OPERATIONAL QUALIFICATION of
HVAC SYSTEM – LVP PLANT
LIST of CONTENT
History of Revision....................................................................................................................................ii
Approval Sheet.........................................................................................................................................ii
1. OBJECTIVE.......................................................................................................................................1
2. SCOPE..............................................................................................................................................1
3. RESPONSIBILITY.............................................................................................................................1
4. PROCEDURE....................................................................................................................................1
5. QUALIFICATION DESCRIPTION......................................................................................................2
6. ITEM CHECK LIST AND QUALIFICATION.......................................................................................3
7. ACCEPTANCE CRITERIA.................................................................................................................5
List of Attachment:
Operational Qualification Form
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date : ii
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
a. History of revision.
Rev. No. Date Revised item Reason Remark
b. Approval record.
No. Department Approval Date Name Signature
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
1
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
I. OBJECTIVE
To demonstrate that the Qualification of the new Heating Ventilation Air Conditioning system (HVAC) installed in
Clean room of Large Volume Parenteral plant of PT Otsuka Indonesia could operate properly as the purchase
specifications, the manufacturer literatures, and meets PT Otsuka Indonesia requirement.
II. SCOPE
For operational of any equipment and component of the HVAC system in Clean room of Large Volume
Parenteral plant of PT Otsuka Indonesia
III. RESPONSIBILITY
It is the responsibility of QA to
a. Approving the protocol.
b. Approving data and conclusion
IV. PROCEDURE
For each AHU, fill in the prepared checklist with the detailed mechanical and electrical specifications, drawings,
etc. (as itemized in the OQ format) for each component as listed in the OQ format.
The individual component checklist includes a space to record the information plus any deviations found during
the operational check.
Responsible person verifies that the information is complete, prepares the deviation report and the Operational
Qualification Report and, submits to QA.
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
2
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
V. QUALIFICATION DESCRIPTION
Qualification of each terminal HEPA-filtered HVAC system is to be carried out and documented. The
documentation should include as-built drawing, commissioning record, operation and maintenance manual,
etc.
The HVAC system should have been qualified upon operational. Prior to validation and after major changes,
those parts of the HVAC systems affected should be re qualified.
HVAC System
Design
Comprehensive drawing, schematic diagrams , and specifications for the complete system defining the
operating ranges for each parameter. Verify that suitable provisions have been included for servicing and
testing HEPA filter systems; such as, DOP ports, monitoring ports, scanning access and filter changing.
Equipment
Comprehensive specifications for each HVAC unit defining its function should be available. Where
applicable, operating parameters should be specified. These may vary with each HVAC unit and may
include but no be limited to the use of the following component, each of which must be calibrated and / or
qualified as required.
Services / Utilities
Electrical
1. HVAC System for Room 10,000 / Class II & Room 100,000 / class III
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
Insulation Test
Insulation test 500 – 1000mΩ
Differential pressure
Static Pressure 3” WG measurement
(Magnehelic)
The HVAC System and its components can meet operational specification and PT. Otsuka Indonesia
standard.
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
DESCRIPTION:
1. HVAC System for Room 10,000 / Class II & Room 100,000 / class III
Equipment name HVAC system
Function Temperature, Relative Humidity , Particle, Microbial and
Differential Pressure controller
Location LVP BS LINE
Group LVP
Date February, 2006
Description Quantity
Supply and install Air Conditioning split duel 1 unit
Cooling capacity : 389,790 BTU/h
Model : CLC P.025
Merk : Trane
Supply and install Booster Fan 1 unit
Capacity : 21,000 m3/h
Static Pressure : 3” WG
Merk : Kruger
Supply and install Ducting 1 lot
Supply and install Pre filter efficiency : 25 – 30 %
Supply and install Medium filter (bag filter90%) 1 unit
Supply and install Pre filter and Medium filter housing galvanized plat 1 unit
(customizing)
Supply and install HEPA filter 23 units
Supply and install HEPA filter housing galvanized plat (customizing) 23 units
Supply and install panel and cabling 1 lot
Dismantling existing equipment and ducting
Note : Air change 25 x / jam
Cable brand : Supreme
Panel brand : PT. SPLN
Filter brand : A.A.F
AC brand : Trane
Fan brand : Kruger
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
Capacity : Anemometer
Booster Fan unit 21,000 m3/h
Static Pressure : Differential pressure
3” WG measurement
(Magnehelic)
Body / Box A.H.U Visual/ Leakage Test
No Leakage
Ducting Installation Visual/ Leakage Test
No Leakage
Installation Avometer / Ampere
Electric system specification meter
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
CONCLUSION :
SUGGESTION:
Approved by : Reported by :
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
Description Quantity
Supply and install local Laminar Flow 1 unit
Size (2400x5400)+(1200x9600)+(2400x4800)
Brand:
Fan filter module : 50 pcs
Stainless Steel 304, thickness 2 mm
C/w - 16 pcs filter efficiency 99.99 %
- 6 no. centrifugal fan
- 1 set Air Curtin glass thickness 6 mm
Ducting
Installation No Leakage Visual/ Leakage Test
Insulation Test
Insulation test 500 – 1000mΩ
/conversion/tmp/scratch/421418254.doc
PT. Otsuka Indonesia Page :
Jl. Sumber Waras No. 25
QUALIFICATION No : PV/GOQ/HVAC/001
LAWANG PROTOCOL Date :
Revision No. : 00.
OPERATIONAL QUALIFICATION FOR Replaced :
HVAC SYSTEM – LVP PLANT No. :-
Date :-
CONCLUSION :
SUGGESTION:
Approved by : Reported by :