Special Transport Algorithms for


Road Network Analysis

Shortest path analysis


Minimum spanning tree

Minimal Spanning Tree Problem


Example: The Municipal planner would like to make sure that all barangays of his
town are connected with good roads, since some barangays have multiple road
connections and because of limited budget for maintenance, determine the least
possible way (in km) of connecting all these barangays. The values connecting the
towns are in kilometers.

Barangays
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

Simple Method: Connect adjacent nodes with the least distance, no cycle
allowed

1
11/4/2013

Let G denote the links in the minimal spanning tree

1st Iteration: G = {(1,3)}


Minimum distance = 1 km

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

2nd Iteration: G = {(1,3), (3,4)}


Minimum distance = (1 + 2) = 3 km

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

2
11/4/2013

3rd Iteration: G = {(1,3), (3,4), (4,6)}


Minimum distance = (1 + 2 + 3) = 6 km

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

4th Iteration: G = {(1,3), (3,4), (4,6), (5,6)}


Minimum distance = (1 + 2 + 3 + 3) = 9 km

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

3
11/4/2013

5th Iteration: G = {(1,3), (3,4), (4,6), (5,6), (2,3)}


Minimum distance = (1 + 2 + 3 + 3 + 4) = 13 km

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

6th Iteration: G = {(1,3), (3,4), (4,6), (5,6), (2,3), (5,7)}


Minimum distance = (1 + 2 + 3 + 3 + 4 + 4) = 17 km

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

4
11/4/2013

7th Iteration: G = {(1,3), (3,4), (4,6), (5,6), (2,3), (5,7), (7,8)}


Minimum distance = (1 + 2 + 3 + 3 + 4 + 4 + 5) = 22 km

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

Minimal Spanning Tree Problem


Summary of results:
1. The final minimal spanning tree is as shown below. Its length is equal to (1 + 4 + 2 +
3 + 3 + 4 + 5 ) 22 kms
2. The difference between the minimal spanning tree problem and the shortest route
problem is that the latter is based from a source node and all the other nodes are
linked to it in the shortest possible way.
3. While the minimal spanning tree problem connects one node to another node the
minimal way without regard to any source node.

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

5
11/4/2013

ASSIGNMENT

Problem: For the road


network of Guimaras as
1 Jordan shown, apply the minimal
spanning tree method by
connecting all important
locations in Guimaras to the
provincial capital Jordan.

5.9 13
2.1
12 4.9
11 2.7 10
3.7 3.3 14
9 1.6
4.4 8 6.2
3.1 6.0
6 1.2
7 15
2.5 6.0 16
5 4.6 3.8
2.8 3.3

1 Jordan 1 Jordan
2.0 3.4 12.4
3 2 17

5.1 10.2
4 8.9 10.0

3.1
31 32 18 4.0
3.0
3.8 19
2.5 30
28 8.3
29 3.4 4.4
8.2
27 2.4 3.3

3.5 26 2.0 22 3.0


2.4 23 2.9 21 20
25 1.0

4.9 5.0

24
Note: Values are in km

6
11/4/2013

Link Estimated Link Estimated


Distance (km) Distance (km) MINIMAL SPANNING TREE
1-2 3.4 16-17 3.3
(Jordan as Center Node)
1-5 2.8 17-19 10.0 5.9
2.1 13
1-17 12.4 18-19 4.0 12 4.9
11 2.7 10
1-18 10.2 18-21 8.3 3.7 3.3 14
9 1.6
1-32 8.9 19-20 8.2 4.4 8 6.2
3.1 6.0
2-3 2.0 20-21 1.0 6 1.2
7 15
2.5 6.0 16
2-4 5.1 21-22 3.0
5 4.6 3.8
5-6 2.5 22-23 2.9 2.8 3.3
1 Jordan
3.4 12.4
2.0
5-7 4.6 22-28 4.4 3 2 17
6-8 4.4 23-24 5.0 5.1 10.2
7-8 1.2 23-26 2.0
4 8.9 10.0
7-9 3.1 26-28 3.3
7-15 6.0 24-25 4.9 3.1
31 32 18 4.0
3.0
8-11 3.7 25-26 2.4 3.8 19
9-10 1.6 25-27 3.5 2.5 30
28 8.3
9-11 3.3 26-27 2.4 29 3.4 4.4
8.2
10-12 2.7 26-28 3.3 27 2.4 3.3
11-12 2.1 28-32 3.8 26 2.0 3.0
3.5 22
12-13 5.9 27-30 3.4 2.4 23 2.9 21 20
25 1.0
13-14 4.9 29-30 2.5
14-15 6.2 30-31 3.0 4.9 5.0

