Вы находитесь на странице: 1из 13

See

discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/288835405

IMPROVING THE TRANSIENT STABILITY OF


NIGERIAN 330KV TRANSMISSION NETWORK
USING STATIC VAR COMPENSATION PART I: THE
BASE STUDY

Article · January 2016


DOI: 10.4314/njt.v35i1.23

CITATIONS READS

0 80

3 authors, including:

Raphael Ayodele Ayodeji Samson Ogunjuyigbe


University of Ibadan University of Ibadan
64 PUBLICATIONS 147 CITATIONS 44 PUBLICATIONS 105 CITATIONS

SEE PROFILE SEE PROFILE

All in-text references underlined in blue are linked to publications on ResearchGate, Available from: Raphael Ayodele
letting you access and read them immediately. Retrieved on: 12 October 2016
Nigerian Journal of Technology (NIJOTECH)
Vol. 35, No. 1, January 2016, pp. 155 – 166
Copyright© Faculty of Engineering, University of Nigeria, Nsukka,
Print ISSN: 0331-8443, Electronic ISSN: 2467-8821
www.nijotech.com
http://dx.doi.org/10.4314/njt.v35i1.23

IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV


TRANSMISSION NETWORK USING STATIC VAR COMPENSATION PART I:
THE BASE STUDY

T. R. Ayodele1, A. S. O Ogunjuyigbe2,*, O. O. Oladele3


1, 2, 3 POWER, ENERGY, MACHINES AND DRIVES (PEMD) RESEARCH GROUP, DEPARTMENT OF ELECTRICAL AND ELECTRONIC

ENGINEERING, UNIVERSITY OF IBADAN, OYO STATE. NIGERIA


E-mail addresses: 1 tr.ayodele@ui.edu.ng, 2 a.ogunjuyigbe@ui.edu.ng, 3 d1excels@yahoo.com

ABSTRACT
In this paper, the base study for improving the transient stability of Nigerian 330kV transmission network using
Static Var Compensation (SVC) is conducted with the focus of developing indices that can appropriately size and
locate SVC within the network. The study is performed using commercially available software Dig SILENT Power
Factory. The overloaded lines which could excite instability in the network are identified. Fixed capacitor thyristor
controlled reactor is used to model the SVC and is appropriately sized and located within the network. Transient
stability of the network is analysed by determining the critical
critical clearing time of the acute generators when a
balanced three phase fault is applied to the middle of the critical lines within the network using step- step-by step
technique. Some of the key results reveal that the lines: Jebba-
Jebba- Osogbo, Shiroro-
Shiroro-Kaduna, Benin-
Benin-Sapele and Benin-
Benin-
Onitsha are the critical lines within the network. The Critical Clearing Times (CCTs) of the acute generators when 3-
3-
phase fault is applied at Jebba-
Jebba- Osogbo and Shiroro-
Shiroro-Kaduna transmission lines are 380ms and 480ms, respectively.
However, generators located at Afam and Sapele that are close to Benin- Benin-Sapele and Benin-
Benin-Onitsha transmission
line, respectively are always losing synchronism to 3- 3-phasefault of any duration. Appropriately sized SVCs with
values 124Mvar, 73Mvar, 62Mvar and 110Mvar located at Osogbo, Kaduna and Benin compensated the network
and increase the CCTs to 470ms, 500ms, 220ms and 120ms, respectively.

Keywords:
Keywords Dig SILENT Power Factory, Transient Stability, Static Var Compensation, Nigerian 330kV transmission
line.

1. INTRODUCTION Generally, transient stability is evaluated by the


In recent years, transmission networks are overloaded system Critical Clearing Time (CCT) in response to
and are pushed closer to their stability limits. This is various large disturbance such as faults, loss of large
as a result of increasing demand for electricity due to load, loss of generation and major lines loss [5]. CCT
growing population. This could have negative effect on gives the maximum duration of time a power system
the power system security. The security of a power can remain stable under a given large disturbance
system is regarded as the ability of the network to condition[6]. The robustness of a power system is
withstand disturbances without breaking down [1]. largely determined by its response to the
One of the indices to assess the state of security of a disturbances. A higher value of CCT denotes a robust
power system is the transient stability [2] and it and better secured system [7].
involves the ability of power system to remain in One of the factors that determine the level of integrity
equilibrium or return to acceptable equilibrium when of a power system (i.e. transmission capability limit
subjected to large disturbances [3]. Various methods and flexibility of power system) is the level of security
of determining the transient instability in power of the network based on transient stability
system includes numerical integration, direct method, assessment[8].Therefore, power system grid integrity
probabilistic method [2] and the artificial intelligent can be enhanced by devising a means of improving
methods such as artificial neural networks [4]. transient stability[9]. The use of Flexible AC

234-
234-802-
*Corresponding author, Tel: +234 802-350-
350-4826
IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

