Вы находитесь на странице: 1из 1280

1 Hire charges of Coaltar Boiler 900 to 1400 litres Day 500

2 Hire charges of Concrete Mixer 0.14 cubic metre Day 400


3 Hire charges of Diesel Road Roller - 8 to 10 tonne Day 500.00
4 Production cost of concrete by batch mix plant. cum 100
5 Hire charges of Diesel Truck - 9 tonne Day 1500
6 Hire charges of Spraying machine including electric Day 100
charges
7 Hire charges of Coaltar Sprayer Day 200
8 Hire charges of Barber green, drying, mixing and Asphalt day 5000
plant with, accessories, capacity 30/45 tonne
9 Pum ping charges of concrete including Hire charges of cum 50
pump, piping work & accessories etc.
10 Hire charges of Derrick monkey rope day 400
11 Hire charges of Pum p set of capacity 4000 litres/ hour Day 200

12 Vibrator (Needle type 40mm) Day 150


13 Machine for rubbing of floors Day Day 150
14 Front end loader Day 5,000.00
16 Mastic Cooker Day 400
17 Hire and running charges of tipper Day 700
18 Hire and running charges of loader. Day 700
19 Hand Grinder For mirror polish Day 100
20 Hydraulic Excavator (3D) with driver and fuel. day 4000
21 Pin vibrator Day 150
22 Surface Vibrator Day 150

24 Hire and running charges of hydraulic piling rig with ower day 20000
unit etc. including complete accessories and shifting at
site

25 Hire and running charges of light crane. day 2000


26 Hire and running charges of bentonite pump. day 3,000.00
27 Hire and running charges of vibrating pile driving hammer day 20000
complete with power unit and acces sories.
28 Hire and running charges of crane 20 tonne capacity. day 8,000.00
29 Carriage of concrete by transit mixer. km/cum 18
30 Generator 250 KVA. day 10,000.00
33 Paint applicator. day 500
37 Mobile crane. day 5000
38 Tractor with ripper attachment. day 600
39 Tractor with trolley. day 600
40 Air compressor 250 cfm with two leads for pneumatic day 1,600.00
cutters/hammers
41 Joint cutting machine with 2-3 blades day 800
42 C.C .batch mix plant. day 88,000.00
43 Road sweeper day 480
45 Slip form paver with sensor. day 12000
46 Water tanker. day 500
47 Concrete joint cutting m achine. day 600
48 Texturing machine. day 600

Notes : - Above hire - charges include cost of services of operating


staff and supply of lubricating oil.
Note :- These rates are exclusive of contractor’s profit and over heads and are inclusive of
wages for weekly (Labour rates w.e.f. 1.04.2012)
100 Bandhani day 180.00
101 Bhisti day 180.00
102 Blacksm ith 1st class day 270.00
103 Blacksmith 2nd class day 223.00
111 Carpenter 1st class day 270.00
112 Carpenter 2nd class day 223.00
113 Chowkidar day 207.00
114 Beldar day 207.00
115 Coolie day 207.00
116 Fitter (grade 1) day 270.00
117 Assistant Fitter or 2nd class Fitter day 223.00
119 Glazier day 180.00
122 Mason (for plas ter of paris work) 1st class day 313.00
123 Mason (brick layer) 1st class day 270.00
124 Mason (brick layer) 2nd class day 223.00
125 Mason (for plain stone w ork) 2nd class) day 223.00
126 Mason (for ornamental stone work) 1st class day 313.00
127 Driver (for Road Roller, Concrete Mixer, Truck etc.) day 223.00
128 Mate day 313.00
130 Mistry day 270.00
131 Painter day 180.00
132 Rock Ex cavator day 180.00
133 Rock Breaker day 180.00
134 Rock Hole Driller day 223.00
135 Stone Chiseller day 180.00
138 Sprayer (for bitumen, tar etc.) day 180.00
139 Skilled Beldar (for floor rubbing etc.) day 180.00
141 White Washer day 180.00
155 * Mason (average) day 180.00
156 * Carpenter (average) day 180.00
157 Operator (Pile/ Special machine) day 223.00
159 Skilled torch operator for laying tack day 180.00
Note :- * These rates are average of 1st class and 2nd class categories. This is for use in
the analysis of rate only.
Un skilled 464.10
Semi Un skilled 192.00
skilled 232.00
Highly skilled 273.00
Note :- These rates are exclusive of contractor’s profit, over
heads and carriage but include octroi, royalty, salestax
(VAT) etc.

222 Seam bolts and nuts 6 mm dia and 25 mm long 10 Nos 30.00
223 Non - Asbestos fibre cement corrugated sheet 6mm sqm 205.00
thick.
224 Non - Asbestos fibre cement close fitting adjustable metre 203.00
ridge.
225 Non - Asbestos fibre cement corrugate serrated metre 174.00
adjustable ridge.
226 Non - Asbestos fibre cement plain wing adjustable ridge. metre 188.00

227 Non - Asbestos fibre cement unserrated adjustable ridge metre 195.00
for hips.
228 Non - Asbestos fibre cement corrugated apron piece. metre 126.00

229 Non - Asbestos fibre cement eaves filler piece. each 93.00
230 Non - Asbestos fibre cem ent north light curves. metre 197.00
231 Non - Asbestos fibre cement ventilator curves. each 267.00
232 Non - Asbestos fibre cement barge boards 6 mm thick. metre 232.00

233 Non - Asbestos fibre cement ridge finial . pair 84.00


234 Non - Asbestos fibre cement special north light curves. each 275.00

235 Non - Asbestos fibre cement S type louvers. each 161.00


236 Non - Asbestos multi purpose fibre cement board 6mm sqm 180.00
thick.
237 Non - Asbestos multi purpose fibre cement board 8mm sqm 239.00
thick.
285 Brick Aggregate (Single size) : 63 mm nominal s ize cum 350.00
286 Brick Aggregate (Single size) : 50 mm nominal s ize cum 355.00
287 Brick Aggregate (Single size) : 40 mm nominal s ize cum 360.00
291 Stone Aggregate (Single size) : 63 mm nominal size cum 900.00

292 Stone Aggregate (Single size) : 50 mm nominal size cum 1000.00

293 Stone Aggregate (Single size) : 40 mm nominal size cum 1000.00

294 Stone Aggregate (Single size) : 25 mm nominal size cum 1100.00

295 Stone Aggregate (Single size) : 20 mm nominal size cum 1100.00

296 Stone Aggregate (Single size) : 12.5 mm nominal size cum 1050.00

297 Stone Aggregate (Single size) : 10 mm nominal size cum 1050.00

298 Stone Aggregate (Single size) : 06 mm nominal size cum 400.00

302 Safeda ballies 125 mm diameter metre 52.00


304 Bajri cum 700.00
305 Bamboo 25 mm dia 2.5 metre long score 192.00
308 Bhusa quintal 200.00
309 Paving bitumen S-90 of approved quality tonne 22500.00
310 Bitumen emulsion tonne 19500.00
312 Bitumen grade PMB - 40 M.T. 35000.00
313 Blown type petroleum bitumen of penetration 85/25 of tonne 35000.00
approved quality
314 Bitumen hot sealing compound : grade A kilogram 35.00
316 Bitumen solution primer of approved quality litre 30.00
317 Premoulded joint filler 12 mm thick sqm 300.00
318 Bitumen felt fibre base (vegetable or animal):Type 2 sqm 45.00
grade 1
322 Bitumen felt :Type 3 grade 1 sqm 45.00
324 Coal Tar litre 16.00
325 Blasting powder kilogram 25.00
326 Blasting fuse (fuse wire) each 10.00
328 White face insulating board:12 mm thick sqm 239.00
332 Natural colour insulating board:12 mm thick sqm 175.00
336 Flame retardant fac e insulating board: 12 mm thick sqm 208.00

339 Flame retardant fac e insulating, Impregnated fibre board sqm 279.00
12 mm thick
341 Flat pressed 3 layer particle board (medium density) sqm 258.00
Grade I :12 mm thick
346 Extra for veneered particle board with : Teak veneering on sqm 198.00
one side and commercial veneered on other side

347 Extra for veneered particle board with : Commercial sqm 102.00
veneering on both sides
348 Extra for veneered particle board with : Teak veneering on sqm 366.00
both sides
362 Brick bats cum 253.00
364 Wire brush each 90.00
365 Soft brush each 50.00
367 Portland Cement tonne 5200.00
368 White Cement tonne 9500.00
370 Coal (steam) quintal 120.00
373 Cramp Gun metal 25x6x300 mm each 53.00
378 Brass butt hinges (light/ordinary type) : 125x70x4 mm 10 Nos 450.00

379 Brass butt hinges (light/ordinary type) : 100x70x4 mm 10 Nos 300.00

380 Brass butt hinges (light/ordinary type) : 75x40x2.5 mm 10 Nos 160.00

381 Brass butt hinges (light/ordinary type) : 50x40x2.5 mm 10 Nos 90.00

382 Brass butt hinges (heavy type) : 125x85x5.5 mm(.70)kg 10 Nos 1500.00

383 Brass butt hinges (heavy type) : 100x85x5.5 mm(.56)kg 10 Nos 1300.00
384 Brass butt hinges (heavy type) :75x65x4.0 mm(.20)kg 11 Nos 450.00

385 Brass parliamentary hinges 150x 125x27x5 mm 10 Nos 1650.00


386 Brass parliamentary hinges 125x 125x27x5 mm 10 Nos 1450.00
387 Brass parliamentary hinges 100x 125x27x5 mm 10 Nos 1175.00
388 Brass parliamentary hinges75x100x20x3.2 mm 10 Nos 888.00
389 Brass single acting spring hinges 150 mm each 200.00
390 Brass single acting spring hinges 125 mm each 158.00
391 Brass single acting spring hinges 100 mm each 106.00
392 Brass double acting spring hinges 150 mm each 317.00
393 Brass double acting spring hinges 125 mm each 216.00
394 Brass double acting spring hinges 100 mm each 173.00
400 Brass tower bolt (barrel type) 250x10 mm each 123.00
401 Brass tower bolt (barrel type) 200x10 mm each 100.00
402 Brass tower bolt (barrel type) 150x10 mm each 75.00
403 Brass tower bolt (barrel type) 100x10 mm each 51.00
404 Brass flush bolt 250 mm each 84.00
405 Brass flush bolt 150 mm each 65.00
406 Brass flush bolt 100 mm each 44.00
408 Brass handles 125 mm with plate 175x32 mm each 85.00
409 Brass handles 100 mm with plate 150x32 mm each 75.00
410 Brass handles75 mm with plate 125x32 mm each 55.00
411 Brass door latch 300x16x5 mm (0.380 kg) each 85.00
412 Brass door latch 250x16x5 mm (0.350 kg) each 82.00
413 Brass m ortice latch and lock 100x65 mm with6 levers each 257.00
and
Brassampair of brass
latchlever handles with a pair of brass
414 ortice 100x65mm each 235.00
lever handles
417 Brass 150 mm floor door stopper (0.357kg) each 104.00
418 Brass hard drawn hooks and eyes 300 mm 10 Nos 457.00
419 Brass hard drawn hooks and eyes 250 mm 10 Nos 423.00
420 Brass hard drawn hooks and eyes 200 mm 10 Nos 390.00
421 Brass hard drawn hooks and eyes 150 mm 10 Nos 364.00
422 Brass hard drawn hooks and eyes 100 mm 10 Nos 300.00
423 Brass casement window fastener each 26.00
424 Brass casement stays (straight peg type ) 300 mm each 66.00
weighing not less than 0.33 kg
425 Brass casement stays (straight peg type ) 250 mm Each 55.00
weighing not less than 0.28 kg
426 Brass casement stays (straight peg type ) 200 mm each 46.00
weighing not less than 0.24 kg
427 Brass quadrant stays 300 mm each 73.00
428 Brass fanlight catch 10 Nos 109.00
429 Brass fanlight pivot 11 Nos 128.00
430 Brass chain with hook for fan light catch each 13.00
431 Brass hasps and staples (safety type) 300 mm 10 Nos 458.00
432 Brass hasps and staples (safety type) 115 mm 10 Nos 378.00
433 Brass hasps and staples (safety type)90 mm 10 Nos 300.00
438 Brass Night latch each 338.00
442 Brass helical spring 150 mm each 185.00
444 Brass curtain rod 20 mm dia 1.25 mm thick metre 63.00
445 Brass curtain rod 25 mm dia 1.25 mm thick metre 79.00
446 Brass brackets (curtain rods) 20 mm each 24.00
447 Brass cupboard knob or ward robe knob 50 mm each 18.00
449 Brass screws 50 mm 100 Nos 107.00
450 Brass screws 40 mm 100 Nos 96.00
451 Brass screws 30 mm 100 Nos 86.00
452 Brass screws 25 mm 100 Nos 76.00
453 Brass screws 20 mm 100 Nos 53.00
524 Chromium plated Brass butt hinges (heavy) type 10 Nos 430.00
75x65x4 .0 mm (200 gms)
525 Chromium plated Brass butt hinges (light/ordinary) type 10 Nos 433.00
125x70x4 mm
526 Chromium plated Brass butt hinges (light/ordinary) type 10 Nos 385.00
100x70x4 mm
527 Chromium plated Brass butt hinges (light/ordinary) type 10 Nos 135.00
75x40x2.5 mm
528 Chromium plated Brass butt hinges (light/ordinary) type 10 Nos 105.00
50x40x2.5 mm
555 Chromium plated Brass handles 125 mm with plate 175 Each 92.00
x32 mm
556 Chromium plated Brass handles 100 mm with plate 150 x Each 79.00
32 mm
557 Chromium plated Brass handles 75mm with plate Each 68.00
125x32 mm
558 Chromium plated Brass mortice latch and lock 100x65 Each 323.00
mm with6 levers and a pair of brass lever handles

568 Chromium plated brass casement window fastener Each 55.00


569 Chromium plated Brass casement stays (straight peg Each 73.00
type ) 300 mm weighing not less than 0.33 kg
570 Chromium plated Brass casement stays (straight peg Each 67.00
type ) 250 mm weighing not less than 0.28 kg
571 Chromium plated Brass casement stays (straight peg Each 56.00
type ) 200 mm weighing not less than 0.24 kg
583 Chromium plated Brass N ight latch Each 383.00
584 Chromium plated Brass Wardrobe Knob 50 mm Each 25.00
585 Chromium plated Brass screws 50 mm 100 Nos 123.00
586 Chromium plated Brass screws 40 mm 100 Nos 150.00
587 Chromium plated Brass screws 30 mm 100 Nos 90.00
588 Chromium plated Brass screws 25 mm 100 Nos 83.00
589 Chromium plated Brass screws 20 mm 100 Nos 63.00
590 Chromium plated Brass curtain rod 12 mm dia 1.25mm metre 122.00
thick
591 Chromium plated Brass curtain rod 20 mm dia 1.25mm metre 143.00
thick
592 Chromium plated Brass curtain rod 25 mm dia 1.25mm metre 239.00
thick
594 Bright finished or black enameled mild steel butt hinges 10 nos 78.00
125x65x2.12 mm
595 Bright finished or black enameled mild steel butt hinges 10 nos 54.00
100x58x1.90 mm
596 Bright finished or black enameled mild steel butt 10 nos 34.00
hinges75x47x1.70
597 Bright finished or black enameled mild steel butt 10 nos 28.00
hinges50x37x1.50 mm
608 Nickel plated mild steel piano hinges 1 mm thick 35 mm metre 21.00
wide
635 Bright finished or black enameled mild steel screws 50 100 Nos 40.00
mm
637 Bright finished or black enameled mild steel screws 40 100 Nos 30.00
mm
638 Bright finished or black enameled mild steel screws 30 100 Nos 24.00
mm
639 Bright finished or black enameled mild steel screws 25 100 Nos 15.00
mm
640 Bright finished or black enameled mild steel screws 20 100 Nos 15.00
mm
641 Bright finished or black enameled mild steel bolts and each 4.00
nuts 50x6mild
mm steel butt hinges 125x65x2.12 mm
642 Oxidised 10 Nos 92.00
643 Oxidised mild steel butt hinges 100x58x1.90 mm 10 Nos 53.00
644 Oxidised mild steel butt hinges75x47x 1.70 mm 10 Nos 32.00
645 Oxidised mild steel butt hinges50x37x 1.50 mm 10 Nos 27.00
646 Oxidised mild steel parliamentary hinges150x125x27x2.8 10 Nos 255.00
mm
647 Oxidised mild steel parliam entary hinges 10 Nos 205.00
125x125x27x2.8 mm
648 Oxidised mild steel parliam entary hinges 10 Nos 165.00
100x125x27x2.8 mm
649 Oxidised mild steel parliam entary hinges 10 Nos 122.00
75x100x20x2.24 mm
650 Oxidised mild steel single acting spring hinges 150 mm each 71.00

651 Oxidised mild steel single acting spring hinges 125 mm each 66.00

652 Oxidised mild steel single acting spring hinges 100 mm each 51.00

653 Oxidised mild s teel double acting spring hinges 150 mm each 73.00

654 Oxidised mild s teel double acting spring hinges 125 mm each 63.00

655 Oxidised mild s teel double acting spring hinges 100 mm each 47.00

656 Nickel plated mild steel piano hinges 1 mm thick 35 mm metre 24.00
wide
660 Oxidised mild steel sliding door bolt 300x16 mm each 45.00
661 Oxidised mild steel sliding door bolt 250x16 mm each 37.00
662 Oxidised mild steel door latch 300x20x6 mm each 25.00
663 Oxidised mild steel door latch 250x20x6 mm each 25.00
664 Oxidised mild s teel tow er bolt (barrel type) 250x10 mm each 25.00

665 Oxidised mild s teel tow er bolt (barrel type) 200x10 mm each 21.00
666 Oxidised mild s teel tow er bolt (barrel type) 150x10 mm each 17.00

667 Oxidised mild s teel tow er bolt (barrel type) 100x10 mm each 12.00

668 Oxidised mild steel handles 125 mm each 7.00


669 Oxidised mild steel handles 100 mm each 5.00
670 Oxidised mild steel handles75 mm each 3.00
679 Oxidised mild steel hasps and staples(safety type) 150 10 Nos 79.00
mm
680 Oxidised mild steel hasps and staples(safety type) 115 10 Nos 70.00
mm
681 Oxidised mild steel hasps and staples(safety type) 90 10 Nos 52.00
mm
682 Oxidised mild steel screw s 50 mm 100 Nos 40.00
683 Oxidised mild steel screw s 40 mm 100 Nos 35.00
684 Oxidised mild steel screw s 30 mm 100 Nos 24.00
685 Oxidised mild steel screw s 25 mm 100 Nos 16.00
686 Oxidised mild steel screw s 20 mm 100 Nos 15.00
687 Anodised Aluminium butt hinges 125x75x4 mm 10 Nos 478.00
688 Anodised Aluminium butt hinges 125x63x4 mm 10 Nos 447.00
689 Anodised Aluminium butt hinges 100x75x4 mm 10 Nos 416.00
690 Anodised Aluminium butt hinges 100x63x3.2 mm 10 Nos 390.00
691 Anodised Aluminium butt hinges 100x63x4 mm 10 Nos 354.00
692 Anodised Aluminium butt hinges 75x63x4 mm 10 Nos 281.00
693 Anodised Aluminium butt hinges 75x63x3.2 mm 10 Nos 215.00
694 Anodised Aluminium butt hinges 75x45x3.2 mm 10 Nos 98.00
696 Anodised Aluminium sliding door bolt 300x16 mm each 125.00
697 Anodised Aluminium sliding door bolt 250x16 mm each 104.00
698 Anodised Aluminium tower bolt (barrel type)300x10 mm 10 Nos 520.00

699 Anodised Aluminium tower bolt (barrel type)250x10 mm 10 Nos 440.00

700 Anodised Aluminium tower bolt (barrel type)200x10 mm 10 Nos 354.00

701 Anodised Aluminium tower bolt (barrel type)150x10 mm 10 Nos 281.00

702 Anodised Aluminium tower bolt (barrel type)100x10 mm 10 Nos 208.00

703 Anodised Aluminium handles 125 mm with plate 175 x 10 Nos 375.00
32 mm 10 Nos 375.00
704 Anodised Aluminium handles 100 mm with plate 150 x 10 Nos 260.00
32 mm 10 Nos 260.00
705 Anodised Aluminium handles 75mm with plate 125 x 32 10 Nos 208.00
mm 10 Nos 208.00
706 Anodised Aluminium kicking plate 50 cm long100x3.15 each 94.00
mm each 94.00
713 Block board construction flush door with teak wood ply sqm 1100.00
on both faces 35mm thickflush door with teak wood ply
714 Block board construction sqm 1050.00
on both faces 30mm thick
715 Block board construction flush door with teak wood ply sqm 1000.00
on both faces 25mm thick
717 Block board construction flush door with commercial sqm 632.00
ply on both faces 35mm thick
718 Block board construction flush door with commercial sqm 610.00
ply on both faces 30mm thick
719 Block board construction flush door with commercial sqm 600.00
ply on both faces 25mm thick
752 Block board construction flush door lipping sqm of 245.00
door area

753 Square vision panel in Bloc k board construction flush sqm of 86.00
door s door area

754 Circular vision panel in Block board construction flush sqm of 118.00
door door area

755 Decorative type Louvers in Block board construction sqm of 210.00


flush door door area

757 Rebate cutting in Block board construction flush door sqm of 57.00
door area

759 Decorative plywood 4 mm sqm 250.00


761 Fuel wood quintal 265.00
763 Glue kilogram 50.00
765 Hessian cloth sqm 10.00
768 Cem ent Concrete Jali 50 mm thick sqm 145.00
769 Cem ent Concrete Jali 40 mm thick sqm 115.00
770 Cem ent Concrete Jali 25 mm thick sqm 92.00
771 Kerosene oil litre 25.00
773 Unslaked lime quintal 400.00
775 Dehradun white lime quintal 400.00
776 Satna lime quintal 400.00
777 Dry hydrated lime (factory made) quintal 200.00
784 Marble dust/ powder cum 800.00
785 Marble chips up to 4mm and downsize White & black quintal 115.00

788 Marble chips large size above 4 mm White & black quintal 115.00
810 Moorum cum 333.00
811 Mud (dry) cum 20.00
815 Dry distemper kilogram 40.00
816 Oil bound washable distemper/ Acrylic distem kilogram 45.00
818 Linseed oil (double boiled) litre 55.00
820 Cem ent primer litre 60.00
821 Distemper primer litre 60.00
823 Pink primer (for wood) litre 150.00
826 Aluminium paint litre 180.00
827 Acid proof paint (chocolate or black) litre 93.00
828 Anticorrosive bituminous paint (black) litre 52.00
829 Black Japan litre 170.00
830 Enamel paint litre 170.00
831 Floor enamel paint in all s hades except green litre 170.00
833 Synthetic enamel paint in black or chocolate shade litre 170.00

834 Synthetic enamel paint in all shades except black or litre 170.00
chocolate shade
835 Plastic emulsion paint litre 150.00
845 Roofing paint for iron sheets in red colour litre 95.00
850 White lead kilogram 100.00
851 Water proofing cement paint kilogram 40.00
855 Wax polish (ready made) kilogram 150.00
856 Ordinary varnish litre 49.00
857 Superior copal varnish litre 100.00
858 Superior spar varnish litre 105.00
859 Oil type wood preservative litre 60.00
863 Putty for wood work kilogram 24.00
865 Pig lead kilogram 140.00
868 Premixed super white gypsum plaster. kilogram 5.20
869 Plaster of Paris kilogram 3.00
870 Plug each 6.00
873 Copper pins 6 mm dia 7.5 cm long each 7.50
874 Black c olour dark shade pigment kilogram 42.00
875 Red, chocolate, orange, buff or yellow (red oxide of iron) kilogram 65.00
light shade pigment
876 Green or blue medium shade pigment kilogram 45.00
886 Standard holder bat clamps for sand cast iron or cast each 20.00
iron pipes 150 mm dia
966 Sand Cast iron plain shoe 150 mm dia each 222.00
967 Copper plate kilogram 195.00
969 Pulley 25 mm dia each 18.00
973 Rolling shutter made of 80x1.25 mm machine rolled sqm 767.00
laths
974 Top cover for rolling shutters metre 400.00
975 27.5 cm long wire spring grade no 2 for rolling shutters each 170.00

976 Ball bearing for rolling shutters each 280.00


977 Extra for mechanical devices chain and cranked sqm 400.00
operation for operating rolling shutters : exceeding 10.00
sq.m and up to 16.80 sqm area of door

978 Extra for mechanical devices chain and cranked sqm 450.00
operation for operating rolling shutters : exceeding 10.00
sq.m and exceeding 16.80 sqm area of door

979 Royalty for good earth cum 11.00


980 Royalty for sludge cum 60.00
982 Coarse sand (zone III) cum 300.00
983 Fine sand (zone IV) cum 300.00
992 Galvanised steel plain sheets quintal 3450.00
994 Standard quality hard board sheet 3 mm thick sqm 103.00
996 Standard quality hard board sheet 4.5 mm thick sqm 120.00
999 Shellac kilogram 192.00
1000 Spirit litre 37.00
1001 Spun yarn kilogram 30.00
1002 Mild steel round bar 12 mm dia and below quintal quintal 4300.00
1003 Mild steel round bar above 12 mm dia quintal quintal 4300.00
1004 Average rate of Mild steel round bars for reinforcements quintal 4300.00
quintal
1005 Twisted steel / deformed bars quintal quintal 4300.00
1006 Mild steel square bars quintal 4300.00
1007 Structural steel such as tees, angles channels and R.S. quintal 4600.00
joists
1008 Flats up to 10 mm in thickness quintal quintal 4600.00
1009 Flats exceeding 10 mm in thickness quintal 4600.00
1010 Mild steel plates quintal 4600.00
1013 Mild steel sheets for tanks quintal 4600.00
1015 Mild steel expanded metal 20x60 mm strands sqm 250.00
1019 Mild steel hooks each 25.00
1020 Mild steel rivets quintal 3500.00
1021 Hard drawn steel wire fabric sqm 350.00
1022 Galvanised steel bolts & nuts 6 mm dia and 25 mm long 10 nos 60.00
round head with slots
1023 Galvanised steel J or L hooks 8 mm dia 10 nos 60.00
1024 Galvanised steel bolts & nuts 10 mm dia and 125 mm each 12.00
long round head with slots
1025 Mild stel bolts 6 mm dia and 25 mm long with hexagonal 10 nos 20.00
head
1028 Straining bolts each 52.00
1029 Galvanised steel barbed wire quintal 6500.00
1030 Galvanised steel turn buckles each 10.00
1031 Galvanised steel bolts & nuts 10 mm dia and 27 cm each 15.00
long both sides threaded with 4 galvanised steel nuts

1032 Galvanised steel bolts 10 mm dia and 7 cm long with each 15.00
nuts
1034 Bolts and nuts up to 300 mm in length quintal 7000.00
1035 Bolts and nuts above 300 mm in length quintal 7000.00
1036 Iron pintels including welded pin each 30.00
1143 Steel beading metre 15.00
1145 Aluminium Plain Strip edging 38x12x3 mm metre 78.00
1149 Glass strip 4 mm thick40 mm deep metre 6.00
1151 Boundary stone top chisel dressed 15x15x90 cm metre 46.00
1154 Through and bond stone 100 Nos 970.00
1157 Stone for masonry work cum 332.00
1158 Stone for pitching 15 cm x 22.5 cm cum 332.00
1159 Stone dust cum 700.00
1160 Red sand stone block 10 cudm 45.00
1161 White sand stone block 10 cudm 50.00
1163 White sand stone slab 75 mm thick (un-dressed) sqm 256.00
1164 Red sand stone slab 40 mm thick (un-dressed) sqm 120.00
1165 White sand stone slab 40 mm thick (un-dressed) sqm 140.00
1166 Red sand stone slab 30 mm thick (un-dressed) sqm 97.00
1168 Kota stone slab 20 mm to 25 mm thick (semi-polished) sqm 250.00

1169 Kota stone slab 25mm thick (rough chiseled) sqm 175.00
1174 Red sand stone slab 45 mm and 50 mm thick (un- sqm 430.00
dressed)
1175 White sand stone slab 45 mm and 50 mm thick (un- sqm 160.00
dressed)
1177 Stone grit 6 mm and dow n size or pea sized gravel cum 700.00
1179 Crushed stone 2.36 mm to 12.5 mm size cum 675.00
1186 Superior class teak wood such as Dandeli, Balarshah or 10 cudm 895.00
Malabar in planks
1187 First class teak wood in scantling 10 cudm 492.00
1188 First class teak wood in planks 10 cudm 506.00
1189 Second class teak wood in scantling 10 cudm 394.00
1190 Second class teak wood in planks 10 cudm 410.00
1194 Second class deodar wood in planks 10 cudm 335.00
1196 First class kail wood in planks 10 cudm 186.00
1197 Second class kail wood in scantling 10 cudm 160.00
1198 Second class kail wood in planks 10 cudm 178.00
1199 Sal wood in scantling 10 cudm 218.00
1201 Precast terrazzo tiles 22 mm thick (light shade) sqm 198.00
1202 Precast terrazzo tiles 22 mm thick(medium shade) sqm 175.00

1203 Precast terrazzo tiles 22 mm thick (dark shade) sqm 170.00


1207 G.I. Limpet washer 100 Nos 20.00
1208 Bitumen washer 100 Nos 18.00
1209 G.I. plain washer thick 100 Nos 27.00
1210 G.I. plain washer thin 100 Nos 20.00
1211 G.I. plain washer for seam bolts 100 Nos 21.00
1213 Water proofing materials kilogram 20.00
1214 Welding by gas plant cm 1.00
1215 Welding by electric plant cm 1.00
1216 Whiting quintal 329.00
1219 Wire nails kilogram 70.00
1220 Wire mesh (rabbit) sqm 38.00
1221 20 mm dia holding dow n bolts quintal 3800.00
1222 Mild steel sheets with bolts and nuts to rest on pintels each 75.00

1224 Hard drawn steel wire quintal 3500.00


1225 Mild steel flat strap fitting quintal 2900.00
1227 Chequered terrazzo tiles 22 mm thick(light shade) sqm 230.00
1228 Chequered terrazzo tiles 22 mm thick(medium shade) sqm 200.00

1229 Chequered terrazzo tiles 22 mm thick (dark shade) sqm 170.00


1231 Extra for selected planks of second class teakwood 10 cudm 72.00

1234 Aluminium Plain Strip edging 57x12x3 mm metre 105.00


1235 Diesel oil litre 53.17
1237 Cutting marble or sand stone slab up to 50 mm thick by metre 6.00
mechanical device
1238 Extra for selected planks of first class teakwood 10 cudm 80.00
1241 Com mercial LPG in cylinder. kg 35.00
1301 Bleaching powder quintal 1550.00
1304 Surface box for stop cock each 72.00
1305 Surface box for sluice valve each 140.00
1307 Surface box for water meter each 185.00
1309 C.I. bracket for wash basin and sinks pair 48.00
1314 C.P.brass chain with 32 mm dia rubber plug each 21.00
1315 C.P.brass chain with 40 mm dia rubber plug each 22.00
1330 Clamps and M.S. stays including bolts and nuts for 100 each 28.00
mm pipe
1331 M.S.Holder bat clamp of approved design for 100 mm each 13.00
S.C.I. pipe
1332 M.S.Holder bat clam p of approved design for75 mm each 11.00
S.C.I. pipe
1334 Clamps and M.S. stays including bolts and nuts for 50 each 20.00
mm pipe
1335 Clamps and M.S. stays including bolts and nuts for 75 each 25.00
mm pipe
1336 Clearing eye with chain and lid 100 mm dia each 37.00
1337 Clearing eye with chain and lid 150 mm dia each 41.00
1339 Brass bib-cock 15 mm dia each 157.00
1340 Brass bib-cock 20 mm dia each 193.00
1342 Brass stop-cock 15 mm dia each 157.00
1343 Brass stop-cock 20 mm dia each 193.00
1350 Mosquito proof coupling of approved design each 23.00
1352 C.I. cover and fram e 300x300 mm inside each 265.00
1353 C.I.cover without frame 300x300mm inside i/c cover of each 170.00
4.50 kg
1354 Rectangular cover 455x610 mm with frame (low duty) each 1395.00

1355 Rectangular cover 455x610mm without frame (low duty) each 844.00

1356 500 mm dia cover with frame (medium duty) each 4257.00
1357 500 mm dia cover without frame (medium duty) each 2129.00
1360 C.I.mouth, brass ferrule 15 mm dia each 80.00
1361 C.I.mouth, brass ferrule 20 mm dia each 114.00
1362 C.I.mouth, brass ferrule 25 mm dia each 156.00
1363 Vitreous china foot rests 250x130x30 mm pair 79.00
1364 C.I. grating 100x100 mm each 10.00
1366 C.I. grating 150x150 mm each 19.00
1367 C.I. grating 180x180 mm each 23.00
1369 S.C.I. gully or nahani grating 100 mm dia each 10.00
1373 Rubber insertions for80 mm dia pipe joints each 9.00
1374 Rubber insertions for 100 mm dia pipe joints each 12.00
1375 Rubber insertions for 125 mm dia pipe joints each 13.00
1376 Rubber insertions for 150 mm dia pipe joints each 15.00
1377 Rubber insertions for 200 mm dia pipe joints each 20.00
1378 Rubber insertions for 250 mm dia pipe joints each 30.00
1379 Rubber insertions for 300 mm dia pipe joints each 38.00
1380 Rubber insertions for 350 mm dia pipe joints each 45.00
1381 Rubber insertions for 400 mm dia pipe joints each 66.00
1382 Rubber insertions for 450 mm dia pipe joints each 83.00
1383 Rubber insertions for 500 mm dia pipe joints each 106.00
1384 Rubber insertions for 600 mm dia pipe joints each 118.00
1392 Mirror of superior make glass 60x45 cm each 249.00
1396 Vitreous china pedestal for wash basin each 527.00
1397 Pig lead kilogram 58.00
1464 S & S.C.I.standard specials up to 300 m m dia (heavy quintal 2400.00
class)
1466 S & S.C.I.standard specials over 300 mm dia (heavy quintal 2595.00
class)
1468 Flanged C.I. standard specials up to 300 mm dia(heavy quintal 4320.00
class)
1470 Flanged C.I. standard specials over 300 mm dia(heavy quintal 4772.00
class)
1472 Casing pipe 100 mm dia metre 292.00
1532 Flush pipe with union spreaders and clamps all in C.P. each 204.00
brass for single stall
1533 Flush pipe with union spreaders and clamps all in C.P. each 333.00
brass for double stall
1534 Flush pipe with union spreaders and clamps all in C.P. each 415.00
brass
Flush for range of three
1535 pipe with union stall
spreaders and clamps all in C.P. each 465.00
1540 brass for range of four stall
Flush pipe and spreaders G.I.for single set of one each 138.00
squatting plate urinal
1541 Flush pipe and spreaders G.I.for range of two squatting each 203.00
plates urinal
1542 Flush pipe and spreaders G.I.for range of three squatting each 255.00
plates urinal
1543 Flush pipe and spreaders G.I.for range of four squatting each 320.00
plates urinal
1545 G.I. pipes 15 mm dia metre 100.00
1546 G.I. pipes 20 mm dia metre 120.00
1547 G.I. pipes 25 mm dia metre 175.00
1548 G.I. pipes 32 mm dia metre 250.00
1549 G.I. pipes 40 mm dia metre 290.00
1550 G.I. pipes 50 mm dia metre 350.00
1551 G.I. pipes 65 mm dia metre 475.00
1552 G.I. pipes 80 mm dia metre 595.00
1555 G.I. back (jam) nuts25 mm dia each 5.00
1559 G.I. back (jam) nuts65 mm dia each 15.00
1608 G.I. tees (equal) 25 mm each 38.00
1612 G.I. tees (equal) 65 mm each 215.00
1614 G.I. inlet connection each 50.00
1616 S.C.I. soil, waste and vent single socketed pipe1.80 each 537.00
metres long : 75mm dia
1617 S.C.I. soil, waste and vent single socketed pipe1.80 each 610.00
metres long: 100 mm dia
1618 S.C.I. soil, waste and vent single socketed pipe1.80 each 1205.00
metres long: 150mm dia
1620 S.C.I. plain bend75mm dia each 140.00
1621 S.C.I. plain bend 100mm dia each 178.00
1622 S.C.I. plain bend 150mm dia each 407.00
1624 S.C.I. bend with access door 75mm dia each 161.00
1625 S.C.I. bend with access door 100mm dia each 194.00
1627 S.C.I. plain single equal junctions75x75x75 mm dia each 205.00
1628 S.C.I. plain single equal junctions100x100x100 mm dia each 265.00

1630 S.C.I. single equal junctions75x75x75 mm dia with each 224.00


access door.
1631 S.C.I. single equal junctions 100x100x100 mm dia with each 297.00
access door.
1633 S.C.I. plain double equal junctions 75x75x75x75 mm dia each 296.00

1634 S.C.I. plain double equal junctions100x100x100x100 mm each 394.00


dia
1636 S.C.I. double equal junctions75x75x75x75 mm dia with each 333.00
access door. equal junctions 100x100x100x100 mm dia
1637 S.C.I. double each 417.00
with access door
1639 Slotted cowl (terminal guard )75 mm dia each 109.00
1640 Slotted cowl (terminal guard ) 100 mm dia each 152.00
1641 G.I. Union 15 mm nominal bore each 45.00
1642 G.I. Union 20 mm nominal bore each 55.00
1643 G.I. Union 25 mm nominal bore each 66.00
1644 G.I. Union 32 mm nominal bore each 110.00
1645 G.I. Union 40 mm nominal bore each 132.00
1646 G.I. Union 50 mm nominal bore each 169.00
1647 G.I. Union 65 mm nominal bore each 180.00
1648 G.I. Union 80mm nominal bore each 250.00
1649 Polyethylene water storage tank with cover and suitable per litre 5.00
locking arrangement
1653 Sand cast iron S&S plain single unequal junctions : each 288.00
100x100x75 mm dia
1656 Sand cast iron S&S single unequal junctions: 100x100x75 each 321.00
mm dia with access door
1659 Sand cast iron S&S plain double unequal junctions : each 423.00
100x100x75x75 mm dia
1662 Sand cast iron S&S double unequal junctions: each 453.00
1666 100x100x75x75 mm dia with access door
Sand cast iron heel rest bend75mm dia each 165.00
1667 Sand cast iron heel rest bend 100mm dia each 197.00
1669 S.C.I. single equal invert branch of required each 239.00
1670 degree75x75x75 mm dia
S.C.I. single equal invert branch of required degree each 321.00
100x100x100 mm dia
1672 S.C.I. double equal invert branc h of required degree each 314.00
75x75x75x75 mm dia
1673 S.C.I. double equal invert branch of required degree each 422.00
100x100x100x100 mm dia
1674 S.C.I. single unequal invert branch of required degree each 382.00
100x100x75 mm dia
1677 S.C.I. double unequal invert branch of required degree each 458.00
100x100x75x75 mm dia
1682 S.C.I. door pieces 75 mm dia each 211.00
1683 S.C.I. door pieces 100 mm dia each 291.00
1685 S.C.I. collar 75 mm dia each 82.00
1686 S.C.I. collar 100 mm dia each 110.00
1687 Unplasticised P.V.C. connection pipe with brass union 30 each 18.00
cm long 15mm bore
1688 Unplasticised P.V.C. connection pipe with brass union 30 each 25.00
cm long 20 mm bore
1689 Unplasticised P.V.C. connection pipe with brass union 45 each 25.00
cm long 15 mm bore
1690 Unplasticised P.V.C. connection pipe with brass union 45 each 35.00
cm long 20 mm bore
1693 S.C.I. hand pump each 450.00
1700 R.C.C. pipes NP2 class 100 mm dia metre 118.00
1701 R.C.C. pipes NP2 class 150 mm dia metre 135.00
1702 R.C.C. pipes NP2 class 250 mm dia metre 157.00
1703 R.C.C. pipes NP2 class 300 mm dia metre 228.00
1704 R.C.C. pipes NP2 class 450 mm dia metre 333.00
1705 R.C.C. pipes NP2 class 500 mm dia metre 398.00
1706 R.C.C. pipes NP2 class 600 mm dia metre 642.00
1707 R.C.C. pipes NP2 class 700 mm dia metre 719.00
1709 R.C.C. pipes NP2 class 800 mm dia metre 836.00
1710 R.C.C. pipes NP2 class 900 mm dia metre 986.00
1711 R.C.C. pipes NP2 class 1000 mm dia metre 1243.00
1712 R.C.C. pipes NP2 class 1100 mm dia metre 1500.00
1713 R.C.C. pipes NP2 class 1200 mm dia metre 1543.00
1714 R.C.C. collarsNP2 class 100 mm dia each 16.00
1715 R.C.C. collarsNP2 class 150 mm dia each 21.00
1716 R.C.C. collarsNP2 class 250 mm dia each 34.00
1717 R.C.C. collarsNP2 class 300 mm dia each 42.00
1718 R.C.C. collarsNP2 class 450 mm dia each 63.00
1719 R.C.C. collarsNP2 class 500 mm dia each 73.00
1720 R.C.C. collarsNP2 class 600 mm dia each 92.00
1721 R.C.C. collarsNP2 class 700 mm dia each 102.00
1723 R.C.C. collarsNP2 class 800 mm dia each 146.00
1724 R.C.C. collarsNP2 class 900 mm dia each 178.00
1725 R.C.C. collarsNP2 class 1000 mm dia each 210.00
1726 R.C.C. collarsNP2 class 1100 mm dia each 241.00
1727 R.C.C. collarsNP2 class 1200 mm dia each 280.00
1854 Stoneware pipes grade A (60 cm long) 100 mm dia each 30.00
1855 Stoneware pipes grade A (60 cm long) 150 mm dia each 42.00
1856 Stoneware pipes grade A (60 cm long) 200 mm dia each 80.00
1857 Stoneware pipes grade A (60 cm long) 230 mm dia each 85.00
1858 Stoneware pipes grade A (60 cm long) 250 mm dia each 113.00
1859 Stoneware pipes grade A (60 cm long) 300 mm dia each 165.00
1863 Fire clay kitchen sink: 600x450x250 mm each 1192.00
1871 White vitreous china laboratory sink450x300x150 mm each 664.00

1872 White vitreous china laboratory sink600x450x200 mm each 1400.00


1875 White plastic seat (solid)w ith lid C.P.brass hinges and each 275.00
1876 rubber buffers
Black plastic seat (solid) with lid C.P.brass hinges and each 250.00
rubber buffers
1878 Shower rose C.P.brass for 15 to 20 mm inlet 100 mm dia each 28.00

1879 Shower rose C.P.brass for 15 to 20 mm inlet 150 mm dia each 40.00

1881 Spun yarn kilogram 30.00


1882 Strainer brass 40 mm dia 1.5 metre long each 405.00
1885 15 mm C.P.brass tap each 180.00
1889 C.P.brass toilet paper holder of standard size each 70.00
1891 C.I. trap for standard urinal with vent arm with operating each 125.00
and other coulings in CP brass : 50mm dia
1893 C.I. trap for standard urinal with vent arm with operating each 158.00
and other coulings in CP brass : 80mm dia
1895 C.P.brass trap40 mm dia each 99.00
1896 100 mm S.C.I. trap with vent heel each 260.00
1897 100 mm S.C.I. trap with 100 mm inlet and 100 mm each 221.00
outlet
1898 100 mm S.C.I. trap with 100 mm inlet and75 mm each 164.00
outlet
1900 S.W. gully trap P type 100x100 mm each 55.00
1902 S.W. gully trap P type 150x100 mm each 86.00
1904 S.W. gully trap P type 180x150 mm each 160.00
1913 Vitreous china lipped front urinal each 380.00
1915 Vitreous china squatting plate urinal each 610.00
1922 H.P. or L.P. ball valve with polythene floats: 15 mm dia each 175.00

1923 H.P. or L.P. ball valve with polythene floats: 20 mm dia each 260.00

1924 H.P. or L.P. ball valve with polythene floats: 25 mm dia each 300.00

1927 Brass full way valve with C.I. wheel (screwed end) 25 each 235.00
mm dia
1928 Brass full way valve with C.I. wheel (screwed end) 32 each 296.00
mm dia
1929 Brass full way valve with C.I. wheel (screwed end) 40 each 330.00
mm dia
1930 Brass full way valve with C.I. wheel (screwed end) 50 each 483.00
mm dia
1931 Brass full way valve with C.I. wheel (screwed end) 65 each 700.00
mm dia
1932 Brass full way valve with C.I. wheel (screwed end) 80 each 1160.00
mm dia
1933 Gunmetal non-return valve-horizontal (screwed end) 25 each 238.00
mm dia
1934 Gunmetal non-return valve-horizontal (screwed end) 32 each 305.00
mm dia
1935 Gunmetal non-return valve-horizontal (screwed end) 40 each 410.00
mm dia
1936 Gunmetal non-return valve-horizontal (screwed end) 50 each 618.00
mm dia
1937 Gunmetal non-return valve-horizontal (screwed end) 65 each 1085.00
mm dia
1938 Gunmetal non-return valve-horizontal (screwed end) 80 each 1540.00
mm dia
1940 C.I.sluice valve (with caps ) class I : 100 mm dia each 4400.00
1941 C.I.sluice valve (with caps ) class I : 125 mm dia each 6000.00
1942 C.I.sluice valve (with caps ) class I : 150 mm dia each 7500.00
1943 C.I.sluice valve (with caps ) class I : 200 mm dia each 9600.00
1944 C.I.sluice valve (with caps ) class I : 250 mm dia each 12000.00
1945 C.I.sluice valve (with caps ) class I : 300 mm dia each 14400.00
1947 Vitreous china flat back wash basin 630x450 mm each 500.00
1949 Vitreous china angle back wash basin 600x480 mm each 540.00
1950 Vitreous china angle back wash basin 400x400 mm each 400.00
1951 C.P. brass waste 32 mm each 48.00
1952 C.P. brass waste 40 mm each 53.00
1953 Vitreous china Indian type w.c. pan size 580 mm each 350.00
1954 Vitreous china orrisa type w.c. pan size 580 mm each 550.00
1955 Vitreous china pedestal type water closet each 600.00
1956 Bolts and nuts 16 mm dia 60 mm long each 8.00
1957 Bolts and nuts 16 mm dia 65 mm long each 8.00
1958 Bolts and nuts 20 mm dia 65 mm long each 12.00
1959 Bolts and nuts 20 mm dia 70 mm long each 12.00
1960 Bolts and nuts 20 mm dia 75 mm long each 12.00
1961 Bolts and nuts 20 mm dia 80 mm long each 13.00
1962 Bolts and nuts 24 mm dia 85 mm long each 24.00
1963 Bolts and nuts 24 mm dia 90 mm long each 26.00
1964 Bolts and nuts 27 mm dia 100 mm long each 30.00
1965 White vitreous china dual purpose closet (Anglo Indian each 850.00
W.C .) suitable for use as squatting pan or European type
water closet as per manuacturer’s specifications
1970 Vitreous china foot rests 250x125x25 mm pair 180.00
1980 Fly ash cum 6.00
1984 F.P.S. bricks tile class designation 35 /100 1000 nos 1600.00
1986 Modular bricks c lass designation 35/75 1000 nos 1600.00
2391 Strips-Aluminium fluted 3.15mm thick and 150mm metre 216.00
wide
2392 Strips Aluminium fluted 3.15m m thick and 200mm metre 288.00
wide
2406 Float glass sheet of nominal thickness 4 mm (weight sqm 248.00
not less than 10 kg/sqm)
2407 Float glass sheet of nominal thickness 5.5 mm.(weight sqm 340.00
not less than 13.5kg/sqm).
2412 Ply wood 5 ply with commercial ply on both faces 6 sqm 282.00
mm thick
2447 Hollock ballies 125 mm diameter metre 60.00
2449 Oxidised mild steel pull bolt lock (locking bolt) of size 85 each 27.00
mm x 42 mm with screws, bolts, nuts and washers
complete
2451 Brass cupboard lock 6 levers (best make of approved each 36.00
quality) 40 mm size
2452 Brass cupboard lock 6 levers (best make of approved each 43.00
quality) 50 mm size
2453 Brass cupboard lock 6 levers (best make of approved each 55.00
quality) 65 mm size
2454 Brass cupboard lock 6 levers (best make of approved each 70.00
quality) 75 mm size
2455 Brass hanging type door stopper 150 mm each 46.00 each 46.00
2456 Hydraulic door closer bottle type M.S. body with each 600.00
necessary accesssories and screws complete
2459 Anodised Aluminium hanging type door stopper each 80.00
2464 Anodised Aluminium pull bolt lock (locking bolt) of size each 34.00
85 mm x42mm with screws, bolts ,nuts and washers
complete

2465 Anodised Aluminium Casement stay 250 mm each 36.00


2466 Hollock wood in scantling 10 cudm 217.00
2467 Chromium plated Brass pull bolt lock (locking bolt) of size each 130.00
85 mm x42mm with screws, bolts, nuts and washers
complete

2468 Nickeled Chromium Brass cupboard lock 40 mm size each 38.00

2469 Nickeled Chromium Brass cupboard lock 50 mm size each 53.00

2470 Nickeled Chromium Brass cupboard lock 65 mm size each 64.00

2471 Nickeled Chromium Brass cupboard lock 75 mm size each 75.00

2480 Ply wood 5 ply w ith teak ply on both faces 9 mm thick sqm 693.00

2481 Ply wood 5 ply with teak ply on one face and commercial sqm 550.00
ply on another face 9mm thick
2483 Ply wood 7 ply with teak ply on one face and commercial sqm 585.00
ply on another face 9mm thick
2500 Extra for selected planks of second class deodar w ood 10 cudm 59.00

2504 Kiln seasoning of timber cum 539.00


2505 Hollock wood in planks 10 cudm 230.00
2602 F.P.S. bricks class designation75 1000 N os 1600.00
2603 F.P.S. bricks class designation50 1000 N os 1600.00
2704 Aluminium Strip 40 mm wide and 2 mm thick kilogram 195.00
2710 White m arble makrana second quality plain veined quintal 105.00
stone pieces for crazy flooring
2750 8 mm thick granite stone tiles (mirror polished of all sqm 555.00
shades)
2751 8 mm thick marble tiles (polished) Raj Nagar sqm 294.00
2901 Stone Aggregate (Single size) : 100 mm nominal size cum 700.00

2902 Stone Aggregate (Single size) : 80 mm nominal size cum 700.00


2903 Stone chippings/ screenings 4.75 mm nominal size cum 350.00

2904 Stone chippings/ screenings 150 micron nominal size cum 350.00

2908 Over burnt (Jhama) Brick Aggregate: 120 mm to 40 mm cum 285.00


size
2909 Over burnt (Jhama) Brick Aggregate: 90 mm to 40 mm cum 320.00
size
2910 Stone chippings/ screenings 12.5/ 13.2 mm nominal s cum 1050.00
ize
2911 Stone chippings/ screenings 10/ 11.2 mm nominal size cum 1050.00

2914 Solvent kilogram 60.00


2916 Paving Asphalt 80/100 penetration tonne 42000.00
3002 Polyvinyl chloride sheet 400 micron thick sqm 26.00
3004 Stone ware spouts 100 mm dia 60 cm long each 28.00
3050 Galvanised steel corrugated sheets quintal 6000.00
3080 Gunmetal non-return valve-horizontal (screwed end) 25 each 455.00
mm dia
3084 Gunmetal non-return valve-horizontal (screwed end) 32 each 550.00
mm dia
3088 Gunmetal non-return valve-horizontal (screwed end) 40 each 680.00
mm dia
3092 Gunmetal non-return valve-horizontal (screwed end) 50 each 900.00
mm dia
3096 Gunmetal non-return valve-horizontal (screwed end) 65 each 1050.00
mm dia
3213 Vitreous china Surgeon type w ash basin of size 660x460 each 810.00
mm each 810.00
3228 600x120 mm glass shelf with anodised aluminium angle each 95.00
frame, C.P. brass brackets and guard rail of standard size

3229 Vitreous china flat back wash basin 550x400 mm each 450.00
3300 Gunmetal non-return valve-horizontal (screwed end) 80 each 2038.00
mm dia
3311 C.I.sluice valve (with caps) class II : 100 mm dia each 1950.00
3314 C.I.sluice valve (with caps) class II : 125 mm dia each 2465.00
3317 C.I.sluice valve (with caps) class II : 150 mm dia each 3000.00
3320 C.I.sluice valve (with caps) class II : 200 mm dia each 5800.00
3321 C.I.sluice valve (with caps) class II : 250 mm dia each 8200.00
3326 C.I.sluice valve (with caps) class II : 300 mm dia each 10250.00
3617 C.P. Brass union 40 mm dia each 130.00
3620 C.C.I.(spun) socketed s oil, waste and vent pipe 1.80 each 978.00
metres long : 100mm dia
3621 C.C.I.(spun) socketed s oil, waste and vent pipe 1.80 each 846.00
metres long : 75mm dia
3624 S.C.I. S&S bends with access door100mm dia each 225.00
3625 S.C.I. S&S bends with access door75mm dia each 179.00
3628 S.C.I. S&S bend100mm dia each 190.00
3629 S.C.I. S&S bend75mm dia each 143.00
3634 S.C.I. S&S heel rest sanitary bend 100mm dia each 233.00
3635 S.C.I. S&S heel rest sanitary bend 75mm dia each 204.00
3640 S.C.I. S&S single equal junctions100x100x100 mm each 367.00
3641 S.C.I. S&S single equal junctions75x75x75 mm each 276.00
3644 S.C.I. S&S single equal junctions with access door each 396.00
100x100x100 mm
3645 S.C.I. S&S single equal junctions with access door each 294.00
75x75x75 mm
3650 S.C.I. S&S double equal junctions100x100x100x100 mm each 467.00

3651 S.C.I. S&S double equal junctions75x75x75x75 mm each 373.00


3654 S.C.I. S&S double equal junctions with access door each 502.00
100x100x100x100 m m.
3655 S.C.I. S&S double equal junctions w ith access door each 400.00
75x75x75x75 mm
3660 S.C.I. S&S single unequal junctions100x100x75 mm each 461.00

3664 S.C.I. S&S single unequal junctions with access door each 523.00
100x100x75 mm
3670 S.C.I. S&S double unequal junctions100x100x75x75 mm each 639.00
each 639.00
3674 S.C.I. S&S double unequal junctions with access door each 700.00
100x100x75x75mm
3681 S.C.I. S&S single equal invert branch of required degree each 325.00
100x100x100 mm dia
3682 S.C.I. S&S single equal invert branch of required degree each 247.00
75x75x75 mm dia
3685 S.C.I. S&S double equal invert branch of required degree each 414.00
100x100x100x100 mm dia
3686 S.C.I. S&S double equal invert branch of required degree each 334.00
75x75x75x75 mm dia
3690 S.C.I. S&S single unequal invert branch of required degree each 422.00
100x100x75 mm dia
3695 S.C.I. S&S double unequal invert branch of required each 574.00
degree 100x100x75x75 mm
3699 S.C.I. S&S, 75 mm offset for75 mm dia pipe each 179.00
3707 S.C.I. S&S, 150 mm offset for75 mm dia pipe each 223.00
3708 S.C.I. S&S, 150 mm offset for100 mm dia pipe each 306.00
3712 S.C.I. S&S, 114 mm offset for75 mm dia pipe each 220.00
3713 S.C.I. S&S, 114 mm offset for100 mm dia pipe each 289.00
3716 S.C.I. S&S, 152 mm offset for75 mm dia pipe each 275.00
3717 S.C.I. S&S, 152 mm offset for100 mm dia pipe each 361.00
3728 S.C.I S&S door pieces 100 mm dia each 230.00
3729 S.C.I S&S door pieces 75 mm dia each 176.00
3733 S.C.I S&S, Slotted Cowl (Terminal Guard) 100 mm each 154.00
3734 S.C.I S&S, Slotted Cowl (Terminal Guard) 75 mm each 142.00
3738 S.C.I S&S, collars 100 mm each 161.00
3739 S.C.I S&S, collars 75 mm each 115.00
3746 S.C.I. S&S, 76 mm offset for75 mm dia pipe each 126.00
3747 S.C.I. S&S, 76 mm offset for100 mm dia pipe each 220.00
3749 Vitreous china toilet paper holder of standard size each 89.00

3860 560 mm dia cover with frame (Heavy duty) each 7634.00
3861 560 mm dia cover without frame (Heavy duty) each 3664.00
4006 Pressed steel door frames (mild steel sheet 1.25mm) metre 170.00
Profile “B”
4007 Pressed steel door frames (mild steel sheet 1.25mm) metre 187.00
Profile “C”
4008 Pressed steel door frames (mild steel sheet 1.25mm) metre 214.00
Profile “E”
4009 Mild steel tubes hot finished welded type kilogram 38.00
4010 Mild steel tubes hot finished seamless type kilogram 38.00
4011 Mild steel tubes electric resistant or induction butt kilogram 53.00
welded
4012 Circular C.I. Box for ceiling fan each 35.00 each 35.00
4013 Pulley 40 mm dia each 19.00
4014 Ready made steel door with necessary hinges, lugs and sqm 1406.00
glazing clips excluding other fittings & their fixing

4201 Aluminium primer litre 63.00


4202 Red oxide Zinc chromate primer litre 58.00
4203 Copper acetate kilogram 228.00
4204 Hydrochloric acid kilogram 27.00
4205 Copper chloride kilogram 244.00
4206 Copper nitrate kilogram 173.00
4207 Ammonium chloride kilogram 12.00
5001 Mobil oil litre 95.00
6001 White m arble slab Makrana second quality plain veined sqm 1722.00
18 mm thick
6007 Pink marble slab plain 18mm thick sqm 546.00
6010 Udaypur green marble slab plain 18m m thick sqm 580.00
6019 Black Zebra marble slab plain 18mm thick sqm 415.00
6501 Sand zone V (J amuna) cum 175.00
7001 Brass 100mm mortice latch and lock w ith6 levers each 150.00
without pair of handles
7003 Pair of Anodised Aluminium lever handles for 100mm each 195.00
mortice latch and lock
7004 Vitreous china flat back wash basin 450x300 mm each 360.00
7005 Vitreous china 10 litres low level cistern w ithout fittings each 824.00

7006 Vitreous china 10 litres low level cistern with fittings each 1390.00

7008 F.P.S. clay fly ash bricks class designation 75 1000 nos 1412.00
7009 Gypsum board sqm 140.00
7010 Ceiling sections metre 36.00
7011 Perimeter channel metre 23.00
7012 Interm ediate channel metre 38.00
7013 Ceiling angle metre 16.00
7014 Connecting clips each 5.00
7015 Soffit cleat each 3.00
7016 Joint filler kilogram 19.00
7017 Joint finisher kilogram 22.00
7018 Joint tape roll roll 120.00
7019 Dash fastener/ Chemical fastener each 8.00
7020 All drive screws ( for gypsum board) 100 nos 40.00
7021 Primer ( for gypsum board) litre 76.00
7022 Chlorpyriphos 20% E.C. / Lindane 20% E.C. litre 150.00
7023 Chromium plated brackets ( curtain rods) each 5.00
7024 Acid Proof cement tonne 7400.00
7027 M.S. Butt hinges 125x90x4 mm 10 nos 80.00
7029 Galvanised wire mes h of average width of aperture 1.4 sqm 142.00
mm and nominal dia. of wire 0.63 mm
7032 Frosted glass sheet of nominal thickness 4 mm sqm 257.00
(weighing not less than 10 kg/sqm)
7034 Nickel plated M.S. pipe 20 mm dia. metre 54.00
7035 Nickel plated M.S. Brackets for curtain rod 20 mm each 3.00
7036 Nickel plated M.S. Brackets for curtain rod 25 mm each 4.00
7040 Oxidised mild steel screw s 35 mm 100 nos 28.00
7042 Mild steel conduit pipe (heavy type) ISI marked-20 mm metre 44.00
dia.
7043 Mild steel conduit pipe (heavy type) ISI marked-25 mm metre 49.00
dia.
7044 Rolling shutters of 80x0.90 mm laths sqm 576.00
7045 Rolling shutters of 80x1.2 m m laths sqm 615.00
7046 Top cover of Rolling shutters 0.90 mm thick metre 205.00
7047 Top cover of Rolling shutters 1.20 mm thick metre 228.00
7048 Raw l plug 50 mm (designation 10 no.) each 7.00
7049 Teak wood lipping of size 25x3 mm in pelmets metre 16.00
7055 Flat pressed 3 layer and graded particle board (medium sqm 301.00
density) Grade 1 conform ing to IS : 3087 - 18 mm thick

7056 Aluminium tee channel (heavy duty) w ith rollers and metre 35.00
stop end
7059 Aluminium hanging floor door stopper with twin rubber & each 44.00
stopper
7060 Hydraulic door closer tubular type Aluminium section each 765.00
body
7063 Oxidised M.S.casement stay (straight peg type) 300 mm each 14.00
not less than .33 kg
7064 Oxidised M.S.casement stay (straight peg type) 250 mm each 12.00
not less than .28 kg
7065 Oxidised M.S.casement stay (straight peg type) 200 mm each 11.00
not less than 0.24 kg
7068 Extra for providing grilled rolling shutters with 8 mm dia sqm 185.00
M.S. rod sqm 185.00
7070 Chequered precast cement concrete tiles 22mm thick sqm 415.00
using marble chips of size 6mm - Light shade using
white Cement

7071 White marble Raj Nagar plain 20 mm thick (slab area sqm 415.00
0.10 sqm to 0.20 sqm)
7077 Acid and alkali resistant tiles 300x300 mm size, 10 m m 10 nos 460.00
thick
7087 S.C.I. Tee 150 mm each 460.00
7090 Expanded polystyrene type N- Normal s sqm 108.00
7091 Expanded polystyrene type - SE sqm 131.00
7095 Stainless steel kitchen sink - with drain board bowl depth each 4900.00
250 mm.
7096 Stainless steel kitchen sink - with drain board 510 x each 4600.00
1040mm
Stainless bowl
steeldepth 225mm
7097 kitchen sink - with drain board 510 x each 4100.00
1040mm bowl depth 200mm
7098 Stainless steel kitchen sink - with drain board each 2600.00
510x1040mm bowl depth 178mm
7101 Stainless steel kitchen sink - without drain board each 2700.00
7102 610x510mm bowlkitchen
Stainless steel depth 200mm
sink - without drain board each 2500.00
7103 610x460mm bowl depth 200mm
Stainless steel kitchen sink - without drain board each 1600.00
7104 470x420mm bowl
Coloured Orissa depthW.C.
pattern 178mmpan 580x440 mm each 1043.00
7105 Coloured Pedestal type W.C. pan 580x440 mm (European each 900.00
type)
7106 Coloured Vitreous china 10 lit. low level cistern each 1300.00
7107 Coloured (other than black) solid P.V.C. seat in European each 250.00
W.C. pan
7112 Circular shape 450 mm dia Mirror with Plastic moulded each 400.00
frame
7113 Rectangular shape 453x357 mm Mirror with Plastic each 350.00
moulded frame
7114 Oval shape 450x 350 mm (outer dimensions) Mirror each 450.00
7115 with Plastic moulded
Rectangular frame
shape 1500x450 mm Mirror with Plastic each 1200.00
moulded frame
7116 Hard board 6 mm thick sqm 151.00
7117 Semi Rigid PVC waste pipe for sink and wash basin 32 each 16.00
mm dia with length not less than 700 mm i/c PVC was
te fittings

7118 Semi Rigid PVC waste pipe for sink and wash basin 40 each 21.00
mm dia with length not less than 700 mm i/c PVC was
te fittings

7119 Flexible (coil shaped) PVC waste pipe for sink and wash each 20.00
basin 32mm dia with length not less than 700 mm i/c
PVC waste fittings

7120 Flexible (coil shaped) PVC waste pipe for sink and wash each 22.00
basin 40mm dia with length not less than 700 mm i/c
PVC waste fittings

7123 Coloured High density polyethylene/ poly propylene 10 each 632.00


lit. (full flush) capacity controlled low level flushing cis
tern with fittings

7126 White Vitreous china 10 lit. (full flush) capacity controlled each 858.00
low level flushing cistern with all fittings

7127 Coloured Vitreous china 10 lit. (full flush) capacity each 1277.00
controlled low level flushing cistern with all fittings

7128 S.W. intercepting trap 100 mm dia each 144.00


7129 S.W. intercepting trap 150 mm dia each 202.00
7130 Rectangular shape 600x450 mm precast R.C.C. manhole each 628.00
cover w ith frame L.D.-25
7131 Square shape 350x350 mm precast R.C.C. manhole cover each 540.00
with frame -L.D.-25
7132 Circular shape 450 mm dia precast R.C.C. manhole cover each 474.00
with frame l.D.-25
7133 Rectangular shape 500x500 mm precast R.C.C. manhole each 575.00
cover with frame - M.D. - 10
7134 Circular shape 500 mm dia precast R.C.C. manhole cover each 575.00
with frame -M.D.-10
7135 Circular shape 560 mm dia precast R.C.C. manhole cover each 838.00
with frame -H.D.-20
7136 Circular shape 560 mm dia precast R.C.C. manhole cover each 935.00
with frame -E.H.D.-35
7137 Factory made 35 mm thick shutters with laminated sqm 1500.00
veneer lumber styles rails as per TADS IS:1995 and
panels of 12 mm thick plain type-I, medium density flat
pressed three layer, graded particle board (FPT-I) as per
IS:3087-1985 bonded with BWP type synthetic resin
adhesive, as per IS:848-1974
7139 Factory made 35 mm thick shutters with laminated sqm 1618.00
veneer lumber styles rails as per TADS IS:1995 and
panels of 12 mm thick both sides prelaminated type-I,
medium density flat pressed three layer, graded particle
board (FPT-I) as per IS:3087-1985 bonded with BWP type
synthetic resin adhesive, as per IS:848-1974
7143 Factory made 35 mm thick shutters with laminated sqm 1572.00
veneer lumber styles rails as per TADS IS:1995 and
panels of 12 mm thick one sides prelaminated type-I, and
other side balancing lamination medium density flat
pressed three layer, graded particle board (FPT-I) as per
IS:3087-1985 bonded with BWP type synthetic resin
adhesive, as per IS:848-1974

7151 Factory made 30 mm thick shutters with laminated sqm 1290.00


veneer lumber styles rails as per TADS IS:1995 and
panels of sheet glass using 10kg/sqm glass panes

7154 Factory made 35 mm thick shutters with laminated sqm 1328.00


veneer lumber styles rails as per TAD S IS:1995 and
panels of galvanised wire gauge with average width of
aperture 1.4 mm on both directions with wire of dia .
63mm

7155 Factory made 30 mm thick shutters with laminated sqm 1150.00


veneer lumber styles rails as per TAD S IS:1995 and
panels of galvanised wire gauge with average width of
aperture 1.4 mm on both directions with wire of dia .
63mm

7157 Laminated veneer lumber confirming to TADSS IS:1995 10 cudm 540.00


manufactured in factory in frames of doors, windows

7181 C.I. pile shoe kilogram 40.00


7182 M.S. clamps for pile shoe kilogram 35.00
7183 Bentonite tonne 2700.00
7184 Oxidised M.S. safety chain (weighing not less than 450 each 43.00
gms) for door
7187 C.I. grating 150 mm dia. (Weighing not less than 440 gm) each 16.00

7188 U-PVC pipes (working pressure 4 kg / cm2) Single metre 58.00


socketed pipe 75mm dia
7189 U-PVC pipes (working pressure 4 kg / cm 2) Single metre 112.00
socketed pipe 110mm dia
7190 U-PVC pipes (working pressure 4 kg / cm2) Rubber (Seal) metre 14.00
Ring 75mm dia
7191 U-PVC pipes (working pressure 4 kg / cm2) Rubber (Seal) metre 17.00
Ring 110mm dia
7192 UPVC coupler for UPVC drainage pipes 75 mm each 30.00
7193 UPVC coupler for UPVC drainage pipes 110 mm each 40.00
7194 UPVC pushfit coupler (single) 75 mm thick each 47.00
7195 UPVC pushfit coupler (single) 110 mm thick each 72.00
7196 UPVC single equal Tee (with door) 75x75x75 mm each 83.00
7197 UPVC single equal Tee (with door) 110x110x110 mm each 115.00
7198 UPVC single equal Tee (with door) 75x75x75 mm each 100.00
7199 UPVC single equal Tee (with door) 110x110x110 mm each 160.00
7208 UPVC bend 87.5o 75 mm bend each 50.00
7209 UPVC bend 87.5o 110 mm bend each 85.00
7212 UPVC plain shoe 75 mm bend each 105.00
7213 UPVC plain shoe 110 mm bend each 196.00
7214 UPVC pipe clip 75 mm bend each 15.00
7215 UPVC pipe clip 110 mm bend each 30.00
7231 Resin Bonded Glass wool 16 kg/m³ 50 mm thick sqm 114.00
7232 Resin Bonded Glass wool 24 kg/m³ 50 mm thick sqm 163.00
7233 Fibre glass tis sue reinforcement Type II Grade I sqm 55.00
7236 Precast chequered cement tiles 22 mm thick Dark shade sqm 193.00
using ordinary cement
7237 Precast chequered cement tiles 22 mm thick Medium sqm 305.00
shade using 50% White cement & 50% Ordinary cement

7239 Epoxy paint litre 280.00


7240 Fire retardant paint litre 318.00
7241 Melamine polish litre 228.00
7244 Table rubbed polished stone 18 mm thick (75x 50cm) sqm 1440.00
Agaria Marble stone - 18 m m thick
7245 Table rubbed polished stone 18mm thick (75x50cm) sqm 1670.00
Granite stone -18mm thick
7246 Vertical load testing (INITIAL) of piles in accordance with per test 19500.00
IS : 2911 (Part - IV) including installation of loading
platform and preparation of pile head or construction of
test cap and dismantling of test cap after test etc.
complete as per specification upto 50MT capacity pile
7247 Vertical load testing (INITIAL) of piles in accordance with per test 27500.00
IS : 2911 (Part - IV) including installation of loading
platform and preparation of pile head or construction of
test cap and dismantling of test cap after test etc.
complete as per specification & above 50MT and up to
100 MT

7248 Vertical load testing (INITIAL) of piles in accordance with per test 37500.00
IS : 2911 (Part - IV) including installation of loading
platform and preparation of pile head or construction of
test cap and dismantling of test cap after test etc.
complete as per specification & group of two or more up
to 50 MT

7249 Cyclic vertical load testing of piles in accordance with IS per test 11500.00
: 2911 (Part -IV) including preparation of pile head etc. for
Single pile up to 50 tonne capacity

7250 Cyclic vertical load testing of piles in accordance with IS per test 18000.00
: 2911 (Part -IV) including preparation of pile head etc. for
Single pile above 50 and up to 100 tonne capacity
7251 Cyclic vertical load testing of piles in accordance with IS per test 23000.00
: 2911 (Part-IV) including preparation of pile head etc.
for Group of two piles up to 50 tonne capacity each

7252 Lateral load testing of single pile in accordance with IS : per test 11500.00
2911 (Part -IV) for determining safe allowable lateral load
on pile. Up to 50 tonne capacity

7253 Lateral load testing of single pile in accordance with IS : per test 18000.00
2911 (Part -IV) for determining safe allowable lateral load
on pile. Above 50 tonne capacity

7254 Hardening Compound litre 29.00


7255 Road marking paint (spirit based) litre 97.00
7256 Superior quality road marking paint litre 148.00
7257 C.P. Brass bibcock 15 mm each 80.00
7258 C.P. Brass long nose bibcock 15 mm each 130.00
7259 C.P. Brass long body bibcock 15 mm each 150.00
7260 C.P. Brass stop cock (concealed) 15 mm each 170.00
7261 C.P. Brass angle valve 15 mm each 180.00
7266 Pressed clay tiles 1000 nos 8900.00
7267 Plain ceiling tiles (BWP type phenol formaldehyde each 90.00
synthetic resin bonded) (600x600x12 mm)

7268 Semi perforated ceiling tiles (600x600x12 mm) each 90.00


7269 25 mm thick particle board sqm 390.00
7270 30 mm thick prelaminated flush door shutter sqm sqm 716.00
716.00
7271 IInd class teak wood lipping 25 m m wide x 12 mm thick metre 28.00

7272 25 mm thick melamine faced prelaminated three layer sqm 708.00


particle board
7295 Granite Black m arble, 18 mm thick slab, above 0.2 sqm sqm 1500.00
up to 0.5 sqm (area wise)
7297 Granite Black m arble, 18 mm thick slab, above 1.0 sqm sqm 1615.00
7306 up to 2.0 sqm
Aluminium T or(area wise)
L sections kilogram 195.00
7307 For flush door shutters Extra for providing teak veneering sqm 225.00
on one side inste ad of commercial veneering

7309 Paving Asphalt 60/70 penetration tonne 23200.00


7312 Expandable fastener with plastic sleeve and M.S. screws. each 6.00
25 mm long
7313 Expandable fastener with plastic sleeve and M.S. screws. each 7.00
32 mm long
7314 Expandable fastener with plastic sleeve and M.S. screws. each 9.00
40 mm long
7315 Expandable fastener with plastic sleeve and M.S. screws. each 11.00
50 mm long
7318 Plasticizer / super plasticizer kilogram 30.00
7319 Wall form panel 1250x500 mm each 700.00
7320 Tie bolt 12 mm dia 100 mm length each 31.00
7321 Tie bolt 12 mm dia 150 mm length each 42.00
7322 Tie bolt 20 mm dia 150 mm length each 57.00
7323 Tie bolt 20 mm dia 225 mm length each 72.00
7324 Spring coil 12 mm each 10.00
7325 Plastic cone 12 mm dia each 12.00
7326 Corner angle 45x45x5 mm 1.50 m long each 175.00
7327 100 mm channel shoulder 2.5 m long each 400.00
7328 Double clip ( bridge clip) each 30.00
7329 Single clip each 30.00
7330 M.S. tube 40 mm dia metre 100.00
7331 Wall form panel 1250x450 mm each 650.00
7332 Corner angle 45x45x5 m 2.50 m long each 200.00
7333 Column clamp 450x1070 m each 1100.00
7334 Prop 2 m ( 2-3.5m) each 750.00
7335 Binding wire kilogram 40.00
7338 Gun metal cramp kilogram 270.00
7339 Stainless steel cramp kilogram 280.00
7340 Stainless steel pin . kilogram 130.00
7342 Adjustable span ESO+SI (2.35-3.40) each 1600.00
7343 Adjustable telescopic prop 3 m (2.02-3.75 m) each 1000.00
7344 Beam clamp 300-380 mm (450-1070 mm) each set 375.00 375.00
7345 Prop 4 m each 1030.00
7346 Double coupler each 45.00
7347 Cadmium plated full threaded steel screws (30x4 m m 100 nos 23.00
dia.)
7348 Aluminium washer 2 mm thick 15 mm dia 100 nos 7.00
7349 12 mm M.S. ‘U’ beading metre 9.00
7354 Plastic encapsulated M .S. foot rest 30x20x15 cm each 93.00
7358 Flushing Cistern P.V.C. 10 lts capacity ( low level ) each 570.00
(White) ( with fittings, accessories and flush pipe)
7359 P.V.C. automatic flushing cistern 5 lts capacity each 430.00
7361 P.V.C. automatic flushing cistern 10 lts capacity each 465.00
7363 15 mm C.P. brass tap with elbow operation lever each 396.00
7364 White glazed fire clay draining board 600x450x25 mm each 390.00

7366 Glass reinforced Gyp sum ( GRG) board 8.5 mm thick sqm 190.00

7367 Galvanised M.S. sheet 0.5 mm thick pressed channel metre 48.00
section of s ize 50x32mm
7369 Galvanised M.S. sheet 0.50 mm thick pressed stud. metre 55.00
48x34x36 mm
7375 G.I. flush pipe and C.P. brass spreader including C.P. each 352.00
7376 connecting
G.I. flush pipe
pipe Single lipped
and C.P. urinal
brass spreader including C.P. each 880.00
connecting pipe Range of two lipped urinals
7377 G.I. flush pipe and C.P. brass spreader including C.P. each 1070.00
connecting pipe Range of three lipped urinals
7378 G.I. flush pipe and C.P. brass spreader including C.P. each 1530.00
connecting pipe Range of four lipped urinals
7379 White vitreous china clay half stall urinal flat back each 1224.00
580x380x350 mm or angle back 450x375x350 mm with
waste fittings as per IS : 2556

7380 Precast R.C.C. grating with frame 500x450 mm horizontal each 533.00
grating
7381 Precast R.C.C. grating with frame 450x100 mm vertical each 250.00
grating
7382 Bitumen emulsion rapid setting (R.S.) confirming to IS : tonne 32000.00
7385 8887-1995
3 mm thick translucent white acrylic plastic sheet sqm 515.00
7386 12 thick particle board ceiling tile sqm 225.00
7388 Dash hold fastener 12.5 mm dia, 40 mm long with 6 mm each 30.00
dia bolt
7389 Anodising 15 microns on aluminium sections kilogram 32.00
7390 Neoprene/EPDM rubber gasket metre 22.00
7391 Anodising 25 microns on aluminium sections kilogram 40.00
7392 Powder coating 50 microns on aluminium sections. kilogram 45.00

7393 Polyester powder coating 50 m icrons on aluminium kilogram 50.00


sections
7394 Double action hydraulic floor spring with stainless steel each 1400.00
cover plate
7395 6 mm dia. G.I. adjustable hangers including clips (up to 1.2 each 25.00
m length)
7396 Double action hydraulic floor spring with brass cover each 1550.00
plate
7400 15 mm PTMT bib cock each 96.00
7401 15 mm PTMT bib cock with flange (fancy) each 220.00
7402 15 mm PTMT bib cock long body w ith flange each 155.00
7403 15 mm dia PTMT stop cock(male thread) each 96.00
7405 20 mm dia. PTMT stop cock each 120.00
7406 PTMT pillar cock each 150.00
7407 PTM T push cock 15 mm dia. each 90.00
7408 PTM T push cock 12 mm dia. 20 mm BSP each 75.00
7409 PTMT grating 100 mm dia. each 30.00
7411 125 mm grating with waste hole each 36.00
7412 Rectangular type with openable circular lid 150 mm size each 90.00
18 mm high with 100 mm dia. (110 gm)
7415 Double acting air valve 50 mm each 3050.00
7416 Double acting air valve 80 mm each 4480.00
7417 Double acting air valve 100 mm each 5800.00
7418 Water meter (including testing charges) 80 mm each 1800.00
7419 Water meter (including testing charges) 100 mm each 2800.00
7420 Water meter (including testing charges) 150 mm each 4000.00
7421 Water meter (including testing charges) 200 mm each 4500.00
7422 Dirt box strainer 80 mm each 2500.00
7423 Dirt box strainer 100 mm each 3750.00
7424 Dirt box strainer 150 mm each 4850.00
7425 Dirt box strainer 200 mm each 6800.00
7426 Cat’s eye each 450.00
7427 Water stops Serrated with central bulb (225 mm wide, metre 330.00
8-11 mm thick)
7428 Water stops Dumb bell with central bulb metre 306.00
7429 Kick ers metre 325.00
7430 Wedge expansion hold fastener 1/4" or 6 mm each 10.00
7431 Wedge expansion hold fastener 3/8" or 10 mm each 12.00
7432 Wedge expansion hold fastener 1/2" or 12 mm each 23.00
7439 8mm thick (mirror polished tiles machine cut edge) Raj sqm 430.00
Nagar white
7442 Wheel 75 mm dia. 40 mm wide each 52.00
7443 Aluminium single cleat of size 30x32x3 each 10.00
7444 Aluminium grip strip of size 50x12x2 each 7.00
7445 25 mm prelaminated flush door both side decorative sqm 650.00

7449 Aluminium U beading kilogram 195.00


7451 Glass sheet (Pin headed) 4 mm thick sqm 160.00
7452 Raj nagar plain white marble (table rubbed and polished) sqm 540.00
18 mm thick above 0.10 sqm up to 0.20 sqm

7453 Raj nagar plain white marble (table rubbed and polished) sqm 580.00
18 mm thick above 0.20 sqm up to 0.50 sqm

7466 Second class deodar teak wood lipping 30 mm metre 15.00


widthx12mm
7468 Veneered particle board with commercial veneering on sqm 418.00
both sides 12mm thick
7477 Prelaminated particle board with one side decorative and sqm 595.00
other side balancing lamination, flat pressed 3 layer &
graded (medium density) I, Type II conforming to IS :
12823 (exterior grade)12 mm thick
7478 Prelaminated particle board with one side decorative and sqm 716.00
other side balancing lamination, flat pressed 3 layer &
graded (medium density) I, Type II conforming to IS :
12823 (exterior grade)18 mm thick

7479 Prelaminated particle board with one side decorative and sqm 775.00
other side balancing lamination, flat pressed 3 layer &
graded (medium density) I, Type II conforming to IS :
12823 (exterior grade)25 mm thick

7480 Prelaminated particle board with both sides decorative sqm 625.00
lamination, flat pressed 3 layer & graded (medium
density) Grade I, Type II conforming to IS : 12823
(exterior grade)12 m m thick

7485 Oxidised M. S. hinges finished with nickel plating 50 mm metre 29.00


(Over all width)
7486 Oxidised M. S. hinges finished with nickel plating 65 mm metre 34.00
(Over all width)
7491 PTM T Waste Coupling 31/32MM Each 45.00
7492 PTM T Waste Coupling 38/40MM Each 66.00
7493 PTMT Bottle Trap 31/32MM Each 295.00
7494 PTMT Bottle Trap 38/40MM Each 320.00
7495 PTM T Ball Cock 15mm Complete with Epoxy Coated Each 121.00
Aluminium Road & HD ball
7496 PTM T Ball Cock 20mm Complete with Epoxy Coated Each 175.00
7497 Aluminium
PTM T BallRoadCock& 25mm
HD ball Complete with Epoxy Coated Each 396.00
7498 Aluminium
PTM T BallRoadCock& 40mm
HD ball Complete with Epoxy Coated Each 745.00
7499 Aluminium
PTM T BallRoadCock& 50mm
HD ball Complete with Epoxy Coated Each 1120.00
Aluminium Road & HD ball
7500 PTM T Angle Stop cock with Flange 15mm Each 120.00
7501 PTM T Swiveling shower 15mm Each 81.00
7503 PTM T Liquid Soap Container of 400ml capacity Each 135.00
7504 PTM T Towel Ring 215xd200x37mm Each 108.00
7505 PTM T Towel R ail (450MM) Each 180.00
7506 PTM T Towel R ail (600MM) Each 210.00
7507 PTMT Shelf 450x124x36mm Each 245.00
7508 PTM T Urinal Spreader 15MM Each 120.00
7509 PTMT Soap Dish/Holder 138x102x75mm Each 108.00
7512 PTMT handle 125x34x24mm Each 27.00
7513 PTMT handle 150x34x24mm Each 30.00
7514 PTMT butt hinges 75x60x10mm Each 36.00
7515 PTMT butt hinges 100x75x10mm Each 48.00
7516 PTM T Tower bolt 152x42x18mm Each 60.00
7517 PTM T Tower bolt 202x42x18mm Each 72.00
7518 PTM T door catcher 72x42mm sqm 24.00
7552 Coir veneered board 4mm thick sqm 235.00
7553 Coir veneered board 6mm thick sqm 308.00
7555 Coir veneered board 12mm thick sqm 548.00
7556 Coir veneered board 18mm thick sqm 820.00
7651 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 Metre 658.00
100mm dia
7652 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 Metre 978.00
150mm dia
7653 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 Metre 1348.00
200mm dia
7654 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 1743.00
250mm dia
7655 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 2238.00
300mm dia
7656 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 2625.00
350mm dia
7657 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 3763.00
400mm dia
7658 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 4175.00
450mm dia
7659 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 5600.00
500mm dia
7660 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 6275.00
600mm dia
7661 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 8538.00
700mm dia
7662 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 9725.00
750mm dia
7663 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 10000.00
800mm dia
7664 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 11663.00
900mm dia
7665 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - Metre 13125.00
1000mm dia
7666 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 25.00
100mm dia
7668 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 35.00
150mm dia
7669 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 62.00
200mm dia
7670 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 68.00
250mm dia
7671 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 98.00
300mm dia
7672 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 123.00
350mm dia
7673 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 248.00
400mm dia
7674 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 275.00
7675 450mm dia
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 285.00
500mm dia
7676 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 348.00
7677 600mm dia
Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 550.00
7678 700mm Gaskets
Rubber dia Conforming to I.S 5382 of S.B.R quality Each 648.00
750mm dia
7679 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 725.00
800mm dia
7680 Rubber Gaskets Conforming to I.S 5382 of S.B.R quality Each 968.00
7681 900mm Gaskets
Rubber dia Conforming to I.S 5382 of S.B.R quality Each 1188.00
1000mm dia
7682 Ductile Iron K - 12 specials suitable for push on jointing Quintal 8938.00
up to 600mm dia
7683 Ductile Iron K - 12 specials suitable for pus h on jointing Quintal 13413.00
over 600mm dia
7684 Ductile Iron specials suitable for mechanical jointing as Quintal 9400.00
per I.S. 9523 -upto 600mm dia
7685 Ductile Iron Specials suitable for m echanical jointing as Quintal 14239.00
per I.S. 9523 over 600mm dia
7686 Ductile Iron Pipe Class K-9 flanges and welding 100mm Metre 1888.00
dia
7687 Ductile Iron Pipe Class K-9 flanges and welding 150mm metre 2613.00
dia
7688 Ductile Iron Pipe Class K-9 flanges and welding 200mm Metre 3388.00
dia
7689 Ductile Iron Pipe Class K-9 flanges and welding 250mm Metre 4498.00
dia
7690 Ductile Iron Pipe Class K-9 flanges and welding 300mm metre 5788.00
dia
7691 Ductile Iron Pipe Class K-9 flanges and welding 350mm Metre 7210.00
dia
7692 Ductile Iron Pipe Class K-9 flanges and welding 400mm Metre 8613.00
dia
7693 Ductile Iron Pipe Class K-9 flanges and welding 450mm Metre 10413.00
dia
7694 Ductile Iron Pipe Class K-9 flanges and welding 500mm Metre 12625.00
dia
7695 Ductile Iron Pipe Class K-9 flanges and welding 600mm Metre 17125.00
dia
7696 Ductile Iron Pipe Class K-9 flanges and welding 700mm Metre 21125.00
dia
7697 S&S Centrifugally (Spun) C.I. Pipe class LA 100mm dia Metre 624.00

7698 S&S Centrifugally (Spun) C.I. Pipe class LA 125mm dia metre 763.00

7699 S&S Centrifugally (Spun) C.I. Pipe class LA 150mm dia metre 901.00

7700 S&S Centrifugally (Spun) C.I. Pipe class LA 200mm dia Metre 1252.00

7701 S&S Centrifugally (Spun) C.I. Pipe class LA 250mm dia Metre 1779.00

7702 S&S Centrifugally (Spun) C.I. Pipe class LA 300mm dia Metre 2366.00

7703 S&S Centrifugally (Spun) C.I. Pipe class LA 350mm dia metre 2918.00

7704 S&S Centrifugally (Spun) C.I. Pipe class LA 400mm dia Metre 3574.00

7705 S&S Centrifugally (Spun) C.I. Pipe class LA 450mm dia Metre 4276.00

7706 S&S Centrifugally (Spun) C.I. Pipe class LA 500mm dia Metre 5211.00

7707 S&S Centrifugally (Spun) C.I. Pipe class LA 600mm dia Metre 6884.00
7708 S&S Centrifugally (Spun) C.I. Pipe Specials as per IS Quintal 3530.00
1538 suitable for lead jointing upto 300mm dia
7709 S&S Centrifugally (Spun) C.I. Pipe Specials as per IS Quintal 3988.00
1538 suitable for lead jointing over 300mm dia
7710 S&S Centrifugally (Spun) C.I. Pipe s pecials suitable for Quintal 5338.00
mechanical joint as per I.S. 13382 up to 300mm dia

7711 S&S Centrifugally (Spun) C.I. Pipe Specials suitable for Quintal 5580.00
mechanical joint as per IS 13382 over 300mm dia
7712 Screwed double flanged centrifugally cast (spun) C.I. Metre 977.00
Pipe of Class B conforming to I.S. 1536, - 100mm dia

7713 Screwed double flanged centrifugally cast (spun) C.I. Metre 1511.00
Pipe of Class B conforming to I.S. 1536, - 150mm dia

7714 Screwed double flanged centrifugally cast (spun) C.I. Metre 2092.00
Pipe of Class B conforming to I.S. 1536, - 200mm dia

7715 Screwed double flanged centrifugally cast (spun) C.I. Metre 2800.00
Pipe of Class B conforming to I.S. 1536, - 250mm dia

7716 Screwed double flanged centrifugally cast (spun) C.I. Metre 3559.00
Pipe of Class B conforming to I.S. 1536, - 300mm dia

7717 Screwed double flanged centrifugally cast (spun) C.I. Metre 4553.00
Pipe of Class B conforming to I.S. 1536, - 350mm dia

7718 Screwed double flanged centrifugally cast (spun) C.I. 5885.00


Pipe of Class B conforming to I.S. 1536, - 400mm dia

7719 Screwed double flanged centrifugally cast (spun) C.I. 7627.00


Pipe of Class B conforming to I.S. 1536, - 450mm dia

7720 Screwed double flanged centrifugally cast (spun) C.I. 9962.00


Pipe of Class B conforming to I.S. 1536, - 500mm dia

7721 Screwed double flanged centrifugally cast (spun) C.I. 12992.00


Pipe of Class B conforming to I.S. 1536, - 600mm dia

7722 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 597.00
100mm dia
7723 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 870.00
150mm dia
7724 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 1237.00
200mm dia
7725 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 1675.00
250mm dia
7726 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 2369.00
300mm dia
7727 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 2728.00
350mm dia
7728 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 3256.00
400mm dia
7729 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 3861.00
450mm dia
7730 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 4557.00
500mm dia
7731 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 6011.00
600mm dia
7732 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 7463.00
700mm dia
7733 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - Metre 10405.00
800mm dia
7734 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 12798.00
900mm dia
7735 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 15505.00
1000mm dia
7736 Extruded burnt flyash clay sewer bric ks conforming to 1000 nos 3550.00
I.S 4885 - 1988
7737 Fly ash lime bricks (FALG Bricks) conforming to I.S. 1000 nos 1792.00
7738 12894-1989
Calcium Silicate Bricks machine moulded confirming to 1000 nos 3083.00
I.S. 4139 -1989
7739 Modified Bitumen Refinery produced CR MB - 55 Tonne 26000.00
7741 Modified Bitumen Refinery produced CR MB - 60 tonne 26300.00
7742 Bitumen emulsion medium setting (M.S.) confirming to tonne 19500.00
IS : 8887-1995
7800 Ceramic Glazed Tiles Ist quality minimum thick ness sqm 268.00
5mm in all colours shades and designs except burgundy,
bottle green, black

7801 Ceramic Glazed Tiles Ist quality 300 x 300mm in all sqm 320.00
shades and designs of White, Ivory, grey, Fume Red brown
etc.

7802 Ceramic Glazed Tiles Ist quality 300 x 300 in all shades sqm 347.00
designs except White, Ivory, Grey, Fume Red Brown etc.

7803 Rectified Ceramic Glazed Tiles Ist quality 300x 300 or sqm 462.00
more in all shades designs White, Ivory, Grey, Fume Red
Brown etc.

7804 Rectified Ceramic Glazed Tiles Ist quality 300 x 300 or sqm 496.00
more in all shades designs except White, Ivory, Grey,
Fume Red Brown etc.

7805 Salem Stainless steel AISI - 304 (18/8) Orrisa pattern each 3350.00
W.C. Pan 724mmx578 mm
7806 Salem Stainless steel AISI - 304 (18/8) Round basin each 1500.00
405mm X 355mm
7807 Salem Stainless steel AISI - 304 (18/8) Wash basin each 1350.00
7808 530mm X 345mm
Centrifugally cast (spun) iron S&S 100 mm inlet and 100 each 309.00
mm outlet
7809 Centrifugally cast (spun) iron S&S 100 mm inlet and 75 each 334.00
mm outlet
7850 Agaria White marble slab plain 18mm thick sqm 1000.00
7857 P.T.M.T. Grating square slit 150mm each 70.00
7858 P.T.M.T. Urinal cock 15mm dia each 90.00
7859 P.T.M.T. Bib cock with nozzle 15mm each 110.00
7861 P.T.M.T. Stop cock (concealed) 15mm each 160.00
7862 15 mm nominal bore and 30 cm length PVC connection each 27.00
pipe with PTMT nuts
7863 15 mm nominal bore and 45 cm length PVC connection each 32.00
pipe with PTMT nuts
7864 P.T.M.T. extension nipple 15mm each 30.00
7865 P.T.M.T. extension nipple 20mm each 36.00
7866 P.T.M.T. extension nipple 25mm each 54.00
7900 Modular bricks of class designation 75 1000 N os 2050.00
7901 Machine moulded perforated FPS bricks of class 1000 N os 3233.00
designation 125
7902 Machine moulded modular perforated bricks of class 1000 N os 3200.00
designation 125
7903 Machine moulded FPS bricks of class designation 125 1000 N os 2767.00

7904 Machine moulded tile bricks of class designation 125 1000 N os 2717.00

8001 24 mm thick Factory made shutters with frame, rails sqm 1830.00
and panels of PVC extruded sections in white, grey or
wooden finish

8002 30 mm thick Factory made shutters with frame, rails sqm 1900.00
and panels of PVC extruded sections in white, grey or
wooden finish

8003 Factory made PVC rigid foam paneled shutter i/c carriage sqm 1743.00

8004 Factory made PVC rigid foam paneled shutter as per IS : sqm 2148.00
4020 i/c carraige
8006 Factory made PVC rigid foam sheet 1mm thick sqm 145.00
8007 Factory made PVC rigid foam sheet 5mm thick sqm 558.00
8008 Factory made prelaminated PVC rigid foam sheet 5mm sqm 660.00
thick
8010 48mmX40mmX1.5mm thick Factory made door frame of Metre 112.00
PVC extruded sections in white, grey or wooden finish

8011 Factory made door frame PVC extruded sheet i/c metre 294.00
carriage
8012 Adhesive solvent cement kg 150.00
8100 Powder coated M.S. butt hinges 100mm 10 nos 66.00
X58mmX1.9mm
8200 A.P.P. modified polymeric felt (two layers) 1.5 m m thick sqm 50.00

8201 A.P.P. modified polymeric felt (two lay ers) 2 mm thick sqm 85.00

8203 A.P.P. modified 2 mm thick membrane reinforced with sqm 147.00


glass fibre matt
8204 A.P.P. modified 3 mm thick membrane reinforced with sqm 185.00
glass fibre matt
8205 A.P.P. modified 3 mm thick membrane reinforced with sqm 221.00
polyester matt
8206 Bitumen primer for bitumen membrane litre 54.00
8207 Geotextile 120 gsm m embrane sqm 25.00
8210 Stainless steel screws 50 mm 100 Nos 213.00
8211 Stainless steel screws 40 mm 100 Nos 157.00
8212 Stainless steel screws 30 mm 100 Nos 98.00
8214 Stainless steel screws 20 mm 100 Nos 63.00
8215 Stainless steel butt hinges 125x64x1.9 mm IS : 12817 10 Nos 200.00
marked
8216 Stainless steel butt hinges 100x58x1.9 mm IS : 12817 10 Nos 143.00
marked
8217 Stainless steel butt hinges 75x47x1.8 mm IS : 12817 10 Nos 112.00
marked
8218 Stainless steel butt hinges 50x37x1.5 mm IS : 12817 10 Nos 90.00
marked
8219 Stainless steel butt hinges (heavy weight) 125x64x2.5 Nos. 261.00
mm IS : 12817 marked
8220 Stainless steel butt hinges (heavy w eight) 100x60x2.5 Nos. 185.00
mm IS : 12817 marked
8221 Stainless steel butt hinges (heavy weight) 75x50x2.5 mm Nos. 155.00
IS : 12817 marked
8222 M.S. heavy weight but hinges 125x90x4.0m m IS : 1341 10 Nos 256.00
marked.
8223 M.S. heavy weight butt hinges 100x75x3.5 mm IS: 1341 10 Nos 133.00
marked
8224 M.S. heavy weight butt hinges 75x60x3.1 mm IS: 1341 10 Nos 67.00
marked
8225 M.S. heavy weight butt hinges 50x40x2.5 mm IS : 1341 10 Nos 52.00
marked
8300 1216 mm PE-AL-PE Composite pressure pipe Metre 79.00
8301 1620 mm PE-AL-PE Composite pressure pipe Metre 97.00
8302 2025 mm PE-AL-PE Composite pressure pipe Metre 126.00
8303 2532 mm PE-AL-PE Composite pressure pipe Metre 172.00
8304 3240 mm PE-AL-PE Composite pressure pipe Metre 227.00
8305 4050 mm PE-AL-PE Composite pressure pipe Metre 304.00
8501 Polymer modified cementation coating kilogram 114.00
8502 Fibre glass cloth sqm 33.00
8504 Multi surface paint litre 264.00
8505 Acrylic exterior paint litre 123.00
8506 Premium Acrylic exterior paint litre 202.00
8507 Textured exterior paint litre 183.00
8508 Primer for cement paint litre 52.00
8509 Special Primer (C.W.) litre 76.00
8510 Metal Primer (U.G.) litre 91.00
8611 Main T ceiling sections 24x38x0.3 mm (3 metre long) each 162.00

8612 Perimeter wall angle 21x21 mm (3 metre long) each 102.00


8613 Intermediate cross channel (1.2 mtrs) each 62.00
8614 Intermediate cross channel (1.6 mtrs) each 29.00
8615 Hanger rod 0.5 mm thick each 5.00
8616 Adjustm ent clip each 4.40
8617 Soffit cleat each 2.30
8618 Dash fastener 6 mm dia 50 mm long each 8.00 each 8.00
8620 Vitrified floor tile 50x50 cm sqm 645.00
8621 Vitrified floor tile 60x60 cm sqm 700.00
8622 Vitrified floor tile 80x80 cm sqm 1076.00
8623 Vitrified floor tile 100x100 cm sqm 1290.00
8625 Poly propylene- Random - Co - Polymer (PPR) pipes SDR metre 29.00
7.4 - 16mm dia
8626 Poly propylene - Random - Co - Polymer (PPR) pipes SDR metre 44.00
7.4 -20mm dia
8627 Poly propylene - Random - Co - polymer (PPR) pipes SDR metre 68.00
7.4 - 25mm outer dia
8628 Poly propylene - Random - Co - poymer (PPR) pipes SDR metre 111.00
7.4 -32mm outer dia
8629 Poly propylene - Random - Co - polymer (PPR) pipes SDR metre 176.00
7.4 -40mm outer dia
8630 Poly propylene - Random - Co - polymer (PPR) pipes SDR metre 257.00
7.4 -50mm uoter dia
8631 Poly propylene - Random - Co - polymer (PPR) pipes SDR metre 400.00
7.4 -63mm outer dia
8632 Poly propylene - Random - Co - polymer (PPR) pipes SDR metre 575.00
7.4 -75mm outer dia
8633 Poly propylene - Random - Co - polymer (PPR) pipes SDR metre 917.00
7.4 -90mm uoter dia
8634 Poly propylene - Random - Co - polymer (PPR) pipes SDR - metre 962.00
11 -110mm outer dia
8635 Poly propylene - Random - Co - polymer (PPR) pipes SDR - metre 2028.00
11-160mm outer dia
8636 Chlorinated Polyvinyl - chloride (CPVC) pipe 15 mm outer metre 45.00
dia.
8637 Chlorinated Polyvinyl - chloride (CPVC) pipe 20 mm outer metre 55.00
dia.
8638 Chlorinated Polyvinyl - chloride (CPVC) pipe 25 mm outer metre 78.00
dia.
8639 Chlorinated Polyvinyl - chloride (CPVC) pipe 32 mm outer metre 105.00
dia.
8640 Chlorinated Polyvinyl - chloride (CPVC) pipe 40 mm outer metre 150.00
dia.
8641 Chlorinated Polyvinyl - chloride (CPVC) pipe 50 mm outer metre 245.00
dia.
8642 Chlorinated Polyvinyl - chloride (CPVC) pipe 62.5mm inner metre 783.00
dia.
8643 Chlorinated Polyvinyl - chloride (CPVC) pipe 75 mm inner metre 1030.00
dia.
8644 Chlorinated Polyvinyl - chloride (CPVC) pipe 100 mm inner metre 1430.00
dia.
8645 Chlorinated Polyvinyl - chloride (CPVC) pipe 150 mm inner metre 2490.00
dia.
8646 Silicon sealant. cartridge 281.00
8647 Stainless steal screws 30mm x4mm. cent 25.00
8648 Hermetically sealed double glazed unit made with 6mm sqm 1980.00
thick clear float glass both side having 12 mm air gap.

8649 Stainless steel (SS 304 grade) adjustable friction window each 145.60
stay. 205 x19mm
8650 Stainless steel (SS 304 grade) adjustable friction window each 161.20
stay 255 x19 mm
8651 Stainless steel (SS 304 grade) adjustable friction window each 208.00
stay. 355 x19 mm
8652 Stainless steel (SS 304 grade) adjustable friction window each 390.00
stay. 510 x 19mm
8653 Stainless steel (SS 304 grade) adjustable friction window each 715.00
stay. 710 x19mm
8654 Masking tape. metre 1.40
8655 Autoclaved aerated cement (AAC) blocks. cum 1650.00
8656 Gypsum panel 666 X 500 X 100 mm size. sqm 544.00
8657 Bonding plaster for Gypsum panel. kg 50.00
8658 Mechanised Autoclaved fly ash lime brick s. 1000 Nos 2200.00
8659 Water proof ply 12mm thick. sqm 572.00
8660 Aluminium casement window fastener (Anodised AC 15 ) each 30.00

8661 Aluminium casement window fastener (powder coated ). each 33.00

8662 Aluminium casement w indow fastener (polyester each 35.00


powder coated).
8663 Aluminium round shape handle (anodised AC 15) each 37.00
8664 Aluminium round shape handle (powder coated) each 41.00
8665 Aluminium round shape handle (polyester powder each 43.00
coated).
8666 Stainless steel s crews 25mm x4mm cent 21.00
8667 UV stabilised 2 mm thick plain FRP sheet . sqm 400.00
8668 UV stabilised 2 mm thick corrugated FRP sheet . sqm 474.00
8669 Mangalore ridge tiles 20mm thick. each 25.00
8670 Mangalore tiles 20mm thick. each 9.50
8671 Precoated galvanised iron profile sheet 0.50 mm TCT sqm 325.00

8672 Precoated galvanised steel plain ridges. metre 330.00


8673 Precoated galvanised steel flashings/aprons. metre 330.00
8674 Precoated galvanised steel gutter metre 360.00
8675 Precoated galvanised steel north light curves. metre 360.00
8676 Precoated galvanised steel barge board. metre 330.00
8677 Precoated galvanised steel crimp curve sqm 420.00
8678 1mm thick 35mm wide bright finished stainless steel metre 30.00
8683 piano hinges
Red sand . gang saw cut 30mm thick.
stone sqm 325.00
8684 White sand stone gang saw cut 30mm thick. sqm 360.00
8685 Delineator each 560.00
8686 Precast C.C. Kerb stone M - 25 cum 3500.00
8687 Thermoplastic paint kg 67.22
8688 Glass beads kg 68.00
8689 Interlocking C.C. paver block ( 60 mm thick, M-30 ) sqm 225.00
8690 High intensity retro - reflective sheet. sqm 1400.00
8691 Punched tape concertina coil 600 m dia. 10m openable bundle 650.00
8692 length (Total length
RBT reinforced 90m)
barbed wire. metre 7.50
8693 Turn buckle and strengthening bolt. each set 35.00
8694 Precast pavement slab 450 x 450 x 50mm (M - 30). each 40.00
8695 Chain link fabric fencing mesh of size 50x50mm made of sqm 225.00
G.I. wire of dia 4mm
8696 Chain link fabric fencing mesh of size 50x50mm made of sqm 250.00
G.I. wire of dia 4m m, PVC coated to outer dia. 5mm.

8697 Chain link fabric fencing mesh of size 25x25mm made of sqm 300.00
G.I. wire of dia 3mm
8698 Stainless steel cramps with nuts, bolts and washer for each 200.00
dry stone cladding
8699 8 mm thick tapered edge calcium silicate board . sqm 194.00
8700 10 mm thick calcium silicate board. sqm 323.00
8703 Telescopic draw er channels 300mm long . set 92.00
8704 Stainless steel roller for sliding arrangement in racks/ each 5.00
cupboards/cabinets/ shutter
8705 50mmX42mmX2mm thick Factory made door frame of metre 117.00
PVC extruded sections in white, grey or wooden finish

8706 25mm thick factory made PVC flush door shutter i/c sqm 1975.00
carriage.
8707 Factory made glass reinforced plastic door frame 90x45 metre 333.00
mm i/c carraige
8708 30 mm thick factory made glass fiber reinforced plastic sqm 1580.00
panel door shutter i/c carraige
8710 Factory made solid PVC door frame 60 x 30mm i/c metre 223.00
carriage.
8711 28mm factory made solid PVC panel door shutter i/c sqm 1975.00
carriage.
8713 Fiber glass reinforced plastic chajja. sqm 3520.00
8714 Magnetic catcher triple strip vertical ty pe. each 13.50
8715 Magnetic catcher double strip horizontal type. each 10.00
8716 100 mm mortice lock with 6 levers for aluminium door. each 152.50

8717 12.5 mm thick Glass fibre reinforced Gypsum board . sqm 130.00

8719 2nd class teak wood lipping/ moulded beading or Taj metre 19.00
beading of size 18x5 mm
8720 Ceiling sections 0.55 mm thick having a knurled web of metre 34.00
51.55mm and two flanges of 26mm each with lips of
10.55mm
8721 Perimeter channel having one flange of 20mm and metre 20.00
another flange of 30mm with thickness of 0.55mm and
web of length 27mm

8722 Nylon sleeves & wooden screws (40mm) each 1.50 each 1.50
8723 Counter sunk ribbed head screw 25mm. cent 60.00 cent 60.00
8724 12mm thick marine plywood conforming to IS:710 sqm 740.00
8725 12mm thick fire retardant plywood conforming to IS: sqm 690.00
5509.
8726 1.5mm thick decorative laminated sheet sqm 405.00
8727 1.0mm thick decorative laminated sheet sqm 330.00
8730 30 mm thick factory made glass fiber reinforced plastic sqm 1960.00
flush door shutter i/c carriage
8731 High polymer modified quickset tile adhesive. per kg 13.75
9999 Sundries L.S. 1.00
220 20 4400
2200 Steam coal tonne 60.81
2201 Bricks 1000 nos 141.88
2202 Stone aggregate below 40 mm nominal size cum 53.21
2203 Coarse sand cum 53.21
2204 Timber cum 60.81
2205 Steel tonne 47.29
2206 Stone aggregate 40 m m nominal size and above cum 57.83
2207 Brick tiles 1000 nos 85.13
2208 Lime cum 53.21
2209 Cement tonne 47.29
2211 Tar bitumen tonne 53.21
2215 Soling stone & m asonry stone cum 62.6
2216 Stone blocks white & red sand stone & kota stone slab tonne 47.29
2224 S.W. pipes100 mm dia 100 metre 70.94
2225 S.W. pipes150 mm dia 100 metre 141.88
2226 S.W. pipes200 mm dia 100 metre 236.47
2227 S.W. pipes230 mm dia 100 metre 337.82
2228 S.W. pipes250 mm dia 100 metre 405.38
2229 S.W. pipes300 mm dia 100 metre 506.73
2241 Good earth cum 66.51
2242 Dum p manure cum 57.83
2260 Brick aggregate cum 57.83
2261 Fine sand (1 part badarpur sand : 2 parts jamuna sand) cum 53.21
2262 Fly ash cum 53.21
2264 Rubbish cum 53.21
2265 Moorum cum 53.21
2266 Surkhi cum 53.21
2267 Stone dust cum 53.21
2268 Marble dust and marble chips cum 53.21
2271 G.I. pipes below 100 mm dia tonne 47.29
2273 A.C.sheet and accessories tonne 47.29
2275 R.C.C. pipes 100 mm dia 100 metre 116.3
2281 R.C.C. pipes 150 mm dia 100 metre 193.83
2287 R.C.C. pipes 250 mm dia 100 metre 448.05
2290 R.C.C. pipes 300 mm dia 100 metre 553.8
2299 R.C.C. pipes 450 & 500 mm dia 100 metre 1,292.20
2302 G.I.sheet and accessories tonne 47.29
2303 R.C.C. pipes 600, 700, 750 & 800 mm dia 100 metre 1,938.30
2308 Plaster of paris tonne 47.29
2309 Cast iron fittings tonne 47.29
2311 Red bajri cum 53.21
2314 Barbed wire tonne 47.29
2317 Sludge cum 57.83
2319 Spun iron S & S pipes 100 mm dia 100 metre 116.3
2320 Spun iron S & S pipes 125 mm dia 100 metre 155.35
2321 Spun iron S & S pipes 150 mm dia 100 metre 193.83
2322 Spun iron S & S pipes 200 mm dia 100 metre 315.3
2323 Spun iron S & S pipes 250 mm dia 100 metre 448.05
2324 Spun iron S & S pipes 300 mm dia 100 metre 553.8
2325 Spun iron S & S pipes 350 mm dia 100 metre 775.32
2326 Spun iron S & S pipes 400 mm dia 100 metre 1,057.26
2327 Spun iron S & S pipes 450 mm dia 100 metre 1,292.20
2328 Spun iron S & S pipes 500 mm dia 100 metre 1,292.20
2329 Spun iron S & S pipes 600mm dia 100 metre 1,938.30
2330 C.I. pipes 500 mm dia 100 metre 1,292.20
2331 R.C.C. pipes 900 mm dia 100 metre 2,907.45
2332 R.C.C. pipes 1000 mm dia 100 metre 3,876.61
2333 R.C.C. pipes 1100 mm dia 100 metre 3,876.61
2334 R.C.C. pipes 1200 mm dia 100 metre 3,876.61
2335 Jamuna sand cum 53.21
2341 Pig lead tonne 47.29
2342 Solvent/ Diesel. quintal 5.32
2343 Ductile iron pipes (k7) 100 mm dia 100 metre 116.3
2344 Cast iron pipes 150 mm dia 100 metre 193.83
2345 Cast iron pipes 200 mm dia 100 metre 315.3
2346 Cast iron pipes 250 mm dia 100 metre 448.05
2347 Cast iron pipes 300 mm dia 100 metre 553.8
2348 Cast iron pipes 350 mm dia 100 metre 775.32
2349 Cast iron pipes 400 mm dia 100 metre 1,057.26
2350 Cast iron pipes 450 mm dia 100 metre 1,292.20
2351 Cast iron pipes 500 mm dia 100 metre 1,292.20
2352 Cast iron pipes 600 mm dia 100 metre 1,938.30
2353 Cast iron pipes 700 mm dia 100 metre 1,938.30
2355 Cast iron pipes 800 mm dia 100 metre 1,938.30
2356 Cast iron pipes 900 mm dia 100 metre 2,907.45
2357 Cast iron pipes 1000 mm dia 100 metre 3,876.61
1.1 By Mechanical Transport
1.0 Carriage of Materials
Data Sheet No 1 for Analysis of Rates
1.1 By Mechanical Transport including loading, unloading and
stacking:
Lead in km Average Nos of Nos of km Litres of Cost of Litres of Cost of Cost of 6
speed trips done in diesel diesel mobile mobile beldars
one day consumed (1235) consume (5001) (114)
@5Km/ lit @Rs./ lit d @Rs./ lit @Rs./ day
@140Km/
lit

1 2 3 4 5 6 7 8 9
1 16 7.11 20.22 4.04 214.8068 0.144 13.68 1242.00
2 17 6.48 31.92 6.38 339.2246 0.228 21.66 1242.00
3 17.5 5.96 41.76 8.35 443.9695 0.298 28.31 1242.00
4 18 5.54 50.32 10.06 534.8902 0.359 34.11 1242.00
5 18.5 5.19 57.90 11.58 615.7086 0.414 39.33 1242.00
6 19 4.9 64.80 12.96 689.0832 0.463 43.99 1242.00
7 19.5 4.66 71.24 14.25 757.6725 0.509 48.36 1242.00
8 20 4.44 77.04 15.41 819.3497 0.55 52.25 1242.00
9 20.5 4.26 82.68 16.54 879.4318 0.591 56.15 1242.00
10 21 4.1 88.00 17.60 935.792 0.629 59.76 1242.00
11 21.5 3.95 92.90 18.58 987.8986 0.664 63.08 1242.00
12 22 3.83 97.92 19.58 1041.069 0.699 66.41 1242.00
13 22.5 3.71 102.46 20.49 1089.453 0.732 69.54 1242.00
14 23 3.61 107.08 21.42 1138.901 0.765 72.68 1242.00
15 23.5 3.51 111.30 22.26 1183.564 0.795 75.53 1242.00
16 24 3.43 115.76 23.15 1230.886 0.827 78.57 1242.00
17 24.5 3.35 119.90 23.98 1275.017 0.856 81.32 1242.00
18 25 3.28 124.08 24.82 1319.679 0.886 84.17 1242.00
19 25.5 3.21 127.98 25.60 1361.152 0.914 86.83 1242.00
20 26 3.15 132.00 26.40 1403.688 0.943 89.59 1242.00
21 26.5 3.09 135.78 27.16 1444.097 0.97 92.15 1242.00
22 27 3.04 139.76 27.95 1486.102 0.998 94.81 1242.00
23 27.5 2.99 143.54 28.71 1526.511 1.025 97.38 1242.00
24 28 2.95 147.60 29.52 1569.578 1.054 100.13 1242.00
25 28.5 2.9 151.00 30.20 1605.734 1.079 102.51 1242.00
26 29 2.86 154.72 30.94 1645.08 1.105 104.98 1242.00
27 29.5 2.83 158.82 31.76 1688.679 1.134 107.73 1242.00
28 30 2.79 162.24 32.45 1725.367 1.159 110.11 1242.00
29 30.5 2.76 166.08 33.22 1766.307 1.186 112.67 1242.00
30 31 2.73 169.80 33.96 1805.653 1.213 115.24 1242.00

1. Number of trips in working day of 8 hours N=8/(2L/S+1) where L= Load in km., S= Speed in km per hou
/unloading.
2. Consumption of diesel taken at 5 km per litres
3. Consumption of mobile oil taken at 140 km per litre.
4. In column 4 of ‘km done’ an allowance of 6.0 km has been made
for movement of truck from parking place to duty & back.
5. (i) Cost of disel @ (12 35) per litre
(ii) Cost of moble oil @ (5001) per litre
(iii) Hire charges of truck @ (0005) for a day of 8 hours.

1.1 By Mechanical Transport


SL. No. Materials Capacity Net qty Unit of CP & Cost per trip per unit
per trip payable rates overhead 1 Km
after @15%
dedn for
looseness

1 2 3 4 5 6 7
1.1.1 Lime , moorum, building 8.00 8 cum 0.10 60.06
1.1.2 rubbish
Earth 8.00 6.4 cum 0.15 75.07
1.1.3 Manure or sludge 8.00 7.36 cum 0.15 65.28
1.1.4 Excavated rock 8.00 4 cum 0.15 120.11
1.1.5 Sand, stone aggregate below
40 mm nominal size 8.00 8 cum 0.15 60.06
1.1.6 Sand, stone aggregate 40 mm
nominal size and above 8.00 7.36 cum 0.15 65.28
1.1.7 Soling stone 8.00 6.8 cum 0.15 70.66
1.1.8 Bricks 3000.00 3000 1000 Nos 0.15 160.15
1.1.9 Brick tiles 5000.00 5000 1000 Nos 0.15 96.09
1.1.10 Cement, stone blocks, G.I.. C.I.,
A.C., & C.C. pipes below 100
mm dia and other heavy
materials
9.00 9 tonne 0.15 53.38
1.1.11 Steel 9.00 9 tonne 0.15 53.38
1.1.12 Timber 7.00 7 cum 0.15 68.64
1.1.13 Tar bitumen 8.00 8 tonne 0.15 60.06
1.1.14 Solvent 80.00 80 quintal 0.15 60.06
1.1.15 Steam coal 7.00 7 tonne 0.15 68.64
1.1.16 S W pipe
1.1.16.1 100mm dia 600.00 600 100 m 0.15 80.08
1.1.16.2 150mm dia 300.00 300 100 m 0.15 160.15
1.1.16.3 200mm dia 180.00 180 100 m 0.15 266.92
1.1.16.4 230mm dia 126.00 126 100 m 0.15 381.32
1.1.16.5 250mm dia 105.00 105 100 m 0.15 457.58
1.1.16.6 300mm dia 84.00 84.00 100 m 0.15 571.97
1.1.16.7 350mm dia 60.00 60.00 100 m 0.15 800.76
1.1.16.8 400mm dia 42.00 42.00 100 m 0.15 1143.95
1.1.16.9 450mm dia 33.00 33.00 100 m 0.15 1455.93
1.1.16.10 500mm dia 30.00 30.00 100 m 0.15 1601.53
1.1.16.11 600mm dia 24.00 24.00 100 m 0.15 2001.91
1.1.17 R.C.C. pipes, A.C. pipes, steel
cylinder, R.C. pipes, C.I. pipes,
C.I. pipes and unreinforced
cement pipes
1.1.17.1 100mm dia 366.00 366.00 100 m 0.15 131.27
1.1.17.2 125mm dia 274.00 274.00 100 m 0.15 175.35
1.1.17.3 150mm dia 219.60 219.60 100 m 0.15 218.79
1.1.17.4 200mm dia 135.00 135.00 100 m 0.15 355.90
1.1.17.5 250mm dia 95.00 95.00 100 m 0.15 505.75
1.1.17.6 300mm dia 76.86 76.86 100 m 0.15 625.11
1.1.17.7 350mm dia 54.90 54.90 100 m 0.15 875.15
1.1.17.8 400mm dia 40.26 40.26 100 m 0.15 1193.39
1.1.17.9 450mm & 500mm dia 32.94 32.94 100 m 0.15 1458.59
1.1.17.10 600mm, 700mm, 750mm &
800mm dia 21.96 21.96 100 m 0.15 2187.88
1.1.17.11 900mm dia 14.64 14.64 100 m 0.15 3281.82
1.1.17.12 1000mm, 1100mm & 1200mm 10.98 10.98 100 m 0.15 4375.76
1.1.17.13 dia

1.2 By Manual Labour including loading, unloading and stacking for lead less than 0.5 KM
SL. No. Materials Capacity Net qty Unit of CP & Cost per 8
per trip payable rates overhead hours a
after @15% day
dedn for
1 2 3 looseness
4 5 6 7
1.2.1 Lime , moorum, building 35.00 35 cum 0.15 1825.84
1.2.2 rubbish
Earth 35.00 28 cum 0.15 1825.84
1.2.3 Manure or sludge 35.00 32.2 cum 0.15 1825.84
1.2.4 Excavated rock 35.00 17.5 cum 0.15 1825.84
1.2.5 Sand, stone aggregate below 28.00 28 cum 0.15 1825.84
1.2.6 40 mmstone
Sand, nominal size
aggregate 40 mm 28.00 25.9 cum 0.15 1825.84
1.2.7 nominal size
Soling stone and above 28.00 23.8 cum 0.15 1825.84
1.2.8 Bricks 15000.00 15000.00 1000 Nos 0.15 1825.84
1.2.9 Brick tiles 24000.00 24000.00 1000 Nos 0.15 1825.84
1.2.10 Steam coal 30.00 30 tonne 0.15 1587.69
1.2.11 Stone blocks, G.I.. C.I., A.C., & 46.00 46 tonne 0.15 2190.06
1.2.12 C.C. pipes below 100 mm dia
Cement 57.99 57.99 tonne 0.15 2190.06
and other heavy materials
1.2.13 Steel 27.00 27 tonne 0.15 2190.06
1.2.14 Timber 42.00 42 cum 0.15 2190.06
1.2.15 Tar bitumen 46.00 46 tonne 0.15 2190.06
1.2.16 S W pipe
1.1.16.1 100mm dia 2298.00 2298.00 100 m 0.15 2190.06
1.1.16.2 150mm dia 1398.00 1398.00 100 m 0.15 2190.06
1.1.16.3 200mm dia 999.00 999.00 100 m 0.15 2190.06
1.1.16.4 230mm dia 780.00 780.00 100 m 0.15 2190.06
1.1.16.5 250mm dia 600.00 600.00 100 m 0.15 2190.06
1.1.16.6 300mm dia 420.00 420.00 100 m 0.15 2190.06
1.1.16.7 350mm dia 300.00 300.00 100 m 0.15 2190.06
1.1.16.8 400mm dia 240.00 240.00 100 m 0.15 2190.06
1.1.16.9 450mm dia 198.00 198.00 100 m 0.15 2190.06
1.1.16.10 500mm dia 152.00 152.00 100 m 0.15 2190.06
1.1.16.11 600mm dia 132.00 132.00 100 m 0.15 2190.06
1.1.17 R.C.C. pipes, A.C. pipes, steel
1.1.17.1 cylinder,
100mm dia R.C. pipes, C.I. pipes, 1702.00 366.00 100 m 0.15 2190.06
C.I. pipes and unreinforced
1.1.17.2 125mm dia
cement pipes 1391.00 274.00 100 m 0.15 2190.06
1.1.17.3 150mm dia 1208.00 219.60 100 m 0.15 2190.06
1.1.17.4 200mm dia 805.00 135.00 100 m 0.15 2190.06
1.1.17.5 250mm dia 458.00 95.00 100 m 0.15 2190.06
1.1.17.6 300mm dia 366.00 76.86 100 m 0.15 2190.06
1.1.17.7 350mm dia 256.00 54.90 100 m 0.15 2190.06
1.1.17.8 400mm dia 220.00 40.26 100 m 0.15 2190.06
1.1.17.9 450mm & 500mm dia 165.00 32.94 100 m 0.15 2190.06
1.1.17.10 600mm, 700mm, 750mm & 150.00 21.96 100 m 0.15 2190.06
1.2.18 800mm
Asbestosdia
cement pipes
1.2.18.1 50mm dia 10064.00 10064.00 100 m 0.15 2190.06
1.2.18.2 80mm dia 3660.00 3660.00 100 m 0.15 2190.06
1.2.18.3 100mm dia 2562.00 2562.00 100 m 0.15 2190.06
1.2.18.4 150mm dia 1830.00 1830.00 100 m 0.15 2190.06
Hire Total cost Cost per increase Average
chrages 6 +8 + 9+ trip 11/3 in cost cost per
of truck 10 per km km after
(5) @Rs./ over prev. 5, 10, 20
day trip km

10 11 12 13 14
1500.00 2970.49 417.79
1500.00 3102.88 478.84
1500.00 3214.28 539.31
1500.00 3311.00 597.65
1500.00 3397.04 654.54
1500.00 3475.07 709.2 54.66
1500.00 3548.03 761.38 52.18
1500.00 3613.60 813.87 52.49
1500.00 3677.58 863.28 49.41
1500.00 3737.55 911.6 48.32 51.41
1500.00 3792.98 960.25 48.65
1500.00 3849.48 1005.09 44.84
1500.00 3900.99 1051.48 46.39
1500.00 3953.58 1095.17 43.69
1500.00 4001.09 1139.91 44.74
1500.00 4051.46 1181.18 41.27
1500.00 4098.34 1223.38 42.2
1500.00 4145.85 1263.98 40.6
1500.00 4189.98 1305.29 41.31
1500.00 4235.28 1344.53 39.24 43.29
1500.00 4278.25 1384.55 40.02
1500.00 4322.91 1422.01 37.46
1500.00 4365.89 1460.16 38.15
1500.00 4411.71 1495.49 35.33
1500.00 4450.24 1534.57 39.08
1500.00 4492.06 1570.65 36.08
1500.00 4538.41 1603.68 33.03
1500.00 4577.48 1640.67 36.99
1500.00 4620.98 1674.27 33.6
1500.00 4662.89 1708.02 33.75 36.35

km., S= Speed in km per hour, 1 hour is allowed for loading


Cost per trip per unit Beyond 5 Beyond Beyond
2 Km 3 Km 4 Km 5 Km km upto 10 km 20 km
10 km upto 20 upto 30
per km km per km per
km km

8 9 10 11 12 13 14
68.83 77.53 85.91 94.09 7.39 6.22 5.23
86.04 96.91 107.39 117.61 9.24 7.78 6.53
74.82 84.27 93.38 102.27 8.03 6.76 5.68
137.67 155.05 171.82 188.18 14.78 12.45 10.45

68.83 77.53 85.91 94.09 7.39 6.22 5.23

74.82 84.27 93.38 102.27 8.03 6.76 5.68


80.98 91.21 101.07 110.69 8.69 7.32 6.15
183.56 206.74 229.10 250.91 19.71 16.59 13.93
110.13 124.04 137.46 150.54 11.82 9.96 8.36

61.19 68.91 76.37 83.64 6.57 5.53 4.64


61.19 68.91 76.37 83.64 6.57 5.53 4.64
78.67 88.60 98.19 107.53 8.45 7.11 5.97
68.83 77.53 85.91 94.09 7.39 6.22 5.23
68.83 77.53 85.91 94.09 7.39 6.22 5.23
78.67 88.60 98.19 107.53 8.45 7.11 5.97

91.78 103.37 114.55 125.45 9.85 8.3 6.97


183.56 206.74 229.10 250.91 19.71 16.59 13.93
305.93 344.56 381.83 418.18 32.85 27.66 23.22
437.04 492.23 545.47 597.40 46.92 39.51 33.18
524.44 590.67 654.57 716.88 56.31 47.41 39.81
655.55 738.34 818.21 896.10 70.38 59.27 49.76
917.78 1033.68 1145.50 1254.54 98.54 82.97 69.67
1311.11 1476.68 1636.42 1792.19 140.77 118.53 99.53
1668.68 1879.41 2082.72 2280.97 179.16 150.86 126.67
1835.55 2067.36 2290.99 2509.07 197.07 165.95 139.34
2294.44 2584.19 2863.74 3136.34 246.34 207.43 174.18

150.46 169.46 187.79 205.66 16.15 13.6 11.42


200.97 226.35 250.84 274.72 21.58 18.17 15.26
250.76 282.43 312.98 342.77 26.92 22.67 19.04
407.90 459.41 509.11 557.57 43.79 36.88 30.96
579.65 652.85 723.47 792.34 62.23 52.4 44
716.45 806.93 894.22 979.34 76.92 64.77 54.39
1003.03 1129.70 1251.91 1371.08 107.69 90.68 76.14
1367.77 1540.50 1707.15 1869.65 146.85 123.65 103.83
1671.72 1882.84 2086.51 2285.13 179.48 151.13 126.9

2507.59 2824.26 3129.77 3427.69 269.22 226.7 190.36


3761.38 4236.38 4694.66 5141.54 403.84 340.05 285.54
5015.17 5648.51 6259.54 6855.38 538.45 453.4 380.71

0.5 KM
Cost per unit
Cost for Cost of addl 50m or
1st 50 m part thereof beoynd
first 50 m upto 0.5
8 km 9
52.17 11.36
65.21 14.20
56.70 12.35
104.33 22.72
65.21 14.20
70.50 15.35
76.72 16.70
121.72 26.50
76.08 16.56
52.92 20.67
47.61 6.99
37.77 5.54
81.11 11.90
52.14 7.65
47.61 6.99

95.30 13.98
156.66 22.99
219.23 32.17
280.78 41.20
365.01 53.56
521.44 76.52
730.02 107.12
912.53 133.90
1106.09 162.31
1440.83 211.43
1659.14 243.46

598.38 87.81
799.29 117.29
997.30 146.34
1622.27 238.05
2305.33 338.28
2849.41 418.12
3989.18 585.37
5439.79 798.23
6648.63 975.61
9972.95 1463.42

21.76 3.19
59.84 8.78
85.48 12.54
119.68 17.56
2.6 2.6 Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas
(exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including disposal of excavated earth,
lead upto 50m and lift upto 1.5m, disposed earth to be levelled and neatly dressed.
2.6.1 All kinds of soil
Code Description Unit Quantity Rate A mount
Details of cost for 10 cum.
Average output of Hydraulic Excavator per
hour = 30cum.
MACHINER Y
20 Hydraulic Excavator (3D) with driver and Day 0.04125 8000 330.00
fuel.
18 Hire and running charges of loader. Day 0.04125 8000 330.00
Labour-
128 Mate Day 0.32 543.83 174.03
115 Beldar/Coolie Day 1.2 464.1 556.92
TOTAL 1390.95
Add I % for water charges 13.91
TOTAL 1404.86
Add 15% for contractor’s profit and overheads 210.73
Cost of 10 cum 1615.58
Cost of 1 cum 161.56
Say 161.56
3.1 Cement Mortar 1 : 1 (1 cement : 1 fine sand)
Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.7175 cum. of cement = 1.02 tonne)
367 Cement tonne 1.02 5200.00
2,209 Carriage of Cement tonne 1.02 47.29
983 Fine sand cum 0.7125 300.00
2261 Carriage of Fine sand cum 0.7125 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.9 1.00
mixer
9999 Sundries L.S. 13.52 1.00
TOTAL Cost for 1 cum
Say
Notes:-
1. Cement required for cement mortar
2. 1 Cum
is 71.25%
of cement weight is 1.1286 Tonne

3.2 Cement Mortar 1 : 2 (1 cement : 1 fine sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.475 cum. of cement = 0.68 tonne)
367 Cement tonne 0.68 5200.00
2209 Carriage of Cem ent tonne 0.68 47.29
983 Fine sand cum 0.95 300.00
2261 Carriage of fine sand cum 0.95 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of L.S. 26.91 1.00
mechanical mixer
9999 Sundries L.S. 13.52 1.00
TOTAL Cost for 1 cum
Say
Note:-
1. Cement required is 47.50%

3.3 Cement Mortar 1 : 3(1 cement : 3 fine sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
M ATER IALS (0.375 cum. of cement = 0.51 tonne)
367 Cement tonne 0.514 5200.00
2209 Carriage of Cement tonne 0.514 47.29
983 Fine sand cum 1.07 300.00
2261 Carriage of fine sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.01 1.00
mixer
TOTAL Cost for 1 cum
Say
Note:-
1. Cement required is 35.70%

3.4 Cement Mortar 1 : 4(1 cement : 4 fine sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATER IALS (0.268 cum. of cement = 0.38 tonne)

367Cement tonne 0.38 5200.00


2209Carriage of Cement tonne 0.38 47.29
983Fine sand cum 1.07 300.00
2261Carriage of fine sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
For measuring, carrying, depositing and
mixing-
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of L.S. 26.91 1.00
mechanical mixer
9999 Sundries L.S. 13.52 1.00
TOTAL Cost for 1 cum
Say
1. Cement required is 26.80%

3.5 Cement Mortar 1 : 5 (1 cement : 5 fine sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
M ATER IALS
(0.214 cum. of cement = 0.31 tonne)
367 Cement tonne 0.314 5200.00
2209 Carriage of Cement tonne 0.314 47.29
983 Fine sand cum 1.07 300.00
2261 Carriage of fine sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 cum
1960.55
Say
1960.55
Note:-
1. Cement required is 21.40%
3.6 Cement Mortar 1 : 6 (1 cement : 6 fine sand)
Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS
(0.178 cum. of cement = 0.25 tonne)
367 Cement tonne 0.25 5200.00
2209 Carriage of Cement tonne 0.25 47.29
983 Fine sand cum 1.07 300.00
2261 Carriage of fine sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cement required is 17.80%

3.7 Cement Mortar 1 : 2 (1 Cement : 2 Coarse sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.476 cum. of cement = 0.68 tonne)
367 Cement tonne 0.68 5200.00
2209 Carriage of Cement tonne 0.68 47.29
982 Coarse sand cum 0.95 300.00
2203 Carriage of Coarse sand cum 0.95 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cem ent required is 47.50%

3.8 Cement Mortar 1 : 3 (1 Cement : 3 Coarse sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.357 cum. of cement = 0.51 tonne)
367 Cement tonne 0.51 5200.00
2209 Carriage of Cement tonne 0.51 47.29
982 Coarse sand cum 1.07 300.00
2203 Carriage of Coarse sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cement required is 35.70%

3.9 Cement Mortar 1 : 4 (1 cement : 4 coarse sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.214 cum. of cement = 0.31 tonne)
367 Cement tonne 0.38 5200.00
2209 Carriage of Cement tonne 0.38 47.29
982 Coarse sand cum 1.07 300.00
2203 Carriage of Coarse sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cement required is 26.80%
3.10 Cement Mortar 1 : 5 (1 cement : 5 coarse sand)
Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.214cum. of cement = 0.31 tonne)
367 Cement tonne 0.31 5200.00
2209 Carriage of Cement tonne 0.31 47.29
982 Coarse sand cum 1.07 300.00
2203 Carriage of Coarse sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cement required is 21.40%

3.11 Cement Mortar 1 : 6 (1 cement : 6 coarse sand)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.178 cum. of cement = 0.25 tonne)
367 Cement tonne 0.25 5200.00
2209 Carriage of Cement tonne 0.25 47.29
982 Coarse sand cum 1.07 300.00
2203 Carriage of Coarse sand cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cement required is 17.80%
3.12 Cement Mortar 1 : 2(1 cement : 2 stone dust)
Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATER IALS
(0.475 cum. of cement = 0.68 tonne)
367 Cement tonne 0.68 5200.00
2209 Carriage of Cement tonne 0.68 47.29
1159 Stone dust cum 0.95 700.00
2267 Carriage of stone dust cum 0.95 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 135.25
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cement required is 47.50%

3.13 Cement Mortar 1 : 2(1 cement : 2 marble dust)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.475 cum. of cement = 0.68 tonne)
367 Cement tonne 0.68 5200.00
2209 Carriage of Cement tonne 0.68 47.29
784 Marble dust cum 0.95 800.00
2268 Carriage of Marble dust cum 0.95 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 c um
Say
Note:-
1. Cem ent required is 47.50%
3.14 Cement Mortar 1 : 5(1 cement : 5marble dust)
Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.214 cum. of cement = 0.31 tonne)
367 Cement tonne 0.31 5200.00
2,209 Carriage of Cement tonne 0.31 47.29
784 Marble dust cum 1.07 800.00
2,268 Carriage of Marble dust cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9,999 Hire and running charges of mechanical L.S. 26.91 1.00
9,999 Sundries L.S. 13.52 1.00
Cost of 1.00 cum
Say

Note:-
1. Cement required is 21.40%

3.15 White Cement Mortar 1 : 2 (1 White cement : 2 marble dust)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS
(0.475 cum. of white cement = 0.68 tonne)
368 White Cement tonne 0.68 9500.00
2209 Carriage of White Cement tonne 0.68 47.29
784 Marble dust cum 0.95 800.00
2268 Carriage of Marble dust cum 0.95 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L..S 26.91 1.00
9999 Sundries L..S 13.52 1.00
Cost of 1.00 cum
Say
Note:-
1. White Cement required is 47.50%

3.16 White Cement Mortar 1 : 3(1 white cement : 3 marble dust)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS
(0.357 cum. of white cement = 0.51 tonne)

368 White Cement tonne 0.51 9500.00


2209 Carriage of White Cement tonne 0.51 47.29
784 Marble dust cum 1.07 800.00
2268 Carriage of Marble dust cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L.S. 26.91 1.00
9999 Sundries L.S. 13.52 1.00
Cost of 1.00 cum
Say
Note:-
1. White C ement required is 35.70%

3.17 White Cement Mortar 1 : 5 (1 white cement : 5 marble dust)


Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS (0.214 cum. of white cement = 0.31 tonne)
368 White Cement tonne 0.31 9500.00
2209 Carriage of White Cement tonne 0.31 47.29
784 Marble dust cum 1.07 800.00
2268 Carriage of Marble dust cum 1.07 53.21
LABOUR For measuring, carrying, depositing and mixing
114 Beldar Day 0.75 207
101 Bhisti Day 0.07 180
9999 Hire and running charges of mechanical L. S. 26.91 1.00
9999 Sundries L. S. 13.52 1.00
Cost of 1.00 cum
Say
Note:-
1. White Cement required is 21.40%
3.18 Mud mortar
Code Discription Unit Quantity Rate
Details of cost for 1 cum
MATERIALS
811 Mud (dry) cum 1.08 20.00
LABOUR
114 Beldar Day 0.63 207
101 Bhisti Day 0.315 180
9999 Sundries L. S. 6.45 1.00
TOTAL Cost for 1 cum
Say
Amount

5304.00
48.24
213.75
37.91

155.25
12.60

26.90
13.52
5812.17
5812.17

Amount

3536.00
32.16
285.00
50.55

155.25
12.60

26.91
13.52
4111.99
4111.99

Amount

2672.80
24.31
321.00
56.93

155.25
12.60

26.01
3268.90
3268.90

Amount

1976.00
17.97
321.00
56.93

155.25
12.60

26.91
13.52
2580.18
2580.18

Amount

1632.80
14.85
321.00
56.93

155.25
12.60
26.91
13.52

Amount

1300.00
11.82
321.00
56.93

155.25
12.60
26.91
13.52
1898.04
1898.04

Amount

3536.00
32.16
285.00
50.55

155.25
12.60
26.91
13.52
4111.99
4111.99
Amount

2652.00
24.12
321.00
56.93

155.25
12.60
26.91
13.52
3262.33
3262.33

Amount

1976.00
17.97
321.00
56.93

155.25
12.60
26.91
13.52
2580.18
2580.18

Amount

1612.00
14.66
321.00
56.93

155.25
12.60
26.91
13.52
2212.87
2212.87

Amount

1300.00
11.82
321.00
56.93

155.25
12.60
26.91
13.52
1898.04
1898.04

Amount

3536.00
32.16
665.00
50.55

101.44
12.60
26.91
13.52
4438.17
4438.17

Amount
3536.00
32.16
760.00
50.55

155.25
12.60
26.91
13.52
4586.99
4586.99

Amount

1612.00
14.66
856.00
56.93

155.25
12.60
26.91
13.52
2747.87
2747.87

Amount

6460.00
32.16
760.00
50.55

155.25
12.60
26.91
13.52
7510.99
7510.99

Amount

4845.00
24.12
856.00
56.93

155.25
12.60
26.91
13.52
5990.33
5990.33

Amount

2945.00
14.66
856.00
56.93

155.25
12.60
26.91
13.52
4080.87
4080.87
Amount

21.60

130.41
56.70
6.45
215.16
215.16
4.1 Providing and laying in position cement concrete of specified grade excluding the cost of centring and
shuttering -All work upto plinth level:
4.1.3 1:2:4 ( 1 Cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
C ode Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
M aterials:
295 Stone aggregate 20mm cum 0.67 1400.00 938.00
297 Stone aggregate 10 mm cum 0.22 1400.00 308.00
2202 Carriage of aggregate cum 0.89 138.63 123.38
982 Coarse sand cum 0.445 800.00 356.00
2203 C arriage of c oarse sand cum 0.445 138.67 61.71
367 Cement (0.2833 cum) tonne 0.32 3960.00 1267.20
2209 Carriage of cement tonne 0.32 123.25 39.44
Labour:
155 M ason Day 0.1 655.69 65.57
114 Beldar Day 1.63 464.1 756.48
101 Bhishti Day 0.7 543.83 380.68
2 M ixer Day 0.07 1000 70.00
12 Vibrator Day 0.07 500 35.00
9999 Sundries L.S. 14.3 1.70 24.31
TOTAL 4425.77
Add 1% for water charges 44.26
TOTAL 4470.03
Add 15 % for contractor’s profit and overheads 670.50
Cost of 1 cum. 5140.53
Say 5,140.53
5.2 Reinforced cement concrete work in walls (any thickness), including attached pilasters,
buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc.
upto floor five level excluding cost of centring, shuttering, finishing and reinforcement :
5.2.2 1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
Code Discription Unit Quantity Rate Amount
Details of cost for 9.18 cum
MATER IALS
295 Stone aggregate 20mm cum 5.2326 1400.00 7325.64
297 Stone aggregate 10mm cum 2.5704 1400.00 3598.56
2202 Carriage of aggregate 20mm and 10 mm cum 7.803 138 1076.81

982 Coarse sand cum 3.9015 800.00 3121.20


2203 Carriage of coarse sand cum 3.9015 138 538.41
367 Cement (0.2225 cum) tonne 3.672 3960.00 14541.12
2209 Carriage of cem ent tunne 3.672 123.25 452.57
Labour;
114 Beldar Day 11.29 464.1 5239.69
115 Coolie Day 7.53 464.1 3494.67
101 Bhishti Day 8.26 543.83 4492.04
123 Mason 1st class Day 0.92 655.69 603.23
124 Mason 2nd class Day 0.92 543.83 500.32
2 Mixer Day 0.64 1000 640.00
12 Vibrator Day 0.64 500 320.00
9999 Sundries L.S 131.82 1.70 224.09
9999 Scaffolding L.S 420.03 1.70 714.05
Extra labour for lifting of material upto floor V level: Coolie (0.75x9.18x2.5)
115 Coolie Day 17.2 464.1 7982.52
TOTAL 54864.94
Add 1% for water charges 548.65
TOTAL 55413.59
Add 15 % for contractor’s profit and overheads 8312.04
Cost of 9.18 cum. 63725.62
cost of 1 cum. 6941.79
Say
attached pilasters,
posts and struts etc.
nt :
ze)

6,941.79
6.1 Brick work with F.P.S. bricks of class designation 75 in foundation and plinth in:
6.1.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
2602 Bricks of c lass designation 75 1000 Nos 494 1600.00
Cement mortar 1:4 (Rate as per item No. 3.9) cum 0.25 2580.18
2201 Carriage of bricks 1000 Nos 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.36 270
124 Mason Ilnd Class Day 0.36 223
115 Coolie Day 1.37 207
101 Bhishti Day 0.2 180
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

6.1 Brick work with F.P.S. bricks of class designation 75 in foundation and plinth in:
6.1.2 Cement mortar 1:6 (1 cement : 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
2602 Bricks of c lass designation 75 1000 Nos 494 1600.00
Cement mortar 1:6 (Rate as per item No. 3.11) cum 0.25 1898.04
2201 Carriage of bricks 1000 Nos 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.36 270
124 Mason Ilnd Class Day 0.36 223
115 Coolie Day 1.37 207
101 Bhishti Day 0.2 180
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

6.2 Brick work with modular bricks of class designation 75 in foundation and plinth in:
6.2.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
7900 Bricks of c lass designation 75 1000 Nos 487 2050.00
Cement mortar 1:4 (Rate as per item No. 3.9) cum 0.22 2580.18
2201 Carriage of bricks 1000 Nos 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.33 270
124 Mason Ilnd Class Day 0.33 223
115 Coolie Day 1 207
101 Bhishti Day 0.18 180
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

6.2 Brick work with modular bricks of class designation 75 in foundation and plinth in:
6.2.2 Cement mortar 1:6 (1 cement : 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
7900 Modulur Bricks of class designation 75 1000 Nos 487 2050.00
Cement mortar 1:4 (Rate as per item No. 3.9) cum 0.22 1898.04
2201 Carriage of bricks 1000 Nos 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.33 270
124 Mason Ilnd Class Day 0.33 223
115 Coolie Day 1 207
101 Bhishti Day 0.18 180
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

6.3 Brick work with machine moulded perforated bricks of class designation 125 conforming to IS: 2222
-1991 in superstructure above plinth level upto floor five level in cement mortar 1:6(1 cement : 6 coarse
sand):
6.3.1 With F.P.S. bricks.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
7901 Machine moulded perforated FPS bricks of class 1000 Nos 494
designation 125 3233.00
Cement mortar 1:4 (Rate as per item No. 3.9) cum 0.25 1898.04
2201 Carriage of bricks 1000 Nos 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.47 270
124 Mason Ilnd Class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 22.36 1.00
Extra labour element required for lifting of materials (above floor two level upto floor five level)
115 Coolie Day 1.13 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

6.3 Brick work with machine moulded perforated bricks of class designation 125 conforming to IS: 2222
-1991 in superstructure above plinth level upto floor five level in cement mortar 1:6(1 cement : 6 coarse
sand):
6.3.2 With Modular bricks.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
7902 Machine moulded modular perforated bricks of 1000 Nos 487
class designation 125 3200.00
Cement mortar 1:4 (Rate as per item No. 3.9) cum 0.22 2580.18
2201 Carriage of bricks 1000 Nos 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.44 270
124 Mason Ilnd Class Day 0.44 223
115 Coolie Day 1.43 207
101 Bhishti Day 0.18 180
9999 Scaffolding L.S. 16.38 1.00
Extra labour element required for lifting of materials (above floor two level upto floor five level)
115 Coolie Day 1.13 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say
6.4 Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V
level in all shapes and sizes in :
6.4.1 Cement mortar 1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
2602 Bricks of c lass designation 75 1000 Nos 494 1600.00
Cement mortar 1:6 (Rate as per item No. 3.9) cum 0.25 1898.04
2201 Carriage of bricks 1000 Nos 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.47 270
124 Mason Ilnd Class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 22.36 1.00
Extra labour element required for lifting of materials (above floor two level upto floor five level)
115 Coolie Day 1.13 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

6.4 Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V
level in all shapes and sizes in :
6.4.2 Cement mortar 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATER IALS :
2602 Bricks of c lass designation 75 1000 Nos 494 1600.00
Cement mortar 1:4 (Rate as per item No. 3.9) cum 0.25 1898.04
2201 Carriage of bricks 1000 Nos 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st Class Day 0.47 270
124 Mason Ilnd Class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 22.36 1.00
Extra labour element required for lifting of materials (above floor two level upto floor five level)
115 Coolie Day 1.13 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

6.5 Extra for brick work in superstructure above floor V level for each four floors or part thereof by
mechanical means by lifting material using mobile crane.
Code Description Unit Quantity Rate
Details of cost for 5.3 cum per four floors .
37 Mobile crane. per day 0.125 5000
1235 Diesel oil litre 8 53.17
TOTAL
Add 1 % for water charges
TOTAL
Add for contractor’s profit and overheads @15%

Cost of 5.3 Cum.


Cost for 1 cum
Say

6.6 Extra for forming cavity 5cm to 7.5cm wide in cavity walls with necessary weep and vent holes including
use of cores and cost of providing and fixing bitumastic coated M .S. ties 300mm long of 25x3mm section at
not less than 3 ties per sqm as per approved design.
Code Description Unit Quantity Rate
Details of cost for 10s qm.
Materials :
1008 Mild steel 25mmx3mm section 30cm long 30 quintal 0.054 4600.00
9999 Painting the steel Bitumen L.S 13.52 1.00
2205 Carriage of mild steel tonne 0.005 47.29
Extra labour for keeping cavity clear and fixing wall ties and delay caused:
123 Mason 1st class Day 0.37 270
124 Mason 2nd Class Day 0.37 223
114 Beldar Day 0.92 207
9999 Add for use of Core L.S 4.55 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say

6.7 Providing half brick masonry with F.P.S. bricks of class designation 75 in cement mortar 1:3 (1 Cement :
3coarse sand) in superstructure for closing cavity 5 to 7.5 cm wide in cavity wall complete with 10 cm / 11.4
cm wide bitumen felt type 3 grade 1.
Code Description Unit Quantity Rate
Details of cost for 10m length
Materials :
Half brick masonry 1:3 (Average) 1x10x0.27 = 2.7 sqm 2.7
Rate as per item No.6.12.1
0322 (B) Bitumen felt type- 3 grade 1 sqm 1.2 45.00
Labour:
0123 (B) Mason 1st class Day 0.12 270
0124 (B) Mason 2nd class Day 0.12 223
0114 (B) Beldar Day 0.06 207
TOTAL
(C) Add for water charges @ 1 % on B
TOTAL
Add for contractor’s profit and overheads at 15%
on (B+C)
Cost of 10 metre
Cost for 1 metre
Say

6.8 Brick work 7 cm thick with F.P.S. brick of class designation 75 in cement mortar 1:3 (1 cement: 3 coarse
sand) in superstructure.
Code Description Unit Quantity Rate
Details of cost for 10sqm.
Materials:
2602 Bricks of class designation 75 1 000 Nos 377 1600.00
Cement mortar 1:3 (Rate as per item no. 3.8 ) cum 0.181 3262.33
2201 Carriage of bricks 1000 Nos 377 141.88
LABOUR:
123 Mason 1st class Day 0.72 270
124 Mason 2nd class Day 0.72 223
115 Coolie Day 1.76 207
101 Bhishti Day 0.36 180
9999 Sundries and scaffolding L.S. 7.15 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say

6.9 Brick work in plain arches in superstructure including centring and shuttering complete for span upto 6
metres with F.P.S. bricks of class designation 75 in cement plete for span upto 6 metres with F.P.S. bricks of
class designation 75 in cement
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
Materials:
2602 Bricks of class designation 75 1 000 Nos 494 1600.00
Cement mortar 1:3 (Rate as per item no. 3.8 ) cum 0.25 3262.33
2201 Carriage of bricks 1000 Nos 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.53 270
124 Mason 2nd class Day 0.53 223
115 Coolie Day 2.29 207
101 Bhishti Day 0.2 180
9999 Sundries and scaffolding L.S. 18.85 1.00
(B) Centering and Shuttering: (Rate same as in item
5.9.9 sqm 2.25 658.69
TOTAL
Add for water charges @ 1% on all except B
TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.10 Brick work in gauged arches in superstructure in cement mortar 1:3 (1 cement : 3 coarse sand)
including centring and shuttering complete, for span upto 6 meters with F.P.S. bricks of class designation 75
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
2602 Bricks of class designation 75 1 000 Nos 538 1600.00
Cement mortar 1:3 (Rate as per item no. 3.8 ) cum 0.25 3262.33
2201 Carriage of bricks 1000 Nos 538 141.88
9999 Sundries L.S. 2.73 1.00
Centring and shuttering (B) (Rate same as per item sqm
No. 5.9.9 2.25 658.69
9999 Scaffolding L.S. 18.85 1.00
LABOUR:
123 Mason 1st class Day 1.13 270
124 Mason 2nd class Day 1.13 223
115 Coolie Day 4.42 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% on all except B
TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.11 Extra for additional cost of centring for arches exceeding 6m span including all shuttering, bolting,
wedging and removal (Area of the soffit to be measured).
Code Description Unit Quantity Rate
Details of cost per sqm.
Centering and shuttering for arches and carved surface exceeding 6m in span (an average of 8m)
Material:
1197 Second class kail wood in scantling 10 cudm 887.9 160.00
2204 Carriage of wood cum 0.8879 60.81
Fittings:
1225 Mild steel flat strap fitting quintal 0.0878 2900.00
1034 Bolts 160 Nos. 254 mm long 16mm dia.- quintal 0.08 7000.00
2302 Carriage of steel = 0.1342 t tonne 0.0168 47.29
Labour:
112 Carpenter 2nd class Day 28 223
114 Beldar Day 24 207
9999 Sundries L.S 134.55 1.00
Less Cost of shuttering etc. for an arch exceeding 6 m span i.e. for an average of 8 m
(A) Rate as per item no- 5.9.9 sqm 33.31 658.69
TOTAL
Add 1% for water charges on all exept ‘A’
TOTAL
Add for contractor’s profit and overheads @15%
on all except ‘A’
Cost of 33.31 sqm.
Cost per sqm.
Say

6.12 Half brick masonry with F.P.S. bricks of class designation 75 in foundation and plinth in:
6.12.1 Cement mortar 1 : 3 (1 cement : 3 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 10 sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565 1600.00
B Cement mortar 1:3 (Rate as per item No. 3.8) cum 0.28 3262.33
2201 Carriage of bricks 1 000 Nos 565 141.88
9999 Sundries & Scaffolding L.S 13.52 1.00
LABOUR:
123 Mason 1 st class Day 0.45 270
124 Mason 2nd class Day 0.45 223
115 Coolie Day 1.55 207
101 Bhishti Day 0.7 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say

6.12 Half brick masonry with F.P.S. bricks of class designation 75 in foundation and plinth in:
6.12.2 Cement mortar 1 : 4 (1 cement : 4coarse sand)
Code Description Unit Quantity Rate
Details of cost per sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565 1600.00
B Cement mortar 1:3 (Rate as per item No. 3.9) cum 0.28 2580.18
2201 Carriage of bricks 1 000 Nos 565 141.88
9999 Sundries & Scaffolding L.S 13.52 1.00
LABOUR:
123 Mason 1 st class Day 0.45 270
124 Mason 2nd class Day 0.45 223
115 Coolie Day 1.55 207
101 Bhishti Day 0.7 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say

6.13 Half brick masonry with F.P.S. bricks of class designation 75 in superstructure above
plinth level upto floor V level in
6.13.1 Cement mortar 1 : 3 (1 cement : 3 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 10 sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565 1600.00
B Cement mortar 1:3 (Rate as per item No. 3.8) cum 0.28 3262.33
2201 Carriage of bricks 1 000 Nos 565 141.88
9999 Sundries & Scaffolding L.S 13.52 1.00
LABOUR:
123 Mason 1 st class Day 0.6 270
124 Mason 2nd class Day 0.6 223
115 Coolie Day 2 207
101 Bhishti Day 0.7 180
Extra labour element required for lifting of materials (above floor two level upto floor five level)
115 Coolie Day 1.29 207
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say
6.13 Half brick masonry with F.P.S. bricks of class designation 75 in superstructure above plinth level upto
floor V level in
6.13.2 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 10 sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565 1600.00
B Cement mortar 1:3 (Rate as per item No. 3.8) cum 0.28 2580.18
2201 Carriage of bricks 1 000 Nos 565 141.88
9999 Sundries & Scaffolding L.S 13.52 1.00
LABOUR:
123 Mason 1 st class Day 0.6 270
124 Mason 2nd class Day 0.6 223
115 Coolie Day 2 207
101 Bhishti Day 0.7 180
Extra labour element required for lifting of materials (above floor two level upto floor five level)
115 Coolie Day 1.29 207
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say

6.14 Extra for half brick masonry in superstructure, above floor V level for every four floors or part thereof
by mechanical means by lifting material using mobile crane.
Code Description Unit Quantity Rate
Details of cost for 59.83 sqm per four floors
37 Mobile crane. per day 0.125 5000
1235 Diesel oil litre 8 53.17
TOTAL
Add 1 % for water charges
TOTAL
Add for contractor’s profit and overheads @15%

Cost of 59.83 sqm


Cost for 1 cum
Say

6.15 Extra for providing and placing in position 2 Nos. 6mm dia. M.S. bars at every third course of half brick
masonry (with F.P.S. bricks)
Code Description Unit Quantity Rate
Details of cost for 10 sqm per four floors
1002 (a) 6mm dia. M.S. bars (round) 2 Nos. @ 30 quintal 0.132 4300.00
2205 (B) Carriage of M.S. Bars tonne 0.0132 47.29
9999 Sundries L.S. 1.82 1.00
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say

6.16 Tile brick masonry with tite bricks of class designation 100 in foundation and plinth in:
6.16.1 Cem en t m o rta r 1 : 4 (1 cem e nt : 4 co ars e san d )
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
1984 Brick tiles of class designation 100 1000 Nos 777 1600.00
Cem ent mortar 1:4(1 Cement: 4 coarse sand) cum 0.4
(Rate as per item no. 3.9) 2580.18
2207 Carriage or brick tiles 1000 Nos 777 85.13
9999 Sundries L.S. 4.55 1.00
Labour:
123 Mason 1st class Day 0.7 270
124 Mason 2nd class Day 0.7 223
115 Coolie Day 1.54 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

6.16 Tile brick masonry with tite bricks of class designation 100 in foundation and plinth in:
6.16.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
1984 Brick tiles of class designation 100 1000 Nos 777 1600.00
Cem ent mortar 1:4(1 Cement: 4 coarse sand) cum 0.4
(Rate as per item no. 3.11) 1898.04
2207 Carriage or brick tiles 1000 Nos 777 85.13
9999 Sundries L.S. 4.55 1.00
Labour:
123 Mason 1st class Day 0.7 270
124 Mason 2nd class Day 0.7 223
115 Coolie Day 1.54 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

6.17 Tile brick masonry with machine moulded tile bricks of class designation 125 conforming to IS : 2690
(Part I) -1993 in foundation and plinth in cement mortar
1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
7904 Machine moulded tile bricks of class designation 1000 Nos 777
125 2717.00
2207 Carriage of Brick tiles 1000 Nos 777 85.13
Cement mortar 1:6 (1 cement: 6 coarse sand). cum
(Rates as per item no. 3.11) 0.4 1898.04
9999 Sundries L.S. 4.55 1.00
Labour:
123 Mason 1st class Day 0.7 270
124 Mason 2nd class Day 0.7 223
115 Coolie Day 1.54 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

6.18 Tile brick masonry with tile brick of class designation 100 in superstructure above
Plinth level upto floor V level in cement mortar 1:6 (1 cement :6coarse sand).
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
1984 Machine moulded tile bricks of class designation 1000 Nos 777
125 1600.00
2207 Carriage of Brick tiles 1000 Nos 777 85.13
Cement mortar 1:6 (1 cement: 6 coarse sand). cum
(Rates as per item no. 3.11) 0.4 1898.04
9999 Sundries L.S. 4.55 1.00
Labour:
123 Mason 1st class Day 0.9 270
124 Mason 2nd class Day 0.9 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
Extra labour for lifting of materials
115 Coolie Day 1.13 207
9999 Cost of scaffolding L.S. 33.8 1.00
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

6.19 Extra for tile brick masonry with tile bricks of class designation 100 in superstructure above floor five
level for every four floors or part thereof.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.5 207
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum

6.20 Tile brick m asonry with tite bricks of class designation 100 in plain arch work in superstructure in
cement mortar 1 : 4 ( 1 cement : 4 coarse sand) including centering and shuttering complete.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS
1984 Machine moulded tile bricks of class designation 1000 Nos 777
125 1600.00
2207 Carriage of Brick tiles 1000 Nos 777 85.13
Cement mortar 1:4 (1 cement: 4 coarse sand). cum
(Rates as per item no. 3.9) 0.35 2580.18
9999 Sundries L.S. 5.46 1.00
Centering and shuttering Rate as per item no. sqm
5.9.9 2.25 658.69
9999 Scaffolding L.S. 18.85 1.00
Labour:
123 Mason 1st class Day 0.79 270
124 Mason 2nd class Day 0.79 223
115 Coolie Day 3.21 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% on all except B
TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.21 Tile brick masonry with tile bricks of class designation 100 in gauged arch work in superstructure in
cement mortar 1:4 (1 cement: 4 coarse sand) including centring and shuttering complete.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS
1984 Machine moulded tile bricks of class designation 1000 Nos 791
125 1600.00
2207 Carriage of Brick tiles 1000 Nos 791 85.13
Cement mortar 1:4 (1 cement: 4 coarse sand). cum
(Rates as per item no. 3.9) 0.35 2580.18
9999 Sundries L.S. 5.46 1.00
Centering and shuttering Rate as per item no. sqm
5.9.9 2.25 658.69
9999 Scaffolding L.S. 18.85 1.00
Labour:
123 Mason 1st class Day 1.5 270
124 Mason 2nd class Day 1.5 223
115 Coolie Day 5.33 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% on all except B
TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.22 Tile brick masonry work 5 cm thick with tile bricks of class designation 100 in cement mortar in 1:3
(1 cement: 3 coarse sand) in superstructure.
Code Description Unit Quantity Rate
Details of cost for 10 sqm.
MATERIALS
1984 Machine moulded tile bricks of class designation 1000 Nos 377
125 1600.00
2207 Carriage of Brick tiles 1000 Nos 377 85.13
Cement mortar 1:3 (1 cement: 3 coarse sand). cum
(Rates as per item no. 3.8) 0.15 3262.33
9999 Sundries & Scaffolding L.S. 8.06 1.00
Labour:
123 Mason 1st class Day 0.94 270
124 Mason 2nd class Day 0.94 223
115 Coolie Day 1.88 207
101 Bhishti Day 0.33 180
TOTAL
Add for water charges @ 1% on all except B
TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 10 sqm
Cost of 1 sqm
Say

6.23 Honey-comb brick work 10/11.4 cm thick with bricks of class designation 75 in cement mortar in 1:4 (1
cement : 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1sqm. of Honey comb
brick works-Materials :
(1) Brick work, with bricks of class designation cum 0.069
75, in cement mortar 1:4 (1 Cement: 4 Coarse
sand) in superstructure Rate as per item no 6.4.1 2482.32
9999 (A) (2) Extra for delay due to fine w ork L.S 20.67 1.00
TOTAL
(B) Add for water charges @ 1 % on ‘A’
TOTAL
Add for contractor’s profit and overheads @15%
on A+B
3.13 Cost for 1 sqm.
Say

6.24 Extra for laying brick work in or under water and/or liquid mud including cost of pumping or bailing
out water and removing slush etc. complete.
Code Description Unit Quantity Rate
Details of cost for depth of water 0.30m.
Quantity of concrete = 14 cum. Pumping hours = 3 hrs. or 0.375 days.
11 Hire charge of pump set of capacity 4000 ltr/hr. Day 0.375 200
114 Beldar for cleaning slush Day 4 207
TOTAL
Add for water charges @ 1% on all except B
TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 10 sqm
Cost of 1 sqm
Say

NOTE :- The quantity will be calculated by multiplying the depth measured from sub - soil water level upto
the centre of gravity of brick work under sub - water with the quantity of brick work in cum executed under
the sub - soil water. The depth of cento of gravity shall be reckoned correct to 0.1m, 0.05m or more shall be
taken as 0.1 m and less than 0.05m ignored.

6.25 Extra for laying brick work in or under foul position.


Code Description Unit Quantity Rate
Details of cost for 1 cum.
Extra labour due to slow progress-
123 Mason 1st class Day 0.02 270
124 Mason 2nd class Day 0.02 223
115 Coolie Day 0.15 207
114 Beldar Day 0.25 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.26 Brick work with selected F.P.S. bricks of class designation 75 in exposed brick work including making
horizontal and vertical grooves 10mm wide 12mm deep complete from ground level upto plinth level in
cement mortar 1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
2602 Bricks of class designation 75 1000 Nos 494 1600.00
2201 Carriage of bricks 1000 Nos 494 141.88
Cement mortar 1:6(1 cement: 6 coarse sand) cum 0.25
(Rate as per item no. 3.11) 1898.04
9999 Sundries including steel/wooden strips for L.S. 16.38
making grooves. For selection of bricks 1.00
Labour:
123 Mason 1st class Day 0.35 270
124 Mason 2nd class Day 0.35 223
115 Coolie Day 1.07 207
114 Beldar Day 0.5 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.27 Brick work with modular bricks of class designation 75 in exposed brick work in-cluding making
horizontal and vertical grooves 10mm wide 12mm deep complete from ground level upto plinth level in
cement mortar 1:6 (1 cement: 6 coarse sand).
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS :
7900 Modular bricks of class designation 75 1000 Nos 487 2050.00
Cement mortar 1:6 (1 cement: 6 coarse sand (Rate cum
as per item no. 3.11) 0.22 1898.04
2201 Carriage of Bricks 1000 Nos 487 141.88
9999 Sundries l/c steel/ wooden strips for-making L.S. 16.38
grooves 1.00
LABOUR:
123 Mason 1st class Day 0.33 270
124 Mason 2nd class Day 0.33 223
115 Coolie Day 1 207
101 Bhishti Day 0.18 180
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.28 Brick work with machine moulded modular bricks of class designation 125 in exposed brick work
including making horizontal and vertical grooves 10mm wide 12mm deep complete from ground level upto
plinth level in cement mortar 1:6 (1 cement: 6 coarse sand).
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS :
1986 Machine moulded tile bricks of class designation 1000 Nos 487
75 1600.00
Cement mortar 1:6 (1 cement: 6 coarse sand (Rate cum
as per item no. 3.11) 0.22 1898.04
2201 Carriage of Bricks 1000 Nos 487 141.88
9999 Sundries l/c steel/ wooden strips for-making L.S. 16.38
grooves 1.00
LABOUR:
123 Mason 1st class Day 0.33 270
124 Mason 2nd class Day 0.33 223
115 Coolie Day 1 207
101 Bhishti Day 0.18 180
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say
6.29 Brick work with machine moulded F.P.S. bricks of class designation 125 in exposed brick work
including making horizontal and vertical grooves 10mm wide 12 mm deep complete from ground level upto
plinth level in cement mortar 1:6(1 cement: 6 coarse sand).
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS :
7903 Machine moulded modular perforated bricks of 1000 Nos 494
class designation 125 2767.00
Cement mortar 1:6 (1 cement: 6 coarse sand (Rate cum
as per item no. 3.11) 0.25 1898.04
2201 Carriage of Bricks 1000 Nos 494 141.88
9999 Sundries l/c steel/ wooden strips for-making L.S. 16.38
grooves 1.00
LABOUR:
123 Mason 1st class Day 0.36 270
124 Mason 2nd class Day 0.36 223
115 Coolie Day 1.37 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.30 Brick work with machine moulded perforated F.P.S. bricks of class designation 125 conforming IS :
2222-1991 in exposed brick work including making horizontal and vertical grooves 10mm wide 12 mm deep
complete from ground level upto plinth level in cement mortar 1:6(1 cement: 6 coarse sand).
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS :
7901 Machine moulded perforated FPS bricks of class 1000 Nos 494
designation 125 3233.00
Cement mortar 1:6 (1 cement: 6 coarse sand (Rate cum
as per item no. 3.11) 0.25 1898.04
2201 Carriage of Bricks 1000 Nos 494 141.88
9999 Sundries l/c steel/ wooden strips for-making L.S. 16.38
grooves 1.00
LABOUR:
123 Mason 1st class Day 0.36 270
124 Mason 2nd class Day 0.36 223
115 Coolie Day 1.37 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% on all except B
TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.31 Brick work with machine moulded perforated modular bricks of class designation 125 conforming to IS :
2222 -1991 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12mm deep
complete from ground level upto plinth level in cement mortar 1:6 (1 cement: 6 coarse sand).
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS :
7902 Machine moulded modular perforated bricks of 1000 Nos 487
class designation 125 3200.00
Cement mortar 1:6 (1 cement: 6 coarse sand (Rate cum
as per item no. 3.11) 0.22 1898.04
2201 Carriage of Bricks 1000 Nos 487 141.88
9999 Sundries l/c steel/ wooden strips for-making L.S. 16.38
grooves 1.00
LABOUR:
123 Mason 1st class Day 0.33 270
124 Mason 2nd class Day 0.33 223
115 Coolie Day 1 207
101 Bhishti Day 0.18 180
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.32 Brick work with clay flyash F.P.S. brick of class designation 75 in superstructure above plinth level upto
floor five level in :
6.32.1 Cement mortar 1:4(1 cement : 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
7008 Clay flyash bricks of class designation 75 1000 Nos 494 1412.00
Cement mortar1: 4 (1 cement: 4 coarse sand) cum 0.25
(Rate as per item no 3.9) 2580.18
2201 Carriage of bricks ‘ 1000 Nos. 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.47 270
124 Mason 2nd class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 8.97 1.00
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.13 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.32 Brick work with clay flyash F.P.S. brick of class designation 75 in superstructure above plinth level upto
floor five level in :
6.32.2 Cement mortar 1:6(1 cement: 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
7008 Clay flyash bricks of class designation 75 1000 Nos 494 1412.00
Cement mortar1: 6 (1 cement: 6 coarse sand) cum 0.25
(Rate as per item no 3.9) 1898.04
2201 Carriage of bricks ‘ 1000 Nos. 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.47 270
124 Mason 2nd class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 8.97 1.00
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.13 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.33 Extra for exposed brick work/clay flyash brick work in superstructure above floor five level, for each
four floors or part thereof.
Code Description Unit Quantity Rate
Details of cost for per cum. per four floor
Extra labour element required for lifting of materials 0.75x2.00=1.50
115 Coolie Day 1.5 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.34 Brick work with modular fly ash lime bricks (FALG Bricks) conforming to IS: 12894-2002, class
designation 100 plinth level upto floor V level in :average compressive strength in super structure above
6.34.1 Cement mortar 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials:
7737 7737 Fly ash bricks of class designation 100 1000 Nos 487 1792.00
Cement mortar1: 4 (1 cement: 4 coarse sand) cum 0.22
(Rate as per item no 3.9) 2580.18
2201 Carriage of bricks ‘ 1000 Nos. 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.47 270
124 Mason 2nd class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 22.36 1.00
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.13 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.34 Brick work with modular fly ash lime bricks (FALG Bricks) conforming to IS: 12894-2002, class
designation 100 plinth level upto floor V level in :average compressive strength in super structure above
6.34.2 Cement mortar 1:6(1 cement: 6 Coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum
Materials :
7737 7737 Fly ash bricks of class designation 100 1000 Nos 487 1792.00
Cement mortar1: 6 (1 cement: 6 coarse sand) cum 0.22
(Rate as per item no 3.11) 1898.04
2201 Carriage of bricks ‘ 1000 Nos. 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.47 270
124 Mason 2nd class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 22.36 1.00
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.13 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.35 Brick work with modular calcium silicate bricks machine moulded conforming to IS:4139-1989, class
designation 100 average compressive strength in super structure above plinth level upto floor V level in :
6.35.1 Cement mortar 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
7738 Calcium silicate bricks of class designation100 1000 Nos. 487 3083.00
Cement mortar1: 4 (1 cement: 4 coarse sand) cum 0.22
(Rate as per item no 3.9) 2580.18
2201 Carriage of bricks ‘ 1000 Nos. 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.47 270
124 Mason 2nd class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 22.36 1.00
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.13 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.35 Brick work with modular calcium silicate bricks machine moulded conforming to IS:4139-1989, class
designation 100 average compressive strength in super structure above plinth level upto floor V level in :
6.35.2 Cement mortar 1:6 (1 cement: 6 Coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
7738 Calcium silicate bricks of class designation100 1000 Nos. 487 3083.00
Cement mortar1: 6 (1 cement: 6 coarse sand) cum 0.22
(Rate as per item no 3.11) 1898.04
2201 Carriage of bricks ‘ 1000 Nos. 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.47 270
124 Mason 2nd class Day 0.47 223
115 Coolie Day 1.8 207
101 Bhishti Day 0.2 180
9999 Scaffolding L.S. 22.36 1.00
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.13 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.36 Brick work with modular extruded burnt fly ash clay sewer bricks (Conforming to IS: 4885 - 1988) in
foundation and plinth :
6.36.1 Cement Mortar 1:4(1 cement: 4 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
7736 Extruded burnt flyash clay sewer bricks 1000 Nos 487 3550.00
Cem ent mortar 1:4(1 cement: 4 coarse sand) 0.22
(Rate as per item No. 3.9) cum 2580.18
2201 Carriage of bricks ‘ 1000 Nos. 487 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.33 270
124 Mason 2nd class Day 0.33 223
115 Coolie Day 1 207
101 Bhishti Day 0.18 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say
6.37 Brick work with modular extruded burnt fly ash clay sewer bricks (conforming to IS : 4885-1988) in
arches in foundation and plinth in cement mortar 1:3(1 cement: 3 fine sand).
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
7736 Extruded burnt flyash clay sewer bricks 1000 Nos 487 3550.00
Cem ent mortar 1:3(1 cement: 3 fine sand) (Rate 0.25
as per item No. 3.3) cum 3268.90
2201 Carriage of bricks ‘ 1000 Nos. 487 141.88
9999 Sundries L.S. 2.73 1.00
(A) Centering and shuttering
(Rate as per item no 5.9.9 SH : RCC) sqm 2.25 658.69
LABOUR:
123 Mason 1st class Day 0.42 270
124 Mason 2nd class Day 0.42 223
115 Coolie Day 1.86 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% except on A
TOTAL
Add for contractor’s profit and overheads
@15% except on A
TOTAL
Say

6.38 Providing and laying autoclaved aerated cement blocks masonry with 100mm thick AAC blocks in super
structure above plinth level upto floor V level in cement mortar 1:4 (1 cement : 4 coarse sand ) The rate
includes providing and placing in position 2 Nos. 6 mm dia M.S. bars at every third course of masonry work.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
MATERIALS :
8655 Autoclaved aerated cement (AAC) blocks. cum 1 1,650.00
Cem ent mortar 1:4(1 cement: 4 coarse sand) 0.15
(Rate as per item No. 3.9) cum 2580.18
2208 Carriage of AAC blocks cum 1 53.21
9999 Sundries L.S. 2.73 1.00
(A) Reinforcement bars
Rate as per item no 5.22.1 of SH : RCC kg 13.2 58.65
LABOUR:
123 Mason 1st class Day 0.36 270
124 Mason 2nd class Day 0.36 223
115 Coolie Day 1.37 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1% except on A
TOTAL
Add for contractor’s profit and overheads
@15% except on A
TOTAL
Say
6.39 Extra for AAC block masonry in superstructure above floor V level for every four floors or part there of
Code Description Unit Quantity Rate
Extra labour element for lifting of materials (upto floor V level)
115 Coolie Day 1.5 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

6.40 Providing and laying Gypsum panel partitions 100mm thick with water proof Gypsum panels of size
666x500x100mm, made of ‘calcite phosphor of Gypsum fixed with tongue and groove, jointed with bonding
plaster as per manufacturers specifications in superstructure above plinth level upto floor V level. Gypsum
blocks will have a minimum compressive strength of 9.3 kg/sq cm

Code Description Unit Quantity Rate


Details of cost for 10 sqm.
MATERIAL
8656 Gypsum panel 666 X 500 X 100 mm size. sqm 10 544.00
8657 Bonding plaster for Gypsum panel. kg 25 50.00
9999 Sundries & scaffolding L.S. 13.52 1.00
LABOUR:
123 Mason 1st class Day 0.5 270
114 Beldar Day 1 207
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 10 sqm
Cost of 1 sqm
Say

6.41 Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part
thereof.
Code Description Unit Quantity Rate
Details of cost for 10 sqm. per four floor
Extra labour element for lifting of materials above floor V level.
115 Coolie Day 1.73 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 10 sqm
Cost of 1 sqm
Say

6.42 Brick work with mechanised autoclaved flyash lime bricks conforming to I:S 12894 : 2002 of class
designation 100 in superstructure above plinth level upto floor V level in.
6.42.1 Cement mortar 1:4 (1 cement :4 coarse sand).
Code Description Unit Quantity Rate
Details of Cost for 10 cum
MATERIALS
8658 Mechanised Autoclaved flyash lime bricks. 1000 Nos 494 2,200.00
Cem ent mortar 1:4(1 cement: 4 coarse sand) 0.25
(Rate as per item No. 3.9) cum 2580.18
2201 Carriage of bricks ‘ 1000 Nos. 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.36 270
124 Mason 2nd class Day 0.36 223
115 Coolie Day 1.37 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

6.42 Brick work with mechanised autoclaved flyash lime bricks conforming to I:S 12894 : 2002 of class
designation 100 in superstructure above plinth level upto floor V level in.
6.42.2 Cement mortar 1:6 (1 cement :6 coarse sand).
Code Description Unit Quantity Rate
Details of Cost for 10 cum
MATERIALS
8658 Mechanised Autoclaved flyash lime bricks. 1000 Nos 494 2,200.00
Cement mortar1: 6 (1 cement: 6 coarse sand) cum 0.25
(Rate as per item no 3.11) 1898.04
2201 Carriage of bricks ‘ 1000 Nos. 494 141.88
9999 Sundries L.S. 2.73 1.00
LABOUR:
123 Mason 1st class Day 0.36 270
124 Mason 2nd class Day 0.36 223
115 Coolie Day 1.37 207
101 Bhishti Day 0.2 180
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

6.43 Extra for mechanised autoclave flyash lime bricks conforming to IS: 12894- 1990 of class designation
100 in superstructure above floor V level for each four floors or part thereof.
Code Description Unit Quantity Rate
Details of cost for 10 sqm. per four floor
Extra labour element for lifting of materials above floor V level.
115 Coolie Day 1.5 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 10 sqm
Say

6.44 Brick edging 7cm wide 11.4cm deep to plinth protection with bricks of class designation 75
including grouting with cement mortar 1:4(1 cement: 4 fine sand).
Code Description Unit Quantity Rate
Details of cost for 10m length
9999 Sundries L.S. 2.73 1.00
2602 Bricks of class designation 75 1000 Nos 46 1600.00
2201 Carriage of bricks 1000 Nos 46 141.88
Cem ent mortat 1:4 (R ate as per item no. 3.4) cum 0.0036 2580.18
LABOUR:
155 Mason Day 0.1 180
114 Beldar Day 0.1 207
101 Bhishti Day 0.03 180
9999 Sundries L.S. 2.73 1.00
TOTAL
Add for water charges @ 1%
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 sqm
Cost of 1 sqm
Say
Amount

790.40
645.05
70.09
2.73

97.20
80.28
283.59
36.00
2005.33
20.05
2025.39

303.81
2329.20
2329.20

Amount

790.40
474.51
70.09
2.73

97.20
80.28
283.59
36.00
1834.80
18.35
1853.15

277.97
2131.12
2131.12

Amount
998.35
567.64
69.10
2.73

89.10
73.59
207.00
32.40
2039.91
20.40
2060.30

309.05
2369.35
2369.35

Amount

998.35
417.57
69.10
2.73

89.10
73.59
207.00
32.40
1889.83
18.90
1908.73

286.31
2195.04
2195.04

conforming to IS: 2222


6(1 cement : 6 coarse

Amount

1597.10
474.51
70.09
2.73

126.90
104.81
372.60
36.00
22.36
r five level)
233.91
3041.01
30.41
3071.42

460.71
3532.13
3532.13

conforming to IS: 2222


6(1 cement : 6 coarse

Amount

1558.40
567.64
69.10
2.73

118.80
98.12
296.01
32.40
16.38
r five level)
233.91
2993.49
29.93
3023.42

453.51
3476.93
3476.93
inth level upto floor V

Amount

790.40
474.51
70.09
2.73

126.90
104.81
372.60
36.00
22.36
r five level)
233.91
2234.31
22.34
2256.65

225.67
2482.32
2482.32

inth level upto floor V

Amount

790.40
474.51
70.09
2.73

126.90
104.81
372.60
36.00
22.36
r five level)
233.91
2234.31
22.34
2256.65
338.50
2595.15
2595.15

ors or part thereof by

Amount

625.00
425.36
1050.36
10.50
1060.86

159.13
1219.99
230.19
230.19

nd vent holes including


g of 25x3mm section at

Amount

248.40
13.52
0.24

99.90
82.51
190.44
4.55
639.56
6.40
645.95

96.89
742.84
74.28
74.28

mortar 1:3 (1 Cement :


plete with 10 cm / 11.4

Amount
0.00
54.00

32.40
26.76
12.42
125.58
1.26
126.84

19.03
145.86
14.59
14.59

1:3 (1 cement: 3 coarse

Amount

603.20
590.48
53.49

194.40
160.56
364.32
64.80
7.15
2038.40
20.38
2058.78

308.82
2367.60
236.76
236.76

mplete for span upto 6


es with F.P.S. bricks of

Amount

790.40
815.58
70.09
2.73

143.10
118.19
474.03
36.00
18.85

1482.05
3951.02
24.69
3975.71

374.05
4349.76
4349.76

ment : 3 coarse sand)


class designation 75
Amount

860.80
815.58
76.33
2.73

1482.05
18.85

305.10
251.99
914.94
36.00
4764.37
32.82
4797.19

497.27
5294.47
5294.47

all shuttering, bolting,

Amount
erage of 8m)

14206.40
53.99

254.62
560.00
0.79

6244.00
4968.00
134.55

-17,144.66
9277.70
264.22
9541.92

4002.99
13544.91
406.63
406.63

inth in:

Amount

904.00
913.45
80.16
13.52

121.50
100.35
320.85
126.00
2579.83
25.80
2605.63

390.84
2996.48
299.65
299.65

plinth in:
Amount

904.00
722.45
80.16
13.52

121.50
100.35
320.85
126.00
2388.83
23.89
2412.72

361.91
2774.63
277.46
277.46

ve

Amount

904.00
913.45
80.16
13.52

162.00
133.80
414.00
126.00
r five level)
267.03
3013.96
30.14
3044.10

456.62
3500.72
350.07
350.07
above plinth level upto

Amount

904.00
722.45
80.16
13.52

162.00
133.80
414.00
126.00
r five level)
267.03
2822.96
28.23
2851.19

427.68
3278.87
327.89
327.89

ur floors or part thereof

Amount

625.00
425.36
1050.36
10.50
1060.86

159.13
1219.99
20.39
20.39

ird course of half brick

Amount

567.60
0.62
1.82
570.04
5.70
575.74

86.36
662.11
66.21
66.21

th in:

Amount

1243.20

1032.07
66.15
4.55

189.00
156.10
318.78
36.00
3045.85
30.46
3076.31

461.45
3537.75
3537.75

th in:

Amount

1243.20

759.22
66.15
4.55

189.00
156.10
318.78
36.00
2772.99
27.73
2800.72

420.11
3220.83
3220.83

onforming to IS : 2690

Amount

2111.11
66.15

759.22
4.55

189.00
156.10
318.78
36.00
3640.90
36.41
3677.31

551.60
4228.91
4228.91

Amount

1243.20
66.15

759.22
4.55

243.00
200.70
372.60
36.00

233.91
33.80
3193.12
31.93
3225.05

483.76
3708.81
3708.81

ucture above floor five

Amount

310.50
310.50
3.11
313.61

47.04
360.65

rk in superstructure in
plete.
Amount

1243.20
66.15

903.06
5.46

1482.05
18.85

213.30
176.17
664.47
36.00
4808.71
33.27
4841.97
503.99
5345.96
5345.96

rk in superstructure in
e.
Amount

1265.60
67.34

903.06
5.46

1482.05
18.85

405.00
334.50
1103.31
36.00
5621.17
41.39
5662.56

627.08
6289.64
6289.64

in cement mortar in 1:3

Amount

603.20
32.09

489.35
8.06

253.80
209.62
389.16
59.40
2044.68
20.45
2065.13

309.77
2374.90
237.49
237.49

cement mortar in 1:4 (1

Amount

171.28
20.67
191.95
0.21
192.16

3.13
195.29
195.29

of pumping or bailing

Amount

75.00
828.00
903.00
9.03
912.03

136.80
1048.83
249.72
249.72

- soil water level upto


in cum executed under
0.05m or more shall be
Amount

5.40
4.46
31.05
51.75
92.66

0.93
93.59

14.04
107.62
107.62

work including making


el upto plinth level in

Amount

790.40
70.09

474.51

16.38

94.50
78.05
221.49
103.50
36.00
1884.92

18.85
1903.77

285.57
2189.33
2189.33

ork in-cluding making


el upto plinth level in

Amount
998.35

417.57
69.10

16.38

89.10
73.59
207.00
32.40
1903.48

19.03
1922.52

288.38
2210.90
2210.90

n exposed brick work


rom ground level upto

Amount

779.20

417.57
69.10

16.38

89.10
73.59
207.00
32.40
1684.33

16.84
1701.18

255.18
1956.35
1956.35
n exposed brick work
from ground level upto

Amount

1366.90

474.51
70.09

16.38

97.20
80.28
283.59
36.00
2424.95

24.25
2449.20

367.38
2816.58
2816.58

n 125 conforming IS :
0mm wide 12 mm deep
and).
Amount

1597.10

474.51
70.09

16.38

97.20
80.28
283.59
36.00
2655.15

26.55
2681.70

402.26
3083.96
3083.96

125 conforming to IS :
0 mm wide 12mm deep
sand).
Amount

1558.40

417.57
69.10

16.38

89.10
73.59
207.00
32.40
2463.53

24.64
2488.17

373.23
2861.40
2861.40

above plinth level upto

Amount

697.53

645.05
70.09
2.73

126.90
104.81
372.60
36.00
8.97

233.91
2298.58

22.99
2321.57

348.24
2669.80
2669.80

above plinth level upto

Amount

697.53

474.51
70.09
2.73

126.90
104.81
372.60
36.00
8.97

233.91
2128.05

21.28
2149.33

322.40
2471.73
2471.73

oor five level, for each

Amount

310.50
310.50
3.11
313.61

47.04
360.65
360.65

IS: 12894-2002, class


r structure above

Amount

872.70

567.64
69.10
2.73

126.90
104.81
372.60
36.00
22.36

233.91
2408.75

24.09
2432.84

364.93
2797.76
2797.76

IS: 12894-2002, class


r structure above

Amount

872.70

417.57
69.10
2.73
126.90
104.81
372.60
36.00
22.36

233.91
2258.68

22.59
2281.27

342.19
2623.45
2623.45

to IS:4139-1989, class
o floor V level in :

Amount

1501.42

567.64
69.10
2.73

126.90
104.81
372.60
36.00
22.36

233.91
3037.47

30.37
3067.84

460.18
3528.02
3528.02

to IS:4139-1989, class
o floor V level in :

Amount
1501.42

417.57
69.10
2.73

126.90
104.81
372.60
36.00
22.36

233.91
2887.40

28.87
2916.27

437.44
3353.71
3353.71

to IS: 4885 - 1988) in

Amount

1728.85

567.64
69.10
2.73

89.10
73.59
207.00
32.40
2770.41
27.70
2798.11

419.72
3217.83
3217.83
to IS : 4885-1988) in

Amount

1728.85

817.23
69.10
2.73

1482.05

113.40
93.66
385.02
36.00
4728.03
32.46
4760.49

491.77
5252.25
5252.25

k AAC blocks in super


coarse sand ) The rate
urse of masonry work.
Amount

1650.00

387.03
53.21
2.73

774.24

97.20
80.28
283.59
36.00
3364.27
25.90
3390.17

392.39
3782.57
3782.57
floors or part there of
Amount

310.50
310.50

3.11
313.61

47.04
360.65
360.65

Gypsum panels of size


e, jointed with bonding
floor V level. Gypsum

Amount

5440.00
1250.00
13.52

135.00
207.00
7045.52
70.32
7115.84

1067.38
8183.22
818.32
818.32

ery four floors or part

Amount

358.11
358.11

3.58
361.69
54.25
415.94
41.59
41.59

12894 : 2002 of class

Amount

1086.80

645.05
70.09
2.73

97.20
80.28
283.59
36.00
2301.73
23.02
2324.75

348.71
2673.46
2673.46

12894 : 2002 of class

Amount

1086.80

474.51
70.09
2.73

97.20
80.28
283.59
36.00
2131.20
21.31
2152.51

322.88
2475.39
2475.39

90 of class designation

Amount

310.50
310.50

3.11
313.61

47.04
360.65
360.65

f class designation 75

Amount

2.73
73.60
6.53
9.29

18.00
20.70
5.40
2.73
138.98
1.39
140.36

21.05
161.42
16.14
16.14
7.1 : R andom rubble masonry with hard stone in foundation and plinth including levellingup with
cement concrete 1:6:12 (1 cement: 6 coarse sand : 12 graded stone aggregate 20mm nominal size) at plinth
level
7.1.1 with :
: Cement mortar 1:6(1 cement: 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Materials :
1157 Stone at quarry cum 1 332.00
1154 Through and bond stones 7 nos. 100 Nos 7 970.00
2215 Carriage of stone- cum 1.16 62.6
Cement mortar 1:6 (1 cement: 6 Coarse sand)
cum 0.33 1898.04
LABOUR
125 Mason 1st Class Day 1.07 223
114 Beldar Day 1.07 207
115 Coolie Day 0.71 207
101 Bhishti Day 0.09 180
9999 Cement concrete 1:6:12 L.S. 45.76 1.00
9999 Sundries L.S. 4.42 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.2 : Extra for random rubble masonry with hard stone in superstructure above plinth level and upto floor
five level, including levelling up with cement concrete 1:6:12 (1 cement: 6 coarse sand : 12 graded stone
aggregate 20mm nominal size) at window sills, ceiling level and the like.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
9999 Scaffolding etc. L.S. 67.34 1.00
Labour:
9999 Labour for laying cement concrete L.S. 10.79 1.00
125 Mason 1st Class Day 0.27 223
114 Beldar Day 0.38 207
Extra labour for lifting of materials upto floor V level
115 Coolie Day 1.13 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say
7.3 : Extra for random rubble masonry with hard stone in superstructure above floor V level for every
four floors or part thereof
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Labour required for lifting of materials
114 Beldar Day 2 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.4 : Extra for random rubble masonry with hard stone in


7.4.1: Square or rectangular pillars
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Labour:
125 Mason 1st Class Day 0.58 223
115 Coolie Day 0.27 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.4 : Extra for random rubble masonry with hard stone in


7.4.2 : Circular pillars.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
1157 Extra Stone at quarry cum 0.29 332.00
2215 Carriage of stone- cum 0.29 62.6
Labour for cutting and dressing stones-
125 Mason 1st Class Day 1.42 223
115 Coolie Day 0.35 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.5 : Extra for random rubble masonry with hard stone curved on plan for a mean radius not exceeding
6 m.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
1157 Extra Stone at quarry cum 0.1 332.00
2215 Carriage of stone- cum 0.1 62.6
Labour for cutting and dressing stones-
125 Mason 1st Class Day 0.27 223
115 Coolie Day 0.53 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.6 : Coursed rubble masonry (first sort) with hard stone in foundation and plinth with :
7.6.1 : Cement mortar 1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
M aterials-
Cement mortar l:6 (R ate as per item N o.3.11)
cum 0.3 1898.04
1157 Stone at quarry cum 1.21 332.00
1154 Through and bond stones 7 nos. 100 Nos 7 970.00
2215 Carriage of stone- cum 1.37 62.6
LABOUR
125 Mason 1st Class Day 2.12 223
114 Beldar Day 1.24 207
115 Coolie Day 0.71 207
101 Bhishti Day 0.09 180
9999 Sundries L.S. 13.52 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.7 : Coursed rubble masonry (second sort) with hard stone in foundation & plinth with:
7.7.1 : Cement mortar 1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate
Details of cost for 1 cum.
M aterials-
Cement mortar l:6 (R ate as per item N o.3.11)
cum 0.3 1898.04
1157 Stone at quarry cum 1.1 332.00
1154 Through and bond stones 7 nos. 100 Nos 7 970.00
2215 Carriage of stone- cum 1.26 62.6
LABOUR
125 Mason 1st Class Day 1.76 223
114 Beldar Day 1.24 207
115 Coolie Day 0.71 207
101 Bhishti Day 0.09 180
9999 Sundries L.S. 13.52 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.8 : Extra for coursed rubble masonry with hard stone (first or second sort) in superstructure
above plinth level and upto floor five level.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
9999 Scaffolding etc. L.S. 24.18 1.00
Labour:
125 Mason 1st Class Day 0.26 223
114 Beldar Day 0.35 207
Extra labour for lifting of materials upto floor V level
115 Coolie Day 1.5 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.9 : Extra for co ursed rubble masonry wit h hard st on e (first or secon d sort) in
superstructure above floor V level for every four floors or part thereof.
Code Description Unit Quantity Rate
Details of cost for per floor per 1 cum.
Labour required for lifting of material
114 Beldar Day 2 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.

7.10 Extra for coursed rubble masonry with hard stone (first or second sort) in :
7.10.1 Square or rectangular pillars
Code Description Unit Quantity Rate
Details of cost for 1 cum.
Labour:
125 Mason 1st Class Day 0.67 223
115 Coolie Day 0.27 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.10 : Extra for coursed rubble masonry with hard stone (first or second sort) in :
7.10.2 : Circular pillars.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
1157 Extra Stone at quarry cum 0.32 332.00
2215 Carriage of stone- cum 0.32 62.6
Labour for cutting and dressing stones-
125 Mason 1st Class Day 1.67 223
115 Coolie Day 0.35 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7.11 : Extra for coursed rubble masonry with hard stone (first or second sort) curved on
plan for a mean radius not exceeding 6 m.
Code Description Unit Quantity Rate
Details of cost for 1 cum.
1157 Extra Stone at quarry cum 0.11 332.00
2215 Carriage of stone- cum 0.11 62.6
Labour for cutting and dressing stones-
125 Mason 1st Class Day 0.33 223
115 Coolie Day 0.53 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 Cum.
Say

7. 12 : Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement :
6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture
of pigment matching the stone shade :
7.12.1 : One face dressed.
7.12.1.1 : Red sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
Materials-
1160 Red sand stone 10 cudm 13.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
Dressing charges Labour:
124 Mason Ilnd Class Day 0.088 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7. 12 : Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement :
6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture
of pigment matching the stone shade :
7.12.1 : One face dressed.
7.12.1.2 : White sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1161 White sand stone 10 cudm 13.33 50.00
2216 Carriage of stone- cum 0.031 47.29
Labour for cutting and dressing stones-
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
Dressing charges Labour:
124 Mason Ilnd Class Day 0.088 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7. 12 : Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement :
6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture
of pigment matching the stone shade :
7.12.2 : Both face dressed.
7.12.2.1 : Red sand stone.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1160 Red sand stone 10 cudm 13.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
Dressing charges Labour:
124 Mason Ilnd Class Day 0.176 223
102 Black smith 1 st class Day 0.012 270
114 Beldar Day 0.088 207
115 Coolie Day 0.044 207
100 Bandhani Day 0.088 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7. 12 : Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement :
6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture
of pigment matching the stone shade :
7.12.2 : Both face dressed.
7.12.2.2: White sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1161 White sand stone 10 cudm 13.33 50.00
2216 Carriage of stone- cum 0.031 47.29
Labour for cutting and dressing stones-
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
Dressing charges Labour:
124 Mason Ilnd Class Day 0.176 223
102 Black smith 1 st class Day 0.012 270
114 Beldar Day 0.088 207
115 Coolie Day 0.044 207
100 Bandhani Day 0.088 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.13 : Stone work plain ashlar in arches in cement mortar 1:3 (1 cement: 3 coarse sand) including centring,
shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of
pigment matching the stone shade.
7.13.1 : Red sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1160 Red sand stone 10 cudm 13.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.088 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Centering and shuttering L.S. 13.52 1.00
9999 Extra for using white cement L.S. 8.06 1.00
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.13 : Stone work plain ashlar in arches in cement mortar 1:3 (1 cement: 3 coarse sand) including centring,
shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of
pigment matching the stone shade.
7.13.2 : White sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1161 White sand stone 10 cudm 13.33 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.088 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Centering and shuttering L.S. 13.52 1.00
9999 Extra for using white cement L.S. 8.06 1.00
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.14 : Stone work plain ashlar in domes in cement mortar 1:3 (1 cement: 3 coarse sand) including centring,
shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of
pigment matching the stone shade.
7.14.1 Red sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1160 Red sand stone 10 cudm 13.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.176 223
102 Black smith 1 st class Day 0.006 270
126 Stone mason (ornamental work) Day 0.176 313
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Centering and shuttering L.S. 33.15 1.00
9999 Extra for using white cement L.S. 8.06 1.00
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.14 : Stone work plain ashlar in domes in cement mortar 1:3 (1 cement: 3 coarse sand) including centring,
shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of
pigment matching the stone shade.
7.14.2 : White sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1161 White sand stone 10 cudm 13.33 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.176 223
102 Black smith 1 st class Day 0.006 270
126 Stone mason (ornamental work) Day 0.176 313
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Centering and shuttering L.S. 33.15 1.00
9999 Extra for using white cement L.S. 8.06 1.00
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.15 : Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1
white cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust)
with an admixture of pigment matching the stone shade.
7.15.1 : Red sand stone.
7.15.1.1: One faced punched.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1160 Red sand stone 10 cudm 13.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.059 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.15 : Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1
white cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust)
with an admixture of pigment matching the stone shade.
7.15.1 : Red sand stone.
7.15.1.2 : Double faced punched.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1160 Red sand stone 10 cudm 13.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.118 223
102 Black smith 1 st class Day 0.012 270
114 Beldar Day 0.088 207
115 Coolie Day 0.044 207
100 Bandhani Day 0.088 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.15 : Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1
white cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust)
with an admixture of pigment matching the stone shade.
7.15.2 : White sand stone.
7.15.2.1: Single face punched.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1161 White sand stone 10 cudm 13.33 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.059 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.15 : Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1
white cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust)
with an admixture of pigment matching the stone shade.
7.15.2 : White sand stone.
7.15.2.2: Double faced punched.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1161 White sand stone 10 cudm 13.33 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.118 223
102 Black smith 1 st class Day 0.012 270
114 Beldar Day 0.088 207
115 Coolie Day 0.044 207
100 Bandhani Day 0.088 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.16 : Extra for stone work, plain ashlar or ashlar punched above floor V level for every four floors or part
thereof.
Code Description Unit Quantity Rate
Details of cost for 10 cudm above floor V level
Labour required for lifting of material (above floor five level for each additional four floors) or part
thereof.
Extra labour for lifting of materials above floor V level (0.01 x 2.00 = 0.020)
114 Beldar Day 0.02 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.17 : Extra for plain ashlar or ashlar punched in :


7.17.1 : Square or rectangular pillars.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
9999 Labour and materials L.S. 8.97 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.18 : Extra for stone work; plain ashlar or ashlar punched curved on plan with a mean radius not
exceeding 6 m.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
9999 Labour and materials L.S. 6.24 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.19 Extra for additional cost of centring for arches exceeding 6m span including all strutting, bolting,
wedging etc. and removal (area of soffit to be measured),
Code Description Unit Quantity Rate
Details of cost per sqm.
Centering and shuttering for arches and carved surface exceeding 6m in span (an average of 8m)
1197
S.C.I. S&S, 76 mm offset for100 mm dia pipe each 887.9 160.00
2204 Carriage of wood cum 0.8879 60.81
Fittings:
1225 Mild steel flat strap fitting quintal 0.0878 2900.00
1034 Bolts 160 Nos. 254 mm long 16mm dia.- quintal 0.08 7000.00
2302 Carriage of steel = 0.1342 t tonne 0.0168 47.29
Labour:
112 Carpenter 2nd class Day 28 223
114 Beldar Day 24 207
9999 Sundries L.S 134.55 1.00
Less Cost of shuttering etc. for an arch exceeding 6 m span i.e. for an average of 8 m
(A) Rate as per item no- 5.9.9 sqm 33.31 0.00
TOTAL
Add 1% for water charges on all exept ‘A’
TOTAL
Add for contractor’s profit and overheads
@15% on all except ‘A’
Cost of 33.31 sqm.
Cost per sqm.
Say

7.20 : Stone work sunk or moulded or sunk and moulded upto floor five level in cement mortar 1:6 (1
cement: 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cem ent : 2 stone dust)
with an admixture of pigment matching the stone shade :
7.20.1 : Red sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1160 Red sand stone 10 cudm 13.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.291 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Extra for using white cement L.S. 8.06 1.00
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.20 : Stone work sunk or moulded or sunk and moulded upto floor five level in cement mortar 1:6 (1
cement: 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cem ent : 2 stone dust)
with an admixture of pigment matching the stone shade :
7.20.2 : White sand stone
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
M aterials-
1161 White sand stone 10 cudm 13.33 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.031 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.291 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.044 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.044 180
Fixing charges
125 Mason 1st Class Day 0.044 223
102 Black smith 1 st class Day 0.006 270
114 Beldar Day 0.022 207
115 Coolie Day 0.022 207
100 Bandhani Day 0.022 180
101 Bhisti Day 0.022 180
9999 Extra for using white cement L.S. 8.06 1.00
9999 Scaffolding etc. L.S. 2.73 1.00
9999 Mortar for laying and pointing L.S. 8.06 1.00
Extra labour for lifting of materials upto floor V level
115 Coolie Day 0.015 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.21 : Extra for stone work sunk or moulded or sunk and mlded or carved in :
7.21.1 : Triangular or Square or rectangular pillars
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
9999 Labour L.S. 11.7 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.21 : Extra for stone work sunk or moulded or sunk and moulded or carved in :
7.21.2 : Circular or polygonal pillars -
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
9999 Labour L.S. 33.15 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.22 : Extra for stone work sunk or moulded in cornices.


