Вы находитесь на странице: 1из 16

Consideration between Site Layout Facilities, Provision of Work

Equipments and Construction Planning for Extremely Large and


Complicated Construction Projects
Raymond W M Wong
Lecturer, City University of Hong Kong, China
Jonathan S C Siu
Former Project Manager, Meco Services Ltd., Hong Kong, China
Dr.Christabel Ho
Lecturer, Hong Kong Polytechnic University, China

ABSTRACT:
The effectiveness in site layout and construction planning for extremely large-scale and complicated con-
struction projects not only affects productivity and cost, it also controls whether a project can be handled and
completed in a practical, safe, orderly, efficient and engineering feasible manner.

Projects qualified to be extremely large and complicated can be in a variety of forms. Take for examples in
Hong Kong’s situation. Construction cost of projects sometimes exceeds billions of dollars. Site covers more
than a few hectares of land with building areas in term of hundred thousands square meters. Or, projects
sometimes involve the construction of super high -rise buildings with more that 60 or 70 storeys in height. This
kind of building development projects, very often, consists of a number of annexed facilities such as a very
deep basement, or a podium with very large interior space and long-span elements. Special structures like
buildings constructed in structural steel or in composite manner. Some projects are located within very
congested urban environment, or located in close proximity to steep slope, or adjacent to sensitive facilities
like underground tunnels. In case of civil engineering projects, sometimes they also involve special provisions,
diversion and interfacing arrangement to very busy servicing traffic and other urban facilities.

