Академический Документы
Профессиональный Документы
Культура Документы
My Courses
Catalog
Free Courses
Knowledge Base
Information becomes valuable only if it is shared
2019 PMP Exam Questions | Sample PMP Exam Questions & Rationales
02 October, 2018
PMP exam questions or sample pmp exam questions are one of the top searches of a PMP aspirant. Because, the best way to get ready for PMP certification exam is practicing
with as many PMP exam questions as possible.
PMP exam questions will help you to see your readiness for the exam and assess your knowledge before sitting on PMP certification exam.
B-) Receiver must reply the message after decoding the message.
C-) Receiver should acknowledge first and then agree with the message sent by the sender.
Johnis a project manager of a complicated project. When he started creating a work breakdown structure for his project, he realized that it is too complex to complete work
breakdown structure on a single sheet. You, as a colleague of John, recommend using a work breakdown structure numbering system to John to:
You are trying to establish a cost performance baseline for your project in Determine Budget Process. You can use the following tool and techniques EXCEPT:
Which of the following techniques includes measuring,examining and validating whether work and deliverables meet requirements and product acceptance criteria?
A-)Workshops
B-)Surveys
C-)Expert Judgment
D-)Inspection
Enroll in our FREE PMP Overview training to learn more about PMP Certification, and how to apply for PMP step-by-step.
A-)Secondary risk
B-)Residual risk
C-)Contingency plan
D-)Unmanageable risks
All of the following are hygiene factors according to Herzberg’s Theory EXCEPT:
A-)Salary
B-)Professional Growth
C-)Security
D-)Relationships at work
You are expected to manage stakeholder’s expectations as a project manager. All of the following are interpersonal skills that you should apply EXCEPT:
A-)Building trust
B-)Resolving conflict
C-)Risk taking
D-)Active listening
There has been several changes in your project and this affected your cost and schedule estimates. This has invalidated the original estimating assumptions. What is the estimate
at completion (EAC) for your project based on following parameters?
BAC = $ 360,000
AC = $ 120,000
EV = $ 180,000
CPI = 1.2
ETC = $ 145,000
A-)$ 300.000
B-)$ 265.000
C-)$ 325.000
D-)$ 360.000
Your Company has entered into a joint venture with Service Company to develop a software program. Which of the following should be cooperatively prepared by both the
buyer and the seller during teaming agreement process?
A-)Contract
Based on Net Present Value (NPV) criterion, which project should be selected?
A-)Project A
B-)Project B
C-)Project C
You are trying to gather ideas related to project and product requirements. Which technique is appropriate for this?
A-)Brainstorming
C-)Affinity Diagram
Your colleague Wayne, a project manager, completed a mp3 player development project. While he was telling his experiences from his project, he mentioned that they delivered
“adjustable screen timeout duration” feature, without a deviation from the plan, although the customer did not require and was not in scope of the project. He added that
customer was very surprised and happy when they saw this additional feature at the end of the project. Which of the following is correct about this story?
B-)Customer satisfaction increased with an additional feature which they did not expect
You have documented all possible risks that can affect your project with appropriate risk responses when they occur in your risk management plan. All other remaining risks are
called as:
A-)Risk Triggers
B-)Unmanageable Risks
C-)Residual Risks
D-)Accepted Risks
You are working as a project manager in a company. You have the highest degree of authority, you are working full-time for your project and you manage the budget of the
project. What is the organization structure in your company?
A-)Strong Matrix
B-)Projectized
C-)Functional
D-)Balanced Matrix
You are the project manager of a software project team consisting of 2 analysts, 4 software developers and 3 test engineers. One new test engineer will join the team in two
weeks. What will be the number of communication channels after new test engineer joins the team?
A-)55
B-)50
C-)45
D-)36
All of the following are tools and techniques that can be used in Identify Stakeholders process EXCEPT:
A-)Expert Judgment
B-)Stakeholder Register
C-)Meetings
D-)Stakeholder Analysis
The seller`s project is undertaken on contract and you are an employee of the seller. Since you earlier worked with XYZ Factory, the buyer, you happen to be aware of the
evaluation criteria used in XYZ Factory to select sellers. You understand that this could be a potential conflict of interest situation. How do you propose to act?
B-)Take appropriate person in XYZ Factory into confidence and discuss this issue with her
C-)Disclose the evaluation criteria to your (seller) organization and help their business growth
During project planning phase, which of the following steps come latest compared to others?
C-)Develop Budget
D-)Develop Schedule
A project is a temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates a definite beginning and ending.