Code Description Unit Quantity Rate
Details of cost for a cornice 30cm long 60cm deep and 15cm projection
125 Mason 2nd Class Day 0.5 223
114 Beldar Day 0.75 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 30cm long 60cm deep and 15cm girth

Cost of per metre per cm girth


Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.1 : Red sand stone - exposed face fine dressed with rough backing.
7.23.1.1 : 70 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 93.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.215 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say
7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.1 : Red sand stone - exposed face fine dressed with rough backing.
7.23.1.2: 60 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 80 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.184 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):

7.23.1 : Red sand stone - exposed face fine dressed with rough backing.
7.23.1.3: 50 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 66.7 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.153 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
with a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including
7.23.1.4: 40 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 53.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.123 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.1 : Red sand stone - exposed face fine dressed with rough backing.
7.23.1.5: 30 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 39.99 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.092 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.2.1: 70 mm thick
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 93.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.215 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.2.2: 60 mm thick
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 80 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.184 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say
7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.2.3: 50 mm thick
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 66.7 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.153 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.2.4: 40 mm thick
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 53.33 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.123 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.2.5: 30 mm thick
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1160 Red sand stone 10 cudm 39.99 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.092 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.3 : White sand stone - exposed face fine dressed with rough backing .
7.23.3.1: 70 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 93.33 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.215 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.3 : White sand stone - exposed face fine dressed with rough backing .
7.23.3.2: 60 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 80 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.184 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.3 : White sand stone - exposed face fine dressed with rough backing .
7.23.3.3: 50 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 66.7 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.153 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say
7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.3 : White sand stone - exposed face fine dressed with rough backing .
7.23.3.4: 40 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 53.3 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.123 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.3 : White sand stone - exposed face fine dressed with rough backing .
7.23.3.5: 30 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 39.99 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.092 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 1.35 223
102 Black smith 1 st class Day 0.032 270
114 Beldar Day 0.224 207
115 Coolie Day 0.112 207
100 Bandhani Day 0.224 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.4 : White sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.4.1: 70 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 93.33 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.215 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.4 White sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.4.2 60 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 80 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.184 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.4 White sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.4.3 50 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 66.7 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.153 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.4 White sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.4.4 40 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 53.3 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.123 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say
7.23 : Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled with a grout of
12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2
(1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to
the backing by means of cramps which shall be paid for separately):
7.23.4 White sand stone - Exposed face machine cut and table rubbed with rough backing.
7.23.4.5 30 mm thick.
Code Description Unit Quantity Rate
Details of cost for 1 sqm.
M aterials-
1161 White sand stone 10 cudm 39.9 50.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.092 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 2.7 223
102 Black smith 1 st class Day 0.064 270
114 Beldar Day 0.448 207
115 Coolie Day 0.224 207
100 Bandhani Day 0.448 180
Fixing charges
125 Mason 1st Class Day 0.448 223
114 Beldar Day 0.336 207
115 Coolie Day 0.336 207
100 Bandhani Day 0.336 180
101 Bhisti Day 0.336 180
9999 Extra for using white cement L.S. 26.91 1.00
9999 Scaffolding etc. L.S. 19.76 1.00
1237 Cutting sand stone slab by mechanical device metre 4
6.00
Mortar for laying and pointing (Rate as per cum 0.018
item No 3.8 of S.H. mortar) 3262.33
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.24 : Extra for stone work (veneer work) curved on plan with a mean radius not exceeding 6 m.
Code Description Unit Quantity Rate
Details of cost for 10 cudm.
9999 Labour and materials L.S. 8.97 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 10 Cudm.
Cost of 1 cum
Say

7.25 : Providing and fixing stainless steel cramps of required size and shape for anchoring stone wall
lining to the backing or securing adjacent stones in stone wall lining in cement mortar 1:2(1 cement: 2
coarse sand) including making the necessary chases in stone and holes in walls wherever required.
Code Description Unit Quantity Rate
Details of cost for one cramp
M aterials:
7339 Stainless steel cramp kilogram 0.107 280.00
9999 Carriage L.S. 3.9 1.00
CM. 1:2 (lcement :2 Coarse sand) (Rate as per
this No. 3.7). cum 0.001 4111.99
9999 Labour iorfixing m position L.S. 6.5 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 0.097 kg.
Cost of 1 cum
Say

7.26 : Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in
cement mortar 1:2 (1 cement: 2 coarse sand) including making the necessary chases.
Code Description Unit Quantity Rate
Details of cost for one dowel
9999 Cost of stone including carriage L.S. 9.1 1.00
Labour for dressing dowel cutting chase and fixing etc.
9999 Labour for dressing dowel cutting chase and
fixing etc. L.S. 5.33 1.00
CM. 1:2 (lcement :2 Coarse sand) (Rate as per
this No. 3.7). cum 0.001 4111.99
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say
7.27 : Providing and fixing copper pins 7.5 cm long 6 mm diameter for securing adjacent stones in stone
wall lining in cement mortar 1:2(1 cement: 2 coarse sand) including making the necessary chases.
Code Description Unit Quantity Rate
Details of cost for one copper pin-
Materials-
873 Copper pins 6 mm dia 7.5 cm long each 1 7.50
Labour for making pin in to required shape and
9999 size, cutting chases in stone and fixing in
position L.S. 3.9 1.00
CM. 1:2 (lcement :2 Coarse sand) (Rate as per
this No. 3.7). cum 0.001 4111.99
9999 Sundries including hire charges of hand cut machi cum 1.95 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 cum
Say

7.28 : Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide beyond the wall as
measured along the slope in cement mortar 1:4 (1 cement : 4 coarse sand) with 12mm diameter anchoring
steel bar 45 cm long fixed in each stone and supported on and including with bricks cove of class
designation 75 in cement mortar 1:4 (1 cement : 4 coarse sand) including pointing in cement mortar 1:2 (1
white cement : 2 stone dust) with an admixture of pigment matching the stone shade:

7.28.1 : Red sand stone:


7.28.1.1: With F.P.S Bricks
Code Description Unit Quantity Rate
Details of cost for a chajja 2.00 sqm. (finished work)
Materials-
1164 White sand stone sqm 2.75 120.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.253 47.29
Dressing charges Labour:
124 Mason Ilnd Class Day 0.5 223
Fixing charges
125 Mason (Plain) 2nd class Day 1 223
114 Beldar Day 1.5 207
9999 Cutting threads and cost of nuts, washers, etc. L.S. 67.34 1.00

9999 Extra for using white cement L.S. 26.91 1.00


9999 Pigment L.S. 6.24 1.00
9999 Scaffolding etc. L.S. 16.12 1.00
1002 Anchoring steel bars 12mm dia. 45cm long quintal 0.02 4300.00
Mortar for pointing 1:2(1 C ement: 2 Stone dust) cum 0.009 4438.17
(Rate as per items no. 3.12)
9999 Cost of Brick cover support. L.S. 104 1.00
B Brick work in triangular gap above cover with cum 0.018 2131.12
bricks of class designation 7.5 in cement
mortar 1:4-Rate as per Item no. 6.1.2 SH: Brick
work.1/2x2.5x0.2x0.07=0.018cum.

TOTAL
Add 1% for water charges excpet B
TOTAL
Add for contractor’s profit and overheads
@15% excpet B
Cost of 2 sqm
Cost of 1 sqm
Say

7.28 : Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide beyond the wall as
measured along the slope in cement mortar 1:4 (1 cement : 4 coarse sand) with 12mm diameter anchoring
steel bar 45 cm long fixed in each stone and supported on and including with bricks cove of class
designation 75 in cement mortar 1:4 (1 cement : 4 coarse sand) including pointing in cement mortar 1:2 (1
white cement : 2 stone dust) with an admixture of pigment matching the stone shade:

7.28.2 : White sand stone:


7.28.2.1: With F.P.S. bricks
Code Description Unit Quantity Rate
Details of cost for a chajja 2.00 sqm. (finished work)
M aterials-
White sand stone slab 40 mm thick (un-
1165 dressed) sqm 2.75 140.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.253 47.29
Labour for dressing:
124 Mason Ilnd Class Day 0.5 223
1002 Anchoring steel bars 12mm dia. 45cm long 5 quintal 0.02 4300.00
Mortar for pointing 1:2(1 C ement: 2 Stone dust) cum 0.009 4438.17
(Rate as per items no. 3.12)
9999 Cutting threads and cost of nuts, washers, etc. L.S. 67.34 1.00
9999 Pigment L.S. 6.24 1.00
9999 Scaffolding etc. L.S. 16.12 1.00
9999 Extra for using white cement L.S. 26.91 1.00
Labour:
125 Mason (Plain) 2nd class Day 1 223
114 Beldar Day 1.5 207
9999 Cost of Brick cover support. L.S. 104 1.00
B Brick work in triangular gap above cover with cum 0.018 2131.12
bricks of class designation 7.5 in cement
mortar 1:4-Rate as per Item no. 6.1.2 SH: Brick
work.1/2x2.5x0.2x0.07=0.018cum.
TOTAL
Add 1% for water charges excpet B
TOTAL
Add for contractor’s profit and overheads
@15% excpet B
Cost of 2 sqm
Cost of 1 sqm
Say

7.29 : Providing and fixing horizontal chajja of stone 40 mm thick and upto 80 cm projection in
cement mortar 1:4 (1 cement: 4 coarse sand) including pointing in white cement mortar 1:2 (1 white
cement: 2 stone dust) with an admixture of pigment matching the stone shade.:
7.29.1 : Red sand stone
Code Description Unit Quantity Rate
Details of cost for (2.5xO.75m) 1.875 sqm.
M aterials-
1164 White sand stone sqm 2.25 120.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.227 47.29
Labour for dressing:
124 Mason Ilnd Class Day 0.45 223
9999 Mortar for pointing 1:2 L.S. 53.82 1.00
9999 Pigment L.S. 6.24 1.00
9999 Scaffolding etc. L.S. 13.52 1.00
9999 Extra for using white cement L.S. 26.91 1.00
Labour:
125 Mason (Plain) 2nd class Day 0.6 223
114 Beldar Day 0.8 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1.875 sqm
Cost of 1 sqm
Say

7.29 : Providing and fixing horizontal chajja of stone 40 mm thick and upto 80 cm projection in
cement mortar 1:4 (1 cement: 4 coarse sand) including pointing in white cement mortar 1:2 (1 white
cement: 2 stone dust) with an admixture of pigment matching the stone shade.:
7.29.2 : White sand stone
Code Description Unit Quantity Rate
Details of cost for (2.5xO.75m) 1.875 sqm.
M aterials-
White sand stone slab 40 mm thick (un-
1165 dressed) sqm 2.25 140.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.227 47.29
Labour for dressing:
124 Mason Ilnd Class Day 0.45 223
9999 Mortar for pointing 1:2 L.S. 53.82 1.00
9999 Pigment L.S. 6.24 1.00
9999 Scaffolding etc. L.S. 13.52 1.00
9999 Extra for using white cement L.S. 26.91 1.00
Labour:
125 Mason (Plain) 2nd class Day 0.6 223
114 Beldar Day 0.8 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1.875 sqm
Cost of 1 sqm
Say

7.30 : 30mm red sand stone sun-shade (chisel-dressed) supported on red sand stone brackets, fixed in
walls with cement mortar 1:4(1 cement: 4 coarse sand) including finishing complete.
Code Description Unit Quantity Rate
Detail of cost for window 1.6m length and 0.70m width = 1.12 sqm.
M aterials:
Red sand stone slab 30 mm thick (un-dressed)
1166 sqm 2 97.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.14 47.29
Labour for dressing:
124 Mason Ilnd Class Day 0.86 223
114 Beldar Day 0.5 207
9999 Mortar L.S. 13.52 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1.12 sqm
Cost of 1 sqm
Say

7.31 : Providing and fixing red sand stone brackets 55x22.5x45cm sunk and moulded including
providing and fixing with 4 Nos. gun metal cramp 25x6mm 30 cm long and dowel bars 7.5 cm long 6 mm
dia as per design.
Code Description Unit Quantity Rate
Details of cost for 1 bracket
1160 Red sand stone block 10 cudm 61.6 45.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.14 47.29
Labour for dressing:
124 Mason Ilnd Class Day 1.7926 223
102 Black smith 1 st class Day 0.037 270
114 Beldar Day 0.271 207
115 Coolie Day 0.1355 207
100 Bandhani Day 0.271 180
Fixing charges
125 Mason 1st Class Day 0.2464 223
102 Black smith 1 st class Day 0.0336 270
114 Beldar Day 0.1232 207
115 Coolie Day 0.1232 207
100 Bandhani Day 0.1232 180
101 Bhisti Day 0.1232 180
9999 Mortar for laying & pointing L.S. 45.14 1.00
9999 Scaffolding etc. L.S. 15.29 1.00
373 Cost of Gun metal cramps 25x6mm x30 cm each 4
long 53.00
Extra labour for ornamental finish :
126 Mason (for ornamental stone work) 1st class Day 0.95 313

TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 bracket
Say

7.32 : Stone work, plain in copings, cornices, string courses and plinth courses, upto 75mm thick in
Cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white
cement : 2 stone dust) with an admixture of pigment matching the stone shade.
7.32.1: Red sand stone
Code Description Unit Quantity Rate
Details of cost for cornices (30cm long 30cm deep and 7.5cm project-iron) = 6.75cudm.
Materials:
Stone w ork plain ashlar cyclopean 3x3x0.75 -
6.75 cudm Rate as per item no 7.12.1.1 of SH :
Stone Work 1000 cudm 17031.31 6.75
9999 (A) Extra for using white cement L.S. 5.33 1.00
Extra labour for making the cornices
124 (A) Mason Ilnd Class Day 0.07 223
114 (A) Beldar Day 0.07 207
TOTAL
(B) Add 1% for water charges on A
TOTAL
Add for contractor’s profit and overheads
(B) @15% on (A+B)
Cost of 6.75 cudm
Cost per cum
Say

7.32 : Stone work, plain in copings, cornices, string courses and plinth courses, upto 75mm thick in
Cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with white cement mortar 1:2 (1 white
cement : 2 stone dust) with an admixture of pigment matching the stone shade.
7.32.2 : White sand stone
Code Description Unit Quantity Rate
Details of cost for cornices (30cm long 30cm deep and 7.5cm project-iron) = 6.75cudm.
Materials:
Stone w ork plain ashlar cyclopean 3x3x0.75 -
6.75 cudm Rate as per item no 7.12.1.1 of SH :
Stone Work 1000 cudm 17805.45 6.75
9999 (A) Extra for using white cement L.S. 5.33 1.00
Extra labour for making the cornices
124 (A) Mason Ilnd Class Day 0.07 223
114 (A) Beldar Day 0.07 207
TOTAL
(B) Add 1% for water charges on A
TOTAL
Add for contractor’s profit and overheads
(B) @15% on (A+B)
Cost of 6.75 cudm
Cost per cum
Say

7.33 : Providing and fixing stone jali 40mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse
sand) including pointing in white cement mortar 1:2(1 white cement: 2 stone dust) with an admixture of
pigment, matching the stone shade, jali slab without any chamfers etc
7.33.1 : Red sand stone
Code Description Unit Quantity Rate
Details of cost for l sqm-
M aterials:
1164 White sand stone sqm 1.1 120.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.101 47.29
Labour for dressing:
124 Mason Ilnd Class Day 12.7 223
114 Beldar Day 8.45 207
9999 Mortar and sundries L.S. 80.73 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 sqm
Say

7.33 : Providing and fixing stone jali 40mm thick throughout in cement mortar 1:3 (1 cement : 3 coarse
sand) including pointing in white cement mortar 1:2(1 white cement: 2 stone dust) with an admixture of
pigment, matching the stone shade, jali slab without any chamfers etc
7.33.2 : White sand stone
Code Description Unit Quantity Rate
Code Description Unit Quantity Rate
Details of cost for l sqm-
M aterials:
White sand stone slab 40 mm thick (un-
1165 dressed) sqm 1.1 140.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.101 47.29
Labour for dressing:
124 Mason Ilnd Class Day 12.7 223
114 Beldar Day 8.45 207
9999 Mortar and sundries L.S. 80.73 1.00
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 1 sqm
Say

7.34 : Extra for laying stone work in or under water and/or liquid mud including cost of pumping or
bailing out water and removing slush etc. complete.
Code Description Unit Quantity Rate
Details of cost for depth of water 0.30m. Quantity of concrete = 14 cum.
11 pumping hours = 3 hrs. on 0.375day. Day 0.375 200
114 Beldar for cleaning slush Day 4 207
TOTAL
Add 1% for water charges
TOTAL
Add for contractor’s profit and overheads
@15%
Cost of 14cum. per 0.30m depth
Cost of cum. per m depth
Say

7.35 : Extra for laying stone work in or under foul position.”


Code Description Unit Quantity Rate
Details of cost for 1 cum.
Extra labour due to slow progress-
123 Mason 1st class Day 0.02 270
124 Mason 2nd class Day 0.02 223
114 Beldar Day 0.25 207
115 Coolie Day 0.15 207
TOTAL
Add for water charges @ 1% on all except B

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost of 1 cum
Say

7.36 : Wall lining butch work upto 10.00m height with Dholpur stone 40 mm thick rough facing on the
exposed surface with stone strips of minimum length 300 mm and required width including embedding
every tenth layer and bottom most layer in masonry or concrete after making necessary chases of size
75x75mm and by providing layer of 75mm thick strips i/c 12mm thick bed of cement mortar 1:3 (1
Cement : 3 coarse sand) i/c ruled pointing in cement m ortar 1:2 (1 white cement : 2 stone dust) with an
admixture of pigment to match the shade of stone complete as per direction of Engineer-in-charge.

Code Description Unit Quantity Rate


Details of cost for lsqm.
White sand stone slab 40 mm thick (un-
1165 dressed) sqm 0.92 140.00
White sand stone slab 75 mm thick (un-
1163 dressed) sqm 0.13 256.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.108 47.29
1237
Cutting stips of stone and giving rough finish metre 20 6.00
Mortar with coarse sand 1:3 for Cement
Mortar (Rate as per items No. 3.8) cum 0.0304 3262.33
Cutting chases and making good with mortar after insurting stone etc.
(A) Rate as per item no. 18.78 of S.H metre 3 36.65
M iscellaneous
9999 White cement and pigment for pointing L.S. 40.43 1.00
Labour:
126 Mason 1st Class Day 0.25 313
124 Mason 2nd Class Day 0.25 223
114 Beldar Day 0.5 207
101 Bhisti Day 0.03 180
9999 Sundries and scaffolding brushes etc. L.S. 26.91 1.00
TOTAL
Add for water charges @ 1% on all except A

TOTAL
Add for contractor’s profit and overheads
@15% except A
Cost of 1 cum
Say

7.37 : Stone work ( machine cut edges) for wall lining upto 10 m height etc. (Veneer work) backing
filled with a grout of 12mm thick cement mortar 1:3 (1 Cement : 3 coarse sand) and jointed with Cement
mortar 1:2 (1 cement : 2 stone dust) including rubbing and polishing complete. (To be secured to the
backing by means of cramps which shall be paid for separately)

7.37.1: Kota stone slabs exposed face dressed and rubbed.


7.37.1.1: 25 mm thick.
Code Description Unit Quantity Rate
Details of cost for 10 sqm.
Materials :
Kota stone slab 25mm thick (rough chiseled)
1169 sqm 11.5 175.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.67 47.29
Mortar with coarse sand 1:3 for Cement
Mortar (Rate as per items No. 3.8) cum 0.144 3262.33
9999 Cement mortar for pointing. L.S. 40.43 1.00
Labour:
124 Mason 2nd Class Day 6.5 223
114 Beldar Day 6.5 207
115 Coolie Day 4.33 207
139 Beldar for rubbing and polishing (special rate) Day 10.8
180
9999 Sundries L.S. 111.54 1.00
TOTAL
Add for water charges @ 1% on all except A

TOTAL
Add for contractor’s profit and overheads
@15% except B
Cost for 10 sqm.
Cost of 1 sqm.
Say

7.38 Stone tile work for wall lining upto 10 m height with special adhesive over 12mm thick bed of
cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement with an admixture of
pigment to match the stone shade.
7.38.1 8mm thick (m irror polished and machine cut edge)
7.38.1.1 Granite stone of any colour and shade.
Code Description Unit Quantity Rate
Details of cost for lOsqm.
Materials :
8 mm thick granite stone tiles (mirror polished
2750 of all shades) sqm 10.25 555.00
9999 Carriage of granite tiles L.S. 40.04 1.00
Mortar with coarse sand 1:3 for Cement
Mortar (Rate as per items No. 3.8) cum 0.14 3262.33
367 Cement slurry @ 3.3 kg/sqm. tonne 0.033 5200.00
9999 Mortar for pointing in white cement L.S. 25.74 1.00
Labour for placing and fixing :
123 Mason 1st class Day 7.7 270
114 Beldar Day 7.7 207
9999 Granular sand particles mixed with araldite to 260.00 1.00
be pasted on each side to form interlocking
arrangement with cement plaster L.S.
9999 Sundries L.S. 171.6 1.00
TOTAL
Add for water charges @ 1% on all
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 10 sqm.
Cost for 1 sqm.
Say
TOTAL

7.38 Stone tile work for wall lining upto 10 m height with special adhesive over 12mm thick bed of
cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement with an admixture of
pigment to match the stone shade.
7.38.1: 8mm thick (m irror polished and machine cut edge)
7.38.1.2: Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble,
Code Description Unit Quantity Rate
Details of cost for lOsqm.
Materials :
7439 8mm thick Raj Nagar white stone tile sqm 10.25 430.00
9999 Carriage of granite tiles L.S. 40.04 1.00
Mortar with coarse sand 1:3 for Cement
Mortar (Rate as per items No. 3.8) cum 0.14 3262.33
367 Cement slurry @ 3.3 kg/sqm. tonne 0.033 5200.00
9999 Mortar for pointing in white cement L.S. 25.74 1.00
Labour for placing and fixing :
123 Mason 1st class Day 7.7 270
114 Beldar Day 7.7 207
9999 Granular sand particles mixed with araldite to 260.00 1.00
be pasted on each side to form interlocking
arrangement with cement plaster L.S.
9999 Sundries L.S. 171.6 1.00
TOTAL
Add for water charges @ 1% on all
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 10 sqm.
Cost for 1 sqm.
Say

7.39 Extra for stone work for wall lining on exterior walls of height more than 10 m from ground level for
every additional height of 3 m or part there of.
ANALYSIS SAME AS ITEM NO 13.114
Code Description Unit Quantity Rate
Detail of cost for 10 sqm
MATERIALS
9999 Scaffolding L.S. 215.28 1.00
11 Hire charges of pumpset of capacity 4000
it/per hour Day 0.375 200
123 Mason 1st class Day 0.3 270
114 Beldar Day 0.3 207
101 Bhisti Day 0.15 180
9999 Sundries L.S. 28.6 1.00
TOTAL
Add for water charges @ 1% on all
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 10 sqm.
Cost for 1 sqm.
Say
7.40 Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stone with
(machine cut edges) of uniform colour and size upto lmxlm, fixed to structural steel frame work and/ or
with the help of cramps, pins etc. and sealing the joints with approved weather sealant as per
Architectural drawing and direction of Engineer-in-charge. (The steel frame work, stainless steel
cramps and pins etc. shall be paid for separately.)

7.40.1 Red sand stone.


Code Description Unit Quantity Rate
Details of cost for 3 sqm.
M aterials-
8683 Red sand stone gang saw cut 30mm thick. sqm 4.35 325.00
1237 Cutting marble or sand stone slab upto 50 mm
thick by mechanical device metre 10 6.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.215 47.29
9999 backing rod L.S. 30.68 1.00
9999 Fixing including weather sealant and removing L.S. 153.4 1.00
9999 Double scafolding L.S. 204.75 1.00
126 Mason (for ornamental stone work) 1 st class Day 2
313
114 Beldar Day 4 207
Labour for lifting stone
114 Beldar Day 1 207
9999 Silicon gun/ pump etc. L.S. 204.75 1.00
Labour for sealing
116 Fitter (grade 1) Day 0.25 270
114 Beldar Day 0.5 207
9999 Sundries L.S. 204.75 1.00
9999 Rubing and polishing vertical surface of stone 1.00
cladding L.S. 51.22
TOTAL
Add for water charges @ 1% on all
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 3 sqm.
Cost for 1 sqm.
Say

7.40 Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stone with
(machine cut edges) of uniform colour and size upto lmxlm, fixed to structural steel frame work and/ or
with the help of cramps, pins etc. and sealing the joints with approved weather sealant as per
Architectural drawing and direction of Engineer-in-charge. (The steel frame work, stainless steel
cramps and pins etc. shall be paid for separately.)

7.40.2 White sand stone


Code Description Unit Quantity Rate
Details of cost for 3 sqm.
M aterials-
8684 Red sand stone gang saw cut 30mm thick. sqm 4.35 360.00
1237 Cutting marble or sand stone slab upto 50 mm
thick by mechanical device metre 10 6.00
2216 Carriage of stone @ 2.30kg/cudm tonne 0.215 47.29
9999 backing rod L.S. 30.68 1.00
9999 Fixing including weather sealant and removing L.S. 153.4 1.00
9999 Double scafolding L.S. 204.75 1.00
126 Mason (for ornamental stone work) 1 st class Day 2
313
114 Beldar Day 4 207
Labour for lifting stone
114 Beldar Day 1 207
9999 Silicon gun/ pump etc. L.S. 204.75 1.00
Labour for sealing
116 Fitter (grade 1) Day 0.25 270
114 Beldar Day 0.5 207
9999 Sundries L.S. 204.75 1.00
9999 Rubing and polishing vertical surface of stone 1.00
cladding L.S. 51.22
TOTAL
Add for water charges @ 1% on all
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 3 sqm.
Cost for 1 sqm.
Say

7.41 Providing and fixing structural steel frame (for dry cladding with 30 mm thick gang saw cut with
machine cut edges sand stone) on walls at all heights using M.S. square/rectangular tube in the required
pattern as per architectural drawing including cost of cutting, bending, welding etc. The frame work shall
be supported in wall with the help of MS brackets/ lugs of angle iron/ flats etc. which shall be welded to
the frame and embedded in brick wall with cement concrete block 1:2:4 (1 cement :2 coarse sand :4
graded stone aggregate 20m m nominal size) of size 300x230x300mm including cost of necessary
centring and shuttering and with approved expansion hold fasteners on CC /RCC surface including
drilling necessary holes. Approved steel work will be given a priming coat of “ZINC ” primer as approved
by Engineer-in-charge and painted with two or more coats of epoxy paint (Shop drawings shall be
submitted by the contractor to the Engineer-in-charge for approval before execution). The frame work
shall be fixed in true horizontal & vertical lines/planes. (Only structural steel frame work shall be
measured for the purpose of payment, stainless steel cramps shall be paid for separately and nothing extra
shall be paid.)

Code Description Unit Quantity Rate


Details of cost for 9 sqm or 88.79 kg.
4009 Mild steel tubes Kilogram 51.47 38.00
1007 Cost of angle iron quintal 0.462 4600.00
Cement concrete 1:2:4 (Rate as per item no
(A) 4.1.3 of SH : Concrete work cum 0.054 5,140.53
Work)
Making holes in brick work=16nos.
Labour
123 Mason 1st class Day 0.26 270
124 Mason 2nd class Day 0.26 223
114 Beldar Day 2 207
1215 Welding by electric plant cm 56 1.00
LABOUR
100 Bandhani Day 0.67 180
114 Beldar Day 4.92 207
102 Blacksmith 1 st clas s Day 1.34 270
9999 Sundries L.S. 80.73 1.00
9999 For labour scaffocaling etc L.S. 80.73 1.00
Painting with epoxy paint over and including sqm 5.82 75.25
priming coat (Rate as per Item no. 13.52.1 of
SH: Finishing.)sqm 5.82 75.25 437.96(A)
TOTAL
Add for water charges @ 1% on all except A

TOTAL
Add for contractor’s profit and overheads
@15% except A
Cost for 88.79 kg
Cost for 1 kg
Say

7.42 Providing and fixing adjustable stainless steel cramps of approved quality and of required shape and
size adjustable with stainless steel nuts bolts and washer (total weight not less than 260 gms) for dry stone
cladding fixed on frame work at suitable location including making necessary recesses in stone slab,
drilling required holes etc complete as per direction of the Engineer-in-charge.
Code Description Unit Quantity Rate
Details of cost for 10 Nos.
8698 Stainless steel cramps with nuts, bolts and
washer for dry stone cladding . each 10 200.00

LABOUR for making holes, recesses etc. and fixing of stainless stul cramps
103 Blacksm ith 2nd class Day 0.1 223
124 Mason 2nd class Day 1 223
114 Beldar Day 1.1 207
9999 Scaffolding, hire charges of drill machine etc. L.S. 20.8 1.00
9999 Sundries L.S. 20.8 1.00
TOTAL
Add for water charges @ 1% on all
TOTAL
Add for contractor’s profit and overheads
@15%
Cost for 10 sqm.
Cost for 1 sqm.
Say
ncluding levellingup with
mm nominal size) at plinth

Amount

332.00
67.90
72.62

626.35

238.61
221.49
146.97
16.20
45.76
4.42
1772.32
17.72
1790.04

268.51
2058.55
2058.55

plinth level and upto floor


se sand : 12 graded stone

Amount

67.34

10.79
60.21
78.66

233.91
450.91
4.51
455.42

68.31
523.73
523.73
ve floor V level for every

Amount

414.00
414.00
4.14
418.14

62.72
480.86
480.86

Amount

129.34
55.89
185.23
1.85
187.08

28.06
215.14
215.14

Amount

96.28
18.15

316.66
72.45
503.54
5.04
508.58

76.29
584.87
584.87

mean radius not exceeding


Amount

33.20
6.26

60.21
109.71
209.38
2.09
211.47

31.72
243.19
243.19

with :

Amount

569.41
401.72
67.90
85.76

472.76
256.68
146.97
16.20
13.52
2030.92
20.31
2051.23

307.68
2358.92
2358.92

h with:

Amount
569.41
365.20
67.90
78.88

392.48
256.68
146.97
16.20
13.52
1907.24
19.07
1926.31

288.95
2215.26
2215.26

d sort) in superstructure

Amount

24.18

57.98
72.45

310.50
465.11
4.65
469.76

70.46
540.23
540.23

sort) in

Amount

414.00
414.00
4.14
418.14

62.72
480.86

Amount

149.41
55.89
205.30
2.05
207.35

31.10
238.46
238.46

Amount

106.24
20.03

372.41
72.45
571.13
5.71
576.84

86.53
663.37
663.37

ved on

Amount

36.52
6.89
73.59
109.71
226.71
2.27
228.97

34.35
263.32
263.32

ent mortar 1:6 (1 cement :


e dust) with an admixture

Amount

59.99
1.47

3.11

19.62
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06
146.63
1.47
148.10

22.21
170.31
17031.31
17031.31

ent mortar 1:6 (1 cement :


e dust) with an admixture

Amount

66.65
1.47

3.11

19.62
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06
153.30
1.53
154.83

23.22
178.05
17805.45
17805.45

ent mortar 1:6 (1 cement :


e dust) with an admixture
Amount

59.99
1.47

3.11

39.25
3.24
18.22
9.11
15.84

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06
189.46
1.89
191.35

28.70
220.06
22005.55
22005.55

ent mortar 1:6 (1 cement :


e dust) with an admixture

Amount

66.65
1.47

3.11
39.25
3.24
18.22
9.11
15.84

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06
196.12
1.96
198.08

29.71
227.80
22779.69
22779.69

sand) including centring,


ust) with an admixture of

Amount

59.99
1.47

19.62
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
13.52
8.06
2.73
8.06
165.11
1.65
166.76

25.01
191.77
19177.18
19177.18

sand) including centring,


ust) with an admixture of

Amount

66.65
1.47

19.62
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
13.52
8.06
2.73
8.06
171.77
1.72
173.49

26.02
199.51
19951.32
19951.32

sand) including centring,


ust) with an admixture of

Amount

59.99
1.47

39.25
1.62
55.09
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
33.15
8.06
2.73
8.06
259.45
2.59
262.04

39.31
301.35
30135.00
30135.00

sand) including centring,


ust) with an admixture of

Amount
66.65
1.47

39.25
1.62
55.09
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
33.15
8.06
2.73
8.06
266.11
2.66
268.78

40.32
309.09
30909.14
30909.14

el in cement mortar 1:6 (1


ite cement: 2 stone dust)

Amount

59.99
1.47

13.16
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06

3.11
140.16
1.40
141.57

21.23
162.80
16280.16
16280.16

el in cement mortar 1:6 (1


ite cement: 2 stone dust)

Amount

59.99
1.47

26.31
3.24
18.22
9.11
15.84

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06

3.11
176.52
1.77
178.29

26.74
205.03
20503.26
20503.26

el in cement mortar 1:6 (1


ite cement: 2 stone dust)

Amount

66.65
1.47

13.16
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06

3.11
146.83
1.47
148.30

22.24
170.54
17054.30
17054.30

el in cement mortar 1:6 (1


ite cement: 2 stone dust)

Amount

66.65
1.47

26.31
3.24
18.22
9.11
15.84

9.81
1.62
4.55
4.55
3.96
3.96
2.73
8.06

3.11
183.19
1.83
185.02

27.75
212.77
21277.40
21277.40

r every four floors or part

Amount
onal four floors) or part

4.14
4.14
0.04
4.18

0.63
4.81
480.86
480.86

Amount

8.97
8.97
0.09
9.06

1.36
10.42
1041.87
1041.87

with a mean radius not

Amount

6.24
6.24
0.06
6.30

0.95
7.25
724.78
724.78

ding all strutting, bolting,

Amount
n average of 8m)

14206.40
53.99

254.62
560.00
0.79

6244.00
4968.00
134.55
f8m
-17,144.66
9277.70
264.22
9541.92

4002.99
13544.91
406.63
406.63

in cement mortar 1:6 (1


te cem ent : 2 stone dust)

Amount

59.99
1.47

64.89
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
8.06
2.73
8.06

3.11
199.96
2.00
201.96

30.29
232.25
23225.47
23225.47

in cement mortar 1:6 (1


te cem ent : 2 stone dust)

Amount

66.65
1.47

64.89
1.62
9.11
4.55
7.92

9.81
1.62
4.55
4.55
3.96
3.96
8.06
2.73
8.06

3.11
206.63
2.07
208.69
31.30
240.00
23999.61
23999.61

Amount

11.70
11.70
0.12
11.82

1.77
13.59
1358.96
1358.96

Amount

33.15
33.15
0.33
33.48

5.02
38.50
3850.37
3850.37

Amount

111.50
155.25
266.75
2.67
269.42

40.41
309.83
13.77
13.77

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

Amount

419.99
10.17

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1339.07
13.39
1352.47

202.87
1555.33
1555.33
ing filled with a grout of
white cement mortar 1:2
shade : (To be secured to

Amount

360.00
8.70

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1277.62
12.78
1290.40

193.56
1483.96
1483.96

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

Amount
300.15
7.24

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1216.31
12.16
1228.47

184.27
1412.74
1412.74

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

ng

Amount

239.99
5.82

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1154.72
11.55
1166.27

174.94
1341.21
1341.21

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

Amount

179.96
4.35

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1093.23
10.93
1104.16

165.62
1269.78
1269.78

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

backing.

Amount

419.99
10.17

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1758.64
17.59
1776.22

266.43
2042.66
2042.66

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

backing.

Amount

360.00
8.70

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1697.19
16.97
1714.16

257.12
1971.28
1971.28
ing filled with a grout of
white cement mortar 1:2
shade : (To be secured to

gh backing.

Amount

300.15
7.24

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1635.87
16.36
1652.23

247.83
1900.06
1900.06

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

backing.

Amount
239.99
5.82

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1574.29
15.74
1590.03

238.50
1828.53
1828.53

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

backing.

Amount

179.96
4.35

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1512.79
15.13
1527.92

229.19
1757.11
1757.11

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

Amount

466.65
10.17

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1385.74
13.86
1399.60

209.94
1609.54
1609.54

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

Amount

400.00
8.70

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1317.62
13.18
1330.80
199.62
1530.42
1530.42

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

Amount

333.50
7.24

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1249.66
12.50
1262.15

189.32
1451.48
1451.48
ing filled with a grout of
white cement mortar 1:2
shade : (To be secured to

Amount

266.50
5.82

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1181.24
11.81
1193.05

178.96
1372.01
1372.01

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

Amount
199.95
4.35

301.05
8.64
46.37
23.18
40.32

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1113.22
11.13
1124.35

168.65
1293.01
1293.01

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

h backing.

Amount

466.65
10.17

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1805.30
18.05
1823.35

273.50
2096.86
2096.86

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

backing.

Amount

400.00
8.70

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1737.19
17.37
1754.56

263.18
2017.74
2017.74

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

backing.

Amount

333.50
7.24

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1669.22
16.69
1685.91

252.89
1938.80
1938.80

ing filled with a grout of


white cement mortar 1:2
shade : (To be secured to

backing.

Amount

266.50
5.82

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1600.80
16.01
1616.81

242.52
1859.33
1859.33
ing filled with a grout of
white cement mortar 1:2
shade : (To be secured to

backing.

Amount

199.50
4.35

602.10
17.28
92.74
46.37
80.64

99.90
69.55
69.55
60.48
60.48
26.91
19.76

24.00

58.72
1532.33
15.32
1547.66

232.15
1779.81
1779.81

us not exceeding 6 m.
Amount

8.97
8.97
0.09
9.06
1.36
10.42
1041.87
1041.87

for anchoring stone wall


t mortar 1:2(1 cement: 2
herever required.
Amount

29.96
3.90

4.11
6.50
44.47
0.44
44.92

6.74
51.65
532.52
532.52

e shape as per design in


ses.
Amount

9.10

5.33

4.11
18.54
0.19
18.73

2.81
21.54
21.54
g adjacent stones in stone
ecessary chases.
Amount

7.50

3.90

4.11
1.95
17.46
0.17
17.64

2.65
20.28
20.28

m wide beyond the wall as


12mm diameter anchoring
with bricks cove of class
g in cement mortar 1:2 (1
ade:

Amount

330.00
11.96

111.50

223.00
310.50
67.34

26.91
6.24
16.12
86.00
39.94
104.00
38.19

1371.71
13.34
1385.04

202.03
1587.07
793.54
793.54

m wide beyond the wall as


12mm diameter anchoring
with bricks cove of class
g in cement mortar 1:2 (1
ade:

Amount

385.00
11.96

111.50
62.00
39.94

67.34
6.24
16.12
26.91

223.00
310.50
104.00
38.19
1402.71
13.65
1416.35

206.72
1623.08
811.54
811.54

pto 80 cm projection in
nt mortar 1:2 (1 white

Amount

270.00
10.73

100.35
53.82
6.24
13.52
26.91

133.80
165.60
780.97
7.81
788.78

118.32
907.10
483.79
483.79

pto 80 cm projection in
nt mortar 1:2 (1 white

Amount
315.00
10.73

100.35
53.82
6.24
13.52
26.91

133.80
165.60
825.97
8.26
834.23

125.14
959.37
511.66
511.66

d stone brackets, fixed in


ete.
Amount

194.00
6.62

191.78
103.50
13.52
509.42
5.09
514.51

77.18
591.69
528.30
528.30

and moulded including


el bars 7.5 cm long 6 mm
Amount

277.20
6.62

399.75
9.99
56.10
28.05
48.78

54.95
9.07
25.50
25.50
22.18
22.18
45.14
15.29

212.00

297.35

1555.64
15.56
1571.20

235.68
1806.88
1806.88

ses, upto 75mm thick in


ment mortar 1:2 (1 white

Amount
= 6.75cudm.

114.96
5.33
15.61
14.49
150.39
0.35
150.75

5.37
156.11
23127.89
23127.89

ses, upto 75mm thick in


ment mortar 1:2 (1 white

Amount
= 6.75cudm.

120.19
5.33

15.61
14.49
155.62
0.35
155.97

5.37
161.34
23902.03
23902.03

1:3 (1 cement : 3 coarse


ust) with an admixture of

Amount

132.00
4.78
2832.10
1749.15
80.73
4798.76
47.99
4846.74

727.01
5573.76
5573.76

1:3 (1 cement : 3 coarse


ust) with an admixture of

Amount
Amount

154.00
4.78

2832.10
1749.15
80.73
4820.76
48.21
4868.96

730.34
5599.31
5599.31

ding cost of pumping or

Amount

75.00
828.00
903.00
9.03
912.03
136.80
1048.83
249.72
249.72

Amount

5.40
4.46
51.75
31.05
92.66

0.93
93.59

14.04
107.62
107.62

hick rough facing on the


dth including embedding
ecessary chases of size
of cement mortar 1:3 (1
nt : 2 stone dust) with an
gineer-in-charge.

Amount

128.80

33.28
5.11

120.00

99.17

109.95

40.43
78.25
55.75
103.50
5.40
26.91
806.55

6.97
813.52

105.54
919.05
919.05

c. (Veneer work) backing


and jointed with Cement
te. (To be secured to the

Amount

2012.50
31.68

469.78
40.43

1449.50
1345.50
896.31

1944.00
111.54
8301.24

82.70
8383.94

1252.84
9636.77
963.68
963.68

over 12mm thick bed of


ent with an admixture of

Amount

5688.75
40.04

456.73
171.60
25.74

2079.00
1593.90
260.00

171.60
10487.36
104.87
10592.23

1588.83
12181.06
1218.11
1218.11

over 12mm thick bed of


ent with an admixture of

le,
Amount

4407.50
40.04
456.73
171.60
25.74

2079.00
1593.90
260.00

171.60
9206.11
92.06
9298.17

1394.73
10692.89
1069.29
1069.29

0 m from ground level for

Amount

215.28

75.00
81.00
62.10
27.00
28.60
488.98
4.89
493.87

74.08
567.95
56.80
56.80
gang saw cut stone with
steel frame work and/ or
eather sealant as per
ame work, stainless steel

Amount

1413.75
60.00

10.17
30.68
153.40
204.75

626.00
828.00

207.00
204.75

67.50
103.50
204.75
51.22

4165.47
41.65
4207.12

631.07
4838.19
1612.73
1612.73

gang saw cut stone with


steel frame work and/ or
eather sealant as per
ame work, stainless steel

Amount
1566.00
60.00

10.17
30.68
153.40
204.75

626.00
828.00

207.00
204.75

67.50
103.50
204.75
51.22

4317.72
43.18
4360.89

654.13
5015.03
1671.68
1671.68

thick gang saw cut with


gular tube in the required
etc. The frame work shall
which shall be welded to
ment :2 coarse sand :4
cluding cost of necessary
/RCC surface including
NC ” primer as approved
Shop drawings shall be
ecution). The frame work
eel frame work shall be
parately and nothing extra

Amount
1955.86
2125.20

277.59

70.20
57.98
414.00
56.00

120.60
1018.44
361.80
80.73
80.73
437.96

7057.08

66.43
7123.51

1006.43
8129.94
91.56
91.56

and of required shape and


an 260 gms) for dry stone
y recesses in stone slab,

Amount

2000.00

22.30
223.00
227.70
20.80
20.80
2514.60
25.15
2539.75

380.96
2920.71
292.07
292.07
8.1 Marble work gang saw cut (polished and machine cut) of thickness 18mm for wall lining
(veneer work) in cement mortar 1:3 (1 cement : 3 coarse sand) including pointing with white
cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match
the marble shade: (To be secured to the backing by means of cramps, which shall be paid for
separately).
8.1.1 Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.
8.1.1.1 Area of slab upto 0.50 sqm
Code Description Unit Quantity Rate Amount
Details of cost for 0.50 sqm.
7452 Raj Nagar plain white marble (polished and sqm 0.6 540.00 324.00
machine cut) 18 mm thick upto 0.50sqm

2216 Carriage of stone @ 2.30kg/cudm tonne 0.03 47.29 1.42


Cem ent mortar 1:3 (1 Cement: 3 Coarse 0.008 3262.33 26.10
sand) Rate as per item No. 3.8 cum
White 1:2 (1 white cement: marble dust) 0.0012 7510.99 9.01
( Rate as per item No.3.15 ) 2 cum 0.0012
7590.25 9.11 cum
Labour: For fixing
126 Stone Mason (ornamental) Day 0.335 313 104.86
128 Mate Day 0.165 313 51.65
102 Black smith 1 st class Day 0.135 270 36.45
114 Beldar Day 0.335 207 69.35
115 Coolie Day 0.335 207 69.35
100 Bandhani Day 0.335 180 60.30
101 Bhisti Day 0.335 180 60.30
9999 Scaffolding etc. L.S. 13.39 1.00 13.39
TOTAL 826.16
Add 1% for water charges 8.26
TOTAL 834.42
Add for contractor’s profit and overheads
@15% 125.16
Cost of 0.5 sqm 959.59
Cost of 1 sqm 1919.17
Say

8.1 Marble work gang saw cut (polished and machine cut) of thickness 18mm for wall lining
(veneer work) in cement mortar 1:3 (1 cement : 3 coarse sand) including pointing with white
cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match
the marble shade: (To be secured to the backing by means of cramps, which shall be paid for
separately).
8.1.1 Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.
8.1.1.2 Area of slab over 0.50 sqm
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
7453 Raj nagar plain white marble (table rubbed sqm 1.2 580.00 696.00
and polished) 18 mm thick above 0.20 sqm
up to 0.50 sqm

2216 Carriage of stone @ 2.30kg/cudm tonne 0.06 47.29 2.84


Cem ent mortar 1:3 (1 Cement: 3 Coarse 0.0144 3262.33 46.98
sand) Rate as per item No. 3.8 cum
White 1:2 (1 white cement: marble dust) 0.0025 7510.99 18.78
( Rate as per item No.3.15 ) cum
Labour: For fixing
126 Stone Mason (ornamental) Day 0.67 313 209.71
128 Mate Day 0.33 313 103.29
102 Black smith 1 st class Day 0.27 270 72.90
114 Beldar Day 0.67 207 138.69
115 Coolie Day 0.67 207 138.69
100 Bandhani Day 0.67 180 120.60
101 Bhisti Day 0.67 180 120.60
9999 Scaffolding etc. L.S. 26.91 1.00 26.91
TOTAL 1695.98
Add 1% for water charges 16.96
TOTAL 1712.94
Add for contractor’s profit and overheads
@15% 256.94
Cost of 1 sqm 1969.88
Say

8.2 Providing and fixing 18mm thick gang saw cut mirror polished (premoulded and
prepolished) machine cut for kitchen platforms, vanity counters ,window sills , facias and
similar locations of required size of approved shade, colour and texture laid over 20mm thick
base cement mortar 1:4 (1 cement : 4 coarse sand) with joints treated with white cement,
mixed with matching pigment, epoxy touch ups, including rubbing, curing moulding and
polishing to edge to give high gloss finish etc. complete at all levels.
8.2.1 Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.
8.2.1.1 Area of slab upto 0.50 sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 0.50 sqm.
7452 Raj Nagar plain white marble (polished and sqm 0.525 540.00 283.50
machine cut) 18 mm thick upto 0.50sqm

Cem ent mortar 1:4 (1 Cement: 3 4oarse 0.012 2580.18 30.96


sand) Rate as per item No. 3.9 cum
Labour: For fixing
123 Mason (brick layer) 1st class Day 0.7 270 189.00
114 Beldar Day 0.325 207 67.28
115 Coolie Day 0.325 207 67.28
9999 Moulding and edge polishing. L.S. 39 1.00 39.00
Sundries apoxy resin & cutting machine L.S. 16.25
9999 etc. 1.00 16.25
TOTAL 693.26
Add 1% for water charges 6.93
TOTAL 700.19
Add for contractor’s profit and overheads
@15% 105.03
Cost of 0.5 sqm 805.22
Cost of 1 sqm 1610.45
Say

8.2 Providing and fixing 18mm thick gang saw cut mirror polished (premoulded and
prepolished) machine cut for kitchen platforms, vanity counters ,window sills , facias and
similar locations of required size of approved shade, colour and texture laid over 20mm thick
base cement mortar 1:4 (1 cement : 4 coarse sand) with joints treated with white cement,
mixed with matching pigment, epoxy touch ups, including rubbing, curing moulding and
polishing to edge to give high gloss finish etc. complete at all levels.
8.2.1 Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.
8.2.1.2 Area of slab over 0.50 sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
7453 Raj nagar plain white marble (table rubbed sqm 1.05 580.00 609.00
and polished) 18 mm thick above 0.20 sqm
up to 0.50 sqm

Cem ent mortar 1:4 (1 Cement: 3 4oarse 0.024 2580.18 61.92


sand) Rate as per item No. 3.9 cum
Labour: For fixing
123 Mason (brick layer) 1st class Day 1.4 270 378.00
114 Beldar Day 0.65 207 134.55
115 Coolie Day 0.65 207 134.55
9999 Moulding and edge polishing. L.S. 78 1.00 78.00
Sundries apoxy resin & cutting machine L.S. 32.5
9999 etc. 1.00 32.50
TOTAL 1428.52
Add 1% for water charges 14.29
TOTAL 1442.81
Add for contractor’s profit and overheads
@15% 216.42
Cost of 1 sqm 1659.23
Say
TOTAL
8.2 Providing and fixing 18mm thick gang saw cut mirror polished (premoulded and
prepolished) machine cut for kitchen platforms, vanity counters ,window sills , facias and
similar locations of required size of approved shade, colour and texture laid over 20mm thick
base cement mortar 1:4 (1 cement : 4 coarse sand) with joints treated with white cement,
mixed with matching pigment, epoxy touch ups, including rubbing, curing moulding and
polishing to edge to give high gloss finish etc. complete at all levels.
8.2.2 Granite of any colour and shade
8.2.2.1 Area of slab upto 0.50 sqm
Code Description Unit Quantity Rate Amount
Details of cost for 0.50 sqm.
7295 Granite Black m arble, 18 mm thick slab, sqm 0.525 1500.00 787.50
above 0.2 sqm up to 0.5 sqm (area wise)
Cem ent mortar 1:4 (1 Cement: 3 4oarse 0.012 2580.18 30.96
sand) Rate as per item No. 3.9 cum
Labour: For fixing
123 Mason (brick layer) 1st class Day 0.7 270 189.00
114 Beldar Day 0.325 207 67.28
115 Coolie Day 0.325 207 67.28
9999 Moulding and edge polishing. L.S. 39 1.00 39.00
Sundries apoxy resin & cutting machine L.S. 16.25
9999 etc. 1.00 16.25
TOTAL 1197.26
Add 1% for water charges 11.97
TOTAL 1209.23
Add for contractor’s profit and overheads
@15% 181.39
Cost of 0.5 sqm 1390.62
Cost of 1 sqm 2781.24
Say

8.2 Providing and fixing 18mm thick gang saw cut mirror polished (premoulded and
prepolished) machine cut for kitchen platforms, vanity counters ,window sills , facias and
similar locations of required size of approved shade, colour and texture laid over 20mm thick
base cement mortar 1:4 (1 cement : 4 coarse sand) with joints treated with white cement,
mixed with matching pigment, epoxy touch ups, including rubbing, curing moulding and
polishing to edge to give high gloss finish etc. complete at all levels.
8.2.2 Granite of any colour and shade
8.2.2.2 Area of slab over 0.50 sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 2.0 sqm.
7297 Granite Black m arble, 18 mm thick slab, sqm 2.1 1615.00 3391.50
above 1.0 sqm up to 2.0 sqm (area wise)
Cem ent mortar 1:4 (1 Cement: 3 4oarse 0.027 2580.18 69.66
sand) Rate as per item No. 3.9 cum
Labour: For fixing
123 Mason (brick layer) 1st class Day 2.8 270 756.00
114 Beldar Day 1.3 207 269.10
115 Coolie Day 1.3 207 269.10
9999 Moulding and edge polishing. L.S. 78 1.00 78.00
Sundries apoxy resin & cutting machine L.S. 65
9999 etc. 1.00 65.00
TOTAL 4898.36
Add 1% for water charges 48.98
TOTAL 4947.35
Add for contractor’s profit and overheads
@15% 742.10
Cost of 2sqm 5689.45
Cost of 1 sqm 2844.73
Say

8.3 Extra for providing edge moulding to 18mm thick marble stone counters, Vanities etc.
including machine polishing to edge to give high gloss finish etc. complete as per design
approved by Engineer-in-Charge.
8.3.1 Marble work
Code Description Unit Quantity Rate Amount
Details of cost for 10 m.
Labour:
19 Hand Grinder for-mirror-polish Day 1.5 100 150
114 Beldar Day 2 207 414.00
9999 Sundries Blades & Polished etc. L.S. 78 1.00 78.00
TOTAL 642.00
Add 1% for water charges 6.42
TOTAL 648.42
Add for contractor’s profit and overheads
@15% 97.26
Cost of 10 m 745.68
Cost of 1 m 74.57
Say

8.3 Extra for providing edge moulding to 18mm thick marble stone counters, Vanities etc.
including machine polishing to edge to give high gloss finish etc. complete as per design
approved by Engineer-in-Charge.
8.3.2 Granite work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 m.
Labour:
19 Hand Grinder for-mirror-polish Day 2.5 100 250
114 Beldar Day 3.5 207 724.50
9999 Sundries Blades & Polished etc. L.S. 117 1.00 117.00
TOTAL 1091.50
Add 1% for water charges 10.92
TOTAL 1102.42
Add for contractor’s profit and overheads
@15% 165.36
Cost of 10 m 1267.78
Cost of 1 m 126.78
Say

8.4 Extra for fixing marble /granite stone over and above corresponding basic item, in facia and
drops of width upto 150 mm with epoxy resin based adhesive including cleaning etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for facia 1.5m long and 0.15m wide
Labour:
123 Mason (brick layer) 1st class Day 0.3 270 81.00
114 Beldar Day 0.3 207 62.10
9999 Scaffolding, expoxy etc L.S. 39 1.00 39.00
Cem ent mortar 1:4 (1 Cement: 3 4oarse 0.005 2580.18 12.90
sand) Rate as per item No. 3.9 cum
TOTAL 195.00
Add 1% for water charges 1.95
TOTAL 196.95
Add for contractor’s profit and overheads
@15% 29.54
Cost of 1.5m long and 0.15m wide 226.49
Cost of 1 m 226.49
Say

8.5 Extra for providing opening of required size & shape for wash basins/ kitchen sink in
kitchen platform, vanity counters and similar location in marble/Granite/stone work including
necessary holes for pillar taps etc. including rubbing and polishing of cut edges etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for providing one opening of required size and shape.
126 Stone Mason (ornamental) Day 0.4 313 125.20
114 Beldar Day 0.4 207 82.80
9999 Sundries L.S. 15.3 1.00 15.30
TOTAL 223.30
Add 1% for water charges 2.23
TOTAL 225.53
Add for contractor’s profit and overheads
@15% 33.83
Cost per opening 259.36
Say

8.6 Mirror polishing on marble work/Granite work/stone work where ever required to give high
Code
gloss finishDescription
complete. Unit Quantity Rate Amount
Details of cost for 10 sqm.
Labour:
13 Floor grinder machine (Granite) Day 1 200 200
114 Beldar Day 2.5 207 517.50
101 Bhisti Day 1.5 180 270.00
9999 Sundries grease, mop grinding stones etc. L.S. 65 1.00 65.00
TOTAL 1052.50
Add 1% for water charges 10.53
TOTAL 1063.03
Add for contractor’s profit and overheads
@15% 159.45
Cost of 10 sqm 1222.48
Cost of 1 sqm 122.25
Say

8.7 Providing and fixing cramps of required size & shape in RCC/ CC backing with
cement mortar 1:2(1 cement :2 coarse sand) including drilling necessary hole in stones and
embedding the cramp in the hole (fastener to be paid separately).
8.7.1 Gunmetal cramps.
Code Description Unit Quantity Rate Amount
Details of cost for one cramp
Materials:
7338 Gun metal cramp Kg. 0.118 270.00 31.86
Cem ent montar 1:2 (1 cement: 2 coarse 0.001 4111.99 4.11
sand). (Rate as per item No. 3.7) cum
9999 Labour for fixing in position L.S. 6.5 1.00 6.50
9999 Carriage L.S. 3.9 1.00 3.90
TOTAL 46.37
Add 1% for water charges 0.46
TOTAL 46.84
Add for contractor’s profit and overheads
@15% 7.03
Cost of 0.107 kg 53.86
Cost of 1 kg 503.37
Say

8.7 Providing and fixing cramps of required size & shape in RCC/ CC backing with
cement mortar 1:2(1 cement :2 coarse sand) including drilling necessary hole in stones and
embedding the cramp in the hole (fastener to be paid separately).
8.7.2 Stainless steel cramps.
Code Description Unit Quantity Rate Amount
Details of cost for one cramp
Materials:
7339 Stainless steel cramp Kg. 0.107 280.00 29.96
Cem ent montar 1:2 (1 cement: 2 coarse 0.001 4111.99 4.11
sand). (Rate as per item No. 3.7) cum
9999 Labour for fixing in position L.S. 6.5 1.00 6.50
9999 Carriage L.S. 3.9 1.00 3.90
TOTAL 44.47
Add 1% for water charges 0.44
TOTAL 44.92
Add for contractor’s profit and overheads
@15% 6.74
Cost of 0.097 kg 51.65
Cost of 1 kg 532.52
Say

8.8 Providing and fixing expansion hold fasteners on C.C. /R.C.C. surface backing
including drilling necessary holes and the cost of bolt etc complete.
8.8.1 Wedge expansion type
8.8.1.1 Fastener with threaded dia 6 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 30nos. W.E.H. fastener
Materials:
7430 Wedge expansion hold fastener size
6mm,36.5mm length each 30 10.00 300
1034 Bolt 6mm dia. Length (36.5+10mm) quintal 0.0045 7000.00 31.5
Labour:
116 Fitter Grade-I Day 0.25 270 67.50
114 Beldar Day 0.25 207 51.75
Hire and running charges for hand drill L.S. 32.5
machine Sundries, drilling bit scaffolding
9999 etc. 1.00 32.50
TOTAL 483.25
Add 1% for water charges 4.83
TOTAL 488.08
Add for contractor’s profit and overheads
@15% 73.21
Cost of 30 Nos. 561.29
Cost of 1 No. 18.71
Say

8.8 Providing and fixing expansion hold fasteners on C.C. /R.C.C. surface backing
including drilling necessary holes and the cost of bolt etc complete.
8.8.1 Wedge expansion type
8.8.1.2 Fastener with threaded dia 10 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 30nos. W.E.H. fastener
Materials:
7431
Wedge expansion hold fastener 3/8" or 10 mm each 30 12.00 360
1034 Bolt 6mm dia. Length (36.5+10mm) quintal 0.006 7000.00 42
Labour:
116 Fitter Grade-I Day 0.25 270 67.50
114 Beldar Day 0.25 207 51.75
Hire and running charges for hand drill L.S. 32.5
machine Sundries, drilling bit scaffolding
9999 etc. 1.00 32.50
TOTAL 553.75
Add 1% for water charges 5.54
TOTAL 559.29
Add for contractor’s profit and overheads
@15% 83.89
Cost of 30 Nos. 643.18
Cost of 1 No. 21.44
Say

8.8 Providing and fixing expansion hold fasteners on C.C. /R.C.C. surface backing
including drilling necessary holes and the cost of bolt etc complete.
8.8.1 Wedge expansion type
8.8.1.3 Fastener with threaded dia 12 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 30nos. W.E.H. fastener
Materials:
7432
Wedge expansion hold fastener 1/2" or 12 mm each 30 23.00 690
1034 Bolt 6mm dia. Length (36.5+10mm) quintal 0.0075 7000.00 52.5
Labour:
116 Fitter Grade-I Day 0.25 270 67.50
114 Beldar Day 0.25 207 51.75
Hire and running charges for hand drill L.S. 32.5
machine Sundries, drilling bit scaffolding
9999 etc. 1.00 32.50
TOTAL 894.25
Add 1% for water charges 8.94
TOTAL 903.19
Add for contractor’s profit and overheads
@15% 135.48
Cost of 30 Nos. 1038.67
Cost of 1 No. 34.62
Say

8.9 Stone tile (polished) work for wall lining over 12mm thick bed of cement mortar 1:3 (1
cement: 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in white cement
complete.
8.9.1 8 mm thick.
8.9.1.1 Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
2751 8 mm thick marble tiles (polished) sqm 1.025 294.00 301.35
Cem ent mortar 1:3 (1 Cement: 3 Coarse 0.014 3262.33 45.67
sand) Rate as per item No. 3.8 cum
367 Cement slurry @ 3.3 kg/sqm. tonne 0.0033 5200.00 17.16
123 Mason (brick layer) 1st class Day 1 270 270.00
114 Beldar Day 1 207 207.00
9999 Mortar for pointing L.S. 25.38 1.00 25.38
9999 Carriage of tiles L.S. 3.95 1.00 3.95
9999 Sundries etc. L.S. 16.9 1.00 16.90
TOTAL 887.41
Add 1% for water charges 8.87
TOTAL 896.29
Add for contractor’s profit and overheads
@15% 134.44
Cost of 1 sqm 1030.73
2061.46
Say

8.9 Stone tile (polished) work for wall lining over 12mm thick bed of cement mortar 1:3 (1
cement: 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in white cement
complete.
8.9.1 8mm thick.
8.9.1.2 Granite of any colour and shade.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
2750 8 mm thick granite stone tiles (mirror
polished of all shades) sqm 1.025 555.00 568.875
Cem ent mortar 1:3 (1 Cement: 3 Coarse 0.014 3262.33 45.67
sand) Rate as per item No. 3.8 cum
367 Cement slurry @ 3.3 kg/sqm. tonne 0.0033 5200.00 17.16
123 Mason (brick layer) 1st class Day 1 270 270.00
114 Beldar Day 1 207 207.00
9999 Mortar for pointing L.S. 25.38 1.00 25.38
9999 Carriage of tiles L.S. 3.95 1.00 3.95
9999 Sundries etc. L.S. 16.9 1.00 16.90
TOTAL 1154.94
Add 1% for water charges 11.55
TOTAL 1166.49
Add for contractor’s profit and overheads
@15% 174.97
Cost of 1 sqm 1341.46
2682.92
Say
8.10 Providing and fixing 18 mm thick stone slab table rubbed, edges rounded and polished of
size 75x50 cm deep and 1.8 cm thick fixed in urinal partitions by cutting a chase of appropriate
width with chase cutter and embedding the stone in the chase with epoxy grout or with cement
concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 6 mm nominal size) as
per direction of Engineer-in-charge and finished smooth.
8.10.1 White Agaria Marble Stone.
Code Description Unit Quantity Rate Amount
Details of cost for one No or 0.375 sqm.
Materials :-
7244 Agaria Marble Stone sqm 0.45 1440.00 648.00
9999 Cem ent concrete 1:2:4 for filling L.S. 21.58 1.00 21.58
Labour for fixing, edge rounding and final L.S. 43.16
9999 polishing. 1.00 43.16
9999 Sundries etc. L.S. 21.58 1.00 21.58
TOTAL 734.32
Add 1% for water charges 7.34
TOTAL 741.66
Add for contractor’s profit and overheads
@15% 111.25
Cost of 0.375 sqm 852.91
Cost of 1 sqm 2274.43
Say

8.10 Providing and fixing 18 mm thick stone slab table rubbed, edges rounded and polished of
size 75x50 cm deep and 1.8 cm thick fixed in urinal partitions by cutting a chase of appropriate
width with chase cutter and embedding the stone in the chase with epoxy grout or with
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 6 mm nominal
size) as per direction of Engineer-in-charge and finished smooth.

8.10.2 Granite Stone of approved shade.


Code Description Unit Quantity Rate Amount
Details of cost for one No or 0.375 sqm.
Materials :-
7245 Granite Stone sqm 0.45 1670.00 751.50
9999 Cem ent concrete 1:2:4 for filling L.S. 21.58 1.00 21.58
Labour for fixing, edge rounding and final L.S. 43.16
9999 polishing. 1.00 43.16
9999 Sundries etc. L.S. 21.58 1.00 21.58
TOTAL 837.82
Add 1% for water charges 8.38
TOTAL 846.20
Add for contractor’s profit and overheads
@15% 126.93
Cost of 0.375 sqm 973.13
Cost of 1 sqm 2595.01
Say
1919.17
1969.88
1610.45

1659.23
2781.24
2844.73

74.57
126.78

226.49

259.36
122.25

503.37
532.52

18.71
21.44

34.62
1030.73

1341.46
2274.43

2595.01
9.1 Providing wood work in frames of doors, windows, clerestory windows and other
frames, wrought framed and fixed in position :
9.1.1 Second class teak wood
Code Description Unit Quantity Rate Amount
Details of cost for Chowkhat of a door
Materials
1,189 Second class teakwood 10 cudm 38 394.00 1497.20
2,204 Carriage of material (timber) cum 0.038 60.81 2.31
Labour:
156 Carpenter (avg.) Day 0.72 180 129.60
114 Beldar Day 0.07 207 14.49
TOTAL 1643.60
Add 1% for water charges 16.44
TOTAL 1660.04
Add for contractor’s profit and 249.01
overheads @15%
Cost of 36 cudm. 1909.04
Cost of 1 cum 53028.95
Say 53028.95

9.1 Providing wood work in frames of doors, windows, clerestory windows and other
frames, wrought framed and fixed in position :
9.1.2 Sal wood
Code Description Unit Quantity Rate Amount
Details of cost for Chowkhat of a door
Materials
1,199 Sal wood in scantling 10 cudm 38 218.00 828.40
2,204 Carriage of material (timber) cum 0.038 60.81 2.31
Labour:
156 Carpenter (avg.) Day 0.72 180 129.60
114 Beldar Day 0.07 207 14.49
TOTAL 974.80
Add 1% for water charges 9.75
TOTAL 984.55
Add for contractor’s profit and 147.68
overheads @15%
Cost of 36 cudm. 1132.23
Cost of 1 cum 31450.86
Say 31450.86

9.1 Providing wood work in frames of doors, windows, clerestory windows and other
frames, wrought framed and fixed in position :
9.1.3 Kiln seasoned and chemically treated Hollock wood.
9.1 Providing wood work in frames of doors, windows, clerestory windows and other
frames, wrought framed and fixed in position :
9.1.2 Sal wood
Code Description Unit Quantity Rate Amount
Details of cost for Chowkhat of a door
Materials
2,466 Hollock wood in scantling 10 cudm 38 217.00 824.60
2,204 Carriage of material (timber) cum 0.038 60.81 2.31
2,504 Kiln seasoning of timber cum 0.038 539.00 20.48
9,999 Chemical treatment L.S. 8.97 1.00 8.97
Labour:
156 Carpenter (avg.) Day 0.72 180 129.60
114 Beldar Day 0.07 207 14.49
TOTAL 1000.45
Add 1% for water charges 10.00
TOTAL 1010.46
Add for contractor’s profit and 151.57
overheads @15%
Cost of 36 cudm. 1162.03
Cost of 1 cum 32278.50
Say 32278.50

9.2 Providing laminated veneer lumber conforming to IS: 14616 and TAD -15:
2001( Part B) in factory made frames of doors, windows, clerestory windows and other
frames, wrought framed and fixed in position as per directions of Engineer-in-charge.
Code Description Unit Quantity Rate Amount
Details of cost for Chowkhat of a door
Materials
7,157 Lam inated veneer lumber 10 cudm 38 540.00 2052.00
2,204 Carriage of material (timber) cum 0.038 60.81 2.31
Labour:
111 Carpenter 1st class Day 0.2 270 54.00
112 Carpenter 2nd class Day 0.2 223 44.60
114 Beldar Day 0.2 207 41.40
TOTAL 2194.31
Add 1% for water charges 21.94
TOTAL 2216.25
Add for contractor’s profit and 332.44
overheads @15%
Cost of 36 cudm. 2548.69
Cost of 1 cum 70797.00
Say 70797.00

9.3 Providing wood work in frames of false ceiling, partitions etc. sawn and put up in
position
9.3.1 Sal: wood
Code Description Unit Quantity Rate Amount
Details of cost for ceiling for a room 3x3m
Materials
1,199 Sal wood in scantling 10 cudm 166 218.00 3618.80
2,204 Carriage of material (timber) cum 0.166 60.81 10.09
Labour:
112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 1 207 207.00
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
TOTAL 4112.71
Add 1% for water charges 41.13
TOTAL 4153.84
Add for contractor’s profit and 623.08
overheads @15%
Cost of 158 cudm. 4776.92
Cost of 1 cum 30233.66
Say 30233.66

9.3 Providing wood work in frames of false ceiling, partitions etc. sawn and put up in
position : seasoned and chemically treated Hollock wood.
9.3.2 Kiln
Code Description Unit Quantity Rate Amount
Details of cost for ceiling for a room 3x3m
Materials
2,466 Hollock wood in scantling 10 cudm 166 217.00 3602.20
2,204 Carriage of material (timber) cum 0.166 60.81 10.09
2,504 Kiln seasoning of timber cum 0.166 539.00 89.47
9,999 Chemical treatment L.S. 18.2 1.00 18.20
Labour:
112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 1 207 207.00
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
TOTAL 4203.79
Add 1% for water charges 42.04
TOTAL 4245.83
Add for contractor’s profit and 636.87
overheads @15%
Cost of 158 cudm. 4882.70
Cost of 1 cum 30903.17
Say 30903.17

9.4 Extra for additional labour for circular works, such as in frames of fan light:
9.4.1 Second class teak wood
Code Description Unit Quantity Rate Amount
Details of cost for Chowkhat of a door
Materials
1,189 Second class teakwood 10 cudm 3.8 394.00 149.72
2,204 Carriage of material (timber) cum 0.0038 60.81 0.23
Labour:
156 Carpenter (avg.) Day 0.072 180 12.96
114 Beldar Day 0.007 207 1.45
TOTAL 164.36
Add 1% for water charges 1.64
TOTAL 166.00
Add for contractor’s profit and 24.90
overheads @15%
Cost of 36 cudm. 190.90
Cost of 1 cum 5302.90
Say 5302.90

9.4 Extra for additional labour for circular works, such as in frames of fan light:
9.4.2 Sal wood
Code Description Unit Quantity Rate Amount
Details of cost for Chowkhat of a door
Materials
1,199 Sal wood in scantling 10 cudm 3.8 218.00 82.84
2,204 Carriage of material (timber) cum 0.0038 60.81 0.23
Labour:
156 Carpenter (avg.) Day 0.072 180 12.96
114 Beldar Day 0.007 207 1.45
TOTAL 97.48
Add 1% for water charges 0.97
TOTAL 98.45
Add for contractor’s profit and 14.77
overheads @15%
Cost of 36 cudm. 113.22
Cost of 1 cum 3145.09
Say 3145.09

9.4 Extra for additional labour for circular works, such as in frames of fan light:
9.4.3 Kiln seasoned and chemically treated Hollock wood.
Code Description Unit Quantity Rate Amount
Details of cost for Chowkhat of a door
Materials
2,466 Hollock wood in scantling 10 cudm 3.8 217.00 82.46
2,204 Carriage of material (timber) cum 0.0038 60.81 0.23
2,504 Kiln seasoning of timber cum 0.0038 539.00 2.05
9,999 Chemical treatment L.S. 0.9 1.00 0.90
Labour:
156 Carpenter (avg.) Day 0.072 180 12.96
114 Beldar Day 0.007 207 1.45
TOTAL 100.05
Add 1% for water charges 1.00
TOTAL 101.05
Add for contractor’s profit and 15.16
overheads @15%
Cost of 36 cudm. 116.21
Cost of 1 cum 3227.95
Say 3227.95

9.5 Providing and fixing panelled or panelled and glazed shutters for doors, windows
and clerestory windows including ISI marked black enamelled M.S butt hinges with
necessary screws excluding panelling which will be paid for separately.
9.5.1 Second class teak wood
9.5.1.1 35 mm thick shutters
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a Door
1,190 Teak wood 10 cudm 51 410.00 2091.00
2,204 Carriage of material (timber) cum 0.051 60.81 3.10
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm
597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60
steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
640 steel
Brightscrews 40
finished mm
or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
114 Beldar Day 0.76 207 157.32
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 2670.30
Add 1% for water charges 26.70
TOTAL 2697.00
Add for contractor’s profit and 404.55
overheads @15%
Cost of 2.16 sqm. 3101.55
Cost of 1 sqm 1435.91
Say 1435.91

9.5 Providing and fixing panelled or panelled and glazed shutters for doors, windows
and clerestory windows including ISI marked black enamelled M.S butt hinges with
necessary screws excluding panelling which will be paid for separately.
9.5.1 Second class teak wood
9.5.1.2 30 mm thick shutters
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a Door
1,190 Teak wood 10 cudm 44 410.00 1804.00
2,204 Carriage of material (timber) cum 0.044 60.81 2.68
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm
597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60
steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel
Brightscrews 40 mm
640 finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
114 Beldar Day 0.76 207 157.32
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 2382.88
Add 1% for water charges 23.83
TOTAL 2406.70
Add for contractor’s profit and 361.01
overheads @15%
Cost of 2.16 sqm. 2767.71
Cost of 1 sqm 1281.35
Say 1281.35

9.5 Providing and fixing panelled or panelled and glazed shutters for doors, windows
and clerestory windows including ISI marked black enamelled M.S butt hinges with
necessary screws excluding panelling which will be paid for separately.
9.5.2 Kiln seasoned and chemically treated Hollock wood.
9.5.2.1 35 mm thick shutters
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a Door
2,505 Hollock wood in planks 10 cudm 51 230.00 1173.00
2,204 Carriage of material (timber) cum 0.051 60.81 3.10
2,504 Kiln seasoning of timber cum 0.051 539.00 27.49
9,999 Chemical treatment L.S. 9.1 1.00 9.10
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel
Brightscrews 40 mm
640 finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
114 Beldar Day 0.76 207 157.32
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 1788.89
Add 1% for water charges 17.89
TOTAL 1806.78
Add for contractor’s profit and 271.02
overheads @15%
Cost of 2.16 sqm. 2077.80
Cost of 1 sqm 961.94
Say 961.94

9.5 Providing and fixing panelled or panelled and glazed shutters for doors, windows
and clerestory windows including ISI marked black enamelled M.S butt hinges with
necessary screws excluding panelling which will be paid for separately.
9.5.2 Kiln seasoned and chemically treated Hollock wood.
9.5.2.2 30 mm thick shutters
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a Door
2,505 Hollock wood in planks 10 cudm 44 230.00 1012.00
2,204 Carriage of material (timber) cum 0.044 60.81 2.68
2,504 Kiln seasoning of timber cum 0.044 539.00 23.72
9,999 Chemical treatment L.S. 9.1 1.00 9.10
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel
Brightscrews 40
finished mm
or black enameled mild 15.00 1.20
640 100 Nos 8
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
114 Beldar Day 0.76 207 157.32
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 1623.69
Add 1% for water charges 16.24
TOTAL 1639.93
Add for contractor’s profit and 245.99
overheads @15%
Cost of 2.16 sqm. 1885.92
Cost of 1 sqm 873.11
Say 873.11

9.6 Providing and fixing 35 mm thick factory made laminated veneer lumber door
shutter conforming to IS : 14616 and TADS 15:2001 (Part B) including ISI marked
black enamelled M.S. butt hinges with necessary screws as per directions of Engineer-
in-charge and panelling with panels of:
9.6.1 12mm thick plain grade - 1, medium density flat pressed three layer particle board
FPT - I or graded wood particle board FPT - I, IS : 3087 marked bonded with BWP type
synthetic Description
resin adhesive as per IS : 848 : Unit Quantity Rate Amount
Code
Details of cost of one shutter 220xl08cm = 2.38sqm.
Materials:
7,137 Factory made 35 mm thick shutters sqm 2.38 1500.00 3570.00
with laminated veneer lumber styles
rails as per TADS IS:1995 and panels of
12 mm thick plain type-I, medium
density flat pressed three layer, graded
particle board (FPT-I) as per IS:3087-
1985 bonded with BWP type synthetic
resin adhesive, as per IS:848-1974

9,999 Carriage of shutters L.S. 29.64 1.00 29.64


595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel
Brightscrews 40
finished mm
or black enameled mild 15.00 1.20
640 100 Nos 8
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 0.52 180 93.60
114 Beldar Day 0.6 207 124.20
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 3906.92
Add 1% for water charges 39.07
TOTAL 3945.99
Add for contractor’s profit and 591.90
overheads @15%
Cost of 2.38 sqm. 4537.89
Cost of 1 sqm 1906.68
Say 1906.68

9.6 Providing and fixing 35 mm thick factory made laminated veneer lumber door
shutter conforming to IS : 14616 and TADS 15:2001 (Part B) including ISI marked
black enamelled M.S. butt hinges with necessary screws as per directions of Engineer-
in-charge and panelling with panels of:
9.6.2 12 mm thick prelaminated (with particle board decorative lamination on both
sides) grade - 1, medium density flat pressed, three layer particle board FPT - I or
graded wood particle board FPT - 1, conforming to IS : 3087 bonded with BWP type
synthetic resin adhesive as per IS : 848 and prelamination conforming to IS : 12823
Grade 1, Type - II marked:
Code Description Unit Quantity Rate Amount
Details of cost of one shutter 220xl08cm = 2.38sqm.
Materials:
7,139 Factory made 35 mm thick shutters sqm 2.38 1618.00 3850.84
with laminated veneer lumber styles
rails as per TADS IS:1995 and panels of
12 mm thick both sides prelaminated
type-I, medium density flat pressed
three layer, graded particle board (FPT-
I) as per IS:3087-1985 bonded with
BWP type synthetic resin adhesive, as
per IS:848-1974

9,999 Carriage of shutters L.S. 29.64 1.00 29.64


595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 0.52 180 93.60
114 Beldar Day 0.6 207 124.20
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 4187.76
Add 1% for water charges 41.88
TOTAL 4229.64
Add for contractor’s profit and 634.45
overheads @15%
Cost of 2.38 sqm. 4864.08
Cost of 1 sqm 2043.73
Say 2043.73

9.6 Providing and fixing 35 mm thick factory made laminated veneer lumber door
shutter conforming to IS : 14616 and TADS 15:2001 (Part B) including ISI marked
black enamelled M.S. butt hinges with necessary screws as per directions of Engineer-
in-charge and panelling with panels of:
9.6.3 12 mm thick one side prelaminated (with particle board decorative lamination on
other sides) and balancing lamination grade - 1 medium density flat pressed, three layer
particle board FPT - I or graded wood particle board FPT-1 conforming to IS :3087
bonded with BWP type synthetic resin adhesive as per IS : 848 and prelamination
conforming to IS : 12823 Grade -1, Type II marked:
Code Description Unit Quantity Rate Amount
Details of cost of one shutter 220xl08cm = 2.38sqm.
Materials:
7,143 Factory made 35 mm thick shutters sqm 2.38 1572.00 3741.36
with laminated veneer lumber styles
rails as per TADS IS:1995 and panels of
12 mm thick one sides prelaminated
type-I, and other side balancing
lamination medium density flat pressed
three layer, graded particle board (FPT-
I) as per IS:3087-1985 bonded with
BWP type synthetic resin adhesive, as 1.00 29.64
9,999 Carriage of shutters
per IS:848-1974 L.S. 29.64
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel
Brightscrews 40
finished mm
or black enameled mild 15.00 1.20
640 100 Nos 8
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 0.52 180 93.60
114 Beldar Day 0.6 207 124.20
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 4078.28
Add 1% for water charges 40.78
TOTAL 4119.06
Add for contractor’s profit and 617.86
overheads @15%
Cost of 2.38 sqm. 4736.92
Cost of 1 sqm 1990.30
Say 1990.30

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.1 Second class teak wood
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
1,190 Teak wood 10 cudm 12.9 410.00 528.90
2,204 Carriage of material (timber) cum 0.0129 60.81 0.78
Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 688.00
Add 1% for water charges 6.88
TOTAL 694.88
Add for contractor’s profit and 104.23
overheads @15%
Cost of 0.67 sqm. 799.12
Cost of 1 sqm 1192.71
Say 1192.71

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.2 kiln seasoned and chemically treated Hollock wood
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
2,505 Hollock wood in planks 10 cudm 12.9 230.00 296.70
2,204 Carriage of material (timber) cum 0.0129 60.81 0.78
2,504 Kiln seasoning of timber cum 0.0129 539.00 6.95
9,999 Chemical treatment L.S. 8.97 1.00 8.97
Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 471.73
Add 1% for water charges 4.72
TOTAL 476.44
Add for contractor’s profit and 71.47
overheads @15%
Cost of 0.66 sqm. 547.91
Cost of 1 sqm 830.17
Say 830.17

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.3 Ply wood 5 ply, 9 mm thick :
9.7.3.1 Decorative plywood both side decorative veneer (Type -1) conforming to IS
1328 BWR
Code Description
type. Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
2480 Ply wood 5 ply with teak ply on both sqm 0.80 693.00 554.40
faces 9m m thick
9,999 Carriage of Plywood L.S. 1.82 1.00 1.82
Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 714.54
Add 1% for water charges 7.15
TOTAL 721.69
Add for contractor’s profit and 108.25
overheads @15%
Cost of 0.67 sqm. 829.94
Cost of 1 sqm 1238.71
Say 1238.71

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.3 Ply wood 5 ply, 9 mm thick :
9.7.3.2 Decorative plywood one side decorative veneer and commercial veneer on other
face (Type 1) conforming to IS 1328 BWR Type
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
2481 Ply wood 5 ply with teak ply on both sqm 0.80 550.00 440.00
faces 9mm thk
9,999 Carriage of Plywood L.S. 1.82 1.00 1.82
Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 600.14
Add 1% for water charges 6.00
TOTAL 606.14
Add for contractor’s profit and 90.92
overheads @15%
Cost of 0.67 sqm. 697.06
Cost of 1 sqm 1040.39
Say 1040.39

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.4 Ply wood 7 ply, 9 mm thick :
9.7.4.1 Decorative plywood one side decorative veneer and commercial veneer on other
face (Type 1) conforming to IS 1328 BWR Type
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
2483 Ply wood 7 ply with teak ply on both sqm 0.80 585.00 468.00
faces 9mm thk
9,999 Carriage of Plywood L.S. 1.82 1.00 1.82
Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 628.14
Add 1% for water charges 6.28
TOTAL 634.42
Add for contractor’s profit and 95.16
overheads @15%
Cost of 0.67 sqm. 729.58
Cost of 1 sqm 1088.93
Say 1088.93

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.5 Particle Board 12 mm thick
9.7.5.1 Plain particle board flat pressed, 3 layer or graded wood particle board medium
density Grade I, IS : 3087 marked.
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
341 Particle board 12mm thick sqm 0.80 258.00 206.40
9,999 Carriage of Plywood L.S. 1.82 1.00 1.82
Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 366.54
Add 1% for water charges 3.67
TOTAL 370.21
Add for contractor’s profit and 55.53
overheads @15%
Cost of 0.67 sqm. 425.74
Cost of 1 sqm 635.43
Say 635.43

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.5 Particle Board 12 mm thick
9.7.5.2 Veneered flat pressed three layer or graded wood particle board with commercial
veneering on both sides conforming to IS:3097, grade I.
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
7468 Veneered particle board with sqm 0.80 418.00 334.40
commercial veneering on both sides
12mm thick

9,999 Carriage of Plywood L.S. 1.82 1.00 1.82


Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 494.54
Add 1% for water charges 4.95
TOTAL 499.49
Add for contractor’s profit and 74.92
overheads @15%
Cost of 0.67 sqm. 574.41
Cost of 1 sqm 857.33
Say 857.33

9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.5 Particle Board 12 mm thick
9.7.5.3 Prelaminated particle board with decorative lamination on one side and
balancing lamination on other side, Grade I, Type II IS: 12823 marked.
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
7477 Prelaminated particle board with one sqm 0.80 595.00 476.00
side decorative and other side
balancing lamination, flat pressed 3
layer & graded (medium density) I, Type
II conforming to IS : 12823 (exterior
grade)12 mm thick

9,999 Carriage of Plywood L.S. 1.82 1.00 1.82


Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 636.14
Add 1% for water charges 6.36
TOTAL 642.50
Add for contractor’s profit and 96.38
overheads @15%
Cost of 0.67 sqm. 738.88
Cost of 1 sqm 1102.80
Say 1102.80
9.7 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (A rea of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 m m to 40 mm thick :
9.7.5 Particle Board 12 mm thick
9.7.5.4 Prelaminated particle board with decorative lamination on both sides, Grade I,
Type Description
Code II, IS: 12823 marked. Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
7480 Prelaminated particle board with both sqm 0.80 625.00 500.00
sides decorative lamination, flat
pressed 3 layer & graded (medium
density) Grade I, Type II conforming to
IS : 12823 (exterior grade)12 m m thick

9,999 Carriage of Plywood L.S. 1.82 1.00 1.82


Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 660.14
Add 1% for water charges 6.60
TOTAL 666.74
Add for contractor’s profit and 100.01
overheads @15%
Cost of 0.67 sqm. 766.75
Cost of 1 sqm 1144.41
Say 1144.41

9.8 Providing and fixing panelling or panelling and glazing in panelled or panelled and
glazed shutters for doors, windows and clerestory windows (area of opening for panel
inserts excluding portion inside grooves or rebates to be measured). Panelling for
panelled or panelled and glazed shutters 25 mm to 40 mm thick. Coir veneer board
(conforming to IS : 14842-2000):
9.8.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
M aterials:
7555 Coir veneered board 12mm thick sqm 0.80 548.00 438.40
9,999 Carriage of Plywood L.S. 1.82 1.00 1.82
Labour:
111 Carpenter Ist Class Day 0.57 270 153.90
9,999 Sundries screws etc. L.S. 4.42 1.00 4.42
TOTAL 598.54
Add 1% for water charges 5.99
TOTAL 604.53
Add for contractor’s profit and 90.68
overheads @15%
Cost of 0.67 sqm. 695.20
Cost of 1 sqm 1037.62
Say 1037.62

9.9 Providing and fixing glazed shutters for doors, windows and clerestory windows
using 4 mm thick float glass panes including black enamelled ISI marked MS butt
hinges with necessary
9.9.1 Second class teakscrews.
wood
9.9.1.1 35 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Teak
1,190 Panelwood
area = 4x45.1x36.55cm = 0.67sqm. 10 cudm 58 410.00 2378.00
2,406 Float glass sheet of nominal thickness 10 cudm 1.27 248.00 314.96
4 mm (weight not less than 10
kg/sqm)

2,204 Carriage of material (timber) cum 0.058 60.81 3.53


595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 3320.71
Add 1% for water charges 33.21
TOTAL 3353.91
Add for contractor’s profit and 503.09
overheads @15%
Cost of 2.16 sqm. 3857.00
Cost of 1 sqm 1785.65
Say 1785.65

9.9 Providing and fixing glazed shutters for doors, windows and clerestory windows
using 4 mm thick float glass panes including black enamelled ISI marked MS butt
hinges with necessary
9.9.1 Second class teakscrews.
wood
9.9.1.1 30 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
1,190 Teak wood 10 cudm 50 410.00 2050.00
2,406 Float glass sheet of nominal thickness 10 cudm 1.27 248.00 314.96
4 mm (weight not less than 10
kg/sqm)

2,204 Carriage of material (timber) cum 0.05 60.81 3.04


595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 2992.22
Add 1% for water charges 29.92
TOTAL 3022.14
Add for contractor’s profit and 453.32
overheads @15%
Cost of 2.16 sqm. 3475.46
Cost of 1 sqm 1609.01
Say 1609.01

9.9 Providing and fixing glazed shutters for doors, windows and clerestory windows
using 4 mm thick float glass panes including black enamelled ISI marked MS butt
hinges withseasoned
9.9.2 Kiln necessary
andscrews.
chemically treated Hollock wood
9.9.2.1 35 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
2,505 Hollock wood in planks 10 cudm 58 230.00 1334.00
2,406 Float glass sheet of nominal thickness 10 cudm 1.27 248.00 314.96
4 mm (weight not less than 10
kg/sqm)

2,204 Carriage of material (timber) cum 0.058 60.81 3.53


2,504 Kiln seasoning of timber cum 0.058 539.00 31.26
9,999 Chemical treatment L.S. 9.1 1.00 9.10
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 2317.07
Add 1% for water charges 23.17
TOTAL 2340.24
Add for contractor’s profit and 351.04
overheads @15%
Cost of 2.16 sqm. 2691.28
Cost of 1 sqm 1245.96
Say 1245.96

9.9 Providing and fixing glazed shutters for doors, windows and clerestory windows
using 4 mm thick float glass panes including black enamelled ISI marked MS butt
hinges withseasoned
9.9.2 Kiln necessary
andscrews.
chemically treated Hollock wood
9.9.2.2 30 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a door with 2/3 rd panelling. ..200x108cm =
2.16sqm. Panel area = 4x45.1x36.55cm = 0.67sqm.
2,505 Hollock wood in planks 10 cudm 50 230.00 1150.00
2,406 Float glass sheet of nominal thickness 10 cudm 1.27 248.00 314.96
4 mm (weight not less than 10
kg/sqm)

2,204 Carriage of material (timber) cum 0.05 60.81 3.04


2,504 Kiln seasoning of timber cum 0.05 539.00 26.95
9,999 Chemical treatment L.S. 9.1 1.00 9.10
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 2128.27
Add 1% for water charges 21.28
TOTAL 2149.55
Add for contractor’s profit and 322.43
overheads @15%
Cost of 2.16 sqm. 2471.99
Cost of 1 sqm 1144.44
Say 1144.44

9.10 Providing and fixing factory made laminated veneer lumber glazed shutter
conforming to IS 14616 and TADS 15:2001 (Part B), using 4mm thick float glass panes
for doors, windows and clerestory windows including ISI marked black enamelled M.S
butt hinges with necessary screws as per directions of Engineer-in-charge
9.10.1 30 mm thick shutters
Code Description Unit Quantity Rate Amount
Details of cost of one shutter 220x108cm = 2.38sqm.
M aterials:
7151 Factory, made shutters glazed sqm 2.38 1290.00 3070.20
laminated veneer lumber door shutter
9999 Carriage of shutters L.S. 29.64 1.00 29.64
Fittings:
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
0640
Labour:
Labour:
156 Carpenter (avg.) Day 0.52 180 93.60
114 Beldar Day 0.6 207 124.20
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 3407.12
Add 1% for water charges 34.07
TOTAL 3441.19
Add for contractor’s profit and 516.18
overheads @15%
Cost of 2.38 sqm. 3957.37
Cost of 1 sqm 1662.76
Say 1662.76

9.11 Extra for providing heavy sheet float glass panes instead of ordinary float glass in
glazed doors, window and clereslory window shutters (Area of opening of glass panes
excluding portion
9.11.1 5.5mm thickinside rebate
instead shallthick.
of 4mm be measured)
Code Description Unit Quantity Rate Amount
Details of cost for one sqm.
Materials:
2407 Glasse Panes of 13.75 kg per sqm. sqm 1.00 340.00 340.00
2406 Deduct panels of 10 kg per sqm. sqm 1.00 248.00 248.00
Net Cost 92.00
Add 1% for water charges 0.92
TOTAL 92.92
Add for contractor’s profit and 13.94
overheads @15%
Cost of 1 sqm 106.86
Say 106.86

9.12 Extra for providing frosted glass panes 4 mm thick instead of ordinary float glass
panes 4 mm thick in doors, windows and clerestory window shutters. (Area of
opening
Code for glass panes excluding portion inside rebateUnit
Description shall be measured).
Quantity Rate Amount
Details of cost for one sqm.
Materials:
7032 Froasted glass panes (4.0mm) sqm 1.00 257.00 257.00
2406 Deduct panels of 10 kg per sqm. sqm 1.00 248.00 248.00
Net Cost 9.00
Add 1% for water charges 0.09
TOTAL 9.09
Add for contractor’s profit and 1.36
overheads @15%
Cost of 1 sqm 10.45
Say 10.45

9. 13 Deduct for providing pin headed glass panes instead of ordinary float glass panes
weighing 4 mm thick in doors, windows and clerestory windows, shutters (Area of
opening for glass panes excluding portion inside rebate shall be measured).
Code Description Unit Quantity Rate Amount
Details of cost for one sqm.
Materials:
7451 Pin headed glass panes (4.0mm) sqm 1.00 160.00 160.00
2406 Deduct panels of 10 kg per sqm. sqm 1.00 248.00 248.00
Net Cost 88.00
Add 1% for water charges 0.88
TOTAL 88.88
Add for contractor’s profit and 13.33
overheads @15%
Cost of 1 sqm 102.21
Say 102.21

9. 14 Extra for providing ISI marked Stainless Steel butt hinges instead of black
enamelled M.S. butt hinges with necessary screws. (Shutter area to be measured).
Code Description Unit Quantity Rate Amount
Details of cost for one door shutter of a door 200xl08cm = 2.16 sqm.
8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00
mm
8218 Stainless steel butt hinges 50x37x1.5 10 Nos 2 90.00 18.00
mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
8214 Stainless steel screws 20 mm 100 Nos 8.00 63.00 5.04
Deduct
595 Bright finished or black enameled mild 10 Nos 6 54.00 -32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 -5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 -14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 -1.20
steel screws 20 mm
TOTAL 155.80
Add 1% for water charges 1.56
TOTAL 157.36
Add for contractor’s profit and 23.60
overheads @15%
Extra cost of 2.16sqm. of shutter area 180.96

Extra cost of 1 sqm. of shutter area 83.78


Say 83.78

9. 15 Deduct if fixed shutters (without hinges) are provided instead of openable shutters
for doors, windows or clerestory windows with :
9.15.1 Stainless steel butt hinges with stainless steel screws:
9.15.1.1 For 2nd class teak wood and other inferior class of wood shutters.
Code Description Unit Quantity Rate Amount
Details of cost for one door shutter of a door 200xl08cm = 2.16 sqm.
8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00
mm
8218 Stainless steel butt hinges 50x37x1.5 10 Nos 2 90.00 18.00
mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
8214 Stainless steel screws 20 mm 100 Nos 8.00 63.00 5.04
TOTAL 209.40
Add 1% for water charges 2.09
TOTAL 211.49
Add for contractor’s profit and 31.72
overheads @15%
Extra cost of 2.16sqm. of shutter area 243.22

Extra cost of 1 sqm. of shutter area 112.60


Say 112.60

9. 15 Deduct if fixed shutters (without hinges) are provided instead of openable shutters
for doors, windows or clerestory windows with :
9.15.2 Black enamelled M.S. butt hinges with necessary screws.
9.15.2.1 For 2nd class teak wood and other inferior class of wood shutters.
Code Description Unit Quantity Rate Amount
Details of cost for one door shutter of a door 200xl08cm = 2.16 sqm.
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
TOTAL 53.60
Add 1% for water charges 0.54
TOTAL 54.14
Add for contractor’s profit and 8.12
overheads @15%
Extra cost of 2.16sqm. of shutter area 62.26

Extra cost of 1 sqm. of shutter area 28.82


Say 28.82

9. 16 Providing and fixing 25 mm thick shutters for cup board etc. :


9.16.1 Panelled or panelled & glazed shutters :
9.16.1.1 Second class teak wood including ISI marked anodised aluminium butt hinges
Description
with necessary
Code screws. Unit Quantity Rate Amount
Details of cost for shutters of a cup-board (half glazed and half panelled) 200x108cm
= 2.16sqm.
Materials:
1,190 Second class teak wood in planks 10 cudm 40 410.00 1640.00
2,204 Carriage of material (timber) cum 0.04 60.81 2.43
2,406 Float glass sheet of nominal thickness 10 cudm 0.99 248.00 245.52
4 mm (weight not less than 10
kg/sqm)

Fittings-
0694 Anodised aluminium butt hinges- 10 Nos 6.00 98.00 58.80
75x45x3.2mm
0586 C.P. brass screws 40mm 100 Nos 48.00 150.00 72.00
Labour:
0111 Carpenter 1st class Day 2.4 270 648.00
119 Glazier Day 0.18 180 32.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 2898.97
Add 1% for water charges 28.99
TOTAL 2927.96
Add for contractor’s profit and 439.19
overheads @15%
Extra cost of 2.16sqm. of shutter area 3367.16

Extra cost of 1 sqm. of shutter area 1558.87


1558.87

9.16 Providing and fixing 25 mm thick shutters for cup board etc. :
9.16.2 Glazed shutters:
9.16.2.1 Second class teak wood including ISI marked anodised aluminium butt hinge
Description
with necessary
Code screws. Unit Quantity Rate Amount
Details of cost for shutters of a cup-board (half glazed and half panelled) 200x108cm
= 2.16sqm.
Materials:
1,190 Second class teak wood in planks 10 cudm 43 410.00 1763.00
2,204 Carriage of material (timber) cum 0.043 60.81 2.61
2,406 Float glass sheet of nominal thickness 10 cudm 1.27 248.00 314.96
4 mm (weight not less than 10
kg/sqm)

Fittings-
0608 Piano hinges 75x45x3.2 mm metre 0.6 21.00 12.60
639 M .S. screws 25 mm 100 Nos 48 15.00 7.20
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 2670.99
Add 1% for water charges 26.71
TOTAL 2697.70
Add for contractor’s profit and 404.66
overheads @15%
Extra cost of 2.16sqm. of shutter area 3102.36

Extra cost of 1 sqm. of shutter area 1436.28


Say 1436.28

9. 17 Providing and fixing flat pressed 3 layer particle board medium density exterior
grade (Grade I) or graded wood particle board IS : 3087 marked to frame, backing or
studding with screws etc. complete (Frames, backing or studding to be paid
separately):
9.17.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 350x200cm = 7sqm.
Materials:
341 Flat pressed 3 layer particle board sqm 7.35 258.00 1896.30
(medium density) Grade I :12 mm thick

9,999 Sundries & screws etc. L.S. 26.91 1.00 26.91


9,999 Carriage of particle board L.S. 13.52 1.00 13.52
Labour:
112 Carpenter IInd class Day 0.9 223 200.70
114 Beldar Day 1 207 207.00
TOTAL 2344.43
Add 1% for water charges 23.44
TOTAL 2367.87
Add for contractor’s profit and 355.18
overheads @15%
Extra cost of 7sqm. of shutter area 2723.06

Extra cost of 1 sqm. of shutter area 389.01


Say 389.01

9. 17 Providing and fixing flat pressed 3 layer particle board medium density exterior
grade (Grade I) or graded wood particle board IS : 3087 marked to frame, backing or
studding with screws etc. complete (Frames, backing or studding to be paid
separately):
9.17.2 18 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 350x200cm = 7sqm.
Materials:
7,055 Flat pressed 3 layer and graded particle sqm 7.35 301.00 2212.35
board (medium density) Grade 1
conform ing to IS : 3087 - 18 mm thick

9,999 Sundries & screws etc. L.S. 26.91 1.00 26.91


9,999 Carriage of particle board L.S. 19.76 1.00 19.76
Labour:
112 Carpenter IInd class Day 0.9 223 200.70
114 Beldar Day 1 207 207.00
TOTAL 2666.72
Add 1% for water charges 26.67
TOTAL 2693.39
Add for contractor’s profit and 404.01
overheads @15%
Extra cost of 7sqm. of shutter area 3097.40

Extra cost of 1 sqm. of shutter area 442.49


Say 442.49

9. 18 Providing and fixing prelaminated flat pressed 3 layer (medium density) particle
board or graded wood particle board IS: 3087 marked with one side decorative and
other side balancing lamination Grade I,Type II exterior grade IS : 12823 marked in
shelves with screws and fittings wherever required, edges to be painted with
polyurethene
9.18.1 18mm primer
thick (fittings to be paid separately).
Code Description Unit Quantity Rate Amount
Details of cost for 4 nos. 75x20cm shelves = 0.60 sqm.
Materials:
7,478 Prelaminated particle board with one sqm 0.63 716.00 451.08
side decorative and other side
balancing lamination, flat pressed 3
layer & graded (medium density) I, Type
II conforming to IS : 12823 (exterior
grade)18 mm thick

9,999 Sundries, Painting edges & Screws L.S. 7.8 1.00 7.80
9,999 Carriage of particle board L.S. 0.91 1.00 0.91
Labour:
112 Carpenter IInd class Day 0.11 223 24.53
114 Beldar Day 0.06 207 12.42
TOTAL 496.74
Add 1% for water charges 4.97
TOTAL 501.71
Add for contractor’s profit and 75.26
overheads @15%
Extra cost of 0.6sqm. of shutter area 576.96

Extra cost of 1 sqm. of shutter area 961.61


Say 961.61

9. 18 Providing and fixing prelaminated flat pressed 3 layer (medium density) particle
board or graded wood particle board IS: 3087 marked with one side decorative and
other side balancing lamination Grade I,Type II exterior grade IS : 12823 marked in
shelves with screws and fittings wherever required, edges to be painted with
polyurethene
9.18.2 25 mmprimer
thick (fittings to be paid separately).
Code Description Unit Quantity Rate Amount
Details of cost for 4 nos. 75x20cm shelves = 0.60 sqm.
Materials:
7,479 Prelaminated particle board with one sqm 0.63 775.00 488.25
side decorative and other side
balancing lamination, flat pressed 3
layer & graded (medium density) I, Type
II conforming to IS : 12823 (exterior
grade)25 mm thick

9,999 Sundries, Painting edges & Screws L.S. 7.8 1.00 7.80
9,999 Carriage of particle board L.S. 1.82 1.00 1.82
Labour:
112 Carpenter IInd class Day 0.11 223 24.53
114 Beldar Day 0.06 207 12.42
TOTAL 534.82
Add 1% for water charges 5.35
TOTAL 540.17
Add for contractor’s profit and 81.03
overheads @15%
Extra cost of 0.6sqm. of shutter area 621.19

Extra cost of 1 sqm. of shutter area 1035.32


Say 1035.32

9.19 Providing and fixing 25 mm thick shutters for cupboards etc. including ISl marked
black enamelled M.S. butt hinges with necessary screws :
9.19.1 Panelled or panelled and glazed shutters
9.19.1.1 Second class teak wood
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a cup board (half panelled and half glazed)
200x108cm
1,190 = wood
Teak 2.16sqm. 10 cudm 40 410.00 1640.00
2,406 Float glass sheet of nominal thickness 10 cudm 0.99 248.00 245.52
4 mm (weight not less than 10
kg/sqm)

2,204 Carriage of material (timber) cum 0.04 60.81 2.43


596 Bright finished or black enameled mild 10 Nos 6 34.00 20.40
steel butt hinges75x47x1.70
638 Bright finished or black enameled mild 100 Nos 48 24.00 11.52
steel screws 30 mm
Labour:
156 Carpenter (avg.) Day 2.4 180 432.00
119 Glazier Day 0.18 180 32.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 2584.09
Add 1% for water charges 25.84
TOTAL 2609.93
Add for contractor’s profit and 391.49
overheads @15%
Cost of 2.16 sqm. 3001.42
Cost of 1 sqm 1389.55
Say 1389.55

9.19 Providing and fixing 25 mm thick shutters for cupboards etc. including ISl marked
black enamelled M.S. butt hinges with necessary screws :
9.19.2 Glazed shutters
9.19.2.1 Second class teak wood
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a cup board (half panelled and half glazed)
200x108cm
1,190 = wood
Teak 2.16sqm. 10 cudm 43 410.00 1763.00
2,406 Float glass sheet of nominal thickness 10 cudm 1.27 248.00 314.96
4 mm (weight not less than 10
kg/sqm)

2,204 Carriage of material (timber) cum 0.043 60.81 2.61


595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries screws etc. L.S. 40.43 1.00 40.43
TOTAL 2704.79
Add 1% for water charges 27.05
TOTAL 2731.84
Add for contractor’s profit and 409.78
overheads @15%
Cost of 2.16 sqm. 3141.62
Cost of 1 sqm 1454.45
Say 1454.45

9.20 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part
I) decorative type, core of block board construction with frame of 1st class hard wood
and well matched teak 3 ply veneering with vertical grains or cross bands and face
veneers on both faces of shutters.
9.20.1 35 mm thick including ISI marked Stainless Steel butt hinges with necessary
screws. Description
Code Unit Quantity Rate Amount
Details of cost for 2.20 sqm.
Materials-
713 35mm thick door shutters sqm 2.2 1100.00 2420.00
9,999 Carriage of door L.S. 29.64 1.00 29.64
8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00
mm
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
Labour-For fixing shutter and fittings
156 Carpenter (avg.) Day 0.55 180 99.00
114 Beldar Day 0.55 207 113.85
TOTAL 2848.85
Add 1% for water charges 28.49
TOTAL 2877.34
Add for contractor’s profit and 431.60
overheads @15%
Cost of 2.2 sqm. 3308.94
Cost of 1 sqm 1504.06
Say 1504.06

9.20 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part
I) decorative type, core of block board construction with frame of 1st class hard wood
and well matched teak 3 ply veneering with vertical grains or cross bands and face
veneers on both faces of shutters.
9.20.2 30 mm thick including ISI marked Stainless Steel butt hinges with
necessaryDescription
Code screws. Unit Quantity Rate Amount
Details of cost for 2.20 sqm.
Materials-
714 30mm thick door shutters sqm 2.2 1050.00 2310.00
9,999 Carriage of door L.S. 29.64 1.00 29.64
8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00
mm
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
Labour-For fixing shutter and fittings
156 Carpenter (avg.) Day 0.55 180 99.00
114 Beldar Day 0.55 207 113.85
TOTAL 2738.85
Add 1% for water charges 27.39
TOTAL 2766.24
Add for contractor’s profit and 414.94
overheads @15%
Cost of 2.2 sqm. 3181.17
Cost of 1 sqm 1445.99
Say 1445.99
9.20 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part
I) decorative type, core of block board construction with frame of 1st class hard wood
and well matched teak 3 ply veneering with vertical grains or cross bands and face
veneers on both faces of shutters.
9.20.3 25 mm thick (for cupboard) including ISI marked nickel plated bright finished
M.S.Piano hinges IS : 3818 marked with necessary screws.
Code Description Unit Quantity Rate Amount
Details of cost for 2.20 sqm.
Materials-
715 25mm thick door shutters sqm 2.2 1000.00 2200.00
9,999 Carriage of door L.S. 29.64 1.00 29.64
0608 Piano hinges 75x45x3.2 mm metre 4.4 21.00 92.40
639 M .S. screws 25 mm 100 Nos 125 15.00 18.75
Labour-For fixing shutter and fittings
156 Carpenter (avg.) Day 0.55 180 99.00
114 Beldar Day 0.55 207 113.85
TOTAL 2553.64
Add 1% for water charges 25.54
TOTAL 2579.18
Add for contractor’s profit and 386.88
overheads @15%
Cost of 2.2 sqm. 2966.05
Cost of 1 sqm 1348.21
Say 1348.21

9.21 Providing and fixing ISI marked flush door shutters conforming to IS: 2202
(Part I) non-decorative type, core of block board construction with frame of 1st class
hard wood and well matched commercial 3 ply veneering with vertical grains or cross
bands and face veneers on both faces of shutters:
9.21.1 35 mm thick including ISI marked Stainless Steel butt hinges with
necessary
Code Description
screws. Unit Quantity Rate Amount
Details of cost for 2.20 sqm.
Materials-
717 35mm thick door shutters sqm 2.2 632.00 1390.40
9,999 Carriage of door L.S. 29.64 1.00 29.64
8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00
mm
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
Labour-For fixing shutter and fittings
156 Carpenter (avg.) Day 0.55 180 99.00
114 Beldar Day 0.55 207 113.85
TOTAL 1819.25
Add 1% for water charges 18.19
TOTAL 1837.44
Add for contractor’s profit and 275.62
overheads @15%
Cost of 2.2 sqm. 2113.06
Cost of 1 sqm 960.48
Say 960.48

9.21 Providing and fixing ISI marked flush door shutters conforming to IS: 2202
(Part I) non-decorative type, core of block board construction with frame of 1st class
hard wood and well matched commercial 3 ply veneering with vertical grains or cross
bands and face veneers on both faces of shutters:
9.21.2 30 mm thick including ISI marked Stainless Steel butt hinges with necessary
screws.
Code Description Unit Quantity Rate Amount
Details of cost for 2.20 sqm.
Materials-
718 30mm thick door shutters sqm 2.2 610.00 1342.00
9,999 Carriage of door L.S. 29.64 1.00 29.64
8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00
mm
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
Labour-For fixing shutter and fittings
156 Carpenter (avg.) Day 0.55 180 99.00
114 Beldar Day 0.55 207 113.85
TOTAL 1770.85
Add 1% for water charges 17.71
TOTAL 1788.56
Add for contractor’s profit and 268.28
overheads @15%
Cost of 2.2 sqm. 2056.84
Cost of 1 sqm 934.93
Say 934.93

9.21 Providing and fixing ISI marked flush door shutters conforming to IS: 2202
(Part I) non-decorative type, core of block board construction with frame of 1st class
hard wood and well matched commercial 3 ply veneering with vertical grains or cross
bands and face veneers on both faces of shutters:
9.21.3 25mm thick (for cupboard) including ISI marked nickel plated bright finished
M.S. piano
Code hinges with necessary screws.
Description Unit Quantity Rate Amount
Details of cost for 2.20 sqm.
Materials-
719 25mm thick door shutters sqm 2.2 600.00 1320.00
9,999 Carriage of door L.S. 29.64 1.00 29.64
0608 Piano hinges 75x45x3.2 mm metre 4.4 21.00 92.40
639 M .S. screws 25 mm 100 Nos 125 15.00 18.75
Labour-For fixing shutter and fittings
156 Carpenter (avg.) Day 0.55 180 99.00
114 Beldar Day 0.55 207 113.85
TOTAL 1673.64
Add 1% for water charges 16.74
TOTAL 1690.38
Add for contractor’s profit and 253.56
overheads @15%
Cost of 2.2 sqm. 1943.93
Cost of 1 sqm 883.61
Say 883.61

9.22 Extra for Providing and fixing flush doors with decorative veneering
9.22.1 On one side in item no. 9.21
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
7307 Extra for providing teak veneering on sqm 1 225.00 225.00
one side instead of commercial
veneering

TOTAL 225.00
Add 1% for water charges 2.25
TOTAL 227.25
Add for contractor’s profit and 34.09
overheads @15%
Cost of 1 sqm 261.34
Say 261.34

9.23 Extra for providing lipping with 2nd class teak wood battens 25 mm minimum
depth on all edges of shutters (over all area of door shutter to be measured) Over item
no. 9.20 and
Code 9.21.
Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
752 Block board construction flush door sqm 1 245.00 245.00
lipping
TOTAL 245.00
Add 1% for water charges 2.45
TOTAL 247.45
Add for contractor’s profit and 37.12
overheads @15%
Cost of 1 sqm 284.57
Say 284.57

9.24 Extra for providing vision panel not exceeding 0.1 sqm in all type of flush doors
(cost of glass excluded) (overall area of door shutter to be measured):
9.24.1 Rectangular or square.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
753 Square vision panel in Bloc k board sqm 1 86.00 86.00
construction flush door s
TOTAL 86.00
Add 1% for water charges 0.86
TOTAL 86.86
Add for contractor’s profit and 13.03
overheads @15%
Cost of 1 sqm 99.89
Say 99.89

9.24 Extra for providing vision panel not exceeding 0.1 sqm in all type of flush doors
(cost of glass excluded) (overall area of door shutter to be measured):
9.24.2 Circular.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
754 Circular vision panel in Block board sqm 1 118.00 118.00
construction flush door
TOTAL 118.00
Add 1% for water charges 1.18
TOTAL 119.18
Add for contractor’s profit and 17.88
overheads @15%
Cost of 1 sqm 137.06
Say 137.06

9.25 Extra if louvers (not exceeding 0.2 sqm) are provided in flush door shutters
(overall area of door shutters to be measured)
9.25.1 Decorative type door.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
755 Decorative type Louvers in Block board sqm 1 210.00 210.00
construction flush door
TOTAL 210.00
Add 1% for water charges 2.10
TOTAL 212.10
Add for contractor’s profit and 31.82
overheads @15%
Cost of 1 sqm 243.92
Say 243.92

9.26 Extra for cutting rebate in flush door shutters (Total area of the shutter to be
Description
measured).
Code Unit Quantity Rate Amount
Details of cost for 1 sqm.
757 Rebate cutting in Block board sqm 1 57.00 57.00
construction flush door 57.00
TOTAL
Add 1% for water charges 0.57
TOTAL 57.57
Add for contractor’s profit and 8.64
overheads @15%
Cost of 1 sqm 66.21
Say 66.21

9.27 Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wire
gauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,
windows and clerestory windows including ISI m arked bright finished or/and black
enamelled M.S. butt hinges with necessary screws:
9.27.1 Second class teak wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
1,190 Teak wood 10 cudm 51.4 410.00 2107.40
7,029 Galvanised wire mes h of average width 10 cudm 1.41 142.00 200.22
of aperture 1.4 mm and nominal dia. of
wire 0.63 mm

2,204 Carriage of material (timber) cum 0.0514 60.81 3.13


595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
0111 Carpenter 1st class Day 1.3 270 351.00
0112 Carpenter 2nd class Day 0.9 223 200.70
114 Beldar Day 1.05 207 217.35
130 Mistry Day 0.105 270 28.35
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 3195.55
Add 1% for water charges 31.96
TOTAL 3227.50
Add for contractor’s profit and 484.13
overheads @15%
Cost of 2.16 sqm. 3711.63
Cost of 1 sqm 1718.35
Say 1718.35

9.27 Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wire
gauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,
windows and clerestory windows including ISI m arked bright finished or/and black
enamelled M.S. butt hinges with necessary screws:
9.27.2 K iln seasoned and chemically treated Hollock wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
2,505 Hollock wood in planks 10 cudm 51.4 230.00 1182.20
2,204 Carriage of material (timber) cum 0.0514 60.81 3.13
2,504 Kiln seasoning of timber cum 0.0514 539.00 27.70
9,999 Chemical treatment L.S. 8.97 1.00 8.97
7,029 Galvanised wire mes h of average width 10 cudm 1.41 142.00 200.22
of aperture 1.4 mm and nominal dia. of
wire 0.63 mm

595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40


steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel
Brightscrews 40 mm
640 finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
0111 Carpenter 1st class Day 1.3 270 351.00
0112 Carpenter 2nd class Day 0.9 223 200.70
114 Beldar Day 1.05 207 217.35
130 Mistry Day 0.105 270 28.35
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 2307.02
Add 1% for water charges 23.07
TOTAL 2330.09
Add for contractor’s profit and 349.51
overheads @15%
Cost of 2.16 sqm. 2679.60
Cost of 1 sqm 1240.56
Say 1240.56

9.28 Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wire
gauze of average width of aperture 1.4mm with wire of dia. 0.63 m m for doors,
windows and clerestory windows including ISI marked stainless steel butt hinges with
necessary screws :
9.28.1 Second class teak wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
1,190 Teak wood 10 cudm 51.4 410.00 2107.40
7,029 Galvanised wire mes h of average width 10 cudm 1.41 142.00 200.22
of aperture 1.4 mm and nominal dia. of
wire 0.63 mm

2,204 Carriage of material (timber) cum 0.0514 60.81 3.13


8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00
mm
8218 Stainless steel butt hinges 50x37x1.5 10 Nos 2 90.00 18.00
mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
8214 Stainless steel screws 20 mm 100 Nos 8.00 63.00 5.04
Labour:
0111 Carpenter 1st class Day 1.3 270 351.00
0112 Carpenter 2nd class Day 0.9 223 200.70
114 Beldar Day 1.05 207 217.35
130 Mistry Day 0.105 270 28.35
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 3351.35
Add 1% for water charges 33.51
TOTAL 3384.86
Add for contractor’s profit and 507.73
overheads @15%
Cost of 2.16 sqm. 3892.59
Cost of 1 sqm 1802.12
Say 1802.12

9.28 Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wire
gauze of average width of aperture 1.4mm with wire of dia. 0.63 m m for doors,
windows and clerestory windows including ISI marked stainless steel butt hinges with
necessary screws :
9.28.2 Kiln seasoned and chemically treated Hollock wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
2,505 Hollock wood in planks 10 cudm 51.4 230.00 1182.20
2,204 Carriage of material (timber) cum 0.0514 60.81 3.13
2,504 Kiln seasoning of timber cum 0.0514 539.00 27.70
9,999 Chemical treatment L.S. 8.97 1.00 8.97
7,029 Galvanised wire mes h of average width 10 cudm 1.41 142.00 200.22
of aperture 1.4 mm and nominal dia. of
wire 0.63 mm

8220 stainless steel butt hinges-100x60x2.5 10 Nos 6.00 185.00 111.00


mm
8218 Stainless steel butt hinges 50x37x1.5 10 Nos 2 90.00 18.00
mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36
8214 Stainless steel screws 20 mm 100 Nos 8.00 63.00 5.04
Labour:
0111 Carpenter 1st class Day 1.3 270 351.00
0112 Carpenter 2nd class Day 0.9 223 200.70
114 Beldar Day 1.05 207 217.35
130 Mistry Day 0.105 270 28.35
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 2462.82
Add 1% for water charges 24.63
TOTAL 2487.45
Add for contractor’s profit and 373.12
overheads @15%
Cost of 2.16 sqm. 2860.57
Cost of 1 sqm 1324.34
Say 1324.34

9.29 Providing and fixing 30mm thick wire gauge shutters using galvanised M.S. wire
gauge of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,
windows and clerestory windows including ISI marked Stainless Steel butt
windows and clerestory windows including ISI marked Stainless Steel butt hinges
9.29.1 Second class
with necessary teak
screws : wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
1,190 Teak wood 10 cudm 44 410.00 1804.00
7,029 Galvanised wire mes h of average width 10 cudm 1.41 142.00 200.22
of aperture 1.4 mm and nominal dia. of
wire 0.63 mm

2,204 Carriage of material (timber) cum 0.044 60.81 2.68


8221 Stainless steel butt hinges (heavy 10 Nos 6.00 155.00 93.00
weight) 75x50x2.5 mm IS : 12817
marked

8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36


Labour:
0111 Carpenter 1st class Day 1.2 270 324.00
0112 Carpenter 2nd class Day 0.8 223 178.40
114 Beldar Day 0.95 207 196.65
130 Mistry Day 0.08 270 21.60
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 2929.71
Add 1% for water charges 29.30
TOTAL 2959.00
Add for contractor’s profit and 443.85
overheads @15%
Cost of 2.16 sqm. 3402.85
Cost of 1 sqm 1575.39
Say 1575.39

9.29 Providing and fixing 30mm thick wire gauge shutters using galvanised M.S. wire
gauge of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,
windows and clerestory windows including ISI marked Stainless Steel butt
windows and clerestory windows including ISI marked Stainless Steel butt hinges
with necessary screws :
9.29.2 Kiln seasoned and chemically treated Hollock wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
2,505 Hollock wood in planks 10 cudm 44 230.00 1012.00
2,204 Carriage of material (timber) cum 0.044 60.81 2.68
2,504 Kiln seasoning of timber cum 0.044 539.00 23.72
9,999 Chemical treatment L.S. 8.97 1.00 8.97
7,029 Galvanised wire mes h of average width 10 cudm 1.41 142.00 200.22
of aperture 1.4 mm and nominal dia. of
wire 0.63 mm

8221 Stainless steel butt hinges (heavy 10 Nos 6.00 155.00 93.00
weight) 75x50x2.5 mm IS : 12817
marked

8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36


Labour:
0111 Carpenter 1st class Day 1.2 270 324.00
0112 Carpenter 2nd class Day 0.8 223 178.40
114 Beldar Day 0.95 207 196.65
130 Mistry Day 0.08 270 21.60
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 2170.39
Add 1% for water charges 21.70
TOTAL 2192.10
Add for contractor’s profit and 328.81
overheads @15%
Cost of 2.16 sqm. 2520.91
Cost of 1 sqm 1167.09
Say 1167.09

9.30 Providing and fixing 30mm thick wire gauze shutters using galvanised M.S. wire
gauze of average width of aperture 1.4mm with wire of dia 0.63 mm for doors,
windows and clerestory windows including ISl marked bright finished or /and black
enamelled M.S. butt hinges with necessary screws :
9.30.1 Second class teak wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
1,190 Teak wood 10 cudm 44 410.00 1804.00
7,029 Galvanised wire mes h of average 10 cudm 1.41 142.00 200.22
width of aperture 1.4 mm and nominal
dia. of wire 0.63 mm
2,204 Carriage of material (timber) cum 0.044 60.81 2.68
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm
637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
0111 Carpenter 1st class Day 1.2 270 324.00
0112 Carpenter 2nd class Day 0.8 223 178.40
114 Beldar Day 1 207 207.00
130 Mistry Day 0.1 270 27.00
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 2830.70
Add 1% for water charges 28.31
TOTAL 2859.00
Add for contractor’s profit and 428.85
overheads @15%
Cost of 2.16 sqm. 3287.85
Cost of 1 sqm 1522.15
Say 1522.15

9.30 Providing and fixing 30mm thick wire gauze shutters using galvanised M.S. wire
gauze of average width of aperture 1.4mm with wire of dia 0.63 mm for doors,
windows and clerestory windows including ISl marked bright finished or /and black
enamelled M.S. butt hinges with necessary screws :
9.30.2 Kiln seasoned and chemically treated Hollock wood.
Code Description Unit Quantity Rate Amount
D etails of cost for door shutters 2.00x1.08m = 2.16 sqm.
M aterials-
2,505 Hollock wood in planks 10 cudm 44 230.00 1012.00
2,204 Carriage of material (timber) cum 0.044 60.81 2.68
2,504 Kiln seasoning of timber cum 0.044 539.00 23.72
9,999 Chemical treatment L.S. 9.1 1.00 9.10
7,029 Galvanised wire mes h of average 10 cudm 1.41 142.00 200.22
width of aperture 1.4 mm and nominal
dia. of wire 0.63 mm 54.00 32.40
595 Bright finished or black enameled mild 10 Nos 6
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
0111 Carpenter 1st class Day 1.2 270 324.00
0112 Carpenter 2nd class Day 0.8 223 178.40
114 Beldar Day 1 207 207.00
130 Mistry Day 0.1 270 27.00
9,999 Sundries screws etc. L.S. 33.8 1.00 33.80
TOTAL 2071.51
Add 1% for water charges 20.72
TOTAL 2092.23
Add for contractor’s profit and 313.83
overheads @15%
Cost of 2.16 sqm. 2406.06
Cost of 1 sqm 1113.92
Say 1113.92

9.31 Providing and fixing wire gauze laminated veneer lumber shutters conforming to
IS :14616, and as per TADS 15 :2001 (Part B) using galvanised wire gauze with
average width of aperture 1.4mm in both directions with wire of dia 0.63mm as per IS :
1568 for doors, windows and clerestory windows including ISI marked bright finished
or/ and black enamelled M.S. butt hinges with necessary screws as per directions of
9.31.1 35 mm thick shutters
Engineer-in-charge:
Code Description Unit Quantity Rate Amount
Details of cost of one shutter 220xl08cm = 2.38sqm.
Materials:
7,154 Factory made 35 mm thick shutters L.S. 2.38 1328.00 3160.64
with laminated veneer lumber styles
rails as per TAD S IS:1995 and panels of
galvanised wire gauge with average
width of aperture 1.4 mm on both
directions with wire of dia .63mm

9,999 Carriage of shutters L.S. 29.64 1.00 29.64


Fittings
:
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
640 steel
Brightscrews 40
finished mm
or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 0.52 180 93.60
114 Beldar Day 0.6 207 124.20
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 3497.56
Add 1% for water charges 34.98
TOTAL 3532.54
Add for contractor’s profit and 529.88
overheads @15%
Cost of 2.38 sqm. 4062.42
Cost of 1 sqm 1706.90
Say 1706.90
9.31 Providing and fixing wire gauze laminated veneer lumber shutters conforming to
IS :14616, and as per TADS 15 :2001 (Part B) using galvanised wire gauze with
average width of aperture 1.4mm in both directions with wire of dia 0.63mm as per IS :
1568 for doors, windows and clerestory windows including ISI marked bright finished
or/ and black enamelled M.S. butt hinges with necessary screws as per directions of
9.31.2 30 mm thick shutters
Engineer-in-charge:
Code Description Unit Quantity Rate Amount
Details of cost of one shutter 220xl08cm = 2.38sqm.
Materials:
7,155 Factory made 30 mm thick shutters L.S. 2.38 1150.00 2737.00
with laminated veneer lumber styles
rails as per TAD S IS:1995 and panels of
galvanised wire gauge with average
width of aperture 1.4 mm on both
directions with wire of dia .63mm

9,999 Carriage of shutters L.S. 29.64 1.00 29.64


Fittings :
595 Bright finished or black enameled mild 10 Nos 6 54.00 32.40
steel butt hinges 100x58x1.90 mm

597 Bright finished or black enameled mild 10 Nos 2 28.00 5.60


steel butt hinges50x37x1.50 mm

637 Bright finished or black enameled mild 100 Nos 48 30.00 14.40
steel screws 40 mm
640 Bright finished or black enameled mild 100 Nos 8 15.00 1.20
steel screws 20 mm
Labour:
156 Carpenter (avg.) Day 0.52 180 93.60
114 Beldar Day 0.6 207 124.20
9,999 Sundries screws etc. L.S. 35.88 1.00 35.88
TOTAL 3073.92

Add 1% for water charges 30.74


TOTAL 3104.66
Add for contractor’s profit and 465.70
overheads @15%
Cost of 2.38 sqm. 3570.36
Cost of 1 sqm 1500.15
Say 1500.15

9.32 Providing 50x50x50mm 2nd class teak wood plugs including cutting brick work
and fixing in cement mortar 1:3 (1 cement: 3 fine sand) and making good the walls etc.
Code Description Unit Quantity Rate Amount
Details of cost for 100 Nos.
Material
s:
1,189 Teak wood 10 cudm 14 394.00 551.60
2,204 Carriage of material (timber) cum 0.014 60.81 0.85
Cement mortar 1:3(1 cement: 3 fine cum 0.002 3268.90 6.54
sand)
Labour:
0112 Carpenter 2nd class Day 0.75 180 135.00
114 Beldar Day 0.75 207 155.25
124 Mason (brick layer) 2nd class Day 0.75 223 167.25
TOTAL 1016.49
Add 1% for water charges 10.16
TOTAL 1026.65
Add for contractor’s profit and 154.00
overheads @15%
Cost of 100 Nos. 1180.65
Cost of 1 No. 11.81
Say 11.81

9.33 Providing and fixing expandable fasteners of specified size with necessary plastic
sleeves and galvanised M.S. screws including drilling holes in masonry work/CC/
R.C.C. andmm
9.33.1 25 making
long good etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 Nos.
Materials:
7,312 Expandable fastener with plastic sleeve each 10 6.00 60.00
and M.S. screws. 25 mm long

9,999 Labour for drilling holes and making L.S. 20.8 1.00 20.80
good etc.
TOTAL 80.80
Add 1% for water charges 0.81
TOTAL 81.61
Add for contractor’s profit and 12.24
overheads @15%
Cost of 10 Nos. 93.85
Cost of 1 No. 9.38
Say 9.38

9.33 Providing and fixing expandable fasteners of specified size with necessary plastic
sleeves and galvanised M.S. screws including drilling holes in masonry work/CC/
R.C.C.
9.33.2 and making
32 mm long good etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 Nos.
Material
s:
7,313 Expandable fastener with plastic sleeve each 10 7.00 70.00
and M.S. screws. 32 mm long

9,999 Labour for drilling holes and making L.S. 26 1.00 26.00
good etc.
TOTAL 96.00
Add 1% for water charges 0.96
TOTAL 96.96
Add for contractor’s profit and 14.54
overheads @15%
Cost of 10 Nos. 111.50
Cost of 1 No. 11.15
Say 11.15

9.33 Providing and fixing expandable fasteners of specified size with necessary plastic
sleeves and galvanised M.S. screws including drilling holes in masonry work/CC/
R.C.C.
9.33.3 and making
40 mm long good etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 Nos.
Materials:
7,314 Expandable fastener with plastic sleeve each 10 9.00 90.00
and M.S. screws. 40 mm long

9,999 Labour for drilling holes and making L.S. 26 1.00 26.00
good etc.
TOTAL 116.00
Add 1% for water charges 1.16
TOTAL 117.16
Add for contractor’s profit and 17.57
overheads @15%
Cost of 10 Nos. 134.73
Cost of 1 No. 13.47
Say 13.47

9.33 Providing and fixing expandable fasteners of specified size with necessary plastic
sleeves and galvanised M.S. screws including drilling holes in masonry work/CC/
R.C.C. andmm
9.33.4 50 making
long good etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 Nos.
Material
s:
7,315 Expandable fastener with plastic sleeve each 10 11.00 110.00
and M.S. screws. 50 mm long

9,999 Labour for drilling holes and making L.S. 26 1.00 26.00
good etc.
TOTAL 136.00
Add 1% for water charges 1.36
TOTAL 137.36
Add for contractor’s profit and 20.60
overheads @15%
Cost of 10 Nos. 157.96
Cost of 1 No. 15.80
Say 15.80

9.34 Providing and fixing 2nd class teak wood plain lining tongued and grooved on and
including wooden plugs complete with necessary screws and prim ing coat on
unexposed surface.
9.34.1 40 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
1,190 Teak wood 10 cudm 440 410.00 18040.00
1,238 Extra for selected planks of first class 10 cudm 440 80.00 3520.00
teakwood
2,204 Carriage of material (timber) cum 0.44 60.81 26.76
Second class teak w ood plugs each 55 11.81 649.36
including cutting brick work and fixing
in cement mortar 1:3 (1 cement: 3 fine
sand) (A) (Rate as per item no 9.32 of
SH: 9)

(B) Priming coat (Rate as per item no sqm 10 26.54 265.39


13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 2.15 270 580.50
114 Beldar Day 1.62 207 335.34
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
TOTAL 23471.17
Add 1% for water charges except 225.56
(A+B)
TOTAL 23696.73
Add for contractor’s profit and 3417.30
overheads @15% except (A+B)
Cost of 10 sqm. 27114.03
Cost of 1 sqm 2711.40
Say 2711.40

9.34 Providing and fixing 2nd class teak wood plain lining tongued and grooved on and
including wooden plugs complete with necessary screws and prim ing coat on
unexposed surface.
9.34.2 25 mm thick.
9.34 Providing and fixing 2nd class teak wood plain lining tongued and grooved on and
including wooden plugs complete with necessary screws and prim ing coat on
unexposed surface.
9.34.1 40 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
1,190 Teak wood 10 cudm 275 410.00 11275.00
1,238 Extra for selected planks of first class 10 cudm 275 80.00 2200.00
teakwood
2,204 Carriage of material (timber) cum 0.275 60.81 16.72
Second class teak w ood plugs each 55 11.81 649.36
including cutting brick work and fixing
in cement mortar 1:3 (1 cement: 3 fine
sand) (A) (Rate as per item no 9.32 of
SH: 9)

(B) Priming coat (Rate as per item no sqm 10 26.54 265.39


13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 2.15 270 580.50
114 Beldar Day 1.62 207 335.34
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
TOTAL 15376.13
Add 1% for water charges except 144.61
(A+B)
TOTAL 15520.75
Add for contractor’s profit and 2190.90
overheads @15% except (A+B)
Cost of 10 sqm. 17711.65
Cost of 1 sqm 1771.16
Say 1771.16

9.34 Providing and fixing 2nd class teak wood plain lining tongued and grooved on and
including wooden plugs complete with necessary screws and prim ing coat on
unexposed surface.
9.34.3 20 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
1,190 Teak wood 10 cudm 220 410.00 9020.00
1,231 Extra for selected planks of second 10 cudm 220 72.00 1584.00
class teakwood
2,204 Carriage of material (timber) cum 0.22 60.81 13.38
Second class teak w ood plugs each 55 11.81 649.36
including cutting brick work and fixing
in cement mortar 1:3 (1 cement: 3 fine
sand) (A) (Rate as per item no 9.32 of
SH: 9)

(B) Priming coat (Rate as per item no sqm 10 26.54 265.39


13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 1.08 270 291.60
0112 Carpenter 2nd class Day 0.8 223 178.40
114 Beldar Day 1.08 207 223.56
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
TOTAL 12279.51
Add 1% for water charges except 113.65
(A+B)
TOTAL 12393.16
Add for contractor’s profit and 1721.76
overheads @15% except (A+B)
Cost of 10 sqm. 14114.92
Cost of 1 sqm 1411.49
Say 1411.49

9.34 Providing and fixing 2nd class teak wood plain lining tongued and grooved on and
including wooden plugs complete with necessary screws and prim ing coat on
unexposed surface.
9.34.4 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
1,190 Teak wood 10 cudm 132 410.00 5412.00
1,231 Extra for selected planks of second 10 cudm 132 72.00 950.40
class teakwood
2,204 Carriage of material (timber) cum 0.132 60.81 8.03
Second class teak w ood plugs each 55 11.81 649.36
including cutting brick work and fixing
in cement mortar 1:3 (1 cement: 3 fine
sand) (A) (Rate as per item no 9.32 of
SH: 9)

(B) Priming coat (Rate as per item no sqm 10 26.54 265.39


13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 1.08 270 291.60
0112 Carpenter 2nd class Day 0.8 223 178.40
114 Beldar Day 1.08 207 223.56
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
TOTAL 8032.56
Add 1% for water charges except 71.18
(A+B)
TOTAL 8103.73
Add for contractor’s profit and 1078.35
overheads @15% except (A+B)
Cost of 10 sqm. 9182.08
Cost of 1 sqm 918.21
Say 918.21

9.35 Providing and fixing in wall lining flat pressed three layer (medium density)
particle board or graded wood prelaminated one side decorative lamination on other
side balancing lamination Grade I,Type II, IS : 12823 marked including priming coat on
unexposed surface, with necessary fixing arrangement and screws etc. complete:
9.35.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Material
s-
7477 Particle board (three layer medium densi sqm 11 595.00 6545.00
7048 Raw l plug 50 mm (designation 10 no) each 55 7.00 385.00
9,999 Sundries screws etc. L.S. 26.91 1.00 26.91
9,999 Carriage of particle board L.S. 13.52 1.00 13.52
Priming coat
(B) Priming coat (Rate as per item no sqm 10 26.54 265.39
13.50.1)
Labour: For planning and fixing
0112 Carpenter 2nd class Day 1.28 223 285.44
114 Beldar Day 1.43 207 296.01
TOTAL 7817.27
Add 1% for water charges except 75.52
(A+B)
TOTAL 7892.79
Add for contractor’s profit and 1144.11
overheads @15% except (A+B)
Cost of 10 sqm. 9036.90
Cost of 1 sqm 903.69
Say 903.69

9.35 Providing and fixing in wall lining flat pressed three layer (medium density)
particle board or graded wood prelaminated one side decorative lamination on other
side balancing lamination Grade I,Type II, IS : 12823 marked including priming coat on
unexposed
9.35.2 18 mmsurface,
thickwith necessary fixing arrangement and screws etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Material
s-
7478 Particle board (three layer medium densi sqm 11 716.00 7876.00
7048 Raw l plug 50 mm (designation 10 no) each 55 7.00 385.00
9,999 Sundries screws etc. L.S. 26.91 1.00 26.91
9,999 Carriage of particle board L.S. 13.52 1.00 13.52
Priming coat
(B) Priming coat (Rate as per item no sqm 10 26.54 265.39
13.50.1)
Labour: For planning and fixing
0112 Carpenter 2nd class Day 1.28 223 285.44
114 Beldar Day 1.43 207 296.01
TOTAL 9148.27
Add 1% for water charges except 88.83
(A+B)
TOTAL 9237.10
Add for contractor’s profit and 1345.76
overheads @15% except (A+B)
Cost of 10 sqm. 10582.86
Cost of 1 sqm 1058.29
Say 1058.29

9.35 Providing and fixing in wall lining flat pressed three layer (medium density)
particle board or graded wood prelaminated one side decorative lamination on other
side balancing lamination Grade I,Type II, IS : 12823 marked including priming coat on
unexposed
9.35.3 25 mmsurface,
thick with necessary fixing arrangement and screws etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Material
s-
7479 Particle board (three layer medium densi sqm 11 775.00 8525.00
7048 Raw l plug 50 mm (designation 10 no) each 55 7.00 385.00
9,999 Sundries screws etc. L.S. 26.91 1.00 26.91
9,999 Carriage of particle board L.S. 13.52 1.00 13.52
Priming coat
(B) Priming coat (Rate as per item no sqm 10 26.54 265.39
13.50.1)
Labour: For planning and fixing
0112 Carpenter 2nd class Day 1.28 223 285.44
114 Beldar Day 1.43 207 296.01
TOTAL 9797.27
Add 1% for water charges except 95.32
(A+B)
TOTAL 9892.59
Add for contractor’s profit and 1444.08
overheads @15% except (A+B)
Cost of 10 sqm. 11336.67
Cost of 1 sqm 1133.67
Say 1133.67

9.36 Providing and fixing specified wood frame work consisting of battens 50x25mm
fixed with rawl plug and drilling necessary holes for rawl plug etc. including priming
coat complete.
9.36.1 Hollock wood
Code Description Unit Quantity Rate Amount
Details of cost for 5 no. battens of size 500cmx50mmx25mm (31.25 cudm)
Materials-
2,505 Hollock wood in planks 10 cudm 33 230.00 759.00
2,204 Carriage of material (timber) cum 0.033 60.81 2.01
7048 Raw l plug 50 mm (designation 10 no) each 55 7.00 385.00
Labour:
111 Carpenter Ist class Day 1 270 270.00
114 Beldar Day 0.25 207 51.75
9,999 Labour for drilling holes steel tape L.S. 71.5 1.00 71.50
9,999 Sundries screws etc. L.S. 6.76 1.00 6.76
(B) Priming coat (Rate as per item no sqm 3.75 26.54 99.52
13.50.1)
TOTAL 1645.54
Add 1% for water charges except B 15.46

TOTAL 1661.00
Add for contractor’s profit and 234.22
overheads @15%
Cost of 31.25 except B
cudm 1895.22
Cost of 1 cum 60647.04
Say 60647.04

9.37 Providing and fixing decorative plywood 4 mm thick one side decorative veneer
conforming to IS: 1328 (type-1) for plain lining / cladding with necessary screws,
priming coat on unexposed
9.37.1 Decorative surface
veneer facings ofwith:
approved manufacture.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials-
759 teak ply wood sqm 12 250.00 3000
9,999 Carriage of ply wood L.S. 5.46 1.00 5.46
Wooden plugs including cutting brick each 55 11.81 649.36
work and fixing in cement mortar (B)
(Rate as per item no 9.32 of SH : Wood
work)

Labour-
111 Carpenter Ist class Day 3.8 270 1026.00
114 Beldar Day 4.6 207 952.20
130 Mistry Day 0.6 270 162.00
9,999 20mm nails without head for fixing L.S. 53.82 1.00 53.82
ply
(B) Priming coat (Rate as per item no sqm 10 26.54 265.39
13.50.1)
TOTAL 6114.23
Add 1% for water charges except 51.99
(A+B)
TOTAL 6166.22
Add for contractor’s profit and 787.72
overheads
Cost of 10 @15%
sqm. except (A+B) 6953.95
Cost of 1 sqm 695.39
Say 695.39

9.38 Providing and fixing 4mm thick coir veneer board, ISI marked IS : 14842 Plain
lining with necessary screws, priming coat on unexposed surface etc., complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials-
7552 Coir veneered board 4mm thick sqm 12 235.00 2820
9,999 Carriage of ply wood L.S. 5.46 1.00 5.46
Wooden plugs including cutting brick each 55 11.81 649.36
work and fixing in cement mortar (B)
(Rate as per item no 9.32 of SH : Wood
work)

Labour-
111 Carpenter Ist class Day 3.8 270 1026.00
114 Beldar Day 4.6 207 952.20
130 Mistry Day 0.6 270 162.00
9,999 20mm nails without head for fixing L.S. 53.82 1.00 53.82
ply
(B) Priming coat (Rate as per item no sqm 10 26.54 265.39
13.50.1)
TOTAL 5934.23
Add 1% for water charges except 50.19
(A+B)
TOTAL 5984.42
Add for contractor’s profit and 760.45
overheads @15% except (A+B)
Cost of 10 sqm. 6744.88
Cost of 1 sqm 674.49

9.39 Providing and fixing skirting of prelaminated with (one side decorative and
other side balancing lamination) flat pressed, 3 layer or graded particle board (medium
density) Grade I, Type II, IS : 12823 marked, with necessary fixing arrangements and
screws including drilling necessary holes for rawl plugs etc. and priming coat on
unexposed
9.39.1 18 mmsurface
thickcomplete :
Code Description Unit Quantity Rate Amount
Details of cost for skirting 200mm wide and 30m long Area = 0.2x30= 6 sqm.
Materials-
7,478 Particle board 18 m m thick sqm 6.6 716.00 4725.60
9,999 Carriage of particle board L.S. 8.11 1.00 8.11
7048 Raw l plug 50 mm (designation 10 no) each 102 7.00 714.00
Labour: For dressing and fixing particle board to skirting
112 Carpenter IIndst class Day 0.77 223 171.71
114 Beldar Day 0.86 207 178.02
9,999 Labour for drilling holes steel tape L.S. 130 1.00 130.00
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
(B) Priming coat (Rate as per item no sqm 6 26.54 159.23
13.50.1)
TOTAL 6140.49
Add 1% for water charges except B 59.81

TOTAL 6200.31
Add for contractor’s profit and 906.16
overheads @15% except B
Cost of 6 sqm 7106.47
Cost of 1 sqm 1184.41
Say 1184.41

9.39 Providing and fixing skirting of prelaminated with (one side decorative and
other side balancing lamination) flat pressed, 3 layer or graded particle board (medium
density) Grade I, Type II, IS : 12823 marked, with necessary fixing arrangements and
screws including drilling necessary holes for rawl plugs etc. and priming coat on
unexposed
9.39.2 25 mmsurface
thickcomplete :
Code Description Unit Quantity Rate Amount
Details of cost for skirting 200mm wide and 30m long Area = 0.2x30= 6 sqm.
Materials-
7,479 Particle board 25 m m thick sqm 6.6 775.00 5115.00
9,999 Carriage of particle board L.S. 8.11 1.00 8.11
7048 Raw l plug 50 mm (designation 10 no) each 102 7.00 714.00
Labour: For dressing and fixing particle board to skirting
112 Carpenter IIndst class Day 0.77 223 171.71
114 Beldar Day 0.86 207 178.02
9,999 Labour for drilling holes steel tape L.S. 130 1.00 130.00
9,999 Sundries screws etc. L.S. 53.82 1.00 53.82
(B) Priming coat (Rate as per item no sqm 6 26.54 159.23
13.50.1)
TOTAL 6529.89
Add 1% for water charges except B 63.71

TOTAL 6593.60
Add for contractor’s profit and 965.15
overheads @15% except B
Cost of 6 sqm 7558.76

Cost of 1 sqm 1259.79


Say 1259.79

9.40 Providing and fixing wooden moulded beading to door and window frames with
iron screws, plugs and priming coat on unexposed surface etc. complete :
9.40.1 2nd class teak wood
9.40.1.1 50x12 mm
Code Description Unit Quantity Rate Amount
Details of cost for beading for a window of size 140x110cm i.e. 500cm long (5
metre)
1,190 Teak wood 10 cudm 3.3 410.00 135.30
637 Iron screws 40 mm 100 Nos 36 30.00 10.80
2,204 Carriage of material (timber) cum 0.0033 60.81 0.20
(B) Priming coat (Rate as per item no sqm 0.37 26.54 9.82
13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 0.53 270 143.10
TOTAL 299.22
Add 1% for water charges except B 2.89

TOTAL 302.11
Add for contractor’s profit and 43.84
overheads @15% except B
Cost of 5 m 345.96
Cost of 1 m 69.19
Say 69.19

9.40 Providing and fixing wooden moulded beading to door and window frames with
iron screws, plugs and priming coat on unexposed surface etc. complete :
9.40.1 2nd class teak wood
9.40.1.2 50x20 mm
Code Description Unit Quantity Rate Amount
Details of cost for beading for a window of size 140x110cm i.e. 500cm long (5
metre)
1,190 Teak wood 10 cudm 5.5 410.00 225.50
637 Iron screws 40 mm 100 Nos 36 30.00 10.80
2,204 Carriage of material (timber) cum 0.0055 60.81 0.33
(B) Priming coat (Rate as per item no sqm 0.45 26.54 11.94
13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 0.53 270 143.10
TOTAL 391.68
Add 1% for water charges except B 3.80

TOTAL 395.47
Add for contractor’s profit and 57.53
overheads @15% except B
Cost of 5 m 453.00
Cost of 1 m 90.60
Say 90.60

9.40 Providing and fixing wooden moulded beading to door and window frames with
iron screws, plugs and priming coat on unexposed surface etc. complete :
9.40.2 Hollock wood
9.40.2.1 50x12 mm
Code Description Unit Quantity Rate Amount
Details of cost for beading for a window of size 140x110cm i.e. 500cm long (5
metre)
2,505 Hollock wood in planks 10 cudm 3.3 230.00 75.90
637 Iron screws 40 mm 100 Nos 36 30.00 10.80
2,204 Carriage of material (timber) cum 0.0033 60.81 0.20
(B) Priming coat (Rate as per item no sqm 0.37 26.54 9.82
13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 0.53 270 143.10
TOTAL 239.82
Add 1% for water charges except B 2.30

TOTAL 242.12
Add for contractor’s profit and 34.85
overheads @15% except B
Cost of 5 m 276.97
Cost of 1 m 55.39
Say 55.39

9.40 Providing and fixing wooden moulded beading to door and window frames with
iron screws, plugs and priming coat on unexposed surface etc. complete :
9.40.2 Hollock wood
9.40.2.2 50x20 mm
Code Description Unit Quantity Rate Amount
Details of cost for beading for a window of size 140x110cm i.e. 500cm long (5
metre)
2,505 Hollock wood in planks 10 cudm 5.5 230.00 126.50
637 Iron screws 40 mm 100 Nos 36 30.00 10.80
2,204 Carriage of material (timber) cum 0.0055 60.81 0.33
(B) Priming coat (Rate as per item no sqm 0.45 26.54 11.94
13.50.1)
Labour: For planning and fixing
0111 Carpenter 1st class Day 0.53 270 143.10
TOTAL 292.68
Add 1% for water charges except B 2.81

TOTAL 295.48
Add for contractor’s profit and 42.53
overheads @15% except B
Cost of 5 m 338.02
Cost of 1 m 67.60
Say 67.60

9.41 Providing and fixing plain jaffri of 35x10 mm laths placed 35 mm apart (frames to
be paid separately) including fixing 50x12 mm beading complete with :
9.41.1 Second class teak wood.
Code Description Unit Quantity Rate Amount
Details of cost of a jaffri 200x110cm = 2.2sqm.
1,190 Teak wood 10 cudm 32 410.00 1312.00
2,204 Carriage of material (timber) cum 0.032 60.81 1.95
Labour: For planning and fixing
0111 Carpenter 1st class Day 0.75 270 202.50
0112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 0.5 207 103.50
130 Mistry Day 0.1 270 27.00
9,999 Sundies L.S. 33.8 1.00 33.80
TOTAL 1903.75
Add 1% for water charges 19.04
TOTAL 1922.78
Add for contractor’s profit and 288.42
overheads @15% except B
Cost of 2.2 sqm 2211.20
Cost of 1 sqm 1005.09
Say 1005.09

9.42 Providing and fixing 18 mm thick, 150 mm wide pelmet of flat pressed 3 layer or
graded wood particle board medium density grade I, IS : 3087 marked including top
cover of 6 mm commercial ply wood conforming to IS: 303 BWR grade, nickel plated
M.S. pipe 20 mm dia ( heavy type ) curtain rod with nickel plated brackets including
fixing with 25x3 mm M.S. flat 10 cm long and rawl plugs 50 mm long (designation 10
Code
no.) etc allDescription
complete Unit Quantity Rate Amount
Details of cost for a pelmet 2m long
Materials-
7055 18mm thick particle board (medium densi sqm 0.32 301.00 96.32
2412 Ply wood 5 ply with commercial ply on b sqm 0.27 282.00 76.14
7034 Nickle plated M .S. pipe 20 mm dia. metre 1.65 54.00 89.10
7035 Nickle plated M.S. Brackets for curtain each 2 3.00 6.00
9,999 Carriage of material L.S. 0.52 1.00 0.52
9,999 M.S. flat 25x3mm and 10cm long over L.S. 8.06 1.00 8.06
brackets
7048 Rawl plug 50 mm (designation 10 no) each 2 7.00 14.00
Labour-
0112 Carpenter 2nd class Day 0.18 223 40.14
114 Beldar Day 0.18 207 37.26
130 Mistry Day 0.11 270 29.70
9,999 Sundies L.S. 2.73 1.00 2.73
TOTAL 399.97
Add 1% for water charges 4.00
TOTAL 403.97
Add for contractor’s profit and 60.60
overheads @15% except B
Cost of 2 m 464.57
Cost of 1 m 232.28
Say 232.28

9.43 Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI
marked IS : 14842 - 2000, including top cover of 6 mm coir veneer board, nickel plated
M.S. Pipe 20 mm dia (heavy type) curtain rod with nickel plated brackets including
fixing
Code with 25x3 mm M.S. Flat 10 cm long and rawl plug
Description Unit50 mm long (designation
Quantity Rate Amount10
No.) etc., all complete
Details of cost for a pelmet 2m long
Materials-
7556 Coir veneered board 18mm thick sqm 0.32 820.00 262.40
7553 Coir veneered board 6mm thick sqm 0.27 308.00 83.16
7034 Nickle plated M .S. pipe 20 mm dia. metre 1.65 54.00 89.10
7035 Nickle plated M.S. Brackets for curtain each 2 3.00 6.00
9,999 Carriage of material L.S. 0.52 1.00 0.52
9,999 M.S. flat 25x3mm and 10cm long over L.S. 8.06 1.00 8.06
brackets
7048 Rawl plug 50 mm (designation 10 no) each 2 7.00 14.00
Labour-
0112 Carpenter 2nd class Day 0.18 223 40.14
114 Beldar Day 0.18 207 37.26
130 Mistry Day 0.11 270 29.70
9,999 Sundies L.S. 2.73 1.00 2.73
TOTAL 573.07
Add 1% for water charges 5.73
TOTAL 578.80
Add for contractor’s profit and 86.82
overheads @15% except B
Cost of 2 m 665.62
Cost of 1 m 332.81
Say 332.81

9.44 Extra for using veneered particle board conforming to IS 3097 Grade I, in item of
pelmet 18mm
9.44.1 Non thick 150mm
decorative veneerwide.
on both sides.
Code Description Unit Quantity Rate Amount
Details of cost for a pelmet 2m long
Materials-
347 Extra cost for c ommercial veneering bot sqm 0.32 102.00 32.64
TOTAL 32.64
Add 1% for water charges 0.33
TOTAL 32.97
Add for contractor’s profit and 4.94
overheads @15% except B
Cost of 2 m 37.91
Cost of 1 m 18.96
Say 18.96

9.44 Extra for using veneered particle board conforming to IS 3097 Grade I, in item of
pelmet 18mm thick
9.44.2 Particle board150mm wide. veneering on both sides.
with decorative
Code Description Unit Quantity Rate Amount
Details of cost for a pelmet 2m long
Materials-
348 Extra cost for prelaminated particle sqm 0.32 366.00 117.12
board with teak finish both sides
TOTAL 117.12
Add 1% for water charges 1.17
TOTAL 118.29
Add for contractor’s profit and 17.74
overheads @15% except B
Cost of 2 m 136.03
Cost of 1 m 68.02
Say 68.02

9.45 Providing and fixing teak wood lipping of size 25x3 mm in pelmet.
Code Description Unit Quantity Rate Amount
Details of cost for a pelmet 10m long
Materials-
7049 Lipping with teak wood 25x3 mm metre 10 16.00 160.00
Labour-
0112 Carpenter 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
TOTAL 267.50
Add 1% for water charges 2.68
TOTAL 270.18
Add for contractor’s profit and 40.53
overheads @15% except B
Cost of 10 m 310.70
Cost of 1 m 31.07
Say 31.07

9.46 Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,
with two chromium plated brass brackets fixed with C.P. brass screws and wooden
plugs,
9.46.1 etc.,
12 mm wherever
dia. necessary complete :
Code Description Unit Quantity Rate Amount
Details of cost for 2m long
Materials-
590 C.P. brass curtain rod 12 mm dia metre 2 122.00 244.00
7023 C.P. brass brackets each 2 5.00 10.00
9,999 Carriage of material L.S. 4.03 1.00 4.03
9,999 M.S. flat 25x3mm and 10cm long over L.S. 1.56 1.00 1.56
brackets
(B) (Rate as per item no 9.32 of SH : Woo each 2 11.81 23.61
Labour-
9,999 Labour L.S. 2.73 1.00 2.73
9,999 Sundies L.S. 1.56 1.00 1.56
TOTAL 287.49
Add 1% for water charges except B 2.64

TOTAL 290.13
Add for contractor’s profit and 39.98
overheads @15% except B
Cost of 2 m 330.11
Cost of 1 m 165.05
Say 165.05

9.46 Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,
with two chromium plated brass brackets fixed with C.P. brass screws and wooden
plugs,
9.46.2 etc.,
20 mm wherever
dia. necessary complete :
Code Description Unit Quantity Rate Amount
Details of cost for 2m long
Materials-
591 C.P. brass curtain rod 20 mm dia metre 2 143.00 286.00
7023 C.P. brass brackets each 2 5.00 10.00
9,999 Carriage of material L.S. 4.03 1.00 4.03
9,999 M.S. flat 25x3mm and 10cm long over L.S. 1.56 1.00 1.56
brackets
(B) (Rate as per item no 9.32 of SH : Woo each 2 11.81 23.61
Labour-
9,999 Labour L.S. 2.73 1.00 2.73
9,999 Sundies L.S. 1.56 1.00 1.56
TOTAL 329.49
Add 1% for water charges except B 3.06

TOTAL 332.55
Add for contractor’s profit and 46.34
overheads @15% except B
Cost of 2 m 378.89
Cost of 1 m 189.45
Say 189.45

9.46 Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,
with two chromium plated brass brackets fixed with C.P. brass screws and wooden
plugs, etc., wherever necessary complete :
9.46.3 25 mm dia.
Code Description Unit Quantity Rate Amount
Details of cost for 2m long
Materials-
592 C.P. brass curtain rod 25 mm dia metre 2 239.00 478.00
7023 C.P. brass brackets each 2 5.00 10.00
9,999 Carriage of material L.S. 4.03 1.00 4.03
9,999 M.S. flat 25x3mm and 10cm long over L.S. 1.56 1.00 1.56
brackets
(B) (Rate as per item no 9.32 of SH : Woo each 2 11.81 23.61
Labour-
9,999 Labour L.S. 2.73 1.00 2.73
9,999 Sundies L.S. 1.56 1.00 1.56
TOTAL 521.49
Add 1% for water charges except B 4.98
TOTAL 526.47
Add for contractor’s profit and 75.43
overheads @15% except B
Cost of 2 m 601.90
Cost of 1 m 300.95
Say 300.95
299.3
9.47 Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated
brackets:
9.47.1 20 mm dia (heavy type)
Code Description Unit Quantity Rate Amount
Details of cost for a pelmet 2m long
Materials-
7042 Nickel plated M.S. pipe 20 mm dia metre 2 44.00 88.00
7035 Nickle plated M.S. Brackets for curtain each 2 3.00 6.00
9,999 Carriage of material L.S. 1.56 1.00 1.56
9,999 Screws L.S. 4.03 1.00 4.03
7048 Rawl plug 50 mm (designation 10 no) each 2 7.00 14.00
Labour-
9,999 Labour including fixing rawl plug L.S. 5.2 1.00 5.20
9,999 Sundies L.S. 1.56 1.00 1.56
TOTAL 120.35
Add 1% for water charges 1.20
TOTAL 121.55
Add for contractor’s profit and 18.23
overheads @15% except B
Cost of 2 m 139.79
Cost of 1 m 69.89
Say 69.89

9.47 Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated
brackets:
9.47.2 25 mm dia (heavy type)
Code Description Unit Quantity Rate Amount
Details of cost for a pelmet 2m long
Materials-
7043 Nickel plated M.S. pipe 25 mm dia metre 2 49.00 98.00
7036 Nickle plated M.S. Brackets for curtain each 2 4.00 8.00
9,999 Carriage of material L.S. 1.56 1.00 1.56
9,999 Screws L.S. 4.03 1.00 4.03
7048 Rawl plug 50 mm (designation 10 no) each 2 7.00 14.00
Labour-
9,999 Labour including fixing rawl plug L.S. 5.2 1.00 5.20
9,999 Sundies L.S. 1.56 1.00 1.56
TOTAL 132.35
Add 1% for water charges 1.32
TOTAL 133.67
Add for contractor’s profit and 20.05
overheads @15% except B
Cost of 2 m 153.72
Cost of 1 m 76.86
Say 76.86

9.48 Providing and fixing M.S. grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. all complete.
9.48.1 Fixed to steel windows by welding.
Code Description Unit Quantity Rate Amount
Details of cost for a grill 90x120cm =1.08sq =18.54 kg
Material-
1003 M.S.bar quintal 0.165 4300.00 709.50
1008 M.S. flat quintal 0.04 4600.00 184.00
2205 Carriage of steel tonne 0.02 47.29 0.95
9,999 Sundries L.S. 26.91 1.00 26.91
9,999 Welding charges L.S. 19.76 1.00 19.76
Labour-
102 Blacksmith 1st class Day 0.86 270 232.20
114 Beldar Day 1.1 207 227.70
TOTAL 1401.02
Add 1% for water charges 14.01
TOTAL 1415.03
Add for contractor’s profit and 212.25
overheads @15% except B
Cost of 18.54 kg 1627.28
Cost of 1 kg 87.77
Say 87.77

9.48 Providing and fixing M.S. grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. all complete.
9.48.2 Fixed to openings /wooden frames with rawl plugs screws etc.
Code Description Unit Quantity Rate Amount
Details of cost for a grill 90x120cm =1.08sq =18.54 kg
Material-
1003 M.S.bar quintal 0.165 4300.00 709.50
1008 M.S. flat quintal 0.04 4600.00 184.00
2205 Carriage of steel tonne 0.02 47.29 0.95
9,999 Sundries L.S. 26.91 1.00 26.91
9,999 Welding charges L.S. 19.76 1.00 19.76
Labour-
102 Blacksmith 1st class Day 0.86 270 232.20
114 Beldar Day 1.1 207 227.70
7048 Rawl plug 50 mm (designation 10 no) each 8 7.00 56.00
9,999 Fixing rawl plug L.S. 26 1.00 26.00
TOTAL 1483.02
Add 1% for water charges 14.83
TOTAL 1497.85
Add for contractor’s profit and 224.68
overheads @15% except B
Cost of 18.54 kg 1722.52
Cost of 1 kg 92.91
Say 92.91

9.49 Providing and fixing expanded metal 20x60mm strands 3.25mm wide and 1.6mm
thick for windows etc. including 62x19mm beading of Ilnd class teak wood.
Code Description Unit Quantity Rate Amount
Details of cost for a window of size 140x110cm =1.54sqm .
1,190 Teak wood 10 cudm 6 410.00 246.00
2,204 Carriage of material (timber) cum 0.006 60.81 0.36
1,015 Expended metal -20x60mm mesh sqm 1.69 250.00 422.50
3.2mm wide
9,999 Carriage L.S. 1.82 1.00 1.82
Labour: For planning and fixing
112 Carpenter 2nd class Day 0.33 223 73.59
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 26.91 1.00 26.91
TOTAL 822.93
Add 1% for water charges 8.23
TOTAL 831.16
Add for contractor’s profit and 124.67
overheads @15%
Cost of 1.54 sqm 955.84
Cost of 1 sqm 620.67
Say 620.67

9.50 Providing and fixing hard drawn steel wire fabric 75x25 mm mesh of weight not
less than 7.75 Kg per sqm to window frames etc. including 62x19 mm beading of
second
Code class teak wood.
Description Unit Quantity Rate Amount
Details of cost for a window of size 140x110cm =1.54sqm .
1,190 Teak wood 10 cudm 6 410.00 246.00
2,204 Carriage of material (timber) cum 0.006 60.81 0.36
1,021 Hard drawn steel wire fabric sqm 1.69 350.00 591.50
9,999 Carriage L.S. 1.82 1.00 1.82
Labour: For planning and fixing
112 Carpenter 2nd class Day 0.33 223 73.59
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 19.76 1.00 19.76
TOTAL 984.78
Add 1% for water charges 9.85
TOTAL 994.63
Add for contractor’s profit and 149.19
overheads @15%
Cost of 1.54 sqm 1143.83
Cost of 1 sqm 742.75
Say 742.75

9.51 Providing and fixing fly proof galvanised M.S. wire gauge to windows and
clerestory windows using galvanised M.S. wire gauge with average width of aperture
1.4 mmWith
9.51.1 in both
2nddirections
class teakwith
woodwire of dia.62X19
beading 0.63 mm.
mm.
Code Description Unit Quantity Rate Amount
Details of cost for a window of size 140x110cm =1.54sqm .
1,190 Teak wood 10 cudm 6 410.00 246.00
2,204 Carriage of material (timber) cum 0.006 60.81 0.36
7,029 Wire gauge sqm 1.69 142.00 239.98
9,999 Carriage L.S. 1.82 1.00 1.82
Labour: For planning and fixing
112 Carpenter 2nd class Day 0.33 223 73.59
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 19.76 1.00 19.76
TOTAL 633.26
Add 1% for water charges 6.33
TOTAL 639.60
Add for contractor’s profit and 95.94
overheads @15%
Cost of 1.54 sqm 735.54
Cost of 1 sqm 477.62
Say 477.62

9.51 Providing and fixing fly proof galvanised M.S. wire gauge to windows and
clerestory windows using galvanised M.S. wire gauge with average width of aperture
1.4 mmWith
9.51.2 in both directions
12 mm withUwire
mild steel of dia. 0.63 mm.
beading.
Code Description Unit Quantity Rate Amount
Details of cost for a window of size 140x110cm =1.54sqm .
7,349 12 mm mild steel U beading metre 5 9.00 45.00
7,029 Wire gauge sqm 1.69 142.00 239.98
9,999 Carriage L.S. 1.82 1.00 1.82
Labour: For planning and fixing
112 Carpenter 2nd class Day 0.33 223 73.59
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 19.76 1.00 19.76
TOTAL 431.90
Add 1% for water charges 4.32
TOTAL 436.22
Add for contractor’s profit and 65.43
overheads @15%
Cost of 1.54 sqm 501.65
Cost of 1 sqm 325.75
Say 325.75

9.52 Deduct for fixing 75x25 mm hard drawn steel wire fabric of weight not less than
7.75 Kg. per sqm in panelled and glazed door and window shutter instead of glass
sheet
Code 4 mm thick.
Description Unit Quantity Rate Amount
Details of cost for 1 sqm .
1,021 Hard drawn steel wire fabric sqm 1 350.00 350.00
2,406 Glass 10 kg/sqm (4 mm) sqm 1 248.00 248.00
Difference of cost 102.00
Add 1% for water charges 1.02
TOTAL 103.02
Add for contractor’s profit and 15.45
overheads @15%
Cost of 1 sqm 118.47
Say 118.47

9.53 Providing 40x5 mm flat iron hold fast 40 cm long including fixing to frame with
10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block
30x10 x 15cm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm
nominal
Code
size)
Description Unit Quantity Rate Amount
Details of cost for 1 hold fast
Material
s-
1008 M.S. flat quintal 0.0067 4600.00 30.82
9999 Carriage of steel L.S. 1.82 1.00 1.82
9,999 Bolts and nuts L.S. 5.46 1.00 5.46
(A) Cement concrete 1:3:6 (Rate as per cum 0.005 3828.42 19.14
item no 4.2.5)
Labour-
103 Blacksmith 2nd class Day 0.03 223 6.69
123 Mason ist class Day 0.03 270 8.10
114 Beldar Day 0.03 207 6.21
TOTAL 78.24
Add 1% for water charges except A 0.59

TOTAL 78.83
Add for contractor’s profit and 8.95
overheads @15% except A
Cost of 1 hold fast 87.79
Say 87.79

9.54 Providing beams including hoisting, fixing in position and applying wood
preservative for the unexposed surfaces, etc. complete with :
9.54.1 Sal wood.
Code Description Unit Quantity Rate Amount
Details of cost for a beam
Material
s-
1,199 Sal wood 10 cudm 207.1 218.00 4514.78
2,204 Carriage of material (timber) cum 0.207 60.81 12.59
(A) Priming coat (wood preservative) sqm 0.54 14.71 7.94
(Rate as per item no 13.57.1)

9,999 Sundries L.S. 26.91 1.00 26.91


Labour-
100 Bandhani Day 0.7 180 126.00
112 Carpenter 2nd class Day 0.7 223 156.10
114 Beldar Day 1.45 207 300.15
TOTAL 5144.47
Add 1% for water charges except A 51.37

TOTAL 5195.84
Add for contractor’s profit and 778.18
overheads @15% except A
Cost of 203 cudm 5974.02
cost of 1 cum 29428.67
Say 29428.67

9.54 Providing beams including hoisting, fixing in position and applying wood
preservative for the unexposed surfaces, etc. complete with :
9.54.2 Hollock wood.
Code Description Unit Quantity Rate Amount
Details of cost for a beam
Material
s-
2,466 Hollock wood 10 cudm 207.1 217.00 4494.07
2,204 Carriage of material (timber) cum 0.207 60.81 12.59
(A) Priming coat (wood preservative) sqm 0.54 14.71 7.94
(Rate as per item no 13.57.1)

9,999 Sundries L.S. 26.91 1.00 26.91


Labour-
100 Bandhani Day 0.7 180 126.00
112 Carpenter 2nd class Day 0.7 223 156.10
114 Beldar Day 1.45 207 300.15
TOTAL 5123.76
Add 1% for water charges except A 51.16

TOTAL 5174.92
Add for contractor’s profit and 775.05
overheads @15% except A
Cost of 203 cudm 5949.96
cost of 1 cum 29310.17
Say 29310.17

9.55 Providing and fixing ISI marked M.S. pressed butt hinges bright finished with
necessary screws etc.mm
9.55.1 125x65x2.12 complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
594 Butt hinges 125x65x2.12 mm 10 Nos. 10 78.00 78.00
635 Iron screws 50 mm 100 Nos. 80 40.00 32.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 162.58
Add 1% for water charges 1.63
TOTAL 164.21
Add for contractor’s profit and 24.63
overheads @15%
Cost of 10 hinges 188.84
cost of 1 hinges 18.88
Say 18.88

9.55 Providing and fixing ISI marked M.S. pressed butt hinges bright finished with
necessary screws etc.mm
9.55.2 100x58x1.90 complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
595 Butt hinges 100x58x1.90 mm 10 Nos. 10 54.00 54.00
637 Iron screws 40 mm 100 Nos. 80 30.00 24.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 130.58
Add 1% for water charges 1.31
TOTAL 131.89
Add for contractor’s profit and 19.78
overheads @15%
Cost of 10 hinges 151.67
cost of 1 hinges 15.17
Say 15.17
9.55 Providing and fixing ISI marked M.S. pressed butt hinges bright finished with
necessary screws etc.
9.55.3 75x47x1.70 mm complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
596 Butt hinges 75x47x1.70 mm 10 Nos. 10 34.00 34.00
638 Iron screws 30 mm 100 Nos. 60 24.00 14.40
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 100.07
Add 1% for water charges 1.00
TOTAL 101.07
Add for contractor’s profit and 15.16
overheads @15%
Cost of 10 hinges 116.23
cost of 1 hinges 11.62
Say 11.62

9.55 Providing and fixing ISI marked M.S. pressed butt hinges bright finished with
necessary screws etc.
9.55.4 50x37x1.50 mm complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
597 Butt hinges 50x37x1.50 mm 10 Nos. 10 28.00 28.00
640 Iron screws 20 mm 100 Nos. 40 15.00 6.00
9,999 Carriage of material cum 0.91 1.00 0.91
Labour-
112 Carpenter 2nd class Day 0.08 223 17.84
TOTAL 52.75
Add 1% for water charges 0.53
TOTAL 53.28
Add for contractor’s profit and 7.99
overheads @15%
Cost of 10 hinges 61.27

cost of 1 hinges 6.13


Say 6.13

9.56 Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with
necessary screws etc.mm
9.56.1 125x90x4.00 complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
8,222 M.S. heavy weight but hinges 10 Nos. 10 256.00 256.00
125x90x4.0mm
635 Iron screws 50 mm 100 Nos. 80 40.00 32.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 340.58
Add 1% for water charges 3.41
TOTAL 343.99
Add for contractor’s profit and 51.60
overheads @15%
Cost of 10 hinges 395.58
cost of 1 hinges 39.56
Say 39.56

9.56 Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with
necessary screws etc.mm
9.56.2 100x75x3.50 complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
8,223 M.S. heavy weight but hinges 10 Nos. 10 133.00 133.00
100x75x3.50 mm
637 Iron screws 40 mm 100 Nos. 80 30.00 24.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 209.58
Add 1% for water charges 2.10
TOTAL 211.68
Add for contractor’s profit and 31.75
overheads @15%
Cost of 10 hinges 243.43
cost of 1 hinges 24.34
Say 24.34

9.56 Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with
necessary screws etc.
9.56.3 75x60x3.10 mm complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
8,224 M.S. heavy weight but hinges 10 Nos. 10 67.00 67.00
75x60x3.10 mm
638 Iron screws 30 mm 100 Nos. 60 24.00 14.40
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 133.07
Add 1% for water charges 1.33

TOTAL 134.40
Add for contractor’s profit and 20.16
overheads @15%
Cost of 10 hinges 154.56
cost of 1 hinges 15.46
Say 15.46

9.56 Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with
necessary screws etc.
9.56.4 50x40x2.50 mm complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
8,225 M.S. heavy weight butt hinges 10 Nos. 10 52.00 52.00
50x40x2.5 mm
640 Iron screws 20 mm 100 Nos. 40 15.00 6.00
9,999 Carriage of material cum 0.91 1.00 0.91
Labour-
112 Carpenter 2nd class Day 0.08 223 17.84
TOTAL 76.75
Add 1% for water charges 0.77
TOTAL 77.52
Add for contractor’s profit and 11.63
overheads @15%
Cost of 10 hinges 89.15
cost of 1 hinges 8.91
Say 8.91

9.57 Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary
screws etc. complete.mm
9.57.1 125x65x2.12
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
642 M.S. butt hinges (oxidised) 10 Nos. 10 92.00 92.00
125x65x2.12 mm
682 Iron screws (oxidised) 50 mm 100 Nos. 80 40.00 32.00
9,999 Carriage of material cum 3.64 1.00 3.64
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 177.49
Add 1% for water charges 1.77
TOTAL 179.26
Add for contractor’s profit and 26.89
overheads @15%
Cost of 10 hinges 206.15
cost of 1 hinges 20.62
Say 20.62

9.57 Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary
screws etc. complete.mm
9.57.2 100x58x1.90
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
643 M.S. butt hinges (oxidised) 10 Nos. 10 53.00 53.00
100x58x1.90 mm
683 Iron screws (oxidised) 40 mm 100 Nos. 80 35.00 28.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 133.58
Add 1% for water charges 1.34
TOTAL 134.92
Add for contractor’s profit and 20.24
overheads @15%
Cost of 10 hinges 155.15
cost of 1 hinges 15.52
Say 15.52

9.57 Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary
screws etc. complete.
9.57.3 75x47x1.70 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
644 M.S. butt hinges (oxidised) 75x47x1.70 10 Nos. 10 32.00 32.00
mm
684 Iron screws (oxidised) 30 mm 100 Nos. 60 24.00 14.40
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 98.07
Add 1% for water charges 0.98
TOTAL 99.05
Add for contractor’s profit and 14.86
overheads @15%
Cost of 10 hinges 113.91
cost of 1 hinges 11.39
Say 11.39

9.57 Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary
screws etc. complete.
9.57.4 50x37x1.50 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
645 M.S. butt hinges (oxidised) 50x37x1.50 10 Nos. 10 27.00 27.00
mm
686 Iron screws (oxidised) 20 mm 100 Nos. 40 15.00 6.00
9,999 Carriage of material cum 0.91 1.00 0.91
Labour-
112 Carpenter 2nd class Day 0.08 223 17.84
TOTAL 51.75
Add 1% for water charges 0.52
TOTAL 52.27
Add for contractor’s profit and 7.84
overheads @15%
Cost of 10 hinges 60.11
cost of 1 hinges 6.01
Say 6.01

9.58 Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges with
necessary screws etc. complete
9.58.1 150x125x27x2.80 mm :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
646 M.S. parliamentary hinges (oxidised) 10 Nos. 10 255.00 255.00
150x125x27x2.80 mm
683 Iron screws (oxidised) 40 mm 100 Nos. 80 35.00 28.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 345.93
Add 1% for water charges 3.46
TOTAL 349.39
Add for contractor’s profit and 52.41
overheads @15%
Cost of 10 hinges 401.80
cost of 1 hinges 40.18
Say 40.18

9.58 Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges with
necessary screws etc. complete
9.58.2 125x125x27x2.80 mm :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
647 M.S. parliamentary hinges (oxidised) 10 Nos. 10 205.00 205.00
125x125x27x2.80 mm
683 Iron screws (oxidised) 40 mm 100 Nos. 80 35.00 28.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 295.93
Add 1% for water charges 2.96
TOTAL 298.89
Add for contractor’s profit and 44.83
overheads @15%
Cost of 10 hinges 343.72
cost of 1 hinges 34.37
Say 34.37

9.58 Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges with
necessary screws etc. complete
9.58.3 100x125x27x2.80 mm :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
648 M.S. parliamentary hinges (oxidised) 10 Nos. 10 165.00 165.00
100x125x27x2.80 mm
683 Iron screws (oxidised) 40 mm 100 Nos. 80 35.00 28.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 255.93
Add 1% for water charges 2.56
TOTAL 258.49
Add for contractor’s profit and 38.77
overheads @15%
Cost of 10 hinges 297.26
cost of 1 hinges 29.73
Say 29.73

9.58 Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges with
necessary screws etc. complete
9.58.4 75x100x20x2.24 mm :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
649 M.S. parliamentary hinges (oxidised) 10 Nos. 10 122.00 122.00
75x100x20x2.24 mm
684 Iron screws (oxidised) 30 mm 100 Nos. 60 24.00 14.40
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 199.33
Add 1% for water charges 1.99
TOTAL 201.32
Add for contractor’s profit and 30.20
overheads @15%
Cost of 10 hinges 231.52
cost of 1 hinges 23.15
Say 23.15

9.59 Providing and fixing ISI marked oxidised M.S. single acting spring hinges with
necessary
9.59.1 150screws
mm etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
650 M.S. single acting spring hinges each 10 71.00 710.00
(oxidised)
682 Iron screws (oxidised) 50 mm 100 Nos. 80 40.00 32.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.4 223 89.20
114 Beldar Day 0.2 207 41.40
TOTAL 875.33
Add 1% for water charges 8.75
TOTAL 884.08
Add for contractor’s profit and 132.61
overheads @15%
Cost of 10 hinges 1016.70
cost of 1 hinges 101.67
Say 101.67

9.59 Providing and fixing ISI marked oxidised M.S. single acting spring hinges with
necessary
9.59.2 125screws
mm etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
651 M.S. single acting spring hinges each 10 66.00 660.00
(oxidised)
682 Iron screws (oxidised) 50 mm 100 Nos. 80 40.00 32.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.4 223 89.20
114 Beldar Day 0.2 207 41.40
TOTAL 825.33
Add 1% for water charges 8.25
TOTAL 833.58
Add for contractor’s profit and 125.04
overheads @15%
Cost of 10 hinges 958.62
cost of 1 hinges 95.86
Say 95.86

9.59 Providing and fixing ISI marked oxidised M.S. single acting spring hinges with
necessary
9.59.3 100screws
mm etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
652 M.S. single acting spring hinges each 10 51.00 510.00
(oxidised)
683 Iron screws (oxidised) 40 mm 100 Nos. 80 35.00 28.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.4 223 89.20
114 Beldar Day 0.2 207 41.40
TOTAL 671.33
Add 1% for water charges 6.71
TOTAL 678.04
Add for contractor’s profit and 101.71
overheads @15%
Cost of 10 hinges 779.75
cost of 1 hinges 77.97
Say 77.97

9.60 Providing and fixing oxidised M.S. double acting spring hinges with necessary
screws etc. mm
9.60.1 150 complete.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
653 M.S. double acting spring hinges each 10 73.00 730.00
(oxidised)
682 Iron screws (oxidised) 50 mm 100 Nos. 80 40.00 32.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.4 223 89.20
114 Beldar Day 0.2 207 41.40
TOTAL 895.33
Add 1% for water charges 8.95
TOTAL 904.28
Add for contractor’s profit and 135.64
overheads @15%
Cost of 10 hinges 1039.93
cost of 1 hinges 103.99
Say 103.99

9.60 Providing and fixing oxidised M.S. double acting spring hinges with necessary
screws etc. mm
9.60.2 125 complete.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
654 M.S. double acting spring hinges each 10 63.00 630.00
(oxidised)
682 Iron screws (oxidised) 50 mm 100 Nos. 80 40.00 32.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.4 223 89.20
114 Beldar Day 0.2 207 41.40
TOTAL 795.33
Add 1% for water charges 7.95
TOTAL 803.28
Add for contractor’s profit and 120.49
overheads @15%
Cost of 10 hinges 923.78
cost of 1 hinges 92.38
Say 92.38

9.60 Providing and fixing oxidised M.S. double acting spring hinges with necessary
screws etc. mm
9.60.3 100 complete.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Material
s-
655 M.S. double acting spring hinges each 10 47.00 470.00
(oxidised)
683 Iron screws (oxidised) 40 mm 100 Nos. 80 35.00 28.00
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.4 223 89.20
114 Beldar Day 0.2 207 41.40
TOTAL 631.33
Add 1% for water charges 6.31
TOTAL 637.64
Add for contractor’s profit and 95.65
overheads @15%
Cost of 10 hinges 733.29
cost of 1 hinges 73.33
Say 73.33

9.61 Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating and
fixing with necessary screws etc., complete.
9.61.1 Overall width 35 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 metre
Material
s-
656 M.S. piano hinges (oxidised) 35 mm w metre 1 24.00 24.00
ide
686 Iron screws (oxidised) 20 mm 100 Nos. 30 15.00 4.50
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 80.17
Add 1% for water charges 0.80
TOTAL 80.97
Add for contractor’s profit and 12.15
overheads @15%
Cost of 1 metre 93.12
Say 93.12
9.61 Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating and
fixing with necessary screws etc., com plete.
9.61.2 Overall width 50 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 metre
Material
s-
7,485 M.S. piano hinges (oxidised) 50 mm w metre 1 29.00 29.00
ide
686 Iron screws (oxidised) 20 mm 100 Nos. 30 15.00 4.50
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 85.17
Add 1% for water charges 0.85
TOTAL 86.02
Add for contractor’s profit and 12.90
overheads @15%
Cost of 1 metre 98.92
Say 98.92

9.61 Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating and
fixing with necessary screws etc., com plete.
9.61.3 Overall width 65 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 metre
Material
s-
7,486 M.S. piano hinges (oxidised) 65 mm w metre 1 34.00 34.00
ide
686 Iron screws (oxidised) 20 mm 100 Nos. 30 15.00 4.50
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 90.17
Add 1% for water charges 0.90
TOTAL 91.07
Add for contractor’s profit and 13.66
overheads @15%
Cost of 1 metre 104.73
Say 104.73

9.62 Providing and fixing ISI m arked oxidised M.S.sliding door bolts with nuts and
screws etc. complete
9.62.1 300x16 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
660 M.S. ‘sliding door bolts (oxidised) each 10 45.00 450.00
300x16 mm
7,040 Iron screws (oxidised) 35 mm 100 Nos. 120 28.00 33.60
641 Bolts and nuts 50x6 mm each 40 4.00 160.00
9,999 Carriage of material cum 6.37 1.00 6.37
Labour-
112 Carpenter 2nd class Day 0.25 223 55.75
TOTAL 705.72
Add 1% for water charges 7.06
TOTAL 712.78
Add for contractor’s profit and 106.92
overheads @15%
Cost of 10 door bolts 819.69
cost of 1 door bolt 81.97
Say 81.97

9.62 Providing and fixing ISI m arked oxidised M.S.sliding door bolts with nuts and
screws
9.62.2 etc. complete
250x16 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
661 M.S. ‘sliding door bolts (oxidised) each 10 37.00 370.00
250x16 mm
7,040 Iron screws (oxidised) 35 mm 100 Nos. 100 28.00 28.00
641 Bolts and nuts 50x6 mm each 40 4.00 160.00
9,999 Carriage of material cum 6.37 1.00 6.37

Labour-
112 Carpenter 2nd class Day 0.25 223 55.75
TOTAL 620.12
Add 1% for water charges 6.20
TOTAL 626.32
Add for contractor’s profit and 93.95
overheads @15%
Cost of 10 door bolts 720.27
cost of 1 door bolt 72.03
Say 72.03

9.63 Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel
type) with necessary screws etc. complete :
9.63.1 250x10 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
664 M.S. tower bolts (oxidised) 250x10 each 10 25.00 250.00
mm
684 Iron screws (oxidised) 30 mm 100 Nos. 100 24.00 24.00
9,999 Carriage of material cum 3.64 1.00 3.64
Labour-
112 Carpenter 2nd class Day 0.1 223 22.30
TOTAL 299.94
Add 1% for water charges 3.00
TOTAL 302.94
Add for contractor’s profit and 45.44
overheads @15%
Cost of 10 tower bolts 348.38
cost of 1 tower bolt 34.84
Say 34.84

9.63 Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel
type) with necessary screws etc. complete :
9.63.2 200x10 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
665 M.S. tower bolts (oxidised) 200x10 mm each 10 21.00 210.00

684 Iron screws (oxidised) 30 mm 100 Nos. 80 24.00 19.20


9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.1 223 22.30
TOTAL 254.23
Add 1% for water charges 2.54
TOTAL 256.77
Add for contractor’s profit and 38.52
overheads @15%
Cost of 10 tower bolts 295.29
cost of 1 tower bolt 29.53
Say 29.53

9.63 Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel
type) with necessary screws etc. complete :
9.63.3 150x10 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
666 M.S. tower bolts (oxidised)150x10 mm each 10 17.00 170.00

684 Iron screws (oxidised) 30 mm 100 Nos. 60 24.00 14.40


9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.1 223 22.30
TOTAL 209.43
Add 1% for water charges 2.09
TOTAL 211.52
Add for contractor’s profit and 31.73
overheads @15%
Cost of 10 tower bolts 243.25
cost of 1 tower bolt 24.33
Say 24.33

9.63 Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel
type) with necessary screws etc. complete :
9.63.4 100x10 mm
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
667 M.S. tower bolts (oxidised) 100x10 mm each 10 12.00 120.00

684 Iron screws (oxidised) 30 mm 100 Nos. 60 24.00 14.40


9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.08 223 17.84
TOTAL 154.97
Add 1% for water charges 1.55
TOTAL 156.52
Add for contractor’s profit and 23.48
overheads @15%
Cost of 10 tower bolts 180.00
cost of 1 tower bolt 18.00
Say 18.00

9.64 Providing and fixing ISI marked 85x42mm oxidised M.S. pull bolt lock
conforming to IS : 7534 with necessary screws bolts, nut and washers etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
2,449 M.S. pull bolts (oxidised) of size 85x42 each 10 27.00 270.00
mm
9,999 Carriage of materials & sundries cum 6.37 1.00 6.37
Labour-
112 Carpenter 2nd class Day 0.25 223 55.75
TOTAL 332.12
Add 1% for water charges 3.32
TOTAL 335.44
Add for contractor’s profit and 50.32
overheads @15%
Cost of 10 pull bolts 385.76
cost of 1 pull bolt 38.58
Say 38.58

9.65 Providing and fixing ISI marked oxidised M.S. door latches conforming to IS:5930
with
9.65.1screws etc. complete
300x20x6 mm :
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
662 M.S. door latches (oxidised) 300x20x6 each 10 25.00 250.00
mm
685 Iron screws (oxidised) 25 mm 100 Nos. 90 16.00 14.40
9,999 Carriage of material cum 3.64 1.00 3.64
Labour-
112 Carpenter 2nd class Day 0.12 223 26.76
TOTAL 294.80
Add 1% for water charges 2.95
TOTAL 297.75
Add for contractor’s profit and 44.66
overheads @15%
Cost of 10 door latches 342.41
cost of 1 door latch 34.24
Say 34.24

9.65 Providing and fixing ISI marked oxidised M.S. door latches conforming to IS:5930
with
9.65.2screws etc. complete
250x20x6 mm :
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
663 M.S. door latches (oxidised) 250x20x6 each 10 25.00 250.00
mm
685 Iron screws (oxidised) 25 mm 100 Nos. 90 16.00 14.40
9,999 Carriage of material cum 3.64 1.00 3.64
Labour-
112 Carpenter 2nd class Day 0.12 223 26.76
TOTAL 294.80
Add 1% for water charges 2.95
TOTAL 297.75
Add for contractor’s profit and 44.66
overheads @15%
Cost of 10 door latches 342.41
cost of 1 door latch 34.24
Say 34.24

9.66 Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992
with
9.66.1necessary
125 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
668 M.S. handle (oxidised) 125 mm each 10 7.00 70.00
685 Iron screws (oxidised) 25 mm 100 Nos. 40 16.00 6.40
9,999 Carriage of material cum 2.73 1.00 2.73
Labour-
112 Carpenter 2nd class Day 0.06 223 13.38
TOTAL 92.51
Add 1% for water charges 0.93
TOTAL 93.44
Add for contractor’s profit and 14.02
overheads @15%
Cost of 10 door handles 107.45
cost of 1 door handle 10.75
Say 10.75

9.66 Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992
with
9.66.2necessary
100 screws
mm etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
669 M.S. handle (oxidised) 100 mm each 10 5.00 50.00
685 Iron screws (oxidised) 25 mm 100 Nos. 40 16.00 6.40
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.06 223 13.38
TOTAL 71.60
Add 1% for water charges 0.72
TOTAL 72.32
Add for contractor’s profit and 10.85
overheads @15%
Cost of 10 door handles 83.16
cost of 1 door handle 8.32
Say 8.32

9.66 Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992
with
9.66.3necessary
75 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for ten nos
Material
s-
670 M.S. handle (oxidised) 75 mm each 10 3.00 30.00
685 Iron screws (oxidised) 25 mm 100 Nos. 40 16.00 6.40
9,999 Carriage of material cum 1.82 1.00 1.82
Labour-
112 Carpenter 2nd class Day 0.06 223 13.38
TOTAL 51.60
Add 1% for water charges 0.52
TOTAL 52.12
Add for contractor’s profit and 7.82
overheads @15%
Cost of 10 door handles 59.93
cost of 1 door handle 5.99
Say 5.99

9.67 Providing and fixing oxidised M.S. hasp and staple (safety type) conforming to
IS : 363 with necessary screws etc. complete :
9.67.1 150 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
679 M.S. hasp and staple (safety type) (oxi 10 Nos 10 79.00 79.00
685 Iron screws (oxidised) 25 mm 100 Nos 80 16.00 12.80
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
112 Carpenter II class Day 0.08 223 17.84
TOTAL 111.46
Add 1% for water charges 1.11
TOTAL 112.57
Add for contractor’s profit and 16.89
overheads @15%
Cost of 10 Nos 129.46
Cost of 1 No. 12.95
Say 12.95

9.67 Providing and fixing oxidised M.S. hasp and staple (safety type) conforming to
IS : 363 with necessary screws etc. complete :
9.67.2 115 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
680 M.S. hasp and staple (safety type) (oxi 10 Nos 10 70.00 70.00
685 Iron screws (oxidised) 25 mm 100 Nos 70 16.00 11.20
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
112 Carpenter II class Day 0.08 223 17.84
TOTAL 100.86
Add 1% for water charges 1.01
TOTAL 101.87
Add for contractor’s profit and 15.28
overheads @15%
Cost of 10 Nos 117.15
Cost of 1 No. 11.71
Say 11.71

9.67 Providing and fixing oxidised M.S. hasp and staple (safety type) conforming to
IS : 363 with necessary screws etc. complete :
9.67.3 90 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
681 M.S. hasp and staple (safety type) (oxi 10 Nos 10 52.00 52.00
685 Iron screws (oxidised) 25 mm 100 Nos 70 16.00 11.20
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
112 Carpenter II class Day 0.08 223 17.84
TOTAL 82.86
Add 1% for water charges 0.83
TOTAL 83.69
Add for contractor’s profit and 12.55
overheads @15%
Cost of 10 Nos 96.24
Cost of 1 No. 9.62
Say 9.62

9.68 Providing and fixing oxidised M.S. casement stays (straight peg type) with
necessary
9.68.1 300screws etc. complete.
mm weighing not less than 200 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
7063 Oxidised M .S. casement stay 300 mm each 10 14.00 140.00
684 Iron screws (oxidised) 30 mm 100 Nos 40 24.00 9.60
9999 Carriage of materials L.S. 0.91 1.00 0.91
Labour-
112 Carpenter II class Day 0.1 223 22.30
TOTAL 172.81
Add 1% for water charges 1.73
TOTAL 174.54
Add for contractor’s profit and 26.18
overheads @15%
Cost of 10 Nos 200.72
Cost of 1 No. 20.07
Say 20.07

9.68 Providing and fixing oxidised M.S. casement stays (straight peg type) with
necessary
9.68.2 250screws etc. complete.
mm weighing not less than 150 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
7064 Oxidised M .S. casement stay 250 mm each 10 12.00 120.00
685 Iron screws (oxidised) 25 mm 100 Nos 40 16.00 6.40
9999 Carriage of materials L.S. 0.91 1.00 0.91
Labour-
112 Carpenter II class Day 0.1 223 22.30
TOTAL 149.61
Add 1% for water charges 1.50
TOTAL 151.11
Add for contractor’s profit and 22.67
overheads @15%
Cost of 10 Nos 173.77
Cost of 1 No. 17.38
Say 17.38

9.68 Providing and fixing oxidised M.S. casement stays (straight peg type) with
necessary
9.68.3 200screws etc. complete.
mm weighing not less than 120 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
7065 Oxidised M .S. casement stay 200 mm each 10 11.00 110.00
685 Iron screws (oxidised) 25 mm 100 Nos 40 16.00 6.40
9999 Carriage of materials L.S. 0.91 1.00 0.91
Labour-
112 Carpenter II class Day 0.1 223 22.30
TOTAL 139.61
Add 1% for water charges 1.40
TOTAL 141.01
Add for contractor’s profit and 21.15
overheads @15%
Cost of 10 Nos 162.16
Cost of 1 No. 16.22
Say 16.22

9.69 Providing and fixing oxidised M.S. Safety chain with necessary fixtures for doors.
(WeighingDescription
Code not less than 450 gms.) Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
7184 Oxidised M.S. safety chain (weighing each 10 43.00 430.00
not less than 450 gms)
685 Iron screws (oxidised) 25 mm 100 Nos 60 16.00 9.60
9999 Carriage of materials L.S. 0.91 1.00 0.91
Labour-
112 Carpenter II class Day 0.1 223 22.30
TOTAL 462.81
Add 1% for water charges 4.63
TOTAL 467.44
Add for contractor’s profit and 70.12
overheads @15%
Cost of 10 Nos 537.55
Cost of 1 No. 53.76
Say 53.76

9.70 Providing and fixing IS : 12817 marked stainlesssteel butt hinges with stainless
steel
9.70.1screws etc. complete
125x64x1.90 mm :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
8215 Stainless steel butt hinges 125x64x1.9 10 nos. 10 200.00 200.00
mm IS : 12817 marked
8210 Stainless steel screws 50 mm 100 Nos 80 213.00 170.40
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 422.98
Add 1% for water charges 4.23
TOTAL 427.21
Add for contractor’s profit and 64.08
overheads @15%
Cost of 10 Nos 491.29
Cost of 1 No. 49.13
Say 49.13

9.70 : Providing and fixing IS : 12817 marked stainless steel butt hinges with
stainless steel screws etc.
9.70.2 : 100X58X1.90 mmcomplete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
8216 S.S. butt hinges 100x58x1.9 mm 10 nos. 10 143.00 143.00
8211 Stainless steel screws 40 mm 100 Nos 80 157.00 125.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 321.18
Add 1% for water charges 3.21
TOTAL 324.39
Add for contractor’s profit and 48.66
overheads @15%
Cost of 10 Nos 373.05
Cost of 1 No. 37.31
Say 37.31

9.70 : Providing and fixing IS : 12817 marked stainless steel butt hinges with
stainless steel screws
9.70.3 75x47x1.80 mmetc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
8217 S.S. butt hinges 75x47x1.8 mm 10 nos. 10 112.00 112.00
8212 Stainless steel screws 30 mm 100 Nos 60 98.00 58.80
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 222.47
Add 1% for water charges 2.22
TOTAL 224.69
Add for contractor’s profit and 33.70
overheads @15%
Cost of 10 Nos 258.40
Cost of 1 No. 25.84
Say 25.84

9.70 : Providing and fixing IS : 12817 marked stainless steel butt hinges with
stainless steel screws mm
9.70.4 : 50x37x1.50 etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
8218 S.S. butt hinges 50x37x1.5 mm 10 nos. 10 90.00 90.00
8214 Stainless steel screws 20 mm 100 Nos 40 63.00 25.20
9999 Carriage of materials L.S. 0.91 1.00 0.91
Labour-
112 Carpenter II class Day 0.08 223 17.84
TOTAL 133.95
Add 1% for water charges 1.34
TOTAL 135.29
Add for contractor’s profit and 20.29
overheads @15%
Cost of 10 Nos 155.58
Cost of 1 No. 15.56
Say 15.56

9.71 : Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)
with stainless steel screws etc. complete :
9.71.1 : 125x64x2.50 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
8219 S.S. butt hinges 125x64x2.5 mm 10 nos. 10 261.00 261.00
8210 Stainless steel screws 50 mm 100 Nos 80 213.00 170.40
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 483.98
Add 1% for water charges 4.84
TOTAL 488.82
Add for contractor’s profit and 73.32
overheads @15%
Cost of 10 Nos 562.14
Cost of 1 No. 56.21
Say 56.21

9.71 : Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)
with stainless steel screws etc. complete :
9.71.2 : 100x60x2.50 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
8220 S.S. butt hinges 100x60x2.5 mm 10 nos. 10 185.00 185.00
8211 Stainless steel screws 40 mm 100 Nos 80 157.00 125.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 363.18
Add 1% for water charges 3.63
TOTAL 366.81
Add for contractor’s profit and 55.02
overheads @15%
Cost of 10 Nos 421.83
Cost of 1 No. 42.18
Say 42.18

9.71 : Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)
with stainless steel screws etc. complete :
9.71.3 ; 75x50x2.50 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
8221 S.S. butt hinges 75x50x2.5 mm 10 nos. 10 155.00 155.00
8212 Stainless steel screws 30 mm 100 Nos 60 98.00 58.80
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 265.47
Add 1% for water charges 2.65
TOTAL 268.12
Add for contractor’s profit and 40.22
overheads @15%
Cost of 10 Nos 308.34
Cost of 1 No. 30.83
Say 30.83

9.72 : Providing and fixing bright finished brass butt hinges with necessaryscrews etc.
complete :
9.72.1: 125x85x5.5 mm (heavy type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
382 Brass butt hinges 125x85x5.5 mm 10 nos. 10 1500.00 1500.00
449 Brass screws 50 mm 100 Nos 100 107.00 107.00
9999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.1 207 20.70
TOTAL 1669.14
Add 1% for water charges 16.69
TOTAL 1685.83
Add for contractor’s profit and 252.87
overheads @15%
Cost of 10 Nos 1938.71
Cost of 1 No. 193.87
Say 193.87
9.72 : Providing and fixing bright finished brass butt hinges with necessary screws
etc. complete
9.72.2 :
: 125x70x4 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
378 Brass butt hinges 125x70x4 mm 10 nos. 10 450.00 450.00
449 Brass screws 50 mm 100 Nos 100 107.00 107.00
9999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.1 207 20.70
TOTAL 619.14
Add 1% for water charges 6.19
TOTAL 625.33
Add for contractor’s profit and 93.80
overheads @15%
Cost of 10 Nos 719.13
Cost of 1 No. 71.91
Say 71.91

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws
etc. complete
9.72.3 :
: 100x85x5.5 mm (heavy type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
383 Brass butt hinges 100x85x5.5 mm 10 nos. 10 1300.00 1300.00
(heavy type)
450 Brass screws 40 mm 100 Nos 80 96.00 76.80
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.1 207 20.70
TOTAL 1438.03
Add 1% for water charges 14.38
TOTAL 1452.41
Add for contractor’s profit and 217.86
overheads @15%
Cost of 10 Nos 1670.27
Cost of 1 No. 167.03
Say 167.03

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws
etc. complete
9.72.4 :
: 100x70x4 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
379 Brass butt hinges 100x70x4 mm 10 nos. 10 300.00 300.00
(ordinary type)
450 Brass screws 40 mm 100 Nos 80 96.00 76.80
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.1 207 20.70
TOTAL 438.03
Add 1% for water charges 4.38
TOTAL 442.41
Add for contractor’s profit and 66.36
overheads @15%
Cost of 10 Nos 508.77
Cost of 1 No. 50.88
Say 50.88

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws
etc.complete : mm (heavy type)
9.72.5 : 75x65x4
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
384 Brass butt hinges 75x65x4 mm (heavy 10 nos. 10 450.00 450.00
type)
451 Brass screws 30 mm 100 Nos 60 86.00 51.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.1 207 20.70
TOTAL 562.83
Add 1% for water charges 5.63
TOTAL 568.46
Add for contractor’s profit and 85.27
overheads @15%
Cost of 10 Nos 653.73
Cost of 1 No. 65.37
Say 65.37

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws
etc.complete :
9.72.6 : 75x40x2.5 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
380 Brass butt hinges 75x40x2.5 mm 10 nos. 10 160.00 160.00
(ordinary type)
451 Brass screws 30 mm 100 Nos 60 86.00 51.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.1 207 20.70
TOTAL 272.83
Add 1% for water charges 2.73
TOTAL 275.56
Add for contractor’s profit and 41.33
overheads @15%
Cost of 10 Nos 316.89
Cost of 1 No. 31.69
Say 31.69

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws
etc.complete :
9.72.7 : 50x40x2.5 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
381 Brass butt hinges 50x40x2.5 mm 10 nos. 10 90.00 90.00
(ordinary type)
453 Brass screws 20 mm 100 Nos 40 53.00 21.20
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.08 270 21.60
TOTAL 134.62
Add 1% for water charges 1.35
TOTAL 135.97
Add for contractor’s profit and 20.39
overheads @15%
Cost of 10 Nos 156.36
Cost of 1 No. 15.64
Say 15.64

9.73 : Providing and fixing bright finished brass parliamentary hinges with necessary
screws
9.73.1 :etc. complete : mm
150x125x27x5
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
385 Parliam entary hingesl50xl25x27x5 mm 10 nos. 10 1650.00 1650.00

450 Brass screws 40 mm 100 Nos 80 96.00 76.80


9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.14 207 28.98
TOTAL 1796.31
Add 1% for water charges 17.96
TOTAL 1814.27
Add for contractor’s profit and 272.14
overheads @15%
Cost of 10 Nos 2086.41
Cost of 1 No. 208.64
Say 208.64

9.73 : Providing and fixing bright finished brass parliamentary hinges with necessary
screws
9.73.2 :etc. complete : mm
125x125x27x5
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
386 Parliam entary hinges 125x125x27x5 10 nos. 10 1450.00 1450.00
mm
450 Brass screws 40 mm 100 Nos 80 96.00 76.80
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.14 207 28.98
TOTAL 1596.31
Add 1% for water charges 15.96
TOTAL 1612.27
Add for contractor’s profit and 241.84
overheads @15%
Cost of 10 Nos 1854.11
Cost of 1 No. 185.41
Say 185.41

9.73 : Providing and fixing bright finished brass parliamentary hinges with necessary
screws
9.73.3 :etc. complete : mm
100x125x27x5
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
387 Parliam entary hinges 100x125x27x5 10 nos. 10 1175.00 1175.00
mm
450 Brass screws 40 mm 100 Nos 80 96.00 76.80
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.14 207 28.98
TOTAL 1321.31
Add 1% for water charges 13.21
TOTAL 1334.52
Add for contractor’s profit and 200.18
overheads @15%
Cost of 10 Nos 1534.70
Cost of 1 No. 153.47
Say 153.47

9.73 : Providing and fixing bright finished brass parliamentary hinges with necessary
screws
9.73.4 :etc. complete : mm
75x100x20x3.2
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
388 Parliam entary hinges 75x100x20x3.2 10 nos. 10 888.00 888.00
mm
451 Brass screws 30 mm 100 Nos 60 86.00 51.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.14 207 28.98
TOTAL 1009.11
Add 1% for water charges 10.09
TOTAL 1019.20
Add for contractor’s profit and 152.88
overheads @15%
Cost of 10 Nos 1172.08
Cost of 1 No. 117.21
Say 117.21

9.74 : Providing and fixing bright finished brass towerbolts (barrel type)with necessary
screws
9.74.1 :etc. complete
250x10 mm :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
400 Brass barrel bolts 250x 10 mm each 10 123.00 1230.00
451 Brass screws 30 mm 100 Nos 100 86.00 86.00
9999 Carriage of materials L.S. 4.55 1.00 4.55
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 1347.55
Add 1% for water charges 13.48
TOTAL 1361.03
Add for contractor’s profit and 204.15
overheads @15%
Cost of 10 Nos 1565.18
Cost of 1 No. 156.52
Say 156.52

9.74 : Providing and fixing bright finished brass towerbolts (barrel type)with necessary
screws
9.74.2 :etc. complete
200x10 mm :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
401 Brass barrel bolts 200x 10 mm each 10 100.00 1000.00
451 Brass screws 30 mm 100 Nos 80 86.00 68.80
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 1098.53
Add 1% for water charges 10.99
TOTAL 1109.52
Add for contractor’s profit and 166.43
overheads @15%
Cost of 10 Nos 1275.94
Cost of 1 No. 127.59
Say 127.59

9.74 : Providing and fixing bright finished brass towerbolts (barrel type)with necessary
screws
9.74.3 :etc. complete
150x10 mm :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
402 Brass barrel bolts 150x 10 mm each 10 75.00 750.00
451 Brass screws 30 mm 100 Nos 80 86.00 68.80
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 848.53
Add 1% for water charges 8.49
TOTAL 857.02
Add for contractor’s profit and 128.55
overheads @15%
Cost of 10 Nos 985.57
Cost of 1 No. 98.56
Say 98.56

9.74 : Providing and fixing bright finished brass towerbolts (barrel type)with necessary
screws
9.74.4: etc. complete
100x10 mm :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
403 Brass barrel bolts 100x 10 mm each 10 51.00 510.00
451 Brass screws 30 mm 100 Nos 60 86.00 51.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 591.33
Add 1% for water charges 5.91
TOTAL 597.24
Add for contractor’s profit and 89.59
overheads @15%
Cost of 10 Nos 686.83
Cost of 1 No. 68.68
Say 68.68

9.75 : Providing and fixing bright finished brass door latch with necessary screws etc.
complete :
9.75.1 : 300x16x5 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
411 Brass door latch 300x16x5 mm each 10 85.00 850.00
452 Brass screws 25 mm 100 Nos 90 76.00 68.40
9999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.12 270 32.40
TOTAL 954.44
Add 1% for water charges 9.54
TOTAL 963.98
Add for contractor’s profit and 144.60
overheads @15%
Cost of 10 Nos 1108.58
Cost of 1 No. 110.86
Say 110.86