This paper will identify various types of construction cases qualified to be of extremely large and complicated
nature under the built environment of Hong Kong. The paper will also illustrate how builders solve such
problems using innovative methods. Relevant brief case examples from civil engineering works in particular
for transportation facilities will also be referred in order to substantiate the explanation of the subject matter.
1 INTRODUCTION
a) Items or facilities
Usually when we are that are essential
talking about site layout and required for the
facili-ties we refer to carrying out of the
essential temporary construction works
facilities that are such as cranage, site
required to be provided transportation
during the period of equipments,
con-struction in order to falsework as
assist in the completion temporary support
of the construction or to facilitate
works. Site layout various storage
facilities and con- purposes, or the
struction planning allocation of
usually has a close temporary work
relationship for some of spaces for work
the major construction vehicles, work-
activities are highly shops, sub-
depended on the contractor yards and
provision of these other essential site
facilities in order to activities.
have the works b) Items or facilities
completed effectively, that are required for
ef-ficiently and the well being,
according to a convenience or
complicated schedule safety of workers
which in most cases is
such as
set under a well
washing/changing
coordinated manner. In
rooms, shelter or
a general sense, these
rest facilities for
facilities include:
workers, canteen,
access to work
fronts, or other
safety provisions.
c) Items or facilities that are required for the overall that are required by the concerning statutory
site logistics, operation and management such as requirements. These facilities include, for ex-
site entrance provision, site office, meeting or ample, the site fencing, supply and routing of
conference areas, supply and routing of essential water, surface drainage system, forming and
services, site laboratory, or other security provi- arrangement of access routing, setting up of
sions. site offices, arrangement for the delivery and
d) Items that are statutory required for the carrying positioning of the essential work equipments,
of the construction works such as fencing or and other provisions as required by relevant
hoarding, signage, wheel washing facility; statutory requirements.
equipment for waste disposal, water treatment, b) At the peak period of the construction project when
noise and dust control, or arrangement for tem- the permanent structural works are to be carried
porary traffic diversion etc. out.
Facilities to be set-up at this stage are more
These facilities usually have specific work targets specific for the carrying out of particular
or operation nature, however, they still have the fol- works, some of them are more temporary in
lowing characteristics in common: nature. Examples of these facilities include the
tower crane, workers lift, material hoist, access
a) Essential or not easy to be substituted for the provision to working fronts, work scaffold,
carrying out of the specific construction works, temporary platform, falsework or additional
b) Fairly temporary in nature, support to the required structures, and other
equipments or mounting up which are required
c) The positioning of these facilities often affects for the external works of the building such as a
the efficiency of the construction in particular power wincher system for the installation of
when they are not properly located, curtain wall units which is operated on a tem-
d) The positioning of the facilities often occupy porarily provided track rail.
significant work spaces and may affect the regu- c) At the final stage of the project when the
lar progress of other major activities, touching up, finishing works or other handing
e) Often required to be relocated to meet the ad- over arrangement are to be carried out.
vancement of works or progress of construction, At this stage of construction majority of the
f) Some of these facilities may have very important site layout facilities are required to dismantle
operational, structural or safety concerns, and remove from site. For some particular
equipments or facilities, some kind of addi-
g) The provision, installation and maintenance of
tional provisions may be required to assist in
these facilities can be quite timely and costly
the dismantling of them. For example, a
thus the providing, relocating, maintaining or winching machine and a lifting rod may be
dismantling of these facilities should be planned erected and set on the roof level to help the
in a very careful manner in order not to inter- dismantling of a tower crane and lowering its
rupted with the master planning of the construc- components down to the ground level for re-
tion works. moval. And of course, provision for the touch-
ing up of the disturbed areas after the disman-
2 INTRODUCTION PROVISION OF SITE tling and removal of the facilities is also
LAYOUT FACILITIES required.
B, Provision of major site layout facilities according
Provision of site layout facilities can be further clas- to types of construction
sified according to stages of construction and types Site layout facilities is relatively a general term
of project. Below are some of the examples of these for the setting up and operation of a construction
classifications and provisions. site for the nature, scale and type of works diver-
sify greatly from project to project. Situation for
A. Provision of site layout facilities according to building projects is relative much simpler when
stages of construction compare to civil projects. Below are the high-
a) At the commencement of the construction pro- lights of some of their feature according to the
ject types of construction.
Site layout facilities to be set-up at this stage a) Building projects involve the construction of
usually include provisions that must be pro- super high-rise tower/s in a relatively confined
vided before the effective carrying out of other site. The site layout facilities for this kind of
major construction works, or other work items projects, for example, include:
(i) Facilities and work spaces for the delivery
of construction materials or placing of con-
crete,
(ii) tower crane, mainly to assist work activi-
ties on floor-top work front,
adjacent to slope
or sensitive
structures either
at grade or
Photo 2 – Storage of underground. The
material can be very involved facilities
difficult for sin-gle tower
for this kind of
Photo 3 – Delivery and
type high-rise building.
project, for
storage of precast
example, include:
This photo shows the components for
temporary storing of congested site can be
semi-prefabricated steel very difficult in