Transmission Systems (FACTS) devices have been while the expanded and fortified grid showed a reduce
identified as cost effective means of improving the power losses of 32MW and 24.7MW, respectively.
transient stability without the need for constructing Onohaebi and Igbinovia [20] are concerned with the
new transmission lines [10]. Several FACTS devices assessment of voltage dip of the post expansion
have been proposed for improving the power system network in comparison with the existing Nigeria
operation and they are [11]: the Static Var 330kV network. Their result showed that the
Compensator (SVC), Controllable Series Compensator incorporation of some additional lines to form more
(CSC), Phase Shifter (PS), Series Capacitors (SC), loops would improve the Nigerian 330kV network to
Thyristor Controlled Series Capacitors (TCSC), Unified acceptable voltage limits of ±5% which could have
Power Flow Controller (UPFC), Convertible Series positive influence on the reliability and security of the
Compensator (CSC), Inter-phase Power Flow network. Similarly, Ogunjuyigbe and Awosope [21] are
Controller (IPFC), Static Synchronous Series of the opinion that adequately sized and optimally
Controller (SSSC), STATCOM etc. Of these various located reactor could improve the network voltage
FACTS devices, SVC is found to be effective for profile to the acceptable limit of ±5% . Recently, an
transient stability improvement when appropriately improvement of voltage stability of Nigerian 330kV
sized[12]and is now forming an integral part of network was studied by Mathew et al [22] using SVC.
modern electrical power systems [2]. It is one of the The result showed that, the system’s voltage stability
key devices that exhibit instantaneous response to was improved by about 33.78% indicating a
system changes and are fabricated from solid semi- significant improvement in the system’s voltage
conductor components [13]. SVCs are basically shunt stability when SVCs were applied.
connected and are usually installed at the midpoint of Most of the aforementioned studies are concerned
the transmission line or at the line ends through a with either the expansion/fortification of the existing
coupling transformer[14]. It has the ability of network, the voltage profile improvement or power
improving transient stability by dynamically loss reduction in order to improve the system security
controlling it’s reactive power output [15]. by expanding the existing network. This present paper
Nigeria power system is faced with series of technical aims at investigating the improvement of the transient
challenges due to long, radial, weak and aging stability of the Nigerian 330kV transmission network
transmission network[16]. Different studies have by appropriately sizing and locating SVC within the
been done on Nigerian 330kV transmission network network. In this way the security of the system is
by various indigenous researchers with each improved thereby challenging the need for immediate
researcher focusing on different aspect of construction of new transmission lines. This would
performance assessment with a view to improve the allow time for proper planning for a later upgrade.
network: Technical losses on the 330kV Nigerian The Nigerian network was modelled using
transmission losses has been studied by Anumaka commercially available software Dig SILENT Power
[17]. The mathematical analysis in relation to Nigerian Factory. The overloaded lines which could trigger
power system technical losses was derived. Onojo et al transient instability in the network were identified.
[18] has performed reliability and efficiency The critical clearing time before and after the
assessment of the proposed (post reform) 10,000MW installation of SVC were compared .Results in this
capacity 330kV transmission network and also paper could be useful as initial technical information
determined the extent to which it will provide that could help in the future expansion and operation
solution to the numerous problems that presently planning of the Nigerian 330kV transmission network.
plague the existing power system network. It was Though the size and location of SVCs in this paper was
concluded that construction of new grid will reduce determined using “wheel barrow” approach, the result
losses and improve the reliability and efficiency of the obtained could serve as a base study to develop
network. Similarly, Izuegbunam et al [19] utilized various indices that could aid optimal sizing and
Power World Simulator to compare the proposed post placement of SVCs within the Nigerian power
expansion network with that of the existing 330kV network.
transmission network with a view of estimating the
real and reactive power flows, power losses as well as 2. NIGERIA 330KV TRANSMISSION NETWORK
the bus voltage angle. The simulation result reveals The Nigeria 330kV power system used in this study
that 85.3MW losses occurred in the existing grid, consists of 7 main power stations which cut across the
Nigerian Journal of Technology Vol. 35, No. 1, January 2016 156
IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

country with long radial interconnected lines. The Detailed model in which the transient and sub-
network consists of 5,523.8km of lines with total transient phenomena are considered [3] was used for
installed transformation capacity of 5,687.32 MVA modelling of all synchronous generator within the
(equivalent to 4,832 MW). The transmission network network in rotor reference frame[23]. The mechanical
is depicted in variables are linked with the electrical variables as
follows:
Figure 1. The transmission line and the generator data LMNO ST
are given in Tables 6 and 7 in the appendix. = WX + WZ (1)
PQO PR SU
Identification Buses and the Generators Where J is the inertia, ωn is the angular speed, pz is the
BusNo Name BusNo Name
pole pair number, Tm and Te are the mechanical and
1 B/Kebbi 20 Ikeja-West
electromagnetic torques of the machine. The
2 Kainji 21 Akangba
3 Jebba 22 Egbin normalized per unit inertia (H) of the generator and
4 Kainji TS 23 Egbin TS the turbine is expressed as inertia time constant given
5 Jebba TS 24 Aja in equation (2)
6 Jebba TS 25 Sapele TS 1 LM\O
[= (2)
7 Osogbo 26 Aladja 2 PQO PR
8 Shiroro 27 Delta TS where ω0 is the synchronous speed.
9 Shiroro TS 28 Afam TS
The electromagnetic torque expressed in terms of the
10 Kaduna 28 Afam
stator flux and stator current is given as:
11 Ajaokuta 30 Delta
12 Kano 31 Sapele
WZ ]^ _` − ]` _^ (3)
13 Jos G1 Kainji Generator whereψ d and ψ q are stator fluxes.
14 Gombe G2 Jebba Generator
15 Benin G3 Egbin Generator 3.2 Power System Model and Load Flow Study
16 Onitsha G4 Shiroro Generator
Electric power network are modelled by sets of non-
17 New Haven G5 Delta Generator
linear equations that describe the state of the power
18 Ayede G6 Sapele Generator
system[24]. The model requires that the real power
19 Alaoji G7 Afam Generator
and bus voltages of the generators within the network
be specified [25]. This is because it is convenient to
specify real power for all generators and to use the
generator bus voltage instead of reactive power [26].
Load flow study is performed on the network model to
solve the non-linear algebraic equations. This allows
the determination of the bus voltages magnitude, its
corresponding angle as well as power flows for
specified generation and bus conditions [27]. There
are several algorithms for performing load flow
analysis[28]. However, Newton-Raphson technique is
adopted in this study because; it is faster and
converges in most cases compared to the other
methods. Although, it requires large computer
memory, but can be overcome through a compact
storage scheme [29].
For an ‘n’ buses, the admittance matrix of the network
Figure 1: Nigeria 31 bus, 7 Generator, 330kV can be written as:
Transmission System as at 2006 gh lhh lhO lhN mh
fg k f l l l kfm k
e O j e Oh OO ON
je Oj
3. THE MODEL APPROACH e.j=e . . . je . j
(4)
3.1 Synchronous Generator Model e.j e . . . je . j
e.j e . . . je . j
dgN i d. lNh lNO lNN i d. mN i

Nigerian Journal of Technology Vol. 35, No. 1, January 2016 157


IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

where I (.) is the current flow within the network, V(.)


