Академический Документы
Профессиональный Документы
Культура Документы
arch April May June July August September October November December January February Marc
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10
1 L&T LOI. No. : MEGP LSTK1-STA-KPR-0006A _ Sat 30-03-19 Wed 26-02-20
PE.Wo.No-1657 Gas Gas Heat Exchanger Rod
2 061-E-111 Sat 30-03-19 Wed 26-02-20
3 ENGINEERING: Sat 30-03-19 Thu 13-06-19
4 Design & Drawing submission Sat 30-03-19 Sat 27-04-19
5 Drawing approval Mon 29-04-19 Wed 15-05-19
6 TDC Release Sat 30-03-19 Sat 27-04-19
7 Submissions of ITP & NDT Procedures Mon 29-04-19 Mon 27-05-19
8 Approval of ITP & NDT Procedures Tue 28-05-19 Thu 13-06-19
9 RAW MATERIALS PROCUREMENT: Sat 30-03-19 Wed 15-01-20
10 Purchase Order for major raw materials Sat 30-03-19 Wed 19-06-19
11 SS Plates Receipt Mon 03-06-19 Sat 10-08-19
12 ANSI Receipt Thu 16-05-19 Wed 28-08-19
13 Pipes Thu 16-05-19 Wed 28-08-19
14 SRN Thu 16-05-19 Wed 02-10-19
15 Tube Sheet Receipt Thu 16-05-19 Wed 02-10-19
16 Tubes Receipt Thu 16-05-19 Mon 14-10-19
17 Gasket and Fasteners Thu 20-06-19 Wed 15-01-20
18 welding consumble Fri 14-06-19 Fri 23-08-19
19 MANUFACTURING: Fri 23-08-19 Wed 26-02-20
20 Preparation Fri 23-08-19 Thu 26-09-19
21 Shell Fabrication Thu 03-10-19 Mon 18-11-19
22 Bundle Fabrication Tue 15-10-19 Thu 05-12-19
23 Shell & Bundle Assmbly Fri 06-12-19 Mon 27-01-20
24 Testing Tue 28-01-20 Fri 07-02-20
25 Surface preparation/Painting Sat 08-02-20 Wed 19-02-20
26 Packing and Dispatch Thu 20-02-20 Wed 26-02-20
27
28 L&T LOI. No. : MEGP LSTK1-STA-KPR-0006B _ Sat 30-03-19 Thu 30-01-20
PE.Wo.No-1658 LAS Heat Exchangers
29 060-E-108 & 060-E-110 Sat 30-03-19 Thu 30-01-20
30 ENGINEERING: Sat 30-03-19 Thu 13-06-19
31 Design & Drawing submission Sat 30-03-19 Sat 27-04-19
32 Drawing approval Mon 29-04-19 Wed 15-05-19
33 TDC Release Sat 30-03-19 Sat 27-04-19
34 Submissions of ITP & NDT Procedures Mon 29-04-19 Mon 27-05-19
35 Approval of ITP & NDT Procedures Tue 28-05-19 Thu 13-06-19
36 RAW MATERIALS PROCUREMENT: Sat 30-03-19 Mon 18-11-19
37 Purchase Order for major raw materials Sat 30-03-19 Wed 19-06-19
38 CS Plates Receipt Mon 03-06-19 Sat 14-09-19
39 LAS Plates Receipt Mon 03-06-19 Sat 14-09-19
40 ANSI Receipt Thu 16-05-19 Wed 02-10-19
41 Pipes Thu 16-05-19 Wed 02-10-19
42 Non Standard Flange Thu 16-05-19 Wed 02-10-19
43 Tube Sheet Receipt Thu 16-05-19 Wed 02-10-19
44 Tubes Receipt Thu 16-05-19 Mon 18-11-19
45 Gasket and Fasteners Thu 16-05-19 Tue 03-09-19
46 welding consumble Mon 08-07-19 Mon 16-09-19
47 Purchase ordering Completion Mon 29-04-19 Wed 11-09-19
48 MANUFACTURING: Mon 16-09-19 Thu 30-01-20
49 Dish forming Mon 16-09-19 Sat 23-11-19
50 Preparation Mon 16-09-19 Mon 14-10-19
51 Shell & Channel Fabrication Tue 15-10-19 Mon 23-12-19
52 Bundle Fabrication Tue 19-11-19 Mon 23-12-19
53 Assembly & Testing Tue 24-12-19 Thu 09-01-20
54 Surface preparation/Painting Fri 10-01-20 Mon 20-01-20
55 Packing and Dispatch Tue 21-01-20 Thu 30-01-20