components on partially particular when the
completed steel floor sequence of installation
beams is taken into
Photo 1 – Tower crane consideration.
used in high-rise building
construc-tion projects can
be mounted in a number
(v)loading
of ways. This photo
platform on
shows a climbing crane
intermediate
used in the construction
floors for the
of a steel frame building.
removal of
materials such
as formwork
panels or Photo 4 – Super-sized
(iii) hoisting propping building site (the
equipment (for components to International Fi-nance
delivery of other floors, Centre) with major
(vi) temporary excavation for basement
mate-rials or
workers hoist construc-tion and other
components to
or lift, associated work activities
structurally
in various locations carried
com-pleted (vii) safety out at the same time.
floors), provisions in
(iv) handling particular
spaces for setting up to
building prevent
materials and workers or
semi- materials
completed falling from
components height etc.
including pre- b) Large-sized
cast items, building projects
(Photo 2) in particular with
very large site
area or involves
works on site
with complicated
shape or layout.
This in-cludes,
for example,
deep and large-
scale ex-
cavation, work
Photo 5 – Another super-sized project example located on
sloping site with site formation, cut-off walling and
foundation works carried out at the same time. Site access is Photo 7 – Special layout and equipments provision for the
a primary problem in the project. construction of large-size basement is required such as the
use of a spoil removal hoist in this 5-level basement con-
structed in top-down method.
(i) Similar to site layout facilities as described
in the above but with the addition of some
other facilities such as access road and (iv) Handling or storage area in particular for
equipments for site internal transportation. intermediate materials handling purposes.
(ii) Set-up for temporary shoring works for the (v)Waste water treatment facilities due to the
protection of deep excavation, slope cutting collection of surface or construction waste
or sensitive structure. water from the large area of site.
(vi) Other environmental protection related fa-
cilities such as dust screen, catch fan or
noise barrier.
(c)Various types of large-scale and complicated
civil projects. Examples of these types of pro-
jects include site formation, slope treatment,
marine works, water supply or drainage works,
highways projects, railway construction, tun-
nel works, bridge construction, and other in-
frastructure development projects.
Site layout provisions for civil work projects
are often in a highly dynamic nature due to the
involved works are mainly in a horizontally-
spread layout without a lot of tall and inde-
Photo 6 – A commercial development located in congested pendent structures. Equipments or facilities
built-up area with the basement work in the peak period. involved are usually different for various kinds
Complicated shoring and ground supporting works can idle of civil works but in general they are very
a congested site for months unless stringent site layout heavy duty in nature for the requirement to
planning arrangement is introduced handle huge amount of materials or very heavy
components, or for the supporting of very large
loading. Very large operating space and
(iii) Involve the construction of a large-size additional equipments are normally required
and deep basement using sophisticated for the erection, maneuvering, operation and
method such as in top-down or other hybrid dismantling of these facilities. Below are some
approach. of the examples of these facilities that are used
in civil engineering works:
(i) Temporary accesses for work machines or
manual workers. These accesses can be
erected over water, over large area of undu-
lated surfaces, down to deep excavation
pits, climb to great height or span between
very tall structures (e.g. bridge towers), or tional work spaces (elevated or suspended),
provide access to very steep slope. for the support of long-span reinforced con-
crete structure which is constructed in in-
situ manner, support for a working platform
over an open -cut basement excavation pit,
or as support to freshly concreted structure
preparing for the temporary placing of addi-
tional loadings etc.
earth-work, where access
conveyor problem for
systems, both delivery
cranes, of the machine
launching or the removal
equipment, of excavated
portal frame, spoil away
hydraulic from the work
Photo 8 – The construction trolley or jack spot always
of a 1.2 km-long temporary systems etc. exist. They will
ramp above sea surface to Sometimes, be stationed in
facilitate the construction of such provi- one location
the bridge piers for an sions may even within a short
elevated expressway.. include the period and
setting up of required to be
temporary Photo 10 – Typical removed at the
unloading falsework arrangement earliest time
facilities such erected for the support of when the work
as a pier for a pier head for the has been
marine works construction of a section completed for
or for the of viaduct. Note that part the onward
delivery of of the system is erected progress of the
large and over a sec-tion of water other works.
heavy channel.
materials
transported to
site by sea. (iv) Site layout
And of course, and equipments
Photo 9 – Provision of a an appropriate for large scale
ac-cess routing earthworks, site
steel ramp from the portal
should also be formation or
area down into a tunnel provided for foundation
constructed using drill-and- the working works. A large
blast method. and handling number of very
of these large work
(ii) Equipments machines such
equipments.
and provisions as excavating
for the trans- (iii) Falsework
system for machines,
portation and graders, rock
lifting of bulky various
purposes such crushing
or very heavy machines,
materials such as support for
dumper trucks,
as excavated temporary
conveyor
spoil materials, work plat-form
system, drilling
structural steel, for machine equip-ments,
precast or stationing, for piling rack or
semi- material foundation
completed handling and equip-ments for
components. storage, large diameter
These materials provision of piles are
sometimes can addi- involved in
weigh up to these kind of
hundreds of projects. These
tons. The in- equipments are
volved often required
equipments, for to work in
example, can difficult typo-
be various graphic
types of work condition
machines for
Photo 11 – The use of large-sized foundation machine such Photo 13 – Erection of a launching gantry in a highway pro-
2
as the Reverse Circulation Drill to form large diame-ter ject which took 2 months and a 3000 m work area for the
bored pile occupies a large operation space including areas completion of the works.
for the working of the associated equipments.