Table 1: Summary result of the Steady State analysis
is the bus voltages and Y(i, j) is the bus admittance
Active
Reactive Apparent
between buses i and j within the network. The active Power
Power(MVar) Power(MVA)
and reactive powers injected into each bus can be (MW)
derived as (5) and (6) Generation 4737.17 3147.20 5687.32
N Grid Losses 15.67 -86.70
Line
Pn = o|mn ||mq | |Yst |cos(unq − vq ) (5) -362.45
Charging
qrh
N Installed
4832.00
Capacity
wn = − o|mn ||mq | |Yst |sin(unq − vq ) (6)
Spinning
qrh 94.83
Reserve
Where Vi is voltage magnitude at bus i, θ i is bus I
voltage angle, δ ik is admittance angle while Yik is the
admittance linking bus i to k Table 2: Steady State busbar voltages and angles
The voltage magnitude and its angle are calculated VOLTAGE
BUS BUS
MAGNITUDE PHASE ANGLE
iteratively using Newton-Raphson’s procedure NUMBER NAME
(p.u) (deg.)
following the determination of Pi and Qi in (5) and
1 B/Kebbi 0.96 -5.71
(6).It is indicative that both the real and reactive 2 Kainji 1.02 -0.89
powers are functions of (|m|, v); 3 Jebba 1.01 -1.03
∆v L L rh ∆P 4 Kainji GS 1.03 0.41
y { = y h O{ y { (7)
∆|m| L| L} ∆w 5 Jebba GS 1.03 0.28
whereJ1, J2, J3 and J4are the elements of the Jacobian 6 Jebba TS 1.01 -1.03
7 Osogbo 1.01 -1.30
matrix in equation (7), the variables at the end of each
8 Shiroro 1.01 -1.41
iteration are updated as below: 9 Shiroro GS 1.03 -0.09
(q~h) (q) (q) (q~h)
vn = vn + ∆vn and •mn • = €mnq € + ∆€mnq € for 10 Kaduna 1.00 -1.88
11 Ajaokuta 1.01 -1.84
i=1,2,…n. Solution converges when ∆P and ∆Q are
12 Kano 0.98 -3.37
obtained lower than stipulated tolerance. 13 Jos 0.98 -3.32
The apparent power at each bus is given as: 14 Gombe 0.96 -4.99
‚n = Pn + ƒwn = mn gn (8) 15 Benin 1.01 -1.62
and the bus current is evaluated using: 16 Onitsha 1.00 -3.07
Pn − ƒwn New
17 0.99 -3.34
gn = (9) Haven
mn
18 Aiyede 0.99 -1.83
The summary of the steady state result after 19 Alaoji 1.00 -2.82
performing the load flow of the Nigerian 330kV 20 Ikeja-West 0.99 -1.88
transmission network is depicted in Tables1and 2. 21 Akangba 0.99 -1.87
Table 1 revealed that the total grid loss in the network 22 Egbin 0.99 -1.62
is 15.67MW with a total spinning reserve of 94.83MW. 23 Egbin GS 1.00 0.00
24 Aja 0.99 -1.62
Results from Table 2 showed that the bus voltages are
25 Sapele GS 1.03 -0.59
within ±5% limit indicating no voltage violation 26 Aladja 1.02 -1.32
under the steady state condition. However, the tie 27 Delta GS 1.04 0.02
lines Benin -Onitsha, Jebba-Osogbo, Shiroro- Kaduna 28 Afam GS 1.02 -1.46
and Benin -Sapele are overloaded as depicted in 29 Afam 1.00 -2.80
30 Delta 1.02 -1.27
Figure 2. As such the lines are identified as critical
31 Sapele 1.02 -1.48
lines in this study because it could cause transient
instability in the network in the event of any large
disturbance on any of the lines. In view of the primary
goal of this paper, it will investigate the network
transient stability should a fault occur on any of these
critical lines.

Nigerian Journal of Technology Vol. 35, No. 1, January 2016 158


IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

Figure 2: Nigerian 330kV highlighting overloaded transmission lines

3.3 Transient Stability The parameters M i , Pmi and Ei are assumed to be


Transient stability of Nigerian 330kV network was
constant values. The electrical power of the x-th
carried out using step by step approach based on
stable generator and the y-th critical generator are
evaluation of Critical Clearing Time (CCT). An
derived from (12) as (13) and (14), respectively[31]:
indicator of the system stability is given by the rotor
angle of the machines and the critical clearing time PZ‹ = …‹O Y‹‹ cosu‹‹ + o …‹ …† …‹† cos‰vŽ − v• − u‹† Š
†∈•
(CCT) of the system before losing equilibrium[30].
The rotor angle ( δ i ) of ith generator using the step by + o …‹ …† …‹† cos u‹† (13)
†∈•,†ˆ‹
step procedure for multi-machine system like that of
Nigerian grid can be determined by the following non-
linear differential equations (10-12), [31]. The step by PZ‘ = …‘O Y‘‘ cosu‘‘ + o …‘ …† …‘† cos‰v• − vŽ − u‘† Š
†∈•
step procedure for determining the critical clearing
time of the network is depicted in Figure 3. + o …‘ …† …‘† cos u‘† (14)
Svn †∈•,†ˆ‘
= MR ‘a’ represents a stable generator, ‘s’ represents a
SU
SMR critical generator, and ‘A’ represents group of all other
„n = PXn − PZn ; _ = 1,2 … n (11)
SU generators.
Where
PZn = …nO Yss cosunn 3.4 Modelling of SVC for Transient Stability
N
Improvement
+ o …n …† …n† cos‰vn − v† The SVC used in this paper is a fixed capacitor
†‡h †ˆn
thyristor controlled reactor (FC-TCR) type as depicted
− un† Š (12)
in Figure 4.
δ i is the rotor angle of the generator, M i is the inertia
coefficient, Pei is the electrical power, Pmi is the
mechanical power, Ei is the internal voltage of the
generator, Y is the reduced admittance matrix, Yij is
the ij-th element of the reduced admittance matrix.