14-16 6.0 31-32 3.1 24


Note: Values are in km
15-16 3.8

Link Estimated Link Estimated


Distance (km) Distance (km) MINIMAL SPANNING TREE
1-2 3.4 16-17 3.3 (Buenavista as Center Node)
1-5 2.8 17-19 10.0 5.9
2.1 13
1-17 12.4 18-19 4.0 12 4.9
11 2.7 10
1-18 10.2 18-21 8.3 3.7 3.3 14
9 1.6
1-32 8.9 19-20 8.2 4.4 8 6.2
3.1 6.0
2-3 2.0 20-21 1.0 6 1.2
7 15
2.5 6.0 16
2-4 5.1 21-22 3.0
5 4.6 Buenavista3.8
5-6 2.5 22-23 2.9 2.8 3.3
2.0 3.4 12.4
5-7 4.6 22-28 4.4 3 2 1 17
6-8 4.4 23-24 5.0 5.1 10.2
7-8 1.2 23-26 2.0
4 8.9 10.0
7-9 3.1 26-28 3.3
7-15 6.0 24-25 4.9 3.1
31 32 18 4.0
3.0
8-11 3.7 25-26 2.4 3.8 19
9-10 1.6 25-27 3.5 2.5 30
28 8.3
9-11 3.3 26-27 2.4 29 3.4 4.4
8.2
10-12 2.7 26-28 3.3 27 2.4 3.3

11-12 2.1 28-32 3.8 3.5 26 2.0 22 3.0


12-13 5.9 27-30 3.4 2.4 23 2.9 21 20
25 1.0
13-14 4.9 29-30 2.5
14-15 6.2 30-31 3.0 4.9 5.0

14-16 6.0 31-32 3.1 24


Note: Values are in km
15-16 3.8

7
11/4/2013

Shortest Path Method


Example: The municipal planning engineer would like to identify the shortest path
coming from all the 7 barangays of the municipality going to the municipal center
and vice-versa. The roads along these shortest paths will be made into all-weather
roads to make them passable all year round. The values along the links are in
kilometers.

Barangays
2

5 4 4
10 5 7
Municipal
Center 1 3 5
1 3 9
2 9
7 8 8
4 6
3

Method of Analysis: Dijkstra’s Algorithm

Solution:
This is a shortest-route problem which can be solved using the Dijkstra’s Algorithm.

1st Iteration:
Nodes 1 2 3 4 5 6 7 8
L(1) 0 5 1 7 ∞ ∞ ∞ ∞
(km)
*
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

8
11/4/2013

2nd Iteration:

Nodes 1 2 3 4 5 6 7 8
L(2) 0 5 1 7 ∞ ∞ ∞ ∞
(km)
* *
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

3rd Iteration:

Nodes 1 2 3 4 5 6 7 8
L(3) 0 5 1 3 11 10 ∞ ∞
(km)
* * *
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

9
11/4/2013

4th Iteration:

Nodes 1 2 3 4 5 6 7 8
L(2) 0 5 1 3 11 6 ∞ ∞
(km)
* * * *
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

5th Iteration:

Nodes 1 2 3 4 5 6 7 8
L(2) 0 5 1 3 11 6 ∞ ∞
(km)
* * * * *
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

10
11/4/2013

6th Iteration:

Nodes 1 2 3 4 5 6 7 8
L(6) 0 5 1 3 9 6 15 14
(km)
* * * * * *
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

7th Iteration:

Nodes 1 2 3 4 5 6 7 8
L(6) 0 5 1 3 9 6 13 14
(km)
* * * * * * *
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

11
11/4/2013

8th Iteration:

Nodes 1 2 3 4 5 6 7 8
L(6) 0 5 1 3 9 6 13 14
(km)
* * * * * * * *

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

Shortest Path Method


Summary of observation:
1. Road segments 1-3, 3-2, 3-4, 4-6, 6-5, 5-7, and 6-8 are roads to be
converted to all-weather roads.
2. Therefore, shortest paths from the municipality (Node 1) to each
barangays are the ff:
Brgy 1 to Brgy 2: 5 km
Brgy 1 to Brgy 3: 1 km
Brgy 1 to Brgy 4: 3 km
Brgy 1 to Brgy 5: 9 km
Brgy 1 to Brgy 6: 6 km
Brgy 1 to Brgy 7: 13 km
Brgy 1 to Brgy 8: 14 km
2

5 4 4
10 5 7
1 3 5
1 3 9
2 9
7 8 8
4 6
3

12
11/4/2013

ASSIGNMENT

Problem: For the road


network of Guimaras as
1 Jordan shown, apply the shortest
path method by connecting
all important locations in
Guimaras to the provincial
capital Jordan.