Photo 14 – Installation of a medium-sized tunnel boring


Photo 12 – Large-scale site formation project often involed
machine at the portal of a tunnel. The portal at a later stage
a number of heavy equipments such as dumper trucks,
will serve also as an depot and materials handling area, as
excavating, drilling or crushing machines. It may take
well as an important transport route to support the tunnleing
years to complete and a realistic site layout planning is
works.
important for this kind of project.
civil work in the
(vi)Provision for built-up area of a
(v) Equipments for diversion works city.
specialized in particular to
construction traffic or other
works such as major services
launching gantry located both
for the con- above or
struction of underground. The
viaduct or involve-ment of
elevated bridges, this kind of works
tunnel boring usually contains a
equipments number of
including the temporary
tunnel boring provisions such
machine (TBM), as the temporary
traveling closure of some
formwork existing fa-
systems or cilities, providing
equipments for of the temporary
ten-sioning works replac-ing
etc. These facilities,
equipments have coordinate with
a lot of common the related agents
features. They are for the diversion
usually very large works,
sized and in very controlling and
heavy weight. monitoring of the
They require very facilities
long time and throughout the
large working process, or to
space to erect, reinstate the items
place to the re- to meet the future
quired location to conditions etc.
commence work, The said
or re-quire diversion works
additional may be carried
equipments to out on ground
erect them or sur-face,
when they are to underground or
be dismantled. even over water.
Typical examples
such as the
diversion of box-
culvert (large
-size underground
water discharge
system) in
reclamation
projects, or to
construct a
section of railway
tunnel under
existing busy
road surface, can
be of-ten found in
A. Require additional time in the setting up, mainte-
nance, relocating and dismantling the facilities,
as well as the touching up of the related areas af-
ter their removal.
Some equipments may need a very long time to
have it set up, tuned, tested and commissioned
before it can be put into actual operation. Routine
maintenance is also essential to ensure they can
work effectively and safely. Sophisticated access
provision is also required for the placing or final
removing of the equipments that may introduce
large amount of additional cost input. Typical
situation can be found in, for examples, tunneling
project using TBM, construction of elevated
Photo 15 – Construction of a section of elevated bridge bridges using precast segments erected by launch-
using precast box-girder within a busy highway network ing gantry, or the hoisting of extremely large and
in which complicated traffic diversion arranged in vari- heavy prefabricated component like sections of
ous phases were required. long-span trusses onto the roof