Nigerian Journal of Technology Vol. 35, No. 1, January 2016 159


IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

Figure 3: Step-by-step procedure for determining the CCT of the transmission network

g•’“ = g” − g“ (15)
’–—˜ ’–—˜
Where g• = ™˜
; g” = ™š
, and Vsvc is the bus voltage
magnitude.
1 2(ž − •) + sin(2•) ž
but = œ” (•) = ; ≤
›” ž›” 2
≤ž [32]
where α is the gate firing angle and hence

g” = m•’“ × œ” ( ) (16)
Since no active power is taken by the SVC, the reactive
power consumed can be expressed as:
w•’“ = g•’“ × m•’“ (17)
Figure 4: Functional diagram of a FC-TCR where VSVC is the bus voltage,
Substituting (15) into (17), yields the following:
One of the SVC branch is purely capacitive while the
other is inductive. As a result, the SVC consumes no w•’“ = (g” − g“ ) × m•’“ (18)
active power. However, it has the capability of either Substituting (16) into (18) yields:
consuming reactive power through the inductive m•’“
w•’“ = £œ” ( ) − ¤ × m O•’“ (19)
branch (TCR) so as to reduce the system’s voltage or ›•
injecting reactive power into the system through the 1
w•’“ = £œ” ( ) − ¤ × m O•’“ (20)
capacitive branch (FC) in order to increase the voltage. ›•
The reactor current IL is positive, while the capacitor The equivalent susceptance of the SVC ( BSVC ( α ) )
current IC is negative. Thus, SVC current (ISVC) value at can be written as:
maximum var is expressed as follows:
Nigerian Journal of Technology Vol. 35, No. 1, January 2016 160
IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

-1 -0.9
with SVC
-1.05 without SVC
-1

Rotor angle (rad)


Rotor angle (rad)

-1.1
-1.1
-1.15

-1.2 -1.2
-1.25
-1.3
-1.3 without SVC
with SVC
-1.35 -1.4
0 200 400 600 800 1000 0 200 400 600 800 1000
time (ms) Time (ms)
Figure 6: Rotor angle plot of the Generator at Shiroro
Figure 5: Response of generator rotor angle at Jebba
with and without SVC following a 200ms 3-phase fault
with and without SVC following a 3-phase fault
with SVC without SVC with SVC without SVC
4 4
Rotor Angle (rad.)

Rotor angle (rad)


2 2

0 0

-2 -2

-4 -4
400 0
600 800200 1000 0 200 400 600 800 1000
Time (ms) time (ms)
Figure 7: Rotor angle plot of the generator located at Figure 8: Rotor angle plot of Generator at Afam with
Sapele with and without SVC following a 3phase fault and without SVC following a 3-phase fault

1 scenarios were determined before and after the


œ•’“ ( ) = £œ” ( ) −
¤ (21)
›• installation of SVC. Also, the CCT and the improvement
The SVC is designed such that the TCR is switched off in the transient stability (CCT) before and after the
when the bus voltage falls below the reference voltage installation of SVC were determined. The location of
and turns on when it is above it. Therefore, the the SVC that provides the best improvement to the
maximum reactive power consumed by the fixed overall stability of the system was determined by trial
capacitor (FC) and the thyristor controlled reactor and error approach. The details of each of the
(TCR) is given as: scenarios are presented in the preceding subsection.
¥Ž‹
w•’“ = œ•’“ ( ) × m O•’“ (22)
while the minimum var consumption is obtained as: 4.1 Case 1: Fault on Jebba - Osogbo Transmission Line
¦s§
1 In this scenario, three-phase short circuit fault was
w•’“ = − m O•’“ (23)
›“ created on Jebba–Osogbo transmission line using step
by step technique. The voltage profiles of all the buses
4. SIMULATION RESULTS AND DISCUSSION in the network before and after the installation of SVC
Four scenarios (Case 1-Case 4) were created to have are furnished in Tables 3 and 4 respectively. The
insight into the transient instability that may arise as a voltage profile under this scenario (at CCT) reveals
result of fault on any of the identified critical lines and that the bus voltage of Kainji, Kaduna, Jos, Kano,
also to determine the size and location of SVC (within Gombe, B/Kebbi and Jebba are 1.34p.u, 1.30p.u,
the network) that would provide improvement to the 1.27p.u, 1.26p.u, 1.24p.u, 1.26p.u and 1.33p.u
security of the network. A three phase fault was respectively. These are in absolute violation of the
created at the middle of each of the critical lines using maximum allowed value of ±5% (i.e. 0.95-1.05p.u).
step by step approach. The bus voltages in each of the
Nigerian Journal of Technology Vol. 35, No. 1, January 2016 161
IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