Answer: D
As part of the communications process, the sender is responsible for the transmission of the message, ensuring the information being communicated is clear and complete, and
confirming the communication is correctly understood. The receiver is responsible for ensuring that the information is received in its entirety, understood correctly, and
acknowledged or responded to appropriately. However, receiver may not agree on received message
Answer: C
Knowledge Area: Communications Management
The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers
provide a structure for hierarchical summation of costs, schedule, and resource information.
Answer: C
Cost aggregation
Reserve analysis
Expert judgment
Historical relationships
Answer: B
Inspection includes activities such as measuring, examining, and validating to determine whether work and deliverables meet requirements and product acceptance criteria.
Answer: D
Secondary risks are risks that arise as a direct result of implementing a risk response
Answer: A
According to Herzberg’s Theory, there are hygiene factors and motivating agents. Inadequate Hygiene factors may destroy motivation but sufficient hygiene factors itself are
not enough to motivate people. Hygiene factors are:
Working card
Salary
Personal Life
Relationships at work
Security
Status
Answer: B
Building trust
Active listening
Answer: C
Answer: B
The relationship among portfolios, programs, and projects is such that a portfolio refers to a collection of projects, programs, sub-portfolios, and operations managed as a group
to achieve strategic objectives.
Answer: C
In some cases, the seller may already be working under a contract funded by the buyer or jointly by both parties. The effort of the buyer and seller in this process is to collectively
prepare a procurement statement of work that will satisfy the requirements of the project. The parties will then negotiate a final contract for award.
Answer: B
Project A has highest NPV of $ 300,000. Time value of money is already taken into account when calculating NPV of a project. Since Project A has the highest NPV, it should be
selected.
Answer: A
A technique used to generate and collect multiple ideas related to project and product requirements.
Answer: A
Gold plating refers to continuing to work on a project or task well past the point where the extra effort is worth the value it adds (if any). After having met the requirements, the
assignee works on further enhancing the product, thinking the customer would be delighted to see additional or more polished features, rather than what was asked for or
expected.
Answer: A
Answer: C
In a projectized organization structure, project manager has the highest level of authority, works full-time and manages the budget of the project.
Answer: B
The total number of potential communication channels is n(n-1)/2, where n represents the number of stakeholders.
Your team has 10 team members already (2 analysts, 4 software developers, 3 test engineers, and you as a project manager). After new test engineer joins, there will be 11 team
members.
Answer: A
Stakeholder analysis, Expert Judgment and Meetings are tools and techniques that can be used in Identify Stakeholders process. Stakeholder Register is an output of Identify
Stakeholders process.
Answer: B
Answer Bis the correct answer. Since the evaluation criteria are proprietary information of XYZ Factory, it is important for you to discuss the matter directly with the
appropriate person in the XYZ Factory.
Answer: B
Develop schedule
Develop budget
Answer: A
You might want to check our 20 PMP Questions and Answers post as well.
I want to thank you for the excellent job you do explaining the process groups and knowledge areas, and the key notes/tips you provided during the lectures were
very helpful! I had also purchased a PMP exam prep book from another...
READ MORE
Received one of the most prestigious certificate in project management area, PMP®, on 11th Oct 2016 and I must thank Master of Project Academy for providing
good learning platform, Mr. Resit Gulec for preparing and providing precise lecture, my wife Seema and kids for supporting throughout (It’s...
READ MORE
PMP is world’s most recognized certification for project management profession. But earning the PMP Certificate might be challenging especially if you are
a working professional, finding time to study PMP might be hard. Is there any PMP study plan? Which PMP study plan will fit me? What are the...
READ MORE
PMP Certification Requirements article will help you to understand eligibility requirements to sit for PMP exam. It will be good to know whether you fulfill the PMP eligibility
requirements before you start your PMP preparation.
PMP Certification Cost article will help you to see all aspects of PMP certification cost. Check all aspects of PMP certification cost and prepare your budget for getting PMP
certification.
PMP online certification article will help you to understand advantages and disadvantages of different PMP preparation methods. You will be able to determine the best option
to prepare for PMP certification after reading this article.
PMP certification salary article will help you to see anticipated salary hike after you get the PMP certification!
Do you want to earn money just by sharing this article? Learn How
PMP Exam Questions
Review by: Resit
5 / 5 stars
Post a comment
James Stallins
Leave a comment...
Post Comment
0 comments
Load more
bout Us
aster of Project Academy delivered online courses to more than 50,000 participants in more than 170 countries around the world. All courses are 100% Online, Self-Paced and 30 Day Money Back
uaranteed. Master of Project Academy course portfolio includes but not limited to:
ollow us on
Company
About Us
Contact
Blog
Media Coverage
Privacy Policy
Terms of Use
Engage with Us
Contact Us
info@masterofproject.com