Photo 16 – An extremely complication diversion ar-


rangement for a large storm water discharge in newly Photo 17 – Erection of an 8.5m diameter tunnel bor-
reclaimed area. Tunnel tube for a new railway line will ing machine inside a 60m x 200m x 25m deep tunnel
be constructed under the new discharge culvert system.. portal. The tunnel machine will be dismantled after
the completion of the tunnel drilling at an access shaft
which is about 1.8 km away from the portal.
3 CONCERNS AND RELATIONSHIP OF SITE
LAYOUT, CONSTRUCTION FACILITIES .
AND CONSTRUCTION PLANNING B. Require additional resources and handling ar-
rangement in the setting up of the site layout fa-
From the contractual point of view, site layout facili- cilities, equipments or other associated works.
ties and other construction related logistic support is Besides requiring a long period of time to set and
very difficult to be accurately predicted or priced be- erect, some layout facilities need much additional
fore the commencement of a project. However, the equipments or facilities to have them set up. Ex-
reasonable catering and costing allowance of such amples such as the forming of a series of large di-
work items will practically dominate the success or ameter bored piles for marine works, in which
profitability of a project. Construction planning in temporary access ramp up to a few hundred me-
reality can hardly be worked out using any pro- ters long and supported on temporary marine
gramming software not because of the imperfection piles and steel deck, has to be provided for the
of these tools. The unpredictability mainly comes purpose.
from the highly dynamic situation, existence of nu-
merous work variables as well as the involvement of C. Require additional working space for the smooth
complicated human factors in such project. Summa- operation of the installed facilities.
rized in below are some of the common scenarios Projects such as large-scale site formation, slope,
that show these concerns and relationship. foundation or tunnel works require huge and so-
phisticated equipments for the carrying out of the
job. Very large working space, sometime on very
difficult ground conditions like on a steep slope, vanced planning and coordination is essential be-
sides of a servicing highway, or areas outside the fore works can be carried out on time.
boundary of the site that belong to other third par- Examples for these works include large and com-
ties, is required for the setting up and operation of plicated precast or prefabricated components, or
the installed facilities. Very often, this addition sophisticated equipments such as a bridge launch-
space can only be provided under very carefully ing gantry or large-diameter tunnel boring ma-
planned and coordinated manner, or even involve chine. Sometimes for building works such as pre-
an application and approval process to various fabricated construction using structural steel or
agents or parties. Sometimes these works may large amount of precast components, production
also affect the normal progress of other major and installation of the curtain wall. These works
work activities that require extra or alternative often require a long lead time in the design, sub-
planning to coordinate them with the basic works contracting, internal decision, prefabrication,
within the scope of the contract. quality control, testing and commission, coordi-
nation (including approval) and transportation of
the items before they can be delivered to site for
the actual operation.
particular for civil
engineering projects.
Whether the equip-
ments are to be
transferred from a
soon complet-ing
project, to buy a new
one, to hire them
from other available
sources or to be
provided by a sub-
Photo 18 – A temporary contractor, is a
service shaft formed in matter of resource
the mid-way of a 3.5km- planning
long tunnel as emergency consideration that Photo 19 – Immersed tubes
access as well as for the may affect the for a harbor crossing tunnel
transportation of working
master planning and were constructed in a dry-
profitability of the dock which takes 4 months
plants and materials.
project. to complete. The process
F. Some components of repeated 3 times to provide
D. The provisions of work or construction 12 tubes for the final tunnel
many of the site opera-tions may alignment. .The completed
layout facilities are require a very long tubes would then be towed
having complicated to the tunnel position for
lead time that ad-
cost implication. sinking into the pre-
dredged seabed.
This is obvious for
Contingency plan to cater
the additional input
for any accident happen
in the provision of
during the entire work
the required facilities
process was an impression
usually involve
issue for the project.
expensive
equipments, cost of
installation, main- G. Construction works
tenance and removal are carried out in
cost, or the various phases
participation of sub- according to the
contractors and other construction
managerial input. planning or other
Care-ful cost
constraints of site.
estimate and analysis
in appropriate stages Large- sized projects
can in most cases often cannot carry
help to minimize the out the whole
cost effect of such contract works at the
extra work to a same time due to the
reasonable and con- very large scale of
trollable level. works as well as
other con-straints
E. Very expensive such as
equipments may be considerations in the
involved that very supply of re-sources,
careful resource limited access; or
planning should be even forming part of
intro-duced. the master planning
Expensive to provide additional
equipments are often work fronts to allow
required for the major activities to be
carrying out of done in par-allel.
specific works in
project and should be considered carefully in the
overall master programme well in advance.
progress of the main that make the
structure. situation even com-
plicated.
H. Sometimes the J. Possible occurrence
construction plan of unforeseeable risks.
may require part of Numerous variable
the structures to be factors co-exist with
completed in an ad- large-size and
Photo 20 – A commercial vanced or deferred complicated
development project manner for various construction projects.
located in congested purposes, such as to One common
built-up area with a 4- provide working characteristic is that
level basement. To make space for the moving these projects often
in or removal of Photo 22 –An 15m slot on involve a great
the construction more
large-sized machines the main structure of the number of work
time-effective, the
basement was sub-
or compo-nents, to Hong Kong Convention parties both in-house
divided into 2 phases with
provide access for and Exhibition Centre was or within the
the first phase on the
the operation of cast in a de-layed stage to contract. Sometimes
some major allow for the moving in of the ex-tent of works