9.75 : Providing and fixing bright finished brass door latch with necessary screws etc.
complete :
9.75.2 : 250x16x5 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
412 Brass door latch 250x16x5 mm each 10 82.00 820.00
452 Brass screws 25 mm 100 Nos 90 76.00 68.40
9999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.12 270 32.40
TOTAL 924.44
Add 1% for water charges 9.24
TOTAL 933.68
Add for contractor’s profit and 140.05
overheads @15%
Cost of 10 Nos 1073.74
Cost of 1 No. 107.37
Say 107.37
9.76 : Providing and fixing bright finished brass 100 mm mortice latch and lock with 6
levers and a pair of lever handles with necessary screws etc. complete (best make of
approved Description
Code quality). Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
413 100 mm mortice latch & lock with 6 each 1 257.00 257.00
levers
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 306.54
Add 1% for water charges 3.07
TOTAL 309.61
Add for contractor’s profit and 46.44
overheads @15%
Cost of 1 No. 356.05
Say 356.05

9.77 : Providing and fixing bright finished brass 100 mm mortice latch with one dead
bolt and a pair of lever handles with necessary screws etc. com plete (best make of
approved Description
Code quality). Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
414 100 mm mortice latch each 1 235.00 235.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 284.54
Add 1% for water charges 2.85
TOTAL 287.39
Add for contractor’s profit and 43.11
overheads @15%
Cost of 1 No. 330.49
Say 330.49

9.78 : Providing and fixing bright finished brass night latch including necessary screws
etc. complete (best make of approved quality).
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
438 Brass night latch each 1 338.00 338.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 387.54
Add 1% for water charges 3.88
TOTAL 391.42
Add for contractor’s profit and 58.71
overheads @15%
Cost of 1 No. 450.13
Say 450.13

9.79 : Providing and fixing special quality bright finished brass cupboard or ward robe
locks with four levers including necessary screws etc. complete (best make of approved
quality):
9.79.1 : 40 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2451 40 mm lock each 1 36.00 36.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 85.54
Add 1% for water charges 0.86
TOTAL 86.40
Add for contractor’s profit and 12.96
overheads @15%
Cost of 1 No. 99.35
Say 99.35

9.79 : Providing and fixing special quality bright finished brass cupboard or ward robe
locks with four levers including necessary screws etc. complete (best make of approved
quality):
9.79.2 : 50 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2452 50 mm lock each 1 43.00 43.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 92.54
Add 1% for water charges 0.93
TOTAL 93.47
Add for contractor’s profit and 14.02
overheads @15%
Cost of 1 No. 107.49
Say 107.49

9.79 : Providing and fixing special quality bright finished brass cupboard or ward robe
locks with four levers including necessary screws etc. complete (best make of approved
quality):
9.79.3 : 65 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2453 65 mm lock each 1 55.00 55.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 104.54
Add 1% for water charges 1.05
TOTAL 105.59
Add for contractor’s profit and 15.84
overheads @15%
Cost of 1 No. 121.42
Say 121.42

9.79 : Providing and fixing special quality bright finished brass cupboard or ward robe
locks with four levers including necessary screws etc. complete (best make of approved
quality):
9.79.4 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2454 75 mm lock each 1 70.00 70.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 119.54
Add 1% for water charges 1.20
TOTAL 120.74
Add for contractor’s profit and 18.11
overheads @15%
Cost of 1 No. 138.85
Say 138.85

9.80 : Providing and fixing 50 mm bright finished brass cup board or wardrobe knob
with necessary screws (best make of approved quality)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
447 Cupboard knob each 10 18.00 180.00
9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
TOTAL 220.53
Add 1% for water charges 2.21
TOTAL 222.74
Add for contractor’s profit and 33.41
overheads @15%
Cost of 10 Nos 256.15
Cost of 1 No. 25.61
Say 25.61

9.81 : Providing and fixing bright finished brass handles with screws etc. complete :
9.81.1 : 125 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
408 Bright finished brass handles 125 mm each 10 85.00 850.00

452 Brass screws 25 mm 100 Nos 40 76.00 30.40


9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 899.33
Add 1% for water charges 8.99
TOTAL 908.32
Add for contractor’s profit and 136.25
overheads @15%
Cost of 10 Nos 1044.57

Cost of 1 No. 104.46


Say 104.46

9.81 : Providing and fixing bright finished brass handles with screws etc. complete :
9.81.2 : 100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
409 Bright finished brass handles 100 mm each 10 75.00 750.00

452 Brass screws 25 mm 100 Nos 40 76.00 30.40


9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 797.51
Add 1% for water charges 7.98
TOTAL 805.49
Add for contractor’s profit and 120.82
overheads @15%
Cost of 10 Nos 926.31
Cost of 1 No. 92.63
Say 92.63
9.81 : Providing and fixing bright finished brass handles with screws etc. complete :
9.81.3 : 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
410 Bright finished brass handles 75 mm each 10 55.00 550.00

452 Brass screws 25 mm 100 Nos 40 76.00 30.40


9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 597.51
Add 1% for water charges 5.98
TOTAL 603.49
Add for contractor’s profit and 90.52
overheads @15%
Cost of 10 Nos 694.01
Cost of 1 No. 69.40
Say 69.40

9.82 : Providing and fixing bright finished brass hanging type floor door stopper with
Code
necessaryDescription
screws, etc. complete. Unit Quantity Rate Amount
Details of cost for 10 hanging floor door stopper
Materials-
2455 Bright finished brass floor door stopper each 10 46.00 460.00

452 Brass screws 25 mm 100 Nos 20 76.00 15.20


9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.03 270 8.10
TOTAL 486.03
Add 1% for water charges 4.86
TOTAL 490.89
Add for contractor’s profit and 73.63
overheads @15%
Cost of 10 Nos 564.52
Cost of 1 No. 56.45
Say 56.45

9.83 : Providing and fixing IS : 3564 marked Aluminium die cast body tubular type
universal hydraulic door closer with necessary accessories and screws etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
2456 Hydraulic door closer with necessary each 10 600.00 6000.00
accessories
451 Brass screws 30 mm 100 Nos 60 86.00 51.60
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
112 Carpenter II class Day 1 223 223.00
TOTAL 6278.24
Add 1% for water charges 62.78
TOTAL 6341.02
Add for contractor’s profit and 951.15
overheads @15%
Cost of 10 Nos 7292.18
Cost of 1 No. 729.22
Say 729.22

9.84 : Providing and fixing IS : 3564 marked aluminium extruded section body tubular
type universal hydraulic door closer with double speed adjustment with necessary
accessories
Code and screws etc. complete.
Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
7060 Hydraulic door closer with necessary each 10 765.00 7650.00
accessories
451 Brass screws 30 mm 100 Nos 60 86.00 51.60
9999 Sundries L.S. 1.04 1.00 1.04
Labour-
112 Carpenter II class Day 1 223 223.00
TOTAL 7925.64
Add 1% for water charges 79.26
TOTAL 8004.90
Add for contractor’s profit and 1200.73
overheads @15%
Cost of 10 Nos 9205.63
Cost of 1 No. 920.56
Say 920.56

9.85 : Providing and fixing bright finished brass casement window fastener with
necessaryDescription
Code screws etc. complete. Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
423 Brass casem ent window fastner each 10 26.00 260.00
452 Brass screws 25 mm 100 Nos 40 76.00 30.40
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 318.31
Add 1% for water charges 3.18
TOTAL 321.49
Add for contractor’s profit and 48.22
overheads @15%
Cost of 10 Nos 369.72
Cost of 1 No. 36.97
Say 36.97

9.86: Providing and fixing bright finished brasscasement stays (straight peg type) with
necessary
9.86.1: 300screws etc. complete
mm weighing : than 330 gms
not less
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
424 Brass casement stayes 300 mm each 10 66.00 660.00
451 Brass screws 30 mm 100 Nos 40 86.00 34.40
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 722.31
Add 1% for water charges 7.22
TOTAL 729.53
Add for contractor’s profit and 109.43
overheads @15%
Cost of 10 Nos 838.96
Cost of 1 No. 83.90
Say 83.90

9.86 : Providing and fixing bright finished brass casement stays (straight peg type) with
necessary screws
9.86.2 : 250 etc. complete
mm weighing : than 280 gms
not less
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
425 Brass casement stayes 250 mm each 10 55.00 550.00
452 Brass screws 25 mm 100 Nos 40 76.00 30.40
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 608.31
Add 1% for water charges 6.08
TOTAL 614.39

Add for contractor’s profit and 92.16


overheads @15%
Cost of 10 Nos 706.55
Cost of 1 No. 70.66
Say 70.66
9.86 : Providing and fixing bright finished brass casement stays (straight peg type) with
necessary
9.86.3: 200screws etc. complete
mm weighing : than 240 gms
not less
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
426 Brass casement stayes 200 mm each 10 46.00 460.00
452 Brass screws 25 mm 100 Nos 40 76.00 30.40
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 518.31
Add 1% for water charges 5.18
TOTAL 523.49
Add for contractor’s profit and 78.52
overheads @15%
Cost of 10 Nos 602.02
Cost of 1 No. 60.20
Say 60.20

9.87 : Providing and fixing bright finished brass hasp and staple (safety type) with
necessary
9.87.1: 150screws
mm etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
431 Brass Safety hasps & staples 150 mm 10 nos 10 458.00 458.00

452 Brass screws 25 mm 100 Nos 80 76.00 60.80


9999 Sundries L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.08 270 21.60
TOTAL 542.22
Add 1% for water charges 5.42
TOTAL 547.64
Add for contractor’s profit and 82.15
overheads @15%
Cost of 10 Nos 629.79
Cost of 1 No. 62.98
Say 62.98

9.87 : Providing and fixing bright finished brass hasp and staple (safety type) with
necessary screws
9.87.2 : 115 mm etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
432 Brass Safety hasps & staples 115 mm 10 nos 10 378.00 378.00
453 Brass screws 20 mm 100 Nos 70 53.00 37.10
9999 Carriage of material L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.08 270 21.60
TOTAL 438.52
Add 1% for water charges 4.39
TOTAL 442.91
Add for contractor’s profit and 66.44
overheads @15%
Cost of 10 Nos 509.34
Cost of 1 No. 50.93
Say 50.93

9.87 : Providing and fixing bright finished brass hasp and staple (safety type) with
necessary
9.87.3: 90 screws
mm etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
433 Brass Safety hasps & staples 90 mm 10 nos 10 300.00 300.00

453 Brass screws 20 mm 100 Nos 70 53.00 37.10


9999 Carriage of material L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.08 270 21.60
TOTAL 360.52
Add 1% for water charges 3.61
TOTAL 364.13
Add for contractor’s profit and 54.62
overheads @15%
Cost of 10 Nos 418.74
Cost of 1 No. 41.87
Say 41.87

9.88 : Providing and fixing chromium plated brass 100 mm mortice latch and
lock with 6 levers and a pair of lever handles with necessary screws etc.
complete
Code (best make of approved quality).
Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
558 100 mm mortice latch & lock with 6 each 1 323.00 323.00
levers
9999 Sundries (screws, carriage etc.) L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 372.54
Add 1% for water charges 3.73
TOTAL 376.27
Add for contractor’s profit and 56.44
overheads @15%
Cost of 1 No. 432.71
Say 432.71

9.89 : Providing and fixing chromium plated brass night latch including necessary
screws etc. complete (Best make of approved quality).
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
583 Brass night latch each 1 383.00 383.00
9999 Sundries (screws, carriage etc.) L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 432.54
Add 1% for water charges 4.33

TOTAL 436.87
Add for contractor’s profit and 65.53
overheads @15%
Cost of 1 No. 502.40
Say 502.40

9.90 : Providing and fixing special quality chromium plated brass cupboard locks with
six levers including necessary screws etc. complete (Best make of approved
quality) of : 40 mm
9.90.1: Size
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2468 40 mm lock each 1 38.00 38.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 87.54
Add 1% for water charges 0.88
TOTAL 88.42
Add for contractor’s profit and 13.26
overheads @15%
Cost of 1 No. 101.68
Say 101.68

9.90 : Providing and fixing special quality chromium plated brass cupboard locks with
six levers including necessary screws etc. complete (Best make of approved
quality) of : 50 mm
9.90.2: Size
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2469 50 mm lock each 1 53.00 53.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 102.54
Add 1% for water charges 1.03
TOTAL 103.57
Add for contractor’s profit and 15.53
overheads @15%
Cost of 1 No. 119.10
Say 119.10

9.90 : Providing and fixing special quality chromium plated brass cupboard locks with
six levers including necessary screws etc. complete (Best make of approved
quality) of : 65 mm
9.90.3: Size
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2470 65 mm lock each 1 64.00 64.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 113.54
Add 1% for water charges 1.14
TOTAL 114.68
Add for contractor’s profit and 17.20
overheads @15%
Cost of 1 No. 131.88
Say 131.88

9.90 : Providing and fixing special quality chromium plated brass cupboard locks with
six levers including necessary screws etc. complete (Best make of approved
quality) of : 75 mm
9.90.4 : Size
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials-
2471 75 mm lock each 1 75.00 75.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 124.54
Add 1% for water charges 1.25
TOTAL 125.79
Add for contractor’s profit and 18.87
overheads @15%
Cost of 1 No. 144.65
Say 144.65

9.91: Providing and fixing chromium plated brass 50 mm cupboard or wardrobe knobs
Code
with nuts Description
complete. Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
584 Cupboard knob each 10 25.00 250.00
9999 Sundries (screws, carriage etc.) L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
TOTAL 290.53
Add 1% for water charges 2.91
TOTAL 293.44
Add for contractor’s profit and 44.02
overheads @15%
Cost of 10 Nos. 337.45
Cost of 1 No. 33.75
Say 33.75

9.92 : Providing and fixing chromium plated brass handles with necessary screws etc.
complete:
9.92.1: 125 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
555 Chromium plated brass handles 125 mm each 10 92.00 920.00

452 Brass screws 25 mm 100 Nos 40 76.00 30.40


9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 969.33
Add 1% for water charges 9.69
TOTAL 979.02
Add for contractor’s profit and 146.85
overheads @15%
Cost of 10 Nos 1125.88
Cost of 1 No. 112.59
Say 112.59

9.92 : Providing and fixing chromium plated brass handles with necessary screws etc.
complete:
9.92.2 : 100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
556 Chromium plated brass handles 100 mm each 10 79.00 790.00

452 Brass screws 25 mm 100 Nos 40 76.00 30.40


9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 837.51
Add 1% for water charges 8.38
TOTAL 845.89
Add for contractor’s profit and 126.88
overheads @15%
Cost of 10 Nos 972.77
Cost of 1 No. 97.28
Say 97.28

9.92 : Providing and fixing chromium plated brass handles with necessary screws etc.
complete:
9.92.3 : 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
557 Chromium plated brass handles 75 mm each 10 68.00 680.00

452 Brass screws 25 mm 100 Nos 40 76.00 30.40


9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 727.51
Add 1% for water charges 7.28
TOTAL 734.79
Add for contractor’s profit and 110.22
overheads @15%
Cost of 10 Nos 845.00
Cost of 1 No. 84.50
Say 84.50

9.93 : Providing and fixing chromium plated brass casement window fastener with
Code
necessaryDescription
screws etc. complete. Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
568 C.P. brass window fastner each 10 55.00 550.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 611.11
Add 1% for water charges 6.11
TOTAL 617.22
Add for contractor’s profit and 92.58
overheads @15%
Cost of 10 Nos 709.80
Cost of 1 No. 70.98
Say 70.98

9.94 : Providing and fixing chromium plated brass casement stays (straight peg type)
with
9.94.1necessary
: 300 mmscrews etc. complete
weighing : 330 gms
not less than
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
569 C.P. brass casement stays 300 mm each 10 73.00 730.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 791.11
Add 1% for water charges 7.91
TOTAL 799.02
Add for contractor’s profit and 119.85
overheads @15%
Cost of 10 Nos 918.87
Cost of 1 No. 91.89
Say 91.89

9.94 : Providing and fixing chromium plated brass casement stays (straight peg type)
with
9.94.2necessary
: 250 mmscrews etc. complete
weighing : 280 gms
not less than
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
570 C.P. brass casement stays 250 mm each 10 67.00 670.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 731.11
Add 1% for water charges 7.31
TOTAL 738.42
Add for contractor’s profit and 110.76
overheads @15%
Cost of 10 Nos 849.18
Cost of 1 No. 84.92
Say 84.92

9.94 : Providing and fixing chromium plated brass casement stays (straight peg type)
with necessary screws etc. complete :
9.94.3 200 mm weighing not less than 240 gms
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
571 C.P. brass casement stays 200 mm each 10 56.00 560.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Sundries L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 621.11
Add 1% for water charges 6.21
TOTAL 627.32
Add for contractor’s profit and 94.10
overheads @15%
Cost of 10 Nos 721.42
Cost of 1 No. 72.14
Say 72.14

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.1:with necessary
125x75x4 mmscrews etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
687 Aluminium butt hinges 125x75x4.00 10 nos. 10 478.00 478.00
mm
585 C.P. brass screws 50 mm 100 Nos 100 123.00 123.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 661.07
Add 1% for water charges 6.61
TOTAL 667.68
Add for contractor’s profit and 100.15
overheads @15%
Cost of 10 Nos 767.83
Cost of 1 No. 76.78
Say 76.78

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.2with necessary
: 125x63x4 mmscrews etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
688 Aluminium butt hinges 125x63x4.00 10 nos. 10 447.00 447.00
mm
585 C.P. brass screws 50 mm 100 Nos 100 123.00 123.00
9999 Sundries L.S. 3.64 1.00 3.64
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 630.07
Add 1% for water charges 6.30
TOTAL 636.37
Add for contractor’s profit and 95.46
overheads @15%
Cost of 10 Nos 731.83
Cost of 1 No. 73.18
Say 73.18

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.3with necessary
100x75x4 mm screws etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
689 Aluminium butt hinges 100x75x4.00 10 nos. 10 416.00 416.00
mm
586 C.P. brass screws 40 mm 100 Nos 80 150.00 120.00
9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 595.16
Add 1% for water charges 5.95
TOTAL 601.11
Add for contractor’s profit and 90.17
overheads @15%
Cost of 10 Nos 691.28
Cost of 1 No. 69.13
Say 69.13

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.4:with necessary
100x63x4 mmscrews etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
691 Aluminium butt hinges 100x63x4.00 10 nos. 10 354.00 354.00
586 C.P. brass screws 40 mm 100 Nos 80 150.00 120.00
9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 533.16
Add 1% for water charges 5.33
TOTAL 538.49
Add for contractor’s profit and 80.77
overheads @15%
Cost of 10 Nos 619.27
Cost of 1 No. 61.93
Say 61.93

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.5with necessarymm
: 100x63x3.2 screws etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
690 Aluminium butt hingesl00x63x3.20 mm 10 nos. 10 390.00 390.00

586 C.P. brass screws 40 mm 100 Nos 80 150.00 120.00


9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 569.16
Add 1% for water charges 5.69
TOTAL 574.85
Add for contractor’s profit and 86.23
overheads @15%
Cost of 10 Nos 661.08
Cost of 1 No. 66.11
Say 66.11

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.6with necessary
: 75x63x4 mm screws etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
692 Aluminium butt hinges 75x63x4.00 10 nos. 10 281.00 281.00
mm
587 C.P. brass screws 30 mm 100 Nos 60 90.00 54.00
9999 Sundries L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 393.25
Add 1% for water charges 3.93
TOTAL 397.18
Add for contractor’s profit and 59.58
overheads @15%
Cost of 10 Nos 456.76
Cost of 1 No. 45.68
Say 45.68

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.7:with necessary
75x63x3.2 mmscrews etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
693 Aluminium butt hinges 75x63x3.20 10 nos. 10 215.00 215.00
mm
587 C.P. brass screws 30 mm 100 Nos 60 90.00 54.00
9999 Sundries L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 327.25
Add 1% for water charges 3.27
TOTAL 330.52
Add for contractor’s profit and 49.58
overheads @15%
Cost of 10 Nos 380.10
Cost of 1 No. 38.01
Say 38.01

9.95 : Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.95.8with necessary
: 75x45x3.2 mmscrews etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
694 Aluminium butt hinges 75x45x3.20 10 nos. 10 98.00 98.00
mm
587 C.P. brass screws 30 mm 100 Nos 60 90.00 54.00
9999 Sundries L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.14 270 37.80
114 Beldar Day 0.09 207 18.63
TOTAL 210.25
Add 1% for water charges 2.10
TOTAL 212.35
Add for contractor’s profit and 31.85
overheads @15%
Cost of 10 Nos 244.21
Cost of 1 No. 24.42
Say 24.42

9.96 Providing and fixing aluminium sliding door bolts ISI marked anodised (anodic
coating not less than grade AC 10 as per IS : 1868) transparent or dyed to required
colour or shademm
9.96.1 300x16 with nuts and screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
696 Aluminium sliding bolt 300x16 mm each 10 125.00 1250.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Sundries L.S. 5.46 1.00 5.46
Labour-
111 Carpenter I class Day 0.5 270 135.00
TOTAL 1423.66
Add 1% for water charges 14.24
TOTAL 1437.90
Add for contractor’s profit and 215.68
overheads @15%
Cost of 10 Nos 1653.58
Cost of 1 No. 165.36
Say 165.36

9.96 Providing and fixing aluminium sliding door bolts ISI marked anodised (anodic
coating not less than grade AC 10 as per IS : 1868) transparent or dyed to required
colour or shademm
9.96.2 250x16 with nuts and screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
697 Aluminium sliding bolt 250x16 mm each 10 104.00 1040.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Sundries L.S. 5.46 1.00 5.46
Labour-
111 Carpenter I class Day 0.5 270 135.00
TOTAL 1213.66
Add 1% for water charges 12.14
TOTAL 1225.80
Add for contractor’s profit and 183.87
overheads @15%
Cost of 10 Nos 1409.67
Cost of 1 No. 140.97
Say 140.97

9.97 : Providing and fixing aluminium tower bolts ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour or
shade
9.97.1with necessary
300x10 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
698 Aluminium tower bolt (barrel 10 nos. 10 520.00 520.00
type)300x10
587 C.P. brass screws 30 mm 100 Nos 80 90.00 72.00
9999 Sundries L.S. 4.42 1.00 4.42
Labour-
111 Carpenter I class Day 0.125 270 33.75
TOTAL 630.17
Add 1% for water charges 6.30
TOTAL 636.47
Add for contractor’s profit and 95.47
overheads @15%
Cost of 10 Nos 731.94
Cost of 1 No. 73.19
Say 73.19

9.97 : Providing and fixing aluminium tower bolts ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour or
shade
9.97.2with necessary
: 250x10 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
699 Aluminium tower bolt (barrel type) 10 nos. 10 440.00 440.00
250x10
587 C.P. brass screws 30 mm 100 Nos 80 90.00 72.00
9999 Sundries L.S. 4.42 1.00 4.42
Labour-
111 Carpenter I class Day 0.125 270 33.75
TOTAL 550.17
Add 1% for water charges 5.50
TOTAL 555.67
Add for contractor’s profit and 83.35
overheads @15%
Cost of 10 Nos 639.02
Cost of 1 No. 63.90
Say 63.90
9.97 : Providing and fixing aluminium tower bolts ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour or
shade
9.97.3with necessary
: 200x10 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
700 Aluminium tower bolt (barrel type) 10 nos. 10 354.00 354.00
200x10
587 C.P. brass screws 30 mm 100 Nos 80 90.00 72.00
9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.125 270 33.75
TOTAL 462.48
Add 1% for water charges 4.62
TOTAL 467.10
Add for contractor’s profit and 70.07
overheads @15%
Cost of 10 Nos 537.17
Cost of 1 No. 53.72
Say 53.72

9.97 : Providing and fixing aluminium tower bolts ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour or
shade
9.97.4with necessary
: 150x10 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
701 Aluminium tower bolt (barrel type) 10 nos. 10 281.00 281.00
150x10
587 C.P. brass screws 30 mm 100 Nos 80 90.00 72.00
9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.08 270 21.60
TOTAL 377.33
Add 1% for water charges 3.77
TOTAL 381.10
Add for contractor’s profit and 57.17
overheads @15%
Cost of 10 Nos 438.27
Cost of 1 No. 43.83
Say 43.83

9.97 : Providing and fixing aluminium tower bolts ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour or
shade
9.97.5with necessary
: 100x10 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
702 Aluminium tower bolt (barrel type) 10 nos. 10 208.00 208.00
100x10
587 C.P. brass screws 30 mm 100 Nos 60 90.00 54.00
9999 Sundries L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.08 270 21.60
TOTAL 286.33
Add 1% for water charges 2.86
TOTAL 289.19
Add for contractor’s profit and 43.38
overheads @15%
Cost of 10 Nos 332.57
Cost of 1 No. 33.26
Say 33.26

9.98 : Providing and fixing aluminium pull bolt lock anodised ISI marked (anodic
coating not less than grade AC 10 as per IS : 1868) transparent or dyed to required
colour
Code and shade with necessary screws bolts, nuts andUnit
Description washers etc. complete.
Quantity Rate Amount
Details of cost for 10 pull bolt lock
Materials-
2464 Aluminum Pull bolt lock with necessary each 10 34.00 340.00
screws bolts, eachnuts and washers
complete

9999 Sundries L.S. 6.37 1.00 6.37


Labour-
112 Carpenter II class Day 0.25 223 55.75
TOTAL 402.12
Add 1% for water charges 4.02
TOTAL 406.14
Add for contractor’s profit and 60.92
overheads @15%
Cost of 10 Nos 467.06
Cost of 1 No. 46.71
Say 46.71
44.35
9.99 : Providing and fixing 50cm long aluminium kicking plate 100x3.15 mm
anodised (anodic coating not less than grade AC 10 as per IS : 1868) transparent or
dyed to required
Code colour or shade with necessary screwsUnit
Description etc.Quantity
complete. Rate Amount
Details of cost for 10 nos.
Materials-
706 Kicking plate 50 cm long - 100x3.15 mm each 10 94.00 940.00

588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20


9999 Carriage of materials L.S. 5.46 1.00 5.46
Labour-
111 Carpenter I class Day 0.07 270 18.90
114 Beldar Day 0.05 207 10.35
TOTAL 1007.91
Add 1% for water charges 10.08
TOTAL 1017.99
Add for contractor’s profit and 152.70
overheads @15%
Cost of 10 Nos 1170.69
Cost of 1 No. 117.07
Say 117.07

9.100 : Providing and fixing aluminium handles ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.100.1with necessary
: 125 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
703 Aluminium handles 125 mm 10 nos. 10 375.00 375.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 427.13
Add 1% for water charges 4.27
TOTAL 431.40
Add for contractor’s profit and 64.71
overheads @15%
Cost of 10 Nos 496.11
Cost of 1 No. 49.61
Say 49.61

9.100 : Providing and fixing aluminium handles ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.100.2with necessary
: 100 mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
704 Aluminium handles 100 mm 10 nos. 10 260.00 260.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 311.22
Add 1% for water charges 3.11
TOTAL 314.33
Add for contractor’s profit and 47.15
overheads @15%
Cost of 10 Nos 361.48
Cost of 1 No. 36.15
Say 36.15

9.100 : Providing and fixing aluminium handles ISI marked anodised (anodic coating
not less than grade AC 10 as per IS : 1868) transparent or dyed to required colour or
shade
9.100.3with
: 75necessary
mm screws etc. complete :
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
705 Aluminium handles 175 mm 10 nos. 10 208.00 208.00
589 C.P. brass screws 20 mm 100 Nos 40 63.00 25.20
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
111 Carpenter I class Day 0.06 270 16.20
TOTAL 251.22
Add 1% for water charges 2.51
TOTAL 253.73
Add for contractor’s profit and 38.06
overheads @15%
Cost of 10 Nos 291.79
Cost of 1 No. 29.18
Say 29.18

9.101: Providing and fixing aluminium hanging floor door stopper ISI marked anodised
(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed to
required colour rubber
9.101.1: Single and shade with necessary screws etc. complete.
stopper
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
2459 Aluminium hanging floor door stopper each 10 80.00 800.00
75 mm
588 C.P. brass screws 25 mm 100 Nos 20 83.00 16.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.03 270 8.10
TOTAL 827.43
Add 1% for water charges 8.27
TOTAL 835.70
Add for contractor’s profit and 125.36
overheads @15%
Cost of 10 Nos 961.06
Cost of 1 No. 96.11
Say 96.11
9.101: Providing and fixing aluminium hanging floor door stopper ISI marked anodised
(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed to
required colourrubber
9.101.2: Twin and shade with necessary screws etc. complete.
stopper
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
7059 Aluminium hanging floor door stopper each 10 44.00 440.00
with twin rubber stopper
588 C.P. brass screws 25 mm 100 Nos 20 83.00 16.60
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.03 270 8.10
TOTAL 467.43
Add 1% for water charges 4.67
TOTAL 472.10
Add for contractor’s profit and 70.82
overheads @15%
Cost of 10 Nos 542.92
Cost of 1 No. 54.29
Say 54.29

9.102 Providing and fixing aluminium casement stays ISI marked anodised (anodic
coating not less than grade AC 10 as per IS : 1868) transparent or dyed to required
colour andDescription
Code shade with necessary screws etc. complete. Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
2465 Aluminium casement stays each 10 36.00 360.00
588 C.P. brass screws 25 mm 100 Nos 40 83.00 33.20
9999 Carriage of materials L.S. 0.91 1.00 0.91
Labour-
111 Carpenter I class Day 0.1 270 27.00
TOTAL 421.11
Add 1% for water charges 4.21
TOTAL 425.32
Add for contractor’s profit and 63.80
overheads @15%
Cost of 10 Nos 489.12
Cost of 1 No. 48.91
Say 48.91

9.103 : Providing and fixing bright finished brass 100 mm mortice latch and lock ISI
marked with six levers and a pair of anodised (anodic coating not less than grade AC 10
as per IS : 1868) aluminium lever handles with necessary screws etc. complete (Best
make
Code
of approved quality).
Description Unit Quantity Rate Amount
Details of cost for 1 lock
Materials-
7001 100 mm mortice latch and lock each 1 150.00 150.00
(without handles)
7003 Pair of aluminium handles each 1 195.00 195.00
9999 Carriage of materials L.S. 4.55 1.00 4.55
Labour-
111 Carpenter I class Day 0.17 270 45.90
TOTAL 395.45
Add 1% for water charges 3.95
TOTAL 399.40
Add for contractor’s profit and 59.91
overheads @15%
Cost of 1 No. 459.32
Say 459.32

9.104 : Providing and fixing aluminium tee channels (heavy duty) with rollers, stop end
Code
in pelmetsDescription
as curtain rod. Unit Quantity Rate Amount
Details of cost for 2m long
Materials-
7056 Aluminium channel (heavy duty) with metre 2 35.00 70.00
and stop end as curtain rod
9999 Carriage of materials L.S. 1.43 1.00 1.43
9999 Labour- L.S. 2.73 1.00 2.73
TOTAL 74.16
Add 1% for water charges 0.74
TOTAL 74.90
Add for contractor’s profit and 11.24
overheads @15%
Cost of 2 m 86.14
Cost of 1 m 43.07
Say 43.07

9.105 : Providing and fixing partition upto ceiling height consisting of G.I. frame
and required board including providing and fixing of frame work made of special
section power pressed/ role form G.I. sheet with zinc coating of grade 175 consisting of
floor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mm thick
fixed to the floor and ceiling at the spacing of 610mm centre to centre with dash
fastener of 12.5mm dia-meter,40mm length and the studs 48mm wide having one flange
of 34mm and other flange 36mm and 0.50mm thick fixed vertically within flanges of
floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia
bolts and nuts at both ends of partition fixed flush to wall with rawl plugs at spacing
450mm centre to centre and fixing of boards to either side of frame work by 25mm
drive all screws on studs, floor and ceiling channels at the spacing of 300mm centre to
9.105.1: 67mm overall
centre, including thickness
jointing partition
and finishing to awith 8.5finish
flush mm thick double skin Glass
with recommended jointing
reinforced
compound,Gypsum
jointing (GRG) board
tape, joint conforming
finisher and twotocoats
IS: 2095: part III
of primer suitable for board as per
Code Description
manufacture’s Unit Quantity
specificatior and direction of engineer-in-charge Rate Amount
all complete.
Materials for 6.00x3.65 = 21.9 sqm. (Partition Panel)
7366 Glass reinforced Gyp sum ( GRG) board sqm 43.8 190.00 8322.00
8.5mm thick
7367 50mm floor and ceiling channel metre 12 48.00 576.00
2x6.00=12 m
7369 48mm stud metre 40.15 55.00 2208.25
7019 Dash fastner each 22 8.00 176.00
7020 Screw 20mm long (drive all scews) 100 Nos 392 40.00 156.80
7021 Primer litre 7.88 76.00 598.88
7048 Rawl plug each 18 7.00 126.00
869 Plaster of paris kilogram 19.27 3.00 57.81
763 Glue kilogram 4.82 50.00 241.00
7018 Paper tape (120m roll) roll 0.584 120.00 70.08
1022 Galvanised steel bolts & nuts 6mm dia. 10 Nos 44 60.00 264.00

1211 G.I. Plain washer for seam bolts 100 Nos 44 21.00 9.24
9999 Sundries L.S. 52 1.00 52.00
9999 Sundries scaffolding L.S. 130 1.00 130.00
Labour for 21.90 sqm.
111 Carpenter I class Day 6.57 270 1773.90
112 Carpenter II class Day 2.847 223 634.88
114 Beldar Day 7.665 207 1586.66
131 Painter Day 1.095 180 197.10
TOTAL 17180.60
Add 1% for water charges 171.81
TOTAL 17352.40
Add for contractor’s profit and 2602.86
overheads @15%
Cost of 21.9 sqm 19955.26
Cost of 1 sqm 911.20
Say 911.20

9.105 : Providing and fixing partition upto ceiling height consisting of G.I. frame
and required board including providing and fixing of frame work made of special
section power pressed/ role form G.I. sheet with zinc coating of grade 175 consisting of
floor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mm thick
fixed to the floor and ceiling at the spacing of 610mm centre to centre with dash
fastener of 12.5mm dia-meter,40mm length and the studs 48mm wide having one flange
of 34mm and other flange 36mm and 0.50mm thick fixed vertically within flanges of
floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia
bolts and nuts at both ends of partition fixed flush to wall with rawl plugs at spacing
450mm centre to centre and fixing of boards to either side of frame work by 25mm
drive all screws on studs, floor and ceiling channels at the spacing of 300mm centre to
centre, including jointing and finishing to a flush finish with recommended jointing
compound, jointing tape, joint finisher and two coats of primer suitable for board as per
manufacture’s
9.105.2: 75mm specificatior and direction
overall thickness of with
partition engineer-in-charge all complete.
12.5mm thick double skin plain
Code Description
Gypsum board conforming to IS: 2095: part I Unit Quantity Rate Amount
Materials for 6.00x3.65 = 21.9 sqm. (Partition Panel)
8717 12.5mm thick Plain sqm 43.8 130.00 5694.00
7367 50mm floor and ceiling channel metre 12 48.00 576.00
2x6.00=12 m
7369 48mm stud metre 40.15 55.00 2208.25
7019 Dash fastner each 22 8.00 176.00
7020 Screw 20mm long (drive all scews) 100 Nos 392 40.00 156.80
7021 Primer litre 7.88 76.00 598.88
7048 Rawl plug each 18 7.00 126.00
869 Plaster of paris kilogram 19.27 3.00 57.81
763 Glue kilogram 4.82 50.00 241.00
7018 Paper tape (120m roll) roll 0.584 120.00 70.08
1022 Galvanised steel bolts & nuts 6mm dia. 10 Nos 44 60.00 264.00

1211 G.I. Plain washer for seam bolts 100 Nos 44 21.00 9.24
9999 Sundries L.S. 52 1.00 52.00
9999 Sundries scaffolding L.S. 130 1.00 130.00
Labour for 21.90 sqm.
111 Carpenter I class Day 6.57 270 1773.90
112 Carpenter II class Day 2.847 223 634.88
114 Beldar Day 7.665 207 1586.66
131 Painter Day 1.095 180 197.10
TOTAL 14552.60
Add 1% for water charges 145.53
TOTAL 14698.12
Add for contractor’s profit and 2204.72
overheads @15%
Cost of 21.9 sqm 16902.84
Cost of 1 sqm 771.82
Say 771.82

9.105 : Providing and fixing partition upto ceiling height consisting of G.I. frame
and required board including providing and fixing of frame work made of special
section power pressed/ role form G.I. sheet with zinc coating of grade 175 consisting of
floor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mm thick
fixed to the floor and ceiling at the spacing of 610mm centre to centre with dash
fastener of 12.5mm dia-meter,40mm length and the studs 48mm wide having one flange
of 34mm and other flange 36mm and 0.50mm thick fixed vertically within flanges of
floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia
bolts and nuts at both ends of partition fixed flush to wall with rawl plugs at spacing
450mm centre to centre and fixing of boards to either side of frame work by 25mm
drive all screws on studs, floor and ceiling channels at the spacing of 300mm centre to
9.105.3: 66mm overall
centre, including thickness
jointing Partition
and finishing to awith
flush8mm thick
finish withdouble skin Calcium
recommended jointing
Silicate
compound,Board madetape,
jointing with joint
Calcareous
finisher&and
Siliceous
two coatsmaterials reinforced
of primer suitablewith cellulose
for board as per
fiber manufactured
manufacture’s through and
specificatior autoclaving
directionprocess to give stable crystalline
of engineer-in-charge structure. Non
all complete.
Combustible & Spread of Flame (as per BS standard 476 Part IV & VII), Water, Term
ite & Fungus Resistant, Compressive Strength 225 kg/sq.cm, Bending
Code Description Unit Quantity Rate Amount
Materials for 6.00x3.65 = 21.9 sqm. (Partition Panel)
8699 8 mm thick tapered edge calcium sqm 43.8 194.00 8497.20
silicate
7367 50mm floor and ceiling channel metre 12 48.00 576.00
2x6.00=12 m
7369 48mm stud metre 40.15 55.00 2208.25
7019 Dash fastner each 22 8.00 176.00
7020 Screw 20mm long (drive all scews) 100 Nos 392 40.00 156.80
7021 Primer litre 7.88 76.00 598.88
7048 Rawl plug each 18 7.00 126.00
869 Plaster of paris kilogram 19.27 3.00 57.81
763 Glue kilogram 4.82 50.00 241.00
7018 Paper tape (120m roll) roll 0.584 120.00 70.08
1022 Galvanised steel bolts & nuts 6mm dia. 10 Nos 44 60.00 264.00

1211 G.I. Plain washer for seam bolts 100 Nos 44 21.00 9.24
9999 Sundries L.S. 52 1.00 52.00
9999 Sundries scaffolding L.S. 130 1.00 130.00
Labour for 21.90 sqm.
111 Carpenter I class Day 6.57 270 1773.90
112 Carpenter II class Day 2.847 223 634.88
114 Beldar Day 7.665 207 1586.66
131 Painter Day 1.095 180 197.10
TOTAL 17355.80
Add 1% for water charges 173.56
TOTAL 17529.35
Add for contractor’s profit and 2629.40
overheads @15%
Cost of 21.9 sqm 20158.76
Cost of 1 sqm 920.49
Say 920.49

9.105 : Providing and fixing partition upto ceiling height consisting of G.I. frame
and required board including providing and fixing of frame work made of special
section power pressed/ role form G.I. sheet with zinc coating of grade 175 consisting of
floor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mm thick
fixed to the floor and ceiling at the spacing of 610mm centre to centre with dash
fastener of 12.5mm dia-meter,40mm length and the studs 48mm wide having one flange
of 34mm and other flange 36mm and 0.50mm thick fixed vertically within flanges of
floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia
bolts and nuts at both ends of partition fixed flush to wall with rawl plugs at spacing
450mm centre to centre and fixing of boards to either side of frame work by 25mm
drive all screws on studs, floor and ceiling channels at the spacing of 300mm centre to
centre,
9.105.4:including jointingthickness
66mm overall and finishing to a flush
partition usingfinish
8mmwith
thickrecommended
double skin jointing
non-
compound,
asbestos jointing tape,
multipurpose joint board
cement finisherreinforced
and two coats
with of primer fibre
cellulose suitable for board as per
manufactured
manufacture’s
through specificatior
autoclaving processand direction
(High of engineer-in-charge
pressure steam cured) as perall IS:complete.
14862, non
combustible, non ignitable ,fire propagation index and surface spread of flame (as per
BS 476 part IV, V, VI and VII), moisture, termite & fungus resistant, with suitable fibre
Code Description
cement screw. Unit Quantity Rate Amount
Materials for 6.00x3.65 = 21.9 sqm. (Partition Panel)
237 8 mm thick multipurpose non asbestos sqm 43.8 239.00 10468.20
fibre
7367 50mm floor and ceiling channel metre 12 48.00 576.00
2x6.00=12 m
7369 48mm stud metre 40.15 55.00 2208.25
7019 Dash fastner each 22 8.00 176.00
7020 Screw 20mm long (drive all scews) 100 Nos 392 40.00 156.80
7021 Primer litre 7.88 76.00 598.88
7048 Rawl plug each 18 7.00 126.00
869 Plaster of paris kilogram 19.27 3.00 57.81
763 Glue kilogram 4.82 50.00 241.00
7018 Paper tape (120m roll) roll 0.584 120.00 70.08
1022 Galvanised steel bolts & nuts 6mm dia. 10 Nos 44 60.00 264.00

1211 G.I. Plain washer for seam bolts 100 Nos 44 21.00 9.24
9999 Sundries L.S. 52 1.00 52.00
9999 Sundries scaffolding L.S. 130 1.00 130.00
Labour for 21.90 sqm.
111 Carpenter I class Day 6.57 270 1773.90
112 Carpenter II class Day 2.847 223 634.88
114 Beldar Day 7.665 207 1586.66
131 Painter Day 1.095 180 197.10
TOTAL 19326.80
Add 1% for water charges 193.27
TOTAL 19520.06
Add for contractor’s profit and 2928.01
overheads @15%
Cost of 21.9 sqm 22448.07
Cost of 1 sqm 1025.03
Say 1025.03

9.106 : Providing and fixing PTMT handles with necessary screws etc. complete.
9.106.1: 125x34x24 mm weighing not less than 23 gms.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Materials-
7512 PTMT handle 125x34x24mm each 10 27.00 270.00
639 Mild steel screws 25 mm 100 Nos 40 15.00 6.00
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.06 223 13.38
TOTAL 292.11
Add 1% for water charges 2.92
TOTAL 295.03
Add for contractor’s profit and 44.25
overheads @15%
Cost of ten 339.29
Cost of one 33.93
Say 33.93

9.106 : Providing and fixing PTMT handles with necessary screws etc. complete.
9.106.2 : 150x34x24 mm weighing not less than 26 gms.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Materials-
7513 PTMT handle 150x34x24mm each 10 30.00 300.00
639 Mild steel screws 25 mm 100 Nos 40 15.00 6.00
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.06 223 13.38
TOTAL 322.11
Add 1% for water charges 3.22
TOTAL 325.33
Add for contractor’s profit and 48.80
overheads @15%
Cost of ten 374.13
Cost of one 37.41
Say 37.41

9.107 Providing and fixing PTMT Butt hinges with necessary screws etc. complete.
9.107.1 75x60x10 mm fitted with 5.5 mm dia M.S.Bright Bar Rod weighing not less
Code Description
than 34 gms. Unit Quantity Rate Amount
Details of cost for ten
Materials-
7514 PTMT butt hinges 75x60x10mm each 10 36.00 360.00
638 Mild steel screws 30 mm 100 Nos 60 24.00 14.40
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 426.07
Add 1% for water charges 4.26
TOTAL 430.33
Add for contractor’s profit and 64.55
overheads @15%
Cost of ten 494.88
Cost of one 49.49
Say 49.49

9.107 Providing and fixing PTMT Butt hinges with necessary screws etc. complete.
9.107.2 100x75x10 mm fitted with 5.5 mm dia MSBright Bar Rod weighing not less
Code Description
than 53gms. Unit Quantity Rate Amount
Details of cost for ten
Materials-
7515 PTMT butt hinges 100x75x 10mm each 10 48.00 480.00
637 Mild steel screws 40 mm 100 Nos 80 30.00 24.00
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.14 223 31.22
114 Beldar Day 0.09 207 18.63
TOTAL 556.58
Add 1% for water charges 5.57
TOTAL 562.15
Add for contractor’s profit and 84.32
overheads @15%
Cost of ten 646.47
Cost of one 64.65
Say 64.65

9.108 Providing and fixing PTMT Tower Bolts with 12 mm one piece rod in side and
necessary screws etc.,
9.108.1 152x42x18 mm complete.
weighing not less than 60 gms.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Materials-
7516 PTMT Tower bolt 152x 42x18mm each 10 60.00 600.00
638 Mild steel screws 30 mm 100 Nos 60 24.00 14.40
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.08 223 17.84
TOTAL 634.97
Add 1% for water charges 6.35
TOTAL 641.32
Add for contractor’s profit and 96.20
overheads @15%
Cost of ten 737.52
Cost of one 73.75
Say 73.75

9.108 Providing and fixing PTMT Tower Bolts with 12 mm one piece rod in side and
necessary screws etc.,
9.108.2 202x42x18 mm complete.
weighing not less than 78 gms.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Materials-
7517 PTMT Tower bolt 202x42x 18mm each 10 72.00 720.00
638 Mild steel screws 30 mm 100 Nos 80 24.00 19.20
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
112 Carpenter II class Day 0.1 223 22.30
TOTAL 764.23
Add 1% for water charges 7.64
TOTAL 771.87
Add for contractor’s profit and 115.78
overheads @15%
Cost of ten 887.65
Cost of one 88.77
Say 88.77

9.109 Providing and fixing PTMT door catcher of length 72 mm and dia. of 42 mm
with suitable washers weighing not less than 33 gms.
Code Description Unit Quantity Rate Amount
Details of cost for ten
Materials-
7518 PTMT door catcher 72x42mm each 10 24.00 240.00
639 Mild steel screws 25 mm 100 Nos 20 15.00 3.00
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
111 Carpenter I class Day 0.03 270 8.10
TOTAL 253.83
Add 1% for water charges 2.54
TOTAL 256.37
Add for contractor’s profit and 38.46
overheads @15%
Cost of ten 294.82
Cost of one 29.48
Say 29.48

9.110 Providing and fixing Bamboo jaffery/ fencing consisting of superior quality
25mm dia (Average) half cut bamboo placed vertically and fixed together with three
numbers horizontal running members of hollock wood in scantling of section
50X25mm
Code fixed with nails and G.I wire to existing support
Description complete as per
Unit Quantity direction
Rate of
Amount
Engineer-in-charge.
Details of cost for a bamboo jaffery of size 1.00m x 2.10m = 2.10 sqm
Materials-
305 Bamboo 25 mm dia 2.5 metre long metre 48.3 3.84 185.47
9999 Carriage of materials L.S. 4.83 1.00 4.83
2466 Hollock wood in scantling 10 cudm 3.94 217.00 85.50
2204 Carriage of Timber cum 0.00394 60.81 0.24
9999 Nails and wire & sundries L.S. 30.3 1.00 30.30
Labour-
114 Beldar Day 0.25 207 51.75
112 Carpenter II class Day 0.25 223 55.75
TOTAL 413.84
Add 1% for water charges 4.14
TOTAL 417.98
Add for contractor’s profit and 62.70
overheads @15%
Cost of 2.1 sqm 480.67
Cost of 1 sqm 228.89
Say 228.89

9.111 Providing and fixing wooden moulded corner beading of triangular shape to the
junction of panelling etc. with iron screws, plugs and priming coat on unexposed
surface
9.111.1 etc.
50x50complete 2ndand
mm (base class teak wood.
height).
Code Description Unit Quantity Rate Amount
Details of cost for beading = 5.00 m
Materials-
1190 Second class teak wood in planks 10 cudm 6.88 410.00 282.08
637 Mild steel screws 40 mm 100 Nos 6 30.00 1.80
A Rate as per item no 13.50.1 of SH : sqm 0.5 26.54 13.27
Finishing
2204 Carriage of Timber cum 0.00688 60.81 0.42
Labour-For plaining, fixing & making design
111 Carpenter II class Day 0.75 270 202.50
TOTAL 500.07
Add 1% for water charges except A 4.87

TOTAL 504.94
Add for contractor’s profit and 73.75
overheads @15% except A
Cost of 5 m 578.69
Cost of 1 m 115.74
Say 115.74

9.112 Providing and fixing 2nd class teak wood lipping/ moulded beading or Taj
beading of size 18X5mm fixed with wooden adhesive like fevicol etc and screws/ nails
on the edges
Code of the prelaminated particle board as per direction
Description of Engineer-in-charge.
Unit Quantity Rate Amount
Details of cost for 10.00 m
MATERIALS
8719 2nd class teak w ood lipping/ moulded b metre 10 19.00 190.00
LABOUR
114 Beldar Day 0.25 207 51.75
112 Carpenter II class Day 0.25 223 55.75
TOTAL 297.50
Add 1% for water charges 2.98
TOTAL 300.48
Add for contractor’s profit and 45.07
overheads @15%
Cost of 10 m 345.55
Cost of 1 m 34.55
Say 34.55

9.113 Providing and fixing bright finished 100mm mortice lock with 6 levers without
pair of handles for aluminium door with necessary screws etc complete (Best make of
approved
Code quality) as per direction of Engineer-in-charge.
Description Unit Quantity Rate Amount
Details of cost for 1 no.
MATERIALS
8716 100 mm mostice lock with 6 levers for metre 1 152.50 152.50
9999 Carriage of materials L.S. 2.6 1.00 2.60
Labour-
111 Carpenter I class Day 0.13 270 35.10
TOTAL 190.20
Add 1% for water charges 1.90
TOTAL 192.10
Add for contractor’s profit and 28.82
overheads @15%
Cost of 1 no. 220.92
Say 220.92

9.114 Providing and fixing magnetic catcher in cupboard / ward robe shutters including
fixing with necessary screws etc. complete (Best make of approved quality.
9.114.1 Triple strip vertical type.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
MATERIALS
8714 Magenatic catcher triple strip verticle t metre 1 13.50 13.50
9999 Sundries including screws and fixing cha L.S. 2.6 1.00 2.60
TOTAL 16.10
Add 1% for water charges 0.16
TOTAL 16.26
Add for contractor’s profit and 2.44
overheads @15%
Cost of 1 no. 18.70
Say 18.70

9.114 Providing and fixing magnetic catcher in cupboard / ward robe shutters including
fixing with necessary screws etc. complete (Best make of approved quality.
9.114.2 Double strip (horizontal type).
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
MATERIALS
8715 Magenatic catcher double strip horizonta metre 1 10.00 10.00
9999 Sundries including screws and fixing cha L.S. 2.6 1.00 2.60
TOTAL 12.60
Add 1% for water charges 0.13
TOTAL 12.73
Add for contractor’s profit and 1.91
overheads @15%
Cost of 1 no. 14.63
Say 14.63

9.115 Providing and fixing powder coated telescopic drawer channels 300mm long with
necessary screws etc. complete as per directions of Engineer-in-charge.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sets
MATERIALS
8703 Telescopic draw er channels 300mm long. metre 10 92.00 920.00
9999 Sundries including screws and fixing cha L.S. 100.1 1.00 100.10
9999 Carriage L.S. 19.5 1.00 19.50
TOTAL 1039.60
Add 1% for water charges 10.40
TOTAL 1050.00
Add for contractor’s profit and 157.50
overheads @15%
Cost of 10 sets 1207.50
Cost of 1 set 120.75
Say 120.75

9.116 Providing and fixing sliding arrangement in racks/ cupboards/cabinets shutter by


P/F stainless steel rollers to run inside C or E aluminium channel section (The payment
of C or E Description
Code channel shall be made separately) Unit Quantity Rate Amount
Details of cost for 1 no.
MATERIALS
8704 Stainless steel roller for sliding metre 1 5.00 5.00
arrangment in racks/ cupboards/
cabinets shutter.

9999 Labour for fixing L.S. 1.04 1.00 1.04


TOTAL 6.04
Add 1% for water charges 0.06
TOTAL 6.10
Add for contractor’s profit and 0.92
overheads @15%
Cost of 1 no. 7.02
Say 7.02

9.117 Providing and fixing factory made UPVC door frame made of UPVC extruded,
section having an overall dimension, as below (tolerance +/- 1mm) with wall thickness
2.0mm+/- 02mm. corners of the door frame to be jointed with galvanized brackets and
stainless steel screws, joint mitred and plastic wilded. The hinge side vertical of the
frames reinforced by galvanized M.S. tube of size 19X19mm and 1 mm +/- 0.1 mm
wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per
9.117.1 Extruded
manufacturers section Profile
specification size 48x40
and direction of mm.
Engineer-in-charge
Code Description Unit Quantity Rate Amount
Details of cost for 5 m
MATERIALS
8010 48mmX40mmX2m m thick Factory metre 5 112.00 560.00
made door frame of PVC extruded
sections in white, grey or wooden finish
9999 Sundries L.S. 4.68 1.00 4.68
LABOUR
114 Beldar Day 0.15 207 31.05
156 Carpenter (average) Day 0.15 180 27.00
TOTAL 622.73
Add 1% for water charges 6.23
TOTAL 628.96
Add for contractor’s profit and 94.34
overheads @15%
Cost of 5 m 723.30
Cost of 1 m 144.66
Say 144.66

9.117 Providing and fixing factory made UPVC door frame made of UPVC extruded,
section having an overall dimension, as below (tolerance +/- 1mm) with wall thickness
2.0mm+/- 02mm. corners of the door frame to be jointed with galvanized brackets and
stainless steel screws, joint mitred and plastic wilded. The hinge side vertical of the
frames reinforced by galvanized M.S. tube of size 19X19mm and 1 mm +/- 0.1 mm
wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per
manufacturers
9.117.2 Extruded specification and direction
section Profile of mm.
size 42x50 Engineer-in-charge
Code Description Unit Quantity Rate Amount
Details of cost for 5 m
MATERIALS
8705 50mm X42mmX 1.5mm thick Factory metre 5 117.00 585.00
made door frame of PVC extruded
sections in white, grey or wooden
9999 Sundries
finish L.S. 4.68 1.00 4.68
LABOUR
114 Beldar Day 0.15 207 31.05
156 Carpenter (average) Day 0.15 180 27.00
TOTAL 647.73
Add 1% for water charges 6.48
TOTAL 654.21
Add for contractor’s profit and 98.13
overheads @15%
Cost of 5 m 752.34
Cost of 1 m 150.47
Say 150.47

9.118 Providing and fixing to existing door frames.


9.118.1 24 mm thick factory made PVC door shutters made of styles and rails of a
UPVC hollow section of size 59x24 mm and wall thickness 2 mm ± 0.2 mm with
inbuilt edging on both sides. The styles and rails mitred and joined at the corners by
means of M.S. galvanised/plastic brackets of size 75x220 mm having wall thickness 1.0
mm and stainless steel screws. The styles of the shutter reinforced by inserting
galvanised M.S. tube of size 20x20 mm and 1 mm ± 0.1 mm wall thickness. The lock
rail made up of’H’ section, a UPVC hollow section of size 100x24 mm and 2 mm ± 0.2
mm wall thickness fixed to the shutter styles by means of plastic/galvanised M.S. ‘U’
cleats. The shutter frame filled with a UPVC multi-chambered single panel of size not
less than 620 mm, having over all thickness of 20 mm and 1 mm ± 0.1 mm wall
thickness . The panels filled vertically and tie bar at two places by inserting horizontally
Code Description Unit Quantity Rate Amount
6 mm galvanised M.S. rod and fastened with nuts and washers, complete as per
Details of cost specification
manufacturer’s for 2.38 sqmand direction of Engineer-in-charge. (For W.C. and
bathroom
MATERIALS door shutter).
8001 24 mm thick Factory made shutters w sqm 2.38 1830.00 4355.40
ith frame, rails and panels of PVC
extruded sections in white, grey or
wooden finish i/c carriage

9999 Sundries L.S. 20.36 1.00 20.36


LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 4530.56
Add 1% for water charges 45.31
TOTAL 4575.87
Add for contractor’s profit and 686.38
overheads @15%
Cost of 2.38 sqm 5262.25
Cost of 1 sqm 2211.03
Say 2211.03

9.118 Providing and fixing to existing door frames.


9.118.2 30mm thick factory made Polyvinyl Chloride (PVC) door shutter made of
styles and rails of a UPVC profile section of size 30mm x 60mm and wall thickness
2mm ±0.2mm with inbuilt decorative moulding edging on one side. The styles and rails
with plastic brackets of size 75x220mm mitre and welded at the corners. The- stiles of
the shutter reinforced by inserting galvanized M.S. tube of size 25x20mm and 1mm ±
0.1mm wall thickness. The lock rail made up of ‘H’ section, a UPVC profile section of
size 30mm x 100mm and 2mm±0.2mm wall thickness welded to the shutter style with
a UPVC profile section single panel of size not less than 620mm, having overall
thickness of 20 mm and 1 mm±0.1 mm wall thickness with 20 mm panel beading of
suitable
Code size /Glass(4mm thick plain glass)/louver section,
Description Unit louver frame ofRate
Quantity suitable size,
Amount
as per manufactures specification and direction of Engineer-in-charge. (For W.C. and
Details
bathroomof door
cost Shutter)
for 2.38 sqm
MATERIALS
8002 30 mm thick Factory made shutters w sqm 2.38 1900.00 4522.00
ith frame, rails and panels of PVC
extruded sections in white, grey or
wooden finish i/c carriage

9999 Sundries L.S. 20.36 1.00 20.36


LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 4697.16
Add 1% for water charges 46.97
TOTAL 4744.13
Add for contractor’s profit and 711.62
overheads @15%
Cost of 2.38 sqm 5455.75
Cost of 1 sqm 2292.33
Say 2292.33

9.118 Providing and fixing to existing door frames.


9.118.3 25mm thick PVC flush door shutters upto 737mm width of colour and shade as
approved by Engineer-in-charge made out of a one piece Multi chamber extruded PVC
section of the size of 762mm X 25mm or less as per requirement with an average
wall thickness of 1mm ± 0.3mm. PVC foam end cap of size 23x10mm are provided on
both vertical edges to ensure the overall thickness of 25mm. An MS tube having
dimensions 19mm x 19mm is inserted along the hinge side of the door. Core of the
door shutter should be filled with High Density Polyurethane foam. The Top & Bottom
edges of the shutter are covered with an end-cap of the size 25mm X 11mm. Door
shutter shall be reinforced with special polymeric reinforcem ents as per
manufactures’
Code specification and drawing to take upUnit
Description necessary hardware
Quantity and fixtures.
Rate Amount
Stickers indicating the locations of hardware will be pasted at appropriate places
Details of cost for 2.38 sqm
MATERIALS
8706 25mm thick factory made PVC flash sqm 2.38 1975.00 4700.50
door shutter.
9999 Sundries L.S. 20.36 1.00 20.36
LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 4875.66
Add 1% for water charges 48.76
TOTAL 4924.42
Add for contractor’s profit and 738.66
overheads @15%
Cost of 2.38 sqm 5663.08
Cost of 1 sqm 2379.44
Say 2379.44
9.119 Providing and fixing factory made P.V.C. door frame of size 50x47mm with a
wall thickness of 5mm, made out of extruded 5mm rigid PVC foam sheet mitred at
corners and joined with 2 Nos. of 150mm long brackets of 15x15mm M.S. square tube,
thevertical door profiles to be reinforced with 19x19mm M.S. square tube of 19 gauge,
EPDM rubber gasket weather seal to be provided through out the frame. The door frame
to be fixed to the wall using M.S. screws of 65/100mm size complete as per
Code Description
manufacturers Unit Quantity
specification and direction of Engineer-in-Charge. Rate Amount
Details of cost for 5 m
MATERIALS
8011 Factory made door frame PVC extruded metre 5 294.00 1470.00
sheet
9999 Sundries L.S. 7.8 1.00 7.80
LABOUR
114 Beldar Day 0.15 207 31.05
156 Carpenter (average) Day 0.15 180 27.00
TOTAL 1535.85
Add 1% for water charges 15.36
TOTAL 1551.21
Add for contractor’s profit and 232.68
overheads @15%
Cost of 5 m 1783.89
Cost of 1 m 356.78
Say 356.78

9.120 Providing and fixing to existing door frames.


9.120.1 30mm thick factory made solid panel PVC door shutter consisting of frame
made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for stiles, top
& bottom rails. M.S .frame shall have a coat of steel primers of approved make and
manufacture M.S. frame covered with 5mm thick heat moulded PVC ‘C channel of size
30mm thickness, 110mm width out of which 90mm shall be flat and 20mm shall be
tapered in 45 degree angle on either side forming stiles; and 5mm thick, 110mm wide
PVC sheet out of which 90mm shall be flat and 20mm shall be tapered on the inner side
to form top and bottom rail and 130mm wide PVC sheet out of which 90mm shall be
flat and 20mm shall be tapered on both sides to form lock rail. Top bottom and lock
rails shall be provided either side of the panel. 10mm (5mm x2) thick, 20mm wide cross
PVC sheet shall be provided as gap insert for top rail & bottom rail. Panelling of 5mm
thick PVC sheet to be fitted in the M.S. frame welded/sealed to the stiles & rails with
Code
7mm (5mm Description
+2mm) thick x 15mm wide PVC sheet bending Unit Quantity Rate
on inner side, Amount
and joined
together
Details ofwith
costsolvent cem
for 2.38 sqment adhesive. An additional 5mm thick PVC strip of 20mm
width is
MATERIALS to be stuck on the interior side of the ‘C Channel using PVC solvent
adhesive
8003 etc.
Factory made shutter i/c carriage of Engineer-in-charge,
complete as per direction sqm manufacture’s
2.38 1743.00 4148.34
specification & drawing.
Powder coated M.S. butt hinges 10 Nos. 4 66.00 26.40
8100
100mmX 58mm X 1.9mm
637 M.S. s crews 40mm 100 Nos. 48 30.00 14.40
640 M.S. s crews 20mm 100 Nos. 8 15.00 1.20
9999 Sundries L.S. 20.36 1.00 20.36
LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 4365.50
Add 1% for water charges 43.66
TOTAL 4409.16
Add for contractor’s profit and 661.37
overheads @15%
Cost of 2.38 sqm 5070.53
Cost of 1 sqm 2130.47
Say 2130.47

9.120 Providing and fixing to existing door frames.


9.120.2 30mm thick factory made solid panel PVC door shutter consisting of frame
made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for stiles, top
& bottom rails. M.S .frame shall have a coat of steel primers of approved make and
manufacture M.S. frame covered with 5mm thick heat moulded PVC ‘C channel of size
30mm thickness, 70mm width out of which 50mm shall be flat and 20mm shall be
tapered in 45 degree angle on either side forming stiles; and 5mm thick, 70mm wide
PVC sheet out of which 50mm shall be flat and 20mm shall be tapered on the inner side
to form top and bottom rail and 95mm wide PVC sheet out of which 75mm shall be flat
and 20mm shall be tapered on both sides to form lock rail. Top bottom and lock rails
shall be provided either side of the panel. 10mm (5mm x2) thick, 20mm wide cross
PVC sheet shall be provided as gap insert for top rail & bottom rail. Panelling of 5mm
thick PVC sheet to be fitted in the M.S. frame welded/sealed to the stiles & rails with
Code
7mm (5mm Description
+2mm) thick x 15mm wide PVC sheet bending Unit Quantity Rate
on inner side, Amount
and joined
together
Details ofwith
costsolvent cem
for 2.38 sqment adhesive. An additional 5mm thick PVC strip of 20mm
width is
MATERIALS to be stuck on the interior side of the ‘C Channel using PVC solvent
adhesive
8004 etc. complete
Factory as per
made PVC direction
shutter i/c of Engineer-in-charge,
sqm manufacture’s
2.38 2148.00 5112.24
specification & drawing.
Powder coated M.S. butt hinges 10 Nos. 4 66.00 26.40
8100
100mmX 58mm X 1.9mm
637 M.S. s crews 40mm 100 Nos. 48 30.00 14.40
640 M.S. s crews 20mm 100 Nos. 8 15.00 1.20
9999 Sundries L.S. 20.36 1.00 20.36
LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 5329.40
Add 1% for water charges 53.29
TOTAL 5382.69
Add for contractor’s profit and 807.40
overheads @15%
Cost of 2.38 sqm 6190.10
Cost of 1 sqm 2600.88
Say 2600.88
9.121 Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of
cross-section 90mm x 45mm having single rebate of 32mm x 15mm to receive shutter
of 30mm thickness .The laminate shall be molded with fire resistant grade unsaturated
polyester resin and chopped mat .Doorframe laminate shall be 2mm thick and shall be
filled with suitable wooden block in all the three legs. The frame shall be covered with
Code
fibreglassDescription Unitbottom
from all sides. MS stay shall be provided at the Quantity
to steadyRate Amount
the frame.
Details of cost for 5 m
MATERIALS
8707 Factory made glass reinforced plastic metre 5 333.00 1665.00
door frame 90x45 mm i/c carriage.

9999 Sundries L.S. 7.8 1.00 7.80


LABOUR
114 Beldar Day 0.15 207 31.05
156 Carpenter (average) Day 0.15 180 27.00
TOTAL 1730.85
Add 1% for water charges 17.31
TOTAL 1748.16
Add for contractor’s profit and 262.22
overheads @15%
Cost of 5 m 2010.38
Cost of 1 m 402.08
Say 402.08

9.122 Providing and fixing to existing door frames.


9.122.1 30 mm thick Glass Fibre Reinforced Plastic (FRP) panelled door shutter of
required colour and approved brand and manufacture, made with fire - retardant
grade unsaturated polyester resin, moulded to 3 mm thick FRP laminate for forming
hollow rails and styles, with wooden frame and suitable blocks of seasoned wood inside
at required places for fixing of fittings, cast monolithically with 5mm thick FRP
laminate for panels confirming to TADS 6: 1993 and / or IS: 14856 - 2000 including
Code Description
fixing to frames. Unit Quantity Rate Amount
Details of cost for 2.38 sqm
MATERIALS
8708 30 mm thick factory made glass fiber sqm 2.38 1580.00 3760.40

8100 Powder coated M.S. butt hinges 10 Nos. 4 66.00 26.40


100mmX 58mm X 1.9mm
637 M.S. s crews 40mm 100 Nos. 48 30.00 14.40
640 M.S. s crews 20mm 100 Nos. 8 15.00 1.20
9999 Sundries L.S. 20.36 1.00 20.36
LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 3977.56
Add 1% for water charges 39.78
TOTAL 4017.34
Add for contractor’s profit and 602.60
overheads @15%
Cost of 2.38 sqm 4619.94
Cost of 1 sqm 1941.15
Say 1941.15

9.122 Providing and fixing to existing door frames.


9.122.2 30mm thick fibreglass reinforced plastice (F.R.P.) flush door shutter in
different plain and wood finish made with fire retardant grade unsaturated polyster
resin, moulded to 3mm thick FRP laminate all around, with suitable wooden blocks
inside at required places for fixing of fittings and polyurethane foam (PUF) /
Polystyrene foam to be used as filler material throughout the hollow panel, casted
Code Description Unit Quantity Rate Amount
monolithically with testing parameters of F.R.P. laminate conforming to table - 3 of IS:
Details of cost
14856 : 2000, for 2.38 sqm
MATERIALS
8730 30 mm thick factory made glass fiber sqm 2.38 1960.00 4664.80

8100 Powder coated M.S. butt hinges 10 Nos. 4 66.00 26.40


100mmX 58mm X 1.9mm
637 M.S. s crews 40mm 100 Nos. 48 30.00 14.40
640 M.S. s crews 20mm 100 Nos. 8 15.00 1.20
9999 Sundries L.S. 20.36 1.00 20.36
LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 4881.96
Add 1% for water charges 48.82
TOTAL 4930.78
Add for contractor’s profit and 739.62
overheads @15%
Cost of 2.38 sqm 5670.40
Cost of 1 sqm 2382.52
Say 2382.52

9.123 Providing and fixing factory made door frame (single rebate) made of solid PVC
foam profile with homogenous fine cellular structure having smooth outer integral skin
having 60mm width & 30mm thickness and shall be fixed to wall as per
instructions
Code
of engineer-in-charge using 100x8 sheet metal
Description
CSK screws. Rate Amount
Unit Quantity
Details of cost for 5 m
MATERIALS
8710 Factory made solid PVC door frame 60 metre 5 223.00 1115.00
x30mm shutter i/c carriage
9999 Sundries L.S. 7.8 1.00 7.80
LABOUR
114 Beldar Day 0.15 207 31.05
156 Carpenter (average) Day 0.15 180 27.00
TOTAL 1180.85
Add 1% for water charges 11.81
TOTAL 1192.66
Add for contractor’s profit and 178.90
overheads @15%
Cost of 5 m 1371.56
Cost of 1 m 274.31
Say 274.31

9.124 Providing and fixing 28 mm thick door shutter made of solid PVC foam profile
with homogenous fine cellular structure having smooth outer integral skin having
71mm width & 28mm thick as vertical & horizontal styles. Joints are made using
solvent adhesive and GI ‘C sections (39mm x 19mm x 0.6mm thick) or M S pipe
(40mm x20mm ) stiffener frame insert & telescopic polymeric ‘L’ corners .The panel
shall be filled with 3mm thick high - pressure compact laminate as per
manufacturer’s specifications and directions of the Engineer-in-charge, cover moulding
shall be provided
Code for covering fixing screws and elegant
Description look.( for W.C.
Unit Quantity bathroom
Rate Amount
door shutter).
Details of cost for 2.38 sqm
MATERIALS
8711 28mm factory made solid PVC panel sqm 2.38 1975.00 4700.50
door
8100 Powder coated M.S. butt hinges 10 Nos. 4 66.00 26.40
100mmX 58mm X 1.9mm
637 M.S. s crews 40mm 100 Nos. 48 30.00 14.40
640 M.S. s crews 20mm 100 Nos. 8 15.00 1.20
9999 Sundries L.S. 20.36 1.00 20.36
LABOUR
114 Beldar Day 0.4 207 82.80
156 Carpenter (average) Day 0.4 180 72.00
TOTAL 4917.66
Add 1% for water charges 49.18
TOTAL 4966.84
Add for contractor’s profit and 745.03
overheads @15%
Cost of 2.38 sqm 5711.86
Cost of 1 sqm 2399.94
Say 2399.94

9.125 Providing and fixing PVC rigid foam sheet 1mm thick on existing door
shutters (bathroom and W.C. doors) using synthetic rubber based adhesive.
Code Description Unit Quantity Rate Amount
Details of cost for 1.0x0.3m = 0.3 sqm
MATERIALS
8006 PVC rigid foam sheet1mm thick sqm 0.33 145.00 47.85
9999 Rubber adhesive L.S. 21.84 1.00 21.84
LABOUR
114 Beldar Day 0.14 207 28.98
111 Carpenter 1 st class Day 0.11 270 29.70
130 Mistry Day 0.02 270 5.40
TOTAL 133.77
Add 1% for water charges 1.34
TOTAL 135.11
Add for contractor’s profit and 20.27
overheads @15%
Cost of 0.3 sqm 155.37
Cost of 1 sqm 517.91
Say 517.91

9.126 Providing and fixing 12mm thick panelling or panelling and glazing in panelled
or panelled and glazed shutters for doors, windows and clerestory windows (area of
opening for panel inserts excluding portion inside grooves or rebates to be
measured). Panelling for panelled or panelled and glazed shutters 25mm to 40mm thick.
9.126.1 Marine plywood conforming to IS: 710
Code Description Unit Quantity Rate Amount
Details of cost for 0.67sqm
MATERIALS
8724 12mm thick marine plywood conforming sqm 0.8 740.00 592.00
IS:710
9999 Carriage of Plywood & sundries L.S. 6.24 1.00 6.24
LABOUR
111 Carpenter 1 st class Day 0.57 270 153.90
TOTAL 752.14
Add 1% for water charges 7.52
TOTAL 759.66
Add for contractor’s profit and 113.95
overheads @15%
Cost of 0.67 sqm 873.61
Cost of 1 sqm 1303.90
Say 1303.90

9.126 Providing and fixing 12mm thick panelling or panelling and glazing in panelled
or panelled and glazed shutters for doors, windows and clerestory windows (area of
opening for panel inserts excluding portion inside grooves or rebates to be
measured). Panelling for panelled or panelled and glazed shutters 25mm to 40mm thick.
9.126.2 Fire retardant plywood conforming to IS: 5509.
Code Description Unit Quantity Rate Amount
Details of cost for 0.67sqm
MATERIALS
8725 12mm thick fire retardant plywood sqm 0.8 690.00 552.00
conform ing to IS: 5509
9999 Carriage of Plywood & sundries L.S. 6.24 1.00 6.24
LABOUR
111 Carpenter 1 st class Day 0.57 270 153.90
TOTAL 712.14
Add 1% for water charges 7.12
TOTAL 719.26
Add for contractor’s profit and 107.89
overheads @15%
Cost of 0.67 sqm 827.15
Cost of 1 sqm 1234.55
Say 1234.55

9.127 Providing & Fixing decorative high pressure laminated sheet of plain / wood
grain in gloss / matt / suede finish with high density protective surface layer and reverse
side of adhesive bonding quality conforming to IS : 2046 Type S including cost of
adhesive of aproved quality
9.127.1 1.5 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 5.00 m
MATERIALS
8726 1.5mm thick decorative laminated sqm 5.5 405.00 2227.50
sheet
9999 Adhesive L.S. 195 1.00 195.00
LABOUR
111 Carpenter 1 st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
9999 Sundries i/c nails etc. L.S. 52 1.00 52.00
TOTAL 2713.00
Add 1% for water charges 27.13
TOTAL 2740.13
Add for contractor’s profit and 411.02
overheads @15%
Cost of 5 m 3151.15
Cost of 1 m 630.23
Say 630.23

9.127 Providing & Fixing decorative high pressure laminated sheet of plain / wood
grain in gloss / matt / suede finish with high density protective surface layer and reverse
side of adhesive bonding quality conforming to IS : 2046 Type S including cost of
adhesive of aproved quality
9.127.2 1.0 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 5.00 m
MATERIALS
8727 1.0mm thick decorative laminated sqm 5.5 330.00 1815.00
sheet
9999 Adhesive L.S. 195 1.00 195.00
LABOUR
111 Carpenter 1 st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
9999 Sundries i/c nails etc. L.S. 52 1.00 52.00
TOTAL 2300.50
Add 1% for water charges 23.01
TOTAL 2323.51
Add for contractor’s profit and 348.53
overheads @15%
Cost of 5 m 2672.03
Cost of 1 m 534.41
Say 534.41

9.128 Providing and fixing factory made Fibreglass Reinforced plastics (F.R.P.) chajja
4mm thick of required colour, size and design made by Resin Transfer Moulding (RTM)
Machine Technology, resulting in void free compact laminate in single piece, having
smooth gradual slope curvature for easy drainage of water and duly reinforced by
50x2mm thick M.S. flat with 12mm in built hole for grouting on the existing wall along
with the flanges duly inserted and sealed in the wall complete in one single piece casted
monolithically, including all necessary fittings . The FRP Chajja should be
manufactured using unsaturated Polyester resin as per IS: 11551 complete with
protective
Code Gelcoat U/V coating on Top for complete resistance
Description from the extreme
Unit Quantity of
Rate Amount
temperature, weather
Detail of cost for a & sunlight,
chajja 0.90 x 0.60 = 0.54 sqm
MATERIALS
8713 Fiber glass reinforced plastic chajja sqm 0.54 3520.00 1900.80
including accessories.
9999 Carriage L.S. 26 1.00 26.00
9999 fixing charges including sundries. L.S. 143 1.00 143.00
TOTAL 2069.80
Add 1% for water charges 20.70
TOTAL 2090.50
Add for contractor’s profit and 313.57
overheads @15%
Cost of 0.54 sqm 2404.07
Cost of 1 sqm 4451.99
Say 4451.99

9.129 Providing and fixing cup board shutters 25mm thick, with prelaminated flat
pressed three layer particle board or graded wood particle board IS: 12823 marked
exterior grade (Grade 1 Type II) having one side decorative lamination and other
side balancing lamination including Ilnd class teak wood lipping of 25mm wide xl2 mm
thick with necessary screws and bright finished stainless steel piano hinges
Code
complete Description
as per direction of the Engineer-in-Charge Unit Quantity Rate Amount
Details of cost for one shutter 2.20x1.00m =2.20sqm.
Materials
7272 25 mm thick cup board shutter sqm 2.2 708.00 1557.60
(prelaminated)
8678 l mm thick 35mm wide bright finished metre 4.4 30.00 132.00
stainless steel piano hinges .

685 Screws 25 mm long 100 Nos. 125 16.00 20.00


9999 Carriage L.S. 29.64 1.00 29.64
7271 Add for wooden lipping 25 mm wide x sqm 7 28.00 196.00
12 mm
LABOUR
111 Carpenter 1 st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
130 Mistry Day 0.07 270 18.90
TOTAL 2192.64
Add 1% for water charges 21.93
TOTAL 2214.57
Add for contractor’s profit and 332.18
overheads @15%
Cost of 2.2 sqm 2546.75
Cost of 1 sqm 1157.61
Say 1157.61

9.130 Providing and fixing cup board shutters with 25mm thick veneered particle board
IS : 3097 marked exterior grade (Grade I) of approved make including Ilnd class teak
wood lipping of 25mm wide x 12 mm thick with necessary screws and bright finished
stainless steel piano hinges complete as per direction of Engineer-in-Charge.
9.130.1 With decorative veneering on one side and commercial veering on other side.
Code Description Unit Quantity Rate Amount
Details of cost for one shutter 2.20x1.00m =2.20sqm.
Materials
7269 25 mm thick cup board shutter sqm 2.2 390.00 858.00
346 Extra for teak veneering on one side sqm 2.2 198.00 435.60
andcommercial veneereing on other
side

8678 l mm thick 35mm wide bright finished metre 4.4 30.00 132.00
stainless steel piano hinges .

685 Screws 25 mm long 100 Nos. 125 16.00 20.00


9999 Carriage L.S. 29.64 1.00 29.64
7271 Add for wooden lipping 25 mm wide x sqm 7 28.00 196.00
12 mm
LABOUR
111 Carpenter 1 st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
130 Mistry Day 0.07 270 18.90
TOTAL 1928.64
Add 1% for water charges 19.29
TOTAL 1947.93
Add for contractor’s profit and 292.19
overheads @15%
Cost of 2.2 sqm 2240.12
Cost of 1 sqm 1018.23
Say 1018.23
9.130 Providing and fixing cup board shutters with 25mm thick veneered particle board
IS : 3097 marked exterior grade (Grade I) of approved make including Ilnd class teak
wood lipping of 25mm wide x 12 mm thick with necessary screws and bright finished
stainless steel piano hinges complete as per direction of Engineer-in-Charge.
9.130.2 With non decorative veneering on both sides.
Code Description Unit Quantity Rate Amount
Details of cost for one shutter 2.20x1.00m =2.20sqm.
Materials
7269 25 mm thick cup board shutter sqm 2.2 390.00 858.00
347 Extra for commercial veneering on both sqm 2.2 102.00 224.40
sides
8678 l mm thick 35mm wide bright finished metre 4.4 30.00 132.00
stainless steel piano hinges .

685 Screws 25 mm long 100 Nos. 125 16.00 20.00


9999 Carriage L.S. 29.64 1.00 29.64
7271 Add for wooden lipping 25 mm wide x sqm 7 28.00 196.00
12 mm
LABOUR
111 Carpenter 1 st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
130 Mistry Day 0.07 270 18.90
TOTAL 1717.44
Add 1% for water charges 17.17
TOTAL 1734.61
Add for contractor’s profit and 260.19
overheads @15%
Cost of 2.2 sqm 1994.81
Cost of 1 sqm 906.73
Say 906.73

9.131 Providing and fixing factory made prelaminated particle board flat pressed three
layer or graded wood particle board with one side decorative finish and other side
balancing lamination conforming to IS: 12823 Grade 1 Type II, of approved design, and
edges sealed with water resistant paint and lipped with aluminium ‘U’ type edge
beading alround the shutter, including fixing with angle cleat, grip strip, cadmium
plated steel screws including fixing of aluminium hinges 100x63x4 mm etc. complete
as per architectural
9.131.1 25 mm thick.drawing and direction of Engineer-in-Charge (Cost of’U’ beading
and hinges
Code will be paid for separately).
Description Unit Quantity Rate Amount
Details of cost for one shutter 2.10x1.00m =2.10sqm.
Materials
7445 Prelaminated particle board sqm 2.21 650.00 1436.50
7443 Aluminium single cleat of size 30x32x3 each 4 10.00 40.00

7444 Aluminium grip strip of size 50x12x2 each 8 7.00 56.00

834 Edge sealing water resistant paint litre 0.15 170.00 25.50
9999 Carriage of materials including loading a L.S. 19.5 1.00 19.50
9999 Sundries and screws etc L.S. 39 1.00 39.00
LABOUR
112 Carpenter 2nd class Day 0.27 223 60.21
114 Beldar Day 0.3 207 62.10
TOTAL 1738.81
Add 1% for water charges 17.39
TOTAL 1756.20
Add for contractor’s profit and 263.43
overheads @15%
Cost of 2.1 sqm 2019.63
Cost of 1 sqm 961.73
Say 961.73

9.132 Providing and fixing aluminum U beading of required size to prelaminated /flush
door shutter including fixing etc. complete as per direction of Engineer-in-charge.
Code Description Unit Quantity Rate Amount
Details of cost for 1 kg
Materials
7449 Aluminium ‘U’ Beading kilogram 1.1 195.00 214.50
9999 Sundries including screw s, fixing, carria L.S. 13 1.00 13.00
9999 Anodized 15 micron L.S. 65 1.00 65.00
TOTAL 292.50
Add 1% for water charges 2.93
TOTAL 295.43
Add for contractor’s profit and 44.31
overheads @15%
Cost of 1 kg 339.74
Say 339.74

9.133 Providing and fixing, in position concealed G.I. section for wall panelling using
board of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurled
web of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed
@610mm C/C in perimeter channel having one flange of 20mm and another flange of
30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel is fixed
on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fully threaded
self-tapping drive all screws. B oard is fixed to the ‘Wprofile with 25 mm countersunk
ribbed head screws @ 200mm C/C, all complete as per the drawing & directions of
engineer-in-charge
9.133.1 Tapered edgethecalcium
joints ofsilicate
the boards
boardare finished
made with with specially
calcareous formulated
& siliceous
jointing compound and 48mm wide fiber tape to provide seamless finish.
materialsreinforced with cellulose fiber manufactured through autoclaving process to
give stable crystalline structure, Non combustible & spread of Flame (as per BS
standard 476 Part IV & VII), Water, Termite & Fungus resistant, compressive strength
9.133.1.1 10mm
225 kg/sq.cm, thick. strength 100 kg/sq.cm.
Bending
Code Description Unit Quantity Rate Amount
Details of cost for 3.66 mx 3.05 m =11.16 sqm.
Materials
8700 10 mm thick calcium silicate board sqm 12.28 323.00 3966.44
8720 Ceiling sections. metre 19.66 34.00 668.44
8721 Perimeter channel metre 9.6 20.00 192.00
8722 Nylon sleeves & wooden screws each 42 1.50 63.00
(40mm)
8723 Counter sunk ribbed head screw 25mm. cent 1.76 60.00 105.60

7018 Joint tape roll roll 0.19 120.00 22.80


9999 Carriage of materials L.S. 26 1.00 26.00
9999 Jointing com pound L.S. 20.8 1.00 20.80
9999 Sundries i/c rawl plug, scaffolding etc. L.S. 52 1.00 52.00
LABOUR
111 Carpenter 1 st class Day 3.8 270 1026.00
114 Beldar Day 4.6 207 952.20
TOTAL 7095.28
Add 1% for water charges 70.95
TOTAL 7166.23
Add for contractor’s profit and 1074.93
overheads @15%
Cost of 11.16 sqm 8241.17
Cost of 1 sqm 738.46
Say 738.46

9.133 Providing and fixing, in position concealed G.I. section for wall panelling using
board of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurled
web of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed
@610mm C/C in perimeter channel having one flange of 20mm and another flange of
30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel is fixed
on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fully threaded
self-tapping drive all screws. B oard is fixed to the ‘Wprofile with 25 mm countersunk
ribbed head screws @ 200mm C/C, all complete as per the drawing & directions of
engineer-in-charge the joints
9.133.2 Non -asb estos multof the boards
ipupose are finished
cement with specially
board reinforced withformulated
cellulose fibre
jointing compound and 48mm wide fiber tape to provide seamless
manufactured through autoclaving process (high pressure steam cured) finish.
as per IS 14862
non combustible , non ignitable, fire propagation index and surface spread of flame (as
per BS 476 part IV, V, VI, and VII) moisture , termite & fungus resistant with suitable
fibre cement8screw.
9.133.2.1 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 3.66 mx 3.05 m =11.16 sqm.
Materials
237 8 mm thick multipurpose non asbestos sqm 12.28 239.00 2934.92
fibre
8720 Ceiling sections. metre 19.66 34.00 668.44
8721 Perimeter channel metre 9.6 20.00 192.00
8722 Nylon sleeves & wooden screws each 42 1.50 63.00
(40mm)
8723 Counter sunk ribbed head screw 25mm. cent 1.76 60.00 105.60

7018 Joint tape roll roll 0.19 120.00 22.80


9999 Carriage of materials L.S. 26 1.00 26.00
9999 Jointing com pound L.S. 20.8 1.00 20.80
9999 Sundries i/c rawl plug, scaffolding etc. L.S. 52 1.00 52.00
LABOUR
111 Carpenter 1 st class Day 3.8 270 1026.00
114 Beldar Day 4.6 207 952.20
TOTAL 6063.76
Add 1% for water charges 60.64
TOTAL 6124.40
Add for contractor’s profit and 918.66
overheads @15%
Cost of 11.16 sqm 7043.06
Cost of 1 sqm 631.10
Say 631.10

9.133 Providing and fixing, in position concealed G.I. section for wall panelling using
board of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurled
web of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed
@610mm C/C in perimeter channel having one flange of 20mm and another flange of
30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel is fixed
on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fully threaded
self-tapping drive all screws. B oard is fixed to the ‘Wprofile with 25 mm countersunk
ribbed head screws @ 200mm C/C, all complete as per the drawing & directions of
engineer-in-charge the joints of the boards are finished with specially formulated
9.133.3 Gypsum board conforming to IS: 2095- 1996: Part - I .
jointing compound and 48mm wide fiber tape to provide seamless finish.
9.133.3.1 12.5 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 3.66 mx 3.05 m =11.16 sqm.
Materials
8717 12.5 mm thick Glass fibre reinforced sqm 12.28 130.00 1596.40
Gypsum
8720 Ceiling sections. metre 19.66 34.00 668.44
8721 Perimeter channel metre 9.6 20.00 192.00
8722 Nylon sleeves & wooden screws each 42 1.50 63.00
(40mm)
8723 Counter sunk ribbed head screw 25mm. cent 1.76 60.00 105.60

7018 Joint tape roll roll 0.19 120.00 22.80


9999 Carriage of materials L.S. 26 1.00 26.00
9999 Jointing com pound L.S. 20.8 1.00 20.80
9999 Sundries i/c rawl plug, scaffolding etc. L.S. 52 1.00 52.00
LABOUR
111 Carpenter 1 st class Day 3.8 270 1026.00
114 Beldar Day 4.6 207 952.20
TOTAL 4725.24
Add 1% for water charges 47.25
TOTAL 4772.49
Add for contractor’s profit and 715.87
overheads @15%
Cost of 11.16 sqm 5488.37
Cost of 1 sqm 491.79
Say 491.79
10.1 : Structural steel work in single section fixed with or without connecting plate including
cutting, hoisting, fixing in position and applying coat of approved steel primer all complete.
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials
1007 Steel quintal 1.05 4600.00 4830.00
2205 Carriage tonne 0.105 47.29 4.97
Labour:
116 Fitter (Grade I) Day 0.5 270 135.00
103 Blacksmith 2nd class Day 0.75 223 167.25
114 Beldar Day 1 207 207.00
(A) Priming cost-(Rate vide item no. sqm 3
13.50.3 finishing) 15.74 47.22
9,999 Sundries L.S. 20.67 1.00 20.67
TOTAL 5412.10
Add 1% for water charges except A 53.65
TOTAL 5465.75
Add for contractor’s profit and overheads
@10% except on A 541.85
Cost of 1 quintal 6007.61
Cost of 1 kg 60.08
Say 60.08

10.2 : Structural steel work riveted, bolted or welded in built up sections, trusses and framed
work, including cutting, hoisting, fixing in position and applying a priming coat of approved
steel primer all complete:
Code Description Unit Quantity Rate Amount
Details of cost for a truss 7.6m clear span
Materials-
1007 Principal Rafter T-iron quintal 1.6 4600.00 7360.00
1009 Ties (flats) 50x12mm quintal 0.53 4600.00 2438.00
1010 Gusset plates 10mm thick quintal 1.9 4600.00 8740.00
1020 16mm dia. 50mm long rivets quintal 0.0684 3500.00 239.40
1221 20mm dia. Holding down bolts quintal 0.0529 3800.00 201.02
2205 Carriage tonne 0.415 47.29 19.63
Labour:
116 Fitter (Grade I) Day 2.7 270 729.00
103 Blacksmith 2nd class Day 3.6 223 802.80
139 Beldars (Special) Day 5.4 180 972.00
114 Beldar Day 3.6 207 745.20
100 Bandhani Day 0.44 180 79.20
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 5.68 15.74 89.40
9,999 Sundries L.S. 80.73 1.00 80.73
TOTAL 22496.38
Add 1% for water charges except A 224.07
TOTAL 22720.45
Add for contractor’s profit and overheads
@15% except on A 3394.66
Cost of 3.95 quintal 26115.10
Cost of 1 kg 66.11
Say 66.11

10.3 : Providing and fixing in position collapsible steel shutters with vertical channels
20xl0x2mm and braced with flat iron diagonals 20x5mm size with top and bottom rail of T-
iron 40x40x6mm with 40mm dia, steel pulleys complete with bolts, nuts, locking arrangement,
stoppers, handles, including applying a priming coat of approved steel primer.
Code Description Unit Quantity Rate Amount
Details of cost for a gate 2.4mxl.5m = 3.6sqm .
M aterials-
1007 M.S. channels quintal 0.66 4600.00 3036.00
1008 Flat iron diagonals quintal 0.6 4600.00 2760.00
2205 Carriage tonne 0.126 47.29 5.96
9999 Cost of rivets fixing hooks and washers L.S. 269.1 3.00 807.30
9999 Cost of locking arrangem ents and handles L.S. 67.34 1.00 67.34
4013 Pulleys 40mm dia. each 10 19.00 190.00
Labour:
116 Fitter (Grade I) Day 3 270 810.00
102 Blacksmith 1st class Day 6 270 1620.00
103 Blacksmith 2nd class Day 6 223 1338.00
123 Mason 1st class Day 0.5 270 135.00
124 Mason 2nd class Day 0.5 223 111.50
114 Beldar Day 8 207 1656.00
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 10.5 15.74 165.26
9,999 Sundries L.S. 161.46 1.00 161.46
TOTAL 12863.82
Add 1% for water charges except A 126.99
TOTAL 12990.81
Add for contractor’s profit and overheads
@15% except on A 1923.83
Cost of 3.6 sqm 14914.64
Cost of 1 sqm 4142.96
Say 4142.96

10.4 : Providing and fixing 1mm thick M.S. sheet sliding-shutters with frame and diagonal
braces of 40x40x6mm angle 3mm M.S. gusset plates at the junction and corners 25mm dia
pulley, 40x40x6mm angle and T-iron guide at the top and bottom respectively including
applying
Code
aDescription
priming coat of approved steel primer. Unit Quantity Rate Amount
Details of cost for one double leaf door size 2.4x2.4m = 5.76sqm .
M aterials-
1013 M.S. Sheet 2x5.76= 11.52 quintal 0.497 4600.00 2286.20
1010 Gusset plates 10mm thick quintal 0.153 4600.00 703.80
1007 Angle iron & channel quintal 1.5 4600.00 6900.00
2205 Carriage tonne 0.216 47.29 10.21
969 25mm dia. Pully each 8 18.00 144.00
9999 Pully guide blocks including drilling holes L.S. 269.1 1.00 269.10
9999 Cost of locking arrangem ents and handles L.S. 167.75 1.00 167.75
Labour:
116 Fitter (Grade I) Day 2 270 540.00
102 Blacksmith 1st class Day 3 270 810.00
103 Blacksmith 2nd class Day 4 223 892.00
123 Mason 1st class Day 0.06 270 16.20
124 Mason 2nd class Day 0.06 223 13.38
114 Beldar Day 4 207 828.00
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 18 15.74 283.31
9,999 Bolts and rivets L.S. 269.1 1.00 269.10
9,999 Cement concrete L.S. 13.52 1.00 13.52
9,999 Sundries L.S. 161.46 1.00 161.46
TOTAL 14308.04
Add 1% for water charges except A 140.25
TOTAL 14448.28
Add for contractor’s profit and overheads
@15% except on A 2124.75
Cost of 5.76 sqm 16573.03
Cost of 1 sqm 2877.26
Say 2877.26

10.5 : Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle iron
and 3mm M.S. gusset plates at the junctions and corners, all necessary fittings complete,
including applying a priming coat of approved steel primer.
10.5.1 : Using M.S. angels 40x40x6 mm for diagonal braces.
Code Description Unit Quantity Rate Amount
Details of cost for a double leaf door of size 2.4m x2.4m =5.76sqm.
M aterials-
1013 M.S. Sheet 2x5.76= 11.52 quintal 0.497 4600.00 2286.20
1010 Gusset plates 10mm thick quintal 0.153 4600.00 703.80
1007 Angle iron & channel quintal 0.936 4600.00 4305.60
2205 Carriage tonne 0.1586 47.29 7.50
1036 Pintles including welded pin each 4 30.00 120.00
1222 M.S. cleats with bolts an nuts to rest on
pintles each 4 75.00 300.00
1019 H ooks each 2 25.00 50.00
9999 Rivets L.S. 269.1 1.00 269.10
9999 Cost of locking arrangem ents and handles L.S. 167.7 1.00 167.70
Labour:
116 Fitter (Grade I) Day 2 270 540.00
102 Blacksmith 1st class Day 3 270 810.00
103 Blacksmith 2nd class Day 4 223 892.00
123 Mason 1st class Day 0.06 270 16.20
124 Mason 2nd class Day 0.06 223 13.38
114 Beldar Day 5 207 1035.00
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 15.41 15.74 242.55
9,999 Sundries L.S. 161.46 1.00 161.46
TOTAL 11920.49
Add 1% for water charges except A 116.78
TOTAL 12037.27
Add for contractor’s profit and overheads
@15% except on A 1769.21
Cost of 5.76 sqm 13806.47
Cost of 1 sqm 2396.96
Say 2396.96

10.5 : Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle iron
and 3mm M.S. gusset plates at the junctions and corners, all necessary fittings complete,
including applying a priming coat of approved steel primer.
10.5.2 : Using flats 30x6mm for diagonal braces and central cross piece.
Code Description Unit Quantity Rate Amount
Details of cost for a double leaf door of size 2.4m x2.4m =5.76sqm.
M aterials-
1013 M.S. Sheet 2x5.76= 11.52 quintal 0.497 4600.00 2286.20
1010 Gusset plates 10mm thick quintal 0.2078 4600.00 955.88
1007 Angle iron & channel quintal 0.554 4600.00 2548.40
1008 Flats quintal 0.188 4600.00 864.80
2205 Carriage tonne 0.1447 47.29 6.84
1036 Pintles including welded pin each 4 30.00 120.00
1222 M.S. cleats with bolts an nuts to rest on
pintles each 4 75.00 300.00
1019 H ooks each 2 25.00 50.00
9999 Rivets L.S. 269.1 1.00 269.10
9999 Cost of locking arrangem ents and handles L.S. 167.7 1.00 167.70
Labour:
116 Fitter (Grade I) Day 2 270 540.00
102 Blacksmith 1st class Day 3 270 810.00
103 Blacksmith 2nd class Day 4 223 892.00
123 Mason 1st class Day 0.06 270 16.20
124 Mason 2nd class Day 0.06 223 13.38
114 Beldar Day 5 207 1035.00
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 14.7 15.74 231.37
9,999 Sundries L.S. 161.46 1.00 161.46
TOTAL 11268.33
Add 1% for water charges except A 110.37
TOTAL 11378.70
Add for contractor’s profit and overheads
@15% except on A 1672.10
Cost of 5.76 sqm 13050.80
Cost of 1 sqm 2265.76

10.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths interlocked together through their entire length and jointed together at the end by end
locks mounted on specially designed pipe shaft with brackets, side guides end by end locks
mounted on specially designed pipe shaft with brackets, side guides and complete including
the cost of providing and fixing necessary 27.5cm long wirearrangements for inside and
outside locking with push and pull operation springs grade No.2 and M.S. top cover of
required thickness for rolling shutters.
10.6.1: 80xl.25mm M.S. laths with 1.25 mm thick top cover.
Code Description Unit Quantity Rate Amount
Details of cost for a shutter of size 3mx2.5m = 7.5sqm.
M aterials-
0 973 Cost of Rolling shutter sqm 7.5 767.00 5752.50
0 974 Top Cover metre 2.5 400.00 1000.00
0 975 Coiled type spring each 1 170.00 170.00
9999 Carriage L.S. 53.82 1.00 53.82
Labour:
116 Fitter (Grade I) Day 2.55 270 688.50
123 Mason 1st class Day 0.12 270 32.40
124 Mason 2nd class Day 0.12 223 26.76
114 Beldar Day 2.55 207 527.85
9,999 Sundries L.S. 60.58 1.00 60.58
TOTAL 8312.41
Add 1% for water charges 83.12
TOTAL 8395.53
Add for contractor’s profit and overheads
@15% 1259.33
Cost of 7.5 sqm 9654.86
Cost of 1 sqm 1287.32
Say 1287.32
10.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths interlocked together through their entire length and jointed together at the end by end
locks mounted on specially designed pipe shaft with brackets, side guides end by end locks
mounted on specially designed pipe shaft with brackets, side guides and complete including
the cost of providing and fixing necessary 27.5cm long wirearrangements for inside and
outside locking with push and pull operation springs grade No.2 and M.S. top cover of
required thickness for rolling shutters.
10.6.2 : 80x1.20 mm M.S. laths with 1.20 mm thick top cover.
Code Description Unit Quantity Rate Amount
Details of cost for a shutter of size 3mx2.5m = 7.5sqm.
M aterials-
7045 Cost of Rolling shutter sqm 7.5 615.00 4612.50
7047 Top Cover metre 2.5 228.00 570.00
0 975 Coiled type spring each 1 170.00 170.00
9999 Carriage L.S. 53.82 1.00 53.82
Labour:
116 Fitter (Grade I) Day 2.55 270 688.50
123 Mason 1st class Day 0.12 270 32.40
124 Mason 2nd class Day 0.12 223 26.76
114 Beldar Day 2.55 207 527.85
9,999 Sundries L.S. 60.58 1.00 60.58
TOTAL 6742.41
Add 1% for water charges 67.42
TOTAL 6809.83
Add for contractor’s profit and overheads
@15% 1021.48
Cost of 7.5 sqm 7831.31
Cost of 1 sqm 1044.17
Say 1044.17

10.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths interlocked together through their entire length and jointed together at the end by end
locks mounted on specially designed pipe shaft with brackets, side guides end by end locks
mounted on specially designed pipe shaft with brackets, side guides and complete including
the cost of providing and fixing necessary 27.5cm long wirearrangements for inside and
outside locking with push and pull operation springs grade No.2 and M.S. top cover of
required thickness for rolling shutters.
10.6.3 : 80x0.90 mm M.S. laths with 0.90 mm thick top cover.
Code Description Unit Quantity Rate Amount
Details of cost for a shutter of size 3mx2.5m = 7.5sqm.
M aterials-
7044 Cost of Rolling shutter sqm 7.5 576.00 4320.00
7046 Top Cover metre 2.5 205.00 512.50
0 975 Coiled type spring each 1 170.00 170.00
9999 Carriage L.S. 53.82 1.00 53.82
Labour:
116 Fitter (Grade I) Day 2.55 270 688.50
123 Mason 1st class Day 0.12 270 32.40
124 Mason 2nd class Day 0.12
223 26.76
114 Beldar Day 2.55 207 527.85
9,999 Sundries L.S. 60.58 1.00 60.58
TOTAL 6392.41
Add 1% for water charges 63.92
TOTAL 6456.33
Add for contractor’s profit and overheads
@15% 968.45
Cost of 7.5 sqm 7424.78
Cost of 1 sqm 989.97
Say 989.97

10.7 : Providing and fixing ball bearing for rolling shutters


Code Description Unit Quantity Rate Amount
Details of cost for 1 N o.
M aterials-
976 Ball bearing each 1 280.00 280.00
9,999 Sundries L.S. 26.91 1.00 26.91
TOTAL 306.91
Add 1% for water charges 3.07
TOTAL 309.98
Add for contractor’s profit and overheads
@15% 46.50
Cost of 1 No. 356.48
Say 356.48

10.8: Extra for providing mechanical device chain and crank operation for operating rolling
shutters.
10.8.1:Exceeding 10.00 sqm and upto 16.80 sqm in the area.
Code Description Unit Quantity Rate Amount
Details of cost for one sqm.
977
Extra for mechanical devices chain and
cranked operation for operating rolling
shutters : exceeding 10.00 sq.m and upto
16.80 sq.m area of door sqm 1 400.00 400.00
9,999 Sundries L.S. 13.52 1.00 13.52
TOTAL 413.52
Add 1% for water charges 4.14
TOTAL 417.66
Add for contractor’s profit and overheads
@15% 62.65
Cost of 1 sqm 480.30
Say 480.30
10.8: Extra for providing mechanical device chain and crank operation for operating rolling
shutters.
10.8.2:Exceeding 16.80 sqm in area.
Code Description Unit Quantity Rate Amount
Details of cost for one sqm.
978
Extra for mechanical devices chain and
cranked operation for operating rolling
shutters : exceeding 16.80 sq.m area of
door sqm 1 450.00 450.00
9,999 Sundries L.S. 13.52 1.00 13.52
TOTAL 463.52
Add 1% for water charges 4.64
TOTAL 468.16
Add for contractor’s profit and overheads
@15% 70.22
Cost of 1 sqm 538.38
Say 538.38

10.9: Extra for providing grilled rolling shutters manufactured out of 8 mm dia. M.S. bar
instead of laths as per design approved by Engineer-in-charge. (area of grill to be measured).
Code Description Unit Quantity Rate Amount
Details of cost for a shutter of width 2.5m and grill height 0.6m Grill Area = 1.50sqm.
Materials-
7068
Extra for providing grilled rolling shutter
manufactured out of 8mm dia. M.S. Bar
instead of laths sqm 1.5 185.00 277.50
TOTAL 277.50
Add 1% for water charges 2.78
TOTAL 280.28
Add for contractor’s profit and overheads
@15% 42.04
Cost of 1.5 sqm 322.32
Cost of 1sqm 214.88
Say 214.88

10.10: Fixing standard steel glazed doors, windows and ventilators in walls with 15x3mm lugs
10 cm long embedded in cement concrete blocks 15xl0xl0cm of 1:3:6 (I cement: 3 coarse sand
: 6 graded stone aggregate 20 mm nominal size) or with wooden plugs and screws or rawl
plugs and screws or with fixing clips or with bolts and nuts as required, including fixing of
float glass panes with glazing clips and special metal-sash putty of approved make, or metal
beading with screws (only steel windows with lugs, glass panes cut to size and glazing clips or
metal beading with screws, shall be supplied by department free of cost.)
Code Description Unit Quantity Rate Amount
Details of cost for one door 2x0.76m =1.52sqm.(weight 15 kg)
Materials-
(A) Cement concrete blocks 15x10x10cm
= 0.009 cum (Rate as per item N o. 4.2.5 of cum 0.009 3828.42 34.46
S.H. C.C.)
Labour:
102 Blacksmith 1st class Day 0.17 270 45.90
123 Mason 1st class Day 0.08 270 21.60
124 Mason 2nd class Day 0.08 223 17.84
114 Beldar Day 0.5 207 103.50
119 Glazier Day 0.17 180 30.60
9,999 Putty and sundries L.S. 134.55 1.00 134.55
TOTAL 388.45
Add 1% for water charges except A 3.54
TOTAL 391.99
Add for contractor’s profit and overheads
@15% except on A 53.63
Cost of 15 kg 445.62
Cost of 1 kg 29.71
Say 29.71

10.11 Providing and fixing factory made ISI marked steel glazed doors, windows and
ventilators side /top /centre hung with beading and all members such as KlIB and K12 B etc.
complete of standard rolled steel sections, joints mitred and flash butt welded and sash bars
tenoned and rivetted with 15x3mm lugs, 10cm long, embedded in cement concrete blocks
15x10x 10cm of 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal
size) or with wooden plugs and screws or rawl plugs and screws or with fixing clips or with
bolts and nuts as required, including providing and fixing of hinges, pivots, float glass panes
with glazing clips and special metal sash putty of approved make and a priming coat of
approved steel primer excluding the cost of metal beading and other fittings except necessary
hinges
Code or pivots complete as per approved design.
Description Unit Quantity Rate Amount
Details of cost for a double leaf door of size 2.075x1.175m = 2.44 sqm. (weight 30 kg).
Materials-
4014 Readymade steel door with necessary
hinges, lugs and glazing clips but excluding
other fittings and their fixing to hold glass
panes etc. sqm 2.44 1406.00 3430.64
2406 Float glass panes 4 mm thick (Area 80%
of opening sqm 1.95 248.00 483.60
9,999 Carriage of steel door and glass panes L.S. 80.73 1.00 80.73
(A)Rate as per item no 10.10 of SH: Steel kg 30 29.71 891.23
work
(B)Apply steel primer (2.44x 1.00 for
both sides =2.44 sqm (Rate as per code N
o. 13.50.3 of SH finishing) sqm 2.44 15.74 38.40
TOTAL 4924.60
Add for water charges @ 1% on all items
except (A+B) 39.95
TOTAL 4964.55
Add for contractor’s profit and overhead
@15% on all except (A+B) 605.24
Cost for 30 kg. 5569.79
Cost of 1 kg. 185.66
Say 185.66

10.12: Extra for providing and fixing steel beading of approved shape and section with screws
instead of glazing clips and metal sash putty in steel doors, windows, ventilators and
composite Description
Code units. Unit Quantity Rate Amount
Details of cost for 1 metre
1143 Cost of 1 metre beading metre 1 15.00 15.00
9999 Applying priming coat L.S. 0.46 1.00 0.46
9999 Fixing charges L.S. 3.01 1.00 3.01
TOTAL 18.47
Add 1% for water charges 0.18
TOTAL 18.65
Add for contractor’s profit and overheads
@15% 2.80
Cost of 1 sqm 21.45
Say 21.45
10.13: Providing and fixing T-iron frames for doors, windows and ventilators of mild steel Tee-
sections, joints mitred and welded with 15x3 mm lugs, 10cm long embedded in stone
aggregate 20 mm nominal size) or with wooden plugs and screws or with dash fastener or
rawl plugs and screws or with fixing clips or with bolts and nuts as requird including fixing.of
necessary butt hinges and screws and applying a priming coat of approved steel primer.
Code Description Unit Quantity Rate Amount
Details of cost for 17.5Kg.
Materials
1007 Tee iron quintal 0.18 4600.00 828.00
1002 M.S. bars quintal 0.006 4300.00 25.80
1008 M.S. flat quintal 0.002 4600.00 9.20
Cement concrete block 1:3:6-
6x15x10x10cm= 0.009 cum (A)(Rate as cum 0.009 3828.42 34.46
per item no.4.2.5 of SH:4)
595 Butt hinges-100x58x 1.90mm 10 Nos. 6 54.00 32.40
Labour:
103 Blacksmith 2nd class Day 0.1 223 22.30
116 Fitter (Grade 1) Day 0.15 270 40.50
114 Beldar Day 0.2 207 41.40
9,999 Sundries L.S. 8.97 1.00 8.97
9,999 For screws and nuts and bolts L.S. 35.88 1.00 35.88
9,999 For applying steel prim er L.S. 17.94 1.00 17.94
9,999 Carriage of material L.S. 5.33 1.00 5.33
TOTAL 1102.18
Add 1% for water charges except A 10.68
TOTAL 1112.85
Add for contractor’s profit and overheads
@15% except on A 161.76
Cost of 17.5 kg 1274.61
Cost of 1 kg 72.84
Say 72.84

10.14 Providing and fixing pressed steel door frames confirming to IS: 4351 manufactured
from commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lock jamb,
bead and if required angle threshold of mild steel angle of section 50x25mm, or base ties of
1.25mm pressed mild steel welded or rigidly fixed together by mechanical means,
adjustable lugs with split end tail to each jamb including steel butt hinges 2.5mm thick with
mortar guards, lock strike-plate and shock absorbers as specified and applying a coat of
approved steel primer after pre-treatment of the surface as directed by Engineer-in-charge:
10.14.1 Profile B
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials-
4006 Pressed steel frame =2+2+lm=5m metre 5 170.00 850.00
7027 Butt hinges-100x58x1.90mm 10 Nos 6 80.00 48.00
1007 Tee iron quintal 0.03 4600.00 138.00
(A) Steel primer-500x2(2x1.2+2x6.0+1 x
12.50cm)=2.69 sqm (Rate as per code N o.
13.50.3 of SH finishing) sqm 2.69 15.74 42.34
Labour:
116 Fitter (Grade 1) Day 0.15 270 40.50
114 Beldar Day 0.2 207 41.40
9,999 Sundries L.S. 8.97 1.00 8.97
9,999 Carriage of material L.S. 5.33 1.00 5.33
TOTAL 1174.54
Add 1% for water charges except A 11.32
TOTAL 1185.86
Add for contractor’s profit and overheads
@15% except on A 171.53
Cost of 5m 1357.39
Cost of 1 m 271.48
Say 271.48

10.14 Providing and fixing pressed steel door frames confirming to IS: 4351 manufactured
from commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lock jamb,
bead and if required angle threshold of mild steel angle of section 50x25mm, or base ties of
1.25mm pressed mild steel welded or rigidly fixed together by mechanical means,
adjustable lugs with split end tail to each jamb including steel butt hinges 2.5mm thick with
mortar guards, lock strike-plate and shock absorbers as specified and applying a coat of
approved steel primer after pre-treatment of the surface as directed by Engineer-in-charge:
10.14.2 Profile C
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials-
4007 Pressed steel frame =2+2+lm=5m metre 5 187.00 935.00
7027 Butt hinges-100x58x1.90mm 10 Nos 6 80.00 48.00
1007
Tee iron quintal 0.03 4600.00 138.00
(A) Steel primer-500x2(2x1.2+2x6.0+1 x
12.50cm)=2.69 sqm (Rate as per code N o.
13.50.3 of SH finishing) sqm 2.69 15.74 42.34
Labour:
116 Fitter (Grade 1) Day 0.15 270 40.50
114 Beldar Day 0.2 207 41.40
9,999 Sundries L.S. 8.97 1.00 8.97
9,999 Carriage of material L.S. 5.33 1.00 5.33
TOTAL 1259.54
Add 1% for water charges except A 12.17
TOTAL 1271.71
Add for contractor’s profit and overheads
@15% except on A 184.41
Cost of 5m 1456.12
Cost of 1 m 291.22
Say 291.22

10.14 Providing and fixing pressed steel door frames confirming to IS: 4351 manufactured
from commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lock jamb,
bead and if required angle threshold of mild steel angle of section 50x25mm, or base ties of
1.25mm pressed mild steel welded or rigidly fixed together by mechanical means,
adjustable lugs with split end tail to each jamb including steel butt hinges 2.5mm thick with
mortar guards, lock strike-plate and shock absorbers as specified and applying a coat of
approved steel primer after pre-treatment of the surface as directed by Engineer-in-charge:
10.14.3 Profile E
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials-
4008 Pressed steel frame =2+2+lm=5m metre 5 214.00 1070.00
7027 Butt hinges-100x58x1.90mm 10 Nos 6 80.00 48.00
1007 Tee iron quintal 0.03 4600.00 138.00
(A) Steel primer-500x2(2x1.2+2x6.0+1 x
12.50cm)=2.69 sqm (Rate as per code N o.
13.50.3 of SH finishing) sqm 2.69 15.74 42.34
Labour:
116 Fitter (Grade 1) Day 0.15 270 40.50
114 Beldar Day 0.2 207 41.40
9,999 Sundries L.S. 8.97 1.00 8.97
9,999 Carriage of material L.S. 5.33 1.00 5.33
TOTAL 1394.54
Add 1% for water charges except A 13.52
TOTAL 1408.06
Add for contractor’s profit and overheads
@15% except on A 204.86
Cost of 5m 1612.92
Cost of 1 m 322.58
Say 322.58

10.15 Providing and fixing M.S. Tubular frames for doors, windows, ventilators and
cupboard with L-Type section made of 1.60mm thick M.S. Sheet, joints mitred and welded
and grinded finish,with profiles of required size with 15x3mm lugs 10cm long embedded in
cement concrete blocks 15x10x10cm of 1:3:6 (1 cement : 3 coarse sand: 6 graded stone
aggregate 20mm nominal size) or with wooden plugs and screws or rawl plugs and screws
or with fixing clips or with bolts and nuts as required including fixing of necessary butt hinges
and screws and applying a priming coat of approved steel primers.
Code Description Unit Quantity Rate Amount
Details of cost for 7.13Kg. Materials
Mild steel tubes electric resistant or
4011 induction butt welded kg 7.49 53.00 396.97
1002 M.S. bars quintal 0.006 4300.00 25.80
1008 M.S. flat quintal 0.002 4600.00 9.20
Cement concrete block 1:3:6-
6x15x10x10cm= 0.009 cum (A)(Rate as cum 0.009 3828.42 34.46
per item no.4.2.5 of SH:4)
595 Butt hinges-100x58x 1.90mm 10 Nos. 6 54.00 32.40
Labour:
103 Blacksmith 2nd class Day 0.04 223 8.92
116 Fitter (Grade 1) Day 0.06 270 16.20
114 Beldar Day 0.08 207 16.56
9,999 Sundries L.S. 3.64 1.00 3.64
9,999 For screws and nuts and bolts L.S. 35.88 1.00 35.88
9,999 For applying steel prim er L.S. 17.94 1.00 17.94
9,999 Carriage of material L.S. 5.33 1.00 5.33
TOTAL 603.30
Add 1% for water charges except A 5.69
TOTAL 608.98
Add for contractor’s profit and overheads
@15% except on A 86.18
Cost of 7.13 kg 695.16
Cost of 1 kg 97.50
Say 97.50

10.16 Steel work in built up tubular trusses including cutting, hoisting fixing in position and
applying a priming coat of approved steel primer, welded and bolted including special shaped
washers etc. finished
10.16.1 Hot complete.welded type tubes
Code Description Unit Quantity Rate Amount
Details of cost for a truss of span 8 metre weight = 119 kg.
Materials
4009 Hot finished welded tubes kg 125 38.00 4750.00
2205 Carriage tonne 0.125 47.29 5.91
1215 Welding cm 357 1.00 357.00
Labour:
102 Blacksmith 1st class Day 1.5 270 405.00
100 Bandhani Day 0.75 180 135.00
114 Beldar Day 5.5 207 1138.50
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 2.8 15.74 44.07
9,999 Sundries L.S. 80.73 1.00 80.73
TOTAL 6916.21
Add 1% for water charges except A 68.72
TOTAL 6984.93
Add for contractor’s profit and overheads
@15% except on A 694.09
Cost of 119 kg 7679.02
Cost of 1 kg 64.53
Say 64.53

10.16 Steel work in built up tubular trusses including cutting, hoisting fixing in position and
applying a priming coat of approved steel primer, welded and bolted including special shaped
washers etc. finished
10.16.2 Hot complete.seamless type tubes
Code Description Unit Quantity Rate Amount
Details of cost for a truss of span 8 metre weight = 119 kg.
Materials
4010 Mild steel tubes hot finished seamless type kg 125 38.00 4750.00
2205 Carriage tonne 0.125 47.29 5.91
1215 Welding cm 357 1.00 357.00
Labour:
102 Blacksmith 1st class Day 1.5 270 405.00
100 Bandhani Day 0.75 180 135.00
114 Beldar Day 5.5 207 1138.50
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 2.8 15.74 44.07
9,999 Sundries L.S. 80.73 1.00 80.73
TOTAL 6916.21
Add 1% for water charges except A 68.72
TOTAL 6984.93
Add for contractor’s profit and overheads
@15% except on A 1041.13
Cost of 119 kg 8026.06
Cost of 1 kg 67.45
Say 67.45
10.16 Steel work in built up tubular trusses including cutting, hoisting fixing in position and
applying a priming coat of approved steel primer, welded and bolted including special shaped
washers etc. complete.
10.16.3 Electric resistance or induction butt welded tubes.
Code Description Unit Quantity Rate Amount
Details of cost for a truss of span 8 metre weight = 119 kg.
Materials
4011 Mild steel tubes electric resistant or
induction butt welded kg 125 53.00 6625.00
2205 Carriage tonne 0.125 47.29 5.91
1215 Welding cm 357 1.00 357.00
Labour:
102 Blacksmith 1st class Day 1.5 270 405.00
100 Bandhani Day 0.75 180 135.00
114 Beldar Day 5.5 207 1138.50
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 2.8 15.74 44.07
9,999 Sundries L.S. 80.73 1.00 80.73
TOTAL 8791.21
Add 1% for water charges except A
87.47
TOTAL 8878.68
Add for contractor’s profit and overheads
@15% except on A 1325.19
Cost of 119 kg 10203.88
Cost of 1 kg 85.75
Say 85.75

10.17 Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar bent to shape
with hooked ends in R.C.C. slabs, beams during laying including painting the exposed portion
of loop, all as per standard design complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 clamp
Materials
1003 Mild steel round bar above 12 mm dia
quintal kg 0.017 4300.00 73.10
Labour:
103 Blacksmith 2nd class Day 0.04 223 8.92
114 Beldar Day 0.04 207 8.28
9,999 Sundries (C arriage, fixing and painting L.S. 1.82
etc.) 1.00 1.82
TOTAL 92.12
Add 1% for water charges 0.92
TOTAL 93.04
Add for contractor’s profit and overheads
@15% 13.96
Cost of 1 clamp 107.00
Say 107.00

10.18 Providing and fixing circular/ Hexagonal cast iron or M.S. sheet box for ceiling fan
clamp of internal dia 140mm, 73mm height, top lid of 1:5mm thick M.S. sheet with its top
surface hacked for proper bonding, top lid shall be screwed into the cast iron/ M.S. sheet box
by means of 3.3mm dia. round headed screws, one lock at the corners. Clamp shall be made of
12mm dia M.S. bar bent to shape as per standard drawing,
Code Description Unit Quantity Rate Amount
Details of cost for 1 box clamp
Materials
4012 Circular C.I. Box including bottom and top each 1 35.00 35.00
1002 M.S. bars quintal 0.008 4300.00 34.40
Labour:
103 Blacksmith 2nd class Day 0.03 223 6.69
114 Beldar Day 0.03 207 6.21
9,999 Sundries (C arriage, fixing and painting L.S. 1.82
etc.) 1.00 1.82
TOTAL 84.12
Add 1% for water charges 0.84
TOTAL 84.96
Add for contractor’s profit and overheads
@15% 12.74
Cost of 1 clamp 97.71
Say 97.71

10.19 Providing and fixing M.S. round holding down with nuts and wahser plates completes.
Code Description Unit Quantity Rate Amount
Details of cost for one bolt 16mm dia. And 1200mm long.
Materials
1035 Bolts and nuts above 300 mm in length
quintal 0.019 7000.00 133.00
1010 Mild steel plates quintal 0.005 4600.00 23.00
Labour:
103 Blacksmith 2nd class Day 0.03 223 6.69
9,999 Carriage and labour for fixing L.S. 4.55 1.00 4.55
TOTAL 167.24
Add 1% for water charges 1.67
TOTAL 168.91
Add for contractor’s profit and overheads
@15% 25.34
Cost of 0.024 quintal 194.25
Cost of 1 kg 80.94
Say 80.94
10. 20 Providing and fixing bolts including nuts and washers complete.
Code Description Unit Quantity Rate Amount
Details of cost for 0.10q of nuts and washers
Materials
1034 Bolts and nuts up to 300 mm in length quintal 0.1 7000.00 700.00
2205 Carriage tonne 0.01 47.29 0.47
Labour:
103 Blacksmith 2nd class Day 0.38 223 84.74
114 Beldar Day 0.38 207 78.66
9,999 Carriage and labour for fixing L.S. 4.55 1.00 4.55
TOTAL 868.42
Add 1% for water charges 8.68
TOTAL 877.11
Add for contractor’s profit and overheads
@15% 131.57
Cost of 0.1 quintal 1008.67
Cost of 1 kg 100.87
Say 100.87

10.21 Providing and fixing M.S. rivets of sizes in position


Code Description Unit Quantity Rate Amount
Details of cost for 0.10q of rivets
Materials
1020 Mild steel rivets quintal 0.1 3500.00 350.00
2205 Carriage tonne 0.01 47.29 0.47
Labour:
139 Beldar special Day 0.83 180 149.40
116 Fitter (Grade I) Day 0.83 270 224.10
9,999 Carriage and labour for fixing L.S. 10.79 1.00 10.79
TOTAL 734.76
Add 1% for water charges 7.35
TOTAL 742.11
Add for contractor’s profit and overheads
@15% 111.32
Cost of 0.1 quintal 853.43
Cost of 1 kg 85.34

10.22 Welding by gas or electric plant including transportion of plant at site etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for one cm.
1214 Welding by gas electric plant including
transportation of welding plant at site etc.
complete cm 1 1.00 1.00
9999 Sundries L.S. 0.26 1.00 0.26
TOTAL 1.26
Add 1% for water charges 0.01
TOTAL 1.27
Add for contractor’s profit and overheads
@15% 0.19
Cost of 1 cm 1.46
Say 1.46

10.23 Providing and fixing bright finished brass casement window fasterners or peg stays to
windows/ventilators with necessary welding and machine screws etc. complete.
Code Description Unit Quantity Rate Amount
Details for ten (10 x 0.20 = 2.00 kg)
Materials-
423 Brass casement window fastener each 10 26.00 260.00
9999 Fixing charges including welding and L.S. 125.58 1.00 125.58
9999 Carriage of materials L.S. 3.64 1.00 3.64
TOTAL 389.22
Add 1% for water charges 3.89
TOTAL 393.11
Add for contractor’s profit and overheads
@15% 58.97
Cost of 2.00kg w indow fasteners 452.08
Cost of 1.00kg w indow fasteners 226.04
Say 226.04

10.24 Providing and fixing 14 mm bright finished brass spring catch to steel centre hung
ventilators with necessary welding and machine screws etc. complete.
Code Description Unit Quantity Rate Amount
Details for ten (10 x 0.20 = 2.00 kg)
Materials-
428 Brass fanlight catch 10 Nos. 10 109.00 109.00
9999 Fixing charges including welding and L.S. 125.58 1.00 125.58
9999 Carriage of materials L.S. 3.64 1.00 3.64
TOTAL 238.22
Add 1% for water charges 2.38
TOTAL 240.60
Add for contractor’s profit and overheads
@15% 36.09
Cost of 10 window spring catch 276.69
Cost of 1 window spring catch 27.67
Say 27.67

10.25 Steel work welded in built up section/framed work including cutting, hoisting, fixing in
position and applying a priming coat of approved steel primer using steel etc. as required.
10.25.1 In stringers, treads, landing etc. of stair cses including use of chequered plate wherever
required, all complete.
Code Description Unit Quantity Rate Amount
Consider a flight of staircase of 2.8m height with tread and riser of 200mm & 0.60m wide.
Materials-
1007 Unequal angles as s tringers-75x50x6mm
quintal 3.161 4600.00 14540.60
1010 Plate for tread quintal 1.103 4600.00 5073.80
1549 G.I. Pipe for railing metre 26.65 290.00 7728.50
1003 M.S. round bars quintal 0.373 4300.00 1603.90
2205 Carriage tonne 0.4637 47.29 21.93
2271 Carriage of g.I. Pipe approx. wt. tonne 0.0991 47.29 4.69
1215 Welding charge (electric) 23.20m cm 2320 1.00 2320.00
Labour:
102 Blacksmith 1st class Day 1.85 270 499.50
100 Bandhani Day 0.6 180 108.00
114 Beldar Day 1.25 207 258.75
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 48.29 15.74 760.06
9,999 Sundries L.S. 110.89 1.00 110.89
TOTAL 33030.61
Add 1% for water charges except A
322.71
TOTAL 33353.32
Add for contractor’s profit and overheads
@15% except on A 4888.99
Cost of 533.1 kg 38242.31
Cost of 1 kg 71.74
Say 71.74

10.25 Steel work welded in built up section/framed work including cutting, hoisting, fixing in
position and applying a priming coat of approved steel primer using steel etc. as required.
10.25.2 In grating, frames, guard bar, railing, brackets, gates and similar works.
Code Description Unit Quantity Rate Amount
Details of Imxlm framed guard bar grating.
Materials-
1008 Flats up to 10 mm in thickness quintal quintal 0.145 4600.00 667.00
1003 M.S. bars quintal 0.084 4300.00 361.20
2205 Carriage tonne 0.0229 47.29 1.08
1215 Welding charge (electric) 23.20m cm 60 1.00 60.00
Labour:
102 Blacksmith 1st class Day 0.7 270 189.00
100 Bandhani Day 0.25 180 45.00
114 Beldar Day 0.5 207 103.50
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 0.6 15.74 9.44
9,999 Sundries L.S. 4.55 1.00 4.55
TOTAL 1440.78
Add 1% for water charges except A 14.31
TOTAL 1455.09
Add for contractor’s profit and overheads
@15% except on A 216.85
Cost of 21.8 kg 1671.94
Cost of 1 kg 76.69
Say 76.69

10.26 Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing and staircase railing including applying a priming coat of approved steel
primer.
10.26.1 M.S. tube
Code Description Unit Quantity Rate Amount
Details of cost for hand rail of railing of two flights of staircase, length of hand rail =
5.40m
Materials-
4009
M.S. tube 40mm nominal bore (medium) kilogram 20.46 38.00 777.48
2205 Carriage of tube tonne 0.0205 47.29 0.97
1215 Welding charges (joints of hand rail and cm 72 1.00 72.00
ballustards)
Labour for cutting assembling & erection
102 Blacksmith 1st class Day 0.24 270 64.80
100 Bandhani Day 0.12 180 21.60
114 Beldar Day 0.9 207 186.30
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 0.82 15.74 12.91
9,999 Sundries L.S. 12.48 1.00 12.48
TOTAL 1148.54
Add 1% for water charges except A 11.36
TOTAL 1159.89
Add for contractor’s profit and overheads
@15% except on A 172.05
Cost of 19.49 kg 1331.94
Cost of 1 kg 68.34
Say 68.34

10.26 Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing and staircase railing including applying a priming coat of approved steel
primer.
10.26.2 E.R.W. tubes.
Code Description Unit Quantity Rate Amount
Details of cost for hand rail of railing of two flights of staircase, length of hand rail = 5.40m
Materials-
4011 E.R.W. tube 40mm nominal bore = 5.40m @
kilogram 18.59 53.00 985.27
2205 Carriage of tube tonne 0.0186 47.29 0.88
Welding charges (joints of hand rail and
1215 ballustards) cm 72 1.00 72.00
Labour for cutting assembling & erection
102 Blacksmith 1st class Day 0.24 270 64.80
100 Bandhani Day 0.12 180 21.60
114 Beldar Day 0.9 207 186.30
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 0.82 15.74 12.91
9,999 Sundries L.S. 12.48 1.00 12.48
TOTAL 1356.24
Add 1% for water charges except A 13.43
TOTAL 1369.67
Add for contractor’s profit and overheads
@15% except on A 203.51
Cost of 17.71 kg 1573.18
Cost of 1 kg 88.83
Say 88.83

10.26 Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing and staircase railing including applying a priming coat of approved steel
primer.
10.26.3 G.I.pipes.
Code Description Unit Quantity Rate Amount
Details of cost for hand rail of railing of two flights of staircase, length of hand rail = 5.40m
Materials-
1549 G.I. pipe 40mm nominal bore = 5.40m metre 5.67 290.00 1644.30
2205 Carriage of tube tonne 0.0211 47.29 1.00
Welding charges (joints of hand rail and
1215 ballustards) cm 72 1.00 72.00
Labour for cutting assembling & erection
102 Blacksmith 1st class Day 0.24 270 64.80
100 Bandhani Day 0.12 180 21.60
114 Beldar Day 0.9 207 186.30
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 0.82 15.74 12.91
9,999 Sundries L.S. 12.48 1.00 12.48
TOTAL 2015.38
Add 1% for water charges except A 20.02
TOTAL 2035.41
Add for contractor’s profit and overheads
@15% except on A 303.38
Cost of 20.09 kg 2338.78
Cost of 1 kg 116.42
Say 116.42
11.1 Brick on edge flooring with bricks of class designation 75 including cement slurry etc.
complete in cement mortar with F.P.S. bricks:
11.1.1 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
2602 Bricks of class designation 75 1000 Nos 565 1600.00 904.00
2201 Carriage of bricks 1000 Nos 565 141.88 80.16
Cement mortar 1:4 (Rate asper item 1119.80
No.3.9) cum 0.434 2580.18
367 Cement for slurry tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
Labour:-
101 Bhisti Day 0.27 180 48.60
124 Mason 2nd class Day 1.08 223 240.84
114 Beldar Day 0.25 207 51.75
115 Coolie Day 1.62 207 335.34
TOTAL 2885.44
Add 1% for water charges except A 28.85
TOTAL 2914.29
Add for contractor’s profit and 437.14
overheads @15% except on A
Cost of 10 sqm 3351.43
Cost of 1 sqm 335.14
Say 335.14

11.1 Brick on edge flooring with bricks of class designation 75 including cement slurry etc.
complete in cement mortar with F.P.S. bricks:
11.1.2 1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
2602 Bricks of class designation 75 1000 Nos 565 1600.00 904.00
2201 Carriage of bricks 1000 Nos 565 141.88 80.16
Cement mortar 1:64 (Rate asper item 823.75
No.3.11) cum 0.434 1898.04
367 Cement for slurry tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
Labour:-
101 Bhisti Day 0.27 180 48.60
124 Mason 2nd class Day 1.08 223 240.84
114 Beldar Day 0.25 207 51.75
115 Coolie Day 1.62 207 335.34
TOTAL 2589.39
Add 1% for water charges except A 25.89
TOTAL 2615.28
Add for contractor’s profit and 392.29
overheads @15% except on A
Cost of 10 sqm 3007.57
Cost of 1 sqm 300.76
Say 300.76
11.2 Brick on edge flooring with bricks of class designation 75 including cement slurry etc.
complete in cement mortar with F.P.S. bricks: on a bed of 12 mm mud mortar including
filling joints
Code with Jamuna sand (with F.P.S. bricks) complete.
Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
2602 Bricks of class designation 75 1000 Nos 645 1600.00 1032.00
2201 Carriage of bricks 1000 Nos 645 141.88 91.51
983 Fine sand cum 0.15 300.00 45.00
2335 Carriage of fine sand cum 0.15 53.21 7.98
Mud mortar (Rate asper item No.3.18) 32.27
cum 0.15 215.16
367 Cement for slurry tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
Labour:-
101 Bhisti Day 0.05 180 9.00
124 Mason 2nd class Day 0.9 223 200.70
115 Coolie Day 1.98 207 409.86
TOTAL 1933.27
Add 1% for water charges except A 19.33
TOTAL 1952.61
Add for contractor’s profit and 292.89
overheads @15% except on A
Cost of 10 sqm 2245.50
Cost of 1 sqm 224.55
Say 224.55

11.3 Cement concrete flooring 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate)
finished with a floating coat of neat cement including cement slurry, but excluding the cost of
nosing of stepsthick
11.3.1 40mm etc. with
complete.
20mm nominal size stone aggregate.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
295 Stone aggregate 20 mm cum 0.267 1100.00 293.70
297 Stone aggregate 10 mm cum 0.089 1050.00 93.45
2202 Carriage of aggregate below 20mm cum 0.356 53.21 18.94
982 Coarse sand cum 0.178 300.00 53.40
2261 Carriage of coarse sand cum 0.178 53.21 9.47
367 Cement (0.2225 cum) tonne 0.17 5200.00 884.00
2209 Carriage of cement tonne 0.17 47.29 8.04
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 0.8 223 178.40
114 Beldar Day 1.4 207 289.80
127 Mixer operator Day 0.03 223 6.69
2 Mixer Day 0.03 400 12.00
9999 Sundries L. S. 40.43 1.00 40.43
TOTAL 2075.52
Add 1% for water charges except A 20.76
TOTAL 2096.28
Add for contractor’s profit and 314.44
overheads @15% except on A
Cost of 10 sqm 2410.72
Cost of 1 sqm 241.07
Say 241.07

11.4 52 mm thick cement concrete flooring with concrete hardener topping under layer 40
mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1
cement hardener mix : 2 graded stone aggregate 6 mm nominal size) by volume .hardening
compound is mixed @ 2 litre per 50kg of cement or as per manufacturers specifications. This
includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
295 Stone aggregate 20 mm cum 0.267 1100.00 293.70
297 Stone aggregate 10 mm cum 0.089 1050.00 93.45
298 Stone aggregate 6 mm cum 0.115 400.00 46.00
2202 Carriage of aggregate below 20mm cum 0.471 53.21 25.06
982 Coarse sand cum 0.178 300.00 53.40
2261 Carriage of coarse sand cum 0.178 53.21 9.47
367 Cement (0.2225 cum) tonne 0.231 5200.00 1201.20

2209 Carriage of cement tonne 0.231 47.29 10.92


7254 Hardening compound liter 2.44 29.00 70.76
Labour:-
101 Bhisti Day 0.27 180 48.60
124 Mason 2nd class Day 2.15 223 479.45
114 Beldar Day 1.6 207 331.20
115 Coolie Day 1.88 207 389.16
9999 Carriage L. S. 2.73 1.00 2.73
9999 Sundries L. S. 53.82 1.00 53.82
TOTAL 3108.93
Add 1% for water charges except A 31.09
TOTAL 3140.02
Add for contractor’s profit and 471.00
overheads @15% except on A
Cost of 10 sqm 3611.02
Cost of 1 sqm 361.10
Say 361.10

11.5 62 mm thick cement concrete flooring with concrete hardener topping under layer 50
mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm
nominal size) and to p layer 12mm thick cement hardener consisting of mix 1:2(1 cement
hardener mix : 2 graded stone aggregate 6mm nominal size) by volume. H ardening
compound is mixed @ 2 litre per 50kg of cement or as per manufactures specifications. This
includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
295 Stone aggregate 20 mm cum 0.334 1100.00 367.40
297 Stone aggregate 10 mm cum 0.111 1050.00 116.55
298 Stone aggregate 6 mm cum 0.115 400.00 46.00
2202 Carriage of aggregate below 20mm cum 0.56 53.21 29.80
982 Coarse sand cum 0.222 300.00 66.60
2261 Carriage of coarse sand cum 0.222 53.21 11.81
367 Cement (0.2225 cum) tonne 0.263 5200.00 1367.60
2209 Carriage of cement tonne 0.263 47.29 12.44
7254 Hardening compound liter 2.44 29.00 70.76
Labour:-
101 Bhisti Day 0.27 180 48.60
124 Mason 2nd class Day 2.15 223 479.45
114 Beldar Day 1.86 207 385.02
115 Coolie Day 1.88 207 389.16
9999 Carriage L. S. 2.73 1.00 2.73
9999 Sundries L. S. 53.82 1.00 53.82
TOTAL 3447.74
Add 1% for water charges except A 34.48
TOTAL 3482.21
Add for contractor’s profit and 522.33
overheads @15% except on A
Cost of 10 sqm 4004.55
Cost of 1 sqm 400.45
Say 400.45

11.6 Cement plaster skirting (upto 30 cm height) with cement mortar 1:3 (1 cement : 3 coarse
sand) finished with a floating coat of neat cement.
11.6.1 18 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
Cement mortar 1:3 (1 Cement: 3 Coarse 766.65
sand) (Rate as per item No. 3.8)
cum 0.235 3262.33
367 Cement (0.2225 cum) tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
Labour:-
101 Bhisti Day 0.54 180 97.20
124 Mason 2nd class Day 1.88 223 419.24
115 Coolie Day 1.88 207 389.16
9999 Sundries L. S. 19.76 1.00 19.76
TOTAL 1796.95
Add 1% for water charges except A 17.97
TOTAL 1814.92
Add for contractor’s profit and 272.24
overheads @15% except on A
Cost of 10 sqm 2087.16
Cost of 1 sqm 208.72
Say 208.72

11.7 Cement concrete pavement with 1:2:4 (1 cement : 2 coarse sand : 4 grated stone
aggregate 20 mm nominal size) including finishing complete.
Code Description Unit Quantity Rate Amount
Details of cost for one cum.
Materials:-
(A) Cement concrete 1:2:4 (Rate as per 4362.73
item No. 4.2.3) cum 1 4,362.73
Extra labour for laying in floors etc.
Labour:-
101 Bhisti Day 0.05 180 9.00
124 Mason 2nd class Day 0.35 223 78.05
114 Beldar Day 0.18 207 37.26
9999 Sundries L. S. 19.76 1.00 19.76
TOTAL 4506.80
Add 1% for water charges except A 1.44
TOTAL 4508.24
Add for contractor’s profit and 21.83
overheads @15% except on A
Cost of 1 cum 4530.07
Say 4530.07

11.8 Extra for making chequers of approved pattern on cement concrete floors, steps, landing,
Code
pavements Description
etc. Unit Quantity Rate Amount
Details of cost for 10 sqm.
Labour:-
124 Mason 2nd class Day 0.36 223 80.28
114 Beldar Day 0.36 207 74.52
9999 Sundries L. S. 13.52 1.00 13.52
TOTAL 168.32
Add 1% for water charges except A 1.68
TOTAL 170.00
Add for contractor’s profit and 25.50
overheads @15% except on A
Cost of 10 sqm 195.50
Cost of 1 sqm 19.55
Say 19.55

11.9 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer
34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 6mm thick with white, black, chocolate, grey,
yellow or green marble chips of sizes from lmm to 4mm nominal size laid in cement marble
powder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cement
marble powder mix : 7 marble chips) by volume including cement slurry etc. complete :
11.9.1 Dark shade pigment with ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
296 Stone aggregate 12.5 mm cum 0.227 1050.00 238.35
297 Stone aggregate 10 mm cum 0.076 1050.00 79.80
2202 Carriage of aggregate below 20mm cum 0.303 53.21 16.12
982 Coarse sand cum 0.151 300.00 45.30
2261 Carriage of coarse sand cum 0.151 53.21 8.03
367 Cement (0.2225 cum) tonne 0.1695 5200.00 881.40
2209 Carriage of cement tonne 0.1695 47.29 8.02
785 Marble chips quintal 0.872 115.00 100.28
2268 Carriage of Marble chips cum 0.051 53.21 2.71
784 Marble chips powder quintal 0.007 800.00 5.60
874 Dark shade pigmeny/3.5kg/ 50kg of kilogra 2.84 42.00 119.28
cement m
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
115 Coolie Day 207 0.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine for rubbing of floors Day 1.6 150 240.00
9999 Carriage of marbe powder L. S. 3.64 1.00 3.64
9999 Sundries L. S. 161.46 1.00 161.46
TOTAL 3106.99
Add 1% for water charges 31.07
TOTAL 3138.06
Add for contractor’s profit and 470.71
overheads @15%
Cost of 10 sqm 3608.77
Cost of 1 sqm 360.88
Say 360.88

11.9 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer
34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 6mm thick with white, black, chocolate, grey,
yellow or green marble chips of sizes from lmm to 4mm nominal size laid in cement marble
powder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cement
marble powder mix : 7 marble chips) by volume including cement slurry etc. complete :
11.9.2 Light shade pigment with white cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.9.1 of SH: 3608.77
Flooring sqm 10 360.88
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 2.84 65.00 184.60
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.0405 9500.00 384.75
367 Deduct for grey cement tonne 0.0405 5200.00 -210.60
TOTAL 3848.24
Add 1% for water charges except A 2.39
TOTAL 3850.63
Add for contractor’s profit and 36.28
overheads @15% except on A
Cost of 10 sqm 3886.91
Cost of 1 sqm 388.69
Say 388.69
11.9 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer
34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 6mm thick with white, black, chocolate, grey,
yellow or green marble chips of sizes from lmm to 4mm nominal size laid in cement marble
powder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cement
marble powder mix : 7 marble chips) by volume including cement slurry etc. complete :
11.9.3 Medium shade pigment with 50% white cement and 50% ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.9.1 of SH: 3608.77
Flooring sqm 10 360.88
Add difference of cost due to using light shade pigment instead of dark shade pigment
876 Add for Green or blue medium shade kilogra 2.84 45.00 127.80
pigm ent m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.0203 9500.00 192.85
367 Deduct for grey cement tonne 0.0203 5200.00 -105.56
TOTAL 3704.58
Add 1% for water charges except A 0.96
TOTAL 3705.53
Add for contractor’s profit and 14.52
overheads @15% except on A
Cost of 10 sqm 3720.05
Cost of 1 sqm 372.00
Say 372.00

11.9 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer
34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 6mm thick with white, black, chocolate, grey,
yellow or green marble chips of sizes from lmm to 4mm nominal size laid in cement marble
powder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cement
marble powder mix : 7 marble chips) by volume including cement slurry etc. complete :
11.9.4 White cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
296 Stone aggregate 12.5 mm cum 0.227 1050.00 238.35
297 Stone aggregate 10 mm cum 0.076 1050.00 79.80
2202 Carriage of aggregate below 20mm cum 0.303 53.21 16.12
982 Coarse sand cum 0.151 300.00 45.30
2261 Carriage of coarse sand cum 0.151 53.21 8.03
367 Cement (0.2225 cum) tonne 0.129 5200.00 670.80
2209 Carriage of cement tonne 0.129 47.29 6.10
785 Marble chips quintal 0.958 115.00 110.17
2268 Carriage of Marble chips cum 0.056 53.21 2.98
784 Marble chips powder quintal 0.007 800.00 5.60
368 White Cement tonne 0.0405 9500.00 384.75
2209 Carriage of cement tonne 0.0405 47.29 1.92
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine for rubbing of floors Day 1.6 150 240.00
9999 Sundries L. S. 161.46 1.00 161.46
TOTAL 3168.37
Add 1% for water charges 31.68
TOTAL 3200.06
Add for contractor’s profit and 480.01
overheads @15%
Cost of 10 sqm 3680.06
Cost of 1 sqm 368.01
Say 368.01

11.9 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer
34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 6mm thick with white, black, chocolate, grey,
yellow or green marble chips of sizes from lmm to 4mm nominal size laid in cement marble
powder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cement
marble powder mix : 7 marble chips) by volume including cement slurry etc. complete :
11.9.5 Light shade pigment with ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.9.1 of SH: 3608.77
Flooring sqm 10 360.88
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 2.84 65.00 184.60
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
TOTAL 3674.09
Add 1% for water charges except A 0.65
TOTAL 3674.74
Add for contractor’s profit and 9.90
overheads @15% except on A
Cost of 10 sqm 3684.63
Cost of 1 sqm 368.46
Say 368.46

11.9 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer
34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 6mm thick with white, black, chocolate, grey,
yellow or green marble chips of sizes from lmm to 4mm nominal size laid in cement marble
powder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cement
marble powder mix
11.9.6 Ordinary : 7 marble
cement withoutchips) by volume including cement slurry etc. complete :
any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.9.1 of SH: 3608.77
Flooring sqm 10 360.88
Add difference of cost due to using light shade pigment instead of dark shade pigment
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
Deduct for carriage of pigment L. S. 7.38 1.00 -7.38
TOTAL 3489.49
Add 1% for water charges except A -1.19
TOTAL 3488.29
Add for contractor’s profit and -18.07
overheads @15% except on A
Cost of 10 sqm 3470.22
Cost of 1 sqm 347.02
Say 347.02

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 3lmm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellow or
green marble chips of sizes from 4mm to 7mm nominal size laid in cement marble powder
mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cement marble
powder : 7 marble chips) by volume including cement slurry etc. complete.
11.10.1 Dark shade pigment with Ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
296 Stone aggregate 12.5 mm cum 0.21 1050.00 220.50
297 Stone aggregate 10 mm cum 0.07 1050.00 73.50
2202 Carriage of aggregate below 20mm cum 0.28 53.21 14.90
982 Coarse sand cum 0.14 300.00 42.00
2261 Carriage of coarse sand cum 0.14 53.21 7.45
367 Cement (0.2225 cum) tonne 0.1783 5200.00 927.16
2209 Carriage of cement tonne 0.1783 47.29 8.43
788 Marble chips large size above 4 mm quintal 1.4 115.00 161.00
White & black
2268 Carriage of Marble chips cum 0.082 53.21 4.36
784 Marble chips powder quintal 0.012 800.00 9.60
874 Dark shade pigmeny/3.5kg/ 50kg of kilogra 4.05 42.00 170.10
cement m
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine for rubbing of floors Day 1.6 150 240.00
9999 Carriage of pigment & marbe powder L. S. 5.46 1.00 5.46
9999 Sundries L. S. 134.55 1.00 134.55
TOTAL 3216.00
Add 1% for water charges 32.16
TOTAL 3248.16
Add for contractor’s profit and 487.22
overheads @15%
Cost of 10 sqm 3735.39
Cost of 1 sqm 373.54
Say 373.54

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellow or
green marble chips of sizes from 4mm to 7mm nominal size laid in cement of 4:7 (4 cement
marble powder : 7 marble chips) by volume including cement slurrymarble powder mix 3:1
(3 cement: 1 marble powder) by weight in proportion etc. complete.
11.10.2 Light shade pigment with white cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.10.1 of SH: 3735.39
Flooring sqm 10 373.54
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 4.05 65.00 263.25
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 4.05 42.00 -170.10
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.0578 9500.00 549.10
367 Deduct for grey cement tonne 0.0578 5200.00 -300.56
TOTAL 4077.08
Add 1% for water charges except A 3.42
TOTAL 4080.49
Add for contractor’s profit and 51.77
overheads @15% except on A
Cost of 10 sqm 4132.26
Cost of 1 sqm 413.23
Say 413.23

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellow or
green marble chips of sizes from 4mm to 7mm nominal size laid in cement of 4:7 (4 cement
marble powder : 7 marble chips) by volume including cement slurrymarble powder mix 3:1
(3 cement: 1 marble powder) by weight in proportion etc. complete.
11.10.3 Medium shade pigment with 50% white cement and 50% ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.10.1 of SH: 3735.39
Flooring sqm 10 373.54
Add difference of cost due to using light shade pigment instead of dark shade pigment
876 Add for Green or blue medium shade kilogra 4.05 45.00 182.25
pigm ent m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 4.05 42.00 -170.10
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.0289 9500.00 274.55
367 Deduct for grey cement tonne 0.0289 5200.00 -150.28
TOTAL 3871.81
Add 1% for water charges except A 1.36
TOTAL 3873.17
Add for contractor’s profit and 20.67
overheads @15% except on A
Cost of 10 sqm 3893.84
Cost of 1 sqm 389.38
Say 389.38

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellow or
green marble chips of sizes from 4mm to 7mm nominal size laid in cement of 4:7 (4 cement
marble powder : 7 marble chips) by volume including cement slurrymarble powder mix 3:1
(3 cement: 1 marble powder) by weight in proportion etc. complete.
11.10.4 White cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
296 Stone aggregate 12.5 mm cum 0.21 1050.00 220.50
297 Stone aggregate 10 mm cum 0.07 1050.00 73.50
2202 Carriage of aggregate below 20mm cum 0.28 53.21 14.90
982 Coarse sand cum 0.14 300.00 42.00
2261 Carriage of coarse sand cum 0.14 53.21 7.45
367 Cement (0.2225 cum) tonne 0.1205 5200.00 626.60
2209 Carriage of cement tonne 0.1205 47.29 5.70
788 Marble chips large size above 4 mm quintal 1.4 115.00 161.00
2268 Carriage of Marble chips cum 0.082 53.21 4.36
784 Marble chips powder quintal 0.012 800.00 9.60
368 White Cement tonne 0.0578 9500.00 549.10
2209 Carriage of cement tonne 0.0578 47.29 2.73
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine for rubbing of floors Day 1.6 150 240.00
9999 Sundries L. S. 161.46 1.00 161.46
TOTAL 3315.89
Add 1% for water charges 33.16
TOTAL 3349.05
Add for contractor’s profit and 502.36
overheads @15%
Cost of 10 sqm 3851.41
Cost of 1 sqm 385.14
Say 385.14

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellow or
green marble chips of sizes from 4mm to 7mm nominal size laid in cement of 4:7 (4 cement
marble powder : 7 marble chips) by volume including cement slurrymarble powder mix 3:1
(3 cement: 1 marble powder) by weight in proportion etc. complete.
11.10.5 Light shade pigment with ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.10.1 of SH: 3735.39
Flooring sqm 10 373.54
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 2.84 65.00 184.60
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
TOTAL 3800.71
Add 1% for water charges except A 0.65
TOTAL 3801.36
Add for contractor’s profit and 9.90
overheads @15% except on A
Cost of 10 sqm 3811.26
Cost of 1 sqm 381.13
Say 381.13

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellow or
green marble chips of sizes from 4mm to 7mm nominal size laid in cement of 4:7 (4 cement
marble powder : 7 marble chips) by volume including cement slurrymarble powder mix 3:1
(3 cement:
11.10.6 1 marble
Ordinary powder)
cement by weight
without in proportion etc. complete.
any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
296 Stone aggregate 12.5 mm cum 0.21 1050.00 220.50
297 Stone aggregate 10 mm cum 0.07 1050.00 73.50
2202 Carriage of aggregate below 20mm cum 0.28 53.21 14.90
982 Coarse sand cum 0.14 300.00 42.00
2261 Carriage of coarse sand cum 0.14 53.21 7.45
367 Cement (0.2225 cum) tonne 0.1205 5200.00 626.60
2209 Carriage of cement tonne 0.1205 47.29 5.70
788 Marble chips large size above 4 mm quintal 1.4 115.00 161.00
2268 Carriage of Marble chips cum 0.082 53.21 4.36
784 Marble chips powder quintal 0.012 800.00 9.60
367 White Cement tonne 0.0578 5200.00 300.56
2209 Carriage of cement tonne 0.0578 47.29 2.73
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine for rubbing of floors Day 1.6 150 240.00
9999 Sundries L. S. 134.55 1.00 134.55
TOTAL 3040.44
Add 1% for water charges 30.40
TOTAL 3070.85
Add for contractor’s profit and 460.63
overheads @15%
Cost of 10 sqm 3531.47
Cost of 1 sqm 353.15
Say 353.15

11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellow or
green marble chips of sizes from 7mm to 10mm nominal size laid in cement marble powder
mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cement marble
powder mix : 3 marble chips) by volume including cement slurry etc. complete :
11.11.1 Dark shade pigment with ordinary cement.
Code Discription Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials-
296 12.5mm stone aggregate cum 0.19 1050.00 199.50
297 10mm stone aggregate cum 0.06 1050.00 63.00
2202 Carriage of stone aggregate cum 0.25 53.21 13.30
982 Coarse sand cum 0.125 300.00 37.50
2203 Carriage of coarse sand cum 0.125 53.21 6.65
367 Cement tonne 0.0897 5200.00 466.44
367 Cement for slurry tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.1097 47.29 5.19
788 Marble chips 7mm to 10mm size quintal 1.734 115.00 199.41
2268 Carriage of marble chips cum 0.102 53.21 5.43
368 Cement tonne 0.081 9500.00 769.50
2209 Carriage of cement tonne 0.081 47.29 3.83
784 Marble powder cum 0.017 800.00 13.60
874 Dark shade pigment @ 3.5kg/50kg of kilogra 5.67 42.00 238.14
cement m
9999 Carriage of pigment and marble powder L.S 6.24 1.00 6.24
etc.
Labour:-
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
101 Bhis ti Day 1.04 180 187.20
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine Day 1.6 150 240.00
9999 Sundries L.S. 156.13 1.00 156.13
TOTAL 3525.35
Add 1% for water charges 35.25
TOTAL 3560.60
Add for contractor’s profit and 534.09
overheads @15%
Cost of 10 sqm 4094.69
Cost of 1 sqm 409.47
Say 409.47
11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellow or
green marble chips of sizes from 7mm to 10mm nominal size laid in cement marble powder
mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cement marble
powder mix : 3 marble chips) by volume including cement slurry etc. complete :
11.11.2 Light shade pigment with white cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.11.1 of SH: 4094.69
Flooring sqm 10 409.47
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 5.67 65.00 368.55
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 5.67 42.00 -238.14
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.081 9500.00 769.50
367 Deduct for grey cement tonne 0.081 5200.00 -421.20
TOTAL 4573.40
Add 1% for water charges except A 4.79
TOTAL 4578.19
Add for contractor’s profit and 72.52
overheads @15% except on A
Cost of 10 sqm 4650.71
Cost of 1 sqm 465.07
Say 465.07
Code Discription Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cost same as per item No 11.11.1 sqm 10 409.47 4094.69
(A) Add difference of cost due to using
light shade pigment instead of dark
shade pigment

11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellow or
green marble chips of sizes from 7mm to 10mm nominal size laid in cement marble powder
mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cement marble
powder mix : 3 marble chips) by volume including cement slurry etc. complete :
11.11.3 Medium shade pigment with 50% white cement and 50% ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.11.1 of SH: 4094.69
Flooring sqm 10 409.47
Add difference of cost due to using light shade pigment instead of dark shade pigment
876 Add for Green or blue medium shade kilogra 5.67 45.00 255.15
pigm ent m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 5.67 42.00 -238.14
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.0405 9500.00 384.75
367 Deduct for grey cement tonne 0.0405 5200.00 -210.60
TOTAL 4285.85
Add 1% for water charges except A 1.91
TOTAL 4287.76
Add for contractor’s profit and 28.96
overheads @15% except on A
Cost of 10 sqm 4316.73
Cost of 1 sqm 431.67
Say 431.67

11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellow or
green marble chips of sizes from 7mm to 10mm nominal size laid in cement marble powder
mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cement marble
powder mix : 3 marble chips) by volume including cement slurry etc. complete :
11.11.4 White cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
296 Stone aggregate 12.5 mm cum 0.19 1050.00 199.50
297 Stone aggregate 10 mm cum 0.06 1050.00 63.00
2202 Carriage of aggregate below 20mm cum 0.25 53.21 13.30
982 Coarse sand cum 0.125 300.00 37.50
2261 Carriage of coarse sand cum 0.125 53.21 6.65
367 Cement (0.2225 cum) tonne 0.1097 5200.00 570.44
2209 Carriage of cement tonne 0.1097 47.29 5.19
788 Marble chips large size above 4 mm quintal 1.916 115.00 220.34
2268 Carriage of Marble chips cum 0.1128 53.21 6.00
784 Marble chips powder quintal 0.017 800.00 13.60
368 White Cement tonne 0.081 9500.00 769.50
2209 Carriage of cement tonne 0.081 47.29 3.83
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine for rubbing of floors Day 1.6 150 240.00
9999 Sundries L. S. 134.55 1.00 134.55
TOTAL 3480.39
Add 1% for water charges 34.80
TOTAL 3515.20
Add for contractor’s profit and 527.28
overheads @15%
Cost of 10 sqm 4042.48
Cost of 1 sqm 404.25
Say 404.25
11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellow or
green marble chips of sizes from 7mm to 10mm nominal size laid in cement marble powder
mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cement marble
powder mix : 3 marble chips) by volume including cement slurry etc. complete :
11.11.5 Light shade pigment with ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A)Rate as per item no 11.11.1 of SH: 4094.69
Flooring sqm 10 409.47
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 5.67 65.00 368.55
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 5.67 42.00 -238.14
50kg of cement m
TOTAL 4225.10
Add 1% for water charges except A 1.30
TOTAL 4226.41
Add for contractor’s profit and 19.76
overheads @15% except on A
Cost of 10 sqm 4246.16
Cost of 1 sqm 424.62
Say 424.62

11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under
layer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellow or
green marble chips of sizes from 7mm to 10mm nominal size laid in cement marble powder
mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cement marble
powder
11.11.6 mix : 3 marble
Ordinary chips)
cement by volume
without including cement slurry etc. complete :
any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
296 Stone aggregate 12.5 mm cum 0.19 1050.00 199.50
297 Stone aggregate 10 mm cum 0.06 1050.00 63.00
2202 Carriage of aggregate below 20mm cum 0.25 53.21 13.30
982 Coarse sand cum 0.125 300.00 37.50
2261 Carriage of coarse sand cum 0.125 53.21 6.65
367 Cement (0.2225 cum) tonne 0.1097 5200.00 570.44
2209 Carriage of cement tonne 0.1097 47.29 5.19
788 Marble chips large size above 4 mm quintal 1.916 115.00 220.34
2268 Carriage of Marble chips cum 0.1128 53.21 6.00
784 Marble chips powder quintal 0.017 800.00 13.60
367 White Cement tonne 0.081 5200.00 421.20
2209 Carriage of cement tonne 0.081 47.29 3.83
Labour:-
101 Bhisti Day 1.04 180 187.20
124 Mason 2nd class Day 1.79 223 399.17
114 Beldar Day 1.99 207 411.93
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

127 Mixer operator Day 0.03 223 6.69


2 Mixer Day 0.03 400 12.00
13 Machine for rubbing of floors Day 1.6 150 240.00
9999 Sundries L. S. 134.55 1.00 134.55
TOTAL 3132.09
Add 1% for water charges 31.32
TOTAL 3163.41
Add for contractor’s profit and 474.51
overheads @15%
Cost of 10 sqm 3637.93
Cost of 1 sqm 363.79
Say 363.79

11.12 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish,
top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes
from smallest to 4 mm nominal size laid in cement marble powder mix 3:1 (3 cement : 1
marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble
chips) by volume :
11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3 coarse
sand):
11.12.1.1 Dark shade pigment with ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
Cement mortar 1:3 (1 Cement: 3 Coarse 567.65
sand) (Rate as per item No. 3.8)
cum 0.174 3262.33
785 Marble chips large size above 4 mm quintal 0.872 115.00 100.28
2268 Carriage of Marble chips cum 0.051 53.21 2.71
784 Marble chips powder quintal 0.007 800.00 5.60
367 Cement tonne 0.0405 5200.00 210.60
2209 Carriage of cement tonne 0.0405 47.29 1.92
874 Dark shade pigmeny/3.5kg/ 50kg of kilogra 2.84 42.00 119.28
cement m
9999 Carriage of pigm ent & marble powder L. S. 3.64 1.00 3.64
etc.
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 3 223 669.00
114 Beldar Day 3 207 621.00
139 Beldar for rubbing and polishing (Special Day 7 180 1260.00

9999 Sundries L. S. 201.89 1.00 201.89


TOTAL 3943.56
Add 1% for water charges 39.44
TOTAL 3983.00
Add for contractor’s profit and 597.45
overheads @15%
Cost of 10 sqm 4580.45
Cost of 1 sqm 458.05
Say 458.05
11.12 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish,
top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes
from smallest to 4 mm nominal size laid in cement marble powder mix 3:1 (3 cement : 1
marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble
chips) by volume :
11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3 coarse
sand):
11.12.1.2 Light shade pigment with white cement.
Code Description Unit Quantity Rate Amount
(A) Details of cost for 10 sqm.
Cost same as per item No. 11.12.1.1 cum 10 458.05 4580.45
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 2.84 65.00 184.60
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.0405 9500.00 384.75
367 Deduct for grey cement tonne 0.0405 5200.00 -210.60
TOTAL 4819.92
Add 1% for water charges except A 2.39
TOTAL 4822.31
Add for contractor’s profit and 36.28
overheads @15% except on A
Cost of 10 sqm 4858.59
Cost of 1 sqm 485.86
Say 485.86
392.95
11.12 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish,
top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes
from smallest to 4 mm nominal size laid in cement marble powder mix 3:1 (3 cement : 1
marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble
chips) by volume :
11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3 coarse
sand):
11.12.1.2 Light shade pigment with white cement.
Code Description Unit Quantity Rate Amount
(A) Details of cost for 10 sqm.
Cost same as per item No. 11.12.1.1 cum 10 458.05 4580.45
Add difference of cost due to using light shade pigment instead of dark shade pigment
876 Add for Green or blue medium shade kilogra 2.84 45.00 127.80
pigm ent m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
Addd difference of cost due to using white cement instead of grey cement
368 Add for White Cement tonne 0.0203 9500.00 192.85
367 Deduct for grey cement tonne 0.0203 5200.00 -105.56
TOTAL 4676.26
Add 1% for water charges except A 0.96
TOTAL 4677.22
Add for contractor’s profit and 14.52
overheads @15% except on A
Cost of 10 sqm 4691.73
Cost of 1 sqm 469.17
Say 469.17
11.12 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish,
top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes
from smallest to 4 mm nominal size laid in cement marble powder mix 3:1 (3 cement : 1
marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble
chips) by volume :
11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3(1 cement: 3 coarse
sand):
11.12.1.4 White cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:-
Cement mortar 1:3 (1 Cement: 3 Coarse 567.65
sand) (Rate as per item No. 3.8)
cum 0.174 3262.33
785 Marble chips large size above 4 mm quintal 0.958 115.00 110.17
2268 Carriage of Marble chips cum 0.056 53.21 2.98
784 Marble chips powder quintal 0.007 800.00 5.60
368 White Cement tonne 0.0405 9500.00 384.75
2209 Carriage of cement tonne 0.0405 47.29 1.92
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 3 223 669.00
114 Beldar Day 3 207 621.00
139 Beldar for rubbing and polishing (Special Day 7 180 1260.00

9999 Sundries L. S. 201.89 1.00 201.89


TOTAL 4004.95
Add 1% for water charges 40.05
TOTAL 4045.00
Add for contractor’s profit and 606.75
overheads @15%
Cost of 10 sqm 4651.75
Cost of 1 sqm 465.17
Say 465.17

11.12 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish,
top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes
from smallest to 4 mm nominal size laid in cement marble powder mix 3:1 (3 cement : 1
marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble
chips) by volume :
11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3
coarse sand):
11.12.1.5 Light shade pigment with ordinary cement.
Code Description Unit Quantity Rate Amount
(A) Details of cost for 10 sqm.
Cost same as per item No. 11.12.1.1 cum 10 458.05 4580.45
Add difference of cost due to using light shade pigment instead of dark shade pigment
875 Add for light shade pigmeny/3.5kg/ kilogra 2.84 65.00 184.60
50kg of cement m
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
TOTAL 4645.77
Add 1% for water charges except A 0.65
TOTAL 4646.42
Add for contractor’s profit and 9.90
overheads @15% except on A
Cost of 10 sqm 4656.32
Cost of 1 sqm 465.63
Say 465.63

11.12 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish,
top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes
from smallest to 4 mm nominal size laid in cement marble powder mix 3:1 (3 cement : 1
marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble
chips) by volume :
11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3
coarse sand):
11.12.1.6 Ordinary cement without any pigment.
Code Description Unit Quantity Rate Amount
(A) Details of cost for 10 sqm.
Cost same as per item No. 11.12.1.1 cum 10 458.05 4580.45
Add difference of cost due to using light shade pigment instead of dark shade pigment
874 Deduct for Dark shade pigmeny/3.5kg/ kilogra 2.84 42.00 -119.28
50kg of cement m
9999 Deduct for Carriage of pigment L. S. 7.38 1.00 -7.38
TOTAL 4453.79
Add 1% for water charges except A -1.27
TOTAL 4452.52
Add for contractor’s profit and -19.19
overheads @15% except on A
Cost of 10 sqm 4433.33
Cost of 1 sqm 443.33
Say 443.33

11.13 Providing and fixing glass strips in joints of terrazo/ cement concrete floors.
11.13.1 40 mm wide and 4 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre length
Materials-
1149 Glass strips metre 11 6.00 66.00
9999 Carriage of glass L. S 2.73 1.00 2.73
Labour:-
124 Mason 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
9999 Sundries L. S. 13.52 1.00 13.52
TOTAL 189.75
Add 1% for water charges 1.90
TOTAL 191.65
Add for contractor’s profit and 28.75
overheads @15%
Cost of 10 m 220.39
Cost of 1 m 22.04
Say 22.04

11.14 Extra for laying terrazo flooring on staircase treads not exceeding 30 cm in width
including cost of forming, nosing etc.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Labour:-
124 Mason 2nd class Day 0.3 223 66.90
114 Beldar Day 0.3 207 62.10
115 Coolie Day 0.3 207 62.10
TOTAL 191.10
Add 1% for water charges 1.91
TOTAL 193.01
Add for contractor’s profit and 28.95
overheads @15%
Cost of 10 sqm 221.96
Cost of 1 sqm 22.20
Say 22.20

11.15 Crazy marble stone flooring including filling the gaps with light shade pigment with
white cement marble powder mixture (3 parts of white cement : 1 part of marble powder) by
weight in proportion of 4:7 (4 cement marble powder mix : 7 white, black or white and black
marble chips of sizes from 1mm to 4mm nominal size by volume) and under layer 25mm
thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm
nominal size) rubbing, polishing and ceme-nt slurry etc. complete :
11.15.1 18 mm thick crazy marble stone white, black or as specified.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
(A) Concrete 1:2:4 (Rate same as in item no. cum 0.25 1132.52
11.7) 4530.07
367 Cement tonne 0.04 5200.00 208.00
2209 Carriage of cement tonne 0.04 47.29 1.89
2710 Marble pieces for crazy flooring quintal 2.4 105.00 252.00
368 White Cement tonne 0.0405 9500.00 384.75
2209 Carriage of cement tonne 0.0405 47.29 1.92
785 Marble chips large size above 4 mm quintal 0.872 115.00 100.28
2268 Carriage of Marble chips cum 0.051 53.21 2.71
784 Marble chips powder quintal 0.007 800.00 5.60
875 Add for light shade pigmeny/3.5kg/ kilogra 2.84 65.00 184.60
50kg of cement m
9999 Carriage of pigm ent & marble powder L. S. 3.64 1.00 3.64
etc.
2216 Carriage of marble stone pieces tonne 0.24 47.29 11.35
Labour:-
101 Bhisti Day 0.54 180 97.20
123 Mason 1st class Day 1.2 270 324.00
114 Beldar Day 1.5 207 310.50
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 134.55 1.00 134.55
TOTAL 4862.51
Add 1% for water charges except A 37.30
TOTAL 4899.81
Add for contractor’s profit and 565.09
overheads @15% except on A
Cost of 10 sqm 5464.90
Cost of 1 sqm 546.49
Say 546.49

11.16 Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mm laid in
floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade
of the tiles including rubbing and polishing complete with precast tiles on 20mm thick bed of
cement mortar 1:4(1 cement :4 coarse sand):
11.16.1 Light shade using white cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
367 Cement tonne 0.044 5200.00 228.80
1201 Terrazo tiles sqm 11 198.00 2178.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
368 White Cement tonne 0.044 9500.00 418.00
2209 Carriage of cement tonne 0.088 47.29 4.16
875 Add for light shade pigmeny/3.5kg/ kilogra 3.08 65.00 200.20
50kg of cement m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 161.98 1.00 161.98
TOTAL 5180.33
Add 1% for water charges 51.80
TOTAL 5232.14
Add for contractor’s profit and 784.82
overheads @15%
Cost of 10 sqm 6016.96
Cost of 1 sqm 601.70
Say 601.70

11.16 Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mm laid in
floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade
of the tiles including rubbing and polishing complete with precast tiles on 20mm thick bed of
cement mortar 1:4(1 cement :4 coarse sand):
11.16.2 Medium shade using 50%white cement and 50% ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
367 Cement tonne 0.066 5200.00 343.20
1202 Terrazo tiles sqm 11 175.00 1925.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
368 White Cement tonne 0.022 9500.00 209.00
2209 Carriage of cement tonne 0.088 47.29 4.16
876 Green or blue medium shade pigm ent kilogra 3.08 45.00 138.60
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 161.98 1.00 161.98
TOTAL 4771.13
Add 1% for water charges 47.71
TOTAL 4818.84
Add for contractor’s profit and 722.83
overheads @15%
Cost of 10 sqm 5541.67
Cost of 1 sqm 554.17
Say 554.17

11.16 Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mm laid in
floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade
of the tiles including rubbing and polishing complete with precast tiles on 20mm thick bed of
cement mortar 1:4(1 cement :4 coarse sand):
11.16.3 Dark shade using ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
367 Cement tonne 0.088 5200.00 457.60
1203 Terrazo tiles sqm 11 170.00 1870.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
2209 Carriage of cement tonne 0.088 47.29 4.16
874 Dark shade pigm ent kilogra 3.08 42.00 129.36
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 161.98 1.00 161.98
TOTAL 4612.29
Add 1% for water charges 46.12
TOTAL 4658.41
Add for contractor’s profit and 698.76
overheads @15%
Cost of 10 sqm 5357.18
Cost of 1 sqm 535.72
Say 535.72

11.16 Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mm laid in
floors, and landings, jointed with neat cement slurry mixed with pigment to match the shade
of the tiles including rubbing and polishing complete with precast tiles on 20mm thick bed of
cement mortar 1:4(1 cement :4 coarse sand):
11.16.4 Ordinary cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
367 Cement tonne 0.088 5200.00 457.60
1203 Terrazo tiles sqm 11 170.00 1870.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
2209 Carriage of cement tonne 0.088 47.29 4.16
874 Less for Dark shade pigm ent kilogra -2.84 42.00 -119.28
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 161.98 1.00 161.98
TOTAL 4363.65
Add 1% for water charges 43.64
TOTAL 4407.29
Add for contractor’s profit and 661.09
overheads @15%
Cost of 10 sqm 5068.38
Cost of 1 sqm 506.84
Say 506.84

11.17 Extra if terrazo tiles are laid in treads of steps not exceeding 30 pccm in width.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Labour:-
124 Mason 2nd class Day 0.22 223 49.06
139 Beldar for rubbing and polishing (Special Day 0.65 180 117.00

115 Coolie Day 0.22 207 45.54


TOTAL 211.60
Add 1% for water charges 2.12
TOTAL 213.72
Add for contractor’s profit and 32.06
overheads @15%
Cost of 10 sqm 245.77
Cost of 1 sqm 24.58
Say 24.58

11.18 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm in
skirting and risers of steps not exceeding 30 cm in height on 12 mm thick cement plaster 1:3
(1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigment to match the
shade of the tiles, including rubbing and polishing complete with tiles of:
11.18.1 Light shade using white cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:3 (1 Cement: 3 Coarse 469.78
sand) (Rate as per item No. 3.8)
cum 0.144 3262.33
1201 Terrazo tiles sqm 11 198.00 2178.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
368 White Cement tonne 0.066 9500.00 627.00
2209 Carriage of cement tonne 0.066 47.29 3.12
875 Light shade pigmeny/3.5kg/ 50kg of kilogra 4.62 65.00 300.30
cement m
Labour:-
124 Mason 2nd class Day 3.25 223 724.75
115 Coolie Day 3.25 207 672.75
139 Beldar for rubbing and polishing (Special Day 7.6 180 1368.00

9999 Sundries including carborandum etc. L. S. 161.46 1.00 161.46


TOTAL 6545.59
Add 1% for water charges 65.46
TOTAL 6611.04
Add for contractor’s profit and 991.66
overheads @15%
Cost of 10 sqm 7602.70
Cost of 1 sqm 760.27
Say 760.27

11.18 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm in
skirting and risers of steps not exceeding 30 cm in height on 12 mm thick cement plaster 1:3
(1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigment to match the
shade of the tiles, including rubbing and polishing complete with tiles of:
11.18.2 Medium shades using 50% white cement and 50% ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:3 (1 Cement: 3 Coarse 469.78
sand) (Rate as per item No. 3.8)
cum 0.144 3262.33
1202 Terrazo tiles sqm 11 175.00 1925.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.033 5200.00 171.60
368 White Cement tonne 0.033 9500.00 313.50
2209 Carriage of cement tonne 0.066 47.29 3.12
876 Green or blue medium shade pigm ent kilogra 4.62 45.00 207.90
m
Labour:-

124 Mason 2nd class Day 3.25 223 724.75


115 Coolie Day 3.25 207 672.75
139 Beldar for rubbing and polishing (Special Day 7.6 180 1368.00

9999 Sundries including carborandum etc. L. S. 161.46 1.00 161.46


TOTAL 5588.51
Add 1% for water charges 55.89
TOTAL 5644.40
Add for contractor’s profit and 846.66
overheads @15%
Cost of 10 sqm 6491.06
Cost of 1 sqm 649.11
Say 649.11

11.18 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm in
skirting and risers of steps not exceeding 30 cm in height on 12 mm thick cement plaster 1:3
(1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigment to match the
shade of the tiles, including rubbing and polishing complete with tiles of:
11.18.3 Dark shade using ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:3 (1 Cement: 3 Coarse 469.78
sand) (Rate as per item No. 3.8)
cum 0.144 3262.33
1203 Terrazo tiles sqm 11 170.00 1870.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.066 5200.00 343.20
2209 Carriage of cement tonne 0.066 47.29 3.12
874 Dark shade pigm ent kilogra 4.62 42.00 194.04
m
Labour:-
124 Mason 2nd class Day 3.25 223 724.75
115 Coolie Day 3.25 207 672.75
139 Beldar for rubbing and polishing (Special Day 7.6 180 1368.00

9999 Sundries including carborandum etc. L. S. 161.46 1.00 161.46


TOTAL 5847.53
Add 1% for water charges 58.48
TOTAL 5906.00
Add for contractor’s profit and 885.90
overheads @15%
Cost of 10 sqm 6791.90
Cost of 1 sqm 679.19
Say 679.19

11.18 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm in
skirting and risers of steps not exceeding 30 cm in height on 12 mm thick cement plaster 1:3
(1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigment to match the
shade of the tiles, including rubbing and polishing complete with tiles of:
11.18.4 Ordinary cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:3 (1 Cement: 3 Coarse 469.78
sand) (Rate as per item No. 3.8)
cum 0.144 3262.33
1203 Terrazo tiles sqm 11 170.00 1870.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.066 5200.00 343.20
2209 Carriage of cement tonne 0.066 47.29 3.12
874 Less for Dark shade pigm ent kilogra -2.84 42.00 -119.28
m
Labour:-
124 Mason 2nd class Day 3.25 223 724.75
115 Coolie Day 3.25 207 672.75
139 Beldar for rubbing and polishing (Special Day 7.6 180 1368.00

9999 Sundries including carborandum etc. L. S. 161.46 1.00 161.46


TOTAL 5534.21
Add 1% for water charges 55.34
TOTAL 5589.55
Add for contractor’s profit and 838.43
overheads @15%
Cost of 10 sqm 6427.98
Cost of 1 sqm 642.80
Say 642.80

11.19 Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in
floors jointed with neat cement slurry mixed with pigment to match the shade of the tiles
including rubbing and polishing complete on 20 mm thick bed of cement mortar 1:4 (1
cement :4 coarse sand):
1.19.1 Light shade using white cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
1227 Terrazo tiles sqm 11 230.00 2530.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.044 5200.00 228.80
368 White Cement tonne 0.044 9500.00 418.00
2209 Carriage of cement tonne 0.088 47.29 4.16
875 Light shade pigmeny/3.5kg/ 50kg of kilogra 3.08 65.00 200.20
cement m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 161.98 1.00 161.98
TOTAL 5532.33
Add 1% for water charges 55.32
TOTAL 5587.66
Add for contractor’s profit and 838.15
overheads @15%
Cost of 10 sqm 6425.80
Cost of 1 sqm 642.58
Say 642.58

11.19 Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in
floors jointed with neat cement slurry mixed with pigment to match the shade of the tiles
including rubbing and polishing complete on 20 mm thick bed of cement mortar 1:4 (1
cement :4 coarse sand):
11.19.2 Medium shade using 50% white cement, 50% ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
1228 Terrazo tiles sqm 11 200.00 2200.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.066 5200.00 343.20
368 White Cement tonne 0.022 9500.00 209.00
2209 Carriage of cement tonne 0.088 47.29 4.16
876 Green or blue medium shade pigm ent kilogra 3.08 45.00 138.60
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 161.98 1.00 161.98
TOTAL 4468.17
Add 1% for water charges 44.68
TOTAL 4512.85
Add for contractor’s profit and 676.93
overheads @15%
Cost of 10 sqm 5189.78
Cost of 1 sqm 518.98
Say 518.98

11.19 Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in
floors jointed with neat cement slurry mixed with pigment to match the shade of the tiles
including rubbing and polishing complete on 20 mm thick bed of cement mortar 1:4 (1
cement :4 coarse sand):
11.19.3 Dark shade using ordinary cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
1229 Terrazo tiles sqm 11 170.00 1870.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.088 5200.00 457.60
2209 Carriage of cement tonne 0.088 47.29 4.16
874 Dark shade pigm ent kilogra 3.08 42.00 129.36
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 161.98 1.00 161.98
TOTAL 4612.29
Add 1% for water charges 46.12
TOTAL 4658.41
Add for contractor’s profit and 698.76
overheads @15%
Cost of 10 sqm 5357.18
Cost of 1 sqm 535.72
Say 535.72

11.19 Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in
floors jointed with neat cement slurry mixed with pigment to match the shade of the tiles
including rubbing and polishing complete on 20 mm thick bed of cement mortar 1:4 (1
cement :4 coarse sand):
11.19.4 Ordinary cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
1229 Terrazo tiles sqm 11 170.00 1870.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.088 5200.00 457.60
2209 Carriage of cement tonne 0.088 47.29 4.16
874 Dark shade pigm ent kilogra -2.84 42.00 -119.28
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
139 Beldar for rubbing and polishing (Special Day 1 180 180.00

13 Machine for rubbing of floors Day 1.6 150 240.00


9999 Sundries including carborandum etc. L. S. 162.59 1.00 162.59
TOTAL 4364.26
Add 1% for water charges 43.64
TOTAL 4407.90
Add for contractor’s profit and 661.19
overheads @15%
Cost of 10 sqm 5069.09
Cost of 1 sqm 506.91
Say 506.91

11.20 Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard jointed
with neat cement slurry mixed with pigment to match the shade of tiles including rubbing
and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse
sand).
11.20.1 Light shade using white cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 567.64
No.3.9) cum 0.22 2580.18
7070 Chequerred C.C. tiles sqm 11 415.00 4565.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.044 5200.00 228.80
368 White Cement tonne 0.048 9500.00 456.00
2209 Carriage of cement tonne 0.092 47.29 4.35
875 Light shade pigmeny/3.5kg/ 50kg of kilogra 3.08 65.00 200.20
cement m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
TOTAL 7013.22
Add 1% for water charges 70.13
TOTAL 7083.35
Add for contractor’s profit and 1062.50
overheads @15%
Cost of 10 sqm 8145.86
Cost of 1 sqm 814.59
Say 814.59

11.20 Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard jointed
with neat cement slurry mixed with pigment to match the shade of tiles including rubbing
and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse
sand).
11.20.2 Medium shade using 50% white cement 50% Grey cement.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 567.64
No.3.9) cum 0.22 2580.18
7237 Chequerred C.C. tiles sqm 11 305.00 3355.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.068 5200.00 353.60
368 White Cement tonne 0.024 9500.00 228.00
2209 Carriage of cement tonne 0.092 47.29 4.35
876 Green or blue medium shade pigm ent kilogra 3.08 45.00 138.60
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
TOTAL 5638.42
Add 1% for water charges 56.38
TOTAL 5694.80
Add for contractor’s profit and 854.22
overheads @15%
Cost of 10 sqm 6549.03
Cost of 1 sqm 654.90
Say 654.90

11.20 Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard jointed
with neat cement slurry mixed with pigment to match the shade of tiles including rubbing
and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse
sand).
11.20.3 Dark shade using ordinary Cement
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 567.64
No.3.9) cum 0.22 2580.18
7236 Chequerred C.C. tiles sqm 11 193.00 2123.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.092 5200.00 478.40
2209 Carriage of cement tonne 0.092 47.29 4.35
874 Dark shade pigm ent kilogra 3.08 42.00 129.36
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
TOTAL 4293.98
Add 1% for water charges 42.94
TOTAL 4336.92
Add for contractor’s profit and 650.54
overheads @15%
Cost of 10 sqm 4987.46
Cost of 1 sqm 498.75
Say 498.75

11.20 Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard jointed
with neat cement slurry mixed with pigment to match the shade of tiles including rubbing
and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse
sand).
11.20.4 Ordinary cement without any pigment.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 567.64
No.3.9) cum 0.22 2580.18
7236 Chequerred C.C. tiles sqm 11 193.00 2123.00
9999 Carriage of tiles L. S. 40.43 1.00 40.43
367 Cement tonne 0.092 5200.00 478.40
2209 Carriage of cement tonne 0.092 47.29 4.35
874 Dark shade pigm ent kilogra -2.84 42.00 -119.28
m
Labour:-
101 Bhisti Day 1 180 180.00
124 Mason 2nd class Day 1.6 223 356.80
115 Coolie Day 2 207 414.00
TOTAL 4045.34
Add 1% for water charges 40.45
TOTAL 4085.79
Add for contractor’s profit and 612.87
overheads @15%
Cost of 10 sqm 4698.66
Cost of 1 sqm 469.87
Say 469.87

11.21 : Providing and fixing 10mm thick acid and/or alkali resistant tiles of approved make
and colour using acid and/or alkali resisting mortar bedding and joints filled with acid and/or
alkali resisting cement as per IS : 4457 complete as per the direction of Engineer-in-
Charge.
11.21.1 : In flooring on a bed of 10 mm thick mortar 1:4(1 acid proof cement: 4 coarse sand).
11.21.1.1:Acid and alkali resistant tile.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
Cement mortar 1:4 (Rate asper item 30.96
No.3.9) cum 0.012 2580.18
7077 Acid proof tiles of size 300x300mm 10 Nos. 12 460.00 552.00

367 Cement tonne 0.0033 5200.00 17.16


9999 Carriage of tiles L. S. 6.24 1.00 6.24
9999 Mortar for pointing in acid/alkali L. S. 40.43 1.00 40.43
resistant
7024 Acid proof cement tonne tonne 0.0079 7400.00 58.46
367 Less for ordinary Cement tonne -0.0079 5200.00 -41.08
Labour:-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 Sundries including carriage of cement L. S. 26.91 1.00 26.91
etc.
TOTAL 786.48
Add 1% for water charges 7.86
TOTAL 794.35
Add for contractor’s profit and 119.15
overheads @15%
Cost of 1 sqm 913.50
Say 913.50

11.21 : Providing and fixing 10mm thick acid and/or alkali resistant tiles of approved make
and colour using acid and/or alkali resisting mortar bedding and joints filled with acid and/or
alkali resisting cement as per IS : 4457 complete as per the direction of Engineer-in-
Charge.
11.21.2 In dado/skirting on 12 mm thick mortar 1:4 (1 acid proof cement: 4 coarse sand).
11.21.2.1 Acid and alkali resistant tile.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
Cement mortar 1:4 (Rate asper item 36.12
No.3.9) cum 0.014 2580.18
7077 Acid proof tiles of size 300x300mm 10 Nos. 12 460.00 552.00

7024 Acid proof cement tonne tonne 0.0033 7400.00 24.42


9999 Carriage of tiles L. S. 6.24 1.00 6.24
9999 Mortar for pointing in acid/alkali L. S. 40.43 1.00 40.43
resistant
7024 Acid proof cement tonne tonne 0.0086 7400.00 63.64
367 Cement tonne -0.0086 5200.00 -44.72
Labour:-
123 Mason 1st class Day 0.25 270 67.50
115 Coolie Day 0.25 207 51.75
9999 Sundries including carriage of cement L. S. 26.91 1.00 26.91
etc.
TOTAL 824.29
Add 1% for water charges 8.24
TOTAL 832.54
Add for contractor’s profit and 124.88
overheads @15%
Cost of 1 sqm 957.42
Say 957.42

11.22 Tile work in skirting, risers of steps and dado (upto 2 m height) over 12 mm thick bed
of cement mortar 1:3 (1 cement :3 coarse sand) and jointed with grey cement slurry @ 3.3
kg/sqm including pointing in white cement mixed with pigment of matching shade
complete.
11.22.1 Marble tiles (polished) Raj Nagar.
11.22.1.1 8 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm.
Cement mortar 1:3 (Rate asper item 45.67
No.3.8) cum 0.014 3262.33
2751 8mm thick marble tiles (polished) Raj sqm 1.061 294.00 311.93
nagar
9999 Carriage of tiles L. S. 3.9 1.00 3.90
9999 Mortar for pointing in white cement L. S. 25.35 1.00 25.35
9999 Pigment L. S. 2.08 1.00 2.08
367 Cement tonne 0.0033 5200.00 17.16
Labour:-
123 Mason 1st class Day 0.25 270 67.50
115 Coolie Day 0.25 207 51.75
9999 Sundries including carriage of cement L. S. 16.9 1.00 16.90
etc.
TOTAL 542.25
Add 1% for water charges 5.42
TOTAL 547.67
Add for contractor’s profit and 82.15
overheads @15%
Cost of 1 sqm 629.82
Say 629.82

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall be
approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar 1:4 (1
cement : 4 coarse sand) laid and jointed with grey cement slurry including rubbing and
polishing complete with :
11.23.1 : Makrana white second quality.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
6001 Makrana white 2nd quality 18 mm thick sqm 11.5 1722.00 19803.00

9999 Carriage of marble slab L. S. 26.91 1.00 26.91


367 Cement tonne 0.05 5200.00 260.00
Labour:-
123 Mason 1st class Day 1.2 270 324.00
114 Beldar Day 1 207 207.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 134.55 1.00 134.55
TOTAL 23040.42
Add 1% for water charges 230.40
TOTAL 23270.82
Add for contractor’s profit and 3490.62
overheads @15%
Cost of 10 sqm 26761.45
Cost of 1 sqm 2676.14
Say 2676.14

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall be
approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar 1:4 (1
cement : 4 coarse sand) laid and jointed with grey cement slurry including rubbing and
polishing complete with :
11.23.2 : Raj Nagar plain.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
7071 Raj nagar plain 18 mm thick marble slab sqm 11.5 415.00 4772.50

9999 Carriage of marble slab L. S. 26.91 1.00 26.91


367 Cement tonne 0.05 5200.00 260.00
Labour:-
123 Mason 1st class Day 1.2 270 324.00
114 Beldar Day 1 207 207.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 134.55 1.00 134.55
TOTAL 8009.92
Add 1% for water charges 80.10
TOTAL 8090.02
Add for contractor’s profit and 1213.50
overheads @15%
Cost of 10 sqm 9303.52
Cost of 1 sqm 930.35
Say 930.35

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall be
approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar 1:4 (1
cement : 4 coarse sand) laid and jointed with grey cement slurry including rubbing and
polishing complete with :
11.23.3 : Agaria White
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
7850 Marble Stone Slab 18mm thick ( Agaria sqm 11.5 1000.00 11500.00
White
9999 Carriage of marble slab L. S. 26.91 1.00 26.91
367 Cement tonne 0.05 5200.00 260.00
Labour:-
123 Mason 1st class Day 1.2 270 324.00
114 Beldar Day 1 207 207.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 134.55 1.00 134.55
TOTAL 14737.42
Add 1% for water charges 147.37
TOTAL 14884.79
Add for contractor’s profit and 2232.72
overheads @15%
Cost of 10 sqm 17117.51
Cost of 1 sqm 1711.75
Say 1711.75

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall be
approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar 1:4 (1
cement : 4 coarse sand) laid and jointed with grey cement slurry including rubbing and
polishing complete with :
11.23.4 : Black Zebra.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
6019 Black Zebra marble slab plain 18mm sqm 11.5 415.00 4772.50
thick
9999 Carriage of marble slab L. S. 26.91 1.00 26.91
367 Cement tonne 0.05 5200.00 260.00
Labour:-
123 Mason 1st class Day 1.2 270 324.00
114 Beldar Day 1 207 207.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 134.55 1.00 134.55
TOTAL 8009.92
Add 1% for water charges 80.10
TOTAL 8090.02
Add for contractor’s profit and 1213.50
overheads @15%
Cost of 10 sqm 9303.52
Cost of 1 sqm 930.35
Say 930.35

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall be
approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar 1:4 (1
cement : 4 coarse sand) laid and jointed with grey cement slurry including rubbing and
polishing complete with :
11.23.5 : Udaipur green marble
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
6010 Udaipur green marble 18 mm thick sqm 11.5 580.00 6670.00
marble slab
9999 Carriage of marble slab L. S. 26.91 1.00 26.91
367 Cement tonne 0.05 5200.00 260.00
Labour:-
123 Mason 1st class Day 1.2 270 324.00
114 Beldar Day 1 207 207.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 134.55 1.00 134.55
TOTAL 9907.42
Add 1% for water charges 99.07
TOTAL 10006.49
Add for contractor’s profit and 1500.97
overheads @15%
Cost of 10 sqm 11507.47
Cost of 1 sqm 1150.75
Say 1150.75

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall be
approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar 1:4 (1
cement : 4 coarse sand) laid and jointed with grey cement slurry including rubbing and
polishing complete
11.23.6: Pink with :
plain marble.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
6007 Pink plain marble 18mm thick marble sqm 11.5 546.00 6279.00
slab
9999 Carriage of marble slab L. S. 26.91 1.00 26.91
367 Less for ordinary Cement tonne 0.05 5200.00 260.00
Labour:-
123 Mason 1st class Day 1.2 270 324.00
114 Beldar Day 1 207 207.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 134.55 1.00 134.55
TOTAL 9516.42
Add 1% for water charges 95.16
TOTAL 9611.58
Add for contractor’s profit and 1441.74
overheads @15%
Cost of 10 sqm 11053.32
Cost of 1 sqm 1105.33
Say 1105.33

11.24 : Extra for prefinished nosing to treads of steps of marble stone.


Code Description Unit Quantity Rate Amount
Details of cost for 10m
Labour:-
126 Mason (Ornamental) marble stone Day 2 313 626.00
114 Beldar Day 1.5 207 310.50
139 Beldar for rubbing and polishing (Special Day 2.5 180 450.00

9999 Sundries including carborandum etc. L. S. 53.82 1.00 53.82


TOTAL 1440.32
Add 1% for water charges 14.40
TOTAL 1454.72
Add for contractor’s profit and 218.21
overheads @15%
Cost of 10 sqm 1672.93
Cost of 1 sqm 167.29
Say 167.29

11.25 : Extra for marble stone flooring in treads of steps and risers using single length upto
2.00 metre .
Labour:-
123 Mason 1st class Day 1.95 270 526.50
114 Beldar Day 1.4 207 289.80
115 Coolie Day 0.75 207 155.25
139 Beldar for rubbing and polishing (Special Day 3.18 180 572.40

9999 Sundries including carborandum etc. L. S. 26.91 1.00 26.91


TOTAL 1570.86
Add 1% for water charges 15.71
TOTAL 1586.57
Add for contractor’s profit and 237.99
overheads @15%
Cost of 10 sqm 1824.55
Cost of 1 sqm 182.46
Say 182.46

11.26 : Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with
grey cement slurry mixed with pigment to match the shade of the slab including rubbing and
polishing complete with base of cement mortar 1 : 4 (1 cement: 4 coarse sand):
11.26.1 : 25 mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:4 (Rate asper item 577.96
No.3.9) cum 0.224 2580.18
1168 25mm thick Kota stone slabs polished sqm 11.5 250.00 2875.00

2216 Carriage of slabs tonne 0.67 47.29 31.68


367 Cement tonne 0.064 5200.00 332.80
2209 Carriage of cement tonne 0.064 47.29 3.03
874 Dark shade pigm ent kilogra 4.5 42.00 189.00
m
Labour:-
124 Mason 2nd class Day 1.2 223 267.60
114 Beldar Day 1 207 207.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 5 180 900.00

13 Machine for rubbing of floors Day 4 150 600.00


9999 Sundries including carborandum etc. L. S. 208.13 1.00 208.13
TOTAL 6399.20
Add 1% for water charges 63.99
TOTAL 6463.19
Add for contractor’s profit and 969.48
overheads @15%
Cost of 10 sqm 7432.67
Cost of 1 sqm 743.27
Say 743.27

11.27 : Kota stone slabs 25 mm thick in risers of steps, skirting, dado and pillars laid on
12mm (average) thick cement mortar 1:3 (1 cement 3 coarse sand) and jointed with grey
cement slurry mixed with pigment to match the shade of the slabs, including rubbing and
polishing complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:3 (Rate asper item 469.78
No.3.8) cum 0.144 3262.33
1168 25mm thick Kota stone slabs polished sqm 11.5 250.00 2875.00

2216 Carriage of slabs tonne 0.67 47.29 31.68


367 Cement tonne 0.064 5200.00 332.80
2209 Carriage of cement tonne 0.064 47.29 3.03
874 Dark shade pigm ent kilogra 4.5 42.00 189.00
m
Labour:-
124 Mason 2nd class Day 3 223 669.00
114 Beldar Day 3 207 621.00
115 Coolie Day 1 207 207.00
139 Beldar for rubbing and polishing (Special Day 7 180 1260.00

9999 Sundries including carborandum etc. L. S. 174.98 1.00 174.98


TOTAL 6833.27
Add 1% for water charges 68.33
TOTAL 6901.60
Add for contractor’s profit and 1035.24
overheads @15%
Cost of 10 sqm 7936.84
Cost of 1 sqm 793.68
Say 793.68

11.28 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement
mortar 1:5 ( 1 cem ent: 5 coarse sand) with joints finished flush.
11.28.1 : Red sand stone
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:5 (Rate asper item 553.22
No.3.10) cum 0.25 2212.87
1164 Red sand stone slab 40 mmthick (un- sqm 11 120.00 1320.00
dressed)
9999 Carriage L. S. 34.06 1.00 34.06
Labour:-
100 Bandhani Day 1.1 180 198.00
101 Bhisti Day 0.27 180 48.60
123 Mason 1st class Day 3.1 270 837.00
115 Coolie Day 0.55 207 113.85
9999 Sundries including carborandum etc. L. S. 10.79 1.00 10.79
TOTAL 3115.52
Add 1% for water charges 31.16
TOTAL 3146.67
Add for contractor’s profit and 472.00
overheads @15%
Cost of 10 sqm 3618.67
Cost of 1 sqm 361.87
Say 361.87

11.28 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement
mortar 1:5 ( 1 cem ent: 5 coarse sand) with joints finished flush.
11.28.2 : White sand stone
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:5 (Rate asper item 553.22
No.3.10) cum 0.25 2212.87
1165 White sand stone slab 40 mmthick (un- sqm 11 140.00 1540.00
dressed)
9999 Carriage L. S. 34.06 1.00 34.06
Labour:-
100 Bandhani Day 1.1 180 198.00
101 Bhisti Day 0.27 180 48.60
123 Mason 1st class Day 3.1 270 837.00
115 Coolie Day 0.55 207 113.85
9999 Sundries including carborandum etc. L. S. 10.79 1.00 10.79
TOTAL 3335.52
Add 1% for water charges 33.36
TOTAL 3368.87
Add for contractor’s profit and 505.33
overheads @15%
Cost of 10 sqm 3874.20
Cost of 1 sqm 387.42
Say 387.42

11.29 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement
mortar 1:5 (1 cement : 5 coarse sand) including pointing with cement mortar 1:2 (1 cement: 2
stone dust) with an admixture of pigment to match the shade of stone.