The generator at Jebba generating station is the most synchronism. It was observed that this generator will
critically disturbed. This is expected as is the closest of always lose synchronism in the event of any 3-phase
the generators to the fault point. Installation of fault of any duration on the tie-line unless FACTS
appropriately sized SVC at Osogbo restores the device is installed. The fault created on the line also
voltage values to allowable limit of 1.03p.u, 1.02p.u, resulted into violation of voltages at B/Kebbi, Gombe,
0.99p.u, 0.96p.u, 0.97p.u, 1.01p.u and 1.02p.u, Ikeja-West, Akangba, Egbin, Aja, Sapele GS, Aladja and
respectively. The response of Jebba generator rotor Sapele with the voltage value of 0.92pu, 0.92pu,
angle to the disturbance with and without SVC is 0.94pu, 0.94pu, 0.94pu, 0.94pu, 1.52pu, 1.52pu and
depicted in Figure 5.The result reveals that with SVC 1.52pu, respectively. The installation of 62MVA SVC
of size 124MVA in place, the critical clearing time was restored all the bus voltages to allowable limit as
increased by 23.68%. shown in Table 4. The CCT before the installation of
SVC could not be determined as it was always losing
4.2 Case 2: Fault on Shiroro–
Shiroro–Kaduna
Kaduna transmission line synchronism to fault of any duration. This shows that,
In this scenario, 3-phase fault was created at the synchronism will always be lost without SVC in an
middle of Shiroro-Kaduna transmission line. The event of any contingency on the line. However, an
occurrence of faulton this overloaded tie line reduced installation of 62MVA SVC at Benin increased the CCT
the bus voltages at Kaduna, Jos, Kano and Gombe to to 220ms indicating much improvement in transient
zero indicating a black out of these areas. This is stability. The rotor angle plot of the generator located
because the areas serviced by this transmission line at Sapele before and after the installation of SVC is
were totally disconnected from the entire network depicted in Figure 7.
since this is the only tie line linking these areas to the
national grid. The fault also resulted into voltage 4.4 Case 4: Fault on Benin – Onitsha Transmission Line
violation at Osogbo, Ikeja-West and Egbin with Benin-Onitsha transmission line is a critical line that
recorded values of 1.11p.u, 1.07p.u and 1.07p.u, serves as the main link for power transfer to the
respectively. However, after the installation of eastern part of Nigeria. Applying three-phase fault on
appropriately sized SVC (73MVA) at Kaduna, all the this line resulted into loss of synchronism of the
bus voltages were restored back to allowable limit generator at Afam station. This is because Benin-
of±5%.. The voltages before and after the installation Onitsha is the only tie line supplying the region.
of SVC for all the buses under this scenario are Therefore, 3-phase fault of any duration without FACT
depicted in Tables 3 and 4, respectively. The transient device will always cause loss of synchronism of the
stability of the network indicated by the CCT was generator at Afam stations. The fault resulted into
improved by 4.17% when SVC was installed on the voltage violation of most of the buses as depicted in
line as revealed in Table 5. The rotor swing of the Table 3. However, installation of SVC at Benin station
generator located at Shiroro station before and after restored all the bus voltages to acceptable limit
the installation of the SVC is depicted in Figure 6. of±5 ± % as furnished in Table 4. The installation of
110MVA SVC at Benin bus increased the
4.3 Case 3: Fault on Benin-
Benin- Sapele Transmission line CCTto120ms.The response of Afam generator rotor
With the creation of 3-phase fault of any duration at angle to 3 phase fault with and without SVC is
the middle of Benin-Sapele transmission line, the depicted in Figure 8. The heavy oscillation without
generator located at Sapele was always losing SVC was easily damped out in the presence of SVC.

Table 3: Case voltages and angles without SVC


CASE 1 CASE 2 CASE 3 CASE 4
BUS
BUS NAME Voltage Angle Voltage Angle Voltage Angle Voltage
NO. Angle (deg.)
(p.u) (deg.) (p.u) (deg.) (p.u) (deg.) (p.u)
1 B/Kebbi 1.26 154.49 1.05 -1.56 0.92 -6.84 1.02 -3.34
2 Kainji 1.34 159.32 1.12 3.26 0.98 -2.01 1.08 1.49
3 Jebba 1.33 159.26 1.11 3.15 0.97 -2.17 1.08 1.37
4 Kainji GS 1.35 160.05 1.13 4.33 0.99 -0.61 1.10 2.62
5 Jebba GS 1.34 160.00 1.13 4.23 0.99 -0.75 1.10 2.52
6 Jebba TS 1.33 159.26 1.11 3.15 0.97 -2.17 1.08 1.37
7 Osogbo 0.88 -4.97 1.11 2.70 0.97 -2.49 1.07 1.19

Nigerian Journal of Technology Vol. 35, No. 1, January 2016 162


IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

CASE 1 CASE 2 CASE 3 CASE 4


BUS
BUS NAME Voltage Angle Voltage Angle Voltage Angle Voltage
NO. Angle (deg.)
(p.u) (deg.) (p.u) (deg.) (p.u) (deg.) (p.u)
8 Shiroro 1.31 157.84 1.15 5.24 0.97 -2.36 1.07 0.66
9 Shiroro GS 1.32 158.62 1.16 6.27 0.99 -0.93 1.09 1.83
10 Kaduna 1.30 157.37 0.00 -135.00 0.97 -2.82 1.07 0.19
11 Ajaokuta 0.92 -3.67 1.09 0.69 0.95 -3.91 1.09 1.99
12 Kano 1.26 155.46 0.00 135.00 0.94 -4.74 1.04 -1.72
13 Jos 1.27 155.93 0.00 135.00 0.94 -4.26 1.04 -1.25
14 Gombe 1.24 154.26 0.00 135.00 0.92 -5.94 1.02 -2.92
15 Benin 0.92 -3.45 1.09 0.91 0.96 -3.69 1.09 2.21
16 Onitsha 0.91 -4.67 1.07 -0.76 0.94 -4.99 0.71 -106.20
17 New Haven 0.91 -4.94 1.06 -1.03 0.94 -5.26 0.71 -106.46
18 Aiyede 0.87 -5.00 1.09 1.80 0.95 -3.05 1.06 0.71
19 Alaoji 0.92 -4.15 1.07 -0.77 0.95 -4.55 0.73 -104.32
20 Ikeja-West 0.88 -4.25 1.07 1.18 0.94 -3.14 1.05 0.75
21 Akangba 0.88 -4.26 1.07 1.18 0.94 -3.15 1.05 0.75
22 Egbin 0.88 -3.91 1.07 1.38 0.94 -2.85 1.05 0.96
23 Egbin GS 0.90 -1.92 1.08 2.75 0.96 -1.08 1.07 2.37
24 Aja 0.88 -3.92 1.07 1.38 0.94 -2.86 1.05 0.95
25 Sapele GS 0.94 -2.24 1.10 1.79 1.52 53.39 1.10 3.09
26 Aladja 0.93 -3.09 1.09 1.15 1.52 53.11 1.10 2.45
27 Delta GS 0.95 -1.52 1.11 2.30 0.99 -1.41 1.11 3.60
28 Afam GS 0.94 -2.59 1.09 0.41 0.97 -3.05 0.75 -101.84
29 Afam 0.92 -4.12 1.07 -0.75 0.95 -4.53 0.73 -104.27
30 Delta 0.93 -3.04 1.10 1.19 0.97 -2.82 1.10 2.49
31 Sapele 0.93 -3.28 1.09 1.03 1.52 53.18 1.09 2.33

