE) In the laboratory

Experimental table after wall installation 5 lines for each 4SQ * 3C, 4SQ * 3C for small oven 2 lines

It is installed and connected. (Additional addition)

B. Dissolver electrical work

a. Primary Power in MCC Room Main Lt Panel, Dissolve Panel, CABLE Duct,

Conduit, explosion proof flexible, sealing fitting, (motor, LOP) are to be constructed in order.
b. Dissolver (D-105) On-site facility All power and control circuits

It should be wired to one pipe.

(Agitator, Hydraulic Pump, Control, RPM Instrument - Hydraulic Diesel)

C. Other Experimental Power Electric Works (Refer to the drawing)

- Spray booth, oven, UV irradiator, etc.

la. Other auxiliary facilities power construction

A. Dust collector, compressor, table lift, air conditioner, electric forklift charger, etc. (see
drawing)

- In addition to other facilities, SUS304 panel for outdoor use is installed outside the factory.

1st and 2nd electric works should be done.

- The electric panel production of each auxiliary facilities is done by the equipment manufacturer.

B. Electric Fork Lift Charger

- Installation of cables from the Utility PANEL to the field installation location in the drawing
(included in the BOQ and drawings)

- The forklift local panel is newly installed outside the charger (Sus304)

After installing MCCB 63A inside the panel, install 6SQ * 4C branch MCCB 30A * 2EA.

(Additional addition)

C. SCALE Power

- Install 10A MCCB in 2p branch of factory light panel and install it in 2.5SQ * 3C (Additional
addition)

hemp. Design Book Electric Works

- Construction should be done in accordance with design books and specification standards.

- Electrical work in explosion-proof areas should be done in accordance with the explosion-proof
standards.
• The electrical materials supplied by our company are electric panels of dissolver and ring mill,
related sealing fit, explosion proof SUS

FLEXIBLE hose, panel and electrical materials other than the above are handled by the integrator.

(Dissolver, Sealing Fitting of Ring Mills, Explosion-proof SUS FLEXIBLE Hose)

• Our paint factory is always related to explosion and fire. Therefore,

The explosion-proof area is used for explosion-proof outlet and lighting.

Construction. Refer to the drawing for cable installation on power installations (dissolver and ring
seal, etc.).

• All electrical appliances and equipment should be grounded.

• When making the main electric panel, we give the production drawing to our company and
make it after approval.

• Electrical products (MCCB, ELB, MC, etc.) are ULFM products.

• For electrical piping specifications, refer to the drawings, and the drawings of the supporter or
channel

Because there is not, it estimates it considering this. Supporters (3-4m apart) and piping are either
saddles or clamps

Fix

• Install a high pressure, low pressure pressure switch (max. 10kgf / cm2) in the pressure tank for
the water and fire pump,

Depending on the pressure setting, the pressure switch can be connected to the control panel for
operation and stop

Lock. ON / OFF Automatic, manual switch is installed.

Fire on the receiver. (Drawings and BOQ confirmation required)

4) Additional work

• Two table lifts and one platform scale foundation work, with separate drawings

• Equipment transfer installation work

- Equipment list: Three dissolvers (10HP, 5HP, 0.5HP each electric panel included), Dry oven (1.5m
* 2m) 1

- Transferred to the new factory from the second floor of the Sungji Paint Factory (Grater Noida)
(Panel MCC room installation, dissolver production site anchor fixing)

- The related electric works are included in the BOQ and provide separate reference specifications

• Installation of equipment (from korea)

- Equipment list: 20 sets of dissolver (20HP), ring mill (1 set, 60HP), chiller, 10 kinds of portable
tanks,

Various experimental equipments

- The related electric works are included in the BOQ and provide separate reference specifications

- Installed factory designated place in our shipping container (2 Dissolver 20HP, 1 RINGMILL 60HP,
1 CHILLER 1

(Unloading equipment from the container, fixing the anchor in the field, providing the anchor)

- Portable tanks and laboratory equipment only get off container

• Chiller side water piping (15A) - Check for BOQ

• Electricity addition: Electricity special specification

5) Coordination of permission for completion

We will cooperate with the designers in order to allow us to operate the factory without any
problems.

6) Others:

Electricity, drawings of HAVC and BOQ are sent by April 24

Confirmation of excluded clean room facilities

8. General

1) Those who received contract work should submit the construction work schedule and
construction schedule within 3 days before and after the start of construction.

shall.

2) This contractor is responsible for construction quality, air, etc. based on the basic design chart,
this specification,
In principle, there is no settlement, so you should be careful when estimating.

3) Even if it is not specified in the design, specification, and BOQ,

The matters that necessarily arise due to the finishing relationship should also be applied in the
contract amount and air.

4) For the process requested by the Supervisor, make sure to submit the construction plan and
proceed with the approval process

5) If the design books are inadequate or wrong during the construction, please consult with the
supervisor before proceeding

6) The site will be arranged and arranged from time to time.

7) The safety management and all the insurance related to the construction shall be made by the
person who received the contract,

Is solely under the responsibility of the contractor. In this case,

All the rules and the training of the workers should be fully prepared.

8) The contractor shall not comply with the relevant laws such as environment, safety,

The contractor is solely responsible for the cost and legal liability.

9) If it is judged that the construction can not be terminated within the due date, we will ask the
contractor for night work

And will not be allowed to incur additional costs.

10) The warranty period of this construction is one year.