11.29.1: Red sand stone


Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:5 (Rate asper item 553.22
No.3.10) cum 0.25 2212.87
Cement mortar 1:2 (Rate asper item 102.08
No.3.12) cum 0.023 4438.17
1164 Red sand stone slab 40 mmthick (un- sqm 11 120.00 1320.00
dressed)
9999 Carriage L. S. 34.06 1.00 34.06
Labour:-
100 Bandhani Day 1.1 180 198.00
101 Bhisti Day 0.55 180 99.00
123 Mason 1st class Day 3.9 270 1053.00
115 Coolie Day 1.4 207 289.80
9999 Sundries including carborandum etc. L. S. 26.91 1.00 26.91
TOTAL 3676.07
Add 1% for water charges 36.76
TOTAL 3712.83
Add for contractor’s profit and 556.92
overheads @15%
Cost of 10 sqm 4269.75
Cost of 1 sqm 426.97
Say 426.97

11.29 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement
mortar 1:5 (1 cement : 5 coarse sand) including pointing with cement mortar 1:2 (1 cement: 2
stone dust) with an admixture of pigment to match the shade of stone.
11.29.2: White sand stone
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:5 (Rate asper item 553.22
No.3.10) cum 0.25 2212.87
Cement mortar 1:2 (Rate asper item 102.08
No.3.12) cum 0.023 4438.17
1165 White sand stone slab 40 mm thick sqm 11 140.00 1540.00
9999 Carriage L. S. 34.06 1.00 34.06
Labour:-
100 Bandhani Day 1.1 180 198.00
101 Bhisti Day 0.55 180 99.00
123 Mason 1st class Day 3.9 270 1053.00
115 Coolie Day 1.4 207 289.80
9999 Sundries including carborandum etc. L. S. 26.91 1.00 26.91
TOTAL 3896.07
Add 1% for water charges 38.96
TOTAL 3935.03
Add for contractor’s profit and 590.25
overheads @15%
Cost of 10 sqm 4525.28
Cost of 1 sqm 452.53
Say 452.53

11.30 : 40 mm thick rubbed stone flooring over 20 mm (average) thick base of cement mortar
1:5(1 cement :5 coarse sand) with joints 3m m thick, side buttered with cement mortar 1:2 (1
cement : 2 stone dust) admixed with pigment to match the shade of stone and pointing with
same mortar
11.30.1: Red sand stone
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:5 (Rate asper item 553.22
No.3.10) cum 0.25 2212.87
Cement mortar 1:2 (Rate asper item 102.08
No.3.12) cum 0.023 4438.17
1164 Red sand stone slab 40 mmthick (un- sqm 11 120.00 1320.00
dressed)
9999 Carriage L. S. 34.06 1.00 34.06
Labour:-
100 Bandhani Day 1.1 180 198.00
101 Bhisti Day 0.55 180 99.00
123 Mason 1st class Day 3.9 270 1053.00
115 Coolie Day 1.4 207 289.80
139 Beldar for rubbing and polishing (Special Day 0.618 180 111.24

13 Machine for rubbing of floors Day 0.988 150 148.20


9999 Sundries including carborandum etc. L. S. 26.91 1.00 26.91
TOTAL 3935.51
Add 1% for water charges 39.36
TOTAL 3974.86
Add for contractor’s profit and 596.23
overheads @15%
Cost of 10 sqm 4571.09
Cost of 1 sqm 457.11
Say 457.11

11.30 : 40 mm thick rubbed stone flooring over 20 mm (average) thick base of cement mortar
1:5(1 cement :5 coarse sand) with joints 3m m thick, side buttered with cement mortar 1:2 (1
cement : 2 stone dust) admixed with pigment to match the shade of stone and pointing with
same mortar
11.30.2: White sand stone
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Cement mortar 1:5 (Rate asper item 553.22
No.3.10) cum 0.25 2212.87
Cement mortar 1:2 (Rate asper item 102.08
No.3.12) cum 0.023 4438.17
1165 White sand stone slab 40 mm thick sqm 11 140.00 1540.00
9999 Carriage L. S. 34.06 1.00 34.06
Labour:-
100 Bandhani Day 1.1 180 198.00
101 Bhisti Day 0.55 180 99.00
123 Mason 1st class Day 3.9 270 1053.00
115 Coolie Day 1.4 207 289.80
139 Beldar for rubbing and polishing (Special Day 0.618 180 111.24

13 Machine for rubbing of floors Day 0.988 150 148.20


9999 Sundries including carborandum etc. L. S. 26.91 1.00 26.91
TOTAL 4155.51
Add 1% for water charges 41.56
TOTAL 4197.06
Add for contractor’s profit and 629.56
overheads @15%
Cost of 10 sqm 4826.62
Cost of 1 sqm 482.66
Say 482.66

11.31 : Extra for pre finished nosing in treads of steps of Kota stone/ sand stone slab.
Code Description Unit Quantity Rate Amount
Details of cost for 10m
Labour:-
126 Stone mason (ornamental) Day 1.5 313 469.50
TOTAL 469.50
Add 1% for water charges 4.70
TOTAL 474.20
Add for contractor’s profit and 71.13
overheads @15%
Cost of 10 sqm 545.32
Cost of 1 sqm 54.53
Say 54.53

11.32 : Extra for Kota stone/ sand stone in treads of steps and risers using single length upto
Code
1.05 metre Description
. Unit Quantity Rate Amount
Details of cost for 10m
Labour:-
124 Mason 2nd class Day 0.2 223 44.60
114 Beldar Day 0.2 207 41.40
TOTAL 86.00
Add 1% for water charges 0.86
TOTAL 86.86
Add for contractor’s profit and 13.03
overheads @15%
Cost of 10 sqm 99.89
Cost of 1 sqm 9.99
Say 9.99

11.33 : 25mm wooden planking, tongued and grooved in flooring including fixing with iron
screws
11.33.1:complete with teak
Second class : wood
Details of cost for 10 sqmm
Code Description Unit Quantity Rate Amount
1190 Second class indian teak wood 10 cudm 298.1 410.00 12222.10
1231 Extra for selected planks 10 cudm 298.1 72.00 2146.32
2204 Carriage of timber cum 0.2981 60.81 18.13
682 Iron screws 50 mm (slotted counters 40.00 80.00
sunk head type) 100 Nos 200
Labour-
111 Carpenter 1st class Day 2.68 270 723.60
114 Beldar Day 1.35 207 279.45
9999 Sundries for glue etc. L. S. 33.28 1.00 33.28
TOTAL 15502.88
Add 1% for water charges 155.03
TOTAL 15657.91
Add for contractor’s profit and 2348.69
overheads @15%
Cost of 10 sqm 18006.59
Cost of 1 sqm 1800.66
Say 1800.66

11.33 : 25mm wooden planking, tongued and grooved in flooring including fixing with iron
screws
11.33.2:complete with deodar
Second class : wood
Details of cost for 10 sqm
Code Description Unit Quantity Rate Amount
1194 First class deodar wood planks 10 cudm 298.1 335.00 9986.35
2500 Extra for selected planks 10 cudm 298.1 59.00 1758.79
2204 Carriage of timber cum 0.2981 60.81 18.13
682 Iron screws 50 mm (slotted counters 40.00 80.00
sunk head type) 100 Nos 200
Labour-
111 Carpenter 1st class Day 2.16 270 583.20
114 Beldar Day 1.08 207 223.56
9999 Sundries for glue etc. L. S. 26.91 1.00 26.91
TOTAL 12676.94
Add 1% for water charges 126.77
TOTAL 12803.71
Add for contractor’s profit and 1920.56
overheads @15%
Cost of 10 sqm 14724.26
Cost of 1 sqm 1472.43
Say 1472.43

11.34 : 38mm thick wood block flooring of first class teak wood laid over 25mm thick
levelling layer of cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate
10mm nominal size) to be paid separately coated with a thin layer of hot bitumen (blown
type) @ 2.45 kg per sqm. including fixing blocks in position after dipping in hot bitumen
(blown type) upto half depth, planed, levelled smooth and finished complete.
Details of cost for 1 sqm
Code Description Unit Quantity Rate Amount
313 Bitumen blown type tonne 0.0044 35000.00 154.00
2211 Carriage of bitumen tonne 0.0044 53.21 0.23
1187 First class declass teak wood in scanting 10 cudm 41.8 492.00 2056.56
2204 Carriage of timber cum 0.0418 60.81 2.54
Labour-
111 Carpenter 1st class Day 1.75 270 472.50
114 Beldar Day 2.25 207 465.75
115 Coolie Day 1.5 207 310.50
130 Mistry Day 0.1 270 27.00
9999 Sundries such as fuel, kerosene oil, sand L. S. 80.73 1.00 80.73
paper
TOTAL 3569.82
Add 1% for water charges 35.70
TOTAL 3605.51
Add for contractor’s profit and 540.83
overheads @15%
Cost of 1 sqm 4146.34
Say 4146.34
11.35 : Providing and fixing M.S. angle 50x50x5 mm to act as nosing with lugs of M.S. flat
10x5 mm 10cm long forked at end 60cm apart (minimum three lugs to be provided )
including necessay welding and applying a priming coat of approved primer on exposed
surface etc. complete.
Details of cost for 3m = 15.63 kg
Code Description Unit Quantity Rate Amount
1007 Angle iron & channel quintal 0.162 4600.00 745.20
1008 Flats quintal 0.0025 4600.00 11.50
2205 Carriage tonne 0.016 47.29 0.76
1215 Welding cm 6 1.00 6.00
Labour-
103 Blacksmith 2nd class Day 0.09 223 20.07
123 Mason 1st class Day 0.45 270 121.50
114 Beldar Day 0.25 207 51.75
(A) Priming cost-(Rate vide item no.
13.50.3 finishing) sqm 0.6 15.74 9.44
9999 Sundries L. S. 9.1 1.00 9.10
TOTAL 975.32
Add 1% for water charges except A 9.66

TOTAL 984.98
Add for contractor’s profit and 146.33
overheads @15% except on A
Cost of 15.63 kg 1131.31
Cost of 1 kg 72.38
Say 72.38

11.36 : Providing and fixing 1st quality ceramic glazed wall tiles conforming to IS : 15622
(thickness to be specified by the manufacture of approved make in all colours, shades except
burgundy, bottle green, black of any size as approved by Engineer-in-Charge in skirting,
risers of steps and dados over 12 mm thick bed of cement Mortar 1:3 (1 cement: 3 coarse
sand) and jointing with grey cement slurry @ 3.3kg per sqm including pointing in white
cement mixed with pigment of matching shade complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
7800 Tiles Sqm. 1.025 268.00 274.70
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:3 (Rate asper item 45.67
No.3.8) cum 0.014 3262.33
9999 Mortar for pointing in white cement L. S. 40.43 1.00 40.43
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.25 270 67.50
115 Coolie Day 0.25 207 51.75
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 530.36
Add 1% for water charges 5.30
TOTAL 535.67
Add for contractor’s profit and 80.35
overheads @15%
Cost of 1 sqm 616.02
Say 616.02

11.37 : Providing and laying Ceramic glazed floor tiles 300x300 mm (thickness to be
specified by the manufacturer) of 1st quality conforming to IS : 15622 of approved make in
colours such as White, Ivory, Grey, Fume Red, Brown laid on 20 mm thick Cement Mortar
1:4 (1 Cement : 4 Coarse sand) including pointing the joints with white cement and matching
pigment etc., complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
7801 Tiles Sqm. 1.025 320.00 328.00
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 20.2 1.00 20.20
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 555.83
Add 1% for water charges 5.56
TOTAL 561.39
Add for contractor’s profit and 84.21
overheads @15%
Cost of 1 sqm 645.60
Say 645.60

11.38 : Providing and laying Ceramic glazed floor tiles 300x300 mm(thickn ess t o be
specified by the manufacturer) of 1st quality conforming to IS : 15622 of approved make in
all colours , shades, except White, Ivory, Grey, Fume Red Brown laid on 20mm thick bed of
Cement Mortar 1:4(1 Cement: 4 Coarse sand) including pointing the joints with white cement
and matching pigments etc., complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
7802 Tiles Sqm. 1.025 347.00 355.68
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 20.2 1.00 20.20
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 583.51
Add 1% for water charges 5.84
TOTAL 589.34
Add for contractor’s profit and 88.40
overheads @15%
Cost of 1 sqm 677.75
Say 677.75

11.39 : Providing and laying rectified Glazed Ceramic floor tiles 300x300 m m or more
(thickness to be specified by the manufacturer) of 1st quality conforming to IS :15622 of
approved make in colours White, Ivory, Grey, Fume Red,, Brown, laid on 20mm thick cement
mortar 1:4 (1 Cement : 4 Coarse sand) including grouting the joints with white cement and
matching pigments etc., complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
7803 Tiles Sqm. 1.025 462.00 473.55
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 13.47 1.00 13.47
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 694.65
Add 1% for water charges 6.95
TOTAL 701.60
Add for contractor’s profit and 105.24
overheads @15%
Cost of 1 sqm 806.84
Say 806.84

11.40 : Providing and laying rectified Glazed Ceramic floor tiles 300x300 mm or more
(thickness to be specified by the manufacturer) of 1st quality conforming to IS :15622 of
approved make in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on
20 mm thick Cement Mortar 1:4 (1 Cement : 4 Coarse sand) including pointing the joints
with white cement and matching pigments etc., complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
7804 Tiles Sqm. 1.025 496.00 508.40
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 13.47 1.00 13.47
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 729.50
Add 1% for water charges 7.30
TOTAL 736.80
Add for contractor’s profit and 110.52
overheads @15%
Cost of 1 sqm 847.32
Say 847.32

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specified
by the manufacturer) with water absorption’s less than 0.08% and conforming to IS : 15622
of approved make in all colours and shades, laid on 20mm thick cement mortar 1:4 (1
cement: 4 coarse sand) including grouting the joints with white cement and matching
pigments etc., complete.
11.41.1: Size of Tile 50x50 cm
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
8620 Tiles Sqm. 1.025 645.00 661.13
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 3.64 1.00 3.64
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 872.40
Add 1% for water charges 8.72
TOTAL 881.12
Add for contractor’s profit and 132.17
overheads @15%
Cost of 1 sqm 1013.29
Say 1013.29

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specified
by the manufacturer) with water absorption’s less than 0.08% and conforming to IS : 15622
of approved make in all colours and shades, laid on 20mm thick cement mortar 1:4 (1
cement: 4 coarse sand) including grouting the joints with white cement and matching
pigments etc., complete.
11.41.2 Size of Tile 60x60 cm
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
8621 Tiles Sqm. 1.025 700.00 717.50
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 3.64 1.00 3.64
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 928.77
Add 1% for water charges 9.29
TOTAL 938.06
Add for contractor’s profit and 140.71
overheads @15%
Cost of 1 sqm 1078.77
Say 1078.77

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specified
by the manufacturer) with water absorption’s less than 0.08% and conforming to IS : 15622
of approved make in all colours and shades, laid on 20mm thick cement mortar 1:4 (1
cement: 4 coarse sand) including grouting the joints with white cement and matching
pigments etc., complete.
11.41.3 : Size of Tile 80x80 cm
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
8622 Tiles Sqm. 1.025 1076.00 1102.90
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 2.6 1.00 2.60
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 1313.13
Add 1% for water charges 13.13
TOTAL 1326.27
Add for contractor’s profit and 198.94
overheads @15%
Cost of 1 sqm 1525.21
Say 1525.21

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specified
by the manufacturer) with water absorption’s less than 0.08% and conforming to IS : 15622
of approved make in all colours and shades, laid on 20mm thick cement mortar 1:4 (1
cement: 4 coarse sand) including grouting the joints with white cement and matching
pigments etc., complete.
11.41.4: Size of Tile 100x100 cm
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
M aterials-
8623 Tiles Sqm. 1.025 1290.00 1322.25
9999 Carriage of tiles L. S. 6.24 1.00 6.24
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 2.6 1.00 2.60
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 1532.48
Add 1% for water charges 15.32
TOTAL 1547.81
Add for contractor’s profit and 232.17
overheads @15%
Cost of 1 sqm 1779.98
Say 1779.98

11.42: Deduet for not using 20mm thick cement mortar 1:4 (1 cement :4 coarse sand )
bedding in laying of floor tiles.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
MATERIALS
Cement mortar 1:4 (Rate asper item 61.92
No.3.9) cum 0.024 2580.18
9999 Mortar for pointing in white cement L. S. 40.43 1.00 40.43
367 Cement tonne 0.0033 5200.00 17.16
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 241.82
Add 1% for water charges 2.42
TOTAL 244.24
Add for contractor’s profit and 36.64
overheads @15%
Cost of 1 sqm 280.88
Say 280.88

11.43: Fixing glazed/ Ceramic/ Vitrified floor tiles with cement based high polymer modified
quick-set tile adhesive (Water based) conforming to IS: 15477 , using 5kg. Adhesive per sqm
of tile area, in average 3mm thickness.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
MATERIALS
8731 High polymer modified quickset tile kg 5 13.75 68.75
adhesive.
9999 Mortar for pointing in white cement L. S. 40.43 1.00 40.43
Labour-
123 Mason 1st class Day 0.2 270 54.00
115 Coolie Day 0.2 207 41.40
9999 undries including carriage of cement etc L. S. 26.91 1.00 26.91

TOTAL 231.49
Add 1% for water charges 2.31
TOTAL 233.80
Add for contractor’s profit and 35.07
overheads @15%
Cost of 1 sqm 268.88
Say 268.88
12.1 Providing corrugated G.S. sheet roofing including vertical/curved surface fixed with
polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet
washers or with G.I. limpet washers filled with white lead and including a coat of approved
steel primer and two coats of approved paint on overlapping of sheets complete upto any
pitch in horizontal/ vertical or curved surfaces) excluding the cost of purlins, rafters and
trusses and including cutting to size and shape wherever required.
12.1.1 1.00mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Details of cost for area of roof. 2x18.09x5.1 = 184.518 sqm.
Materials:
3050 C.G.S. sheets quintal 23.26 6000.00 139560.00
2302 Carriage of sheet tonne 2.326 47.29 110.00
1022 Bolts and nuts 10 Nos 884 60.00 5304.00
1023 G.I., J or L hooks 10 Nos 810 60.00 4860.00
1207 Limpet washers (total of seam and J bolts) 00 Nos 1694 20.00 338.80
1208 Bitumen washers 00 Nos 1694 18.00 304.92
9999 Carriage of bolts and w ashers L.S. 26.91 1.00 26.91
9999 Sundries L.S. 53.82 1.00 53.82
Labour:
130 Mistry Day 1.3 270 351.00
131 Painter Day 3.66 180 658.80
112 Carpenter 2nd class Day 15.5 223 3456.50
114 Beldar Day 15.5 207 3208.50
115 Coolie Day 3.66 207 757.62
4202 Zink chromate yellow primer litre 2.53 58 146.74
845 Ready mixed paint on new work litre 3.75 95 356.25
9,999 Brushes, sand papers i/c L.S. 82.55 1.00 82.55
9,999 Carriage of paint L.S. 6.76 1.00 6.76
9,999 Sundries L.S. 38.09 1.00 38.09
TOTAL 159621.26
Add 1% for water charges 1596.21
TOTAL 161217.47
Add for contractor’s profit and overheads 24182.62
@15%
Cost of 184.518 sqm 185400.09
Cost of 1 sqm 1004.78
Say 1004.78

12.1 Providing corrugated G.S. sheet roofing including vertical/curved surface fixed with
polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet
washers or with G.I. limpet washers filled with white lead and including a coat of approved
steel primer and two coats of approved paint on overlapping of sheets complete upto any
pitch in horizontal/ vertical or curved surfaces) excluding the cost of purlins, rafters and
trusses and including cutting to size and shape wherever required.
12.1.2 0.80mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Details of cost for area of roof. 2x18.09x5.1 = 184.518 sqm.
Materials:
3050 C.G.S. sheets quintal 19.02 6000.00 114120.00
2302 Carriage of sheet tonne 1.902 47.29 89.95
1022 Bolts and nuts 10 Nos 884 60.00 5304.00
1023 G.I., J or L hooks 10 Nos 810 60.00 4860.00
1207 Limpet washers (total of seam and J bolts) 00 Nos 1694 20.00 338.80
1208 Bitumen washers 00 Nos 1694 18.00 304.92
9999 Carriage of bolts and w ashers L.S. 26.91 1.00 26.91
9999 Sundries L.S. 53.82 1.00 53.82
Labour:
130 Mistry Day 1.3 270 351.00
131 Painter Day 3.66 180 658.80
112 Carpenter 2nd class Day 15.5 223 3456.50
114 Beldar Day 15.5 207 3208.50
115 Coolie Day 3.66 207 757.62
4202 Zink chromate yellow primer litre 2.53 58 146.74
845 Ready mixed paint on new work litre 3.75 95 356.25
9,999 Brushes, sand papers i/c L.S. 82.55 1.00 82.55
9,999 Carriage of paint L.S. 6.76 1.00 6.76
9,999 Sundries L.S. 38.09 1.00 38.09
TOTAL 134161.21
Add 1% for water charges 1341.61
TOTAL 135502.82
Add for contractor’s profit and overheads
@15% 20325.42
Cost of 184.518 sqm 155828.24
Cost of 1 sqm 844.52
Say 844.52

12.1 Providing corrugated G.S. sheet roofing including vertical/curved surface fixed with
polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet
washers or with G.I. limpet washers filled with white lead and including a coat of approved
steel primer and two coats of approved paint on overlapping of sheets complete upto any
pitch in horizontal/ vertical or curved surfaces) excluding the cost of purlins, rafters and
trusses and including cutting to size and shape wherever required.
12.1.3 0.63 mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Details of cost for area of roof. 2x18.09x5.1 = 184.518 sqm.
Materials:
3050 C.G.S. sheets quintal 15.41 6000.00 92460.00
2302 Carriage of sheet tonne 1.541 47.29 72.87
1022 Bolts and nuts 10 Nos 884 60.00 5304.00
1023 G.I., J or L hooks 10 Nos 810 60.00 4860.00
1207 Limpet washers (total of seam and J bolts) 00 Nos 1694 20.00 338.80
1208 Bitumen washers 00 Nos 1694 18.00 304.92
9999 Carriage of bolts and w ashers L.S. 26.91 1.00 26.91
9999 Sundries L.S. 53.82 1.00 53.82
Labour:
130 Mistry Day 1.3 270 351.00
131 Painter Day 3.66 180 658.80
112 Carpenter 2nd class Day 15.5 223 3456.50
114 Beldar Day 15.5 207 3208.50
115 Coolie Day 3.66 207 757.62
4202 Zink chromate yellow primer litre 2.53 58 146.74
845 Ready mixed paint on new work litre 3.75 95 356.25
9,999 Brushes, sand papers i/c L.S. 82.55 1.00 82.55
9,999 Carriage of paint L.S. 6.76 1.00 6.76
9,999 Sundries L.S. 38.09 1.00 38.09
TOTAL 112484.13
Add 1% for water charges 1124.84
TOTAL 113608.98
Add for contractor’s profit and overheads
@15% 17041.35
Cost of 184.518 sqm 130650.32
Cost of 1 sqm 708.06
Say 708.06

12.2 Extra for straight cutting in C.G.S. sheet roofing for making opening of area
exceeding 40 sq. decimeter for chimney stacks, sky light etc. :
12.2.1 1.00 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 3 metres periphery
Labour:
114 Beldar Day 0.15 207 31.05
102 Blacksmith first class Day 0.15 270 40.50
TOTAL 71.55
Add 1% for water charges 0.72
TOTAL 72.27
Add for contractor’s profit and overheads
@15% 10.84
Cost of 3 m 83.11
Cost of 1 m 27.70
Say 27.70

12.2 Extra for straight cutting in C.G.S. sheet roofing for making opening of area
exceeding 40 sq. decimeter for chimney stacks, sky light etc. :
12.2.2 0.80 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 3 metres periphery
Labour:
114 Beldar Day 0.12 207 24.84
102 Blacksmith first class Day 0.12 270 32.40
TOTAL 57.24
Add 1% for water charges 0.57
TOTAL 57.81
Add for contractor’s profit and overheads
@15% 8.67
Cost of 3 m 66.48
Cost of 1 m 22.16
Say 22.16

12.2 Extra for straight cutting in C.G.S. sheet roofing for making opening of area
exceeding 40 sq. decimeter for chimney stacks, sky light etc. :
12.2.3 0.63 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 3 metres periphery
Labour:
114 Beldar Day 0.12 207 24.84
102 Blacksmith first class Day 0.12 270 32.40
TOTAL 57.24
Add 1% for water charges 0.57
TOTAL 57.81
Add for contractor’s profit and overheads
@15% 8.67
Cost of 3 m 66.48
Cost of 1 m 22.16
Say 22.16
12.3 Extra for circular cutting in C.G.S. sheet roofing for making opening of area
exceeding 40 square decimeter :
12.3.1 1.00 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 holes of 0.5 metre dia-metre Perimetre of 10 nos 10x22/7x0.5 =
15.71
Labour:
114 Beldar Day 6.26 207 1295.82
102 Blacksmith first class Day 3.13 270 845.10
TOTAL 2140.92
Add 1% for water charges 21.41
TOTAL 2162.33
Add for contractor’s profit and overheads
@15% 324.35
Cost of 15.71 m 2486.68
Cost of 1 m 158.29
Say 158.29
12.3 Extra for circular cutting in C.G.S. sheet roofing for making opening of area
exceeding 40 square decimeter :
12.3.2 0.80 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 holes of 0.5 metre dia-metre Perimetre of 10 nos 10x22/7x0.5 =
15.71
Labour:
114 Beldar Day 5 207 1035.00
102 Blacksmith first class Day 2.5 270 675.00
TOTAL 1710.00
Add 1% for water charges 17.10
TOTAL 1727.10
Add for contractor’s profit and overheads
@15% 259.07
Cost of 15.71 m 1986.17
Cost of 1 m 126.43
Say 126.43

12.3 Extra for circular cutting in C.G.S. sheet roofing for making opening of area
exceeding 40 square decimeter :
12.3.3 0.63 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 holes of 0.5 metre dia-metre Perimetre of 10 nos 10x22/7x0.5 =
15.71
Labour:
114 Beldar Day 5 207 1035.00
102 Blacksmith first class Day 2.5 270 675.00
TOTAL 1710.00
Add 1% for water charges 17.10
TOTAL 1727.10
Add for contractor’s profit and overheads
@15% 259.07
Cost of 15.71 m 1986.17
Cost of 1 m 126.43
Say 126.43
12.4 Providing ridges or hips of width 60 cm over all width plain G.S. sheet fixed with
polymer coated J. or L hooks, bolts and nuts 8 mm dia. G.I. limpet and bitumen washers
complete.
12.4.1 0.80mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Details of cost for 10.35 metre long ridge.
Materials:
992 G.I. plain sheets quintal quintal 0.58 3450.00 2001.00
2302 Carriage of sheet tonne 0.058 47.29 2.74
222 Seam bolts and nuts 6 mm dia and 25 mm l tonne 28 30.00 84.00
1208 Bitumen washers 00 Nos 28 18.00 5.04
1211 G.I. plain washers 01 Nos 28 21.00 5.88
9999 Carriage of bolts and w ashers L.S. 1.82 1.00 1.82
9999 Sundries L.S. 13.52 1.00 13.52
Labour:
130 Mistry Day 0.4 270 108.00
102 Blacksmith first class Day 1.2 270 324.00
103 Blacksmith second class Day 0.8 223 178.40
114 Beldar Day 2.4 207 496.80
TOTAL 3221.20
Add 1% for water charges 32.21
TOTAL 3253.41
Add for contractor’s profit and overheads
@15% 488.01
Cost of 10.35 metres 3741.43
Cost of 1 metre 361.49
Say 361.49

12.4 Providing ridges or hips of width 60 cm over all width plain G.S. sheet fixed with
polymer coated J. or L hooks, bolts and nuts 8 mm dia. G.I. limpet and bitumen washers
complete.
12.4.2 0.63mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Details of cost for 10.35 metre long ridge.
Materials:
992 G.I. plain sheets quintal quintal 0.47 3450.00 1621.50
2302 Carriage of sheet tonne 0.047 47.29 2.22
222 Seam bolts and nuts 6 mm dia and 25 mm l tonne 28 30.00 84.00
1208 Bitumen washers 00 Nos 28 18.00 5.04
1211 G.I. plain washers 01 Nos 28 21.00 5.88
9999 Carriage of bolts and w ashers L.S. 1.82 1.00 1.82
9999 Sundries L.S. 13.52 1.00 13.52
Labour:
130 Mistry Day 0.4 270 108.00
102 Blacksmith first class Day 1.2 270 324.00
103 Blacksmith second class Day 0.8 223 178.40
114 Beldar Day 2.4 207 496.80
TOTAL 2841.18
Add 1% for water charges 28.41
TOTAL 2869.59
Add for contractor’s profit and overheads
@15% 430.44
Cost of 10.35 metres 3300.03
Cost of 1 metre 318.84
Say 318.84

12.5 Providing valleys of 90cm wide overall in plain G.S. sheet fixed with polymer coated J,
or L hooks, bolts and nuts 8mm dia.. G.I. limpet and bitumen washers complete :
12.5.1 1.60mm thick with zinc coating not less than 350gm/sqm
Code Description Unit Quantity Rate Amount
Details of cost for 9.325m
Materials:
992 G.I. plain sheets quintal quintal 1.222 3450.00 4215.90
2302 Carriage of sheet tonne 0.12 47.29 5.67
222 Seam bolts and nuts 6 mm dia and 25 mm l tonne 12 30.00 36.00
1208 Bitumen washers 00 Nos 12 18.00 2.16
1211 G.I. plain washers 01 Nos 12 21.00 2.52
9999 Carriage of bolts and w ashers L.S. 0.91 1.00 0.91
9999 Sundries L.S. 13.52 1.00 13.52
Labour:
130 Mistry Day 0.4 270 108.00
102 Blacksmith first class Day 1.2 270 324.00
103 Blacksmith second class Day 0.8 223 178.40
114 Beldar Day 2.4 207 496.80
TOTAL 5383.88
Add 1% for water charges 53.84
TOTAL 5437.72
Add for contractor’s profit and overheads
@15% 815.66
Cost of 9.325 metres 6253.38
Cost of 1 metre 670.60
Say 670.60

12.6 Providing flashing of 40 cm over all width in plain, G.S. sheet fixed with polymer
coated J, or L hooks, bolts and nuts, G.I. limpet and bitumen washer complete, bent to shape
and fixed in wall with cement mortar 1:3 (1 cement: 3 coarse sand).
12.6.1 1.00mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Details of cost for 12.125m
Materials:
992 G.I. plain sheets quintal quintal 0.4211 3450.00 1452.80
2302 Carriage of sheet tonne 0.042 47.29 1.99
222 Seam bolts and nuts 6 mm dia and 25 mm l tonne 6 30.00 18.00
1208 Bitumen washers 00 Nos 6 18.00 1.08
1207 Limpet washers 00 Nos 6 20.00 1.20
9999 Carriage of bolts and w ashers L.S. 0.39 1.00 0.39
9999 Sundries L.S. 10.79 1.00 10.79
Labour:
130 Mistry Day 0.5 270 135.00
102 Blacksmith first class Day 1.48 270 399.60
103 Blacksmith second class Day 1 223 223.00
114 Beldar Day 3 207 621.00
TOTAL 2864.84
Add 1% for water charges 28.65
TOTAL 2893.49
Add for contractor’s profit and overheads 434.02
@15%
Cost of 12.125 metres 3327.51
Cost of 1 metre 274.43
Say 274.43

12.7: Providing and fixing 15 cm wide 45 cm over all semi circular plain G.S. sheet gutter
with iron brackets 40x3mm size, bolts, nuts and washers etc. including making necessary
connections with rain water pipes complete.
12.7.1: 0.80mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Consider a length of 9.04m
Materials:
992 G.I. plain sheets quintal quintal 0.3164 3450.00 1091.58
2302 Carriage of sheet tonne 0.0316 47.29 1.49
1008 Flats upto 10 mm in thickness quintal 0.0749 4600.00 344.54
1022 Bolts and nuts 10 Nos 20 60.00 120.00
1024 Galvanised steel bolts and nuts 10 mm dia each 30 12.00 360.00
1208 Bitumen washers 00 Nos 40 18.00 7.20
1210 G.I. plain washer thin 00 Nos 70 20.00 14.00
9999 Carriage of bolts and w ashers L.S. 2.73 1.00 2.73
9999 Sundries L.S. 17.94 1.00 17.94
Labour:
130 Mistry Day 0.28 270 75.60
102 Blacksmith first class Day 1.34 270 361.80
112 Carpenter 2nd class Day 0.62 223 138.26
114 Beldar Day 2.18 207 451.26
TOTAL 2986.40
Add 1% for water charges 29.86
TOTAL 3016.27
Add for contractor’s profit and overheads 452.44
@15%
Cost of 9.04 metres 3468.71
Cost of 1 metre 383.71
Say 383.71

12.7: Providing and fixing 15 cm wide 45 cm over all semi circular plain G.S. sheet gutter
with iron brackets 40x3mm size, bolts, nuts and washers etc. including making necessary
connections with rain water pipes complete.
12.7.2 : 0.63mm thick with zinc coating not less than 275gm/sqm
Code Description Unit Quantity Rate Amount
Consider a length of 9.04m
Materials:
992 G.I. plain sheets quintal quintal 0.2364 3450.00 815.58
2302 Carriage of sheet tonne 0.0236 47.29 1.12
1008 Flats upto 10 mm in thickness quintal 0.0749 4600.00 344.54
1022 Bolts and nuts 10 Nos 20 60.00 120.00
1024 Galvanised steel bolts and nuts 10 mm dia each 30 12.00 360.00
1208 Bitumen washers 00 Nos 40 18.00 7.20
1210 G.I. plain washer thin 00 Nos 70 20.00 14.00
9999 Carriage of bolts and w ashers L.S. 2.73 1.00 2.73
9999 Sundries L.S. 17.94 1.00 17.94
Labour:
130 Mistry Day 0.28 270 75.60
102 Blacksmith first class Day 1.34 270 361.80
112 Carpenter 2nd class Day 0.62 223 138.26
114 Beldar Day 2.18 207 451.26
TOTAL 2710.03
Add 1% for water charges 27.10
TOTAL 2737.13
Add for contractor’s profit and overheads
@15% 410.57
Cost of 9.04 metres 3147.70
Cost of 1 metre 348.20
Say 348.20

12.8 Providing non-asbestos high impact Polypropylene reinforced cement 6 mm thick


corrugated sheets (As per IS: 14871) roofing upto any pitch and fixing with polymer coated
J, or L hooks, bolts and nuts 8mm dia. G.I. plain and bitumen washers or with self drilling
fastener and EPDM washers etc. complete excluding the cost of purlins, rafters and trusses
corrugated sheets and including cutting to size and shape wherever required
Code Description Unit Quantity Rate Amount
Area of roof-20.2x10.70m = 216.14 sqm.
Materials:
223 Non - Asbestos fibre cement corrugated sh sqm 237.93 205.00 48775.65
2273 Carriage of sheet tonne 3.184 47.29 150.57
1023 G.I. J or L hooks with nuts and bolts 8 mm 10 Nos 476 60.00 2856.00
1208 Bitumen washers 00 Nos 476 18.00 85.68
1209 G.I. plain washer thick 00 Nos 476 27.00 128.52
9999 Carriage of bolts and w ashers L.S. 8.06 1.00 8.06
9999 Sundries L.S. 39.52 1.00 39.52
Labour:
130 Mistry Day 2.34 270 631.80
112 Carpenter 2nd class Day 9.34 223 2082.82
114 Beldar Day 9.34 207 1933.38
TOTAL 56692.00
Add 1% for water charges 566.92
TOTAL 57258.92
Add for contractor’s profit and overheads
@15% 8588.84
Cost of 216.14 sqm 65847.76
Cost of 1 sqm 304.65
Say 304.65

12.9 : Extra for straight cutting in non- asbestos polypropylene reinforced cement
corrugated, semi-corrugated 6 mm thick sheet roofing for making openings of area
exceeding 40 square decimeter for chimney stacks, skylights etc.
Code Description Unit Quantity Rate Amount
Details of cost for 3 m etres of periphery
Labour:
111 Carpenter Ist class Day 0.12 270 32.40
114 Beldar Day 0.12 207 24.84
TOTAL 57.24
Add 1% for water charges 0.57
TOTAL 57.81
Add for contractor’s profit and overheads
@15% 8.67
Cost of 3.0 metres 66.48
Cost of 1 metre 22.16
Say 22.16

12.10 Extra for circular cutting in non-asbestos polypropylene reinforced cement


corrugated/semi-corrugated 6 mm thick sheet roofing for making openings of area exceeding
40 square decimeter.
Code Description Unit Quantity Rate Amount
Details of cost for 4 holes of 0.72 metre diameter i.e. 9.05 metre periphery
Labour:
111 Carpenter 1st class Day 1 270 270.00
114 Beldar Day 1 207 207.00
TOTAL 477.00
Add 1% for water charges 4.77
TOTAL 481.77
Add for contractor’s profit and overheads
@15% 72.27
Cost of 9.05 metres of periphery 554.04
Cost of 1 metre of periphery 61.22
Say 61.22

12.11: Extra for providing and fixing wind ties of 40x 6mm flat iron section
Code Description Unit Quantity Rate Amount
Extra for providing and fixing wind ties of 40x6m m flat iron section.
1008 Flats upto 10 mm in thickness quintal 0.5985 4600.00 2753.10
2302 Carriage of sheet tonne 0.06 47.29 2.84
9999 Sundries L.S. 20.67 1.00 20.67
Labour:
102 Blacksmith first class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
TOTAL 3015.11
Add 1% for water charges 30.15
TOTAL 3045.26
Add for contractor’s profit and overheads
@15% 456.79
Cost of 9.04 metres
3502.05
Cost of 1 metre 116.73
Say 116.73

12.12 Providing and fixing ridges and hips in non-asbestos fibre cement high impact
polypropylene reinforced roofing with suitable fixing accessories or self drilling fastener and
EPDM
12.12.1washer etc. complete.
Corrugated serrated adjustable ridges
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:
225 Non - Asbestos fibre cement corrugate
serrated adjustable ridge. metre 24.339 174.00 4234.99
9999 Carriage (The ridge is to be fixed with the
same hooks as the Sheets) L.S. 13.52 1.00 13.52
9999 Sundries L.S. 6.76 1.00 6.76
Labour:
130 Mistry Day 0.14 270 37.80
112 Carpenter 2nd class Day 0.62 223 138.26
114 Beldar Day 1.64 207 339.48
TOTAL 4770.81
Add 1% for water charges 47.71
TOTAL 4818.51
Add for contractor’s profit and overheads
@15% 722.78
Cost of 20.2 metres 5541.29
Cost of 1 metre 274.32
Say 274.32

12.12 Providing and fixing ridges and hips in non-asbestos fibre cement high impact
polypropylene reinforced roofing with suitable fixing accessories or self drilling fastener and
EPDM
12.12.2washer etc. complete.
: Plain wing adjustable ridges
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:
226 Non - Asbestos fibre cement plain wing
adjustable ridge. metre 24.339 188.00 4575.73
9999
Carriage (The ridge is to be fixed with the
same hooks as the Sheets) L.S. 13.52 1.00 13.52
9999 Sundries L.S. 6.76 1.00 6.76
Labour:
130 Mistry Day 0.14 270 37.80
112 Carpenter 2nd class Day 0.55 223 122.65
114 Beldar Day 1.64 207 339.48
TOTAL 5095.94
Add 1% for water charges 50.96
TOTAL 5146.90
Add for contractor’s profit and overheads
@15% 772.04
Cost of 20.2 metres 5918.94
Cost of 1 metre 293.02
Say 293.02

12.12 Providing and fixing ridges and hips in non-asbestos fibre cement high impact
polypropylene reinforced roofing with suitable fixing accessories or self drilling fastener and
EPDM
12.12.3:washer etc. complete.
Close fitting adjustable ridges
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:
224 Non - Asbestos fibre cement close fitting
adjustable ridge. metre 28.182 203.00 5720.95
9999 Carriage (The ridge is to be fixed with the
same hooks as the Sheets) L.S. 16.12 1.00 16.12
9999 Sundries L.S. 7.15 1.00 7.15
Labour:
130 Mistry Day 0.14 270 37.80
112 Carpenter 2nd class Day 0.55 223 122.65
114 Beldar Day 1.64 207 339.48
TOTAL 6244.15
Add 1% for water charges 62.44
TOTAL 6306.59
Add for contractor’s profit and overheads
@15% 945.99
Cost of 20.2 metres 7252.58
Cost of 1 metre 359.04
Say 359.04

12.12 Providing and fixing ridges and hips in non-asbestos fibre cement high impact
polypropylene reinforced roofing with suitable fixing accessories or self drilling fastener and
EPDM
12.12.4washer etc. complete.
Unserrated adjustable hips
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:
227 Non - Asbestos fibre cement unserrated
adjustable ridge. metre 24.339 195.00 4746.11
9999 Carriage (The ridge is to be fixed with the
same hooks as the Sheets) L.S. 6.76 1.00 6.76
9999 Sundries L.S. 6.63 1.00 6.63
Labour:
130 Mistry Day 0.14 270 37.80
112 Carpenter 2nd class Day 0.55 223 122.65
114 Beldar Day 1.64 207 339.48
TOTAL 5259.43
Add 1% for water charges 52.59
TOTAL 5312.02
Add for contractor’s profit and overheads
@15% 796.80
Cost of 20.2 metres 6108.82
Cost of 1 metre 302.42
Say 302.42

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM washer etc. complete:
12.13.1: Corrugated apron pieces
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:
228 Non - Asbestos fibre cement corrugated
appron piece. metre 23.52 126.00 2963.52
9999 Carriage of appron pieces L.S. 3.25 1.00 3.25
9999 Sundries L.S. 3.25 1.00 3.25
Labour:
130 Mistry Day 0.07 270 18.90
112 Carpenter 2nd class Day 0.28 223 62.44
114 Beldar Day 0.82 207 169.74
TOTAL 3221.10
Add 1% for water charges 32.21
TOTAL 3253.31
Add for contractor’s profit and overheads
@15% 488.00
Cost of 20.2 metres 3741.31
Cost of 1 metre 185.21
Say 185.21
12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM washer etc. complete:
12.13.2 : Eave’s filler pieces
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:Non - Asbestos fibre cement eaves filler
229 piece each 21 93.00 1953.00
9999 Carriage of eaves filler L.S. 3.25 1.00 3.25
9999 Sundries L.S. 3.25 1.00 3.25
Labour:
130 Mistry Day 0.07 270 18.90
112 Carpenter 2nd class Day 0.28 223 62.44
114 Beldar Day 0.82 207 169.74
TOTAL 2210.58
Add 1% for water charges 22.11
TOTAL 2232.69
Add for contractor’s profit and overheads
@15% 334.90
Cost of 20.2 metres 2567.59
Cost of 1 metre 127.11
Say 127.11

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM
12.13.3: washer
North lightetc. complete:
curves
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:
230
Non - Asbestos fibre cement north light metre 21.336 197.00 4203.19
1023 G.I., J or L hooks 10 Nos 40 60.00 240.00
1209 Bitumen washers 00 Nos 40 27.00 10.80
1208 Bitumen washers thick 00 Nos 40 18.00 7.20
9999 Carriage of hooks, nuts, washers and
curves L.S. 9.88 1.00 9.88
9999 Sundries L.S. 6.24 1.00 6.24
Labour:
130 Mistry Day 0.1 270 27.00
112 Carpenter 2nd class Day 0.3 223 66.90
114 Beldar Day 1 207 207.00
TOTAL 4778.21
Add 1% for water charges 47.78
TOTAL 4825.99
Add for contractor’s profit and overheads
@15% 723.90
Cost of 20.2 metres 5549.89
Cost of 1 metre 274.75
Say 274.75

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM washer etc. complete:
12.13.4 : ventilator curves
Code Description Unit Quantity Rate Amount
Length of ridges 20.2 metre
M aterials:
231 Non - Asbestos fibre cement ventilator
curves. each 21.336 267.00 5696.71
1023 G.I., J or L hooks 10 Nos 40 60.00 240.00
1209 Bitumen washers 00 Nos 40 27.00 10.80
1208 Bitumen washers thick 00 Nos 40 18.00 7.20
9999 Carriage of hooks, nuts, washers and
curves L.S. 9.88 1.00 9.88
9999 Sundries L.S. 6.24 1.00 6.24
Labour:
130 Mistry Day 0.1 270 27.00
112 Carpenter 2nd class Day 0.3 223 66.90
114 Beldar Day 1 207 207.00
TOTAL 6271.73
Add 1% for water charges 62.72
TOTAL 6334.45
Add for contractor’s profit and overheads
@15% 950.17
Cost of 20.2 metres 7284.62
Cost of 1 metre 360.62
Say 360.62

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM washer etc. complete:
12.13.5: Barge boards
Code Description Unit Quantity Rate Amount
Length of ridges 9.7 metre
M aterials:
232 Non - Asbestos fibre cement barge boards each 10.5 232.00 2436.00
222 Seam bolts and nuts 6 mm dia and 25 mm l tonne 5 30.00 15.00
1208 Bitumen washers 00 Nos 5 18.00 0.90
1211 G.I. plain washers 00 Nos 10 21.00 2.10
9999 Carriage of hooks, nuts, washers and
curves L.S. 9.36 1.00 9.36
9999 Sundries L.S. 6.76 1.00 6.76
Labour:
130 Mistry Day 0.04 270 10.80
112 Carpenter 2nd class Day 0.06 223 13.38
114 Beldar Day 0.4 207 82.80
TOTAL 2577.10
Add 1% for water charges 25.77
TOTAL 2602.87
Add for contractor’s profit and overheads
@15% 390.43
Cost of 9.7 metres 2993.30
Cost of 1 metre 308.59
Say 308.59

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM washer etc. complete:
12.13.6 : Ridge finials
Code Description Unit Quantity Rate Amount
Details of a pair of ridge finials
M aterials:
233
Non - Asbestos fibre cement ridge finial. pair 1.05 84.00 88.20
9999
arriage, sundries, fixing charges including
providing and fixing, seam bolts and nuts,
with G.I. and bitumen washers L.S. 10.79 1.00 10.79
TOTAL 98.99
Add 1% for water charges 0.99
TOTAL 99.98
Add for contractor’s profit and overheads
@15% 15.00
Cost of 1 pair 114.98
Say 114.98

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM washer etc. complete:
12.13.7: Special north light curves
Code Description Unit Quantity Rate Amount
Details for 20 nos.
M aterials:
234 Non - Asbestos fibre cement special north
light curves. each 21 275.00 5775.00
1023 G.I., J or L hooks 10 Nos 40 60.00 240.00
1208 Bitumen washers 00 Nos 40 18.00 7.20
1209 G.I. plain washers thick 00 Nos 40 27.00 10.80
9999 Carriage of hooks, nuts, washers and
curves L.S. 9.88 1.00 9.88
9999 Sundries L.S. 6.24 1.00 6.24
Labour:
130 Mistry Day 0.1 270 27.00
112 Carpenter 2nd class Day 0.3 223 66.90
114 Beldar Day 1 207 207.00
TOTAL 6350.02
Add 1% for water charges 63.50
TOTAL 6413.52
Add for contractor’s profit and overheads
@15% 962.03
Cost of 20 Nos. 7375.55
Cost of 1 No. 368.78
Say 368.78

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene
reinforced roofing accessories in all colour with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener
and EPDM washer etc. complete:
12.13.8 S type louvers
Code Description Unit Quantity Rate Amount
Details of cost for 8.74 metres
M aterials:
235 Non - Asbestos fibre cement S type
louvers each 5.25 161.00 845.25
1031 Galvanised steel bolts & nuts 10 mm dia each 6 15.00 90.00
1032 Galvanised steel bolts 10 m m dia and 7 each 6 15.00 90.00
cm long with
Bitumen nuts
washers 00 Nos 18 18.00 3.24
1208
1210 G.I. plain washer thin 00 Nos 36 20.00 7.20
9999 Carriage L.S. 13.52 1.00 13.52
9999 Sundries L.S. 13.39 1.00 13.39
Labour:
102 Blacksm ith 1st class Day 0.12 270 32.40
111 Carpenter 1st class Day 1 270 270.00
114 Beldar Day 1 207 207.00
TOTAL 1572.00
Add 1% for water charges 15.72
TOTAL 1587.72
Add for contractor’s profit and overheads
@15% 238.16
Cost of 8.74 metres 1825.88
Cost of 1 metre 208.91
Say 208.91

12.14 Providing flat iron brackets 50x3mm size with necessary bolts, nuts and washers etc.
for fixing asbestos cement/G.S. sheets gutters with purlins.
Code Description Unit Quantity Rate Amount
Detail of cost for 20 metre
M aterial:
1008 Fits upto 10 mm in thicknes quintal 0.1163 4600.00 534.98
1025 Mild stel bolts 6 mm dia and 25 mm long
with hexagonal head 10 Nos. 38 20.00 76.00
1024 Galvanised steel bolts & nuts 10 mm dia
and 125 mm long round head with slots
each 19 12.00 228.00
1210 G.I. plain washer thin 00 Nos 19 20.00 3.80
9999 Sundries L.S. 1.04 1.00 1.04
Labour:
102 Blacksm ith 1st class Day 0.38 270 102.60
114 Beldar Day 0.38 207 78.66
TOTAL 1025.08
Add 1% for water charges 10.25
TOTAL 1035.33
Add for contractor’s profit and overheads
@15% 155.30
Cost of 20 metres 1190.63
Cost of 1 metre 59.53
Say 59.53

12.15: Painting top of roofs with bitumen of approved quality at 17kg per 10 sqm
impregnated with a coat of coarse sand at 60 cudm per 10 sqm including cleaning the slab
surface with brushes and finally with a piece of cloth lightly soaked in kerosene oil
complete :
12.15.1: With residual type petroleum bitumen of penetration 80/100
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
M aterial:
309 Cost of Bitumen 80/100 tonne 0.017 22500.00 382.50
771 Cost of kerosene oil litre 1.22 25.00 30.50
370 Cost of fuel for heating (steam coal) quintal 0.035 120.00 4.20
2211 Carriage of bitumen 80/100 tonne 0.017 53.21 0.90
982 Coarse sand cum 0.06 300.00 18.00
2203 Carriage of coarse sand cum 0.06 53.21 3.19
9999 Sundries (Brushes and T and P) L.S. 13.52 1.00 13.52
Labour:
131 Painter Day 0.15 180 27.00
114 Beldar Day 0.38 207 78.66
TOTAL 558.48
Add 1% for water charges 5.58
TOTAL 564.06
Add for contractor’s profit and overheads
@15% 84.61
Cost of 10 sqm 648.67
Cost of 1 sqm 64.87
Say 64.87

12.16 : 10 cm thick (average) mud phaska of damped brick earth on roofs laid to slope
consolidated and plastered with 25 mm thick mud mortar mixed with bhusa at 35kg per
cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow dung) and covered with flat
tile bricks of class designation 100 grouted with cement mortar 1:3 (1 cement: 3 fine sand)
mixed with 2% of integral water proofing compound by weight of cement and finished neat:

12.16.1: With F.P.S. brick tiles


Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
M aterial:
811 Mud phuska cum 1.257 20.00 25.14
Mud mortar for 25 mm thick plaster
over phuska item as per 3.18 litre 0.263 215.16 56.59
308 Bhusa quintal 0.1 200.00 20.00
9999 Cow dung L.S. 5.33 1.00 5.33
9999 Mud mortar for gobri leaping L.S. 8.06 1.00 8.06
9999 Carriage of bhusa and cowdung L.S. 2.73 1.00 2.73
1984 Tile bricks 22.9x11.4x4.4cm of designation 00 N os 380 1600.00 608.00
2207 Carriage of tiles 1000 N os 00 N os 380 85.13 32.35
Cement mortar for grouting 1:3 (1 cemerit
3 fine sand) Rate as for item No. 3.3
cum 0.061 3268.90 199.40
1213 Integral water proofing com pound 2% by
weight of cement ilogram 0.006 20.00 0.12
9999 Sundries L.S. 6.76 1.00 6.76
Labour:
101 Bhisti Day 1.1 180 198.00
124 Mason 2nd class Day 1.3 223 289.90
114 Beldar Day 3.75 207 776.25
TOTAL 2228.63
Add 1% for water charges 22.29
TOTAL 2250.92
Add for contractor’s profit and overheads
@15% 337.64
Cost of 10 sqm 2588.55
Cost of 1 sqm 258.86
Say 258.86

12.17 10cm thick (average) mud phaska of damped brick earth on roofs laid to slope
consolidated and plastered with 25mm thick mud mortar with bhusha at 35kg per cum of
earth and gobri leaping with mix 1:1 (1 clay : 1 cowdung) and covered with machine
moulded tile bricks of class designation 125 conforming to IS : 2690 (Part I)-1992 grouted
water proofing compound by weight of cement and finished neat.with cement mortar 1:3(1
cement: 3 fine sand ) mixed with 2% of integral
12.17.1With machine moulded F.P.S. brick tiles
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
M aterial:
811 Mud phuska cum 1.257 20.00 25.14
Mud mortar for 25 mm thick plaster
over phuska item as per 3.18 litre 0.263 215.16 56.59
308 Bhusa quintal 0.1 200.00 20.00
9999 Cow dung L.S. 5.33 1.00 5.33
9999 Mud mortar for gobri leaping L.S. 8.06 1.00 8.06
9999 Carriage of bhusa and cowdung L.S. 2.73 1.00 2.73
7904 Machine moulded tile bricks of class desig00 N os 380 2717.00 1032.46
2207 Carriage of tiles 1000 N os 00 N os 380 85.13 32.35
Cement mortar for grouting 1:3 (1 cemerit
3 fine sand) Rate as for item No. 3.3
cum 0.061 3268.90 199.40
1213 Integral water proofing com pound 2% by
weight of cement ilogram 0.006 20.00 0.12
9999 Sundries L.S. 6.76 1.00 6.76
Labour:
101 Bhisti Day 1.1 180 198.00
124 Mason 2nd class Day 1.3 223 289.90
114 Beldar Day 3.75 207 776.25
TOTAL 2653.09
Add 1% for water charges 26.53
TOTAL 2679.62
Add for contractor’s profit and overheads
@15% 401.94
Cost of 10 sqm 3081.56
Cost of 1 sqm 308.16
Say 308.16

12.18 Extra for every additional 1 cm thickness of mud phaska


Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
M aterial:
811 Mud phuska cum 0.13 20.00 2.60
101 Bhisti Day 0.04 180 7.20
9999 Labour for leaping and carring to roof L.S. 26.91 1.00 26.91
114 Beldar Day 0.07 207 14.49
TOTAL 51.20
Add 1% for water charges 0.51
TOTAL 51.71
Add for contractor’s profit and overheads
@15% 7.76
Cost of 10 sqm 59.47
Cost of 1 sqm 5.95
Say 5.95

12.19 Providing and laying brick tiles of class designation 100 over mumty roofs grouted
with cement mortar 1:3 (1 cement: 3 fine sand) mixed with 2% of integral water proofing
compound by weight of cement, over a 12 mm layer of cement mortar 1:3 (1 cement: 3 fine
sand) and finished neat:
12.19.1 With F.P.S. brick tiles
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
M aterial:
1984 Bricks tiles of designation 100 00 N os 380 1600.00 608.00
2207 Carriage of tiles 1000 N os 00 N os 380 85.13 32.35
Cement mortar for grouting 1:3 (1 cemerit
3 fine sand) Rate as for item No. 3.3
cum 0.179 3268.90 585.13
1213 Integral water proofing com pound 2% by
weight of cement ilogram 0.005 20.00 0.10
9999 Sundries L.S. 1.82 1.00 1.82
Labour:
101 Bhisti Day 0.27 180 48.60
124 Mason 2nd class Day 0.81 223 180.63
115 Coolie Day 1.08 207 223.56
TOTAL 1680.19
Add 1% for water charges 16.80
TOTAL 1696.99
Add for contractor’s profit and overheads
@15% 254.55
Cost of 10 sqm 1951.54
Cost of 1 sqm 195.15
Say 195.15

12.20 Providing and laying pressed clay tiles (as per approved pattern 20 mm nominal
thickness and of approved size) on roofs jointed with cement mortar 1:4 (1 cement : 4 coarse
sand) mixed with 2% integral water proofing compound laid over a bed of 20 mm thick
cement mortar 1:4(1 cement: 4 coarse sand) and finished neat complete.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
M aterial:
7266 Manglore tiles/Pressed clay Tiles) 00 N os 160 8900.00 1424.00
2207 Carriage of tiles 1000 N os 00 N os 160 85.13 13.62
Cement mortar for grouting 1:4 (1 cemerit
4 coarse sand) Rate as for item No. 3.9
cum 0.57 2580.18 1470.70
1213 Integral water proofing com pound 2% by
weight of cement ilogram 0.01 20.00 0.20
9999 Sundries L.S. 13 1.00 13.00
Labour:
123 Mason 1st class Day 0.6 270 162.00
114 Beldar Day 2.6 207 538.20
TOTAL 3621.72
Add 1% for water charges
36.22
TOTAL 3657.94
Add for contractor’s profit and overheads
@15% 548.69
Cost of 10 sqm 4206.63
Cost of 1 sqm 420.66
Say 420.66

12.21 Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 stone
aggregate 10mm and down gauge) including finishing with cement mortar 1:3 (1 cement: 3
fine sand) as per standard design :
12.21.1 In 75x75mm deep chase
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres cement concrete
297 Stone Aggregate (Single size): 10 mm nomin cum 0.0836 1050.00 87.78
2202 Carriage of Stone Aggregate below 40 mm cum 0.0836 53.21 4.45
982 Coarse sand cum 0.0418 300.00 12.54
2203 Carriage of coarse sand cum 0.0418 53.21 2.22
367 Portland cement tonne 0.03 5200.00 156.00
2209 Carriage of cement tonne 0.03 47.29 1.42
Cement mortar for grouting 1:3 (1 cemerit
3 fine sand) Rate as for item No. 3.3
cum 0.009 3268.90 29.42
9999 Hire and running charge of mechanical mixe L.S. 4.16 1.00 4.16
Labour:
123 Mason 1st class Day 0.405 270 109.35
114 Beldar Day 1.085 207 224.60
101 Bhisti Day 0.058 180 10.44
124 Mason 2nd class Day 0.405 223 90.32
115 Coolie Day 0.157 207 32.50
128 Mate Day 0.0037 313 1.16
155 Mason Day 0.081 180 14.58
9999 Sundries L.S. 10.27 1.00 10.27
9999 Carriage L.S. 8.06 1.00 8.06
TOTAL 799.26
Add 1% for water charges 7.99
TOTAL 807.25
Add for contractor’s profit and overheads
@15% 121.09
Cost of 10 metres 928.34
Cost of 1 metre 92.83
Say 92.83

12.22 Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm nominal size) over
P.V.C. sheet 1mx 1mx 400 micron, finished with 12mm cement plaster 1:3 (1 cement : 3
coarse sand) and a coat of neat cement rounding the edge and making and finishing the outlet
complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
295 Stone Aggregate (Single size): 20 mm nomin cum 0.0067 1100.00 7.37
297 Stone Aggregate (Single size): 10 mm nomin cum 0.0022 1050.00 2.31
2202 Carriage of Stone Aggregate below 40 mm cum 0.0089 53.21 0.47
982 Coarse sand cum 0.0044 300.00 1.32
2203 Carriage of coarse sand cum 0.0044 53.21 0.23
367 Portland cement tonne 0.0038 5200.00 19.76
2209 Carriage of cement tonne 0.0038 47.29 0.18
Cement mortar for grouting 1:3 (1 cemerit
3 coarse sand) Rate as for item No. 3.8
cum 0.0041 3262.33 13.38
9999 Hire and running charge of mechanical mixe L.S. 0.26 1.00 0.26
3002 PVC sheet 400 micron thick sqm 1 26.00 26.00
Labour:
123 Mason 1st class Day 0.001 270 0.27
114 Beldar Day 0.009 207 1.86
101 Bhisti Day 0.0132 180 2.38
115 Coolie Day 0.0435 207 9.00
128 Mate Day 0.0004 313 0.13
155 Mason Day 0.0315 180 5.67
9999 Sundries L.S. 14.04 1.00 14.04
9999 Rounding of edges and making outlet L.S. 0.26 1.00 0.26
TOTAL 104.89
Add 1% for water charges 1.05
TOTAL 105.94
Add for contractor’s profit and overheads
@15% 15.89
Cost of 1 no. 121.83
Say 121.83
12.23 Providing sand stone slab for roofing and laying them in cement mortar 1 : 4 (1
cement: 4 coarse sand) over wooden karries or R.C.C. battens (Karries and battens to be
paid separately) including pointing the ceiling joints with cement mortar 1:3 (1 cement: 3
fine sand ) complete :
12.23.1 Red sand stone slab
12.23.1.1 40 to 50 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
1174 Stone slab including wastage @ 10% = 11 s sqm 11 430.00 4730.00
2216 Carriage of Stone slab cum 1.27 47.29 60.06
Cement mortar for grouting 1:4 (1 cemerit
4 coarse sand) Rate as for item No. 3.9
cum 0.0095 2580.18 24.51
Cement mortar for grouting 1:3 (1 cemerit
3 fine sand) Rate as for item No. 3.3
cum 0.0075 3268.90 24.52
9999 Hire and running charge of mechanical mixe L.S. 4.16 1.00 4.16
Labour:
100 Bandhani Day 1.82 180 327.60
101 Bhisti Day 0.3 180 54.00
115 Coolie Day 1.52 207 314.64
155 Mason Day 1.52 180 273.60
9999 Sundries L.S. 16.12 1.00 16.12
TOTAL 5829.21
Add 1% for water charges 58.29
TOTAL 5887.50
Add for contractor’s profit and overheads 883.12
@15%
Cost of 10 sqm 6770.62
Cost of 1 sqm 677.06
Say 677.06

12.23 Providing sand stone slab for roofing and laying them in cement mortar 1 : 4 (1
cement: 4 coarse sand) over wooden karries or R.C.C. battens (Karries and battens to be
paid separately) including pointing the ceiling joints with cement mortar 1:3 (1 cement: 3
fine sand ) complete :
12.23.2 White sand stone slab :
12.23.2.1 40 to 50 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
1175 Stone slab including wastage @ 10% = 11 s sqm 11 160.00 1760.00
2216 Carriage of Stone slab cum 1.27 47.29 60.06
Cement mortar for grouting 1:4 (1 cemerit
4 coarse sand) Rate as for item No. 3.9
cum 0.0095 2580.18 24.51
Cement mortar for grouting 1:3 (1 cemerit
3 fine sand) Rate as for item No. 3.3
cum 0.0075 3268.90 24.52
9999 Hire and running charge of mechanical mixe L.S. 4.16 1.00 4.16
Labour:
100 Bandhani Day 1.82 180 327.60
101 Bhisti Day 0.3 180 54.00
115 Coolie Day 1.52 207 314.64
155 Mason Day 1.52 180 273.60
9999 Sundries L.S. 16.12 1.00 16.12
TOTAL 2859.21
Add 1% for water charges 28.59
TOTAL 2887.80
Add for contractor’s profit and overheads
@15% 433.17
Cost of 10 sqm 3320.97
Cost of 1 sqm 332.10
Say 332.10

12.24 Providing and fixing insulating board ceiling of approved quality with necessary nails
etc. complete (frame work to be paid separately):
12.24.1 Natural colour insulating board
12.24.1.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
332 Insulating board including 10% wastage sqm 11 175.00 1925.00
9999 Carriage of material L.S. 17.55 1.00 17.55
Labour:
111 Carpenter 1st class Day 2.5 270 675.00
114 Beldar Day 2 207 414.00
9999 Scaffolding L.S. 31.07 1.00 31.07
9999 Sundries L.S. 31.07 1.00 31.07
9999 Nails L.S. 26.91 1.00 26.91
TOTAL 3120.60
Add 1% for water charges 31.21
TOTAL 3151.81
Add for contractor’s profit and overheads
@15% 472.77
Cost of 10 sqm 3624.58
Cost of 1 sqm 362.46
Say 362.46

12.24 Providing and fixing insulating board ceiling of approved quality with necessary nails
etc. complete (frame work to be paid separately):
12.24.2 White face insulating board
12.24.2.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
328 White face insulating board 12 mm thick sqm 11 239.00 2629.00
9999 Carriage of material L.S. 17.55 1.00 17.55
Labour:
111 Carpenter 1st class Day 2.5 270 675.00
114 Beldar Day 2 207 414.00
9999 Scaffolding L.S. 31.07 1.00 31.07
9999 Sundries L.S. 31.07 1.00 31.07
9999 Nails L.S. 26.91 1.00 26.91
TOTAL 3824.60
Add 1% for water charges 38.25
TOTAL 3862.85
Add for contractor’s profit and overheads
@15% 579.43
Cost of 10 sqm 4442.27
Cost of 1 sqm 444.23
Say 444.23

12.24 Providing and fixing insulating board ceiling of approved quality with necessary nails
etc. complete (frame work to be paid separately):
12.24.3 Flame retardant face insulating board
12.24.3.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
336 Flame retardent face insulating board 12 mm sqm 11 208.00 2288.00
9999 Carriage of material L.S. 17.55 1.00 17.55
Labour:
111 Carpenter 1st class Day 2.5 270 675.00
114 Beldar Day 2 207 414.00
9999 Scaffolding L.S. 31.07 1.00 31.07
9999 Sundries L.S. 31.07 1.00 31.07
9999 Nails L.S. 26.91 1.00 26.91
TOTAL 3483.60
Add 1% for water charges 34.84
TOTAL 3518.44
Add for contractor’s profit and overheads
@15% 527.77
Cost of 10 sqm 4046.20
Cost of 1 sqm 404.62
Say 404.62

12.25 Providing and fixing flat pressed 3 layer medium density particle board or graded
particle board (Grade I) IS: 3087 marked in ceiling with necessary nails etc. complete (frame
work to be paid separately):
12.25.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
341 Standard quality board 12mm thick sqm 11 258.00 2838.00
9999 Carriage of material L.S. 14.95 1.00 14.95
Labour:
111 Carpenter 1st class Day 2.5 270 675.00
114 Beldar Day 2 207 414.00
9999 Scaffolding L.S. 31.07 1.00 31.07
9999 Sundries L.S. 31.07 1.00 31.07
9999 Nails L.S. 26.91 1.00 26.91
TOTAL 4031.00
Add 1% for water charges 40.31
TOTAL 4071.31
Add for contractor’s profit and overheads
@15% 610.70
Cost of 10 sqm 4682.01
Cost of 1 sqm 468.20
Say 468.20

12.26 Providing and fixing plain multipurpose cement board (high pressure steam cured )
as per IS 14862: 2000 with suitable fibre cement screw in ceiling etc complete, (frame work
to be paid
12.26.1 separately
6 mm ).
thick cement board
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
236 Non - Asbestos multi purpose fibre cement sqm 11 180.00 1980.00
9999 Carriage of material L.S. 14.95 1.00 14.95
Labour:
111 Carpenter 1st class Day 2.5 270 675.00
114 Beldar Day 2 207 414.00
9999 Scaffolding L.S. 31.07 1.00 31.07
9999 Sundries L.S. 31.07 1.00 31.07
9999 Nails L.S. 26.91 1.00 26.91
TOTAL 3173.00
Add 1% for water charges 31.73
TOTAL 3204.73
Add for contractor’s profit and overheads
@15% 480.71
Cost of 10 sqm 3685.44
Cost of 1 sqm 368.54
Say 368.54

12.27 Extra for Circular cutting and waste in ceiling with:


12.27.1 2nd class teak wood planks 20 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 15.71 metre
Materials :-
1190 Teak wood 2nd class 0 cudm 41.16 410.00 1687.56
2204 Carriage cum 0.041 60.81 2.49
637 M.S. screws 40 mm long 00 Nos 31 30.00 9.30
Labour:
111 Carpenter 1st class Day 2.65 270 715.50
112 Carpenter 2nd class Day 0.145 223 32.34
114 Beldar Day 2.79 207 577.53
9999 Scaffolding L.S. 7.8 1.00 7.80
9999 Sundries L.S. 14.69 1.00 14.69
TOTAL 3047.21
Add 1% for water charges 30.47
TOTAL 3077.68
Add for contractor’s profit and overheads
@15% 461.65
Cost of 15.71 m 3539.33
Cost of 1 m 225.29
Say 225.29

12.27 Extra for Circular cutting and waste in ceiling with:


12.27.2 Natural colour insulating board
12.27.2.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 15.71 metre
Materials :-
332 Insulating board including 10% wastage sqm 2.15 175.00 376.25
9999 Carriage L.S. 3.38 1.00 3.38
9999 Nails L.S. 5.33 1.00 5.33
Labour:
111 Carpenter 1st class Day 2.99 270 807.30
114 Beldar Day 2.89 207 598.23
9999 Scaffolding L.S. 16.9 1.00 16.90
9999 Sundries L.S. 6.11 1.00 6.11
TOTAL 1813.50
Add 1% for water charges 18.14
TOTAL 1831.64
Add for contractor’s profit and overheads
@15% 274.75
Cost of 15.71 m 2106.38
Cost of 1 m 134.08
Say 134.08

12.27 Extra for Circular cutting and waste in ceiling with:


12.27.3 White face insulating board:
12.27.3.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 15.71 metre
Materials :-
328 White face insulating board 12 mm thick sqm 2.15 239.00 513.85
9999 Carriage L.S. 3.38 1.00 3.38
9999 Nails L.S. 5.33 1.00 5.33
Labour:
111 Carpenter 1st class Day 2.99 270 807.30
114 Beldar Day 2.89 207 598.23
9999 Scaffolding L.S. 16.9 1.00 16.90
9999 Sundries L.S. 6.11 1.00 6.11
TOTAL 1951.10
Add 1% for water charges 19.51
TOTAL 1970.61
Add for contractor’s profit and overheads
@15% 295.59
Cost of 15.71 m 2266.20
Cost of 1 m 144.25
Say 144.25

12.27 Extra for Circular cutting and waste in ceiling with:


12.27.4 Flame retardant face insulating board:
12.27.4.1 12 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 15.71 metre
Materials :-
336 Flame retardent face insulating board 12 mm sqm 2.15 208.00 447.20
9999 Carriage L.S. 3.38 1.00 3.38
9999 Nails L.S. 5.33 1.00 5.33
Labour:
111 Carpenter 1st class Day 2.99 270 807.30
114 Beldar Day 2.89 207 598.23
9999 Scaffolding L.S. 16.9 1.00 16.90
9999 Sundries L.S. 6.11 1.00 6.11
TOTAL 1884.45
Add 1% for water charges 18.84
TOTAL 1903.29
Add for contractor’s profit and overheads
@15% 285.49
Cost of 15.71 m 2188.79
Cost of 1 m 139.32
Say 139.32

12.27 Extra for Circular cutting and waste in ceiling with:


12.27.5 Standard quality hard board sheet:
12.27.5.1 3 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 15.71 metre
Materials :-
994 Insulating board sqm 2.15 103.00 221.45
9999 Carriage L.S. 2.73 1.00 2.73
9999 Nails L.S. 5.33 1.00 5.33
Labour:
111 Carpenter 1st class Day 2.99 270 807.30
114 Beldar Day 2.89 207 598.23
9999 Scaffolding L.S. 16.9 1.00 16.90
9999 Sundries L.S. 6.11 1.00 6.11
TOTAL 1658.05
Add 1% for water charges 16.58
TOTAL 1674.63
Add for contractor’s profit and overheads
@15% 251.19
Cost of 15.71 m 1925.83
Cost of 1 m 122.59
Say 122.59

12.27 Extra for Circular cutting and waste in ceiling with:


12.27.5 Standard quality hard board sheet:
12.27.5.2 4.5 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 15.71 metre
Materials :-
996 Insulating board sqm 2.15 120.00 258.00
9999 Carriage L.S. 2.86 1.00 2.86
9999 Nails L.S. 5.33 1.00 5.33
Labour:
111 Carpenter 1st class Day 2.99 270 807.30
114 Beldar Day 2.89 207 598.23
9999 Scaffolding L.S. 16.9 1.00 16.90
9999 Sundries L.S. 6.11 1.00 6.11
TOTAL 1694.73
Add 1% for water charges 16.95
TOTAL 1711.68
Add for contractor’s profit and overheads
@15% 256.75
Cost of 15.71 m 1968.43
Cost of 1 m 125.30
Say 125.30
12.28 Extra for providing and fixing ceiling to curved surfaces in narrow widths
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Labour:
111 Carpenter 1st class Day 1 270 270.00
112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 2 207 414.00
TOTAL 907.00
Add 1% for water charges 9.07
TOTAL 916.07
Add for contractor’s profit and overheads
@15% 137.41
Cost of 10 sqm 1053.48
Cost of 1 sqm 105.35
Say 105.35

12.29 Providing and fixing false ceiling with 12 mm thick plain/ semi perforated or with
design ceiling tiles of BWP type phenol formaldehyde synthetic resin bonded pressed
particle board conforming to IS:3087 finished with a coat of aluminium primer on particle
board conforming to IS:3087 finished with a coat of aluminium primer on both sides &
edges and two coats of synthetic enamel paint of approved quality on exposed face fixed to a
grid made out of anodised aluminium (with 15 micron anodic coating) T-sections 35 xl5xl.5
mm size main runners and cross runners 23.5x19x1.5mm fixed to main runners placed 600
mm centre to centre both ways so as to form a grid of 600 mm square. The frame work shall
be suspended from ceiling by level adjusting hangers of 6 mm dia M.S rod fixed to roof slab
by means of ceiling cleats. The suspenders shall be placed 600x 1200 mm centre to centre
including fixing to the frame with C.P brace screws and applying a priming coat of zinc
chromate yellow primer ( aluminium frame work shall be paid separately.)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
Materials :-
7267 Plain ceiling tiles 600x600x12 mm thick each 11 90.00 990.00
9999 Carriage of tiles L.S. 14.82 1.00 14.82
9999 C.P. brase screws L.S. 26.91 1.00 26.91
Labour:
111 Carpenter 1st class Day 2.5 270 675.00
114 Beldar Day 2 207 414.00
9999 Scaffolding L.S. 31.07 1.00 31.07
9999 Sundries L.S. 31.07 1.00 31.07
TOTAL 2182.87
Add 1% for water charges 21.83
TOTAL 2204.70
Add for contractor’s profit and overheads
@15% 330.70
Cost of 10 sqm 2535.40
Cost of 10 sqm 253.54
Say 253.54

12.30 Extra for providing 3 mm thick translucent white acrylic plastic sheets of approved
quality in false ceiling instead of 12 mm thick plain/or with design particle board ceiling tiles
in item above.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
Materials :-
7385 3 mm thick translucent white acrylic sqm 10 515.00 5150.00
7386 Cost of 3 mm thick translucent white acryl sqm 10 225.00 2250.00
Difference in cost 2900.00
Add 1% for water charges 29.00
TOTAL 2929.00
Add for contractor’s profit and overheads
@15% 439.35
Cost of 10 sqm 3368.35
Cost of 10 sqm 336.84
Say 336.84

12.31 Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling upto a height of 5
m above floor level over first class kail wood strips 25x6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to wooden frame (frame work to be paid
separately):
12.31.1 Flat surfaces
Code Description Unit Quantity Rate Amount
Details of cos t for 4.00x2.5=10sqm.
Materials :-
1196 Kail wood 1 st class 0 cudm 47.52 186.00 883.87
2204 Carriage of timber cum 0.0475 60.81 2.89
1219
Nail required for fixing the laths to frame
work including breakage and wastage of
nails ilogram 0.75 70.00 52.50
1220 Rabbit wire mesh sqm 10.2 38.00 387.60
869 Plaster of Paris ilogram 219.76 3.00 659.28
2308 Carriage of Plaster of Paris tonne 0.22 47.29 10.40
9999 Carriage of wiremesh and nails etc. L.S. 2.73 1.00 2.73
Labour:
101 Bhisti Day 0.54 180 97.20
111 Carpenter 1st class Day 1.6 270 432.00
122 Mason Day 3.23 313 1010.99
114 Beldar Day 4.83 207 999.81
9999 Scaffolding L.S. 83.98 1.00 83.98
9999 Sundries L.S. 53.82 1.00 53.82
TOTAL 4677.07
Add 1% for water charges 46.77
TOTAL 4723.84
Add for contractor’s profit and overheads
@15% 708.58
Cost of 10 sqm 5432.42
Cost of 1 sqm 543.24
Say 543.24

12.31 Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling upto a height of 5
m above floor level over first class kail wood strips 25x6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to wooden frame (frame work to be paid
separately):
12.31.2 Curved surfaces
Code Description Unit Quantity Rate Amount
Details of cos t for 4.00x2.5=10sqm.
Materials :-
1196 Kail wood 1 st class 0 cudm 47.52 186.00 883.87
2204 Carriage of timber cum 0.0475 60.81 2.89
1219
Nail required for fixing the laths to frame
work including breakage and wastage of
nails ilogram 0.75 70.00 52.50
1220 Rabbit wire mesh sqm 10.2 38.00 387.60
869 Plaster of Paris ilogram 219.76 3.00 659.28
2308 Carriage of Plaster of Paris tonne 0.22 47.29 10.40
9999 Carriage of wiremesh and nails etc. L.S. 2.73 1.00 2.73
Labour:
101 Bhisti Day 0.54 180 97.20
111 Carpenter 1st class Day 2.1 270 567.00
122 Mason Day 4.23 313 1323.99
114 Beldar Day 6.33 207 1310.31
9999 Scaffolding L.S. 83.98 1.00 83.98
9999 Sundries L.S. 53.82 1.00 53.82
TOTAL 5435.57
Add 1% for water charges 54.36
TOTAL 5489.93
Add for contractor’s profit and overheads
@15% 823.49
Cost of 10 sqm 6313.42
Cost of 1 sqm 631.34
Say 631.34

12.32 Extra for any sunk or raised mouldings in the plaster of Paris (Gypsum anhydrous)
ceiling Description
Code Unit Quantity Rate Amount
Details of cost for 10 sqm.
869 Plaster of Paris ilogram 109.88 3.00 329.64
2308 Carriage of Plaster of Paris tonne 0.11 47.29 5.20
Labour:
101 Bhisti Day 0.25 180 45.00
122 Mason Day 2 313 626.00
114 Beldar Day 2 207 414.00
9999 Scaffolding & sundries L.S. 13.52 1.00 13.52
TOTAL 1433.36
Add 1% for water charges 14.33
TOTAL 1447.70
Add for contractor’s profit and overheads
@15% 217.15
Cost of 10 sqm 1664.85
Cost of 1 sqm 166.48
Say 166.48

12.33 Extra for providing plaster of Paris (Gypsum anhydrous) ceiling above 5 metres
height from
Code floor level
Description Unit Quantity Rate Amount
Details of cost for l0sqm/metre height
Labour:
101 Bhisti Day 0.25 180 45.00
122 Mason Day 1 313 313.00
114 Beldar Day 1 207 207.00
9999 Scaffolding & sundries L.S. 13.52 1.00 13.52
TOTAL 578.52
Add 1% for water charges 5.79
TOTAL 584.31
Add for contractor’s profit and overheads
@15% 87.65
Cost of.10.00sqm / metre height 671.95
Cost of 1.00 sqm. / metre height 67.20
Say 67.20

12.34 Providing and fixing thermal insulation of ceiling (under deck insulation) with Resin
Bonded Fibre glass wool conforming to IS : 8183 density 24kg/m3, 50mm thick, wrapped
in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm
and wire mesh of 12.5mm x 24g wire and mesh, for top most ceiling of building.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00sqm.
7232 Resin Bonded Glass wool 24 kg/m 50 mm
thick sqm 11 163.00 1793.00
Labour:
111 Carpenter 1st class Day 1 270 270.00
114 Beldar Day 2 207 414.00
9999 Sundries including GI wire 20 SWG and
Virgin polythene bags 200 gram L.S. 104 1.00 104.00
9999 GI chiken m esh 12.5mm x 24 SWG L.S. 351 1.00 351.00
TOTAL 2932.00
Add 1% for water charges 29.32
TOTAL 2961.32
Add for contractor’s profit and overheads
@15% 444.20
Cost of 10 sqm 3405.52
Cost of 1 sqm 340.55
Say 340.55

12.35 Providing and fixing thermal insulation with Resin Bonded Fibre glass wool
conforming to IS : 8183. Density 16kg/m3 50mm thick, wrapped in 200G Virgin
Polythene bags placed over existing false ceiling and held in position by criss-crossing GI
wire.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00sqm.
7231 Resin Bonded Glass wool 16 kg/m 50 mm
thick sqm 11 114.00 1254.00
Labour:
111 Carpenter 1st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
9999 Sundries including GI wire 20 SWG and
Virgin polythene bags 200 gram L.S. 52 1.00 52.00
TOTAL 1544.50
Add 1% for water charges 15.45
TOTAL 1559.95
Add for contractor’s profit and overheads
@15% 233.99
Cost of 10 sqm 1793.94
Cost of 1 sqm 179.39
Say 179.39
168.35
12.36 Thermal Insulation of roofing with Expanded polystyrene fixed with suitable
adhesive to the false ceiling as per the directions of the Engineer-in-charge :
12.36.1 With Type N - Normal 50 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10.00sqm.
7090 Expanded polystyrene type N- Normal sqm 11 108.00 1188.00
314 Adhesive Bitumen hot sealing compound :
grade A ilogram 0.25 35.00 8.75
Labour:
111 Carpenter 1st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
9999 Sundries L.S. 13 1.00 13.00
TOTAL 1448.25
Add 1% for water charges 14.48
TOTAL 1462.73
Add for contractor’s profit and overheads
@15% 219.41
Cost of 10 sqm 1682.14
Cost of 1 sqm 168.21
Say 168.21

12.36 Thermal Insulation of roofing with Expanded polystyrene fixed with suitable
adhesive to the false ceiling as per the directions of the Engineer-in-charge :
12.36.2 With Type SE - Self Extinguishing type 50 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for 10.00sqm.
7091 Expanded polystyrene type - SE sqm 11 131.00 1441.00
314 Adhesive Bitumen hot sealing compound :
grade A ilogram 0.25 35.00 8.75
Labour:
111 Carpenter 1st class Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
9999 Sundries L.S. 13 1.00 13.00
TOTAL 1701.25
Add 1% for water charges 17.01
TOTAL 1718.26
Add for contractor’s profit and overheads 257.74
@15%
Cost of 10 sqm 1976.00
Cost of 1 sqm 197.60
Say 197.60

12.37 Providing and fixing 100 mm diameter and 60 cm long rain water spout in cement
mortar 1:4 (1 cement: 4 fine sand)
12.37.1 Stone ware spout
Code Description Unit Quantity Rate Amount
Details of cost for 10 stone ware spout of 60cm long
3004 Stone ware spouts 100 mm dia 60 cm
long each 6 28.00 168.00
9999 Carriage L.S. 13.52 1.00 13.52
9999 Mortar L.S. 13.52 1.00 13.52
Labour for fixing and placing in position
124 Mason Day 0.4 223 89.20
114 Beldar Day 0.4 207 82.80
9999 Sundries L.S. 5.33 1.00 5.33
TOTAL 372.37
Add 1% for water charges 3.72
TOTAL 376.09
Add for contractor’s profit and overheads
@15% 56.41
Cost of 10 sqm 432.51
Cost of 1 sqm 43.25
Say 43.25
12.38 Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I, rain
water pipes embedded in and including cement concrete blocks 10x10x 10cm of 1:2:4 mix (1
cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting
holes and making good the walls etc. :
12.38.1 100 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost of 5 nos.
1331 M.S. holder bat clamps each 5 13.00 65.00
295 Stone aggregate 20 mm cum 0.0033 1100.00 3.63
297 Stone aggregate 10 mm cum 0.0011 1050.00 1.16
2202 Carriage of aggregate below 20mm cum 0.0044 53.21 0.23
982 Coarse sand cum 0.0022 300.00 0.66
2261 Carriage of coarse sand cum 0.0022 53.21 0.12
367 Cement (0.15674 cum) tonne 0.0016 5200.00 8.32
2209 Carriage of cement tonne 0.0016 47.29 0.08
9999 Sundries L.S. 7.15 1.00 7.15
9999 Carriage of bat clamps L.S. 2.47 1.00 2.47
Labour for fixing and placing in position
101 Bhisti Day 0.0014 180 0.25
123 Mason ist class Day 0.0003 270 0.08
124 Mason 2nd class Day 0.7503 223 167.32
128 Mate Day 0.0002 313 0.06
114 Beldar Day 0.5045 207 104.43
115 Coolie Day 0.0032 207 0.66
116 Fitter Day 0.125 270 33.75
9999 Hire charges of machine etc. L.S. 0.26 1.00 0.26
9999 Sundries L.S. 0.26 1.00 0.26
TOTAL 395.89
Add 1% for water charges 3.96
TOTAL 399.85
Add for contractor’s profit and overheads
@15% 59.98
Cost of 5 nos. of bat clamps 459.82
Cost of 1 no of bat clamp 91.96
Say 91.96

12.38 Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I, rain
water pipes embedded in and including cement concrete blocks 10x10x 10cm of 1:2:4 mix (1
cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting
holes and making good the walls etc. :
12.38.2 150 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost of 5 nos.
886 M.S. holder bat clamps each 5 20.00 100.00
295 Stone aggregate 20 mm cum 0.0033 1100.00 3.63
297 Stone aggregate 10 mm cum 0.0011 1050.00 1.16
2202 Carriage of aggregate below 20mm cum 0.0044 53.21 0.23
982 Coarse sand cum 0.0022 300.00 0.66
2261 Carriage of coarse sand cum 0.0022 53.21 0.12
367 Cement (0.15674 cum) tonne 0.0016 5200.00 8.32
2209 Carriage of cement tonne 0.0016 47.29 0.08
9999 Sundries L.S. 7.15 1.00 7.15
9999 Carriage of bat clamps L.S. 2.47 1.00 2.47
Labour for fixing and placing in position
101 Bhisti Day 0.0014 180 0.25
123 Mason ist class Day 0.0003 270 0.08
124 Mason 2nd class Day 0.7503 223 167.32
128 Mate Day 0.0002 313 0.06
114 Beldar Day 0.5045 207 104.43
115 Coolie Day 0.0032 207 0.66
116 Fitter Day 0.125 270 33.75
9999 Hire charges of machine etc. L.S. 0.26 1.00 0.26
9999 Sundries L.S. 0.26 1.00 0.26
TOTAL 430.89
Add 1% for water charges 4.31
TOTAL 435.20
Add for contractor’s profit and overheads
@15% 65.28
Cost of 5 nos. of bat clamps 500.48
Cost of 1 no of bat clamp 100.10
Say 100.10

12.39 Providing lead caulked joints to sand cast iron rain water pipes and fittings:
12.39.1 100mm dia. Pipe
Code Description Unit Quantity Rate Amount
Details of cost for one joint.
865 Pig lead ilogram 0.98 140.00 137.20
1001 Spunyarn ilogram 0.11 30.00 3.30
9999 Kerosene oil fuel and sundries L.S. 13.52 1.00 13.52
9999 Carriage of materials L.S. 1.43 1.00 1.43
Labour for fixing and placing in position
114 Beldar Day 0.12 207 24.84
117 Assistant fitter Day 0.06 223 13.38
116 Fitter Day 0.06 270 16.20
TOTAL 209.87
Add 1% for water charges 2.10
TOTAL 211.97
Add for contractor’s profit and overheads
@15% 31.80
Cost of 1.00 joint. 243.76
Say 243.76
12.39 Providing lead caulked joints to sand cast iron rain water pipes and fittings.
12.39.2 150mm dia. Pipe
Code Description Unit Quantity Rate Amount
Details of cost for one joint.
865 Pig lead ilogram 1.48 140.00 207.20
1001 Spunyarn ilogram 0.17 30.00 5.10
9999 Kerosene oil fuel and sundries L.S. 13.52 1.00 13.52
9999 Carriage of materials L.S. 2.73 1.00 2.73
Labour for fixing and placing in position
114 Beldar Day 0.15 207 31.05
117 Assistant fitter Day 0.08 223 17.84
116 Fitter Day 0.08 270 21.60
TOTAL 299.04
Add 1% for water charges 2.99
TOTAL 302.03
Add for contractor’s profit and overheads
@15% 45.30
Cost of 1.00 joint. 347.33
Say 347.33

12.40 Providing, fixing and embedding sand cast iron accessories for rain water pipes in the
masonry surrounded with” 12mm thick cement mortar of the same mix, as that of masonry
(lead caulking will be paid for separately):
12.40.1 Sand cast iron plain shoes :
12.40.1.1 150 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for one shoe
966 150 mm sand cast iron plain shoe each 1 222.00 222.00
9999 Carriage, fixing and mortar L.S. 17.55 1.00 17.55
TOTAL 239.55
Add 1% for water charges 2.40
TOTAL 241.95
Add for contractor’s profit and overheads
@15% 36.29
Cost of 1.00 joint. 278.24
Say 278.24

12.41 Providing and fixing on wall face unplasticised Rigid PVC rain water pipes
conforming to IS : 13592 Type A including jointing with seal ring conforming to IS : 5382
leaving 10 mm gap for thermal expansion, (i) Single socketed pipes
12.41.1 75 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for 6.00 metres
7188 Cost of 6.00 m etres pipe metre 6 58.00 348.00
7190 Seal rings metre 1 14.00 14.00
9999 Carriage of materials L.S. 13.52 1.00 13.52
9999 Adhesive, and sundries L.S. 6.76 1.00 6.76
Labour :-
116 Fitter (Grade- 1) Day 0.19 270 51.30
100 Bandhani Day 0.08 180 14.40
114 Beldar Day 0.37 207 76.59
9999 Scaffolding etc. L.S 18.59 1.00 18.59
TOTAL 543.16
Add 1% for water charges 5.43
TOTAL 548.59
Add 15% for contractor’s profit and
overheads 82.29
Cost of 6 metres 630.88
Cost of 1 metre 105.15
Say 105.15

12.41 Providing and fixing on wall face unplasticised Rigid PVC rain water pipes
conforming to IS : 13592 Type A including jointing with seal ring conforming to IS : 5382
leaving 10 mm gap for thermal expansion, (i) Single socketed pipes

12.41.2 110 mm diameter


Code Description Unit Quantity Rate Amount
Details of cost for 6.00 metres
7189 Cost of 6.00 m etres pipe metre 6 112.00 672.00
7191 Seal rings metre 1 17.00 17.00
9999 Carriage of materials L.S. 17.55 1.00 17.55
9999 Adhesive, and sundries L.S. 8.06 1.00 8.06
Labour :-
116 Fitter (Grade- 1) Day 0.23 270 62.10
100 Bandhani Day 0.11 180 19.80
114 Beldar Day 0.45 207 93.15
9999 Scaffolding etc. L.S 18.59 1.00 18.59
TOTAL 908.25
Add 1% for water charges 9.08
TOTAL 917.33
Add 15% for contractor’s profit and
overheads 137.60
Cost of 6 metres 1054.93
Cost of 1 metre 175.82
Say 175.82
12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.1 Coupler
12.42.1.1 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 coupler
Materials :-
7192 UPVC coupler for pipes 75 mm each 1 30.00 30.00
7190 Seal rings metre 2 14.00 28.00
9999 Adhesive, and sundries L.S. 2.73 1.00 2.73
Labour:
9999 Carriage and fixing charges L.S. 9.36 1.00 9.36
TOTAL 70.09
Add 1% for water charges 0.70
TOTAL 70.79
Add for contractor’s profit and overheads
@15% 10.62
Cost of 1 coupler 81.41
Say 81.41

12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.1 Coupler
12.42.1.2 110 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 coupler
Materials :-
7193 UPVC coupler for pipes 110 mm each 1 40.00 40.00
7191 Seal rings metre 2 17.00 34.00
9999 Adhesive, and sundries L.S. 2.73 1.00 2.73
Labour:
9999 Carriage and fixing charges L.S. 10.79 1.00 10.79
TOTAL 87.52
Add 1% for water charges 0.88
TOTAL 88.40
Add for contractor’s profit and overheads
@15% 13.26
Cost of 1 coupler 101.65
Say 101.65
12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.2 Single push fit Coupler:
12.42.2.1 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 coupler
Materials :-
7194 UPVC coupler for pipes 75 mm each 1 47.00 47.00
7190 Seal rings metre 2 14.00 28.00
9999 Adhesive, and sundries L.S. 2.73 1.00 2.73
Labour:
9999 Carriage and fixing charges L.S. 9.36 1.00 9.36
TOTAL 87.09
Add 1% for water charges 0.87
TOTAL 87.96
Add for contractor’s profit and overheads
@15% 13.19
Cost of 1 coupler 101.16
Say 101.16

12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.2 Single push fit Coupler:
12.42.2.2 110 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 coupler
Materials :-
7195 UPVC coupler for pipes 110 mm each 1 72.00 72.00
7191 Seal rings metre 2 17.00 34.00
9999 Adhesive, and sundries L.S. 2.73 1.00 2.73
Labour:
9999 Carriage and fixing charges L.S. 10.79 1.00 10.79
TOTAL 119.52
Add 1% for water charges 1.20
TOTAL 120.72
Add for contractor’s profit and overheads
@15% 18.11
Cost of 1 coupler 138.82
Say 138.82
12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.3 Single tee with door
12.42.3.1 75x75x75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 tee
Materials :-
7198 75x75x75 mm single equal tee (with door)
including cost of bolts and nuts each 1 100.00 100.00
7190 Seal rings metre 3 14.00 42.00
9999 Adhesive, Carriage of material rubber
washer L.S. 10.76 1.00 10.76
TOTAL 152.76
Add 1% for water charges 1.53
TOTAL 154.29
Add for contractor’s profit and overheads
@15% 23.14
Cost of 1 coupler 177.43
Say 177.43

12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.3 Single tee with door
12.42.3.2 110x110x110 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 tee
Materials :-
7199 110x110x110 mm single equal tee (with
door) including cost of bolts and nuts each 1 160.00 160.00
7191 Seal rings metre 3 17.00 51.00
9999 Adhesive, Carriage of material rubber
washer L.S. 13.47 1.00 13.47
TOTAL 224.47
Add 1% for water charges 2.24
TOTAL 226.71
Add for contractor’s profit and overheads
@15% 34.01
Cost of 1 coupler 260.72
Say 260.72
12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.4 Single tee with door
12.42.4.1 75x75x75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 tee
Materials :-
7196 75x75x75 mm single equal tee (with door)
including cost of bolts and nuts each 1 83.00 83.00
7190 Seal rings metre 3 14.00 42.00
9999 Adhesive, Carriage of material rubber
washer L.S. 10.76 1.00 10.76
TOTAL 135.76
Add 1% for water charges 1.36
TOTAL 137.12
Add for contractor’s profit and overheads
@15% 20.57
Cost of 1 tee 157.69
Say 157.69

12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.4 Single tee with door
12.42.4.2 110x110x110 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 tee
Materials :-
7197 110x110x110 mm single equal tee (with
door) including cost of bolts and nuts each 1 115.00 115.00
7191 Seal rings metre 3 17.00 51.00
9999 Adhesive, Carriage of material rubber
washer L.S. 13.47 1.00 13.47
TOTAL 179.47
Add 1% for water charges 1.79
TOTAL 181.26
Add for contractor’s profit and overheads
@15% 27.19
Cost of 1 tee 208.45
Say 208.45
12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.5 Bend 87.5°
12.42.5.1 75 mm bend
Code Description Unit Quantity Rate Amount
Details of cost for 1 bend
7208 Cost of bend each 1 50.00 50.00
7190 Seal rings metre 1 14.00 14.00
9999 Adhesive, and sundries etc. L.S 2.73 1.00 2.73
9999 Carriage and fixing charges L.S 9.36 1.00 9.36
TOTAL 76.09
Add 1% for water charges 0.76
TOTAL 76.85
Add for contractor’s profit and overheads
@15% 11.53
Cost of 1 bend 88.38
Say 88.38

12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.5 Bend 87.5°
12.42.5.2 110 mm bend
Code Description Unit Quantity Rate Amount
Details of cost for 1 bend
7209 Cost of bend each 1 85.00 85.00
7191 Seal rings metre 1 17.00 17.00
9999 Adhesive, and sundries etc. L.S 2.73 1.00 2.73
9999 Carriage and fixing charges L.S 10.79 1.00 10.79
TOTAL 115.52
Add 1% for water charges 1.16
TOTAL 116.68
Add for contractor’s profit and overheads
@15% 17.50
Cost of 1 bend 134.18
Say 134.18

12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.6 Shoe (Plain)
12.42.6.1 75 mm Shoe
Code Description Unit Quantity Rate Amount
Details of cost for 1 shoe
7212 Cost of shoe each 1 105.00 105.00
7190 Seal rings metre 1 14.00 14.00
9999 Adhesive, and sundries etc. L.S 2.73 1.00 2.73
9999 Carriage and fixing charges L.S 9.36 1.00 9.36
TOTAL 131.09
Add 1% for water charges 1.31
TOTAL 132.40
Add for contractor’s profit and overheads
@15% 19.86
Cost of 1 shoe 152.26
Say 152.26

12.42 Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories
for unplasticised R igid PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion.
12.42.6 Shoe (Plain)
12.42.6.2 110 mm Shoe
Code Description Unit Quantity Rate Amount
Details of cost for 1 shoe
7213 Cost of shoe each 1 196.00 196.00
7191 Seal rings metre 1 17.00 17.00
9999 Adhesive, and sundries etc. L.S 2.73 1.00 2.73
9999 Carriage and fixing charges L.S 10.79 1.00 10.79
TOTAL 226.52
Add 1% for water charges 2.27
TOTAL 228.79
Add for contractor’s profit and overheads
@15% 34.32
Cost of 1 shoe 263.10
Say
263.10

12.43 Providing and fixing unplasticised -PVC pipe clips of approved design to
unplasticised - PVC rain water pipes by means of 50x50x50mm hard wood plugs, screwed
with M.S. screws of required length including cutting brick work and fixing in cement
mortar 1:4(1 cement: 4 coarse sand) and making good the wall etc. complete.

12.43.1 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 5 nos.
7214 U-PVC pipe clips each 5 15.00 75.00
870 Hardwood plug 50x50x50 each 10 6.00 60.00
9999 Carriage of U-PVC pipe clips L.S 2.47 1.00 2.47
Labour :-
116 Fitter (Grade- 1) Day 0.125 270 33.75
124 Mason 2nd class Day 0.75 223 167.25
114 Beldar Day 0.5 207 103.50
9999 Sundries L.S 8.06 1.00 8.06
9999 Sundries cement mortar 1:4(1 Cement: 4 L.S 3.9
1.00 3.90
TOTAL 453.93
Add 1% for water charges 4.54
TOTAL 458.47
Add 15% for contractor’s profit and
overheads 68.77
Cost of 5 Nos. 527.24
Cost of 1 No. 105.45
Say 105.45

12.43 Providing and fixing unplasticised -PVC pipe clips of approved design to
unplasticised - PVC rain water pipes by means of 50x50x50mm hard wood plugs, screwed
with M.S. screws of required length including cutting brick work and fixing in cement
mortar 1:4(1 cement: 4 coarse sand) and making good the wall etc. complete.

12.43.2 110 mm
Code Description Unit Quantity Rate Amount
Details of cost for 5 nos.
7215 U-PVC pipe clips each 5 30.00 150.00
870 Hardwood plug 50x50x50 each 10 6.00 60.00
9999 Carriage of U-PVC pipe clips L.S 2.47 1.00 2.47
Labour :-
116 Fitter (Grade- 1) Day 0.125 270 33.75
124 Mason 2nd class Day 0.75 223 167.25
114 Beldar Day 0.5 207 103.50
9999 Sundries L.S 8.06 1.00 8.06
9999 Sundries cement mortar 1:4(1 Cement: 4 L.S 3.9
1.00 3.90
TOTAL 528.93
Add 1% for water charges 5.29
TOTAL 534.22
Add 15% for contractor’s profit and
overheads 80.13
Cost of 5 Nos. 614.35
Cost of 1 No. 122.87
Say 122.87

12.44 Providing and fixing to the inlet mouth of rain water pipe cast iron grating 15 cm
diameter and weighing not less than 440 grams.
Code Description Unit Quantity Rate Amount
Details of cost for 1 grating
Materials :-
7187 150 mm cast iron grating for rain water pipe
each 1 16.00 16.00
9999 Carriage & fixing charges L.S. 4.16 1.00 4.16
TOTAL 20.16
Add 1% for water charges 0.20
TOTAL 20.36
Add for contractor’s profit and overheads
@15% 3.05
Cost of each grating 23.42
Say 23.42

12.45 Providing and fixing at all height false ceiling including providing and fixing of frame
work made of special sections power pressed from M.S. sheet and galvanised in
accordance with zinc coating of grade 350 as per IS : 277 and consisting of angle cleats of
size 25mm wide x 1.6mm thick with flanges of 22mm and 37mm at 1200mm centre to centre
one flange fixed to the ceiling with dash fastener 12.5mm diax40mm long with 6mm dia
bolts to the angle hangers of 25x25x0.55mm of required length, and other end of angle
hanger being fixed with nut and bolts to G.I. channels 45x15x0.9mm running at the rate of
1200mm centre to centre to which the ceiling section 0.5mm thick bottom wedge of 80mm
with tapered flanges of 26mm each having clips of 10.5mm at 450mm centre to centre shall
be fixed in a direction perpendicular to G.I. channel with connecting clips made out of
2.64mm diax230mm long G.I. wire at every junction including fixing the gypsum board with
ceiling section and perimeter channels 0.5mm thick 27mm high having flanges of 20mm
and 30mm long, the perimeter of ceiling fixed to wall/partition with the help of rawl plugs at
450mm centre to centre with 25mm long drive-all screws @ 230mm interval including
jointing and fixing to a flush finish of tapered and square edges of the board with
recommended filler, jointing tapes, finisher and two coats of primer suitable for board
as per manufactures specification and also including the cost of making openings for light
fittings, grills, diffusers, cutouts made with frame of perimeter channels suitably fixed all
complete as per drawing and specification and direction of the Engineer in Charge but
excluding the cost of painting with :

12.45.1 12.5 mm thick tapered edge gypsum board conforming to IS: 2095- Part I,
Code Description Unit Quantity Rate Amount
Details of cost for 10.8x9.6m = 103.68sqm.
Materials
Materials:

7009 Gypsum board 12.5mm thick sqm 108.86 140.00 15240.40


7010 Ceiling sections metre 238.14 36.00 8573.04
7011 Perimetre channel metre 41.14 23.00 946.22
7012 Intermediate channel metre 90.72 38.00 3447.36
7013 Strap hanger (Ceiling angle) metre 10.8 16.00 172.80
7014 Connecting clips each 189 5.00 945.00
7015 Connecting clips each 72 3.00 216.00
7016 Joint filler kilogr 22.81
am 19.00 433.39
7017 Joint finisher kilogr 34.21
am 22.00 752.62
7018 Joint tape roll 1.27 120.00 152.40
7019 Dash fastner 12 mm dia 40 mm long with each 72
6mm dia bolt 8.00 576.00
7020 Drive all screws 25 mm long 100 1000
Nos. 40.00 400.00
7021 Primer for two coats litre 18.66 76.00 1418.16
9999 Sundries like rawl plug scaffolding etc L.S. 807.3 1.00 807.30
9999 Carriage of material etc. L.S. 447.2 1.00 447.20
Labour:
131 Painter Day 10.368 180 1866.24
112 Carpenter 2nd class Day 31.104 223 6936.19
114 Beldar Day 31.104 207 6438.53
TOTAL 49768.85
Add 1% for water charges 497.69
TOTAL 50266.54
Add 15% for contractor’s profit and
overheads 7539.98
Cost of 103.68 Sqm. 57806.52
Cost of 1 sqm 557.55
Say 557.55

12.46 Providing and fixing to the inlet mouth of rain water pipe PTMT (an Engineering
Thermoplastic) grating sqare (Slit) 150 mm sqare with a height of 8 mm and weighing not
less than 100 gms
Discription Unit Quantity Rate A mount
Code
Details of cost for 1 grating
Materials
7857 P.T.M.T. Grating square slit 150mm each 1 70.00 70.00
9999 Carriage of material and fixing charges L.S 4.16 1.00 4.16
TOTAL 74.16
Add 1% for water charges 0.74
TOTAL 74.90
Add 15% for contractor’s profit and
overheads 11.24
Cost of each grating 86.14
Say 86.14
12.47 Providing & fixing UV stabilised fiberglass reinforced plastic sheet roofing upto any
pitch including fixing with polymer coated ‘J’ or ‘L’ hooks, bolts & nuts 8mm dia. G.I
plain/bitumen washers complete but excluding the cost of purlins, rafters, trusses etc. The
sheets shall be manufactured out of 2400 TEX panel rovigs incorporating minimum 0.3%
Ultra-voilet stabiliser in resin system under approximately 2400 psi and hot cured. They
shall be of uniform pigmentation and thickness without air pockets and shall confoim to IS
10192 and IS 12866.The sheets shall be opaque or translucent, clear or pigmented, textured
or smooth as specified.
12.47.1 2mm thick corrugated (2.5" or 4.2" or 6") or step-down (2"or 3"or 6") as
specified.
Code Discription Unit Quantity Rate A mount
Details of cost for area of roof. 2x18.09x5.1 = 184.518 sqm.
Materials:

8668 UV stabilised 2 mm thick corrugated sqm 240.408


FRP 474.00 113953.39
9999 Carriage of sheet L.S. 104 1.00 104.00
1022 G.I.Seam bolts and nuts 60cm 10 884
Nos 60.00 5304.00
1023 G.I., J or L hooks 10 810
Nos 60.00 4860.00
1207 Limpet washers (total of seam and J bolts) 100 1694
Nos 20.00 338.80
1208 Bitumen washers 100 1694
Nos 18.00 304.92
9999 Carriage of bolts and washers L.S. 26.91 1.00 26.91
9999 Sundries L.S. 53.82 1.00 53.82
Labour:
130 Mistry Day 1.3 270 351.00
112 Carpenter 2nd class Day 15.5 223 3456.50
114 Beldar Day 15.5 207 3208.50
TOTAL 131961.84
Add 1% for water charges 1319.62
TOTAL 133281.46
Add 15% for contractor’s profit and
overheads 19992.22
Cost of 184.518 Sqm. 153273.68
Cost of 1 sqm 830.67
Say 830.67
12.47 Providing & fixing UV stabilised fiberglass reinforced plastic sheet roofing upto any
pitch including fixing with polymer coated ‘J’ or ‘L’ hooks, bolts & nuts 8mm dia. G.I
plain/bitumen washers complete but excluding the cost of purlins, rafters, trusses etc. The
sheets shall be manufactured out of 2400 TEX panel rovigs incorporating minimum 0.3%
Ultra-voilet stabiliser in resin system under approximately 2400 psi and hot cured. They
shall be of uniform pigmentation and thickness without air pockets and shall confoim to IS
10192 and IS 12866.The sheets shall be opaque or translucent, clear or pigmented, textured
or smooth as specified.
12.47.2 2mm thick flat
Code Discription Unit Quantity Rate A mount
Details of cost for area of roof. 2x18.09x5.1 = 184.518 sqm.
Materials:
8667 UV stabilised 2 mm thick plain FRP sheet sqm 240.408
400.00 96163.20
9999 Carriage of sheet L.S. 104 1.00 104.00
1022 G.I.Seam bolts and nuts 60cm 10 884
Nos 60.00 5304.00
1023 G.I., J or L hooks 10 810
Nos 60.00 4860.00
1207 Limpet washers (total of seam and J bolts) 100 1694
Nos 20.00 338.80
1208 Bitumen washers 100 1694
Nos 18.00 304.92
9999 Carriage of bolts and washers L.S. 26.91 1.00 26.91
9999 Sundries L.S. 53.82 1.00 53.82
Labour:
130 Mistry Day 1.3 270 351.00
112 Carpenter 2nd class Day 15.5 223 3456.50
114 Beldar Day 15.5 207 3208.50
TOTAL 114171.65
Add 1% for water charges 1141.72
TOTAL 115313.37
Add 15% for contractor’s profit and
overheads 17297.00
Cost of 184.518 Sqm. 132610.37
Cost of 1 sqm 718.69
Say 718.69

12.48 Providing & fixing on roof pressed clay tile (Mangalor tile of 20 mm nominal
thickness and of approved size and as per approved pattern sfeel frame work complete (steel
frame
Code
workDiscription
to be paid separately) Unit Quantity Rate A mount
Details of cost for area 10 sqm.
Materials:

8670 Manglore tiles 20 mm thick. each 160 9.50 1520.00


2207 Carriage of tiles 1000 160
Nos 85.13 13.62
9999 Sundries L.S. 13 1.00 13.00
Labour:
123 Mason 1st class Day 0.3 270 81.00
114 Beldar Day 1.56 207 322.92
TOTAL 1950.54
Add 1% for water charges 19.51
TOTAL 1970.05
Add 15% for contractor’s profit and
overheads 295.51
Cost of 10 Sqm. 2265.55
Cost of 1 sqm 226.56
Say 226.56

12.49 Providing & laying on roof pressed clay tile ridge (Mangalore tile) of 20mm thickness
and of approved pattern on steel frame work complete (sfeel frame work to be paid
separately)Discription Unit Quantity Rate A mount
Code
Details of cost for area 3.6 sqm.
Materials:
8669 Manglore tiles 20 mm thick. each 12 25.00 300.00
2207 Carriage of tiles 1000 12
Nos 85.13 1.02
9999 Sundries L.S. 2.6 1.00 2.60
Labour:
123 Mason 1st class Day 0.01 270 2.70
114 Beldar Day 0.15 207 31.05
TOTAL 337.37
Add 1% for water charges 3.37
TOTAL 340.75
Add 15% for contractor’s profit and
overheads 51.11
Cost of 3.6 Sqm. 391.86
Cost of 1 sqm 108.85
Say 108.85
12.50 Providing and fixing precoatedgalvanized iron profile sheets (size, shape and pitch of
corrugation as 5% total coated thickness (TC T), Zinc coating 120gsm as per IS:277 in
approved by Engineer-in-charge) 0.05 mm. 240 mpa mm steel grade, 5-7 microns epoxy
primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have
protective guard film of 25 microns minimum to avoid scratches while transportation and
should be supplied in single length upto 12 metre or as desired by Engineer-in-charge. The
sheet shall be fixed using self drilling /self tapping screws of size (5.5x 55mm) with EPDM
seal or with polymer coated J or L hooks, bolts and nuts 8mm diameter with bitumen and
G.I. limpet washers or with G.I. limpet washers filled with white lead complete upto any
pitch in horizontal/ vertical or curved surfaces excluding the cost of purlins, rafters and
trusses and including cutting to size and shape wherever required.
Code Discription Unit Quantity Rate A mount
Details of cost for 216.14 sqm.
Materials:
8671 Precoated galvanised iron profile sheet 0.50 sqm 233.65
325.00 75936.25
9999 Carriage of sheet L.S. 104 1.00 104.00
1023 G.I., J or L hooks 10 476
Nos 60.00 2856.00
1209 Bitumen washers thick 100 476
Nos 27.00 128.52
1208 Bitumen washers 100 476
Nos 18.00 85.68
9999 Carriage of bolts and nuts L.S. 8.06 1.00 8.06
9999 Sundries L.S. 39.52 1.00 39.52
Labour:
130 Mistry Day 2.34 270 631.80
112 Carpenter 2nd class Day 9.34 223 2082.82
114 Beldar Day 9.34 207 1933.38
TOTAL 83806.03
Add 1% for water charges 838.06
TOTAL 84644.09
Add 15% for contractor’s profit and
overheads 12696.61
Cost of 216.14 Sqm. 97340.70
Cost of 1 sqm 450.36
Say 450.36

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50mm
+ 5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel
grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18
microns using self drilling/ self tapping screws or with polymer coated J or L hooks, bolts
and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.1 Ridges plain (500 - 600mm).


Code Discription Unit Quantity Rate A mount
Details of cost for 20.20 metre
Materials:
8672 Precoated galvanised steel plain ridges. sqm 23.11
330.00 7626.30
9999 Carriage of sheet L.S. 13.52 1.00 13.52
9999 Sundries L.S. 6.76 1.00 6.76
Labour:
130 Mistry Day 0.14 270 37.80
112 Carpenter 2nd class Day 0.55 223 122.65
114 Beldar Day 1.64 207 339.48
TOTAL 8146.51
Add 1% for water charges 81.47
TOTAL 8227.98
Add 15% for contractor’s profit and
overheads 1234.20
Cost of 20.20 m 9462.17
Cost of 1 m 468.42
Say 468.42

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +
5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade,
5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns
using self drilling/ self tapping screws or with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.2 Flashing/ Aprons (Up to 600 mm)


Code Discription Unit Quantity Rate A mount
Details of cost for 20.20 metre
Materials:
8673 Precoated galvanised steel plain ridges. sqm 23.11
330.00 7626.30
9999 Carriage of sheet L.S. 3.25 1.00 3.25
9999 Sundries L.S. 3.25 1.00 3.25
Labour:
130 Mistry Day 0.07 270 18.90
112 Carpenter 2nd class Day 0.28 223 62.44
114 Beldar Day 0.82 207 169.74
TOTAL 7883.88
Add 1% for water charges 78.84
TOTAL 7962.72
Add 15% for contractor’s profit and
overheads 1194.41
Cost of 20.20 m 9157.13
Cost of 1 m 453.32
Say 453.32
12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +
5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade,
5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns
using self drilling/ self tapping screws or with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.3 North light curves.


Code Discription Unit Quantity Rate A mount
Details of cost for 20.20 metre
Materials:
8675 Precoated galvanised steel north light sqm 23.11
curves. 360.00 8319.60
1023 G.I., J or L hooks 10 40
Nos 60.00 240.00
1209 Bitumen washers thick 100 40
Nos 27.00 10.80
1208 Bitumen washers 100 40
Nos 18.00 7.20
9999 Carriage of hooks, nuts, washers and L.S. 9.88
curves 1.00 9.88
9999 Sundries L.S. 6.24 1.00 6.24
Labour:
130 Mistry Day 0.1 270 27.00
112 Carpenter 2nd class Day 0.3 223 66.90
114 Beldar Day 1 207 207.00
TOTAL 8894.62
Add 1% for water charges 88.95
TOTAL 8983.57
Add 15% for contractor’s profit and
overheads 1347.53
Cost of 20.20 m 10331.10
Cost of 1 m 511.44
Say 511.44

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +
5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade,
5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns
using self drilling/ self tapping screws or with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.4 Barge board (Upto 300 mm).


Code Description Unit Quantity Rate Amount
Details of cost of 8.23 metres
Material
8676 Precoated galvanised steel barge board. metre 8.64 330.00 2851.20
222 Seam bolts and nuts 6 mm dia and 25 mm l 10 Nos 5 30.00 15.00
1211 G.I. plain washers for seam bolts. 00 Nos 10 21.00 2.10
1208 Bitumen washers 00 Nos 5 18.00 0.90
9999 Carriage of barge boards, bolts, nuts and L.S 9.36
washers 1.00 9.36
9999 Sundries L. S. 6.76 1.00 6.76
Labour:
114 Beldar Day 0.4 207 82.80
130 Mistry Day 0.04 270 10.80
112 Carpenter 2nd class Day 0.06 223 13.38
TOTAL 2992.30
Add 1% for water charges 29.92
TOTAL 3022.22
Add 15% for contractor’s profit and
overheads 453.33
Cost of 8.23 metres 3475.56
Cost of 1.00 metre 422.30
Say 422.30

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +
5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade,
5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns
using self drilling/ self tapping screws or with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.5 Crimp curve


Code Description Unit Quantity Rate Amount
Details of crimp curve 20.2 metres long
Material
8677 Precoated galvanised steel crimp curve metre 22.483
420.00 9442.86
1023 G.I. J or L hooks with nuts and bolts 8
mm dia 10 Nos 40 60.00 240.00
1209 G.I plain washer thick 00 Nos 40 27.00 10.80
1208 Bitumen washers 00 Nos 40 18.00 7.20
9999 Carriage of hooks, nuts, washers and L.S 9.88
curves 1.00 9.88
9999 Sundries L. S. 6.24 1.00 6.24
Labour:
114 Beldar Day 1 207 207.00
130 Mistry Day 0.1 270 27.00
112 Carpenter 2nd class Day 0.3 223 66.90
TOTAL 10017.88
Add 1% for water charges 100.18
TOTAL 10118.06
Add 15% for contractor’s profit and 1517.71
overheads
Cost of 21.412 metres 11635.77
Cost of 1.00 metre 543.42
Say 543.42

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +
5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade,
5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns
using self drilling/ self tapping screws or with polymer coated J or L hooks, bolts and nuts
and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.6 Gutter .(600 mm over all girth).


Code Description Unit Quantity Rate Amount
Details of cost 10 metre.
Material
8674 Precoated galvanised steel gutter metre 10 360.00 3600.00
9999 Carriage of gutter L.S 1.04 1.00 1.04
1008 Flats upto 10 mm in thickness quintal 0.0749
4600.00 344.54
1022 Bolts and nuts 10 Nos 20 60.00 120.00
1024
Galvanised steel bolts and nuts 10 mm dia
and 25 mm long round head with slot each 30 12.00 360.00
1208 Bitumen washers 00 Nos 40 18.00 7.20
1210 G.I. plain w ashers thin 00 Nos 70 20.00 14.00
9999 Carriage of G.I. seam bolts and L.S. 2.73 1.00 2.73
9999 Sundries L. S. 2.73 1.00 2.73
Labour:
102 Black smith first class Day 1.34 270 361.80
114 Beldar Day 2.18 207 451.26
130 Mistry Day 0.28 270 75.60
9999 Sundries L.S 12.61 1.00 12.61
112 Carpenter 2nd class Day 0.62 223 138.26
TOTAL 5491.77
Add 1% for water charges 54.92
TOTAL 5546.69
Add 15% for contractor’s profit and 832.00
overheads
Cost of 10.00 metres 6378.69
Cost of 1.00 metre 637.87
Say 637.87
12.52 Providing and fixing tiled False Ceiling of approved materials of size 595x595 mm in
true horizontal level suspended on inter locking metal grid of hot dipped galvanised steel
sections ( galvanized @ 170 gsm/sqm.) consisting of main “T” runner with suitably spaced
joints to get required length and of size 24x38mm made from 0.30mm thick (minimum)
sheet spaced at 1200mm center to center and cross “T” of size 24x25mm made of 0.30mm
thick (minimum) sheet, 1200mm long spaced between main “T” at 600mm center to center
to form a grid of 1200x600 mm and secondary cross “T” of length 600mm and size
24x25mm made of 0.30 mm thick (minimum) sheet to be interlocked at middle of the
1200x600mm panel to form grids of 600x600mm and wall angle of size 21x21x0.30 mm
and laying false ceiling tiles of approved texture in the grid including, wherever, required,
cutting/making, opening for services like diffusers, grills, light fittings, fixtures, smoke
detectors etc. Main “T” runners to be suspended from ceiling using GI slotted cleats fixed to
ceiling with 6mm dia and 50mm long dash fasteners, 4mm GI adjustable rods with
galvanised level clips spaced at 1200mm center to center along main T, bottom exposed
width of 24mm of all T-sections shall be pre-painted with polyester paint, all complete at all
heights as per specifications drawings and as directed by Engineer-in-Charge. (The rate is
excluding the cost of tiles which will be paid for separately ).
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm.
Materials-
GRID
8,611 Main T ceiling sections 24x38x0.3 mm each 29.5 162.00
(3.00 metre long) Including Wastage @
10% 4779.00
8,612 Perimeter wall angle 21x21 x 0.30mm (3 each 13.5 102.00
metre long) Inc luding Wastage @ 10%
1377.00
8,613 Intermediate cross T-section each 147 62.00
24x25x0.30mm (1.2 mtrs long) Inc luding
Wastage @ 10% on Grid for cutouts
9114.00
8,614 Intermediate cross T-section each 147 29.00
24x25x0.30mm (0.6 mtrs long) Inc luding
Wastage @ 10% on Grid for cutouts
4263.00
8,615 Hanger rod 0.5 mm thick each 72 5.00 360.00
8,616 Adjustment clip each 72 4.40 316.80
8,617 Soffit cleat each 72 2.30 165.60
8,618 Dash fastener 6 mm dia 50 m m long each 72 8.00 576.00
9,999 Sundries i.e. scaffolding etc. L.S. 187.95 1.00 187.95
9,999 Carriage of materials etc. L.S. 89.28 1.00 89.28
LABOUR
111 Catpenter 1 st class Day 3 270 810.00
114 Beldar Day 3 207 621.00
TOTAL 22659.63
Add 1 % for water charges 226.60
TOTAL 22886.23
Add 15% for contractor’s profit and
overheads 3432.93
Cost of 100 sqm. 26319.16
Cost of 1 sqm. 263.19
Say 263.19
13.1 12 mm cement plaster of mix:
13.1.1 1:4 (1 cement : 4 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement: 4 fine cum 0.144
sand). (Rate as per item no. 3.4) 2580.18 371.55
LABOUR
155 Mason Day 0.67 180 120.60
115 Coolie Day 0.75 207 155.25
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 825.61
Add 1% for water charges 8.26
TOTAL 833.86
Add 15% for contractor’s profit and
overheads 125.08
Cos t of 10.00 sqm 958.94
Cost of 1.00 sqm 95.89
Say 95.89

13.1 12 mm cement plaster of mix:


13.1.2 1:6 (1 cement : 6 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 6 (1 cement: 6 fine cum 0.144
sand). (Rate as per item no. 3.6) 1898.04 273.32
LABOUR
155 Mason Day 0.67 180 120.60
115 Coolie Day 0.75 207 155.25
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 727.38
Add 1% for water charges 7.27
TOTAL 734.65
Add 15% for contractor’s profit and
overheads 73.47
Cos t of 10.00 sqm 808.12
Cost of 1.00 sqm 80.81
Say 80.81

13. 2 15 m m cement plaster on rough side of single or half brick wall of mix:-
13.2.1 1:4 (1 cement : 4 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement: 4 fine cum 0.172 2580.18 443.79
sand). (Rate as per item no. 3.4)
LABOUR
155 Mason Day 0.8 180 144.00
115 Coolie Day 0.88 207 182.16
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 960.76
Add 1% for water charges 9.61
TOTAL 970.37
Add 15% for contractor’s profit and
overheads 145.56
Cos t of 10.00 sqm 1115.92
Cost of 1.00 sqm 111.59
Say 111.59

13.2 15 mm cement plaster on the rough side of single or half brick wall of mix :
13.2.2 1: 6 (1 cement: 6 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 6 (1 cement: 6 fine cum 0.172 1898.04 326.46
sand). (Rate as per item no. 3.6)
LABOUR
155 Mason Day 0.8 180 144.00
115 Coolie Day 0.88 207 182.16
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 843.43
Add 1% for water charges 8.43
TOTAL 851.87
Add 15% for contractor’s profit and
overheads 127.78
Cos t of 10.00 sqm 979.65
Cost of 1.00 sqm 97.96
Say 97.96

13.3 20 m m cement plaster of mix


13.3.1 1:4 (1 cement : 4 find sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement: 4 fine cum 0.224 2580.18 577.96
sand). (Rate as per item no. 3.4)
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 1.1 180 198.00
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1168.91
Add 1% for water charges 11.69
TOTAL 1180.60
Add 15% for contractor’s profit and
overheads 177.09
Cos t of 10.00 sqm 1357.69
Cost of 1.00 sqm 135.77
Say 135.77

13.3 20 mm cement plaster of mix


13.3.2 1:6 (1 cement : 6 find sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 6 (1 cement: 6 fine cum 0.224 1898.04 425.16
sand). (Rate as per item no. 3.6)
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 1.1 180 198.00
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1016.11
Add 1% for water charges 10.16
TOTAL 1026.27
Add 15% for contractor’s profit and
overheads 153.94
Cos t of 10.00 sqm 1180.21
Cost of 1.00 sqm 118.02
Say 118.02

13.4 12 mm cement plaster of mix


13.4.1 1:4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement: 4 cum 0.144
coarse sand). (Rate as per item no. 3.9)
2580.18 371.55
LABOUR
155 Mason Day 0.67 180 120.60
115 Coolie Day 0.75 207 155.25
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 825.61
Add 1% for water charges 8.26
TOTAL 833.86
Add 15% for contractor’s profit and
overheads 125.08
Cos t of 10.00 sqm 958.94
Cost of 1.00 sqm 95.89
Say 95.89

13.4 12 mm cement plaster of mix


13.4.2 1:6 (1 cement : 6 coarse sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 6 (1 cement: 6 cum 0.144
coarse sand). (Rate as per item no. 3.11)
1898.04 273.32
LABOUR
155 Mason Day 0.67 180 120.60
115 Coolie Day 0.75 207 155.25
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 727.38
Add 1% for water charges 7.27
TOTAL 734.65
Add 15% for contractor’s profit and
overheads 110.20
Cos t of 10.00 sqm 844.85
Cost of 1.00 sqm 84.48
Say 84.48

13.5 15 mm cement plaster on rough side of single or half brick wall of mix :
13.5.1 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement: 4 cum 0.172
coarse sand). (Rate as per item no. 3.9)
2580.18 443.79
LABOUR
155 Mason Day 0.8 180 144.00
115 Coolie Day 0.88 207 182.16
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 960.76
Add 1% for water charges 9.61
TOTAL 970.37
Add 15% for contractor’s profit and
overheads 145.56
Cos t of 10.00 sqm 1115.92
Cost of 1.00 sqm 111.59
Say 111.59

13.5 15 mm cement plaster on rough side of single or half brick wall of mix
13.5.2 1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 6 (1 cement: 6 cum 0.172
coarse sand). (Rate as per item no. 3.11)
1898.04 326.46
LABOUR
155 Mason Day 0.8 180 144.00
115 Coolie Day 0.88 207 182.16
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 843.43
Add 1% for water charges 8.43
TOTAL 851.87
Add 15% for contractor’s profit and
overheads 127.78
Cos t of 10.00 sqm 979.65
Cost of 1.00 sqm 97.96
Say 97.96

13.6 20 mm cement plaster of mix : -


13.6.1 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement: 4 cum 0.224
coarse sand). (Rate as per item no. 3.9)
2580.18 577.96
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 1.1 180 198.00
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1168.91
Add 1% for water charges 11.69
TOTAL 1180.60
Add 15% for contractor’s profit and
overheads 177.09
Cos t of 10.00 sqm 1357.69
Cost of 1.00 sqm 135.77
Say 135.77

13.6 20 mm cement plaster of mix :


13.6.2 1:6 (1 cement: 6 coarse sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 6 (1 cement: 6 cum 0.224
coarse sand). (Rate as per item no. 3.11) 1898.04 425.16
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 1.1 180 198.00
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1016.11
Add 1% for water charges 10.16
TOTAL 1026.27
Add 15% for contractor’s profit and
overheads 153.94
Cos t of 10.00 sqm 1180.21
Cost of 1.00 sqm 118.02
Say 118.02

13.7 12 mm cement plaster finished with a floating coat of neat cement of m ix :


13.7.1 1:3 ( 1 cement : 3 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.144
sand). (Rate as per item no. 3.3) 3268.90 470.72
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 20.67 1.00 20.67
TOTAL 1142.28
Add 1% for water charges 11.42
TOTAL 1153.70
Add 15% for contractor’s profit and
overheads 173.06
Cos t of 10.00 sqm 1326.76
Cost of 1.00 sqm 132.68
Say 132.68

13.7 12 mm cement plaster finished with a floating coat of neat cement of mix
13.7.2 1:4 (1 cement: 4 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.144
sand). (Rate as per item no. 3.4) 2580.18 371.55
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 20.67 1.00 20.67
TOTAL 1043.10
Add 1% for water charges 10.43
TOTAL 1053.53
Add 15% for contractor’s profit and
overheads 158.03
Cos t of 10.00 sqm 1211.56
Cost of 1.00 sqm 121.16
Say 121.16

13.8 15 mm cement plaster on rough side of single or half brick wall finished with a
floating coat of neat cement of mix :
13.8.1 1:3 (1 cem ent: 3 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.172
sand). (Rate as per item no. 3.3) 3268.90 562.25
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
LABOUR
155 Mason Day 1.07 180 192.60
115 Coolie Day 1.15 207 238.05
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 20.67 1.00 20.67
TOTAL 1296.72
Add 1% for water charges 12.97
TOTAL 1309.68
Add 15% for contractor’s profit and
overheads 196.45
Cos t of 10.00 sqm 1506.14
Cost of 1.00 sqm 150.61
Say 150.61

13.8 15 mm cement plaster on rough side of single or half brick wall finished with a
floating coat of neat cement of mix :
13.8.2 1:4 (1 cement: 4 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.172
sand). (Rate as per item no. 3.4) 2580.18 443.79
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
LABOUR
155 Mason Day 1.07 180 192.60
115 Coolie Day 1.15 207 238.05
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 20.67 1.00 20.67
TOTAL 1178.26
Add 1% for water charges 11.78
TOTAL 1190.04
Add 15% for contractor’s profit and
overheads 178.51
Cos t of 10.00 sqm 1368.55
Cost of 1.00 sqm 136.85
Say 136.85

13.9 Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat
cement.
13.9.1 12mm cement plaster.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 coarse cum 0.144
sand). (Rate as per item no. 3.8)
3262.33 469.78
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 20.67 1.00 20.67
TOTAL 1141.33
Add 1% for water charges 11.41
TOTAL 1152.74
Add 15% for contractor’s profit and
overheads 172.91
Cos t of 10.00 sqm 1325.66
Cost of 1.00 sqm 132.57
Say 132.57

13.9 Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat of neat
cement.
13.9.2 20 mm cement plaster.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 coarse cum 0.224
sand). (Rate as per item no. 3.8)
3262.33 730.76
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
LABOUR
155 Mason Day 1.21 180 217.80
115 Coolie Day 1.3 207 269.10
101 Bhisti Day 1.1 180 198.00
9999 Scaffolding and sundries L.S 20.67 1.00 20.67
TOTAL 1541.28
Add 1% for water charges 15.41
TOTAL 1556.69
Add 15% for contractor’s profit and
overheads 233.50
Cos t of 10.00 sqm 1790.19
Cost of 1.00 sqm 179.02
Say 179.02

13.10 15 mm cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat
of neat cement on the roughside of single or half brick wall.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 coarse cum 0.172
sand). (Rate as per item no. 3.8)
3262.33 561.12
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
LABOUR
155 Mason Day 1.07 180 192.60
115 Coolie Day 1.15 207 238.05
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 20.67 1.00 20.67
TOTAL 1295.59
Add 1% for water charges 12.96
TOTAL 1308.54
Add 15% for contractor’s profit and
overheads 196.28
Cos t of 10.00 sqm 1504.82
Cost of 1.00 sqm 150.48
Say 150.48

13.11 18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5 (1
cement : 5 coarse sand) finished with a top layer 6mm th ick cement plaster 1:6 (1
cement: 6 fine sand ).
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Under layer Cement mortar 1:5(1 cum 0.144
cement: 5 coarse sand) (Rate as per item 2212.87 318.65
no. 3.10)
Cem ent mortar 1 : 6 (1 cement:6 fine cum 0.072
sand). (Rate as per item no. 3.6) 1898.04 136.66
LABOUR
155 Mason Day 1.21 180 217.80
115 Coolie Day 1.29 207 267.03
101 Bhisti Day 1.05 180 189.00
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1141.75
Add 1% for water charges 11.42
TOTAL 1153.17
Add 15% for contractor’s profit and
overheads 172.98
Cos t of 10.00 sqm 1326.15
Cost of 1.00 sqm 132.61
Say 132.61

13.12 18 mm cemen t plaster in two coats un der layer 12 m m thick cement plaster 1:5
(1 cement: 5 coarse sand) and a top layer 6m m thick cement plaster 1:3(1 cement:3
coarse sand) finished rou gh with sponge
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Under layer Cement mortar 1:5(1 cum 0.144
cement: 5 coarse sand) (Rate as per item
no. 3.10) 2212.87 318.65
Cem ent mortar 1 : 6 (1 cement:6 coarse cum 0.072
sand). (Rate as per item no. 3.8)
3262.33 234.89
LABOUR
155 Mason Day 1.21 180 217.80
115 Coolie Day 1.29 207 267.03
101 Bhisti Day 1.05 180 189.00
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1239.98
Add 1% for water charges 12.40
TOTAL 1252.38
Add 15% for contractor’s profit and
overheads 187.86
Cos t of 10.00 sqm 1440.24
Cost of 1.00 sqm 144.02
Say 144.02

13.13 12 mm cement plaster 1 : 2 ( 1 cement : 2 stone dust)


Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Under layer Cement mortar 1:2(1 cum 0.144
cement: 5 stone dust) (Rate as per item
no. 3.12) 4438.17 639.10
LABOUR
155 Mason Day 0.67 180 120.60
115 Coolie Day 0.75 207 155.25
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1093.16
Add 1% for water charges 10.93
TOTAL 1104.09
Add 15% for contractor’s profit and
overheads 165.61
Cos t of 10.00 sqm 1269.70
Cost of 1.00 sqm 126.97
Say 126.97

13.14 15 mm cement plaster 1 : 2 ( 1 cement : 2 stone dust) on the rough side of single
or half brick wall
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Under layer Cement mortar 1:2(1 cum 0.172
cement: 5 stone dust) (Rate as per item
no. 3.12) 4438.17 763.37
LABOUR
155 Mason Day 0.8 180 144.00
115 Coolie Day 0.88 207 182.16
101 Bhisti Day 0.99 180 178.20
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1280.34
Add 1% for water charges 12.80
TOTAL 1293.14
Add 15% for contractor’s profit and
overheads 193.97
Cos t of 10.00 sqm 1487.11
Cost of 1.00 sqm 148.71
Say 148.71

13.15 20 m m cement plaster 1 : 2 ( 1 cement : 2 stone dust)


Detail of cost for 10 sqm
MATERIALS
Under layer Cement mortar 1:2(1 cum 0.224
cement: 5 stone dust) (Rate as per item
no. 3.12) 4438.17 994.15
LABOUR
155 Mason Day 0.94 180 169.20
115 Coolie Day 1.02 207 211.14
101 Bhisti Day 1.1 180 198.00
9999 Scaffolding and sundries L.S 12.61 1.00 12.61
TOTAL 1585.10
Add 1% for water charges 15.85
TOTAL 1600.95
Add 15% for contractor’s profit and
overheads 240.14
Cos t of 10.00 sqm 1841.09
Cost of 1.00 sqm 184.11
Say 184.11

13.16 6 mm cement plaster of mix:


13.16.1 1:3 ( 1 cement : 3 fine sand)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.072
sand). (Rate as per item no. 3.3) 3268.90 235.36
LABOUR
155 Mason Day 0.51 180 91.80
115 Coolie Day 0.75 207 155.25
101 Bhisti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S 25.09 1.00 25.09
TOTAL 673.10
Add 1% for water charges 6.73
TOTAL 679.83
Add 15% for contractor’s profit and
overheads 101.97
Cos t of 10.00 sqm 781.81
Cost of 1.00 sqm 78.18
Say 78.18

13.17 6 mm cement plaster 1:3 (1 cement : 3 fine sand) Finished with a flooting coat of
neat cement and thick coat of lime wash on top of walls when dry for bearing of R.C.C
slabs and beams.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.072
sand). (Rate as per item no. 3.3) 3268.90 235.36
367 Cement tonne 0.02 5200.00 104.00
2209 Carriage of cement tonne 0.02 47.29 0.95
776 Satna lime quintal 0.01 400.00 4.00
LABOUR
155 Mason Day 0.78 180 140.40
115 Coolie Day 1.09 207 225.63
101 Bhisti Day 0.92 180 165.60
141 White washer Day 0.07 180 12.60
9999 Scaffolding and sundries L.S 38.48 1.00 38.48
TOTAL 927.02
Add 1% for water charges 9.27
TOTAL 936.29
Add 15% for contractor’s profit and
overheads 140.44
Cos t of 10.00 sqm 1076.73
Cost of 1.00 sqm 107.67
Say 107.67
F
13.18 Neat cement punning
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
367 Cement tonne 0.022 5200.00 114.40
2209 Carriage of cement tonne 0.022 47.29 1.04
LABOUR
155 Mason Day 0.27 180 48.60
115 Coolie Day 0.27 207 55.89
9999 Scaffolding and sundries L.S 8.06 1.00 8.06
TOTAL 227.99
Add 1% for water charges 2.28
TOTAL 230.27
Add 15% for contractor’s profit and
overheads 34.54
Cos t of 10.00 sqm 264.81
Cost of 1.00 sqm 26.48
Say 26.48

13.19 Rough cast plaster upto 10m height above ground level with a mixture of sand and
gravel or crushed stone from 6mm to 10mm nominal size dashed over and including the
fresh plaster in two layers, under layer 12mm cement plaster 1:4 (1 cement: 4 coarse
sand) and top layer 10mm cement plaster 1:3 (1 cement : 3 fine sand) mixed with 10%
finely grounded hydrated lime by volume of cement.

13.19.1 Ordinary cement finish using ordinary cement


Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Under layer Cement mortar 1:4(1 cum 0.144
cement: 4 coarse sand) (Rate as per item
no. 3.9) 2580.18 371.55
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.12
sand). (Rate as per item no. 3.3) 3268.90 392.27
1179 Sand and gravel or crushed stone 2.36 cum 0.1
m m to 12.5mm size 675.00 67.50
777 Grounded hydrated lime (factory made) quintal 0.09 200.00 18.00

9999 Carriage of lime L.S 3.64 1.00 3.64


LABOUR
155 Mason Day 1.78 180 320.40
123 Mason I class Day 0.25 270 67.50
115 Coolie Day 2.19 207 453.33
101 Bhisti Day 1.88 180 338.40
9999 Scaffolding and sundries L.S 29.64 1.00 29.64
TOTAL 2062.22
Add 1% for water charges 20.62
TOTAL 2082.85
Add 15% for contractor’s profit and
overheads 312.43
Cos t of 10.00 sqm 2395.27
Cost of 1.00 sqm 239.53
Say 239.53

13.20 Pebble dash plaster upto 10m height above ground level with a mixture of washed
pebble or crushed stone 6mm to 12.5 mm nominal size dashed over and including the
fresh plaster in two layers, under layer 12mm cement plaster 1:4 (1 cement: 4 coarse
sand) and top layer 10mm cement plaster 1:3 (1 cement : 3 fine sand) mixed with 10%
finely grounded hydrated lime by volume of cement.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Under layer Cement mortar 1:4(1 cum 0.144
cement: 4 coarse sand) (Rate as per item
no. 3.9) 2580.18 371.55
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.12
sand). (Rate as per item no. 3.3) 3268.90 392.27
1179 Sand and gravel or crushed stone 2.36 cum 0.1
m m to 12.5mm size 675.00 67.50
777 Grounded hydrated lime (factory made) quintal 0.09 200.00 18.00

9999 Carriage of lime L.S 3.64 1.00 3.64


LABOUR
155 Mason Day 1.78 180 320.40
115 Coolie Day 1.94 207 401.58
101 Bhisti Day 1.88 180 338.40
9999 Scaffolding and sundries L.S 34.06 1.00 34.06
TOTAL 1947.39
Add 1% for water charges 19.47
TOTAL 1966.87
Add 15% for contractor’s profit and
overheads 295.03
Cos t of 10.00 sqm 2261.90
Cost of 1.00 sqm 226.19
Say 226.19

13.21 Extra for providing and mixing water proofing material in cement plaster work in
proportion recommended by the manufacturers.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm of 12 mm cem ent plaster 1:3= 1.48 bags of cement
1213 Water proofing materials kilogra 1.48
m 20.00 29.60
9999 Sundries L.S 7.15 1.00 7.15
TOTAL 36.75
Add 1% for water charges 0.37
TOTAL 37.12
Add 15% for contractor’s profit and
overheads 5.57
Cos t of 1.48 bags of cement 42.69
Cos t of 1 bag of cement 28.84
Say 28.84

13.22 Extra for plastering exterior walls of height more than 10 m from ground level for
every additional height of 3 m or part thereof.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
9999 Carriage of lime L.S 53.82 1.00 53.82
LABOUR
155 Mason Day 0.2 180 36.00
115 Coolie Day 0.3 207 62.10
101 Bhisti Day 0.1 180 18.00
9999 Sundries L.S 7.15 1.00 7.15
TOTAL 177.07
Add 1% for water charges 1.77
TOTAL 178.84
Add 15% for contractor’s profit and
overheads 26.83
Cos t of 10.00 sqm 205.67
Cost of 1.00 sqm 20.57
Say 20.57

13.23 Extra for plastering on circular work not exceeding 6 m in radius:


13.23.1 In one coat
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 0.2 180 36.00
114 Beldar Day 0.2 207 41.40
9999 Sundries L.S 7.15 1.00 7.15
TOTAL 84.55
Add 1% for water charges 0.85
TOTAL 85.40
Add 15% for contractor’s profit and
overheads 12.81
Cos t of 10.00 sqm 98.20
Cost of 1.00 sqm 9.82
Say 9.82

13.23 Extra for plastering on circular work not exceeding 6 m in radius:


13.23.2 In two coat
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 0.3 180 54.00
114 Beldar Day 0.3 207 62.10
9999 Sundries L.S 13.39 1.00 13.39
TOTAL 129.49
Add 1% for water charges 1.29
TOTAL 130.78
Add 15% for contractor’s profit and
overheads 19.62
Cos t of 10.00 sqm 150.40
Cost of 1.00 sqm 15.04
Say 15.04

13.24 Extra for plastering done on moulding cornices or architraves including neat finish
to line and level:
13.24.1 In one coat
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 3 180 540.00
114 Beldar Day 2 207 414.00
115 Cooile Day 1 207 207.00
101 Bhisti Day 0.25 180 45.00
9999 Sundries L.S 13.39 1.00 13.39
TOTAL 1219.39
Add 1% for water charges 12.19
TOTAL 1231.58
Add 15% for contractor’s profit and
overheads 184.74
Cos t of 10.00 sqm 1416.32
Cost of 1.00 sqm 141.63
Say 141.63

13.24 Extra for plastering done on moulding cornices or architraves including neat finish
to line and level:
13.24.2 In two coats
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 5 180 900.00
114 Beldar Day 3 207 621.00
115 Cooile Day 2 207 414.00
101 Bhisti Day 0.33 180 59.40
9999 Sundries L.S 13.39 1.00 13.39
TOTAL 2007.79
Add 1% for water charges 20.08
TOTAL 2027.87
Add 15% for contractor’s profit and
overheads 304.18
Cos t of 10.00 sqm 2332.05
Cost of 1.00 sqm 233.20
Say 233.20
13.25 Extra for plastering
13.25.1 Spherical ceiling
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 0.75 180 135.00
114 Beldar Day 0.74 207 153.18
9999 Sundries L.S 26.91 1.00 26.91
TOTAL 315.09
Add 1% for water charges 3.15
TOTAL 318.24
Add 15% for contractor’s profit and
overheads 47.74
Cos t of 10.00 sqm 365.98
Cost of 1.00 sqm 36.60
Say 36.60

13.25 Extra for plastering


13.25.2 Groined ceiling
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 0.8 180 144.00
114 Beldar Day 0.8 207 165.60
9999 Sundries L.S 34.06 1.00 34.06
TOTAL 343.66
Add 1% for water charges 3.44
TOTAL 347.10
Add 15% for contractor’s profit and
overheads 52.06
Cos t of 10.00 sqm 399.16
Cost of 1.00 sqm 39.92
Say 39.92

13.25 Extra for plastering


13.25.3 Flewing ceiling
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 0.5 180 90.00
114 Beldar Day 0.5 207 103.50
9999 Sundries L.S 13.39 1.00 13.39
TOTAL 206.89
Add 1% for water charges 2.07
TOTAL 208.96
Add 15% for contractor’s profit and
overheads 31.34
Cos t of 10.00 sqm 240.30
Cost of 1.00 sqm 24.03
Say 24.03

13.26 Providing and applying plaster of paris putty of 2 mm thickness over plastered
surface to prepare the surface even and smooth complete
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
869 Plaster of Paris kg 23 3.00 69.00
9999 Carriage of lime L.S 3.9 1.00 3.90
LABOUR
122 Special Mason Day 0.91 313 284.83
114 Beldar Day 0.91 207 188.37
9999 Sundries L.S 83.98 1.00 83.98
TOTAL 630.08
Add 1% for water charges 6.30
TOTAL 636.38
Add 15% for contractor’s profit and
overheads 95.46
Cos t of 10.00 sqm 731.84
Cost of 1.00 sqm 73.18
Say 73.18

13.27 Extra for lining out plaster to imitate stone or concrete blocks walling
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
155 Mason Day 0.5 180 90.00
114 Beldar Day 0.5 207 103.50
9999 Sundries L.S 1.82 1.00 1.82
TOTAL 195.32
Add 1% for water charges 1.95
TOTAL 197.27
Add 15% for contractor’s profit and
overheads 29.59
Cos t of 10.00 sqm 226.86
Cost of 1.00 sqm 22.69
Say 22.69

13.28 12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.28.1 Flush Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.014
sand). (Rate as per item no. 3.4) 2580.18 36.12
LABOUR
155 Mason Day 0.27 180 48.60
115 Coolie Day 0.27 207 55.89
101 Bhisti Day 0.05 180 9.00
9999 Scaffolding and sundries L.S 1.43 1.00 1.43
TOTAL 151.04
Add 1% for water charges 1.51
TOTAL 152.55
Add 15% for contractor’s profit and
overheads 22.88
cost for 10 m etre long and 10 cm wide
band 175.44
cost for 1 metre long and 1 cm wide
band 1.75
Say 1.75

13.28 12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.28.2 Sunk Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.014
sand). (Rate as per item no. 3.4) 2580.18 36.12
LABOUR
155 Mason Day 0.3 180 54.00
115 Coolie Day 0.3 207 62.10
101 Bhisti Day 0.05 180 9.00
9999 Scaffolding and sundries L.S 2.08 1.00 2.08
TOTAL 163.30
Add 1% for water charges 1.63
TOTAL 164.94
Add 15% for contractor’s profit and
overheads 24.74
cost for 10 m etre long and 10 cm wide
band 189.68
cost for 1 metre long and 1 cm wide
band 1.90
Say 1.90

13.28 12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.28.3 Raised Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.014
sand). (Rate as per item no. 3.4) 2580.18 36.12
LABOUR
155 Mason Day 0.35 180 63.00
115 Coolie Day 0.35 207 72.45
101 Bhisti Day 0.05 180 9.00
9999 Scaffolding and sundries L.S 2.73 1.00 2.73
TOTAL 183.30
Add 1% for water charges 1.83
TOTAL 185.14
Add 15% for contractor’s profit and
overheads 27.77
cost for 10 m etre long and 10 cm wide
band 212.91
cost for 1 metre long and 1 cm wide
band 2.13
Say 2.13

13.28 12 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.28.4 Moulded Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.014
sand). (Rate as per item no. 3.4) 2580.18 36.12
LABOUR
155 Mason Day 0.65 180 117.00
115 Coolie Day 0.65 207 134.55
101 Bhisti Day 0.05 180 9.00
9999 Scaffolding and sundries L.S 1.56 1.00 1.56
TOTAL 298.23
Add 1% for water charges 2.98
TOTAL 301.21
Add 15% for contractor’s profit and
overheads 45.18
cost for 10 m etre long and 10 cm wide
band 346.40
cost for 1 metre long and 1 cm wide
band 3.46
Say 3.46

13.29 18 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.29.1 Flush Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.02
sand). (Rate as per item no. 3.4) 2580.18 51.60
LABOUR

155 Mason Day 0.32 180 57.60


115 Coolie Day 0.32 207 66.24
101 Bhisti Day 0.06 180 10.80
9999 Scaffolding and sundries L.S 2.08 1.00 2.08
TOTAL 188.32
Add 1% for water charges 1.88
TOTAL 190.21
Add 15% for contractor’s profit and
overheads 28.53
cost for 10 m etre long and 10 cm wide
band 218.74
cost for 1 metre long and 1 cm wide
band 2.19
Say 2.19

13.29 18 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.29.2 Sunk Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.02
sand). (Rate as per item no. 3.4) 2580.18 51.60
LABOUR
155 Mason Day 0.36 180 64.80
115 Coolie Day 0.36 207 74.52
101 Bhisti Day 0.06 180 10.80
9999 Scaffolding and sundries L.S 2.73 1.00 2.73
TOTAL 204.45
Add 1% for water charges 2.04
TOTAL 206.50
Add 15% for contractor’s profit and
overheads 30.97
cost for 10 m etre long and 10 cm wide
band 237.47
cost for 1 metre long and 1 cm wide
band 2.37
Say 2.37

13.29 18 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.29.3 Raised Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.02
sand). (Rate as per item no. 3.4) 2580.18 51.60
LABOUR
155 Mason Day 0.42 180 75.60
115 Coolie Day 0.42 207 86.94
101 Bhisti Day 0.06 180 10.80
9999 Scaffolding and sundries L.S 4.42 1.00 4.42
TOTAL 229.36
Add 1% for water charges 2.29
TOTAL 231.66
Add 15% for contractor’s profit and
overheads 34.75
cost for 10 m etre long and 10 cm wide
band 266.41
cost for 1 metre long and 1 cm wide
band 2.66
Say 2.66

13.29 18 mm thick plain cement mortar bands in cement mortar 1:4 (1 cement: 4 fine
sand):
13.29.4 Moulded Band
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.024
sand). (Rate as per item no. 3.4) 2580.18 61.92
LABOUR

155 Mason Day 0.86 180 154.80


115 Coolie Day 0.86 207 178.02
101 Bhisti Day 0.05 180 9.00
9999 Scaffolding and sundries L.S 2.73 1.00 2.73
TOTAL 406.47
Add 1% for water charges 4.06
TOTAL 410.54
Add 15% for contractor’s profit and
overheads 61.58
cost for 10 m etre long and 10 cm wide
band 472.12
cost for 1 metre long and 1 cm wide
band 4.72
Say 4.72
13.30 18 mm thick moulded cement mortar band in two coats under layer 12mm thick
with cement mortar 1:5 (1cement: 5 coarse sand) top layer 6mm thick with cement
mortar 1:4 (1 cement: 4 fine sand). .
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m etre long and 10 cm wide band
MATERIALS
Under layer Cement mortar 1:5(1 cum 0.014
cement: 5 coarse sand) (Rate as per item
no. 3.10) 2212.87 30.98
Cem ent mortar 1 : 4 (1 cement:4 fine cum 0.01
sand). (Rate as per item no. 3.4) 2580.18 25.80
LABOUR
155 Mason Day 0.86 180 154.80
115 Coolie Day 0.86 207 178.02
101 Bhisti Day 0.05 180 9.00
9999 Scaffolding and sundries L.S 2.73 1.00 2.73
TOTAL 401.33
Add 1% for water charges 4.01
TOTAL 405.35
Add 15% for contractor’s profit and
overheads 60.80
cost for 10 m etre long and 10 cm wide
band 466.15
cost for 1 metre long and 1 cm wide
band 4.66
Say 4.66

13.31 Pointing on brick work or brick flooring with cement mortar 1:3 (1 cem ent: 3 fine
sand):
13.31.1 Flush / Ruled/ Struck or weathered pointing.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.03
sand). (Rate as per item no. 3.3) 3268.90 98.07
LABOUR
155 Mason Day 0.5 180 90.00
115 Coolie Day 0.6 207 124.20
101 Bhisti Day 0.93 180 167.40
9999 Scaffolding and sundries L.S 21.45 1.00 21.45
TOTAL 501.12
Add 1% for water charges 5.01
TOTAL 506.13
Add 15% for contractor’s profit and
overheads 75.92
Cos t of 10.00 sqm 582.05
Cost of 1.00 sqm 58.20
Say 58.20

13.31 Pointing on brick work or brick flooring with cement mortar 1:3 (1 cem ent: 3 fine
sand):
13.31.2 Raised and cut pointing.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.046
sand). (Rate as per item no. 3.3) 3268.90 150.37
LABOUR
155 Mason Day 1.07 180 192.60
115 Coolie Day 1.31 207 271.17
101 Bhisti Day 1 180 180.00
9999 Scaffolding and sundries L.S 23.27 1.00 23.27
TOTAL 817.41
Add 1% for water charges 8.17
TOTAL 825.58
Add 15% for contractor’s profit and
overheads 123.84
Cos t of 10.00 sqm 949.42
Cost of 1.00 sqm 94.94
Say 94.94

13.32 Pointing on tile brick work with cement mortar 1:3 (1 cement :3 fine sand):
13.32.1 Flush/Ruled/Struck or weathered pointing
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.046
sand). (Rate as per item no. 3.3) 3268.90 150.37
LABOUR
155 Mason Day 0.67 180 120.60
115 Coolie Day 0.8 207 165.60
101 Bhisti Day 1.28 180 230.40
9999 Scaffolding and sundries L.S 23.27 1.00 23.27
TOTAL 690.24
Add 1% for water charges 6.90
TOTAL 697.14
Add 15% for contractor’s profit and
overheads 104.57
Cos t of 10.00 sqm 801.71
Cost of 1.00 sqm 80.17
Say 80.17

13.33 Pointing on stone work with cem ent mortar 1:3 (1 cement :3 fine sand):
13.33.1 Flush/Ruled pointing
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.023
sand). (Rate as per item no. 3.3) 3268.90 75.18
LABOUR
155 Mason Day 0.92 180 165.60
115 Coolie Day 1.37 207 283.59
101 Bhisti Day 0.93 180 167.40
9999 Scaffolding and sundries L.S 23.27 1.00 23.27
TOTAL 715.04
Add 1% for water charges 7.15
TOTAL 722.20
Add 15% for contractor’s profit and
overheads 108.33
Cos t of 10.00 sqm 830.52
Cost of 1.00 sqm 83.05
Say 83.05

13.33 Pointing on stone work with cement mortar 1:3 (1 cement :3 fine sand):
13.33.2 Raised and cut pointing
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 fine cum 0.038
sand). (Rate as per item no. 3.3) 3268.90 124.22
LABOUR
155 Mason Day 2 180 360.00
115 Coolie Day 2.96 207 612.72
101 Bhisti Day 1 180 180.00
9999 Scaffolding and sundries L.S 23.27 1.00 23.27
TOTAL 1300.21
Add 1% for water charges 13.00
TOTAL 1313.21
Add 15% for contractor’s profit and
overheads 196.98
Cos t of 10.00 sqm 1510.19
Cost of 1.00 sqm 151.02
Say 151.02

13.34 Raised and cut pointing on stone work in white cement mortar 1:3 ( 1 white
cement : 3 marble dust)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 3 (1 cement:3 marble cum 0.038 5990.33 227.63
dust). (Rate as per item no. 3.16)
LABOUR
155 Mason Day 2 180 360.00
115 Coolie Day 2.96 207 612.72
101 Bhisti Day 1 180 180.00
9999 Scaffolding and sundries L.S 23.27 1.00 23.27
TOTAL 1403.62
Add 1% for water charges 14.04
TOTAL 1417.66
Add 15% for contractor’s profit and
overheads 212.65
Cos t of 10.00 sqm 1630.31
Cost of 1.00 sqm 163.03
Say 163.03

13.35 Pointing on stone slab ceiling with cement mortar 1:2 ( 1 cement : 2 fine dust)
13.35.1 Flush/Ruled pointed
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 2 (1 cement:2 fine cum 0.015 4111.99 61.68
dust). (Rate as per item no. 3.2)
LABOUR
155 Mason Day 0.47 180 84.60
115 Coolie Day 0.69 207 142.83
101 Bhisti Day 0.59 180 106.20
9999 Scaffolding and sundries L.S 16.12 1.00 16.12
TOTAL 411.43
Add 1% for water charges 4.11
TOTAL 415.54
Add 15% for contractor’s profit and
overheads 62.33
Cos t of 10.00 sqm 477.88
Cost of 1.00 sqm 47.79
Say 47.79

13.36 Extra for pointing on walls on the outside at height more than 10 m from ground
level for every additional height of 3 m or part thereof.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
9999 Scaffolding and sundries L.S 26.78 1.00 26.78
TOTAL 26.78
Add 1% for water charges 0.27
TOTAL 27.05
Add 15% for contractor’s profit and
overheads 4.06
Cos t of 10.00 sqm 31.10
Cost of 1.00 sqm 3.11
Say 3.11

13.37 White washing with lime to give an even shade: —


13.37.1 New work (three or more coats)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
775 Dehradun white lime quintal 0.03 400.00 12.00
9999 Carriage of lime L.S 0.91 1.00 0.91
LABOUR
141 White Washer Day 0.2 180 36.00
115 Coolie Day 0.1 207 20.70
9999 indigo gums, ladders etc L.S 7.15 1.00 7.15
TOTAL 76.76
Add 1% for water charges 0.77
TOTAL 77.53
Add 15% for contractor’s profit and
overheads 11.63
Cos t of 10.00 sqm 89.16
Cost of 1.00 sqm 8.92
Say 8.92

13.38 Satna lime wash on wallls one coat


Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
776 Satna lime quintal 0.01 400.00 4.00
9999 Carriage of lime L.S 2.08 1.00 2.08
LABOUR
141 White Washer Day 0.08 180 14.40
115 Coolie Day 0.04 207 8.28
9999 indigo gums, ladders etc L.S 3.25 1.00 3.25
TOTAL 32.01
Add 1% for water charges 0.32
TOTAL 32.33
Add 15% for contractor’s profit and
overheads 4.85
Cos t of 10.00 sqm 37.18
Cost of 1.00 sqm 3.72
Say 3.72

13.39 Colour washing such as green, blue or buff to give an even shade : ,—
13.39.1 New work (two or more coats) with a base coat of white washing with lime
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
775 Dehradun white lime quintal 0.03 400.00 12.00
9999 Carriage of lime L.S 8.06 1.00 8.06
9999 Colouring staff L.S 0.91 1.00 0.91
LABOUR
141 White Washer Day 0.3 180 54.00
115 Coolie Day 0.1 207 20.70
9999 indigo gums, ladders etc L.S 7.15 1.00 7.15
TOTAL 102.82
Add 1% for water charges 1.03
TOTAL 103.85
Add 15% for contractor’s profit and
overheads 10.38
Cos t of 10.00 sqm 114.23
Cost of 1.00 sqm 11.42
Say 11.42

13.39 Colour washing such as green, blue or buff to give an even shade : ,—
13.39.2 New work (two or more coats) with a base coat of whiting
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
775 Dehradun white lime quintal 0.03 400.00 12.00
9999 Carriage of lime L.S 8.06 1.00 8.06
9999 Colouring staff L.S 0.91 1.00 0.91
LABOUR
141 White Washer Day 0.3 180 54.00
115 Coolie Day 0.1 207 20.70
9999 indigo gums, ladders etc L.S 5.46 1.00 5.46
TOTAL 101.13
Add 1% for water charges 1.01
TOTAL 102.14
Add 15% for contractor’s profit and
overheads 10.21
Cos t of 10.00 sqm 112.36
Cost of 1.00 sqm 11.24
Say 11.24

13.40 Distempering with dry distemper of approved brand and manufacture (two or more
coats) and of required shade on new work, over and including priming to give an even
shade:-coat of whiting
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
1216 Whiting quintal 0.01 329.00 3.29
815 Dry distemper kilogra 1.5 40.00 60.00
m
9999 Carriage of material L.S 1.56 1.00 1.56
9999 Putty, glue etc L.S 2.73 1.00 2.73
LABOUR
131 Painter Day 0.8 180 144.00
115 Coolie Day 0.4 207 82.80
9999 Sundries, brushes, sand paers etc L.S 12.53 1.00 12.53
TOTAL 306.91
Add 1% for water charges 3.07
TOTAL 309.98
Add 15% for contractor’s profit and
overheads 46.50
Cos t of 10.00 sqm 356.48
Cost of 1.00 sqm 35.65
Say 35.65

13.41 Distem pering with oil bound washable distemper of approved brand and
manufacture to give an even shade
13.41.1 New work (two or more coats) over and including priming coat with cement
primer:- Description
Code Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
816 Oil bound washable distemper/ Acrylic kilogra 1.5 45.00 67.50
distem m
820 Cement primer litre 0.7 60.00 42.00
9999 Carriage of material L.S 4.42 1.00 4.42
9999 Brushes, Putty, etc L.S 18.85 1.00 18.85
LABOUR
131 Painter Day 1 180 180.00
115 Coolie Day 0.5 207 103.50
9999 Sundries, brushes, sand paers etc L.S 16.12 1.00 16.12
TOTAL 432.39
Add 1% for water charges 4.32
TOTAL 436.71
Add 15% for contractor’s profit and
overheads 65.51
Cos t of 10.00 sqm 502.22
Cost of 1.00 sqm 50.22
Say 50.22

13.42 Distempering with 1st quality acrylic washable distemper (ready made) of
approved manufacturer and of required shade and colour complete, as per manufacturer’s
specification.
13.42.1 Two or more coats on new work.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
816 Oil bound washable distemper/ Acrylic kilogra 1.5 45.00 67.50
distem m
9999 Carriage of material L.S 4.42 1.00 4.42
9999 Brushes, Putty, etc L.S 11.57 1.00 11.57
LABOUR
131 Painter Day 0.4 180 72.00
115 Coolie Day 0.46 207 95.22
9999 Sundries, brushes, sand paers etc L.S 8.06 1.00 8.06
TOTAL 258.77
Add 1% for water charges 2.59
TOTAL 261.36
Add 15% for contractor’s profit and
overheads 39.20
Cos t of 10.00 sqm 300.56
Cost of 1.00 sqm 30.06
Say 30.06

13.43 Applying one coat of cement primer of approved brand and manufacture on wall
surface
13.43.1 Cement primer
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
820 Cement primer litre 0.7 60.00 42.00
9999 Brushes, Putty, etc L.S 7.15 1.00 7.15
LABOUR
131 Painter Day 0.4 180 72.00
115 Coolie Day 0.2 207 41.40
9999 Sundries, brushes, sand paers etc L.S 8.06 1.00 8.06
TOTAL 170.61
Add 1% for water charges 1.71
TOTAL 172.32
Add 15% for contractor’s profit and
overheads 25.85
Cos t of 10.00 sqm 198.16
Cost of 1.00 sqm 19.82
Say 19.82

13.44 Finishing walls with water proofing cement paint of required shade
13.44.1 New work (Two or more coats applied @ 3.84 kg/10 sqm).
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
851 Water proofing c ement paint kilogra 3.84 40.00 153.60
m
9999 Carriage of material L.S 1.56 1.00 1.56
LABOUR
131 Painter Day 0.46 180 82.80
115 Coolie Day 0.23 207 47.61
101 Bhishti Day 0.1 180 18.00
9999 Sundries, brushes, sand paers etc L.S 15.21 1.00 15.21
TOTAL 318.78
Add 1% for water charges 3.19
TOTAL 321.97
Add 15% for contractor’s profit and
overheads 48.30
Cos t of 10.00 sqm 370.26
Cost of 1.00 sqm 37.03
Say 37.03

13.45 Finishing walls with textured exterior paint of required shade :


13.45.1 New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including
base coat of water proofing cement paint applied @ 2.20kg/10 sqm.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
8507 Textured exterior paint litre 3.28 183.00 600.24
851 Water proofing c ement paint kilogra 2.2 40.00 88.00
m
9999 Carriage of material L.S 1.56 1.00 1.56
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.3 207 62.10
101 Bhishti Day 0.05 180 9.00
9999 Sundries, brushes, sand paers etc L.S 15.21 1.00 15.21
TOTAL 884.11
Add 1% for water charges 8.84
TOTAL 892.95
Add 15% for contractor’s profit and
overheads 133.94
Cos t of 10.00 sqm 1026.89
Cost of 1.00 sqm 102.69
Say 102.69

13.46 Finishing walls with Acrylic Smooth exterior paint of required shade : —
13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including base
coat of water proofing cement paint applied @ 2.20 kg/ 10 sqm).
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
8505 Acrylic exterior paint litre 1.67 123.00 205.41
851 Water proofing c ement paint kilogra 2.2 40.00 88.00
m
9999 Carriage of material L.S 1.56 1.00 1.56
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.3 207 62.10
101 Bhishti Day 0.05 180 9.00
9999 Sundries, brushes, sand paers etc L.S 15.21 1.00 15.21
TOTAL 489.28
Add 1% for water charges 4.89
TOTAL 494.17
Add 15% for contractor’s profit and
overheads 74.13
Cos t of 10.00 sqm 568.30
Cost of 1.00 sqm 56.83
Say 56.83

13.47 Finishing walls with Premium Acrylic Smooth exterior paint with Silicone
additives of required shade —
13.47.1 New work (Two or more coats applied @ 1.43 ltr/ 10 sqm. over and including
base coat of water proofing cement paint applied @ 2.20 kg/ 10 sqm).
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
8506 Premium Acrylic exterior paint litre 1.43 202.00 288.86
851 Water proofing c ement paint kilogra 2.2 40.00 88.00
m
9999 Carriage of material L.S 1.56 1.00 1.56
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.3 207 62.10
101 Bhishti Day 0.05 180 9.00
9999 Sundries, brushes, sand paers etc L.S 15.21 1.00 15.21
TOTAL 572.73
Add 1% for water charges 5.73
TOTAL 578.46
Add 15% for contractor’s profit and
overheads 86.77
Cos t of 10.00 sqm 665.23
Cost of 1.00 sqm 66.52
Say 66.52

13.48 Finishing walls with Deluxe Multi surface paint system for interiors and exteriors
using Primer as permanufacturers specifications :
13.48.1 Two or more coats applied @ 1.25 ltr/10 sqm. over and including one coat of
Special primer applied @0.75 ltr/10 sqm.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
8504 Multi surface paint litre 1.25 264.00 330.00
8509 Special Primer kilogra 0.75 76.00 57.00
m
9999 Carriage of material L.S 1.56 1.00 1.56
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.3 207 62.10
101 Bhishti Day 0.05 180 9.00
9999 Sundries, brushes, sand paers etc L.S 15.08 1.00 15.08
TOTAL 582.74
Add 1% for water charges 5.83
TOTAL 588.57
Add 15% for contractor’s profit and
overheads 88.29
Cos t of 10.00 sqm 676.85
Cost of 1.00 sqm 67.69
Say 67.69

13.48 Finishing walls with Deluxe Multi surface paint system for interiors and exteriors
using Primer as permanufacturers specifications :
13.48.2 Painting wood work with Deluxe Multi Surface Paint of required shade. Two or
more coat applied @0.90 ltr/10 sqm over an under coat of primer applied @0.75 ltr/10
sqm of approved brand or manufacture
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
8504 Multi surface paint litre 0.9 264.00 237.60
8509 Special Primer kilogra 0.75 76.00 57.00
m
9999 Carriage of material L.S 1.56 1.00 1.56
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.3 207 62.10
101 Bhishti Day 0.05 180 9.00
9999 Sundries, brushes, sand paers etc L.S 15.08 1.00 15.08
TOTAL 490.34
Add 1% for water charges 4.90
TOTAL 495.24
Add 15% for contractor’s profit and
overheads 74.29
Cos t of 10.00 sqm 569.53
Cost of 1.00 sqm 56.95
Say 56.95

13.48 Finishing walls with Deluxe Multi surface paint system for interiors and exteriors
using Primer as permanufacturers specifications :
13.48.3 Painting wood work with Deluxe Multi Surface Paint of required shade. Two
or more coat applied @0.90 ltr/10 sqm over an under coat of primer applied @0.80
ltr/10 sqm of approved brand or manufacture
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
8504 Multi surface paint litre 0.9 264.00 237.60
8510 Metal Primer kilogra 0.8 91.00 72.80
m
9999 Carriage of material L.S 1.56 1.00 1.56
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.3 207 62.10
101 Bhishti Day 0.05 180 9.00
9999 Sundries, brushes, sand paers etc L.S 15.08 1.00 15.08
TOTAL 506.14
Add 1% for water charges 5.06
TOTAL 511.20
Add 15% for contractor’s profit and
overheads 76.68
Cos t of 10.00 sqm 587.88
Cost of 1.00 sqm 58.79
Say 58.79

13.49 Extra for applying water proofing cement paint as primer applied @ 2.2 kg/ 0 sqm
instead of primer for exterior finishing in Item No. 13.48.1
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
851 Water proofing c ement paint kilogra 2.2 40.00 88.00
m
8509 Special Primer kilogra 0.75 76.00 -57.00
m
TOTAL 31.00
Add 1% for water charges 0.31
TOTAL 31.31
Add 15% for contractor’s profit and
overheads 4.70
Cos t of 10.00 sqm 36.01
Cost of 1.00 sqm 3.60
Say 3.60
13.50 Applying priming coat:-
13.50.1 With ready mixed pink or Grey primer of approved brand and manufacture
on wood work (hard and soft wood)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
823 Pink primer (for wood) litre 0.75 150.00 112.50
9999 Carriage of material L.S 0.39 1.00 0.39
9999 Putty L.S 2.73 1.00 2.73
LABOUR
131 Painter Day 0.25 180 45.00
115 Coolie Day 0.25 207 51.75
9999 Sundries, brushes, sand paers etc L.S 16.12 1.00 16.12
TOTAL 228.49
Add 1% for water charges 2.28
TOTAL 230.77
Add 15% for contractor’s profit and
overheads 34.62
Cos t of 10.00 sqm 265.39
Cost of 1.00 sqm 26.54
Say 26.54

13.50 Applying priming coat:-


13.50.2 With ready mixed aluminium primer of approved brand and manufacture or
resinous wood and plywood.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
4201 Aluminium primer litre 0.75 63.00 47.25
9999 Carriage of material L.S 0.39 1.00 0.39
9999 Putty L.S 2.73 1.00 2.73
LABOUR
131 Painter Day 0.25 180 45.00
115 Coolie Day 0.25 207 51.75
9999 Sundries, brushes, sand paers etc L.S 16.12 1.00 16.12
TOTAL 163.24
Add 1% for water charges 1.63
TOTAL 164.87
Add 15% for contractor’s profit and
overheads 24.73
Cos t of 10.00 sqm 189.60
Cost of 1.00 sqm 18.96
Say 18.96

13.50 Applying priming coat:


13.50.3 With ready mixed red oxide zinc chromate prim er of approved brand and
manufacture on steel galvanised iron/steel works:-
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.54 58.00 31.32

9999 Carriage of material L.S 0.52 1.00 0.52


LABOUR
131 Painter Day 0.24 180 43.20
115 Coolie Day 0.24 207 49.68
9999 Sundries, brushes, sand paers etc L.S 10.79 1.00 10.79
TOTAL 135.51
Add 1% for water charges 1.36
TOTAL 136.87
Add 15% for contractor’s profit and
overheads 20.53
Cos t of 10.00 sqm 157.39
Cost of 1.00 sqm 15.74
Say 15.74

13.50 Applying priming coat:


13.50.4 With ready mixed red oxide zinc chromate primer of approved brand and
manufacture on steel work (second coat)
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.36 58.00 20.88

9999 Carriage of material L.S 0.39 1.00 0.39


LABOUR
131 Painter Day 0.12 180 21.60
115 Coolie Day 0.12 207 24.84
9999 Sundries, brushes, sand paers etc L.S 7.15 1.00 7.15
TOTAL 74.86
Add 1% for water charges 0.75
TOTAL 75.61
Add 15% for contractor’s profit and
overheads 11.34
Cos t of 10.00 sqm 86.95
Cost of 1.00 sqm 8.69
Say 8.69

13.51 Painting one thin coat with white lead of approved brand and manufacture on wet
or patchy portion of plastered surfaces
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
850 White lead kilogra 0.86 100.00 86.00
m
818 Linseed oil (double boiled) litre 0.61 55.00 33.55
9999 Carriage of material L.S 0.52 1.00 0.52
9999 Putty L.S 2.73 1.00 2.73
LABOUR
131 Painter Day 0.27 180 48.60
115 Coolie Day 0.27 207 55.89
9999 Sundries, brushes, sand paers etc L.S 16.12 1.00 16.12
TOTAL 243.41
Add 1% for water charges 2.43
TOTAL 245.84
Add 15% for contractor’s profit and
overheads 36.88
Cos t of 10.00 sqm 282.72
Cost of 1.00 sqm 28.27
Say 28.27

13.52 Finishing with Epoxy paint (two or more coats) at all locations prepared and
applied as per manufacturer’ specifications including appropriate priming coat,
preparation of surface, etc. complete.
13.52.1 On Steel work
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.75 58.00 43.50

7239 Epoxy paint litre 1.25 280.00 350.00


9999 Carriage of material L.S 1.82 1.00 1.82
9999 Putty L.S 2.73 1.00 2.73
LABOUR
131 Painter Day 0.79 180 142.20
115 Coolie Day 0.79 207 163.53
9999 Sundries, brushes, sand paers etc L.S 30.94 1.00 30.94
TOTAL 734.72
Add 1% for water charges 7.35
TOTAL 742.07
Add 15% for contractor’s profit and
overheads 111.31
Cos t of 10.00 sqm 853.38
Cost of 1.00 sqm 85.34
Say 85.34
13.52 Finishing with Epoxy paint (two or more coats) at all locations prepared and
applied as per manufacturer’ specifications including appropriate priming coat,
preparation of surface, etc. complete.
13.52.2 On concrete work:-
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
821 Distemper primer litre 0.84 60.00 50.40
7239 Epoxy paint litre 1.21 280.00 338.80
9999 Carriage of material L.S 1.95 1.00 1.95
9999 Putty L.S 20.28 1.00 20.28
LABOUR
131 Painter Day 0.79 180 142.20
115 Coolie Day 0.79 207 163.53
9999 Sundries, brushes, sand paers etc L.S 28.34 1.00 28.34
TOTAL 745.50
Add 1% for water charges 7.46
TOTAL 752.96
Add 15% for contractor’s profit and
overheads 112.94
Cos t of 10.00 sqm 865.90
Cost of 1.00 sqm 86.59
Say 86.59

13.53 Painting on G.S. sheet with synthetic enamel paint of approved brand and
manufacture of required colour to give an even shade : -
13.53.1 New work (two or more coats) including a coat of approved steel primer
but excluding a coat of mordant solution.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.36 58.00 20.88

834 Synthetic enamel paint in all shades litre 0.8 170.00 136.00

9999 Carriage of material L.S 1.82 1.00 1.82


LABOUR
131 Painter Day 0.66 180 118.80
115 Coolie Day 0.66 207 136.62
9999 Sundries, brushes, sand paers etc L.S 21.97 1.00 21.97
TOTAL 436.09
Add 1% for water charges 4.36
TOTAL 440.45
Add 15% for contractor’s profit and
overheads 66.07
Cos t of 10.00 sqm 506.52
Cost of 1.00 sqm 50.65
Say 50.65

13.54 Applying a coat of mordant solution on G.S. sheet


13.54.1 With a solution of 38 gms of copper acetate in a litre of soft water
Code Description Unit Quantity Rate Amount
Detail of cost for 25 sqm
Materials
4203 Copper acetate kilogra 0.038 228.00 8.66
m
9999 Soft water L.S 1.82 1.00 1.82
9999 Carriage of material L.S 0.91 1.00 0.91
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.6 207 124.20
9999 Sundries, brushes, sand paers etc L.S 71.68 1.00 71.68
TOTAL 315.27
Add 1% for water charges 3.15
TOTAL 318.43
Add 15% for contractor’s profit and
overheads 47.76
Cos t of 25 sqm 366.19
Cost of 1.00 sqm 14.65
Say 14.65

13.54 Applying a coat of mordant solution on G.S. sheet


13.54.2 With a solution made of 13 gms of hydrochloric acid in a solution of 13 gms
each of copper chloride,. copper nitrate and am monium chloride dissolved in a litre of
soft
Codewater.Description Unit Quantity Rate Amount
Detail of cost for 25 sqm
Materials
4204 Hydrochloric acid kilogra 0.013 27.00 0.35
m
4205 Copper chloride kilogra 0.013 244.00 3.17
m
4206 Copper nitrate kilogra 0.013 173.00 2.25
m
4207 Ammonium chloride kilogra 0.013 12.00 0.16
m
9999 Soft water L.S 1.82 1.00 1.82
9999 Carriage of material L.S 0.91 1.00 0.91
LABOUR
131 Painter Day 0.6 180 108.00
115 Coolie Day 0.6 207 124.20
9999 Sundries, brushes, sand paers etc L.S 71.68 1.00 71.68
TOTAL 312.54
Add 1% for water charges 3.13
TOTAL 315.66
Add 15% for contractor’s profit and
overheads 47.35
Cos t of 25 sqm 363.01
Cost of 1.00 sqm 14.52
Say 14.52

13.55 Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings
with black anticorrosive bitumastic paint approved brand and manufacture over and
including a priming coat of readymixed zinc chromate yellow primer on new work : -—
13.55.1 100 mm diameter pipes
Code Description Unit Quantity Rate Amount
Detail of cost for 30 metres
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.54 58.00 31.32

828 Anticorrosive bituminous paint (black) litre 0.95 52.00 49.40


9999 Carriage of material L.S 1.95 1.00 1.95
LABOUR
131 Painter Day 0.78 180 140.40
115 Coolie Day 0.78 207 161.46
9999 Sundries, brushes, sand paers etc L.S 29.51 1.00 29.51
9999 Extra for delays L.S 61.1 1.00 61.10
TOTAL 475.14
Add 1% for water charges 4.75
TOTAL 479.89
Add 15% for contractor’s profit and
overheads 71.98
Cos t of 30 metre 551.88
Cost of 1.00 metre 18.40
Say 18.40

13.55 Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings
with black anticorrosive bitumastic paint approved brand and manufacture over and
including a priming coat of readymixed zinc chromate yellow primer on new work : -—
13.55.2 150 mm diameter pipes
Code Description Unit Quantity Rate Amount
Detail of cost for 30 metres
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.8 58.00 46.40

828 Anticorrosive bituminous paint (black) litre 1.41 52.00 73.32

9999 Carriage of material L.S 2.99 1.00 2.99


LABOUR
131 Painter Day 1.16 180 208.80
115 Coolie Day 1.16 207 240.12
9999 Sundries, brushes, sand paers etc L.S 43.16 1.00 43.16
9999 Extra for delays L.S 94.12 1.00 94.12
TOTAL 708.91
Add 1% for water charges 7.09
TOTAL 716.00
Add 15% for contractor’s profit and
overheads 107.40
Cos t of 30 metre 823.40
Cost of 1.00 metre 27.45
Say 27.45

13.56 Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings
with synthetic enamel paint of approved brand and manufacture and required colour over
a priming coat of approved steel primer on new work.
13.56.1 100 mm diameter pipes
Code Description Unit Quantity Rate Amount
Detail of cost for 30 metres
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.54 58.00 31.32

826 Aluminium paint litre 0.8 180.00 144.00


9999 Carriage of material L.S 1.95 1.00 1.95
LABOUR
131 Painter Day 0.78 180 140.40
115 Coolie Day 0.78 207 161.46
9999 Sundries, brushes, sand paers etc L.S 34.84 1.00 34.84
9999 Extra for delays L.S 66.43 1.00 66.43
TOTAL 580.40
Add 1% for water charges 5.80
TOTAL 586.20
Add 15% for contractor’s profit and
overheads 87.93
Cos t of 30 metre 674.13
Cost of 1.00 metre 22.47
Say 22.47

13.56 Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings
with synthetic enamel paint of approved brand and manufacture and required colour over
a priming coat of approved steel primer on new work.
13.56.2 150 mm diameter pipes
Code Description Unit Quantity Rate Amount
Detail of cost for 30 metres
Materials
4202 Red oxide Zinc chromate yellow primer litre 0.8 58.00 46.40

826 Aluminium paint litre 1.19 180.00 214.20


9999 Carriage of material L.S 2.99 1.00 2.99
LABOUR
131 Painter Day 1.16 180 208.80
115 Coolie Day 1.16 207 240.12
9999 Sundries, brushes, sand paers etc L.S 51.74 1.00 51.74
9999 Extra for delays L.S 101.4 1.00 101.40
TOTAL 865.65
Add 1% for water charges 8.66
TOTAL 874.31
Add 15% for contractor’s profit and
overheads 131.15
Cos t of 30 metre 1005.45
Cost of 1.00 metre 33.52
Say 33.52

13.57 Painting with oil type wood preservative of approved brand and manufacture:
13.57.1 New work (Two or more coats )
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
859 Oil type wood preservative litre 1 60.00 60.00
9999 Carriage of material L.S 0.52 1.00 0.52
LABOUR
131 Painter Day 0.15 180 27.00
115 Coolie Day 0.15 207 31.05
9999 Sundries, brushes, sand paers etc L.S 8.06 1.00 8.06
TOTAL 126.63
Add 1% for water charges 1.27
TOTAL 127.90
Add 15% for contractor’s profit and
overheads 19.18
Cos t of 10.00 sqm 147.08
Cost of 1.00 sqm 14.71
Say 14.71

13.58 Providing and applying two coats of fire retardant paint unthinned on cleaned
wood/ ply surface @ 3.5 sqm per litre per coat including preparation of base surface as
per recommendations of manufacturer to make the surface fire retardant.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
7240 Fire retardant paint litre 5.7 318.00 1812.60
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.54 180 97.20
115 Coolie Day 0.54 207 111.78
9999 Sundries, brushes, sand paers etc L.S 14.82 1.00 14.82
TOTAL 2037.83
Add 1% for water charges 20.38
TOTAL 2058.21
Add 15% for contractor’s profit and
overheads 308.73
Cos t of 10.00 sqm 2366.94
Cost of 1.00 sqm 236.69
Say 236.69

13.59 Coal tarring two coats on new work using 0.16 and 0.12 litre coal tar per sqm in
the first coat and second coat respectively.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
324 Coal tar litre 2.8 16.00 44.80
771 Kerosene oil litre 0.5 25.00 12.50
9999 Lime L.S 1.43 1.00 1.43
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
114 Beldar Day 0.43 207 89.01
9999 Sundries, brushes, sand paers etc L.S 10.66 1.00 10.66
TOTAL 159.83
Add 1% for water charges 1.60
TOTAL 161.43
Add 15% for contractor’s profit and
overheads 24.21
Cos t of 10.00 sqm 185.64
Cost of 1.00 sqm 18.56
Say 18.56

13.60 Wall painting with plastic emulsion paint of approved brand and manufacture to
give an even shade
13.60.1 Two or more coats on new work-
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
835 Plastic emulsion paint litre 1.21 150.00 181.50
9999 Putty L.S 6.76 1.00 6.76
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.54 180 97.20
115 Coolie Day 0.54 207 111.78
9999 Sundries, brushes, sand paers etc L.S 17.55 1.00 17.55
TOTAL 416.22
Add 1% for water charges 4.16
TOTAL 420.38
Add 15% for contractor’s profit and
overheads 63.06
Cos t of 10.00 sqm 483.44
Cost of 1.00 sqm 48.34
Say 48.34

13.61 Painting with synthetic enamel paint of approved brand and manufacture to give an
even shade:
13.61.1 Two or more coats on new work
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
833 Synthetic enamel paint litre 1.16 170.00 197.20
9999 Putty L.S 5.33 1.00 5.33
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.54 180 97.20
115 Coolie Day 0.54 207 111.78
9999 Sundries, brushes, sand paers etc L.S 14.82 1.00 14.82
TOTAL 427.76
Add 1% for water charges 4.28
TOTAL 432.04
Add 15% for contractor’s profit and
overheads 64.81
Cos t of 10.00 sqm 496.84
Cost of 1.00 sqm 49.68
Say 49.68

13.62 Painting with synthetic enamel paint of approved brand and manufacture of
required colour to give an even shade:
13.62.1 Two or more coats on new work over an under coat of suitable shade with
ordinary paint of approved brand and manufacture.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
833 Synthetic enamel paint litre 1.16 170.00 197.20
823 Pink primer (for wood) litre 0.75 150.00 112.50
9999 Putty L.S 2.73 1.00 2.73
9999 Carriage of material L.S 1.82 1.00 1.82
LABOUR
131 Painter Day 0.79 180 142.20
115 Coolie Day 0.79 207 163.53
9999 Sundries, brushes, sand paers etc L.S 30.94 1.00 30.94
TOTAL 650.92
Add 1% for water charges 6.51
TOTAL 657.43
Add 15% for contractor’s profit and
overheads 98.61
Cos t of 10.00 sqm 756.04
Cost of 1.00 sqm 75.60
Say 75.60

13.63 Painting with aluminium enamel paint of approved brand and manufacture to give
an even shade:
13.63.1 Two or more coats on new work
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
826 Aluminium paint litre 0.8 180.00 144.00
9999 Putty L.S 5.33 1.00 5.33
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.54 180 97.20
115 Coolie Day 0.54 207 111.78
9999 Sundries, brushes, sand paers etc L.S 18.72 1.00 18.72
TOTAL 378.46
Add 1% for water charges 3.78
TOTAL 382.24
Add 15% for contractor’s profit and
overheads 57.34
Cos t of 10.00 sqm 439.58
Cost of 1.00 sqm 43.96
Say 43.96

13.64 Painting with acid proof paint of approved brand and manufacture to give an even
shade:
13.64.1 Two or more coats on new work
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
827 Acid proof paint litre 1.16 93.00 107.88
9999 Putty L.S 5.33 1.00 5.33
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.54 180 97.20
115 Coolie Day 0.54 207 111.78
9999 Sundries, brushes, sand paers etc L.S 14.82 1.00 14.82
TOTAL 338.44
Add 1% for water charges 3.38
TOTAL 341.82
Add 15% for contractor’s profit and
overheads 51.27
Cos t of 10.00 sqm 393.10
Cost of 1.00 sqm 39.31
Say 39.31

13.65 Painting with black anti-corrosive bitumastic paint of approved brand and
manufacture to give an even shade:
13.65.1 Two or more coats on new work
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
828 Black anticorrosive bitumastic paint litre 0.95 52.00 49.40
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.54 180 97.20
115 Coolie Day 0.54 207 111.78
9999 Sundries, brushes, sand paers etc L.S 13.39 1.00 13.39
TOTAL 273.20
Add 1% for water charges 2.73
TOTAL 275.93
Add 15% for contractor’s profit and
overheads 41.39
Cos t of 10.00 sqm 317.32
Cost of 1.00 sqm 31.73
Say 31.73

13.66 Floor Painting with floor enamel paint of approved brand and manufacture to give
an even shade:
13.66.1 Two or more coats on new work
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
831 Floor enamel paint in all shades litre 1.48 170.00 251.60
9999 Putty L.S 5.33 1.00 5.33
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.54 180 97.20
115 Coolie Day 0.54 207 111.78
9999 Sundries, brushes, sand paers etc L.S 14.82 1.00 14.82
TOTAL 482.16
Add 1% for water charges 4.82
TOTAL 486.98
Add 15% for contractor’s profit and
overheads 73.05
Cos t of 10.00 sqm 560.03
Cost of 1.00 sqm 56.00
Say 56.00

13.67 Varnishing with varnish of approved brand and manufacture:


13.67.1 Two or more coats of glue sizing with copal varnish over an under coat of flatting
varnish.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
856 Undercoat flatting varnish litre 0.7 49.00 34.30
857 Copal varnish litre 1.16 100.00 116.00
763 Glue for sizing kilogra 0.07 50.00 3.50
m
9999 Putty L.S 5.33 1.00 5.33
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.9 180 162.00
115 Coolie Day 0.9 207 186.30
9999 Sundries, brushes, sand paers etc L.S 13.91 1.00 13.91
TOTAL 522.77
Add 1% for water charges 5.23
TOTAL 528.00
Add 15% for contractor’s profit and
overheads 79.20
Cos t of 10.00 sqm 607.20
Cost of 1.00 sqm 60.72
Say 60.72

13.67 Varnishing with varnish of approved brand and manufacture:


13.67.2 Two or more coats glue sizing with spar varnish or an under coat of flatting
Code
varnish. Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
856 Undercoat flatting varnish litre 0.7 49.00 34.30
858 Superior spar varnish litre 0 105.00 0.00
763 Glue for sizing kilogra 0.07 50.00 3.50
m
9999 Putty L.S 2.73 1.00 2.73
9999 Carriage of material L.S 1.43 1.00 1.43
LABOUR
131 Painter Day 0.9 180 162.00
115 Coolie Day 0.9 207 186.30
9999 Sundries, brushes, sand paers etc L.S 13.91 1.00 13.91
TOTAL 404.17
Add 1% for water charges 4.04
TOTAL 408.21
Add 15% for contractor’s profit and
overheads 61.23
Cos t of 10.00 sqm 469.44
Cost of 1.00 sqm 46.94
Say 46.94

13.68 French spirit polishing:


13.68.1 Two or more coats on new works including a coat of wood filler.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
1000 Spirit litre 1.63 37.00 60.31
999 Shellac litre 0.24 192.00 46.08
9999 Pigment, white woolen cloth ,putty, sand L.S 38.09
paper linseed oil etc. 1.00 38.09
9999 Carriage of material L.S 2.73 1.00 2.73
LABOUR
131 Painter Day 3.5 180 630.00
9999 Sundries, brushes, sand paers etc L.S 8.06 1.00 8.06
TOTAL 785.27
Add 1% for water charges 7.85
TOTAL 793.12
Add 15% for contractor’s profit and
overheads 118.97
Cos t of 10.00 sqm 912.09
Cost of 1.00 sqm 91.21
Say 91.21

13.69 Polishing on wood work with ready made wax polish of approved brand and
manufacture :
13.69.1 New work
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
855 Ready made Wax polish kilogra 0.5 150.00 75.00
m
9999 Carriage of material L.S 0.39 1.00 0.39
LABOUR
131 Painter Day 0.8 180 144.00
115 Coolie Day 0.8 207 165.60
9999 Sundries, brushes, sand paers etc L.S 11.31 1.00 11.31
TOTAL 396.30
Add 1% for water charges 3.96
TOTAL 400.26
Add 15% for contractor’s profit and
overheads 60.04
Cos t of 10.00 sqm 460.30
Cost of 1.00 sqm 46.03
Say 46.03

13.70 Floor polishing on masonry or concrete floors with wax polish of approved brand
and manufacture.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
855 Ready made Wax polish kilogra 0.1 150.00 15.00
m
LABOUR
131 Painter Day 0.4 180 72.00
115 Coolie Day 0.4 207 82.80
9999 Sundries, brushes, sand paers etc L.S 13.39 1.00 13.39
TOTAL 183.19
Add 1% for water charges 1.83
TOTAL 185.02
Add 15% for contractor’s profit and
overheads 27.75
Cos t of 10.00 sqm 212.78
Cost of 1.00 sqm 21.28
Say 21.28

13.71 Lettering with black Japan paint of approved brand and manufacture
Code Description Unit Quantity Rate Amount
Detail of cost for 100 letters of 15 cm height
MATERIALS
829 Paint litre 0.56 170.00 95.20
9999 Carriage of material L.S 0.91 1.00 0.91
LABOUR
131 Painter Day 6 180 1080.00
115 Coolie Day 2 207 414.00
9999 Sundries, Painting brushes, turpentine, L.S 21.45
stencil etc 1.00 21.45
TOTAL 1611.56
Add 1% for water charges 16.12
TOTAL 1627.68
Add 15% for contractor’s profit and
overheads 244.15
Cost of 100 letters of 15cm height 1871.83
Cost of 1 letter of 1 cm height 1.25
Say 1.25
13.72 Washed stone grit plaster on exterior walls of height upto 10 M. above ground
level in two layers, under layer 12mm cement plaster 1:4 (1 cement : 4 coarse sand )
furrowing the under layer with scratching tool, applying cement slurry on the under layer
@ 2 Kg of cement per square metre, top layer 15mm cement plaster 1:1/2:2 (1 cement:
1/2 coarse sand : 2 stone chipping 10mm nominal size) in panels with groove all around
as per approved pattern including scrubbing and washing, the top layer with brushes and
water to expose the stone chippings ,complete as per specification and direction of
Engineer-in- charge (Payment for providing grooves shall be made separately).

Code Description Unit Quantity Rate Amount


Detail of cost for 10 sqm
MATERIALS
Cem ent mortar 1 : 4 (1 cement:4 coarse cum 0.144
sand). (Rate as per item no. 3.9)
2580.18 371.55
367 Cement tonne 0.12 5200.00 624.00
2209 Carriage of cement tonne 0.12 47.29 5.67
2911 Stone aggregate 10mm cum 0.14 1050.00 147.00
2202 Carriage of aggregate 20mm and 10 mm cum 0.14 53.21 7.45

982 Coarse sand cum 0.04 300.00 12.00


2203 Carriage of coarse sand cum 0.04 53.21 2.13
LABOUR
155 Mason Day 0.67 180 120.60
123 Mason ist class Day 2.75 270 742.50
114 Beldar Day 2.1 207 434.70
115 Coolie Day 1.25 207 258.75
101 Bhisti Day 1.27 180 228.60
9999 Scaffolding and sundries L.S 65 1.00 65.00
TOTAL 3019.95
Add 1% for water charges 30.20
TOTAL 3050.15
Add 15% for contractor’s profit and
overheads 457.52
Cos t of 10.00 sqm 3507.67
Cost of 1.00 sqm 350.77
Say 350.77

13.73 Forming groove of uniform size in the top layer of washed stone grit plaster as per
approved pattern using wooden battens, nailed to the under layer including removal of
wooden battens, repair to the edges of panels and finishing the groove complete as per
specifications and direction of the Engineer-in-charge :
13.73.1 15 mm wide and 15 mm deep groove
Code Description Unit Quantity Rate Amount
Detail of cost for 30 metres
MATERIALS
1,198 Second class kail wood in planks 10 1.48
cudm 178.00 26.34
9999 Carriage of material L.S 0.39 1.00 0.39
LABOUR
112 Carpenter IInd class Day 0.15 223 33.45
114 Beldar Day 0.85 207 175.95
123 Mason ist class Day 0.7 270 189.00
9999 Sundries , nails etc. L.S 74.62 1.00 74.62
TOTAL 499.75
Add 1% for water charges 5.00
TOTAL 504.75
Add 15% for contractor’s profit and
overheads 75.71
Cost of 30 metres 580.46
Cost of 1 metre 19.35
Say 19.35

13.73 Forming groove of uniform size in the top layer of washed stone grit plaster as per
approved pattern using wooden battens, nailed to the under layer including removal of
wooden battens, repair to the edges of panels and finishing the groove complete as per
specifications and direction of the Engineer-in-charge :

13.73.2 20 mm wide and 15 mm deep groove


Code Description Unit Quantity Rate Amount
Detail of cost for 30 metres
MATERIALS
1,198 Second class kail wood in planks 10 1.98
cudm 178.00 35.24
9999 Carriage of material L.S 0.52 1.00 0.52
LABOUR
112 Carpenter IInd class Day 0.15 223 33.45
114 Beldar Day 0.85 207 175.95
123 Mason ist class Day 0.7 270 189.00
9999 Sundries , nails etc. L.S 74.62 1.00 74.62
TOTAL 508.78
Add 1% for water charges 5.09
TOTAL 513.87
Add 15% for contractor’s profit and
overheads 77.08
Cost of 30 metres 590.95
Cost of 1 metre 19.70
Say 19.70

13.74 Extra for washed grit plaster on exterior walls of height more than 10m from
ground level for every additional height of 3 m or part thereof.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Materials
9999 Scaffolding L.S 215.28 1.00 215.28
LABOUR
101 Bhishti Day 0.15 180 27.00
114 Beldar Day 0.3 207 62.10
123 Mason ist class Day 0.3 270 81.00
9999 Sundries L.S 28.6 1.00 28.60
TOTAL 413.98
Add 1% for water charges 4.14
TOTAL 418.12
Add 15% for contractor’s profit and
overheads 62.72
Cos t of 10.00 sqm 480.84
Cost of 1.00 sqm 48.08
Say 48.08

13.75 Extra for washed stone grit plaster on circular work not exceeding 6m in radius (in
two coats).
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
LABOUR
114 Beldar Day 0.5 207 103.50
123 Mason ist class Day 0.5 270 135.00
9999 Sundries L.S 53.82 1.00 53.82
TOTAL 292.32
Add 1% for water charges 2.92
TOTAL 295.24
Add 15% for contractor’s profit and
overheads 44.29
Cos t of 10.00 sqm 339.53
Cost of 1.00 sqm 33.95
Say 33.95

13.76 Forming groove of uniform size from 12xl2mm and upto 25xl5mm in plastered
surface as per approved pattern using wooden battens, nailed to the under layer including
removal of wooden battens, repairs to the edges of plaster panel and finishing the groove
complete as per specifications and direction of the Engineer-in-Charge..
Code Description Unit Quantity Rate Amount
Detail of cost for 30 metres
MATERIALS
1,198 Second class kail wood in planks 10 1.5
cudm 178.00 26.70
9999 Carriage of material L.S 0.39 1.00 0.39
LABOUR
112 Carpenter IInd class Day 0.15 223 33.45
114 Beldar Day 0.85 207 175.95
123 Mason ist class Day 0.7 270 189.00
9999 Sundries , nails etc. L.S 74.72 1.00 74.72
TOTAL 500.21
Add 1% for water charges 5.00
TOTAL 505.21
Add 15% for contractor’s profit and
overheads 75.78
Cost of 30 metres 580.99
Cost of 1 metre 19.37
Say 19.37

13.77 Extra for using white cement in place of ordinary cement in the top layer of the
item of washed stone grit, plaster.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
368 (A) Add for White Cement tonne 0.1 9500.00 950.00
367 (B) Duduct for Ordinary Cement tonne 0.1 5200.00 -520.00
TOTAL 430.00
Add 1% for water charges 4.30
TOTAL 434.30
Add 15% for contractor’s profit and
overheads 65.15
Cos t of 10.00 sqm 499.45
Cost of 1.00 sqm 49.94
Say 49.94

13.78 Providing and applying 12 mm thick (average) premixed formulated one coat
gypsum lightweight plaster having additives and light weight aggregates as vermiculite/
perlite respectively conforming to IS: 2547 (Part - 1 & II) 1976, applied on hacked /
uneven background such as bare brick/ block/ RCC work on walls & ceiling at all floors
and locations, finished in smooth line and level etc. complete.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
MATERIALS
868 Premixed super white gypsum plaster kilogram 169.47 5.20 881.24
LABOUR
155 Mason Day 1.2 180 216.00
115 Coolie Day 1.2 207 248.40
9999 Sundries & scaffolding L.S 12.61 1.00 12.61
TOTAL 1358.25
Add 1% for water charges 13.58
TOTAL 1371.84
Add 15% for contractor’s profit and
overheads 205.78
Cos t of 10.00 sqm 1577.61
Cost of 1.00 sqm 157.76
Say 157.76
14.1 Repairs to plaster of thickness 12mm to 20mm in patches of area 2.5 sq. metres and under
including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of
the walls complete including disposal of rubbish to the dumping ground within 50metres lead :
14.1.1 With cement mortar 1:4 (1 cement: 4 fine sand)
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIALS
Cem ent mortar 1:4 (1 cement: 4 fine cum 0.183 2580.18 472.17
sand). (Rate as per item No 3.4)
Labour:
155 Mason Day 1.21 180 217.80
115 Coolie Day 1.29 207 267.03
114 Beldar Day 0.54 207 111.78
101 Bhishti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S. 15.21 1.00 15.21
TOTAL 1249.59
Add 1% for water charges 12.50
TOTAL 1262.09
Add 15 % for contractor’s profit and 189.31
overheads
Cost of 10 sqm 1451.40
Cost of 1 sqm 145.14
Say 145.14

14.1 Repairs to plaster of thickness 12mm to 20mm in patches of area 2.5 sq. metres and under
including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of
the walls complete including disposal of rubbish to the dumping ground within 50metres lead :
14.1.2 With cement mortar 1:4(1 cement: 4 coarse sand).
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIALS
Cem ent mortar 1:4 (1 cement: 4 corse cum 0.183 2580.18 472.17
sand). (Rate as per item No 3.9)
Labour:
155 Mason Day 1.21 180 217.80
115 Coolie Day 1.29 207 267.03
114 Beldar Day 0.54 207 111.78
101 Bhishti Day 0.92 180 165.60
9999 Scaffolding and sundries L.S. 15.21 1.00 15.21
TOTAL 1249.59
Add 1% for water charges 12.50
TOTAL 1262.09
Add 15 % for contractor’s profit and 189.31
overheads
Cost of 10 sqm 1451.40
Cost of 1 sqm 145.14
Say 145.14

14.2 Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting
masonry for holdfasts embedding hold fasts in cement concrete blocks with cement concrete 1:3:6 (1
cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) painting two coats of approved
wood preservative to sides of chowkhats and making good the damages to walls and floors as required
complete including disposal of rubbish to the dumping ground within 50 metres lead :

14.2.1 Door chowkhats


Code Description Unit Quantity Rate Amount
Details of cost for 1.00 No.
295 Stone aggregate 20 mm cum 0.021 1100.00 23.10
297 Stone aggregate 10 mm cum 0.0072 1050.00 7.56
2202 Carriage of aggregate below 20mm cum 0.0282 53.21 1.50
982 Coarse sand cum 0.0141 300.00 4.23
2261 Carriage of coarse sand cum 0.0141 53.21 0.75
367 Cement tonne 0.0066 5200.00 34.32
2209 Carriage of cement tonne 0.0066 47.29 0.31
Labour:
115 Coolie Day 0.0195 207 4.04
114 Beldar Day 0.777 207 160.84
123 Mason ist class Day 0.0018 270 0.49
124 Mason 2nd class Day 0.0018 223 0.40
130 Mistry Day 0.0084 270 2.27
128 Mate Day 0.0012 313 0.38
155 Mason Day 0.5 180 90.00
9999 Scaffolding L. S. 1.43 1.00 1.43
9999 Hire and running charges of mechanical L. S. 0.78 1.00 0.78
mixer
9999 Sundries L. S. 3.12 1.00 3.12
9999 Cement concrete 1:2:4 filled in chase L. S. 24.18 1.00 24.18
cut
9999 Painting two coats of coaltar L. S. 13.52 1.00 13.52
9999 Disposal of mulba L. S. 1.82 1.00 1.82

Cem ent mortar 1:6 (1 cement: 6 fine cum 0.01 1898.04 18.98
sand) (Rate as per item no. 3.6)
TOTAL 394.01
Add 1% for water charges 3.94
TOTAL 397.95
Add 15 % for contractor’s profit and overheads 59.69
Cost of 1 no. 457.64
Say 457.64

14.2 Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting
masonry for holdfasts embedding hold fasts in cement concrete blocks with cement concrete 1:3:6 (1
cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) painting two coats of approved
wood preservative to sides of chowkhats and making good the damages to walls and floors as required
complete including disposal of rubbish to the dumping ground within 50 metres lead :

14.2.2 Window chowkhats


Code Description Unit Quantity Rate Amount
Details of cost for 1.00 No.
295 Stone aggregate 20 mm cum 0.014 1100.00 15.40
297 Stone aggregate 10 mm cum 0.0048 1050.00 5.04
2202 Carriage of aggregate below 20mm cum 0.0188 53.21 1.00
982 Coarse sand cum 0.0094 300.00 2.82
2261 Carriage of coarse sand cum 0.0094 53.21 0.50
367 Cement tonne 0.0044 5200.00 22.88
2209 Carriage of cement tonne 0.0044 47.29 0.21
Labour:
115 Coolie Day 0.013 207 2.69
114 Beldar Day 0.518 207 107.23
123 Mason ist class Day 0.0012 270 0.32
124 Mason 2nd class Day 0.0012 223 0.27
130 Mistry Day 0.0056 270 1.51
128 Mate Day 0.0008 313 0.25
155 Mason Day 0.33 180 59.40
9999 Scaffolding L. S. 0.91 1.00 0.91
9999 Hire and running charges of mechanical L. S. 0.52 1.00 0.52
mixer
9999 Sundries L. S. 0.26 1.00 0.26
9999 Cement concrete 1:2:4 filled in chase L. S. 9.88 1.00 9.88
cut
9999 Painting two coats of coaltar L. S. 0.91 1.00 0.91
Cem ent mortar 1:6 (1 cement: 6 fine cum 0.006 1898.04 11.39
sand) (Rate as per item no. 3.6)
TOTAL 243.39
Add 1% for water charges 2.43
TOTAL 245.82
Add 15 % for contractor’s profit and overheads 36.87
Cost of 1 no. 282.69
Say 282.69
14.2 Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting
masonry for holdfasts embedding hold fasts in cement concrete blocks with cement concrete 1:3:6 (1
cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) painting two coats of approved
wood preservative to sides of chowkhats and making good the damages to walls and floors as required
complete including disposal of rubbish to the dumping ground within 50 metres lead :

14.2.3 Clerestory window chowkhats


Code Description Unit Quantity Rate Amount
Details of cost for 1.00 No.
295 Stone aggregate 20 mm cum 0.007 1100.00 7.70
297 Stone aggregate 10 mm cum 0.0024 1050.00 2.52
2202 Carriage of aggregate below 20mm cum 0.0094 53.21 0.50
982 Coarse sand cum 0.0047 300.00 1.41
2261 Carriage of coarse sand cum 0.0047 53.21 0.25
367 Cement tonne 0.0022 5200.00 11.44
2209 Carriage of cement tonne 0.0022 47.29 0.10
Labour:
115 Coolie Day 0.0065 207 1.35
114 Beldar Day 0.509 207 105.36
123 Mason ist class Day 0.0006 270 0.16
124 Mason 2nd class Day 0.0006 223 0.13
130 Mistry Day 0.0028 270 0.76
128 Mate Day 0.0004 313 0.13
155 Mason Day 0.17 180 30.60
9999 Scaffolding L. S. 0.52 1.00 0.52
9999 Hire and running charges of mechanical L. S. 0.26 1.00 0.26
mixer
9999 Sundries L. S. 2.86 1.00 2.86
9999 Cement concrete 1:2:4 filled in chase L. S. 8.06 1.00 8.06
cut
9999 Painting two coats of coaltar L. S. 0.91 1.00 0.91
Cem ent mortar 1:6 (1 cement: 6 fine cum 0.003 1898.04 5.69
sand) (Rate as per item no. 3.6)
TOTAL 180.71
Add 1% for water charges 1.81
TOTAL 182.52
Add 15 % for contractor’s profit and overheads 27.38
Cost of 1 no. 209.90
Say 209.90

14.3 Fixing chowkhat in existing opening in brick / RCC wall with dash fasteners/chemical fastners of
appropriate size (3nos on each vertical member of door chowkhat and 2 nos. on each vertical
member and 1 no. on each horizontal member of window chowkhat) including Cost of dash
fasteners/ chemical fasteners.
Code Description Unit Quantity Rate Amount
Details of cost for 1 chowkhat
Labour:
115 Coolie Day 0.0195 207 4.04
114 Beldar Day 0.027 207 5.59
130 Mistry Day 0.0084 270 2.27
128 Mate Day 0.0012 313 0.38
9999 Disposal of mulba L. S. 1.82 1.00 1.82
9999 Hire charges of drill machine, L. S. 12.22 1.00 12.22
scaffolding and sundries
7019 Dash fastner/ chemical fastner each 6 8.00 48.00
TOTAL 74.31
Add 1% for water charges 0.74
TOTAL 75.05
Add 15 % for contractor’s profit and overheads 11.26
Cost of 1 no. 86.31
Say 86.31

14.4 Making the opening in brick masonry including dismantling in floor or walls by cutting masonry
and making good the damages to walls, flooring and jambs complete to match existing surface i/c
disposal of mulba/ rubbish to the nearest dumping ground.
14.4.1 For door/ window/ clerestory window.
Code Description Unit Quantity Rate Amount
Details of cost for 1 opening of size 0.90 X 2.10=1.89 sqm .
Labour:
115 Coolie Day 0.4 207 82.80
114 Beldar Day 1.2 207 248.40
124 Mason 2nd class Day 0.5 223 111.50
9999 Scaffolding & Sundries L. S. 3.5 1.00 3.50
9999 Cement concrete 1:2:4 filled in chase L. S. 24.57 1.00 24.57
cut
Cem ent mortar 1:6 (1 cement: 6 fine cum 0.01 1898.04 18.98
sand) (Rate as per item no. 3.6)
TOTAL 489.75
Add 1% for water charges 4.90
TOTAL 494.65
Add 15 % for contractor’s profit and overheads 74.20
Cost of 1.89 sqm 568.85
Cost of 1 sqm 300.98
Say 300.98

14.5 Renewing glass panes, with putty and nails wherever necessary:
14.5.1 Float glass panes of thickness 4 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 glasses area each 0.10 Sqm.
MATERIALS
2406 Glass panes sqm 1.1 248.00 272.80
9999 Carriage including sundries L. S. 1.82 1.00 1.82
863 Putty for wood work kilogram 0.68 24.00 16.32
9999 Painting or varnishing or beewaxing L. S. 5.33 1.00 5.33
9999 Sundries Nails etc. L. S. 6.76 1.00 6.76
Labour:
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.23 207 47.61
9999 Sundries such as Rag, cotton etc L. S. 1.43 1.00 1.43
TOTAL 393.47
Add 1% for water charges 3.93
TOTAL 397.40
Add 15 % for contractor’s profit and overheads 59.61
Cost of 1 sqm 457.02
Say 457.02

14.5 Renewing glass panes, with putty and nails wherever necessary:
14.5.2 Float glass panes of thickness 5.5 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 glasses area each 0.10 Sqm.
MATERIALS
2407 Glass panes sqm 1.1 340.00 374.00
9999 Carriage including sundries L. S. 1.82 1.00 1.82
863 Putty for wood work kilogram 0.68 24.00 16.32
9999 Painting or varnishing or beewaxing L. S. 5.33 1.00 5.33
9999 Sundries Nails etc. L. S. 6.76 1.00 6.76
Labour:
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.23 207 47.61
9999 Sundries such as Rag, cotton etc L. S. 1.43 1.00 1.43
TOTAL 494.67
Add 1% for water charges 4.95
TOTAL 499.62
Add 15 % for contractor’s profit and overheads 74.94
Cost of 1 sqm 574.56
Say 574.56

14.6 Renewing glass panes, with wooden fillets wherever necessary:


14.6.1 Float glass panes of thickness 4 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 glasses area each 0.10 Sqm.
MATERIALS
2406 Glass panes sqm 1.1 248.00 272.80
1189 Second class teak wood in scantling 10 cudm 0.25 394.00 9.85
1194 Second class deodar wood in planks 10 cudm 0.25 335.00 8.38
1196 First class kail wood in planks 10 cudm 0.25 186.00 4.65
9999 Painting or varnishing or beewaxing L. S. 4.42 1.00 4.42
9999 Sundries Nails etc. L. S. 2.73 1.00 2.73
Labour:
0112 Carpenter 2nd class Day 0.2 223 44.60
119 Glazier Day 0.25 180 45.00
114 Beldar Day 0.45 207 93.15
9999 Sundries such as Rag, cotton etc L. S. 1.82 1.00 1.82
TOTAL 487.40
Add 1% for water charges 4.87
TOTAL 492.27
Add 15 % for contractor’s profit and overheads 73.84
Cost of 1 sqm 566.11
Say 566.11

14.6 Renewing glass panes, with wooden fillets wherever necessary:


14.6.2 Float glass panes of thickness 5.5 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 glasses area each 0.10 Sqm.
MATERIALS
2407 Glass panes sqm 1.1 340.00 374.00
1189 Second class teak wood in scantling 10 cudm 0.25 394.00 9.85
1194 Second class deodar wood in planks 10 cudm 0.25 335.00 8.38
1196 First class kail wood in planks 10 cudm 0.25 186.00 4.65
9999 Painting or varnishing or beewaxing L. S. 4.42 1.00 4.42
9999 Sundries Nails etc. L. S. 2.73 1.00 2.73
Labour:
0112 Carpenter 2nd class Day 0.2 223 44.60
119 Glazier Day 0.25 180 45.00
114 Beldar Day 0.45 207 93.15
9999 Sundries such as Rag, cotton etc L. S. 1.82 1.00 1.82
TOTAL 588.60
Add 1% for water charges 5.89
TOTAL 594.48
Add 15 % for contractor’s profit and overheads 89.17
Cost of 1 sqm 683.65
Say 683.65
14.7 Renewing glass panes and refixing existing wooden fillets:
14.7.1 Float glass panes of thickness 4 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 glasses area each 0.10 Sqm.
MATERIALS
2406 Glass panes sqm 1.1 248.00 272.80
9999 Carriage of glasspanes and other L. S. 2.73 1.00 2.73
materials
9999 Methylated spirit L. S. 5.33 1.00 5.33
9999 Sundries Nails etc. L. S. 9.88 1.00 9.88
Labour:
119 Glazier Day 0.3 180 54.00
114 Beldar Day 0.3 207 62.10
9999 Sundries such as Rag, cotton etc L. S. 1.43 1.00 1.43
TOTAL 408.27
Add 1% for water charges 4.08
TOTAL 412.35
Add 15 % for contractor’s profit and overheads 61.85
Cost of 1 sqm 474.21
Say 474.21

14.7 Renewing glass panes and refixing existing wooden fillets:


14.7.2 Float glass panes of thickness 5.5 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 glasses area each 0.10 Sqm.
MATERIALS
2407 Glass panes sqm 1.1 340.00 374.00
9999 Carriage of glasspanes and other L. S. 2.73 1.00 2.73
materials
9999 Methylated spirit L. S. 5.33 1.00 5.33
9999 Sundries Nails etc. L. S. 9.88 1.00 9.88
Labour:
119 Glazier Day 0.3 180 54.00
114 Beldar Day 0.3 207 62.10
9999 Sundries such as Rag, cotton etc L. S. 1.43 1.00 1.43
TOTAL 509.47
Add 1% for water charges 5.09
TOTAL 514.56
Add 15 % for contractor’s profit and overheads 77.18
Cost of 1 sqm 591.75
Say 591.75

14.8 Supplying and fixing new wooden fillets wherever necessary:


14.8.1 2nd class teak wood fillets
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 metres length
MATERIALS
1190 2nd class teak wood in planks 10 cudm 1.15 410.00 47.15
9999 Sundries Nails etc. L. S. 26.91 1.00 26.91
Labour:
0112 Carpenter 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
9999 Sundries such as Rag, cotton etc L. S. 2.73 1.00 2.73
TOTAL 184.29
Add 1% for water charges 1.84
TOTAL 186.13
Add 15 % for contractor’s profit and overheads 27.92
Cost of 10 metres 214.05
Cost of 1 metre 21.41
Say 21.41

14.8 Supplying and fixing new wooden fillets wherever necessary:


14.8.2 Hollock wood fillets.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 metres length
MATERIALS
2466 Hollock wood in scantling 10 cudm 1.15 217.00 24.96
9999 Sundries Nails etc. L. S. 26.91 1.00 26.91
Labour:
0112 Carpenter 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
9999 Sundries such as Rag, cotton etc L. S. 2.73 1.00 2.73
TOTAL 162.10
Add 1% for water charges 1.62
TOTAL 163.72
Add 15 % for contractor’s profit and overheads 24.56
Cost of 10 metres 188.27
Cost of 1 metre 18.83
Say 18.83

14.9 Renewal of old putty of glass panes (length)


Code Description Unit Quantity Rate Amount
Details of cost for 13.00 metres length
MATERIALS
863 Putty for wood work kilogram 0.68 24.00 16.32
9999 Sundries Nails etc. L. S. 7.15 1.00 7.15
9999 Spirit L. S. 2.73 1.00 2.73
Labour:
0112 Carpenter 2nd class Day 0.3 223 66.90
114 Beldar Day 0.3 207 62.10
9999 Sundries such as Rag, cotton etc L. S. 1.43 1.00 1.43
TOTAL 156.63
Add 1% for water charges 1.57
TOTAL 158.20
Add 15 % for contractor’s profit and overheads 23.73
Cost of 13 metres 181.93
Cost of 1 metre 13.99
Say 13.99

14.10 Refixing old glass panes with putty and nails


Code Description Unit Quantity Rate Amount
Details of cost for 10 glasses area each 0.10 sqm.
MATERIALS
863 Putty for wood work kilogram 0.68 24.00 16.32
9999 Sundries Nails etc. L. S. 7.15 1.00 7.15
9999 Spirit L. S. 2.73 1.00 2.73
Labour:
119 Glazier Day 0.3 180 54.00
114 Beldar Day 0.3 207 62.10
9999 Sundries such as Rag, cotton etc L. S. 1.43 1.00 1.43
TOTAL 143.73
Add 1% for water charges 1.44
TOTAL 145.17
Add 15 % for contractor’s profit and overheads 21.78
Cost of 1 sqm 166.94
Say 166.94

14.11 Fixing old glass panes with wooden fillets (excluding cost of fillets)
Code Description Unit Quantity Rate Amount
Details of cost for 1.00 sqm
LABOUR
119 Glazier Day 0.3 180 54.00
114 Beldar Day 0.3 207 62.10
9999 Sundries Nails etc. L. S. 3.9 1.00 3.90
9999 Sundries L. S. 1.43 1.00 1.43
TOTAL 121.43
Add 1% for water charges 1.21
TOTAL 122.64
Add 15 % for contractor’s profit and overheads 18.40
Cost of 1 sqm 141.04
Say 141.04

14.12 Providing and fixing 16 mm M.S. Fan clamps of standard shape and size in existing R.C.C. slab
including cutting chase and making good and painting exposed portion of the clamps complete.
Code Description Unit Quantity Rate Amount
Details of cost for each fan clamp.
MATERIALS
1003 M.S.bar 16mm dia quintal 0.00632 4300.00 27.18
9999 Cement concrete 1:2:4 (1 Cement: 2 L. S. 13.52 1.00 13.52
Coarse sand : 4 graded stone aggregate
20mm nominal size) mortar for rendering
or plastering

9999 Painting two or more coats to exposed L. S. 7.15 1.00 7.15


portion of the clamp including priming
coat

Labour for fixing


102 Blacksmith 1st class Day 0.03 270 8.10
124 Mason 2nd class Day 0.12 223 26.76
114 Beldar Day 0.25 207 51.75
9999 Sundries L. S. 2.73 1.00 2.73
TOTAL 137.19
Add 1% for water charges 1.37
TOTAL 138.56
Add 15 % for contractor’s profit and overheads 20.78
Cost of 1 sqm 159.34
Say 159.34

14.13 Regrading terracing of mud phaska covered with tiles or brick, in cement by dismantling
tiles or bricks, removing mud plaster preparing the surface of mud phaska to proper slope relaying m ud
plaster gobri leaping and tiles or bricks, grouted in cement mortar 1:3 (1 cement : 3 fine sand) including
replacing unserviceable tiles or bricks with new ones and disposal of unservice able material to the
dumping ground (the cost of the new tiles or brick excluded) within 50 metres lead.