Table 4: Case voltages and angles with SVC


CASE 1 CASE 2 CASE 3 CASE 4
BUS
BUS NAME Voltage Angle Voltage Angle Voltage Angle Voltage Angle
No.
(p.u) (deg.) (p.u) (deg.) (p.u) (deg.) (p.u) (deg.)
1 B/Kebbi 1.01 -4.26 1.01 -1.56 1.03 -3.34 1.01 -6.84
2 Kainji 1.03 -3.51 1.02 3.26 1.02 1.49 1.02 -2.01
3 Jebba 1.02 -1.32 1.01 -2.17 1.02 1.37 1.01 -2.45
4 Kainji GS 1.01 2.92 1.02 -0.61 1.03 -2.42 1.02 -5.76
5 Jebba GS 1.00 1.24 1.01 -0.75 1.03 -5.52 1.02 -1.03
6 Jebba TS 1.02 -3.09 1.01 -2.17 1.02 -3.37 1.01 -3.15
7 Osogbo 0.98 -1.52 1.02 -2.49 1.01 -5.19 0.99 2.70
8 Shiroro 1.01 7.84 1.00 5.24 1.01 -1.34 1.00 -2.36
9 Shiroro GS 1.00 0.62 1.00 0.27 1.02 -0.83 1.01 -10.93
10 Kaduna 1.02 -7.37 0.98 0.75 1.01 0.19 0.99 -2.82
11 Ajaokuta 0.98 -2.67 0.97 0.96 1.00 1.99 0.97 -3.91
12 Kano 0.96 -15.46 0.99 2.37 1.00 -1.72 0.98 -4.74
13 Jos 0.99 -4.25 0.98 0.95 1.01 -1.25 0.97 -4.26
14 Gombe 0.97 -4.26 0.97 -2.09 0.99 -2.92 0.96 -5.94
15 Benin 0.98 -8.45 0.99 -2.45 0.98 2.21 0.98 -3.69
16 Onitsha 0.96 -4.99 0.97 -5.76 0.99 -10.20 0.96 -4.99
17 New Haven 0.96 25.93 0.97 -1.03 0.98 -46.32 0.95 -5.26
18 Aiyede 0.97 -2.59 0.99 1.80 0.98 -8.73 0.97 -3.05
19 Alaoji 1.01 -4.12 0.98 -0.27 1.00 -24.32 0.98 -3.32
20 Ikeja-West 0.98 -3.04 0.99 -2.18 0.99 -18.58 0.97 7.84
21 Akangba 0.97 -3.28 0.98 -1.48 0.98 -4.55 0.96 0.62
22 Egbin 1.02 -3.43 1.03 2.48 1.03 -3.14 1.02 -7.37
23 Egbin GS 1.03 -4.67 1.03 0.75 1.03 -3.15 1.02 12.35
24 Aja 1.01 -4.94 1.01 1.38 1.02 -2.65 1.01 -7.81
25 Sapele GS 1.02 -15.13 1.02 1.79 1.03 -1.08 1.03 53.39
26 Aladja 1.02 -4.15 1.01 1.15 1.01 -2.86 1.01 53.11

Nigerian Journal of Technology Vol. 35, No. 1, January 2016 163


IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

CASE 1 CASE 2 CASE 3 CASE 4


BUS
BUS NAME Voltage Angle Voltage Angle Voltage Angle Voltage Angle
No.
(p.u) (deg.) (p.u) (deg.) (p.u) (deg.) (p.u) (deg.)
27 Delta GS 1.01 3.15 1.03 -1.41 1.03 3.60 1.02 -3.51
28 Afam GS 1.01 4.33 1.02 -3.05 1.01 -1.84 1.01 -1.32
29 Afam 1.01 4.23 1.02 -4.53 1.01 -1.25 1.01 -5.52
30 Delta 1.00 -3.15 1.01 -2.82 1.01 2.44 1.00 -3.37
31 Sapele 1.00 2.70 1.00 -3.01 1.00 4.31 1.00 53.18

Table 5: Critical clearing time with and without SVC when a 3-phase fault occurs on the critical line
Case Line Fault % CCT without CCT with SVC SVC Sizing Best location
% Improvement
No. Loading SVC (ms) (ms) (MVar) of SVC
1. Jebba -Osogbo 120 380 470 124 Osogbo 23.68
2. Shiroro-Kaduna 100 480 500 73 Kaduna 4.17
3. Benin-Sapele 123 - 220 62 Benin much
4. Benin-Onitsha 118 - 120 110 Benin much
Values cannot be determined