office tower side. The
construction a series of 80m-long may even extend
remaining phase will be
activities that works prefabricated roof truss across countries (e.g.
done at the same time
in paral-lel with the sections. Note also the prefabricate a 400-
with the construction of
main structure, or to tempo-rary loading pier on ton steel roof truss in
the 42-storey office
allow some de-layed the seawall for the delivery Philippine and send
tower.
or second- fix works of the truss sections. it to China for final
to catch up. This touch-up and
kind of arrangement I. Sometimes a site may transport back to
may seriously affect be handed over to Hong Kong for
a pre-arranged site contrac-tor to assembly). The
layout plan or master commence work in occurrence of risk is
planning of a separated stages or not so uncommon for
re-quired to the unimaginable
complete the works involvement of huge
in various phases for amount of variable
factors. These factors
handing back to the
leading to risks may
client.
come from
Under this kind of contractual,
project situation, managerial or sub-
beside the re-source contractors matters;
planning or engineering,
contractual technical, finan-cial,
consideration is-sues, resources issues; the
alternative or occurrence of work
teething arrangement ac-cidents, or even
in the site layout and come from other
the related provisions natural or social
Photo 21 – Owing to the will obvi-ously be matters such as
locating of shallow much complicated extreme inclement
rock-head on one side of and sometimes may weather, in-dustrial
site, the construction of affect the overall strike or other human
this semi-basement for a planning of the errors. To minimize
commercial complex construction. In the loss coming from
introduced an addi- some extreme these risks, thorough
tional phase in the circumstances, risk management in
master planning another main con- all aspects and a
program (left portion in tractor may also be feasible reaction
photo) to avoid working at the same
interruption to the time within the site
plan should be made practically in the early stage E. Input sufficient manpower for the control and
of the project. management of all works. A good and workable
master plan does not work alone without the pro-
K. Encountering of significant technical or engi- viding of sufficient manpower. The reason is sim-
neering difficulties ple for the carrying out of the construction works,
in particular for those highly dynamic and sophis-
In some project situations in particular those in- ticated activities like the site layout provisions
volve geo -technical elements such as slope work, and all other major production activities, it re-
basement construction or even some marine quires a great number of frontline staff to super-
works, although stringent investigation has been vise, monitor, participate and coordinate in order
carried out before hand, very difficult technical or to have the works being done properly.
engineering problems may still appear during the
course of work. The appearance of such problem F. Develop an effective and high quality manage-
may have very short notice time and require a ment system. In a general sense, management in-
great number of additional resources or planning volves five fundamental elements including or-
input to have them rectified. And of course, the ganization, planning, coordination, control and
site layout and other relevant provisions will be decision. These elements are universal for all
greatly interrupted when such situations occur. kinds of construction works. The reasons and phi-
losophy how a good management system brings
to site layout planning and the related construc-
4 SOLUTIONS TO ENSURE THE EFFECTIVE tion work implementation is understandable.
RUNNING OF A PROJECT G. Careful monitoring of all the significant works
including both the frontline activities, communi-
There is no single and right-away solution to solve cation and contractual matter. Monitoring of work
difficult or multi-issue problems. Effective solutions is an assurance to make works being carried out
depend on a number of things (including luck and in the as-planned manner as well as to avoid the
fortune). Highlight in below are some factors that possible occurrence of unpredictable risk dur-ing
almost a thumb-rule leading to successful site prac- the course of work. Monitoring of work should be
tice. done in the right time, achieve the right
A. Master planning should be done in well advance observation, made the correct judgment and be
covering the detail construction plan, method able to initiate the appropriate response action.
statements, work scheduling, resources planning This is particularly important for highly dynamic
or budgeting factors. In the information technol- construction works.
ogy age, such planning can be very sophisticated
that sometimes involved a huge amount of data
collection, statistical analysis, laboratory works, 5 CONCLUSION
computer modeling, alternative design or the
alike. Inaccurate planning may result to the gen- Experience tells the industry that there is no fix rule
or extremely powerful software in the planning of
eration of more variables and risks.
site layout, construction operations and the related
B. Provide adequate provisions for all aspects of issues. There are only basic principles. There are
work within the contract budget for the support of numerous options, alternative schemes, action
the project. A well interest-balance between the agenda, management strategy or contingency plans
cost controller and the frontline executives should to meet the actual requirements before or during the
be maintained at all time. This is not easy to course of a construction project. How to make the
achieve for the provision for most of the site lay- correct observation, identify the problems and arrive
out facilities or production equipments are fairly at the right decision is the main key to achieve the
expensive. best solution. A well- experienced and practical con-
C. Ensure detail understanding and produce a high- struction executive or work team supported by a rea-
sonable resources and management back up should
quality construction plan for the project based on
be the best solution to all problems. This paper
contract specification, drawing details and other serves only to highlight some of the related factors
contract documents. with simple case examples so that the complication
D. Develop closer communication means between or uncountable variables and options in the running
various contract parties and all nominated sub- of large-size construction projects may be better
contractors or in-house sub-contractors to ensure comprehended.
work can be carried out swiftly, correctly and in a
harmony manner without absolute conflict and
misunderstanding.

Вам также может понравиться