Code Description Unit Quantity Rate Amount


Details of cost for 10.00 sqm
(i) Dismantling tiles/bricks in cement mortar including removing mud plaster and cleaning the
tiles/bricks
LABOUR

155 Mason Day 0.54 180 97.20


114 Beldar Day 0.54 207 111.78
(ii) Preparing the surface, for mud phuska to proper slope, relaying mud plaster gobri leeping.
155 Mason Day 0.27 180 48.60
25mm thick mud plaster including gobri leaping
MATERIALS
Mud mortar (Rate as per item No 3.18 ) cum 0.24 215.16 51.64

308 Bhusa quintal 0.084 200.00 16.80


2131 Gobri mortar cum 0.12 215.16 25.82
LABOUR
114 Beldar Day 0.25 207 51.75
(iii) relay ing tiles/bricks including cum 0.061 3268.90 199.40
Cement mortar 1:3 (1 Cement: 3 fine
sand) for grouting (Rate as per item No.
3.3

155 Mason Day 1.2 180 216.00


114 Beldar Day 1.5 207 310.50
101 Bhishti Day 1 180 180.00
9999 Disposal of mulba L. S. 5.33 1.00 5.33
9999 Sundries L. S. 2.73 1.00 2.73
TOTAL 1317.55
Add 1% for water charges 13.18
TOTAL 1330.73
Add 15 % for contractor’s profit and overheads 199.61
Cost of 10 sqm 1530.33
Cost of 1 sqm 153.03
Say 153.03

14.14 Replacing sand stone slabs in roofing laid in cement mortar 1:4 (1 cement: 4 coarse sand)
including necessary repairs and cement pointing with same mortar complete including disposal of
rubbish to dumping ground within 50 metres of lead:
14.14.1 Red/ white sand stone slabs 30 to 50 mm thick.
Details of cost for 10.00 sqm
Code Description Unit Quantity Rate Amount
1,174 Red sand stone slab 45 mm and 50 sqm 11 430.00 4730.00
mm thick (un-dressed)
2,216 Carriage of Stone slabs cum 1.41 47.29 66.68
Details of cost for 10.00 sqm
114 Beldar Day 0.885 207 183.20
115 Coolie Day 2.065 207 427.46
Cement mortar, 1:4(1 cement: 4 coarse cum 0.0105 2580.18 27.09
sand) (Rate as per item No. 3.9 of SH -
Mortar)
Cement mortar 1:3 (1 Cement: 3 fine cum 0.0075 3268.90 24.52
sand) for grouting (Rate as per item No.
3.3 of SH- Mortar)
155 Mason Day 1.69 180 304.20
100 Bandhani Day 2.03 180 365.40
101 Bhishti Day 0.34 180 61.20
9999 Cleaning the surface including L. S. 40.43 1.00 40.43
necessary repairs
2,264 Carriage of rubbish cum 0.5 53.21 26.61
9999 Sundries L. S. 20.15 1.00 20.15
TOTAL 6276.92
Add 1% for water charges 62.77
TOTAL 6339.69
Add 15 % for contractor’s profit and 950.95
overheads
Cost of 10 sqm 7290.65
Cost of 1 sqm 729.06
Say 729.06

14.15 Renewing wooden battens in roofs, including making good the holes in wall and painting with
oil type wood preservative of approved brand and manufacture complete including removal of
rubbish to the dumping ground within 50 metres lead:
14.15.1 Sal wood battens.
Code Description Unit Quantity Rate Amount
Details of cost for 10 battens i.e. 300 cudm 3 metres long of 100x100mm
MATERIALS
1199 Sal wood battens 10 cudm 306 218.00 6670.80
2204 Carriage of battens cum 0.306 60.81 18.61
859 Oil type wood preservative litre 1.22 60.00 73.20
LABOUR
Taking out the existing battens and refixing new one including supporting the roof
112 Carpenter 2nd class Day 0.5 223 111.50
114 Beldar Day 2 207 414.00
115 Coolie Day 0.183 207 37.88
131 Painter Day 0.183 180 32.94
9999 Disposal of mulba L. S. 5.33 1.00 5.33
9999 Making good the holes including L. S. 80.73 1.00 80.73
sundries
9999 Carriage L. S. 0.78 1.00 0.78
9999 Brushes L. S. 5.07 1.00 5.07
9999 Sundries L. S. 4.81 1.00 4.81
TOTAL 7455.65
Add 1% for water charges 74.56
TOTAL 7530.21
Add 15 % for contractor’s profit and 1129.53
overheads
Cost of 300 cudm 8659.74
Cost of 1 cum 28865.79
Say 28,865.79

14.16 Renewing wooden beams in roofs including making good the holes in walls and painting with
oil type wood preservative of approved brand and manufacture complete including removal of
rubbish to the dumping ground within 50 metres lead :
14.16.1 Not exceeding 4.00 metres in length.
14.16.1.1 Sal wood beams
Code Description Unit Quantity Rate Amount
Details of cost for 1 beam i.e. 300 cudm
MATERIALS
1199 Sal wood battens 10 cudm 3.125 218.00 68.13
2204 Carriage of battens cum 0.0228 60.81 1.39
LABOUR
112 Carpenter 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
Taking out the existing beams etc.
155 Mason Day 0.13 180 23.40
114 Beldar Day 0.33 207 68.31
100 Bandhani Day 0.5 180 90.00
Renewal
1199 Sal wood battens 10 cudm 306 218.00 6670.80
2204 Carriage of battens cum 0.306 60.81 18.61
859 Oil type wood preservative litre 0.455 60.00 27.30
112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 1 207 207.00
100 Bandhani Day 0.5 180 90.00
115 Coolie Day 0.07 207 14.49
131 Painter Day 0.07 180 12.60
302 Safeda ballies 125 mm diameter metre 2.5 52.00 130.00
9999 Making good the holes including L. S. 47.58 1.00 47.58
sundries
9999 Carriage L. S. 1.82 1.00 1.82
9999 Brushes L. S. 1.82 1.00 1.82
9999 Sundries L. S. 0.13 1.00 0.13
TOTAL 7803.87
Add 1% for water charges 78.04
TOTAL 7881.91
Add 15 % for contractor’s profit and 1182.29
overheads
Cost of 300 cudm 9064.19
Cost of 1 cum 30213.98
Say 30,213.98

14.16 Renewing wooden beams in roofs including making good the holes in walls and painting with
oil type wood preservative of approved brand and manufacture complete including removal of
rubbish to the dumping ground within 50 metres lead :
14.16.1 Not exceeding 4.00 metres in length.
14.16.1.2 Hollock wood beams
Code Description Unit Quantity Rate Amount
Details of cost for 1 beam i.e. 300 cudm
MATERIALS
2,466 Hollock wood in scantling 10 cudm 3.125 217.00 67.81
2204 Carriage of battens cum 0.0228 60.81 1.39
LABOUR
112 Carpenter 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
Taking out the existing beams etc.
155 Mason Day 0.13 180 23.40
114 Beldar Day 0.33 207 68.31
100 Bandhani Day 0.5 180 90.00
Renewal
2,466 Hollock wood in scantling 10 cudm 306 217.00 6640.20
2204 Carriage of battens cum 0.306 60.81 18.61
859 Oil type wood preservative litre 0.455 60.00 27.30
112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 1 207 207.00
100 Bandhani Day 0.5 180 90.00
115 Coolie Day 0.07 207 14.49
131 Painter Day 0.07 180 12.60
302 Safeda ballies 125 mm diameter metre 2.5 52.00 130.00
9999 Making good the holes including L. S. 47.58 1.00 47.58
sundries
9999 Carriage L. S. 1.82 1.00 1.82
9999 Brushes L. S. 1.82 1.00 1.82
9999 Sundries L. S. 0.13 1.00 0.13
TOTAL 7772.96
Add 1% for water charges 77.73
TOTAL 7850.69
Add 15 % for contractor’s profit and 1177.60
overheads
Cost of 300 cudm 9028.29
Cost of 1 cum 30094.30
Say 30,094.30

14.16 Renewing wooden beams in roofs including making good the holes in walls and painting with
oil type wood preservative of approved brand and manufacture complete including removal of
rubbish to the dumping ground within 50 metres lead :
14.16.2 Above 4.00 metres and upto 5.00 metres length.
14.16.2.1 Sal wood beams
Code Description Unit Quantity Rate Amount
Details of cost for 1 beam i.e. 375 cudm
MATERIALS
1,199 Sal wood in scantling 10 cudm 3.75 218.00 81.75
2204 Carriage of battens cum 0.0498 60.81 3.03
LABOUR
112 Carpenter 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
Taking out the existing beams etc.
155 Mason Day 0.25 180 45.00
114 Beldar Day 0.5 207 103.50
100 Bandhani Day 0.63 180 113.40
Renewal
1,199 Sal wood in scantling 10 cudm 383 218.00 8349.40
2204 Carriage of battens cum 0.383 60.81 23.29
859 Oil type wood preservative litre 0.565 60.00 33.90
112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 2 207 414.00
100 Bandhani Day 1 180 180.00
115 Coolie Day 0.08 207 16.56
131 Painter Day 0.08 180 14.40
302 Safeda ballies 125 mm diameter metre 3.75 52.00 195.00
9999 Making good the holes including L. S. 53.82 1.00 53.82
sundries
9999 Carriage L. S. 2.34 1.00 2.34
9999 Brushes L. S. 2.21 1.00 2.21
9999 Sundries L. S. 0.26 1.00 0.26
TOTAL 9962.36
Add 1% for water charges 99.62
TOTAL 10061.98
Add 15 % for contractor’s profit and 1509.30
overheads
Cost of 375 cudm 11571.28
Cost of 1 cum 30856.75
Say 30,856.75

14.16 Renewing wooden beams in roofs including making good the holes in walls and painting with
oil type wood preservative of approved brand and manufacture complete including removal of
rubbish to the dumping ground within 50 metres lead :
14.16.2 Above 4.00 metres and upto 5.00 metres length.
14.16.2.2 Hollock wood beams
Code Description Unit Quantity Rate Amount
Details of cost for 1 beam i.e. 375 cudm
MATERIALS
2,466 Hollock wood in scantling 10 cudm 3.75 217.00 81.38
2204 Carriage of battens cum 0.0375 60.81 2.28
LABOUR
112 Carpenter 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
Taking out the existing beams etc.
155 Mason Day 0.25 180 45.00
114 Beldar Day 0.5 207 103.50
100 Bandhani Day 0.63 180 113.40
Renewal
2,466 Hollock wood in scantling 10 cudm 383 217.00 8311.10
2204 Carriage of battens cum 0.383 60.81 23.29
859 Oil type wood preservative litre 0.565 60.00 33.90
112 Carpenter 2nd class Day 1 223 223.00
114 Beldar Day 2 207 414.00
100 Bandhani Day 1 180 180.00
115 Coolie Day 0.08 207 16.56
131 Painter Day 0.08 180 14.40
302 Safeda ballies 125 mm diameter metre 3.75 52.00 195.00
9999 Making good the holes including L. S. 53.82 1.00 53.82
sundries
9999 Carriage L. S. 2.34 1.00 2.34
9999 Brushes L. S. 2.21 1.00 2.21
9999 Sundries L. S. 0.26 1.00 0.26
TOTAL 9922.94
Add 1% for water charges 99.23
TOTAL 10022.16
Add 15 % for contractor’s profit and 1503.32
overheads
Cost of 375 cudm 11525.49
Cost of 1 cum 30734.64
Say 30,734.64

14.17 Raking out joints in lime or cement mortar and preparing the surface for re-pointing or
replastering including disposal of rubbish to the dumping ground within 50 metres lead.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
LABOUR
114 Beldar Day 0.53 207 109.71
115 Coolie Day 0.08 207 16.56
101 Bhishti Day 0.07 180 12.60
9999 Sundries L. S. 1.43 1.00 1.43
TOTAL 140.30
Add 1% for water charges 1.40
TOTAL 141.70
Add 15 % for contractor’s profit and 21.26
overheads
Cost of 10 sqm 162.96
Cost of 1 sqm 16.30
Say 16.30

14.18 Flush pointing with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water
proofing compound by weight of cement for flat tile bricks on top of mud phaska :
14.18.1 With F.P.S. brick tiles
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIALS
1,213 Water proofing materials kilogram 0.153 20.00 3.06
Cement mortar 1:3 (1 Cement: 3 fine cum 0.015 3268.90 49.03
sand) for grouting (Rate as per item No.
3.3 of SH- Mortar)
Labour
101 Bhishti Day 0.36 180 64.80
124 Mason 2nd class Day 0.36 223 80.28
115 Coolie Day 0.36 207 74.52
9999 Sundries L. S. 18.85 1.00 18.85
TOTAL 290.54
Add 1% for water charges 2.91
TOTAL 293.45
Add 15 % for contractor’s profit and 44.02
overheads
Cost of 10 sqm 337.47
Cost of 1 sqm 33.75
Say 33.75

14.18 Flush pointing with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% of integral water
proofing compound by weight of cement for flat tile bricks on top of mud phaska :
14.18.2 With modular brick tiles
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIALS
1,213 Water proofing materials kilogram 0.173 20.00 3.46
Cement mortar 1:3 (1 Cement: 3 fine cum 0.017 3268.90 55.57
sand) for grouting (Rate as per item No.
3.3 of SH- Mortar)
Labour
101 Bhishti Day 0.36 180 64.80
124 Mason 2nd class Day 0.36 223 80.28
115 Coolie Day 0.36 207 74.52
9999 Sundries L. S. 18.85 1.00 18.85
TOTAL 297.48
Add 1% for water charges 2.97
TOTAL 300.46
Add 15 % for contractor’s profit and 45.07
overheads
Cost of 10 sqm 345.52
Cost of 1 sqm 34.55
Say 34.55

14.19 Taking out wind ties from roof including cutting out rusted bolts, nuts etc. and removing
materials to any distance within compound and stacking.
Code Description Unit Quantity Rate Amount
Detail of cost for 30 mtrs = 63 kg
LABOUR
100 Bandhani Day 0.06 180 10.80
103 Blacksmith 2nd class Day 0.09 223 20.07
114 Beldar Day 0.16 207 33.12
TOTAL 63.99
Add 1% for water charges 0.64
TOTAL 64.63
Add 15 % for contractor’s profit and 9.69
overheads
Cost of 63 kg 74.32
Cost of 1 kg 1.18
Say 1.18
14.20 Fixing of old wind tie with new fittings including painting two or more coats with anticorrosive
bitumastic paint of approved brand & manufacturer over and including priming coat of ready mixed
zinc chromate yellow primer of approved brand.
Code Description Unit Quantity Rate Amount
Detail of cost for 20.2 m wind tie
MATERIALS
1023 G.I. - J or L hooks with nuts and bolts 8 10 Nos 68 60.00 408.00
1208 mm
Bitumen washer 100 Nos 68 18.00 12.24
1209 G.I. Washer (thick) 100 Nos 68 27.00 18.36
9999 Carriage of bolts, nuts and washers etc. L. S. 1.17 1.00 1.17
LABOUR
102 Blacksmith 1st class Day 0.34 270 91.80
114 Beldar Day 0.34 207 70.38
9,999 Sundries L.S. 13.91 1.00 13.91
Applying priming coat with ready sqm 1.86
mixed zink chromate yellow primer
(Rate as per item no 13.50.3 of SH
Finishing)
15.74 29.28
Painting with ready mixed black anti sqm 1.86 31.73 59.02
TOTAL corrosive bitumastic paint (‘R ate as per 704.16
item no 13.65.1 of SH Finishing)
Add 1% for water charges except on A
6.16
TOTAL 710.32
Add for contractor’s profit and
overheads @15% except on A 93.30
Cost of 20.2 metre 803.62
Cost of 1 metre 39.78
Say 39.78

14.21 Renewing bottom rail and/or top rubber of collapsible gate including making good all damages
and applying priming coat of zinc chromate yellow primer of approved brand and manufacturer.
Code Description Unit Quantity Rate Amount
Detail of cost for gate of size 1.52x2.4 m (weight 11.55 kg)
MATERIALS
1007 Structural steel such as tees, angles quintal 0.13 4600.00 598.00
channels and R.S. joists
2205 Carriage of Tee tonne 0.013 47.29 0.61
A Taking out collapsible gate including each 1 115.08 115.08
frame (Rate as per item no 15.12.2 of SH
Dismantling and Demolishing)
Refixing of collapsible gate including mending good the demaged floor, wall etc.frame
A Cement concrete 1:3:6 (1 cement: 3 cum 0.03 3,828.42 114.85
coarse sand : 6 graded stone aggregate 20
mm nominal size) (Rate as per item no
4.2.5 of SH concrete work)

Cem ent mortar, 1:6 (1 cement: 6 fine cum 0.01 1898.04 18.98
sand) (Rate as per item No. 3.6 of SH-
mortar)
9,999 Cement concrete 1:2:4 filled in chase L.S. 24.18
cut 1.00 24.18
9,999 Disposal of mulba L.S. 1.82 1.00 1.82
A Priming coat on Tees (Rate as per item sqm 0.53 15.74
no 13.50 of SH Finishing) 8.34
Labour for fixing the gate
155 Mason Day 0.5 180 90.00
114 Beldar Day 0.75 207 155.25
9999 Sundries L.S 2.6 1.00 2.60
TOTAL 1129.72
Add 1% for water charges except on A
8.91
TOTAL 1138.64
Add for contractor’s profit and 135.05
overheads @15%
Cost of 11.55 kg except on A 1273.69
Cost of 1 kg 110.28
Say 110.28

14.22 Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the
same with necessary clamps, nuts and bolts/welding and erection etc. complete.
14.22.1 Wheel 50 mm dia. and below.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 wheels of 40 mm dia.
Labour for dismantling:
103 Blacksmith 2nd class Day 0.01 223 2.23
100 Bandhani Day 0.01 180 1.80
114 Beldar Day 0.02 207 4.14
9999 Sundries L.S 0.39 1.00 0.39
Renewing the wheels with clamps :-
MATERIALS
7442 10 nos wheels 40 mm dia. 40 mm wide each 10 52.00 520.00
1008 M.S. flat quintal 0.035 4600.00 161.00
1034 M.S. bolt/pin 10 mm dia 10 cm long 10 quintal 0.006
nos 7000.00 42.00
1215 Welding charges (electrical) cm 80 1.00 80.00
Labour for cutting, assembling and errection charges;
102 Blacksmith 1st class Day 0.03 270 8.10
100 Bandhani Day 0.02 180 3.60
114 Beldar Day 0.11 207 22.77
9999 Sundries L.S 1.69 1.00 1.69
Priming coat: (Rate as per item no sqm 0.165 15.74 2.60
13.50.3 of SH Finishing)
TOTAL 850.32
Add 1% for water charges except on A
8.48
TOTAL 858.79
Add for contractor’s profit and
overheads @15% except on A 128.43
Cost of 10 wheels 987.22
Cost of 1 wheel 98.72
Say 98.72

14.22 Renewing Wrought iron or M.S. Wheel or roller of steel door or gate and fitting and fixing the
same with necessary clamps, nuts and bolts/welding and erection etc. complete.
14.22.2 Wheel above 50 mm dia.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 wheels of 50 mm dia.
Labour for dismantling:
103 Blacksmith 2nd class Day 0.04 223 8.92
100 Bandhani Day 0.03 180 5.40
114 Beldar Day 0.06 207 12.42
9999 Sundries L.S 1.04 1.00 1.04
Renewing the wheels with clamps :-
MATERIALS
7442 10 nos wheels 40 mm dia. 40 mm wide each 10 52.00 520.00
1008 M.S. flat quintal 0.1 4600.00 460.00
1034 M.S. bolt/pin 10 mm dia 10 cm long 10 quintal 0.016
nos 7000.00 112.00
1215 Welding charges (electrical) cm 120 1.00 120.00
Labour for cutting, assembling and errection charges;
102 Blacksmith 1st class Day 0.1 270 27.00
100 Bandhani Day 0.05 180 9.00
114 Beldar Day 0.36 207 74.52
9999 Sundries L.S 5.33 1.00 5.33
Priming coat: (Rate as per item no sqm 0.34 15.74 5.35
13.50.3 of SH Finishing)
TOTAL 1360.98
Add 1% for water charges except on A
13.56
TOTAL 1374.54
Add for contractor’s profit and
overheads @15% except on A 205.38
Cost of 10 wheels 1579.92
Cost of 1 wheel 157.99
Say 157.99

14.23 Pumping out water caused by springs, tidal or river seepage, broken water mains or drains and
the like.
Code Description Unit Quantity Rate Amount
Details for 10.91 Kiloletre
Pumping hours 3 hrs. or 0.375 days
11 Cost of pumping water with 4000 Iitres h per Day 0.375 200 75.00
114 Beldar for clearing slush Day 2 207 414.00
TOTAL 489.00
Add 1% for water charges 4.89
TOTAL 493.89
Add for contractor’s profit and
overheads @15% 74.08
Cost of 10.91 kilo litre 567.97
Cost of 1.0 kilo litre 52.06
Say 52.06

14.24 Mud mortar


Code Description Unit Quantity Rate Amount
Detail of cost for one cum
MATERIALS
811 Mud (dry) cum 1.08 20.00 21.60
LABOUR
114 Beldar Day 0.63 207 130.41
101 Bhishti Day 0.315 180 56.70
9,999 Sundries L.S. 6.45 1.00 6.45
TOTAL Cost of 1 cum 215.16
Say 215.16

14.25 Brick work with bricks of class designation 75 in mud mortar


Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
2602 Bricks of class designation 75 1000 nos 494 1600.00 790.40
2131 Mud mortar cum 0.25 215.16 53.79
2201 Carriage of bricks 1000 nos 494 141.88 70.09
9,999 Sundries L.S. 2.73 1.00 2.73
LABOUR:
115 Coolie Day 1.37 207 283.59
101 Bhishti Day 0.2 180 36.00
123 Mason ist class Day 0.36 270 97.20
124 Mason 2nd class Day 0.36 223 80.28
TOTAL 1414.08
Add 1% for water charges 14.14
TOTAL 1428.22
Add 15 % for contractor’s profit and 214.23
overheads
Cost of 1 cum 1642.45
Say 1,642.45

14.26 Providing and fixing 25 mm thick shutters for cup board etc. :
14.26.1 Panelled or panelled & glazed shutters:
14.26.1.1 Superior class teak wood including nickel plated bright finished M.S. piano hinges with
necessary screws.
Code Description Unit Quantity Rate Amount
Details of cost for shutter of cup-board 200xl08cm = 2.16 sqm.
Materials:
Beading-
1186 Superior class teak wood 10 cudm 40 895.00 3580.00
2204 Carriage of timber cum 0.04 60.81 2.43
2406 Glasses 10kg/sqm 4m m thick sqm 0.99 248.00 245.52
Fittings-
608 Nickle plated bright finished M.S. metre 4
Piano hinges 21.00 84.00
639 Screws 25 mm 100 Nos 120 15.00 18.00
Labour:
0111 Carpenter 1st class Day 2.4 270 648.00
119 Glazier Day 0.18 180 32.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries L.S. 40.43 1.00 40.43
TOTAL 4810.17
Add 1% for water charges 48.10
TOTAL 4858.27
Add for contractor’s profit and
overheads @15% 728.74
Cost of 2.16 sqm. 5587.02
Cost of 1 sqm 2586.58
Say 2586.58

14.26 Providing and fixing 25 mm thick shutters for cup board etc.:
14.26.1 Panelled or panelled & glazed shutters :
14.26.1.2 1st class teak wood including nickel plated bright finished M.S piano hinges with necessary
screws.
Code Description Unit Quantity Rate Amount
Details of cost for shutters of a cup-board (half glazed and half panelled) 200xl08cm = 2.16 sqm
Materials:
Beading-
1188 First class teak wood in planks 10 cudm 40 506.00 2024.00
2204 Carriage of timber cum 0.04 60.81 2.43
2406 Glasses 10kg/sqm 4m m thick sqm 0.99 248.00 245.52
Fittings-
608 Nickle plated bright finished M.S. metre 4
Piano hinges 21.00 84.00
639 Screws 25 mm 100 Nos 120 15.00 18.00
Labour:
0111 Carpenter 1st class Day 2.4 270 648.00
119 Glazier Day 0.18 180 32.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries L.S. 40.43 1.00 40.43
TOTAL 3254.17
Add 1% for water charges 32.54
TOTAL 3286.71
Add for contractor’s profit and
overheads @15% 493.01
Cost of 2.16 sqm. 3779.72
Cost of 1 sqm 1749.87
Say 1749.87

14.26 Providing and fixing 25 mm thick shutters for cup board etc. :
14.26.2 Glazed shutters:
14.26.2.1 Superior class teak wood including nickel plated bright finished MS. piano hinges with
necessary screws.
Code Description Unit Quantity Rate Amount
Details of cost for shutter of cup-board 200xl08cm = 2.16 sqm.
Materials:
Beading-
1186 Superior class teak wood 10 cudm 43 895.00 3848.50
2204 Carriage of timber cum 0.043 60.81 2.61
2406 Glasses 10kg/sqm 4m m thick sqm 1.27 248.00 314.96
Fittings-
608 Nickle plated bright finished M.S. metre 4
Piano hinges 21.00 84.00
639 Screws 25 mm 100 Nos 120 15.00 18.00
597 Bright finished or black enameled mild 10 Nos 2
steel butt hinges50x37x1.50 mm 28.00 5.60
640 Bright finished or black enameled mild 100 Nos 8
steel screws 20 mm 15.00 1.20
Labour:
156 * Carpenter (average) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries L.S. 40.43 1.00 40.43
TOTAL 4845.49
Add 1% for water charges 48.45
TOTAL 4893.95
Add for contractor’s profit and
overheads @15% 734.09
Cost of 2.16 sqm. 5628.04
Cost of 1 sqm 2605.58
Say 2605.58

14.26 Providing and fixing 25 mm thick shutters for cup board etc. :
14.26.2 Glazed shutters :
14.26.2.2 1st class teak wood including nickel plated bright finished M.S. piano hinges with necessary
screws.
Code Description Unit Quantity Rate Amount
Details of cost for shutter of cup-board 200xl08cm = 2.16 sqm.
Materials:
Beading-
1188 First class teak wood in planks 10 cudm 43 506.00 2175.80
2204 Carriage of timber cum 0.043 60.81 2.61
2406 Glasses 10kg/sqm 4m m thick sqm 1.27 248.00 314.96
Fittings-
608 Nickle plated bright finished M.S. metre 4
Piano hinges 21.00 84.00
639 Screws 25 mm 100 Nos 120 15.00 18.00
597 Bright finished or black enameled mild 10 Nos 2
steel butt hinges50x37x1.50 mm 28.00 5.60
640 Bright finished or black enameled mild 100 Nos 8
steel screws 20 mm 15.00 1.20
Labour:
156 * Carpenter (average) Day 1.83 180 329.40
119 Glazier Day 0.23 180 41.40
114 Beldar Day 0.77 207 159.39
9,999 Sundries L.S. 40.43 1.00 40.43
TOTAL 3172.79
Add 1% for water charges 31.73
TOTAL 3204.52
Add for contractor’s profit and
overheads @15% 480.68
Cost of 2.16 sqm. 3685.20
Cost of 1 sqm 1706.11
Say 1706.11

14.27 Providing and fixing plain jaffri door and window shutters including bright or/and black
enamelled M.S. butt hinges with necessary screws 35xl0mm laths placed 35mm apart (frames to be
paid separately) including fixing 50x12mm beading complete with
14.27.1 Second class teak wood.
Code Description Unit Quantity Rate Amount
Details of cost of a jaffri shutter 176x 86 cm =1.51 sqm
Materials:
Beading-
1190 Teak wood 2nd class 10 cudm 18 410.00 738.00
2204 Carriage of timber cum 0.018 60.81 1.09
Fittings-
595 Bright finished or black enameled mild 10 Nos 6
steel butt hinges 100x58x1.90 mm
54.00 32.40
597 Bright finished or black enameled mild 10 Nos 2
steel butt hinges50x37x1.50 mm 28.00 5.60
637 Bright finished or black enameled mild 100 Nos 48
steel screws 40 mm 30.00 14.40
640 Bright finished or black enameled mild 100 Nos 8
steel screws 20 mm 15.00 1.20
Labour:
0112 Carpenter 2nd class Day 0.3 223 66.90
A Plain Jaffri work (Rate as per item no. sqm 1.51
9.41) 1005.09 1517.69
TOTAL 2377.28
Add 1% for water charges except on A 8.60

TOTAL 2385.88
Add 15% for contractor’s profit and 130.23
overheads except on A
Cos t of 1.51 sqm 2516.11
Cost of 1.00 sqm 1666.30
Say 1666.30

14.28 Providing and fixing curtain rods of 1.25mm thick brass plates with two brass brackets fixed
with brass screws and wooden plugs etc. wherever necessary complete.
14.28.1 20 mm diameter.
Code Description Unit Quantity Rate Amount
Detail of cost for 2 m long
Materials
444 Brass curtain rod 20 mm dia metre 2 63.00 126.00
446 Brass bracket each 2 24.00 48.00
9999 Screws L.S 2.73 1.00 2.73
9999 Carriage L.S 1.56 1.00 1.56
A Wooden plugs including cutting brick each 2 11.81
work and fixing in cement mortar (Rate
as per item no 9.32) 23.61
9999 Labour L.S 2.73 1.00 2.73
9999 Sundries L.S 1.56 1.00 1.56
TOTAL 206.19
Add 1% for water charges except on A 1.83

TOTAL 208.02
Add 15% for contractor’s profit and 27.66
overheads except on A
Cos t of 2 metre 235.68
Cost of 1.00 metre 117.84
Say 117.84

14.28 Providing and fixing curtain rods of 1.25mm thick brass plates with two brass brackets fixed
with brass screws and wooden plugs etc. wherever necessary complete.
14.28.2 25 mm diameter.
Code Description Unit Quantity Rate Amount
Detail of cost for 2 m long
Materials
445 Brass curtain rod 25 mm dia metre 2 79.00 158.00
446 Brass bracket each 2 24.00 48.00
9999 Screws L.S 2.73 1.00 2.73
9999 Carriage L.S 1.56 1.00 1.56
A Wooden plugs including cutting brick each 2 11.81
work and fixing in cement mortar (Rate
as per item no 9.32) 23.61
9999 Labour L.S 2.73 1.00 2.73
9999 Sundries L.S 1.56 1.00 1.56
TOTAL 238.19
Add 1% for water charges except on A 2.15

TOTAL 240.34
Add 15% for contractor’s profit and 32.51
overheads except on A
Cos t of 2 metre 272.85
Cost of 1.00 metre 136.42
Say 136.42

14.29 Providing and fixing M.S. round or square bars with M.S. flats at required spcing in wooden
frames of windows and clerestory windows.
Code Description Unit Quantity Rate Amount
Details of cost for window -140x110cm
Materials:
1003 M.S. bars quintal 0.307 4300.00 1320.10
1008 Flats up to 10 mm in thickness quintal quintal 0.063 4600.00 289.80
2205 Carriage tonne 0.037 47.29 1.75
9999 Sundries L.S 26.91 1.00 26.91
Labour-
103 Blacksm ith 2nd class Day 0.35 223 78.05
112 Carpenter 2nd class Day 0.2 223 44.60
114 Beldar Day 0.45 207 93.15
TOTAL 1854.36
Add 1% for water charges 18.54
TOTAL 1872.90
Add 15% for contractor’s profit and 280.94
overheads
Cos t of 33.67 kg 2153.84
Cost of 1.00 kg 63.97
Say 63.97

14.30 Providing joists (karries) including hoisting fixing in position and applying wood preservative on
unexposed surface etc. complete with:
14.30.1 Sal wood.
Code Description Unit Quantity Rate Amount
Details of cost for 300cudm.
M aterials-
1199 Sal wood 10 cudm 306 218.00 6670.80
2204 Carriage of timber cum 0.306 60.81 18.61
Labour-
100 Bandhani Day 0.7 180 126.00
112 Carpenter 2nd class Day 0.7 223 156.10
114 Beldar Day 1.45 207 300.15
A Priming coat (Wood preservative) (Rate sqm 0.8 14.71 11.77
as per item no 13.57.1)
9999 Sundries L.S 26.91 1.00 26.91
TOTAL 7310.33
Add 1% for water charges except on A 72.99

TOTAL 7383.32
Add 15% for contractor’s profit and 1105.73
overheads except on A
Cos t of 300 cudm 8489.05
Cost of 1.00 cum 28296.84
Say 28296.84

14.30 Providing joists (karries) including hoisting fixing in position and applying wood preservative on
unexposed surface etc. complete with:
14.30.2 Hollock wood.
Code Description Unit Quantity Rate Amount
Details of cost for 300cudm.
M aterials-
2466 Hollock wood in scantling 10 cudm 306 217.00 6640.20
2204 Carriage of timber cum 0.306 60.81 18.61
Labour-
100 Bandhani Day 0.7 180 126.00
112 Carpenter 2nd class Day 0.7 223 156.10
114 Beldar Day 1.45 207 300.15
A Priming coat (Wood preservative) (Rate sqm 0.8 14.71 11.77
as per item no 13.57.1)
9999 Sundries L.S 26.91 1.00 26.91
TOTAL 7279.73
Add 1% for water charges except on A 72.68

TOTAL 7352.41
Add 15% for contractor’s profit and 1101.10
overheads except on A
Cos t of 300 cudm 8453.51
Cost of 1.00 cum 28178.37
Say 28178.37

14.31 Providing and fixing bright finished brass single acting spring hinges with necessary screws etc.
complete :
14.31.1 150 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
389 Brass spring hinges 150 mm each 10 200.00 2000.00
449 Brass screws 50 mm 100 Nos 80 107.00 85.60
9,999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
0111 Carpenter 1st class Day 0.4 270 108.00
114 Beldar Day 0.2 207 41.40
TOTAL 2238.64
Add 1% for water charges 22.39
TOTAL 2261.03
Add 15% for contractor’s profit and 339.15
overheads
Cos t of 10.00 hinges 2600.18
Cost of 1.00 hinge 260.02
Say 260.02

14.31 Providing and fixing bright finished brass single acting spring hinges with necessary screws etc.
complete :
14.31.2 125 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
390 Brass spring hinges 125 mm each 10 158.00 1580.00
449 Brass screws 50 mm 100 Nos 80 107.00 85.60
9,999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
0111 Carpenter 1st class Day 0.4 270 108.00
114 Beldar Day 0.2 207 41.40
TOTAL 1818.64
Add 1% for water charges 18.19
TOTAL 1836.83
Add 15% for contractor’s profit and 275.52
overheads
Cos t of 10.00 hinges 2112.35
Cost of 1.00 hinge 211.24
Say 211.24

14.31 Providing and fixing bright finished brass single acting spring hinges with necessary screws etc.
complete :
14.31.3: 100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
391 Brass spring hinges 100 mm each 10 106.00 1060.00
450 Brass screws 40 mm 100 Nos 80 96.00 76.80
9,999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
0111 Carpenter 1st class Day 0.4 270 108.00
114 Beldar Day 0.2 207 41.40
TOTAL 1289.84
Add 1% for water charges 12.90
TOTAL 1302.74
Add 15% for contractor’s profit and 195.41
overheads
Cos t of 10.00 hinges 1498.15
Cost of 1.00 hinge 149.81
Say 149.81

14.32: Providing and fixing bright finished brass double acting spring hinges with necessary screws etc.
complete
14.32.1: 150 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
392 Brass double acting spring hinges 150 each 10 317.00 3170.00
mm
449 Brass screws 50 mm 100 Nos 80 107.00 85.60
9,999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
0111 Carpenter 1st class Day 0.4 270 108.00
114 Beldar Day 0.2 207 41.40
TOTAL 3408.64
Add 1% for water charges 34.09
TOTAL 3442.73
Add 15% for contractor’s profit and 516.41
overheads
Cos t of 10.00 hinges 3959.14
Cost of 1.00 hinge 395.91
Say 395.91
14.32: Providing and fixing bright finished brass double acting spring hinges with necessary screws etc.
complete
14.32.2 :125 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
393 Brass double acting spring hinges 150 each 10 216.00 2160.00
mm
449 Brass screws 50 mm 100 Nos 80 107.00 85.60
9,999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
0111 Carpenter 1st class Day 0.4 270 108.00
114 Beldar Day 0.2 207 41.40
TOTAL 2398.64
Add 1% for water charges 23.99
TOTAL 2422.63
Add 15% for contractor’s profit and 363.39
overheads
Cos t of 10.00 hinges 2786.02
Cost of 1.00 hinge 278.60
Say 278.60

14.32: Providing and fixing bright finished brass double acting spring hinges with necessary screws etc.
complete
14.32.3 100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
394 Brass double acting spring hinges 100 each 10 173.00 1730.00
mm
450 Brass screws 40 mm 100 Nos 80 96.00 76.80
9,999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
0111 Carpenter 1st class Day 0.4 270 108.00
114 Beldar Day 0.2 207 41.40
TOTAL 1959.84
Add 1% for water charges 19.60
TOTAL 1979.44
Add 15% for contractor’s profit and 296.92
overheads
Cos t of 10.00 hinges 2276.35
Cost of 1.00 hinge 227.64
Say 227.64
14.33 : Providing and fixing bright finished brass flush bolts with necessary screws etc. complete :
14.33.1: 250 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
404 Brass flush bolt 250 mm each 10 84.00 840.00
452 Brass screws 25 mm 100 Nos 60 76.00 45.60
9,999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
0111 Carpenter 1st class Day 0.2 270 54.00
TOTAL 943.24
Add 1% for water charges 9.43
TOTAL 952.67
Add 15% for contractor’s profit and 142.90
overheads
Cos t of 10.00 hinges 1095.57
Cost of 1.00 hinge 109.56
Say 109.56

14.33 : Providing and fixing bright finished brass flush bolts with necessary screws etc. complete :
14.33.2: 150 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
405 Brass flush bolt 150 mm each 10 65.00 650.00
452 Brass screws 25 mm 100 Nos 60 76.00 45.60
9,999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
0111 Carpenter 1st class Day 0.17 270 45.90
TOTAL 744.23
Add 1% for water charges 7.44
TOTAL 751.67
Add 15% for contractor’s profit and 112.75
overheads
Cos t of 10.00 hinges 864.42
Cost of 1.00 hinge 86.44
Say 86.44

14.33 : Providing and fixing bright finished brass flush bolts with necessary screws etc. complete :
14.33.3: 100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
406 Brass flush bolt 100 mm each 10 44.00 440.00
452 Brass screws 25 mm 100 Nos 60 76.00 45.60
9,999 Carriage of materials L.S. 2.73 1.00 2.73
Labour-
0111 Carpenter 1st class Day 0.17 270 45.90
TOTAL 534.23
Add 1% for water charges 5.34
TOTAL 539.57
Add 15% for contractor’s profit and 80.94
overheads
Cos t of 10.00 hinges 620.51
Cost of 1.00 hinge 62.05
Say 62.05

14.34 : Providing and fixing 150 mm bright finished floor brass door stopper with rubber cushion,
screws etc. to suit shutter thickness complete
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
Materials-
417 Brass door stopper 150 mm each 10 104.00 1040.00
450 Brass screws 40 mm 100 Nos 40 96.00 38.40
9,999 Carriage of materials L.S. 2.73 1.00 2.73
9,999 Sundries (wooden plugs including fixing L.S. 6.37 1.00 6.37
in the floor)
Labour-
0111 Carpenter 1st class Day 0.07 270 18.90
TOTAL 1106.40
Add 1% for water charges 11.06
TOTAL 1117.46
Add 15% for contractor’s profit and 167.62
overheads
Cos t of 10.00 door stopper 1285.08
Cost of 1.00 door stopper 128.51
Say 128.51

14.35 : Providing and fixing bright finished brass hard drawn hooks and eyes :
14.35.1: 300 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
418 Bright finished brass hooks & eyes 300 10 Nos 10 457.00 457.00
mm
9,999 Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.06 270 16.20
TOTAL 474.11
Add 1% for water charges 4.74
TOTAL 478.85
Add 15% for contractor’s profit and 71.83
overheads
Cos t of 10.00 hookes & eyes 550.68
Cost of 1.00 hookes & eyes 55.07
Say 55.07

14.35 : Providing and fixing bright finished brass hard drawn hooks and eyes :
14.35.2 250 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
419 Bright finished brass hooks & eyes 250 10 Nos 10 423.00 423.00
9,999 mm
Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.06 270 16.20
TOTAL 440.11
Add 1% for water charges 4.40
TOTAL 444.51
Add 15% for contractor’s profit and 66.68
overheads
Cos t of 10.00 hookes & eyes 511.19
Cost of 1.00 hookes & eyes 51.12
Say 51.12

14.35 : Providing and fixing bright finished brass hard drawn hooks and eyes :
14.35.3 : 200 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
420 Bright finished brass hooks & eyes 200 10 Nos 10 390.00 390.00
mm
9,999 Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.06 270 16.20
TOTAL 407.11
Add 1% for water charges 4.07
TOTAL 411.18
Add 15% for contractor’s profit and 61.68
overheads
Cos t of 10.00 hookes & eyes 472.86
Cost of 1.00 hookes & eyes 47.29
Say 47.29

14.35 : Providing and fixing bright finished brass hard drawn hooks and eyes :
14.35.4: 150 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
421 Bright finished brass hooks & eyes 150 10 Nos 10 364.00 364.00
mm
9,999 Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.06 270 16.20
TOTAL 381.11
Add 1% for water charges 3.81
TOTAL 384.92
Add 15% for contractor’s profit and 57.74
overheads
Cos t of 10.00 hookes & eyes 442.66
Cost of 1.00 hookes & eyes 44.27
Say 44.27

14.35: Providing and fixing bright finished brass hard drawn hooks and eyes :
14.35.5: 100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
422 Bright finished brass hooks & eyes 100 10 Nos 10 300.00 300.00
mm
9,999 Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.06 270 16.20
TOTAL 317.11
Add 1% for water charges 3.17
TOTAL 320.28
Add 15% for contractor’s profit and 48.04
overheads
Cos t of 10.00 hookes & eyes 368.32
Cost of 1.00 hookes & eyes 36.83
Say 36.83

14.36 : Providing and fixing bright finished brass fan light pivot with necessary screws etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
429 Brass fan light pivot 10 Nos 10 128.00 128.00
450 Brass screws 40 mm 100 Nos 40 96.00 38.40
9,999 Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.08 270 21.60
TOTAL 188.91
Add 1% for water charges 1.89
TOTAL 190.80
Add 15% for contractor’s profit and 28.62
overheads
Cos t of 10.00 fanlight pivot 219.42
Cost of 1.00 fanlight pivot 21.94
Say 21.94

14.37 Providing and fixing 300 mm long bright finished brass chain with hook for fan light including
necessary screws etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
430 Brass fan light pivot each 10 13.00 130.00
452 Brass screws 25 mm 100 Nos 40 76.00 30.40
9,999 Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.1 270 27.00
TOTAL 188.31
Add 1% for water charges 1.88
TOTAL 190.19
Add 15% for contractor’s profit and 28.53
overheads
Cos t of 10.00 chain with hooks 218.72
Cost of 1.00 chain with hooks 21.87
Say 21.87

14.38 Providing and fixing bright finished brass quadrant stay 300mm long with necessary
screws etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
427 Brass quadrant stay 300 mm long each 10 73.00 730.00
452 Brass screws 25 mm 100 Nos 40 76.00 30.40
9,999 Carriage of material L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.1 270 27.00
TOTAL 788.31
Add 1% for water charges 7.88
TOTAL 796.19
Add 15% for contractor’s profit and 119.43
overheads
Cos t of 10.00 quadrant stays 915.62
Cost of 1.00 quadrant stays 91.56
Say 91.56

14.39 : Providing and fixing bright finished brass helical door spring (superior quality).
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
442 Helical door spring (superior quality) 150 each 10 185.00 1850.00
mm
449 Brass screws 50 mm 100 Nos 40 107.00 42.80
452 Brass screws 25 mm 100 Nos 20 76.00 15.20
Labour-
114 Beldar Day 0.2 207 41.40
0111 Carpenter 1st class Day 0.4 270 108.00
TOTAL 2057.40
Add 1% for water charges 20.57
TOTAL 2077.97
Add 15% for contractor’s profit and 311.70
overheads
Cos t of 10.00 quadrant stays 2389.67
Cost of 1.00 quadrant stays 238.97
Say 238.97

14.40 Providing and fixing chromium plated brass butt hinges with necessary screws etc. complete.
14.40.1 125x70x4 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
525 Brass butt hinges (chrom ium plated) 10 Nos 10 433.00 433.00
125x70x4 mm (ordinary type)
585 CP Brass screws 50 mm 100 Nos 100 123.00 123.00
9999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
114 Beldar Day 0.1 207 20.70
0111 Carpenter 1st class Day 0.14 270 37.80
TOTAL 618.14
Add 1% for water charges 6.18
TOTAL 624.32
Add 15% for contractor’s profit and 93.65
overheads
Cost of 10.00 nos 717.97
Cost of 1.00 no 71.80
Say 71.80

14.40 Providing and fixing chromium plated brass butt hinges with necessary screws etc. complete.
14.40.2 : 100x70x4 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
526 Brass butt hinges (chrom ium plated) 10 Nos 10 385.00 385.00
100x70x4 mm (ordinary type)
586 CP Brass screws 40 mm 100 Nos 80 150.00 120.00
9999 Carriage of materials L.S. 3.64 1.00 3.64
Labour-
114 Beldar Day 0.1 207 20.70
0111 Carpenter 1st class Day 0.14 270 37.80
TOTAL 567.14
Add 1% for water charges 5.67
TOTAL 572.81
Add 15% for contractor’s profit and 85.92
overheads
Cost of 10.00 nos 658.73
Cost of 1.00 no 65.87
Say 65.87

14.40 Providing and fixing chromium plated brass butt hinges with necessary screws etc. complete.
14.40.3 : 75x65x4 mm (heavy type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
524 Brass butt hinges (chrom ium plated) 10 Nos 10 430.00 430.00
75x65x4 mm (heavy type)
587 CP Brass screws 30 mm 100 Nos 60 90.00 54.00
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
114 Beldar Day 0.1 207 20.70
0111 Carpenter 1st class Day 0.14 270 37.80
TOTAL 544.32
Add 1% for water charges 5.44
TOTAL 549.76
Add 15% for contractor’s profit and 82.46
overheads
Cost of 10.00 nos 632.23
Cost of 1.00 no 63.22
Say 63.22

14.40 Providing and fixing chromium plated brass butt hinges with necessary screws etc. complete.
14.40.4: 75x40x2.5 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
527 Brass butt hinges (chrom ium plated) 10 Nos 10 135.00 135.00
75x40x2.5 mm (ordinary type)
587 CP Brass screws 30 mm 100 Nos 60 90.00 54.00
9999 Carriage of materials L.S. 1.82 1.00 1.82
Labour-
114 Beldar Day 0.1 207 20.70
0111 Carpenter 1st class Day 0.14 270 37.80
TOTAL 249.32
Add 1% for water charges 2.49
TOTAL 251.81
Add 15% for contractor’s profit and 37.77
overheads
Cost of 10.00 nos 289.59
Cost of 1.00 no 28.96
Say 28.96

14.40 Providing and fixing chromium plated brass butt hinges with necessary screws etc. complete.
14.40.5 : 50x40x2.5 mm (ordinary type)
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
528 Brass butt hinges (chrom ium plated) 10 Nos 10 105.00 105.00
50x40x2.5 mm (ordinary type)
589 CP Brass screws 20 mm 100 Nos 40 63.00 25.20
9999 Carriage of materials L.S. 0.91 1.00 0.91
Labour-
0111 Carpenter 1st class Day 0.08 270 21.60
TOTAL 152.71
Add 1% for water charges 1.53
TOTAL 154.24
Add 15% for contractor’s profit and 23.14
overheads
Cost of 10.00 nos 177.37
Cost of 1.00 no 17.74
Say 17.74

14.41 Providing and fixing 85x42mm chromium plated brass pull bolt lock with necessary screws, nuts,
bolts and washers etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos.
M aterials-
2467 Chromium plated brass pull bolt lock each 10 130.00 1300.00
including bolts, nuts & washers
9999 Carriage of materials & sndries L.S. 6.37 1.00 6.37
Labour-
112 Carpenter 2nd class Day 0.25 223 55.75
TOTAL 1362.12
Add 1% for water charges 13.62
TOTAL 1375.74
Add 15% for contractor’s profit and 206.36
overheads
Cost of 10.00 nos 1582.10
Cost of 1.00 no 158.21
Say 158.21

14.42 : White washing with lime to give an even shade :


14.42.1: Old work (two or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M aterials-
775 Dehradun white lime quintal 0.02 400.00 8.00
9999 Carriage of lime L.S. 0.52 1.00 0.52
9999 Indigo gum etc L.S. 2.73 1.00 2.73
9999 Sundries ladders etc L.S. 2.73 1.00 2.73
Labour-
115 Coolie Day 0.06 207 12.42
141 White Washer Day 0.11 180 19.80
TOTAL 46.20
Add 1% for water charges 0.46
TOTAL 46.66
Add 15% for contractor’s profit and 7.00
overheads
Cost of 10.00 sqm 53.66
Cost of 1.00 sqm 5.37
Say 5.37

14.42 : White washing with lime to give an even shade :

Code Description Unit Quantity Rate Amount


Details of cost for 10 sqm
M aterials-
775 Dehradun white lime quintal 0.01 400.00 4.00
9999 Carriage of lime L.S. 0.52 1.00 0.52
9999 Indigo gum etc L.S. 2.08 1.00 2.08
9999 Sundries ladders etc L.S. 2.73 1.00 2.73

Labour-
115 Coolie Day 0.03 207 6.21
141 White Washer Day 0.07 180 12.60
TOTAL 28.14
Add 1% for water charges 0.28

TOTAL 28.42
Add 15% for contractor’s profit and 4.26
overheads

Cost of 10.00 sqm 32.68

Cost of 1.00 sqm 3.27


Say 3.27

14.43 Removing white or colour wash by scrapping and sand papering and preparing the surface
smooth including necessary repairs to scratches etc. complete
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
9999 Sundries such as sand paper and L.S. 2.73 1.00 2.73
scrapper
9999 Repair to scraches L.S. 1.82 1.00 1.82
Labour-
114 Beldar Day 0.09 207 18.63
115 Coolie Day 0.04 207 8.28
101 Bhishti Day 0.04 180 7.20
TOTAL 38.66
Add 1% for water charges 0.39
TOTAL 39.05
Add 15% for contractor’s profit and 5.86
overheads
Cost of 10.00 sqm 44.90
Cost of 1.00 sqm 4.49
Say 4.49

14.44: Distempering with dry distemper of approved brand and manufacture (one or more coats) and of
required shade on old work to give an even shade.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M aterials-
815 Dry distemper kilogram 1 40.00 40.00
9999 Carriage of distemper L.S. 0.91 1.00 0.91
9999 Brushes, sand-paper etc. L.S. 5.33 1.00 5.33
9999 Sundries L.S. 4.42 1.00 4.42
Labour-
115 Coolie Day 0.17 207 35.19
131 Painter Day 0.33 180 59.40
TOTAL 145.25
Add 1% for water charges 1.45
TOTAL 146.70
Add 15% for contractor’s profit and 22.01
overheads
Cost of 10.00 sqm 168.71
Cost of 1.00 sqm 16.87
Say 16.87

14.45 Distempering with oil bound washable distemper of approved brand and manufacture to
give an even shade :
14.45.1: Old work (one or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M aterials-
816 Oil bound washable distemper kilogram 1 45.00 45.00
9999 Brushes, putty etc. L.S. 0.52 1.00 0.52
9999 Sundries including carriage L.S. 10.79 1.00 10.79
9999 Sundries L.S. 7.15 1.00 7.15
Labour-
115 Coolie Day 0.17 207 35.19
131 Painter Day 0.33 180 59.40
TOTAL 158.05
Add 1% for water charges 1.58
TOTAL 159.63
Add 15% for contractor’s profit and 23.94
overheads
Cost of 10.00 sqm 183.58
Cost of 1.00 sqm 18.36
Say 18.36

14.46 : Removing dry or oil bound distemper, water proofing cement paint and the like by scrapping,
sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
9999 Scrapper, sand paper etc. L.S. 6.24 1.00 6.24
9999 Sundries including mortar to repair the L.S. 1.82 1.00 1.82
surface
Labour-
114 Beldar Day 0.11 207 22.77
115 Coolie Day 0.05 207 10.35
101 Bhishti Day 0.05 180 9.00
TOTAL 50.18
Add 1% for water charges 0.50
TOTAL 50.68
Add 15% for contractor’s profit and 7.60
overheads
Cost of 10.00 sqm 58.28
Cost of 1.00 sqm 5.83
Say 5.83

14.47 : Painting on G.S. sheet with synthetic enamel paint of approved brand and manufacture of
required colour to give an even shade :
14.47.1: Old work (one or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M aterials-
845 Roofing paint litre 0.46 95.00 43.70
9999 Carriage of paint L.S. 0.52 1.00 0.52
9999 Putty, brushes sand paper etc. L.S. 6.67 1.00 6.67
9999 Sundries L.S. 8.06 1.00 8.06
Labour-
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 198.27
Add 1% for water charges 1.98
TOTAL 200.25
Add 15% for contractor’s profit and 30.04
overheads
Cost of 10.00 sqm 230.29
Cost of 1.00 sqm 23.03
Say 23.03

14.48 : Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings with black
anticorrosive bitumastic paint of approved brand and manufacture over and including a priming coat of
ready mixed zinc chromate yellow primer on new work :
14.48.1: 75 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
4202 Zinc chromate red oxide primer litre 0.41 58.00 23.78
9999 Carriage of materials L.S. 0.39 1.00 0.39
9999 Brushes, sand paper etc L.S. 8.19 1.00 8.19
Labour
115 Coolie Day 0.18 207 37.26
131 Painter Day 0.18 180 32.40
828 Anticorrosive bituminous paint (black) litre 0.73 52.00 37.96

9999 Carriage of materials L.S. 1.04 1.00 1.04


9999 Putty, sand paper etc L.S. 4.16 1.00 4.16
9999 Sundries L.S. 6.24 1.00 6.24
9999 Wire brushes for cleaning L.S. 4.42 1.00 4.42
9999 Extra for delays L.S. 40.3 1.00 40.30
Labour
115 Coolie Day 0.41 207 84.87
131 Painter Day 0.41 180 73.80
TOTAL 354.81
Add 1% for water charges 3.55
TOTAL 358.36
Add for contractor’s profit and 53.75
overheads @15%
Cost of 30 metres 412.11
Cost of 1 metre 13.74
Say 13.74
14.49 : Painting (one or more coats) on rain water, soil, waste and vent pipes and fittings with black
anticorrosive bitumastic paint of approved brand and manufacture on old work :
14.49.1: 75 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
828 Anticorrosive bituminous paint (black) litre 0.43 52.00 22.36

9999 Carriage of materials L.S. 0.39 1.00 0.39


9999 Putty, sand paper etc L.S. 4.16 1.00 4.16
9999 Sundries L.S. 6.24 1.00 6.24
9999 Wire brushes for cleaning L.S. 4.42 1.00 4.42
9999 Extra for delays L.S. 26.91 1.00 26.91
Labour
115 Coolie Day 0.27 207 55.89
131 Painter Day 0.27 180 48.60
TOTAL 168.97
Add 1% for water charges 1.69
TOTAL 170.66
Add for contractor’s profit and 25.60
overheads @15%
Cost of 30 metres 196.26
Cost of 1 metre 6.54
Say 6.54

14.50: Painting (two or more coats) on rain water, soil, waste and vent pipes and fittings with
aluminium paint of approved brand and manufacture over a priming coat of ready mixed zinc chromate
yellow primer on new work :
14.50.1 : 75 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
4202 Red oxide Zinc chromate primer litre 0.41 58.00 23.78
826 Aluminium paint litre 0.61 180.00 109.80
9999 Carriage of materials L.S. 1.43 1.00 1.43
9999 Putty, sand paper etc L.S. 4.16 1.00 4.16
9999 Sundries L.S. 13.39 1.00 13.39
9999 Wire brushes for cleaning L.S. 9.1 1.00 9.10
9999 Extra for delays L.S. 44.85 1.00 44.85
Labour
115 Coolie Day 0.59 207 122.13
131 Painter Day 0.59 180 106.20
TOTAL 434.84
Add 1% for water charges 4.35
TOTAL 439.19
Add for contractor’s profit and 65.88
overheads @15%
Cost of 30 metres 505.07
Cost of 1 metre 16.84
Say 16.84

14.51 : Painting (one or more coats) on rain water, soil, waste and vent pipes and fittings with synthetic
enamel paint of approved brand and manufacture and required colour on old work :
14.51.1: 75 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
826 Aluminium paint litre 0.35 180.00 63.00
9999 Carriage of materials L.S. 2.08 1.00 2.08
9999 Putty, sand paper etc L.S. 4.55 1.00 4.55
9999 Sundries L.S. 6.24 1.00 6.24
9999 Wire brushes for cleaning L.S. 4.42 1.00 4.42
9999 Extra for delays L.S. 26.91 1.00 26.91
Labour
115 Coolie Day 0.28 207 57.96
131 Painter Day 0.28 180 50.40
TOTAL 215.56
Add 1% for water charges 2.16
TOTAL 217.72
Add for contractor’s profit and 32.66
overheads @15%
Cost of 30 metres 250.37
Cost of 1 metre 8.35
Say 8.35

14.51 : Painting (one or more coats) on rain water, soil, waste and vent pipes and fittings with synthetic
enamel paint of approved brand and manufacture and required colour on old work :
14.51.2: 100 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
826 Aluminium paint litre 0.46 180.00 82.80
9999 Carriage of materials L.S. 2.73 1.00 2.73
9999 Putty, sand paper etc L.S. 5.85 1.00 5.85
9999 Sundries L.S. 8.06 1.00 8.06
9999 Wire brushes for cleaning L.S. 5.33 1.00 5.33
9999 Extra for delays L.S. 34.06 1.00 34.06
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 278.15
Add 1% for water charges 2.78
TOTAL 280.93
Add for contractor’s profit and 42.14
overheads @15%
Cost of 30 metres 323.07
Cost of 1 metre 10.77
Say 10.77

14.51 : Painting (one or more coats) on rain water, soil, waste and vent pipes and fittings with synthetic
enamel paint of approved brand and manufacture and required colour on old work :
14.51.3: 150 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
826 Aluminium paint litre 0.68 180.00 122.40
9999 Carriage of materials L.S. 3.9 1.00 3.90
9999 Putty, sand paper etc L.S. 8.58 1.00 8.58
9999 Sundries L.S. 11.96 1.00 11.96
9999 Wire brushes for cleaning L.S. 7.15 1.00 7.15
9999 Extra for delays L.S. 40.3 1.00 40.30
Labour
115 Coolie Day 0.53 207 109.71
131 Painter Day 0.53 180 95.40
TOTAL 399.40
Add 1% for water charges 3.99
TOTAL 403.39
Add for contractor’s profit and 60.51
overheads @15%
Cost of 30 metres 463.90
Cost of 1 metre 15.46
Say 15.46

14.52 : Painting with oil type wood preservative of approved brand and manufacture
14.52.1: Old work (one or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
859 Oil type wood preservative litre 0.81 60.00 48.60
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, etc L.S. 2.73 1.00 2.73
9999 Sundries L.S. 2.73 1.00 2.73
Labour
115 Coolie Day 0.11 207 22.77
131 Painter Day 0.11 180 19.80
TOTAL 97.15
Add 1% for water charges 0.97
TOTAL 98.12
Add for contractor’s profit and 14.72
overheads @15%
Cost of 10 sqm 112.84
Cost of 1 sqm 11.28
Say 11.28

14.53 : Wall painting with plastic emulsion paint of approved brand and manufacture to give an even
shade
14.53.1: One or more coats on old work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
835 Plastic emulsion paint litre 0.73 150.00 109.50
9999 Materials for filling in holes and cracks L.S. 0.52 1.00 0.52
(putty etc)
9999 Carriage of materials L.S. 5.33 1.00 5.33
9999 Brushes, etc L.S. 8.06 1.00 8.06
9999 Sundries L.S. 6.76 1.00 6.76
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 269.49
Add 1% for water charges 2.69
TOTAL 272.18
Add for contractor’s profit and 40.83
overheads @15%
Cost of 10 sqm 313.01
Cost of 1 sqm 31.30
Say 31.30
14.54 : Painting with synthetic enamel paint of approved brand and manufacture of required colour to
give an even shade :
14.54.1: One or more coats on old work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
833 Synthetic enamel paint in black or litre 0.7 170.00 119.00
chocolate shade
9999 Materials for filling in holes and cracks L.S. 2.73 1.00 2.73
(putty etc)
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, etc L.S. 5.33 1.00 5.33
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 274.96
Add 1% for water charges 2.75
TOTAL 277.71
Add for contractor’s profit and 41.66
overheads @15%
Cost of 10 sqm 319.37
Cost of 1 sqm 31.94
Say 31.94

14.55 : Painting with aluminium paint of approved brand and manufacture to give an even shade
14.55.1: One or more coats on old work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
826 Aluminium paint litre 0.46 180.00 82.80
9999 Materials for filling in holes and cracks L.S. 2.73 1.00 2.73
(putty etc)
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, etc L.S. 5.33 1.00 5.33
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 238.76
Add 1% for water charges 2.39
TOTAL 241.15
Add for contractor’s profit and 36.17
overheads @15%
Cost of 10 sqm 277.32
Cost of 1 sqm 27.73
Say 27.73

14.56 : Painting with acid proof paint of approved brand and manufacture of required colour to give
an even shade :
14.56.1: One or more coats on old work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
827 Acid proof paint litre 0.7 93.00 65.10
9999 Materials for filling in holes and cracks L.S. 2.73 1.00 2.73
(putty etc)
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, etc L.S. 5.33 1.00 5.33
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 221.06
Add 1% for water charges 2.21
TOTAL 223.27
Add for contractor’s profit and 33.49
overheads @15%
Cost of 10 sqm 256.76
Cost of 1 sqm 25.68
Say 25.68

14.57 : Painting with black anti-corrosive bitumastic paint of approved brand and manufacture to
give an even shade :
14.57.1: One or more coats on old work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
828 Black anticorrosive bitumastic paint litre 0.57 52.00 29.64
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, etc L.S. 5.33 1.00 5.33
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 182.87
Add 1% for water charges 1.83
TOTAL 184.70
Add for contractor’s profit and 27.70
overheads @15%
Cost of 10 sqm 212.40
Cost of 1 sqm 21.24
Say 21.24

14.58 : French spirit polishing:


14.58.1: One or more coats on old work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
999 Shellac kilogram 0.13 192.00 24.96
1000 Spirit litre 0.98 37.00 36.26
9999 Carriage of materials L.S. 0.91 1.00 0.91
9999 Turpentine oil sand paper L.S. 10.79 1.00 10.79
cotton/woolen cloth putty etc.
9999 Linseed oil L.S. 0.52 1.00 0.52
9999 Sundries L.S. 8.06 1.00 8.06
Labour
131 Painter Day 1.76 180 316.80
TOTAL 398.30
Add 1% for water charges 3.98
TOTAL 402.28
Add for contractor’s profit and 60.34
overheads @15%
Cost of 10 sqm 462.63
Cost of 1 sqm 46.26
Say 46.26

14.59 : Polishing on wood work with ready made wax polish of approved brand and manufacture :
14.59.1: Old work
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
855 Ready made Wax polish kilogram 0.25 150.00 37.50
9999 Carriage of materials L.S. 0.39 1.00 0.39
9999 Soap, brushes, cloth etc L.S. 4.16 1.00 4.16
9999 Sundries L.S. 4.42 1.00 4.42
Labour
115 Coolie Day 0.4 207 82.80
131 Painter Day 0.4 180 72.00
TOTAL 201.27
Add 1% for water charges 2.01
TOTAL 203.28
Add for contractor’s profit and 30.49
overheads @15%
Cost of 10 sqm 233.78
Cost of 1 sqm 23.38
Say 23.38

14.60 : Re-lettering with black Japan paint of approved brand and manufacture.
Code Description Unit Quantity Rate Amount
Detail of cost for 100 letters of 15 cm height
M ATER IALS
829 Paint (Black Japan) litre 0.37 170.00 62.90
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Painting brushes, turpentine, stencil etc L.S. 7.15 1.00 7.15

9999 Sundries L.S. 8.06 1.00 8.06


Labour
115 Coolie Day 1 207 207.00
131 Painter Day 4 180 720.00
TOTAL 1005.63
Add 1% for water charges 10.06
TOTAL 1015.69
Add for contractor’s profit and 152.35
overheads @15%
Cost of 100 letters of 15 cm height 1168.04
Cost of 1 letters of 1 cm height 0.78
Say 0.78

14.61 Painting (one or more coats) with black Japan paint of approved brand and manufacture to
give an even shade.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
829 Paint (Black Japan) litre 0.7 170.00 119.00
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Putty, etc. L.S. 2.73 1.00 2.73
9999 Brushes, sand paper etc. L.S. 5.33 1.00 5.33
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 274.96
Add 1% for water charges 2.75
TOTAL 277.71
Add for contractor’s profit and 41.66
overheads @15%
Cost of 10 sqm 319.37
Cost of 1 sqm 31.94
Say 31.94

14.62 : Providing and fixing C.P. brass chain and rubber plug complete for sink or wash basin :
14.62.1: 32mm dia
Code Description Unit Quantity Rate Amount
Detail of cost for one no.
M aterials-
1314 C.P. brass chain with 32 mm dia rubber each 1 21.00 21.00
plug
9999 Carriage of materials and fixing charges L.S. 8.06 1.00 8.06

TOTAL 29.06
Add 1% for water charges 0.29
TOTAL 29.35
Add for contractor’s profit and 4.40
overheads @15%
Cost of 1 no. 33.75
Say 33.75

14.62 : Providing and fixing C.P. brass chain and rubber plug complete for sink or wash basin :
14.62.2 40 mm dia
Code Description Unit Quantity Rate Amount
Detail of cost for one no.
M aterials-
1315 C.P. brass chain with 40 mm dia rubber each 1 22.00 22.00
plug
9999 Carriage of materials and fixing charges L.S. 8.06 1.00 8.06

TOTAL 30.06
Add 1% for water charges 0.30
TOTAL 30.36
Add for contractor’s profit and 4.55
overheads @15%
Cost of 1 no. 34.91
Say 34.91

14.63 : Distempering with 1st quality acrylic washable distemper (ready made) of approved
manufacturer and of required shade and colour complete, as per manufacturer’s specification.
14.63.1: One or more coats on old work.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
816 Oil bound washable distemper kilogram 1 45.00 45.00
9999 Brushes, putty etc L.S. 0.52 1.00 0.52
9999 Sundries including carriage of material L.S. 10.76 1.00 10.76

9999 Sundries L.S. 7.15 1.00 7.15


Labour
114 Beldar Day 0.22 207 45.54
131 Painter Day 0.22 180 39.60
TOTAL 148.57
Add 1% for water charges 1.49
TOTAL 150.06
Add for contractor’s profit and 22.51
overheads @15%
Cost of 10 sqm 172.56
Cost of 1 sqm 17.26
Say 17.26

14.64 Finishing walls with water proofing cement paint of required shade :
14.64.1 Old work (one or more coats applied @ 2.20 kg/10 sqm) over priming coat of primer applied
@ 0.80 litrs/10 sqm complete including cost of Priming coat.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
851 Water proofing cement paint kilogram 2.2 40.00 88.00
8508 Primer for cement paint litre 0.8 52.00 41.60
9999 Carriage of materials L.S. 1.56 1.00 1.56
9999 Brushes, sand paper etc L.S. 7.15 1.00 7.15
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.23 207 47.61
101 Bhishti Day 0.05 180 9.00
131 Painter Day 0.46 180 82.80
TOTAL 285.78
Add 1% for water charges 2.86
TOTAL 288.64
Add for contractor’s profit and 43.30
overheads @15%
Cost of 10 sqm 331.93
Cost of 1 sqm 33.19
Say 33.19

14.65 : Finishing walls with textured exterior paint of required shade :


14.65.1 : Old work (Two or more coats on existing cement paint surface applied @ 3.28Itr/10 sqm.

Code Description Unit Quantity Rate Amount


Details of cost for 10 sqm
M ATER IALS
8507 Textured exterior paint litre 3.28 183.00 600.24
9999 Carriage of materials L.S. 1.56 1.00 1.56
9999 Brushes, sand L.S. 7.15 1.00 7.15
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.23 207 47.61
131 Painter Day 0.46 180 82.80
TOTAL 747.42
Add 1% for water charges 7.47
TOTAL 754.89
Add for contractor’s profit and 113.23
overheads @15%
Cost of 10 sqm 868.13
Cost of 1 sqm 86.81
Say 86.81

14.65 : Finishing walls with textured exterior paint of required shade :


14.65.2 : Old work (One or more coats) applied @ 1.82 ltr/10 sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
8507 Textured exterior paint litre 1.82 183.00 333.06
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, sand L.S. 7.15 1.00 7.15
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.17 207 35.19
131 Painter Day 0.33 180 59.40
TOTAL 443.38
Add 1% for water charges 4.43
TOTAL 447.81
Add for contractor’s profit and 67.17
overheads @15%
Cost of 10 sqm 514.99
Cost of 1 sqm 51.50
Say 51.50

14.66 : Finishing walls with Acrylic Smooth exterior paint of required shade :
14.66.1: Old work (Two or more coat applied @ 1.67 ltr/10 sqm) on existing cement paint surface).
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
8505 Acrylic exterior paint litre 1.67 123.00 205.41
9999 Carriage of materials L.S. 0.91 1.00 0.91
9999 Brushes, sand L.S. 4.81 1.00 4.81
9999 Sundries L.S. 5.33 1.00 5.33
Labour
115 Coolie Day 0.23 207 47.61
131 Painter Day 0.46 180 82.80
TOTAL 346.87
Add 1% for water charges 3.47
TOTAL 350.34
Add for contractor’s profit and 52.55
overheads @15%
Cost of 10 sqm 402.89
Cost of 1 sqm 40.29
Say 40.29

14.66 : Finishing walls with Acrylic Smooth exterior paint of required shade :
14.66.2: Old work (One or more coat applied @ 0.90 ltr/10 sqm).
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
8505 Acrylic exterior paint litre 0.9 123.00 110.70
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, sand L.S. 7.15 1.00 7.15
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.17 207 35.19
131 Painter Day 0.33 180 59.40
TOTAL 221.02
Add 1% for water charges 2.21
TOTAL 223.23
Add for contractor’s profit and 33.48
overheads @15%
Cost of 10 sqm 256.71
Cost of 1 sqm 25.67
Say 25.67

14.67 Finishing walls with Premium Acrylic Smooth exterior paint of required shade
14.67.1 Old work (Two or more coats applied @ 1.43 ltr/10sqm ) over existing cement paint surface.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
8506 Premium Acrylic exterior paint litre 1.43 202.00 288.86
9999 Carriage of materials L.S. 1.04 1.00 1.04
9999 Brushes, sand L.S. 7.15 1.00 7.15
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.23 207 47.61
131 Painter Day 0.46 180 82.80
TOTAL 435.52
Add 1% for water charges 4.36
TOTAL 439.88
Add for contractor’s profit and 65.98
overheads @15%
Cost of 10 sqm 505.86
Cost of 1 sqm 50.59
Say 50.59

14.67 : Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required
shade
14.67.2: Old work (one or more coats applied @ 0.83 ltr/10 sqm).
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
8506 Premium Acrylic exterior paint litre 0.83 202.00 167.66
9999 Carriage of materials L.S. 0.91 1.00 0.91
9999 Brushes, sand L.S. 7.15 1.00 7.15
9999 Sundries L.S. 8.06 1.00 8.06
Labour
115 Coolie Day 0.17 207 35.19
131 Painter Day 0.33 180 59.40
TOTAL 278.37
Add 1% for water charges 2.78
TOTAL 281.15
Add for contractor’s profit and 42.17
overheads @15%
Cost of 10 sqm 323.33
Cost of 1 sqm 32.33
Say 32.33

14.68 Painting (one or more coats) on rain water, soil, waste and vent pipes and fittings with black
anticorrosive bitumastic paint of approved brand and manufacture on old work :
14.68.1 100 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
828 Anticorrosive bituminous paint (black) litre 0.57 52.00 29.64

9999 Carriage of materials L.S. 0.52 1.00 0.52


9999 Putty, sand paper etc L.S. 5.33 1.00 5.33
9999 Sundries L.S. 8.06 1.00 8.06
9999 Wire brushes for cleaning L.S. 5.33 1.00 5.33
9999 Extra for delays L.S. 34.06 1.00 34.06
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 222.26
Add 1% for water charges 2.22
TOTAL 224.48
Add for contractor’s profit and 33.67
overheads @15%
Cost of 30 metres 258.15
Cost of 1 metre 8.61
Say 8.61

14.68 Painting (one or more coats) on rain water, soil, waste and vent pipes and fittings with black
anticorrosive bitumastic paint of approved brand and manufacture on old work :
14.68.2: 150 mm diameter pipes
Code Description Unit Quantity Rate Amount
Details of cost for 30 m
M ATER IALS
828 Anticorrosive bituminous paint (black) litre 0.85 52.00 44.20

9999 Carriage of materials L.S. 0.65 1.00 0.65


9999 Putty, sand paper etc L.S. 8.06 1.00 8.06
9999 Sundries L.S. 11.96 1.00 11.96
9999 Wire brushes for cleaning L.S. 7.15 1.00 7.15
9999 Extra for delays L.S. 40.3 1.00 40.30
Labour
115 Coolie Day 0.53 207 109.71
131 Painter Day 0.53 180 95.40
TOTAL 317.43
Add 1% for water charges 3.17
TOTAL 320.60
Add for contractor’s profit and 48.09
overheads @15%
Cost of 30 metres 368.69
Cost of 1 metre 12.29
Say 12.29

14.69 : Varnishing with varnish of approved brand and manufacture:


14.69.1: One or more coats with copal varnish.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M ATER IALS
857 Superior copal varnish litre 0.7 100.00 70.00
9999 Repair to the surface L.S. 2.73 1.00 2.73
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, sand L.S. 5.33 1.00 5.33
9999 Sundries L.S. 2.73 1.00 2.73
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 220.63
Add 1% for water charges 2.21
TOTAL 222.84
Add for contractor’s profit and 33.43
overheads @15%
Cost of 10 sqm 256.26
Cost of 1 sqm 25.63
Say 25.63

14.69 : Varnishing with varnish of approved brand and manufacture:


14.69.2 : One or more coats with spar varnish.
Code Description Unit Quantity Rate Amount
M ATER IALS
Details of cost for 10 sqm
858 Superior spar varnish litre 0.75 105.00 78.75
9999 Repair to the surface L.S. 2.73 1.00 2.73
9999 Carriage of materials L.S. 0.52 1.00 0.52
9999 Brushes, sand L.S. 4.16 1.00 4.16
9999 Sundries L.S. 2.73 1.00 2.73
Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 228.21
Add 1% for water charges 2.28
TOTAL 230.49
Add for contractor’s profit and 34.57
overheads @15%
Cost of 10 sqm 265.07
Cost of 1 sqm 26.51
Say 26.51

14.70 Melamine polishing on wood work (one or more coats)


Code Description Unit Quantity Rate Amount
M ATER IALS
Details of cost for 10 sqm
7241 Melamine polish litre 0.65 228.00 148.20
6 Hire charges of Spraying machine Day 0.78 100.00 78.00
including electric charges
9999 Carriage of machine & materials L.S. 4.42 1.00 4.42
9999 Sundries L.S. 4.42 1.00 4.42
Labour
115 Coolie Day 0.35 207 72.45
131 Painter Day 0.35 180 63.00
TOTAL 370.49
Add 1% for water charges 3.70
TOTAL 374.19
Add for contractor’s profit and 56.13
overheads @15%
Cost of 10 sqm 430.32
Cost of 1 sqm 43.03
Say 43.03

14.71 Varnishing with flatting varnish of approved brand and manufacture one or more coats on old
work.
Code Description Unit Quantity Rate Amount
M ATER IALS
Details of cost for 10 sqm
856 Flatting varnish litre 0.7 49.00 34.30
9999 Carriage L.S. 1.82 1.00 1.82
9999 Glue, putty etc L.S. 2.73 1.00 2.73
9999 Painting brushes, turpentine, stencil etc L.S. 24.18 1.00 24.18

Labour
115 Coolie Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
TOTAL 202.35
Add 1% for water charges 2.02
TOTAL 204.37
Add for contractor’s profit and 30.66
overheads @15%
Cost of 10 sqm 235.03
Cost of 1 sqm 23.50
Say 23.50

14.72 : Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven
story height made with 40mm dia. M.S. tube 1.5 m centre to centre horizontal & vertical tubes joining
with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in
the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required
duration as approved and removing it there after .The scaffolding system shall be stiffened with
bracings, runners, connection with the building etc wherever required for inspection of work at required
locations with essential safety features for the workmen etc. complete as per directions and approval of
Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The
payment will be made once irrespective of duration of scaffolding. (To be used for maintenance work
judicially . necessary deduction for scaffolding in the existing item to be done.)

Code Description Unit Quantity Rate Amount


M ATER IALS
Details of cost for 9 sqm
4009 Mild steel tubes hot finished welded kilogram 70.98 38.00 2697.24
type
1007 Structural steel such as tees, angles quintal 0.462 4600.00 2125.20
channels and R.S. joists
7340 Stainless steel pin . kg 2.568 130.00 333.84
Cement concerete 1:2:4 (Rate as per cum 0.054 5140.53 277.59 A
item no 4.1.3 of SH : Concrete Work)
Painting with epoxy paint over and sqm 5.82 85.34 496.67 A
including priming coat Rate as per Item
no. 13.52.1 of S.H . Finis hing
1215 Welding by electric plant cm 980 1.00 980.00
9999 Sundries L.S. 80.73 1.00 80.73
9999 Labour for scaffolding L.S. 299 1.00 299.00
Making holes in brick work
114 Beldar Day 6.37 207 1318.59
123 Mason 1st class Day 0.25 270 67.50
124 Mason 2nd class Day 0.25 223 55.75
Labour
102 Blacksmith 1st class Day 1.34 270 361.80
100 Bandhani Day 0.67 180 120.60
TOTAL 9214.50
Add 1% for water charges except A 84.40

TOTAL 9298.91
Add for contractor’s profit and 1278.70
overheads @15% except on A
Cost of 106.52 kg 10577.60
Cost of 1 kg 99.30
Say 99.30
14.42 : White washing with lime to give an even shade :
14.42.2 : Old work (one or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm
M aterials-
775 Dehradun white lime quintal 0.03 800.00 24.00
9999 Carriage of lime L.S. 1.56 1.00 1.56
9999 Indigo gum etc L.S. 6.24 1.00 6.24
9999 Sundries ladders etc L.S. 8.19 1.00 8.19

Labour-
115 Coolie Day 0.3 169 50.70
141 White Washer Day 0.1 192 19.20
TOTAL 109.89
Add 1% for water charges 1.10

TOTAL 110.99
Add 15% for contractor’s profit and 16.65
overheads

Cost of 10.00 sqm 127.64

Cost of 1.00 sqm 12.76


Say
4.25
15.1 Demolishing lime concrete manually/ by mechanical means and disposal of
material within 50 metres lead as per direction of Engineer in charge.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.37 207 76.59
114 Beldar Day 0.44 207 91.08
9,999 Sundries L.S. 1.04 1.00 1.04
TOTAL 168.71
Add 1% for water charges 1.69
TOTAL 170.40
Add for contractor’s profit and
overheads @15% 25.56
Cost of 1 cum 195.96
Say 195.96

15.2 Demolishing cement concrete manually/ by mechanical means including disposal


of material within 50 metres lead as per direction of Engineer in charge.
15.2.1 1:3:6 or richer mix
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.72 207 149.04
114 Beldar Day 1.59 207 329.13
9,999 Sundries L.S. 4.81 1.00 4.81
TOTAL 482.98
Add 1% for water charges 4.83
TOTAL 487.81
Add for contractor’s profit and
overheads @15% 48.78
Cost of 1 cum 536.59
Say 536.59

15.2 Demolishing cement concrete manually/ by mechanical means including disposal


of material within 50 metres lead as per direction of Engineer in charge.
15.2.2 1:4:8 or leaner mix
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.55 207 113.85
114 Beldar Day 0.88 207 182.16
9,999 Sundries L.S. 1.95 1.00 1.95
TOTAL 297.96
Add 1% for water charges 2.98
TOTAL 300.94
Add for contractor’s profit and
overheads @15% 45.14
Cost of 1 cum 346.08
Say 346.08

15.3 Demolishing R .C.C. work, including stacking of steel bars and disposal o f
unserviceable material within 50 metres lead as per direction of Engineer - in- charge.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.72 207 149.04
114 Beldar Day 2.65 207 548.55
9,999 Sundries L.S. 7.02 1.00 7.02
TOTAL 704.61
Add 1% for water charges 7.05
TOTAL 711.66
Add for contractor’s profit and
overheads @15% 106.75
Cost of 1 cum 818.40
Say 818.40

15.4 Demolishing R.B. work manually / by mechanical means including stacking of


steel bars and disposal of unserviceable material within 50 metres lead as per direction
of Engineer
Code - in- charge.
Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.9 207 186.30
114 Beldar Day 2.12 207 438.84
9,999 Sundries L.S. 4.68 1.00 4.68
TOTAL 629.82
Add 1% for water charges 6.30
TOTAL 636.12
Add for contractor’s profit and
overheads @15% 95.42
Cost of 1 cum 731.54
Say 731.54

15.5 Extra for cutting reinforcem ent bars manually / by mechanical means in R.C.C. or
R .B. work (Payment shall be made on the cross sectional area of R.C.C. or R.B. work)
as per direction
Code of Engineer - in -charge.
Description Unit Quantity Rate Amount
Detail of cost for 1 sqm
Labour:
103 Blacksmith 2nd class Day 0.5 223 111.50
114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 13.39 1.00 13.39
TOTAL 228.39
Add 1% for water charges 2.28
TOTAL 230.67
Add for contractor’s profit and
overheads @15% 34.60
Cost of 1 sqm 265.27
Say 265.27

15.6 Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B.
Code
work Description Unit Quantity Rate Amount
Detail of cost for 10 Nos = 94.8 kg
Labour:
103 Blacksmith 2nd class Day 0.25 223 55.75
114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 13.39 1.00 13.39
TOTAL 172.64
Add 1% for water charges 1.73
TOTAL 174.37
Add for contractor’s profit and
overheads @15% 26.15
Cost of 94.8 kg 200.52
Cost of 1 kg 2.12
Say 2.12

15.7 Demolishing brick work, manually/ by mechanical means including stacking of


serviceable material and disposal of unserviceable materialwithin 50 metres lead as per
direction
15.7.1 In of
mudEngineer-in-charge.
mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.37 207 76.59
114 Beldar Day 0.3 207 62.10
9,999 Sundries L.S. 1.04 1.00 1.04
TOTAL 139.73
Add 1% for water charges 1.40
TOTAL 141.13
Add for contractor’s profit and
overheads @15% 21.17
Cost of 1 cum 162.30
Say 162.30

15.7 Demolishing brick work, manually/ by mechanical means including stacking of


serviceable material and disposal of unserviceable materialwithin 50 metres lead as per
direction of Engineer-in-charge.
15.7.2 In lime mortar with old mughal bricks.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.46 207 95.22
114 Beldar Day 1.24 207 256.68
9,999 Sundries L.S. 1.04 1.00 1.04
TOTAL 352.94
Add 1% for water charges 3.53
TOTAL 356.47
Add for contractor’s profit and
overheads @15% 53.47
Cost of 1 cum 409.94
Say 409.94

15.7 Demolishing brick work, manually/ by mechanical means including stacking of


serviceable material and disposal of unserviceable materialwithin 50 metres lead as per
direction
15.7.3 In of Engineer-in-charge.
lime mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.37 207 76.59
114 Beldar Day 0.44 207 91.08
9,999 Sundries L.S. 1.04 1.00 1.04
TOTAL 168.71
Add 1% for water charges 1.69
TOTAL 170.40
Add for contractor’s profit and
overheads @15% 25.56
Cost of 1 cum 195.96
Say 195.96

15.7 Demolishing brick work, manually/ by mechanical means including stacking of


serviceable material and disposal of unserviceable materialwithin 50 metres lead as per
direction
15.7.4 In of Engineer-in-charge.
Cement mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.9 207 186.30
114 Beldar Day 1.06 207 219.42
9,999 Sundries L.S. 2.47 1.00 2.47
TOTAL 408.19
Add 1% for water charges 4.08
TOTAL 412.27
Add for contractor’s profit and
overheads @15% 41.23
Cost of 1 cum 453.50
Say 453.50
15.8 Removing mortar from bricks and cleaning bricks including stacking within a lead
of 50 m (stacks of cleaned bricks shall be measured):
15.8.1 From brick work in mud mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1000 Nos.
Labour:
115 Coolie Day 1.6 207 331.20
114 Beldar Day 2.4 207 496.80
124 Mason 2nd class Day 0.4 223 89.20
9,999 Sundries L.S. 1.82 1.00 1.82
TOTAL 919.02
Add 1% for water charges 9.19
TOTAL 928.21
Add for contractor’s profit and
overheads @15% 139.23
Cost of 1000 nos 1067.44
Say 1067.44

15.8 Removing mortar from bricks and cleaning bricks including stacking within a lead
of 50 m (stacks of cleaned bricks shall be measured):
15.8.2 From brick work in lime mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1000 Nos.
Labour:
115 Coolie Day 1.4 207 289.80
114 Beldar Day 2.8 207 579.60
124 Mason 2nd class Day 0.8 223 178.40
9,999 Sundries L.S. 8.97 1.00 8.97
TOTAL 1056.77
Add 1% for water charges 10.57
TOTAL 1067.34
Add for contractor’s profit and
overheads @15% 160.10
Cost of 1000 nos 1227.44
Say 1227.44

15.8 Removing mortar from bricks and cleaning bricks including stacking within a lead
of 50 m (stacks of cleaned bricks shall be measured):
15.8.3 From brick work in cement mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1000 Nos.
Labour:
115 Coolie Day 1.5 207 310.50
114 Beldar Day 3.5 207 724.50
124 Mason 2nd class Day 1.24 223 276.52
9,999 Sundries L.S. 8.06 1.00 8.06
TOTAL 1319.58
Add 1% for water charges 13.20
TOTAL 1332.78
Add for contractor’s profit and
overheads @15% 199.92
Cost of 1000 nos 1532.69
Say 1532.69

15.9 Demolishing stone rubble masonry manually/by machanical means including


stacking of serviceable material and disposal of unserviceable material within 50 metres
lead asIn
15.9.1 perlime
directionof
mortar Engineer-in-charge:
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.49 207 101.43
114 Beldar Day 0.61 207 126.27
9,999 Sundries L.S. 1.95 1.00 1.95
TOTAL 229.65
Add 1% for water charges 2.30
TOTAL 231.95
Add for contractor’s profit and
overheads @15% 34.79
Cost of 1 cum 266.74
Say 266.74

15.9 Demolishing stone rubble masonry manually/by machanical means including


stacking of serviceable material and disposal of unserviceable material within 50 metres
lead asIn
15.9.2 percement
directionof
mortarEngineer-in-charge:
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 1.04 207 215.28
114 Beldar Day 1.3 207 269.10
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 487.11
Add 1% for water charges 4.87
TOTAL 491.98
Add for contractor’s profit and
overheads @15% 73.80
Cost of 1 cum 565.78
Say 565.78

15.10 Dismantling dressed stone work ashlar face stone work, marble work or precast
concrete work manually/by m achanical means including stacking of serviceable and
disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-
charge:
15.10.1 In lime mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.61 207 126.27
114 Beldar Day 0.78 207 161.46
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 290.46
Add 1% for water charges 2.90
TOTAL 293.36
Add for contractor’s profit and
overheads @15% 44.00
Cost of 1 cum 337.37
Say 337.37

15.10 Dism antling dressed stone work ashlar face stone work, marble work or precast
concrete work manually/by m achanical means including stacking of serviceable and
disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-
charge:
15.10.2 In cement mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 1.19 207 246.33
114 Beldar Day 1.55 207 320.85
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 569.91
Add 1% for water charges 5.70
TOTAL 575.61
Add for contractor’s profit and
overheads @15% 86.34
Cost of 1 cum 661.95
Say 661.95

15.11 Removing mortar from and cleaning stones and concrete articles (net quantity of
stacks of cleaned m aterial will be measured):
15.11.1 In lime mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.2 207 41.40
114 Beldar Day 0.2 207 41.40
124 Mason 2nd class Day 0.05 223 11.15
9,999 Sundries L.S. 0.52 1.00 0.52
TOTAL 94.47
Add 1% for water charges 0.94
TOTAL 95.41
Add for contractor’s profit and
overheads @15% 14.31
Cost of 1 cum 109.73
Say 109.73

15.11 Removing mortar from and cleaning stones and concrete articles (net quantity of
stacks of cleaned m aterial will be measured):
15.11.2 In cement mortar
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.2 207 41.40
114 Beldar Day 0.4 207 82.80
124 Mason 2nd class Day 0.05 223 11.15
9,999 Sundries L.S. 0.91 1.00 0.91
TOTAL 136.26
Add 1% for water charges 1.36
TOTAL 137.62
Add for contractor’s profit and
overheads @15% 20.64
Cost of 1 cum 158.27
Say 158.27

15.12 Dismantling doors, windows and clerestory windows (steel or wood) shutter
including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres
lead : Of area 3 sq. metres and below
15.12.1
Code Description Unit Quantity Rate Amount
Detail of cost for each
Labour:
103 Blacksmith 2nd class Day 0.05 223 11.15
114 Beldar Day 0.18 207 37.26
124 Mason 2nd class Day 0.1 223 22.30
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 72.14
Add 1% for water charges 0.72
TOTAL 72.86
Add for contractor’s profit and
overheads @15% 10.93
Cost of each 83.79
Say 83.79

15.12 Dismantling doors, windows and clerestory windows (steel or wood) shutter
including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres
lead : Of area beyond 3.00 sqm
15.12.2
Code Description Unit Quantity Rate Amount
Detail of cost for each
Labour:
103 Blacksmith 2nd class Day 0.07 223 15.61
114 Beldar Day 0.25 207 51.75
124 Mason 2nd class Day 0.13 223 28.99
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 99.08
Add 1% for water charges 0.99
TOTAL 100.07
Add for contractor’s profit and
overheads @15% 15.01
Cost of each 115.08
Say 115.08

15.13 Taking out doors, windows and clerestory window shutters (steel or wood)
including stacking within 50 metres lead:
15.13.1 Of area 3 sq. metre and below
Code Description Unit Quantity Rate Amount
Detail of cost for each
Labour:
112 Carpenter 2nd class Day 0.05 223 11.15
114 Beldar Day 0.08 207 16.56
9,999 Sundries L.S. 0.52 1.00 0.52
TOTAL 28.23
Add 1% for water charges 0.28
TOTAL 28.51
Add for contractor’s profit and
overheads @15% 4.28
Cost of each 32.79
Say 32.79

15.13 Taking out doors, windows and clerestory window shutters (steel or wood)
including stacking within 50 metres lead:
15.13.2 Of area beyond 3.00 sqm
Code Description Unit Quantity Rate Amount
Detail of cost for each
Labour:
112 Carpenter 2nd class Day 0.07 223 15.61
114 Beldar Day 0.1 207 20.70
9,999 Sundries L.S. 0.91 1.00 0.91
TOTAL
37.22
Add 1% for water charges 0.37
TOTAL 37.59
Add for contractor’s profit and
overheads @15% 5.64
Cost of each 43.23
Say 43.23

15.14 Dismantling wood work in frames, trusses, purlins and rafters upto 10 metres span
and 5 metres height including stacking the material within 50 metres lead:
15.14.1 Of sectional area 40 square centimetres and above.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
112 Carpenter 2nd class Day 2 223 446.00
114 Beldar Day 2 207 414.00
9,999 Sundries L.S. 13.39 1.00 13.39
TOTAL 873.39
Add 1% for water charges 8.73
TOTAL 882.12
Add for contractor’s profit and
overheads @15% 132.32
Cost of each 1014.44
Say 1014.44

15.14 Dismantling wood work in frames, trusses, purlins and rafters upto 10 metres span
and 5 metres height including stacking the material within 50 metres lead:
15.14.2 Of sectional area below 40 square centimetres.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 m
Labour:
112 Carpenter 2nd class Day 0.08 223 17.84
114 Beldar Day 0.08 207 16.56
9,999 Sundries L.S. 0.52 1.00 0.52
TOTAL 34.92
Add 1% for water charges 0.35
TOTAL 35.27
Add for contractor’s profit and
overheads @15% 5.29
Cost of 10 m 40.56
Cost of 1 m 4.06
Say 4.06

15.15 Extra for dismantling trusses, rafters, purlins etc. of wood work for every
additional span of one metre or part thereof beyond 10 metres:
15.15.1 Of sectional area 40 square centimetres and above.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum for every additional span of 1 metre
Labour:
103 Blacksmith 2nd class Day 0.2 223 44.60
114 Beldar Day 0.3 207 62.10
9,999 Sundries L.S. 13.39 1.00 13.39
TOTAL 120.09
Add 1% for water charges 1.20
TOTAL 121.29
Add for contractor’s profit and
overheads @15% 18.19
Cost of 1 cum / span 139.48
Say 139.48

15.15 Extra for dismantling trusses, rafters, purlins etc. of wood work for every
additional span of one metre or part thereof beyond 10 metres:
15.15.2 Of sectional area below 40 square centimetres.
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre for every additional span of 1 metre
Labour:
103 Blacksmith 2nd class Day 0.006 223 1.34
114 Beldar Day 0.008 207 1.66
9,999 Sundries L.S. 0.39 1.00 0.39
TOTAL 3.38
Add 1% for water charges 0.03
TOTAL 3.42
Add for contractor’s profit and
overheads @15% 0.51
Cost of 10 m 3.93
Cost of 1 m 0.39
Say 0.39

15.16 Extra for dismantling trusses, rafters, purlins etc. of wood work for every
additional height of one metre or part thereof beyond 5 metres:
15.16.1 Of sectional area 40 square centimetres and above.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum for every additional span of 1 metre
Labour:
103 Blacksmith 2nd class Day 0.25 223 55.75
114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 13.39 1.00 13.39
TOTAL 172.64
Add 1% for water charges 1.73
TOTAL 174.37
Add for contractor’s profit and
overheads @15% 26.15
Cost of 1 cum / span 200.52
Say 200.52

15.16 Extra for dismantling trusses, rafters, purlins etc. of wood work for every
additional height of one metre or part thereof beyond 5 metres:
15.16.2 Of sectional area below 40 square centimetres.
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre for every additional span of 1 metre
Labour:
103 Blacksmith 2nd class Day 0.01 223 2.23
114 Beldar Day 0.02 207 4.14
9,999 Sundries L.S. 0.39 1.00 0.39
TOTAL 6.76
Add 1% for water charges 0.07
TOTAL 6.83
Add for contractor’s profit and
overheads @15% 1.02
Cost of 10 m 7.85
Cost of 1 m 0.79
Say 0.79

15.17 Dism antling steel work in single sections including dismembering and stacking
within 50 metres lead in:
15.17.1 R.S. Joists
Code Description Unit Quantity Rate Amount
Detail of cost for 1 quintal
Labour:
103 Blacksmith 2nd class Day 0.05 223 11.15
100 Bandhani Day 0.1 180 18.00
114 Beldar Day 0.15 207 31.05
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 62.93
Add 1% for water charges 0.63
TOTAL 63.56
Add for contractor’s profit and
overheads @15% 9.53
Cost of 1 quintal 73.09
Cost of 1 kg 0.73
Say 0.73

15.17 Dismantling steel work in single sections including dismembering and stacking
within 50 metres lead in:
15.17.2 Channels, angles, tees and flats
Code Description Unit Quantity Rate Amount
Detail of cost for 1 quintal
Labour:
103 Blacksmith 2nd class Day 0.05 223 11.15
100 Bandhani Day 0.06 180 10.80
114 Beldar Day 0.1 207 20.70
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 45.38
Add 1% for water charges 0.45
TOTAL 45.83
Add for contractor’s profit and
overheads @15% 6.88
Cost of 1 quintal 52.71
Cost of 1 kg 0.53
Say 0.53

15.18 Dismantling steel work in built up sections in angles, tees, flats and channels
including all gusset plates, bolts, nuts, cutting rivets, welding etc. Including
dismembering
Code and stacking within 50metres lead. Unit Quantity
Description Rate Amount
Detail of cost for 1 quintal
Labour:
103 Blacksmith 2nd class Day 0.15 223 33.45
100 Bandhani Day 0.1 180 18.00
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 4.16 1.00 4.16
TOTAL 107.36
Add 1% for water charges 1.07
TOTAL 108.43
Add for contractor’s profit and
overheads @15% 16.27
Cost of 1 quintal 124.70
Cost of 1 kg 1.25
Say 1.25

15.19: Dismantling steel work manually/by mechanical means in built up sections


without dismembering and stacking within 50 metres lead as per direction of Engineer-
in-charge.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 quintal
Labour:
100 Bandhani Day 0.1 180 18.00
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 4.16 1.00 4.16
TOTAL 73.91
Add 1% for water charges 0.74
TOTAL 74.65
Add for contractor’s profit and
overheads @15% 11.20
Cost of 1 quintal 85.85
Cost of 1 kg 0.86
Say 0.86

15.20: Extra for dismantling trusses, rafters, purlins etc. of steel work for every
additional span of one metre or part thereof beyond 10 metres
Code Description Unit Quantity Rate Amount
Detail of cost for 1 quintal for every additional span of 1 metre beyond 10 metre
Labour:
100 Bandhani Day 0.02 180 3.60
114 Beldar Day 0.06 207 12.42
9,999 Sundries L.S. 0.39 1.00 0.39
TOTAL 16.41
Add 1% for water charges 0.16
TOTAL 16.57
Add for contractor’s profit and
overheads @15% 2.49
Cost of 1 quintal/ m span 19.06
Cost of 1 kg / m span 0.19
Say 0.19

15.21: Extra for dismantling trusses, rafters, purlins etc. of steel work for every
additional height of one metre or part thereof beyond 5 metres.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 quintal for every additional height of 1 metre beyond 5 metre
Labour:
100 Bandhani Day 0.02 180 3.60
114 Beldar Day 0.06 207 12.42
9,999 Sundries L.S. 0.39 1.00 0.39
TOTAL 16.41
Add 1% for water charges 0.16
TOTAL 16.57
Add for contractor’s profit and
overheads @15% 2.49
Cost of 1 quintal/ m height 19.06
Cost of 1 kg / m height 0.19
Say 0.19

15.22: Extra for marking of structural steel work required to be re-erected.


Code Description Unit Quantity Rate Amount
Detail of cost for 1 quintal
LABOUR

Labour:
130 Mistry Day 0.2 270 54.00
114 Beldar Day 0.2 207 41.40
TOTAL 95.40
Add 1% for water charges 0.95
TOTAL 96.35
Add for contractor’s profit and
overheads @15% 14.45
Cost of 1 quintal/ m height 110.81
Cost of 1 kg / m height 1.11
Say 1.11
15.23 : Dismantling tile work in floors and roofs laid in cement mortar including
stacking material within 50 metre lead.
15.23.1: For thickness of tiles above 10 mm and upto 25 mm
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.24 207 49.68
114 Beldar Day 0.12 207 24.84
124 Mason 2nd class Day 0.3 223 66.90
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 144.15
Add 1% for water charges 1.44
TOTAL 145.59
Add for contractor’s profit and
overheads @15% 21.84
Cost of 10 sqm 167.43
Cost of 1 sqm 16.74
Say 16.74

15.23 : Dismantling tile work in floors and roofs laid in cement mortar including
stacking material within 50 metre lead.
15.23.2: For thickness of tiles above 25 mm and upto 40 mm
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.24 207 49.68
114 Beldar Day 0.18 207 37.26
124 Mason 2nd class Day 0.59 223 131.57
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 221.24
Add 1% for water charges 2.21
TOTAL 223.45
Add for contractor’s profit and
overheads @15% 33.52
Cost of 10 sqm 256.97
Cost of 1 sqm 25.70
Say 25.70

15.24 : Demolishing dry brick pitching in floors, drains etc. including stacking
serviceable material and disposal of unserviceable material within 50 metres lead :
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 1 207 207.00
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 261.48
Add 1% for water charges 2.61
TOTAL 264.09
Add for contractor’s profit and
overheads @15% 39.61
Cost of 1 cum 303.71
Say 303.71

15.25: Dismantling stone slab flooring laid in cement mortar including stacking
of serviceable material and disposal of unserviceable material within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.75 207 155.25
114 Beldar Day 1.77 207 366.39
9,999 Sundries L.S. 8.06 1.00 8.06
TOTAL 529.70
Add 1% for water charges 5.30
TOTAL 535.00
Add for contractor’s profit and
overheads @15% 80.25
Cost of 10 sqm 615.25
Cost of 1 sqm 61.52
Say 61.52

15.26 : Demolishing brick tile covering in terracing including stacking of serviceable


material and disposal of unserviceable material within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.24 207 49.68
114 Beldar Day 0.16 207 33.12
124 Mason 2nd class Day 0.54 223 120.42
9,999 Sundries L.S. 2.47 1.00 2.47
TOTAL 205.69
Add 1% for water charges 2.06
TOTAL 207.75
Add for contractor’s profit and
overheads @15% 31.16
Cost of 10 sqm 238.91
Cost of 1 sqm 23.89
Say 23.89

15.27: Demolishing mud phaska in terracing and disposal ofmaterial within 50 metres
lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 cum
Labour:
115 Coolie Day 0.62 207 128.34
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 1.04 1.00 1.04
TOTAL 181.13
Add 1% for water charges 1.81
TOTAL 182.94
Add for contractor’s profit and
overheads @15% 27.44
Cost of 1 cum 210.38
Say 210.38

15.28 : Dismantling roofing including ridges, hips valleys and gutters etc., and stacking
the material within 50 metres lead of:
15.28.1 : G.S. Sheet
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
112 Carpenter 2nd class Day 0.5 223 111.50
114 Beldar Day 1 207 207.00
9,999 Sundries L.S. 6.76 1.00 6.76
TOTAL 325.26
Add 1% for water charges 3.25
TOTAL 328.51
Add for contractor’s profit and
overheads @15% 49.28
Cost of 10 sqm 377.79
Cost of 1 sqm 37.78
Say 37.78

15.28 : Dismantling roofing including ridges, hips valleys and gutters etc., and stacking
the material within 50 metres lead of:
15.28.2: Asbestos Sheet
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
112 Carpenter 2nd class Day 0.2 223 44.60
114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 5.33 1.00 5.33
TOTAL 153.43
Add 1% for water charges 1.53
TOTAL 154.96
Add for contractor’s profit and
overheads @15% 23.24
Cost of 10 sqm 178.21
Cost of 1 sqm 17.82
Say 17.82

15.29 : Dismantling stone slab roofing over wooden karries or R.C.C. battens
(dismantling karries and battens to be paid for separately) including stacking of
serviceable material and disposal of unserviceable material within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 sqm
Labour:
115 Coolie Day 0.75 207 155.25
114 Beldar Day 1.77 207 366.39
9,999 Sundries L.S. 8.06 1.00 8.06
TOTAL 529.70
Add 1% for water charges 5.30
TOTAL 535.00
Add for contractor’s profit and
overheads @15% 80.25
Cost of 1 sqm 615.25
Say 615.25

15.30 : Dismantling jack arch roofing and floors including stacking of serviceable
material and disposal of unserviceable material within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 1.21 207 250.47
114 Beldar Day 1.19 207 246.33
9,999 Sundries L.S. 8.06 1.00 8.06
TOTAL 504.86
Add 1% for water charges 5.05
TOTAL 509.91
Add for contractor’s profit and
overheads @15% 76.49
Cost of 10 sqm 586.39
Cost of 1 sqm 58.64
Say 58.64

15.31: Dismantling tiled roofing with battens boarding etc. complete including stacking
of serviceable material and disposal of unserviceable material within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.25 207 51.75
114 Beldar Day 1.73 207 358.11
9,999 Sundries L.S. 8.06 1.00 8.06
TOTAL 417.92
Add 1% for water charges 4.18
TOTAL 422.10
Add for contractor’s profit and
overheads @15% 63.31
Cost of 10 sqm 485.41
Cost of 1 sqm 48.54
Say 48.54

15.32 : Demolishing thatch roofing including mats, bamboo, jaffari etc. complete
including stacking of serviceable material and disposal of unserviceable material within
50 metres Description
Code lead. Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
114 Beldar Day 0.54 207 111.78
9,999 Sundries L.S. 3.64 1.00 3.64
TOTAL 115.42
Add 1% for water charges 1.15
TOTAL 116.57
Add for contractor’s profit and
overheads @15% 17.49
Cost of 10 sqm 134.06
Cost of 1 sqm 13.41
Say 13.41

15.33: Dismantling wooden bailies in posts and struts including stacking within 50
Code lead.
metres Description Unit Quantity Rate Amount
Detail of cost for 50 metres
Labour:
115 Coolie Day 0.5 207 103.50
114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 0.52 1.00 0.52
TOTAL 207.52
Add 1% for water charges 2.08
TOTAL 209.60
Add for contractor’s profit and
overheads @15% 31.44
Cost of 50 metres 241.03
Cost of 1 metre 4.82
Say 4.82

15.34 : Dismantling and stacking within 50 metres lead, fencing posts or struts including
all earth work and dismantling of concrete etc. in base of:
15.34.1: ‘T’ or ‘L’ iron or pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for each
Labour:
115 Coolie Day 0.067 207 13.87
114 Beldar Day 0.107 207 22.15
9,999 Sundries, excavation & lifting etc. L.S. 15.08 1.00 15.08
TOTAL 51.10
Add 1% for water charges 0.51
TOTAL 51.61
Add for contractor’s profit and
overheads @15% 7.74
Cost of each 59.35
Say 59.35

15.34 : Dismantling and stacking within 50 metres lead, fencing posts or struts including
all earth work and dismantling of concrete etc. in base of:
15.34.2: R.C.C
Code Description Unit Quantity Rate Amount
Detail of cost for each
Labour:
115 Coolie Day 0.06 207 12.42
114 Beldar Day 0.097 207 20.08
9,999 Sundries, excavation & lifting etc. L.S. 24.44 1.00 24.44
TOTAL 56.94
Add 1% for water charges 0.57
TOTAL 57.51
Add for contractor’s profit and
overheads @15% 8.63
Cost of each 66.13
Say 66.13

15.35 : Cutting bailies or wooden posts of fencing at the point of projection above
the concrete or ground and stacking the same within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 1ballie (post)
Labour:
9,999 Cutting and transportation L.S. 4.16 1.00 4.16
TOTAL 4.16
Add 1% for water charges 0.04
TOTAL 4.20
Add for contractor’s profit and
overheads @15% 0.63
Cost of each 4.83
Say 4.83

15.36 : Dismantling barbed wire or flexible wire rope in fencing including making rolls
and stacking within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 quintal
Labour:
114 Beldar Day 3.5 207 724.50
9,999 Sundries L.S. 5.33 1.00 5.33
TOTAL 729.83
Add 1% for water charges 7.30
TOTAL 737.13
Add for contractor’s profit and
overheads @15% 110.57
Cost of 1 quintal 847.70
Cost of 1 kg 8.48
Say 8.48

15.37 : Dismantling wooden trellis work excluding frames but including stacking
the serviceable material within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.25 207 51.75
114 Beldar Day 0.25 207 51.75
124 Mason 2nd class Day 0.1 223 22.30
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 128.53
Add 1% for water charges 1.29
TOTAL 129.82
Add for contractor’s profit and
overheads @15% 19.47
Cost of 10 sqm 149.29
Cost of 1 sqm 14.93
Say 14.93

15.38 : Dismantling expanded metal or I.R.C. fabrics with necessary battens and beading
including stacking the serviceable material within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.2 207 41.40
114 Beldar Day 0.4 207 82.80
112 Carpenter 2nd class Day 0.1 223 22.30
9,999 Sundries L.S. 4.16 1.00 4.16
TOTAL 150.66
Add 1% for water charges 1.51
TOTAL 152.17
Add for contractor’s profit and
overheads @15% 22.82
Cost of 10 sqm 174.99
Cost of 1 sqm 17.50
Say 17.50

15.39 : Dism antling wooden boardings in lining of walls and partitions, excluding
supporting members but includmg stacking within 50 metres lead :
15.39.1: Upto 10mm thick
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.2 207 41.40
114 Beldar Day 0.2 207 41.40
112 Carpenter 2nd class Day 0.15 223 33.45
9,999 Sundries L.S. 5.33 1.00 5.33
TOTAL 121.58
Add 1% for water charges 1.22
TOTAL 122.80
Add for contractor’s profit and
overheads @15% 18.42
Cost of 10 sqm 141.22
Cost of 1 sqm 14.12
Say 14.12

15.39: Dismantling wooden boardings in lining of walls and partitions, excluding


supporting members but includmg stacking within 50 metres lead :
15.39.2 Thickness above 10 mm upto 25 mm
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.25 207 51.75
114 Beldar Day 0.25 207 51.75
112 Carpenter 2nd class Day 0.2 223 44.60
9,999 Sundries L.S. 6.76 1.00 6.76
TOTAL 154.86
Add 1% for water charges 1.55
TOTAL 156.41
Add for contractor’s profit and
overheads @15% 23.46
Cost of 10 sqm 179.87
Cost of 1 sqm 17.99
Say 17.99

15.39: Dismantling wooden boardings in lining of walls and partitions, excluding


supporting members but includmg stacking within 50 metres lead :
15.39.3 Thickness above 25 mm upto 40 mm
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.3 207 62.10
114 Beldar Day 0.3 207 62.10
112 Carpenter 2nd class Day 0.2 223 44.60
9,999 Sundries L.S. 13.39 1.00 13.39
TOTAL 182.19
Add 1% for water charges 1.82
TOTAL 184.01
Add for contractor’s profit and
overheads @15% 27.60
Cost of 10 sqm 211.61
Cost of 1 sqm 21.16
Say 21.16

15.40: Dismantling precast conerete or stone slab in walls, partition walls etc, including
stacking within 50 metres lead.
15.40.1: Thickness upto 40mm
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.5 207 103.50
114 Beldar Day 2 207 414.00
124 Mason 2nd class Day 0.2 223 44.60
9,999 Sundries L.S. 13.39 1.00 13.39
TOTAL 575.49
Add 1% for water charges 5.75
TOTAL 581.24
Add for contractor’s profit and
overheads @15% 87.19
Cost of 10 sqm 668.43
Cost of 1 sqm 66.84
Say 66.84

15.40: Dismantling precast conerete or stone slab in walls, partition walls etc, including
stacking within 50 metres lead.
15.40.2 Thickness above 40 mm upto 75 mm
Code Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
115 Coolie Day 0.75 207 155.25
114 Beldar Day 3 207 621.00
124 Mason 2nd class Day 0.3 223 66.90
9,999 Sundries L.S. 18.85 1.00 18.85
TOTAL 862.00
Add 1% for water charges 8.62
TOTAL 870.62
Add for contractor’s profit and
overheads @15% 130.59
Cost of 10 sqm 1001.21
Cost of 1 sqm 100.12
Say 100.12

15.41 : Dismantling cement asbestos, Celotax or other hard board ceiling or partition
walls including stacking of serviceable materials and disposal of unserviceable materials
within 50 metres
Code lead.
Description Unit Quantity Rate Amount
Detail of cost for 10 sqm
Labour:
114 Beldar Day 0.3 207 62.10
112 Carpenter 2nd class Day 0.2 223 44.60
9,999 Sundries L.S. 5.33 1.00 5.33
TOTAL 112.03
Add 1% for water charges 1.12
TOTAL 113.15
Add for contractor’s profit and
overheads @15% 16.97
Cost of 10 sqm 130.12
Cost of 1 sqm 13.01
Say 13.01

15.42: Dismantling C.I. or asbestos rain water pipe with fittings and clamps including
stacking the material within 50 metres lead :
5.42.1 75 to 80 mm dia pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 metres
Labour:
115 Coolie Day 0.36 207 74.52
114 Beldar Day 0.36 207 74.52
9,999 Sundries L.S. 0.91 1.00 0.91
TOTAL 149.95
Add 1% for water charges 1.50
TOTAL 151.45
Add for contractor’s profit and
overheads @15% 22.72
Cost of 10 m 174.17
Cost of 1 m 17.42
Say 17.42

15.42: Dismantling C.I. or asbestos rain water pipe with fittings and clamps including
stacking the material within 50 metres lead :
5.42.2: 100 mm dia pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 metres
Labour:
115 Coolie Day 0.36 207 74.52
114 Beldar Day 0.38 207 78.66
9,999 Sundries L.S. 1.56 1.00 1.56
TOTAL 154.74
Add 1% for water charges 1.55
TOTAL 156.29
Add for contractor’s profit and
overheads @15% 23.44
Cost of 10 m 179.73
Cost of 1 m 17.97
Say 17.97

15.42: Dismantling C.I. or asbestos rain water pipe with fittings and clamps including
stacking the material within 50 metres lead :
5.42.3: 150 mm dia pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 metres
Labour:
115 Coolie Day 0.36 207 74.52
114 Beldar Day 0.4 207 82.80
9,999 Sundries L.S. 2.08 1.00 2.08
TOTAL 159.40
Add 1% for water charges 1.59
TOTAL 160.99
Add for contractor’s profit and
overheads @15% 24.15
Cost of 10 m 185.14
Cost of 1 m 18.51
Say 18.51

15.43: Dismantling manually / by mechanical means including stacking of serviceable


material and disposal of unserviceable material within 50metres lead as per direction of
Engineer-in-charge : macadam road
15.43.1: Water bound
Code Description Unit Quantity Rate Amount
Detail of cost for 36 sqm
Labour:
115 Coolie Day 2.4 207 496.80
114 Beldar Day 4.8 207 993.60
9,999 Sundries L.S. 89.7 1.00 89.70
TOTAL 1580.10
Add 1% for water charges 15.80
TOTAL 1595.90
Add for contractor’s profit and
overheads @15% 239.39
Cost of 36 sqm 1835.29
Cost of 1 sqm 50.98
Say 50.98

15.43: Dismantling manually / by mechanical means including stacking of serviceable


material and disposal of unserviceable material within 50metres lead as per direction of
Engineer-in-charge
15.43.2: Bituminous: road
Code Description Unit Quantity Rate Amount
Detail of cost for 36 sqm
Labour:
115 Coolie Day 4.8 207 993.60
114 Beldar Day 9.6 207 1987.20
9,999 Sundries L.S. 107.64 1.00 107.64
TOTAL 3088.44
Add 1% for water charges 30.88
TOTAL 3119.32
Add for contractor’s profit and
overheads @15% 467.90
Cost of 36 sqm 3587.22
Cost of 1 sqm 99.65
Say 99.65

15.44 Dism antling G.I. pipes (external work) including excavation and refilling
trenches after taking out the pipes manually / by machanical means including stacking of
pipes within 50 metres lead as per direction of Engineer-in-charge :
15.44.1 15 mm to 40 mm nominal bore
Code Description Unit Quantity Rate Amount
Detail of cost for 10 metres
Labour:
115 Coolie Day 0.66 207 136.62
114 Beldar Day 0.66 207 136.62
9,999 Sundries L.S. 35.88 1.00 35.88
TOTAL 309.12
Add 1% for water charges 3.09
TOTAL 312.21
Add for contractor’s profit and
overheads @15% 46.83
Cost of 10 m 359.04
Cost of 1 m 35.90
Say 35.90

15.44 Dism antling G.I. pipes (external work) including excavation and refilling
trenches after taking out the pipes manually / by machanical means including stacking of
pipes within 50 metres lead as per direction of Engineer-in-charge :
15.44.2 Above 40 mm nominal bore
Code Description Unit Quantity Rate Amount
Detail of cost for 10 metres
Labour:
115 Coolie Day 0.66 207 136.62
114 Beldar Day 0.66 207 136.62
9,999 Sundries L.S. 71.76 1.00 71.76
TOTAL 345.00
Add 1% for water charges 3.45
TOTAL 348.45
Add for contractor’s profit and
overheads @15% 52.27
Cost of 10 m 400.72
Cost of 1 m 40.07
Say 40.07

15.45 Dismantling C.I. pipes including excavation and refilling trenches after taking out
the pipes manually / by machanical means, breaking lead caulked joints, melting of lead
and making into blocks including stacking of pipes, lead at site within 50 metre lead as
per direction of Engineer-in-charge:
15.45.1 Upto 150 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 40.26 metre or 11 nos joints
761 Fuel wood quintal 0.46 265.00 121.90
771 Kerosene oil litre 0.38 25.00 9.50
LABOUR

115 Coolie Day 4.8 207 993.60


117 Assistant Fitter or 2nd class Fitter Day 0.63 223 140.49
114 Beldar Day 9.17 207 1898.19
101 Bhisti Day 0.27 180 48.60
9,999 Sundries L.S. 53.82 1.00 53.82
TOTAL 3266.10
Add 1% for water charges 32.66
TOTAL 3298.76
Add for contractor’s profit and
overheads @15% 494.81
Cost of 40.26 m 3793.58
Cost of 1 m 94.23
Say 94.23

15.45 Dism antling C.I. pipes including excavation and refilling trenches after taking out
the pipes manually / by machanical means, breaking lead caulked joints, melting of lead
and making into blocks including stacking of pipes, lead at site within 50 metre lead as
per direction of Engineer-in-charge:
15.45.2 Above 150 mm dia upto 300 mm dia.
Code Description Unit Quantity Rate Amount
Detail of cost for 40.26 metre or 11 nos joints
761 Fuel wood quintal 1.03 265.00 272.95
771 Kerosene oil litre 1.14 25.00 28.50
LABOUR

115 Coolie Day 5.12 207 1059.84


117 Assistant Fitter or 2nd class Fitter Day 1.3 223 289.90
114 Beldar Day 12.49 207 2585.43
101 Bhisti Day 0.29 180 52.20
9,999 Sundries L.S. 80.73 1.00 80.73
TOTAL 4369.55
Add 1% for water charges 43.70
TOTAL 4413.25
Add for contractor’s profit and
overheads @15% 661.99
Cost of 40.26 m 5075.23
Cost of 1 m 126.06
Say 126.06

15.45 Dism antling C.I. pipes including excavation and refilling trenches after taking out
the pipes manually / by machanical means, breaking lead caulked joints, melting of lead
and making into blocks including stacking of pipes, lead at site within 50 metre lead as
per direction
15.45.3 Above of300
Engineer-in-charge:
mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 40.26 metre or 11 nos joints
761 Fuel wood quintal 1.4 265.00 371.00
771 Kerosene oil litre 2.27 25.00 56.75
LABOUR

115 Coolie Day 5.46 207 1130.22


117 Assistant Fitter or 2nd class Fitter Day 2.25 223 501.75
114 Beldar Day 16.82 207 3481.74
101 Bhisti Day 0.31 180 55.80
9,999 Sundries L.S. 134.55 1.00 134.55
TOTAL 5731.81
Add 1% for water charges 57.32
TOTAL 5789.13
Add for contractor’s profit and
overheads @15% 868.37
Cost of 40.26 m 6657.50
Cost of 1 m 165.36
Say 165.36

15.46 Dism antling steel cylinder R.C. pipes including excavation and refilling trenches
after taking out the pipes manually/ by machanical maeans breaking lead caulked joints,
melting of lead and making into blocks including stacking of pipes, lead at site within 50
metres
15.46.1lead
Uptoas600
per mm
direction of Engineer-in-charge:
diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 40.26 metre or 11 nos joints
761 Fuel wood quintal 1.4 265.00 371.00
771 Kerosene oil litre 2.27 25.00 56.75
LABOUR

115 Coolie Day 5.46 207 1130.22


117 Assistant Fitter or 2nd class Fitter Day 2.25 223 501.75
114 Beldar Day 16.82 207 3481.74
101 Bhisti Day 0.31 180 55.80
9,999 Sundries L.S. 134.55 1.00 134.55
TOTAL 5731.81
Add 1% for water charges 57.32
TOTAL 5789.13
Add for contractor’s profit and
overheads @15% 868.37
Cost of 40.26 m 6657.50
Cost of 1 m 165.36
Say 165.36

15.46 Dism antling steel cylinder R.C. pipes including excavation and refilling trenches
after taking out the pipes manually/ by machanical maeans breaking lead caulked joints,
melting of lead and making into blocks including stacking of pipes, lead at site within 50
metres
15.46.2lead as per
Above 600direction of Engineer-in-charge:
mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 40.26 metre or 11 nos joints
761 Fuel wood quintal 3.08 265.00 816.20
771 Kerosene oil litre 5 25.00 125.00
LABOUR

115 Coolie Day 16.25 207 3363.75


117 Assistant Fitter or 2nd class Fitter Day 10 223 2230.00
114 Beldar Day 35.82 207 7414.74
101 Bhisti Day 0.93 180 167.40
9,999 Sundries L.S. 179.4 1.00 179.40
TOTAL 14296.49
Add 1% for water charges 142.96
TOTAL 14439.45
Add for contractor’s profit and
overheads @15% 2165.92
Cost of 40.26 m 16605.37
Cost of 1 m 412.45
Say 412.45

15.47 Dism antling asbestos cement pressure pipes including excavation and refilling
trenches after taking out the pipes manually / by mechanical means and stacking pipes
within 50 metres lead as per direction of Engineer-in-charge:
15.47.1 Upto 150 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10 metre or 11 nos joints
LABOUR

115 Coolie Day 1.57 207 324.99


114 Beldar Day 1.52 207 314.64
101 Bhisti Day 0.07 180 12.60
9,999 Sundries L.S. 1.56 1.00 1.56
TOTAL 653.79
Add 1% for water charges 6.54
TOTAL 660.33
Add for contractor’s profit and
overheads @15% 99.05
Cost of 10 m 759.38
Cost of 1 m 75.94
Say 75.94

15.47 Dism antling asbestos cement pressure pipes including excavation and refilling
trenches after taking out the pipes manually / by mechanical means and stacking pipes
within 50 metres lead as per direction of Engineer-in-charge:
15.47.2 Above 150 m m diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10 metre or 11 nos joints
LABOUR

115 Coolie Day 2.16 207 447.12


114 Beldar Day 1.6 207 331.20
101 Bhisti Day 0.07 180 12.60
9,999 Sundries L.S. 3.77 1.00 3.77
TOTAL 794.69
Add 1% for water charges 7.95
TOTAL 802.64
Add for contractor’s profit and
overheads @15% 120.40
Cost of 10 m 923.03
Cost of 1 m 92.30
Say 92.30

15.48 Taking out C .I. cover with frame from R.C.C. top slab of manholes of various
sizes including demolishing of R.C.C. work manually / by mechanical means and
stacking of usefull materials near the site and disposal of unserviceable materials within
50 metres lead as per direction of Engineer-in-charge.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 man hole
LABOUR

115 Coolie Day 0.14 207 28.98


114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 8.45 1.00 8.45
TOTAL 140.93
Add 1% for water charges 1.41
TOTAL 142.34
Add for contractor’s profit and
overheads @15% 21.35
Cost of each 163.69
Say 163.69

15.49 Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of
various sizes including demolishing of R.C.C. work manually/ by mechanical means and
stacking of useful materials near the site and disposal of unserviceable materials within
50 metres Description
Code lead as per direction of Engineer-in-charge.Unit Quantity Rate Amount
Detail of cost for 1 man hole
LABOUR

115 Coolie Day 0.08 207 16.56


114 Beldar Day 0.29 207 60.03
9,999 Sundries L.S. 5.98 1.00 5.98
TOTAL 82.57
Add 1% for water charges 0.83
TOTAL 83.40
Add for contractor’s profit and
overheads @15% 12.51
Cost of each 95.91
Say 95.91

15.50 Dismantling of R.C.C. spun vent shaft including excavating the cement concrete
pit completely, taking out the shaft, refilling the excavated gap, stacking the useful
materials near the site and disposal of unserviceable materials within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 each
LABOUR

115 Coolie Day 0.58 207 120.06


114 Beldar Day 1.97 207 407.79
123 Mason 1st class Day 0.12 270 32.40
124 Mason 2nd class Day 0.12 223 26.76
130 Mistry Day 0.25 270 67.50
100 Bandhani Day 1 180 180.00
9,999 Sundries L.S. 56.16 1.00 56.16
TOTAL 890.67
Add 1% for water charges 8.91
TOTAL 899.58
Add for contractor’s profit and
overheads @15% 134.94
Cost of each 1034.51
Say 1034.51

15.51 Dismantling of road gully chamber of various sizes including C.I. grating with
frame including stacking of useful materials near the site and disposal of unserviceable
materials into municipal dumps within 50 metres lead including refilling the
excavated gap.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 chamber
LABOUR
115 Coolie Day 0.37 207 76.59
114 Beldar Day 0.52 207 107.64
9,999 Sundries L.S. 8.32 1.00 8.32
TOTAL 192.55
Add 1% for water charges 1.93
TOTAL 194.48
Add for contractor’s profit and
overheads @15% 29.17
Cost of each 223.65
Say 223.65

15.52 Dismantling of flushing cistern of any size including stacking of useful materials
near the site and disposal of unserviceable materials within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost for each
LABOUR

116 Fitter (grade 1) Day 0.25 270 67.50


114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 17.94 1.00 17.94
TOTAL 188.94
Add 1% for water charges 1.89
TOTAL 190.83
Add for contractor’s profit and
overheads @15% 28.62
Cost of each 219.45
Say 219.45

15.53 Dismantling of C.I. sluice valve including stacking of useful materials within a
lead of 50
15.53.1 metres
Upto 150mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost of dismantling 10 sluice valves
LABOUR

116 Fitter (grade 1) Day 0.6 270 162.00


117 Assistant Fitter or 2nd class Fitter Day 0.4 223 89.20
114 Beldar Day 1.6 207 331.20
9,999 Sundries L.S. 89.7 1.00 89.70
TOTAL 672.10
Add 1% for water charges 6.72
TOTAL 678.82
Add for contractor’s profit and
overheads @15% 101.82
Cost of 10 nos. 780.64
Cost of 1 no. 78.06
Say 78.06

15.53 Dismantling of C.I. sluice valve including stacking of useful materials within a
lead of 50
15.53.2 metres
Above 150 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost of dismantling 10 sluice valves
LABOUR

116 Fitter (grade 1) Day 2.4 270 648.00


117 Assistant Fitter or 2nd class Fitter Day 1.54 223 343.42
114 Beldar Day 6.4 207 1324.80
9,999 Sundries L.S. 89.7 1.00 89.70
TOTAL 2405.92
Add 1% for water charges 24.06
TOTAL 2429.98
Add for contractor’s profit and
overheads @15% 364.50
Cost of 10 nos. 2794.48
Cost of 1 no. 279.45
Say 279.45

15.54 Dismantling of spindle fire hydrant including stacking of useful materials within
50 metres Description
Code lead. Unit Quantity Rate Amount
Detail of cost of 10 nos
LABOUR

116 Fitter (grade 1) Day 1.5 270 405.00


9,999 Sundries L.S. 89.7 1.00 89.70
114 Beldar Day 4 207 828.00
TOTAL 1322.70
Add 1% for water charges 13.23
TOTAL 1335.93
Add for contractor’s profit and
overheads @15% 200.39
Cost of 10 nos. 1536.32
Cost of 1 no. 153.63
Say 153.63

15.55 Dismantling of cement concrete platform along with curtain walls and base
concrete etc. including stacking of useful materials near the site and disposal of
unserviceable
15.55.1 120 x materials within to
120 cm (outside 50outside)
metres lead :
Code Description Unit Quantity Rate Amount
Detail of cost for one platform
LABOUR

115 Coolie Day 0.45 207 93.15


114 Beldar Day 0.6 207 124.20
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 218.78
Add 1% for water charges 2.19
TOTAL 220.97
Add for contractor’s profit and
overheads @15% 33.15
Cost of each 254.11
Say 254.11

15.55 Dismantling of cement concrete platform along with curtain walls and base
concrete etc. including stacking of useful materials near the site and disposal of
unserviceable
15.55.2 210 x materials within to
120 cm (outside 50outside)
metres lead :
Code Description Unit Quantity Rate Amount
Detail of cost for one platform
LABOUR

115 Coolie Day 0.67 207 138.69


114 Beldar Day 0.94 207 194.58
9,999 Sundries L.S. 2.34 1.00 2.34
TOTAL 335.61
Add 1% for water charges 3.36
TOTAL 338.97
Add for contractor’s profit and
overheads @15% 50.84
Cost of each 389.81
Say 389.81

15.55 Dismantling of cement concrete platform along with curtain walls and base
concrete etc. including stacking of useful materials near the site and disposal of
unserviceable
15.55.3 320 x materials within to
120 cm (outside 50outside
metres lead :
Code Description Unit Quantity Rate Amount
Detail of cost for one platform
LABOUR

115 Coolie Day 0.96 207 198.72


114 Beldar Day 1.32 207 273.24
9,999 Sundries L.S. 2.99 1.00 2.99
TOTAL 474.95
Add 1% for water charges 4.75
TOTAL 479.70
Add for contractor’s profit and
overheads @15% 71.95
Cost of each 551.65
Say 551.65

15.56 Dismantling old plaster or skirting raking out joints and cleaning the surface for
plaster including disposal of rubbish to the dumping ground within 50 metres lead.
Code Description Unit Quantity Rate Amount
Detail of cost of 10 sqm
LABOUR

115 Coolie Day 0.08 207 16.56


101 Bhisti Day 0.07 180 12.60
9,999 Sundries L.S. 1.43 1.00 1.43
114 Beldar Day 0.36 207 74.52
TOTAL 105.11
Add 1% for water charges 1.05
TOTAL 106.16
Add for contractor’s profit and
overheads @15% 15.92
Cost of 10 sqm 122.09
Cost of 1 sqm 12.21
Say 12.21

15.57 Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and
false ceiling including disposal of unserviceable surplus m aterial and stacking of
serviceable material with in 50 meters lead as directed by Engineer-in-charge.
Code Description Unit Quantity Rate Amount
Detail of cost of 10 sqm
LABOUR

112 Carpenter 2nd class Day 0.2 223 44.60


9,999 Sundries L.S. 5.38 1.00 5.38
114 Beldar Day 0.3 207 62.10
TOTAL 112.08
Add 1% for water charges 1.12
TOTAL 113.20
Add for contractor’s profit and
overheads @15% 16.98
Cost of 10 sqm 130.18
Cost of 1 sqm 13.02
Say 13.02

15.58 Demolishing C.C. /R.C.C. work by mechanical means and stockpiling at


designated locations and disposal of dismantled materials upto a lead of 1000m,
stacking serviceable and unserviceable material separately including cutting
reinforcement
Code bars.
Description Unit Quantity Rate Amount
Details of cost for 1 cum
LABOUR

128 Mate Day 0.03 313 9.39


139 Skilled Beldar Day 0.5 180 90.00
103 Blacksmith 2nd class Day 0.5 223 111.50
39 Tractor trolley Day 0.05 600.00 30.00
40 Air compressor 250 cfm with two leads Day 0.125
for preumatic cutters/ ham mers.
### 200.00
41 Joint cutting machine with 2-3 blades Day 0.125
800.00 100.00
114 Beldar Day 1 207 207.00
TOTAL 747.89
Add 1% for water charges 7.48
TOTAL 755.37
Add for contractor’s profit and
overheads @15% 113.31
Cost of 1 cum 868.67
Say 868.67

15.59 Dismantling of flexible pavement (bituminous courses) by mechanical means and


disposal of dismantled material upto a lead of 1000 metres, as per direction of
Engineer-in-charge.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
LABOUR

128 Mate Day 0.01 313 3.13


39 Tractor trolley Day 0.0475 600.00 28.50
38 Tractor with ripper attachment Day 0.002 600.00 1.20
114 Beldar Day 0.3 207 62.10
TOTAL 94.93
Add 1% for water charges 0.95
TOTAL 95.88
Add for contractor’s profit and
overheads @15% 14.38
Cost of 1 cum 110.26
Say 110.26
16.1 : Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne
capacity after excavating earth to an average of 22.5 cm. depth, dressing to camber and
consolidating with road roller including making good the undulations etc. and re-rolling
the sub grade and disposal of surplus earth lead upto 50 metres.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm.
Materials:
1235 Diesel oil litre 1.944 53.17 103.36
Labour:
128 Mate Day 1.8 313 563.40
113 Chowkidar Day 0.108 207 22.36
114 Beldar Day 0.27 207 55.89
115 Coolie Day 18 207 3726.00
3 Hire charges of Diesel Road Roller - 8 to litre 0.108
10 tonne 500.00 54.00
9,999 Carriage of diesel L.S. 2.86 1.00 2.86
9,999 Sundries L.S. 13.52 1.00 13.52
TOTAL 4541.39
Add 1% for water charges 45.41
TOTAL 4586.80
Add for contractor’s profit and
overheads @15% 688.02
Cost of 100 sqm 5274.82
Cost of 1 sqm 52.75
Say 52.75

16.2 : Extra for compaction of earth work in embankment under optimum moisture
conditions to give at least 95% of the maximum dry density (proctor density).
Code Description Unit Quantity Rate Amount
Details of cost for 10 cum
Materials:
1235 Diesel oil litre 0.144 53.17 7.66
Labour:
101 Bhishti Day 0.17 180 30.60
113 Chowkidar Day 0.008 207 1.66
3 Hire charges of Diesel Road Roller - 8 to litre 0.008
10 tonne 500.00 4.00
9,999 Carriage of diesel L.S. 0.39 1.00 0.39
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 45.73
Add 1% for water charges 0.46
TOTAL 46.19
Add for contractor’s profit and
overheads @15% 6.93
Cost of 10 cum 53.12
Cost of 1 cum 5.31
Say 5.31

16.3 : Supplying and stacking at site.


16.3.1 : 90 mm to 45 mm size stone aggregate.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
2901 Stone Aggregate 125 mm (one size) cum 0.1 700.00 70.00
2902 Stone Aggregate 90 mm (one size) cum 0.65 700.00 455.00
291 Stone Aggregate 63 mm (one size) cum 0.25 900.00 225.00
2206 Carriage of stone cum 1 57.83 57.83
TOTAL 807.83
Add 1% for water charges 8.08
TOTAL 815.91
Add for contractor’s profit and
overheads @15% 122.39
Cost of 1 cum 938.29
Say 938.29

16.3 Supplying and stacking at site.


16.3.2 63 mm to 45 mm size stone aggregate.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
2902 Stone Aggregate 90 mm (one size) cum 0.1 700.00 70.00
291 Stone Aggregate 63 mm (one size) cum 0.65 900.00 585.00
292 Stone Aggregate 53 mm (one size) cum 0.25 1000.00 250.00
2206 Carriage of stone cum 1 57.83 57.83
TOTAL 962.83
Add 1% for water charges 9.63
TOTAL 972.46
Add for contractor’s profit and
overheads @15% 145.87
Cost of 1 cum 1118.33
Say 1118.33

16.3 : Supplying and stacking at site.


16.3.3 : 53 mm to 22.4 mm size stone aggregate.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
291 Stone Aggregate 63 mm (one size) cum 0.05 900.00 45.00
292 Stone Aggregate 53 mm (one size) cum 0.3 1000.00 300.00
293 Stone Aggregate 45 mm (one size) cum 0.65 1000.00 650.00
2206 Carriage of stone cum 1 57.83 57.83
TOTAL 1052.83
Add 1% for water charges 10.53
TOTAL 1063.36
Add for contractor’s profit and
overheads @15% 159.50
Cost of 1 cum 1222.86
Say 1222.86

16.3 Supplying and stacking at site.


16.3.4 Over burnt (Jhama) brick aggregate 120 mm to 40 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
2908 Brick aggregate 120 mm to 40 mm size cum 1 285.00 285.00
2260 Carriage cum 1 57.83 57.83
TOTAL 342.83
Add 1% for water charges 3.43
TOTAL 346.26
Add for contractor’s profit and
overheads @15% 51.94
Cost of 1 cum 398.20
Say 398.20
16.3 Supplying and stacking at site.
16.3.5 Over burnt (Jhama) brick aggregate 90 mm to 45 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
2909 Brick aggregate 90mm to 45mm cum 1 320.00 320.00
2260 Carriage cum 1 57.83 57.83
TOTAL 377.83
Add 1% for water charges 3.78
TOTAL 381.61
Add for contractor’s profit and
overheads @15% 57.24
Cost of 1 cum 438.85
Say 438.85

16.3 Supplying and stacking at site.


16.3.6 Stone screening 13.2 mm nominal size (Type A).
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
2910 Stone chippings 13.2mm cum 0.05 1050.00 52.50
2911 Stone chippings 10mm/11.2mm cum 0.8 1050.00 840.00
2903 Stone chippings 5.6mm cum 0.15 350.00 52.50
2202 Carriage of stone cum 1 53.21 53.21
TOTAL 998.21
Add 1% for water charges 9.98
TOTAL 1008.19
Add for contractor’s profit and
overheads @15% 151.23
Cost of 1 cum 1159.42
Say 1159.42

16.3 Supplying and stacking at site.


16.3.7 Stone screening 11.2 mm nominal size (Type B)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
2911 Stone chippings 10mm/11.2mm cum 0.1 1050.00 105.00
2903 Stone chippings 5.6mm cum 0.75 350.00 262.50
2904 Stone s creenings 180 mircorn cum 0.15 350.00 52.50
2202 Carriage of stone cum 0.85 53.21 45.23
2267 Carriage of stone screenings cum 0.15 53.21 7.98
TOTAL 473.21
Add 1% for water charges 4.73
TOTAL 477.94
Add for contractor’s profit and
overheads @15% 71.69
Cost of 1 cum 549.63
Say 549.63

16.3 Supplying and stacking at site.


16.3.8 Red bajri
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
304 Cost of bajri at quarry cum 1 700.00 700.00
2311 Carriage of bajri cum 1 53.21 53.21
TOTAL 753.21
Add 1% for water charges 7.53
TOTAL 760.74
Add for contractor’s profit and
overheads @15% 114.11
Cost of 1 cum 874.85
Say 874.85

16.3 Supplying and stacking at site.


16.3.9 Good earth.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Labour:
114 Beldar Day 0.177 207 36.64
115 Coolie Day 0.167 207 34.57
979 Royalty for good earth cum 1 11.00 11.00
2241 Carriage of good earth by mechanical cum 1 66.51 66.51
transport upto 1 km lead
TOTAL 148.72
Add 1% for water charges 1.49
TOTAL 150.21
Add for contractor’s profit and
overheads @15% 22.53
Cost of 1 cum 172.74
Say 172.74

16.3 Supplying and stacking at site.


16.3.10 Moorum.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Labour:
810 Cost of moorum at quarry cum 1 333.00 333.00
2265 Carriage cum 1 53.21 53.21
TOTAL 386.21
Add 1% for water charges 3.86
TOTAL 390.07
Add for contractor’s profit and
overheads @15% 58.51
Cost of 1 cum 448.58
Say 448.58

16.4 Laying , spreading and compacting stone aggregate of specified sizes to WBM
specifications including spreading in uniform thickness, hand picking , rolling with 3
wheeled road / vibratory roller 8-10 tonne in stages to proper grade and camber, applying
and brooming requisite type of screening / binding material to fillup interstices of
coarse aggregate watering and compacting to the required density.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
1235 Diesel oil litre 0.59 53.17 31.37
Labour:
101 Bhishti Day 0.26 180 46.80
113 Chowkidar Day 0.033 207 6.83
114 Beldar Day 0.26 207 53.82
115 Coolie Day 0.26 207 53.82
3 Hire charges of Diesel Road Roller - 8 to litre 0.033
10 tonne 500.00 16.50
9,999 Carriage of diesel L.S. 1.43 1.00 1.43
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 213.30
Add 1% for water charges 2.13
TOTAL 215.43
Add for contractor’s profit and
overheads @15% 32.32
Cost of 1 cum 247.75
Say 247.75

16.5 Laying water bound macadam sub-base with brick aggregate and blinding
material, earth etc. including screening, sorting and spreading to template and
consolidation with light power road-roller etc. complete. (payment for brick aggregate
and moorum etc. to be made separately)
16.5.1 Over burnt (Jhama) brick aggregate 120 mm to 40 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
1235 Diesel oil litre 0.072 53.17 3.83
Labour:
101 Bhishti Day 0.18 180 32.40
113 Chowkidar Day 0.004 207 0.83
114 Beldar Day 0.35 207 72.45
115 Coolie Day 0.26 207 53.82
3 Hire charges of Diesel Road Roller - 8 to litre 0.004
10 tonne 500.00 2.00
9,999 Carriage of diesel L.S. 0.39 1.00 0.39
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 168.45
Add 1% for water charges 1.68
TOTAL 170.13
Add for contractor’s profit and
overheads @15% 25.52
Cost of 1 cum 195.65
Say 195.65

16.5 Laying water bound macadam sub-base with brick aggregate and blinding
material, earth etc. including screening, sorting and spreading to template and
consolidation with light power road-roller etc. complete. (payment for brick aggregate
and moorum etc. to be made separately)
16.5.2 Over burnt (Jhama) brick aggregate 90 mm to 45 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials:
1235 Diesel oil litre 0.072 53.17 3.83
Labour:
101 Bhishti Day 0.18 180 32.40
113 Chowkidar Day 0.004 207 0.83
114 Beldar Day 0.35 207 72.45
115 Coolie Day 0.26 207 53.82
3 Hire charges of Diesel Road Roller - 8 to litre 0.004
10 tonne 500.00 2.00
9,999 Carriage of diesel L.S. 0.39 1.00 0.39
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL
168.45
Add 1% for water charges 1.68
TOTAL 170.13
Add for contractor’s profit and
overheads @15% 25.52
Cost of 1 cum 195.65
Say 195.65

16.6 Supplying, stacking and Spreading 6 mm thick red bajri, watering and rolling
complete including preparation of the surface and rolling.
16.6.1 With road roller/ hand roller.
Code Description Unit Quantity Rate Amount
Details of cost for 6 m m thick and 100.00 sqmarea = 0.60 cum.
304 Cost of bajri at quarry cum 0.6 700.00 420.00
2311 Carriage of bajri cum 0.6 53.21 31.93
1235 Diesel oil litre 0.972 53.17 51.68
Labour:
101 Bhishti Day 0.54 180 97.20
113 Chowkidar Day 0.054 207 11.18
114 Beldar Day 0.54 207 111.78
3 Hire charges of Diesel Road Roller - 8 to litre 0.054
10 tonne 500.00 27.00
9,999 Carriage of diesel L.S. 1.43 1.00 1.43
TOTAL 752.20
Add 1% for water charges 7.52
TOTAL 759.72
Add for contractor’s profit and
overheads @15% 113.96
Cost of 100 sqm 873.67
Cost of 1 sqm 8.74
Say 8.74

16.7 Brick edging in full brick width and half brick depth including excavation,
refilling and disposal of surplus earth lead upto 50 metres.
16.7.1 With F.P.S. bricks of class designation 75
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 m.
M aterial
2602 Bricks of class designation 75
including 12% wastage 0 Nos 160 1600.00 256.00
2201 Carriage of Bricks 00 Nos 160 141.88 22.70
Labour:
115 Coolie Day 0.35 207 72.45
123 Mason ist class Day 0.17 270 45.90
124 Mason 2nd class Day 0.17 223 37.91
9,999 Removal of rubbish & sundries L.S. 26.91 1.00 26.91
TOTAL 461.87
Add 1% for water charges 4.62
TOTAL 466.49
Add for contractor’s profit and
overheads @15% 69.97
Cost of 10 m 536.46
Cost of 1 m 53.65
Say 53.65

16.8 Brick edging laid lengthwise with half brick depthincluding excavation, refilling
and disposal of surplus earth lead upto50 metres :
16.8.1 With F.P.S. bricks of class designation 75
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 m.
M aterial
2602 Bricks of class designation 75
including 12% wastage 0 Nos 49 1600.00 78.40
2201 Carriage of Bricks 00 Nos 49 141.88 6.95
Labour:
115 Coolie Day 0.09 207 18.63
123 Mason ist class Day 0.04 270 10.80
124 Mason 2nd class Day 0.04 223 8.92
9,999 Removal of rubbish L.S. 4.16 1.00 4.16
TOTAL 127.86
Add 1% for water charges 1.28
TOTAL 129.14
Add for contractor’s profit and
overheads @15% 19.37
Cost of 10 m 148.51
Cost of 1 m 14.85
Say 14.85

16.9 Scarifying metalled (water-bound) road surface including disposal of rubbish lead
upto 50m and consolidation of the aggregate received from scarifying with power road
roller of 8 Description
Code to l0 tonne capacity. Unit Quantity Rate Amount
Details of cost for 100 sqm
Materials:
1235 Diesel oil litre 2.376 53.17 126.33
Labour:
113 Chowkidar Day 0.132 207 27.32
114 Beldar Day 1.35 207 279.45
115 Coolie Day 1.08 207 223.56
3 Hire charges of Diesel Road Roller - 8 to litre 0.132
10 tonne 500.00 66.00
9,999 Carriage of diesel L.S. 1.43 1.00 1.43
9,999 Sundries L.S. 5.46 1.00 5.46
TOTAL 729.56
Add 1% for water charges 7.30
TOTAL 736.85
Add for contractor’s profit and
overheads @15% 110.53
Cost of 100 sqm 847.38
Cost of 1 sqm 8.47
Say 8.47
Cost of 1 cum 847.38

16.10 Making bajri path including preparation of subgrade, supplying and laying brick
aggregate of 50mm nominal size 7.5 cm deep with blinding material consisting of 12 mm
moorum and 12 mm red bajri consolidated with road roller.
Code Description Unit Quantity Rate Amount
Details of cost for 6 m m thick and 100.00 sqm
Earth w ork in excavation including
dressing A)(Rate as per item no. 2.6.1 of
S.H. Earth work)
cum 7.5 161.56 1211.70
Supply staking Red Bajri (A) (Rate as
per item No.16.3.8) cum 1.2 874.85 1049.82
Collection and stacking of moorum at
site (Rate as per item No.16.3.10)
cum 1.2 448.58 538.30
286 Brick Aggregate 53 mm nominal size
cum 7.5 355.00 2662.50
2260 Carriage of brick aggregate cum 7.5 57.83 433.73
1235 Diesel oil litre 3.402 53.17 180.88
Labour:
101 Bhishti Day 1.35 180 243.00
113 Chowkidar Day 0.189 207 39.12
114 Beldar Day 1.95 207 403.65
115 Coolie Day 2.63 207 544.41
3 Hire charges of Diesel Road Roller - 8 to litre 0.189
10 tonne 500.00 94.50
9,999 Carriage of diesel L.S. 12.22 1.00 12.22
9,999 Sundries L.S. 20.15 1.00 20.15
TOTAL 7433.99
Add 1% for water charges except A
46.34
TOTAL 7480.33
Add for contractor’s profit and
overheads @15% except A 702.08
Cost of 100 sqm 8182.40
Cost of 1 sqm 81.82
Say 81.82

16.11 Dry stone pitching 22.5 cm thick including supply of stones and preparing surface
Code
complete. Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm.
M aterial
1158 Stone for pitching 15 cm x22.5 crn
thick cum 2.25 332.00 747.00
2216 Carriage of stone tonne 5.05 47.29 238.81
Labour;
114 Beldar Day 2.15 207 445.05
115 Coolie Day 1.61 207 333.27
123 Mason 1st class Day 1.08 270 291.60
124 Mason 2nd class Day 1.08 223 240.84
9999 Sundries L.S 6.76 1.00 6.76
TOTAL 2303.33
Add 1% for water charges 23.03
TOTAL 2326.37
Add 15 % for contractor’s profit and overheads 348.96
Cost of 10 sqm 2675.32
cost of 1 sqm 267.53
Say 267.53

16.12 Dry brick pitching half brick thick in drains including supply of bricks and
preparing the surface complete :
16.12.1 With F.P.S. bricks of class designation 75
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm.
M aterial
2602 Bricks of class designation 75 00 nos. 645 1600.00 1032.00
2201 Carriage of Bricks 00 nos. 645 141.88 91.51
Labour;
114 Beldar Day 1.08 207 223.56
123 Mason 1st class Day 0.4 270 108.00
124 Mason 2nd class Day 0.4 223 89.20
TOTAL 1544.27
Add 1% for water charges 15.44
TOTAL 1559.72
Add 15 % for contractor’s profit and overheads 233.96
Cost of 10 sqm 1793.67
cost of 1 sqm 179.37
Say 179.37

16.13 Cutting road and making good the same including supply of extra quantities of
materials i.e. aggregate, moorum screening, red bajri and labour required.
16.13.1 bituminous portion
Code Description Unit Quantity Rate Amount
Details of cost for 1.08cum.
Material
Supplying and stacking stone aggregate
53mm to 24mm nominal size at site.
(Rate as per item No 16.3.3)
cum 0.09 1222.86 110.06 A
Supplying and stacking red bajri at site
(Rate as per item No. 16.3.8) cum 0.023 874.85 20.12 A
Supplying and stacking moorum at site
(Rate as per item No. 16.3.10) 0.022 448.58 9.87 A
2911 Stone chipping 11.2mm size 0.092 1050.00 96.60
2202 Carriage of aggregate cum 0.092 53.21 4.90
309 Paving Bitumen A-90 or S-90 tonne 0.011 22500.00 247.50
2211 Carriage of tonne tonne 0.011 53.21 0.59
Labour
114 Beldar Day 2.39 207 494.73
115 Coolie Day 1.68 207 347.76
101 Bhishti Day 0.1 180 18.00
9999 Barrier, chowkidar, sprayman, mate, L. S. 40.43 1.00 40.43
etc.
TOTAL 1390.55
Add 1% for water charges except on A 12.51

TOTAL 1403.05
Add 15 % for contractor’s profit and overheads 189.45
Cost of 1.08 sqm 1592.50
cost of 1 sqm 1474.54
Say 1,474.54

16.13 Cutting road and making good the same including supply of extra quantities of
materials i.e. aggregate, moorum screening, red bajri and labour required.
16.13.2 Water bound macadam.
Code Description Unit Quantity Rate Amount
Details of cost for 0.90 cum.
Material
Supplying and stacking stone aggregate
53mm to 24mm nominal size at site.
(Rate as per item No 16.3.3)
cum 0.09 1222.86 110.06 A
Supplying and stacking red bajri at site
(Rate as per item No. 16.3.8) cum 0.023 874.85 20.12 A
Supplying and stacking moorum at site
(Rate as per item No. 16.3.10) 0.022 448.58 9.87 A
Labour
114 Beldar Day 1.2 207 248.40
115 Coolie Day 0.96 207 198.72
101 Bhishti Day 0.1 180 18.00
9999 Barrier, chowkidar, sprayman, mate, L. S. 53.82 1.00 53.82
etc.
TOTAL 658.99
Add 1% for water charges except on A 5.19

TOTAL 664.18
Add 15 % for contractor’s profit and 78.62
overheads except on A
Cost of 0.90 sqm 742.80
cost of 1 sqm 825.33
Say 825.33

16.14 Cutting bajri paths and making good the same including supply of extra quantities
of brick aggregate, moorum and red bajri required.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm.
M aterial
286 Supplying and stacking 50mm brick
aggregate at site(extra quantity) cum 0.19 355.00 67.45
2260 Carriage cum 0.19 57.83 10.99
A Supplying and stacking red bajri at site
(Rate as per item No. 16.3.8) cum 0.06 874.85 52.49
A Supplying and stacking moorum at site
(Rate as per item No. 16.3.10) cum 0.06 448.58 26.91
Labour;For cutting, sorting out, spreading and consolidation of aggregate
114 Beldar Day 1.6 207 331.20
115 Coolie Day 0.8 207 165.60
TOTAL 654.64
Add 1% for water charges except on A 5.75

TOTAL 660.40
Add 15 % for contractor’s profit and 87.15
overheads
Cost of 10except
sqm on A 747.54
cost of 1 sqm 74.75
Say 74.75
16.15 Supplying at site :
16.15.1 R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 ( 1 cement : 1.5 coarse
sand : 3 graded stone aggregate 12.5 mm nominal size) with wooden plugs or 6mm bar
nibs,
Code wherever required as per direction of Engineer-in-charge
Description cost of earth
Unit Quantity works in
Rate Amount
excavation, concrete works to be paid
Details of cost for 10 posts = 0.336cum separately).
A Cement concrete 1:1.5:3 (1 Cement: 1.5
Coarse sand : 3 graded stone aggregate
12.5mm nominal size) (Rate as per item no
4.1.2 cum 0.336 4,181.21 1404.89
M.S. Reinforcement 6mm dia. Bars (Rate as
per item No. 5.22.2) kg 26.44 46.48 1229.01
Centering and shuttering (Rate as in item no
5.9.1) sqm 6.99 234.53 1639.35
Extra labour for laying cement concrete in RCC work
114 Beldar Day 0.034 207.00 7.04
123 Mason 1st class Day 0.013 270.00 3.51
124 Mason 2nd class Day 0.013 223.00 2.90
128 Mate Day 0.013 313.00 4.07
101 Bhishti Day 0.067 180.00 12.06
367 Cement tonne 0.05 5200.00 260.00
2209 Carriage of cem ent tunne 0.05 0 0.00
983 Fine sand cum 0.07 300.00 21.00
2261 Carriage of fine sand cum 0.07 0 0.00
155 Mason Day 0.64 180.00 115.20
114 Beldar Day 0.05 207.00 10.35
101 Bhishti Day 0.29 180.00 52.20
115 Coolie Day 0.8 207.00 165.60
9999 Hire and running charges of mixer L. S. 1.95 1.00 1.95
9999 Extra for removing burr, cleaning with L. S. 13.26 1.00 13.26
wire brushes, pock making with
pointed tool etc. complete
9999 Scaffolding and sundries L. S. 11.57 1.00 11.57
9999 Carriage of RCC posts L. S. 53.82 1.00 53.82
9999 Wooden plugs or 6 m m bar nibs L. S. 12.22 1.00 12.22
9999 Sundries L. S. 13.52 1.00 13.52
TOTAL 5033.51
Add 1% for water charges except on A 7.60

TOTAL 5041.12
Add 10 % for contractor’s profit and 76.79
overheads except on A
Cost of 0.366 cum 5117.90
cost of 1 cum 13983.34
Say 13,983.34

16.15 Supplying
16.15.2 Welded steelatwire
site :fabric of required width rectangular mesh painted with two or
more coats of enamel paint of approved shade over a coat of primer (Painting to be paid
for separately.)
Code Description Unit Quantity Rate Amount
Details of cost for 27 sqm.
Material
1021 Hard drawn steel wire fabric sqm 27 350.00 9450.00
2314 Carriage of wire tonne 0.209 47.29 9.88
TOTAL 9459.88
Add 1% for water charges except on A 94.60

TOTAL 9554.48
Add 15 % for contractor’s profit and 1433.17
overheads except on A
Cost of 209.25 sqm 10987.65
cost of 1 sqm 52.51
Say 52.51

16.16 Supplying and fixing turn buckles and straining bolts for barbed wire fencing.
Code Description Unit Quantity Rate Amount
Details of cost for one set
Material
1030 Turn buckles each 1 10.00 10.00
1028 Straining bolts each 1 52.00 52.00
9999 Carriage of turn buckles and straining bol L. S. 2.73 1.00 2.73
Labour for fixing straining bolts and turn buckles
103 Blacksmith 2nd class Day 0.1 223 22.30
TOTAL 87.03
Add 1% for water charges except on A 0.87

TOTAL 87.90
Add 15 % for contractor’s profit and 13.19
overheads except on A
cost of 1 sqm 101.09
Say 101.09
88.15
16.17 Fencing with R.C.C. post placed at required distance, embedded in cement concrete
blocks, every 15th post, last but one end post and corner post shall be strutted on both
sides and end post one side only, provided with horizontal lines and two diagonals of
barbed wire 9.38 kg per 100 metres (min) between the two posts fitted and fixed with G.I.
staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the
post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :-
Payment to be made per metre cost of total length of barbed wire used.
16.17.1 With G.I. barbed wire
Code Description Unit Quantity Rate Amount
Details of cost for 30m
Material
1029 G.I. barbed wire quintal 0.31 6500.00 2015.00
2314 Carriage tonne 0.03 47.29 1.42
9999 G.I. staples or binding w ire L. S. 49.4 1.00 49.40
Labour for fixing costs in line, fixing and stretching wire
123 Mason 1st class Day 0.12 270 32.40
124 Mason 2nd class Day 0.12 223 26.76
103 Blacksmith 2nd class Day 0.5 223 111.50
114 Beldar Day 0.5 207 103.50
102 Blacksmith 1st class Day 0.5 270 135.00
9999 Sundries L. S. 13.52 1.00 13.52
TOTAL 2488.50
Add 1% for water charges 24.88
TOTAL 2513.38
Add 10% for contractor’s profit and
overheads 251.34
Cos t of 333 metres 2764.72
Cost of 1.00 metre 8.30
Say 8.30
16.18 Fencing with angle iron post placed at required distance embedded in cement
concrete blocks, every 15th post, last but one end post and corner post shall be strutted on
both sides and end post on one side only and provided with horizontal lines and two
diagonals interwoven with horizontal wires, of barbed wire 9.38 kg per 100 m (minimum)
between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost
of posts, struts, earth work and concrete work to be paid for separately):- Payment to be
made per metre cost of total length of barbed wire used.
16.18.1 With G.I. barbed wire
Code Description Unit Quantity Rate Amount
Details of cost for 30m
Material
1029 G.I. barbed wire quintal 0.31 6500.00 2015.00
2314 Carriage tonne 0.031 47.29 1.47
9999 G.I. staples or binding w ire L. S. 49.4 1.00 49.40
A Turn buckle & staple (Rate same as per each 10 101.09 1010.85
item No. 16.16) set
Labour for fixing costs in line, fixing and stretching wire
123 Mason 1st class Day 0.12 270 32.40
124 Mason 2nd class Day 0.12 223 26.76
103 Blacksmith 2nd class Day 0.5 223 111.50
114 Beldar Day 0.5 207 103.50
102 Blacksmith 1st class Day 0.5 270 135.00
TOTAL 3485.88
Add 1% for water charges except on A
24.75
TOTAL 3510.63
Add 15% for contractor’s profit and
overheads except on A 374.97
Cos t of 333 metres 3885.60
Cost of 1.00 metre 11.67
Say 11.67

16.19 Supplying at site Angle iron post & strut of required size including bottom to be
split and bent at right angle in opposite direction for 10 cm length and drilling holes upto
10 mm dia.Description
Code etc.. complete. Unit Quantity Rate Amount
Details of cost for 1 quintal
Material
Structural steel such as tees, angles
1007 channels and R.S. joists quintal 1.05 4600.00 4830.00
2314 Carriage tonne 0.105 47.29 4.97
Labour
103 Blacksmith 2nd class Day 0.75 223 167.25
114 Beldar Day 0.5 207 103.50
For spotting, bending of angle and drilling holes etc. :
103 Blacksmith 2nd class Day 1 223 223.00
114 Beldar Day 1 207 207.00
9999 Sundries such as drilling bit etc. L. S. 19.76 1.00 19.76
TOTAL 5555.48
Add 1% for water charges 55.55
TOTAL 5611.03
Add 15% for contractor’s profit and
overheads 841.65
Cos t of 1 quintal 6452.68
Cost of 1.00 kg 64.53
Say 64.53
16.20 welded steel wire fabric fencing with posts of specified material and of standard
design placed and embedded in cement concrete blocks 45x45x60cm of mix 1:5:10 (1
cement:5 fine sand : 10 graded stone aggregate 40mm nominal size) every 15th post, last
but one end post and corner post shall be strutted on both sides and end post on one side
only and struts embedded in cement concrete blocks 70x45x50cm of the same mix,
provided with welded steel wire fabric fixed between the posts fitted and fixed with G.I.
staples on wooden plugs or tied to 6 mm bar nibs with G.I. binding wire (cost of posts,
welded steel wire fabric, painting, earth work in excavation and concrete to be paid for
separately):
Code Description Unit Quantity Rate Amount
Details of cost for 30m i.e.30xl.20=36.00sqm
Labour for fixing posts in line fixing and stretching - welded wire fabric :
123 Mason 1st class Day 0.12 270 32.40
124 Mason 2nd class Day 0.12 223 26.76
103 Blacksmith 2nd class Day 0.5 223 111.50
114 Beldar Day 0.5 207 103.50
102 Blacksmith 1st class Day 0.5 270 135.00
9999 G.I. staples or binding w ire L. S. 53.82 1.00 53.82
9999 Sundries L. S. 53.82 1.00 53.82
TOTAL 516.80
Add 1% for water charges except on A
5.17
TOTAL 521.97
Add 15% for contractor’s profit and
overheads except on A 78.30
Cos t of 36 sqm 600.26
Cost of 1.00 sqm 16.67
Say 16.67

16.21 Engraving letters in hard stone


Code Description Unit Quantity Rate Amount
Details of cost for 6 letters 8 cm height
Labour for For Engraving stone- :
126 Mason (for ornamental stone work) Day 0.38 313 118.94
1st class
9999 Sundries L. S. 6.76 1.00 6.76
TOTAL 125.70
Add 1% for water charges except on A
1.26
TOTAL 126.96
Add 15% for contractor’s profit and
overheads except on A 19.04
Cost of 6 letters of 8cm heights 146.00
Cost per cm. height per letter 3.04
Say 3.04

16.22 Providing and fixing 15xl5x90cm boundary stone of hard stone with top 30 cm
chisel dressed on all four sides and on top (cost of excavation, refilling and concrete etc. to
be paid forDescription
Code separately). Unit Quantity Rate Amount
Details of cost for one stone
1151 Cost of stone 15x15x90cm with 30cm 46.00
chisel dress each 1 46.00
Labour for fixing
114 Beldar Day 0.12 207 24.84
9999 Carriage to site L. S. 4.16 1.00 4.16
TOTAL 75.00
Add 1% for water charges 0.75
TOTAL 75.75
Add 15% for contractor’s profit and
overheads 11.36
Cost of each 87.11
Say 87.11

16.23 Providing and fixing 15cm dia at top 20cm at bottom and 90cm high precast
reinforced cement concrete 1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate
20mm nominal size) boundary stone as per standard design including finishing smooth
with cement mortar 1:3 (1 cement: 3 fine sand) (cost of excavation, refilling and
concreting to be paid for separately).
Code Description Unit Quantity Rate Amount
Details of cost for one stone
A Cement concrete 1:1.5:3 (1 Cement:
1.5 Coarse sand : 3 graded stone
aggregate 12.5mm nominal size) (Rate
as per item no 4.1.2
cum 0.02 4,181.21 83.62
M.S. Reinforcement 6mm dia. Bars
(Rate as per item No. 5.22.2) kg 1.32 58.65 77.42
Centering and shuttering (Rate as in item
no 5.9.1) sqm 0.5 234.53 117.26
Extra labour for laying cement concrete in RCC work
114 Beldar Day 0.002 207 0.41
123 Mason 1st class Day 0.0008 270 0.22
124 Mason 2nd class Day 0.0008 223 0.18
128 Mate Day 0.0008 313 0.25
101 Bhishti Day 0.004 180 0.72
367 Cement tonne 0.0018 5200.00 9.36
2209 Carriage of cem ent tunne 0.0018 47.29 0.09
983 Fine sand cum 0.0385 300.00 11.55
2261 Carriage of fine sand cum 0.0385 53.21 2.05
155 Mason Day 0.026 180 4.68
114 Beldar Day 0.1227 207 25.40
101 Bhishti Day 0.0462 180 8.32
115 Coolie Day 0.038 207 7.87
9999 Hire and running charges of mixer L. S. 0.1 1.00 0.10
9999 Extra for removing burr L. S. 0.68 1.00 0.68
9999 Scaffolding and sundries L. S. 0.6 1.00 0.60
9999 Carriage of site L. S. 4.16 1.00 4.16
9999 Sundries L. S. 0.05 1.00 0.05
TOTAL 354.99
Add 1% for water charges except on A 0.77

TOTAL 355.75
Add 15 % for contractor’s profit and 11.62
overheads except on A
Cost of each 367.37
Say 367.37

16.24 Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement: 1.5
coarse sand : 3 graded stone aggregate 20mm nominal size) kilometre stone as per
standard design including finishing smooth in 1:3 cement mortar (1 cement: 3 fine sand)
but excluding the cost of earth work, concrete in foundation, painting and lettering etc.
which shall be paid for separately.
16.24.1 35x111x25 cm size.
Code Description Unit Quantity Rate Amount
Details of cost for one stone
A Cement concrete 1:1.5:3 (1 Cement:
1.5 Coarse sand : 3 graded stone
aggregate 12.5mm nominal size) (Rate
as per item no 4.1.2
cum 0.1 4,181.21 418.12
M.S. Reinforcement 6mm dia. Bars
(Rate as per item No. 5.22.2) kg 4.81 58.65 282.13
Centering and shuttering (Rate as in item
no 5.9.1) sqm 1.09 234.53 255.64
Extra labour for laying cement concrete in RCC work
114 Beldar Day 0.01 207 2.07
123 Mason 1st class Day 0.004 270 1.08
124 Mason 2nd class Day 0.004 223 0.89
128 Mate Day 0.004 313 1.25
101 Bhishti Day 0.02 180 3.60
367 Cement tonne 0.054 5200.00 280.80
2209 Carriage of cem ent tunne 0.054 47.29 2.55
983 Fine sand cum 0.011 300.00 3.30
2261 Carriage of fine sand cum 0.011 53.21 0.59
155 Mason Day 0.075 180 13.50
114 Beldar Day 0.208 207 43.06
101 Bhishti Day 0.1367 180 24.61
115 Coolie Day 0.111 207 22.98
9999 Hire and running charges of mixer L. S. 0.03 1.00 0.03
9999 Extra for removing burr L. S. 1.95 1.00 1.95
9999 Scaffolding and sundries L. S. 1.82 1.00 1.82
9999 Carriage of site L. S. 13.52 1.00 13.52
9999 Sundries L. S. 0.13 1.00 0.13
TOTAL 1373.61
Add 1% for water charges except on A 4.18

TOTAL 1377.78
Add 15 % for contractor’s profit and 63.28
overheads except on A
Cost of each 1441.07
Say 1,441.07

16.24 Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement: 1.5
coarse sand : 3 graded stone aggregate 20mm nominal size) kilometre stone as per
standard design including finishing smooth in 1:3 cement mortar (1 cement: 3 fine sand)
but excluding the cost of earth work, concrete in foundation, painting and lettering etc.
which shall be paid for separately.
16.24.2 50x152.5x25 cm size.
Code Description Unit Quantity Rate Amount
Details of cost for one stone
A Cement concrete 1:1.5:3 (1 Cement:
1.5 Coarse sand : 3 graded stone
aggregate 12.5mm nominal size) (Rate
as per item no 4.1.2
cum 0.19 4,181.21 794.43
M.S. Reinforcement 6mm dia. Bars
(Rate as per item No. 5.22.2) kg 9.13 58.65 535.51
Centering and shuttering (Rate as in item
no 5.9.1) sqm 1.72 234.53 403.39
Extra labour for laying cement concrete in RCC work
114 Beldar Day 0.019 207 3.93
123 Mason 1st class Day 0.008 270 2.16
124 Mason 2nd class Day 0.008 223 1.78
128 Mate Day 0.008 313 2.50
101 Bhishti Day 0.038 180 6.84
367 Cement tonne 0.009 5200.00 46.80
2209 Carriage of cem ent tunne 0.009 47.29 0.43
983 Fine sand cum 0.2 300.00 60.00
2261 Carriage of fine sand cum 0.2 53.21 10.64
155 Mason Day 0.126 180 22.68
114 Beldar Day 0.213 207 44.09
101 Bhishti Day 0.228 180 41.04
115 Coolie Day 0.185 207 38.30
9999 Hire and running charges of mixer L. S. 0.52 1.00 0.52
9999 Extra for removing burr L. S. 3.38 1.00 3.38
9999 Scaffolding and sundries L. S. 2.86 1.00 2.86
9999 Carriage of site L. S. 13.52 1.00 13.52
9999 Sundries L. S. 0.26 1.00 0.26
TOTAL 2035.07
Add 1% for water charges except on A 3.02

TOTAL 2038.09
Add 15 % for contractor’s profit and 45.71
overheads except on A
Cost of each 2083.80
Say 2,083.80

16.24 Providing and fixing precast reinforced cement concrete 1:1.5:3 (1 cement: 1.5
coarse sand : 3 graded stone aggregate 20mm nominal size) kilometre stone as per
standard design including finishing smooth in 1:3 cement mortar (1 cement: 3 fine sand)
but excluding the cost of earth work, concrete in foundation, painting and lettering etc.
which shall be paid for separately.
16.24.3 35x93.5x18 cm size.
Code Description Unit Quantity Rate Amount
Details of cost for one stone
A Cement concrete 1:1.5:3 (1 Cement:
1.5 Coarse sand : 3 graded stone
aggregate 12.5mm nominal size) (Rate
as per item no 4.1.2
cum 0.06 4,181.21 250.87
M.S. Reinforcement 6mm dia. Bars
(Rate as per item No. 5.22.2) kg 2.88 58.65 168.92
Centering and shuttering (Rate as in item
no 5.9.1) sqm 0.81 234.53 189.97
Extra labour for laying cement concrete in RCC work
114 Beldar Day 0.006 207 1.24
123 Mason 1st class Day 0.0024 270 0.65
124 Mason 2nd class Day 0.0024 223 0.54
128 Mate Day 0.0024 313 0.75
101 Bhishti Day 0.012 180 2.16
367 Cement tonne 0.042 5200.00 218.40
2209 Carriage of cem ent tunne 0.042 47.29 1.99
983 Fine sand cum 0.009 300.00 2.70
2261 Carriage of fine sand cum 0.009 53.21 0.48
155 Mason Day 0.058 180 10.44
114 Beldar Day 0.106 207 21.94
101 Bhishti Day 0.1056 180 19.01
115 Coolie Day 0.086 207 17.80
9999 Hire and running charges of mixer L. S. 0.23 1.00 0.23
9999 Extra for removing burr L. S. 1.56 1.00 1.56
9999 Scaffolding and sundries L. S. 1.3 1.00 1.30
9999 Carriage of site L. S. 13.52 1.00 13.52
9999 Sundries L. S. 0.13 1.00 0.13
TOTAL 924.60
Add 1% for water charges except on A 3.15

TOTAL 927.75
Add 15 % for contractor’s profit and 47.70
overheads except on A
Cost of each 975.44
Say 975.44

16.25 Surface dressing on new surface with paving bitumen of grade A -90/S-90 of
approved quality using 2.25 Kg of bitumen per sqm with 1.65 cum of stone chippings 13.2
mm nominal size per 100 sem of road surface including consolidation with road roller of 6
to 8 tonne capacity etc. complete:
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
309 Bitumen S-90 tonne 0.225 22500.00 5062.50
2211 Carriage of bitumen tonne 0.225 53.21 11.97
2910 Stone chippings 13.2mm cum 1.65 1050.00 1732.50
2202 Carriage of stone aggregate cum 1.65 53.21 87.80
370 Steam coal for heating bitumen quintal 0.45 120.00 54.00
2200 Carrige of steam coal tonne 0.045 60.81 2.74
Labour for cleaning the road surface, heating and spraying bitumen and aggregate
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.11 313 34.43
115 Coolie Day 1.4 207 289.80
(b) For heating and spraying bitumen :
130 Mistry Day 0.08 270 21.60
138 Spray man Day 0.11 180 19.80
114 Beldar Day 0.93 207 192.51
(c) For screening and spreading aggregate :
114 Beldar Day 0.93 207 192.51
128 Mate Day 0.11 313 34.43
115 Coolie Day 1.55 207 320.85
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.12 500.00 60.00
Hire charges for boiler day
7 per 0.11 200.00 22.00
Hire charges for tar sprayer unit day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Sundries L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 6.76 1.00 6.76
TOTAL 8708.42
Add for water charges @ 1% 87.08
TOTAL 8795.50
Add for contractor’s profit and
overheads @15% 1319.32
Cost of 100 sqm 10114.82
Cost of 1 sqm 101.15
Say 101.15
16.26 Surface dressing on new surface in two coats with bitumen of grade A-90/S-90 of
approved quality using 1.8kg.of bitumen per sqm with 1.5cum of stone chippings 13.2mm
nominal size per 100 sqm of road surface for first coat and 1.1kg. of bitumen per sqm.
with 1.00 cu. metre of stone chippings 11.2mm nominal size per 100 sqm. of road surface
for second coat including consolidation of each coat separately with road roller of 6 to 8
tonne capacity etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
309 Bitumen S-90 tonne 0.18 22500.00 4050.00
2211 Carriage of bitumen tonne 0.18 53.21 9.58
2910 Stone chippings 13.2mm cum 1.5 1050.00 1575.00
2202 Carriage of stone aggregate cum 1.5 53.21 79.82
370 Steam coal for heating bitumen quintal 0.36 120.00 43.20
2200 Carrige of steam coal tonne 0.036 60.81 2.19
Labour for cleaning the road surface, heating and spraying bitumen and aggregate
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.11 313 34.43
115 Coolie Day 1.4 207 289.80
(b) For heating and spraying bitumen :
130 Mistry Day 0.08 270 21.60
138 Spray man Day 0.11 180 19.80
114 Beldar Day 1.38 207 285.66
(c) For screening and spreading aggregate :
114 Beldar Day 0.85 207 175.95
128 Mate Day 0.27 313 84.51
115 Coolie Day 0.85 207 175.95
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.11
and for road roller) 207 22.77
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.12 500.00 60.00
Hire charges for boiler day
7 per 0.11 200.00 22.00
Hire charges for tar sprayer unit day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Sundries L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 16.38 1.00 16.38
309 Bitumen S-90 tonne 0.11 22500.00 2475.00
2211 Carriage of bitumen tonne 0.11 53.21 5.85
2910 Stone chippings 13.2mm cum 1 1050.00 1050.00
2202 Carriage of stone aggregate cum 1 53.21 53.21
370 Steam coal for heating bitumen quintal 0.22 120.00 26.40
2200 Carrige of steam coal tonne 0.022 60.81 1.34
128 Mate Day 0.06 313 18.78
115 Coolie Day 0.97 207 200.79
(b) For heating and spraying bitumen :
130 Mistry Day 0.05 270 13.50
138 Spray man Day 0.07 180 12.60
114 Beldar Day 0.75 207 155.25
(c) For screening and spreading aggregate :
114 Beldar Day 0.62 207 128.34
128 Mate Day 0.07 313 21.91
115 Coolie Day 0.62 207 128.34
113 Chowkidar (at barriers for night watch Day 0.15
and for road roller) 207 31.05
101 Bhishti Day 0.06 180 10.80
3 per 0.06 500.00 30.00
Hire charges of road roller day
7 per 0.07 200.00 14.00
Hire charges for tar sprayer unit day
1235 Diesel for road roller @ 18 litres litre 1.08 53.17 57.42
9999 Carriage of diesel L. S. 1.43 1.00 1.43
1 per 0.06 500.00 30.00
Hire charges for boiler day
364 Brushes etc. for cleaning, Wire bursh 0.03 90.00 2.70
(with thick wire) each
365 Soft brush each 0.09 50.00 4.50
9999 Sundries L. S. 9.49 1.00 9.49

TOTAL 11957.67
Add for water charges @ 1% 119.58
TOTAL 12077.24
Add for contractor’s profit and
overheads @15% 1811.59
Cost of two coats per 100 sqm 13888.83
Cost of 1 sqm 138.89
Say 138.89

16.27 : Surface dressing on old surface with hot bitumen of grade A-90/ S-90 of approved
quality using 1.95 kg of bitumen per sqm . with 1.50 cum of stone chippings 11.2 mm
nominal size per 100 sqm of road surface including consolidation with road roller of 6 to 8
tonne
Code
capacity, etc. complete.
Description Unit Quantity Rate Amount
Details of cost for 100 sqm.
Material:
309 Bitumen S-90 tonne 0.195 22500.00 4387.50
2211 Carriage of bitumen tonne 0.195 53.21 10.38
2911 Stone chippings 11.2mm nominal size cum 1.5 1050.00 1575.00
2202 Carriage of stone aggregate cum 1.5 53.21 79.82
370 Steam coal for heating bitumen quintal 0.39 120.00 46.80
2200 Carrige of steam coal tonne 0.039 60.81 2.37
Labour for cleaning the road surface, heating and spraying bitumen and aggregate
114 Beldar Day 0.49 207 101.43
128 Mate Day 0.06 313 18.78
115 Coolie Day 0.97 207 200.79
(b) For heating and spraying bitumen :
130 Mistry Day 0.05 270 13.50
138 Spray man Day 0.06 180 10.80
114 Beldar Day 0.69 207 142.83
(c) For screening and spreading aggregate :
114 Beldar Day 0.51 207 105.57
128 Mate Day 0.66 313 206.58
115 Coolie Day 0.51 207 105.57
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.15
and for road roller) 207 31.05
101 Bhishti Day 0.06 180 10.80
3 per 0.06 500.00 30.00
Hire charges of road roller day
1 per 0.06 500.00 30.00
Hire charges for boiler day
7 per 0.06 200.00 12.00
Hire charges for tar sprayer unit day
1235 Diesel for road roller @ 18 litres litre 1.08 53.17 57.42
9999 Carriage of diesel L. S. 1.43 1.00 1.43
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.05 90.00 4.50
(with thick wire) each
365 Soft brush each 0.12 50.00 6.00
9999 Brooms and gunny bags L. S. 2.73 1.00 2.73
9999 Sundries L. S. 5.33 1.00 5.33
TOTAL 7198.98
Add for water charges @ 1% 71.99
TOTAL 7270.97
Add for contractor’s profit and
overheads @15% 1090.64
Cost of two coats per 100 sqm 8361.61
Cost of 1 sqm 83.62
Say 83.62

16.28 Surface dressing one coat on new surface with bitumen of specified grade at a rate
of 1.95 kg/sqm. of surface area with 1.5 cum. of stone chippings 13.2 mm nominal size
per 100 sqm. of road surface including consolidation with road roller of 6 to 8 tonne
capacity , etc. complete :
16.28.1 Using bitumen emulsion (minimum 50% bitumen content - RS grade conforming
Code Description
to IS : 8887). Unit Quantity Rate Amount
Details of cost for 100 sqm.
Material:
310 Bitumen emulsion tonne 0.195 19500.00 3802.50
2211 Carriage of bitumen tonne 0.195 53.21 10.38
2910 Stone chippings 13.2mm nominal size cum 1.5 1050.00 1575.00
2202 Carriage of stone aggregate cum 1.5 53.21 79.82
Labour for cleaning the road surface, heating and spraying bitumen and aggregate
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.11 313 34.43
115 Coolie Day 1.4 207 289.80
(b) For heating and spraying bitumen :
130 Mistry Day 0.07 270 18.90
138 Spray man Day 0.1 180 18.00
114 Beldar Day 1 207 207.00
(c) For screening and spreading aggregate :
114 Beldar Day 0.85 207 175.95
128 Mate Day 0.11 313 34.43
115 Coolie Day 0.85 207 175.95
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.27 180 48.60
3 per 0.11 500.00 55.00
Hire charges of road roller day
7 per 0.1 200.00 20.00
Hire charges for tar sprayer unit day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 7042.66
Add for water charges @ 1% 70.43
TOTAL 7113.09
Add for contractor’s profit and
overheads @15% 1066.96
Cost of two coats per 100 sqm 8180.05
Cost of 1 sqm 81.80
Say 81.80

16.29 Surface dressing one coat on old surface with bitumen of specified grade at the
rate of 1.22 kg/ sqm of surface area with 1.10 cum of stone chippings 11.2 mm nominal
size per 100 sqm. of road surface including consolidation with road roller of 6 to 8 tonne
capacity etc. complete :
16.29.1 Using bitumen emulsion (minimum 50% bitumen content - RS grade conforming
Code Description
to IS : 8887). Unit Quantity Rate Amount
Details of cost for 100 sqm.
Material:
310 Bitumen emulsion tonne 0.122 19500.00 2379.00
2211 Carriage of bitumen tonne 0.122 53.21 6.49
2910 Stone chippings 13.2mm nominal size cum 1.1 1050.00 1155.00
2202 Carriage of stone aggregate cum 1.1 53.21 58.53
Labour for cleaning the road surface, heating and spraying bitumen and aggregate
114 Beldar Day 0.49 207 101.43
128 Mate Day 0.06 313 18.78
115 Coolie Day 0.97 207 200.79
(b) For heating and spraying bitumen :
130 Mistry Day 0.05 270 13.50
138 Spray man Day 0.06 180 10.80
114 Beldar Day 0.63 207 130.41
(c) For screening and spreading aggregate :
114 Beldar Day 0.62 207 128.34
128 Mate Day 0.07 313 21.91
115 Coolie Day 0.62 207 128.34
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.15
and for road roller) 207 31.05
101 Bhishti Day 0.15 180 27.00
3 per 0.06 500.00 30.00
Hire charges of road roller day
7 per 0.06 200.00 12.00
Hire charges for tar sprayer unit day
1235 Diesel for road roller @ 18 litres litre 1.08 53.17 57.42
9999 Carriage of diesel L. S. 1.43 1.00 1.43
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 2.73 1.00 2.73
9999 Sundries L. S. 5.33 1.00 5.33
TOTAL 4546.19
Add for water charges @ 1% 45.46
TOTAL 4591.65
Add for contractor’s profit and
overheads @15% 688.75
Cost of two coats per 100 sqm 5280.40
Cost of 1 sqm 52.80
Say 52.80

16.30 Providing and applying tack coat using hot straight run bitumen of grade 80/ 100
including heating the bitumen, spraying the bitumen with mechanically operated spray
unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per
specifications :
16.30.1 On W.B.M. @ 0.75 Kg / sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm.
Material:
2916 Bitumen 80/100 tonne 0.075 42000.00 3150.00
2211 Carriage of bitumen tonne 0.075 53.21 3.99
370 Steam coal for heating bitumen quintal 0.15 120.00 18.00
2200 Carrige of steam coal tonne 0.015 60.81 0.91
Labour for cleaning
114 Beldar Day 1.46 207 302.22
128 Mate Day 0.06 313 18.78
(b) For heating bitumen :
114 Beldar Day 0.19 207 39.33
(c) For applying tack coat :
114 Beldar Day 0.47 207 97.29
(d) Materials for claening the road surface
7 per 0.03 200.00 6.00
Hire charges for tar sprayer unit day
364 Brushes etc. for cleaning, Wire bursh 0.05 90.00 4.50
(with thick wire) each
365 Soft brush each 0.12 50.00 6.00
9999 Gunny bags L. S. 7.8 1.00 7.80
9999 Sundries L. S. 9.1 1.00 9.10
TOTAL 3663.92
Add for water charges @ 1% 36.64
TOTAL 3700.56
Add for contractor’s profit and
overheads @15% 555.08
Cost of two coats per 100 sqm 4255.65
Cost of 1 sqm 42.56
Say 42.56

16.30 Providing and applying tack coat using hot straight run bitumen of grade 80/ 100
including heating the bitumen, spraying the bitumen with mechanically operated spray
unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per
specifications :
16.30.2 On bituminous surface @ 0.50 Kg/sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm.
Material:
2916 Bitumen 80/100 tonne 0.05 42000.00 2100.00
2211 Carriage of bitumen tonne 0.05 53.21 2.66
370 Steam coal for heating bitumen quintal 0.1 120.00 12.00
2200 Carrige of steam coal tonne 0.01 60.81 0.61
Labour for cleaning
114 Beldar Day 1.46 207 302.22
128 Mate Day 0.06 313 18.78
(b) For heating bitumen :
114 Beldar Day 0.19 207 39.33
(c) For applying tack coat :
114 Beldar Day 0.47 207 97.29
(d) Materials for claening the road surface
7 per 0.03 200.00 6.00
Hire charges for tar sprayer unit day
364 Brushes etc. for cleaning, Wire bursh 0.05 90.00 4.50
(with thick wire) each
365 Soft brush each 0.12 50.00 6.00
9999 Gunny bags L. S. 7.8 1.00 7.80
9999 Sundries L. S. 9.1 1.00 9.10
TOTAL 2606.29
Add for water charges @ 1% 26.06
TOTAL 2632.35
Add for contractor’s profit and
overheads @15% 394.85
Cost of two coats per 100 sqm 3027.20
Cost of 1 sqm 30.27
Say 30.27

16.31 Providing and applying tack coat using bitumen emulsion (Rapid Setting)
complying with IS 8887-1995, spraying the bitumen emulsion with mechanically operated
spray unit, cleaning and preparing the existing road surface as per specifications:
16.31.1 On W.B.M @ 0.4kg/sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm.
Material:
7382 Bitumen emulsion tonne 0.04 32000.00 1280.00
2211 Carriage of bitumen tonne 0.04 53.21 2.13
Labour for cleaning
114 Beldar Day 1.46 207 302.22
128 Mate Day 0.06 313 18.78
b) For applying tack coat :
114 Beldar Day 0.25 207 51.75
c) Materials for claening the road surface
7 per 0.03 200.00 6.00
Hire charges for tar sprayer unit day
364 Brushes etc. for cleaning, Wire bursh 0.05 90.00 4.50
(with thick wire) each
365 Soft brush each 0.12 50.00 6.00
9999 Gunny bags L. S. 7.8 1.00 7.80
9999 Sundries L. S. 9.1 1.00 9.10
TOTAL 1688.28
Add for water charges @ 1% 16.88
TOTAL 1705.16
Add for contractor’s profit and
overheads @15% 255.77
Cost of two coats per 100 sqm 1960.94
Cost of 1 sqm 19.61
Say 19.61

16.31 Providing and applying tack coat using bitumen emulsion (Rapid Setting)
complying with IS 8887-1995, spraying the bitumen emulsion with mechanically operated
spray unit, cleaning and preparing the existing road surface as per specifications:
16.31.2 On bituminous surface @ 0,25kg/sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm.
Material:
7382 Bitumen emulsion tonne 0.025 32000.00 800.00
2211 Carriage of bitumen tonne 0.025 53.21 1.33
Labour for cleaning
114 Beldar Day 1.46 207 302.22
128 Mate Day 0.06 313 18.78
b) For applying tack coat :
114 Beldar Day 0.235 207 48.65
c) Materials for claening the road surface
7 per 0.03 200.00 6.00
Hire charges for tar sprayer unit day
364 Brushes etc. for cleaning, Wire bursh 0.05 90.00 4.50
(with thick wire) each
365 Soft brush each 0.12 50.00 6.00
9999 Gunny bags L. S. 7.8 1.00 7.80
9999 Sundries L. S. 9.1 1.00 9.10
TOTAL 1204.38
Add for water charges @ 1% 12.04
TOTAL 1216.42
Add for contractor’s profit and
overheads @15% 182.46
Cost of two coats per 100 sqm 1398.88
Cost of 1 sqm 13.99
Say 13.99

16.32 2 cm premix carpet surfacing with 1.8 cum and 0.90 cum of stone chippings of 13.2
mm size and 11.2 mm size respectively per 100 sqm. and 52 kg. and 56 kg. of hot bitumen
per cum of stone chippings of 13.2 mm and 11.2 mm size respectively including a tack
coat with hot straight run bitumen including consolidation with road roller of 6 to 9
tonne capacity etc. complete: (tack coat to be paid for separately).

16.32.1 With paving Asphalt 80/100 heated and then mixed with solvent at the rate of 70
grams per kg of asphalt.
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
2916 Paving Asphalt 80/100 penetration tonne 0.144 42000.00 6048.00
2211 Carriage of bitumen tonne 0.144 53.21 7.66
2914 Solvent kg 10.08 60.00 604.80
2342 Carriage of solvent qunital 0.1008 5.32 0.54
2910 Stone chippings 13.2mm cum 1.8 1050.00 1890.00
2911 Stone chippings 11.2mm nominal size cum 0.9 1050.00 945.00
2202 Carriage of stone aggregate cum 2.7 53.21 143.67
370 Steam coal for heating bitumen quintal 0.288 120.00 34.56
2200 Carrige of steam coal tonne 0.0288 60.81 1.75
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.08 313 25.04
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 0.57 207 117.99
(c) For screening and spreading premixed aggregate :
114 Beldar Day 5 207 1035.00
130 Mistry Day 0.19 270 51.30
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.13 500.00 65.00
Hire charges for boiler day
13 per 0.04 150.00 6.00
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 11837.82
Add for water charges @ 1% 118.38
TOTAL 11956.19
Add for contractor’s profit and
overheads @15% 1793.43
Cost of 100 sqm 13749.62
Cost of 1 sqm 137.50
Say 137.50

16.32 2 cm premix carpet surfacing with 1.8 cum and 0.90 cum of stone chippings of 13.2
mm size and 11.2 mm size respectively per 100 sqm. and 52 kg. and 56 kg. of hot bitumen
per cum of stone chippings of 13.2 mm and 11.2 mm size respectively including a tack
coat with hot straight run bitumen including consolidation with road roller of 6 to 9
tonne capacity etc. complete: (tack coat to be paid for separately).

16.32.2 With paving Asphalt 60/70 with no solvent


Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7309 Paving Asphalt 60/70 penetration tonne 0.144 23200.00 3340.80
2211 Carriage of bitumen tonne 0.144 53.21 7.66
2910 Stone chippings 13.2mm cum 1.8 1050.00 1890.00
2911 Stone chippings 11.2mm nominal size cum 0.9 1050.00 945.00
2202 Carriage of stone aggregate cum 2.7 53.21 143.67
370 Steam coal for heating bitumen quintal 0.288 120.00 34.56
2200 Carrige of steam coal tonne 0.0288 60.81 1.75
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.08 313 25.04
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 0.57 207 117.99
(c) For screening and spreading premixed aggregate :
114 Beldar Day 5 207 1035.00
130 Mistry Day 0.19 270 51.30
(d) Consolidation Charges
Chowkidar (at barriers for night watch
113 and for road roller) Day 0.27 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.13 500.00 65.00
Hire charges for boiler day
13 per 0.04 150.00 6.00
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
(e) M isc: Brushes etc. for cleaning, Wire bursh
364 (with thick wire) each 0.11 90.00 9.90
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 8525.28
Add for water charges @ 1% 85.25
TOTAL 8610.53
Add for contractor’s profit and
overheads @15% 1291.58
Cost of 100 sqm 9902.11
Cost of 1 sqm 99.02
Say 99.02

16.32 2 cm premix carpet surfacing with 1.8 cum and 0.90 cum of stone chippings of 13.2
mm size and 11.2 mm size respectively per 100 sqm. and 52 kg. and 56 kg. of hot bitumen
per cum of stone chippings of 13.2 mm and 11.2 mm size respectively including a tack
coat with hot straight run bitumen including consolidation with road roller of 6 to 9
tonne capacity etc. complete: (tack coat to be paid for separately).