5. CONCLUSION
6. REFERENCES
The assessment of Nigerian 330kV transient stability
1 Ayodele T R, Jimoh A A, Munda J L, and Agee J T,
has been performed with a view to improve on the
2012. Challenges of grid integration of wind power
stability of the network with appropriately sized and on power system grid integrity: A review.
located SVC. The result shows that Jebba- Osogbo, International Journal of Renewable Energy
Shiroro-Kaduna, Benin-Sapele and Benin-Onitsha are Research, 2, 618-626.
the critical lines within the network that can excite 2 Ayodele T R, Jimoh A A, Munda J L, and Agee J T,
instability in the network. At steady state, the network 2012. The impact of wind power on power system
transient stability based on probabilistic weighting
bus voltages are within acceptable ±5% voltage limit. method. Journal of Renewable and Sustainable
However, the bus voltages of some of the buses within Energy, 4, 1-18.
the network were expectedly violated when 3-phase 3 Kundur P, Power system stability and control,. New
fault were applied at the middle of these critical lines. York: McGraw-Hill, Inc., 1994.
Installation of appropriately sized SVC with the values 4 El-Amin I M and Al-Shams A A M, 1997. Transient
of 124MVA, 73MVA, 62MVA and 110MVA at Oshogbo, stability assessment using artificial neural
Kaduna and Benin maintained the bus voltage within networks. Electric Power Systems Research, 40, 7-
acceptable limit in event of 3-phase fault. The critical 16.
clearing time of the acute generators when 3-phase 5 Kundur P, Paserba J, Ajjarapu V, Andersson G, Bose
A, Canizares C, Hatziargyriou N, Hill D, Stankovic A,
fault occurs on Jebba-Oshogbo and Shiroro-Kaduna
Taylor C, Van Cutsem T, and Vittal V, 2004.
increases from 380ms, 480ms to 470ms and 500ms, Definition and classification of power system
respectively with the installation of the SVC. The stability. IEEE Transactions on Power Systems, 19,
generators located in Sapele and Afam station will 1387-1401.
always lose synchronism in an even of 3-phase fault 6 Gupta A and Sharma P R, (2013), Static and
on Benin-Sapele and Benin-Onitsha transmission line. transient stability enhancement of power system by
However, the CCT was increased to 220ms and 120ms, optimally placing upfc (unified power flow
controller), in Advanced Computing and
respectively with installation of SVC at Benin station. Communication Technologies (ACCT), 2013 Third
This paper may be useful to the Nigerian electricity International Conference on. 121-125.
utility companies for proper planning of Nigerian 7 Ayodele T R, Jimoh A A, Munda J L, and Agee J T,
national grid and also in the formulation of policy on 2010 "The impact of wind power loading on the
improving Nigerian Power system. Future research power system transient stability " presented at the
will focus on development of indices that will aid the IASTED International Conference on Power and
Energy Systems (AsiaPES 2010), Phuket, Thailand,
sizing and location of SVC within the Nigerian 330kV
pp 103-110.
power system network with the aim of improving the
8 Dhaval N T, Bhavesh B, and Vijay M, 2012. Roll of
transient stability of the network. pss and svc for improving the transient stability of
power system. International Journal of Engineering
and Advanced Technology 1, 137-140.
Nigerian Journal of Technology Vol. 35, No. 1, January 2016 164
IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

9 Ashraf M A, Shojaeian S, and Koofigar H R, 2013. critical lines. Journal of Applied Science,
Improving transient stability of a multi-machine Engineering and Technology, 4, 49-54
power network using facts devices and nonlinear 22 Matthew S, Wara S T, Adejumobi A I, Ajisegiri E S A,
controller tuned by pso. Research Journal of and Olanipekun A J, 2014. Power system’s voltage
Applied Sciences, Engineering and Technology, 5, stability improvement using static var
280-285. compensator. International Journal of Emerging
10 Ayodele T R, "Analysis of wind energy resource and Technology and Advanced Engineering, 4, 494-501.
impact of its integration into power systems " 23 DigSILENT, "Digsilent technical documentation on
Doctor Technologie, Electrical and Electronic synchronous generator," ed. Germany: DigSILENT
Engineering, Tshwane University of Technology,pp GmbH, 2009, pp. 1-21.
268, Pretoria, 2012.
24 Chikezie B U, 2011. Computational model for
11 Praveen K A, Nishant A, and Devendra M, 2014 transient stability analysis of power system in
"Improvement in power system stability with nigeria. International Journal of Engineering and
implementation of fact devices," presented at the Mathematical Intelligence, 2, 48-53.
2nd International e-Conference on Emerging
Trends in Technology, India, pp 12-15. 25 Ariyo F K and Omoigui M O, 2013. Investigation of
nigerian 330 kv electrical network with distributed
12 Udhayashankar C, Thottungal R, and Yuvaraj M, generation penetration – part i: Basic analyses.
2014 "Transient stability improvement in Electrical and Electronic Engineering, 3, 49-71.
transmission system using svc with fuzzy logic
control," presented at the International Conference 26 Dube A, Sharma P R, and Hooda N, (2012), Stability
on Advances in Electrical Engineering (ICAEE), enhancement in a multi-machine power system
Vellore, pp 1-4. using unified power flow controller, in Power India
Conference, 2012 IEEE Transaction on Power
13 Simeon M, Tita W S, Isaiah A A, Ajisegiri E S A, and System. 1-5.
Joseph O A, January 2014 2014. Power system’s
voltage stability improvement using static var 27 Nabavi-Niaki A and Iravani M R, 1996. Steady-state
compensator. International Journal of Emerging and dynamic models of unified power flow
Technology and Advanced Engineering, 4, 494-501. controller (upfc) for power system studies. IEEE
Transactions on Power System, 11, 1937-1943.
14 Kumar S V R and Nagaraju S S, 2007. Transient
stability improvement using upfc and svc. ARPN 28 Adejumobi I A, Adepoju G A, and Hamzat K A, 2013.
Journal of Engineering and Applied Sciences, 2, 1-6. Iterative techniques for load flow study: A
comparative study for nigerian 330kv grid system
15 Kaur T and Kakran S, 2012. Transient stability as a case study. International Journal of Engineering
improvement of long transmission line system by and Advanced Technology, 3, 153-158.
using svc. International Journal of Advanced
Research in Electrical, Electronics and 29 Ubisse A V, Folly K A, Awodele K O, and Oyedokun D
Instrumentation Engineering, 4, 218-227. T, (2010), Comparison of matlab pst, psat and
digsilent for transient stability studies on parallel
16 Ogunjuyigbe A S O and Ayodele T R, 2015. Techno- hvachvdc transmission lines, in 2010 45th
economic analysis of stand-alone hybrid energy International Universities Power Engineering
system for nigerian telecom industry. Int. J. Conference (UPEC). 1-6.
Renewable Energy Technology, in Press,
30 Liu C, Chen Z, Bak C L, Liu Z, Lund P, and Ronne-
17 Anumaka M C, 2012. Analysis of technical losses in Hansen P, 2012. Transient stability assessment of
electrical power system (nigerian 330kv network as power system with large amount of wind power
a case study) IJRRAS, 12, 320-327. penetration: The danish case study. Proceedings of
18 Onojo O J, Ononiwu G C, and Okozi S O, 2013. the 10th International Power and Energy
Analysis of power flow of nigerian 330kv grid Conference, IPEC 2012,461-467.
system (pre and post ) using matlab. European 31 El-Amin I M and Al-Shams A-A M, 1997. Transient
Journal of Natural and Applied Sciences, 1, 59-66. stability assessment using artificial neural
19 Izuegbunam F I, Duruibe S I, and Ojukwu G G, 2011. networks. Electric Power Systems Research, 40, 7-
Power flow and contingency assessment simulation 16.
of the expanding 330kv nigeria grid using power 32 Keskes S, Bahloul W, and Kammoun M B A, 2014.
world simulator. Journal of Emerging Trends in Improvement of power system stability by static
Engineering and Applied Sciences, 2, 1002-1008. var compensator and tuning employing genetic
20 Onohaebi O S and Igbinovia S O, 2008. Voltgae dip algorithm. International Journal of Modern
reduction in he nigerian 330kv trasmission grid. Nonlinear Theory and Application, 3, 113-123.
Journal of Engineering and Applied Science 3, 496-
503.
21 Ogunjuyigbe A S O and Awosope C O A, 2004.
Invariance of reactor location with the outaging of

