Академический Документы
Профессиональный Документы
Культура Документы
A project is a set of activities that ends with specific accomplishment and which has non-
routine tasks, distinct start/finish dates, and time, money, people, and equipment resource
constraints (Jones, 2005). It is essential that projects are successfully completed, and are
within time, quality, and cost parameters (Burke, 2002). Several tools are used in the design,
and implementation of projects.
Budget
It is a financial plan that shows the resources that are required in a project/programme
It projects expenditure that is allocated to cost centre (departments) and cost units
(activities)
Budget helps to ensure that the project/programme is completed within set cost
parameters.
Budgets also help to prevent unauthorised expenditure. Any expenditure not budgeted
for should not be made
Sometimes, there are variations in terms of the expenses for cost units and costs
centres and there can be excesses and shortages in some areas. When this happens,
there can be transfer of money from one cost centre/unit to the other (virement)
WBS
A number of activities are to be conducted to ensure the launch of the project. These
activities are specified in the work-breakdown structure (WBS). According to Wright (1998),
a WBS contains the smallest work components of a project and the activities should have a
clear start and end dates. A WBS provides a scope for project costing and is an entry point
into any project. Table 1 shows the work-breakdown structure.
Gantt Chart
A Gantt Chart is a graphic way of portraying the project using horizontal lines that represent
activities that must be completed and the time they should be completed (Krahn, 2006).
According to Durfee and Chase (2003), Gantt charts are a project planning tool that can be
used to represent the timing of tasks required to complete a project. Because Gantt charts are
simple to understand and easy to construct, they are used by most project managers for all but
the most complex projects (Clark, 2002).
1
In a Gantt Chart, each task takes up on row. Dates run along the top in increments of days,
weeks or months, depending on the total length of the project. The expected time for each
task is represented by a horizontal bar whose left end marks the expected beginning of the
task and whose right end marks the expected completion date. Tasks may run sequentially, in
parallel or overlapping (Nancy, 2004).
The Gantt Chart (Table 2) shows the expected duration of the project. It shows that the
hospital is expected to take 15 months to construct.
Advantages of WBS
Helps to ensure that all activities to be done in a project/programme are indentified
and none is overlooked
The scope of work to be done is determined through a WBS
Limitation of WBS
2
It can also be used for projects that have been implemented somewhere before. In
case of totally new projects, some activities may be overlooked, only to be known
during the implementation of the project.
Projects are unique, in terms of location and contextual factors and some activities can
just emerge during the implementation stage. There might be unforeseen
circumstances, for example the case of Tokwe-Mukorsi Dam, when there was a need
to provide shelter to villagers affected by floods in 2015. The case of Kariba dam,
when there was a need to rescue animal trapped by the dam water.
WBS cannot indicate when the project should be completed and does not show the
link between activities, hence the need for other tools like Gantt Chart and Network
Analysis.
In addition, Tinnirello (1999) argued that, when a project is under way, Gantt charts help to
monitor whether the project is on schedule. They are also simple to prepare, information is
portrayed in easy to understand format, and they make it easy to summarize information.
Moreover, PriceWaterhouseCoopers (2004) believed that Gantt charts are essential in time
management. Time is a very important resource in project management and in some cases it
can be referred to as a constraint. Time is also a measure of project success. This view is
supported by Kerzner (1989) who contends that successful project management can be
defined as having achieved the project objectives within time and cost, at the desired
performance or technology level and while utilizing assigned resources effectively and
efficiently. Kirkpatrick (1991) supports this view by arguing that time is one of the three
basic elements in a project. The other two basic elements are tasks and resources.
Kerzner (1989) further argues that it is extremely critical for project managers to manage
their time effectively, and Gantt charts can be helpful in this endeavour. He believes that if
the project manager cannot control time, then he/she will control nothing else in the project.
Time is a resource, which when lost or misplaced is gone forever.
Time is often seen as a constraint and effective time management principles must be
employed to make it a resource. Project managers have developed techniques for making sure
that time becomes a resource. These techniques include the Gantt chart.