16.32.3 With Refinery Modified Bitumen CRMB 55 conforming to IRC : SP : 53-1999.


Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7739 Modified Bitumen Refinery produced 26000.00 3744.00
CR MB - 55 tonne 0.144
2211 Carriage of bitumen tonne 0.144 53.21 7.66
2914 Solvent kg 10.08 60.00 604.80
2910 Stone chippings 13.2mm cum 1.8 1050.00 1890.00
2911 Stone chippings 11.2mm nominal size cum 0.9 1050.00 945.00
2202 Carriage of stone aggregate cum 2.7 53.21 143.67
370 Steam coal for heating bitumen quintal 0.288 120.00 34.56
2200 Carrige of steam coal tonne 0.0288 60.81 1.75
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.08 313 25.04
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 0.57 207 117.99
(c) For screening and spreading premixed aggregate :
114 Beldar Day 5 207 1035.00
130 Mistry Day 0.19 270 51.30
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.13 500.00 65.00
Hire charges for boiler day
13 per 0.04 150.00 6.00
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 9533.28
Add for water charges @ 1% 95.33
TOTAL 9628.61
Add for contractor’s profit and
overheads @15% 1444.29
Cost of 100 sqm 11072.91
Cost of 1 sqm 110.73
Say 110.73

16.33 2.5 cm premix carpet surfacing with 1.8 cum and 0.90 cum of stone chippings of
13.2 mm size and 11.2 mm size respectively per 100 sqm. and 52 kg. and 56 kg. of hot
bitumen per cum of stone chippings of 13.2 mm and 11.2 mm size respectively including a
tack coat with hot straight run bitumen including consolidation with road roller of 6 to 9
tonne capacity etc. complete: (tack coat to be paid for separately).

16.33.1 With paving Asphalt 80/100 heated and then mixed with solvent at the rate of
70 grams per kg of asphalt.
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
2916 Paving Asphalt 80/100 penetration tonne 0.18 42000.00 7560.00
2211 Carriage of bitumen tonne 0.18 53.21 9.58
2914 Solvent kg 12.6 60.00 756.00
2342 Carriage of solvent qunital 0.126 5.32 0.67
2910 Stone chippings 13.2mm cum 2.25 1050.00 2362.50
2911 Stone chippings 11.2mm nominal size cum 1.12 1050.00 1176.00
2202 Carriage of stone aggregate cum 3.37 53.21 179.32
370 Steam coal for heating bitumen quintal 0.36 120.00 43.20
2200 Carrige of steam coal tonne 0.036 60.81 2.19
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.08 313 25.04
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 0.71 207 146.97
(c) For screening and spreading premixed aggregate :
114 Beldar Day 6.25 207 1293.75
130 Mistry Day 0.19 270 51.30
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.15 500.00 75.00
Hire charges for boiler day
13 per 0.04 150.00 6.00
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 14549.02
Add for water charges @ 1% 145.49
TOTAL 14694.52
Add for contractor’s profit and
overheads @15% 2204.18
Cost of 100 sqm 16898.69
Cost of 1 sqm 168.99
Say 168.99

16.33 2.5 cm premix carpet surfacing with 1.8 cum and 0.90 cum of stone chippings of
13.2 mm size and 11.2 mm size respectively per 100 sqm. and 52 kg. and 56 kg. of hot
bitumen per cum of stone chippings of 13.2 mm and 11.2 mm size respectively including a
tack coat with hot straight run bitumen including consolidation with road roller of 6 to 9
tonne capacity etc. complete: (tack coat to be paid for separately).

16.33.2 With paving Asphalt 60/70 with no solvent


Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7309 Paving Asphalt 60/70 penetration tonne 0.18 23200.00 4176.00
2211 Carriage of bitumen tonne 0.18 53.21 9.58
2910 Stone chippings 13.2mm cum 2.25 1050.00 2362.50
2911 Stone chippings 11.2mm nominal size cum 1.12 1050.00 1176.00
2202 Carriage of stone aggregate cum 3.37 53.21 179.32
370 Steam coal for heating bitumen quintal 0.36 120.00 43.20
2200 Carrige of steam coal tonne 0.036 60.81 2.19
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.08 313 25.04
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 0.71 207 146.97
(c) For screening and spreading premixed aggregate :
114 Beldar Day 6.25 207 1293.75
130 Mistry Day 0.19 270 51.30
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.15 500.00 75.00
Hire charges for boiler day
13 per 0.04 150.00 6.00
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 10408.35
Add for water charges @ 1% 104.08
TOTAL 10512.44
Add for contractor’s profit and
overheads @15% 1576.87
Cost of 100 sqm 12089.30
Cost of 1 sqm 120.89
Say 120.89

16.33 2.5 cm premix carpet surfacing with 1.8 cum and 0.90 cum of stone chippings of
13.2 mm size and 11.2 mm size respectively per 100 sqm. and 52 kg. and 56 kg. of hot
bitumen per cum of stone chippings of 13.2 mm and 11.2 mm size respectively including a
tack coat with hot straight run bitumen including consolidation with road roller of 6 to 9
tonne capacity etc. complete: (tack coat to be paid for separately).

16.33.3 With Refinery Modified Bitumen CRMB 55 conforming to IRC : SP : 53-


Code
1999. Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7739 Modified Bitumen Refinery produced 26000.00 4680.00
CR MB - 55 tonne 0.18
2211 Carriage of bitumen tonne 0.18 53.21 9.58
2914 Solvent kg 12.6 60.00 756.00
2342 Carriage of solvent qunital 0.126 5.32 0.67
2910 Stone chippings 13.2mm cum 2.25 1050.00 2362.50
2911 Stone chippings 11.2mm nominal size cum 1.12 1050.00 1176.00
2202 Carriage of stone aggregate cum 3.37 53.21 179.32
370 Steam coal for heating bitumen quintal 0.36 120.00 43.20
2200 Carrige of steam coal tonne 0.036 60.81 2.19
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.08 313 25.04
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 0.71 207 146.97
(c) For screening and spreading premixed aggregate :
114 Beldar Day 6.25 207 1293.75
130 Mistry Day 0.19 270 51.30
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1 per 0.15 500.00 75.00
Hire charges for boiler day
13 per 0.04 150.00 6.00
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.11 90.00 9.90
(with thick wire) each
365 Soft brush each 0.32 50.00 16.00
9999 Brooms and gunny bags L. S. 6.76 1.00 6.76
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 11669.02
Add for water charges @ 1% 116.69
TOTAL 11785.72
Add for contractor’s profit and
overheads @15% 1767.86
Cost of 100 sqm 13553.57
Cost of 1 sqm 135.54
Say 135.54
16.34 2 cm premix carpet surfacing with 2.4cum of stone chippings 11.2 mm nominal size
per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen content)
complying with IS : 8887-1995 using 96kg per cum of chipping including consolidation
with road roller of 6 to 9 tonne capacity etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7742 Bitumen emulsion medium setting 19500.00 4485.00
(M.S.) confirming to IS : 8887-1995 tonne 0.23
2211 Carriage of bitumen tonne 0.23 53.21 12.24
2911 Stone chippings 11.2mm nominal size cum 2.4 1050.00 2520.00
2202 Carriage of stone aggregate cum 2.4 53.21 127.70
Labour For mixing and spreading premixed aggregate :
114 Beldar Day 3.54 207 732.78
130 Mistry Day 0.19 270 51.30
Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
13 per 0.04 150.00 6.00
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 8184.27
Add for water charges @ 1% 81.84
TOTAL 8266.12
Add for contractor’s profit and
overheads @15% 1239.92
Cost of 100 sqm 9506.03
Cost of 1 sqm 95.06
Say 95.06

16.35 2.5 cm premix carpet surfacing with 3 cum of stone chippings 10 mm nominal size
per 100 sqm and bitumen emulsion (medium setting min. 65% bitumen contents)
complying with IS : 8887-1995 using 96 kg per cum of chippings of road surface
including consolidation with road roller etc complete
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7742 Bitumen emulsion medium setting 19500.00 5616.00
(M.S.) confirming to IS : 8887-1995 tonne 0.288
2211 Carriage of bitumen tonne 0.288 53.21 15.32
2911 Stone chippings 11.2mm nominal size cum 3 1050.00 3150.00
2202 Carriage of stone aggregate cum 3 53.21 159.63
Labour For mixing and spreading premixed aggregate :
114 Beldar Day 4.1 207 848.70
130 Mistry Day 0.19 270 51.30
Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.27
and for road roller) 207 55.89
101 Bhishti Day 0.11 180 19.80
3 per 0.11 500.00 55.00
Hire charges of road roller day
1235 Diesel for road roller @ 18 litres litre 2 53.17 106.34
9999 Carriage of diesel L. S. 2.73 1.00 2.73
9999 Sundries L. S. 9.49 1.00 9.49
TOTAL 10090.20
Add for water charges @ 1% 100.90
TOTAL 10191.11
Add for contractor’s profit and
overheads @15% 1528.67
Cost of 100 sqm 11719.77
Cost of 1 sqm 117.20
Say 117.20

16.36 Providing and laying Bitumen Penetration Macadam with hard stone aggregate of
quality, size and grading as specified, with bitumen of suitable penetration grade including
required key aggregate as specified, spreading coarse aggregate with the help of self
propelled / tipper tail mounted aggregate spreader and applying bitumen by a pressure
distributor and then spreading key aggregate with the help of aggregate spreader complete
including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve
specified values of compaction and surface accuracy :
16.36.1 For 50mm compacted thickness using coarse aggregate of size 50-20 mm graded
@ 0.60 cum per 10 sqm key aggregate of size 12.5 mm graded @ 0.15 cum per 10 sqm.
With paving asphalt 80/100 @ 50 kg/10 sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 370 sqm.
(A) Material:
295 Stone aggregate 20mm cum 12.1 1100.00 13310.00
296 Stone Aggregate (Single size) : 12.5 mm cum 2.66 1050.00 2793.00
nominal size
297 Stone aggregate 10mm cum 1.78 1100.00 1958.00
293 Stone aggregate 40mm cum 9.99 1000.00 9990.00
2206 Carriage of aggregate 40mm cum 9.99 57.83 577.72
2202 Carriage of aggregate 20mm and 10 cum 16.54 53.21 880.09
mm
1159 Stone dust cum 1.16 700.00 812.00
2267 Carriage of stone dust. cum 1.16 53.21 61.72
2916 Paving Asphalt 80/100 penetration tonne 1.85 42000.00 77700.00
2211 Carriage of bitumen tonne 1.85 53.21 98.44
(B) Labour:
114 Beldar Day 34.67 207 7176.69
138 Sprayer Day 0.67 180 120.60
128 Mate Day 1.77 313 554.01
(C) Machinery :
1 per 0.45 500.00 225.00
Hire charges for boiler day
3 per 0.61 500.00 305.00
Hire charges of road roller day
9999 Misc. items as spray nozzle, joint L. S. 351 1.00 351.00
paper,coconut oil, country soap etc.

(D) Fuel:
1235 Diesel for road roller @ 18 litres litre 50.98 53.17 2710.61
9999 Carriage of diesel L. S. 70.07 1.00 70.07
TOTAL 119693.95
Add for water charges @ 1% 1196.94
TOTAL 120890.89
Add for contractor’s profit and
overheads @15% 18133.63
Cost of 370 sqm 139024.53
Cost of 1 sqm 375.74
Say 375.74

16.36 Providing and laying Bitumen Penetration Macadam with hard stone aggregate of
quality, size and grading as specified, with bitumen of suitable penetration grade including
required key aggregate as specified, spreading coarse aggregate with the help of self
propelled / tipper tail mounted aggregate spreader and applying bitumen by a pressure
distributor and then spreading key aggregate with the help of aggregate spreader complete
including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve
specified values of compaction and surface accuracy :
16.36.2 For 75 mm compacted thickness in two layers using stone aggregate of size 63-41
mm graded @ 0.90 cum per 10 sqm key aggregate of size 20.0 mm graded @ 0.18 cum
per 10 sqm. With paving asphalt 80/100 @ 68 kg/10 sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 300 sqm.
(A) Material:
292 Stone Aggregate (Single size) : 50 mm cum 8.1 1000.00 8100.00
nominal size
294 Stone Aggregate (Single size) : 25 mm cum 2.05 1100.00 2255.00
nominal size
295 Stone aggregate 20mm cum 14.58 1100.00 16038.00
296 Stone Aggregate (Single size) : 12.5 mm cum 2.57 1050.00 2698.50
nominal size
297 Stone aggregate 10mm cum 5.13 1100.00 5643.00
2202 Carriage of aggregate 20mm and 10 cum 32.43 53.21 1725.60
mm
2916 Paving Asphalt 80/100 penetration tonne 2.04 42000.00 85680.00
2211 Carriage of bitumen tonne 2.04 53.21 108.55
(B) Labour:
114 Beldar Day 52 207 10764.00
138 Sprayer Day 1 180 180.00
128 Mate Day 2.65 313 829.45
(C) Machinery :
1 per 0.5 500.00 250.00
Hire charges for boiler day
3 per 0.75 500.00 375.00
Hire charges of road roller day
9999 Misc. items as spray nozzle, joint L. S. 429 1.00 429.00
paper,coconut oil, country soap etc.

(D) Fuel:
1235 Diesel for road roller @ 18 litres litre 53.5 53.17 2844.60
9999 Carriage of diesel L. S. 73.06 1.00 73.06
TOTAL 137993.75
Add for water charges @ 1% 1379.94
TOTAL 139373.69
Add for contractor’s profit and
overheads @15% 20906.05
Cost of 300 sqm 160279.74
Cost of 1 sqm 534.27
Say 534.27

16.37 Providing and laying bitumen mastic wearing course (as per specifications) with industrial
bitumen of grade 85/25 conforming to IS : 702 prepared by using mastic cooker and laid to required
level and slope including providing antiskid surface with bitumen precoated fine grained hard stone
chipping of approved size at the rate of 0.005 cum per 10 sqm and at approximate spacing of 10cm
centre to centre in both directions, pressed into surface protruding 1mm to 4mm over mastic
surface, including cleaning the surface, removal of debris etc. all complete. (Considering bitumen using
10.2% as per MORTH specification.)
16.37.1 25mm thick.
Code Description Unit Quantity Rate Amount
Details of cost for surface area of 17.40 sqm for single layer of 25 mm finished
thickness.
(A) Material:
313 Blown type petroleum bitumen of cum 0.1023 35000.00 3580.50
penetration 85/25 of approved quality

295 Stone aggregate 20mm cum 0.02 1100.00 22.00


296 Stone Aggregate (Single size) : 12.5 mm cum 0.202 1050.00 212.10
nominal size
297 Stone aggregate 10mm cum 0.009 1100.00 9.90
2202 Carriage of aggregate 20mm and 10 cum 0.231 53.21 12.29
mm
1159 Stone dust cum 0.083 700.00 58.10
2267 Carriage of stone dust. cum 0.083 53.21 4.42
784 Lime aggregate tonne 0.174 800.00 139.20
2208 Carriage of lime aggregate tonne 0.174 53.21 9.26
2211 Carriage of bitumen tonne 0.1023 53.21 5.44
(B) Labour:
138 Sprayer Day 3.5 180 630.00
139 Skilled beldar Day 1.75 180 315.00
128 Mate Day 0.5 313 156.50
130 Mistry Day 0.5 270 135.00
(C) Machinery :
16 Mastic Cooker per 0.5 400.00 200.00
day
9999 Misc. items as spray nozzle, joint L. S. 153.27 1.00 153.27
paper,coconut oil, country soap etc.

(D) Fuel:
1235 Diesel for road roller @ 18 litres litre 100 53.17 5317.00
9999 Carriage of diesel L. S. 136.5 1.00 136.50
TOTAL 11096.48
Add for water charges @ 1% 110.96
TOTAL 11207.44
Add for contractor’s profit and
overheads @15% 1681.12
Cost of 17.4 sqm 12888.56
Cost of 1 sqm 740.72
Say 740.72

16.37 Providing and laying bitumen mastic wearing course (as per specifications) with industrial
bitumen of grade 85/25 conforming to IS : 702 prepared by using mastic cooker and laid to required
level and slope including providing antiskid surface with bitumen precoated fine grained hard stone
chipping of approved size at the rate of 0.005 cum per 10 sqm and at approximate spacing of 10cm
centre to centre in both directions, pressed into surface protruding 1mm to 4mm over mastic
surface, including cleaning the surface, removal of debris etc. all complete. (Considering bitumen using
10.2% as per MORTH specification.)
16.37. 2 40 mm thick
Code Description Unit Quantity Rate Amount
Details of cost for surface area of 10.875 sqm for single layer of 25 mm finished
thickness.
(A) Material:
313 Blown type petroleum bitumen of cum 0.1023 35000.00 3580.50
penetration 85/25 of approved quality

295 Stone aggregate 20mm cum 0.02 1100.00 22.00


296 Stone Aggregate (Single size) : 12.5 mm cum 0.202 1050.00 212.10
nominal size
297 Stone aggregate 10mm cum 0.009 1100.00 9.90
2202 Carriage of aggregate 20mm and 10 cum 0.231 53.21 12.29
mm
1159 Stone dust cum 0.083 700.00 58.10
2267 Carriage of stone dust. cum 0.083 53.21 4.42
784 Lime aggregate tonne 0.174 800.00 139.20
2208 Carriage of lime aggregate tonne 0.174 53.21 9.26
2211 Carriage of bitumen tonne 0.1023 53.21 5.44
(B) Labour:
138 Sprayer Day 3.5 180 630.00
139 Skilled beldar Day 1.75 180 315.00
128 Mate Day 0.5 313 156.50
130 Mistry Day 0.5 270 135.00
(C) Machinery :
16 Mastic Cooker per 0.5 400.00 200.00
day
9999 Misc. items as spray nozzle, joint L. S. 153.27 1.00 153.27
paper,coconut oil, country soap etc.

(D) Fuel:
1235 Diesel for road roller @ 18 litres litre 100 53.17 5317.00
9999 Carriage of diesel L. S. 136.5 1.00 136.50
TOTAL 11096.48
Add for water charges @ 1% 110.96
TOTAL 11207.44
Add for contractor’s profit and
overheads @15% 1681.12
Cost of 10.875 sqm 12888.56
Cost of 1 sqm 1185.16
Say 1185.16

16.38 2.5 cm thick bitumastic sheet with hot bitumen of approved quality using stone chippings (60%
12.5 mm nominal size and 40% 10 mm nominal size) @ 1.65 cum per 100 sqm and coarse sand at 1.65
cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum,
of sand over a tack coat with hot straight run bitumen including consolidation with road roller of 8 to 10
tonne etc. complete, (tack coat to be paid separately):

16.38.1 With paving Asphalt 80/100 heated and then mixed with solvent at the rate of 70 grams per kg
of asphalt.Description
Code Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
2916 Paving Asphalt 80/100 penetration tonne 0.303 42000.00 12726.00
2211 Carriage of bitumen tonne 0.303 53.21 16.12
2914 Solvent kg 21.21 60.00 1272.60
2342 Carriage of solvent qunital 0.2121 5.32 1.13
2910 Stone chippings 13.2mm cum 0.99 1050.00 1039.50
2911 Stone chippings 11.2mm nominal size cum 0.66 1050.00 693.00
2202 Carriage of stone aggregate cum 1.65 53.21 87.80
370 Steam coal for heating bitumen quintal 0.606 120.00 72.72
2200 Carrige of steam coal tonne 0.0606 60.81 3.69
982 Coarse sand cum 1.65 300.00 495.00
2203 Carriage of coarse sand cum 1.65 53.21 87.80
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.16 313 50.08
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 1.19 207 246.33
(c) For screening and spreading premixed aggregate :
114 Beldar Day 6.12 207 1266.84
130 Mistry Day 0.24 270 64.80
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.34
and for road roller) 207 70.38
101 Bhishti Day 0.13 180 23.40
3 per 0.13 500.00 65.00
Hire charges of road roller day
1 per 0.21 500.00 105.00
Hire charges for boiler day
13 per 0.05 150.00 7.50
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2.34 53.17 124.42
9999 Carriage of diesel L. S. 5.33 1.00 5.33
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.13 90.00 11.70
(with thick wire) each
365 Soft brush each 0.4 50.00 20.00
9999 Brooms and gunny bags L. S. 7.15 1.00 7.15
9999 Sundries L. S. 8.97 1.00 8.97
TOTAL 19151.85
Add for water charges @ 1% 191.52
TOTAL 19343.37
Add for contractor’s profit and
overheads @15% 2901.50
Cost of 100 sqm 22244.87
Cost of 1 sqm 222.45
Say 222.45

16.38 2.5 cm thick bitumastic sheet with hot bitumen of approved quality using stone chippings (60%
12.5 mm nominal size and 40% 10 mm nominal size) @ 1.65 cum per 100 sqm and coarse sand at 1.65
cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum,
of sand over a tack coat with hot straight run bitumen including consolidation with road roller of 8 to 10
tonne etc. complete, (tack coat to be paid separately):

16.38.2 With paving Asphalt 60/70.


Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7309 Paving Asphalt 60/70 penetration tonne 0.303 23200.00 7029.60
2211 Carriage of bitumen tonne 0.303 53.21 16.12
2910 Stone chippings 13.2mm cum 0.99 1050.00 1039.50
2911 Stone chippings 11.2mm nominal size cum 0.66 1050.00 693.00
2202 Carriage of stone aggregate cum 1.65 53.21 87.80
370 Steam coal for heating bitumen quintal 0.606 120.00 72.72
2200 Carrige of steam coal tonne 0.0606 60.81 3.69
982 Coarse sand cum 1.65 300.00 495.00
2203 Carriage of coarse sand cum 1.65 53.21 87.80
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.16 313 50.08
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 1.19 207 246.33
(c) For screening and spreading premixed aggregate :
114 Beldar Day 6.12 207 1266.84
130 Mistry Day 0.24 270 64.80
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.34
and for road roller) 207 70.38
101 Bhishti Day 0.13 180 23.40
3 per 0.13 500.00 65.00
Hire charges of road roller day
1 per 0.21 500.00 105.00
Hire charges for boiler day
13 per 0.05 150.00 7.50
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2.34 53.17 124.42
9999 Carriage of diesel L. S. 5.33 1.00 5.33
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.13 90.00 11.70
(with thick wire) each
365 Soft brush each 0.4 50.00 20.00
9999 Brooms and gunny bags L. S. 7.15 1.00 7.15
9999 Sundries L. S. 8.97 1.00 8.97
TOTAL 12181.72
Add for water charges @ 1% 121.82
TOTAL 12303.54
Add for contractor’s profit and
overheads @15% 1845.53
Cost of 100 sqm 14149.07
Cost of 1 sqm 141.49
Say 141.49

16.38 2.5 cm thick bitumastic sheet with hot bitumen of approved quality using stone chippings (60%
12.5 mm nominal size and 40% 10 mm nominal size) @ 1.65 cum per 100 sqm and coarse sand at 1.65
cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum,
of sand over a tack coat with hot straight run bitumen including consolidation with road roller of 8 to 10
tonne etc. complete, (tack coat to be paid separately):

16.38.3 With Refinery Modified Bitumen CRMB 55 conforming to IRC : SP : 53-1999.


Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7739 Modified Bitumen Refinery produced 26000.00 7878.00
CR MB - 55 tonne 0.303
2211 Carriage of bitumen tonne 0.303 53.21 16.12
2914 Solvent kg 21.21 60.00 1272.60
2342 Carriage of solvent qunital 0.2121 5.32 1.13
2910 Stone chippings 13.2mm cum 0.99 1050.00 1039.50
2911 Stone chippings 11.2mm nominal size cum 0.66 1050.00 693.00
2202 Carriage of stone aggregate cum 1.65 53.21 87.80
370 Steam coal for heating bitumen quintal 0.606 120.00 72.72
2200 Carrige of steam coal tonne 0.0606 60.81 3.69
982 Coarse sand cum 1.65 300.00 495.00
2203 Carriage of coarse sand cum 1.65 53.21 87.80
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.16 313 50.08
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 1.19 207 246.33
(c) For screening and spreading premixed aggregate :
114 Beldar Day 6.12 207 1266.84
130 Mistry Day 0.24 270 64.80
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.34
and for road roller) 207 70.38
101 Bhishti Day 0.13 180 23.40
3 per 0.13 500.00 65.00
Hire charges of road roller day
1 per 0.21 500.00 105.00
Hire charges for boiler day
13 per 0.05 150.00 7.50
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 2.34 53.17 124.42
9999 Carriage of diesel L. S. 5.33 1.00 5.33
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.13 90.00 11.70
(with thick wire) each
365 Soft brush each 0.4 50.00 20.00
9999 Brooms and gunny bags L. S. 7.15 1.00 7.15
9999 Sundries L. S. 8.97 1.00 8.97
TOTAL 14303.85
Add for water charges @ 1% 143.04
TOTAL 14446.89
Add for contractor’s profit and
overheads @15% 2167.03
Cost of 100 sqm 16613.92
Cost of 1 sqm 166.14
Say 166.14

16.39 4 cm thick bitumastic sheet with hot bitumen of approved quality using stone chippings (60%
12.5mm nominal size and 40% 10mm nominal size) @ 2.60cum per 100 sqm and coarse sand at
2.60cum per 100 sqm of road surface and with bitumen @ 56 kg/cum, of stone chippings and at 128
kg/cum of sand over a tack coat with hot straight run bitumen including consolidation with road roller of
8 to 10 tonne etc. complete, (tack coat to be paid separately):

16.39.1 With paving Asphalt 80/100 heated and then mixed with solvent at the rate of 70 grams per kg
of asphalt.Description
Code Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
2916 Paving Asphalt 80/100 penetration tonne 0.479 42000.00 20118.00
2211 Carriage of bitumen tonne 0.479 53.21 25.49
2914 Solvent kg 33.53 60.00 2011.80
2342 Carriage of solvent qunital 0.3353 5.32 1.78
2910 Stone chippings 13.2mm cum 1.56 1050.00 1638.00
2911 Stone chippings 11.2mm nominal size cum 1.04 1050.00 1092.00
2202 Carriage of stone aggregate cum 2.6 53.21 138.35
370 Steam coal for heating bitumen quintal 0.958 120.00 114.96
2200 Carrige of steam coal tonne 0.0958 60.81 5.83
982 Coarse sand cum 2.6 300.00 780.00
2203 Carriage of coarse sand cum 2.6 53.21 138.35
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.16 313 50.08
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 1.88 207 389.16
(c) For screening and spreading premixed aggregate :
114 Beldar Day 9.46 207 1958.22
130 Mistry Day 0.31 270 83.70
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.45
and for road roller) 207 93.15
101 Bhishti Day 0.18 180 32.40
3 per 0.18 500.00 90.00
Hire charges of road roller day
1 per 0.3 500.00 150.00
Hire charges for boiler day
13 per 0.03 150.00 4.50
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 3.24 53.17 172.27
9999 Carriage of diesel L. S. 4.42 1.00 4.42
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.09 90.00 8.10
(with thick wire) each
365 Soft brush each 0.27 50.00 13.50
9999 Brooms and gunny bags L. S. 5.33 1.00 5.33
9999 Sundries L. S. 16.12 1.00 16.12
TOTAL 29715.10
Add for water charges @ 1% 297.15
TOTAL 30012.25
Add for contractor’s profit and
overheads @15% 4501.84
Cost of 100 sqm 34514.09
Cost of 1 sqm 345.14
Say 345.14

16.39 4 cm thick bitumastic sheet with hot bitumen of approved quality using stone chippings (60%
12.5mm nominal size and 40% 10mm nominal size) @ 2.60cum per 100 sqm and coarse sand at
2.60cum per 100 sqm of road surface and with bitumen @ 56 kg/cum, of stone chippings and at 128
kg/cum of sand over a tack coat with hot straight run bitumen including consolidation with road roller of
8 to 10 tonne etc. complete, (tack coat to be paid separately):

16.39.2 With paving asphalt 60/70 with no solvent


Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7309 Paving Asphalt 60/70 penetration tonne 0.479 23200.00 11112.80
2211 Carriage of bitumen tonne 0.479 53.21 25.49
2910 Stone chippings 13.2mm cum 1.56 1050.00 1638.00
2911 Stone chippings 11.2mm nominal size cum 1.04 1050.00 1092.00
2202 Carriage of stone aggregate cum 2.6 53.21 138.35
370 Steam coal for heating bitumen quintal 0.958 120.00 114.96
2200 Carrige of steam coal tonne 0.0958 60.81 5.83
982 Coarse sand cum 2.6 300.00 780.00
2203 Carriage of coarse sand cum 2.6 53.21 138.35
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.16 313 50.08
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 1.88 207 389.16
(c) For screening and spreading premixed aggregate :
114 Beldar Day 9.46 207 1958.22
130 Mistry Day 0.31 270 83.70
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.45
and for road roller) 207 93.15
101 Bhishti Day 0.18 180 32.40
3 per 0.18 500.00 90.00
Hire charges of road roller day
1 per 0.3 500.00 150.00
Hire charges for boiler day
13 per 0.03 150.00 4.50
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 3.24 53.17 172.27
9999 Carriage of diesel L. S. 4.42 1.00 4.42
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.09 90.00 8.10
(with thick wire) each
365 Soft brush each 0.27 50.00 13.50
9999 Brooms and gunny bags L. S. 5.33 1.00 5.33
9999 Sundries L. S. 16.12 1.00 16.12
TOTAL 18696.32
Add for water charges @ 1% 186.96
TOTAL 18883.28
Add for contractor’s profit and
overheads @15% 2832.49
Cost of 100 sqm 21715.77
Cost of 1 sqm 217.16
Say 217.16

16.39 4 cm thick bitumastic sheet with hot bitumen of approved quality using stone chippings (60%
12.5mm nominal size and 40% 10mm nominal size) @ 2.60cum per 100 sqm and coarse sand at
2.60cum per 100 sqm of road surface and with bitumen @ 56 kg/cum, of stone chippings and at 128
kg/cum of sand over a tack coat with hot straight run bitumen including consolidation with road roller of
8 to 10 tonne etc. complete, (tack coat to be paid separately):

16.39.3 With Refinery Modified Bitumen CRMB 55 conforming to IRC : SP : 53-1999.


Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
7739 Modified Bitumen Refinery produced 26000.00 12454.00
CR MB - 55 tonne 0.479
2211 Carriage of bitumen tonne 0.479 53.21 25.49
2914 Solvent kg 33.53 60.00 2011.80
2342 Carriage of solvent qunital 0.3353 5.32 1.78
2910 Stone chippings 13.2mm cum 1.56 1050.00 1638.00
2911 Stone chippings 11.2mm nominal size cum 1.04 1050.00 1092.00
2202 Carriage of stone aggregate cum 2.6 53.21 138.35
370 Steam coal for heating bitumen quintal 0.958 120.00 114.96
2200 Carrige of steam coal tonne 0.0958 60.81 5.83
982 Coarse sand cum 2.6 300.00 780.00
2203 Carriage of coarse sand cum 2.6 53.21 138.35
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.16 313 50.08
115 Coolie Day 1.4 207 289.80
(b) For heating bitumen :
114 Beldar Day 1.88 207 389.16
(c) For screening and spreading premixed aggregate :
114 Beldar Day 9.46 207 1958.22
130 Mistry Day 0.31 270 83.70
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.45
and for road roller) 207 93.15
101 Bhishti Day 0.18 180 32.40
3 per 0.18 500.00 90.00
Hire charges of road roller day
1 per 0.3 500.00 150.00
Hire charges for boiler day
13 per 0.03 150.00 4.50
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 3.24 53.17 172.27
9999 Carriage of diesel L. S. 4.42 1.00 4.42
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.09 90.00 8.10
(with thick wire) each
365 Soft brush each 0.27 50.00 13.50
9999 Brooms and gunny bags L. S. 5.33 1.00 5.33
9999 Sundries L. S. 16.12 1.00 16.12
TOTAL 22051.10
Add for water charges @ 1% 220.51
TOTAL 22271.61
Add for contractor’s profit and
overheads @15% 3340.74
Cost of 100 sqm 25612.35
Cost of 1 sqm 256.12
Say 256.12

16.40 Providing and laying seal coat of premixed fine aggregate ( passing 2.36 mm and retained on
180 micron sieve) with bitumen using 128 kg of bitumen of grade 80 /100 bitumen per cum of fine
aggregate and 0.60cum of fine aggregate per 100 sqm of road surface including rolling and finishing
withroad
Code
roller all complete.
Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
2916 Paving Asphalt 80/100 penetration tonne 0.0768 42000.00 3225.60
2211 Carriage of bitumen tonne 0.0768 53.21 4.09
370 Steam coal for heating bitumen quintal 1.536 120.00 184.32
2200 Carrige of steam coal tonne 0.1536 60.81 9.34
982 Coarse sand cum 0.6 300.00 180.00
2203 Carriage of coarse sand cum 0.6 53.21 31.93
Labour for cleaning .
114 Beldar Day 0.49 207 101.43
128 Mate Day 0.06 313 18.78
115 Coolie Day 0.97 207 200.79
(b) For heating bitumen :
114 Beldar Day 0.3 207 62.10
(c) For screening and spreading premixed aggregate :
114 Beldar Day 1.11 207 229.77
130 Mistry Day 0.05 270 13.50
(d) Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.15
and for road roller) 207 31.05
101 Bhishti Day 0.06 180 10.80
3 per 0.06 500.00 30.00
Hire charges of road roller day
1 per 0.05 500.00 25.00
Hire charges for boiler day
13 per 0.01 150.00 1.50
Hire charges for mixer day
1235 Diesel for road roller @ 18 litres litre 1.08 53.17 57.42
9999 Carriage of diesel L. S. 0.26 1.00 0.26
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.05 90.00 4.50
(with thick wire) each
365 Soft brush each 0.12 50.00 6.00
9999 Sundries L. S. 18.2 1.00 18.20
TOTAL 4446.38
Add for water charges @ 1% 44.46
TOTAL 4490.84
Add for contractor’s profit and
overheads @15% 673.63
Cost of 100 sqm 5164.47
Cost of 1 sqm 51.64
Say 51.64

16.41 Providing and laying seal coat over prepared surface of road with bitumen heated in bitumen
boiler fitted with the spray set spraying using 98 kg of bitumen of grade 80/100 and blinding surface
with 0.90cum of stone aggregate of 6.7 mm size (Passing 11.2mm sieve and retained on 2.36mm sieve)
per 100 sqm of road surface including rolling and finishing with power road roller all complete.
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm.
2916 Paving Asphalt 80/100 penetration tonne 0.098 42000.00 4116.00
2211 Carriage of bitumen tonne 0.098 53.21 5.21
370 Steam coal for heating bitumen quintal 1.96 120.00 235.20
2200 Carrige of steam coal tonne 0.196 60.81 11.92
298 Stone Aggregate (Single size) : 06 mm cum 0.9 400.00 360.00
nominal size
2202 Carriage of stone aggregate cum 0.9 53.21 47.89
For heating bitumen, cleaning road surface and spreading :
138 Sprayer Day 0.06 180 10.80
130 Mistry Day 0.04 270 10.80
114 Beldar Day 0.69 207 142.83
Labour for cleaning .
114 Beldar Day 1.4 207 289.80
128 Mate Day 0.11 313 34.43
115 Coolie Day 1.4 207 289.80
Labour for screening and spreading aggregate :
114 Beldar Day 0.51 207 105.57
128 Mate Day 0.05 313 15.65
Consolidation Charges
113 Chowkidar (at barriers for night watch Day 0.15
and for road roller) 207 31.05
101 Bhishti Day 0.06 180 10.80
3 per 0.06 500.00 30.00
Hire charges of road roller day
7 Hire charges of Coaltar Sprayer per 0.06 200.00 12.00
day
1 per 0.06 500.00 30.00
Hire charges for boiler day
1235 Diesel for road roller @ 18 litres litre 1.08 53.17 57.42
9999 Carriage of diesel L. S. 0.26 1.00 0.26
(e) M isc:
364 Brushes etc. for cleaning, Wire bursh 0.05 90.00 4.50
(with thick wire) each
365 Soft brush each 0.12 50.00 6.00
9999 Brooms and gunny bags L. S. 2.73 1.00 2.73
9999 Sundries L. S. 18.2 1.00 18.20
TOTAL 5878.87
Add for water charges @ 1% 58.79
TOTAL 5937.65
Add for contractor’s profit and
overheads @15% 890.65
Cost of 100 sqm 6828.30
Cost of 1 sqm 68.28
Say 68.28

16.42 Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size)
in pavements, laid to required slope and camber in panels as required including consolidation finishing
and tamping complete.
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
293 Stone aggregate 40mm cum 0.52 1000.00 520.00
295 Stone aggregate 20 mm cum 0.22 1100.00 242.00
297 Stone aggregate 10 mm cum 0.11 1050.00 115.50
2206 Carriage of aggregate 40mm cum 0.52 57.83 30.07
2202 Carriage of aggregate 20mm cum 0.33 53.21 17.56
982 Coarse sand cum 0.445 300.00 133.50
2261 Carriage of coarse sand cum 0.445 53.21 23.68
367 Cement tonne 0.32 5200.00 1664.00
2209 Carriage of cement tonne 0.32 47.29 15.13
Labour:
155 Mason Day 0.1 180 18.00
114 Beldar Day 1.63 207 337.41
101 Bhishti Day 0.7 180 126.00
2 Mixer Day 0.077 400 30.80
12 Vibrator Day 0.07 150 10.50
9999 Sundries L. S. 26 1.00 26.00
side shuttering (Rate as per 5.9.1 of sqm 0.407 234.53 95.45
subhead RCC)
9999 Sundries L. S. 1.43 1.00 1.43
TOTAL 3407.04
Add 1% for water charges 34.07
TOTAL 3441.11
Add 15 % for contractor’s profit and overheads 516.17
Cost of 1 cum. 3957.27
Say 3,957.27

16.43 Providing and laying design mix cement concrete in roads, taxi tracks and runways having a
minimum works test beam flexural strength of 30 kg. per sq. cm at 28 days using not less than 340 Kg.
of cement per cum of finished concrete, coarse sand and graded stone aggregate of 40mm nominal size
in appropriate proportions as per specified design criteria approved by Engineer-in-charge,mechanically.
vibrated using needle and surface vibrators including steel form work with sturdy M- S. channel
sections including curing and providing and filling construction joints and dummy joints with approved
joint filter Primer or equivalent including rounding of the edges and filling the grooves 10x25mm deep
at top for construction joints and 10mmx50mm deep at top for dummy joints with joint sealing
compound (conforming to grade B of IS : 1834) including making necessary arrangements for
expansion joints etc. all complete.
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
293 Stone aggregate 40mm cum 0.52 1000.00 520.00
295 Stone aggregate 20 mm cum 0.22 1100.00 242.00
297 Stone aggregate 10 mm cum 0.11 1050.00 115.50
2206 Carriage of aggregate 40mm cum 0.52 57.83 30.07
2202 Carriage of aggregate 20mm cum 0.33 53.21 17.56
982 Coarse sand cum 0.445 300.00 133.50
2261 Carriage of coarse sand cum 0.445 53.21 23.68
367 Cement tonne 0.34 5200.00 1768.00
2209 Carriage of cement tonne 0.34 47.29 16.08
Labour:
114 Beldar Day 0.9 207 186.30
115 Coolie Day 0.6 207 124.20
101 Bhishti Day 0.27 180 48.60
123 Mason 1st class Day 0.05 270 13.50
124 Mason 2nd class Day 0.05 223 11.15
128 Mate Day 0.04 313 12.52
2 Mixer Day 0.05 400 20.00
21 Pin vibrator Day 0.025 150 3.75
22 Surface Vibrator Day 0.05 150 7.50
1235 Diesel litre 1.7 53.17 90.39
9999 Tirrection and transportation and L.S 9.49 1.00 9.49
testing of weigh batch plant etc
155 Mason Day 0.07 180 12.60
114 Beldar Day 0.07 207 14.49
Add for construction and filling of sqm 1 163.68 163.68
dummy joints as per Ann-A
Add for steel form work as per Ann-B sqm 1 379.58 379.58

9999 Sundries L. S. 1.43 1.00 1.43


TOTAL 3965.57
Add 1% for water charges 39.66
TOTAL 4005.22
Add 15 % for contractor’s profit and overheads 600.78
Cost of 1 cum. 4606.00
Say 4,606.00

ANNEXTU RE ‘A’ to item No. 16.43


Details of cost for 8.50 cum.
Materials:
316 Bitumen solution primer of approved 30.00 23.40
quality lit 0.78
9999 Carriage of primer L. S. 0.91 1.00 0.91
314 Bitumen hot sealing compound : grade 35.00 338.80
A ilogram 9.68
9999 Carriage of sealinh compound L. S. 0.91 1.00 0.91
370 Steam coal for heating bitumen quintal 0.015 120.00 1.80
9999 Carriage of steam coal L. S. 0.91 1.00 0.91
114 Beldar Day 0.68 207 140.76
131 Painter Day 0.1 180 18.00
123 Mason 1st class Day 3 270 810.00
124 Mason 2nd class Day 0.25 223 55.75
TOTAL 1391.24
Cost of 8.5 cum. 1391.24
Cost of 1 cum. 163.68
Say 163.68

ANNEXTU RE B to item No. 16.43


STEEL FORM WORK :
Materials :
1007 M.S. channels quintal 0.0407104 4600.00 187.27
2205 Carriage tonne 0.004071 47.29 0.19
114 Beldar Day 11.46 207 2372.22
103 Blacksmith 2nd class Day 2.86 223 637.78
7254 Hardening Compound litre 1 29.00 29.00
TOTAL 3226.46
Cost of 50 slabs of 8.5 cum 3226.46
Cost of 1 cum. 379.58
Say 379.58

16.44 Extra for providing and mixing hardening campound of approved quality as per manufacturer’s
specification in cement concrete.
Code Description Unit Quantity Rate Amount
Details of cost for 1.00 litre
Materials :
7254 Hard crete (including cartage) litre 1 29.00 29.00
TOTAL 29.00
Add 1% for water charges 0.29
TOTAL 29.29
Add 15% for contractor’s profit and
overheads 4.39
Cost of per litre 33.68
Say 33.68

16.45 Providing and fixing in position premoulded joint filler in expansion joints.
Code Description Unit Quantity Rate Amount
Details of cost for 18mm thick 15cm deep and 300m in length = 300x0.15 = 45 sqm.
317 18mm thick joint filler sqm 45 300.00 13500.00
2211 Carriage of filler tonne 0.21 53.21 11.17
Labour for fixing etc. :
114 Beldar Day 3 207 621.00
124 Mason 2nd class Day 1 223 223.00
9999 Sundries L. S. 26.91 1.00 26.91
TOTAL 14382.08
Add 1% for water charges 143.82
TOTAL 14525.90
Add 15 % for contractor’s profit and overheads 2178.89
Cost for 300m length, 18mm width and 16704.79
15cm depth
Cost for one cm. depth one cm . width 2.06
per metre length.
Say 2.06

16.46 Providing and laying in position bitumen hot sealing compound for expansion joints etc.
16.46.1 Using grade ‘A’ sealing com pound.
Code Description Unit Quantity Rate Amount
Details of cost for 20mm wide 20mm deep and 300 metres in length.
314 Bitumen hot sealing compound : grade 1076.60
A ilogram 30.76 35.00
2211 Carriage of filler tonne 0.03 53.21 1.60
Labour for filling:
114 Beldar Day 2.5 207 517.50
124 Mason 2nd class Day 1 223 223.00
9999 Sundries L. S. 20.67 1.00 20.67
TOTAL 1839.37
Add 1% for water charges 18.39
TOTAL 1857.76
Add 15 % for contractor’s profit and overheads 278.66
Cost for 300m length, 20mm width and 2136.42
20mm depth
Cost for one cm. depth one cm . width 1.78
per metre length.
Say 1.78

16.47 Painting runway/taxi track/apron marking with adequate no. of coats to give uniform finish with
road marking paint of superior make as approved by the Engineer-in-charge i/c cleaning the surface of
all dirt, scales, oil, grease and other foreign material etc. and lining out complete.
16.47.1 New work (Two or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10sqm.
Material:
7256 Road marking paint litre 2.79 148.00 412.92
9999 Carriage of paint L. S. 5.07 1.00 5.07
Labour:
114 Beldar Day 0.54 207 111.78
131 Painter Day 0.54 180 97.20
9999 Sundries (including painting brush, wire L. S. 36.4 1.00 36.40
brush, labour for controlling traffic and
other T&P etc.)
TOTAL 663.37
Add 1% for water charges 6.63
TOTAL 670.00
Add 15 % for contractor’s profit and 100.50
overheads
Cost of 10 sqm 770.50
Cost of 1 sqm 77.05
Say 77.05

16.47 Painting runway/taxi track/apron marking with adequate no. of coats to give uniform finish with
road marking paint of superior make as approved by the Engineer-in-charge i/c cleaning the surface of
all dirt, scales, oil, grease and other foreign material etc. and lining out complete.
16.47.2 Old work (One or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10sqm.
Material:
7256 Road marking paint litre 1.66 148.00 245.68
Labour:
114 Beldar Day 0.36 207 74.52
131 Painter Day 0.36 180 64.80
9999 Sundries (including painting brush, wire L. S. 24.44 1.00 24.44
brush, labour for controlling traffic and
other T&P etc.)
TOTAL 409.44
Add 1% for water charges 4.09
TOTAL 413.53
Add 15 % for contractor’s profit and 62.03
overheads
Cost of 10 sqm 475.56
Cost of 1 sqm 47.56
Say 47.56

16.48 Painting road surface marking with adequate no. of coats to give uniform finish with ready
mixed road marking paint conforming to IS : 164, on bituminous surface in white/yellow shade
including cleaning the surface of all dirt, scales, oil, grease and foreign material etc. complete.
16.48.1 New work (Two or more coats).
Code Description Unit Quantity Rate Amount
Details of cost for 10sqm.
Material:
7255 Road marking paint (spirit based) litre 1.48 97.00 143.56
9999 Carriage of paint L. S. 2.65 1.00 2.65
Labour:
114 Beldar Day 1.68 207 347.76
131 Painter Day 0.54 180 97.20
128 Mate Day 0.1 313 31.30
9999 Sundries (including painting brush, wire L. S. 36.4 1.00 36.40
brush, labour for controlling traffic and
other T&P etc.)
TOTAL 658.87
Add 1% for water charges 6.59
TOTAL 665.46
Add 15 % for contractor’s profit and 99.82
overheads
Cost of 10 sqm 765.28
Cost of 1 sqm 76.53
Say 76.53

16.48 Painting road surface marking with adequate no. of coats to give uniform finish with ready
mixed road marking paint conforming to IS : 164, on bituminous surface in white/yellow shade
including cleaning the surface of all dirt, scales, oil, grease and foreign material etc. complete.
16.48.2 Old work (One or more coats)
Code Description Unit Quantity Rate Amount
Details of cost for 10sqm.
Material:
7255 Road marking paint (spirit based) litre 0.89 97.00 86.33
9999 Carriage of paint L. S. 0.65 1.00 0.65
Labour:
114 Beldar Day 1.12 207 231.84
131 Painter Day 0.36 180 64.80
128 Mate Day 0.06 313 18.78
9999 Sundries (including painting brush, wire L. S. 24.44 1.00 24.44
brush, labour for controlling traffic and
other T&P etc.)
TOTAL 426.84
Add 1% for water charges 4.27
TOTAL 431.11
Add 15 % for contractor’s profit and 64.67
overheads
Cost of 10 sqm 495.77
Cost of 1 sqm 49.58
Say 49.58

16.49 Making bell mouth opening/ entrance of size 100x50x50cm for drainage pipe under footpath
including providing cement concrete 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20mm
nominal size) for shape of bell mouth including plastering providing and fixing precast R.C.C./
S.F.R.C. slab including plastering with cement mortar 1:3 (1 cement: 3 fine sand) of 6 mm thickness on
exposed surface of the slab & bell mouth including centring, shuttering & neat cement punning inside
the bell mouth etc. all complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 Nos.
(i) Earth work in excavation (Rate as 121.96
A per item no. 2.8.1) cum 0.94 129.74
Cement concrete 1:4:8 (Rate as per item 425.43
A no.4.1.8) cum 0.15 2,836.20
Cement concrete 1:3:6 (Rate as per item 6654.03
A no.4.1.5) cum 1.95 3,412.32
RC C in shelves 1:2:4 (Rate as per item 1067.44
A no. 5.3 SH : R.C.C.) cum 0.25 4,269.75
Reinforcement for RCC (Rate as per 1466.36
A item no 5.22.1) kg 25 58.65
Centering and shuttering (Rate as per 3088.73
A item no.5.9.1) sqm 13.17 234.53
cement plaster on RCC slab (Rate as per 508.17
A item no.13.16.1) sqm 6.5 78.18
Neat cement punning: (Rate as per item 127.37
A no.l3.18 S.H. Finishing) sqm 4.81 26.48
367 Cement tonne 0.024 5200.00 124.80
2209 Carriage of cem ent tonne 0.024 47.29 1.13
983 Fine sand cum 0.05 300.00 15.00
2261 Carriage of fine sand cum 0.05 53.21 2.66
114 Beldar Day 0.035 207 7.25
101 Bhishti Day 0.003 180 0.54
9999 Hire charges of mixer L. S. 1.27 1.00 1.27
9999 Sundries L. S. 1.27 1.00 1.27
Labour for plaster
155 Mason Day 0.33 180 59.40
115 Coolie Day 0.488 207 101.02
101 Bhishti Day 0.6 180 108.00
9999 Extra for removing burr L. S. 8.71 1.00 8.71
9999 Scaffolding L. S. 7.62 1.00 7.62

TOTAL 13898.16
Add 1% for water charges except on A 4.39

TOTAL 13902.55
Add 15 % for contractor’s profit and 66.46
overheads except on A
Cost of 10 nos 13969.01
Cost of 1 no 1396.90
Say 1,396.90

16.50 Providing and fixing Glow studs of size 100x20 mm made of heavy duty body shall be moulded
ASA (Acrylic styrene Acryloretrite ) or HIP (High impact polystyrene) or ABS having electronically
welded micro- prismatic lens with abrasion resistant coating as approved by Engineer in charge. The
glow stud shall support a load of 13635 kg tested in accordance with ASTM D4280. The slope of retro-
reflective surface shall be 35 +/-5 degrees to base .The reflective panels on both sides with at least 12
cm of reflective area up each side. The luminance intensity should be as per the specificatio n and
shall be tested as described in ASTM I: 809 as recommended in BS : 873 part 4 : 1973. The studs
shall be fixed to the Road surface using the adhesive conform ing to IS, as per procedure
recommended by the manufacturer complete and as per direction of Engineer-in-charge.
Code Description Unit Quantity Rate Amount
Details of cost for 15 Nos.
Materials:
7426 Cats eye each 15 450.00 6750.00
Labour:
114 Beldar Day 0.5 207 103.50
124 Mason 2nd class Day 0.5 223 111.50
9999 Sundries (including material required for L. S. 39 1.00 39.00
fixing cats eyes and providing
barricading to divert traffic )
TOTAL 7004.00
Add 1% for water charges 70.04
TOTAL 7074.04
Add 15 % for contractor’s profit and overheads 1061.11
Cost of 15 nos 8135.15
Cost of 1 no 542.34
Say 542.34

16.51 Preparation of sub-base road pavement with commercial dry lime (slaked), fly ash stabilised soil
with a mix of 3% lime, 12% fly ash and 85% local suitable soil by weight, so as to achieve minimum
field C.B.R. of 20 including mixing, rolling with road roller curing etc. all complete.
16.51.1 Minimum thickness 15 cm.
Code Description Unit Quantity Rate Amount
Details of cost for 6.67 sqm. or 1 cum.
Materials:
777 slaked lime quintal 0.41 200.00 82.00
2208 Carriage of lime cum 0.0683333 53.21 3.64
1980 Flyash cum 0.277 6.00 1.66
2262 Carriage of Flyash cum 0.277 53.21 14.74
979 Royalty for good earth cum 0.655 11.00 7.21
2241 Carriage of good earth cum 0.655 66.51 43.56
Labour:
(i)For earth work:
114 Beldar Day 0.116 207 24.01
115 Coolie Day 0.116 207 24.01
(i)For mixing:
114 Beldar Day 0.025 207 5.18
115 Coolie Day 0.025 207 5.18
(i)For rolling layers:
113 Chowkidar Day 0.0008 207 0.17
3 Hire charges of roller Day 0.0008 500.00 0.40
1235 Diesel for road roller litre 0.0144 53.17 0.77
2342 Carriage of diesel quintal 0.0002 5.32 0.00

9999 Sundries L. S. 0.18 1.00 0.18


114 Beldar Day 0.26 207 53.82
115 Coolie Day 0.26 207 53.82
101 Bhishti Day 0.18 180 32.40
TOTAL 352.73
Add 1% for water charges 3.53
TOTAL 356.26
Add 15 % for contractor’s profit and overheads 53.44
Cost of 1 no 409.70
Say 409.70

16.52 Providing and fixing precast lime fly ash concrete blocks 1:2:3:6 (1 lime : 2 fly ash : 3 coarse sand
: 6 graded stone aggregate 20 mm nominal size) including finishing with 10mm thick cement mortar 1:3
(1 cement: 3 coarse sand) in foot paths including preparation of sub grade with a hand rammer, laying
10 mm thick leveling course of fine sand (jamuna sand) and filling the joints with fine sand.
Code Description Unit Quantity Rate Amount
Sub Analysis - X
Details of cost for 1 cum of lime Flyash mortar 1:2:3 (lime:2 flyash:3 c oarse sand).
Materials:
773 Unslaked lime quintal 1.52 400.00 608.00
2208 Carriage of unslaked lime cum 0.24 53.21 12.77
1980 Flyash cum 0.48 6.00 2.88
2262 Carriage of Flyash cum 0.48 53.21 25.54
982 Coarse sand cum 0.72 300.00 216.00
2261 Carriage of coarse sand cum 0.72 53.21 38.31
Labour:
(i)For earth work:
114 Beldar Day 0.9 207 186.30
101 Bhishti Day 0.45 180 81.00
9999 Running and upkeep of the mortar mile L. S. 26.91 1.00 26.91

9999 Sundries L. S. 13.52 1.00 13.52


TOTAL 1211.23
Cost of 1 sqm 1211.23
Say 1,211.23

Sub Analysis - Y
Details of cost for 1 cum. of cement concrete
Materials:
Lime Flyash mortar
Rate as per Sub Analysis 16.52 (Marked cum 0.4 1,211.23 484.49
295 ‘X’)
Stone aggregate 20 mm cum 0.64 1100.00 704.00
297 Stone aggregate 10 mm cum 0.21 1050.00 220.50
2202 Carriage of aggregate below 20mm cum 0.85 53.21 45.23
Labour:
115 Coolie Day 0.65 207 134.55
114 Beldar Day 0.6 207 124.20
101 Bhishti Day 0.27 180 48.60
123 Mason ist class Day 0.05 270 13.50
124 Mason 2nd class Day 0.05 223 11.15
128 Mate Day 0.04 313 12.52
9999 Hire and running charges of mixer L. S. 26.91 1.00 26.91
9999 Hire charges of steel moulds, table L. S. 53.82 1.00 53.82
vibrators, rammers , bolts, nuts and
washers etc.
9999 Sundries L. S. 13.52 1.00 13.52
TOTAL 1892.99
Cost of 1 cum. 1892.99
Say 1,892.99

Details of cost for a path of area 10.00 sqm. no. of blocks required for 10.00 sqm. = 108 nos.
(a) Concrete in blocks
(108x0.30x0.30x0.09 = 0.875 cum.)
(Rate as per sub analysis Marked ‘Y’)
cum 0.875 1413.58 1236.88 cum 0.875 1,892.99 1656.37
(b) Labour for Surface excav ation .
115 Coolie Day 0.72 207 149.04
114 Beldar Day 0.6 207 124.20
(c) For levelling course of fine sand
6501 Jamuna sand cum 0.1 175.00 17.50
2335 Carriage of Jamuna sand cum 0.1 53.21 5.32
Labour:
115 Coolie Day 0.0089 207 1.84
114 Beldar Day 0.0107 207 2.21
101 Bhishti Day 0.0035 180 0.63
(d) For finishing with 10mm thick cement plaster 1:3 qty. for 9.72sqm.
cement mortar 1:3(1 Cement: 3 Coarse s cum 0.0972 3262.33 317.10
155 Mason Day 0.787 180 141.66
115 Coolie Day 0.787 207 162.91
101 Bhishti Day 0.262 180 47.16
9999 Scaffolding and Sundries L.S. 12.22 1.00 12.22
(e) For laying blocks and filling joints with
6501 Jamuna sand cum 0.005 175.00 0.88
2335 Carriage of Jamuna sand cum 0.005 53.21 0.27
101 Bhishti Day 0.05 180 9.00
123 Mason ist class Day 0.9 270 243.00
115 Coolie Day 1.98 207 409.86

TOTAL 3301.16
Add 1% for water charges 33.01
TOTAL 3334.18
Add 15 % for contractor’s profit and overheads 500.13
Cost of 10 sqm or .9 cum. 3834.30
Cost of 1 cum. 4260.34
Say 4,260.34

16.53 Providing and fixing concertina coil fencing with required dia 600 mm upto 3m height of wall
with existing angle iron ‘Y’ shaped placed 2.4 m or 3.00 m apart and with 9 horizontal R.B.T. stud tied
with G.I. staples and G.I. clips to retain horizontal including necessary bolts or G.I. barbed wire tied to
angle iron all complete as per direction of Engineer-in-charge with reinforced barbed tape (R.B.T.) /
Spring core (2.5mm thick) wire of high tensile strength of 165 kg/ sq.mm. with tape (0.52 mm thick) of
Supreme make or equivalent and weight 43.478gm/ metre (cost of M.S. angle, C.C. blocks shall be paid
separately)
Code Description Unit Quantity Rate Amount
Details of cost for 30.00 m length
Materials :
8691 650.00 1950.00
10m
Punched tape concertina coil 600 m bundl
dia. openable length (Total length 90m) e 3
8692 R.B.T. Reinforced Barbed Tape 9 rounds metre 270 7.50 2025.00
8693 Turn buckle and strengthening bolt. ach set 10 35.00 350.00
9999 G.I. staples clips etc. LS 49.4 1.00 49.40
Labour for fixing straightening cutting of tape/ coils & wire
102 Blacksmith 1st class Day 0.5 270 135.00
103 Blacksmith 2nd class Day 0.5 223 111.50
114 Beldar Day 1 207 207.00
TOTAL 4827.90
Add 1% for water charges 48.28
TOTAL 4876.18
Add for contractor’s profit and
overheads @15% 731.43
Cost of 30 metre 5607.61
Cost of 1 metre 186.92
Say 186.92

16.54 Providing and laying Dense Bituminous macadam on prepared surface with specified graded
crushed stone aggregate for profile corrective base/ binding course including loading of aggregate with
FE loader and hot mixing of stone aggregate, filler and bitumen in hot mix plant, transporting the
mixed material by tippers to paver and laying the mixed material with paver finisher fitted with
electronic sensing device to the required level and grade and rolling by road roller as per MORTH
specifications, to achieve the desired density, but excluding the cost of primer / tack coat.

16.54.1 50/75mm average compacted thickness with bitumen of 60/70 grade @ 5% (percentage
by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate).
Code Description Unit Quantity Rate Amount
Details of cost for 63.91 cum (or 147 M.T.) (A day’s output of hot mix plant).
Materials
7309 Paving Asphalt 60/70 penetration tonne 7.35 23200.00 170520.00
2211 Carriage of bitumen tonne 7.35 53.21 391.09
294 Stone Aggregate (Single size) : 25 mm cum 29.36 1100.00 32296.00
nominal size
296 Stone Aggregate (Single size) : 12.5 mm cum 27.4 1050.00 28770.00
nominal size
2202 Carriage of aggregate stone aggregate cum 56.76 53.21 3020.20

1159 Stone dust cum 36.68 700.00 25676.00


2267 Carriage of stone dust. cum 36.68 53.21 1951.74
777 slaked lime quintal 27.93 200.00 5586.00
2208 Carriage of lime cum 2.16 53.21 114.93
(B) Labour required for loading platform, paver and for taking level etc.
114 Beldar Day 11 207 2277.00
113 Chowkidar Day 3 207 621.00
130 Mistry Day 1 270 270.00
101 Bhishti Day 3.45 180 621.00
(C) Machinery/ H ire charges:
8 Hire charges of B.G. Plant. Day 1 5,000.00 5000.00
17 Hire charges of tipper Day 3.54 700.00 2478.00
18 Hire charges of loader Day 1 700.00 700.00
3 Hire charges of Road roller Day 3.45 500.00 1725.00
(D) Fuel charges:
1235 Diesel litre 1013.95 53.17 53911.72
9999 Carriage of diesel LS 1388.01 1.00 1388.01
5001 Mobil oil litre 1.47 95.00 139.65
TOTAL 337457.35
Add 1% for water charges 3374.57
TOTAL 340831.92
Add for contractor’s profit and
overheads @15% 51124.79
Cost of 63.91 cum (147 MT) 391956.71
Cost of 1 cum 6132.95
Say 6132.95

16.55 Providing and laying Bituminous Macadam on prepared surface with specified graded crushed
stone aggregate for profile corrective base/ binder course including loading of aggregate with F.E. loader
, hot mixing of stone aggregates and bitumen in hot mix plant, transporting the mixed material by
tippers to paver and laying the mixed material with paver finisher fitted with electronic sensing device
to the required level and grade and rolling with road rollers, as per MORTH specification to achieve the
desired density and compaction but excluding the cost of primer/ tack coat.

16.55.1 50mm / 75mm average compacted thickness with bitumen of 60/70 grade @ 3.5% (Percentage
by weight of total mix)
Code Description Unit Quantity Rate Amount
Details of cost for 66.81 cum
Materials
7309 Paving Asphalt 60/70 penetration tonne 5.15 23200.00 119480.00
2211 Carriage of bitumen tonne 5.15 53.21 274.03
294 Stone Aggregate (Single size) : 25 mm cum 21.87 1100.00 24057.00
nominal size
296 Stone Aggregate (Single size) : 12.5 mm cum 74.55 1050.00 78277.50
nominal size
2202 Carriage of aggregate stone aggregate cum 96.42 53.21 5130.51

1159 Stone dust cum 2.98 700.00 2086.00


2267 Carriage of stone dust. cum 2.98 53.21 158.57
(B) Labour required for loading platform, paver and for taking level etc.
114 Beldar Day 11 207 2277.00
113 Chowkidar Day 3 207 621.00
130 Mistry Day 1 270 270.00
101 Bhishti Day 3.61 180 649.80
(C) Machinery/ H ire charges:
8 Hire charges of B.G. Plant. Day 1 5,000.00 5000.00
17 Hire charges of tipper Day 3.54 700.00 2478.00
18 Hire charges of loader Day 1 700.00 700.00
3 Hire charges of Road roller Day 3.61 500.00 1805.00
(D) Fuel charges:
1235 Diesel litre 1016.83 53.17 54064.85
9999 Carriage of diesel LS 1388.01 1.00 1388.01
5001 Mobil oil litre 1.47 95.00 139.65
TOTAL 298856.92
Add 1% for water charges 2988.57
TOTAL 301845.49
Add for contractor’s profit and
overheads @15% 45276.82
Cost of 66.81 cum 347122.31
Cost of 1 cum 5195.66
Say 5195.66

16.56 Providing and laying Dense Bituminous concrete on prepared surface with specified graded
stone aggregate for wearing course including loading of aggregate with F.E. loader , and hot mixing of
bitum en with filler and stone aggregate in hot mix plant , transporting the mixed material by tippers to
paver and laying the mixed material with mechanical paver finisher fitted with electronic sensing device
to the required level and grade and rolling with road rollers, as per MORTH specification, to achieve the
desired density and compaction but excluding cost of primer/ tack coat.

16.56.1 40 mm/50mm compacted thickness with bitumen of grade 60/ 70 @ 5.5% and lime @3%
(percentage by weight of total mix).
Code Description Unit Quantity Rate Amount
Details of cost for 62.29 cum
Materials
7309 Paving Asphalt 60/70 penetration tonne 8.085 23200.00 187572.00
2211 Carriage of bitumen tonne 8.085 53.21 430.20
296 Stone Aggregate (Single size) : 12.5 mm cum 4.71 1050.00 4945.50
nominal size
297 Stone Aggregate (Single size) : 10 mm cum 47.13 1050.00 49486.50
nominal size
2202 Carriage of aggregate stone aggregate cum 51.84 53.21 2758.41

1159 Stone dust cum 39.74 700.00 27818.00


2267 Carriage of stone dust. cum 39.74 53.21 2114.57
777 slaked lime quintal 44.1 200.00 8820.00
2208 Carriage of lime cum 3.42 53.21 181.98
(B) Labour required for loading platform, paver and for taking level etc.
114 Beldar Day 11 207 2277.00
113 Chowkidar Day 3 207 621.00
130 Mistry Day 1 270 270.00
101 Bhishti Day 3.39 180 610.20
(C) Machinery/ H ire charges:
8 Hire charges of B.G. Plant. Day 1 5,000.00 5000.00
17 Hire charges of tipper Day 3.54 700.00 2478.00
18 Hire charges of loader Day 1 700.00 700.00
3 Hire charges of Road roller Day 3.39 500.00 1695.00
(D) Fuel charges:
1235 Diesel litre 998.17 53.17 53072.70
9999 Carriage of diesel LS 1348.88 1.00 1348.88
5001 Mobil oil litre 1.47 95.00 139.65
TOTAL 352339.58
Add 1% for water charges 3523.40
TOTAL 355862.98
Add for contractor’s profit and
overheads @15% 53379.45
Cost of 62.29 cum 409242.42
Cost of 1 cum 6569.95
Say 6569.95

16.57 Providing and laying Dense B itum inous Concrete on prepared surface with specified graded
stone aggregate for wearing course including loading of aggregate with F.E. loader, and hot mixing
of bitumen with filler and stone aggregate in hot mix plant, transporting the mixed material by tippers to
paver and laying the mixed material with mechanical paver finisher fitted with electronic sensing device
to the required level and grade and rolling with road rollers, as per MORTH specifications, to
achieve the desired density and compaction but excluding cost of primer/ tack coat.

16.57.1 40 mm/50mm compacted thickness with bitumen of grade CRMB - 60 @ 5.5% and lime @3%
(percentage by weight of total mix).
Code Description Unit Quantity Rate Amount
Details of cost for 62.29 cum
Materials
7741 Modified Bitumen Refinery produced 26300.00 212635.50
CR MB - 60 tonne 8.085
2211 Carriage of bitumen tonne 8.085 53.21 430.20
296 Stone Aggregate (Single size) : 12.5 mm cum 4.71 1050.00 4945.50
nominal size
297 Stone Aggregate (Single size) : 10 mm cum 47.13 1050.00 49486.50
nominal size
2202 Carriage of aggregate stone aggregate cum 51.84 53.21 2758.41

1159 Stone dust cum 39.74 700.00 27818.00


2267 Carriage of stone dust. cum 39.74 53.21 2114.57
777 slaked lime quintal 44.1 200.00 8820.00
2208 Carriage of lime cum 3.42 53.21 181.98
(B) Labour required for loading platform, paver and for taking level etc.
114 Beldar Day 11 207 2277.00
113 Chowkidar Day 3 207 621.00
130 Mistry Day 1 270 270.00
101 Bhishti Day 3.39 180 610.20
(C) Machinery/ H ire charges:
8 Hire charges of B.G. Plant. Day 1 5,000.00 5000.00
17 Hire charges of tipper Day 3.54 700.00 2478.00
18 Hire charges of loader Day 1 700.00 700.00
3 Hire charges of Road roller Day 3.39 500.00 1695.00
(D) Fuel charges:
1235 Diesel litre 998.17 53.17 53072.70
9999 Carriage of diesel LS 1348.88 1.00 1348.88
5001 Mobil oil litre 1.47 95.00 139.65
TOTAL 377403.08
Add 1% for water charges 3774.03
TOTAL 381177.11
Add for contractor’s profit and
overheads @15% 57176.57
Cost of 62.29 cum 438353.68
Cost of 1 cum 7037.30
Say 7037.30
16.58 Providing and laying Dense Bituminous Concrete on prepared surface with specified graded
stone aggregate for wearing course including loading of aggregate with F.E. loader, and hot mixing
of bitumen with filler and stone aggregate in hot mix plant, transporting the mixed material by tippers to
paver and laying the mixed material with mechanical paver finisher fitted with electronic sensing device
to the required level and grade “and rolling with road rollers, as per MORTH specifications, to
achieve the desired density and compaction but excluding cost of primer/ tack coat.

16.58.1 40 mm/50mm compacted thickness with bitumen of grade PMB - 40 @ 5.5% and lime @3%
(percentage by weight of total mix).
Code Description Unit Quantity Rate Amount
Details of cost for 62.29 cum
Materials
7382 Modified Bitumen Refinery produced 30000.00 242550.00
PMB - 40 tonne 8.085
2211 Carriage of bitumen tonne 8.085 53.21 430.20
296 Stone Aggregate (Single size) : 12.5 mm cum 4.71 1050.00 4945.50
nominal size
297 Stone Aggregate (Single size) : 10 mm cum 47.13 1050.00 49486.50
nominal size
2202 Carriage of aggregate stone aggregate cum 51.84 53.21 2758.41

1159 Stone dust cum 39.74 700.00 27818.00


2267 Carriage of stone dust. cum 39.74 53.21 2114.57
777 slaked lime quintal 44.1 200.00 8820.00
2208 Carriage of lime cum 3.42 53.21 181.98
(B) Labour required for loading platform, paver and for taking level etc.
114 Beldar Day 11 207 2277.00
113 Chowkidar Day 3 207 621.00
130 Mistry Day 1 270 270.00
101 Bhishti Day 3.39 180 610.20
(C) Machinery/ H ire charges:
8 Hire charges of B.G. Plant. Day 1 5,000.00 5000.00
17 Hire charges of tipper Day 3.54 700.00 2478.00
18 Hire charges of loader Day 1 700.00 700.00
3 Hire charges of Road roller Day 3.39 500.00 1695.00
(D) Fuel charges:
1235 Diesel litre 998.17 53.17 53072.70
9999 Carriage of diesel LS 1348.88 1.00 1348.88
5001 Mobil oil litre 1.47 95.00 139.65
TOTAL 407317.58
Add 1% for water charges 4073.18
TOTAL 411390.76
Add for contractor’s profit and
overheads @15% 61708.61
Cost of 62.29 cum 473099.37
Cost of 1 cum 7595.11
Say 7595.11
16.59 Manufacturing supplying and fixing retro reflective sign boards made up of 2mm thick aluminium
sheet, face to be fully covered with high intensity encapsulated type heat activated retro reflective
sheeting conforming to type - IV of ASTM-D 4956-01 in blue and silver white or other colour
combination including subject matter, message (bi-lingual), symbols and borders etc. as per IRC ;
67:2001, pasted on substrate by an adhesive backing which shall be activated by applying heat and
pressure conforming to class -2 of ASTM-D-4956-01 and fixing the same with suitable sized aluminium
alloy rivets @ 20 cm c/c to back support frame of M.S. angle iron of size 25x25x3 mm alongwith theft
resistant measures, mounted and fixed with 2 Nos. M.S. angles of size 35x35x5 mm to a vertical post
made up of M.S. Tee section ISMT 50x50x6 mm welded with base plate of size 100x100x5 mm at the
bottom end and including making holes in pipes, angles flats, providing & fixing M.S. message plate of
required size steel work to be painted with two or more coats of synthetic enamel paint of required
shade and of approved brand & manufacture over priming coat of zinc chromate yellow primer
(vertical MS-Tee support to be painted in black and white colours). Backside of aluminium sheet to be
painted with two or more coats of epoxy paint over and including appropriate priming coat including all
leads and lifts etc. complete as per drawing . specification and direction of Engineer—in-charge.

16.59.1 Mandatory/ R egulatory sign boards of 900mm dia- metre withpart as lengt h of 3750mm.
Code Discription Unit Quantity Rate Amount
Details cost for one board of 0.636 sqm
2704 Aluminium sheet 2mm thick ilogram 3.92 195.00 764.40
2302 Carnage of sheet tonne 0.00392 47.29 0.19
8690 High intensity retro - reflective sheet sqm 0.98 1400.00 1372.00
Labour
128 Mate Day 0.01 313 3.13
114 Beldar Day 0.25 207 51.75
9999 Cost of material for drilling holes, nut
bolts & rivets, facrication etc. L.S. 65 1.00 65.00
9999 Sundries & hole fast etc, L.S. 78 1.00 78.00
Labour charges for manufacturing of board including.
Angle iron 40x40x4mm Rate as per
item no 10.2 kg 21.67 66.11 1432.69
Painting with synthetic enamel paint
Rate as per item no 13.61.1 sqm 1.07 49.68 53.16
Painting with epoxy paint on back side
of aluminium sheet, Rate as per Item
no.13.52.1 sqm 0.636 85.34 54.27
TOTAL 3874.60
Add 1% for water charges except on A 23.34

TOTAL 3897.94
Add 15 % for contractor’s profit and 353.67
overheads except on A
Cost of 1 board 4251.61
Say 4,251.61
16.59 Manufacturing supplying and fixing retro reflective sign boards made up of 2mm thick aluminium
sheet, face to be fully covered with high intensity encapsulated type heat activated retro reflective
sheeting conforming to type - IV of ASTM-D 4956-01 in blue and silver white or other colour
combination including subject matter, message (bi-lingual), symbols and borders etc. as per IRC ;
67:2001, pasted on substrate by an adhesive backing which shall be activated by applying heat and
pressure conforming to class -2 of ASTM-D-4956-01 and fixing the same with suitable sized aluminium
alloy rivets @ 20 cm c/c to back support frame of M.S. angle iron of size 25x25x3 mm alongwith theft
resistant measures, mounted and fixed with 2 Nos. M.S. angles of size 35x35x5 mm to a vertical post
made up of M.S. Tee section ISMT 50x50x6 mm welded with base plate of size 100x100x5 mm at the
bottom end and including making holes in pipes, angles flats, providing & fixing M.S. message plate of
required size steel work to be painted with two or more coats of synthetic enamel paint of required
shade and of approved brand & manufacture over priming coat of zinc chromate yellow primer
(vertical MS-Tee support to be painted in black and white colours). Backside of aluminium sheet to be
painted with two or more coats of epoxy paint over and including appropriate priming coat including all
leads and lifts etc. complete as per drawing . specification and direction of Engineer—in-charge.

16.59.2 Cautionary /warning sign boards of equilateral triangular shape having each side of 900mm with
support length of 3650mm.
Code Discription Unit Quantity Rate Amount
Details cost for one board of 0.35 sqm
2704 Aluminium sheet 2mm thick ilogram 2.18 195.00 425.10
2302 Carnage of sheet tonne 0.00218 47.29 0.10
8690 High intensity retro - reflective sheet sqm 0.55 1400.00 770.00
Labour
128 Mate Day 0.01 313 3.13
114 Beldar Day 0.25 207 51.75
9999 Cost of material for drilling holes, nut
bolts & rivets, facrication etc. L.S. 65 1.00 65.00
9999 Sundries & hole fast etc, L.S. 65 1.00 65.00
Labour charges for manufacturing of board including.
Angle iron 40x40x4mm Rate as per
item no 10.2 kg 21.05 66.11 1391.70
Painting with synthetic enamel paint
Rate as per item no 13.61.1 sqm 1.036 49.68 51.47
Painting with epoxy paint on back side
of aluminium sheet, Rate as per Item
no.13.52.1 sqm 0.35 85.34 29.87
TOTAL 2853.13
Add 1% for water charges except on A 13.80

TOTAL 2866.93
Add 15 % for contractor’s profit and 209.08
overheads except on A
Cost of 1 board 3076.01
Say 3,076.01
16.60 Manufacturing supplying and fixing retro reflective overhead signage boards made up of 2mm
thick aluminium sheet face to be fully covered with high intensity and encapsulated lens type heat
activated retro reflective sheeting conforming to type -III of ASTM-D-4956-01 as approved by
Engineer-in-charge letters, borders etc. as per IRC : 67-2001 in silver white with blue colour back
ground and with high intensity grade, pasted on substrate by pressure sensitive adhesive backing which
shall be activated by applying pressure conforming to class II of ASTM-D-4956-01 and fixing the same
to the plate of structural frame work by means of suitable sized aluminium alloys, rivets or bolts & nuts
@ 300 mm centre to centre all along the periphery as well as in two vertical rows alongwith theft
resistant measures including the cost of painting with two’or more coats of epoxy paint in grey colour
on the back side of aluminium sheet including appropriate priming coat. The rate includes the cost of
rounding off the corners, lowering down the structural frame work from the gantry, fixing and erecting
the same in position all complete as per drawings, specification and direction of the engineer-in-
charge. (Structural frame work including M.S. plate to be provided separately. Rectangular area of the
sheet only shall be measured for payment).
16.60.1 Overhead informatory road signage.
Code Discription Unit Quantity Rate Amount
Details of cost for boards area 3.00x1.20=3.60 sqm
2704 Aluminium sheet 2mm thick ilogram 21.17 195.00 4128.15
2302 Carnage of sheet tonne 0.02117 47.29 1.00
8690 High intensity retro - reflective sheet sqm 5.04 1400.00 7056.00
588 Chromium plated Brass screws 25 mm 00 Nos. 34 83.00 28.22
Labour charges for drilling holes
9999 Hire charges of drill m achine and sundrie L.S. 52 1.00 52.00
9999 Hoisting board L.S. 390 1.00 390.00
Labour charges for manufacturing of board including.
9999 fixing retro reflective sheet L.S. 564 1.00 564.00
Painting with epoxy paint on back side
of Aluminium sheet, Rate as per Item
no. 13.52.1 sqm 3.6 85.34 307.22
TOTAL 12526.59
Add 1% for water charges except on A 122.19

TOTAL 12648.78
Add 15 % for contractor’s profit and 1851.23
overheads except on A
Cost of 3.6 sqm 14500.02
Cost of 1 sqm 4027.78
Say 4,027.78

16.61 Providing Retro-reflective regulatory sign board of size 900mm dia meter made out of 2m m
thick aluminium sheet, face to be f ully covered with high intensity encapsulated lens type retro
-reflective sheeting as approved by Engineer-in-charge. Letter , symbols, borders etc. will be as per IRC
- 67 with required colour scheme on the boards and with the high intensity grade A. The aluminium
sheet to be riveted to M.S. frame of angle iron of stze 40x40x4mm The boards will be fixed to 1 No.
50x50mm square post made of M.S. angle 50x50x4m, 4m long welded to the frame with adequate anti-
theft arrangement .Sheet work to be painted with two or more coats of synthetic enamel paint over an
under coat (primer) and back side of aluminium sheet to be painted with two or more coats of epoxy
paint including appropriate priming coat complete in all respects as per direction of Engineer-in-charge.
Code Discription Unit Quantity Rate Amount
Details cost for one board of 0.635 sqm
2704 Aluminium sheet 2mm thick ilogram 3.98 195.00 776.10
8690 High intensity retro - reflective sheet sqm 0.98 1400.00 1372.00
Labour
128 Mate Day 0.01 313 3.13
114 Beldar Day 0.25 207 51.75
9999 Cost of material for drilling holes, nut
bolts & rivets, facrication etc. L.S. 70.23 1.00 70.23
9999 Sundries & hole fast etc, L.S. 31.2 1.00 31.20
Labour charges for manufacturing of board including.
Angle iron 40x40x4mm Rate as per
item no 10.2 kg 29.76 66.11 1967.56
Painting with synthetic enamel paint
Rate as per item no 13.61.1 sqm 1.09 49.68 54.16
Painting with epoxy paint on back side
of aluminium sheet, Rate as per Item
no.13.52.1 sqm 0.635 85.34 54.19
TOTAL 4380.31
Add 1% for water charges except on A 23.04

TOTAL 4403.36
Add 15 % for contractor’s profit and 349.12
overheads except on A
Cost of 1 board 4752.48
Say 4,752.48

16.62 Providing and applying 2.5mm thick road marking strips (retro-reflective) of specified shade/
colour using hot thermoplastic material by fully/ semi automatic thermoplastic paint applicator machine
fitted with profile shoe, glass beads dispenser, propane tank heater and profile shoe heater, driven by
experienced operator on road surface including cost of material, labour ,T&P, cleaning the road surface
of all dirt, seals, oil, grease and foreign material etc. complete as per direction of Engineer-in-charge and
accordance with applicable specifications.
Code Discription Unit Quantity Rate Amount
Details of cost for 100.00 sqm (Area covered on one day):-
Materials
8687 Thermoplastic paint kg 525 67.22 35290.50
8688 Glass beads kg 25 68.00 1700.00
MACHINERY
33 Hiring charges of paint applicator machi per day 1 500 500.00
5 Hire charges of trucks for local shifting per day 1 1500 1500.00
1241
LPG cylinder of heating (Com mercial
cylinder of 19.00 kg capacity) kg 71.06 35.00 2487.10
Labour for spreading, ramming and consolidation.
157 Machine operator. Day 1 223 223.00
139 Skilled labour. Day 4 180 720.00
114 Beldar for erecting barricades, traffic Day 4.2 207 869.40
diversions, stretching ropes etc.

9999 Labour for cleaning for road surface. L.S. 364 1.00 364.00
TOTAL 43654.00
Add 1% for water charges 436.54
TOTAL 44090.54
Add 15 % for contractor’s profit and overheads 6613.58
Cost of 100 sqm 50704.12
Cost of 1 sqm 507.04
Say 507.04

16.63 Providing and laying and making kerb channel 30cm wide and 50mm thick of cement concrete
1:3:6 (1 cement:3 coarse sand:6 graded stone aggregate 20mm nominal size) over 75mm bed of dry
brick ballast 40 mm nominal size well rammed and consolidated and grouted with fine sand including
finishing the top smooth etc. complete and as per direction of Engineer-in-charge.
Code Discription Unit Quantity Rate Amount
Details of cost for 10.00 sqm.
Meterials
287 Brick Aggregate 40 mm nominal size cum 1 360.00 360.00
2260 Carriage of Brick Aggregate cum 1 57.83 57.83
6501 Jamuna sand cum 0.08 175.00 14.00
2335 Carriage of Jamuna sand cum 0.08 53.21 4.26
Labour for spreading, ramming and consolidation.
115 Coolie Day 0.26 207 53.82
114 Beldar Day 0.35 207 72.45
101 Bhishti Day 0.18 180 32.40
A Cement concrete-1:3:6 (Rate as per item cum 0.5 3,273.34 1636.67
no. 4.1.6)
TOTAL 2231.43
Add 1% for water charges except on A 5.95

TOTAL 2237.38
Add 15 % for contractor’s profit and 90.11
overheads except on A
Cost of 10 sqm 2327.48
Cost of 1 sqm 232.75
Say 232.75

16.64 Providing and laying 75mm thick compacted bed of dry brick aggregate of 40mm thick nominal
size including spreading, well ramming, consolidating and with jamuna sand including finishing smooth
etc. complete as per direction of grouting Engineer-in-charge.
Code Discription Unit Quantity Rate Amount
Details of cost for 10.00 sqm.
Meterials
287 Brick Aggregate 40 mm nominal size cum 1 360.00 360.00
2260 Carriage of Brick Aggregate cum 1 57.83 57.83
6501 Jamuna sand cum 0.08 175.00 14.00
2335 Carriage of Jamuna sand cum 0.08 53.21 4.26
Labour for spreading, ramming and consolidation.
115 Coolie Day 0.26 207 53.82
114 Beldar Day 0.35 207 72.45
101 Bhishti Day 0.18 180 32.40
TOTAL 594.76
Add 1% for water charges 5.95
TOTAL 600.70
Add 15 % for contractor’s profit and overheads 90.11
Cost of 10 sqm 690.81
Cost of 1 sqm 69.08
Say 69.08

16.65 Providing and fixing post delineators (made of ABS body fitted with 2 nose 100mm dia )
reflective and reflectors are mounted on MS pipe of 65mm dia dully powder coated anti-rust steel to be
installed as per direction of Engineer-in-charge.
Code Discription Unit Quantity Rate Amount
Details of cost for 1 no.
Materials.
8685 Delinator each 1 560.00 560.00
9999 Fixing charges L.S. 78 1.00 78.00
9999 Fixing material L.S. 39 1.00 39.00
TOTAL 677.00
Add 1% for water charges 6.77
TOTAL 683.77
Add for contractor’s profit and
overheads @15% 102.57
Cost of each 786.34
Say 786.34

16.66 Excavating holes upto 0.10 cum including getting out the excavated soil, then returning the soil as
deported in layers not exceeding 20cm in depth including consolidating and deposited layer by ramming
watering etc. Disposing of surplus excavated soil as directed with in a lead of 50m and lift upto 1.5 m.
16.66.1 All kind of soil.
Code Discription Unit Quantity Rate Amount
Details of cost for 30 holes-
A Earth work Rate vide item no. 2.8.1 cum 3 129.74 389.22
9999 Sundries L.S. 13.52 1.00 13.52
TOTAL 402.74
Add 1% for water charges except A 0.14

TOTAL 402.88
Add for contractor’s profit and 2.05
overheads @15% except on A
Cost of 30 holes 404.92
Cost of 1 hole 13.50
Say 13.50

16.67 Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of
size 450x450x50mm (HPL or equivalent ) including reinforcement with 6mm dia M.S. bars 4 nose on
each side including setting in position in footpath to the required level and line over a bed of 20mm
average thick cement mortar 1:3 (1 cement : 3 coarse sand ) having thickness not more than 5mm
except on curve including filling of joints with same cement mortar and making grooves etc. complete
as per direction of Engineer-in-charge.
Code Discription Unit Quantity Rate Amount
Details of cost for 10.00 sqm
Materials.
8694 Precast pavement slab 450 x 450 x
50mm (M - 30). each 48 40.00 1920.00
9999 carriage of slab L.S. 52 1.00 52.00
9999 Sundries L.S. 10.79 1.00 10.79
20mm (bed and joints) CM. 1:5 (1
cement: 5 coarse sand (Rate as per item
no. 3.10 of SH. Mortar) cum 0.25 2212.87 553.22
Labour for fixing of Kerb stone
155 Mason Day 1.1 180 198.00
100 Bandhani Day 1.1 180 198.00
114 Beldar Day 0.55 207 113.85
101 Bhishti Day 0.27 180 48.60
TOTAL 3094.46
Add 1% for water charges 30.94
TOTAL 3125.40
Add for contractor’s profit and
overheads @15% 468.81
Cost of 10 sqm 3594.21
Cost of 1 sqm 359.42
Say 359.42

16.68 Providing and laying 60mm thick factory made cement concrete interlocking paver block of M
-30 grade made by block making machine with strong vibratory compaction and of approved size
and design/ shape laid in required colour and pattern over and including 50mm thick compacted bed of
course sand, filling the joints with coarse sand etc. all complete as per the direction of Engineer-in-
charge.
Code Discription Unit Quantity Rate Amount
Details of cost for 10.00 sqm
Materials.
8689 Interlocking C.C. paver block ( 60 mm
thick), M.30 Bedding Layer 50mm
thick sqm 10 225.00 2250.00
983 Fine sand cum 0.15 300.00 45.00
2261 Carriage of fine sand cum 0.15 53.21 7.98
982 Coarse sand cum 0.5 300.00 150.00
2203 Carriage of Coarse sand cum 0.5 53.21 26.61
Labour for fixing of Kerb stone
115 Coolie Day 0.5 207 103.50
114 Beldar Day 1 207 207.00
123 Mason ist class Day 0.5 270 135.00
124 Mason 2nd class Day 0.5 223 111.50
TOTAL 3036.59
Add 1% for water charges 30.37
TOTAL 3066.95
Add for contractor’s profit and
overheads @15% 460.04
Cost of 10 sqm 3527.00
Cost of 1 sqm 352.70
Say 352.70

16.69 Providing and laying at or near ground level factory made kerb stone of M-25 grade cement in
position to the required line, level and curvature jointed with cement mortar 1:3(1 cement: 3 coarse sand
) including making joints with or without grooves (thickness of joints except at sharp curve shall not
to more than 5mm) including making drainage opening wherever required complete etc. as per direction
of Engineer-in-charge (length of finished kerb edging shall be measured for payment). (Precast C.C.
kerb stone shall be approved by Engineer-in-charge).
Code Discription Unit Quantity Rate Amount
Details of cost for 100.00 metre i.e. 100x0.375x0.20=7.50 cum.
8686 Precast C.C. Kerb stone M - 25 cum 7.41 3500.00 25935.00
CM.1 :3 (1 cement: 3 coarse sand) as
per item no. 3.8 of SH mortar cum 0.073 3262.33 238.15
Labour for fixing of Kerb stone
115 Coolie Day 1.65 207 341.55
114 Beldar Day 2.5 207 517.50
123 Mason ist class Day 2.5 270 675.00
124 Mason 2nd class Day 2.5 223 557.50
TOTAL 28264.70
Add 1% for water charges 282.65
TOTAL 28547.35
Add for contractor’s profit and
overheads @15% 4282.10
Cost of 7.5 cum 32829.45
Cost of 1 cum 4377.26
Say 4377.26

16.70 Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50mm
including strengthening with 2mm dia wire or nuts, bolts and washers as required complete as
per the direction of Engineer-in-charge.
16.70.1 Made of G.I. wire of dia 4mm.
Code Discription Unit Quantity Rate Amount
Details of cost for 10 sqm.
Material.
8695
Chain link fabric fancing mesh of size
50x50mm made of G.I. wire of dia.
4mm. sqm 10.5 225.00 2362.50
9999 Carriage L.S. 156 1.00 156.00
Labour
103 Blacksmith 2nd class Day 2.14 223 477.22
114 Beldar Day 1.62 207 335.34
9999 Sundries including G.I. wire, nuts and
bolts and warshers. L.S. 174.75 1.00 174.75
TOTAL 3505.81
Add 1% for water charges 35.06
TOTAL 3540.87
Add for contractor’s profit and
overheads @15% 531.13
Cost of 10 sqm 4072.00
Cost of 1 sqm 407.20
Say 407.20

16.70 Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50mm
including strengthening with 2mm dia wire or nuts, bolts and washers as required complete as
per the direction of Engineer-in-charge.
16.70.2 Made of G.I. wire of dia. 4mm, PVC coated to achieve outer dia. not less than 5mm in required
colour andDiscription
Code shade. Unit Quantity Rate Amount
Details of cost for 10 sqm.
Material.
8696 Chain link fabric fencing mesh of size
50x50mm made of G.I. wire of dia 4m
m, PVC coated to outer dia. 5mm.

sqm 10.5 250.00 2625.00


9999 Carriage L.S. 156 1.00 156.00
Labour
103 Blacksmith 2nd class Day 2.14 223 477.22
114 Beldar Day 1.62 207 335.34
9999 Sundries including G.I. wire, nuts and
bolts and warshers. L.S. 174.75 1.00 174.75
TOTAL 3768.31
Add 1% for water charges 37.68
TOTAL 3805.99
Add for contractor’s profit and
overheads @15% 570.90
Cost of 10 sqm 4376.89
Cost of 1 sqm 437.69
Say 437.69

16.71 Providing and fixing G.I. chain link fabric fencing of required width in mesh size 25x25 mm
made of G.I. wire of dia. 3mm including strengthening with 2mm dia. wire or nuts, bolts and washers
as required complete as per the direction of Engineer-in-charge.
Code Discription Unit Quantity Rate Amount
Details of cost for 10 sqm.
Material.
8697 Chain link fabric fencing mesh of size
25x25mm made of G.I. wire of dia 3mm
sqm 10.5 300.00 3150.00
9999 Carriage L.S. 156 1.00 156.00
Labour
103 Blacksmith 2nd class Day 2.14 223 477.22
114 Beldar Day 1.62 207 335.34
9999 Sundries including G.I. wire, nuts and
bolts and warshers. L.S. 174.75 1.00 174.75
TOTAL 4293.31
Add 1% for water charges 42.93
TOTAL 4336.24
Add for contractor’s profit and
overheads @15% 650.44
Cost of 10 sqm 4986.68
Cost of 1 sqm 498.67
Say 498.67

16.72 Supplying and stacking of hard stone (for stone pitching) 22.5 cm thick at site.
Code Discription Unit Quantity Rate Amount
Details of cost for 2.25 cum
MATERIALS
1158 22.5 cm thick stone (Hard) cum 2.25 332.00 747.00
2215 Carriage by mechanical transport i/c cum 2.25 62.6 140.85
loading unloading and stacking
TOTAL 887.85
Add 1% for water charges 8.88
TOTAL 896.73
Add for contractor’s profit and
overheads @15% 134.51
Cost of 2.25 cum 1031.24
Cost of 1 cum 458.33
Say 458.33

16.73 Dry stone pitching 22.5cm thick laid in courses and required profile with hammer dressed stones
having no side less than 15 cm, with minimum depth of 20cm including preparing the bedding surface
etc. all complete. (Payment for Stone to be made separately)
Code Discription Unit Quantity Rate Amount
Detail of cost for 10.00 sqm
LABOUR
114 Beldar Day 2.15 207 445.05
115 Coolie Day 1.61 207 333.27
123 Mason ist class Day 1.08 270 291.60
124 Mason 2nd class Day 1.08 223 240.84
9999 Sundries L.S. 6.76 1.00 6.76
TOTAL 1317.52
Add 1% for water charges 13.18
TOTAL 1330.70
Add for contractor’s profit and
overheads @15% 199.60
Cost of 10 sqm 1530.30
Cost of 1 sqm 153.03
Say 153.03

16.74 75 mm thick back filling for pitching including supplying of required materials and consolidation
etc. complete with:
16.74.1 Moorum
Code Description Unit Quantity Rate Amount
Detail of cost for 100.00 sqm
MATERIALS
810 Moorum cum 7.5 333.00 2497.50
2265 Carriage by mechanical transport i/c cum 7.5 53.21 399.08
loading unloading and stacking
LABOUR
114 Beldar Day 1.64 207 339.48
101 Bhishti Day 0.13 180 23.40
TOTAL 3259.46
Add 1% for water charges 32.59
TOTAL 3292.05
Add 15 % for contractor’s profit and overheads 493.81
Cost of 100 sqm 3785.86
Cost of 1 sqm 37.86
Say 37.86

16.74 75 mm thick back filling for pitching including supplying of required materials and consolidation
etc. complete with:
16.74.2 Stone aggregate 20 mm nominal size.
Code Description Unit Quantity Rate Amount
Detail of cost for 100.00 sqm
MATERIALS
295 Stone aggregate 20mm cum 7.5 1100.00 8250.00
2202 Carriage of aggregate 20mm and 10 cum 7.5 53.21 399.08
mm
LABOUR
114 Beldar Day 2.05 207 424.35
101 Bhishti Day 0.13 180 23.40
TOTAL 9096.83
Add 1% for water charges 90.97
TOTAL 9187.79
Add 15 % for contractor’s profit and overheads 1378.17
Cost of 100 sqm 10565.96
Cost of 1 sqm 105.66
Say 105.66

16.74 75 mm thick back filling for pitching including supplying of required materials and consolidation
etc. complete with:
16.74.3 Stone aggregate 40 mm nominal size.
Code Description Unit Quantity Rate Amount
Detail of cost for 100.00 sqm
MATERIALS
293 Stone aggregate 40mm cum 7.5 1000.00 7500.00
2206 Carriage of aggregate 40mm cum 7.5 57.83 433.73
LABOUR
114 Beldar Day 2.05 207 424.35
101 Bhishti Day 0.13 180 23.40
TOTAL 8381.48
Add 1% for water charges 83.81
TOTAL 8465.29
Add 15 % for contractor’s profit and overheads 1269.79
Cost of 100 sqm 9735.08
Cost of 1 sqm 97.35
Say 97.35

16.75 Providing and laying C.C. pavement of mix M25 with ready mixed concrete from batching plant.
The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering
process and finally finished by floating, brooming with wire brush etc. complete as per specifications
and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately ).
Code Description Unit Quantity Rate Amount
Details of cost for 1.00 cum
A Ready mix concrete M 25 = 1.00 cum.
i/c placing of concrete, vibrating,
leveling etc. (Rate as per item No. 5.37
of SH. R.C.C.)
cum 1 4,998.32 4998.32
9999 Operational charges for vacuum L.S. 57.2 1.00 57.20
dewatering system i/c screed
vibration , placing of filter mat, top
mat, vacuum process, floating ,
troweling, Brooming etc.

9999 T& P charges i/c consumable power L.S. 41.6 1.00 41.60
charges, loading , unloading and hire
charges of equipments

TOTAL 5097.12
Add 1% for water charges except on A 0.99

TOTAL 5098.11
Add 15 % for contractor’s profit and 14.97
overheads except on A
Cost of 1 cum 5113.08
Say 5,113.08

16.76 Deduct for using of M 20 grade concrete instead of M-25 grade concrete in C.C. pavement.
Code Description Unit Quantity Rate Amount
Details of cost for 1.00 cum
Cement for M-25 mix = tonne 0.41
Cement for M- 20 mix = tonne 0.383
367 D ifference tonne 0.027 5200.00 140.40
2209 Carriage of Cement tonne 0.027 47.29 1.28
Plasticizer for M-25 mix ilogram 2.05
Plasticizer for M- 20 mix ilogram 1.915
7318 Difference ilogram 0.135 30.00 4.05
TOTAL 145.73
Add 1% for water charges 1.46
TOTAL 147.18
Add 15 % for contractor’s profit and 22.08
overheads
Cost of 1 cum 169.26
Say 169.26

16.77 Scarifiying the existing bituminous road surface to depth of 50mm and disposal of scarified
material withyin all lifts and lead upto 1000 metre (by mechanincal means).
Code Description Unit Quantity Rate Amount
Details of cost for 100.00 sqm
LABOUR
128 Mate Day 0.01 313 3.13
114 Beldar Day 0.25 207 51.75
MACHINERY
38 Tractor with ripper attachment per day 0.01 600 6.00
14 Front end loader per day 0.025 5,000.00 125.00
17 Hire and runining charges of tipper per day 0.02875 700.00 20.13
TOTAL 206.01
Add 1% for water charges 2.06
TOTAL 208.07
Add 15 % for contractor’s profit and 31.21
overheads
Cost of 100 sqm 239.27
Cost of 1 sqm 2.39
Say 2.39
17.1 Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100mm sand cast
Iron P or S trap, 10 litre low level white P.V.C. flushing cistern with manually controlled device (handle
lever) conforming to IS : 7231, with all fittings and fixtures complete including cutting and making
good the walls and floors wherever required :
17.1.1 White Vitreous china Orissa pattern W.C. pan of size 580x440mm with integral type foot rests.
Code Description Unit Quantity Rate Amount
Details of cost for 1 pan
Materials:
1954 White Vitreous china Orrisa pattern W.C. pan
each 1 550.00 550.00
7358 10 litre low level P.V.C. flushing cistern with
fitting accessories and flush pipe each 1 570.00 570.00
1896 100 mm Sand C.I. ‘P’ or’S’ trap with vent
horn each 1 260.00 260.00
Labour:
116 Fitter (grade 1) Day 1.25 270.00 337.50
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 1 207.00 207.00
9,999 Carriage of material L.S. 26.91 1.00 26.91
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 2113.32
Add 1% for water charges 21.13
TOTAL 2134.45
Add for contractor’s profit and overheads
@15% 320.17
Cost of 1 pan 2454.62
Say

17.1 Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100mm sand cast
Iron P or S trap, 10 litre low level white P.V.C. flushing cistern with manually controlled device (handle
lever) conforming to IS : 7231, with all fittings and fixtures complete including cutting and making
good the walls and floors wherever required :
17.1.2 Stainless Steel AISI-304(18/8) Orissa pattern W.C. pan of size 585x480 mm with flush pipe and
integrated type foot rests.
Code Description Unit Quantity Rate Amount
Details of cost for 1 pan
Materials:
7805 Salem Stainless steel AISI - 304 (18/8)
Orrisa pattern W.C . pan 724mm X 578mm
each 1 3350.00 3350.00
7358 10 litre low level P.V.C. flushing cistern with
fitting accessories and flush pipe each 1 570.00 570.00
1896 100 mm Sand C.I. ‘P’ or’S’ trap with vent
horn each 1 260.00 260.00
Labour:
116 Fitter (grade 1) Day 1.25 270.00 337.50
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 1 207.00 207.00
9,999 Carriage of material L.S. 26.91 1.00 26.91
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 4913.32
Add 1% for water charges 49.13
TOTAL 4962.45
Add for contractor’s profit and overheads
@15% 744.37
Cost of 1 pan 5706.82
Say

17.2 Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan)
with seat and lid, 10 litre low level white P.V.C. flushing cistern with manually controlled device
(handle lever), conforming to IS : 7231, with all fittings and fixtures complete including cutting and
making good the walls and floors wherever required :
17.2.1 W.C pan with ISI marked white solid plastic seat and lid
Code Description Unit Quantity Rate Amount
Details of cost for 1 pan
Materials:
1875 White solid plastic seat and lid with C.P.
brass hinges and rubber buffers complete
each 1 275.00 275.00
1955 White vitreous china pedestal type W.C. pan
each 1 600.00 600.00
7358 10 litre low level P.V.C. flushing cistern with
fitting accessories and flush pipe each 1 570.00 570.00
Labour:
116 Fitter (grade 1) Day 1.25 270.00 337.50
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 1 207.00 207.00
9,999 Carriage of material L.S. 26.91 1.00 26.91
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 2178.32
Add 1% for water charges 21.78
TOTAL 2200.10
Add for contractor’s profit and overheads
@15% 330.02
Cost of 1 pan 2530.12
Say

17.2 Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan)
with seat and lid, 10 litre low level white P.V.C. flushing cistern with manually controlled device
(handle lever), conforming to IS : 7231, with all fittings and fixtures complete including cutting and
making good the walls and floors wherever required :
17.2.2 W.C. pan with ISI marked black solid plastic seat and lid
Code Description Unit Quantity Rate Amount
Details of cost for 1 pan
Materials:
1876 Black plastic seat (solid) with lid C.P.brass
hinges and rubber buffers each 1 250.00 250.00
1955 White vitreous china pedestal type W.C. pan
each 1 600.00 600.00
7358 10 litre low level P.V.C. flushing cistern with
fitting accessories and flush pipe each 1 570.00 570.00
Labour:
116 Fitter (grade 1) Day 1.25 270.00 337.50
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 1 207.00 207.00
9,999 Carriage of material L.S. 26.91 1.00 26.91
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 2153.32
Add 1% for water charges 21.53
TOTAL 2174.85
Add for contractor’s profit and overheads
@15% 326.23
Cost of 1 pan 2501.08
Say

17.3 Providing and fixing white vitreous china pedestal type water closet (European type) with seat
and lid, 10 litre low level white vitreous china flushing cistern & C.P. flush bend with fittings & C.I.
brackets, 40mm flush bend, overflow arrangement with specials of standard make and mosquito proof
coupling of approved municipal design complete including painting of fittings and brackets, cutting
and making good the walls and floors wherever required :
17.3.1 W.C. pan with ISI marked white solid plastic seat and lid.
Code Description Unit Quantity Rate Amount
Details of cost for 1 pan
Materials:
1875 White solid plastic seat and lid with C.P.
brass hinges and rubber buffers complete
each 1 275.00 275.00
1955 White vitreous china pedestal type W.C. pan
each 1 600.00 600.00
7006 Vitreous china 10 litres low level cistern
with fittings each 1 1390.00 1390.00
1350 Mosquito proof coupling of approved
design each 1 23.00 23.00
Labour:
116 Fitter (grade 1) Day 1 270.00 270.00
123 Mason ist class Day 1 270.00 270.00
114 Beldar Day 1 207.00 207.00
9,999 Overflow arrangement and specials for L.S. 62.79
oveflow pipe 1.00 62.79
9,999 Plugs,screws etc. L.S. 13.52 1.00 13.52
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 26.91 1.00 26.91
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 3181.25
Add 1% for water charges 31.81
TOTAL 3213.06
Add for contractor’s profit and overheads
@15% 481.96
Cost of 1 pan 3695.02
Say

17.3 Providing and fixing white vitreous china pedestal type water closet (European type) with seat
and lid, 10 litre low level white vitreous china flushing cistern & C.P. flush bend with fittings & C.I.
brackets, 40mm flush bend, overflow arrangement with specials of standard make and mosquito proof
coupling of approved municipal design complete including painting of fittings and brackets, cutting
and making good the walls and floors wherever required :
17.3.2 W.C. pan with ISI marked black solid plastic seat and lid.
Code Description Unit Quantity Rate Amount
Details of cost for 1 pan
Materials:
1876 Black plastic seat (solid) with lid C.P.brass
hinges and rubber buffers each 1 250.00 250.00
1955 White vitreous china pedestal type W.C. pan
each 1 600.00 600.00
7006 Vitreous china 10 litres low level cistern
with fittings each 1 1390.00 1390.00
1350 Mosquito proof coupling of approved
design each 1 23.00 23.00
Labour:
116 Fitter (grade 1) Day 1 270.00 270.00
123 Mason ist class Day 1 270.00 270.00
114 Beldar Day 1 207.00 207.00
9,999 Overflow arrangement and specials for L.S. 62.79
oveflow pipe 1.00 62.79
9,999 Plugs,screws etc. L.S. 13.52 1.00 13.52
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 26.91 1.00 26.91
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 3156.25
Add 1% for water charges 31.56
TOTAL 3187.81
Add for contractor’s profit and overheads
@15% 478.17
Cost of 1 pan 3665.98
Say

17.4 Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin
of 430x260x350mm and 340x410x265mm sizes respectively with automatic flushing cistern with
standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including
painting of fittings and brackets, cutting and making good the walls and floors wherever required :
17.4.1 One urinal basin with 5 litre white P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1913 Vitreous china lipped front urinal each 1 380.00 380.00
7359 5 litre PVC automatic flushing c istern with
fitting each 1 430.00 430.00
7375 G.I. flush pipe and C.P. brass spreader
including C.P. connecting pipe Single lipped
urinal
each 1 352.00 352.00
Labour:
116 Fitter (grade 1) Day 0.88 270.00 237.60
123 Mason ist class Day 0.88 270.00 237.60
114 Beldar Day 1.5 207.00 310.50
9,999 Painting of fittings etc. L.S. 39 1.00 39.00
9,999 Plugs,screws etc. L.S. 13.52 1.00 13.52
9,999 Red lead, white lead and gasket L.S. 13.52 1.00 13.52
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 2054.17
Add 1% for water charges 20.54
TOTAL 2074.71
Add for contractor’s profit and overheads
@15% 311.21
Cost of 1 pan 2385.92
Say

17.4 Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin
of 430x260x350mm and 340x410x265mm sizes respectively with automatic flushing cistern with
standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including
painting of fittings and brackets, cutting and making good the walls and floors wherever required :

17.4.2 Range of two urinal basins with 5 litre white P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1913 Vitreous china lipped front urinal each 2 380.00 760.00
7359 5 litre PVC automatic flushing c istern with
fitting each 1 430.00 430.00
7376 G.I. flush pipe and C.P. brass spreader
including C.P. connecting pipe Range of two
lipped urinals
each 1 880.00 880.00
Labour:
116 Fitter (grade 1) Day 1.5 270.00 405.00
123 Mason ist class Day 1.5 270.00 405.00
114 Beldar Day 2 207.00 414.00
9,999 Painting of fittings etc. L.S. 39 1.00 39.00
9,999 Plugs,screws etc. L.S. 20.28 1.00 20.28
9,999 Red lead, white lead and gasket L.S. 20.28 1.00 20.28
9,999 Carriage of material L.S. 20.28 1.00 20.28
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 3420.75
Add 1% for water charges 34.21
TOTAL 3454.96
Add for contractor’s profit and overheads
@15% 518.24
Cost of 1 pan 3973.20
Say

17.4 Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin
of 430x260x350mm and 340x410x265mm sizes respectively with automatic flushing cistern with
standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including
painting of fittings and brackets, cutting and making good the walls and floors wherever required :
17.4.3 Range of three urinal basins with 10 litre white P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1913 Vitreous china lipped front urinal each 3 380.00 1140.00
7361 P.V.C. automatic flushing cistern 10 lts each 1 465.00 465.00
capacity
7377 G.I. flush pipe and C.P. brass spreader
including C.P. connecting pipe Range of three
lipped urinals
each 1 1070.00 1070.00
Labour:
116 Fitter (grade 1) Day 2 270.00 540.00
123 Mason ist class Day 2 270.00 540.00
114 Beldar Day 3 207.00 621.00
9,999 Painting of fittings etc. L.S. 39 1.00 39.00
9,999 Plugs,screws etc. L.S. 33.67 1.00 33.67
9,999 Red lead, white lead and gasket L.S. 33.67 1.00 33.67
9,999 Carriage of material L.S. 33.67 1.00 33.67
9,999 Cement, sand and grit etc. L.S. 40.3 1.00 40.30
TOTAL 4556.31
Add 1% for water charges 45.56
TOTAL 4601.87
Add for contractor’s profit and overheads
@15% 690.28
Cost of 1 pan 5292.15
Say

17.4 Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin
of 430x260x350mm and 340x410x265mm sizes respectively with automatic flushing cistern with
standard flush pipe and C.P. brass spreaders with brass unions and G.I clamps complete, including
painting of fittings and brackets, cutting and making good the walls and floors wherever required :
17.4.4 Range of four urinal basins with 10 litre white P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1913 Vitreous china lipped front urinal each 4 380.00 1520.00
7361 P.V.C. automatic flushing cistern 10 lts each 1 465.00 465.00
capacity
G.I. flush pipe and C.P. brass spreader
7378
including C.P. connecting pipe Range of four
lipped urinals
each 1 1530.00 1530.00
Labour:
116 Fitter (grade 1) Day 3 270.00 810.00
123 Mason ist class Day 3 270.00 810.00
114 Beldar Day 4 207.00 828.00
9,999 Painting of fittings etc. L.S. 39 1.00 39.00
9,999 Plugs,screws etc. L.S. 53.82 1.00 53.82
9,999 Red lead, white lead and gasket L.S. 53.82 1.00 53.82
9,999 Carriage of material L.S. 53.82 1.00 53.82
9,999 Cement, sand and grit etc. L.S. 53.82 1.00 53.82
TOTAL 6217.28
Add 1% for water charges 62.17
TOTAL 6279.45
Add for contractor’s profit and overheads
@15% 941.92
Cost of 1 pan 7221.37
Say

17.5 Providing and fixing white vitreous ch ina flat back half stall urinal of size
580x380x350mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass
flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I.
trap with outlet grating and other couplings in C.P. brass including painting of fittings and cutting and
making good the walls and floors wherever required :
17.5.1 Single half stall urinal with 5 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7379 White vitreous china clay half stall urinal
flat back 580x380x350 mm or angle back
450x375x350 mm with waste fittings as per
IS : 2556
each 1 1224.00 1224.00
7359 5 litre PVC automatic flushing c istern with
fitting each 1 430.00 430.00
1532 Flush pipe with union spreaders and clamps
all in C.P. brass for single stall each 1 204.00 204.00
1891 C.I. trap for standard urinal with vent arm
with operating and other coulings in CP
brass : 50mm dia
each 1 125.00 125.00
Labour:
116 Fitter (grade 1) Day 1.75 270.00 472.50
123 Mason ist class Day 2 270.00 540.00
114 Beldar Day 4 207.00 828.00
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 40.43 1.00 40.43
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 3934.39
Add 1% for water charges 39.34
TOTAL 3973.73
Add for contractor’s profit and overheads
@15% 596.06
Cost of 1 pan 4569.79
Say

17.5 Providin g and f ixing white vitreous ch ina flat back half stall urinal of size
580x380x350mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass
flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I.
trap with outlet grating and other couplings in C.P. brass including painting of fittings and cutting and
making good the walls and floors wherever required :
17.5.2 Range of two half stall urinals with 5 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7379 White vitreous china clay half stall urinal
flat back 580x380x350 mm or angle back
450x375x350 mm with waste fittings as per
IS : 2556
each 2 1224.00 2448.00
7359 5 litre PVC automatic flushing c istern with
fitting each 1 430.00 430.00
1533 Flush pipe with union spreaders and clamps
all in C.P. brass for double stall each 1 333.00 333.00
1891 C.I. trap for standard urinal with vent arm
with operating and other coulings in CP
brass : 50mm dia
each 1 125.00 125.00
Labour:
116 Fitter (grade 1) Day 2.5 270.00 675.00
123 Mason ist class Day 3 270.00 810.00
114 Beldar Day 6 207.00 1242.00
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 53.82 1.00 53.82
9,999 Cement, sand and grit etc. L.S. 53.82 1.00 53.82
TOTAL 6214.19
Add 1% for water charges 62.14
TOTAL 6276.33
Add for contractor’s profit and overheads
@15% 941.45
Cost of 1 pan 7217.78
Say

17.5 Providin g and f ixing white vitreous ch ina flat back half stall urinal of size
580x380x350mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass
flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I.
trap with outlet grating and other couplings in C.P. brass including painting of fittings and cutting and
making good the walls and floors wherever required :
17.5.3 Range of three half stall urinals with 10 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7379 White vitreous china clay half stall urinal
flat back 580x380x350 mm or angle back
450x375x350 mm with waste fittings as per
IS : 2556
each 3 1224.00 3672.00
7361 P.V.C. automatic flushing cistern 10 lts each 1 465.00 465.00
capacity
Flush pipe with union spreaders and clamps
1534
all in C.P. brass for range of three stall
each 1 415.00 415.00
1893 C.I. trap for standard urinal with vent arm
with operating and other coulings in CP
brass : 80mm dia
each 1 158.00 158.00
Labour:
116 Fitter (grade 1) Day 3 270.00 810.00
123 Mason ist class Day 3.5 270.00 945.00
114 Beldar Day 7 207.00 1449.00
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 67.21 1.00 67.21
9,999 Cement, sand and grit etc. L.S. 80.73 1.00 80.73
TOTAL 8105.49
Add 1% for water charges 81.05
TOTAL 8186.54
Add for contractor’s profit and overheads
@15% 1227.98
Cost of 1 pan 9414.53
Say

17.5 Providin g and f ixing white vitreous ch ina flat back half stall urinal of size
580x380x350mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass
flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I.
trap with outlet grating and other couplings in C.P. brass including painting of fittings and cutting and
making good the walls and floors wherever required :
17.5.4 Range of four half stall urinals with 10 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7379 White vitreous china clay half stall urinal
flat back 580x380x350 mm or angle back
450x375x350 mm with waste fittings as per
IS : 2556
each 4 1224.00 4896.00
7361 P.V.C. automatic flushing cistern 10 lts
capacity each 1 465.00 465.00
1535 Flush pipe with union spreaders and clamps
all in C.P. brass for range of four stall
each 1 465.00 465.00
1893 C.I. trap for standard urinal with vent arm
with operating and other coulings in CP
brass : 80mm dia
each 1 158.00 158.00
Labour:
116 Fitter (grade 1) Day 3.5 270.00 945.00
123 Mason ist class Day 4 270.00 1080.00
114 Beldar Day 8 207.00 1656.00
9,999 Painting of fittings etc. L.S. 39 1.00 39.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 80.73 1.00 80.73
9,999 Cement, sand and grit etc. L.S. 107.64 1.00 107.64
TOTAL 9909.92
Add 1% for water charges 99.10
TOTAL 10009.02
Add for contractor’s profit and overheads
@15% 1501.35
Cost of 1 pan 11510.37
Say

17.6 Providing and fixing one piece construction white vitreous china squatting plate with an integral
longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I.
flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P.
brass coupling complete including painting of fittings and cutting and making good the walls and floors
etc. wherever required :
17.6.1 Single squatting plate with 5 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7359 5 litre PVC automatic flushing c istern with
fitting each 1 430.00 430.00
1915 Vitreous china squatting plate urinal each 1 610.00 610.00
1540 Flush pipe and spreaders G.I.for single set
of one squatting plate urinal each 1 138.00 138.00
Labour:
116 Fitter (grade 1) Day 1.75 270.00 472.50
123 Mason ist class Day 0.75 270.00 202.50
114 Beldar Day 3 207.00 621.00
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 26.91 1.00 26.91
9,999 Cement, sand and grit etc. L.S. 26.91 1.00 26.91
TOTAL 2571.37
Add 1% for water charges 25.71
TOTAL 2597.08
Add for contractor’s profit and overheads
@15% 389.56
Cost of 1 pan 2986.65
Say

17.6 Providing and fixing one piece construction white vitreous china squatting plate with an integral
longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I.
flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P.
brass coupling complete including painting of fittings and cutting and making good the walls and floors
etc. wherever required :
17.6.2 Range of two squatting plates with 5 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7359 5 litre PVC automatic flushing c istern with
fitting each 1 430.00 430.00
1915 Vitreous china squatting plate urinal each 2 610.00 1220.00
1541 Flush pipe and spreaders G.I.for single set
of two squatting plate urinal each 1 203.00 203.00
Labour:
116 Fitter (grade 1) Day 2.5 270.00 675.00
123 Mason ist class Day 1 270.00 270.00
114 Beldar Day 4 207.00 828.00
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 33.15 1.00 33.15
9,999 Cement, sand and grit etc. L.S. 53.82 1.00 53.82
TOTAL 3756.52
Add 1% for water charges 37.57
TOTAL 3794.09
Add for contractor’s profit and overheads
@15% 569.11
Cost of 1 pan 4363.20
Say

17.6 Providing and fixing one piece construction white vitreous china squatting plate with an integral
longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I.
flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P.
brass coupling complete including painting of fittings and cutting and making good the walls and floors
etc. wherever required :
17.6.3 Range of three squatting plates with 10 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7361 10 litre PVC automatic flushing c istern
with fitting each 1 465.00 465.00
1915 Vitreous china squatting plate urinal each 3 610.00 1830.00
1542 Flush pipe and spreaders G.I.for single set
of three squatting plate urinal each 1 255.00 255.00
Labour:
116 Fitter (grade 1) Day 3 270.00 810.00
123 Mason ist class Day 1.5 270.00 405.00
114 Beldar Day 5 207.00 1035.00
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 42.12 1.00 42.12
9,999 Cement, sand and grit etc. L.S. 80.73 1.00 80.73
TOTAL 4966.40
Add 1% for water charges 49.66
TOTAL 5016.06
Add for contractor’s profit and overheads
@15% 752.41
Cost of 1 pan 5768.47
Say

17.6 Providing and fixing one piece construction white vitreous china squatting plate with an integral
longitudinal flushing pipe, white P.V.C. automatic flushing cistern, with fittings, standard size G.I.
flush pipe for back and front flush with standard spreader pipes with fittings, G.I clamps and C.P.
brass coupling complete including painting of fittings and cutting and making good the walls and floors
etc. wherever required :
17.6.4 Range of four squatting plates with 10 litre P.V.C. automatic flushing cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7361 10 litre PVC automatic flushing c istern
with fitting each 1 465.00 465.00
1915 Vitreous china squatting plate urinal each 4 610.00 2440.00
1543 Flush pipe and spreaders G.I.for single set
of four squatting plate urinal each 1 320.00 320.00
Labour:
116 Fitter (grade 1) Day 3.5 270.00 945.00
123 Mason ist class Day 1.75 270.00 472.50
114 Beldar Day 5.5 207.00 1138.50
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Red lead, white lead and gasket L.S. 17.55 1.00 17.55
9,999 Carriage of material L.S. 69.03 1.00 69.03
9,999 Cement, sand and grit etc. L.S. 107.64 1.00 107.64
TOTAL 6001.22
Add 1% for water charges 60.01
TOTAL 6061.23
Add for contractor’s profit and overheads
@15% 909.18
Cost of 1 pan 6970.42
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the walls
17.7.1 wherever
White require
Vitreous China: Wash basin size 630x450 mm with a pair of 15 mm C.P. brass pillar taps.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
1947 630x450 mm flat back wash basin of white
vitreous china each 1 500.00 500.00
1885 15 mm C.P. brass piller taps each 2 180.00 360.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.67 207.00 138.69
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1342.83
Add 1% for water charges 13.43
TOTAL 1356.26
Add for contractor’s profit and overheads
@15% 203.44
Cost of 1 pan 1559.70
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the walls
17.7.2 wherever
White require
Vitreous China: Wash basin size 630x450 m m with a single 15 mm C.P. brass pillar tap.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
1947 630x450 mm flat back wash basin of white
vitreous china each 1 500.00 500.00
1885 15 mm C.P. brass piller taps each 1 180.00 180.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1146.45
Add 1% for water charges 11.46
TOTAL 1157.91
Add for contractor’s profit and overheads
@15% 173.69
Cost of 1 pan
1331.60
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the walls
17.7.3 wherever
White require
Vitreous China: Wash basin size 550x400 mm with a pair of 15 mm C.P. brass pillar taps.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
3229 500x400 mm flat back wash basin of white
vitreous china each 1 450.00 450.00
1885 15 mm C.P. brass piller taps each 2 180.00 360.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.67 207.00 138.69
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1292.83
Add 1% for water charges 12.93
TOTAL 1305.76
Add for contractor’s profit and overheads
@15% 195.86
Cost of 1 pan 1501.62
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the walls
17.7.4 wherever
White require
Vitreous : Flat back wash basin size 550x400 mm with single 15 mm C.P. brass
China
pillar tap. Description
Code Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
3229 500x400 mm flat back wash basin of white
vitreous china each 1 450.00 450.00
1885 15 mm C.P. brass piller taps each 1 180.00 180.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1096.45
Add 1% for water charges 10.96
TOTAL 1107.41
Add for contractor’s profit and overheads
@15% 166.11
Cost of 1 pan 1273.53
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the wallsWhite
17.7.5 wherever require
Vitreous : Angle back wash basin size 600x480 mm with single 15 mm C.P. brass
China
Code
pillar tap. Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
1949 600x480 mm flat back wash basin of white
vitreous china each 1 540.00 540.00
1885 15 mm C.P. brass piller taps each 1 180.00 180.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1186.45
Add 1% for water charges 11.86
TOTAL 1198.31
Add for contractor’s profit and overheads
@15% 179.75
Cost of 1 no 1378.06
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the walls
17.7.6 wherever
White require
Vitreous China: Angle back wash basin size 400x400 mm with single 15 mm C.P. brass
Code
pillar tap. Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
1950 400x400 mm flat back wash basin of white
vitreous china each 1 400.00 400.00
1885 15 mm C.P. brass piller taps each 1 180.00 180.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1046.45
Add 1% for water charges 10.46
TOTAL 1056.91
Add for contractor’s profit and overheads
@15% 158.54
Cost of 1 no 1215.45
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the walls
17.7.7 wherever
White require
Vitreous : Flat back wash basin size 450x300 mm with single 15 mm C.P. brass
China
pillar tap. Description
Code Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
7004 450x300 mm flat back wash basin of white
vitreous china each 1 360.00 360.00
1885 15 mm C.P. brass piller taps each 1 180.00 180.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1006.45
Add 1% for water charges 10.06
TOTAL 1016.51
Add for contractor’s profit and overheads
@15% 152.48
Cost of 1 no 1168.99
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the wallsWhite
17.7.8 wherever require
Vitreous : Surgeon type wash basin of size 660x460 mm with a pair of 15mm C.P.
China
brass pillar taps with elbow operated levers.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
3213 660x460 mm flat back wash basin of white
vitreous china each 1 810.00 810.00
7363 15 mm C.P. brass tap with elbow operation
lever each 2 396.00 792.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.67 207.00 138.69
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 2084.83
Add 1% for water charges 20.85
TOTAL 2105.68
Add for contractor’s profit and overheads
@15% 315.85
Cost of 1 no 2421.53
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the walls
17.7.9 wherever
White require
Vitreous : Surgeon type wash basin of size 660x460 mm with single 15mm C.P.
China
brass pillar taps with elbow operated levers ISI marked.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
3213 660x460 mm flat back wash basin of white
vitreous china each 1 810.00 810.00
7363 15 mm C.P. brass tap with elbow operation
lever each 1 396.00 396.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1672.45
Add 1% for water charges 16.72
TOTAL 1689.17
Add for contractor’s profit and overheads
@15% 253.38
Cost of 1 no 1942.55
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the wallsStainless
17.7.10 whereverSteel
require :
AISI-304(18/8) Round basin 405x355 mm with single 15 mm C.P. brass pillar
tap.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
7806 Salem Stainless steel AISI - 304 (18/8)
Round basin 405mm X 355mm each 1 1500.00 1500.00
1885 15 mm C.P. brass piller taps each 1 180.00 180.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 2146.45
Add 1% for water charges 21.46
TOTAL 2167.91
Add for contractor’s profit and overheads
@15% 325.19
Cost of 1 no 2493.10
Say

17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P.
brass waste of standard pattern, including painting of fittings and brackets, cutting and making good
the wallsStainless
17.7.11 whereverSteel
require :
AISI-304(18/8) Wash basin 530x345 mm with single 15 mm C.P. brass pillar
tap.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
7807 Salem Stainless steel AISI - 304 (18/8)
Round basin 530mm X 345mm each 1 1350.00 1350.00
1885 15 mm C.P. brass piller taps each 1 180.00 180.00
1951 32 mm diameter C.P. brass waste of standard
pattern each 1 48.00 48.00
Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.63 207.00 130.41
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1996.45
Add 1% for water charges 19.96
TOTAL 2016.41
Add for contractor’s profit and overheads
@15% 302.46
Cost of 1 no 2318.88
Say

17.8 Providing and fixing white vitreous china pedestal for wash basin completely recessed at the
back for the reception of pipes and fittings.
Code Description Unit Quantity Rate Amount
Details of cost for 1 pedestal
Materials:
1396 Vitreous china pedestal for wash basin pair 1 527.00 527.00
Labour:
9,999 White cement mortar L.S. 40.3 1.00 40.30
9,999 Carriage of materials and fixing charges L.S. 40.43 1.00 40.43
TOTAL 607.73
Add 1% for water charges 6.08
TOTAL 613.81
Add for contractor’s profit and overheads
@15% 92.07
Cost of 1 no 705.88
Say

17.9 Providing and fixing kitchen sink with C.I. brackets, C.P. brass chain with rubber plug, 40 mm
C.P. brass waste complete, including painting the fittings and brackets, cutting and making good the
walls wherever required :
17.9.1 White glazed fire clay kitchen sink of size 600x450x250 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
1315 C.P.brass chain with 40 mm dia rubber plug
each 1 22.00 22.00
1863 Fire clay kitchen sink: 600x450x250 mm
each 1 1192.00 1192.00
1952 C.P. brass waste 40 mm each 1 53.00 53.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.56 207.00 115.92
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1649.36
Add 1% for water charges 16.49
TOTAL 1665.85
Add for contractor’s profit and overheads
@15% 249.88
Cost of 1 no 1915.73
Say

17.10 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I.
brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making
good the walls wherever required:
17.10.1 Kitchen sink with drain board
17.10.1.1 510x1040 mm bowl depth 250mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 2 48.00 96.00
7095 Stainless steel kitchen sink - with drain
board bowl depth 250 mm. each 1 4900.00 4900.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.6 270.00 162.00
114 Beldar Day 0.82 207.00 169.74
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 27.04 1.00 27.04
TOTAL 5454.61
Add 1% for water charges 54.55
TOTAL 5509.16
Add for contractor’s profit and overheads
@15% 826.37
Cost of 1 no 6335.53
Say

17.10 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I.
brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making
good the walls wherever required:
17.10.1 Kitchen sink with drain board
17.10.1.2 510x1040 mm bowl depth 225mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 2 48.00 96.00
7096 Stainless steel kitchen sink - with drain
board 510 x 1040mm bowl depth 225mm
each 1 4600.00 4600.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.6 270.00 162.00
114 Beldar Day 0.82 207.00 169.74
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 27.04 1.00 27.04
TOTAL 5154.61
Add 1% for water charges 51.55
TOTAL 5206.16
Add for contractor’s profit and overheads
@15% 780.92
Cost of 1 no 5987.08
Say

17.10 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I.
brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making
good the walls wherever required:
17.10.1 Kitchen sink with drain board
17.10.1.3 510x1040 mm bowl depth 200mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 2 48.00 96.00
7097 Stainless steel kitchen sink - with drain
board 510 x 1040mm bowl depth 200mm
each 1 4100.00 4100.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.6 270.00 162.00
114 Beldar Day 0.82 207.00 169.74
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 27.04 1.00 27.04
TOTAL 4654.61
Add 1% for water charges 46.55
TOTAL 4701.16
Add for contractor’s profit and overheads
@15% 705.17
Cost of 1 no 5406.33
Say

17.10 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I.
brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making
good the walls wherever required:
17.10.1 Kitchen sink with drain board
17.10.1.4 510x1040 mm bowl depth 178mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 2 48.00 96.00
7098 Stainless steel kitchen sink - with drain
board 510 x 1040mm bowl depth 178mm
each 1 2600.00 2600.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.6 270.00 162.00
114 Beldar Day 0.82 207.00 169.74
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 27.04 1.00 27.04
TOTAL 3154.61
Add 1% for water charges 31.55
TOTAL 3186.16
Add for contractor’s profit and overheads
@15% 477.92
Cost of 1 no 3664.08
Say

17.10 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I.
brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making
good the walls wherever required:
17.10.2 Kitchen sink without drain board
17.10.2.1 610x510 mm bowl depth 200 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
7101 Stainless steel kitchen sink - without drain
board 610x510mm bowl depth 200mm
each 1 2700.00 2700.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.56 207.00 115.92
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.52 1.00 13.52
TOTAL 3066.37
Add 1% for water charges 30.66
TOTAL 3097.03
Add for contractor’s profit and overheads
@15% 464.56
Cost of 1 no 3561.59
Say
17.10 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I.
brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making
good the walls wherever required:
17.10.2 Kitchen sink without drain board
17.10.2.2 610x460 mm bowl depth 200 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
7102 Stainless steel kitchen sink - without drain
board 610x460mm bowl depth 200mm each 1 2500.00 2500.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.56 207.00 115.92
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.52 1.00 13.52
TOTAL 2866.37
Add 1% for water charges 28.66
TOTAL 2895.03
Add for contractor’s profit and overheads
@15% 434.26
Cost of 1 no 3329.29
Say

17.10 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I.
brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making
good the walls wherever required:
17.10.2 Kitchen sink without drain board
17.10.2.3 470x420 mm bowl depth 178 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
7103 Stainless steel kitchen sink - without drain
board 470x420mm bowl depth 178mm
each 1 1600.00 1600.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.56 207.00 115.92
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.52 1.00 13.52
TOTAL 1966.37
Add 1% for water charges 19.66
TOTAL 1986.03
Add for contractor’s profit and overheads
@15% 297.91
Cost of 1 no 2283.94
Say

17.11 Providing and fixing white vitreous china laboratory sink with C.I. brackets, C.P. brass chain
with rubber plug 40mm C.P brass waste and 40mm C.P. brass trap with necessary C.P. brass unions
complete including painting of fittings and brackets, cutting and making good the wall wherever
required :
17.11.1 Size 450x300x150mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
1315 C.P.brass chain with 40 mm dia rubber plug
each 1 22.00 22.00
1871 White vitreous china laboratory
sink450x300x150 mm each 1 664.00 664.00
1895 C.P.brass trap40 mm dia each 1 99.00 99.00
1952 C.P. brass waste 40 mm each 1 53.00 53.00
3617 C.P. Brass union 40 mm dia each 1 130.00 130.00
Labour:
116 Fitter (grade 1) Day 0.22 270.00 59.40
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.56 207.00 115.92
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 1350.36
Add 1% for water charges 13.50
TOTAL 1363.86
Add for contractor’s profit and overheads
@15% 204.58
Cost of 1 no 1568.44
Say

17.11 Providing and fixing white vitreous china laboratory sink with C.I. brackets, C.P. brass chain
with rubber plug 40mm C.P brass waste and 40mm C.P. brass trap with necessary C.P. brass unions
complete including painting of fittings and brackets, cutting and making good the wall wherever
required :
17.11.2 Size 600x450x200mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
1315 C.P.brass chain with 40 mm dia rubber plug
each 1 22.00 22.00
1872 White vitreous china laboratory sink
650x450x200 mm each 1 1400.00 1400.00
1895 C.P.brass trap40 mm dia each 1 99.00 99.00
1952 C.P. brass waste 40 mm each 1 53.00 53.00
3617 C.P. Brass union 40 mm dia each 1 130.00 130.00
Labour:
116 Fitter (grade 1) Day 0.22
270.00 59.40
123 Mason ist class Day 0.33 270.00 89.10
114 Beldar Day 0.56 207.00 115.92
9,999 Painting of fittings etc. L.S. 26.91 1.00 26.91
9,999 Red lead, white lead and gasket L.S. 16.12 1.00 16.12
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 2086.36
Add 1% for water charges 20.86
TOTAL 2107.22
Add for contractor’s profit and overheads
@15% 316.08
Cost of 1 no 2423.31
Say

17.12 Providing and fixing draining board with C.I. brackets including painting of brackets, cutting
and making good the walls wherever required :
17.12.1 White glazed fire clay draining board of size 600x450x25mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1309 C.I./M.S. brackets pair 1 48.00 48.00
7364 White glazed fire clay draining board
600x450x25 mm each 1 390.00 390.00
Labour:
116 Fitter (grade 1) Day 0.06 270.00 16.20
123 Mason ist class Day 0.17 270.00 45.90
114 Beldar Day 0.22 207.00 45.54
9,999 Painting of fittings etc. L.S. 26 1.00 26.00
9,999 Carriage of material L.S. 7.8 1.00 7.80
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 592.83
Add 1% for water charges 5.93
TOTAL 598.76
Add for contractor’s profit and overheads
@15% 89.81
Cost of 1 pan 688.57
Say

17.13 Providing and fixing white vitreous china water closet squatting pan (Indian type)
17.13.1 Long pattern W.C. pan of size 580 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1953 Vitreous china Indian type w.c. pan size 580
mm each 1 350.00 350.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 615.41
Add 1% for water charges 6.15
TOTAL 621.56
Add for contractor’s profit and overheads
@15% 93.23
Cost of 1 no 714.80
Say

17.13 Providing and fixing white vitreous china water closet squatting pan (Indian type)
17.13.2 Orissa pattern W.C . pan of size 580x440 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1954 Vitreous china orrisa type w.c. pan size 580
mm each 1 550.00 550.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 815.41
Add 1% for water charges 8.15
TOTAL 823.56
Add for contractor’s profit and overheads
@15% 123.53
Cost of 1 no 947.10
Say

17.14 Extra for using coloured W.C. pan instead of white W.C. pan
17.14.1 Orissa pattern W.C. pan 580x440 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1954 Vitreous china orrisa type w.c. pan size 580
mm each 1 550.00 -550.00
7104 Coloured Orissa pattern W.C. pan 580x440
mm each 1 1043.00 1043.00
TOTAL 493.00
Add 1% for water charges 4.93
TOTAL 497.93
Add for contractor’s profit and overheads
@15% 74.69
Cost of 1 pan 572.62
Say

17.15 Providing and fixing white vitreous china pedestal type (European type/ wash down type) water
closet pan.Description
Code Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1955 Vitreous china pedestal type water clos et
each 1 600.00 600.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of material L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 13.39 1.00 13.39
TOTAL 865.41
Add 1% for water charges 8.65
TOTAL 874.06
Add for contractor’s profit and overheads
@15% 131.11
Cost of 1 pan 1005.17
Say

17.16 Extra for using coloured pedestal type W.C pan (European type) with low level cistern of same
colour instead of white vitreous china W.C pan and cistern.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1955 Vitreous china pedestal type water clos et
each 1 600.00 -600.00
7105 Coloured Pedestal type W.C. pan 580x440
mm (European type) each 1 900.00 900.00
7106 Coloured Vitreous china 10 lit. low level
cistern each 1 1300.00 1300.00
7005 Vitreous china 10 litres low level cistern w
ithout fittings each 1 824.00 -824.00
TOTAL 776.00
Add 1% for water charges 7.76
TOTAL 783.76
Add for contractor’s profit and overheads
@15% 117.56
Cost of 1 no 901.32
Say

17.17 Providing and fixing a pair of white vitreous china foot rests of standard pattern for squatting pan
water closet:
17.17.1 250x130x30 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 pair
Materials:
1363 Vitreous china foot rests 250x130x30 mm
pair 1 79.00 79.00
Labour:
123 Mason ist class Day 0.06 270.00 16.20
9,999 Cement, sand including carriage of L.S. 8.06
materials 1.00 8.06
TOTAL 103.26
Add 1% for water charges 1.03
TOTAL 104.29
Add for contractor’s profit and overheads
@15% 15.64
Cost of 1 no 119.94
Say

17.17 Providing and fixing a pair of white vitreous china foot rests of standard pattern for squatting pan
water closet:
17.17.2 250x125x25 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 pair
Materials:
1970 Vitreous china foot rests 250x125x25 mm
pair 1 180.00 180.00
Labour:
123 Mason ist class Day 0.06 270.00 16.20
9,999 Cement, sand including carriage of L.S. 8.06
materials 1.00 8.06
TOTAL 204.26
Add 1% for water charges 2.04
TOTAL 206.30
Add for contractor’s profit and overheads
@15% 30.95
Cost of 1 pair 237.25
Say

17.18 Providing and fixing P.V.C. low level flushing cistern with manually controlled device (handle
lever) conforming to IS : 7231, with all fittings and fixtures complete.
17.18.1 10 litre capacity-White
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7358 Flushing Cistern P.V.C. 10 lts capacity ( low
level ) (White) ( with fittings, accessories
and flush pipe)
each 1 570.00 570.00
Labour:
116 Fitter (grade 1) Day 0.125 270.00 33.75
114 Beldar Day 0.125 207.00 25.88
9,999 Carriage of materials L.S. 5.2 1.00 5.20
TOTAL 634.83
Add 1% for water charges 6.35
TOTAL 641.17
Add for contractor’s profit and overheads
@15% 96.18
Cost of 1 no 737.35
Say

17.18 Providing and fixing P.V.C. low level flushing cistern with manually controlled device (handle
lever) conforming to IS : 7231, with all fittings and fixtures complete.
17.18.2 10 litre capacity-coloured
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7123 Coloured High density polyethylene/ poly
propylene 10 lit. (full flush) capacity
controlled low level flushing cis tern with
fittings
each 1 632.00 632.00
Labour:
116 Fitter (grade 1) Day 0.125 270.00 33.75
114 Beldar Day 0.125 207.00 25.88
9,999 Carriage of materials L.S. 7.02 1.00 7.02
TOTAL 698.65
Add 1% for water charges 6.99
TOTAL 705.63
Add for contractor’s profit and overheads
@15% 105.84
Cost of 1 no 811.48
Say

17.19 Providing and fixing controlled flush, low level cistern made of vitreous china with all fittings
complete.
17.19.1 10 litre (full flush) capacity-white
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7126 White Vitreous china 10 lit. (full flush)
capacity controlled low level flushing
cistern with all fittings
each 1 858.00 858.00
Labour:
116 Fitter (grade 1) Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of materials L.S. 13.52 1.00 13.52
TOTAL 1110.02
Add 1% for water charges 11.10
TOTAL 1121.12
Add for contractor’s profit and overheads
@15% 168.17
Cost of 1 no 1289.29
Say

17.19 Providing and fixing controlled flush, low level cistern made of vitreous china with all fittings
complete.
17.19.2 10 litre (full flush) capacity-coloured
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7127 Coloured Vitreous china 10 lit. (full flush)
capacity controlled low level flushing cistern
with all fittings
each 1 1277.00 1277.00
Labour:
116 Fitter (grade 1) Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of materials L.S. 13.52 1.00 13.52
TOTAL 1529.02
Add 1% for water charges 15.29
TOTAL 1544.31
Add for contractor’s profit and overheads
@15% 231.65
Cost of 1 no 1775.96
Say

17.20 Providing and fixing solid plastic seat with lid for pedestal type W.C. pan complete :
17.20.1 White solid plastic seat with lid
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1875 White plastic seat (solid)w ith lid C.P.brass
hinges and rubber buffers each 1 275.00 275.00
Labour:
9,999 Carriage of materials L.S. 13.39 1.00 13.39
TOTAL 288.39
Add 1% for water charges 2.88
TOTAL 291.27
Add for contractor’s profit and overheads
@15% 43.69
Cost of 1 no 334.96
Say

17.20 Providing and fixing solid plastic seat with lid for pedestal type W.C. pan complete :
17.20.2 Black solid plastic seat with lid
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1876 Black plastic seat (solid) with lid C.P.brass
hinges and rubber buffers each 1 250.00 250.00
Labour:
9,999 Carriage of materials L.S. 13.39 1.00 13.39
TOTAL 263.39
Add 1% for water charges 2.63
TOTAL 266.02
Add for contractor’s profit and overheads
@15% 39.90
Cost of 1 no 305.93
Say

17.21 Extra for providing coloured other than black solid P.V.C. plastic seat and cover in European
type W.C. pan, instead of white plastic seat and cover.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1875 White plastic seat (solid)w ith lid C.P.brass
hinges and rubber buffers each 1 275.00 -275.00
7107 Coloured (other than black) solid P.V.C. seat
in European W.C. pan each 1 250.00 250.00
TOTAL -25.00
Add 1% for water charges -0.25
TOTAL -25.25
Add for contractor’s profit and overheads
@15% -3.79
Cost of 1 no -29.04
Say

17.22 Providing and fixing G.I. inlet connection for flush pipe connecting with W.C. pan.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1614 G.I. inlet connection each 1 50.00 50.00
Labour:
9,999 Carriage of materials L.S. 13.39 1.00 13.39
TOTAL 63.39
Add 1% for water charges 0.63
TOTAL 64.02
Add for contractor’s profit and overheads
@15% 9.60
Cost of 1 pan 73.63
Say

17.23 Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin
of 430x260x350mm and 340x410x265mm sizes respectively.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1913 Vitreous china lipped front urinal each 1 380.00 380.00
Labour:
116 Fitter (grade 1) Day 0.38 270.00 102.60
114 Beldar Day 0.38 207.00 78.66
9,999 Carriage of materials L.S. 9.49 1.00 9.49
TOTAL 570.75
Add 1% for water charges 5.71
TOTAL 576.46
Add for contractor’s profit and overheads
@15% 86.47
Cost of 1 no. 662.93
Say

17.24 Providing and fixing white vitreous china squatting plate urinal with integral rim longitudinal
Code
flush pipe.Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1915 Vitreous china squatting plate urinal each 1 610.00 610.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00
116 Fitter (grade 1) Day 0.5 270.00 135.00
114 Beldar Day 1 207.00 207.00
9,999 Carriage of material L.S. 13.39 1.00 13.39
9,999 Cement, sand and grit etc. L.S. 10.79 1.00 10.79
TOTAL 1111.18
Add 1% for water charges 11.11
TOTAL 1122.29
Add for contractor’s profit and overheads
@15% 168.34
Cost of 1 no. 1290.64
Say

17.25 Providing and fixing white vitreous china wash basin including making all connections but
excluding the cost of fittings:
17.25.1 Flat back wash basin of size 630x450mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1947 Vitreous china flat back wash basin
630x450 mm each 1 500.00 500.00
Labour:
9,999 Fixing charges L.S. 53.82 1.00 53.82
9,999 Carriage of materials L.S. 9.49 1.00 9.49
TOTAL 563.31
Add 1% for water charges 5.63
TOTAL 568.94
Add for contractor’s profit and overheads
@15% 85.34
Cost of 1 no. 654.28
Say

17.25 Providing and fixing white vitreous china wash basin including making all connections but
excluding the cost of fittings:
17.25.2 Flat back wash basin of size 550x400mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
3229 Vitreous china flat back wash basin
550x400 mm each 1 450.00 450.00
Labour:
9,999 Fixing charges L.S. 53.82 1.00 53.82
9,999 Carriage of materials L.S. 9.49 1.00 9.49
TOTAL 513.31
Add 1% for water charges 5.13
TOTAL 518.44
Add for contractor’s profit and overheads
@15% 77.77
Cost of 1 no. 596.21
Say

17.25 Providing and fixing white vitreous china wash basin including making all connections but
excluding the cost of fittings:
17.25.3 Angle back wash basin of size 600x480mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1949 Vitreous china angle back wash basin
600x480 mm each 1 540.00 540.00
Labour:
9,999 Fixing charges L.S. 53.82 1.00 53.82
9,999 Carriage of materials L.S. 9.49 1.00 9.49
TOTAL 603.31
Add 1% for water charges 6.03
TOTAL 609.34
Add for contractor’s profit and overheads
@15% 91.40
Cost of 1 no. 700.74
Say

17.25 Providing and fixing white vitreous china wash basin including making all connections but
excluding the cost of fittings:
17.25.4 Angle back wash basin of size 400x400mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1950 Vitreous china angle back wash basin
400x400 mm each 1 400.00 400.00
Labour:
9,999 Fixing charges L.S. 53.82 1.00 53.82
9,999 Carriage of materials L.S. 9.49 1.00 9.49
TOTAL 463.31
Add 1% for water charges 4.63
TOTAL 467.94
Add for contractor’s profit and overheads
@15% 70.19
Cost of 1 no. 538.13
Say

17.25 Providing and fixing white vitreous china wash basin including making all connections but
excluding the cost of fittings:
17.25.5 Flat back wash basin of size 450x300mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7004 Vitreous china flat back wash basin
450x300 mm each 1 360.00 360.00
Labour:
9,999 Fixing charges L.S. 53.82 1.00 53.82
9,999 Carriage of materials L.S. 9.49 1.00 9.49
TOTAL 423.31
Add 1% for water charges 4.23
TOTAL 427.54
Add for contractor’s profit and overheads
@15% 64.13
Cost of 1 no. 491.67
Say

17.25 Providing and fixing white vitreous china wash basin including making all connections but
excluding the cost of fittings:
17.25.6 Surgeon type wash basin of size 660x460mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
3213 Vitreous china Surgeon type w ash basin of
size 660x460 mm each 1 810.00 810.00
Labour:
9,999 Fixing charges L.S. 53.82 1.00 53.82
9,999 Carriage of materials L.S. 9.49 1.00 9.49
TOTAL 873.31
Add 1% for water charges 8.73
TOTAL 882.04
Add for contractor’s profit and overheads
@15% 132.31
Cost of 1 no. 1014.35
Say

17.26 Providing and fixing kitchen sink including making all connections excluding cost of fittings.
17.26.1 White glazed fire clay sink of size 600x450x250mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1863 Fire clay kitchen sink: 600x450x250 mm
each 1 1192.00 1192.00
Labour:
9,999 Fixing charges L.S. 40.42 1.00 40.42
9,999 Carriage of materials L.S. 10.79 1.00 10.79
TOTAL 1243.21
Add 1% for water charges 12.43
TOTAL 1255.64
Add for contractor’s profit and overheads
@15% 188.35
Cost of 1 no. 1443.99
Say

17.27 Providing and fixing white vitreous china laboratory sink including making all connections
excluding cost of fittings:
17.27.1 Size 450x300x150 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1871 White vitreous china laboratory
sink450x300x150 mm each 1 664.00 664.00
Labour:
9,999 Fixing charges L.S. 40.42 1.00 40.42
9,999 Carriage of materials L.S. 10.79 1.00 10.79
TOTAL 715.21
Add 1% for water charges 7.15
TOTAL 722.36
Add for contractor’s profit and overheads
@15% 108.35
Cost of 1 no. 830.72
Say

17.27 Providing and fixing white vitreous china laboratory sink including making all connections
excluding cost of fittings:
17.27.2 Size 600x450x200 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1872 White vitreous china laboratory sink
600x450x200 mm. each 1 1400.00 1400.00
Labour:
9,999 Fixing charges L.S. 40.42 1.00 40.42
9,999 Carriage of materials L.S. 10.79 1.00 10.79
TOTAL 1451.21
Add 1% for water charges 14.51
TOTAL 1465.72
Add for contractor’s profit and overheads
@15% 219.86
Cost of 1 no. 1685.58
Say

17.28 Providing and fixing P.V.C. waste pipe for sink or wash basin including P.V.C. waste fittings
complete.
17.28.1 Semi rigid pipe
17.28.1.1 32mmdia
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7117 Semi Rigid PVC waste pipe for sink and
wash basin 32 mm dia with length not less
than 700 mm i/c PVC was te fittings

each 1 16.00 16.00


9,999 Carriage of materials & Fixing charges L.S. 20.28 1.00 20.28
TOTAL 36.28
Add 1% for water charges 0.36
TOTAL 36.64
Add for contractor’s profit and overheads
@15% 5.50
Cost of 1 no. 42.14
Say

17.28 Providing and fixing P.V.C. waste pipe for sink or wash basin including P.V.C. waste fittings
complete.
17.28.1 Semi rigid pipe
17.28.1.2 40mmdia
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7118 Semi Rigid PVC waste pipe for sink and
wash basin 40 mm dia with length not less
than 700 mm i/c PVC was te fittings

each 1 21.00 21.00


9,999 Carriage of materials & Fixing charges L.S. 20.28 1.00 20.28
TOTAL 41.28
Add 1% for water charges 0.41
TOTAL 41.69
Add for contractor’s profit and overheads
@15% 6.25
Cost of 1 no. 47.95
Say

17.28 Providing and fixing P.V.C. waste pipe for sink or wash basin including P.V.C. waste fittings
complete.
17.28.2 Flexible pipe
17.28.2.1 32mm dia
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7119 Flexible (coil shaped) PVC waste pipe for
sink and wash basin 32mm dia with length
not less than 700 mm i/c PVC waste
fittings
each 1 20.00 20.00
9,999 Carriage of materials & Fixing charges L.S. 20.28 1.00 20.28
TOTAL 40.28
Add 1% for water charges 0.40
TOTAL 40.68
Add for contractor’s profit and overheads
@15% 6.10
Cost of 1 no. 46.79
Say

17.28 Providing and fixing P.V.C. waste pipe for sink or wash basin including P.V.C. waste fittings
complete.
17.28.2 Flexible pipe
17.28.2.2 40mmdia
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
7120 Flexible (coil shaped) PVC waste pipe for
sink and wash basin 40mm dia with length
not less than 700 mm i/c PVC waste
fittings
each 1 22.00 22.00
9,999 Carriage of materials & Fixing charges L.S. 20.28 1.00 20.28
TOTAL 42.28
Add 1% for water charges 0.42
TOTAL 42.70
Add for contractor’s profit and overheads
@15% 6.41
Cost of 1 no. 49.11
Say

17.29 Providing and fixing 100 m m sand cast Iron grating for gully trap.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1369 S.C.I. gully or nahani grating 100 mm dia
each 1 10.00 10.00
9,999 Carriage of materials & Fixing charges L.S. 4.16 1.00 4.16
TOTAL 14.16
Add 1% for water charges 0.14
TOTAL 14.30
Add for contractor’s profit and overheads
@15% 2.15
Cost of 1 no 16.45
Say

17.30 Providing and fixing in position 25mm diameter mosquito proof coupling of approved municipal
design. Description
Code Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1350 Mosquito proof coupling of approved
design each 1 23.00 23.00
9,999 Carriage of materials & Fixing charges L.S. 1.82 1.00 1.82
TOTAL 24.82
Add 1% for water charges 0.25
TOTAL 25.07
Add for contractor’s profit and overheads
@15% 3.76
Cost of 1 no. 28.83
Say

17.31 Providing and fixing 600x450 mm bevelled edge mirror of superior glass (of approved quality)
complete with 6 mm thick hard board ground fixed to wooden cleats with C.P. brass screws and
washers
Code complete.
Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1392 Mirror of superior make glass each 1 249.00 249.00
7116 Hard board 6 mm thick sqm 0.27 151.00 40.77
Wooden cleates (Rate as per item no 9.32 of
SH : Wood work) each 4 11.81 47.23
588 Chromium plated Brass screws 25 mm 100 Nos 4
83.00 3.32
0112 Carpenter 2nd class Day 0.33 180 59.40
114 Beldar Day 0.33 207 68.31
9,999 Carriage of materials L.S. 4.16 1.00 4.16
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 473.62
Add 1% for water charges except A 4.26
TOTAL 477.88
Add for contractor’s profit and overheads
@15% 64.60
Cost of 1 no. 542.48
Say

17.32 Providing and fixing mirror of superior glass (of approved quality) and of required shape and
size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing :
17.32.1 Circular shape 450mm dia.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7112 Circular shape 450 mm dia Mirror with
Plastic moulded frame each 1 400.00 400.00
7116 Hard board 6 mm thick sqm 0.22 151.00 33.22
7048 Raw l plug 50 mm (designation 10 no.) each 2 7.00 14.00
588 Chromium plated Brass screws 25 mm 100 Nos 2
83.00 1.66
0112 Carpenter 2nd class Day 0.33 180 59.40
114 Beldar Day 0.33 207 68.31
9,999 Carriage of materials L.S. 4.16 1.00 4.16
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 582.18
Add 1% for water charges except A 5.82
TOTAL 588.00
Add for contractor’s profit and overheads
@15% 88.20
Cost of 1 no. 676.20
Say

17.32 Providing and fixing mirror of superior glass (of approved quality) and of required shape and
size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing :
17.32.2 Rectangular shape 453x357mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7113 Rectangular shape 453x357 mm Mirror
with Plastic moulded frame each 1 350.00 350.00
7116 Hard board 6 mm thick sqm 0.18 151.00 27.18
7048 Raw l plug 50 mm (designation 10 no.) each 4 7.00 28.00
588 Chromium plated Brass screws 25 mm 100 Nos 4
83.00 3.32
0112 Carpenter 2nd class Day 0.33 180 59.40
114 Beldar Day 0.33 207 68.31
9,999 Carriage of materials L.S. 4.16 1.00 4.16
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 541.80
Add 1% for water charges except A 5.42
TOTAL 547.22
Add for contractor’s profit and overheads
@15% 82.08
Cost of 1 no. 629.30
Say

17.32 Providing and fixing mirror of superior glass (of approved quality) and of required shape and
size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing :
17.32.3 Oval shape 450x350mm (outer dimensions)
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7114 Oval shape 450x 350 mm (outer
dimensions) Mirror with Plastic moulded
frame
each 1 450.00 450.00
7116 Hard board 6 mm thick sqm 0.17 151.00 25.67
7048 Raw l plug 50 mm (designation 10 no.) each 4 7.00 28.00
588 Chromium plated Brass screws 25 mm 100 Nos 4
83.00 3.32
0112 Carpenter 2nd class Day 0.33
180 59.40
114 Beldar Day 0.33 207 68.31
9,999 Carriage of materials L.S. 4.16 1.00 4.16
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 640.29
Add 1% for water charges except A 6.40
TOTAL 646.69
Add for contractor’s profit and overheads
@15% 97.00
Cost of 1 no. 743.70
Say

17.32 Providing and fixing mirror of superior glass (of approved quality) and of required shape and
size with plastic moulded frame of approved make and shade with 6 mm thick hard board backing :
17.32.4 Rectangular shape 1500x450 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7115 Rectangular shape 1500x450 mm Mirror
with Plastic moulded frame each 1 1200.00 1200.00
7116 Hard board 6 mm thick sqm 0.74 151.00 111.74
7048 Raw l plug 50 mm (designation 10 no.) each 6 7.00 42.00
588 Chromium plated Brass screws 25 mm 100 Nos 6
83.00 4.98
0112 Carpenter 2nd class Day 0.33 180 59.40
114 Beldar Day 0.33 207 68.31
9,999 Carriage of materials L.S. 4.16 1.00 4.16
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 1492.02
Add 1% for water charges 14.92
TOTAL 1506.94
Add for contractor’s profit and overheads
@15% 226.04
Cost of 1 no. 1732.98
Say
17.33 Providing and fixing 600x120x5mm glass shelf with edges round of supported on anodised
aluminium angle frame with C.P. brass brackets and guard rail complete fixed with 40 mm long screws,
rawl
Code plugsDescription
etc., complete. Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3228 600x120 mm glass shelf with anodised
aluminium angle frame, C.P. brass brackets
and guard rail of standard size

each 1 95.00 95.00


7048 Raw l plug 50 mm (designation 10 no.) each 2 7.00 14.00
586 Chromium plated Brass screws 40 mm 100 Nos 4
150.00 6.00
0112 Carpenter 2nd class Day 0.25 180 45.00
114 Beldar Day 0.25 207 51.75
9,999 Carriage of materials L.S. 4.16 1.00 4.16
TOTAL 215.91
Add 1% for water charges 2.16
TOTAL 218.07
Add for contractor’s profit and overheads
@15% 32.71
Cost of 1 no. 250.78
Say

17.34 Providing and fixing toilet paper holder :


17.34.1 C.P. brass
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1889 C.P.brass toilet paper holder of standard size
each 1 70.00 70.00
Wooden cleates (Rate as per item no 9.32 of
SH : Wood work) each 2 11.81 23.61
588 Chromium plated Brass screws 25 mm 100 Nos 2
83.00 1.66
0112 Carpenter 2nd class Day 0.12 180 21.60
114 Beldar Day 0.12 207 24.84
9,999 Carriage of materials L.S. 4.29 1.00 4.29
TOTAL 146.00
Add 1% for water charges except A 1.22
TOTAL 147.23
Add for contractor’s profit and overheads
@15% 18.54
Cost of 1 no. 165.77
Say

17.34 Providing and fixing toilet paper holder:


17.34.2 Vitreous china
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3749 Vitreous china toilet paper holder of
standard size each 1 89.00 89.00
Wooden cleates (Rate as per item no 9.32 of
SH : Wood work) each 2 11.81 23.61
588 Chromium plated Brass screws 25 mm 100 Nos 6
83.00 4.98
0112 Carpenter 2nd class Day 0.12 180 21.60
114 Beldar Day 0.12 207 24.84
9,999 Carriage of materials L.S. 4.29 1.00 4.29
TOTAL 168.32
Add 1% for water charges except A 1.45
TOTAL 169.77
Add for contractor’s profit and overheads
@15% 21.92
Cost of 1 no. 191.69
Say

17.35 Providing and fixing soil, waste and vent pipes:


17.35.1 100 mm dia.
17.35.1.1 Sand cast iron S&S pipe as per IS: 1729.
Code Description Unit Quantity Rate Amount
Details of cost for 17.37 m
Materials:
1617 S.C.I. soil, waste and vent single socketed
pipe1.80 metres long: 100 mm dia
each 10.5 610.00 6405.00
116 Fitter I class Day 0.42 270 113.40
100 Bandhani Day 0.21 180 37.80
114 Beldar Day 0.83 207 171.81
9,999 Scaffolding L.S. 80.73 1.00 80.73
9,999 Carriage of materials L.S. 53.82 1.00 53.82
TOTAL 6862.56
Add 1% for water charges 68.63
TOTAL 6931.19
Add for contractor’s profit and overheads
@15% 1039.68
Cost of 17.37 m 7970.86
Cost of 1 m 458.89
Say

17.35 Providing and fixing soil, waste and vent pipes :


17.35.1 100 mm dia.
17.35.1.2 Centrifugally cast (spun) iron socketed pipe as per IS: 3989.
Code Description Unit Quantity Rate Amount
Details of cost for 16.87 m
Materials:
3620 C.C.I.(spun) socketed s oil, waste and vent
pipe 1.80 metres long : 100mm dia each 10.5 978.00 10269.00
116 Fitter I class Day 0.42 270 113.40
100 Bandhani Day 0.21 180 37.80
114 Beldar Day 0.83 207 171.81
9,999 Scaffolding L.S. 80.73 1.00 80.73
9,999 Carriage of materials L.S. 53.82 1.00 53.82
TOTAL 10726.56
Add 1% for water charges 107.27
TOTAL 10833.83
Add for contractor’s profit and overheads
@15% 1625.07
Cost of 16.87 m 12458.90
Cost of 1 m 738.52
Say

17.35 Providing and fixing soil, waste and vent pipes :


17.35.2 75 mm diameter :
17.35.2.1 Sand cast iron S&S pipe as per IS: 1729.
Code Description Unit Quantity Rate Amount
Details of cost for 17.42 m
Materials:
1616 S.C.I. soil, waste and vent single socketed
pipe1.80 metres long: 75 mm dia
each 10.5 537.00 5638.50
116 Fitter I class Day 0.35 270 94.50
100 Bandhani Day 0.17 180 30.60
114 Beldar Day 0.7 207 144.90
9,999 Scaffolding L.S. 80.73 1.00 80.73
9,999 Carriage of materials L.S. 40.38 1.00 40.38
TOTAL 6029.61
Add 1% for water charges 60.30
TOTAL 6089.91
Add for contractor’s profit and overheads
@15% 913.49
Cost of 17.42 m 7003.39
Cost of 1 m 402.03
Say

17.35 Providing and fixing soil, waste and vent pipes :


17.35.2 75 mm diameter:
17.35.2.2 Centrifugally cast (spun) iron socketed pipe as per IS: 3989.
Code Description Unit Quantity Rate Amount
Details of cost for 16.92 m
Materials:
3621 C.C.I.(spun) socketed s oil, waste and vent
pipe 1.80 metres long : 75mm dia each 10.5 846.00 8883.00
116 Fitter I class Day 0.35 270 94.50
100 Bandhani Day 0.17 180 30.60
114 Beldar Day 0.7 207 144.90
9,999 Scaffolding L.S. 80.73 1.00 80.73
9,999 Carriage of materials L.S. 40.38 1.00 40.38
TOTAL 9274.11
Add 1% for water charges 92.74
TOTAL 9366.85
Add for contractor’s profit and overheads
@15% 1405.03
Cost of 16.92 m 10771.88
Cost of 1 m 636.64
Say

17.36 Providing and filling the joints with spun yarn cement slurry and cement mortar 1:2 (1 cement: 2
fine sand) in S.C.I./C.I. Pipes:
17.36.1 75mm dia pipe
Code Description Unit Quantity Rate Amount
Details of cost for 4 joints
Materials:
9,999 Cement mortar, spun yarn etc. L.S. 6.89 1.00 6.89
116 Fitter I class Day 0.28 270 75.60
114 Beldar Day 0.28 207 57.96
TOTAL 140.45
Add 1% for water charges 1.40
TOTAL 141.85
Add for contractor’s profit and overheads
@15% 21.28
Cost of 4 joints 163.13
Cost of 1 joint 40.78
Say

17.36 Providing and filling the joints with spun yarn cement slurry and cement mortar 1:2 (1 cement: 2
fine sand) in S.C.I./C.I. Pipes:
17.36.2 100 mm dia pipe
Code Description Unit Quantity Rate Amount
Details of cost for 4 joints
Materials:
9,999 Cement mortar, spun yarn etc. L.S. 8.06 1.00 8.06
116 Fitter I class Day 0.33 270 89.10
114 Beldar Day 0.33 207 68.31
TOTAL 165.47
Add 1% for water charges 1.65
TOTAL 167.12
Add for contractor’s profit and overheads
@15% 25.07
Cost of 4 joints 192.19
Cost of 1 joint 48.05
Say
17.37 Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/ cast iron
(spun) pipe embedded in and including cement concrete blocks 10x10x10cm of 1:2:4 mix (1 cement: 2
coarse sand : 4 graded stone aggregate 20mm nominal size) including cost of cutting holes and making
good the walls etc. :
17.37.1 For 100 mm dia. Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 nos.
MATERIALS
Materials:
1331 M.S.Holder bat clamp of approved design
for 100 mm S.C.I. pipe each 5 13.00 65.00
9,999 Carraige of bat clamps L.S. 2.47 1.00 2.47
295 Stone aggregate 20mm cum 0.0033 1100.00 3.63
297 Stone aggregate 10mm cum 0.0011 1100.00 1.21
2202 Carriage of aggregate 20mm and 10 mm cum 0.0044 53.21 0.23
982 Coarse sand cum 0.0022 300.00 0.66
2203 Carriage of coarse sand cum 0.0022 53.21 0.12
367 Cement tonne 0.0016 5200.00 8.32
2209 Carriage of cem ent tunne 0.0016 47.29 0.08
Labour;
116 Fitter I class Day 0.125 270 33.75
114 Beldar Day 0.5045 207 104.43
115 Coolie Day 0.0032 207 0.66
101 Bhishti Day 0.0014 180 0.25
123 Mason 1st class Day 0.0003 270 0.08
124 Mason 2nd class Day 0.7503 223 167.32
128 Mate Day 0.0002 313 0.06
9999 Higher charges of machines etc L.S 0.26 1.00 0.26
9999 Sundries L.S 7.41 1.00 7.41
TOTAL 395.94
Add 1% for water charges 3.96
TOTAL 399.90
Add for contractor’s profit and overheads
@15% 59.99
Cost of 4 nos. 459.89
Cost of 1 no. 91.98
Say

17.37 Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/ cast iron
(spun) pipe embedded in and including cement concrete blocks 10x10x10cm of 1:2:4 mix (1 cement: 2
coarse sand : 4 graded stone aggregate 20mm nominal size) including cost of cutting holes and making
good the walls etc. :
17.37.2 For 75 mm dia. Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 nos.
MATERIALS
Materials:
1332 M.S.Holder bat clamp of approved design
for 75 mm S.C.I. pipe each 5 11.00 55.00
9,999 Carraige of bat clamps L.S. 2.47 1.00 2.47
295 Stone aggregate 20mm cum 0.0033 1100.00 3.63
297 Stone aggregate 10mm cum 0.0011 1100.00 1.21
2202 Carriage of aggregate 20mm and 10 mm cum 0.0044 53.21 0.23

982 Coarse sand cum 0.0022 300.00 0.66


2203 Carriage of coarse sand cum 0.0022 53.21 0.12
367 Cement tonne 0.0016 5200.00 8.32
2209 Carriage of cem ent tunne 0.0016 47.29 0.08
Labour;
116 Fitter I class Day 0.125 270 33.75
114 Beldar Day 0.5045 207 104.43
115 Coolie Day 0.0032 207 0.66
101 Bhishti Day 0.0014 180 0.25
123 Mason 1st class Day 0.0003 270 0.08
124 Mason 2nd class Day 0.7503 223 167.32
128 Mate Day 0.0002 313 0.06
9999 Higher charges of machines etc L.S 0.26 1.00 0.26
9999 Sundries L.S 7.41 1.00 7.41
TOTAL 385.94
Add 1% for water charges 3.86
TOTAL
389.80
Add for contractor’s profit and overheads
@15% 58.47
Cost of 4 nos. 448.27
Cost of 1 no. 89.65
Say

17.38 Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm
thick, bolts and nuts complete.
17.38.1 100 mm
17.38.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1625 100 mm dia sand cast iron bend with
access each 1 194.00 194.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Cement, sand including carriage of L.S. 13.52
materials 1.00 13.52
TOTAL 219.52
Add 1% for water charges 2.20
TOTAL 221.72
Add for contractor’s profit and overheads
@15% 33.26
Cost of 1 no. 254.97
Say

17.38 Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm
thick, bolts and nuts complete.
17.38.1 100 mm
17.38.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3624 S.C.I. S&S bends with access door100mm
dia each 1 225.00 225.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Cement, sand including carriage of L.S. 13.52
materials 1.00 13.52
TOTAL 250.52
Add 1% for water charges 2.51
TOTAL 253.03
Add for contractor’s profit and overheads
@15% 37.95
Cost of 1 no. 290.98
Say

17.38 Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm
thick, bolts and nuts complete.
17.38.2 75 mm dia
17.38.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1624 75 mm dia sand cast iron bend with access
each 1 161.00 161.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Cement, sand including carriage of L.S. 10.79
materials 1.00 10.79
TOTAL 180.79
Add 1% for water charges 1.81
TOTAL 182.60
Add for contractor’s profit and overheads
@15% 27.39
Cost of 1 no. 209.99
Say

17.38 Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm
thick, bolts and nuts complete.
17.38.2 75 mm dia
17.38.2.2 Sand cast iron S& S as per IS- 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3625 S.C.I. S&S bends with access door 75mm
dia each 1 179.00 179.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Cement, sand including carriage of L.S. 10.79
materials 1.00 10.79
TOTAL 198.79
Add 1% for water charges 1.99
TOTAL 200.78
Add for contractor’s profit and overheads
@15% 30.12
Cost of 1 no. 230.89
Say

17.39 Providing and fixing plain bend of required degree.


17.39.1 100 mm
17.39.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1621 100 mm sand cast iron plain bend each 1 178.00 178.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 191.52
Add 1% for water charges 1.92
TOTAL 193.44
Add for contractor’s profit and overheads
@15% 29.02
Cost of 1 no. 222.45
Say

17.39 Providing and fixing plain bend of required degree.


17.39.1 100 mm
17.39.1.2 Sand cast iron S&S as per IS : 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3628 100 mm dia sand cast iron S & S plain bend
each 1 190.00 190.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 203.52
Add 1% for water charges 2.04
TOTAL 205.56
Add for contractor’s profit and overheads
@15% 30.83
Cost of 1 no. 236.39
Say

17.39 Providing and fixing plain bend of required degree.


17.39.2 75 mm
17.39.2.1 Sand cast iron S&S as per IS -1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1620 75 mm sand cast iron plain bend each 1 140.00 140.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 150.79
Add 1% for water charges 1.51
TOTAL 152.30
Add for contractor’s profit and overheads
@15% 22.84
Cost of 1 no. 175.14
Say

17.39 Providing and fixing plain bend of required degree.


17.39.2 75 mm
17.39.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3629 75 mm dia sand cast iron S & S plain bend
each 1 143.00 143.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 153.79
Add 1% for water charges 1.54
TOTAL 155.33
Add for contractor’s profit and overheads
@15% 23.30
Cost of 1 no. 178.63
Say

17.40 Providing and fixing heel rest sanitary bend


17.40.1 100 mm dia
17.40.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1667 100 mm sand cast iron heel rest bend each 1 197.00 197.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 210.52
Add 1% for water charges 2.11
TOTAL 212.63
Add for contractor’s profit and overheads
@15% 31.89
Cost of 1 no. 244.52
Say

17.40 Providing and fixing heel rest sanitary bend


17.40.1 100 mm dia
17.40.1.2Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3634 100 mm dia sand cast iron S & S heel rest
sanitary bend each 1 233.00 233.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 246.52
Add 1% for water charges 2.47
TOTAL 248.99
Add for contractor’s profit and overheads
@15% 37.35
Cost of 1 no. 286.33
Say

17.40 Providing and fixing heel rest sanitary bend


17.40.2 75 mm
17.40.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1666 75 mm sand cast iron heel rest bend each 1 165.00 165.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 175.79
Add 1% for water charges 1.76
TOTAL 177.55
Add for contractor’s profit and overheads
@15% 26.63
Cost of 1 no. 204.18
Say

17.40 Providing and fixing heel rest sanitary bend


17.40.2 75 mm
17.40.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3635 75 mm dia sand cast iron S & S heel rest
sanitary bend each 1 204.00 204.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 214.79
Add 1% for water charges 2.15
TOTAL 216.94
Add for contractor’s profit and overheads
@15% 32.54
Cost of 1 no. 249.48
Say

17.41 Providing and fixing double equal junction of required degree with access door, insertion rubber
washer 3 mm thick, bolts and nuts complete :
17.41.1 100x100x100x100mm
17.41.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1637 S.C.I. double equal junctions
100x100x100x100 mm dia with access door
each 1 417.00 417.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.39 1.00 13.39
TOTAL
442.39
Add 1% for water charges 4.42
TOTAL 446.81
Add for contractor’s profit and overheads
@15% 67.02
Cost of 1 no. 513.84
Say

17.41 Providing and fixing double equal junction of required degree with access door, insertion rubber
washer 3 mm thick, bolts and nuts complete :
17.41.1 100x100x100x100mm
17.41.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3654 S.C.I. S&S double equal junctions with
access door 100x100x100x100 m m. each 1 502.00 502.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.39 1.00 13.39
TOTAL
527.39
Add 1% for water charges 5.27
TOTAL 532.66
Add for contractor’s profit and overheads
@15% 79.90
Cost of 1 no. 612.56
Say
17.41 Providing and fixing double equal junction of required degree with access door, insertion rubber
washer 3 mm thick, bolts and nuts complete :
17.41.2 75x75x75x75 mm
17.41.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1636 S.C.I. double equal junctions 75x75x75x75
mm dia with access door each 1 333.00 333.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 352.79
Add 1% for water charges 3.53
TOTAL 356.32
Add for contractor’s profit and overheads
@15% 53.45
Cost of 1 no. 409.77
Say

17.41 Providing and fixing double equal junction of required degree with access door, insertion rubber
washer 3 mm thick, bolts and nuts complete :
17.41.2 75x75x75x75 mm
17.41.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3655 S.C.I. S&S double equal junctions with
access door 75x75x75x75 mm. each 1 400.00 400.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 419.79
Add 1% for water charges 4.20
TOTAL 423.99
Add for contractor’s profit and overheads
@15% 63.60
Cost of 1 no. 487.59
Say

17.42 Providing and fixing double equal plain junction of required degree.
17.42.1 100x100x100x100 mm
17.42.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1634 S.C.I. plain double equal
junctions100x100x100x100 mm dia
each 1 394.00 394.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 407.52
Add 1% for water charges 4.08
TOTAL 411.60
Add for contractor’s profit and overheads
@15% 61.74
Cost of 1 no. 473.33
Say

17.42 Providing and fixing double equal plain junction of required degree.
17.42.1 100x100x100x100 mm
17.42.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3650 S.C.I. S&S double equal
junctions100x100x100x100 mm each 1 467.00 467.00
Labour:

9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 480.52
Add 1% for water charges 4.81
TOTAL 485.33
Add for contractor’s profit and overheads
@15% 72.80
Cost of 1 no. 558.12
Say

17.42 Providing and fixing double equal plain junction of required degree.
17.42.2 75x75x75x75 mm
17.42.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1633 S.C.I. plain double equal junctions
75x75x75x75 mm dia each 1 296.00 296.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 306.79
Add 1% for water charges 3.07
TOTAL 309.86
Add for contractor’s profit and overheads
@15% 46.48
Cost of 1 no. 356.34
Say

17.42 Providing and fixing double equal plain junction of required degree.
17.42.2 75x75x75x75 mm
17.42.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3651 S.C.I. S&S double equal junctions
75x75x75x75 mm each 1 373.00 373.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 383.79
Add 1% for water charges 3.84
TOTAL 387.63
Add for contractor’s profit and overheads
@15% 58.14
Cost of 1 no. 445.77
Say

17.43 Providing and fixing single equal plain junction of required degree with access door, insertion
rubber washer 3 mm thick, bolts and nuts complete.
17.43.1 100x100x100 mm
17.43.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1631 S.C.I. single equal junctions 100x100x100
mm dia with access door. each 1 297.00 297.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 322.52
Add 1% for water charges 3.23
TOTAL 325.75
Add for contractor’s profit and overheads
@15% 48.86
Cost of 1 no. 374.61
Say

17.43 Providing and fixing single equal plain junction of required degree with access door, insertion
rubber washer 3 mm thick, bolts and nuts complete.
17.43.1 100x100x100 mm
17.43.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3644 S.C.I. S&S single equal junctions with
access door 100x100x100 mm each 1 396.00 396.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 421.52
Add 1% for water charges 4.22
TOTAL 425.74
Add for contractor’s profit and overheads
@15% 63.86
Cost of 1 no. 489.60
Say

17.43 Providing and fixing single equal plain junction of required degree with access door, insertion
rubber washer 3 mm thick, bolts and nuts complete.
17.43.2 75x75x75 mm
17.43.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1630 S.C.I. single equal junctions 75x75x75 mm
dia with access door. each 1 224.00 224.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 243.79
Add 1% for water charges 2.44
TOTAL 246.23
Add for contractor’s profit and overheads
@15% 36.93
Cost of 1 no. 283.16
Say

17.43 Providing and fixing single equal plain junction of required degree with access door, insertion
rubber washer 3 mm thick, bolts and nuts complete.
17.43.2 75x75x75 mm
17.43.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3645 S.C.I. S&S single equal junctions with
access door 75x75x75 mm each 1 294.00 294.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 313.79
Add 1% for water charges 3.14
TOTAL 316.93
Add for contractor’s profit and overheads
@15% 47.54
Cost of 1 no. 364.47
Say
17.44 Providing and fixing single equal plain junction of required degree
17.44.1 100x100x100 mm
17.44.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1628 S.C.I. plain single equal
junctions100x100x100 mm dia each 1 265.00 265.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 278.52
Add 1% for water charges 2.79
TOTAL 281.31
Add for contractor’s profit and overheads
@15% 42.20
Cost of 1 no. 323.50
Say

17.44 Providing and fixing single equal plain junction of required degree
17.44.1 100x100x100 mm
17.44.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3640 S.C.I. S&S single equal
junctions100x100x100 mm each 1 367.00 367.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 380.52
Add 1% for water charges 3.81
TOTAL 384.33
Add for contractor’s profit and overheads
@15% 57.65
Cost of 1 no. 441.97
Say

17.44 Providing and fixing single equal plain junction of required degree
17.44.2 75x75x75 mm
17.44.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1627 S.C.I. plain single equal junctions 75x75x75
mm dia each 1 205.00 205.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 215.79
Add 1% for water charges 2.16
TOTAL 217.95
Add for contractor’s profit and overheads
@15% 32.69
Cost of 1 no. 250.64
Say

17.44 Providing and fixing single equal plain junction of required degree:
17.44.2 75x75x75 mm
17.44.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3641 S.C.I. S&S single equal junctions75x75x75
mm each 1 276.00 276.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 286.79
Add 1% for water charges 2.87
TOTAL 289.66
Add for contractor’s profit and overheads
@15% 43.45
Cost of 1 no. 333.11
Say

17.45 Providing and fixing double unequal junction of required degree with access door, insertion
rubber washer 3 mm thick, bolts and nuts complete :
17.45.1 100x100x75x75 mm
17.45.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1662 Sand cast iron S&S double unequal
junctions: 100x100x75x75 mm dia with
access door
each 1 453.00 453.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 478.52
Add 1% for water charges 4.79
TOTAL 483.31
Add for contractor’s profit and overheads
@15% 72.50
Cost of 1 no. 555.80
Say

17.45 Providing and fixing double unequal junction of required degree with access door, insertion
rubber washer 3 mm thick, bolts and nuts complete :
17.45.1 100x100x75x75 mm
17.45.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3674 S.C.I. S&S double unequal junctions with
access door 100x100x75x75mm each 1 700.00 700.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 725.52
Add 1% for water charges 7.26
TOTAL 732.78
Add for contractor’s profit and overheads
@15% 109.92
Cost of 1 no. 842.69
Say

17.46 Providing and fixing double unequal plain junction of required degree:
17.46.1 100x100x75x75 mm
17.46.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1659 Sand cast iron S&S plain double unequal
junctions : 100x100x75x75 mm dia
each 1 423.00 423.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 436.52
Add 1% for water charges 4.37
TOTAL 440.89
Add for contractor’s profit and overheads
@15% 66.13
Cost of 1 no. 507.02
Say

17.46 Providing and fixing double unequal plain junction of required degree:
17.46.1 100x100x75x75 mm
17.46.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3670 S.C.I. S&S double unequal
junctions100x100x75x75 mm each 639.00
each 1 639.00 639.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 652.52
Add 1% for water charges 6.53
TOTAL 659.05
Add for contractor’s profit and overheads
@15% 98.86
Cost of 1 no. 757.90
Say

17.47 Providing and fixing single unequal junction of required degree with access door, insertion
rubber washer 3 m m thick, bolts and nuts complete :
17.47.1 100x100x75 mm
17.47.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1656 Sand cast iron S&S single unequal junctions:
100x100x75 mm dia with access door
each 1 321.00 321.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 346.52
Add 1% for water charges 3.47
TOTAL 349.99
Add for contractor’s profit and overheads
@15% 52.50
Cost of 1 no. 402.48
Say

17.47 Providing and fixing single unequal junction of required degree with access door, insertion
rubber washer 3 m m thick, bolts and nuts complete :
17.47.1 100x100x75 mm
17.47.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3664 S.C.I. S&S single unequal junctions with
access door 100x100x75 mm each 1 523.00 523.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 548.52
Add 1% for water charges 5.49
TOTAL 554.01
Add for contractor’s profit and overheads
@15% 83.10
Cost of 1 no. 637.11
Say

17.48 Providing and fixing single unequal plain junction of required degree :
17.48.1 100x100x75 mm
17.48.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1653 Sand cast iron S&S plain single unequal
junctions : 100x100x75 mm dia each 1 288.00 288.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 301.52
Add 1% for water charges 3.02
TOTAL 304.54
Add for contractor’s profit and overheads
@15% 45.68
Cost of 1 no. 350.22
Say

17.48 Providing and fixing single unequal plain junction of required degree
17.48.1 100x100x75 mm
17.48.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3660 S.C.I. S&S single unequal
junctions100x100x75 mm each 1 461.00 461.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 474.52
Add 1% for water charges 4.75
TOTAL 479.27
Add for contractor’s profit and overheads
@15% 71.89
Cost of 1 no. 551.15
Say

17.49 Providing and fixing double equal plain invert branch of required degree:
17.49.1 100x100x100x100mm
17.49.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1673 S.C.I. double equal invert branch of required
degree 100x100x100x100 mm dia
each 1 422.00 422.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 435.52
Add 1% for water charges 4.36
TOTAL 439.88
Add for contractor’s profit and overheads
@15% 65.98
Cost of 1 no. 505.86
Say

17.49 Providing and fixing double equal plain invert branch of required degree:
17.49.1 100x100x100x100mm
17.49.1.2 Sand cast iron S&S as per IS 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3685 S.C.I. S&S double equal invert branch of
required degree 100x100x100x100 mm dia
each 1 414.00 414.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 427.52
Add 1% for water charges 4.28
TOTAL 431.80
Add for contractor’s profit and overheads
@15% 64.77
Cost of 1 no. 496.56
Say

17.49 Providing and fixing double equal plain invert branch of required degree:
17.49.2 75x75x75x75 mm
17.49.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1672 S.C.I. double equal invert branch of required
degree 75x75x75x75 mm dia each 1 314.00 314.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 324.79
Add 1% for water charges 3.25
TOTAL 328.04
Add for contractor’s profit and overheads
@15% 49.21
Cost of 1 no. 377.24
Say

17.49 Providing and fixing double equal plain invert branch of required degree:
17.49.2 75x75x75x75 mm
17.49.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3686 S.C.I. S&S double equal invert branch of
required degree 75x75x75x75 mm dia
each 1 334.00 334.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 344.79
Add 1% for water charges 3.45
TOTAL 348.24
Add for contractor’s profit and overheads
@15% 52.24
Cost of 1 no. 400.47
Say

17.50 Providing and fixing single equal plain invert branch of required degree:
17.50.1 100x100x100 mm
17.50.1.1 Sand cast iron S&S as per iron 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1670 S.C.I. single equal invert branch of
required degree 100x100x100 mm dia each 1 321.00 321.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 334.52
Add 1% for water charges 3.35
TOTAL 337.87
Add for contractor’s profit and overheads
@15% 50.68
Cost of 1 no. 388.54
Say

17.50 Providing and fixing single equal plain invert branch of required degree:
17.50.1 100x100x100 mm
17.50.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3681 S.C.I. S&S single equal invert branch of
required degree 100x100x100 mm dia
each 1 325.00 325.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 338.52
Add 1% for water charges 3.39
TOTAL 341.91
Add for contractor’s profit and overheads
@15% 51.29
Cost of 1 no. 393.19
Say

17.50 Providing and fixing single equal plain invert branch of required degree:
17.50.2 75x75x75 mm
17.50.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1669 S.C.I. single equal invert branch of
required degree 75x75x75 mm dia each 1 239.00 239.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 249.79
Add 1% for water charges 2.50
TOTAL 252.29
Add for contractor’s profit and overheads
@15% 37.84
Cost of 1 no. 290.13
Say

17.50 Providing and fixing single equal plain invert branch of required degree:
17.50.2 75x75x75 mm
17.50.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3682 S.C.I. S&S single equal invert branch of
required degree 75x75x75 mm dia each 1 247.00 247.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 257.79
Add 1% for water charges 2.58
TOTAL 260.37
Add for contractor’s profit and overheads
@15% 39.06
Cost of 1 no. 299.42
Say

17.51 Providing and fixing double unequal invert branch of required degree
17.51.1 100x100x75x75 mm
17.51.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1677 S.C.I. double unequal invert branch of
required degree 100x100x75x75 mm dia
each 1 458.00 458.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 471.52
Add 1% for water charges 4.72
TOTAL 476.24
Add for contractor’s profit and overheads
@15% 71.44
Cost of 1 no. 547.67
Say

17.51 : Providing and fixing double unequal invert branch of required degree
17.51.1: 100x100x75x75 mm
17.51.1.2 :Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3695 S.C.I. S&S double unequal invert branch of
required degree 100x100x75x75 mm
each 1 574.00 574.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 587.52
Add 1% for water charges 5.88
TOTAL 593.40
Add for contractor’s profit and overheads
@15% 89.01
Cost of 1 no. 682.40
Say

17.52 : Providing and fixing single unequal plain invert branch of required degree :
17.52.1: 100x100x75 mm
17.52.1.1: Sand cast iron S& S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1674 S.C.I. single unequal invert branch of
required degree 100x100x75 mm dia each 1 382.00 382.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 395.52
Add 1% for water charges 3.96
TOTAL 399.48
Add for contractor’s profit and overheads
@15% 59.92
Cost of 1 no. 459.40
Say

17.52 : Providing and fixing single unequal plain invert branch of required degree :
17.52.1: 100x100x75 mm
17.52.1.2 : Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3690 S.C.I. S&S single unequal invert branch of
required degree 100x100x75 mm dia each 1 422.00 422.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 435.52
Add 1% for water charges 4.36
TOTAL 439.88
Add for contractor’s profit and overheads
@15% 65.98
Cost of 1 no. 505.86
Say

17.53 : Providing and fixing sand cast iron S&S offsets as per IS: 1729
17.53.1: 76 mm offsets
17.53.1.1: With 75 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3746 S.C.I. S&S, 76 mm offset for75 mm dia
pipe each 1 126.00 126.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 136.79
Add 1% for water charges 1.37
TOTAL 138.16
Add for contractor’s profit and overheads
@15% 20.72
Cost of 1 no. 158.88
Say

17.53 : Providing and fixing sand cast iron S&S offsets as per IS: 1729
17.53.1: 76 mm offsets
17.53.1.2: With 100 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3747 S.C.I. S&S, 76 mm offset for100 mm dia
pipe each 1 220.00 220.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 230.79
Add 1% for water charges 2.31
TOTAL 233.10
Add for contractor’s profit and overheads
@15% 34.96
Cost of 1 no. 268.06
Say

17.53 : Providing and fixing sand cast iron S&S offsets as per IS: 1729
17.53.2 : 114 mm offsets
17.53.2.1: With 75 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3712 S.C.I. S&S, 114 mm offset for75 mm dia
pipe each 1 220.00 220.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 230.79
Add 1% for water charges 2.31
TOTAL 233.10
Add for contractor’s profit and overheads
@15% 34.96
Cost of 1 no. 268.06
Say

17.53 : Providing and fixing sand cast iron S&S offsets as per IS: 1729
17.53.2 : 114 mm offsets
17.53.2.2 : With 100 mm dia. Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3713 S.C.I. S&S, 114 mm offset for 100 mm dia
pipe each 1 289.00 289.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 302.52
Add 1% for water charges 3.03
TOTAL 305.55
Add for contractor’s profit and overheads
@15% 45.83
Cost of 1 no. 351.38
Say

17.53 : Providing and fixing sand cast iron S&S offsets as per IS: 1729
17.53.3 : 152 mm offsets
17.53.3.1: With 75 mm dia. Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3716 S.C.I. S&S, 152 mm offset for75 mm dia
pipe each 1 275.00 275.00
9,999 Carriage of materials and fixing charges L.S. 17.94 1.00 17.94
TOTAL 292.94
Add 1% for water charges 2.93
TOTAL 295.87
Add for contractor’s profit and overheads
@15% 44.38
Cost of 1 no. 340.25
Say

17.53 : Providing and fixing sand cast iron S&S offsets as per IS: 1729
17.53.3 : 152 mm offsets
17.53.3.2 : With 100 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3717 S.C.I. S&S, 152 mm offset for 100 mm dia
pipe each 1 361.00 361.00
9,999 Carriage of materials and fixing charges L.S. 17.94 1.00 17.94
TOTAL 378.94
Add 1% for water charges 3.79
TOTAL 382.73
Add for contractor’s profit and overheads
@15% 57.41
Cost of 1 no. 440.14
Say

17.54 : Providing and fixing sand cast iron S&S offsets as per IS: 3989.
17.54.1 : 75 mm offsets
17.54.1.1: With 75 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3699 S.C.I. S&S, 75 mm offset for75 mm dia
pipe each 1 179.00 179.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 189.79
Add 1% for water charges 1.90
TOTAL 191.69
Add for contractor’s profit and overheads
@15% 28.75
Cost of 1 no. 220.44
Say

17.54 Providing and fixing sand cast iron S&S offsets as per IS: 3989.
17.54.2 150 mm offsets
17.54.2.1 With 75 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3707 S.C.I. S&S, 150 mm offset for75 mm dia
pipe each 1 223.00 223.00
9,999 Carriage of materials and fixing charges L.S. 16.12 1.00 16.12
TOTAL 239.12
Add 1% for water charges 2.39
TOTAL 241.51
Add for contractor’s profit and overheads
@15% 36.23
Cost of 1 no. 277.74
Say

17.54 Providing and fixing sand cast iron S&S offsets as per IS: 3989.
17.54.2 150 mm offsets
17.54.2.2 With 100 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3708 S.C.I. S&S, 150 mm offset for 100 mm dia
pipe each 1 306.00 306.00
9,999 Carriage of materials and fixing charges L.S. 16.12 1.00 16.12
TOTAL 322.12
Add 1% for water charges 3.22
TOTAL 325.34
Add for contractor’s profit and overheads
@15% 48.80
Cost of 1 no. 374.14
Say

17.55 Providing and fixing door piece, insertion rubber washer 3mm thick, bolts & nuts complete :
17.55.1 100mm
17.55.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1683 S.C.I. door pieces 100 mm dia each 1 291.00 291.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 316.52
Add 1% for water charges 3.17
TOTAL 319.69
Add for contractor’s profit and overheads
@15% 47.95
Cost of 1 no. 367.64
Say

17.55 Providing and fixing door piece, insertion rubber washer 3mm thick, bolts & nuts complete :
17.55.1 100 mm
17.55.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3728 S.C.I S&S door pieces 100 mm dia each 1 230.00 230.00
1374 Insertion rubber washer 3 mm thick each 1 12.00 12.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 255.52
Add 1% for water charges 2.56
TOTAL 258.08
Add for contractor’s profit and overheads
@15% 38.71
Cost of 1 no. 296.79
Say
17.55 Providing and fixing door piece, insertion rubber washer 3mm thick, bolts & nuts complete :
17.55.2 75 mm
17.55.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1682 S.C.I. door pieces 75 mm dia each 1 211.00 211.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 230.79
Add 1% for water charges 2.31
TOTAL 233.10
Add for contractor’s profit and overheads
@15% 34.96
Cost of 1 no. 268.06
Say

17.55 Providing and fixing door piece, insertion rubber washer 3mm thick, bolts & nuts complete :
17.55.2 75 mm
17.55.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3729 S.C.I S&S door pieces 75 mm dia each 1 176.00 176.00
1373 Insertion rubber washer 3 mm thick each 1 9.00 9.00
Labour:
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 195.79
Add 1% for water charges 1.96
TOTAL 197.75
Add for contractor’s profit and overheads
@15% 29.66
Cost of 1 no. 227.41
Say

17.56 Providing and fixing terminal guard:


17.56.1 100 mm
17.56.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1640 Slotted cowl (terminal guard ) 100 mm dia
each 1 152.00 152.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 165.52
Add 1% for water charges 1.66
TOTAL 167.18
Add for contractor’s profit and overheads
@15% 25.08
Cost of 1 no. 192.25
Say

17.56 Providing and fixing terminal guard:


17.56.1 100 mm
17.56.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3733 S.C.I S&S, Slotted Cowl (Terminal Guard)
100 mm each 1 154.00 154.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 167.52
Add 1% for water charges 1.68
TOTAL 169.20
Add for contractor’s profit and overheads
@15% 25.38
Cost of 1 no. 194.57
Say

17.56 Providing and fixing terminal guard:


17.56.2 75 mm
17.56.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1640 Slotted cowl (terminal guard ) 75 mm dia
each 1 109.00 109.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 119.79
Add 1% for water charges 1.20
TOTAL 120.99
Add for contractor’s profit and overheads
@15% 18.15
Cost of 1 no. 139.14
Say

17.56 Providing and fixing terminal guard:


17.56.2 75 mm
17.56.2.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3734 S.C.I S&S, Slotted Cowl (Terminal Guard) 75
mm each 1 142.00 142.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 152.79
Add 1% for water charges 1.53
TOTAL 154.32
Add for contractor’s profit and overheads
@15% 23.15
Cost of 1 no. 177.47
Say

17.57 Providing and fixing collar:


17.57.1 100 mm
17.57.1.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1686 S.C.I. collar 100 mm dia each 1 110.00 110.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 123.52
Add 1% for water charges 1.24
TOTAL 124.76
Add for contractor’s profit and overheads
@15% 18.71
Cost of 1 no. 143.47
Say

17.57 Providing and fixing collar:


17.57.1 100 mm
17.57.1.2 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3738 S.C.I S&S, collars 100 mm each 1 161.00 161.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 174.52
Add 1% for water charges 1.75
TOTAL 176.27
Add for contractor’s profit and overheads
@15% 26.44
Cost of 1 no. 202.70
Say

17.57 Providing and fixing collar:


17.57.2 75 mm
17.57.2.1 Sand cast iron S&S as per IS - 1729
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1685 S.C.I. collar 75 mm dia each 1 82.00 82.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 92.79
Add 1% for water charges 0.93
TOTAL 93.72
Add for contractor’s profit and overheads
@15% 14.06
Cost of 1 no. 107.78
Say

17.57 Providing and fixing collar:


17.57.2 75 mm
17.57.2.2 Sand cast iron S&S as per IS- 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
3739 S.C.I S&S, collars 75 mm each 1 115.00 115.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 125.79
Add 1% for water charges 1.26
TOTAL 127.05
Add for contractor’s profit and overheads
@15% 19.06
Cost of 1 no. 146.11
Say

17.58 Providing lead caulked joints to sand cast iron/centrifugally cast (spun) iron pipes and
fittings of diameter:
17.58.1 100mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 joint
Materials:
1397 Pig lead kilogram 0.98 58.00 56.84
1881 Spun yarn kilogram 0.11 30.00 3.30
Labour:
116 Fitter (grade 1) Day 0.06 270.00 16.20
116 Astt. Fitter Day 0.06 223.00 13.38
114 Beldar Day 0.12 207.00 24.84
9,999 Kerosene oil, fuel and other sundries L.S. 13.52 1.00 13.52
9,999 Carriage of material L.S. 1.43 1.00 1.43
TOTAL 129.51
Add 1% for water charges 1.30
TOTAL 130.81
Add for contractor’s profit and overheads
@15% 19.62
Cost of 1 joint 150.43
Say

17.58 Providing lead caulked joints to sand cast iron/centrifugally cast (spun) iron pipes and
fittings of diameter:
17.58.2 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 joint
Materials:
1397 Pig lead kilogram 0.88 58.00 51.04
1881 Spun yarn kilogram 0.09 30.00 2.70
Labour:
116 Fitter (grade 1) Day 0.05 270.00 13.50
116 Astt. Fitter Day 0.05 223.00 11.15
114 Beldar Day 0.09 207.00 18.63
9,999 Kerosene oil, fuel and other sundries L.S. 10.79 1.00 10.79
9,999 Carriage of material L.S. 1.43 1.00 1.43
TOTAL 109.24
Add 1% for water charges 1.09
TOTAL 110.33
Add for contractor’s profit and overheads
@15% 16.55
Cost of 1 joint 126.88
Say

17.58 Providing lead caulked joints to sand cast iron/centrifugally cast (spun) iron pipes and
fittings of diameter:
17.58.3 50 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 joint
Materials:
1397 Pig lead kilogram 0.77 58.00 44.66
1881 Spun yarn kilogram 0.06 30.00 1.80
Labour:
116 Fitter (grade 1) Day 0.04 270.00 10.80
116 Astt. Fitter Day 0.05 223.00 11.15
114 Beldar Day 0.05 207.00 10.35
9,999 Kerosene oil, fuel and other sundries L.S. 6.76 1.00 6.76
9,999 Carriage of material L.S. 1.43 1.00 1.43
TOTAL 86.95
Add 1% for water charges 0.87
TOTAL 87.82
Add for contractor’s profit and overheads
@15% 13.17
Cost of 1 joint 100.99
Say

17.59 Providing and fixing M.S. stays and clamps for sand cast iron/centrifugally cast (spun)
iron pipes of diameter :
17.59.1 100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1330 Clamps and M.S. stays including bolts and
nuts for 100 mm pipe each 1 28.00 28.00
9,999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 41.52
Add 1% for water charges 0.42
TOTAL 41.94
Add for contractor’s profit and overheads
@15% 6.29
Cost of 1 no. 48.23
Say

17.59 Providing and fixing M.S. stays and clamps for sand cast iron/centrifugally cast (spun)
iron pipes of diameter :
17.59.2 75 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1335 Clamps and M.S. stays including bolts and
nuts for 75 mm pipe each 1 25.00 25.00
9,999 Carriage of materials and fixing charges L.S. 10.79 1.00 10.79
TOTAL 35.79
Add 1% for water charges 0.36
TOTAL 36.15
Add for contractor’s profit and overheads
@15% 5.42
Cost of 1 no. 41.57
Say

17.59 Providing and fixing M.S. stays and clamps for sand cast iron/centrifugally cast (spun)
iron pipes of diameter :
17.59.3 50 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1334 Clamps and M.S. stays including bolts and
nuts for 50 mm pipe each 1 20.00 20.00
9,999 Carriage of materials and fixing charges L.S. 9.49 1.00 9.49
TOTAL 29.49
Add 1% for water charges 0.29
TOTAL 29.78
Add for contractor’s profit and overheads
@15% 4.47
Cost of 1 no. 34.25
Say

17.60 Providing and fixing trap of self cleansing design with screwed down or hinged
grating with or without vent arm complete, including cost of cutting and making good the
walls and floors :
17.60.1 100 mm inlet and 100 mm outlet
17.60.1.1 Sand cast iron S&S as per IS: 3989.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7808 Centrifugally cast (spun) iron S&S 100 mm
inlet and 100 mm outlet each 1 309.00 309.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of material L.S. 2.73 1.00 2.73
9,999 Cement, sand and grit etc. L.S. 13.52 1.00 13.52
TOTAL 563.75
Add 1% for water charges 5.64
TOTAL 569.39
Add for contractor’s profit and overheads
@15% 85.41
Cost of 1 no 654.80
Say

17.60 Providing and fixing trap of self cleansing design with screwed down or hinged
grating with or without vent arm complete, including cost of cutting and making good the
walls and
17.60.1 floors
100 mm :inlet and 100 mm outlet
17.60.1.2 Sand Cast Iron S&S as per IS: 1729.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1897 100 mm S.C.I. trap with 100 mm inlet and
100 mm outlet each 1 221.00 221.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of material L.S. 2.73 1.00 2.73
9,999 Cement, sand and grit etc. L.S. 13.52 1.00 13.52
TOTAL 475.75
Add 1% for water charges
4.76
TOTAL 480.51
Add for contractor’s profit and overheads
@15% 72.08
Cost of 1 no 552.58
Say

17.60 Providing and fixing trap of self cleansing design with screwed down or hinged
grating with or without vent arm complete, including cost of cutting and making good the
walls and
17.60.2 floors
100 mm :inlet and 75 mm outlet
17.60.2.1 Sand cast iron S&S as per IS - 3989
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7809 Centrifugally cast (spun) iron S&S 100 mm
inlet and 75 mm outlet each 1 334.00 334.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00

114 Beldar Day 0.5 207.00 103.50


9,999 Carriage of material L.S. 2.73 1.00 2.73
9,999 Cement, sand and grit etc. L.S. 13.52 1.00 13.52
TOTAL 588.75
Add 1% for water charges 5.89
TOTAL 594.64
Add for contractor’s profit and overheads
@15% 89.20
Cost of 1 no 683.83
Say

17.60 Providing and fixing trap of self cleansing design with screwed down or hinged
grating with or without vent arm complete, including cost of cutting and making good the
walls and
17.60.2 floors
100 mm :inlet and 75 mm outlet
17.60.2.2 Sand Cast Iron S&S as per IS- 1729.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1898 100 mm S.C.I. trap with 100 mm inlet and
75 mm outlet each 1 164.00 164.00
Labour:
123 Mason ist class Day 0.5 270.00 135.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of material L.S. 2.73 1.00 2.73
9,999 Cement, sand and grit etc. L.S. 13.52 1.00 13.52
TOTAL 418.75
Add 1% for water charges 4.19
TOTAL 422.94
Add for contractor’s profit and overheads
@15% 63.44
Cost of 1 no 486.38
Say

17.61 Cutting chases in brick masonry walls for following diameter sand cast
iron/centrifiigally cast (spun) iron pipes and making good the same with cement concrete
1:3:6 ( 1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size ) including
necessary plaster and pointing in cement mortar 1:4 (1 cement: 4 coarse sand):
17.61.1 100mmdia.
Code Description Unit Quantity Rate Amount
Details of cost for 1 metre
Materials:
Cement concrete 1:3:6 (1 cement :3
coarse sand :6 graded stone aggregate ) (Rate
as per item no. 4.2.5) cum 0.022 3828.42 84.23
Labour:
123 Mason ist class Day 0.14 270.00 37.80
114 Beldar Day 0.27 207.00 55.89
9,999 Carriage of material L.S. 4.16 1.00 4.16
9,999 Plastering in cement mortar L.S. 10.4 1.00 10.40
TOTAL 192.48
Add 1% for water charges except A

1.08
TOTAL 193.56
Add for contractor’s profit and overheads
@15% except on A 16.40
Cost of 1 metre 209.96
Say

17.61 Cutting chases in brick masonry walls for following diameter sand cast
iron/centrifiigally cast (spun) iron pipes and making good the same with cement concrete
1:3:6 ( 1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size ) including
necessary plaster and pointing in cement mortar 1:4 (1 cement: 4 coarse sand):
17.61.2 75mmdia.
Code Description Unit Quantity Rate Amount
Details of cost for 1 metre
Materials:
Cement concrete 1:3:6 (1 cement :3
coarse sand :6 graded stone aggregate ) (Rate
as per item no. 4.2.5) cum 0.015 3828.42 57.43
Labour:
123 Mason ist class Day 0.1 270.00 27.00
114 Beldar Day 0.2 207.00 41.40
9,999 Carriage of material L.S. 3.51 1.00 3.51
9,999 Plastering in cement mortar L.S. 7.8 1.00 7.80
TOTAL 137.14
Add 1% for water charges except A 0.80
TOTAL 137.93
Add for contractor’s profit and overheads
@15% except on A 12.08
Cost of 1 metre 150.01
Say

17.61 Cutting chases in brick masonry walls for following diameter sand cast
iron/centrifiigally cast (spun) iron pipes and making good the same with cement concrete
1:3:6 ( 1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size ) including
necessary plaster and pointing in cement mortar 1:4 (1 cement: 4 coarse sand):
17.61.3 50mmdia.
Code Description Unit Quantity Rate Amount
Details of cost for 1 metre
Materials:
Cement concrete 1:3:6 (1 cement :3
coarse sand :6 graded stone aggregate ) (Rate
as per item no. 4.2.5) cum 0.008 3828.42 30.63
Labour:
123 Mason ist class Day 0.07 270.00 18.90
114 Beldar Day 0.14 207.00 28.98
9,999 Carriage of material L.S. 2.73 1.00 2.73
9,999 Plastering in cement mortar L.S. 5.2 1.00 5.20
TOTAL 86.44
Add 1% for water charges except A 0.56
TOTAL 87.00
Add for contractor’s profit and overheads
@15% except on A 8.46
Cost of 1 metre 95.45
Say

17.62 Painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and white
paint over a coat of zinc chromate yellow primer (of approved quality ) on the outside
surface of the cistern flush pipe, other fittings, etc. complete for new work.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cistern with fittings
Materials:
828 Anticorrosive bituminous paint (black) litre 0.23 52.00 11.96
834 Synthetic enamel paint in all shades except
black or chocolate shade litre 0.4 170.00 68.00
4202 Red oxide Zinc chromate primer litre 0.2 58.00 11.60
Labour:
131 Painter Day 0.25 180.00 45.00
114 Beldar Day 0.5 207.00 103.50
9,999 Carriage of material L.S. 1.43 1.00 1.43
9,999 Sundries (brush sand paper etc.) L.S. 6.76 1.00 6.76
TOTAL 248.25
Add 1% for water charges 2.48
TOTAL 250.73
Add for contractor’s profit and overheads
@15% 37.61
Cost of 1 no 288.34
Say

17.63 Re-painting C.I. cistern with bitumastic or any other anti-corrosive paint inside and
white paint on the outside surface of the cistern, flush pipe, other fittings, etc. complete
including polishing of wooden seat and lid and cleaning of W.C. pan with acid wherever
necessary.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cistern with fittings
Materials:
828 Anticorrosive bituminous paint (black) litre 0.23 52.00 11.96
834 Synthetic enamel paint in all shades except
black or chocolate shade litre 0.2 170.00 34.00
Labour:
131 Painter Day 0.2 180.00 36.00
114 Beldar Day 0.25 207.00 51.75
9,999 Polishing of wooden seat and cleaning of L.S. 20.67
W.C. pan with acid 1.00 20.67
9,999 Sundries and carriage of materials L.S. 7.15 1.00 7.15
TOTAL 161.53
Add 1% for water charges 1.62
TOTAL 163.15
Add for contractor’s profit and overheads
@15% 24.47
Cost of 1 no 187.62
Say

17.64 Repainting C.I. cistern with synthetic enamel paint of approved colour brand and
manufacture on the outside surface of cistern flush pipe, other fittings etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cistern with fittings
Materials:
834 Synthetic enamel paint in all shades except
black or chocolate shade litre 0.2 170.00 34.00
Labour:
131 Painter Day 0.09 180.00 16.20
114 Beldar Day 0.12 207.00 24.84
9,999 Sundries and carriage of materials L.S. 3.64 1.00 3.64
TOTAL 78.68
Add 1% for water charges 0.79
TOTAL 79.47
Add for contractor’s profit and overheads
@15% 11.92
Cost of 1 no 91.39
Say

17.65 Painting sand cast iron/ centrifugally cast (spun) iron soil, waste vent pipes and fittings
with paint of any colour such as chocolate grey, or buff etc. over a coat of primer (of
approved quality)
17.65.1 100 for new pipe
mm diameter work :
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
Priming coat (Rate as per item no. 13.50.3
of S.H. finishing) sqm 3.46 15.74 54.46
Painting two coats with paint of any colour
such as chocalate, grey or buff etc. (Rate
as per item no 13.61 of S.H. finishing )
sqm 3.46 49.68 171.91
9,999 Add for delay L.S. 17.16 1.00 17.16
TOTAL 243.53
Add 1% for water charges except A 0.17
TOTAL 243.70
Add for contractor’s profit and overheads
@15% except on A 2.60
Cost of 10 metre 246.30
Cost of 1 metre 24.63
Say

17.65 Painting sand cast iron/ centrifugally cast (spun) iron soil, waste vent pipes and fittings
with paint of any colour such as chocolate grey, or buff etc. over a coat of primer (of
approved
17.65.2 quality)
75 mmfor new work
diameter pipe:
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
Priming coat (Rate as per item no. 13.50.3
of S.H. finishing) sqm 2.6 15.74 40.92
Painting two coats with paint of any colour
such as chocalate, grey or buff etc. (Rate
as per item no 13.61 of S.H. finishing )
sqm 2.6 49.68 129.18
9,999 Add for delay L.S. 15.21 1.00 15.21
TOTAL 185.31
Add 1% for water charges except A 0.15
TOTAL 185.46
Add for contractor’s profit and overheads
@15% except on A 2.30
Cost of 10 metre 187.77
Cost of 1 metre 18.78
Say

17.66 Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes
and fittings with paint of any colour such as chocolate, grey or buff etc :
17.66.1 100 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
Painting one coat with paint of any colour
such as chocolate,grey or buff etc. (Rate as
per item no 14.54.1) sqm 3.46 22.85 79.06
9,999 Add for delay L.S. 12.22 1.00 12.22
TOTAL 91.28
Add 1% for water charges except A 0.12
TOTAL 91.40
Add for contractor’s profit and overheads
@15% except on A 1.85
Cost of 10 metre 93.25
Cost of 1 metre 9.33
Say

17.66 Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes
and fittings with paint of any colour such as chocolate, grey or buff etc :
17.66.2 75 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
Painting one coat with paint of any colour sqm 2.577
such as chocolate,grey or buff etc. (Rate as
per item no 14.54.1) 31.94 82.30
9,999 Add for delay L.S. 9.49 1.00 9.49
TOTAL 91.79
Add 1% for water charges except A 0.09
TOTAL 91.89
Add for contractor’s profit and overheads
@15% except on A 1.44
Cost of 10 metre 93.32
Cost of 1 metre 9.33
Say

17.67 Repainting bath tub of size 1700x730x430mm with enamel paint.


Code Description Unit Quantity Rate Amount
Details of cost for 1 tub
Materials:
830 Enamel paint litre 0.9 170.00 153.00
Labour:
131 Painter Day 0.25 180.00 45.00
114 Beldar Day 0.25 207.00 51.75
9,999 Sundries and carriage of materials L.S. 6.76 1.00 6.76
TOTAL 256.51
Add 1% for water charges 2.57
TOTAL 259.08
Add for contractor’s profit and overheads
@15% 38.86
Cost of 1 no 297.94
Say

17.68 Providing and fixing vitreous china dual purpose closet suitable for use as
squatting pan or European type water closet (Anglo Indian W.C pan) with seat lid with C.P.
brass hinges and rubber buffers, 10 litre low level flushing cistern with fitting and brackets,
40mm flush bend 20mm over flow pipe with specials of standard make and mosquito
proof coupling of approved municipal design complete, including painting of fittings and
brackets, cutting and making good the walls and floors wherever required :
17.68.1 White vitreous china dual purpose WC pan with white solid plastic seat and lid with
white vitreous china flushing cistern and C.P. flush bend.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
Materials:
1350 Mosquito proof coupling of approved
design pair 1 23.00 23.00
1875 White plastic seat (solid)w ith lid C.P.brass
hinges and rubber buffers each 1 275.00 275.00
7006 Vitreous china 10 litres low level cistern
with fittings each 1 1390.00 1390.00
1965 White vitreous china dual purpose closet
(Anglo Indian W.C .) suitable for use as
squatting pan or European type water closet
as per manuacturer’s specifications

each 1 850.00 850.00


9,999 20 mm G.I. over flow pipe and specials for L.S. 276.25
over flow pipe 1.00 276.25
Labour:
116 Fitter (grade 1) Day 1 270.00 270.00
123 Mason ist class Day 1 270.00 270.00
114 Beldar Day 1 207.00 207.00
9,999 Plugs, screws etc. L.S. 59.15 1.00 59.15
9,999 Red lead, white lead and gasket L.S. 71.76 1.00 71.76
9,999 Carriage of material L.S. 118.43 1.00 118.43
9,999 Cement, sand and grit etc. L.S. 118.43 1.00 118.43
TOTAL 3929.02
Add 1% for water charges 39.29
TOTAL 3968.31
Add for contractor’s profit and overheads
@15% 595.25
Cost of 1 pan 4563.56
Say

17.69 Providing and fixing PTMT Waste Coupling for washbasin and sink, of approved
quality and colour.
17.69.1 Waste coupling 3.1 mm of 79mm length and 62mm breadth weighing not less than
45gms. Description
Code Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7491 PTM T Waste Coupling 31/32MM each 1 45.00 45.00
9,999 Carriage of materials and fixing charges L.S. 20.28 1.00 20.28
TOTAL 65.28
Add 1% for water charges 0.65
TOTAL 65.93
Add for contractor’s profit and overheads
@15% 9.89
Cost of 1 no. 75.82
Say

17.69 Providing and fixing PTMT Waste Coupling for washbasin and sink, of approved
quality and colour.
17.69.2 Waste coupling 38mm of 83mm length and 77mm breadth, weighing not less than
60gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7492 PTM T Waste Coupling 38/40MM each 1 66.00 66.00
9,999 Carriage of materials and fixing charges L.S. 20.28 1.00 20.28
TOTAL 86.28
Add 1% for water charges 0.86
TOTAL 87.14
Add for contractor’s profit and overheads
@15% 13.07
Cost of 1 no. 100.21
Say

17.70 Providing and fixing PTMT Bottle Trap for Wash basin and sink.
17.70.1 Bottle trap 31mm single piece moulded with height of 270mm, effective length
of tail pipe 260mm from the centre of the waste coupling 77mm breadth with 25mm
minimum water seal, weighing not less than 260gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7493 P.T.M.T. bottle trap 31/32 mm each 1 295.00 295.00
9,999 Carriage of materials and fixing charges L.S. 20.28 1.00 20.28
TOTAL 315.28
Add 1% for water charges 3.15
TOTAL 318.43
Add for contractor’s profit and overheads
@15% 47.76
Cost of 1 no. 366.20
Say

17.70 Providing and fixing PTMT Bottle Trap for Wash basin and sink.
17.70.2 Bottle trap 38mm single piece moulded with height of 270mm, effective length
of tail pipe 260mm from the centre of the waste coupling 77mm breadth with 25mm
minimum water seal, weighing not less than 263gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7494 P.T.M.T. bottle trap 38/40 mm each 1 320.00 320.00
9,999 Carriage of materials and fixing charges L.S. 20.28 1.00 20.28
TOTAL 340.28
Add 1% for water charges 3.40
TOTAL 343.68
Add for contractor’s profit and overheads
@15% 51.55
Cost of 1 no. 395.24
Say
17.71 Providing and fixing PTMT liquid soap container 109mm wide, 125mm high and
112mm distance from wall of standard shape with bracket of the same materials with snap
fittin gs of approved q uality and colours weighing not less than 105 gms
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7503 PTM T Liquid Soap Container of 400ml
capacity each 1 135.00 135.00
9,999 Carriage of materials and fixing charges L.S. 6.76 1.00 6.76
TOTAL 141.76
Add 1% for water charges 1.42
TOTAL 143.18
Add for contractor’s profit and overheads
@15% 21.48
Cost of 1 no. 164.65
Say

17.72 Providing and fixing PTMT towel ring trapezoidal shape 215mm long, 200mm wide
with a minimum distances of 37mm from wall face with concealed fittings arrangement of
approved quality and colours weighing not less than 80 gms
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7504 PTM T Towel Ring 215xd200x37mm each 1 108.00 108.00
9,999 Carriage of materials and fixing charges L.S. 20.28 1.00 20.28
TOTAL 128.28
Add 1% for water charges 1.28
TOTAL 129.56
Add for contractor’s profit and overheads
@15% 19.43
Cost of 1 no. 149.00
Say

17.73 Providing and fixing PTMT towel rail complete with brackets fixed to wooden cleats
with CP brass screws with concealed fitting arrangement of approved quality and colour.
17.73.1 450mm long towel rail with total length of 495mm, 78mm wide and effective height
of 88mm, weighing not less than 170gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7505 PTM T Towel R ail (450MM) each 1 180.00 180.00
Wooden cleates (Rate as per item no 9.32 of
SH : Wood work) each 2 11.81 23.61
588 Chromium plated Brass screws 25 mm 100 Nos 6
83.00 4.98
0112 Carpenter 2nd class Day 0.17 180 30.60
114 Beldar Day 0.17 207 35.19
9,999 Carriage of materials and fixing charges L.S. 4.16 1.00 4.16
TOTAL 278.54
Add 1% for water charges except A 2.55
TOTAL 281.09
Add for contractor’s profit and overheads
@15% 38.62
Cost of 1 no. 319.71
Say

17.73 Providing and fixing PTMT towel rail complete with brackets fixed to wooden cleats
with CP brass screws with concealed fitting arrangement of approved quality and colour.
17.73.2 600m m long towel rail with total length of 645mm, width 78mm and effective
height of 88mm, weighing not less than 190gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7506 PTM T Towel R ail (600MM) each 1 210.00 210.00
Wooden cleates (Rate as per item no 9.32 of
SH : Wood work) each 2 11.81 23.61
588 Chromium plated Brass screws 25 mm 100 Nos 6
83.00 4.98
0112 Carpenter 2nd class Day 0.17 180 30.60
114 Beldar Day 0.17 207 35.19
9,999 Carriage of materials and fixing charges L.S. 4.16 1.00 4.16
TOTAL 308.54
Add 1% for water charges except A 2.85
TOTAL 311.39
Add for contractor’s profit and overheads
@15% 43.17
Cost of 1 no. 354.56
Say

17.74 Providing and fixing PTMT shelf 440 mm long, 124 mm widthand 36 mm height of
approved quality and colour, weighing not less than 300gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
7507 PTMT Shelf 450x124x36mm each 1 245.00 245.00
Wooden cleates (Rate as per item no 9.32 of
SH : Wood work) each 2 11.81 23.61
588 Chromium plated Brass screws 25 mm 100 Nos 6
83.00 4.98
0112 Carpenter 2nd class Day 0.17 180 30.60
114 Beldar Day 0.17 207 35.19
9,999 Carriage of materials and fixing charges L.S. 4.16 1.00 4.16
TOTAL 343.54
Add 1% for water charges except A 3.20
TOTAL 346.74
Add for contractor’s profit and overheads
@15% 48.47
Cost of 1 no. 395.21
Say

17.75 Providing and fixing PTMT 15 mm Urinal spreader size 95x69x100 mm with 1/2"
BSP thread and shapes, weighing not less than 60gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 No.
Materials:
7508 P.T.M.T. Urinal spreader 15 mm each 1 120.00 120.00
9,999 Carriage of materials and fixing charges L.S. 6.76 1.00 6.76
TOTAL 126.76
Add 1% for water charges 1.27
TOTAL 128.03
Add 15 % for contractor’s profit and overheads 19.20
Cost of 1 no. 147.23
Say

17.76 Providing and fixing PTMT urinal cock of approved quality and colour.
17.76.1 15 mm nominal bore, 80mm long. 42 mm high and 30mm wide with BSP female
threads weighing not less than 48gms
Code Description Unit Quantity Rate Amount
Details of cost for 1 No.
Materials:
7858 P.T.M.T. Urinal cock 15mm dia each 1 90.00 90.00
9,999 Carriage of materials and fixing charges L.S. 8.06 1.00 8.06
TOTAL 98.06
Add 1% for water charges 0.98
TOTAL 99.04
Add 15 % for contractor’s profit and overheads 14.86
Cost of 1 no. 113.90
Say

17.77 Providing and fixing M.S. holder bat clam p of approved design to sand cast iron/ cast
iron (spun) pipes comprising of M.S. flat brackets made of 50x5mm flat of specified shape,
projecting 75mm outside the wall surface and fixed on wall with 4nos, 6mm dia expansion
hold fasteners including drilling necessary holes in brick wall/ CC/ RCC surface and the cost
of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30mm
x1.6mm galvanised M.S. flats of specified shape and of total length 420mm and shall be
fixed with M.S. nuts, bolts, & washers of size 25x6mm, one bolts on each side of the pipe.