Nigerian Journal of Technology Vol. 35, No. 1, January 2016 165


IMPROVING THE TRANSIENT STABILITY OF NIGERIAN 330KV TRANSMISSION NETWORK USING SVC, T. R. Ayodele, et al

APPENDIX
Table 6: Transmission Line Data for 330kV Nigeria Power System
LINE PARAMETERS (P.U)
LINE NO. FROM BUS i TO BUS J
R X B TAP PHASE
1 1 2 0.01218 0.09163 1.0269
2 2 3 0.00159 0.01197 0.5366
3 2 4 0 0.01351 0 1 0
4 3 6 0.00016 0.00118 0.053
5 3 7 0.00206 0.01547 1.56
6 3 8 0.00480 0.03606 1.6165
7 5 6 0 0.01932 0 1 0
8 7 15 0.00987 0.07419 0.8315
9 7 18 0.00412 0.03098 0.3472
10 7 20 0.01163 0.08750 0.9805
11 8 9 0 0.01638 0 1 0
12 8 10 0.00189 0.01419 0.636
13 10 12 0.00904 0.06799 0.7619
14 10 13 0.00774 0.05832 0.6526
15 11 15 0.00766 0.05764 0.646
16 13 14 0.01042 0.07833 0.8778
17 15 16 0.00538 0.04050 0.4538
18 15 20 0.00550 0.04139 1.885
19 15 30 0.00287 0.02158 0.2418
20 15 31 0.00098 0.00739 0.3313
21 16 17 0.00377 0.02838 0.318
22 16 19 0.00605 0.04552 0.5101
23 18 20 0.00538 0.04050 0.454
24 19 29 0.00049 0.00369 0.1656
25 20 21 0.00036 0.00266 0.119
26 20 22 0.00122 0.00916 0.4108
27 22 23 0 0.00648 0 1 0
28 22 24 0.00028 0.00207 0.0928
29 25 31 0 0.01204 0 1 0
30 26 30 0.00102 0.00769 0.08613
31 26 31 0.00248 0.01862 0.2087
32 27 30 0 0.01333 0 1 0
33 28 29 0 0.01422 0 1 0

Table 7: Generator Data for 330kV Nigeria Power System


Gen. Names MVA H xd x'd x"d xq x'q x"q T’d0 T”d0 T’q0 T”q0 xl R
G1 Kainji 450 3.34 0.75 0.28 0.21 0.53 - 0.21 6.0 0.04 - 0.16 0.16 0.004
G2 Jebba 600 3.39 0.65 0.26 0.24 0.44 - 0.24 5.2 0.06 - 0.24 0.14 0.0037
G3 Egbin 1500 3.09 1.87 0.262 0.23 1.87 0.45 0.22 7.1 0.063 1.0 0.11 0.18 0.004
G4 Shiroro 700 3.24 0.80 0.30 0.2 0.49 - 0.24 5.57 0.05 - 0.34 0.16 0.004
G5 Sapele 440 8.91 2.17 0.25 0.18 1.92 - 0.18 8.8 0.05 - 0.20 0.13 0.004
G6 Delta 550 6.70 2.16 0.234 0.17 2.16 - 0.16 8.6 0.05 - 0.20 0.12 0.002
G7 Afam 330 9.01 2.09 0.20 0.15 1.89 - 0.15 6.93 0.05 - 0.20 0.11 0.003

Nigerian Journal of Technology Vol. 35, No. 1, January 2016 166

Вам также может понравиться