3
Disadvantages of Gantt Charts
A number of weaknesses are observed when one uses Gantt charts. According to Wright
(1988), Gantt charts do not show effects of going off schedule, and are difficult to use for
detailed schedule analysis. Also, Gantt charts do not show the dependency of each activity or
schedule method, and do not show the uncertainty presented during the activity’s duration or
events.
Despite the mentioned disadvantages, Gantt charts are useful tools for managing projects.
They need to be complemented by other tools like Critical Path Method (CPM) or Network
Analysis.
Network Analysis/CPM
Time is a very important resource in project management and in some cases it can be referred
to as a constraint. Time is also a measure of project success. This view is supported by
Kerzner (1989) who contends that successful project management can be defined as having
achieved the project objectives within time and cost, at the desired performance or
technology level and while utilizing assigned resources effectively and efficiently.
Kirkpatrick (1991) supports this view by arguing that time is one of the three basic elements
in a project. The other two basic elements are tasks and resources.
Kerzner (1989) further argues that it is extremely critical for project managers to manage
their time effectively. He believes that if the project manager cannot control time, then he/she
will control nothing else in the project. Time is a resource, which when lost or misplaced is
gone forever.
Time is often seen as a constraint and effective time management principles must be
employed to make it a resource. Project managers have developed techniques for making sure
that time becomes a resource. These techniques include Network Analysis/CPM. Wright
(1998) said that CPM is a technique for modelling the logic of a project with the aid of a
network. CPM provides an approach for ensuring that a project is completed in time. CPM
helps in prioritisation in terms of the conduct of activities as the critical activities, which
should not be delayed, are identified. The amount of time in which the non-critical activities
can be delayed (float) is also established.
Advantages of CPM
Used to aid the planning and control of complicated projects
A network diagram is constructed to show sequential relationships between the
various components. This enables planners to calculate the minimum time needed to
complete the project and identify critical activities where delay would prevent
completion of the overall project within the minimum time specified. By identifying
these critical activities, managers can pursue a more rational approach to the planning
of resources.
identify activities that cause, or are likely to cause, bottlenecks and delays.
determine when resources and components are needed.
plan the use of resources.
Limitations
not suitable for new projects that have never been implemented somewhere.
Projects are unique and circumstances may change, leading to the shortening or
lengthening of activity durations.
4
CPM is only concerned about one aspect of the project, which is time. It does not
focus on other issues like quality.
5
• Outcomes
• Outputs
• Activities
Activities lead to Outputs, Outputs lead to Outcomes, and Outcomes lead to Goals.
OBJECTIVES
OUTPUTS
ACTIVITIES
Summary
BUDGET: I want to determine how much money is needed, and when
6
References
Besner, C. and Hobbs, B. (2006), The Perceived Value and Potential Contribution of Project
Management Practices to Project Success, Project Management Institute Research
Conference Proceedings, London.
Davis E.W (Editor) (1976), Project Management, Techniques, Application and Managerial
Issues, American Institute of Industrial Engineers, Norcross, Georgia.
Durfee, W. and Chase, T. (2003), Brief Tutorial on Gantt charts, University of Minnesota.
Jones, M.P. (2005), Practical Project Management, Dorset House, New York.
Krahn, J. (2006), Effective Project Leadership: A Combination of Project Manager Skills and
Competencies in Context, Project Management Institute Research Conference Proceedings,
London.
Nancy, R. (2004), The Quality Toolbox, Second Edition, ASQ Quality Press, New York.
PriceWaterhouseCoopers (2004), Boosting Business Performance through Programme and
Project Management, London.
Project Management Institute (2001), Project Management Fact Book, Second Edition,
London.
Project Management Institute (2007), Project Management Salary Survey, Fifth Edition,
London.
Tinnirello P.C (Editor) (1999), Project Management, Best Practice Series, Auerbach, Boca
Raton, Florida.
Ultimate Business Library (2003), Best Practice: Ideas and Insights from the World’s
Foremost Business Thinkers, New York.
Wright E.A. (1998), Practical Project Planning, University of Zimbabwe Publications, Mount
Pleasant, Harare.