17.77.1 Total bracket length 580mm of approved shape and design (for single 100mm dia
Code
pipe). Description Unit Quantity Rate Amount
Details of cost for 5 nos.
MATERIALS
1007 Steel quintal 0.0686 4600.00 315.56
2205 Carriage tonne 0.00686 47.29 0.32
Labour:
116 Fitter (Grade I) Day 0.033 270.00 8.91
103 Blacksmith 2nd class Day 0.049 223.00 10.93
114 Beldar Day 0.065 207.00 13.46
A Priming cost-(Rate vide item no. 13.50.1 sqm 0.45
finishing) 26.54 11.94
A P/F expansion hold fasteners Rate asper each 20
item no. 8.8.1.1 of SH :- Marble 18.71 374.20
9,999 Sundries L.S. 1.35 1.00 1.35
TOTAL 736.67
Add 1% for water charges except A 3.51
TOTAL 740.17
Add for contractor’s profit and overheads
@15% except on A 53.10
Cost of 5 nos 793.28
Cost of 1 no 158.66
Say

17.77 Providing and fixing M.S. holder bat clam p of approved design to sand cast iron/ cast
iron (spun) pipes comprising of M.S. flat brackets made of 50x5mm flat of specified shape,
projecting 75mm outside the wall surface and fixed on wall with 4nos, 6mm dia expansion
hold fasteners including drilling necessary holes in brick wall/ CC/ RCC surface and the cost
of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30mm
x1.6mm galvanised M.S. flats of specified shape and of total length 420mm and shall be
fixed with M.S. nuts, bolts, & washers of size 25x6mm, one bolts on each side of the pipe.

17.77.2 Total bracket length 810mm of approved shape and design (for two 100mm dia
Code
pipes). Description Unit Quantity Rate Amount
Details of cost for 5 nos.
MATERIALS
1007 Steel quintal 0.1006 4600.00 462.76
2205 Carriage tonne 0.01006 47.29 0.48
Labour:
116 Fitter (Grade I) Day 0.048 270.00 12.96
103 Blacksmith 2nd class Day 0.072 223.00 16.06
114 Beldar Day 0.096 207.00 19.87
A Priming cost-(Rate vide item no. 13.50.1 sqm 0.71
finishing) 26.54 18.84
A P/F expansion hold fasteners Rate asper each 20
item no. 8.8.1.1 of SH :- Marble 18.71 374.20
9,999 Sundries L.S. 1.98 1.00 1.98
TOTAL 907.14
Add 1% for water charges except A 5.14
TOTAL 912.28
Add for contractor’s profit and overheads
@15% except on A 77.89
Cost of 5 nos 990.17
Cost of 1 no 198.03
Say
17.77 Providing and fixing M.S. holder bat clam p of approved design to sand cast iron/ cast
iron (spun) pipes comprising of M.S. flat brackets made of 50x5mm flat of specified shape,
projecting 75mm outside the wall surface and fixed on wall with 4nos, 6mm dia expansion
hold fasteners including drilling necessary holes in brick wall/ CC/ RCC surface and the cost
of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30mm
x1.6mm galvanised M.S. flats of specified shape and of total length 420mm and shall be
fixed with M.S. nuts, bolts, & washers of size 25x6mm, one bolts on each side of the pipe.

17.77.3 Total bracket length 1040mm of approved shape and design (for three 100mm dia
Code
pipes). Description Unit Quantity Rate Amount
Details of cost for 5 nos.
MATERIALS
1007 Steel quintal 0.1326 4600.00 609.96
2205 Carriage tonne 0.01326 47.29 0.63
Labour:
116 Fitter (Grade I) Day 0.063 270.00 17.01
103 Blacksmith 2nd class Day 0.095 223.00 21.19
114 Beldar Day 0.126 207.00 26.08
A Priming cost-(Rate vide item no. 13.50.1 sqm 0.97
finishing) 26.54 25.74
A P/F expansion hold fasteners Rate asper each 20
item no. 8.8.1.1 of SH :- Marble 18.71 374.20
9,999 Sundries L.S. 2.6 1.00 2.60
TOTAL 1077.40
Add 1% for water charges except A 6.77
TOTAL 1084.18
Add for contractor’s profit and overheads
@15% except on A 102.64
Cost of 5 nos 1186.81
Cost of 1 no 237.36
Say
ith 100mm sand cast
rolled device (handle
cutting and making

gral type foot rests.

2454.62

ith 100mm sand cast


rolled device (handle
cutting and making
m with flush pipe and
5706.82

pean type W.C. pan)


ly controlled device
ncluding cutting and

2530.12

pean type W.C. pan)


ly controlled device
ncluding cutting and
2501.08

opean type) with seat


with fittings & C.I.
e and mosquito proof
and brackets, cutting
3695.02

opean type) with seat


with fittings & C.I.
e and mosquito proof
and brackets, cutting

3665.98

d front urinal basin


flushing cistern with
complete, including
rever required :
2385.92

d front urinal basin


flushing cistern with
complete, including
rever required :

istern.
3973.20

d front urinal basin


flushing cistern with
complete, including
rever required :
stern.

5292.15

d front urinal basin


flushing cistern with
complete, including
rever required :
stern.
7221.37

ll urinal of size
dard size C.P. brass
as per IS : 2556, C.I.
ings and cutting and
4569.79

all urinal of size


dard size C.P. brass
as per IS : 2556, C.I.
ings and cutting and
n.

7217.78

all urinal of size


dard size C.P. brass
as per IS : 2556, C.I.
ings and cutting and
rn.
9414.53

all urinal of size


dard size C.P. brass
as per IS : 2556, C.I.
ings and cutting and
n.
11510.37

plate with an integral


, standard size G.I.
G.I clamps and C.P.
d the walls and floors

2986.65

plate with an integral


, standard size G.I.
G.I clamps and C.P.
d the walls and floors
4363.20

plate with an integral


, standard size G.I.
G.I clamps and C.P.
d the walls and floors
n.
5768.47

plate with an integral


, standard size G.I.
G.I clamps and C.P.
d the walls and floors
n.

6970.42

illar taps,32mm C.P.


ng and making good
.P. brass pillar taps.
1559.70

illar taps,32mm C.P.


ng and making good
C.P. brass pillar tap.

1331.60

illar taps,32mm C.P.


ng and making good
C.P. brass pillar taps.
1501.62

illar taps,32mm C.P.


ng and making good
e 15 mm C.P. brass
1273.53

illar taps,32mm C.P.


ng and making good
le 15 mm C.P. brass

1378.06

illar taps,32mm C.P.


ng and making good
le 15 mm C.P. brass
1215.45

illar taps,32mm C.P.


ng and making good
e 15 mm C.P. brass

1168.99

illar taps,32mm C.P.


ng and making good
a pair of 15mm C.P.
2421.53

illar taps,32mm C.P.


ng and making good
h single 15mm C.P.
1942.55

illar taps,32mm C.P.


ng and making good
mm C.P. brass pillar

2493.10

illar taps,32mm C.P.


ng and making good
mm C.P. brass pillar
2318.88

etely recessed at the

705.88

rubber plug, 40 mm
nd making good the
1915.73

r IS 13983 with C.I.


, cutting and making

6335.53

r IS 13983 with C.I.


, cutting and making
5987.08

r IS 13983 with C.I.


, cutting and making

5406.33

r IS 13983 with C.I.


, cutting and making
3664.08

r IS 13983 with C.I.


, cutting and making

3561.59
r IS 13983 with C.I.
, cutting and making

3329.29

r IS 13983 with C.I.


, cutting and making
2283.94

ets, C.P. brass chain


C.P. brass unions
d the wall wherever

1568.44

ets, C.P. brass chain


C.P. brass unions
d the wall wherever
2423.31

g of brackets, cutting

688.57

ian type)
714.80

type)

947.10
572.62

sh down type) water

1005.17

level cistern of same

901.32

ern for squatting pan


119.94

ern for squatting pan

237.25

olled device (handle


737.35

olled device (handle

811.48

hina with all fittings


1289.29

hina with all fittings

1775.96

n complete :

334.96

n complete :
305.93

nd cover in European

-29.04

W.C. pan.

73.63

ed front urinal basin


662.93

gral rim longitudinal

1290.64

g all connections but


654.28

g all connections but

596.21

g all connections but

700.74

g all connections but


538.13

g all connections but

491.67

g all connections but


1014.35

uding cost of fittings.

1443.99

king all connections

830.72

king all connections


1685.58

P.V.C. waste fittings

42.14

P.V.C. waste fittings


47.95

P.V.C. waste fittings

46.79

P.V.C. waste fittings

49.11
16.45

approved municipal

28.83

of approved quality)
P. brass screws and

542.48

f required shape and


d board backing :
676.20

f required shape and


d board backing :

629.30

f required shape and


d board backing :
743.70

f required shape and


d board backing :

1732.98
pported on anodised
40 mm long screws,

250.78

165.77
A

191.69

458.89
738.52

402.03
636.64

rtar 1:2 (1 cement: 2

40.78

rtar 1:2 (1 cement: 2

48.05
Cast iron/ cast iron
2:4 mix (1 cement: 2
ng holes and making

91.98

Cast iron/ cast iron


2:4 mix (1 cement: 2
ng holes and making
89.65

ubber washer 3 mm
254.97

ubber washer 3 mm

290.98

ubber washer 3 mm

209.99

ubber washer 3 mm
230.89

222.45
236.39

175.14

178.63
244.52

286.33

204.18
249.48

oor, insertion rubber

513.84

oor, insertion rubber

612.56
oor, insertion rubber

409.77

oor, insertion rubber

487.59
473.33

558.12

356.34
445.77

ccess door, insertion

374.61

ccess door, insertion


489.60

ccess door, insertion

283.16

ccess door, insertion

364.47
323.50

441.97
250.64

333.11

ccess door, insertion

555.80

ccess door, insertion


842.69

507.02
757.90

ccess door, insertion

402.48

ccess door, insertion

637.11
350.22

551.15
505.86

496.56

377.24
400.47

388.54

393.19
290.13

299.42

547.67
682.40

459.40

:
505.86

158.88

268.06
268.06

351.38

340.25
440.14

220.44

277.74
374.14

nuts complete :

367.64

nuts complete :

296.79
nuts complete :

268.06

nuts complete :

227.41
192.25

194.57

139.14
177.47

143.47

202.70
107.78

146.11

150.43
126.88

100.99
48.23

41.57

34.25
654.80

552.58
683.83

486.38
A

209.96

150.01
A

95.45

288.34
187.62

91.39

A
24.63

18.78

A
9.33

9.33

297.94
4563.56

75.82
100.21

366.20

395.24
164.65

149.00

A
319.71

354.56

A
395.21

147.23

113.90
158.66

198.03
237.36
18.1: Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure
Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for hot & cold
water supply, capable to withstand temperature up to 80° C including all special fittings of composite
material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees ,reducers,
couplers & connectors etc. with clamps at 1.00 metre spacing. This includes testing of joints complete
as per direction of the Engineer in charge. Internal work - Exposed on wall
18.1.1: 1216 (16 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8300 1216 mm PE-AL-PE Composite pressure each 10 79.00 790.00
pipe
Extra fo fitting & wastage 237.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 1402.63
Add 1% for water charges 14.03
TOTAL 1416.66
Add for contractor’s profit and 212.50
overheads @15%
Cost of 10 metres 1629.15
Cost of 1 metres 162.92
Say 162.92

18.1: Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for hot & cold
water supply, capable to withstand temperature up to 80° C including all special fittings of composite
material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees ,reducers,
couplers & connectors etc. with clamps at 1.00 metre spacing. This includes testing of joints complete
as per direction of the Engineer in charge. Internal work - Exposed on wall
18.1.2 : 1620 (20 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8301 1620 mm PE-AL-PE Composite pressure each 10 97.00 970.00
pipe
Extra fo fitting & wastage 291.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.82 223.00 182.86
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 1672.31
Add 1% for water charges 16.72
TOTAL 1689.03
Add for contractor’s profit and 253.35
overheads @15%
Cost of 10 metres 1942.39
Cost of 1 metres 194.24
Say 194.24

18.1: Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for hot & cold
water supply, capable to withstand temperature up to 80° C including all special fittings of composite
material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees ,reducers,
couplers & connectors etc. with clamps at 1.00 metre spacing. This includes testing of joints complete
as per direction of the Engineer in charge. Internal work - Exposed on wall
18.1.3 : 2025 (25 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8302 2025 mm PE-AL-PE Composite pressure each 10 126.00 1260.00
pipe
Extra fo fitting & wastage 378.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 2084.99
Add 1% for water charges 20.85
TOTAL 2105.84
Add for contractor’s profit and 315.88
overheads @15%
Cost of 10 metres 2421.72
Cost of 1 metres 242.17
Say 242.17

18.1: Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for hot & cold
water supply, capable to withstand temperature up to 80° C including all special fittings of composite
material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees ,reducers,
couplers & connectors etc. with clamps at 1.00 metre spacing. This includes testing of joints complete
as per direction of the Engineer in charge. Internal work - Exposed on wall
18.1.4: 2532 (32 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8303 2532 mm PE-AL-PE Composite pressure each 10 172.00 1720.00
pipe
Extra fo fitting & wastage 516.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.98 207.00 202.86
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
TOTAL 2750.66
Add 1% for water charges 27.51
TOTAL 2778.17
Add for contractor’s profit and 416.72
overheads @15%
Cost of 10 metres 3194.89
Cost of 1 metres 319.49
Say 319.49

18.1: Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for hot & cold
water supply, capable to withstand temperature up to 80° C including all special fittings of composite
material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees ,reducers,
couplers & connectors etc. with clamps at 1.00 metre spacing. This includes testing of joints complete
as per direction of the Engineer in charge. Internal work - Exposed on wall
18.1.5 : 3240 (40 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8304 3240 mm PE-AL-PE Composite pressure each 10 227.00 2270.00
pipe
Extra fo fitting & wastage 681.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.31 223.00 292.13
114 Beldar Day 1.31 207.00 271.17
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 3608.73
Add 1% for water charges 36.09
TOTAL 3644.82
Add for contractor’s profit and 546.72
overheads @15%
Cost of 10 metres 4191.54
Cost of 1 metres 419.15
Say 419.15
18.1: Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure
Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for hot & cold
water supply, capable to withstand temperature up to 80° C including all special fittings of composite
material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees ,reducers,
couplers & connectors etc. with clamps at 1.00 metre spacing. This includes testing of joints complete
as per direction of the Engineer in charge. Internal work - Exposed on wall
18.1.6 : 4050 (50 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8305 4050 mm PE-AL-PE Composite pressure each 10 304.00 3040.00
pipe
Extra fo fitting & wastage 912.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.31 223.00 292.13
114 Beldar Day 1.31 207.00 271.17
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 4609.73
Add 1% for water charges 46.10
TOTAL 4655.83
Add for contractor’s profit and 698.37
overheads @15%
Cost of 10 metres 5354.20
Cost of 1 metres 535.42
Say 535.42

18.2 : Providing and fixing P olyethelene-A lum in iu m-P olyethelene ( PE-A L-PE ) Composite
Pressure Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for
hot & cold water supply, capable to withstand temperature up to 80°C including all special fittings
of composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,
tees, reducers, couplers & connectors etc. with clamps at 1.00 metre spacing. This includes the costs of
cutting chases and including testing of joints complete as per direction of the engineer in charge.
Concealed work including cutting chases and making good the wall etc.
18.2.1 : 1216 (16 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8300 1216 mm PE-AL-PE Composite pressure each 10 79.00 790.00
pipe
Add 75% for fitting,clamps and wastage 592.50
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2292.12
Add 1% for water charges except on A 17.55

TOTAL 2309.68
Add for contractor’s profit and 265.94
overheads @15% except on A
Cost of 10 metres 2575.62
Cost of 1 metres 257.56
Say 257.56

18.2 : P roviding and fixing P olyethelene-A lum in iu m-P olyethelene ( PE-A L-PE ) Composite
Pressure Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for
hot & cold water supply, capable to withstand temperature up to 80°C including all special fittings
of composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,
tees, reducers, couplers & connectors etc. with clamps at 1.00 metre spacing. This includes the costs of
cutting chases and including testing of joints complete as per direction of the engineer in charge.
Concealed work including cutting chases and making good the wall etc.
18.2.2 : 1620 (20 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8301 1620 mm PE-AL-PE Composite pressure each 10 97.00 970.00
pipe
Add 75% for fitting,clamps and wastage 727.50
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2607.12
Add 1% for water charges except on A 20.70

TOTAL 2627.83
Add for contractor’s profit and 313.67
overheads @15% except on A
Cost of 10 metres 2941.49
Cost of 1 metres 294.15
Say 294.15
18.2 : P roviding and fixing P olyethelene-A lum in iu m-P olyethelene ( PE-A L-PE ) Composite
Pressure Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for
hot & cold water supply, capable to withstand temperature up to 80°C including all special fittings
of composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,
tees, reducers, couplers & connectors etc. with clamps at 1.00 metre spacing. This includes the costs of
cutting chases and including testing of joints complete as per direction of the engineer in charge.
Concealed work including cutting chases and making good the wall etc.
18.2.3 : 2025 (25 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8302 2025 mm PE-AL-PE Composite pressure each 10 126.00 1260.00
pipe
Add 75% for fitting,clamps and wastage 945.00
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 3114.62
Add 1% for water charges except on A 25.78

TOTAL 3140.40
Add for contractor’s profit and 390.55
overheads @15% except on A
Cost of 10 metres 3530.95
Cost of 1 metres 353.10
Say 353.10

18.2 : P roviding and fixing P olyethelene-A lum in iu m-P olyethelene ( PE-A L-PE ) Composite
Pressure Pipes conforming to IS - 15450 U.V. stabilised with carbon black having thermal stability for
hot & cold water supply, capable to withstand temperature up to 80°C including all special fittings
of composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,
tees, reducers, couplers & connectors etc. with clamps at 1.00 metre spacing. This includes the costs of
cutting chases and including testing of joints complete as per direction of the engineer in charge.
Concealed work including cutting chases and making good the wall etc.
18.2.4: 2532 (32 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8303 2532 mm PE-AL-PE Composite pressure each 10 172.00 1720.00
pipe
Add 75% for fitting,clamps and wastage 1290.00
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 3919.62
Add 1% for water charges except on A 33.83

TOTAL 3953.45
Add for contractor’s profit and 512.51
overheads @15% except on A
Cost of 10 metres 4465.96
Cost of 1 metres 446.60
Say 446.60

18.3 : Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 - 2004 U.V. stabilised with carbon black having thermal stability for hot
& cold water supply, capable to withstand temperature up to 80° C including all special fittings of
composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees
,reducers, couplers & connectors etc. with trenching, refilling and testing of joints complete as per
direction of the engineer in charge. External work
18.3.1 : 1216 (16 mm OD) pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8300 1216 mm PE-AL-PE Composite pressure each 10 79.00 790.00
pipe
Extra fo fitting & wastage 237.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 1354.96
Add 1% for water charges 13.55
TOTAL 1368.51
Add for contractor’s profit and 205.28
overheads @15%
Cost of 10 metres 1573.79
Cost of 1 metres 157.38
Say 157.38
18.3 : Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure
Pipes conforming to IS - 15450 - 2004 U.V. stabilised with carbon black having thermal stability for hot
& cold water supply, capable to withstand temperature up to 80° C including all special fittings of
composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees
,reducers, couplers & connectors etc. with trenching, refilling and testing of joints complete as per
direction of the engineer in charge. External work
18.3.2 1620 (20 mm OD) pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8301 1620 mm PE-AL-PE Composite pressure each 10 97.00 970.00
pipe
Extra fo fitting & wastage 291.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 1588.96
Add 1% for water charges 15.89
TOTAL 1604.85
Add for contractor’s profit and 240.73
overheads @15%
Cost of 10 metres 1845.58
Cost of 1 metres 184.56
Say 184.56

18.3 : Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 - 2004 U.V. stabilised with carbon black having thermal stability for hot
& cold water supply, capable to withstand temperature up to 80° C including all special fittings of
composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees
,reducers, couplers & connectors etc. with trenching, refilling and testing of joints complete as per
direction of the engineer in charge. External work
18.3.3. 2025 (25 mm OD ) pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8302 2025 mm PE-AL-PE Composite pressure each 10 126.00 1260.00
pipe
Extra fo fitting & wastage 378.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 1965.96
Add 1% for water charges 19.66
TOTAL 1985.62
Add for contractor’s profit and 297.84
overheads @15%
Cost of 10 metres 2283.46
Cost of 1 metres 228.35
Say 228.35

18.3 : Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 - 2004 U.V. stabilised with carbon black having thermal stability for hot
& cold water supply, capable to withstand temperature up to 80° C including all special fittings of
composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees
,reducers, couplers & connectors etc. with trenching, refilling and testing of joints complete as per
direction of the engineer in charge. External work
18.3.4 : 2532 (32 mm OD ) pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8303 2532 mm PE-AL-PE Composite pressure each 10 172.00 1720.00
pipe
Extra fo fitting & wastage 516.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 2563.96
Add 1% for water charges 25.64
TOTAL 2589.60
Add for contractor’s profit and 388.44
overheads @15%
Cost of 10 metres 2978.04
Cost of 1 metres 297.80
Say 297.80

18.3 : Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 - 2004 U.V. stabilised with carbon black having thermal stability for hot
& cold water supply, capable to withstand temperature up to 80° C including all special fittings of
composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees
,reducers, couplers & connectors etc. with trenching, refilling and testing of joints complete as per
direction of the engineer in charge. External work
18.3.5: 3240 (40 mm OD ) pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8304 3240 mm PE-AL-PE Composite pressure each 10 227.00 2270.00
pipe
Extra fo fitting & wastage 681.00
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.99 207.00 204.93
TOTAL 3335.75
Add 1% for water charges 33.36
TOTAL 3369.11
Add for contractor’s profit and 505.37
overheads @15%
Cost of 10 metres 3874.47
Cost of 1 metres 387.45
Say 387.45

18.3 : Providing and fixing Polyethelene-Aluminium-Polyethelene (PE-AL-PE) Composite Pressure


Pipes conforming to IS - 15450 - 2004 U.V. stabilised with carbon black having thermal stability for hot
& cold water supply, capable to withstand temperature up to 80° C including all special fittings of
composite material (engineering plastic blend and brass inserts wherever required ) e.g. elbows ,tees
,reducers, couplers & connectors etc. with trenching, refilling and testing of joints complete as per
direction of the engineer in charge. External work
18.3.6: 4050 (50 mm OD ) pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8305 4050 mm PE-AL-PE Composite pressure each 10 304.00 3040.00
pipe
Extra fo fitting & wastage 912.00
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.99 207.00 204.93
TOTAL 4336.75
Add 1% for water charges 43.37
TOTAL 4380.12
Add for contractor’s profit and 657.02
overheads @15%
Cost of 10 metres 5037.14
Cost of 1 metres 503.71
Say 503.71

18.4 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti -microbial fusion welded, having thermal stability for hot & cold water supply
including all PP - R plain & brass threaded polypropylene random fittings i/c fixing the pipe with clamps
at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer in Charge.
(Internal work-exposed on wall)
18.4.1 PN-16 Pipe, 16 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8625 3 layer PP-R pipe (PN-16/SDR 7.4) 16mm each 10 29.00 290.00
outer dia
Extra fo fitting & wastage 87.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 752.63
Add 1% for water charges 7.53
TOTAL 760.16
Add for contractor’s profit and 114.02
overheads @15%
Cost of 10 metres 874.18
Cost of 1 metres 87.42
Say 87.42

18.4 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti -microbial fusion welded, having thermal stability for hot & cold water supply
including all PP - R plain & brass threaded polypropylene random fittings i/c fixing the pipe with clamps
at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer in Charge.
(Internal work-exposed on wall)
18.4.2 : PN-16 Pipe, 20 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8626 3 layer PP-R pipe (PN-16/SDR 7.4) 20mm each 10 44.00 440.00
outer dia
Extra fo fitting & wastage 132.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.82 223.00 182.86
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 983.31
Add 1% for water charges 9.83
TOTAL 993.14
Add for contractor’s profit and 148.97
overheads @15%
Cost of 10 metres 1142.11
Cost of 1 metres 114.21
Say 114.21
18.4 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti -microbial fusion welded, having thermal stability for hot & cold water supply
including all PP - R plain & brass threaded polypropylene random fittings i/c fixing the pipe with clamps
at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer in Charge.
(Internal work-exposed on wall)
18.4.3 : PN - 16 Pipe, 25 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8627 3 layer PP-R pipe (PN-16/SDR 7.4) 25mm each 10 68.00 680.00
outer dia
Extra fo fitting & wastage 204.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 1330.99
Add 1% for water charges 13.31
TOTAL 1344.30
Add for contractor’s profit and 201.64
overheads @15%
Cost of 10 metres 1545.94
Cost of 1 metres 154.59
Say 154.59

18.4 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti -microbial fusion welded, having thermal stability for hot & cold water supply
including all PP - R plain & brass threaded polypropylene random fittings i/c fixing the pipe with clamps
at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer in Charge.
(Internal work-exposed on wall)
18.4.4 : PN-16 Pipe, 32 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8628 3 layer PP-R pipe (PN-16/SDR 7.4) 32mm each 10 111.00 1110.00
outer dia
Extra fo fitting & wastage 333.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.98 207.00 202.86
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
TOTAL 1957.66
Add 1% for water charges 19.58
TOTAL 1977.24
Add for contractor’s profit and 296.59
overheads @15%
Cost of 10 metres 2273.82
Cost of 1 metres 227.38
Say 227.38

18.4 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti -microbial fusion welded, having thermal stability for hot & cold water supply
including all PP - R plain & brass threaded polypropylene random fittings i/c fixing the pipe with clamps
at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer in Charge.
(Internal work-exposed on wall)
18.4.5 : PN-16 Pipe, 40 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8629 3 layer PP-R pipe (PN-16/SDR 7.4) 40mm each 10 176.00 1760.00
outer dia
Extra fo fitting & wastage 528.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.31 223.00 292.13
114 Beldar Day 1.31 207.00 271.17
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 2945.73
Add 1% for water charges 29.46
TOTAL 2975.19
Add for contractor’s profit and 446.28
overheads @15%
Cost of 10 metres 3421.47
Cost of 1 metres 342.15
Say 342.15

18.4 Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti -microbial fusion welded, having thermal stability for hot & cold water supply
including all PP - R plain & brass threaded polypropylene random fittings i/c fixing the pipe with clamps
at 1.00 m spacing. This includes testing of joints complete as per direction of Engineer in Charge.
(Internal work-exposed on wall)
18.4.6 : PN- 16 Pipe, 50 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8630 3 layer PP-R pipe (PN-16/SDR 7.4) 50mm each 10 257.00 2570.00
outer dia
Extra fo fitting & wastage 771.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.31 223.00 292.13
114 Beldar Day 1.31 207.00 271.17
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 3998.73
Add 1% for water charges 39.99
TOTAL 4038.72
Add for contractor’s profit and 605.81
overheads @15%
Cost of 10 metres 4644.52
Cost of 1 metres 464.45
Say 464.45

18.5 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes the cost of cutting chases and making good the same
including testing of joints complete as per direction of Engineer in Chajge. (Concealed work including
cutting chases and making good the walls etc.,)
18.5.1 PN- 16 Pipe, 16 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8625 3 layer PP-R pipe (PN-16/SDR 7.4) 16mm each 10 29.00 290.00
outer dia
Add 75% for fitting,clamps and wastage 217.50
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 1417.12
Add 1% for water charges except on A 8.80

TOTAL 1425.93
Add for contractor’s profit and 133.38
overheads @15% except on A
Cost of 10 metres 1559.31
Cost of 1 metres 155.93
Say 155.93
18.5 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes the cost of cutting chases and making good the same
including testing of joints complete as per direction of Engineer in Chajge. (Concealed work including
cutting chases and making good the walls etc.,)
18.5.2: PN-16 Pipe, 20 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8626 3 layer PP-R pipe (PN-16/SDR 7.4) 20mm each 10 44.00 440.00
outer dia
Add 75% for fitting,clamps and wastage 330.00
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 1679.62
Add 1% for water charges except on A 11.43

TOTAL 1691.05
Add for contractor’s profit and 173.15
overheads @15% except on A
Cost of 10 metres 1864.20
Cost of 1 metres 186.42
Say 186.42

18.5 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes the cost of cutting chases and making good the same
including testing of joints complete as per direction of Engineer in Chajge. (Concealed work including
cutting chases and making good the walls etc.,)
18.5.3 : PN-16 Pipe, 25 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8627 3 layer PP-R pipe (PN-16/SDR 7.4) 25mm each 10 68.00 680.00
outer dia
Add 75% for fitting,clamps and wastage 510.00
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2099.62
Add 1% for water charges except on A 15.63

TOTAL 2115.25
Add for contractor’s profit and 236.78
overheads @15% except on A
Cost of 10 metres 2352.03
Cost of 1 metres 235.20
Say 235.20

18.5 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes the cost of cutting chases and making good the same
including testing of joints complete as per direction of Engineer in Chajge. (Concealed work including
cutting chases and making good the walls etc.,)
18.5.4 : PN-16 Pipe, 32 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8628 3 layer PP-R pipe (PN-16/SDR 7.4) 32mm each 10 111.00 1110.00
outer dia
Add 75% for fitting,clamps and wastage 832.50
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2852.12
Add 1% for water charges except on A 23.15

TOTAL 2875.28
Add for contractor’s profit and 350.78
overheads @15% except on A
Cost of 10 metres 3226.06
Cost of 1 metres 322.61
Say 322.61

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)
18.6.1 : PN-16 Pipe, 16 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8625 3 layer PP-R pipe (PN-16/SDR 7.4) 16mm each 10 29.00 290.00
outer dia
Extra fo fitting & wastage 87.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 704.96
Add 1% for water charges 7.05
TOTAL 712.01
Add for contractor’s profit and 106.80
overheads @15%
Cost of 10 metres 818.81
Cost of 1 metres 81.88
Say 81.88

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)
18.6.2 : PN-16 Pipe, 20 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8626 3 layer PP-R pipe (PN-16/SDR 7.4) 20mm each 10 44.00 440.00
outer dia
Extra fo fitting & wastage 132.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 899.96
Add 1% for water charges 9.00
TOTAL 908.96
Add for contractor’s profit and 136.34
overheads @15%
Cost of 10 metres 1045.30
Cost of 1 metres 104.53
Say 104.53

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)
18.6.3: PN - 16 Pipe, 25 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8627 3 layer PP-R pipe (PN-16/SDR 7.4) 25mm each 10 68.00 680.00
outer dia
Extra fo fitting & wastage 204.00
Labour:
116 Fitter (grade 1) Day 0.12 270.00 32.40
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.91 207.00 188.37
TOTAL 1241.39
Add 1% for water charges 12.41
TOTAL 1253.80
Add for contractor’s profit and 188.07
overheads @15%
Cost of 10 metres 1441.87
Cost of 1 metres 144.19
Say 144.19

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)

18.6.4 : PN-16 Pipe, 32 mm OD


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8628 3 layer PP-R pipe (PN-16/SDR 7.4) 32mm each 10 111.00 1110.00
outer dia
Extra fo fitting & wastage 333.00
Labour:
116 Fitter (grade 1) Day 0.12 270.00 32.40
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.91 207.00 188.37
TOTAL 1800.39
Add 1% for water charges 18.00
TOTAL 1818.39
Add for contractor’s profit and 272.76
overheads @15%
Cost of 10 metres 2091.15
Cost of 1 metres 209.12
Say 209.12

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)
18.6.5 : PN-16 Pipe, 40 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8629 3 layer PP-R pipe (PN-16/SDR 7.4) 40mm each 10 176.00 1760.00
outer dia
Extra fo fitting & wastage 528.00
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.99 207.00 204.93
TOTAL 2672.75
Add 1% for water charges 26.73
TOTAL 2699.48
Add for contractor’s profit and 404.92
overheads @15%
Cost of 10 metres 3104.40
Cost of 1 metres 310.44
Say 310.44

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)

18.6.6 : PN - 16 Pipe, 50 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8630 3 layer PP-R pipe (PN-16/SDR 7.4) 50mm each 10 257.00 2570.00
outer dia
Extra fo fitting & wastage 771.00
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.99 207.00 204.93
TOTAL 3725.75
Add 1% for water charges 37.26
TOTAL 3763.01
Add for contractor’s profit and 564.45
overheads @15%
Cost of 10 metres 4327.46
Cost of 1 metres 432.75
Say 432.75

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)

18.6.7: PN - 16 Pipe, 63mm OD


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8631 3 layer PP-R pipe (PN-16/SDR 7.4) 63mm each 10 400.00 4000.00
outer dia
Extra fo fitting & wastage 1200.00
Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 1.32 207.00 273.24
TOTAL 5677.36
Add 1% for water charges 56.77
TOTAL 5734.13
Add for contractor’s profit and 860.12
overheads @15%
Cost of 10 metres 6594.25
Cost of 1 metres 659.43
Say 659.43

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)

18.6.8 : PN - 16 Pipe, 75 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8632 3 layer PP-R pipe (PN-16/SDR 7.4) 75mm each 10 575.00 5750.00
outer dia
Extra fo fitting & wastage 1725.00
Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 1.32 207.00 273.24
TOTAL 7952.36
Add 1% for water charges 79.52
TOTAL 8031.88
Add for contractor’s profit and 1204.78
overheads @15%
Cost of 10 metres 9236.67
Cost of 1 metres 923.67
Say 923.67

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)

18.6.9 : PN - 16 Pipe, 90 mm OD
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8632 3 layer PP-R pipe (PN-16/SDR 7.4) 90mm each 10 917.00 9170.00
outer dia
Extra fo fitting & wastage 2751.00
Labour:
116 Fitter (grade 1) Day 0.37 270.00 99.90
115 Coolie Day 0.8 207.00 165.60
114 Beldar Day 1.77 207.00 366.39
TOTAL 12552.89
Add 1% for water charges 125.53
TOTAL 12678.42
Add for contractor’s profit and 1901.76
overheads @15%
Cost of 10 metres 14580.18
Cost of 1 metres 1458.02
Say 1458.02
18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)

18.6.10: PN - 10 Pipe, 110 mm OD (SDR - 11)


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8633 3 layer PP-R pipe (PN-10/SDR 11) 110mm each 10 962.00 9620.00
outer dia
Extra fo fitting & wastage 2886.00
Labour:
116 Fitter (grade 1) Day 0.37 270.00 99.90
115 Coolie Day 0.8 207.00 165.60
114 Beldar Day 1.77 207.00 366.39
TOTAL 13137.89
Add 1% for water charges 131.38
TOTAL 13269.27
Add for contractor’s profit and 1990.39
overheads @15%
Cost of 10 metres 15259.66
Cost of 1 metres 1525.97
Say 1525.97

18.6 : Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply
including all PP-R plain & brass threaded polypropylene random fittings i/c trenching .refilling &
testing of joints complete as per direction of Engineer in Charge. (External work)

18.6.11 PN-10 Pipe, 160 mm OD (SDR- 11)


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8634 3 layer PP-R pipe (PN-10/SDR 11) 160mm each 10 2028.00 20280.00
outer dia
Extra fo fitting & wastage 6084.00
Labour:
116 Fitter (grade 1) Day 0.58 270.00 156.60
115 Coolie Day 1.2 207.00 248.40
114 Beldar Day 2.74 207.00 567.18
TOTAL 27336.18
Add 1% for water charges 273.36
TOTAL 27609.54
Add for contractor’s profit and 4141.43
overheads @15%
Cost of 10 metres 31750.97
Cost of 1 metres 3175.10
Say 3175.10

18.7 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC ) pipes, having thermal stability
for hot & cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes jointing of pipes & fittings with o ne step C PVC solven t
cement and testing of joints com plete as per direction of Engineer in Charge. (Internal work Exposed on
wall)
18.7.1: 15 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8636 Chlorinated Polyvinyl - chloride (CPVC) each 10 45.00 450.00
pipe 15 mm outer dia.
Extra fo fitting & wastage 135.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.82 223.00 182.86
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 996.31
Add 1% for water charges 9.96
TOTAL 1006.27
Add for contractor’s profit and 150.94
overheads @15%
Cost of 10 metres 1157.21
Cost of 1 metres 115.72
Say 115.72

18.7 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC ) pipes, having thermal stability
for hot & cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes jointing of pipes & fittings with o ne step C PVC solven t
cement and testing of joints com plete as per direction of Engineer in Charge. (Internal work Exposed on
wall)
18.7.2 20 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8637 Chlorinated Polyvinyl - chloride (CPVC) each 10 55.00 550.00
pipe 20 mm outer dia.
Extra fo fitting & wastage 165.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 1161.99
Add 1% for water charges 11.62
TOTAL 1173.61
Add for contractor’s profit and 176.04
overheads @15%
Cost of 10 metres 1349.65
Cost of 1 metres 134.97
Say 134.97

18.7 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC ) pipes, having thermal stability
for hot & cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes jointing of pipes & fittings with o ne step C PVC solven t
cement and testing of joints com plete as per direction of Engineer in Charge. (Internal work Exposed on
wall)
18.7.3 : 25 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8638 Chlorinated Polyvinyl - chloride (CPVC) each 10 78.00 780.00
pipe 25 mm outer dia.
Extra fo fitting & wastage 234.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.66 207.00 136.62
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 1460.99
Add 1% for water charges 14.61
TOTAL 1475.60
Add for contractor’s profit and 221.34
overheads @15%
Cost of 10 metres 1696.94
Cost of 1 metres 169.69
Say 169.69

18.7 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC ) pipes, having thermal stability
for hot & cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes jointing of pipes & fittings with o ne step C PVC solven t
cement and testing of joints com plete as per direction of Engineer in Charge. (Internal work Exposed on
wall)
18.7.4 32 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8639 Chlorinated Polyvinyl - chloride (CPVC) each 10 105.00 1050.00
pipe 32 mm outer dia.
Extra fo fitting & wastage 315.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.98 207.00 202.86
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
TOTAL 1879.66
Add 1% for water charges 18.80
TOTAL 1898.46
Add for contractor’s profit and 284.77
overheads @15%
Cost of 10 metres 2183.23
Cost of 1 metres 218.32
Say 218.32

18.7 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC ) pipes, having thermal stability
for hot & cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes jointing of pipes & fittings with o ne step C PVC solven t
cement and testing of joints com plete as per direction of Engineer in Charge. (Internal work Exposed on
wall)
18.7.5: 40 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8640 Chlorinated Polyvinyl - chloride (CPVC) each 10 150.00 1500.00
pipe 40 mm outer dia.
Extra fo fitting & wastage 450.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.31 223.00 292.13
114 Beldar Day 1.31 207.00 271.17
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 2607.73
Add 1% for water charges 26.08
TOTAL 2633.81
Add for contractor’s profit and 395.07
overheads @15%
Cost of 10 metres 3028.88
Cost of 1 metres 302.89
Say 302.89

18.7 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC ) pipes, having thermal stability
for hot & cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with
clamps at 1.00 m spacing. This includes jointing of pipes & fittings with o ne step C PVC solven t
cement and testing of joints com plete as per direction of Engineer in Charge. (Internal work Exposed on
wall)
18.7.6: 50 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8641 Chlorinated Polyvinyl - chloride (CPVC) each 10 245.00 2450.00
pipe 50 mm outer dia.
Extra fo fitting & wastage 735.00
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.31 223.00 292.13
114 Beldar Day 1.31 207.00 271.17
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 3842.73
Add 1% for water charges 38.43
TOTAL 3881.16
Add for contractor’s profit and 582.17
overheads @15%
Cost of 10 metres 4463.33
Cost of 1 metres 446.33
Say 446.33

18.8 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with clamps at
1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the
cost of cutting chases and making good the same including testing of joints complete as per direction of
Engineer in Charge. (Concealed work including cutting chases and making good the walls etc.,)

18.8.1: 15 mm nominal outer dia .Pipes.


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8636 Chlorinated Polyvinyl - chloride (CPVC) each 10 45.00 450.00
pipe 15 mm outer dia.
Add 75% for fitting,clamps and wastage 337.50
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 1697.12
Add 1% for water charges except on A 11.60

TOTAL 1708.73
Add for contractor’s profit and 175.80
overheads @15% except on A
Cost of 10 metres 1884.53
Cost of 1 metres 188.45
Say 188.45

18.8 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with clamps at
1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the
cost of cutting chases and making good the same including testing of joints complete as per direction of
Engineer in Charge. (Concealed work including cutting chases and making good the walls etc.,)

18.8.2 : 20 mm nominal outer dia .Pipes.


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8637 Chlorinated Polyvinyl - chloride (CPVC) each 10 55.00 550.00
pipe 20 mm outer dia.
Add 75% for fitting,clamps and wastage 412.50
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 1872.12
Add 1% for water charges except on A 13.35

TOTAL 1885.48
Add for contractor’s profit and 202.31
overheads @15% except on A
Cost of 10 metres 2087.79
Cost of 1 metres 208.78
Say 208.78

18.8 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with clamps at
1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the
cost of cutting chases and making good the same including testing of joints complete as per direction of
Engineer in Charge. (Concealed work including cutting chases and making good the walls etc.,)

18.8.3 : 25 mm nominal outer dia .Pipes.


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8638 Chlorinated Polyvinyl - chloride (CPVC) each 10 78.00 780.00
pipe 25 mm outer dia.
Add 75% for fitting,clamps and wastage 585.00
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2274.62
Add 1% for water charges except on A 17.38

TOTAL 2292.00
Add for contractor’s profit and 263.29
overheads @15% except on A
Cost of 10 metres 2555.29
Cost of 1 metres 255.53
Say 255.53

18.8 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with clamps at
1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the
cost of cutting chases and making good the same including testing of joints complete as per direction of
Engineer in Charge. (Concealed work including cutting chases and making good the walls etc.,)

18.8.4 32 m m nominal outer dia .Pipes.


Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8639 Chlorinated Polyvinyl - chloride (CPVC) each 10 105.00 1050.00
pipe 32 mm outer dia.
Add 75% for fitting,clamps and wastage 787.50
etc
A Making chases upto 7.5 x 7.5 cm. in metre 10 53.67 536.72
walls and making good the same Rate as
per item no. 18.78
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2747.12
Add 1% for water charges except on A 22.10
TOTAL 2769.23
Add for contractor’s profit and 334.88
overheads @15% except on A
Cost of 10 metres 3104.10
Cost of 1 metres 310.41
Say 310.41

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.1 15 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8636 Chlorinated Polyvinyl - chloride (CPVC) each 10 45.00 450.00
pipe 15 mm outer dia.
Extra fo fitting & wastage 135.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 912.96
Add 1% for water charges 9.13
TOTAL 922.09
Add for contractor’s profit and 138.31
overheads @15%
Cost of 10 metres 1060.40
Cost of 1 metres 106.04
Say 106.04

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.2 20 m m nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8637 Chlorinated Polyvinyl - chloride (CPVC) each 10 55.00 550.00
pipe 20 mm outer dia.
Extra fo fitting & wastage 165.00
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.82 207.00 169.74
TOTAL 1042.96
Add 1% for water charges 10.43
TOTAL 1053.39
Add for contractor’s profit and 158.01
overheads @15%
Cost of 10 metres 1211.40
Cost of 1 metres 121.14
Say 121.14

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction
18.9.3 25 of
mmEngineer
nominal in Charge.
outer (External work).
dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8638 Chlorinated Polyvinyl - chloride (CPVC) each 10 78.00 780.00
pipe 25 mm outer dia.
Extra fo fitting & wastage 234.00
Labour:
116 Fitter (grade 1) Day 0.12 270.00 32.40
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.91 207.00 188.37
TOTAL 1371.39
Add 1% for water charges 13.71
TOTAL 1385.10
Add for contractor’s profit and 207.77
overheads @15%
Cost of 10 metres 1592.87
Cost of 1 metres 159.29
Say 159.29

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.4 32 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8639 Chlorinated Polyvinyl - chloride (CPVC) each 10 105.00 1050.00
pipe 32 mm outer dia.
Extra fo fitting & wastage 315.00
Labour:
116 Fitter (grade 1) Day 0.12 270.00 32.40
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.91 207.00 188.37
TOTAL 1722.39
Add 1% for water charges 17.22
TOTAL 1739.61
Add for contractor’s profit and 260.94
overheads @15%
Cost of 10 metres 2000.56
Cost of 1 metres 200.06
Say 200.06

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.5 40 mm nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8640 Chlorinated Polyvinyl - chloride (CPVC) each 10 150.00 1500.00
pipe 40 mm outer dia.
Extra fo fitting & wastage 450.00
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.99 207.00 204.93
TOTAL 2334.75
Add 1% for water charges 23.35
TOTAL 2358.10
Add for contractor’s profit and 353.71
overheads @15%
Cost of 10 metres 2711.81
Cost of 1 metres 271.18
Say 271.18

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.6 50 m m nominal outer dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8641 Chlorinated Polyvinyl - chloride (CPVC) each 10 245.00 2450.00
pipe 50 mm outer dia.
Extra fo fitting & wastage 735.00
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 0.99 207.00 204.93
TOTAL 3569.75
Add 1% for water charges 35.70
TOTAL 3605.45
Add for contractor’s profit and 540.82
overheads @15%
Cost of 10 metres 4146.26
Cost of 1 metres 414.63
Say 414.63

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.7 62.50 mm nominal inner dia Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8642 Chlorinated Polyvinyl - chloride (CPVC) each 10 783.00 7830.00
pipe 62.5 mm outer dia.
Extra fo fitting & wastage 2349.00
Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 1.32 207.00 273.24
TOTAL 10656.36
Add 1% for water charges 106.56
TOTAL 10762.92
Add for contractor’s profit and 1614.44
overheads @15%
Cost of 10 metres 12377.36
Cost of 1 metres 1237.74
Say 1237.74

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.8 75 mm nominal inner dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8643 Chlorinated Polyvinyl - chloride (CPVC) each 10 1030.00 10300.00
pipe 75 mm outer dia.
Extra fo fitting & wastage 3090.00
Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
115 Coolie Day 0.66 207.00 136.62
114 Beldar Day 1.32 207.00 273.24
TOTAL 13867.36
Add 1% for water charges 138.67
TOTAL 14006.03
Add for contractor’s profit and 2100.91
overheads @15%
Cost of 10 metres 16106.94
Cost of 1 metres 1610.69
Say 1610.69

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.9 100mm nominal inner dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8644 Chlorinated Polyvinyl - chloride (CPVC) each 10 1430.00 14300.00
pipe 100 mm outer dia.
Extra fo fitting & wastage 4290.00
Labour:
116 Fitter (grade 1) Day 0.37 270.00 99.90
115 Coolie Day 0.8 207.00 165.60
114 Beldar Day 1.77 207.00 366.39
TOTAL 19221.89
Add 1% for water charges 192.22
TOTAL 19414.11
Add for contractor’s profit and 2912.12
overheads @15%
Cost of 10 metres 22326.23
Cost of 1 metres 2232.62
Say 2232.62

18.9 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot
& cold water supply including all CPVC plain & brass threaded fittings, this included jointing of pipes
& fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as
per direction of Engineer in Charge. (External work).
18.9.10 150 mm nominal inner dia .Pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
8645 Chlorinated Polyvinyl - chloride (CPVC) each 10 2490.00 24900.00
pipe 150 mm outer dia.
Extra fo fitting & wastage 7470.00
Labour:
116 Fitter (grade 1) Day 0.58 270.00 156.60
115 Coolie Day 1.2 207.00 248.40
114 Beldar Day 2.74 207.00 567.18
TOTAL 33342.18
Add 1% for water charges 333.42
TOTAL 33675.60
Add for contractor’s profit and 5051.34
overheads @15%
Cost of 10 metres 38726.94
Cost of 1 metres 3872.69
Say 3872.69

18.10 Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and
making good the walls etc. Iinternal work - Exposed on wall:
18.10.1 15 mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1545 G.I. pipes 15 mm dia metre 11.5 100.00 1150.00
2271 Carriage of pipe tonne 0.014145 47.29 0.67
9,999 White lead, hemp, oil etc. L.S. 8.06 1.00 8.06
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 1534.36
Add 1% for water charges 15.34
TOTAL 1549.70
Add for contractor’s profit and 232.46
overheads @15%
Cost of 10 metres 1782.16
Cost of 1 metres 178.22
Say 178.22

18.10 Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and
making good the walls etc. Iinternal work - Exposed on wall:
18.10.2 20 mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1546 G.I. pipes 20 mm dia metre 11.5 120.00 1380.00
2271 Carriage of pipe tonne 0.018285 47.29 0.86
9,999 White lead, hemp, oil etc. L.S. 8.06 1.00 8.06
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.82 223.00 182.86
114 Beldar Day 0.66 207.00 136.62
TOTAL 1800.23
Add 1% for water charges 18.00
TOTAL 1818.24
Add for contractor’s profit and 272.74
overheads @15%
Cost of 10 metres 2090.97
Cost of 1 metres 209.10
Say 209.10

18.10 Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and
making good the walls etc. Iinternal work - Exposed on wall:
18.10.3 25 mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1547 G.I. pipes 25 mm dia metre 11.5 175.00 2012.50
2271 Carriage of pipe tonne 0.028289 47.29 1.34
9,999 White lead, hemp, oil etc. L.S. 9.49 1.00 9.49
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.66 207.00 136.62
TOTAL 2471.75
Add 1% for water charges 24.72
TOTAL 2496.47
Add for contractor’s profit and 374.47
overheads @15%
Cost of 10 metres 2870.94
Cost of 1 metres 287.09
Say 287.09

18.10 Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and
making good the walls etc. Iinternal work - Exposed on wall:
18.10.4 32 mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1548 G.I. pipes 32 mm dia metre 11.5 250.00 2875.00
2271 Carriage of pipe tonne 0.036455 47.29 1.72
9,999 White lead, hemp, oil etc. L.S. 9.49 1.00 9.49
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.98 223.00 218.54
114 Beldar Day 0.98 207.00 202.86
TOTAL 3400.87
Add 1% for water charges 34.01
TOTAL 3434.88
Add for contractor’s profit and 515.23
overheads @15%
Cost of 10 metres 3950.12
Cost of 1 metres 395.01
Say 395.01

18.10 Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and
making good the walls etc. Iinternal work - Exposed on wall:
18.10.5 40 mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1549 G.I. pipes 40 mm dia metre 11.5 290.00 3335.00
2271 Carriage of pipe tonne 0.041975 47.29 1.98
9,999 White lead, hemp, oil etc. L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.31 223.00 292.13
114 Beldar Day 1.31 207.00 271.17
TOTAL 4008.23
Add 1% for water charges 40.08
TOTAL 4048.32
Add for contractor’s profit and 607.25
overheads @15%
Cost of 10 metres 4655.56
Cost of 1 metres 465.56
Say 465.56

18.10 Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and
making good the walls etc. Iinternal work - Exposed on wall:
18.10.6 50 mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1550 G.I. pipes 50 mm dia metre 11.5 350.00 4025.00
2271 Carriage of pipe tonne 0.059455 47.29 2.81
9,999 White lead, hemp, oil etc. L.S. 13.52 1.00 13.52
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 1.64 223.00 365.72
114 Beldar Day 1.64 207.00 339.48
TOTAL 4840.96
Add 1% for water charges 48.41
TOTAL 4889.37
Add for contractor’s profit and 733.41
overheads @15%
Cost of 10 metres 5622.78
Cost of 1 metres 562.28
Say 562.28

18.11 Concealed pipe including painting with anti corrosive bitumastic paint, cutting chases and
making good the wall
18.11.1 15 m m dia nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1545 G.I. pipes 15 mm dia metre 11.5 100.00 1150.00
2271 Carriage of pipe tonne 0.014145 47.29 0.67
9,999 White lead, hemp, oil etc. L.S. 8.06 1.00 8.06
Painting G.I. pipe with anti-corrosive metre 10 3.07 30.71
bitumastic paint tw o or more coats
(Rate same as per item no. 18.40.1 A
Making chases upto 7.5x7.5cm in walls metre 10 53.67 536.72
and making good the same Rate as per
item no. 18.78 A
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2099.06
Add 1% for water charges except on A 15.32

TOTAL 2114.37
Add for contractor’s profit and 232.04
overheads @15% except on A
Cost of 10 metres 2346.41
Cost of 1 metres 234.64
Say 234.64

18.11 Concealed pipe including painting with anti corrosive bitumastic paint, cutting chases and
making good the wall
18.11.2 20 mm dia nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1546 G.I. pipes 20 mm dia metre 11.5 120.00 1380.00
2271 Carriage of pipe tonne 0.014145 47.29 0.67
9,999 White lead, hemp, oil etc. L.S. 8.06 1.00 8.06
Painting G.I. pipe with anti-corrosive metre 10 3.62 36.16
bitumastic paint two or more coats
(Rate same as per item no. 18.40.1 A
Making chases upto 7.5x7.5cm in walls metre 10 53.67 536.72
and making good the same Rate as per
item no. 18.78 A
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
117 Astt. Fitter Day 0.66 223.00 147.18
114 Beldar Day 0.66 207.00 136.62
TOTAL 2334.51
Add 1% for water charges except on A 17.62

TOTAL 2352.13
Add for contractor’s profit and 266.89
overheads @15% except on A
Cost of 10 metres 2619.02
Cost of 1 metres 261.90
Say 261.90

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.1 15work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1545 G.I. pipes 15 mm dia metre 10.2 100.00 1020.00
2271 Carriage of pipe tonne 0.012456 47.29 0.59
9,999 White lead, hemp, oil etc. L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
114 Beldar Day 0.82 207.00 169.74
115 Coolie Day 0.66 207.00 136.62
TOTAL 1353.88
Add 1% for water charges except on A 13.54

TOTAL 1367.42
Add for contractor’s profit and 205.11
overheads @15% except on A
Cost of 10 metres 1572.53
Cost of 1 metres 157.25
Say 157.25

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.2 20work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1546 G.I. pipes 20 mm dia metre 10.2 120.00 1224.00
2271 Carriage of pipe tonne 0.016218 47.29 0.77
9,999 White lead, hemp, oil etc. L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 0.08 270.00 21.60
114 Beldar Day 0.82 207.00 169.74
115 Coolie Day 0.66 207.00 136.62
TOTAL 1558.06
Add 1% for water charges except on A 15.58

TOTAL 1573.64
Add for contractor’s profit and 236.05
overheads @15% except on A
Cost of 10 metres 1809.68
Cost of 1 metres 180.97
Say 180.97

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.3 25work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1547 G.I. pipes 25 mm dia metre 10.2 175.00 1785.00
2271 Carriage of pipe tonne 0.025092 47.29 1.19
9,999 White lead, hemp, oil etc. L.S. 6.76 1.00 6.76
Labour:
116 Fitter (grade 1) Day 0.12 270.00 32.40
114 Beldar Day 0.91 207.00 188.37
115 Coolie Day 0.66 207.00 136.62
TOTAL 2150.34
Add 1% for water charges except on A 21.50

TOTAL 2171.84
Add for contractor’s profit and 325.78
overheads @15% except on A
Cost of 10 metres 2497.62
Cost of 1 metres 249.76
Say 249.76

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.4 32work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1548 G.I. pipes 32 mm dia metre 10.2 250.00 2550.00
2271 Carriage of pipe tonne 0.032334 47.29 1.53
9,999 White lead, hemp, oil etc. L.S. 6.76 1.00 6.76
Labour:
116 Fitter (grade 1) Day 0.12 270.00 32.40
114 Beldar Day 0.91 207.00 188.37
115 Coolie Day 0.66 207.00 136.62
TOTAL 2915.68
Add 1% for water charges except on A 29.16

TOTAL 2944.84
Add for contractor’s profit and 441.73
overheads @15% except on A
Cost of 10 metres 3386.56
Cost of 1 metres 338.66
Say 338.66

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.5 40work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1549 G.I. pipes 40 mm dia metre 10.2 290.00 2958.00
2271 Carriage of pipe tonne 0.03723 47.29 1.76
9,999 White lead, hemp, oil etc. L.S. 9.49 1.00 9.49
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
114 Beldar Day 0.99 207.00 204.93
115 Coolie Day 0.66 207.00 136.62
TOTAL 3354.00
Add 1% for water charges except on A 33.54

TOTAL 3387.54
Add for contractor’s profit and 508.13
overheads @15% except on A
Cost of 10 metres 3895.67
Cost of 1 metres 389.57
Say 389.57

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.6 50work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1550 G.I. pipes 50 mm dia metre 10.2 350.00 3570.00
2271 Carriage of pipe tonne 0.05273 47.29 2.49
9,999 White lead, hemp, oil etc. L.S. 9.49 1.00 9.49
Labour:
116 Fitter (grade 1) Day 0.16 270.00 43.20
114 Beldar Day 0.99 207.00 204.93
115 Coolie Day 0.66 207.00 136.62
TOTAL 3966.73
Add 1% for water charges except on A 39.67

TOTAL 4006.40
Add for contractor’s profit and 600.96
overheads @15% except on A
Cost of 10 metres 4607.36
Cost of 1 metres 460.74
Say 460.74

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.7 65work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1551 G.I. pipes 65 mm dia metre 10.2 475.00 4845.00
2271 Carriage of pipe tonne 0.067626 47.29 3.20
9,999 White lead, hemp, oil etc. L.S. 13.52 1.00 13.52
Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
114 Beldar Day 1.32 207.00 273.24
115 Coolie Day 0.66 207.00 136.62
TOTAL 5339.08
Add 1% for water charges except on A 53.39

TOTAL 5392.47
Add for contractor’s profit and 808.87
overheads @15% except on A
Cost of 10 metres 6201.34
Cost of 1 metres 620.13
Say 620.13

18.12 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc.
(external
18.12.8 80work):
mm dia. nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
1552 G.I. pipes 80 mm dia metre 10.2 595.00 6069.00
2271 Carriage of pipe tonne 0.088128 47.29 4.17
9,999 White lead, hemp, oil etc. L.S. 13.52 1.00 13.52
Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
114 Beldar Day 1.32 207.00 273.24
115 Coolie Day 0.66 207.00 136.62
TOTAL 6564.05
Add 1% for water charges except on A 65.64

TOTAL 6629.69
Add for contractor’s profit and 994.45
overheads @15% except on A
Cost of 10 metres 7624.14
Cost of 1 metres 762.41
Say 762.41

18.13 Making connection of G.I. distribution branch with G.I. main of following sizes by providing and
fixing tee, including cutting and threading the pipe etc. complete :
18.13.1 25 to 40 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1608 G.I. tees (equal) 25 mm each 1 38.00 38.00
1555 G.I. back (jam) nuts25 mm dia each 1 5.00 5.00
9,999 Carriage L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
114 Beldar Day 0.33 207.00 68.31
TOTAL 205.74
Add 1% for water charges except on A 2.06

TOTAL 207.80
Add for contractor’s profit and 31.17
overheads @15% except on A
Cost of 1 no 238.97
Say 238.97

18.13 Making connection of G.I. distribution branch with G.I. main of following sizes by providing and
fixing tee, including cutting and threading the pipe etc. complete :
18.13.2 50 to 80 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no
Materials:
1612 G.I. tees (equal) 65 mm each 1 215.00 215.00
1559 G.I. back (jam) nuts65 mm dia each 1 15.00 15.00
9,999 Carriage L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 0.45 270.00 121.50
114 Beldar Day 0.45 207.00 93.15
TOTAL 449.98
Add 1% for water charges except on A 4.50

TOTAL 454.48
Add for contractor’s profit and 68.17
overheads @15% except on A
Cost of 1 no 522.65
Say 522.65

18.14 Fixing water meter and stop cock in G.I. pipe line including cutting and threading the pipe and
making long screws etc. complete (cost of water meter and stop cock to be paid separately).
Code Description Unit Quantity Rate Amount
Details of cost for one meter with stop cock
Materials:
1555 G.I. back (jam) nuts25 mm dia each 1 5.00 5.00
9,999 Carriage L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 0.33 270.00 89.10
114 Beldar Day 0.33 207.00 68.31
TOTAL 167.74
Add 1% for water charges except on A 1.68

TOTAL 169.42
Add for contractor’s profit and 25.41
overheads @15% except on A
Cost of 1 no 194.83
Say 194.83

18.15 Providing and fixing brass bib cock of approved quality :


18.15.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one meter with stop cock
Materials:
1339 Brass bib-cock 15 mm dia each 1 157.00 157.00
9,999 Carriage & fixing charges L.S. 8.06 1.00 8.06
TOTAL 165.06
Add 1% for water charges except on A 1.65

TOTAL 166.71
Add for contractor’s profit and 25.01
overheads @15% except on A
Cost of 1 no 191.72
Say 191.72

18.15 Providing and fixing brass bib cock of approved quality:


18.15.2 20 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one meter with stop cock
Materials:
1340 Brass bib-cock 20 mm dia each 1 193.00 193.00
9,999 Carriage & fixing charges L.S. 9.49 1.00 9.49
TOTAL 202.49
Add 1% for water charges except on A 2.02

TOTAL 204.51
Add for contractor’s profit and 30.68
overheads @15% except on A
Cost of 1 no 235.19
Say 235.19

18.16 Providing and fixing brass stop cock of approved quality :


18.16.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one meter with stop cock
Materials:
1342 Brass stop-cock 15 mm dia each 1 157.00 157.00
9,999 Carriage & fixing charges L.S. 8.06 1.00 8.06
TOTAL 165.06
Add 1% for water charges except on A 1.65
TOTAL 166.71
Add for contractor’s profit and 25.01
overheads @15% except on A
Cost of 1 no 191.72
Say 191.72

18.16 Providing and fixing brass stop cock of approved quality :


18.16.2 20 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one meter with stop cock
Materials:
1343 Brass stop-cock 20 mm dia each 1 193.00 193.00
9,999 Carriage & fixing charges L.S. 9.49 1.00 9.49
TOTAL 202.49
Add 1% for water charges except on A 2.02

TOTAL 204.51
Add for contractor’s profit and 30.68
overheads @15% except on A
Cost of 1 no 235.19
Say 235.19

18.17 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end):
18.17.1 25 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1927 25mm dia. Gun metal gate valve with each 1 235.00 235.00
wheel
9,999 Carriage & fixing charges L.S. 10.79 1.00 10.79
TOTAL 245.79
Add 1% for water charges except on A 2.46

TOTAL 248.25
Add for contractor’s profit and 37.24
overheads @15% except on A
Cost of 1 no 285.49
Say 285.49

18.17 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end):
18.17.2 32 mm nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1928 32mm dia. Gun metal gate valve with each 1 296.00 296.00
wheel
9,999 Carriage & fixing charges L.S. 12.22 1.00 12.22
TOTAL 308.22
Add 1% for water charges except on A 3.08

TOTAL 311.30
Add for contractor’s profit and 46.70
overheads @15% except on A
Cost of 1 no 358.00
Say 358.00

18.17 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end):
18.17.3 40 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1929 40mm dia. Gun metal gate valve with each 1 330.00 330.00
wheel
9,999 Carriage & fixing charges L.S. 13.52 1.00 13.52
TOTAL 343.52
Add 1% for water charges except on A 3.44

TOTAL 346.96
Add for contractor’s profit and 52.04
overheads @15% except on A
Cost of 1 no 399.00
Say 399.00

18.17 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end):
18.17.4 50 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1930 50mm dia. Gun metal gate valve with each 1 483.00 483.00
wheel
9,999 Carriage & fixing charges L.S. 14.82 1.00 14.82
TOTAL 497.82
Add 1% for water charges except on A 4.98

TOTAL 502.80
Add for contractor’s profit and 75.42
overheads @15% except on A
Cost of 1 no 578.22
Say 578.22
18.17 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end):
18.17.5 65 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1931 65mm dia. Gun metal gate valve with each 1 700.00 700.00
wheel
9,999 Carriage & fixing charges L.S. 16.12 1.00 16.12
TOTAL 716.12
Add 1% for water charges except on A 7.16

TOTAL 723.28
Add for contractor’s profit and 108.49
overheads @15% except on A
Cost of 1 no 831.77
Say 831.77

18.17 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end):
18.17.6 80 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1932 80mm dia. Gun metal gate valve with each 1 1160.00 1160.00
wheel
9,999 Carriage & fixing charges L.S. 18.85 1.00 18.85
TOTAL 1178.85
Add 1% for water charges except on A 11.79

TOTAL 1190.64
Add for contractor’s profit and 178.60
overheads @15% except on A
Cost of 1 no 1369.23
Say 1369.23

18.18 Providing and fixing ball valve (brass) of approved quality complete :
18.18.1 High or low pressure with plastic floats:
18.18.1.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1922 15 mm dia ball valve each 1 175.00 175.00
9,999 Carriage & fixing charges L.S. 21.58 1.00 21.58
TOTAL 196.58
Add 1% for water charges except on A 1.97

TOTAL 198.55
Add for contractor’s profit and 29.78
overheads @15% except on A
Cost of 1 no 228.33
Say 228.33

18.18 Providing and fixing ball valve (brass) of approved quality complete :
18.18.1 High or low pressure with plastic floats :
18.18.1.2 20 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1923 20 mm dia ball valve each 1 260.00 260.00
9,999 Carriage & fixing charges L.S. 26.91 1.00 26.91
TOTAL 286.91
Add 1% for water charges except on A 2.87

TOTAL 289.78
Add for contractor’s profit and 43.47
overheads @15% except on A
Cost of 1 no 333.25
Say 333.25

18.18 Providing and fixing ball valve (brass) of approved quality complete :
18.18.1 High or low pressure with plastic floats:
18.18.1.3 25 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1924 25 mm dia ball valve each 1 300.00 300.00
9,999 Carriage & fixing charges L.S. 32.24 1.00 32.24
TOTAL 332.24
Add 1% for water charges except on A 3.32

TOTAL 335.56
Add for contractor’s profit and 50.33
overheads @15% except on A
Cost of 1 no 385.90
Say 385.90

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.1 25 mm nominal bore
18.19.1.1 Horizontal
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1933 25mm non return valve each 1 238.00 238.00
9,999 Carriage & fixing charges L.S. 13.52 1.00 13.52
TOTAL 251.52
Add 1% for water charges except on A 2.52

TOTAL 254.04
Add for contractor’s profit and 38.11
overheads @15% except on A
Cost of 1 no 292.14
Say 292.14

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.1 25 mm nominal bore
18.19.1.2 Vertical
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
3080 25mm non return valve each 1 455.00 455.00
9,999 Carriage & fixing charges L.S. 13.52 1.00 13.52
TOTAL 468.52
Add 1% for water charges except on A 4.69

TOTAL 473.21
Add for contractor’s profit and 70.98
overheads @15% except on A
Cost of 1 no 544.19
Say 544.19

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.2 32 mm nominal bore
18.19.2.1 Horizontal
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1934 32mm non return valve each 1 305.00 305.00
9,999 Carriage & fixing charges L.S. 14.82 1.00 14.82
TOTAL 319.82
Add 1% for water charges except on A 3.20

TOTAL 323.02
Add for contractor’s profit and 48.45
overheads @15% except on A
Cost of 1 no 371.47
Say 371.47

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.2 32 mm nominal bore
18.19.2.2 Vertical
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
3084 32mm non return valve each 1 550.00 550.00
9,999 Carriage & fixing charges L.S. 14.82 1.00 14.82
TOTAL 564.82
Add 1% for water charges except on A 5.65

TOTAL 570.47
Add for contractor’s profit and 85.57
overheads @15% except on A
Cost of 1 no 656.04
Say 656.04

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.3 40 mm nominal bore
18.19.3.1 Horizontal
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1935 40mm non return valve each 1 410.00 410.00
9,999 Carriage & fixing charges L.S. 16.12 1.00 16.12
TOTAL 426.12
Add 1% for water charges except on A 4.26

TOTAL 430.38
Add for contractor’s profit and 64.56
overheads @15% except on A
Cost of 1 no 494.94
Say 494.94

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.3 40 mm nominal bore
18.19.3.2 Vertical
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
3088 40mm non return valve each 1 680.00 680.00
9,999 Carriage & fixing charges L.S. 16.12 1.00 16.12
TOTAL 696.12
Add 1% for water charges except on A 6.96

TOTAL 703.08
Add for contractor’s profit and 105.46
overheads @15% except on A
Cost of 1 no 808.54
Say 808.54

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.4 50 mm nominal bore
18.19.4.1 Horizontal
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1936 50mm non return valve each 1 618.00 618.00
9,999 Carriage & fixing charges L.S. 17.55 1.00 17.55
TOTAL 635.55
Add 1% for water charges except on A 6.36

TOTAL 641.91
Add for contractor’s profit and 96.29
overheads @15% except on A
Cost of 1 no 738.19
Say 738.19

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.4 50 mm nominal bore
18.19.4.2 Vertical
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
3092 50mm non return valve each 1 900.00 900.00
9,999 Carriage & fixing charges L.S. 17.55 1.00 17.55
TOTAL 917.55
Add 1% for water charges except on A 9.18

TOTAL 926.73
Add for contractor’s profit and 139.01
overheads @15% except on A
Cost of 1 no 1065.73
Say 1065.73

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.5 65 mm nominal bore
18.19.5.1 Horizontal
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1937 65mm non return valve each 1 1085.00 1085.00
9,999 Carriage & fixing charges L.S. 18.85 1.00 18.85
TOTAL 1103.85
Add 1% for water charges except on A 11.04

TOTAL 1114.89
Add for contractor’s profit and 167.23
overheads @15% except on A
Cost of 1 no 1282.12
Say 1282.12

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.5 65 mm nominal bore.
18.19.5.2 Vertical
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
3096 65mm non return valve each 1 1050.00 1050.00
9,999 Carriage & fixing charges L.S. 18.85 1.00 18.85
TOTAL 1068.85
Add 1% for water charges except on A 10.69

TOTAL 1079.54
Add for contractor’s profit and 161.93
overheads @15% except on A
Cost of 1 no 1241.47
Say 1241.47

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.6 80 mm nominal bore
18.19.6.1 Horizontal
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1938 80mm non return valve each 1 1540.00 1540.00
9,999 Carriage & fixing charges L.S. 20.28 1.00 20.28
TOTAL 1560.28
Add 1% for water charges except on A 15.60

TOTAL 1575.88
Add for contractor’s profit and 236.38
overheads @15% except on A
Cost of 1 no 1812.27
Say 1812.27

18.19 Providing and fixing gun metal non-return valve of approved quality (screwed end):
18.19.6 80 mm nominal bore
18.19.6.2 Vertical
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
3300 65mm non return valve each 1 2038.00 2038.00
9,999 Carriage & fixing charges L.S. 20.28 1.00 20.28
TOTAL 2058.28
Add 1% for water charges except on A 20.58

TOTAL 2078.86
Add for contractor’s profit and 311.83
overheads @15% except on A
Cost of 1 no 2390.69
Say 2390.69

18.20 Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the
main :
18.20.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1360 15mrn diameter brass-ferrule each 1 80.00 80.00
9,999 Carriage & fixing charges L.S. 40.3 1.00 40.30
TOTAL 120.30
Add 1% for water charges except on A 1.20

TOTAL 121.50
Add for contractor’s profit and 18.23
overheads @15% except on A
Cost of 1 no 139.73
Say 139.73

18.20 Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the
main : 20 mm nominal bore
18.20.2
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1361 20mrn diameter brass-ferrule each 1 114.00 114.00
9,999 Carriage & fixing charges L.S. 47.19 1.00 47.19
TOTAL 161.19
Add 1% for water charges except on A 1.61

TOTAL 162.80
Add for contractor’s profit and 24.42
overheads @15% except on A
Cost of 1 no 187.22
Say 187.22

18.20 Providing and fixing brass ferrule with C.I. mouth cover including boring and tapping the
main :
18.20.3 25 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1362 25mrn diameter brass-ferrule each 1 156.00 156.00
9,999 Carriage & fixing charges L.S. 53.82 1.00 53.82
TOTAL 209.82
Add 1% for water charges except on A 2.10

TOTAL 211.92
Add for contractor’s profit and 31.79
overheads @15% except on A
Cost of 1 no 243.71
Say 243.71

18.21 Providing and fixing uplasticised PVC connection pipe with brass unions :
18.21.1 30 cm length
18.21.1.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1687 15mm P.V.C. connection.pipe with brass each 1 18.00 18.00

9,999 Carriage & fixing charges L.S. 12.22 1.00 12.22


TOTAL 30.22
Add 1% for water charges except on A 0.30

TOTAL 30.52
Add for contractor’s profit and 4.58
overheads @15% except on A
Cost of 1 no 35.10
Say 35.10

18.21 Providing and fixing uplasticised PVC connection pipe with brass unions :
18.21.1 30 cm length
18.21.1.2 20 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1688 20mm P.V.C. connection.pipe with brass each 1 25.00 25.00

9,999 Carriage & fixing charges L.S. 12.22 1.00 12.22


TOTAL 37.22
Add 1% for water charges except on A 0.37

TOTAL 37.59
Add for contractor’s profit and 5.64
overheads @15% except on A
Cost of 1 no 43.23
Say 43.23

18.21 Providing and fixing uplasticised PVC connection pipe with brass unions :
18.21.2 45 cm length
18.21.2.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1689 15mm P.V.C. connection.pipe with brass each 1 25.00 25.00
9,999 Unions
Carriage & fixing charges L.S. 13.52 1.00 13.52
TOTAL 38.52
Add 1% for water charges except on A 0.39

TOTAL 38.91
Add for contractor’s profit and 5.84
overheads @15% except on A
Cost of 1 no 44.74
Say 44.74

18.21 Providing and fixing uplasticised PVC connection pipe with brass unions :
18.21.2 45 cm length
18.21.2.2 20 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1690 20mm P.V.C. connection.pipe with brass each 1 35.00 35.00
Unions
9,999 Carriage & fixing charges L.S. 13.52 1.00 13.52
TOTAL 48.52
Add 1% for water charges except on A 0.49
TOTAL 49.01
Add for contractor’s profit and 7.35
overheads @15% except on A
Cost of 1 no 56.36
Say 56.36

18.22 Providing and fixing C.P. brass shower rose with 15 or 20 mm inlet:
18.22.1 100 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1878 100mm dia. C,P., brass shower rose each 1 28.00 28.00
9,999 Carriage & fixing charges L.S. 6.76 1.00 6.76
TOTAL 34.76
Add 1% for water charges except on A 0.35

TOTAL 35.11
Add for contractor’s profit and 5.27
overheads @15% except on A
Cost of 1 no 40.37
Say 40.37

18.22 Providing and fixing C.P. brass shower rose with 15 or 20 mm inlet:
18.22.2 150 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials:
1879 150mm dia. C,P., brass shower rose each 1 40.00 40.00
9,999 Carriage & fixing charges L.S. 8.06 1.00 8.06
TOTAL 48.06
Add 1% for water charges except on A 0.48

TOTAL 48.54
Add for contractor’s profit and 7.28
overheads @15% except on A
Cost of 1 no 55.82
Say 55.82

18.23 Laying in position centrifugally cast (spun) iron S&S or flanged pipes (excluding cost
Code
of pipe) Description Unit Quantity Rate Amount
Details of cost for 5.14 quintal
Labour for laying pipe
116 Fitter (grade 1) Day 0.17 270.00 45.90
117 Astt. Fitter Day 0.17 223.00 37.91
114 Beldar Day 1.33 207.00 275.31
9,999 Cement, sand and grit etc. L.S. 16.12 1.00 16.12
TOTAL 375.24
Add 1% for water charges 3.75
TOTAL 378.99
Add for contractor’s profit and 56.85
overheads @15%
Cost of 5.14 quintal 435.84
Cost of 1 quintal 84.79
Say 84.79

18.24 Laying in position S&S or flanged C.I. special such tees, bends collars, tapers and caps
etc. (excluding cost of specials).
Details of cost for 7 quintal
Labour for laying pipe
116 Fitter (grade 1) Day 0.93 270.00 251.10
117 Astt. Fitter Day 0.62 223.00 138.26
114 Beldar Day 2.48 207.00 513.36
9,999 Cement, sand and grit etc. L.S. 40.17 1.00 40.17
TOTAL 942.89
Add 1% for water charges 9.43
TOTAL 952.32
Add for contractor’s profit and 142.85
overheads @15%
Cost of 7 quintal 1095.17
Cost of 1 quintal 156.45
Say 156.45

18.25 Providing and laying S&S C.I. standard specials such as tees, bends, collars, tapers,
caps etc.(Heavy class):
18.25.1 Upto 300 mm dia.
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
1464 Cost of specials quintal 1 2400.00 2400.00
2309 Carriage tonne 0.1 47.29 4.73
LABOUR

A For laying rate as per Item No 18.24 quintal 1 156.45 156.45


TOTAL 2561.18
Add 1% for water charges except on A 24.05

TOTAL 2585.23
Add for contractor’s profit and 364.32
overheads @15% except on A
Cost of 1 quintal 2949.55
Say 2949.55

18.25 Providing and laying S&S C.I. standard specials such as tees, bends, collars, tapers,
caps etc.(Heavy class):
18.25.2 Over 300 mm dia.
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
1466 Cost of specials quintal 1 2595.00 2595.00
2309 Carriage tonne 0.1 47.29 4.73
LABOUR

A For laying rate as per Item No 18.24 quintal 1 156.45 156.45


TOTAL 2756.18
Add 1% for water charges except on A 26.00

TOTAL 2782.18
Add for contractor’s profit and 393.86
overheads @15% except on A
Cost of 1 quintal 3176.04
Say 3176.04

18.26 Providing and laying flanged C.I. standard specials such as tees, bends, collars,
tapers, caps etc., suitable for flanged jointing as per IS : 1538 :
18.26.1 Upto 300 mm dia.
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
1468 Cost of specials quintal 1 4320.00 4320.00
2309 Carriage tonne 0.1 47.29 4.73
LABOUR

A For laying rate as per Item No 18.24 quintal 1 156.45 156.45


TOTAL 4481.18
Add 1% for water charges except on A 43.25

TOTAL 4524.43
Add for contractor’s profit and 655.20
overheads @15% except on A
Cost of 1 quintal 5179.63
Say 5179.63

18.26 Providing and laying flanged C.I. standard specials such as tees, bends, collars,
tapers, caps etc., suitable for flanged jointing as per IS : 1538 :
18.26.2 Over 300 mm dia.
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
1470 Cost of specials quintal 1 4772.00 4772.00
2309 Carriage tonne 0.1 47.29 4.73
LABOUR

A For laying rate as per Item No 18.24 quintal 1 156.45 156.45


TOTAL 4933.18
Add 1% for water charges except on A 47.77

TOTAL 4980.95
Add for contractor’s profit and 723.67
overheads @15% except on A
Cost of 1 quintal 5704.62
Say 5704.62

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.1 100 mm dia, pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7697 Cost of pipe metre 10 624.00 6240.00
2319 Carriage 100metre 0.1 116.3 11.63
LABOUR

A For laying rate as per Item No 18.23 quintal 1.98 84.79 167.89
TOTAL 6419.52
Add 1% for water charges except on A 62.52

TOTAL 6482.04
Add for contractor’s profit and 947.12
overheads @15% except on A
Cost of 10 metres 7429.16
Cost of 1 metre 742.92
Say 742.92

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.2 125 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7698 Cost of pipe metre 10 763.00 7630.00
2320 Carriage 100metre 0.1 155.35 15.54
LABOUR

A For laying rate as per Item No 18.23 quintal 2.58 84.79 218.77
TOTAL 7864.30
Add 1% for water charges except on A 76.46

TOTAL 7940.76
Add for contractor’s profit and 1158.30
overheads @15% except on A
Cost of 10 metres 9099.06
Cost of 1 metre 909.91
Say 909.91

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.3 150 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7699 Cost of pipe metre 10 901.00 9010.00
2321 Carriage 100metre 0.1 193.83 19.38
LABOUR

A For laying rate as per Item No 18.23 quintal 3.22 84.79 273.04
TOTAL 9302.42
Add 1% for water charges except on A 90.29

TOTAL 9392.71
Add for contractor’s profit and 1367.95
overheads @15% except on A
Cost of 10 metres 10760.67
Cost of 1 metre 1076.07
Say 1076.07

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.4 200 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7700 Cost of pipe metre 10 1252.00 12520.00
2322 Carriage 100metre 0.1 315.3 31.53
LABOUR
A For laying rate as per Item No 18.23 quintal 4.71 84.79 399.38
TOTAL 12950.91
Add 1% for water charges except on A 125.52

TOTAL 13076.43
Add for contractor’s profit and 1901.56
overheads @15% except on A
Cost of 10 metres 14977.98
Cost of 1 metre 1497.80
Say 1497.80

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.5 250 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7701 Cost of pipe metre 10 1779.00 17790.00
2323 Carriage 100metre 0.1 448.05 44.81
LABOUR

A For laying rate as per Item No 18.23 quintal 6.35 84.79 538.44
TOTAL 18373.25
Add 1% for water charges except on A 178.35

TOTAL 18551.60
Add for contractor’s profit and 2701.97
overheads @15% except on A
Cost of 10 metres 21253.57
Cost of 1 metre 2125.36
Say 2125.36

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.6 300 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7702 Cost of pipe metre 10 2366.00 23660.00
2324 Carriage 100metre 0.1 553.8 55.38
LABOUR

A For laying rate as per Item No 18.23 quintal 8.18 84.79 693.62
TOTAL 24409.00
Add 1% for water charges except on A 237.15

TOTAL 24646.15
Add for contractor’s profit and 3592.88
overheads @15% except on A
Cost of 10 metres 28239.03
Cost of 1 metre 2823.90
Say 2823.90

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.7 350 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7703 Cost of pipe metre 10 2918.00 29180.00
2325 Carriage 100metre 0.1 775.32 77.53
LABOUR

A For laying rate as per Item No 18.23 quintal 10.31 84.79 874.23
TOTAL 30131.76
Add 1% for water charges except on A 292.58

TOTAL 30424.33
Add for contractor’s profit and 4432.52
overheads @15% except on A
Cost of 10 metres 34856.85
Cost of 1 metre 3485.68
Say 3485.68

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.8 400 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7704 Cost of pipe metre 10 3574.00 35740.00
2326 Carriage 100metre 0.1 1,057.26 105.73
LABOUR

A For laying rate as per Item No 18.23 quintal 12.55 84.79 1064.16
TOTAL 36909.89
Add 1% for water charges except on A 358.46

TOTAL 37268.35
Add for contractor’s profit and 5430.63
overheads @15% except on A
Cost of 10 metres 42698.98
Cost of 1 metre 4269.90
Say 4269.90

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.9 450 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7705 Cost of pipe metre 10 4276.00 42760.00
2327 Carriage 100metre 0.1 1,292.20 129.22
LABOUR

A For laying rate as per Item No 18.23 quintal 15.13 84.79 1282.93
TOTAL 44172.15
Add 1% for water charges except on A 428.89

TOTAL 44601.05
Add for contractor’s profit and 6497.72
overheads @15% except on A
Cost of 10 metres 51098.76
Cost of 1 metre 5109.88
Say 5109.88

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.10 500 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7706 Cost of pipe metre 10 5211.00 52110.00
2328 Carriage 100metre 0.1 1,292.20 129.22
LABOUR

A For laying rate as per Item No 18.23 quintal 17.71 84.79 1501.70
TOTAL 53740.92
Add 1% for water charges except on A 522.39

TOTAL 54263.31
Add for contractor’s profit and 7914.24
overheads @15% except on A
Cost of 10 metres 62177.56
Cost of 1 metre 6217.76
Say 6217.76

18.27 Providing and laying S&S centrifugally cast ( spun) iron pipes (C lass LA )
conforming to IS - 1536
18.27.11 600 mm dia. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7707 Cost of pipe metre 10 6884.00 68840.00
2329 Carriage 100metre 0.1 1,938.30 193.83
LABOUR

A For laying rate as per Item No 18.23 quintal 23.6 84.79 2001.14
TOTAL 71034.97
Add 1% for water charges except on A 690.34

TOTAL 71725.31
Add for contractor’s profit and 10458.63
overheads @15% except on A
Cost of 10 metres 82183.93
Cost of 1 metre 8218.39
Say 8218.39

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.1 100 mm diameter pipe
Materials :-
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 1.7 30.00 51.00
761 Fuel wood kg 0.28 265.00 74.20
771 Kerosene oil litre 0.38 25.00 9.50
9,999 Sundries L.S. 6.76 1.00 6.76
9,999 Carriage of materials L.S. 5.33 1.00 5.33
Labour:
116 Fitter (grade 1) Day 1 270.00 270.00
117 Astt. Fitter Day 1 223.00 223.00
114 Beldar Day 2 207.00 414.00
TOTAL 1053.79
Add 1% for water charges 10.54
TOTAL 1064.33
Add for contractor’s profit and 159.65
overheads @15%
Cost of 10 joints 1223.98
Cost of 1 joint 122.40
Say 122.40

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.2 125 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 2 30.00 60.00
761 Fuel wood kg 0.37 265.00 98.05
771 Kerosene oil litre 0.76 25.00 19.00
9,999 Sundries L.S. 9.49 1.00 9.49
9,999 Carriage of materials L.S. 9.49 1.00 9.49
Labour:
116 Fitter (grade 1) Day 1.5 270.00 405.00
117 Astt. Fitter Day 1.5 223.00 334.50
114 Beldar Day 3 207.00 621.00
TOTAL 1556.53
Add 1% for water charges 15.57
TOTAL 1572.10
Add for contractor’s profit and 235.81
overheads @15%
Cost of 10 joints 1807.91
Cost of 1 joint 180.79
Say 180.79

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.3 150 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 2.3 30.00 69.00
761 Fuel wood kg 0.42 265.00 111.30
771 Kerosene oil litre 0.76 25.00 19.00
9,999 Sundries L.S. 10.79 1.00 10.79
9,999 Carriage of materials L.S. 10.79 1.00 10.79
Labour:
116 Fitter (grade 1) Day 1.5 270.00 405.00
117 Astt. Fitter Day 1.5 223.00 334.50
114 Beldar Day 3 207.00 621.00
TOTAL 1581.38
Add 1% for water charges 15.81
TOTAL 1597.19
Add for contractor’s profit and 239.58
overheads @15%
Cost of 10 joints 1836.77
Cost of 1 joint 183.68
Say 183.68

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.4 200 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 3 30.00 90.00
761 Fuel wood kg 0.56 265.00 148.40
771 Kerosene oil litre 0.76 25.00 19.00
9,999 Sundries L.S. 13.52 1.00 13.52
9,999 Carriage of materials L.S. 13.52 1.00 13.52
Labour:
116 Fitter (grade 1) Day 2 270.00 540.00
117 Astt. Fitter Day 2 223.00 446.00
114 Beldar Day 4 207.00 828.00
TOTAL 2098.44
Add 1% for water charges 20.98
TOTAL 2119.42
Add for contractor’s profit and 317.91
overheads @15%
Cost of 10 joints 2437.34
Cost of 1 joint 243.73
Say 243.73

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.5 250 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 4 30.00 120.00
761 Fuel wood kg 0.65 265.00 172.25
771 Kerosene oil litre 1.14 25.00 28.50
9,999 Sundries L.S. 17.55 1.00 17.55
9,999 Carriage of materials L.S. 17.55 1.00 17.55
Labour:
116 Fitter (grade 1) Day 2.5 270.00 675.00
117 Astt. Fitter Day 2.5 223.00 557.50
114 Beldar Day 5 207.00 1035.00
TOTAL 2623.35
Add 1% for water charges 26.23
TOTAL 2649.58
Add for contractor’s profit and 397.44
overheads @15%
Cost of 10 joints 3047.02
Cost of 1 joint 304.70
Say 304.70

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.6 300 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 5.4 30.00 162.00
761 Fuel wood kg 0.75 265.00 198.75
771 Kerosene oil litre 1.52 25.00 38.00
9,999 Sundries L.S. 20.28 1.00 20.28
9,999 Carriage of materials L.S. 20.28 1.00 20.28
Labour:
116 Fitter (grade 1) Day 3 270.00 810.00
117 Astt. Fitter Day 3 223.00 669.00
114 Beldar Day 6 207.00 1242.00
TOTAL 3160.31
Add 1% for water charges 31.60
TOTAL 3191.91
Add for contractor’s profit and 478.79
overheads @15%
Cost of 10 joints 3670.70
Cost of 1 joint 367.07
Say 367.07

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.7 350 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 6.2 30.00 186.00
761 Fuel wood kg 0.93 265.00 246.45
771 Kerosene oil litre 1.7 25.00 42.50
9,999 Sundries L.S. 24.18 1.00 24.18
9,999 Carriage of materials L.S. 24.18 1.00 24.18
Labour:
116 Fitter (grade 1) Day 3 270.00 810.00
117 Astt. Fitter Day 3 223.00 669.00
114 Beldar Day 6 207.00 1242.00
TOTAL 3244.31
Add 1% for water charges 32.44
TOTAL 3276.75
Add for contractor’s profit and 491.51
overheads @15%
Cost of 10 joints 3768.27
Cost of 1 joint 376.83
Say 376.83

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.8 400 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 7.4 30.00 222.00
761 Fuel wood kg 1.12 265.00 296.80
771 Kerosene oil litre 1.7 25.00 42.50
9,999 Sundries L.S. 26.91 1.00 26.91
9,999 Carriage of materials L.S. 26.91 1.00 26.91
Labour:
116 Fitter (grade 1) Day 4 270.00 1080.00
117 Astt. Fitter Day 4 223.00 892.00
114 Beldar Day 8 207.00 1656.00
TOTAL 4243.12
Add 1% for water charges 42.43
TOTAL 4285.55
Add for contractor’s profit and 642.83
overheads @15%
Cost of 10 joints 4928.38
Cost of 1 joint 492.84
Say 492.84

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.9 450 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 7.9 30.00 237.00
761 Fuel wood kg 1.21 265.00 320.65
771 Kerosene oil litre 2.27 25.00 56.75
9,999 Sundries L.S. 31.07 1.00 31.07
9,999 Carriage of materials L.S. 31.07 1.00 31.07
Labour:
116 Fitter (grade 1) Day 4.5 270.00 1215.00
117 Astt. Fitter Day 4.5 223.00 1003.50
114 Beldar Day 9 207.00 1863.00
TOTAL 4758.04
Add 1% for water charges 47.58
TOTAL 4805.62
Add for contractor’s profit and 720.84
overheads @15%
Cost of 10 joints 5526.46
Cost of 1 joint 552.65
Say 552.65

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.10 500 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 8.5 30.00 255.00
761 Fuel wood kg 1.31 265.00 347.15
771 Kerosene oil litre 2.27 25.00 56.75
9,999 Sundries L.S. 33.67 1.00 33.67
9,999 Carriage of materials L.S. 33.67 1.00 33.67
Labour:
116 Fitter (grade 1) Day 4.75 270.00 1282.50
117 Astt. Fitter Day 4.75 223.00 1059.25
114 Beldar Day 9.5 207.00 1966.50
TOTAL 5034.49
Add 1% for water charges 50.34
TOTAL 5084.83
Add for contractor’s profit and 762.73
overheads @15%
Cost of 10 joints 5847.56
Cost of 1 joint 584.76
Say 584.76

18.28 Providing lead caulked joints to spun iron or C.I. pipes and specials including testing of joints but
excluding the cost of pig lead :
18.28.11 600 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1881 Spun yarn kg 10.2 30.00 306.00
761 Fuel wood kg 1.68 265.00 445.20
771 Kerosene oil litre 2.84 25.00 71.00
9,999 Sundries L.S. 40.3 1.00 40.30
9,999 Carriage of materials L.S. 40.3 1.00 40.30
Labour:
116 Fitter (grade 1) Day 6.5 270.00 1755.00
117 Astt. Fitter Day 6.5 223.00 1449.50
114 Beldar Day 13 207.00 2691.00
TOTAL 6798.30
Add 1% for water charges 67.98
TOTAL 6866.28
Add for contractor’s profit and 1029.94
overheads @15%
Cost of 10 joints 7896.23
Cost of 1 joint 789.62
Say 789.62

18.29 Supplying pig lead at site of work.


Code Description Unit Quantity Rate Amount
Details of cost for 1 quintal
materials-
1397 Lead kilogram 100 58.00 5800.00
2341 Carrigae tonne 0.1 47.29 4.73
TOTAL 5804.73
Add 1% for water charges 58.05
TOTAL 5862.78
Add for contractor’s profit and 879.42
overheads @15%
Cost of 10 joints 6742.19
Say 6742.19

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.1 80 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1956 Bolts and nuts 16 mm dia 60 mm long each 40 8.00 320.00

1373 Insertion rubber washer 3 mm thick each 10 9.00 90.00


Labour:
116 Fitter (grade 1) Day 0.15 270.00 40.50
117 Astt. Fitter Day 0.15 223.00 33.45
114 Beldar Day 0.8 207.00 165.60
9,999 Cement, sand and grit etc. L.S. 2.73 1.00 2.73
TOTAL 652.28
Add 1% for water charges 6.52
TOTAL 658.80
Add for contractor’s profit and 98.82
overheads @15%
Cost of 10 joints 757.62
Cost of 1 joint 75.76
Say 75.76

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.2 100 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1956 Bolts and nuts 16 mm dia 60 mm long each 80 8.00 640.00

1374 Insertion rubber washer 3 mm thick each 10 12.00 120.00


Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
117 Astt. Fitter Day 0.25 223.00 55.75
114 Beldar Day 1 207.00 207.00
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
TOTAL 1094.41
Add 1% for water charges 10.94
TOTAL 1105.35
Add for contractor’s profit and 165.80
overheads @15%
Cost of 10 joints 1271.16
Cost of 1 joint 127.12
Say 127.12

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.3 125 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1957 Bolts and nuts 16 mm dia 65 mm long each 80 8.00 640.00

1375 Insertion rubber washer 3 mm thick each 10 13.00 130.00


Labour:
116 Fitter (grade 1) Day 0.25 270.00 67.50
117 Astt. Fitter Day 0.25 223.00 55.75
114 Beldar Day 1 207.00 207.00
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
TOTAL 1104.41
Add 1% for water charges 11.04
TOTAL 1115.45
Add for contractor’s profit and 167.32
overheads @15%
Cost of 10 joints 1282.77
Cost of 1 joint 128.28
Say 128.28

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.4 150 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1958 Bolts and nuts 20mm dia 65 mm long each 80 12.00 960.00

1376 Insertion rubber washer 3 mm thick each 10 15.00 150.00


Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
117 Astt. Fitter Day 0.3 223.00 66.90
114 Beldar Day 1.1 207.00 227.70
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
TOTAL 1489.76
Add 1% for water charges 14.90
TOTAL 1504.66
Add for contractor’s profit and 225.70
overheads @15%
Cost of 10 joints 1730.36
Cost of 1 joint 173.04
Say 173.04

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.5 200 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1959 Bolts and nuts 20mm dia 70 mm long each 80 12.00 960.00

1377 Insertion rubber washer 3 mm thick each 10 20.00 200.00


Labour:
116 Fitter (grade 1) Day 0.3 270.00 81.00
117 Astt. Fitter Day 0.3 223.00 66.90
114 Beldar Day 1.1 207.00 227.70
9,999 Cement, sand and grit etc. L.S. 4.16 1.00 4.16
TOTAL 1539.76
Add 1% for water charges 15.40
TOTAL 1555.16
Add for contractor’s profit and 233.27
overheads @15%
Cost of 10 joints 1788.43
Cost of 1 joint 178.84
Say 178.84

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.6 250 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1960 Bolts and nuts 20mm dia 75 mm long each 120 12.00 1440.00

1378 Insertion rubber washer 3 mm thick each 10 30.00 300.00


Labour:
116 Fitter (grade 1) Day 0.4 270.00 108.00
117 Astt. Fitter Day 0.4 223.00 89.20
114 Beldar Day 1.3 207.00 269.10
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 2211.63
Add 1% for water charges 22.12
TOTAL 2233.75
Add for contractor’s profit and 335.06
overheads @15%
Cost of 10 joints 2568.81
Cost of 1 joint 256.88
Say 256.88

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.7 300 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1960 Bolts and nuts 20mm dia 75 mm long each 120 12.00 1440.00

1379 Insertion rubber washer 3 mm thick each 10 38.00 380.00


Labour:
116 Fitter (grade 1) Day 0.4 270.00 108.00
117 Astt. Fitter Day 0.4 223.00 89.20
114 Beldar Day 1.3 207.00 269.10
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 2291.63
Add 1% for water charges 22.92
TOTAL 2314.55
Add for contractor’s profit and 347.18
overheads @15%
Cost of 10 joints 2661.73
Cost of 1 joint 266.17
Say 266.17

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.8 350 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1961 Bolts and nuts 20mm dia 80 mm long each 160 13.00 2080.00

1380 Insertion rubber washer 3 mm thick each 10 45.00 450.00


Labour:
116 Fitter (grade 1) Day 0.5 270.00 135.00
117 Astt. Fitter Day 0.5 223.00 111.50
114 Beldar Day 1.5 207.00 310.50
9,999 Cement, sand and grit etc. L.S. 5.33 1.00 5.33
TOTAL 3092.33
Add 1% for water charges 30.92
TOTAL 3123.25
Add for contractor’s profit and 468.49
overheads @15%
Cost of 10 joints 3591.74
Cost of 1 joint 359.17
Say 359.17

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.9 400 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1962 Bolts and nuts 24mm dia 85 mm long each 160 24.00 3840.00

1381 Insertion rubber washer 3 mm thick each 10 66.00 660.00


Labour:
116 Fitter (grade 1) Day 0.5 270.00 135.00
117 Astt. Fitter Day 0.5 223.00 111.50
114 Beldar Day 1.5 207.00 310.50
9,999 Cement, sand and grit etc. L.S. 8.06 1.00 8.06
TOTAL 5065.06
Add 1% for water charges 50.65
TOTAL 5115.71
Add for contractor’s profit and 767.36
overheads @15%
Cost of 10 joints 5883.07
Cost of 1 joint 588.31
Say 588.31

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.10 450 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1962 Bolts and nuts 24mm dia 85 mm long each 200 24.00 4800.00

1382 Insertion rubber washer 3 mm thick each 10 83.00 830.00


Labour:
116 Fitter (grade 1) Day 0.6 270.00 162.00
117 Astt. Fitter Day 0.6 223.00 133.80
114 Beldar Day 1.7 207.00 351.90
9,999 Cement, sand and grit etc. L.S. 8.06 1.00 8.06
TOTAL 6285.76
Add 1% for water charges 62.86
TOTAL 6348.62
Add for contractor’s profit and 952.29
overheads @15%
Cost of 10 joints 7300.91
Cost of 1 joint 730.09
Say 730.09

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.11 500 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1963 Bolts and nuts 24 mm dia 90 mm long each 200 26.00 5200.00

1383 Insertion rubber washer 3 mm thick each 10 106.00 1060.00


Labour:
116 Fitter (grade 1) Day 0.65 270.00 175.50
117 Astt. Fitter Day 0.65 223.00 144.95
114 Beldar Day 1.8 207.00 372.60
9,999 Cement, sand and grit etc. L.S. 8.06 1.00 8.06
TOTAL 6961.11
Add 1% for water charges 69.61
TOTAL 7030.72
Add for contractor’s profit and 1054.61
overheads @15%
Cost of 10 joints 8085.33
Cost of 1 joint 808.53
Say 808.53

18.30 Providing flanged joints to double flanged C.l./ D.I pipes and specials including testing of joints :
18.30.12 600 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 joints
Materials:
1964 Bolts and nuts 27 mm dia 100 mm long each 200 30.00 6000.00

1384 Insertion rubber washer 3 mm thick each 10 118.00 1180.00


Labour:
116 Fitter (grade 1) Day 0.75 270.00 202.50
117 Astt. Fitter Day 0.75 223.00 167.25
114 Beldar Day 2 207.00 414.00
9,999 Cement, sand and grit etc. L.S. 9.49 1.00 9.49
TOTAL 7973.24
Add 1% for water charges 79.73
TOTAL 8052.97
Add for contractor’s profit and 1207.95
overheads @15%
Cost of 10 joints 9260.92
Cost of 1 joint 926.09
Say 926.09

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.1 100 mm diameter
18.31.1.1 Class I
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
1940 100mm dia. sluice valves (with cap) each 10 4400.00 44000.00
2309 Carriage of sluice valves tonne 0.44 47.29 20.81
A Providing flanged joints to sluice valves each 20 127.12 2542.31
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.2)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 4.43 156.45 693.08
TOTAL 47256.21
Add 1% for water charges except on A 440.21

TOTAL 47696.41
Add for contractor’s profit and 6669.15
overheads @15% except on A
Cost of 10 valves 54365.57
Cost of 1 valve 5436.56
Say 5436.56

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.1 100 mm diameter
18.31.1.2 Class II
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
3311 100mm dia. sluice valves (with cap) each 10 1950.00 19500.00
2309 Carriage of sluice valves tonne 0.56 47.29 26.48
A Providing flanged joints to sluice valves each 20 127.12 2542.31
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.2)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 5.63 156.45 880.83
TOTAL 22949.62
Add 1% for water charges except on A 195.26

TOTAL 23144.89
Add for contractor’s profit and 2958.26
overheads @15% except on A
Cost of 10 valves 26103.15
Cost of 1 valve 2610.32
Say 2610.32

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.2 125 mm diameter
18.31.2.1 Class I
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
1941 125mm dia. sluice valves (with cap) each 10 6000.00 60000.00
2309 Carriage of sluice valves tonne 0.56 47.29 26.48
A Providing flanged joints to sluice valves each 20 128.28 2565.54
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.3)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 5.63 156.45 880.83
TOTAL 63472.85
Add 1% for water charges except on A 600.26

TOTAL 64073.12
Add for contractor’s profit and 9094.01
overheads @15% except on A
Cost of 10 valves 73167.13
Cost of 1 valve 7316.71
Say 7316.71

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.2 125 mm diameter
18.31.2.2 Class II
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
3314 125mm dia. sluice valves (with cap) each 10 2465.00 24650.00
2309 Carriage of sluice valves tonne 0.68 47.29 32.16
A Providing flanged joints to sluice valves each 20 128.28 2565.54
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.2)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 6.83 156.45 1068.57
TOTAL 28316.27
Add 1% for water charges except on A 246.82

TOTAL 28563.09
Add for contractor’s profit and 3739.35
overheads @15% except on A
Cost of 10 valves 32302.44
Cost of 1 valve 3230.24
Say 3230.24

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.3 150 mm diameter
18.31.3.1 Class I
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
1942 150mm dia. sluice valves (with cap) each 10 7500.00 75000.00
2309 Carriage of sluice valves tonne 0.72 47.29 34.05
A Providing flanged joints to sluice valves each 20 173.04 3460.71
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.4)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 7.25 156.45 1134.28
TOTAL 79629.04
Add 1% for water charges except on A 750.34

TOTAL 80379.38
Add for contractor’s profit and 11367.66
overheads @15% except on A
Cost of 10 valves 91747.04
Cost of 1 valve 9174.70
Say 9174.70

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.3 150 mm diameter
18.31.3.2 Class II
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
3317 150mm dia. sluice valves (with cap) each 10 3000.00 30000.00
2309 Carriage of sluice valves tonne 0.865 47.29 40.91
A Providing flanged joints to sluice valves each 20 173.04 3460.71
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.2)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 8.65 156.45 1353.31
TOTAL 34854.93
Add 1% for water charges except on A 300.41

TOTAL 35155.34
Add for contractor’s profit and 4551.20
overheads @15% except on A
Cost of 10 valves 39706.54
Cost of 1 valve 3970.65
Say 3970.65
18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.4 200 mm diameter
18.31.4.1 Class I
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
1943 200mm dia. sluice valves (with cap) each 10 9600.00 96000.00
2309 Carriage of sluice valves tonne 1.22 47.29 57.69
A Providing flanged joints to sluice valves each 20 178.84 3576.86
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.5)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 12.15 156.45 1900.90
TOTAL 101535.45
Add 1% for water charges except on A 960.58

TOTAL 102496.03
Add for contractor’s profit and 14552.74
overheads @15% except on A
Cost of 10 valves 117048.77
Cost of 1 valve 11704.88
Say 11704.88

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.4 200 mm diameter
18.31.4.2 Class II
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
3320 200mm dia. sluice valves (with cap) each 10 5800.00 58000.00
2309 Carriage of sluice valves tonne 1.5 47.29 70.94
A Providing flanged joints to sluice valves each 20 178.84 3576.86
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.5)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 15.05 156.45 2354.61
TOTAL 64002.41
Add 1% for water charges except on A 580.71

TOTAL 64583.12
Add for contractor’s profit and 8797.75
overheads @15% except on A
Cost of 10 valves 73380.86
Cost of 1 valve 7338.09
Say 7338.09

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.5 250 mm diameter
18.31.5.1 Class I
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
1943 250mm dia. sluice valves (with cap) each 10 12000.00 120000.00
2309 Carriage of sluice valves tonne 1.8 47.29 85.12
A Providing flanged joints to sluice valves each 20 256.88 5137.62
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.6)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 17.99 156.45 2814.58
TOTAL 128037.32
Add 1% for water charges except on A 1200.85

TOTAL 129238.17
Add for contractor’s profit and 18192.90
overheads @15% except on A
Cost of 10 valves 147431.06
Cost of 1 valve 14743.11
Say 14743.11

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.5 250 mm diameter
18.31.5.2 Class II
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
3321 250mm dia. sluice valves (with cap) each 10 8200.00 82000.00
2309 Carriage of sluice valves tonne 2.3 47.29 108.77
A Providing flanged joints to sluice valves each 20 256.88 5137.62
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.6)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 22.99 156.45 3596.84
TOTAL 90843.22
Add 1% for water charges except on A 821.09

TOTAL 91664.31
Add for contractor’s profit and 12439.48
overheads @15% except on A
Cost of 10 valves 104103.79
Cost of 1 valve 10410.38
Say 10410.38

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.6 300 mm diameter
18.31.6.1 Class 1
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
1945 300mm dia. sluice valves (with cap) each 10 14400.00 144000.00
2309 Carriage of sluice valves tonne 2.42 47.29 114.44
A Providing flanged joints to sluice valves each 20 266.17 5323.46
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.7)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 24.24 156.45 3792.41
TOTAL 153230.30
Add 1% for water charges except on A 1441.14

TOTAL 154671.45
Add for contractor’s profit and 21833.34
overheads @15% except on A
Cost of 10 valves 176504.79
Cost of 1 valve 17650.48
Say 17650.48

18.31 Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc.
(the tail pieces if required will be paid separately):
18.31.6 300 mm diameter
18.31.6.2 Class II
Code Description Unit Quantity Rate Amount
Details of cost for 10 sluice valves
Materials:
3326 250mm dia. sluice valves (with cap) each 10 10250.00 102500.00
2309 Carriage of sluice valves tonne 3.034 47.29 143.48
A Providing flanged joints to sluice valves each 20 266.17 5323.46
with bolts, nuts and rubber insertion
etc. (Rate as per item No. 18.30.7)

Labour for laying sluice valve


A (Rate as per item No. 18.24) quintal 30.34 156.45 4746.77
TOTAL 112713.70
Add 1% for water charges except on A 1026.43

TOTAL 113740.13
Add for contractor’s profit and 15550.49
overheads @15% except on A
Cost of 10 valves 129290.62
Cost of 1 valve 12929.06
Say 12929.06

18.32 : Constructing masonry Chamber 30x30x50 cm, inside with 75 class designation brick work in
cement mortar 1:4( cement :4 coarse) for sluice valve, with C.I. surface box 100 mm. top diameter, 160
mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:2:4 mix (1
cement :2 coarse sand : 4 graded stone aggregate 20 mm nominal size) necessary excavation foundation
concrete 1:5:10(1 cement : 5 fine sand: 10 graded stone aggregate 40 mm nominal size) and inside
plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick finished with a floating coat
of neat cement complete as per standard design :
18.32.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost for one chamber
Materials :-
Earth work in excavation including
refilling and disposal of surplus earth
(Rate as per item No. 2.8.1) cum 0.3 129.74 38.92
(Rate as per item No. 2.25) cum 0.3 71.56 21.47
Cement concrete 1:5:10 (1 Cement: 5 cum 0.04 2,719.53
fine sand : 10 graded stone aggregate
40mm nominal size) (Rate as per item
No.4.1.11)
108.78
Second class brick work in cement cum 0.1 2329.20
mortar 1:4 (1 Cement: 4 coarse sand) in
foundations and plinth (Rate as per item
no 6.1.1 of SH : Brick Work)
232.92
12mm cement plaster 1:3 (1 Cement: 3 sqm 0.7 132.57
Coarse sand) finished w ith a floating
coat of neat cement (Rate as per item no .
13.9.1)
92.80
Cement concrete 1:2:4 (1 Cement: 2 cum 0.02 4,269.75
Coarse sand ; 4 graded stone aggregate
20mm nominal size) (Rate as per item
No.5.3)
85.40
1304 C.I. surface box with hinged cover each 1 72.00 (A)
100x100x75mm (inside) 72.00
9999 Carriage of C.I. surface box L.S. 1.43 1.00 1.43 (A)
9999 Sundries L.S. 4.16 1.00 4.16 (A)
TOTAL 657.87
Add for water charges @ 1 % on ‘A 0.78 (B)
TOTAL 658.65
Add 15% for contractor’s profit and 11.75
overheads on (A+B)
Cost of one chamber 670.40
Say 670.40

18.33 : Constructing masonry Chamber 60x60x75 cm, inside with 75 class designation brick work in
cement mortar 1:4( cement :4 coarse) for sluice valve, with C.I. surface box 100 mm. top diameter, 160
mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:2:4 mix (1
cement :2 coarse sand : 4 graded stone aggregate 20 mm nominal size) necessary excavation foundation
concrete 1:5:10(1 cement : 5 fine sand: 10 graded stone aggregate 40 mm nominal size) and inside
plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick finished with a floating coat
of neat cement complete as per standard design :
18.33.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost for one chamber
Materials :-
Earth work in excavation including
refilling and disposal of surplus earth
(Rate as per item No. 2.8.1) cum 1.46 129.74 189.42
(Rate as per item No. 2.25) cum 1.46 71.56 104.48
Cement concrete 1:5:10 (1 Cement: 5 cum 0.15 2,719.53
fine sand : 10 graded stone aggregate
40mm nominal size) (Rate as per item
No.4.1.11)
407.93
Second class brick work in cement cum 0.57 2329.20
mortar 1:4 (1 Cement: 4 coarse sand) in
foundations and plinth (Rate as per item
no 6.1.1 of SH : Brick Work)
1327.64
12mm cement plaster 1:3 (1 Cement: 3 sqm 2.16 132.57
Coarse sand) finished w ith a floating
coat of neat cement (Rate as per item no .
13.9.1)
286.34
Cement concrete 1:2:4 (1 Cement: 2 cum 0.17 4,269.75
Coarse sand ; 4 graded stone aggregate
20mm nominal size) (Rate as per item
No.5.3)
725.86
(viii) Mild steel reinforcement for RCC kg 13.2 58.65
work (Rate as per item No.5.22.1
774.24
Form work (Rate as per item No.5.9.3) sqm 0.86 506.86
435.90
1305 C.I. surface box with hinged cover each 1 140.00 140.00 (A)
9999 Carriage of C.I. surface box L.S. 8.06 1.00 8.06 (A)
9999 Sundries L.S. 8.06 1.00 8.06 (A)
TOTAL 4407.93
Add for water charges @ 1 % on ‘A 1.56 (B)
TOTAL 4409.49
Add 15% for contractor’s profit and 23.65
overheads on (A+B)
Cost of one chamber 4433.14
Say 4433.14

18.34 : Constructing masonry Chamber 90x90x100 cm, inside with 75 class designation brick work in
cement mortar 1:4( cement :4 coarse) for sluice valve, with C.I. surface box 100 mm. top diameter, 160
mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:2:4 mix (1
cement :2 coarse sand : 4 graded stone aggregate 20 mm nominal size) necessary excavation foundation
concrete 1:5:10(1 cement : 5 fine sand: 10 graded stone aggregate 40 mm nominal size) and inside
plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick finished with a floating coat
of neat cement complete as per standard design :
18.34.1: With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost for one chamber
Materials :-
Earth work in excavation including
refilling and disposal of surplus earth
(Rate as per item No. 2.8.1) cum 2.85 129.74 369.76
(Rate as per item No. 2.25) cum 2.85 71.56 203.95
Cement concrete 1:5:10 (1 Cement: 5 cum 0.23 2,719.53
fine sand : 10 graded stone aggregate
40mm nominal size) (Rate as per item
No.4.1.11)
625.49
Second class brick work in cement cum 1.04 2329.20
mortar 1:4 (1 Cement: 4 coarse sand) in
foundations and plinth (Rate as per item
no 6.1.1 of SH : Brick Work)
2422.36
12mm cement plaster 1:3 (1 Cement: 3 sqm 4.41 132.57
Coarse sand) finished w ith a floating
coat of neat cement (Rate as per item no .
13.9.1)
584.61
Cement concrete 1:2:4 (1 Cement: 2 cum 0.27 4,269.75
Coarse sand ; 4 graded stone aggregate
20mm nominal size) (Rate as per item
No.5.3)
1152.83
(viii) Mild steel reinforcement for RCC kg 21.92 58.65
work (Rate as per item No.5.22.1
1285.70
Form work (Rate as per item No.5.9.3) sqm 1.49 506.86
755.22
1305 C.I. surface box with hinged cover each 1 140.00 140.00 (A)
9999 Carriage of C.I. surface box L.S. 8.06 1.00 8.06 (A)
9999 Sundries L.S. 8.06 1.00 8.06 (A)
TOTAL 7556.06
Add for water charges @ 1 % on ‘A 1.56 (B)
TOTAL 7557.62
Add 15% for contractor’s profit and 23.65
overheads on (A+B)
Cost of one chamber 7581.27
Say 7581.27

18.35 : Constructing masonry Chamber 120x120x100 cm, inside with 75 class designation brick work in
cement mortar 1:4( cement :4 coarse) for sluice valve, with C.I. surface box 100 mm. top diameter, 160
mm bottom diameter and 180 mm deep ( inside) with chained lid and RCC top slab 1:2:4 mix (1
cement :2 coarse sand : 4 graded stone aggregate 20 mm nominal size) necessary excavation foundation
concrete 1:5:10(1 cement : 5 fine sand: 10 graded stone aggregate 40 mm nominal size) and inside
plastering with cement mortar 1:3 (1 cement : 3 coarse sand) 12 mm thick finished with a floating coat
of neat cement complete as per standard design :
18.35.1: With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost for one chamber
Materials :-
Earth work in excavation including
refilling and disposal of surplus earth
(Rate as per item No. 2.8.1) cum 4.1 129.74 531.93
(Rate as per item No. 2.25) cum 4.1 71.56 293.40
Cement concrete 1:5:10 (1 Cement: 5 cum 0.33 2,719.53
fine sand : 10 graded stone aggregate
40mm nominal size) (Rate as per item
No.4.1.11)
897.45
Second class brick work in cement cum 1.32 2329.20
mortar 1:4 (1 Cement: 4 coarse sand) in
foundations and plinth (Rate as per item
no 6.1.1 of SH : Brick Work)
3074.54
12mm cement plaster 1:3 (1 Cement: 3 sqm 6.42 132.57
Coarse sand) finished w ith a floating
coat of neat cement (Rate as per item no .
13.9.1)
851.07
Cement concrete 1:2:4 (1 Cement: 2 cum 0.41 4,269.75
Coarse sand ; 4 graded stone aggregate
20mm nominal size) (Rate as per item
No.5.3)
1750.60
(viii) Mild steel reinforcement for RCC kg 32.8 58.65
work (Rate as per item No.5.22.1
1923.86
Form work (Rate as per item No.5.9.3) sqm 2.3 506.86
1165.78
1305 C.I. surface box with hinged cover each 1 140.00 140.00 (A)
9999 Carriage of C.I. surface box L.S. 8.06 1.00 8.06 (A)
9999 Sundries L.S. 8.06 1.00 8.06 (A)
TOTAL 10644.75
Add for water charges @ 1 % on ‘A 1.56 (B)
TOTAL 10646.31
Add 15% for contractor’s profit and 23.65
overheads on (A+B)
Cost of one chamber 10669.96
Say 10669.96

18.36 : Constructing masonry Chamber 60x45x50 cm, inside with 75 class designation brick work in
cement mortar 1:4(1 cement : 4 coarse sand) for water meter complete with C.I. double flap surface box
400x200x200 mm (inside) with locking arrangement and RCC top slab 1:2:4 mix (1 cement : 2 coarse
sand : 4 graded stone aggregate 20 mm nominal size) necessary excavation foundation concrete 1:5:10
( 1 cement: 5 fine sand:10 graded stone aggregate 40 mm nominal size) and inside plastering with
cement mortar 1:3 (1 cement: 3 coarse sand) 12 mm thick finished with a floating coat of neat cement
complete as per standard design :
18.36.1: With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost for one chamber
Materials :-
Earth work in excavation including
refilling and disposal of surplus earth
(Rate as per item No. 2.8.1) cum 1.46 129.74 189.42
(Rate as per item No. 2.25) cum 1.46 71.56 104.48
Cement concrete 1:5:10 (1 Cement: 5 cum 0.15 2,719.53
fine sand : 10 graded stone aggregate
40mm nominal size) (Rate as per item
No.4.1.11)
407.93
Second class brick work in cement cum 0.57 2329.20
mortar 1:4 (1 Cement: 4 coarse sand) in
foundations and plinth (Rate as per item
no 6.1.1 of SH : Brick Work)
1327.64
12mm cement plaster 1:3 (1 Cement: 3 sqm 2.16 132.57
Coarse sand) finished w ith a floating
coat of neat cement (Rate as per item no .
13.9.1)
286.34
Cement concrete 1:2:4 (1 Cement: 2 cum 0.13 4,269.75
Coarse sand ; 4 graded stone aggregate
20mm nominal size) (Rate as per item
No.5.3)
555.07
(viii) Mild steel reinforcement for RCC kg 10.48 58.65
work (Rate as per item No.5.22.1
614.70
Form work (Rate as per item No.5.9.3) sqm 0.86 506.86
435.90
1305 C.I. surface box with hinged cover each 1 140.00 140.00 (A)
9999 Carriage of C.I. surface box L.S. 53.82 1.00 53.82 (A)
9999 Sundries L.S. 8.06 1.00 8.06 (A)
TOTAL 4123.36
Add for water charges @ 1 % on ‘A 2.02 (B)
TOTAL 4125.38
Add 15% for contractor’s profit and 30.58
overheads on (A+B)
Cost of one chamber 4155.96
Say 4155.96

18.37 : Constructing masonry Chamber 60x45x50 cm, inside with 75 class designation brick work in
cement mortar 1:4(1 cement : 4 coarse sand) for water meter complete with C.I. double flap surface box
400x200x200 mm (inside) with locking arrangement and RCC top slab 1:2:4 mix (1 cement : 2 coarse
sand : 4 graded stone aggregate 20 mm nominal size) necessary excavation foundation concrete 1:5:10
( 1 cement: 5 fine sand:10 graded stone aggregate 40 mm nominal size) and inside plastering with
cement mortar 1:3 (1 cement: 3 coarse sand) 12 mm thick finished with a floating coat of neat cement
complete as per standard design :
18.37.1: With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost for one chamber
Materials :-
Earth work in excavation including
refilling and disposal of surplus earth
(Rate as per item No. 2.8.1) cum 1.09 129.74 141.42
(Rate as per item No. 2.25) cum 1.09 71.56 78.00
Cement concrete 1:5:10 (1 Cement: 5 cum 0.13 2,719.53
fine sand : 10 graded stone aggregate
40mm nominal size) (Rate as per item
No.4.1.11)
353.54
Second class brick work in cement cum 0.35 2329.20
mortar 1:4 (1 Cement: 4 coarse sand) in
foundations and plinth (Rate as per item
no 6.1.1 of SH : Brick Work)
815.22
12mm cement plaster 1:3 (1 Cement: 3 sqm 1.32 132.57
Coarse sand) finished w ith a floating
coat of neat cement (Rate as per item no .
13.9.1)
174.99
Cement concrete 1:2:4 (1 Cement: 2 cum 0.22 4,269.75
Coarse sand ; 4 graded stone aggregate
20mm nominal size) (Rate as per item
No.5.3)
939.35
(viii) Mild steel reinforcement for RCC kg 17.84 58.65
work (Rate as per item No.5.22.1
1046.39
Form work (Rate as per item No.5.9.3) sqm 1.03 506.86
522.07
1307 C.I. surface box 400x200x200mm each 1 185.00 (A)
(inside) with locking arrangement 185.00
9999 Carriage of C.I. surface box L.S. 13.52 1.00 13.52 (A)
9999 Sundries L.S. 8.06 1.00 8.06 (A)
TOTAL 4277.55
Add for water charges @ 1 % on ‘A 2.07 (B)
TOTAL 4279.61
Add 15% for contractor’s profit and 31.30
overheads on (A+B)
Cost of one chamber 4310.91
Say 4310.91

18.38: Painting G.I. pipes and fittings with synthetic enamel white paint over a ready mixed priming
coat, both of approved quality for new work :
18.38.1: 15 mm diameter pipe. -—
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Priming Coat (Rate as per item No. sqm 0.673 15.74 10.59
13.50.3 of SH: Finishing)
Painting two coats excluding priming sqm 0.673 49.68 33.44
coat with white paint on new work. (Rate
as per item N o. 13.61.1)
9999 Add for delay L.S. 13.52 1.00 13.52 A
TOTAL 57.55
Add 1% for water charges on A 0.14
TOTAL 57.69
Add for contractor’s profit and 2.03
overheads @15% on A
Cost of 10 metres 59.71
Cost of 1 metres 5.97
Say 5.97

18.38: Painting G.I. pipes and fittings with synthetic enamel white paint over a ready mixed priming
coat, both of approved quality for new work :
18.38.2: 20 mm diameter pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Priming Coat (Rate as per item No. sqm 0.845 15.74 13.30
13.50.3 of SH: Finishing)
Painting two coats excluding priming sqm 0.845 49.68 41.98
coat with white paint on new work. (Rate
as per item N o. 13.61.1)
9999 Add for delay L.S. 13.52 1.00 13.52 A
TOTAL 68.80
Add 1% for water charges on A 0.14
TOTAL 68.94
Add for contractor’s profit and 2.03
overheads @15% on A
Cost of 10 metres 70.97
Cost of 1 metres 7.10
Say 7.10

18.38: Painting G.I. pipes and fittings with synthetic enamel white paint over a ready mixed priming
coat, both of approved quality for new work :
18.38.3 : 25 mm diameter pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Priming Coat (Rate as per item No. sqm 1.061 15.74 16.70
13.50.3 of SH: Finishing)
Painting two coats excluding priming sqm 1.061 49.68 52.72
coat with white paint on new work. (Rate
as per item N o. 13.61.1)
9999 Add for delay L.S. 20.28 1.00 20.28 A
TOTAL 89.69
Add 1% for water charges on A 0.20
TOTAL 89.90
Add for contractor’s profit and 3.04
overheads @15% on A
Cost of 10 metres 92.94
Cost of 1 metres 9.29
Say 9.29

18.38: Painting G.I. pipes and fittings with synthetic enamel white paint over a ready mixed priming
coat, both of approved quality for new work :
18.38.4: 32 mm diameter pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Priming Coat (Rate as per item No. sqm 1.334 15.74 21.00
13.50.3 of SH: Finishing)
Painting two coats excluding priming sqm 1.334 49.68 66.28
coat with white paint on new work. (Rate
as per item N o. 13.61.1)
9999 Add for delay L.S. 20.28 1.00 20.28 A
TOTAL 107.56
Add 1% for water charges on A 0.20
TOTAL 107.76
Add for contractor’s profit and 3.04
overheads @15% on A
Cost of 10 metres 110.80
Cost of 1 metres 11.08
Say 11.08

18.38: Painting G.I. pipes and fittings with synthetic enamel white paint over a ready mixed priming
coat, both of approved quality for new work :
18.38.5: 40 mm diameter pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Priming Coat (Rate as per item No. sqm 1.52 15.74 23.92
13.50.3 of SH: Finishing)
Painting two coats excluding priming sqm 1.52 49.68 75.52
coat with white paint on new work. (Rate
as per item N o. 13.61.1)
9999 Add for delay L.S. 26.91 1.00 26.91 A
TOTAL 126.35
Add 1% for water charges on A 0.27
TOTAL 126.62
Add for contractor’s profit and 4.04
overheads @15% on A
Cost of 10 metres 130.66
Cost of 1 metres 13.07
Say 13.07
18.38: Painting G.I. pipes and fittings with synthetic enamel white paint over a ready mixed priming
coat, both of approved quality for new work :
18.38.6: 50 mm diameter pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres

Priming Coat (Rate as per item No. sqm 1.894 15.74 29.81
13.50.3 of SH: Finishing)
Painting two coats excluding priming sqm 1.894 49.68 94.10
coat with white paint on new work. (Rate
as per item N o. 13.61.1)
9999 Add for delay L.S. 26.91 1.00 26.91 A
TOTAL 150.82
Add 1% for water charges on A 0.27
TOTAL 151.09
Add for contractor’s profit and 4.04
overheads @15% on A
Cost of 10 metres 155.13
Cost of 1 metres 15.51
Say 15.51

18.39 : Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality :
18.39.1: 15 mm diameter pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting one coat with white paint on sqm 0.673 31.94 21.49
old work. (Rate as per item N o. 14.54.1)

9999 Add for delay L.S. 8.06 1.00 8.06 A


TOTAL 29.55
Add 1% for water charges on A 0.08
TOTAL 29.63
Add for contractor’s profit and 1.21
overheads @15% on A
Cost of 10 metres 30.84
Cost of 1 metres 3.08
Say 3.08

18.39 : Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality :
18.39.2: 20 mm diameter pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting one coat with white paint on sqm 0.845 31.94 26.99
old work. (Rate as per item N o. 14.54.1)
9999 Add for delay L.S. 8.06 1.00 8.06 A
TOTAL 35.05
Add 1% for water charges on A 0.08
TOTAL 35.13
Add for contractor’s profit and 1.21
overheads @15% on A
Cost of 10 metres 36.34
Cost of 1 metres 3.63
Say 3.63

18.39 : Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality :
18.39.3 25 mm diam eter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting one coat with white paint on sqm 1.061 31.94 33.88
old work. (Rate as per item N o. 14.54.1)

9999 Add for delay L.S. 10.79 1.00 10.79 A


TOTAL 44.67
Add 1% for water charges on A 0.11
TOTAL 44.78
Add for contractor’s profit and 1.62
overheads @15% on A
Cost of 10 metres 46.40
Cost of 1 metres 4.64
Say 4.64

18.39 : Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality :
18.39.4 : 32 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting one coat with white paint on sqm 1.334 31.94 42.60
old work. (Rate as per item N o. 14.54.1)

9999 Add for delay L.S. 10.92 1.00 10.92 A


TOTAL 53.52
Add 1% for water charges on A 0.11
TOTAL 53.63
Add for contractor’s profit and 1.64
overheads @15% on A
Cost of 10 metres 55.27
Cost of 1 metres 5.53
Say 5.53

18.39 : Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality :
18.39.5: 40 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting one coat with white paint on sqm 1.52 31.94 48.54
old work. (Rate as per item N o. 14.54.1)

9999 Add for delay L.S. 13.52 1.00 13.52 A


TOTAL 62.06
Add 1% for water charges on A 0.14
TOTAL 62.20
Add for contractor’s profit and 2.03
overheads @15% on A
Cost of 10 metres 64.23
Cost of 1 metres 6.42
Say 6.42

18.39 : Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality :
18.39.6 : 50 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting one coat with white paint on sqm 1.894 31.94 60.49
old work. (Rate as per item N o. 14.54.1)

9999 Add for delay L.S. 13.52 1.00 13.52 A


TOTAL 74.01
Add 1% for water charges on A 0.14
TOTAL 74.14
Add for contractor’s profit and 2.03
overheads @15% on A
Cost of 10 metres 76.17
Cost of 1 metres 7.62
Say 7.62

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.1:: 15 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 0.673 31.73 21.36
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 8.06 1.00 8.06 A
TOTAL 29.42
Add 1% for water charges on A 0.08
TOTAL 29.50
Add for contractor’s profit and 1.21
overheads @15% on A
Cost of 10 metres 30.71
Cost of 1 metres 3.07
Say 3.07

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.2:: 20 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 0.845 31.73 26.81
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 8.06 1.00 8.06 A
TOTAL 34.87
Add 1% for water charges on A 0.08
TOTAL 34.95
Add for contractor’s profit and 1.21
overheads @15% on A
Cost of 10 metres 36.16
Cost of 1 metres 3.62
Say 3.62

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.3:: 25 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 1.061 31.73 33.67
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 10.79 1.00 10.79 A
TOTAL 44.46
Add 1% for water charges on A 0.11
TOTAL 44.57
Add for contractor’s profit and 1.62
overheads @15% on A
Cost of 10 metres 46.18
Cost of 1 metres 4.62
Say 4.62

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.4:: 32 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 1.334 31.73 42.33
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 10.79 1.00 10.79 A
TOTAL 53.12
Add 1% for water charges on A 0.11
TOTAL 53.23
Add for contractor’s profit and 1.62
overheads @15% on A
Cost of 10 metres 54.85
Cost of 1 metres 5.48
Say 5.48

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.5:: 40 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 1.52 31.73 48.23
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 12.22 1.00 12.22 A
TOTAL 60.45
Add 1% for water charges on A 0.12
TOTAL 60.58
Add for contractor’s profit and 1.83
overheads @15% on A
Cost of 10 metres 62.41
Cost of 1 metres 6.24
Say 6.24

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.6:: 50 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 1.894 31.73 60.10
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 12.22 1.00 12.22 A
TOTAL 72.32
Add 1% for water charges on A 0.12
TOTAL 72.44
Add for contractor’s profit and 1.83
overheads @15% on A
Cost of 10 metres 74.28
Cost of 1 metres 7.43
Say 7.43

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.7:: 65 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 2.387 31.73 75.74
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 13.52 1.00 13.52 A
TOTAL 89.26
Add 1% for water charges on A 0.14
TOTAL 89.40
Add for contractor’s profit and 2.03
overheads @15% on A
Cost of 10 metres 91.43
Cost of 1 metres 9.14
Say 9.14

18.40 : Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved
quality
18.40.8:: 80 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Painting with anti-corrosive paint two sqm 2.796 31.73 88.72
coats.(Rate as per item13.65.1 sub-head
finishing)
9999 Add for delay L.S. 14.82 1.00 14.82 A
TOTAL 103.54
Add 1% for water charges on A 0.15
TOTAL 103.69
Add for contractor’s profit and 2.22
overheads @15% on A
Cost of 10 metres 105.91
Cost of 1 metres 10.59
Say 10.59

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.1: 15mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum sand
M aterials
6501 Sand zone V (J amuna) cum 1 175.00 175.00
2235 Carriage of coarse sand cum 1 53.21 53.21
Labour;
114 Beldar Day 0.09 207 18.63
115 Coolie Day 0.11 207 22.77
TOTAL 269.61
Add 1% for water charges 2.70
TOTAL 272.31
Add 15 % for contractor’s profit and overheads 40.85
(A) cost of 1 cum. 313.15
Details of cost of sand filling alround 15mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 0.74 313.15 231.73
Rate as in Item No 18.41.1 marked (A)

TOTAL 231.73
Cost of 10 metre 231.73
Cost of one metre 23.17
Say 23.17

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.2: 20 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 20mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 0.75 313.15 234.86
Rate as in Item No 18.41.1 marked (A)

TOTAL 234.86
Cost of 10 metre 234.86
Cost of one metre 23.49
Say 23.49

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.3 25 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 25mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 0.77 313.15 241.13
Rate as in Item No 18.41.1 marked (A)

TOTAL 241.13
Cost of 10 metre 241.13
Cost of one metre 24.11
Say 24.11

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.4: 32 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 32mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 0.79 313.15 247.39
Rate as in Item No 18.41.1 marked (A)

TOTAL 247.39
Cost of 10 metre 247.39
Cost of one metre 24.74
Say 24.74

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.5: 40 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 40mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 0.8 313.15 250.52
Rate as in Item No 18.41.1 marked (A)

TOTAL 250.52
Cost of 10 metre 250.52
Cost of one metre 25.05
Say 25.05

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.6: 50 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 50mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 0.83 313.15 259.92
Rate as in Item No 18.41.1 marked (A)

TOTAL 259.92
Cost of 10 metre 259.92
Cost of one metre 25.99
Say 25.99

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.7: 65 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 65mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 1.31 313.15 410.23
Rate as in Item No 18.41.1 marked (A)

TOTAL 410.23
Cost of 10 metre 410.23
Cost of one metre 41.02
Say 41.02

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.8: 80 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 80mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 1.35 313.15 422.76
Rate as in Item No 18.41.1 marked (A)

TOTAL 422.76
Cost of 10 metre 422.76
Cost of one metre 42.28
Say 42.28

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.9: 100 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 100mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 1.43 313.15 447.81
Rate as in Item No 18.41.1 marked (A)

TOTAL 447.81
Cost of 10 metre 447.81
Cost of one metre 44.78
Say 44.78

18.41: Providing and filling sand of grading zone V or coarser grade alround the G.I. pipes in external
work.
18.41.10:150 mm diameter pipe
Code Description Unit Quantity Rate Amount
Details of cost of sand filling alround 150mm dia. pipe 10 metre long.
Cost of sand filling for 10 metre pipe cum 2.13 313.15 667.01
Rate as in Item No 18.41.1 marked (A)

TOTAL 667.01
Cost of 10 metre 667.01
Cost of one metre 66.70
Say 66.70

18.42: Boring with 100 mm diameter casing pipe for hand pump/ tube well in all soils except ordinary
hard rocks requiring blasting including removing the casing pipe after the hand pipe/tube well is lowered
and testedUpto
18.42.1: : 6 metres depth.
Code Description Unit Quantity Rate Amount
Labour For boring and removing the pipe-
114 Beldar Day 3 207 621.00
116 Fitter (grade 1) Day 0.5 270.00 135.00
10 Hire charges for derick monkey rope Day 0.5 400.00 200.00
and other accessories
1472 Depreciation @ 2% of the cost of casing metre 0.12 292.00 35.04
pipe 6metre @ Rs. per metre
9999 Sundries L.S 13.52 1.00 13.52
TOTAL 1004.56
Add for water charges @ 1 % 10.05
TOTAL 1014.61
Add for contractor’s profit and over head 152.19
@ 15%
Cost of 6 metre 1166.80
Cost per metre 194.47
Say 194.47

18.42: Boring with 100 mm diameter casing pipe for hand pump/ tube well in all soils except ordinary
hard rocks requiring blasting including removing the casing pipe after the hand pipe/tube well is lowered
and testedBeyond
18.42.2: : 6m and upto 12 m depth.
Code Description Unit Quantity Rate Amount
Labour For boring and removing the pipe-
114 Beldar Day 3.5 207 724.50
116 Fitter (grade 1) Day 0.62 270.00 167.40
10 Hire charges for derick monkey rope Day 0.62 400.00 248.00
and other accessories
1472 Depreciation @ 2% of the cost of casing metre 0.12 292.00 35.04
pipe 6metre @ Rs. per metre
9999 Sundries L.S 13.52 1.00 13.52
TOTAL 1188.46
Add for water charges @ 1 % 11.88
TOTAL 1200.34
Add for contractor’s profit and over head 180.05
@ 15%
Cost of 6 metre 1380.40
Cost per metre 230.07
Say 230.07

18.42: Boring with 100 mm diameter casing pipe for hand pump/ tube well in all soils except ordinary
hard rocks requiring blasting including removing the casing pipe after the hand pipe/tube well is lowered
and tested
18.42.3 :
: Beyond 12 m and upto 18 m depth.
Code Description Unit Quantity Rate Amount
Labour For boring and removing the pipe-
114 Beldar Day 4 207 828.00
116 Fitter (grade 1) Day 0.75 270.00 202.50
10 Hire charges for derick monkey rope Day 0.75 400.00 300.00
and other accessories
1472 Depreciation @ 2% of the cost of casing metre 0.12 292.00 35.04
pipe 6metre @ Rs. per metre
9999 Sundries L.S 13.52 1.00 13.52
TOTAL 1379.06
Add for water charges @ 1 % 13.79
TOTAL 1392.85
Add for contractor’s profit and over head 208.93
@ 15%
Cost of 6 metre 1601.78
Cost per metre 266.96
Say 266.96

18.43 : Providing and placing in position filters of 40 mm diameter G.I. pipe with brass strainer of
approved quality.
Code Description Unit Quantity Rate Amount
Details of cost for one strainer 1.5 long
M aterials
114 Beldar Day 0.17 207 35.19
116 Fitter (grade 1) Day 0.17 270.00 45.90
1882 Cost of strainer 40mm diameter 1.5m each 1 405.00 405.00
long
9999 Carriage to site L.S 13.52 1.00 13.52
9999 Sundries L.S 7.15 1.00 7.15
TOTAL 506.76
Add for water charges @ 1 % 5.07
TOTAL 511.83
Add for contractor’s profit and over head 76.77
@ 15%
Cost of 1.5 metre 588.60
Cost per metre 392.40
Say 392.40

18.44: Providing and fixing to filter and lowering to proper levels 40 mm G.I. pipe for tube well
including cleaning and prim ing the tube well.
Code Description Unit Quantity Rate Amount
Details of cost for 10m
M aterials
1549 G.I. pipes 40 mm dia metre 10.2 290.00 2958.00
2271 carriage of 40mm pipe(36.5kg) tonne 0.03723 47.29 1.76
Labour
114 Beldar Day 0.75 207 155.25
116 Fitter (grade 1) Day 0.33 270.00 89.10
9999 White lead, hamp and oil etc. L.S 6.76 1.00 6.76
9999 Sundries L.S 7.25 1.00 7.25
TOTAL 3218.12
Add for water charges @ 1 % 32.18
TOTAL 3250.30
Add for contractor’s profit and over head 487.55
@ 15%
Cost of 10 metre 3737.85
Cost per metre 373.78
Say 373.78

18.45 : Providing and placing in position hand pump of approved quality for 40 mm diameter G.I. pipe
complete with all accessories.
Code Description Unit Quantity Rate Amount
Details of cost for one hand pump
M aterials
1693 S.C.I. hand pump each 1 450.00 450.00
9999 Carriage L.S 13.52 1.00 13.52
Labour
114 Beldar Day 0.1 207 20.70
116 Fitter (grade 1) Day 0.1 270.00 27.00
9999 Sundries L.S 4.42 1.00 4.42
TOTAL 515.64
Add for water charges @ 1 % 5.16
TOTAL 520.80
Add for contractor’s profit and over head 78.12
@ 15%
Cost of one hand pump 598.92
Say 598.92

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.1: 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1641 G.I. Union 15 mm nominal bore each 1 45.00 45.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.11 207 22.77
116 Fitter (grade 1) Day 0.11 270.00 29.70
TOTAL 99.29
Add for water charges @ 1 % 0.99
TOTAL 100.28
Add for contractor’s profit and over head 15.04
@ 15%
Cost of one no 115.33
Say 115.33

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.2: 20 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1642 G.I. Union 20mm nominal bore each 1 55.00 55.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.11 207 22.77
116 Fitter (grade 1) Day 0.11 270.00 29.70
TOTAL 109.29
Add for water charges @ 1 % 1.09
TOTAL 110.38
Add for contractor’s profit and over head 16.56
@ 15%
Cost of one no 126.94
Say 126.94

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.3: 25 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1643 G.I. Union 25mm nominal bore each 1 66.00 66.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.11 207 22.77
116 Fitter (grade 1) Day 0.11 270.00 29.70
TOTAL 120.29
Add for water charges @ 1 % 1.20
TOTAL 121.49
Add for contractor’s profit and over head 18.22
@ 15%
Cost of one no 139.72
Say 139.72

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.4: 32 mm nominal
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1644 G.I. Union 32mm nominal bore each 1 110.00 110.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.11 207 22.77
116 Fitter (grade 1) Day 0.11 270.00 29.70
TOTAL 164.29
Add for water charges @ 1 % 1.64
TOTAL 165.93
Add for contractor’s profit and over head 24.89
@ 15%
Cost of one no 190.82
Say 190.82

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.5: 40 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1645 G.I. Union 40mm nominal bore each 1 132.00 132.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.11 207 22.77
116 Fitter (grade 1) Day 0.11 270.00 29.70
TOTAL 186.29
Add for water charges @ 1 % 1.86
TOTAL 188.15
Add for contractor’s profit and over head 28.22
@ 15%
Cost of one no 216.38
Say 216.38

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.6: 50mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1646 G.I. Union 50mm nominal bore each 1 169.00 169.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.15 207 31.05
116 Fitter (grade 1) Day 0.15 270.00 40.50
TOTAL 242.37
Add for water charges @ 1 % 2.42
TOTAL 244.79
Add for contractor’s profit and over head 36.72
@ 15%
Cost of one no 281.51
Say 281.51

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.7: 65mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1647 G.I. Union 65mm nominal bore each 1 180.00 180.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.15 207 31.05
116 Fitter (grade 1) Day 0.15 270.00 40.50
TOTAL 253.37
Add for water charges @ 1 % 2.53
TOTAL 255.90
Add for contractor’s profit and over head 38.39
@ 15%
Cost of one no 294.29
Say 294.29

18.46: Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making
long screws etc. complete (New work)
18.46.8: 80 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1648 G.I. Union 80mm nominal bore each 1 250.00 250.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.15 207 31.05
116 Fitter (grade 1) Day 0.15 270.00 40.50
TOTAL 323.37
Add for water charges @ 1 % 3.23
TOTAL 326.60
Add for contractor’s profit and over head 48.99
@ 15%
Cost of one no 375.59
Say 375.59

18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.1: 15 mmwherever
nominal required
bore. :
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1641 G.I. Union 15mm nominal bore each 1 45.00 45.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.33 207 68.31
116 Fitter (grade 1) Day 0.33 270.00 89.10
TOTAL 204.23
Add for water charges @ 1 % 2.04
TOTAL 206.27
Add for contractor’s profit and over head 30.94
@ 15%
Cost of one no 237.21
Say 237.21

18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.2: 20 mmwherever
nominal required
bore. :
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1642 G.I. Union 20mm nominal bore each 1 55.00 55.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.33 207 68.31
116 Fitter (grade 1) Day 0.33 270.00 89.10
TOTAL 214.23
Add for water charges @ 1 % 2.14
TOTAL 216.37
Add for contractor’s profit and over head 32.46
@ 15%
Cost of one no 248.83
Say 248.83

18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.3: 25 mmwherever
nominal required
bore. :
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1643 G.I. Union 25mm nominal bore each 1 66.00 66.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.33 207 68.31
116 Fitter (grade 1) Day 0.33 270.00 89.10
TOTAL 225.23
Add for water charges @ 1 % 2.25
TOTAL 227.48
Add for contractor’s profit and over head 34.12
@ 15%
Cost of one no 261.60
Say 261.60

18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.4: 32 mmwherever
nominal required
bore. :
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1644 G.I. Union 32mm nominal bore each 1 110.00 110.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.33 207 68.31
116 Fitter (grade 1) Day 0.33 270.00 89.10
TOTAL 269.23
Add for water charges @ 1 % 2.69
TOTAL 271.92
Add for contractor’s profit and over head 40.79
@ 15%
Cost of one no 312.71
Say 312.71

18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.5 40 mm wherever required :
nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1645 G.I. Union 40mm nominal bore each 1 132.00 132.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.33 207 68.31
116 Fitter (grade 1) Day 0.33 270.00 89.10
TOTAL 291.23
Add for water charges @ 1 % 2.91
TOTAL 294.14
Add for contractor’s profit and over head 44.12
@ 15%
Cost of one no 338.26
Say 338.26
18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.6 50 mm wherever required :
nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1646 G.I. Union 50mm nominal bore each 1 169.00 169.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.45 207 93.15
116 Fitter (grade 1) Day 0.45 270.00 121.50
TOTAL 385.47
Add for water charges @ 1 % 3.85
TOTAL 389.32
Add for contractor’s profit and over head 58.40
@ 15%
Cost of one no 447.72
Say 447.72

18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.7 65 mm wherever required :
nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1647 G.I. Union 65mm nominal bore each 1 180.00 180.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.45 207 93.15
116 Fitter (grade 1) Day 0.45 270.00 121.50
TOTAL 396.47
Add for water charges @ 1 % 3.96
TOTAL 400.43
Add for contractor’s profit and over head 60.07
@ 15%
Cost of one no 460.50
Say 460.50

18.47 Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and
making long screws including excavation, refilling the earth or cutting of wall and making good the
same complete
18.47.8 80 mm wherever required :
nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for one no
M aterials
1648 G.I. Union 80mm nominal bore each 1 250.00 250.00
9999 Carriage & sundries L.S 1.82 1.00 1.82
Labour
114 Beldar Day 0.45 207 93.15
116 Fitter (grade 1) Day 0.45 270.00 121.50
TOTAL 466.47
Add for water charges @ 1 % 4.66
TOTAL 471.13
Add for contractor’s profit and over head 70.67
@ 15%
Cost of one no 541.80
Say 541.80

18.48 Providing and placing on terrace (at all floor levels) polyethylene water storage tank ISI : 12701
marked with cover and suitable locking arrangement and making necessary holes for inlet, outlet and
overflow pipes but without fittings and the base support for tank
Code Description Unit Quantity Rate Amount
Details of cost for 500 litres, tank 1 no.
M aterials
1649 Polyethylene water storage tank per litre 500 5.00 2500.00
9999 Carriage to site L.S 179.4 1.00 179.40
9999 Placing at terrace L.S 89.7 1.00 89.70
TOTAL 2769.10
Add for water charges @ 1 % 27.69
TOTAL 2796.79
Add for contractor’s profit and over head 419.52
@ 15%
Cost of 500 litres 3216.31
Cost of 1 litre 6.43
Say 6.43

18.49 Providing and fixing C.P. brass bib cock of approved quality conforming to IS:8931
18.49.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7257 15mm diameter C .P. brass bib cock each 1 80.00 80.00
9999 Carriage & fixing charges L.S 11.57 1.00 11.57
TOTAL 91.57
Add for water charges @ 1 % 0.92
TOTAL 92.49
Add for contractor’s profit and over head 13.87
@ 15%
Cost of 1 no 106.36
Say 106.36
18.50 Providing and fixing C.P. brass long nose bib cock of approved quality conforming to IS standards
and weighing not less than 810 gms.
18.50.1 15mm nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7258 15mm diameter C .P. brass long nose each 1 130.00 130.00
bib cock
9999 Carriage & fixing charges L.S 16.25 1.00 16.25
TOTAL 146.25
Add for water charges @ 1 % 1.46
TOTAL 147.71
Add for contractor’s profit and over head 22.16
@ 15%
Cost of 1 no 169.87
Say 169.87

18.51 Providing and fixing C.P. brass long body bib cock of approved quality conforming to IS
standards and weighing not less than 690 gms.
18.51.1 15mm nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7259 15mm diameter C .P. brass long body each 1 150.00 150.00
9999 bib cock & fixing charges
Carriage L.S 13.91 1.00 13.91
TOTAL 163.91
Add for water charges @ 1 % 1.64
TOTAL 165.55
Add for contractor’s profit and over head 24.83
@ 15%
Cost of 1 no 190.38
Say 190.38

18.52 Providing and fixing C.P. brass stop cock (concealed) of standard design and of approved make
conforming to IS:8931.
18.52.1 15mm nominal bore.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7260 15mm diameter C.P. brass stop cock each 1 170.00 170.00

9999 Carriage & fixing charges L.S 11.57 1.00 11.57


TOTAL 181.57
Add for water charges @ 1 % 1.82
TOTAL 183.39
Add for contractor’s profit and over head 27.51
@ 15%
Cost of 1 no 210.89
Say 210.89

18.53 Providing and fixing C.P. brass angle valve for basin mixer and geyser points of approved quality
conforming to IS:8931
18.53.1 15 mm nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7261 C.P. brass angle valve each 1 180.00 180.00
9999 Carriage & fixing charges L.S 11.31 1.00 11.31
TOTAL 191.31
Add for water charges @ 1 % 1.91
TOTAL 193.22
Add for contractor’s profit and over head 28.98
@ 15%
Cost of 1 no 222.21
Say 222.21

18.54 Providing and fixing PTMT bib cock of approved quality and colour.
18.54.1 15mm nominal bore, 86 mm long, weighing not less than 88 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7400 15mm dia P.T.M.T. bib cock each 1 96.00 96.00
9999 Carriage & fixing charges L.S 8.06 1.00 8.06
TOTAL 104.06
Add for water charges @ 1 % 1.04
TOTAL 105.10
Add for contractor’s profit and over head 15.77
@ 15%
Cost of 1 no 120.87
Say 120.87

18.54 Providing and fixing PTMT bib cock of approved quality and colour.
18.54.2 15 m m nominal bore, 122mm long weighing not less than 99 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7401 15mm dia P.T.M.T. bib cock each 1 220.00 220.00
9999 Carriage & fixing charges L.S 8.06 1.00 8.06
TOTAL 228.06
Add for water charges @ 1 % 2.28
TOTAL 230.34
Add for contractor’s profit and over head 34.55
@ 15%
Cost of 1 no 264.89
Say 264.89

18.54 Providing and fixing PTMT bib cock of approved quality and colour.
18.54.3 15 mm nominal bore, 165 mm long, weighing not less than 110 grams.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7402 15mm dia P.T.M.T. bib cock each 1 155.00 155.00
9999 Carriage & fixing charges L.S 8.06 1.00 8.06
TOTAL 163.06
Add for water charges @ 1 % 1.63
TOTAL 164.69
Add for contractor’s profit and over head 24.70
@ 15%
Cost of 1 no 189.39
Say 189.39

18.54 Providing and fixing PTMT bib cock of approved quality and colour.
18.54.4 15mm nominal bore, 90mm long, weighing not less than 93 grams.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7859 15mm P.T.M .T. bib cock with nozzle each 1 110.00 110.00
9999 Carriage & fixing charges L.S 8.06 1.00 8.06
TOTAL 118.06
Add for water charges @ 1 % 1.18
TOTAL 119.24
Add for contractor’s profit and over head 17.89
@ 15%
Cost of 1 no 137.13
Say 137.13

18.55 Providing and fixing PTMT stop cock of approved quality and colour.
18.55.1 15 mm nominal bore, 86mm long, weighing not less than 88 grams.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7403 15mm dia P.T.M.T. stop cock each 1 96.00 96.00
9999 Carriage & fixing charges L.S 8.06 1.00 8.06
TOTAL 104.06
Add for water charges @ 1 % 1.04
TOTAL 105.10
Add for contractor’s profit and over head 15.77
@ 15%
Cost of 1 no 120.87
Say 120.87

18.55 Providing and fixing PTMT stop cock of approved quality and colour.
18.55.2 20mm nominal bore, 89mm long, weighing not less than 88 grams.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7405 20mm dia P.T.M.T. stop cock each 1 120.00 120.00
9999 Carriage & fixing charges L.S 8.06 1.00 8.06
TOTAL 128.06
Add for water charges @ 1 % 1.28
TOTAL 129.34
Add for contractor’s profit and over head 19.40
@ 15%
Cost of 1 no 148.74
Say 148.74

18.55 Providing and fixing PTMT stop cock of approved quality and colour.
18.55.3 Concealed stop cock, 15mm nominal bore, 108mm long, weighing not less than 108 grams.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7861 P.T.M.T. stop cock (concealed) 15 mm each 1 160.00 160.00

9999 Carriage & fixing charges L.S 8.06 1.00 8.06


TOTAL 168.06
Add for water charges @ 1 % 1.68
TOTAL 169.74
Add for contractor’s profit and over head 25.46
@ 15%
Cost of 1 no 195.20
Say 195.20

18.56 Providing and fixing PTMT pillar cock of approved quality and colour .
18.56.1 15mm nominal bore, 107mm long, weighing not less than 110 grams.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7406 15mm dia P.T.M.T. pillar cock each 1 150.00 150.00
9999 Carriage & fixing charges L.S 9.49 1.00 9.49
TOTAL 159.49
Add for water charges @ 1 % 1.59
TOTAL 161.08
Add for contractor’s profit and over head 24.16
@ 15%
Cost of 1 no 185.25
Say 185.25

18.56 Providing and fixing PTMT pillar cock of approved quality and colour .
18.56.2 15mm nominal bore, 125mm long foam flow, Weighing not less than 120 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7401 15mm dia P.T.M.T. bib cockwith flange each 1 220.00 220.00
(fancy)
9999 Carriage & fixing charges L.S 9.49 1.00 9.49
TOTAL 229.49
Add for water charges @ 1 % 2.29
TOTAL 231.78
Add for contractor’s profit and over head 34.77
@ 15%
Cost of 1 no 266.55
Say 266.55

18.57 Providing and fixing PTMT, push cock of approved quality and colour.
18.57.1 15 mm nominal bore, 98mm long, Weighing not less than 75 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7407 15mm P.T.M.T. push cock each 1 90.00 90.00
9999 Carriage & fixing charges L.S 8.06 1.00 8.06
TOTAL 98.06
Add for water charges @ 1 % 0.98
TOTAL 99.04
Add for contractor’s profit and over head 14.86
@ 15%
Cost of 1 no 113.90
Say 113.90

18.57 Providing and fixing PTMT, push cock of approved quality and colour.
18.57.2 15 mm nominal bore, 80mm long, Weighing not less than 46 gms.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7408 P.T.M.T. push cock 12mm dia 20 mm BSP each 1 75.00 75.00

9999 Carriage & fixing charges L.S 8.06 1.00 8.06


TOTAL 83.06
Add for water charges @ 1 % 0.83
TOTAL 83.89
Add for contractor’s profit and over head 12.58
@ 15%
Cost of 1 no 96.47
Say 96.47

18.58 Providing and fixing PTMT grating of approved quality and colour.
18.58.1 Circular type.
18.58.1.1 100 mm nominal dia.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7409 100mm dia P.T.M.T. grating each 1 30.00 30.00
9999 Carriage & fixing charges L.S 4.16 1.00 4.16
TOTAL 34.16
Add for water charges @ 1 % 0.34
TOTAL 34.50
Add for contractor’s profit and over head 5.18
@ 15%
Cost of 1 no 39.68
Say 39.68

18.58 Providing and fixing PTMT grating of approved quality and colour.
18.58.1 Circular type.
18.58.1.2 125 mm nominal dia with 25 mm waste hole.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7411 125mm dia P.T.M.T. grating each 1 36.00 36.00
9999 Carriage & fixing charges L.S 4.16 1.00 4.16
TOTAL 40.16
Add for water charges @ 1 % 0.40
TOTAL 40.56
Add for contractor’s profit and over head 6.08
@ 15%
Cost of 1 no 46.65
Say 46.65

18.58 Providing and fixing PTMT grating of approved quality and colour.
18.58.2 Rectangular type with openable circular lid.
18.58.2.1 150 mm nominal size square 100 mm diameter of the inner hinged round grating.
Code Description Unit Quantity Rate Amount
Details of cost for 1 no.
M aterials
7412 150mm size square P.T.M.T. grating each 1 90.00 90.00
9999 Carriage & fixing charges L.S 4.16 1.00 4.16
TOTAL 94.16
Add for water charges @ 1 % 0.94
TOTAL 95.10
Add for contractor’s profit and over head 14.27
@ 15%
Cost of 1 no 109.37
Say 109.37

18.59 Providing and fixing C.I. double acting air valve of approved quality with bolts, nuts, rubber
insertions etc. complete (The tail pieces, tapers etc if required will be paid separately):
18.59.1 50mm dia
Code Description Unit Quantity Rate Amount
Details of cost for 10 no. double acting air valves
M aterials
7415 50mm dia, double acting air valve each 10 3050.00 30500.00
9999 Carriage of air valves L.S 26 1.00 26.00
9999 Labour for laying double acting air valve L.S 39 1.00 39.00
A Providing flanged joints to double acting each 10 75.76 757.62
air valves with bolts, nuts and rubber
insertions etc. (Rate as per item no 18.30.1
of SH : Water Supply)

TOTAL 31322.62
Add for water charges @ 1 % except on 305.65
A
TOTAL 31628.27
Add for contractor’s profit and over head 4630.60
@ 15% except on A
Cost of 10 no of air valves 36258.87
Cost of 1 no of air valve 3625.89
Say 3625.89

18.59 Providing and fixing C.I. double acting air valve of approved quality with bolts, nuts, rubber
insertions etc. complete (The tail pieces, tapers etc if required will be paid separately):
18.59.2 80 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for 10 no. double acting air valves
M aterials
7416 80mm dia, double acting air valve each 10 4480.00 44800.00
9999 Carriage of air valves L.S 26 1.00 26.00
9999 Labour for laying double acting air valve L.S 39 1.00 39.00
A Providing flanged joints to double acting each 10 75.76 757.62
air valves with bolts, nuts and rubber
insertions etc. (Rate as per item no 18.30.1
of SH : Water Supply)

TOTAL 45622.62
Add for water charges @ 1 % except on 448.65
A
TOTAL 46071.27
Add for contractor’s profit and over head 6797.05
@ 15% except on A
Cost of 10 no of air valves 52868.32
Cost of 1 no of air valve 5286.83
Say 5286.83

18.59 Providing and fixing C.I. double acting air valve of approved quality with bolts, nuts, rubber
insertions etc. complete (The tail pieces, tapers etc if required will be paid separately):
18.59.3 100mm dia
Code Description Unit Quantity Rate Amount
Details of cost for 10 no. double acting air valves
M aterials
7417 100mm dia, double acting air valve each 10 5800.00 58000.00
9999 Carriage of air valves L.S 26 1.00 26.00
9999 Labour for laying double acting air valve L.S 52 1.00 52.00
A Providing flanged joints to double acting each 10 127.12 1271.16
air valves with bolts, nuts and rubber
insertions etc. (Rate as per item no 18.30.2
of SH : Water Supply)

TOTAL 59349.16
Add for water charges @ 1 % except on 580.78
A
TOTAL 59929.94
Add for contractor’s profit and over head 8798.82
@ 15% except on A
Cost of 10 no of air valves 68728.75
Cost of 1 no of air valve 6872.88
Say 6872.88

18.60 Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by
Municipal B oard complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be
paid separately):
18.60.1 80 mm dia nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no. of water meter
M aterials
7418 80mm dia, double acting air valve each 1 1800.00 1800.00
9999 Testing charges L.S 130 1.00 130.00
9999 Carriage of air valves L.S 26 1.00 26.00
9999 Labour for laying double acting air valve L.S 39 1.00 39.00
A Providing flanged joints to double acting each 2 75.76 151.52
air valves with bolts, nuts and rubber
insertions etc. (Rate as per item no 18.30.1
of SH : Water Supply)

TOTAL 2146.52
Add for water charges @ 1 % except on 19.95
A
TOTAL 2166.47
Add for contractor’s profit and over head 302.24
@ 15% except on A
Cost of 1 no of air valve 2468.72
Say 2468.72

18.60 Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by
Municipal B oard complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be
paid separately):
18.60.2 100 mm dia nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no. of water meter
M aterials
7419 100mm dia, double acting air valve each 1 2800.00 2800.00
9999 Testing charges L.S 130 1.00 130.00
9999 Carriage of air valves L.S 26 1.00 26.00
9999 Labour for laying double acting air valve L.S 52 1.00 52.00
A Providing flanged joints to double acting each 2 127.12 254.23
air valves with bolts, nuts and rubber
insertions etc. (Rate as per item no 18.30.2
of SH : Water Supply)

TOTAL 3262.23
Add for water charges @ 1 % except on 30.08
A
TOTAL 3292.31
Add for contractor’s profit and over head 455.71
@ 15% except on A
Cost of 1 no of air valve 3748.02
Say 3748.02

18.60 Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by
Municipal B oard complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be
paid separately):
18.60.3 150 mm dia nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no. of water meter
M aterials
7420 150mm dia, double acting air valve each 1 4000.00 4000.00
9999 Testing charges L.S 156 1.00 156.00
9999 Carriage of air valves L.S 39 1.00 39.00
9999 Labour for laying double acting air valve L.S 65 1.00 65.00
A Providing flanged joints to double acting each 2 173.04 346.07
air valves with bolts, nuts and rubber
insertions etc. (Rate as per item no 18.30.4
of SH : Water Supply)

TOTAL 4606.07
Add for water charges @ 1 % except on 42.60
A
TOTAL 4648.67
Add for contractor’s profit and over head 645.39
@ 15% except on A
Cost of 1 no of air valve 5294.06
Say 5294.06

18.60 Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by
Municipal B oard complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be
paid separately):
18.60.4 200 mm dia nominal bore
Code Description Unit Quantity Rate Amount
Details of cost for 1 no. of water meter
M aterials
7421 200mm dia, double acting air valve each 1 4500.00 4500.00
9999 Testing charges L.S 156 1.00 156.00
9999 Carriage of air valves L.S 52 1.00 52.00
9999 Labour for laying double acting air valve L.S 104 1.00 104.00
A Providing flanged joints to double acting each 2 178.84 357.69
air valves with bolts, nuts and rubber
insertions etc. (Rate as per item no 18.30.5
of SH : Water Supply)

TOTAL 5169.69
Add for water charges @ 1 % except on 48.12
A
TOTAL 5217.81
Add for contractor’s profit and over head 729.02
@ 15% except on A
Cost of 1 no of air valve 5946.82
Say 5946.82

18.61 Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber
insertions etc. complete conforming to IS : 2373 :
18.61.1 80 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one no. dirt box strainer
Materials:
7422 80mm dia. dirt box strainer each 1 2500.00 2500.00
9999 Carriage of dirt box strainer L.S. 26 1.00 26.00
9999 Labour for faying dirt box strainer L.S. 39 1.00 39.00
Providing flanged joints to double acting
air valves with bolts, nuts and rubber
insertions etc.
(A) (Rate as per item no 18.30.1 of SH : Water each 2 75.76
Supply) 151.52
TOTAL 2716.52
Add 1% for water charges except on A
25.65
TOTAL 2742.17
Add for contractor’s profit and
overheads @15% except on A 388.60
Cost of 1 no. 3130.77
Say 3130.77

18.61 Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber
insertions etc. complete conforming to IS : 2373 :
18.61.2 100mm dia.
Code Description Unit Quantity Rate Amount
Details of cost for one no. dirt box strainer
Materials:
7423 100mm dia. dirt box strainer each 1 3750.00 3750.00
9999 Carriage of dirt box strainer L.S. 26 1.00 26.00
9999 Labour for faying dirt box strainer L.S. 52 1.00 52.00
Providing flanged joints to double acting
air valves with bolts, nuts and rubber
insertions etc.
(A) (Rate as per item no 18.30.2 of SH : Water each 2 127.12
Supply) 254.23
TOTAL 4082.23
Add 1% for water charges except on A
38.28
TOTAL 4120.51
Add for contractor’s profit and
overheads @15% except on A 579.94
Cost of 1 no. 4700.45
Say 4700.45

18.61 Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber
insertions etc. complete conforming to IS : 2373 :
18.61.3 150 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one no. dirt box strainer
Materials:
7424 150mm dia. dirt box strainer each 1 4850.00 4850.00
9999 Carriage of dirt box strainer L.S. 39 1.00 39.00
9999 Labour for faying dirt box strainer L.S. 65 1.00 65.00
Providing flanged joints to double acting
air valves with bolts, nuts and rubber
insertions etc.
(A) (Rate as per item no 18.30.4 of SH : Water each 2 173.04
Supply) 346.07
TOTAL 5300.07
Add 1% for water charges except on A
49.54
TOTAL 5349.61
Add for contractor’s profit and
overheads @15% except on A 750.53
Cost of 1 no. 6100.14
Say 6100.14

18.61 Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber
insertions etc. complete conforming to IS : 2373 :
18.61.4 200mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one no. dirt box strainer
Materials:
7425 200mm dia. dirt box strainer each 1 6800.00 6800.00
9999 Carriage of dirt box strainer L.S. 52 1.00 52.00
9999 Labour for faying dirt box strainer L.S. 104 1.00 104.00
Providing flanged joints to double acting
air valves with bolts, nuts and rubber
insertions etc.
(A) (Rate as per item no 18.30.5 of SH : Water each 2 178.84
Supply) 357.69
TOTAL 7313.69
Add 1% for water charges except on A
69.56
TOTAL 7383.25
Add for contractor’s profit and
overheads @15% except on A 1053.83
Cost of 1 no. 8437.08
Say 8437.08

18.62 Providing and fixing PTMT Ball cock of approved quality, colour and make complete with Epoxy
coated aluminium rod with L.P./ H.P.H.D. plastic ball.
18.62.1 15 mm nominal bore, 105mm long, weighing not less than 138gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7495 P.T.M.T. ball cock 15 mm complete with each 1 121.00
aluminium rod & H.D. ball 121.00
9999 Carriage of materials and fixing charges L.S. 21.58 1.00 21.58
TOTAL 142.58
Add 1% for water charges 1.43
TOTAL 144.01
Add for contractor’s profit and
overheads @15% 21.60
Cost of 1 no. 165.61
Say 165.61

18.62 Providing and fixing PTMT Ball cock of approved quality, colour and make complete with Epoxy
coated aluminium rod with L.P./ H.P.H.D. plastic ball.
18.62.2 20 mm nominal bore, 120mm long, weighing not less than 198gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7496 P.T.M.T. ball cock 20 mm complete with each 1 175.00
aluminium rod & H.D. ball 175.00
9999 Carriage of materials and fixing charges L.S. 26.91 1.00 26.91
TOTAL 201.91
Add 1% for water charges 2.02
TOTAL 203.93
Add for contractor’s profit and
overheads @15% 30.59
Cost of 1 no. 234.52
Say 234.52

18.62 Providing and fixing PTMT Ball cock of approved quality, colour and make complete with Epoxy
coated aluminium rod with L.P./ H.P.H.D. plastic ball.
18.62.3 25 mm nominal bore, 152mm long, weighing not less than 440gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7497 P.T.M.T. ball cock 25 mm complete with each 1 396.00
aluminium rod & H.D. ball 396.00
9999 Carriage of materials and fixing charges L.S. 32.24 1.00 32.24
TOTAL 428.24
Add 1% for water charges 4.28
TOTAL 432.52
Add for contractor’s profit and
overheads @15% 64.88
Cost of 1 no. 497.40
Say 497.40

18.62 Providing and fixing PTMT Ball cock of approved quality, colour and make complete with Epoxy
coated aluminium rod with L.P./ H.P.H.D. plastic ball.
18.62.4 40mm nominal bore, 206mm long, weighing not less than 690gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7498 P.T.M.T. ball cock 40 mm complete with each 1 745.00
aluminium rod & H.D. ball 745.00
9999 Carriage of materials and fixing charges L.S. 32.24 1.00 32.24
TOTAL 777.24
Add 1% for water charges 7.77
TOTAL 785.01
Add for contractor’s profit and
overheads @15% 117.75
Cost of 1 no. 902.76
Say 902.76

18.62 Providing and fixing PTMT Ball cock of approved quality, colour and make complete with Epoxy
coated aluminium rod with L.P./ H.P.H.D. plastic ball.
18.62.5 50mm nominal bore, 242mm long, weighing not less than 1240gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7499 P.T.M.T. ball cock 50 mm complete with each 1 1120.00
aluminium rod & H.D. ball 1120.00
9999 Carriage of materials and fixing charges L.S. 32.24 1.00 32.24
TOTAL 1152.24
Add 1% for water charges 11.52
TOTAL 1163.76
Add for contractor’s profit and
overheads @15% 174.56
Cost of 1 no. 1338.33
Say 1338.33

18.63 Providing and fixing PTMT angle stop cock 15 mm nominal bore, weighing not less than 85gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7500 P.T.M.T. angle stop cock with flange each 1 120.00 120.00
9999 Carriage of materials and fixing charges L.S. 8.06 1.00 8.06
TOTAL 128.06
Add 1% for water charges 1.28
TOTAL 129.34
Add for contractor’s profit and
overheads @15% 19.40
Cost of 1 no. 148.74
Say 148.74

18.64 Providing and fixing PTMT swivelling shower, 15 mm nominal bore, weighing not less than
40gms. Description
Code Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7501 Swiveling shower 15 mm each 1 81.00 81.00
9999 Carriage of materials and fixing charges L.S. 6.76 1.00 6.76
TOTAL 87.76
Add 1% for water charges 0.88
TOTAL 88.64
Add for contractor’s profit and
overheads @15% 13.30
Cost of 1 no. 101.93
Say 101.93

18.65 Providing and fixing PTMT soap Dish Holder having length of 138mm, breadth 102mm, height
of 75mm with concealed fitting arrangements weighing not less than 106 gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
Materials:
7509 Soap Dish/Holder 138x102x75mm each 1 108.00 108.00
9999 Carriage of materials and fixing charges L.S. 6.76 1.00 6.76
TOTAL 114.76
Add 1% for water charges 1.15
TOTAL 115.91
Add for contractor’s profit and
overheads @15% 17.39
Cost of 1 no. 133.29
Say 133.29

18.66 Providing and laying S&S C.I. Standard specials such as tees, bends, collars tapers and caps etc,
suitable for flanged jointing as per IS : 1538 :
18.66.1 Upto300mmdia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7708 Cost of specials quintal 1 3530.00 3530.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 3691.18
Add 1% for water charges except on A
35.35
TOTAL 3726.53
Add for contractor’s profit and
overheads @15% except on A 535.51
Cost of 1 no. 4262.04
Say 4262.04

18.66 Providing and laying S&S C.I. Standard specials such as tees, bends, collars tapers and caps etc,
suitable for flanged jointing as per IS : 1538 :
18.66.2 Above 300 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7709 Cost of specials quintal 1 3988.00 3988.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 4149.18
Add 1% for water charges except on A
39.93
TOTAL 4189.11
Add for contractor’s profit and
overheads @15% except on A 604.90
Cost of 1 no. 4794.01
Say 4794.01

18.67 Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382
18.67.1 Upto 300mmdia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7710 Cost of specials quintal 1 5338.00 5338.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 5499.18
Add 1% for water charges except on A
53.43
TOTAL 5552.61
Add for contractor’s profit and
overheads @15% except on A 809.42
Cost of 1 no. 6362.03
Say 6362.03
18.67 Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382
18.67.2 Above 300 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7711 Cost of specials quintal 1 5580.00 5580.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 5741.18
Add 1% for water charges except on A
55.85
TOTAL 5797.03
Add for contractor’s profit and
overheads @15% except on A 846.09
Cost of 1 no. 6643.12
Say 6643.12

18.68 Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523
18.68.1 Upto 600mmdia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7682 Cost of specials quintal 1 8938.00 8938.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 9099.18
Add 1% for water charges except on A
89.43
TOTAL 9188.61
Add for contractor’s profit and
overheads @15% except on A 1354.82
Cost of 1 no. 10543.43
Say 10543.43

18.68 Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523
18.68.2 Above 600 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7683 Cost of specials quintal 1 13413.00 13413.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 13574.18
Add 1% for water charges except on A
134.18
TOTAL 13708.36
Add for contractor’s profit and
overheads @15% except on A 2032.79
Cost of 1 no. 15741.14
Say 15741.14

18.69 Providing and laying D.I Specials of Class K-12suitable for mechanical jointing as per IS :9523
18.69.1 Upto 600 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7684 Cost of specials quintal 1 9400.00 9400.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 9561.18
Add 1% for water charges except on A
94.05
TOTAL 9655.23
Add for contractor’s profit and
overheads @15% except on A 1424.82
Cost of 1 no. 11080.05
Say 11080.05

18.69 Providing and laying D.I Specials of Class K-12suitable for mechanical jointing as per IS :9523
18.69.2 Above 600 mm dia
Code Description Unit Quantity Rate Amount
Details of cost for one quintal
Materials:
7685 Cost of specials quintal 1 14239.00 14239.00
2309 Carriage of materials tonne 0.1 47.29 4.73
Labour
(A) For laying Rate as per item No. 18.24 quintal 1 156.45 156.45
TOTAL 14400.18
Add 1% for water charges except on A
142.44
TOTAL 14542.62
Add for contractor’s profit and
overheads @15% except on A 2157.92
Cost of 1 no. 16700.54
Say 16700.54
18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.1 100 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7666 Cost of rubber gasket quintal 50 25.00 1250.00
Labour
116 Fitter (grade 1) Day 1 270 270.00
117 Assistant Fitter or 2nd class Fitter Day 1 223 223.00
114 Beldar Day 1 207 207.00
TOTAL 1950.00
Add 1% for water charges 19.50
TOTAL 1969.50
Add for contractor’s profit and
overheads @15% 295.43
Cost for 50 joints 2264.93
Cost of 1 joint 45.30
Say 45.30

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.2 150 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7668 Cost of rubber gasket quintal 50 35.00 1750.00
Labour
116 Fitter (grade 1) Day 1.5 270 405.00
117 Assistant Fitter or 2nd class Fitter Day 1.5 223 334.50
114 Beldar Day 3 207 621.00
TOTAL 3110.50
Add 1% for water charges 31.11
TOTAL 3141.61
Add for contractor’s profit and
overheads @15% 471.24
Cost for 50 joints 3612.85
Cost of 1 joint 72.26
Say 72.26

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.3 200 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7669 Cost of rubber gasket quintal 50 62.00 3100.00
Labour
116 Fitter (grade 1) Day 2 270 540.00
117 Assistant Fitter or 2nd class Fitter Day 2 223 446.00
114 Beldar Day 4 207 828.00
TOTAL 4914.00
Add 1% for water charges 49.14
TOTAL 4963.14
Add for contractor’s profit and
overheads @15% 744.47
Cost for 50 joints 5707.61
Cost of 1 joint 114.15
Say 114.15

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.4 250 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7670 Cost of rubber gasket quintal 50 68.00 3400.00
Labour
116 Fitter (grade 1) Day 2.5 270 675.00
117 Assistant Fitter or 2nd class Fitter Day 2.5 223 557.50
114 Beldar Day 5 207 1035.00
TOTAL 5667.50
Add 1% for water charges 56.68
TOTAL 5724.18
Add for contractor’s profit and
overheads @15% 858.63
Cost for 50 joints 6582.80
Cost of 1 joint 131.66
Say 131.66

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.5 300 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7671 Cost of rubber gasket quintal 50 98.00 4900.00
Labour
116 Fitter (grade 1) Day 3 270 810.00
117 Assistant Fitter or 2nd class Fitter Day 3 223 669.00
114 Beldar Day 6 207 1242.00
TOTAL 7621.00
Add 1% for water charges 76.21
TOTAL 7697.21
Add for contractor’s profit and
overheads @15% 1154.58
Cost for 50 joints 8851.79
Cost of 1 joint 177.04
Say 177.04

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.6 350 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7672 Cost of rubber gasket quintal 50 123.00 6150.00
Labour
116 Fitter (grade 1) Day 3 270 810.00
117 Assistant Fitter or 2nd class Fitter Day 3 223 669.00
114 Beldar Day 6 207 1242.00
TOTAL 8871.00
Add 1% for water charges 88.71
TOTAL 8959.71
Add for contractor’s profit and
overheads @15% 1343.96
Cost for 50 joints 10303.67
Cost of 1 joint 206.07
Say 206.07

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.7 400 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7673 Cost of rubber gasket quintal 50 248.00 12400.00
Labour
116 Fitter (grade 1) Day 4 270 1080.00
117 Assistant Fitter or 2nd class Fitter Day 4 223 892.00
114 Beldar Day 8 207 1656.00
TOTAL 16028.00
Add 1% for water charges 160.28
TOTAL 16188.28
Add for contractor’s profit and
overheads @15% 2428.24
Cost for 50 joints 18616.52
Cost of 1 joint 372.33
Say 372.33

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.8 450 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7674 Cost of rubber gasket quintal 50 275.00 13750.00
Labour
116 Fitter (grade 1) Day 4.5 270 1215.00
117 Assistant Fitter or 2nd class Fitter Day 4.5 223 1003.50
114 Beldar Day 9 207 1863.00
TOTAL 17831.50
Add 1% for water charges 178.32
TOTAL 18009.82
Add for contractor’s profit and
overheads @15% 2701.47
Cost for 50 joints 20711.29
Cost of 1 joint 414.23
Say 414.23

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.9 500 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7675 Cost of rubber gasket quintal 50 285.00 14250.00
Labour
116 Fitter (grade 1) Day 4.75 270 1282.50
117 Assistant Fitter or 2nd class Fitter Day 4.75 223 1059.25
114 Beldar Day 9.5 207 1966.50
TOTAL 18558.25
Add 1% for water charges 185.58
TOTAL 18743.83
Add for contractor’s profit and
overheads @15% 2811.57
Cost for 50 joints 21555.41
Cost of 1 joint 431.11
Say 431.11
18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.10 600 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7676 Cost of rubber gasket quintal 50 348.00 17400.00
Labour
116 Fitter (grade 1) Day 6.5 270 1755.00
117 Assistant Fitter or 2nd class Fitter Day 6.5 223 1449.50
114 Beldar Day 13 207 2691.00
TOTAL 23295.50
Add 1% for water charges 232.96
TOTAL 23528.46
Add for contractor’s profit and
overheads @15% 3529.27
Cost for 50 joints 27057.72
Cost of 1 joint 541.15
Say 541.15

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.11 650 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7677 Cost of rubber gasket quintal 50 550.00 27500.00
Labour
116 Fitter (grade 1) Day 7.7 270 2079.00
117 Assistant Fitter or 2nd class Fitter Day 7.7 223 1717.10
114 Beldar Day 15.4 207 3187.80
TOTAL 34483.90
Add 1% for water charges 344.84
TOTAL 34828.74
Add for contractor’s profit and
overheads @15% 5224.31
Cost for 50 joints 40053.05
Cost of 1 joint 801.06
Say 801.06

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.12 700 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7678 Cost of rubber gasket quintal 50 648.00 32400.00
Labour
116 Fitter (grade 1) Day 7.7 270 2079.00
117 Assistant Fitter or 2nd class Fitter Day 7.7 223 1717.10
114 Beldar Day 15.4 207 3187.80
TOTAL 39383.90
Add 1% for water charges 393.84
TOTAL 39777.74
Add for contractor’s profit and
overheads @15% 5966.66
Cost for 50 joints 45744.40
Cost of 1 joint 914.89
Say 914.89

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.13 800 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7679 Cost of rubber gasket quintal 50 725.00 36250.00
Labour
116 Fitter (grade 1) Day 8.5 270 2295.00
117 Assistant Fitter or 2nd class Fitter Day 8.5 223 1895.50
114 Beldar Day 17 207 3519.00
TOTAL 43959.50
Add 1% for water charges 439.60
TOTAL 44399.10
Add for contractor’s profit and
overheads @15% 6659.86
Cost for 50 joints 51058.96
Cost of 1 joint 1021.18
Say 1021.18

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.14 900 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7680 Cost of rubber gasket quintal 50 968.00 48400.00
Labour
116 Fitter (grade 1) Day 10 270 2700.00
117 Assistant Fitter or 2nd class Fitter Day 10 223 2230.00
114 Beldar Day 20 207 4140.00
TOTAL 57470.00
Add 1% for water charges 574.70
TOTAL 58044.70
Add for contractor’s profit and
overheads @15% 8706.71
Cost for 50 joints 66751.41
Cost of 1 joint 1335.03
Say 1335.03

18.70 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including
testing of joints and including the cost of rubber gasket:
18.70.15 1000 mm dia pipes
Code Description Unit Quantity Rate Amount
Details of cost for 50 joints
Materials:
7681 Cost of rubber gasket quintal 50 1188.00 59400.00
Labour
116 Fitter (grade 1) Day 11 270 2970.00
117 Assistant Fitter or 2nd class Fitter Day 11 223 2453.00
114 Beldar Day 22 207 4554.00
TOTAL 69377.00
Add 1% for water charges 693.77
TOTAL 70070.77
Add for contractor’s profit and
overheads @15% 10510.62
Cost for 50 joints 80581.39
Cost of 1 joint 1611.63
Say 1611.63

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.1 100 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7712 Screwed double flanged centrifugally metre 5 977.00 4885.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 100mm dia

2319 Ductile iron pipes (k7) 100 mm dia 00 metre 5 116.3 5.82
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 1.35 84.79 114.47
Water Supply
TOTAL 5005.29
Add 1% for water charges except on A 48.91

TOTAL 5054.20
Add for contractor’s profit and 740.96
overheads @15% except on A
Cost of 5 metres 5795.15
Cost of 1 metres 1159.03
Say 1159.03

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.2 150 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7713 Screwed double flanged centrifugally metre 5 1511.00 7555.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 150mm dia

2321 Ductile iron pipes (k7) 150 mm dia 00 metre 5 193.83 9.69
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 2.21 84.79 187.39
Water Supply
TOTAL 7752.09
Add 1% for water charges except on A 75.65

TOTAL 7827.73
Add for contractor’s profit and 1146.05
overheads @15% except on A
Cost of 5 metres 8973.78
Cost of 1 metres 1794.76
Say 1794.76

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.3 200 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7714 Screwed double flanged centrifugally metre 5 2092.00 10460.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 200mm dia

2322 Ductile iron pipes (k7) 200 mm dia 00 metre 5 315.3 15.77
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 3.18 84.79 269.64
Water Supply
TOTAL 10745.41
Add 1% for water charges except on A 104.76

TOTAL 10850.17
Add for contractor’s profit and 1587.08
overheads @15% except on A
Cost of 5 metres 12437.25
Cost of 1 metres 2487.45
Say 2487.45

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.4 250 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7715 Screwed double flanged centrifugally metre 5 2800.00 14000.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 250mm dia

2323 Ductile iron pipes (k7) 250 mm dia 00 metre 5 448.05 22.40
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 4.27 84.79 362.07
Water Supply
TOTAL 14384.47
Add 1% for water charges except on A 140.22

TOTAL 14524.70
Add for contractor’s profit and 2124.39
overheads @15% except on A
Cost of 5 metres 16649.09
Cost of 1 metres 3329.82
Say 3329.82

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.5 300 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7716 Screwed double flanged centrifugally metre 5 3559.00 17795.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 300mm dia

2324 Ductile iron pipes (k7) 300 mm dia 00 metre 5 553.8 27.69
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 5.5 84.79 466.37
Water Supply
TOTAL 18289.06
Add 1% for water charges except on A 178.23

TOTAL 18467.28
Add for contractor’s profit and 2700.14
overheads @15% except on A
Cost of 5 metres 21167.42
Cost of 1 metres 4233.48
Say 4233.48

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.6 350 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7717 Screwed double flanged centrifugally metre 5 4553.00 22765.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 350mm dia

2325 Ductile iron pipes (k7) 350 mm dia 00 metre 5 775.32 38.77
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 6.79 84.79 575.75
Water Supply
TOTAL 23379.52
Add 1% for water charges except on A 228.04

TOTAL 23607.56
Add for contractor’s profit and 3454.77
overheads @15% except on A
Cost of 5 metres 27062.33
Cost of 1 metres 5412.47
Say 5412.47

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.7 400 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7718 Screwed double flanged centrifugally metre 5 5885.00 29425.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 400mm dia

2326 Ductile iron pipes (k7) 400 mm dia 00 metre 5 1,057.26 52.86
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 8.34 84.79 707.18
Water Supply
TOTAL 30185.05
Add 1% for water charges except on A 294.78

TOTAL 30479.82
Add for contractor’s profit and 4465.90
overheads @15% except on A
Cost of 5 metres 34945.72
Cost of 1 metres 6989.14
Say 6989.14

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.8 450 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7719 Screwed double flanged centrifugally metre 5 7627.00 38135.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 450mm dia

2327 Ductile iron pipes (k7) 450 mm dia 00 metre 5 1,292.20 64.61
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 10.08 84.79 854.72
Water Supply
TOTAL 39054.33
Add 1% for water charges except on A 382.00

TOTAL 39436.33
Add for contractor’s profit and 5787.24
overheads @15% except on A
Cost of 5 metres 45223.57
Cost of 1 metres 9044.71
Say 9044.71

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.9 500 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7720 Screwed double flanged centrifugally metre 5 9962.00 49810.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 500mm dia
2328 Ductile iron pipes (k7) 500 mm dia 00 metre 5 1,292.20 64.61
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 11.74 84.79 995.48
Water Supply
TOTAL 50870.09
Add 1% for water charges except on A 498.75