5.9 13
2.1
12 4.9
11 2.7 10
3.7 3.3 14
9 1.6
4.4 8 6.2
3.1 6.0
6 1.2
7 15
2.5 6.0 16
5 4.6 3.8
2.8 3.3

1 Jordan 1 Jordan
2.0 3.4 12.4
3 2 17

5.1 10.2
4 8.9 10.0

3.1
31 32 18 4.0
3.0
3.8 19
2.5 30
28 8.3
29 3.4 4.4
8.2
27 2.4 3.3

3.5 26 2.0 22 3.0


2.4 23 2.9 21 20
25 1.0

4.9 5.0

24
Note: Values are in km

13
11/4/2013

Link Estimated Link Estimated


Distance (km) Distance (km) SHORTEST PATH METHOD
1-2 3.4 16-17 3.3
(Jordan as Center Node)
1-5 2.8 17-19 10.0 5.9
2.1 13
1-17 12.4 18-19 4.0 12 4.9
11 2.7 10
1-18 10.2 18-21 8.3 3.7 3.3 14
9 1.6
1-32 8.9 19-20 8.2 4.4 8 6.2
3.1 6.0
2-3 2.0 20-21 1.0 6 1.2
7 15
2.5 6.0 16
2-4 5.1 21-22 3.0
5 4.6 3.8
5-6 2.5 22-23 2.9 2.8 3.3
1 Jordan
3.4 12.4
2.0
5-7 4.6 22-28 4.4 3 2 17
6-8 4.4 23-24 5.0 5.1 10.2
7-8 1.2 23-26 2.0
4 8.9 10.0
7-9 3.1 26-28 3.3
7-15 6.0 24-25 4.9 3.1
31 32 18 4.0
3.0
8-11 3.7 25-26 2.4 3.8 19
9-10 1.6 25-27 3.5 2.5 30
28 8.3
9-11 3.3 26-27 2.4 29 3.4 4.4
8.2
10-12 2.7 26-28 3.3 27 2.4 3.3
11-12 2.1 28-32 3.8 26 2.0 3.0
3.5 22
12-13 5.9 27-30 3.4 2.4 23 2.9 21 20
25 1.0
13-14 4.9 29-30 2.5
14-15 6.2 30-31 3.0 4.9 5.0

14-16 6.0 31-32 3.1 24


Note: Values are in km
15-16 3.8

Link Estimated Link Estimated


Distance (km) Distance (km) SHORTEST PATH METHOD
1-2 3.4 16-17 3.3 (Buenavista as Center Node)
1-5 2.8 17-19 10.0 5.9
2.1 13
1-17 12.4 18-19 4.0 12 4.9
11 2.7 10
1-18 10.2 18-21 8.3 3.7 3.3 14
9 1.6
1-32 8.9 19-20 8.2 4.4 8 6.2
3.1 6.0
2-3 2.0 20-21 1.0 6 1.2
7 15
2.5 6.0 16
2-4 5.1 21-22 3.0
5 4.6 Buenavista3.8
5-6 2.5 22-23 2.9 2.8 3.3
2.0 3.4 12.4
5-7 4.6 22-28 4.4 3 2 1 17
6-8 4.4 23-24 5.0 5.1 10.2
7-8 1.2 23-26 2.0
4 8.9 10.0
7-9 3.1 26-28 3.3
7-15 6.0 24-25 4.9 3.1
31 32 18 4.0
3.0
8-11 3.7 25-26 2.4 3.8 19
9-10 1.6 25-27 3.5 2.5 30
28 8.3
9-11 3.3 26-27 2.4 29 3.4 4.4
8.2
10-12 2.7 26-28 3.3 27 2.4 3.3

11-12 2.1 28-32 3.8 3.5 26 2.0 22 3.0


12-13 5.9 27-30 3.4 2.4 23 2.9 21 20
25 1.0
13-14 4.9 29-30 2.5
14-15 6.2 30-31 3.0 4.9 5.0

14-16 6.0 31-32 3.1 24


Note: Values are in km
15-16 3.8

14
11/4/2013

Application to Actual Road Network

Siquijor Provincial Hospital

Lazi Community
Hospital

Shortest Path to the Hospitals, Siquijor Island Province

Missing
road link

Base case: Complete road Scenario 1: One road link


network missing

2 Missing
road links

Scenario 2: Two road links


missing

15
11/4/2013

Estimated Market Threshold of Public Markets/Talipapa, Siquijor Island


- Shortest path (distance) method

Example: Find the following: (a) the minimal spanning tree and (b) the
shortest path from Zone A to Zone D and also from Zone B to Zone C.

16
11/4/2013

SEATWORK: 20 pts, ½ sheet


For the network shown, find (a) the minimal spanning tree, and (b)
the shortest route from Node 1 to Node 8. The link values (cost) are
in km.
4
3 6
2
2 1 3

1 2 5 6 5
8
1
3 6
1 2 7

2 5 4 7
8

END

17