TOTAL 51368.84
Add for contractor’s profit and 7556.00
overheads @15% except on A
Cost of 5 metres 58924.84
Cost of 1 metres 11784.97
Say 11784.97

18.71 Providing and laying Double Flanged (screwed/ welded) Centrifugally (Spun) Cast Iron, Class B
(IS : 1536):
18.71.10 600 mm dia C.I. Double Flanged Pipe
Code Description Unit Quantity Rate Amount
Details of cost for 5 metres
Materials:
7721 Screwed double flanged centrifugally metre 5 12992.00 64960.00
cast (spun) C.I. Pipe of Class B
conforming to I.S. 1536, - 600mm dia

2329 Ductile iron pipes (k7) 600 mm dia 00 metre 5 1,938.30 96.92
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 15.77 84.79 1337.20
Water Supply
TOTAL 66394.12
Add 1% for water charges except on A 650.57

TOTAL 67044.69
Add for contractor’s profit and 9856.12
overheads @15% except on A
Cost of 5 metres 76900.81
Cost of 1 metres 15380.16
Say 15380.16

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.1 100 mm dia D uctile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7722 Ductile Iron Class K- 7 pipe conforming to metre 10 597.00 5970.00
I.S. 8329 - 100mm dia
2343 Ductile iron pipes (k7) 100 mm dia 00 metre 10 116.3 11.63
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 1.54 84.79 130.58
Water Supply
TOTAL 6112.21
Add 1% for water charges except on A 59.82

TOTAL 6172.03
Add for contractor’s profit and 906.22
overheads @15% except on A
Cost of 10 metres 7078.25
Cost of 1 metres 707.82
Say 707.82

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.2 150 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7723 Ductile Iron Class K- 7 pipe conforming to metre 10 870.00 8700.00
I.S. 8329 - 150mm dia
2344 Ductile iron pipes (k7) 150 mm dia 00 metre 10 193.83 19.38
Labour for laying
A Rate same as per item no 18.23 SH : quintal 2.28 84.79 193.33
Water Supply
TOTAL 8912.71
Add 1% for water charges except on A 87.19

TOTAL 8999.91
Add for contractor’s profit and 1320.99
overheads @15% except on A
Cost of 10 metres 10320.89
Cost of 1 metres 1032.09
Say 1032.09

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.3 200 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7724 Ductile Iron Class K- 7 pipe conforming to metre 10 1237.00 12370.00
I.S. 8329 - 200mm dia
2345 Ductile iron pipes (k7) 200 mm dia 00 metre 10 315.3 31.53
Labour for laying
A Rate same as per item no 18.23 SH : quintal 3.01 84.79 255.23
Water Supply
TOTAL 12656.76
Add 1% for water charges except on A 124.02

TOTAL 12780.78
Add for contractor’s profit and 1878.83
overheads @15% except on A
Cost of 10 metres 14659.61
Cost of 1 metres 1465.96
Say 1465.96

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.4 250 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7725 Ductile Iron Class K- 7 pipe conforming to metre 10 1675.00 16750.00
I.S. 8329 - 250mm dia
2346 Ductile iron pipes (k7) 250 mm dia 00 metre 10 448.05 44.81
Labour for laying
A Rate same as per item no 18.23 SH : quintal 3.93 84.79 333.24
Water Supply
TOTAL 17128.05
Add 1% for water charges except on A 167.95

TOTAL 17295.99
Add for contractor’s profit and 2544.41
overheads @15% except on A
Cost of 10 metres 19840.41
Cost of 1 metres 1984.04
Say 1984.04

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.5 300 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7726 Ductile Iron Class K- 7 pipe conforming to metre 10 2369.00 23690.00
I.S. 8329 - 300mm dia
2347 Ductile iron pipes (k7) 300 mm dia 00 metre 10 553.8 55.38
Labour for laying
A Rate same as per item no 18.23 SH : quintal 4.84 84.79 410.40
Water Supply
TOTAL 24155.78
Add 1% for water charges except on A 237.45
TOTAL 24393.24
Add for contractor’s profit and 3597.43
overheads @15% except on A
Cost of 10 metres 27990.66
Cost of 1 metres 2799.07
Say 2799.07

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.6 350 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7727 Ductile Iron Class K- 7 pipe conforming to metre 10 2728.00 27280.00
I.S. 8329 - 350mm dia
2348 Ductile iron pipes (k7) 350 mm dia 00 metre 10 775.32 77.53
Labour for laying
A Rate same as per item no 18.23 SH : quintal 6.6 84.79 559.64
Water Supply
TOTAL 27917.17
Add 1% for water charges except on A 273.58

TOTAL 28190.75
Add for contractor’s profit and 4144.67
overheads @15% except on A
Cost of 10 metres 32335.41
Cost of 1 metres 3233.54
Say 3233.54

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72..7 400 mm dia Ductile Iron Class K.-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7728 Ductile Iron Class K- 7 pipe conforming to metre 10 3256.00 32560.00
I.S. 8329 - 400mm dia
2349 Ductile iron pipes (k7) 400 mm dia 00 metre 10 1,057.26 105.73
Labour for laying
A Rate same as per item no 18.23 SH : quintal 7.83 84.79 663.94
Water Supply
TOTAL 33329.66
Add 1% for water charges except on A 326.66

TOTAL 33656.32
Add for contractor’s profit and 4948.86
overheads @15% except on A
Cost of 10 metres 38605.18
Cost of 1 metres 3860.52
Say 3860.52

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.8 450 mm dia D uctile Iron Class K.-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7729 Ductile Iron Class K- 7 pipe conforming to metre 10 3861.00 38610.00
I.S. 8329 - 450mm dia
2350 Ductile iron pipes (k7) 450 mm dia 00 metre 10 1,292.20 129.22
Labour for laying
A Rate same as per item no 18.23 SH : quintal 9.14 84.79 775.02
Water Supply
TOTAL 39514.24
Add 1% for water charges except on A 387.39

TOTAL 39901.63
Add for contractor’s profit and 5868.99
overheads @15% except on A
Cost of 10 metres 45770.62
Cost of 1 metres 4577.06
Say 4577.06

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.9 500 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7730 Ductile Iron Class K- 7 pipe conforming to metre 10 4557.00 45570.00
I.S. 8329 - 500mm dia
2351 Ductile iron pipes (k7) 500 mm dia 00 metre 10 1,292.20 129.22
Labour for laying
A Rate same as per item no 18.23 SH : quintal 10.66 84.79 903.90
Water Supply
TOTAL 46603.12
Add 1% for water charges except on A 456.99

TOTAL 47060.12
Add for contractor’s profit and 6923.43
overheads @15% except on A
Cost of 10 metres 53983.55
Cost of 1 metres 5398.35
Say 5398.35
18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.10 600 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7731 Ductile Iron Class K- 7 pipe conforming to metre 10 6011.00 60110.00
I.S. 8329 - 600mm dia
2352 Ductile iron pipes (k7) 600 mm dia 00 metre 10 1,938.30 193.83
Labour for laying
A Rate same as per item no 18.23 SH : quintal 13.86 84.79 1175.25
Water Supply
TOTAL 61479.08
Add 1% for water charges except on A 603.04

TOTAL 62082.11
Add for contractor’s profit and 9136.03
overheads @15% except on A
Cost of 10 metres 71218.14
Cost of 1 metres 7121.81
Say 7121.81

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.11 700 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7732 Ductile Iron Class K- 7 pipe conforming to metre 10 7463.00 74630.00
I.S. 8329 - 700mm dia
2353 Ductile iron pipes (k7) 700 mm dia 00 metre 10 1,938.30 193.83
Labour for laying
A Rate same as per item no 18.23 SH : quintal 18.89 84.79 1601.76
Water Supply
TOTAL 76425.59
Add 1% for water charges except on A 748.24

TOTAL 77173.83
Add for contractor’s profit and 11335.81
overheads @15% except on A
Cost of 10 metres 88509.64
Cost of 1 metres 8850.96
Say 8850.96

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.12 800 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7733 Ductile Iron Class K- 7 pipe conforming to metre 10 10405.00 104050.00
I.S. 8329 - 800mm dia
2355 Ductile iron pipes (k7) 800 mm dia 00 metre 10 1,938.30 193.83
Labour for laying
A Rate same as per item no 18.23 SH : quintal 24.35 84.79 2064.73
Water Supply
TOTAL 106308.56
Add 1% for water charges except on A 1042.44

TOTAL 107351.00
Add for contractor’s profit and 15792.94
overheads @15% except on A
Cost of 10 metres 123143.94
Cost of 1 metres 12314.39
Say 12314.39

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.13 900 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7734 Ductile Iron Class K- 7 pipe conforming to metre 10 12798.00 127980.00
I.S. 8329 - 900mm dia
2356 Ductile iron pipes (k7) 900 mm dia 00 metre 10 2,907.45 290.75
Labour for laying
A Rate same as per item no 18.23 SH : quintal 28.27 84.79 2397.13
Water Supply
TOTAL 130667.87
Add 1% for water charges except on A 1282.71

TOTAL 131950.58
Add for contractor’s profit and 19433.02
overheads @15% except on A
Cost of 10 metres 151383.60
Cost of 1 metres 15138.36
Say 15138.36

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.14 1000 mm dia Ductile Iron Class K-7 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7735 Ductile Iron Class K- 7 pipe conforming to metre 10 15505.00 155050.00
I.S. 8329 - 900mm dia
2357 Ductile iron pipes (k7) 900 mm dia 00 metre 10 3,876.61 387.66
Labour for laying
A Rate same as per item no 18.23 SH : quintal 34.82 84.79 2952.53
Water Supply
TOTAL 158390.19
Add 1% for water charges except on A 1554.38

TOTAL 159944.57
Add for contractor’s profit and 23548.81
overheads @15% except on A
Cost of 10 metres 183493.37
Cost of 1 metres 18349.34
Say 18349.34

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.15 100 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7651 Ductile Iron Class K- 9 pipe conforming to metre 10 658.00 6580.00
I.S. 8329 - 100mm dia
2319 Ductile iron pipes (k9) 100 mm dia 00 metre 10 116.3 11.63
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 1.776 84.79 150.59
Water Supply
TOTAL 6742.22
Add 1% for water charges except on A 65.92

TOTAL 6808.14
Add for contractor’s profit and 998.63
overheads @15% except on A
Cost of 10 metres 7806.77
Cost of 1 metres 780.68
Say 780.68

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.16 150 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7652 Ductile Iron Class K- 9 pipe conforming to metre 10 978.00 9780.00
I.S. 8329 - 150mm dia
2321 Ductile iron pipes (k9) 150 mm dia 00 metre 10 193.83 19.38
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 2.627 84.79 222.75
Water Supply
TOTAL 10022.14
Add 1% for water charges except on A 97.99

TOTAL 10120.13
Add for contractor’s profit and 1484.61
overheads @15% except on A
Cost of 10 metres 11604.74
Cost of 1 metres 1160.47
Say 1160.47

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.17 200 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7653 Ductile Iron Class K- 9 pipe conforming to metre 10 1348.00 13480.00
I.S. 8329 - 200mm dia
2322 Ductile iron pipes (k9) 200 mm dia 00 metre 10 315.3 31.53
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 3.615 84.79 306.53
Water Supply
TOTAL 13818.06
Add 1% for water charges except on A 135.12

TOTAL 13953.18
Add for contractor’s profit and 2047.00
overheads @15% except on A
Cost of 10 metres 16000.17
Cost of 1 metres 1600.02
Say 1600.02

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.18 250 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7654 Ductile Iron Class K- 9 pipe conforming to metre 10 1743.00 17430.00
I.S. 8329 - 250mm dia
2323 Ductile iron pipes (k9) 250 mm dia 00 metre 10 448.05 44.81
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 4.8 84.79 407.01
Water Supply
TOTAL 17881.82
Add 1% for water charges except on A 174.75

TOTAL 18056.56
Add for contractor’s profit and 2647.43
overheads @15% except on A
Cost of 10 metres 20704.00
Cost of 1 metres 2070.40
Say 2070.40

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.19 300 mm dia D uctile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7655\ Ductile Iron Class K- 9 pipe conforming to metre 10 2238.00 22380.00
I.S. 8329 - 300mm dia
2324 Ductile iron pipes (k9) 300 mm dia 00 metre 10 553.8 55.38
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 6.049 84.79 512.92
Water Supply
TOTAL 22948.30
Add 1% for water charges except on A 224.35

TOTAL 23172.65
Add for contractor’s profit and 3398.96
overheads @15% except on A
Cost of 10 metres 26571.61
Cost of 1 metres 2657.16
Say 2657.16

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.20 350 mm dia D uctile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7656 Ductile Iron Class K- 9 pipe conforming to metre 10 2625.00 26250.00
I.S. 8329 - 350mm dia
2325 Ductile iron pipes (k9) 350 mm dia 00 metre 10 775.32 77.53
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 7.973 84.79 676.06
Water Supply
TOTAL 27003.59
Add 1% for water charges except on A 263.28
TOTAL 27266.87
Add for contractor’s profit and 3988.62
overheads @15% except on A
Cost of 10 metres 31255.49
Cost of 1 metres 3125.55
Say 3125.55

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.21 400 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7657 Ductile Iron Class K- 9 pipe conforming to metre 10 3763.00 37630.00
I.S. 8329 - 400mm dia
2326 Ductile iron pipes (k9) 400 mm dia 00 metre 10 1,057.26 105.73
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 9.48 84.79 803.85
Water Supply
TOTAL 38539.57
Add 1% for water charges except on A 377.36

TOTAL 38916.93
Add for contractor’s profit and 5716.96
overheads @15% except on A
Cost of 10 metres 44633.89
Cost of 1 metres 4463.39
Say 4463.39

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.22 450 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7658 Ductile Iron Class K- 9 pipe conforming to metre 10 4175.00 41750.00
I.S. 8329 - 450mm dia
2327 Ductile iron pipes (k9) 450 mm dia 00 metre 10 1,292.20 129.22
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 11.097 84.79 940.96
Water Supply
TOTAL 42820.18
Add 1% for water charges except on A 418.79

TOTAL 43238.97
Add for contractor’s profit and 6344.70
overheads @15% except on A
Cost of 10 metres 49583.67
Cost of 1 metres 4958.37
Say 4958.37

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.23 500 mm dia D uctile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7659 Ductile Iron Class K- 9 pipe conforming to metre 10 5600.00 56000.00
I.S. 8329 - 500mm dia
2328 Ductile iron pipes (k9) 500 mm dia 00 metre 10 1,292.20 129.22
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 12.948 84.79 1097.91
Water Supply
TOTAL 57227.13
Add 1% for water charges except on A 561.29

TOTAL 57788.43
Add for contractor’s profit and 8503.58
overheads @15% except on A
Cost of 10 metres 66292.00
Cost of 1 metres 6629.20
Say 6629.20

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.24 600 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7660 Ductile Iron Class K- 9 pipe conforming to metre 10 6275.00 62750.00
I.S. 8329 - 600mm dia
2329 Ductile iron pipes (k9) 600 mm dia 00 metre 10 1,938.30 193.83
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 16.868 84.79 1430.31
Water Supply
TOTAL 64374.14
Add 1% for water charges except on A 629.44

TOTAL 65003.57
Add for contractor’s profit and 9535.99
overheads @15% except on A
Cost of 10 metres 74539.56
Cost of 1 metres 7453.96
Say 7453.96
18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.25 700 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7661 Ductile Iron Class K- 9 pipe conforming to metre 10 8538.00 85380.00
I.S. 8329 - 700mm dia
2330 Ductile iron pipes (k9) 700 mm dia 00 metre 10 1,292.20 129.22
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 21.754 84.79 1844.61
Water Supply
TOTAL 87353.83
Add 1% for water charges except on A 855.09

TOTAL 88208.92
Add for contractor’s profit and 12954.65
overheads @15% except on A
Cost of 10 metres 101163.57
Cost of 1 metres 10116.36
Say 10116.36

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.26 750 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7662 Ductile Iron Class K- 9 pipe conforming to metre 10 9725.00 97250.00
I.S. 8329 - 750mm dia
2331 Ductile iron pipes (k9) 750 mm dia 00 metre 10 2,907.45 290.75
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 24.26 84.79 2057.10
Water Supply
TOTAL 99597.85
Add 1% for water charges except on A 975.41

TOTAL 100573.26
Add for contractor’s profit and 14777.42
overheads @15% except on A
Cost of 10 metres 115350.68
Cost of 1 metres 11535.07
Say 11535.07

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.27 800 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7663 Ductile Iron Class K- 9 pipe conforming to metre 10 10000.00 100000.00
I.S. 8329 - 800mm dia
2332 Ductile iron pipes (k9) 800 mm dia 00 metre 10 3,876.61 387.66
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 26.71 84.79 2264.85
Water Supply
TOTAL 102652.51
Add 1% for water charges except on A 1003.88

TOTAL 103656.39
Add for contractor’s profit and 15208.73
overheads @15% except on A
Cost of 10 metres 118865.12
Cost of 1 metres 11886.51
Say 11886.51

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.28 900 mm dia Ductile Iron Class K-9 pipes
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7664 Ductile Iron Class K- 9 pipe conforming to metre 10 11663.00 116630.00
I.S. 8329 - 900mm dia
2333 Ductile iron pipes (k9) 900 mm dia 00 metre 10 3,876.61 387.66
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 32.129 84.79 2724.35
Water Supply
TOTAL 119742.01
Add 1% for water charges except on A 1170.18

TOTAL 120912.18
Add for contractor’s profit and 17728.18
overheads @15% except on A
Cost of 10 metres 138640.36
Cost of 1 metres 13864.04
Say 13864.04

18.72 Providing and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming to IS :
8329
18.72.29 1000 mm dia Ductile Iron Class K-9 pipes.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Materials:
7665 Ductile Iron Class K- 9 pipe conforming to metre 10 13125.00 131250.00
I.S. 8329 - 1000mm dia
2334 Ductile iron pipes (k9) 1000 mm dia 00 metre 10 3,876.61 387.66
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 38.019 84.79 3223.78
Water Supply
TOTAL 134861.44
Add 1% for water charges except on A 1316.38

TOTAL 136177.82
Add for contractor’s profit and 19943.11
overheads @15% except on A
Cost of 10 metres 156120.93
Cost of 1 metres 15612.09
Say 15612.09

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.1 100 mm dia Ductile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7686 100 mm dia. ductile iron pipes double metre 5 1888.00 9440.00
flanged
2319 Ductile iron pipes (k9) 100 mm dia 00 metre 5 116.30 5.82
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 1.09 84.79 92.43
Water Supply
TOTAL 9538.24
Add 1% for water charges except on A 94.46

TOTAL 9632.70
Add for contractor’s profit and 1431.04
overheads @15% except on A
Cost of 5 metres 11063.74
Cost of 1 metres 2212.75
Say 2212.75

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.2 150 mm dia Ductile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7687 150 mm dia. ductile iron pipes double metre 5 2613.00 13065.00
flanged
2321 Ductile iron pipes (k9) 150 mm dia 00 metre 5 193.83 9.69
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 1.63 84.79 138.21
Water Supply
TOTAL 13212.91
Add 1% for water charges except on A 130.75

TOTAL 13343.65
Add for contractor’s profit and 1980.82
overheads @15% except on A
Cost of 5 metres 15324.47
Cost of 1 metres 3064.89
Say 3064.89

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.3 200 mm dia D uctile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7688 200 mm dia. ductile iron pipes double metre 5 3388.00 16940.00
flanged
2322 Ductile iron pipes (k9) 200 mm dia 00 metre 5 315.3 15.77
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 2.21 84.79 187.39
Water Supply
TOTAL 17143.16
Add 1% for water charges except on A 169.56

TOTAL 17312.72
Add for contractor’s profit and 2568.80
overheads @15% except on A
Cost of 5 metres 19881.52
Cost of 1 metres 3976.30
Say 3976.30

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.4 250 mm dia Ductile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7689 250 mm dia. ductile iron pipes double metre 5 4498.00 22490.00
flanged
2323 Ductile iron pipes (k9) 250 mm dia 00 metre 5 448.05 22.40
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 2.97 84.79 251.84
Water Supply
TOTAL 22764.24
Add 1% for water charges except on A 225.12

TOTAL 22989.36
Add for contractor’s profit and 3410.63
overheads @15% except on A
Cost of 5 metres 26399.99
Cost of 1 metres 5280.00
Say 5280.00

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.5 300 mm dia D uctile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7690 300 mm dia. ductile iron pipes double metre 5 5788.00 28940.00
flanged
2324 Ductile iron pipes (k9) 300 mm dia 00 metre 5 553.8 27.69
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 3.82 84.79 323.91
Water Supply
TOTAL 29291.60
Add 1% for water charges except on A 289.68

TOTAL 29581.28
Add for contractor’s profit and 4388.61
overheads @15% except on A
Cost of 5 metres 33969.89
Cost of 1 metres 6793.98
Say 6793.98

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.6 350 mm dia Ductile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7691 350 mm dia. ductile iron pipes double metre 5 7210.00 36050.00
flanged
2325 Ductile iron pipes (k9) 350 mm dia 00 metre 5 775.32 38.77
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 4.57 84.79 387.51
Water Supply
TOTAL 36476.27
Add 1% for water charges except on A 360.89

TOTAL 36837.16
Add for contractor’s profit and 5467.45
overheads @15% except on A
Cost of 5 metres 42304.61
Cost of 1 metres 8460.92
Say 8460.92

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.7 400 mm dia D uctile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7692 400 mm dia. ductile iron pipes double metre 5 8613.00 43065.00
flanged
2326 Ductile iron pipes (k9) 400 mm dia 00 metre 5 1,057.26 52.86
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 5.4 84.79 457.89
Water Supply
TOTAL 43575.75
Add 1% for water charges except on A 431.18

TOTAL 44006.93
Add for contractor’s profit and 6532.36
overheads @15% except on A
Cost of 5 metres 50539.29
Cost of 1 metres 10107.86
Say 10107.86

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.8 450 mm dia Ductile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7693 450 mm dia. ductile iron pipes double metre 5 10413.00 52065.00
flanged
2327 Ductile iron pipes (k9) 450 mm dia 00 metre 5 1,292.20 64.61
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 6.39 84.79 541.83
Water Supply
TOTAL 52671.44
Add 1% for water charges except on A 521.30

TOTAL 53192.74
Add for contractor’s profit and 7897.64
overheads @15% except on A
Cost of 5 metres 61090.38
Cost of 1 metres 12218.08
Say 12218.08

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.9 500 mm dia D uctile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7694 500 mm dia. ductile iron pipes double metre 5 12625.00 63125.00
flanged
2328 Ductile iron pipes (k9) 500 mm dia 00 metre 5 1,292.20 64.61
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 7.4 84.79 627.48
Water Supply
TOTAL 63817.09
Add 1% for water charges except on A 631.90

TOTAL 64448.98
Add for contractor’s profit and 9573.23
overheads @15% except on A
Cost of 5 metres 74022.21
Cost of 1 metres 14804.44
Say 14804.44

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.10 600 mm dia Ductile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7695 600 mm dia. ductile iron pipes double metre 5 17125.00 85625.00
flanged
2329 Ductile iron pipes (k9) 600 mm dia 00 metre 5 1,938.30 96.92
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 9.95 84.79 843.70
Water Supply
TOTAL 86565.62
Add 1% for water charges except on A 857.22

TOTAL 87422.83
Add for contractor’s profit and 12986.87
overheads @15% except on A
Cost of 5 metres 100409.70
Cost of 1 metres 20081.94
Say 20081.94

18.73 Providing and laying Double Flanged (Screwed/ Welded) Centrifugally (Spun) Ductile Iron Pipes
of Class K 9 conforming to IS : 8329 :
18.73.11 700 mm dia D uctile Iron Double Flanged
Code Description Unit Quantity Rate Amount
Details of cost for 5 metre
Materials:
7696 700 mm dia. ductile iron pipes double metre 5 21125.00 105625.00
flanged
2330 Ductile iron pipes (k9) 700 mm dia 00 metre 5 1,292.20 64.61
Labour for laying
A (A) Rate same as per item no 18.23 SH : quintal 12.75 84.79 1081.12
Water Supply
TOTAL 106770.73
Add 1% for water charges except on A 1056.90

TOTAL 107827.63
Add for contractor’s profit and 16011.98
overheads @15% except on A
Cost of 5 metres 123839.61
Cost of 1 metres 24767.92
Say 24767.92

18.74 Providing and fixing unplastisised P.V.C. connection pipe with PTMT Nuts of approved quality
and colour.
18.74.1 15 mm nominal bore with 30cm length.
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials :
7862 15 mm nominal bore and 30 cm length each 1 27.00
PVC connection pipe with P.T.M.T. Nuts
27.00
9999 Carriage of materials and fixing charges L.S. 12.22 1.00 12.22
TOTAL 39.22
Add 1% for water charges 0.39
TOTAL 39.61
Add for contractor’s profit and 5.94
overheads @15%
Cost of 1 no. 45.55
Say 45.55

18.74 Providing and fixing unplastisised P.V.C. connection pipe with PTMT Nuts of approved quality
and colour.
18.74.2 15 mm nominal bore with 45 cm length.
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials :
7863 15 mm nominal bore and 45 cm length each 1 32.00
PVC connection pipe with P.T.M.T. Nuts
32.00
9999 Carriage of materials and fixing charges L.S. 13.52 1.00 13.52
TOTAL 45.52
Add 1% for water charges 0.46
TOTAL 45.98
Add for contractor’s profit and 6.90
overheads @15%
Cost of 1 no. 52.87
Say 52.87

18.75 Providing and fixing PTMT extension nipple for water tank pipe, fittings of approved
quality
18.75.1and colour.
15 mm nominal bore. Weighing not less than 32gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials :
7864 P.T.M.T extension nipple 15mm each 1 30.00 30.00
9999 Carriage of materials and fixing charges L.S. 3.38 1.00 3.38
TOTAL 33.38
Add 1% for water charges 0.33
TOTAL 33.71
Add for contractor’s profit and 5.06
overheads @15%
Cost of 1 no. 38.77
Say 38.77

18.75 Providing and fixing PTMT extension nipple for water tank pipe, fittings of approved
quality
18.75.2and colour.
20mm nominal bore. Weighing not less than 40gms.
Code Description Unit Quantity Rate Amount
Details of cost for one no
Materials :
7865 P.T.M.T extension nipple 20mm each 1 36.00 36.00
9999 Carriage of materials and fixing charges L.S. 3.38 1.00 3.38
TOTAL 39.38
Add 1% for water charges 0.39
TOTAL 39.77
Add for contractor’s profit and 5.97
overheads @15%
Cost of 1 no. 45.74
Say 45.74

18.76 Cutting holes upto 30x30 cm in walls including making good the same :
18.76.1 With F.P.S. bricks.
Code Description Unit Quantity Rate Amount
Details of cost 10 holes
Materials :-
123 Mason 1st Class Day 0.16 270 43.20
124 Mason Ilnd Class Day 0.16 223 35.68
114 Beldar Day 1.25 207 258.75
Brick work with bricks of class cum 0.21 2482.32
designation 75 in cement mortar 1:4 (1
Cement: 4 coarse sand) in foundations
and plinth (Rate as per item no 6.4.1 of
SH : Brick Work)
521.29 A
12mm cement plaster 1:4 (1 Cement: 4 sqm 1.2 95.89
Coarse sand) finished w ith a floating
coat of neat cement (Rate as per item no .
13.4.1)
115.07 A
9999 Add for delay L.S. 16.12 1.00 16.12
9999 Sundries L.S. 8.06 1.00 8.06
TOTAL 998.17
Add for water charges @ 1 % excpet on ‘A 3.62 (B)
TOTAL 1001.79
Add 15% for contractor’s profit and 54.81
overheads on (A+B)
Cost of 10 no. of holes 1056.60
Cost of 1no. of hole 105.66
Say 105.66

18.77 Cutting holes upto 15x15 cm in R.C.C. floors and roofs for passing drain pipe etc. and
repairing the hole after insertion of drain pipe etc. with cement concrete 1:2:4 (1 cement : 2
coarse sand : 4 graded stone aggregate 20 mm nominal size) including finishing complete so
as to make
Details of itcost
leak10
proof.
holes
Materials :-
123 Mason 1st Class Day 0.83 270 224.10
124 Mason Ilnd Class Day 0.83 223 185.09
114 Beldar Day 1.67 207 345.69
Cement concrete 1:2:4 (1 cement: 2 cum 0.02 5140.53
coarse sand ; 4 graded stone aggregate 20
mm nominal size) (Rate as per item no 102.81 A
4.1.3 SH : Concrete work)
9999 Finishing top and bottom and making the L.S. 121.16 1.00 121.16
9999 Add for delay L.S. 40.3 1.00 40.30
9999 Sundries L.S. 21.58 1.00 21.58
TOTAL 1040.73
Add for water charges @ 1 % excpet on ‘A 9.38 (B)
TOTAL 1050.11
Add 15% for contractor’s profit and 142.09
overheads excpet on ‘A
Cost of 10 no. of holes 1192.20
Cost of 1no. of hole 119.22
Say 119.22

18.78 Making chases upto 7.5x7.5 cm in wails including making good and finishing with
matching surface after housing G.I. pipe etc.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Labour for making chases
114 Beldar Day 1 207 207.00
123 Mason 1st class Day 0.25 270 67.50
124 Mason 2nd class Day 0.25 223 55.75
Cement concrete 1:3:6 (1 cement: 3 cum 0.04 3,828.42 153.14
coarse sand : 6 graded stone aggregate 20
mm nominal size) (Rate as per item no
4.2.5 SH : C oncrete work)
A
TOTAL 483.39
Add 1% for water charges except on A 3.30

TOTAL 486.69
Add for contractor’s profit and 50.03
overheads @15% except on A
Cost of 10 m 536.72
Cost of 1 m 53.67
Say 53.67

18.79 Making hole upto 20x20 cm and embedding pipes upto 150 mm diameter in
masonry and filling with cement concrete 1:3:6 (1 cement: 3 coarse sand : 6 graded stone
aggregate 20 mm nominal size) including disposal of malba.
Code Description Unit Quantity Rate Amount
Details of cost for 10 metres
Labour for making chases
9999 Disposal of malba L.S 13.52 1.00 13.52
Cement concrete 1:3:6 (1 cement: 3 cum 0.22 3,828.42 842.25
coarse sand : 6 graded stone aggregate 20
mm nominal size) (Rate as per item no
4.2.5 SH : C oncrete work)
A
TOTAL 855.77
Add 1% for water charges except on A 0.14

TOTAL 855.91
Add for contractor’s profit and 2.05
overheads @15% except on A
Cost of 10 m 857.96
Cost of 1 m 85.80
Say 85.80

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.1 80mm diametre C.I, pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.008 1550.00 12.40
9,999 Sundries including testing of samples L.S. 9.88 1.00 9.88
116 Fitter I class Day 0.33 270 89.10
114 Beldar Day 1.31 207 271.17
TOTAL 382.55
Add 1% for water charges 3.83
TOTAL 386.38
Add for contractor’s profit and 57.96
overheads @15%
Cost of 100 metres 444.33
Say 444.33

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.2 100 mm dia metre C.l.pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.012 1550.00 18.60
9,999 Sundries including testing of samples L.S. 13.52 1.00 13.52
116 Fitter I class Day 0.49 270 132.30
114 Beldar Day 1.64 207 339.48
TOTAL 503.90
Add 1% for water charges 5.04
TOTAL 508.94
Add for contractor’s profit and 76.34
overheads @15%
Cost of 100 metres 585.28
Say 585.28

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.3 125 mm diametre C.I, pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.018 1550.00 27.90
9,999 Sundries including testing of samples L.S. 17.94 1.00 17.94
116 Fitter I class Day 0.66 270 178.20
114 Beldar Day 1.97 207 407.79
TOTAL 631.83
Add 1% for water charges 6.32
TOTAL 638.15
Add for contractor’s profit and 95.72
overheads @15%
Cost of 100 metres 733.87
Say 733.87

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.4 150mm dia metre C.l,pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.027 1550.00 41.85
9,999 Sundries including testing of samples L.S. 22.88 1.00 22.88
116 Fitter I class Day 0.82 270 221.40
114 Beldar Day 2.3 207 476.10
TOTAL 762.23
Add 1% for water charges 7.62
TOTAL 769.85
Add for contractor’s profit and 115.48
overheads @15%
Cost of 100 metres 885.33
Say 885.33
18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.5 200mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.047 1550.00 72.85
9,999 Sundries including testing of samples L.S. 31.46 1.00 31.46
116 Fitter I class Day 1.15 270 310.50
114 Beldar Day 2.95 207 610.65
TOTAL 1025.46
Add 1% for water charges 10.25
TOTAL 1035.71
Add for contractor’s profit and 155.36
overheads @15%
Cost of 100 metres 1191.07
Say 1191.07

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.6 250 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.074 1550.00 114.70
9,999 Sundries including testing of samples L.S. 40.3 1.00 40.30
116 Fitter I class Day 1.48 270 399.60
114 Beldar Day 3.61 207 747.27
TOTAL 1301.87
Add 1% for water charges 13.02
TOTAL 1314.89
Add for contractor’s profit and 197.23
overheads @15%
Cost of 100 metres 1512.12
Say 1512.12

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.7 300 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.106 1550.00 164.30
9,999 Sundries including testing of samples L.S. 44.46 1.00 44.46
116 Fitter I class Day 1.64 270 442.80
114 Beldar Day 3.94 207 815.58
TOTAL 1467.14
Add 1% for water charges 14.67
TOTAL 1481.81
Add for contractor’s profit and 222.27
overheads @15%
Cost of 100 metres 1704.08
Say 1704.08

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.8 350 mm diametre C.I, pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.144 1550.00 223.20
9,999 Sundries including testing of samples L.S. 48.36 1.00 48.36
116 Fitter I class Day 1.8 270 486.00
114 Beldar Day 4.27 207 883.89
TOTAL 1641.45
Add 1% for water charges 16.41
TOTAL 1657.86
Add for contractor’s profit and 248.68
overheads @15%
Cost of 100 metres 1906.54
Say 1906.54

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.9 400 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.189 1550.00 292.95
9,999 Sundries including testing of samples L.S. 53.82 1.00 53.82
116 Fitter I class Day 1.97 270 531.90
114 Beldar Day 4.59 207 950.13
TOTAL 1828.80
Add 1% for water charges 18.29
TOTAL 1847.09
Add for contractor’s profit and 277.06
overheads @15%
Cost of 100 metres 2124.15
Say 2124.15

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.10 450 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.239 1550.00 370.45
9,999 Sundries including testing of samples L.S. 58.24 1.00 58.24
116 Fitter I class Day 2.13 270 575.10
114 Beldar Day 4.92 207 1018.44
TOTAL 2022.23
Add 1% for water charges 20.22
TOTAL 2042.45
Add for contractor’s profit and 306.37
overheads @15%
Cost of 100 metres 2348.82
Say 2348.82

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.11 500 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.295 1550.00 457.25
9,999 Sundries including testing of samples L.S. 63.7 1.00 63.70
116 Fitter I class Day 2.3 270 621.00
114 Beldar Day 5.25 207 1086.75
TOTAL 2228.70
Add 1% for water charges 22.29
TOTAL 2250.99
Add for contractor’s profit and 337.65
overheads @15%
Cost of 100 metres 2588.64
Say 2588.64

18.80 Disinfecting C.I. water mains by flushing with water containing bleaching powder at
0.5 gms per litre of water and cleaning the same with fresh water, operation to be repeated
three times including getting the sample of water from the disinfected main tested in the
municipal laboratory :
18.80.12 600 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.424 1550.00 657.20
9,999 Sundries including testing of samples L.S. 71.37 1.00 71.37
116 Fitter I class Day 2.62 270 707.40
114 Beldar Day 5.91 207 1223.37
TOTAL 2659.34
Add 1% for water charges 26.59
TOTAL 2685.93
Add for contractor’s profit and 402.89
overheads @15%
Cost of 100 metres 3088.82
Say 3088.82

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.1 80 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.003 1550.00 4.65
9,999 Sundries including testing of samples L.S. 4.42 1.00 4.42
116 Fitter I class Day 0.11 270 29.70
114 Beldar Day 0.49 207 101.43
TOTAL 140.20
Add 1% for water charges 1.40
TOTAL 141.60
Add for contractor’s profit and 21.24
overheads @15%
Cost of 100 metres 162.84
Say 162.84

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.2 100mm diametreC.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.004 1550.00 6.20
9,999 Sundries including testing of samples L.S. 4.42 1.00 4.42
116 Fitter I class Day 0.16 270 43.20
114 Beldar Day 0.57 207 117.99
TOTAL 171.81
Add 1% for water charges 1.72
TOTAL 173.53
Add for contractor’s profit and 26.03
overheads @15%
Cost of 100 metres 199.56
Say 199.56

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.3 125mm dia metre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.006 1550.00 9.30
9,999 Sundries including testing of samples L.S. 5.46 1.00 5.46
116 Fitter I class Day 0.22 270 59.40
114 Beldar Day 0.66 207 136.62
TOTAL 210.78
Add 1% for water charges 2.11
TOTAL 212.89
Add for contractor’s profit and 31.93
overheads @15%
Cost of 100 metres 244.82
Say 244.82

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.4 150 mm dia metre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.009 1550.00 13.95
9,999 Sundries including testing of samples L.S. 7.15 1.00 7.15
116 Fitter I class Day 0.27 270 72.90
114 Beldar Day 0.74 207 153.18
TOTAL 247.18
Add 1% for water charges 2.47
TOTAL 249.65
Add for contractor’s profit and 37.45
overheads @15%
Cost of 100 metres 287.10
Say 287.10

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.5 200 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.016 1550.00 24.80
9,999 Sundries including testing of samples L.S. 9.88 1.00 9.88
116 Fitter I class Day 0.58 270 156.60
114 Beldar Day 0.9 207 186.30
TOTAL 377.58
Add 1% for water charges 3.78
TOTAL 381.36
Add for contractor’s profit and 57.20
overheads @15%
Cost of 100 metres 438.56
Say 438.56

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.6 250 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.025 1550.00 38.75
9,999 Sundries including testing of samples L.S. 10.79 1.00 10.79
116 Fitter I class Day 0.6 270 162.00
114 Beldar Day 1.1 207 227.70
TOTAL 439.24
Add 1% for water charges 4.39
TOTAL 443.63
Add for contractor’s profit and 66.54
overheads @15%
Cost of 100 metres 510.18
Say 510.18

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.7 300 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.035 1550.00 54.25
9,999 Sundries including testing of samples L.S. 13.52 1.00 13.52
116 Fitter I class Day 0.6 270 162.00
114 Beldar Day 1.3 207 269.10
TOTAL 498.87
Add 1% for water charges 4.99
TOTAL 503.86
Add for contractor’s profit and 75.58
overheads @15%
Cost of 100 metres 579.44
Say 579.44

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.8 350 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.048 1550.00 74.40
9,999 Sundries including testing of samples L.S. 16.12 1.00 16.12
116 Fitter I class Day 0.7 270 189.00
114 Beldar Day 1.5 207 310.50
TOTAL 590.02
Add 1% for water charges 5.90
TOTAL 595.92
Add for contractor’s profit and 89.39
overheads @15%
Cost of 100 metres 685.31
Say 685.31

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.9 400 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.063 1550.00 97.65
9,999 Sundries including testing of samples L.S. 17.64 1.00 17.64
116 Fitter I class Day 0.8 270 216.00
114 Beldar Day 1.7 207 351.90
TOTAL 683.19
Add 1% for water charges 6.83
TOTAL 690.02
Add for contractor’s profit and 103.50
overheads @15%
Cost of 100 metres 793.53
Say 793.53

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.10 450 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.08 1550.00 124.00
9,999 Sundries including testing of samples L.S. 20.67 1.00 20.67
116 Fitter I class Day 0.9 270 243.00
114 Beldar Day 1.9 207 393.30
TOTAL 780.97
Add 1% for water charges 7.81
TOTAL 788.78
Add for contractor’s profit and 118.32
overheads @15%
Cost of 100 metres 907.10
Say 907.10

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.11 500 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.098 1550.00 151.90
9,999 Sundries including testing of samples L.S. 23.27 1.00 23.27
116 Fitter I class Day 1 270 270.00
114 Beldar Day 2.1 207 434.70
TOTAL 879.87
Add 1% for water charges 8.80
TOTAL 888.67
Add for contractor’s profit and 133.30
overheads @15%
Cost of 100 metres 1021.97
Say 1021.97

18.81 Extra for every operation of disinfecting the C.I. main by flushing with water
containing bleaching powder at 0.5 gms per litre of water and cleaning the same with fresh
water, including getting the samples of water tested in the municipal laboratory :
18.81.12 600 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
Materials:
1301 Bleaching powder quintal 0.141 1550.00 218.55
9,999 Sundries including testing of samples L.S. 26 1.00 26.00
116 Fitter I class Day 1.2 270 324.00
114 Beldar Day 2.5 207 517.50
TOTAL 1086.05
Add 1% for water charges 10.86
TOTAL 1096.91
Add for contractor’s profit and 164.54
overheads @15%
Cost of 100 metres 1261.45
Say 1261.45

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of mm
18.82.1 80 pipesdiametre
at site lead
C.I.upto
pipe.50 metre :
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 16.31 129.74 2116.06
A {Rate as per item no. 2.25) cum 16.31 71.56 1167.14
Materials:
761 Fuel wood quintal 0.373 265.00 98.85
771 Kerosene oil quintal 0.379 25.00 9.48
9,999 Sundries including testing of samples L.S. 53.82 1.00 53.82
117 Fitter II class Day 0.5 223 111.50
114 Beldar Day 4 207 828.00
TOTAL 4384.84
Add 1% for water charges except on A 11.02

TOTAL 4395.86
Add for contractor’s profit and 166.90
overheads @15% except on A
Cost of 40.26 metres 4562.76
Cost of 1 metre 113.33
Say 113.33

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipesdiametre
18.82.2 100mm at site lead
C.I.upto
pipe.50 metre :
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 16.17 129.74 2097.90
A {Rate as per item no. 2.25) cum 16.17 71.56 1157.13
Materials:
761 Fuel wood quintal 0.466 265.00 123.49
771 Kerosene oil quintal 0.379 25.00 9.48
9,999 Sundries including testing of samples L.S. 53.82 1.00 53.82
117 Fitter II class Day 0.63 223 140.49
114 Beldar Day 4.5 207 931.50
TOTAL 4513.80
Add 1% for water charges except on A 12.59

TOTAL 4526.38
Add for contractor’s profit and 190.70
overheads @15% except on A
Cost of 40.26 metres 4717.09
Cost of 1 metre 117.17
Say 117.17

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes
18.82.3 125 at site lead
mm diametre upto
C.I, 50 metre :
pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 15.96 129.74 2070.65
A {Rate as per item no. 2.25) cum 15.96 71.56 1142.10
Materials:
761 Fuel wood quintal 0.559 265.00 148.14
771 Kerosene oil quintal 0.568 25.00 14.20
9,999 Sundries including testing of samples L.S. 53.82 1.00 53.82
117 Fitter II class Day 0.75 223 167.25
114 Beldar Day 5 207 1035.00
TOTAL 4631.15
Add 1% for water charges except on A 14.18

TOTAL 4645.34
Add for contractor’s profit and 214.89
overheads @15% except on A
Cost of 40.26 metres 4860.23
Cost of 1 metre 120.72
Say 120.72

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipesdia
18.82.4 150mm at site
metrelead upto
C.I. 50 metre :
pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 15.7 129.74 2036.92
A {Rate as per item no. 2.25) cum 15.7 71.56 1123.49
Materials:
761 Fuel wood quintal 0.653 265.00 173.05
771 Kerosene oil quintal 0.568 25.00 14.20
9,999 Sundries including testing of samples L.S. 67.21 1.00 67.21
117 Fitter II class Day 0.887 223 197.80
114 Beldar Day 5.5 207 1138.50
TOTAL 4751.17
Add 1% for water charges except on A 15.91

TOTAL 4767.07
Add for contractor’s profit and 241.00
overheads @15% except on A
Cost of 40.26 metres 5008.07
Cost of 1 metre 124.39
Say 124.39

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes
18.82.5 200 at site lead
mm diametre upto
C.I. 50 metre :
pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 16.56 129.74 2148.49
A {Rate as per item no. 2.25) cum 16.56 71.56 1185.03
Materials:
761 Fuel wood quintal 0.84 265.00 222.60
771 Kerosene oil quintal 0.7576 25.00 18.94
9,999 Sundries including testing of samples L.S. 67.21 1.00 67.21
117 Fitter II class Day 1.1 223 245.30
114 Beldar Day 6.5 207 1345.50
TOTAL 5233.08
Add 1% for water charges except on A 19.00

TOTAL 5252.07
Add for contractor’s profit and 287.78
overheads @15% except on A
Cost of 40.26 metres 5539.86
Cost of 1 metre 137.60
Say 137.60

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes
18.82.6 250 at site lead
mm diametre upto
C.I. 50 metre :
pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 17.26 129.74 2239.31
A {Rate as per item no. 2.25) cum 17.26 71.56 1235.13
Materials:
761 Fuel wood quintal 1.026 265.00 271.89
771 Kerosene oil quintal 1.1365 25.00 28.41
9,999 Sundries including testing of samples L.S. 80.73 1.00 80.73
117 Fitter II class Day 1.3 223 289.90
114 Beldar Day 7.5 207 1552.50
TOTAL 5697.87
Add 1% for water charges except on A 22.23

TOTAL 5720.10
Add for contractor’s profit and 336.85
overheads @15% except on A
Cost of 40.26 metres 6056.95
Cost of 1 metre 150.45
Say 150.45

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes
18.82.7 300 at site lead
mm diametre upto
C.I. 50 metre :
pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 17.79 129.74 2308.07
A {Rate as per item no. 2.25) cum 17.79 71.56 1273.05
Materials:
761 Fuel wood quintal 1.12 265.00 296.80
771 Kerosene oil quintal 1.515 25.00 37.88
9,999 Sundries including testing of samples L.S. 94.12 1.00 94.12
117 Fitter II class Day 1.5 223 334.50
114 Beldar Day 8.5 207 1759.50
TOTAL 6103.92
Add 1% for water charges except on A 25.23

TOTAL 6129.15
Add for contractor’s profit and 382.20
overheads @15% except on A
Cost of 40.26 metres 6511.35
Cost of 1 metre 161.73
Say 161.73
18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes at site lead upto 50 metre :
18.82.8 350 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 18.14 129.74 2353.48
A {Rate as per item no. 2.25) cum 18.14 71.56 1298.10
Materials:
761 Fuel wood quintal 1.213 265.00 321.45
771 Kerosene oil quintal 1.515 25.00 37.88
9,999 Sundries including testing of samples L.S. 107.64 1.00 107.64
117 Fitter II class Day 1.75 223 390.25
114 Beldar Day 9.5 207 1966.50
TOTAL 6475.29
Add 1% for water charges except on A 28.24

TOTAL 6503.53
Add for contractor’s profit and 427.79
overheads @15% except on A
Cost of 40.26 metres 6931.32
Cost of 1 metre 172.16
Say 172.16

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipesdia
18.82.9 400mm at site
metrelead
C.l.upto 50 metre :
pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 18.23 129.74 2365.16
A {Rate as per item no. 2.25) cum 18.23 71.56 1304.54
Materials:
761 Fuel wood quintal 1.306 265.00 346.09
771 Kerosene oil quintal 1.894 25.00 47.35
9,999 Sundries including testing of samples L.S. 121.03 1.00 121.03
117 Fitter II class Day 2 223 446.00
114 Beldar Day 10.5 207 2173.50
TOTAL 6803.67
Add 1% for water charges except on A 31.34

TOTAL 6835.01
Add for contractor’s profit and 474.80
overheads @15% except on A
Cost of 40.26 metres 7309.81
Cost of 1 metre 181.56
Say 181.56

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes at site lead upto 50 metre :
18.82.10 450 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 18.38 129.74 2384.62
A {Rate as per item no. 2.25) cum 18.38 71.56 1315.27
Materials:
761 Fuel wood quintal 1.4 265.00 371.00
771 Kerosene oil quintal 2.273 25.00 56.83
9,999 Sundries including testing of samples L.S. 134.55 1.00 134.55
117 Fitter II class Day 2.25 223 501.75
114 Beldar Day 11.5 207 2380.50
TOTAL 7144.52
Add 1% for water charges except on A 34.45

TOTAL 7178.97
Add for contractor’s profit and 521.86
overheads @15% except on A
Cost of 40.26 metres 7700.83
Cost of 1 metre 191.28
Say 191.28

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes at site lead upto 50 metre :
18.82.11 500 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 18.24 129.74 2366.46
A {Rate as per item no. 2.25) cum 18.24 71.56 1305.25
Materials:
761 Fuel wood quintal 1.492 265.00 395.38
771 Kerosene oil quintal 2.652 25.00 66.30
9,999 Sundries including testing of samples L.S. 147.94 1.00 147.94
117 Fitter II class Day 2.5 223 557.50
114 Beldar Day 12.5 207 2587.50
TOTAL 7426.33
Add 1% for water charges except on A 37.55

TOTAL 7463.88
Add for contractor’s profit and 568.82
overheads @15% except on A
Cost of 40.26 metres 8032.70
Cost of 1 metre 199.52
Say 199.52

18.82 Dismantling old C.I. pipes including excavation and refilling trenches after taking out
the pipes, breaking lead caulked joints, melting of lead and making into blocks including
stacking of pipes at site lead upto 50 metre :
18.82.12 600 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Details of cost for 40.26 metres or 11 no. of joints
Materials:
Earth work in excavationfor
dismantling pipes including refilling
of excavated earth
A (Rate as per item no. 2.8.1) cum 17.44 129.74 2262.67
A {Rate as per item no. 2.25) cum 17.44 71.56 1248.01
Materials:
761 Fuel wood quintal 1.68 265.00 445.20
771 Kerosene oil quintal 3.41 25.00 85.25
9,999 Sundries including testing of samples L.S. 174.85 1.00 174.85
117 Fitter II class Day 3 223 669.00
114 Beldar Day 14.5 207 3001.50
TOTAL 7886.47
Add 1% for water charges except on A 43.76

TOTAL 7930.23
Add for contractor’s profit and 662.93
overheads @15% except on A
Cost of 40.26 metres 8593.16
Cost of 1 metre 213.44
Say 213.44

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.1 80 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.06 270 16.20
114 Beldar Day 0.06 207 12.42
9999 Scaffolding and sundries L.S 1.82 1.00 1.82
TOTAL 30.44
Add 1% for water charges 0.30
TOTAL 30.74
Add 15% for contractor’s profit and 4.61
overheads
Cost of each cut 35.36
Say 35.36

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.2 100 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.08 270 21.60
114 Beldar Day 0.08 207 16.56
9999 Scaffolding and sundries L.S 2.73 1.00 2.73
TOTAL 40.89
Add 1% for water charges 0.41
TOTAL 41.30
Add 15% for contractor’s profit and 6.19
overheads
Cost of each cut 47.49
Say 47.49

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.3 125 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.11 270 29.70
114 Beldar Day 0.11 207 22.77
9999 Scaffolding and sundries L.S 4.42 1.00 4.42
TOTAL 56.89
Add 1% for water charges 0.57
TOTAL 57.46
Add 15% for contractor’s profit and 8.62
overheads
Cost of each cut 66.08
Say 66.08

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.4 150 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.15 270 40.50
114 Beldar Day 0.15 207 31.05
9999 Scaffolding and sundries L.S 5.33 1.00 5.33
TOTAL 76.88
Add 1% for water charges 0.77
TOTAL 77.65
Add 15% for contractor’s profit and 11.65
overheads
Cost of each cut 89.30
Say 89.30

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.5 200 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.2 270 54.00
114 Beldar Day 0.2 207 41.40
9999 Scaffolding and sundries L.S 7.15 1.00 7.15
TOTAL 102.55
Add 1% for water charges 1.03
TOTAL 103.58
Add 15% for contractor’s profit and 15.54
overheads
Cost of each cut 119.11
Say 119.11

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.6 250 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.25 270 67.50
114 Beldar Day 0.25 207 51.75
9999 Scaffolding and sundries L.S 8.06 1.00 8.06
TOTAL 127.31
Add 1% for water charges 1.27
TOTAL 128.58
Add 15% for contractor’s profit and 19.29
overheads
Cost of each cut 147.87
Say 147.87

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.7 300 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.3 270 81.00
114 Beldar Day 0.3 207 62.10
9999 Scaffolding and sundries L.S 9.88 1.00 9.88
TOTAL 152.98
Add 1% for water charges 1.53
TOTAL 154.51
Add 15% for contractor’s profit and 23.18
overheads
Cost of each cut 177.69
Say 177.69

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.8 350 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.35 270 94.50
114 Beldar Day 0.35 207 72.45
9999 Scaffolding and sundries L.S 10.79 1.00 10.79
TOTAL 177.74
Add 1% for water charges 1.78
TOTAL 179.52
Add 15% for contractor’s profit and 26.93
overheads
Cost of each cut 206.45
Say 206.45

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.9 400 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.4 270 108.00
114 Beldar Day 0.4 207 82.80
9999 Scaffolding and sundries L.S 12.48 1.00 12.48
TOTAL 203.28
Add 1% for water charges 2.03
TOTAL 205.31
Add 15% for contractor’s profit and 30.80
overheads
Cost of each cut 236.11
Say 236.11

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.10 450 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.45 270 121.50
114 Beldar Day 0.45 207 93.15
9999 Scaffolding and sundries L.S 13.52 1.00 13.52
TOTAL 228.17
Add 1% for water charges 2.28
TOTAL 230.45
Add 15% for contractor’s profit and 34.57
overheads
Cost of each cut 265.02
Say 265.02

18.83 Labour for cutting C.I. pipe with steel saw.


18.83.11 500 mm diametre C.I. pipe
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.5 270 135.00
114 Beldar Day 0.5 207 103.50
9999 Scaffolding and sundries L.S 15.21 1.00 15.21
TOTAL 253.71
Add 1% for water charges 2.54
TOTAL 256.25
Add 15% for contractor’s profit and 38.44
overheads
Cost of each cut 294.68
Say 294.68
18.83 Labour for cutting C.I. pipe with steel saw.
18.83.12 600 mm diametre C.I. pipe.
Code Description Unit Quantity Rate Amount
Detail of cost for one cut
LABOUR
116 Fitter (Grade I) Day 0.6 270 162.00
114 Beldar Day 0.6 207 124.20
9999 Scaffolding and sundries L.S 16.12 1.00 16.12
TOTAL 302.32
Add 1% for water charges 3.02
TOTAL 305.34
Add 15% for contractor’s profit and 45.80
overheads
Cost of each cut 351.14
Say 351.14
19.1 Providing, laying and jointing glazed stoneware pipes grade ‘A’ with stiff mixture of cement mortar
in the of 1:1 (1 cement: 1 fine sand) including testing of joints etc. complete :
19.1.1 100 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for 30 metre
M ATER IALS
1854 100 mm s tone ware pipes 60 cm long each 55 30.00 1650.00
2224 Carriage of pipes 100m 33 70.94 23.41
367 Cement for slurry tonne 0.019 5200.00 98.80
2209 Carriage of cem ent tunne 0.019 47.29 0.90
983 Fine sand cum 0.01 300.00 3.00
2261 Carriage of fine sand cum 0.01 53.21 0.53
1881 Spun yarn kg 4.5 30.00 135.00
LABOUR
123 Mason ist class Day 1 270 270.00
124 Mason 2nd class Day 1 223 223.00
114 Beldar Day 3 207 621.00
101 Bhishti Day 1 180 180.00
TOTAL 3205.64
Add 1% for water charges 32.06
TOTAL 3237.70
Add for contractor’s profit and overheads 485.65
@15%
Cost of 30 metres 3723.35
Cost of 1 metres 124.11
Say 124.11

19.1 Providing, laying and jointing glazed stoneware pipes grade ‘A’ with stiff mixture of cement mortar
in the of 1:1 (1 cement: 1 fine sand) including testing of joints etc. complete :
19.1.2 150 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for 30 metre
M ATER IALS
1855 150 mm s tone ware pipes 60 cm long each 55 42.00 2310.00
2225 Carriage of pipes 100m 33 141.88 46.82
367 Cement for slurry tonne 0.036 5200.00 187.20
2209 Carriage of cem ent tunne 0.036 47.29 1.70
983 Fine sand cum 0.019 300.00 5.70
2261 Carriage of fine sand cum 0.019 53.21 1.01
1881 Spun yarn kg 9 30.00 270.00
LABOUR
123 Mason ist class Day 1.5 270 405.00
124 Mason 2nd class Day 1.5 223 334.50
114 Beldar Day 4 207 828.00
101 Bhishti Day 1 180 180.00
TOTAL 4569.93
Add 1% for water charges 45.70
TOTAL 4615.63
Add for contractor’s profit and overheads 692.34
@15%
Cost of 30 metres 5307.98
Cost of 1 metres 176.93
Say 176.93

19.1 Providing, laying and jointing glazed stoneware pipes grade ‘A’ with stiff mixture of cement mortar
in the of 1:1 (1 cement: 1 fine sand) including testing of joints etc. complete :
19.1.3 200 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for 30 metre
M ATER IALS
1856 200 mm stone ware pipes 60 cm long each 55 80.00 4400.00
2226 Carriage of pipes 100m 33 236.47 78.04
367 Cement for slurry tonne 0.053 5200.00 275.60
2209 Carriage of cem ent tunne 0.053 47.29 2.51
983 Fine sand cum 0.028 300.00 8.40
2261 Carriage of fine sand cum 0.028 53.21 1.49
1881 Spun yarn kg 12 30.00 360.00
LABOUR
123 Mason ist class Day 1.75 270 472.50
124 Mason 2nd class Day 1.75 223 390.25
114 Beldar Day 4.5 207 931.50
101 Bhishti Day 1.25 180 225.00
TOTAL 7145.28
Add 1% for water charges 71.45
TOTAL 7216.73
Add for contractor’s profit and overheads 1082.51
@15%
Cost of 30 metres 8299.24
Cost of 1 metres 276.64
Say 276.64

19.1 Providing, laying and jointing glazed stoneware pipes grade ‘A’ with stiff mixture of cement mortar
in the of 1:1 (1 cement: 1 fine sand) including testing of joints etc. complete :
19.1.4 230 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for 30 metre
M ATER IALS
1857 230 mm stone ware pipes 60 cm long each 55 85.00 4675.00
2227 Carriage of pipes 100m 33 337.82 111.48
367 Cement for slurry tonne 0.065 5200.00 338.00
2209 Carriage of cem ent tunne 0.065 47.29 3.07
983 Fine sand cum 0.036 300.00 10.80
2261 Carriage of fine sand cum 0.036 53.21 1.92
1881 Spun yarn kg 13.5 30.00 405.00
LABOUR
123 Mason ist class Day 2 270 540.00
124 Mason 2nd class Day 2 223 446.00
114 Beldar Day 5 207 1035.00
101 Bhishti Day 1.5 180 270.00
TOTAL 7836.27
Add 1% for water charges 78.36
TOTAL 7914.63
Add for contractor’s profit and overheads 1187.19
@15%
Cost of 30 metres 9101.83
Cost of 1 metres 303.39
Say 303.39

19.1 Providing, laying and jointing glazed stoneware pipes grade ‘A’ with stiff mixture of cement mortar
in the proportion of 1:1 (1 cement: 1 fine sand) including testing of joints etc. complete :
19.1.5 250 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for 30 metre
M ATER IALS
1858 250 mm stone ware pipes 60 cm long each 55 113.00 6215.00
2228 Carriage of pipes 100m 33 405.38 133.78
367 Cement for slurry tonne 0.094 5200.00 488.80
2209 Carriage of cem ent tunne 0.094 47.29 4.45
983 Fine sand cum 0.05 300.00 15.00
2261 Carriage of fine sand cum 0.05 53.21 2.66
1881 Spun yarn kg 15 30.00 450.00
LABOUR
123 Mason ist class Day 2.25 270 607.50
124 Mason 2nd class Day 2.25 223 501.75
114 Beldar Day 5.5 207 1138.50
101 Bhishti Day 1.5 180 270.00
TOTAL 9827.43
Add 1% for water charges 98.27
TOTAL 9925.71
Add for contractor’s profit and overheads 1488.86
@15%
Cost of 30 metres 11414.56
Cost of 1 metres 380.49
Say 380.49
19.1 Providing, laying and jointing glazed stoneware pipes grade ‘A’ with stiff mixture of cement mortar
in the proportion of 1:1 (1 cement: 1 fine sand) including testing of joints etc. complete :
19.1.6 300 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for 30 metre
M ATER IALS
1859 250 mm stone ware pipes 60 cm long each 55 165.00 9075.00
2229 Carriage of pipes 100m 33 506.73 167.22
367 Cement for slurry tonne 0.125 5200.00 650.00
2209 Carriage of cem ent tunne 0.125 47.29 5.91
983 Fine sand cum 0.075 300.00 22.50
2261 Carriage of fine sand cum 0.075 53.21 3.99
1881 Spun yarn kg 18 30.00 540.00
LABOUR
123 Mason ist class Day 2.5 270 675.00
124 Mason 2nd class Day 2.5 223 557.50
114 Beldar Day 6 207 1242.00
101 Bhishti Day 1.5 180 270.00
TOTAL 13209.12
Add 1% for water charges 132.09
TOTAL 13341.21
Add for contractor’s profit and overheads 2001.18
@15%
Cost of 30 metres 15342.40
Cost of 1 metres 511.41
Say 511.41

19.2 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) alround S.W. pipes including bed concrete as per standard design:
19.2.1 100 mm diameter S. W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 1.48 cum
Rate as per item no 4.1.10 of SH : Concrete cum 1.48 2,724.82 4032.73
Work
Cost of 10 metres 4032.73
Cost per metre 403.27
Say 403.27
19.2 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) alround S.W. pipes including bed concrete as per standard design:
19.2.2 150 mm diameter S.W, pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 1.81 cum
Rate as per item no 4.1.10 of SH : Concrete cum 1.81 2,724.82 4931.92
Work
Cost of 10 metres 4931.92
Cost per metre 493.19
Say 493.19

19.2 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) alround S.W. pipes including bed concrete as per standard design:
19.2.3 200 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 2.11 cum
Rate as per item no 4.1.10 of SH : Concrete cum 2.11 2,724.82 5749.36
Work
Cost of 10 metres 5749.36
Cost per metre 574.94
Say 574.94

19.2 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) alround S.W. pipes including bed concrete as per standard design:
19.2.4 230 mm diameter S.W, pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 2.31 cum
Rate as per item no 4.1.10 of SH : Concrete cum 2.31 2,724.82 6294.33
Work
Cost of 10 metres 6294.33
Cost per metre 629.43
Say 629.43

19.2 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) alround S.W. pipes including bed concrete as per standard design:
19.2.5 250 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 2.44 cum
Rate as per item no 4.1.10 of SH : Concrete cum 2.44 2,724.82 6648.55
Work
Cost of 10 metres 6648.55
Cost per metre 664.86
Say 664.86

19.3 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) upto haunches of S.W. pipes including bed concrete as per standard design :
19.3.1 100 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 0.7034 cum
Rate as per item no 4.1.10 of SH : Concrete cum 0.7034 2,724.82 1916.64
Work
Cost of 10 metres 1916.64
Cost per metre 191.66
Say 191.66

19.3 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) upto haunches of S.W. pipes including bed concrete as per standard design :
19.3.2 150 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 1.14 cum
Rate as per item no 4.1.10 of SH : Concrete cum 1.14 2,724.82 3106.29
Work
Cost of 10 metres 3106.29
Cost per metre 310.63
Say 310.63

19.3 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) upto haunches of S.W. pipes including bed concrete as per standard design :
19.3.3 200 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 1.34 cum
Rate as per item no 4.1.10 of SH : Concrete cum 1.34 2,724.82 3651.25
Work
Cost of 10 metres 3651.25
Cost per metre 365.13
Say 365.13

19.3 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) upto haunches of S.W. pipes including bed concrete as per standard design :
19.3.4: 230 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 1.47 cum
Rate as per item no 4.1.10 of SH : Concrete cum 1.47 2,724.82 4005.48
Work
Cost of 10 metres 4005.48
Cost per metre 400.55
Say 400.55

19.3 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) upto haunches of S.W. pipes including bed concrete as per standard design :
19.3.5: 250 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 1.56 cum
Rate as per item no 4.1.10 of SH : Concrete cum 1.56 2,724.82 4250.71
Work
Cost of 10 metres 4250.71
Cost per metre 425.07
Say 425.07

19.3 Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate
40 mm nominal size) upto haunches of S.W. pipes including bed concrete as per standard design :
19.3.6: 300 mm diameter S.W. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
For 10 m length qty. of concrete reqd. = 1.8 cum
Rate as per item no 4.1.10 of SH : Concrete cum 1.8 2,724.82 4904.67
Work
Cost of 10 metres 4904.67
Cost per metre 490.47
Say 490.47

19.4 : Providing and fixing square-mouth S.W. gully trap grade ‘A” complete with C.I. grating brick
masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of
cover to be not less than 4.50 kg and frame to be not mm size (inside) the weight of cover to be not less
than 4.50 kg and frame to be not less than 2.70 kg as per standard design :
19.4.1: 100x100 mm size P type
19.4.1.1: With F.P.S. Bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one gully trap
1900 100x100 mm Gully trap ‘P’ type each 1 55.00 55.00
1364 C.I. grating .100x100 mm each 1 10.00 10.00
1352 C.l. cover with frame 300x300mm inside each 1 265.00 265.00
9999 Carriage of materials L.S. 4.5 1.00 4.50
A Cement concrete 1:5:10 ( 1 cement: 5 fine cum 0.09 2,719.53 244.76
sand : 10 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.11 of
S.H. : Concrete)
A Brick work with 75 class designation brick cum 0.13 2329.20 302.80
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.008 4362.73 34.90
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.29 132.57 38.44
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 955.40
Add 1 % for water charges except on (A) 3.35
TOTAL 958.74
Add 15% for contractor’s profit and 50.68
overheads except on (A)
Cost for 1 trap 1009.42
Say 1009.42

19.4 : Providing and fixing square-mouth S.W. gully trap grade ‘A” complete with C.I. grating brick
masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of
cover to be not less than 4.50 kg and frame to be not mm size (inside) the weight of cover to be not less
than 4.50 kg and frame to be not less than 2.70 kg as per standard design :
19.4.1: 100x100 mm size P type
19.4.1.2:With Sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one gully trap
1900 100x100 mm Gully trap ‘P’ type each 1 55.00 55.00
1364 C.I. grating .100x100 mm each 1 10.00 10.00
1352 C.l. cover with frame 300x300mm inside each 1 265.00 265.00
9999 Carriage of materials L.S. 4.5 1.00 4.50
A Cement concrete 1:5:10 ( 1 cement: 5 fine cum 0.09 2,719.53 244.76
sand : 10 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.11 of
S.H. : Concrete)
A Brick work with sewer bricksconforming to cum 0.13 3217.83 418.32
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.008 4362.73 34.90


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.29 132.57 38.44
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 1070.92
Add 1 % for water charges except on (A) 3.35

TOTAL 1074.27
Add 15% for contractor’s profit and 50.68
overheads except on (A)
Cost for 1 trap 1124.94
Say 1124.94

19.4 : Providing and fixing square-mouth S.W. gully trap grade ‘A” complete with C.I. grating brick
masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of
cover to be not less than 4.50 kg and frame to be not mm size (inside) the weight of cover to be not less
than 4.50 kg and frame to be not less than 2.70 kg as per standard design :
19.4.2: 150 x 100 mm size P type.
19.4.2.1: With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one gully trap
1902 150x100 mm Gully trap ‘P’ type each 1 86.00 86.00
1365 C.I. grating .150x150 mm each 1 19.00 19.00
1352 C.l. cover with frame 300x300mm inside each 1 265.00 265.00
9999 Carriage of materials L.S. 4.5 1.00 4.50
A Cement concrete 1:5:10 ( 1 cement: 5 fine cum 0.08 2,719.53 217.56
sand : 10 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.11 of
S.H. : Concrete)
A Brick work with 75 class designation brick cum 0.13 2329.20 302.80
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.008 4362.73 34.90
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.3 132.57 39.77
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 969.53
Add 1 % for water charges except on (A) 3.75

TOTAL 973.27
Add 15% for contractor’s profit and 56.74
overheads except on (A)
Cost for 1 trap 1030.01
Say 1030.01

19.4 : Providing and fixing square-mouth S.W. gully trap grade ‘A” complete with C.I. grating brick
masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of
cover to be not less than 4.50 kg and frame to be not mm size (inside) the weight of cover to be not less
than 4.50 kg and frame to be not less than 2.70 kg as per standard design :
19.4.2: 150 x 100 mm size P type.
19.4.2.2: With sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one gully trap
1902 150x100 mm Gully trap ‘P’ type each 1 86.00 86.00
1365 C.I. grating .150x150 mm each 1 19.00 19.00
1352 C.l. cover with frame 300x300mm inside each 1 265.00 265.00
9999 Carriage of materials L.S. 4.5 1.00 4.50
A Cement concrete 1:5:10 ( 1 cement: 5 fine cum 0.08 2,719.53 217.56
sand : 10 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.11 of
S.H. : Concrete)
A Brick work with sewer bricksconforming to cum 0.13 3217.83 418.32
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.008 4362.73 34.90


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.3 132.57 39.77
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 1085.05
Add 1 % for water charges except on (A) 3.75

TOTAL 1088.80
Add 15% for contractor’s profit and 56.74
overheads except on (A)
Cost for 1 trap 1145.53
Say 1145.53
19.4 : Providing and fixing square-mouth S.W. gully trap grade ‘A” complete with C.I. grating brick
masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of
cover to be not less than 4.50 kg and frame to be not mm size (inside) the weight of cover to be not less
than 4.50 kg and frame to be not less than 2.70 kg as per standard design :
19.4.3: 180x150 mm size P type
19.4.3.1: With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one gully trap
1904 180x150 mm Gully trap ‘P’ type each 1 160.00 160.00
1367 C.I. grating .180x180 mm each 1 23.00 23.00
1352 C.l. cover with frame 300x300mm inside each 1 265.00 265.00
9999 Carriage of materials L.S. 4.5 1.00 4.50
A Cement concrete 1:5:10 ( 1 cement: 5 fine cum 0.08 2,719.53 217.56
sand : 10 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.11 of
S.H. : Concrete)
A Brick work with 75 class designation brick cum 0.13 2329.20 302.80
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.008 4362.73 34.90
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.16 132.57 21.21
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 1028.97
Add 1 % for water charges except on (A) 4.53

TOTAL 1033.50
Add 15% for contractor’s profit and 68.55
overheads except on (A)
Cost for 1 trap 1102.05
Say 1102.05

19.4 : Providing and fixing square-mouth S.W. gully trap grade ‘A” complete with C.I. grating brick
masonry chamber with water tight C.I. cover with frame of 300 x300 mm size (inside) the weight of
cover to be not less than 4.50 kg and frame to be not mm size (inside) the weight of cover to be not less
than 4.50 kg and frame to be not less than 2.70 kg as per standard design :
19.4.3: 180x150 mm size P type
19.4.3.2: With Sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one gully trap
1904 180x150 mm Gully trap ‘P’ type each 1 160.00 160.00
1367 C.I. grating .180x180 mm each 1 23.00 23.00
1352 C.l. cover with frame 300x300mm inside each 1 265.00 265.00
9999 Carriage of materials L.S. 4.5 1.00 4.50
A Cement concrete 1:5:10 ( 1 cement: 5 fine cum 0.08 2,719.53 217.56
sand : 10 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.11 of
S.H. : Concrete)
A Brick work with sewer bricksconforming to cum 0.13 3217.83 418.32
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.008 4362.73 34.90


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.16 132.57 21.21
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 1144.49
Add 1 % for water charges except on (A) 4.53

TOTAL 1149.02
Add 15% for contractor’s profit and 68.55
overheads except on (A)
Cost for 1 trap 1217.57
Say 1217.57

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.1: 100 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.49 207 101.43
115 Coolie Day 0.36 207 74.52
TOTAL 175.95
Add 1% for water charges 1.76
TOTAL 177.71
Add for contractor’s profit and overheads 26.66
@15%
Cost of 10 m 204.37
Cost of 1 m 20.44
Say 20.44

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.2: 150 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.49 207 101.43
115 Coolie Day 0.45 207 93.15
TOTAL 194.58
Add 1% for water charges 1.95
TOTAL 196.53
Add for contractor’s profit and overheads 29.48
@15%
Cost of 10 m 226.00
Cost of 1 m 22.60
Say 22.60

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.3 200 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.49 207 101.43
115 Coolie Day 0.51 207 105.57
TOTAL 207.00
Add 1% for water charges 2.07
TOTAL 209.07
Add for contractor’s profit and overheads 31.36
@15%
Cost of 10 m 240.43
Cost of 1 m 24.04
Say 24.04

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.4 230 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.49 207 101.43
115 Coolie Day 0.54 207 111.78
TOTAL 213.21
Add 1% for water charges 2.13
TOTAL 215.34
Add for contractor’s profit and overheads 32.30
@15%
Cost of 10 m 247.64
Cost of 1 m 24.76
Say 24.76

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.5 250 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.49 207 101.43
115 Coolie Day 0.57 207 117.99
TOTAL 219.42
Add 1% for water charges 2.19
TOTAL 221.61
Add for contractor’s profit and overheads 33.24
@15%
Cost of 10 m 254.86
Cost of 1 m 25.49
Say 25.49

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.6 300 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.49 207 101.43
115 Coolie Day 0.63 207 130.41
TOTAL 231.84
Add 1% for water charges 2.32
TOTAL 234.16
Add for contractor’s profit and overheads 35.12
@15%
Cost of 10 m 269.28
Cost of 1 m 26.93
Say 26.93

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.7 350 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.6 207 124.20
115 Coolie Day 0.69 207 142.83
TOTAL 267.03
Add 1% for water charges 2.67
TOTAL 269.70
Add for contractor’s profit and overheads 40.46
@15%
Cost of 10 m 310.16
Cost of 1 m 31.02
Say 31.02

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.8 400 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.66 207 136.62
115 Coolie Day 0.75 207 155.25
TOTAL 291.87
Add 1% for water charges 2.92
TOTAL 294.79
Add for contractor’s profit and overheads 44.22
@15%
Cost of 10 m 339.01
Cost of 1 m 33.90
Say 33.90

19.5 : Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful
materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps:
19.5.9 450 mm diameter
Code Description Unit Quantity Rate Amount
Detail of cost for 10.00 metre
Labour:
114 Beldar Day 0.66 207 136.62
115 Coolie Day 0.81 207 167.67
TOTAL 304.29
Add 1% for water charges 3.04
TOTAL 307.33
Add for contractor’s profit and overheads 46.10
@15%
Cost of 10 m 353.43
Cost of 1 m 35.34
Say 35.34

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete :
19.6.1 100 mm dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1700 100 mm dia pipe (in 2 m . length = 5 nos.) metre 10 118.00 1180.00
1714 Collars 5 Nos. each 5 16.00 80.00
2275 carriage of pipes 100 m 10 116.3 11.63
367 Cement for slurry tonne 0.005 5200.00 26.00
2209 Carriage of cem ent tunne 0.005 47.29 0.24
983 Fine sand cum 0.006 300.00 1.80
2261 Carriage of fine sand cum 0.006 53.21 0.32
LABOUR
123 Mason ist class Day 0.32 270 86.40
124 Mason 2nd class Day 0.32 223 71.36
114 Beldar Day 0.63 207 130.41
101 Bhishti Day 0.16 180 28.80
TOTAL 1616.96
Add 1% for water charges 16.17
TOTAL 1633.13
Add for contractor’s profit and overheads 244.97
@15%
Cost of 10 metres 1878.09
Cost of 1 metres 187.81
Say 187.81

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.2 :
150m mdia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1701 150 mm dia pipe (in 2 m . length = 5 nos.) metre 10 135.00 1350.00
1715 Collars 5 Nos. each 5 21.00 105.00
2281 carriage of pipes 100 m 10 193.83 19.38
367 Cement for slurry tonne 0.006 5200.00 31.20
2209 Carriage of cem ent tunne 0.006 47.29 0.28
983 Fine sand cum 0.008 300.00 2.40
2261 Carriage of fine sand cum 0.008 53.21 0.43
LABOUR
123 Mason ist class Day 0.39 270 105.30
124 Mason 2nd class Day 0.39 223 86.97
114 Beldar Day 0.78 207 161.46
101 Bhishti Day 0.16 180 28.80
TOTAL 1891.22
Add 1% for water charges 18.91
TOTAL 1910.13
Add for contractor’s profit and overheads 286.52
@15%
Cost of 10 metres 2196.65
Cost of 1 metres 219.67
Say 219.67

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.3 250 mm: dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1702 250 mm dia pipe (in 2.5 m . length =4 nos.) metre 10 157.00 1570.00
1716 Collars 5 Nos. each 5 34.00 170.00
2290 carriage of pipes 100 m 10 448.05 44.81
367 Cement for slurry tonne 0.009 5200.00 46.80
2209 Carriage of cem ent tunne 0.009 47.29 0.43
983 Fine sand cum 0.012 300.00 3.60
2261 Carriage of fine sand cum 0.012 53.21 0.64
LABOUR
123 Mason ist class Day 0.54 270 145.80
124 Mason 2nd class Day 0.54 223 120.42
114 Beldar Day 1.5 207 310.50
101 Bhishti Day 0.23 180 41.40
TOTAL 2454.39
Add 1% for water charges 24.54
TOTAL 2478.93
Add for contractor’s profit and overheads 371.84
@15%
Cost of 10 metres 2850.77
Cost of 1 metres 285.08
Say 285.08

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.4 300 mm: dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1703 300 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 228.00 2280.00
1717 Collars 4 Nos. each 4 42.00 168.00
2290 carriage of pipes 100 m 10 553.8 55.38
367 Cement for slurry tonne 0.011 5200.00 57.20
2209 Carriage of cem ent tunne 0.011 47.29 0.52
983 Fine sand cum 0.015 300.00 4.50
2261 Carriage of fine sand cum 0.015 53.21 0.80
LABOUR
123 Mason ist class Day 0.59 270 159.30
124 Mason 2nd class Day 0.59 223 131.57
114 Beldar Day 1.16 207 240.12
101 Bhishti Day 0.2 180 36.00
TOTAL 3133.39
Add 1% for water charges 31.33
TOTAL 3164.72
Add for contractor’s profit and overheads 474.71
@15%
Cost of 10 metres 3639.43
Cost of 1 metres 363.94
Say 363.94

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.5 450 mm: dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1704 450 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 333.00 3330.00
1718 Collars 4 Nos. each 4 63.00 252.00
2299 carriage of pipes 100 m 10 1,292.20 129.22
367 Cement for slurry tonne 0.024 5200.00 124.80
2209 Carriage of cem ent tunne 0.024 47.29 1.13
983 Fine sand cum 0.033 300.00 9.90
2261 Carriage of fine sand cum 0.033 53.21 1.76
LABOUR
123 Mason ist class Day 0.75 270 202.50
124 Mason 2nd class Day 0.75 223 167.25
114 Beldar Day 1.5 207 310.50
101 Bhishti Day 0.33 180 59.40
TOTAL 4588.46
Add 1% for water charges 45.88
TOTAL 4634.35
Add for contractor’s profit and overheads 695.15
@15%
Cost of 10 metres 5329.50
Cost of 1 metres 532.95
Say 532.95

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc.
9.6.6complete
500 mm:dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1705 500 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 398.00 3980.00
1719 Collars 4 Nos. each 4 73.00 292.00
2299 carriage of pipes 100 m 10 1,292.20 129.22
367 Cement for slurry tonne 0.026 5200.00 135.20
2209 Carriage of cem ent tunne 0.026 47.29 1.23
983 Fine sand cum 0.036 300.00 10.80
2261 Carriage of fine sand cum 0.036 53.21 1.92
LABOUR
123 Mason ist class Day 0.81 270 218.70
124 Mason 2nd class Day 0.81 223 180.63
114 Beldar Day 1.62 207 335.34
101 Bhishti Day 0.33 180 59.40
TOTAL 5344.44
Add 1% for water charges 53.44
TOTAL 5397.88
Add for contractor’s profit and overheads 809.68
@15%
Cost of 10 metres 6207.56
Cost of 1 metres 620.76
Say 620.76

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.7 600 mm: dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1706 600 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 642.00 6420.00
1720 Collars 4 Nos. each 4 92.00 368.00
2303 carriage of pipes 100 m 10 1,938.30 193.83
367 Cement for slurry tonne 0.032 5200.00 166.40
2209 Carriage of cem ent tunne 0.032 47.29 1.51
983 Fine sand cum 0.043 300.00 12.90
2261 Carriage of fine sand cum 0.043 53.21 2.29
LABOUR
123 Mason ist class Day 0.92 270 248.40
124 Mason 2nd class Day 0.92 223 205.16
114 Beldar Day 1.83 207 378.81
101 Bhishti Day 0.33 180 59.40
TOTAL 8056.70
Add 1% for water charges 80.57
TOTAL 8137.27
Add for contractor’s profit and overheads 1220.59
@15%
Cost of 10 metres 9357.86
Cost of 1 metres 935.79
Say 935.79

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.8 700 mm: dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1707 700 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 719.00 7190.00
1721 Collars 4 Nos. each 4 102.00 408.00
2303 carriage of pipes 100 m 10 1,938.30 193.83
367 Cement for slurry tonne 0.037 5200.00 192.40
2209 Carriage of cem ent tunne 0.037 47.29 1.75
983 Fine sand cum 0.05 300.00 15.00
2261 Carriage of fine sand cum 0.05 53.21 2.66
LABOUR
123 Mason ist class Day 1.03 270 278.10
124 Mason 2nd class Day 1.03 223 229.69
114 Beldar Day 2.06 207 426.42
101 Bhishti Day 0.42 180 75.60
TOTAL 9013.45
Add 1% for water charges 90.13
TOTAL 9103.58
Add for contractor’s profit and overheads 1365.54
@15%
Cost of 10 metres 10469.12
Cost of 1 metres 1046.91
Say 1046.91

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.9 800 mm: dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1708 800 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 836.00 8360.00
1722 Collars 4 Nos. each 4 146.00 584.00
2303 carriage of pipes 100 m 10 1,938.30 193.83
367 Cement for slurry tonne 0.042 5200.00 218.40
2209 Carriage of cem ent tunne 0.042 47.29 1.99
983 Fine sand cum 0.057 300.00 17.10
2261 Carriage of fine sand cum 0.057 53.21 3.03
LABOUR
123 Mason ist class Day 1.14 270 307.80
124 Mason 2nd class Day 1.14 223 254.22
114 Beldar Day 2.28 207 471.96
101 Bhishti Day 0.42 180 75.60
TOTAL 10487.93
Add 1% for water charges 104.88
TOTAL 10592.81
Add for contractor’s profit and overheads 1588.92
@15%
Cost of 10 metres 12181.73
Cost of 1 metres 1218.17
Say 1218.17

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete :
19.6.10 900 mm dia. R.C.C. pipe
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1709 900 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 986.00 9860.00
1723 Collars 4 Nos. each 4 178.00 712.00
2331 carriage of pipes 100 m 10 2,907.45 290.75
367 Cement for slurry tonne 0.049 5200.00 254.80
2209 Carriage of cem ent tunne 0.049 47.29 2.32
983 Fine sand cum 0.066 300.00 19.80
2261 Carriage of fine sand cum 0.066 53.21 3.51
LABOUR
123 Mason ist class Day 1.25 270 337.50
124 Mason 2nd class Day 1.25 223 278.75
114 Beldar Day 3 207 621.00
101 Bhishti Day 0.5 180 90.00
TOTAL 12470.42
Add 1% for water charges 124.70
TOTAL 12595.13
Add for contractor’s profit and overheads 1889.27
@15%
Cost of 10 metres 14484.40
Cost of 1 metres 1448.44
Say 1448.44

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.11 : dia. R.C.C. pipe
1000 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1710 1000 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 1243.00 12430.00
1724 Collars 4 Nos. each 4 210.00 840.00
2332 carriage of pipes 100 m 10 3,876.61 387.66
367 Cement for slurry tonne 0.055 5200.00 286.00
2209 Carriage of cem ent tunne 0.055 47.29 2.60
983 Fine sand cum 0.074 300.00 22.20
2261 Carriage of fine sand cum 0.074 53.21 3.94
LABOUR
123 Mason ist class Day 1.36 270 367.20
124 Mason 2nd class Day 1.36 223 303.28
114 Beldar Day 4.33 207 896.31
101 Bhishti Day 0.5 180 90.00
TOTAL 15629.19
Add 1% for water charges 156.29
TOTAL 15785.48
Add for contractor’s profit and overheads 2367.82
@15%
Cost of 10 metres 18153.30
Cost of 1 metres 1815.33
Say 1815.33

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.12 : dia. R.C.C. pipe
1100 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1711 1100 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 1500.00 15000.00
1725 Collars 4 Nos. each 4 241.00 964.00
2333 carriage of pipes 100 m 10 3,876.61 387.66
367 Cement for slurry tonne 0.061 5200.00 317.20
2209 Carriage of cem ent tunne 0.061 47.29 2.88
983 Fine sand cum 0.082 300.00 24.60
2261 Carriage of fine sand cum 0.082 53.21 4.36
LABOUR
123 Mason ist class Day 1.47 270 396.90
124 Mason 2nd class Day 1.47 223 327.81
114 Beldar Day 6.3 207 1304.10
101 Bhishti Day 0.6 180 108.00
TOTAL 18837.52
Add 1% for water charges 188.38
TOTAL 19025.89
Add for contractor’s profit and overheads 2853.88
@15%
Cost of 10 metres 21879.78
Cost of 1 metres 2187.98
Say 2187.98

19.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with
stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints
etc. complete
19.6.13 : dia. R.C.C. pipe
1200 mm
Code Description Unit Quantity Rate Amount
Details of cost for 10 metre
MATERIALS
1712 1200 mm dia pipe (in 2.5 m . length = 4 nos.) metre 10 1543.00 15430.00
1726 Collars 4 Nos. each 4 280.00 1120.00
2334 carriage of pipes 100 m 10 3,876.61 387.66
367 Cement for slurry tonne 0.068 5200.00 353.60
2209 Carriage of cem ent tunne 0.068 47.29 3.22
983 Fine sand cum 0.092 300.00 27.60
2261 Carriage of fine sand cum 0.092 53.21 4.90
LABOUR
123 Mason ist class Day 1.59 270 429.30
124 Mason 2nd class Day 1.59 223 354.57
114 Beldar Day 8.67 207 1794.69
101 Bhishti Day 0.67 180 120.60
TOTAL 20026.13
Add 1% for water charges 200.26
TOTAL 20226.39
Add for contractor’s profit and overheads 3033.96
@15%
Cost of 10 metres 23260.35
Cost of 1 metres 2326.04
Say 2326.04

19.7 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) R.C.C. top
slab with 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size),
foundation concrete 1:4:8 mix (1 cement: 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
inside plastering 12mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with floating
coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20mm nominal size) finished with a floating coat of neat cement complete as per
standard design :
19.7.1 Inside size 90x80 cm and .45 cm deep including C.I. cover with frame (light duty) 455x610 mm
internal dimensions total weight of cover and frame to be not less than 38 kg (weight of cover 23 kg and
weight of frame 15 kg):
19.7.1.1 With F.P.S. bricks with class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:4:8 ( 1 cement: 4 coarse cum 0.43 2,836.20 1219.57
sand : 8 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.8 of S.H.
: Concrete)

Brick work with 75 class designation brick cum 0.34 2329.20 791.93
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.16 5140.53 822.49


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 0.25 132.57 33.14


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Reinforced Cement concrete 1:2:4 ( 1 cum 0.22 4269.75 939.35


cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) (Rate as per
item 5.3 of S.H. : concrete)

(viii) Mild steel reinforcement for RCC work kg 10.57 58.65 619.98
(Rate as per item No.5.22.1
Form work (Rate as per item No.5.9.3) sqm 0.44 506.86 223.02
123 Mason 1st class Day 0.06 270 16.20
124 Mason 2nd class Day 0.06 223 13.38
1354 C.I. Cover with frame 455x610 mm (inside) each 1 1395.00 1395.00 (A)

9999 Carriage of C.I. surface box L.S. 6.76 1.00 6.76 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 6.76 1.00 6.76 (A)
9999 Sundries L.S. 13.52 1.00 13.52 (A)
TOTAL 6101.08
Add for water charges @ 1 % on ‘A 14.52 (B)
TOTAL 6115.60
Add 15% for contractor’s profit and overheads 219.92
on (A+B)
Cost of one manhole 6335.52
Say 6335.52
19.7 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) R.C.C. top
slab with 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size),
foundation concrete 1:4:8 mix (1 cement: 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
inside plastering 12mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with floating
coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20mm nominal size) finished with a floating coat of neat cement complete as per
19.7.1 Inside
standard size
design : 90x80 cm and .45 cm deep including C.I. cover with frame (light duty) 455x610 mm
internal dimensions total weight of cover and frame to be not less than 38 kg (weight of cover 23 kg and
weight
19.7.1.2ofWith
frame 15 kg):
Sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:4:8 ( 1 cement: 4 coarse cum 0.43 2,836.20 1219.57
sand : 8 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.8 of S.H.
: Concrete)

Brick work with sewer bricksconforming to cum 0.34 3217.83 1094.06


IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.16 5140.53 822.49


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 0.25 132.57 33.14


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Reinforced Cement concrete 1:2:4 ( 1 cum 0.22 4269.75 939.35


cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) (Rate as per
item 5.3 of S.H. : concrete)

(viii) Mild steel reinforcement for RCC work kg 10.57 58.65 619.98
(Rate as per item No.5.22.1
Form work (Rate as per item No.5.9.3) sqm 0.44 506.86 223.02
123 Mason 1st class Day 0.06 270 16.20
124 Mason 2nd class Day 0.06 223 13.38
1354 C.I. Cover with frame 455x610 mm (inside) each 1 1395.00 1395.00 (A)

9999 Carriage of C.I. surface box L.S. 6.76 1.00 6.76 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 6.76 1.00 6.76 (A)
9999 Sundries L.S. 13.52 1.00 13.52 (A)
TOTAL 6403.21
Add for water charges @ 1 % on ‘A 14.52 (B)
TOTAL 6417.73
Add 15% for contractor’s profit and overheads 219.92
on (A+B)
Cost of one manhole 6637.65
Say 6637.65

19.7 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) R.C.C. top
slab with 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size),
foundation concrete 1:4:8 mix (1 cement: 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
inside plastering 12mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with floating
coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20mm nominal size) finished with a floating coat of neat cement complete as per
standard
19.7.2 design
Inside : 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm
size
internal diameter, total weight of cover and frame to be not less than 116 kg (weight of cover 58 kg and
weight
19.7.2.1ofWith
frame 58 kg):
F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:4:8 ( 1 cement: 4 coarse cum 0.55 2,836.20 1559.91
sand : 8 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.8 of S.H.
: Concrete)

Brick work with 75 class designation brick cum 0.93 2329.20 2166.15
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.25 5140.53 1285.13


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.19 132.57 290.32


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Reinforced Cement concrete 1:2:4 ( 1 cum 0.31 4269.75 1323.62


cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) (Rate as per
item 5.3 of S.H. : concrete)

(viii) Mild steel reinforcement for RCC work kg 24.83 58.65 1456.39
(Rate as per item No.5.22.1
Form work (Rate as per item No.5.9.3) sqm 0.88 506.86 446.04
123 Mason 1st class Day 0.08 270 21.60
124 Mason 2nd class Day 0.08 223 17.84
1356 500 mm dia cover with frame (medium duty) each 1 4257.00 4257.00 (A)

9999 Carriage of C.I. surface box L.S. 6.76 1.00 6.76 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 6.76 1.00 6.76 (A)
9999 Sundries L.S. 16.64 1.00 16.64 (A)
TOTAL 12854.16
Add for water charges @ 1 % on ‘A 43.27 (B)
TOTAL 12897.43
Add 15% for contractor’s profit and overheads 655.48
on (A+B)
Cost of one manhole 13552.91
Say 13552.91

19.7 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) R.C.C. top
slab with 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size),
foundation concrete 1:4:8 mix (1 cement: 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
inside plastering 12mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with floating
coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20mm nominal size) finished with a floating coat of neat cement complete as per
19.7.2 Inside
standard size
design : 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm
internal diameter, total weight of cover and frame to be not less than 116 kg (weight of cover 58 kg and
weight
19.7.2.2ofWith
frame 58 kg):
Sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:4:8 ( 1 cement: 4 coarse cum 0.55 2,836.20 1559.91
sand : 8 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.8 of S.H.
: Concrete)

Brick work with sewer bricksconforming to cum 0.93 3217.83 2992.58


IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.25 5140.53 1285.13


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.19 132.57 290.32


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Reinforced Cement concrete 1:2:4 ( 1 cum 0.31 4269.75 1323.62


cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) (Rate as per
item 5.3 of S.H. : concrete)

(viii) Mild steel reinforcement for RCC work kg 24.83 58.65 1456.39
(Rate as per item No.5.22.1
Form work (Rate as per item No.5.9.3) sqm 0.88 506.86 446.04
123 Mason 1st class Day 0.08 270 21.60
124 Mason 2nd class Day 0.08 223 17.84
1356 500 mm dia cover with frame (medium duty) each 1 4257.00 4257.00 (A)

9999 Carriage of C.I. surface box L.S. 6.76 1.00 6.76 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 6.76 1.00 6.76 (A)
9999 Sundries L.S. 16.64 1.00 16.64 (A)
TOTAL 13680.59
Add for water charges @ 1 % on ‘A 43.27 (B)
TOTAL 13723.86
Add 15% for contractor’s profit and overheads 655.48
on (A+B)
Cost of one manhole 14379.33
Say 14379.33

19.7 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) R.C.C. top
slab with 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size),
foundation concrete 1:4:8 mix (1 cement: 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
inside plastering 12mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with floating
coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20mm nominal size) finished with a floating coat of neat cement complete as per
19.7.3 Inside
standard size
design : 120x90 cm and 90 cm deep including C.I. cover with frame (heavy duty) 560 mm
internal diameter, total weight of cover and frame to be not less than 208 kg (weight of cover 108 kg and
weight of frame 100 kg)
19.7.3.1 With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:4:8 ( 1 cement: 4 coarse cum 0.55 2,836.20 1559.91
sand : 8 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.8 of S.H.
: Concrete)

Brick work with 75 class designation brick cum 0.8 2329.20 1863.36
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.25 5140.53 1285.13


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.41 132.57 319.48


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Reinforced Cement concrete 1:2:4 ( 1 cum 0.33 4269.75 1409.02


cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) (Rate as per
item 5.3 of S.H. : concrete)
(viii) Mild steel reinforcement for RCC work kg 26.43 58.65 1550.23
(Rate as per item No.5.22.1
Form work (Rate as per item No.5.9.3) sqm 0.83 506.86 420.70
123 Mason 1st class Day 0.08 270 21.60
124 Mason 2nd class Day 0.08 223 17.84
3860 560 mm dia cover with frame (Heavy duty) each 1 7634.00 7634.00 (A)

9999 Carriage of C.I. surface box L.S. 13.52 1.00 13.52 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 6.76 1.00 6.76 (A)
9999 Sundries L.S. 20.28 1.00 20.28 (A)
TOTAL 16121.83
Add for water charges @ 1 % on ‘A 77.14 (B)
TOTAL 16198.97
Add 15% for contractor’s profit and overheads 1168.67
on (A+B)
Cost of one manhole 17367.64
Say 17367.64

19.7 Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) R.C.C. top
slab with 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size),
foundation concrete 1:4:8 mix (1 cement: 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
inside plastering 12mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with floating
coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20mm nominal size) finished with a floating coat of neat cement complete as per
standard
19.7.3 design
Inside : 120x90 cm and 90 cm deep including C.I. cover with frame (heavy duty) 560 mm
size
internal diameter, total weight of cover and frame to be not less than 208 kg (weight of cover 108 kg and
weight
19.7.3.2ofWith
frame 100 kg)
Sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:4:8 ( 1 cement: 4 coarse cum 0.55 2,836.20 1559.91
sand : 8 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.8 of S.H.
: Concrete)

Brick work with sewer bricksconforming to cum 0.8 3217.83 2574.26


IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.25 5140.53 1285.13


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.41 132.57 319.48


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)
Reinforced Cement concrete 1:2:4 ( 1 cum 0.33 4269.75 1409.02
cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) (Rate as per
item 5.3 of S.H. : concrete)

(viii) Mild steel reinforcement for RCC work kg 26.43 58.65 1550.23
(Rate as per item No.5.22.1
Form work (Rate as per item No.5.9.3) sqm 0.83 506.86 420.70
123 Mason 1st class Day 0.08 270 21.60
124 Mason 2nd class Day 0.08 223 17.84
3860 560 mm dia cover with frame (Heavy duty) each 1 7634.00 7634.00 (A)

9999 Carriage of C.I. surface box L.S. 13.52 1.00 13.52 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 6.76 1.00 6.76 (A)
9999 Sundries L.S. 20.28 1.00 20.28 (A)
TOTAL 16832.74
Add for water charges @ 1 % on ‘A 77.14 (B)
TOTAL 16909.88
Add 15% for contractor’s profit and overheads 1168.67
on (A+B)
Cost of one manhole 18078.55
Say 18078.55

19.8 Extra for depth for manholes


19.8.1 Size 90x80 cm
19.8.1.1 With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Brick work with 75 class designation brick cum 0.99 2329.20 2305.90
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 3.4 132.57 450.72


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 2756.63
Cost of one metre 2756.63
Say 2756.63

19.8 Extra for depth for manholes


19.8.1 Size 90x80 cm
19.8.1.2 With Sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Brick work with sewer bricksconforming to cum 0.99 3217.83 3185.65
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 3.4 132.57 450.72


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 3636.37
Cost of one metre 3636.37
Say 3636.37

19.8 Extra for depth for manholes


19.8.2 Size 120x90 cm
19.8.2.1 With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Brick work with 75 class designation brick cum 1.18 2329.20 2748.45
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 4.2 132.57 556.78


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 3305.23
Cost of one metre 3305.23
Say 3305.23

19.8 Extra for depth for manholes


19.8.2 Size 120x90 cm
19.8.2.2 With Sewer bricks conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Brick work with sewer bricksconforming to cum 1.18 3217.83 3797.03
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 4.2 132.57 556.78


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 4353.81
Cost of one metre 4353.81
Say 4353.81

19.9 Constructing brick masonry circular type manhole 0.91m internal dia at bottom and 0.56m dia at/in
cement mortar 1:4 (1 cement :4 coarse sand), in side cement plaster 12 mm thick with cement mortar 1:3
(1 cement: 3 coarse sand) finished with a floating coat of neat cement, foundation concrete 1:3:6 mix (1
cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size), and making necessary channel in
cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
finished with a floating coat of neat cement all complete as per standard design :
19.9.1 0.91 m deep with S.F.R.C. cover and frame (heavy duty, HD-20 grade designation) 560mm
internal diameter conforming to I.S. 12592, total-weight of cover and frame to be not less than 182kg.,
fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
including centering shuttering all complete. (Excavation, foot rests and 12mm thick cement plaster at the
external
19.9.1.1 surface shallbricks
With F.P.S. be paid fordesignation
class separately):75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:3:6 ( 1 cement: 6 coarse cum 0.63 3,273.34 2062.21
sand : 6 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.6 of S.H.
: Concrete)

Brick work with 75 class designation brick cum 0.53 2329.20 1234.47
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Brick work with 75 class designation brick cum 0.02 4349.76 87.00
in cement mortar 1:3 (1 cement: 3 coarse
sand) Rate as per item no 6.9 of SH : Brick
Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.12 5140.53 616.86


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.09 4362.73 392.65


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 1.75 132.57 231.99


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.06 270 16.20


124 Mason 2nd class Day 0.06 223 13.38
7135 Circular shape 560 mm dia precast R.C.C. each 1 838.00 838.00 (A)
manhole cover with frame -H.D.-20

9999 Painting of C.I. cover & frame with coal tar L.S. 6.89 1.00 6.89 (A)
9999 Sundries L.S. 16.9 1.00 16.90 (A)
TOTAL 5516.54
Add for water charges @ 1 % on ‘A 8.91 (B)
TOTAL 5525.46
Add 15% for contractor’s profit and overheads 135.04
on (A+B)
Cost of one manhole 5660.50
Say 5660.50

19.9 Constructing brick masonry circular type manhole 0.91m internal dia at bottom and 0.56m dia at/in
cement mortar 1:4 (1 cement :4 coarse sand), in side cement plaster 12 mm thick with cement mortar 1:3
(1 cement: 3 coarse sand) finished with a floating coat of neat cement, foundation concrete 1:3:6 mix (1
cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size), and making necessary channel in
cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
finished with a floating coat of neat cement all complete as per standard design :
19.9.1 0.91 m deep with S.F.R.C. cover and frame (heavy duty, HD-20 grade designation) 560mm
internal diameter conforming to I.S. 12592, total-weight of cover and frame to be not less than 182kg.,
fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
including centering shuttering all complete. (Excavation, foot rests and 12mm thick cement plaster at the
external
19.9.1.2 surface shallbricks
With Sewer be paid for separately):
conforming to IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:3:6 ( 1 cement: 6 coarse cum 0.63 3,273.34 2062.21
sand : 6 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.6 of S.H.
: Concrete)

Brick work with sewer bricksconforming to cum 0.53 3217.83 1705.45


IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

Brick work moduler extruded burnt fire clay cum 0.02 5252.25 105.05
sewer bricks in arches in cement mortar
1:3 (1 cement: 3 coarse sand) Rate as per
item no 6.37 of SH : Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.12 5140.53 616.86


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.09 4362.73 392.65


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)
12mm cement plaster 1:3 (1 Cement: 3 sqm 1.75 132.57 231.99
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.06 270 16.20


124 Mason 2nd class Day 0.06 223 13.38
7135 Circular shape 560 mm dia precast R.C.C. each 1 838.00 838.00 (A)
manhole cover with frame -H.D.-20

9999 Painting of C.I. cover & frame with coal tar L.S. 6.89 1.00 6.89 (A)
9999 Sundries L.S. 16.9 1.00 16.90 (A)
TOTAL 6005.57
Add for water charges @ 1 % on ‘A 8.91 (B)
TOTAL 6014.48
Add 15% for contractor’s profit and overheads 135.04
on (A+B)
Cost of one manhole 6149.52
Say 6149.52

19.10 Extra depth for circular type manhole 0.91m internal dia (at bottom) beyond 0.91m to 1.67m
19.10.1 With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of Cost for 0.76m depth.
Brick work with 75 class designation brick cum 0.63 2329.20 1467.39
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.01 5140.53 51.41


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.33 132.57 308.88


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 1827.68
Cost of 0.76 m 1827.68
Cost per metre 2404.84
Say 2404.84

19.10 Extra depth for circular type manhole 0.91m internal dia (at bottom) beyond 0.91m to 1.67m
19.10.2 With Sewer bricks conforming IS : 4885
Code Description Unit Quantity Rate Amount
Details of Cost for 0.76m depth.
Brick work with sewer bricksconforming to cum 0.63 3217.83 2027.23
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.01 5140.53 51.41


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.33 132.57 308.88


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 2387.51
Cost of 0.76 m 2387.51
Cost per metre 3141.46
Say 3141.46

19.11 Constructing brick masonry circular manhole 1.22m internal dia at bottom and 0.56m dia at top in
cement mortar 1:4 (1 cement :4 coarse sand) inside cement plaster 12mm thick with cement mortar 1:3
(1 cement :3 coarse sand) finished with a floating coat of neat cement^foundation concrete 1:3:6 (1
cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size) and making necessary
channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone complete as per standard
design :
19.11.1 1.68 m deep with SFRC Cover and frame (heavy duty HD-20 grade designation) 560mm internal
diameter conforming to I.S. 12592, total weight of cover and frame to be not less than 182kg. fixed in
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
including centering shuttering all complete. (Excavation, foot rests and 12 mm thick cement plaster at the
external surface shall be paid for separately):
19.11.1.1 With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:3:6 ( 1 cement: 6 coarse cum 1.18 3,273.34 3862.54
sand : 6 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.6 of S.H.
: Concrete)

Brick work with 75 class designation brick cum 1.29 2329.20 3004.66
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Brick work with 75 class designation brick cum 0.02 4349.76 87.00
in cement mortar 1:3 (1 cement: 3 coarse
sand) Rate as per item no 6.9 of SH : Brick
Work
Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.26 5140.53 1336.54
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.09 4362.73 392.65


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 4.48 132.57 593.89


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.1 270 27.00


124 Mason 2nd class Day 0.1 223 22.30
7135 Circular shape 560 mm dia precast R.C.C. each 1 838.00 838.00 (A)
manhole cover with frame -H.D.-20

9999 Painting of C.I. cover & frame with coal tar L.S. 6.89 1.00 6.89 (A)
9999 Sundries L.S. 16.9 1.00 16.90 (A)
TOTAL 10188.37
Add for water charges @ 1 % on ‘A 9.11 (B)
TOTAL 10197.48
Add 15% for contractor’s profit and overheads 138.03
on (A+B)
Cost of one manhole 10335.51
Say 10335.51

19.11 Constructing brick masonry circular manhole 1.22m internal dia at bottom and 0.56m dia at top in
cement mortar 1:4 (1 cement :4 coarse sand) inside cement plaster 12mm thick with cement mortar 1:3
(1 cement :3 coarse sand) finished with a floating coat of neat cement^foundation concrete 1:3:6 (1
cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size) and making necessary
channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone complete as per standard
design :
19.11.1 1.68 m deep with SFRC Cover and frame (heavy duty HD-20 grade designation) 560mm internal
diameter conforming to I.S. 12592, total weight of cover and frame to be not less than 182kg. fixed in
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
including centering shuttering all complete. (Excavation, foot rests and 12 mm thick cement plaster at the
external surface shall be paid for separately):
19.11.1.2 With Sewer bricks conforming IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:3:6 ( 1 cement: 6 coarse cum 1.18 3,273.34 3862.54
sand : 6 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.6 of S.H.
: Concrete)
Brick work with sewer bricksconforming to cum 1.29 3217.83 4151.00
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

Brick work moduler extruded burnt fire clay cum 0.02 5252.25 105.05
sewer bricks in arches in cement mortar
1:3 (1 cement: 3 coarse sand) Rate as per
item no 6.37 of SH : Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.26 5140.53 1336.54


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.09 4362.73 392.65


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 4.48 132.57 593.89


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.1 270 27.00


124 Mason 2nd class Day 0.1 223 22.30
7135 Circular shape 560 mm dia precast R.C.C. each 1 838.00 838.00 (A)
manhole cover with frame -H.D.-20

9999 Painting of C.I. cover & frame with coal tar L.S. 6.89 1.00 6.89 (A)
9999 Sundries L.S. 16.9 1.00 16.90 (A)
TOTAL 11352.75
Add for water charges @ 1 % on ‘A 9.11 (B)
TOTAL 11361.86
Add 15% for contractor’s profit and overheads 138.03
on (A+B)
Cost of one manhole 11499.89
Say 11499.89

19.12 Extra depth for circular type manhole 1.22m internal dia (at bottom) beyond 1.68 m to 2.29 m :
19.12.1 With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of Cost for 0.61m depth.
Brick work with 75 class designation brick cum 0.66 2329.20 1537.27
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
12mm cement plaster 1:3 (1 Cement: 3 sqm 2.56 132.57 339.37
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 1876.64
Cost of 0.61 m 1876.64
Cost per metre 3076.45
Say 3076.45

19.12 Extra depth for circular type manhole 1.22m internal dia (at bottom) beyond 1.68 m to 2.29 m :
19.12.2 With Sewer bricks conforming IS : 4885
Code Description Unit Quantity Rate Amount
Details of Cost for 0.61m depth.
Brick work with sewer bricksconforming to cum 0.66 3217.83 2123.76
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.56 132.57 339.37


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 2463.13
Cost of 0.61 m 2463.13
Cost per metre 4037.92
Say 4037.92

19.13 Constructing brick masonry circular manhole 1.52 m internal dia at bottom and 0.56 m dia at
top in cement mortar 1:4 (1 cement : 4 coarse sand) inside cement plaster 12mm thick with cement
mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of neat cement, foundation concrete
1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size) and making necessary
channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal
size) finished with a floating coat of neat cement all complete as per standard design :
19.13.1 2.30m deep with SFRC Cover and frame (heavy duty HD-20 grade designation) 560mm internal
diameter conforming to I.S. 12592, total weight of cover and frame to be not less than 182 kg. fixed in
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
including centering shuttering all complete. (Excavation, foot rests and 12 mm thick cement plaster at
the external surface shall be paid for separately):
19.13.1.1 With F.P.S. bricks class designation 75
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:3:6 ( 1 cement: 6 coarse cum 2.25 3,273.34 7365.02
sand : 6 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.6 of S.H.
: Concrete)
Brick work with 75 class designation brick cum 3.68 2329.20 8571.44
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Brick work with 75 class designation brick cum 0.04 4349.76 173.99
in cement mortar 1:3 (1 cement: 3 coarse
sand) Rate as per item no 6.9 of SH : Brick
Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.42 5140.53 2159.02


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.09 4362.73 392.65


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 7.61 132.57 1008.82


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.1 270 27.00


124 Mason 2nd class Day 0.1 223 22.30
7135 Circular shape 560 mm dia precast R.C.C. each 1 838.00 838.00 (A)
manhole cover with frame -H.D.-20

9999 Painting of C.I. cover & frame with coal tar L.S. 6.89 1.00 6.89 (A)
9999 Sundries L.S. 16.9 1.00 16.90 (A)
TOTAL 20582.03
Add for water charges @ 1 % on ‘A 9.11 (B)
TOTAL 20591.14
Add 15% for contractor’s profit and overheads 138.03
on (A+B)
Cost of one manhole 20729.17
Say 20729.17

19.13 Constructing brick masonry circular manhole 1.52 m internal dia at bottom and 0.56 m dia at
top in cement mortar 1:4 (1 cement : 4 coarse sand) inside cement plaster 12mm thick with cement
mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of neat cement, foundation concrete
1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size) and making necessary
channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal
size) finished with a floating coat of neat cement all complete as per standard design :
19.13.1 2.30m deep with SFRC Cover and frame (heavy duty HD-20 grade designation) 560mm internal
diameter conforming to I.S. 12592, total weight of cover and frame to be not less than 182 kg. fixed in
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
including centering shuttering all complete. (Excavation, foot rests and 12 mm thick cement plaster at
the external surface shall be paid for separately):
19.13.1.2 With Sewer bricks conforming IS : 4885
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cement concrete 1:3:6 ( 1 cement: 6 coarse cum 2.25 3,273.34 7365.02
sand : 6 graded stone aggregate 40 mm
nominal size) (Rate as per item 4.1.6 of S.H.
: Concrete)

Brick work with sewer bricksconforming to cum 3.68 3217.83 11841.60


IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

Brick work moduler extruded burnt fire clay cum 0.04 5252.25 210.09
sewer bricks in arches in cement mortar
1:3 (1 cement: 3 coarse sand) Rate as per
item no 6.37 of SH : Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.42 5140.53 2159.02


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.09 4362.73 392.65


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 7.61 132.57 1008.82


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.1 270 27.00


124 Mason 2nd class Day 0.1 223 22.30
7135 Circular shape 560 mm dia precast R.C.C. each 1 838.00 838.00 (A)
manhole cover with frame -H.D.-20

9999 Painting of C.I. cover & frame with coal tar L.S. 6.89 1.00 6.89 (A)
9999 Sundries L.S. 16.9 1.00 16.90 (A)
TOTAL 23888.29
Add for water charges @ 1 % on ‘A 9.11 (B)
TOTAL 23897.40
Add 15% for contractor’s profit and overheads 138.03
on (A+B)
Cost of one manhole 24035.43
Say 24035.43

19.14 Extra depth for circular type manhole 1.52 m internal dia (at bottom) beyond 2.30 m:
19.14.1 With F.P.S bricks class desigantion
Code Description Unit Quantity Rate Amount
Details of Cost for 1.88m extra depth.
Brick work with 75 class designation brick cum 5.26 2329.20 12251.57
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 8.99 132.57 1191.77


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 13443.33
Cost of 1.88 m 13443.33
Cost per metre 7150.71
Say 7150.71

19.14 Extra depth for circular type manhole 1.52 m internal dia (at bottom) beyond 2.30 m :
19.14.2 With Sewer bricks conforming IS : 4885
Code Description Unit Quantity Rate Amount
Details of Cost for 1.88m extra depth.
Brick work with sewer bricksconforming to cum 5.26 3217.83 16925.76
IS:4885 in cement mortar 1:4(1 cement: 4
coarse sand) Rate as per item no 6.36.1 of
SH : Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 8.99 132.57 1191.77


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 18117.53
Cost of 1.88 m 18117.53
Cost per metre 9636.98
Say 9636.98

19.15 Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks
1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design :
19.15.1 With 20x20 mm square bar
Code Description Unit Quantity Rate Amount
Details of cost for one MS foot rest
MATERIALS
1006 M.S. round bars 20 mm dia 0.75 m quintal 0.024 4300.00 103.20
9999 Carriage,painting, and other sundries L.S. 1.82 1.00 1.82
Labour
103 Black smith (2nd class) Day 0.1 223 22.30
114 Beldar Day 0.15 207 31.05
123 Mason ist class Day 0.02 270 5.40
124 Mason 2nd class Day 0.02 223 4.46
A Cem ent concrete 1:3:6 Rate as per item no cum 0.004 3,828.42 15.31
4.2.5 of SH : Concrete
TOTAL 183.54
Add 1% for water charges except on A 1.68
TOTAL 185.23
Add for contractor’s profit and overheads 25.49
@15% except on A
Cost of 1 no. 210.71
Say 210.71

19.15 Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks
1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design :
19.15.2 With 20 mm diameter round bar
Code Description Unit Quantity Rate Amount
Details of cost for one MS foot rest
MATERIALS
1003 Mild steel round bar above 12 mm dia quintal quintal 0.018 4300.00 77.40

9999 Carriage,painting, and other sundries L.S. 1.82 1.00 1.82


Labour
103 Black smith (2nd class) Day 0.1 223 22.30
114 Beldar Day 0.15 207 31.05
123 Mason ist class Day 0.02 270 5.40
124 Mason 2nd class Day 0.02 223 4.46
A Cem ent concrete 1:3:6 Rate as per item no cum 0.004 3,828.42 15.31
4.2.5 of SH : Concrete
TOTAL 157.74
Add 1% for water charges except on A 1.42
TOTAL 159.17
Add for contractor’s profit and overheads 21.58
@15% except on A
Cost of 1 no. 180.75
Say 180.75

19.16 Providing orange colour safety foot rest of minimum 6 m m th ick plastic encapsulated as
per IS : 10910 on 12mm dia steel bar conforming to IS : 1786 having minimum cross section as 23
mmx25mm and over all minimum length 263 mm and width as 165mm with minimum 112 mm space
between protruded legs having 2 mm tread on top surface by ribbing or chequering besides
necessary and adequate anchoring projections on tail length on 138 mm as per standard drawing and
suitable to with stand the bend test and chemical resistance test as per specifications and having
manufacture’s permanent identification mark to be visible even after fixing, including fixing in manholes
with 30x20x15 cm cement concrete block 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20
mm nominal
Code size) complete as per design.
Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7354 Plastic encaps ulated M .S. foot rest 30x20x1 each 1 93.00 93.00
9999 Carriage and other sundries L.S. 1.82 1.00 1.82
Cement conc rete 1:3:6 Rate as per item no cum 0.009 3,828.42 34.46
4.2.5 of SH : Concrete work
114 Beldar Day 0.05 207 10.35
123 Mason ist class Day 0.02 270 5.40
124 Mason 2nd class Day 0.2 223 44.60
TOTAL 189.63
Add 1% for water charges except on A 1.55
TOTAL 191.18
Add for contractor’s profit and overheads 23.51
@15% except on A
Cost of 1 no. 214.69
Say 214.69

19.17 Replacement of M.S. foot rests in manholes including dismantling concrete blocks and fixing with
20x20x10 cm cement concrete blocks 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20 mm
nominal size):20x20 mm square bar
19.17.1 With
Code Description Unit Quantity Rate Amount
Details of cost for one MS foot rest
MATERIALS
1006 M.S. round bars 20 mm dia 0.75 m quintal 0.024 4300.00 103.20
9999 Carriage,painting, and other sundries L.S. 1.82 1.00 1.82
Labour
103 Black smith (2 nd class) Day 0.1 223 22.30
114 Beldar Day 0.2 207 41.40
123 Mason ist class Day 0.05 270 13.50
124 Mason 2nd class Day 0.05 223 11.15
A Cem ent concrete 1:3:6 Rate as per item no cum 0.004 3,828.42 15.31
4.2.5 of SH : Concrete
TOTAL 208.68
Add 1% for water charges except on A 1.93
TOTAL 210.62
Add for contractor’s profit and overheads 29.30
@15% except on A
Cost of 1 no. 239.91
Say 239.91

19.17 Replacement of M.S. foot rests in manholes including dismantling concrete blocks and fixing with
20x20x10 cm cement concrete blocks 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20 mm
nominal size):20 mm diameter round bar
19.17.2 With
Code Description Unit Quantity Rate Amount
Details of cost for one MS foot rests
MATERIALS
1003 M.S. round bars 20 mm dia 0.75 m quintal 0.018 4300.00 77.40
9999 Carriage,painting, and other sundries L.S. 1.82 1.00 1.82
Labour
103 Black smith (2 nd class) Day 0.1 223 22.30
114 Beldar Day 0.2 207 41.40
123 Mason ist class Day 0.05 270 13.50
124 Mason 2nd class Day 0.05 223 11.15
A Cem ent concrete 1:3:6 Rate as per item no cum 0.004 3,828.42 15.31
4.2.5 of SH : Concrete
TOTAL 182.88
Add 1% for water charges except on A 1.68
TOTAL 184.56
Add for contractor’s profit and overheads 25.39
@15% except on A
Cost of 1 no. 209.95
Say 209.95

19.18 Supplying and fixing C.I. cover without frame for manholes :
19.18.1 455x610 mm rectangular C.I. cover (light duty)the weight of the cover to be not less than 23 kg.
Code Description Unit Quantity Rate Amount
Details of cost for one cover
MATERIALS
1355 C.I. Man-hole cover without frame each 1 844.00 844.00
9999 Carriage of C.I. Man-hole cover L.S. 7.15 1.00 7.15
Labour
114 Beldar Day 0.12 207 24.84
TOTAL 875.99
Add 1% for water charges 8.76
TOTAL 884.75
Add for contractor’s profit and overheads 132.71
@15%
Cost of 1 no. 1017.46
Say 1017.46

19.18 Supplying and fixing C.I. cover without frame for manholes :
19.18.2 500 mm diameter C.I. cover (medium duty) the weight of the cover to be not less than 58 kg.
Code Description Unit Quantity Rate Amount
Details of cost for one cover
MATERIALS
1357 C.I. Man-hole cover without frame each 1 2129.00 2129.00
9999 Carriage of C.I. Man-hole cover L.S. 13.47 1.00 13.47
Labour
114 Beldar Day 0.12 207 24.84
TOTAL 2167.31
Add 1% for water charges 21.67
TOTAL 2188.98
Add for contractor’s profit and overheads 328.35
@15%
Cost of 1 no. 2517.33
Say 2517.33

19.18 Supplying and fixing C.I. cover without frame for manholes :
19.18.3 560 mm diameter C.I, cover (heavy duty) the weight of the cover to be not less than 108 kg.
Code Description Unit Quantity Rate Amount
Details of cost for one cover
MATERIALS
3861 C.I. Man-hole cover without frame (heavy each 1 3664.00 3664.00
each duty) 560 mm internal diameter

9999 Carriage of C.I. Man-hole cover L.S. 16.12 1.00 16.12


Labour
114 Beldar Day 0.12 207 24.84
TOTAL 3704.96
Add 1% for water charges 37.05
TOTAL 3742.01
Add for contractor’s profit and overheads 561.30
@15%
Cost of 1 no. 4303.31
Say 4303.31

19.19 Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
and approved quality
19.19.1 LD-2.5
19.19.1.1 Rectangular shape 600x450mm internal dimensions
Code Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7130 Rectangular shape 600x450 mm precast each 1 628.00 628.00
R.C.C. manhole cover w ith frame L.D.-25
9999 Carriage of Man-hole cover L.S. 6.76 1.00 6.76
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.04 5140.53 205.62
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

9999 Sundries L.S. 13.52 1.00 13.52


TOTAL 853.90
Add 1% for water charges except on A 6.48
TOTAL 860.38
Add for contractor’s profit and overheads 98.21
@15% except on A
Cost of 1 no. 958.60
Say 958.60

19.19 Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
and approved quality
19.19.1 LD-2.5
19.19.1.2 Square shape 450mm internal dimensions
Code Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7131 R.C.C manhole cover and frame 450 mm squar each 1 540.00 540.00
9999 Carriage of Man-hole cover L.S. 6.76 1.00 6.76
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.03 5140.53 154.22
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

9999 Sundries L.S. 13.52 1.00 13.52


TOTAL 714.50
Add 1% for water charges except on A 5.60
TOTAL 720.10
Add for contractor’s profit and overheads 84.88
@15% except on A
Cost of 1 no. 804.98
Say 804.98

19.19 Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
and approved quality
19.19.1 L D- 2.5
19.19.1.3 Circular shape 450mm internal diameter
Code Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7132 Circular shape 450 mm dia precast R.C.C. each 1 474.00 474.00
manhole cover with frame l.D.-25
9999 Carriage of Man-hole cover L.S. 6.76 1.00 6.76
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.03 5140.53 154.22
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

9999 Sundries L.S. 13.52 1.00 13.52


TOTAL 648.50
Add 1% for water charges except on A 4.94
TOTAL 653.44
Add for contractor’s profit and overheads 74.88
@15% except on A
Cost of 1 no. 728.32
Say 728.32

19.19 Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
and approved quality
19.19.2 MD- 10
19.19.2.1 Square shape 450mm x450mm finternal dimension
Code Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7133 Rectangular shape 500x500 mm precast each 1 575.00 575.00
R.C.C. manhole cover with frame - M.D. - 10

9999 Carriage of Man-hole cover L.S. 6.76 1.00 6.76


A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.04 5140.53 205.62
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

9999 Sundries L.S. 16.64 1.00 16.64


TOTAL 804.02
Add 1% for water charges except on A 5.98
TOTAL 810.01
Add for contractor’s profit and overheads 90.66
@15% except on A
Cost of 1 no. 900.66
Say 900.66

19.19 Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
and approved quality
19.19.2 MD-10
19.19.2.2 Circular shape 500mm internal diameter
Code Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7134 Circular shape 500 mm dia precast R.C.C. each 1 575.00 575.00
manhole cover with frame -M.D.-10

9999 Carriage of Man-hole cover L.S. 6.76 1.00 6.76


A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.03 5140.53 154.22
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

9999 Sundries L.S. 16.64 1.00 16.64


TOTAL 752.62
Add 1% for water charges except on A 5.98
TOTAL 758.60
Add for contractor’s profit and overheads 90.66
@15% except on A
Cost of 1 no. 849.26
Say 849.26

19.19 Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
and approved quality
19.19.3 HD-20
19.19.3.1 Circular shape 560 mm internal diam eter
Code Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7135 Circular shape 560 mm dia precast R.C.C. each 1 838.00 838.00
manhole cover with frame -H.D.-20

9999 Carriage of Man-hole cover L.S. 13.52 1.00 13.52


A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.03 5140.53 154.22
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)

9999 Sundries L.S. 20.28 1.00 20.28


TOTAL 1026.02
Add 1% for water charges except on A 8.72
TOTAL 1034.73
Add for contractor’s profit and overheads 132.08
@15% except on A
Cost of 1 no. 1166.81
Say 1166.81

19.19 Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
and approved quality
19.19.4 EHD - 35
19.19.4.1 Circular shape 560 mm internal dia.
Code Description Unit Quantity Rate Amount
Details of cost for one no.
MATERIALS
7136 Circular shape 560 mm dia precast R.C.C. each 1 935.00 935.00
manhole cover with frame -E.H.D.-35

9999 Carriage of Man-hole cover L.S. 13.52 1.00 13.52


A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.03 5140.53 154.22
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)
9999 Sundries L.S. 20.28 1.00 20.28
TOTAL 1123.02
Add 1% for water charges except on A 9.69
TOTAL 1132.70
Add for contractor’s profit and overheads 146.77
@15% except on A
Cost of 1 no. 1279.48
Say 1279.48

19.20 Supplying and fixing C.I. cover 300x300 mm without frame for gully trap (standard pattern) the
weight of cover to be not less than 4.5kg.
Code Description Unit Quantity Rate Amount
Details of cost for one cover
MATERIALS
1353 C.I.cover without frame 300x300mm inside each 1 170.00 170.00
i/c cover of 4.50 kg
9999 Carriage of C.I. Man-hole cover L.S. 2.7 1.00 2.70
Labour
114 Beldar Day 0.03 207 6.21
TOTAL 178.91
Add 1% for water charges 1.79
TOTAL 180.70
Add for contractor’s profit and overheads 27.10
@15%
Cost of 1 no. 207.80
Say 207.80

19.21 Making connection of drain or sewer line with existing manhole including breaking into and
making good the walls, floors with cement concrete 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3
coarse sand) finished with a floating coat of neat cement and making necessary channels for the drain
etc. complete :
19.21.1 For pipes 100 to 230 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for one connection
MATERIALS
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.01 5140.53 51.41
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.25 132.57 33.14
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.12 270 32.40


124 Mason 2nd class Day 0.12 223 26.76
114 Beldar Day 0.25 207 51.75
9999 Add for delay and sundries L.S. 20.15 1.00 20.15
TOTAL 215.61
Add for water charges @ 1 % except on ‘A 1.31
TOTAL 216.92
Add 15% for contractor’s profit and overheads 19.86
on (A+B)
Cost of one connection 236.77
Say 236.77

19.21 Making connection of drain or sewer line with existing manhole including breaking into and
making good the walls, floors with cement concrete 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3
coarse sand) finished with a floating coat of neat cement and making necessary channels for the drain
etc. complete :
19.21.2 For pipes 250 to 300 mm diameter
Code Description Unit Quantity Rate Amount
Details of cost for one connection
MATERIALS
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.02 5140.53 102.81
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.32 132.57 42.42
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.12 270 32.40


124 Mason 2nd class Day 0.12 223 26.76
114 Beldar Day 0.25 207 51.75
9999 Add for delay and sundries L.S. 20.67 1.00 20.67
TOTAL 276.81
Add for water charges @ 1 % except on ‘A 1.32
TOTAL 278.13
Add 15% for contractor’s profit and overheads 19.93
on (A+B)
Cost of one connection 298.06
Say 298.06

19.21 Making connection of drain or sewer line with existing manhole including breaking into and
making good the walls, floors with cement concrete 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3
coarse sand) finished with a floating coat of neat cement and making necessary channels for the drain
etc. complete
19.21.3 : 350 to 450 mm diameter
For pipes
Code Description Unit Quantity Rate Amount
Details of cost for one connection
MATERIALS
A Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.03 5140.53 154.22
sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.1.3 of S.H.
: concrete)
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.6 132.57 79.54
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

123 Mason 1st class Day 0.16 270 43.20


124 Mason 2nd class Day 0.16 223 35.68
114 Beldar Day 0.33 207 68.31
9999 Add for delay and sundries L.S. 26.91 1.00 26.91
TOTAL 407.86
Add for water charges @ 1 % except on ‘A 1.74
TOTAL 409.60
Add 15% for contractor’s profit and overheads 26.38
on (A+B)
Cost of one connection 435.97
Say 435.97

19.22 Providing sand cast iron drop connection externally for 60 cm drop from branch sewer line to
main sewer manhole including inspection and cleaning eye with chain and lid, sand cast iron drop pipe
and bend encased alround with cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone
aggregate 40 mm nominal size) with all centring and shuttering required, cutting holes in walls and
making good with brick work in cement mortar 1:4 (1 cement : 4 coarse sand) plastered with cement
mortar 1:3 (1 cement : 3 coarse sand) on inside of the manhole wall lead caulked joints between sand
cast iron pipes, and fittings, stiff cement mortar 1:1 (1 cement: 1 fine sand) joints between sand cast iron
tee and S.W. pipe, making required channels complete as per standard design and specifications :
19.22.1 100 mm dia. sand cast iron drop connection
Code Description Unit Quantity Rate Amount
Details of cost for one drop connection
MATERIALS
1617 100 mm diameter sand cost iron pipe 1.8 m 1 610.00 338.89
1621 Sand cast iron bend plain each 1 178.00 178.00
1336 Cleaning eye with chain and lid each 1 37.00 37.00
1628 Sand cast iron tee each 1 265.00 265.00
9,999 Carriage of pipe L.S. 1.43 1.00 1.43
Cutting charges
A Rate as per item no 18.83.2 of SH water each cut 3 47.49 142.48
supply
A Brick work with 75 class designation brick cum 0.007 2329.20 16.30
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
A Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.21 2,719.53 571.10
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.06 132.57 7.95
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

A Providing lead caulked joints to 150 mm each 4 243.76 975.06


diameter pipe and special Rate as per item no.
12.39.1 of SH : Roofing
A Form work Rate as per item no 5.9.2 of SH : sqm 1.36 475.79 647.08
RCC
9,999 Providing joint to S.W. pipe with cement L.S. 26.91 1.00 26.91
mortar 1:1 (1 cement: 1 fine sand)
9,999 Sundries including carriage of bends etc. L.S. 26.91 1.00 26.91

LABOUR For cutting holes 45 holes 5 cm deep toothing in alternate course of brick work benching
and making channel
114 Beldar Day 2.7 207 558.90
123 Mason ist class Day 0.7 270 189.00
124 Mason 2nd class Day 0.7 223 156.10
TOTAL 4138.12
Add 1% for water charges except on A 17.78
TOTAL 4155.90
Add for contractor’s profit and overheads 269.39
@15% except on A
Cost of 1 no. 4425.29
Say 4425.29

19.22 Providing sand cast iron drop connection externally for 60 cm drop from branch sewer line to
main sewer manhole including inspection and cleaning eye with chain and lid, sand cast iron drop pipe
and bend encased alround with cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone
aggregate 40 mm nominal size) with all centring and shuttering required, cutting holes in walls and
making good with brick work in cement mortar 1:4 (1 cement : 4 coarse sand) plastered with cement
mortar 1:3 (1 cement : 3 coarse sand) on inside of the manhole wall lead caulked joints between sand
cast iron pipes, and fittings, stiff cement mortar 1:1 (1 cement: 1 fine sand) joints between sand cast iron
tee and S.W. pipe, making required channels complete as per standard design and specifications :
19.22.2 150 mm dia. sand cast iron drop connection
Code Description Unit Quantity Rate Amount
Details of cost for one drop connection
MATERIALS
1618 150 mm diameter sand cost iron pipe 1.8 m 1 1205.00 669.44
1622 Sand cast iron bend plain each 1 407.00 407.00
1337 Cleaning eye with chain and lid each 1 41.00 41.00
7087 Sand cast iron tee each 1 460.00 460.00
9,999 Carriage of pipe L.S. 1.82 1.00 1.82
Cutting charges
A Rate as per item no 18.83.4 of SH water each cut 3 89.30 267.89
supply
A Brick work with 75 class designation brick cum 0.005 2329.20 11.65
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
A Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.28 2,719.53 761.47
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete
A 12mm cement plaster 1:3 (1 Cement: 3 sqm 0.06 132.57 7.95
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

A Providing lead caulked joints to 150 mm each 4 347.33 1389.34


diameter pipe and special Rate as per item no.
12.39.2 of SH : Roofing
A Form work Rate as per item no 5.9.2 of SH : sqm 1.67 475.79 794.58
RCC
9,999 Providing joint to S.W. pipe with cement L.S. 39.91 1.00 39.91
mortar 1:1 (1 cement: 1 fine sand)
9,999 Sundries including carriage of bends etc. L.S. 34.06 1.00 34.06

LABOUR For cutting holes 45 holes 5 cm deep toothing in alternate course of brick work benching
and making channel
114 Beldar Day 3.5 207 724.50
123 Mason ist class Day 0.85 270 229.50
124 Mason 2nd class Day 0.85 223 189.55
TOTAL 6029.66
Add 1% for water charges except on A 27.97
TOTAL 6057.63
Add for contractor’s profit and overheads 423.71
@15% except on A
Cost of 1 no. 6481.34
Say 6481.34

19.23 Extra for depths beyond 60 cm of sand cast iron drop connection complete :
19.23.1 For 100 mm dia. sand cast iron drop connection
Code Description Unit Quantity Rate Amount
Details of cost for one metre
MATERIALS
1617 100 mm diameter sand cost iron pipe 1.8 m 1 610.00 338.89
9,999 Carriage of materials and fixing charges L.S. 13.39 1.00 13.39
A Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.16 2,719.53 435.13
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete
A Form work Rate as per item no 5.9.2 of SH : sqm 1.3 475.79 618.53
RCC
9,999 Sundries L.S. 7.15 1.00 7.15
LABOUR For cutting holes 5 cm deep in alternate course of brick work
114 Beldar Day 0.04 207 8.28
123 Mason ist class Day 0.04 270 10.80
124 Mason 2nd class Day 0.04 223 8.92
TOTAL 1441.09
Add 1% for water charges except on A 3.87
TOTAL 1444.96
Add for contractor’s profit and overheads 58.70
@15% except on A
Cost of 1 metre 1503.66
Say 1503.66

19.23 Extra for depths beyond 60 cm of sand cast iron drop connection complete :
19.23.2 For 150 mm dia. sand cast iron drop connection
Code Description Unit Quantity Rate Amount
Details of cost for one metre
MATERIALS
1618 150 mm diameter sand cost iron pipe 1.8 m 1 1205.00 669.44
9,999 Carriage of materials and fixing charges L.S. 13.39 1.00 13.39
A Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.2 2,719.53 543.91
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete
A Form work Rate as per item no 5.9.2 of SH : sqm 1.45 475.79 689.90
RCC
9,999 Sundries L.S. 8.09 1.00 8.09
LABOUR For cutting holes 5 cm deep in alternate course of brick work
114 Beldar Day 0.05 207 10.35
123 Mason ist class Day 0.05 270 13.50
124 Mason 2nd class Day 0.05 223 11.15
TOTAL 1959.73
Add 1% for water charges except on A 7.26
TOTAL 1966.99
Add for contractor’s profit and overheads 109.98
@15% except on A
Cost of 1 metre 2076.97
Say 2076.97
19.24 Dismantling of manhole including R.C.C. top slab, C.I. cover with frame including stacking of
useful materials near the site and disposal of unserviceable materials into municipal dumps within 50 m
lead : Rectangular manhole 90x80 cm and 45 cm deep
19.24.1
Code Description Unit Quantity Rate Amount
Details of cost of a manhole 90x80 and 45 cm deep
Dismantling of cement concrete 1:4:8 (1 cum 0.43 346.08 148.81
cement: 4 coarse sand 8 : aggregate stone
40mm nominal size) Rate as per item no.
15.2.2 of SH: Dismantling and demolishing

Dismantling of second class brick w ork in cum 0.34 453.50 154.19


Cement mortar 1:4 (1cement : 4 coarse sand)
Rate as per item no. 15.7.4 of SH
-.dismantling Rate as per item no. 15.7.4 of
SH -.dismantling

Dismantling cement concrete 1:2:4 ( 1 cum 0.16 536.59 85.85


cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) Rate as per
item no. 15.2.1 of SH: Dismantling and
demolishing

Dismantling of R.C.C slab of 1:2:4 (1 cum 0.22 818.40 180.05


cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

9,999 Rem oval of C.I. Cover with frame L.S. 7.15 1.00 7.15 A
TOTAL 576.06
Add 1% for water charges on A 0.07
TOTAL 576.13
Add for contractor’s profit and overheads 1.08
@15% on A
Cost of 1 metre 577.21
Say 577.21

19.24 Dismantling of manhole including R.C.C. top slab, C.I. cover with frame including stacking of
useful materials near the site and disposal of unserviceable materials into municipal dumps within 50 m
lead :
19.24.2
Code Description Unit Quantity Rate Amount
Details of cost of a manhole 120x90 cm and 90 cm deep
Dismantling of cement concrete 1:4:8 (1 cum 0.55 346.08 190.34
cement: 4 coarse sand 8 : aggregate stone
40mm nominal size) Rate as per item no.
15.2.2 of SH: Dismantling and demolishing
Dismantling of second class brick w ork in cum 0.93 453.50 421.75
Cement mortar 1:4 (1cement : 4 coarse sand)
Rate as per item no. 15.7.4 of SH
-.dismantling Rate as per item no. 15.7.4 of
SH -.dismantling

Dismantling cement concrete 1:2:4 ( 1 cum 0.25 536.59 134.15


cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) Rate as per
item no. 15.2.1 of SH: Dismantling and
demolishing

Dismantling of R.C.C slab of 1:2:4 (1 cum 0.31 818.40 253.71


cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

9,999 Rem oval of C.I. Cover with frame L.S. 7.15 1.00 7.15 A
TOTAL 1007.10
Add 1% for water charges on A 0.07
TOTAL 1007.17
Add for contractor’s profit and overheads 1.08
@15% on A
Cost of 1 metre 1008.26
Say 1008.26

19.24 Dismantling of manhole including R.C.C. top slab, C.I. cover with frame including stacking of
useful materials near the site and disposal of unserviceable materials into municipal dumps within 50 m
lead : Rectangular arch type manhole 140x90cm and 2.45m deep.
19.24.3
Code Description Unit Quantity Rate Amount
Details of cost of a manhole 140x90cm and 2.45m deep.
Dismantling of cement concrete 1:4:8 (1 cum 0.72 346.08 249.18
cement: 4 coarse sand 8 : aggregate stone
40mm nominal size) Rate as per item no.
15.2.2 of SH: Dismantling and demolishing

Dismantling of second class brick w ork in cum 2.89 453.50 1310.61


Cement mortar 1:4 (1cement : 4 coarse sand)
Rate as per item no. 15.7.4 of SH
-.dismantling Rate as per item no. 15.7.4 of
SH -.dismantling

Dismantling cement concrete 1:2:4 ( 1 cum 0.29 536.59 155.61


cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) Rate as per
item no. 15.2.1 of SH: Dismantling and
demolishing
Dismantling of R.C.C slab of 1:2:4 (1 cum 0.19 818.40 155.50
cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

9,999 Rem oval of C.I. Cover with frame L.S. 7.15 1.00 7.15 A
9,999 Rem oval of MS foot rest L.S. 8.06 1.00 8.06 A
TOTAL 1886.11
Add 1% for water charges on A 0.15
TOTAL 1886.26
Add for contractor’s profit and overheads 2.30
@15% on A
Cost of 1 metre 1888.56
Say 1888.56

19.24 Dismantling of manhole including R.C.C. top slab, C.I. cover with frame including stacking of
useful materials near the site and disposal of unserviceable materials into municipal dumps within 50 m
lead :
19.24.4 Circular manhole 122 cm diameter and 1.68 m deep.
Code Description Unit Quantity Rate Amount
Details of cost of a manhole 1.22 in internal diameter 1.68m deep
Dismantling of cement concrete 1:3 :6 (1 cum 1.18 346.08 408.38
cement: 3 coarse sand 6 : aggregate stone
40mm nominal size) Rate as per item no.
15.2.2 of SH: Dismantling and demolishing

Dismantling of second class brick w ork in cum 1.31 453.50 594.08


Cement mortar 1:4 (1cement : 4 coarse sand)
Rate as per item no. 15.7.4 of SH
-.dismantling Rate as per item no. 15.7.4 of
SH -.dismantling

Form work (Rate as per item No.5.9.3) sqm 0.45 506.86 228.09
Dismantling of R.C.C slab of 1:2:4 (1 cum 0.31 818.40 253.71
cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

9,999 Rem oval of C.I. Cover with frame L.S. 7.15 1.00 7.15 A
9,999 Rem oval of MS foot rest L.S. 8.06 1.00 8.06 A
TOTAL 1499.46
Add 1% for water charges on A 0.15
TOTAL 1499.61
Add for contractor’s profit and overheads 2.30
@15% on A
Cost of 1 metre 1501.92
Say 1501.92
19.25 Extra for depth of manholes dismantled:
19.25.1 Rectangular manhole 90x80 cm and 45 cm deep
Code Description Unit Quantity Rate Amount
Details of cost for dismantling one manhole
A Dismantling of second class brick work in cum 0.99 453.50 448.96
cement mortar 1:5 (1 Cement: 5 fine sand)
Rate as per item no. 15.7.4 SH:- Dismantling

9,999 Removing of M.S. foot rests L.S. 1.82 1.00 1.82


TOTAL 450.78
Add 1% for water charges except on A 0.02
TOTAL 450.80
Add for contractor’s profit and overheads 0.28
@15% except on A
Cost of 1 manhole 451.08
Say 451.08

19.25 Extra for depth of manholes dismantled:


19.25.2 Rectangular manhole 120x90 cm and 90 cm deep
Code Description Unit Quantity Rate Amount
Details of cost for dismantling one manhole
A Dismantling of second class brick work in cum 1.18 453.50 535.13
cement mortar 1:5 (1 Cement: 5 fine sand)
Rate as per item no. 15.7.4 SH:- Dismantling

9,999 Removing of M.S. foot rests L.S. 1.82 1.00 1.82


TOTAL 536.95
Add 1% for water charges except on A 0.02
TOTAL 536.97
Add for contractor’s profit and overheads 0.28
@15% except on A
Cost of 1 manhole 537.24
Say 537.24

19.25 : Extra for depth of manholes dismantled:


19.25.3: Rectangular arch type manhole 140x90 cm and 2.45m deep (upto 4.25 m depth).
Code Description Unit Quantity Rate Amount
Details of cost for dismantling one manhole 140x90 cm and 2.45m deep (upto 4.25 m depth)
Dismantling of second class brick work in cum 1.49 453.50 675.71
cement mortar 1:5 (1 Cement: 5 fine sand)
Rate as per item no. 15.7.4 SH:- Dismantling
Dismantling cement concrete 1:2:4 ( 1 cum 0.2 536.59 107.32
cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) Rate as per
item no. 15.2.1 of SH: Dismantling and
demolishing

TOTAL 783.03
Cost of 1.8 metre 783.03
Cost per metre 435.02
Say 435.02

19.25 : Extra for depth of manholes dismantled:


19.25.4: Circular manhole 122 cm diameter and 1.68 m deep (upto 2.29 m depth)
Code Description Unit Quantity Rate Amount
Details of cost of a manhole 140x90cm and 2.29m deep.
Dismantling cement concrete 1:2:4 ( 1 cum 3.5 536.59 1878.07
cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) Rate as per
item no. 15.2.1 of SH: Dismantling and
demolishing

9,999 Rem oval of SRFC Cover L.S. 7.15 1.00 7.15 A


9,999 Rem oval of MS foot rest L.S. 8.06 1.00 8.06 A
TOTAL 1893.28
Add 1% for water charges on A 0.15
TOTAL 1893.43
Add for contractor’s profit and overheads 2.30
@15% on A
Cost of 2.29 metre 1895.73
Deduct cost of dismantling manhole 1.68m each 1 1501.92 -1501.92
deep Rate as per item no 19.24.4 of SH : D
rainage
Cost of manhole of 0.61 m metre 393.82
Cost of per metre of manhole 645.60
Say 645.60

19.26: Raising manhole cover and frame slab to required level including dismantling existing slab and
making good the damage as required (Raising depth of manhole to be paid separately):
19.26.1 : Rectangular manhole 90x80 cm with rectangular cover 600x450 mm of grade LD - 2.5
Code Description Unit Quantity Rate Amount
Details of cost of a manhole
Cement concrete 1:2:4 ( 1 cement : 2 cum 0.17 4269.75 725.86
coarse sand : 4 graded stone aggregate 20 mm
nominal size) Rate as per item no. 5.3 of SH:
concrete work
Dismantling of R.C.C slab of 1:2:4 (1 cum 0.17 818.40 139.13
cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

Form work (Rate as per item No.5.9.3) sqm 0.45 506.86 228.09
9,999 Rem oval of R.C.C. Cover with frame L.S. 7.15 1.00 7.15 A
9,999 Sundries L.S. 13.52 1.00 13.52 A
TOTAL 1113.74
Add 1% for water charges on A 0.21
TOTAL 1113.95
Add for contractor’s profit and overheads 3.13
@15% on A
Cost of 1 metre 1117.08
Say 1117.08

19.26: Raising manhole cover and frame slab to required level including dismantling existing slab and
making good the damage as required (Raising depth of manhole to be paid separately):
19.26.2: Rectangular manhole 120x90 cm with circular cover 500 mm dia of grade MD - 10
Code Description Unit Quantity Rate Amount
Details of cost of a manhole
Cement concrete 1:2:4 ( 1 cement : 2 cum 0.26 4269.75 1110.14
coarse sand : 4 graded stone aggregate 20 mm
nominal size) Rate as per item no. 5.3 of SH:
concrete work

Dismantling of R.C.C slab of 1:2:4 (1 cum 0.26 818.40 212.79


cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

Form work (Rate as per item No.5.9.3) sqm 0.88 506.86 446.04
9,999 Rem oval of R.C.C. Cover with frame L.S. 7.15 1.00 7.15 A
9,999 Sundries L.S. 16.64 1.00 16.64 A
TOTAL 1792.75
Add 1% for water charges on A 0.24
TOTAL 1792.99
Add for contractor’s profit and overheads 3.60
@15% on A
Cost of 1 metre 1796.59
Say 1796.59

19.26: Raising manhole cover and frame slab to required level including dismantling existing slab and
making good the damage as required (Raising depth of manhole to be paid separately):
19.26.3 : Rectangular manhole 120x90 cm with circular cover 560 mm dia of grade HD - 20
Code Description Unit Quantity Rate Amount
Details of cost of a manhole
Cement concrete 1:2:4 ( 1 cement : 2 cum 0.24 4269.75 1024.74
coarse sand : 4 graded stone aggregate 20 mm
nominal size) Rate as per item no. 5.3 of SH:
concrete work

Dismantling of R.C.C slab of 1:2:4 (1 cum 0.24 818.40 196.42


cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

Form work (Rate as per item No.5.9.3) sqm 0.83 506.86 420.70
9,999 Rem oval of R.C.C. Cover with frame L.S. 7.15 1.00 7.15 A
9,999 Sundries L.S. 20.28 1.00 20.28 A
TOTAL 1669.28
Add 1% for water charges on A 0.27
TOTAL 1669.56
Add for contractor’s profit and overheads 4.16
@15% on A
Cost of 1 metre 1673.71
Say 1673.71

19.26: Raising manhole cover and frame slab to required level including dismantling existing slab and
making good the damage as required (Raising depth of manhole to be paid separately):
19.26.4: Circular manhole 140 cm dia with circular cover 600 mm dia of grade EHD - 35
Code Description Unit Quantity Rate Amount
Details of cost of a manhole
Cement concrete 1:2:4 ( 1 cement : 2 cum 0.02 4362.73 87.25
coarse sand : 4 graded stone aggregate 20 mm
nominal size) Rate as per item no. 4.2.3 of
SH: concrete work

Dismantling of R.C.C slab of 1:2:4 (1 cum 0.02 818.40 16.37


cement: 2 coarse sand : 4 grade stone
aggregate 20 mm nominal size) Rate as per
item no 15.3 of SH : Demolishing and
dismantling

9,999 Rem oval of R.C.C. Cover with frame L.S. 8.06 1.00 8.06 A
9,999 Sundries L.S. 20.28 1.00 20.28 A
TOTAL 131.96
Add 1% for water charges on A 0.28
TOTAL 132.25
Add for contractor’s profit and overheads 4.29
@15% on A
Cost of 1 metre 136.54
Say 136.54
19.27: Constructing brick masonry road gully chamber 50x45x60 cm with bricks of class designation 75
in cement mortar 1:4 (1 cement : 4 coarse sand) including 500x450 mm precast R.C.C. horizontal grating
with frame
19.27.1: complete
With as per standard design :
F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one chamber
A Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.18 2,719.53 489.52
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete
A Brick work with 75 class designation brick cum 0.29 2329.20 675.47
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.1 4362.73 436.27


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 1.08 132.57 143.17


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

A Form work Rate as per item no 5.9.2 of SH : sqm 0.53 475.79 252.17
RCC
7380 Precast R.C.C. grating with frame 500x450 each 1 533.00 533.00 (A)
mm horizontal grating
9999 Carriage of R.C.C. grating L.S. 7.15 1.00 7.15 (A)
9999 Fixing R.C.C. grating L.S. 5.33 1.00 5.33 (A)
TOTAL 2542.08
Add for water charges @ 1 % on ‘A 5.45 (B)
TOTAL 2547.53
Add 15% for contractor’s profit and overheads 82.64
on (A+B)
Cost of one chamber 2630.17
Say 2630.17

19.28: Constructing brick masonry road gully chamber 45x45x77.5 cm with bricks of class designation
75 in cement w mortar 1:4(1 cement: 4 coarse sand ) with precast R.C.C. vertical grating complete as
per standard design :
19.28.1: With F.P.S. Bricks
Code Description Unit Quantity Rate Amount
Details of cost of one chamber
A Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.17 2,719.53 462.32
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete
A Brick work with 75 class designation brick cum 0.43 2329.20 1001.55
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Cement concrete 1:2:4 ( 1 cement : 2 cum 0.06 4269.75 256.19


coarse sand : 4 graded stone aggregate 20 mm
nominal size) Rate as per item no. 5.3 of SH:
concrete work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.001 4362.73 4.36


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 1.55 132.57 205.48


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

(viii) Mild steel reinforcement for RCC work kg 4.96 58.65 290.93
(Rate as per item No.5.22.1
A Form work Rate as per item no 5.9.2 of SH : sqm 0.55 475.79 261.69
RCC
7381 Precast R.C.C. grating with frame 450x100 each 1 250.00 250.00 (A)
mm vertical grating
9999 Fixing & carriage of R.C.C. grating L.S. 20.67 1.00 20.67 (A)
TOTAL 2753.18
Add for water charges @ 1 % on ‘A 2.71 (B)
TOTAL 2755.89
Add 15% for contractor’s profit and overheads 41.01
on (A+B)
Cost of one chamber 2796.89
Say 2796.89

19.29: Constructing brick masonry road gully chamber 110x50x77.5 cm with bricks of class designation
75 in cement mortar 1:4 (1 cement : 4 coarse sand) including 500x450 mm precast R.C.C. horizontal
grating with frame and vertical grating complete as per standard design :
19.29.1: With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one chamber
Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.29 2,719.53 788.66
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete

Brick work with 75 class designation brick cum 0.54 2329.20 1257.77
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
RCC 1:2:4 ( 1 cement : 2 coarse sand : 4 cum 0.06 4269.75 256.19
graded stone aggregate 20 mm nominal size)
Rate as per item no. 5.3 of SH: concrete work

RCC 1:2:4 ( 1 cement : 2 coarse sand : 4 cum 0.04 6749.19 269.97


graded stone aggregate 20 mm nominal size)
in lintels Rate as per item no. 5.13 of SH:RCC
work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.07 4362.73 305.39


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.36 132.57 312.85


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Mild steel reinforcement for RCC work (Rate kg 8 58.65 469.23


as per item No.5.22.1
A Form work Rate as per item no 5.9.2 of SH : sqm 0.91 475.79 432.97
RCC
7381 Precast R.C.C. grating with frame 450x100 each 1 250.00 250.00 (A)
mm vertical grating
7380 Precast R.C.C. grating with frame 500x450 each 1 533.00 533.00 (A)
mm horizontal grating
9999 Carriage of R.C.C. grating L.S. 7.15 1.00 7.15 (A)
9999 Labour for fixing pre cast R.C.C. grating and fra L.S. 34.06 1.00 34.06 (A)
TOTAL 4917.25
Add for water charges @ 1 % on ‘A 8.24 (B)
TOTAL 4925.49
Add 15% for contractor’s profit and overheads 124.87
on (A+B)
Cost of one chamber 5050.36
Say 5050.36

19.30 Constructing brick masonry chamber for underground C.I. inspection chamber and bends with 75
class designation bricks in cement mortar 1:4 (1 cement : 4 coarse sand) C.I. cover with frame (light
duty) 455x610 mm internal dimensions, total weight of cover with frame to be not less than 38 kg
(weight of cover 23 kg and weight of frame 15 kg) R.C.C. top slab with 1:2:4 mix (1 cement :2 coarse
sand : 4 graded stone aggregate 20 mm nominal size) foundation concrete 1:5:10 (1 cement: 5 fine sand
: 10 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar
1:3 (1 cement: 3 coarse sand) finished smooth with a floating coat of neat cement on walls and bed
concrete etc. complete as per standard design :
19.30.1: Inside dimensions 455x610 mm and 45 cm deep for single pipe line :
19.30.1.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.2 2,719.53 543.91
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete

Brick work with 75 class designation brick cum 0.21 2329.20 489.13
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

Cement concrete 1:2:4 ( 1 cement: 2 coarse cum 0.11 4362.73 479.90


sand : 4 graded stone aggregate 20 mm
nominal size) (Rate as per item 4.2.3 of S.H.
: concrete)

12mm cement plaster 1:3 (1 Cement: 3 sqm 0.9 132.57 119.31


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

A Form work Rate as per item no 5.9.2 of SH : sqm 0.56 475.79 266.44
RCC
1354 C.I. Cover with frame 455x610 mm (inside) each 1 1395.00 1395.00 (A)

9999 Carriage of C.I. C.I. cover & frame L.S. 7.15 1.00 7.15 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 7.15 1.00 7.15 (A)
9999 Sundries L.S. 13.52 1.00 13.52 (A)
TOTAL 3321.51
Add for water charges @ 1 % on ‘A 14.23 (B)
TOTAL 3335.74
Add 15% for contractor’s profit and overheads 215.56
on (A+B)
Cost of one manhole 3551.30
Say 3551.30

19.30 Constructing brick masonry chamber for underground C.I. inspection chamber and bends with 75
class designation bricks in cement mortar 1:4 (1 cement : 4 coarse sand) C.I. cover with frame (light
duty) 455x610 mm internal dimensions, total weight of cover with frame to be not less than 38 kg
(weight of cover 23 kg and weight of frame 15 kg) R.C.C. top slab with 1:2:4 mix (1 cement :2 coarse
sand : 4 graded stone aggregate 20 mm nominal size) foundation concrete 1:5:10 (1 cement: 5 fine sand
: 10 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar
1:3 (1 cement: 3 coarse sand) finished smooth with a floating coat of neat cement on walls and bed
concrete etc. complete as per standard design :
19.30.2 Inside dimensions 500x700 mm and 45 cm deep for pipe line with one or two inlets :
19.30.2.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.22 2,719.53 598.30
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete

Brick work with 75 class designation brick cum 0.22 2329.20 512.42
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

RCC 1:2:4 ( 1 cement : 2 coarse sand : 4 cum 0.13 4269.75 555.07


graded stone aggregate 20 mm nominal size)
Rate as per item no. 5.3 of SH: concrete work

12mm cement plaster 1:3 (1 Cement: 3 sqm 1.05 132.57 139.19


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Mild steel reinforcement for RCC work (Rate kg 6.25 58.65 366.59
as per item No.5.22.1
Form work Rate as per item no 5.9.2 of SH : sqm 0.67 475.79 318.78
RCC
1354 C.I. Cover with frame 455x610 mm (inside) each 1 1395.00 1395.00 (A)

9999 Carriage of C.I. C.I. cover & frame L.S. 7.15 1.00 7.15 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 7.15 1.00 7.15 (A)
9999 Sundries L.S. 13.52 1.00 13.52 (A)
TOTAL 3913.17
Add for water charges @ 1 % on ‘A 14.23 (B)
TOTAL 3927.40
Add 15% for contractor’s profit and overheads 215.56
on (A+B)
Cost of one manhole 4142.96
Say 4142.96

19.30 Constructing brick masonry chamber for underground C.I. inspection chamber and bends with 75
class designation bricks in cement mortar 1:4 (1 cement : 4 coarse sand) C.I. cover with frame (light
duty) 455x610 mm internal dimensions, total weight of cover with frame to be not less than 38 kg
(weight of cover 23 kg and weight of frame 15 kg) R.C.C. top slab with 1:2:4 mix (1 cement :2 coarse
sand : 4 graded stone aggregate 20 mm nominal size) foundation concrete 1:5:10 (1 cement: 5 fine sand
: 10 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar
1:3 (1 cement: 3 coarse sand) finished smooth with a floating coat of neat cement on walls and bed
concrete etc. complete as per standard design :
19.30.3 Inside dimensions 600x 850 mm and 45 cm deep for pipe line with three or more inlets :
19.30.3.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one manhole
Cem ent concrete 1:5:10 (1 cement: 5 fine cum 0.26 2,719.53 707.08
sand : 10 graded stone aggregate 40 mm
nominal size) Rate as per item no 4.1.11 of
SH : Concrete

Brick work with 75 class designation brick cum 0.26 2329.20 605.59
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

RCC 1:2:4 ( 1 cement : 2 coarse sand : 4 cum 0.17 4269.75 725.86


graded stone aggregate 20 mm nominal size)
Rate as per item no. 5.3 of SH: concrete work

12mm cement plaster 1:3 (1 Cement: 3 sqm 1.34 132.57 177.64


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

Mild steel reinforcement for RCC work (Rate kg 8.17 58.65 479.21
as per item No.5.22.1
Form work Rate as per item no 5.9.2 of SH : sqm 0.91 475.79 432.97
RCC
1354 C.I. Cover with frame 455x610 mm (inside) each 1 1395.00 1395.00 (A)

9999 Carriage of C.I. C.I. cover & frame L.S. 7.15 1.00 7.15 (A)
9999 Painting of C.I. cover & frame with coal tar L.S. 7.15 1.00 7.15 (A)
9999 Sundries L.S. 13.52 1.00 13.52 (A)
TOTAL 4551.16
Add for water charges @ 1 % on ‘A 14.23 (B)
TOTAL 4565.39
Add 15% for contractor’s profit and overheads 215.56
on (A+B)
Cost of one manhole 4780.95
Say 4780.95

19.31 Extra for depth beyond 45 cm of brick masonry chamber :


19.31.1 For 455x610 mm size
19.31.1.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one metre
Brick work with 75 class designation brick cum 0.7 2329.20 1630.44
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work
12mm cement plaster 1:3 (1 Cement: 3 sqm 2.13 132.57 282.36
Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 1912.80
Cost of one metre 1912.80
Say 1912.80

19.31 Extra for depth beyond 45 cm of brick masonry chamber :


19.31.2 For 500x700 mm size
19.31.2.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one metre
Brick work with 75 class designation brick cum 0.76 2329.20 1770.19
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.4 132.57 318.16


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 2088.35
Cost of one metre 2088.35
Say 2088.35

19.31 Extra for depth beyond 45 cm of brick masonry chamber :


19.31.3 For 600x850 mm size
19.31.3.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost of one metre
Brick work with 75 class designation brick cum 0.88 2329.20 2049.69
in cement mortar 1:4(1 cement: 4 coarse
sand) Rate as per item no 6.1.1 of SH :
Brick Work

12mm cement plaster 1:3 (1 Cement: 3 sqm 2.9 132.57 384.44


Coarse sand) finished w ith a floating coat of
neat cement (Rate as per item no .13.9.1)

TOTAL 2434.13
Cost of one metre 2434.13
Say 2434.13

19.32 Making soak pit 2.5 m diameter 3.0 metre deep with 45 x 45 cm dry brick honey comb shaft with
bricks of class designation 75 and S.W. drain pipe 100 mm diameter, 1.8 m long complete as per
standard design.
19.32.1 With F.P.S. bricks
Code Description Unit Quantity Rate Amount
Details of cost for one soak pit
Materials :-
Earth work in excavation including refilling
and disposal of surplus earth
A (Rate as per item No. 2.8.1) cum 14.73 129.74 1911.07
A (Rate as per item No. 2.26.1) cum 7.37 30.08 221.69
Precast R.C.C.slabs 7.5 cm thick in cement cum 0.02 5710.65 114.21
concrete 1:2:4 (1 cement: 2 coarse sand : 4
graded stone aggregate 20 m m nominal
size) Rate as per item no 5.12 of SH : RCC
work

Mild steel reinforcement for RCC work (Rate kg 1.6 58.65 93.85
as per item No.5.22.1
2nd class brick edging laid length wise with metre 8.17 14.85 121.33
half brick depth. Rate as per item no. 16.8.1
2602 of SH bricks
F.P.S. : Roadclass
workdesignation75 000 N os 145 1600.00 232.00
362 Brick bats cum 2.74 253.00 693.22
285 Brick Aggregate (Single size) : 50-80 mm size cum 4.13 350.00 1445.50

287 Brick Aggregate (Single size) : 40 mm size cum 6.91 360.00 2487.60

1854 Stoneware pipes grade A (60 cm long) 100 each 3 30.00 90.00
mm dia
2260 Carriage of Brick aggregate cum 13.78 57.83 796.90
2201 Carriage of Brick 000 N os 145 141.88 20.57
9999 Single matting L.S. 112.14 1.00 112.14
Labour
114 Beldar Day 3 207 621.00
115 coolie Day 3 207 621.00
123 Mason 1st class Day 0.5 270 135.00
124 Mason 2nd class Day 0.5 223 111.50
TOTAL 9828.58
Add for water charges @ 1 % except on ‘A 73.66
TOTAL 9902.25
Add 15% for contractor’s profit and overheads 1116.01
except on A
Cost of one soak pit 11018.26
Say 11018.26

19.33 Constructing soak pit 1.20x1.20x1.20m filled with brickbats including S.W. drain pipe 100
mm diameter and 1.20 m long complete as per standard design.
Code Description Unit Quantity Rate Amount
Details of cost for one soak pit
Materials :-
Earth work in excavation including refilling
and disposal of surplus earth
A (Rate as per item No. 2.8.1) cum 1.73 129.74 224.45
2nd class brick edging laid length wise with metre 5.2 14.85 77.23
half brick depth. Rate as per item no. 16.8.1
of SH : Road work
362 Brick bats cum 1.73 253.00 437.69
1854 Stoneware pipes grade A (60 cm long) 100 each 2 30.00 60.00
mm dia
2260 Carriage of Brick aggregate cum 1.73 57.83 100.05
9999 Single matting L.S. 25.84 1.00 25.84
9999 Sundries L.S. 13.52 1.00 13.52
Labour
114 Beldar Day 0.5 207 103.50
TOTAL 1042.27
Add for water charges @ 1 % except on ‘A 7.41
TOTAL 1049.68
Add 15% for contractor’s profit and overheads 112.20
except on A
Cost of one soak pit 1161.88
Say 1161.88

19.34 Providing and fixing S.W. intercepting trap in manholes with stiff mixture of cement mortar 1:1 (1
cement: 1 fine sand) including testing of joints etc. complete :
19.34.1 100 mm dia
Code Description Unit Quantity Rate Amount
Details of cost of one no.
MATERIALS
7128 S.W intercepting trap 100 mm dia each 1 144.00 144.00
9999 Carriage of trap L.S 1.04 1.00 1.04
983 Fine sand cum 0.001 300.00 0.30
2261 Carriage of fine sand cum 0.001 53.21 0.05
367 Cement (0.1175 cum) tonne 0.0013 5200.00 6.76
2209 Carriage of cement 0.0013 47.29 0.06
1881 Spun yarn or plain gaskin kilogram 0.09 30.00 2.70
LABOUR

114 (B) Beldar Day 0.06 207 12.42


101 (B) Bhishti Day 0.02 180 3.60
123 (B) Mason 1st class Day 0.02 270 5.40
124 (B) Mason 2nd class Day 0.02 223 4.46
TOTAL 180.79
Add 1% for water charges 1.81
TOTAL 182.60
Add 15 % for contractor’s profit and overheads 27.39
Cost of 1 cum. 209.99
209.99

19.34 Providing and fixing S.W. intercepting trap in manholes with stiff mixture of cement mortar 1:1 (1
cement: 1 fine sand) including testing of joints etc. complete :
19.34.2 150 mm dia
Code Description Unit Quantity Rate Amount
Details of cost of one no.
MATERIALS
7129 S.W intercepting trap 150 mm dia each 1 202.00 202.00
9999 Carriage of trap L.S 2.08 1.00 2.08
983 Fine sand cum 0.0014 300.00 0.42
2261 Carriage of fine sand cum 0.0014 53.21 0.07
367 Cement (0.1175 cum) tonne 0.0019 5200.00 9.88
2209 Carriage of cement 0.0019 47.29 0.09
1881 Spun yarn or plain gaskin kilogram 0.18 30.00 5.40
LABOUR

114 (B) Beldar Day 0.08 207 16.56


101 (B) Bhishti Day 0.03 180 5.40
123 (B) Mason 1st class Day 0.03 270 8.10
124 (B) Mason 2nd class Day 0.03 223 6.69
TOTAL 256.69
Add 1% for water charges 2.57
TOTAL 259.26
Add 15 % for contractor’s profit and overheads 38.89
Cost of 1 cum. 298.15
298.15
20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):

20.1.1 400 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 2.51 4,772.99 11980.20
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 2.51 112.84 283.23
work
9,999 Sundries L.S. 521.08 1.00 521.08
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.36 20000 7200.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
LABOUR
130 Work supervisor (Mistri) Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 24965.11
Add 1% for water charges except on A 127.02

TOTAL 25092.13
Add for contractor’s profit and 1924.30
overheads @15% except on A
Cost of 20 metre of pile 27016.43
Cost of 1 metre of pile 1350.82
Say 1350.82

20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):

20.1.2 450 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 3.18 4,772.99 15178.10
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 3.18 112.84 358.83
work
9,999 Sundries L.S. 392.7 1.00 392.70
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.48 20000 9600.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
LABOUR
130 Work supervisor (Mistri) Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 30510.24
Add 1% for water charges except on A 149.73

TOTAL 30659.97
Add for contractor’s profit and 2268.45
overheads @15% except on A
Cost of 20 metre of pile 32928.43
Cost of 1 metre of pile 1646.42
Say 1646.42

20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):

20.1.3 500 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 3.925 4,772.99 18733.98
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 3.925 112.84 442.90
work
9,999 Sundries L.S. 530 1.00 530.00
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.6 20000 12000.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
LABOUR
130 Work supervisor (Mistri) Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 36687.48
Add 1% for water charges except on A 175.11

TOTAL 36862.59
Add for contractor’s profit and 2652.86
overheads @15% except on A
Cost of 20 metre of pile 39515.44
Cost of 1 metre of pile 1975.77
Say 1975.77

20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):

20.1.4 550 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 4.75 4,772.99 22671.70
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 4.75 112.84 536.00
work
9,999 Sundries L.S. 371.88 1.00 371.88
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.6 20000 12000.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
LABOUR
130 Work supervisor (Mistri) Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 40560.17
Add 1% for water charges except on A 173.52

TOTAL 40733.70
Add for contractor’s profit and 2628.90
overheads @15% except on A
Cost of 20 metre of pile 43362.60
Cost of 1 metre of pile 2168.13
Say 2168.13

20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):

20.1.5 750 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 15 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 6.62 4,772.99 31597.19
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 6.62 112.84 747.01
work
9,999 Sundries L.S. 573.57 1.00 573.57
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.7 20000 14000.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
LABOUR
130 Work supervisor (Mistri) Day 0.14 270 37.80
114 Beldar Day 3.5 207 724.50
TOTAL 52225.06
Add 1% for water charges except on A 198.81

TOTAL 52423.87
Add for contractor’s profit and 3011.95
overheads @15% except on A
Cost of 15 metre of pile 55435.82
Cost of 1 metre of pile 3695.72
Say 3695.72
20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):

20.1.6 1000 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 10 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 7.85 4,772.99 37467.96
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 7.85 112.84 885.80
work
9,999 Sundries L.S. 897.89 1.00 897.89
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.68 20000 13600.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
LABOUR
130 Work supervisor (Mistri) Day 0.16 270 43.20
114 Beldar Day 4 207 828.00
TOTAL 58267.85
Add 1% for water charges except on A 199.14

TOTAL 58467.00
Add for contractor’s profit and 3016.98
overheads @15% except on A
Cost of 10 metre of pile 61483.98
Cost of 1 metre of pile 6148.40
Say 6148.40

20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):
20.1.7 1200 mm dia piles.
Code Description Unit Quantity Rate Amount
Details of cost for 9 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 10.17 4,772.99 48541.30
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 10.17 112.84 1147.59
work
9,999 Sundries L.S. 733.37 1.00 733.37
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.67 20000 13400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
LABOUR
130 Work supervisor (Mistri) Day 0.18 270 48.60
114 Beldar Day 4.5 207 931.50
TOTAL 69347.36
Add 1% for water charges except on A 196.58

TOTAL 69543.94
Add for contractor’s profit and 2978.26
overheads @15% except on A
Cost of 9 metre of pile 72522.20
Cost of 1 metre of pile 8058.02
Say 8058.02

20.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified
diameter and length below the pile cap M 35 in cement concrete, to carry safe working load not less than
specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile
to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top
of shoe to the bottom of pile cap):

20.1.8 1500 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 9 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 15.9 4,772.99 75890.52
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 15.9 112.84 1794.17
work
9,999 Sundries L.S. 1113.48 1.00 1113.48
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. clamps for shoes @ 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.77 20000 15400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.1 2000 200.00
LABOUR
130 Work supervisor (Mistri) Day 0.2 270 54.00
114 Beldar Day 5 207 1035.00
TOTAL 99912.17
Add 1% for water charges except on A 222.27

TOTAL 100134.45
Add for contractor’s profit and 3367.46
overheads @15% except on A
Cost of 9 metre of pile 103501.91
Cost of 1 metre of pile 11500.21
Say 11500.21

20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.1 300 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 1.41 4,772.99 6729.91
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 1.41 112.84 159.11
work
9,999 Sundries L.S. 289.85 1.00 289.85
7183 Bentonite tonne 0.16 2700.00 432.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.36 20000 7200.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.38 3,000.00 1140.00
pump.
18 Hire and running charges of loader. hour 0.3 700 210.00
17 Hire and running charges of tipper hour 0.3 700 210.00
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 2 207 414.00
TOTAL 16937.27
Add 1% for water charges except on A 100.48

TOTAL 17037.75
Add for contractor’s profit and 1522.31
overheads @15% except on A
Cost of 20 metre of pile 18560.06
Cost of 1 metre of pile 928.00
Say 928.00

20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.2 400 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 2.51 4,772.99 11980.20
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 2.51 112.84 283.23
work
9,999 Sundries L.S. 79.06 1.00 79.06
7183 Bentonite tonne 0.225 2700.00 607.50
MACHINERY
24 Hire and running charges of hydraulic hour 0.36 20000 7200.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.38 3,000.00 1140.00
pump.
18 Hire and running charges of loader. hour 0.3 700 210.00
17 Hire and running charges of tipper hour 0.3 700 210.00
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 2 207 414.00
TOTAL 22276.39
Add 1% for water charges except on A 100.13

TOTAL 22376.52
Add for contractor’s profit and 1516.96
overheads @15% except on A
Cost of 20 metre of pile 23893.49
Cost of 1 metre of pile 1194.67
Say 1194.67

20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.3 450 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 3.18 4,772.99 15178.10
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 3.18 112.84 358.83
work
9,999 Sundries L.S. 230.69 1.00 230.69
7183 Bentonite tonne 0.25 2700.00 675.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.47 20000 9400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.63 2000 1260.00
26 Hire and running charges of bentonite hour 0.38 3,000.00 1140.00
pump.
18 Hire and running charges of loader. hour 0.3 700 210.00
17 Hire and running charges of tipper hour 0.3 700 210.00
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 2.5 207 517.50
TOTAL 29212.53
Add 1% for water charges except on A 136.76

TOTAL 29349.28
Add for contractor’s profit and 2071.85
overheads @15% except on A
Cost of 20 metre of pile 31421.14
Cost of 1 metre of pile 1571.06
Say 1571.06
20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.4 500 mm dia. piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 3.925 4,772.99 18733.98
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 3.925 112.84 442.90
work
9,999 Sundries L.S. 87.95 1.00 87.95
7183 Bentonite tonne 0.28 2700.00 756.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.6 20000 12000.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.38 3,000.00 1140.00
pump.
18 Hire and running charges of loader. hour 0.3 700 210.00
17 Hire and running charges of tipper hour 0.3 700 210.00
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 2.5 207 517.50
TOTAL 34250.73
Add 1% for water charges except on A 150.74

TOTAL 34401.47
Add for contractor’s profit and 2283.69
overheads @15% except on A
Cost of 20 metre of pile 36685.16
Cost of 1 metre of pile 1834.26
Say 1834.26
20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.5 600 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 5.65 4,772.99 26967.39
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 5.65 112.84 637.55
work
9,999 Sundries L.S. 317.43 1.00 317.43
7183 Bentonite tonne 0.33 2700.00 891.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.75 20000 15000.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.38 3,000.00 1140.00
pump.
18 Hire and running charges of loader. hour 0.3 700 210.00
17 Hire and running charges of tipper hour 0.3 700 210.00
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 3 207 621.00
TOTAL 46146.77
Add 1% for water charges except on A 185.42

TOTAL 46332.19
Add for contractor’s profit and 2809.09
overheads @15% except on A
Cost of 20 metre of pile 49141.27
Cost of 1 metre of pile 2457.06
Say 2457.06
20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.6 750 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 15 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 6.62 4,772.99 31597.19
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 6.62 112.84 747.01
work
9,999 Sundries L.S. 131.58 1.00 131.58
7183 Bentonite tonne 0.3 2700.00 810.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.7 20000 14000.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.75 3,000.00 2250.00
pump.
18 Hire and running charges of loader. hour 0.3 700 210.00
17 Hire and running charges of tipper hour 0.3 700 210.00
LABOUR
130 Work supervisor Day 0.14 270 37.80
114 Beldar Day 3.5 207 724.50
TOTAL 50838.07
Add 1% for water charges except on A 184.94

TOTAL 51023.01
Add for contractor’s profit and 2801.82
overheads @15% except on A
Cost of 15 metre of pile 53824.84
Cost of 1 metre of pile 3588.32
Say 3588.32
20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.7 1000 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 10 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 7.85 4,772.99 37467.96
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 7.85 112.84 885.80
work
9,999 Sundries L.S. 175.89 1.00 175.89
7183 Bentonite tonne 0.35 2700.00 945.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.69 20000 13800.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.75 3,000.00 2250.00
pump.
18 Hire and running charges of loader. hour 0.4 700 280.00
17 Hire and running charges of tipper hour 0.4 700 280.00
LABOUR
130 Work supervisor Day 0.16 270 43.20
114 Beldar Day 4 207 828.00
TOTAL 57075.85
Add 1% for water charges except on A 187.22

TOTAL 57263.08
Add for contractor’s profit and 2836.40
overheads @15% except on A
Cost of 10 metre of pile 60099.47
Cost of 1 metre of pile 6009.95
Say 6009.95
20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.8 1200 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 9 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 10.17 4,772.99 48541.30
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 10.17 112.84 1147.59
work
9,999 Sundries L.S. 290.79 1.00 290.79
7183 Bentonite tonne 0.385 2700.00 1039.50
MACHINERY
24 Hire and running charges of hydraulic hour 0.67 20000 13400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.75 3,000.00 2250.00
pump.
18 Hire and running charges of loader. hour 0.5 700 350.00
17 Hire and running charges of tipper hour 0.5 700 350.00
LABOUR
130 Work supervisor Day 0.18 270 48.60
114 Beldar Day 4.5 207 931.50
TOTAL 68469.28
Add 1% for water charges except on A 187.80

TOTAL 68657.08
Add for contractor’s profit and 2845.23
overheads @15% except on A
Cost of 9 metre of pile 71502.31
Cost of 1 metre of pile 7944.70
Say 7944.70
20.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified
diameter and length below the pile cap M 35 in cement concrete, to carry a safe working load not less
than specified, excluding the cost of steel reinforcement but including the cost of boring with,
bentonite solution and temporary casing of appropriate length for setting out and removal of same and
the length of the pile to be embedded in the pile cap etc. all earth with all lifts and leads (Length of pile
for payment shall be measured uptocomplete, including removal of excavated bottom of pile cap).

20.2.9 1500 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 9 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 15.9 4,772.99 75890.52
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 15.9 112.84 1794.17
work
9,999 Sundries L.S. 593.48 1.00 593.48
7183 Bentonite tonne 0.45 2700.00 1215.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.77 20000 15400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.1 2000 200.00
26 Hire and running charges of bentonite hour 0.9 3,000.00 2700.00
pump.
18 Hire and running charges of loader. hour 0.75 700 525.00
17 Hire and running charges of tipper hour 0.75 700 525.00
LABOUR
130 Work supervisor Day 0.25 270 67.50
114 Beldar Day 5 207 1035.00
TOTAL 99945.67
Add 1% for water charges except on A 222.61

TOTAL 100168.28
Add for contractor’s profit and 3372.54
overheads @15% except on A
Cost of 9 metre of pile 103540.82
Cost of 1 metre of pile 11504.54
Say 11504.54

20.3 Boring, Providing and installing cast in situ single under reamed piles of specified diameter and
length below pile cap in M 35 cement concrete, to carry a safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the
length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be
measured upto the bottom of pile cap):
20.3.1 300 mm dia piles.
Code Description Unit Quantity Rate Amount
Details of cost for 10 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 0.778 4,772.99 3713.39
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 0.778 112.84 87.79
work
9,999 Sundries L.S. 410.92 1.00 410.92
7183 Bentonite tonne 0.08 2700.00 216.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.36 20000 7200.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.03 2000 60.00
26 Hire and running charges of bentonite hour 0.02 3,000.00 60.00
pump.
LABOUR
130 Work supervisor Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 12183.70
Add 1% for water charges except on A 83.83

TOTAL 12267.52
Add for contractor’s profit and 1269.95
overheads @15% except on A
Cost of 10 metre of pile 13537.47
Cost of 1 metre of pile 1353.75
Say 1353.75

20.3 Boring, Providing and installing cast in situ single under reamed piles of specified diameter and
length below pile cap in M 35 cement concrete, to carry a safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the
length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be
measured upto the bottom of pile cap):

20.3.2 400 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 10 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 1.478 4,772.99 7054.48
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 1.478 112.84 166.78
work
9,999 Sundries L.S. 276.82 1.00 276.82
7183 Bentonite tonne 0.15 2700.00 405.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.36 20000 7200.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.02 3,000.00 60.00
pump.
LABOUR
130 Work supervisor Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 15718.68
Add 1% for water charges except on A 84.97

TOTAL 15803.65
Add for contractor’s profit and 1287.36
overheads @15% except on A
Cost of 10 metre of pile 17091.01
Cost of 1 metre of pile 1709.10
Say 1709.10

20.3 Boring, Providing and installing cast in situ single under reamed piles of specified diameter and
length below pile cap in M 35 cement concrete, to carry a safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the
length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be
measured upto the bottom of pile cap):

20.3.3 450 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 10 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 1.906 4,772.99 9097.32
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 1.906 112.84 215.08
work
9,999 Sundries L.S. 194.81 1.00 194.81
7183 Bentonite tonne 0.19 2700.00 513.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.36 20000 7200.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.02 3,000.00 60.00
pump.
LABOUR
130 Work supervisor Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 17835.80
Add 1% for water charges except on A 85.23

TOTAL 17921.04
Add for contractor’s profit and 1291.30
overheads @15% except on A
Cost of 10 metre of pile 19212.33
Cost of 1 metre of pile 1921.23
Say 1921.23

20.3 Boring, Providing and installing cast in situ single under reamed piles of specified diameter and
length below pile cap in M 35 cement concrete, to carry a safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the
length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be
measured upto the bottom of pile cap):

20.3.4 550 mm dia piles


Code Description Unit Quantity Rate Amount
Details of cost for 10 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 2.4 4,772.99 11455.17
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 2.4 112.84 270.82
work
9,999 Sundries L.S. 208.15 1.00 208.15
7183 Bentonite tonne 0.2 2700.00 540.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.36 20000 7200.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.06 2000 120.00
26 Hire and running charges of bentonite hour 0.02 3,000.00 60.00
pump.
LABOUR
130 Work supervisor Day 0.08 270 21.60
114 Beldar Day 2 207 414.00
TOTAL 20289.74
Add 1% for water charges except on A 85.64

TOTAL 20375.38
Add for contractor’s profit and 1297.41
overheads @15% except on A
Cost of 10 metre of pile 21672.79
Cost of 1 metre of pile 2167.28
Say 2167.28

20.4 Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified
diameter (Only the quantity of extra bulbs are to be paid).
20.4.1 300mm dia piles.
Code Description Unit Quantity Rate Amount
Details of cost for 1 bulb
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 0.033 4,772.99 157.51
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 0.033 112.84 3.72
work
7183 Bentonite tonne 0.003 2700.00 8.10
MACHINERY
24 Hire and running charges of hydraulic hour 0.02 20000 400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.01 2000 20.00
26 Hire and running charges of bentonite hour 0.01 3,000.00 30.00
pump.
LABOUR
130 Work supervisor Day 0.02 270 5.40
114 Beldar Day 1 207 207.00
TOTAL 831.73
Add 1% for water charges except on A 6.71

TOTAL 838.44
Add for contractor’s profit and 101.58
overheads @15% except on A
Cost of 1 bulb 940.02
Say 940.02

20.4 Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified
diameter (Only the quantity of extra bulbs are to be paid).
20.4.2 400mm dia piles.
Code Description Unit Quantity Rate Amount
Details of cost for 1 bulb
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 0.063 4,772.99 300.70
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 0.063 112.84 7.11
work
7183 Bentonite tonne 0.006 2700.00 16.20
MACHINERY
24 Hire and running charges of hydraulic hour 0.02 20000 400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.01 2000 20.00
26 Hire and running charges of bentonite hour 0.01 3,000.00 30.00
pump.
LABOUR
130 Work supervisor Day 0.02 270 5.40
114 Beldar Day 1 207 207.00
TOTAL 986.41
Add 1% for water charges except on A 6.79

TOTAL 993.19
Add for contractor’s profit and 102.81
overheads @15% except on A
Cost of 1 bulb 1096.00
Say 1096.00

20.4 Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified
diameter (Only the quantity of extra bulbs are to be paid).
20.4.3 450 mm dia piles.
Code Description Unit Quantity Rate Amount
Details of cost for 1 bulb
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 0.081 4,772.99 386.61
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 0.081 112.84 9.14
work
7183 Bentonite tonne 0.008 2700.00 21.60
MACHINERY
24 Hire and running charges of hydraulic hour 0.02 20000 400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.01 2000 20.00
26 Hire and running charges of bentonite hour 0.01 3,000.00 30.00
pump.
LABOUR
130 Work supervisor Day 0.02 270 5.40
114 Beldar Day 1 207 207.00
TOTAL 1079.75
Add 1% for water charges except on A 6.84

TOTAL 1086.59
Add for contractor’s profit and 103.63
overheads @15% except on A
Cost of 1 bulb 1190.22
Say 1190.22

20.4 Extra over item No. 20.3 for providing additional bulb in under reamed piles, under specified
diameter (Only the quantity of extra bulbs are to be paid).
20.4.4 550 mm dia piles.
Code Description Unit Quantity Rate Amount
Details of cost for 1 bulb
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 0.102 4,772.99 486.84
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 0.102 112.84 11.51
work
7183 Bentonite tonne 0.01 2700.00 27.00
MACHINERY
24 Hire and running charges of hydraulic hour 0.02 20000 400.00
piling rig with power unit etc. including
complete accessories and shifting at site.

25 Hire and running charges of light crane. hour 0.01 2000 20.00
26 Hire and running charges of bentonite hour 0.02 3,000.00 60.00
pump.
LABOUR
130 Work supervisor Day 0.02 270 5.40
114 Beldar Day 1 207 207.00
TOTAL 1217.75
Add 1% for water charges except on A 7.19

TOTAL 1224.95
Add for contractor’s profit and 108.99
overheads @15% except on A
Cost of 1 bulb 1333.94
Say 1333.94
20.5 Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified
diameter and length below the pile cap in M 35 cement concrete to carry safe working load not less than
specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with
cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure
complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting
casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be
measured from top of the shoe to the bottom of pile cap).

20.5.1 400 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 2.51 4,772.99 11980.20
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 2.51 112.84 283.23
work
(A) Rate as per Item No 5.19 S.H.: R.C.C. cum 2.51 7,550.75 18952.38
(A) work
Deduct Rate as per Item No 5.1.3 S.H.: cum -2.51 4,090.88 -10268.11
R.C.C. work
Cement mortar 1:2 for grout(Rate as per cum 0.025 4,111.99 102.80
item3.7)
9,999 Sundries L.S. 442 1.00 442.00
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. shoes® 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
27 Hire and running charges of vibrating hour 0.38 20000 7600.00
pile driving hammer complete with power
unit and acces sories.

28 Hire and running charges of crane 20 hour 0.06 8,000.00 480.00


tonne capacity.
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 3 207 621.00
TOTAL 34650.90
Add 1% for water charges except on A 137.03

TOTAL 34787.93
Add for contractor’s profit and 2076.03
overheads @15% except on A
Cost of 20 metre of pile 36863.97
Cost of 1 metre of pile 1843.20
Say 1843.20
20.5 Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified
diameter and length below the pile cap in M 35 cement concrete to carry safe working load not less than
specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with
cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure
complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting
casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be
measured from top of the shoe to the bottom of pile cap).

20.5.2 450 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 3.18 4,772.99 15178.10
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 3.18 112.84 358.83
work
(A) Rate as per Item No 5.19 S.H.: R.C.C. cum 3.18 7,550.75 24011.39
work
(A) Deduct Rate as per Item No 5.1.3 S.H.: cum -3.18 4,090.88 -13009.01
R.C.C. work
Cement mortar 1:2 for grout(Rate as per cum 0.025 4,111.99 102.80
item3.7)
9,999 Sundries L.S. 442 1.00 442.00
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. shoes® 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
27 Hire and running charges of vibrating hour 0.38 20000 7600.00
pile driving hammer complete with power
unit and acces sories.

28 Hire and running charges of crane 20 hour 0.06 8,000.00 480.00


tonne capacity.
LABOUR
130 Work supervisor Day 1.08 270 291.60
114 Beldar Day 10.78 207 2231.46
TOTAL 42112.18
Add 1% for water charges except on A 155.73

TOTAL 42267.91
Add for contractor’s profit and 2359.29
overheads @15% except on A
Cost of 20 metre of pile 44627.20
Cost of 1 metre of pile 2231.36
Say 2231.36
20.5 Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified
diameter and length below the pile cap in M 35 cement concrete to carry safe working load not less than
specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with
cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure
complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting
casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be
measured from top of the shoe to the bottom of pile cap).

20.5.3 500 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 3.925 4,772.99 18733.98
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 3.925 112.84 442.90
work
(A) Rate as per Item No 5.19 S.H.: R.C.C. cum 3.925 7,550.75 29636.69
(A) work
Deduct Rate as per Item No 5.1.3 S.H.: cum -3.925 4,090.88 -16056.71
R.C.C. work
Cement mortar 1:2 for grout(Rate as per cum 0.025 4,111.99 102.80
item3.7)
9,999 Sundries L.S. 442 1.00 442.00
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. shoes® 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
27 Hire and running charges of vibrating hour 0.38 20000 7600.00
pile driving hammer complete with power
unit and acces sories.

28 Hire and running charges of crane 20 hour 0.06 8,000.00 480.00


tonne capacity.
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 3 207 621.00
TOTAL 46460.06
Add 1% for water charges except on A 137.03

TOTAL 46597.10
Add for contractor’s profit and 2076.03
overheads @15% except on A
Cost of 20 metre of pile 48673.13
Cost of 1 metre of pile 2433.66
Say 2433.66
20.5 Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified
diameter and length below the pile cap in M 35 cement concrete to carry safe working load not less than
specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with
cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure
complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting
casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be
measured from top of the shoe to the bottom of pile cap).

20.5.4 550 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 4.75 4,772.99 22671.70
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 4.75 112.84 536.00
work
(A) Rate as per Item No 5.19 S.H.: R.C.C. cum 4.75 7,550.75 35866.06
work
(A) Deduct Rate as per Item No 5.1.3 S.H.: cum -4.75 4,090.88 -19431.69
R.C.C. work
Cement mortar 1:2 for grout(Rate as per cum 0.025 4,111.99 102.80
item3.7)
9,999 Sundries L.S. 442 1.00 442.00
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. shoes® 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
27 Hire and running charges of vibrating hour 0.38 20000 7600.00
pile driving hammer complete with power
unit and acces sories.

28 Hire and running charges of crane 20 hour 0.06 8,000.00 480.00


tonne capacity.
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 3 207 621.00
TOTAL 53345.26
Add 1% for water charges except on A 137.03

TOTAL 53482.30
Add for contractor’s profit and 2076.03
overheads @15% except on A
Cost of 20 metre of pile 55558.33
Cost of 1 metre of pile 2777.92
Say 2777.92
20.5 Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified
diameter and length below the pile cap in M 35 cement concrete to carry safe working load not less than
specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with
cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure
complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting
casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be
measured from top of the shoe to the bottom of pile cap).

20.5.5 750 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 10.88 4,772.99 51930.12
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 10.88 112.84 1227.71
work
(A) Rate as per Item No 5.19 S.H.: R.C.C. cum 10.88 7,550.75 82152.16
(A) work
Deduct Rate as per Item No 5.1.3 S.H.: cum -10.88 4,090.88 -44508.80
R.C.C. work
Cement mortar 1:2 for grout(Rate as per cum 0.025 4,111.99 102.80
item3.7)
9,999 Sundries L.S. 442 1.00 442.00
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. shoes® 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
27 Hire and running charges of vibrating hour 0.38 20000 7600.00
pile driving hammer complete with power
unit and acces sories.

28 Hire and running charges of crane 20 hour 0.06 8,000.00 480.00


tonne capacity.
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 3 207 621.00
TOTAL 104504.39
Add 1% for water charges except on A 137.03

TOTAL 104641.42
Add for contractor’s profit and 2076.03
overheads @15% except on A
Cost of 20 metre of pile 106717.46
Cost of 1 metre of pile 5335.87
Say 5335.87
20.5 Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified
diameter and length below the pile cap in M 35 cement concrete to carry safe working load not less than
specified. With a central through preformed hole with M.S. black pipe of dia 40mm for grouting with
cement sand grouting of mix 1:2(1 cement: 2 coarse sand) under sufficient positive pressure to ensure
complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting
casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be
measured from top of the shoe to the bottom of pile cap).

20.5.6 1000 mm dia piles.


Code Description Unit Quantity Rate Amount
Details of cost for 20 m length of pile
MATERIAL
(A) Concrete Rate as per item No. 5.33 of SH : cum 15.7 4,772.99 74935.92
RCC work
(A) Rate as per Item No 5.34.2 S.H.: R.C.C. cum 15.7 112.84 1771.61
work
(A) Rate as per Item No 5.19 S.H.: R.C.C. cum 15.7 7,550.75 118546.78
(A) work
Deduct Rate as per Item No 5.1.3 S.H.: cum -15.7 4,090.88 -64226.85
R.C.C. work
Cement mortar 1:2 for grout(Rate as per cum 0.025 4,111.99 102.80
item3.7)
9,999 Sundries L.S. 442 1.00 442.00
7181 C.I. Shoes @ 80 kg per pile kilogram 80 40.00 3200.00
7182 M.S. shoes® 35 kg per pile kilogram 35 35.00 1225.00
MACHINERY
27 Hire and running charges of vibrating hour 0.38 20000 7600.00
pile driving hammer complete with power
unit and acces sories.

28 Hire and running charges of crane 20 hour 0.06 8,000.00 480.00


tonne capacity.
LABOUR
130 Work supervisor Day 0.12 270 32.40
114 Beldar Day 3 207 621.00
TOTAL 144730.66
Add 1% for water charges except on A 137.03

TOTAL 144867.69
Add for contractor’s profit and 2076.03
overheads @15% except on A
Cost of 20 metre of pile 146943.72
Cost of 1 metre of pile 7347.19
Say 7347.19
20.6 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of
loading platform and preparation of pile head or construction of test cap and dismantling of test cap after
test etc. complete as per specification & the direction of Engineer in-charge.
20.6.1 Single pile upto 50 tonne capacity
20.6.1.1 Initial test.
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7246 Cost per test Per test 1 19500.00 19500.00
TOTAL 19500.00
Add 1% for water charges 195.00
TOTAL 19695.00
Add for contractor’s profit and 2954.25
overheads @15%
Cost of per test 22649.25
Say 22649.25

20.6 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of
loading platform and preparation of pile head or construction of test cap and dismantling of test cap after
test etc. complete as per specification & the direction of Engineer in-charge.
20.6.1 Single pile upto 50 tonne capacity
20.6.1.2 Routine test
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7249 Cyclic verticle load testing of piles in Per test 1 11500.00 11500.00
accordance with IS : 2911 (Part-IV)
including prepration of pile head etc. for
Single pile upto 50 tonne capacity

TOTAL 11500.00
Add 1% for water charges 115.00
TOTAL 11615.00
Add for contractor’s profit and 1742.25
overheads @15%
Cost of per test 13357.25
Say 13357.25

20.6 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of
loading platform and preparation of pile head or construction of test cap and dismantling of test cap after
test etc. complete as per specification & the direction of Engineer in-charge.
20.6.2 Single pile above 50 tonne and upto 100 tonne capacity
20.6.2.1Initial test
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7247 Vertical load testing (INITIAL) of piles in Per test 1 27500.00 27500.00
accordance with IS : 2911 (Part - IV)
including installation of loading platform
and preparation of pile head or
construction of test cap and dismantling
of test cap after test etc. complete as per
specification & above 50MT and up to
100 MT

TOTAL 27500.00
Add 1% for water charges 275.00
TOTAL 27775.00
Add for contractor’s profit and 4166.25
overheads @15%
Cost of per test 31941.25
Say 31941.25

20.6 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of
loading platform and preparation of pile head or construction of test cap and dismantling of test cap after
test etc. complete as per specification & the direction of Engineer in-charge.
20.6.2 Single pile above 50 tonne and upto 100 tonne capacity
20.6.2.2 Routine test.
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7250 Cyclic vertical load testing of piles in Per test 1 18000.00 18000.00
accordance with IS : 2911 (Part -IV)
including preparation of pile head etc. for
Single pile above 50 and up to 100 tonne
capacity

TOTAL 18000.00
Add 1% for water charges 180.00
TOTAL 18180.00
Add for contractor’s profit and 2727.00
overheads @15%
Cost of per test 20907.00
Say 20907.00

20.6 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of
loading platform and preparation of pile head or construction of test cap and dismantling of test cap after
test etc. complete as per specification & the direction of Engineer in-charge.
20.6.3 Group of two or more piles upto 50 tonne capacity
20.6.3.1 Initial test
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7248 Vertical load testing (INITIAL) of piles in Per test 1 37500.00 37500.00
accordance with IS : 2911 (Part - IV)
including installation of loading platform
and preparation of pile head or
construction of test cap and dismantling
of test cap after test etc. complete as per
specification & group of two or more up
to 50 MT

TOTAL 37500.00
Add 1% for water charges 375.00
TOTAL 37875.00
Add for contractor’s profit and 5681.25
overheads @15%
Cost of per test 43556.25
Say 43556.25

20.6 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of
loading platform and preparation of pile head or construction of test cap and dismantling of test cap after
test etc. complete as per specification & the direction of Engineer in-charge.
20.6.3 Group of two or more piles upto 50 tonne capacity
20.6.3.2 Routine test
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7251 Cyclic vertical load testing of piles in Per test 1 23000.00 23000.00
accordance with IS : 2911 (Part-IV)
including preparation of pile head etc. for
Group of two piles up to 50 tonne
capacity each

TOTAL 23000.00
Add 1% for water charges 230.00
TOTAL 23230.00
Add for contractor’s profit and 3484.50
overheads @15%
Cost of per test 26714.50
Say 26714.50

20.7 Cyclic vertical load testing of pile in accordance with IS C ode of practice IS : 2911 (part IV)
including preparation of pile head etc for.
20.7.1 Single pile.
20.7.1.1 Upto 50 tonne capacity pile.
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7249 Cyclic vertical load testing of piles in Per test 1 11500.00 11500.00
accordance with IS : 2911 (Part -IV)
including preparation of pile head etc. for
Single pile up to 50 tonne capacity

TOTAL 11500.00
Add 1% for water charges 115.00
TOTAL 11615.00
Add for contractor’s profit and 1742.25
overheads @15%
Cost of per test 13357.25
Say 13357.25

20.7 Cyclic vertical load testing of pile in accordance with IS C ode of practice IS : 2911 (part IV)
including preparation of pile head etc for.
20.7.1 Single pile.
20.7.1.2 Above 50 tonne and upto 100 tonne capacity pile.
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7250 Cyclic vertical load testing of piles in Per test 1 18000.00 18000.00
accordance with IS : 2911 (Part -IV)
including preparation of pile head etc. for
Single pile above 50 and up to 100 tonne
capacity

TOTAL 18000.00
Add 1% for water charges 180.00
TOTAL 18180.00
Add for contractor’s profit and 2727.00
overheads @15%
Cost of per test 20907.00
Say 20907.00

20.7 Cyclic vertical load testing of pile in accordance with IS C ode of practice IS : 2911 (part IV)
including preparation of pile head etc for.
20.7.2 Group of two piles.
20.7.2.1 Upto 50 tonne capacity each .
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7251 Cyclic vertical load testing of piles in Per test 1 23000.00 23000.00
accordance with IS : 2911 (Part-IV)
including preparation of pile head etc. for
Group of two piles up to 50 tonne
capacity each

TOTAL 23000.00
Add 1% for water charges 230.00
TOTAL 23230.00
Add for contractor’s profit and 3484.50
overheads @15%
Cost of per test 26714.50
Say 26714.50

20.8 Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for
determining safe allowable lateral load on pile :
20.8.1 Upto 50 tonne capacity pile.
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7252 Lateral load testing of single pile in Per test 1 11500.00 11500.00
accordance with IS : 2911 (Part -IV) for
determining safe allowable lateral load on
pile. Up to 50 tonne capacity

TOTAL 11500.00
Add 1% for water charges 115.00
TOTAL 11615.00
Add for contractor’s profit and 1742.25
overheads @15%
Cost of per test 13357.25
Say 13357.25

20.8 Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for
determining safe allowable lateral load on pile :
20.8.2 Above 50 tonne and upto 100 tonne capacity pile.
Code Description Unit Quantity Rate Amount
Details of cost for 1 test
7253 Lateral load testing of single pile in Per test 1 18000.00 18000.00
accordance with IS : 2911 (Part -IV) for
determining safe allowable lateral load on
pile. Above 50 tonne capacity

TOTAL 18000.00
Add 1% for water charges 180.00
TOTAL 18180.00
Add for contractor’s profit and 2727.00
overheads @15%
Cost of per test 20907.00
Say 20907.00
21.1 Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded
built up standard tubular sections/ appropriate Z sections and other sections of approved make
conforming to IS: 733 and IS : 1285, fixed with rawl plugs and screws or with fixing clips, or with
expansion hold fasteners including necessary filling up of gaps at junctions, at top, bottom and sides
with required PVC/neoprene felt etc. Aluminium sections shall be smooth, rust free, straight, mitred and
jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing /
panelling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the
directions of Engineer-in-charge. (Glazing and panelling to be paid for separately):

21.1.1 For fixed portion.


21.1.1.1 Anodised aluminium (anodised transparent or dyed to required shade according to IS: 1868,
Minimum anodic coating of grade AC 15)
Code Description Unit Quantity Rate Amount
Details of cost for 40.02 kg
MATERIAL :
7306 Aluminium T or L sections kilogram 42.02 195.00 8193.90
589 C.P. brass /stainless steel screws 20 mm 100 Nos. 72 63.00 45.36
7019 Dash hold fastners each 12 8.00 96.00
7389 Anodising 15 microns on aluminium kilogram 42.02 32.00 1344.64
sections
9999 Carriage of material L.S. 52 1.00 52.00
LABOUR For fabrication of frame
116 Fitter Day 0.62 270 167.40
139 Beldar (Special) Day 0.54 180 97.20
114 Beldar Day 0.36 207.00 74.52
100 Bandhani Day 0.04 180.00 7.20
9999 Labour for drilling holes, hire charges of L.S. 52
drill, electricity charges, carriage of dash
hold fastners & sundries
1.00 52.00
TOTAL 10130.22
Add 1% for water charges 101.30
TOTAL 10231.52
Add for contractor’s profit and overheads
@15% 1534.73
Cost of 40.02 kg 11766.25
Cost of 1 kg 294.01
Say 294.01

21.1 Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded
built up standard tubular sections/ appropriate Z sections and other sections of approved make
conforming to IS: 733 and IS : 1285, fixed with rawl plugs and screws or with fixing clips, or with
expansion hold fasteners including necessary filling up of gaps at junctions, at top, bottom and sides
with required PVC/neoprene felt etc. Aluminium sections shall be smooth, rust free, straight, mitred and
jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing /
panelling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the
directions of Engineer-in-charge. (Glazing and panelling to be paid for separately):
2l.1.1 For fixed portion.
2.1.1.2 Powder coated aluminium (minimum thickness of powder coating 50 micron)
Code Description Unit Quantity Rate Amount
Details of cost for 40.02 kg
MATERIAL :
7306 Aluminium T or L sections kilogram 42.02 195.00 8193.90
589 C.P. brass /stainless steel screws 20 mm 100 Nos. 72 63.00 45.36
7019 Dash hold fastners each 12 8.00 96.00
7392 Powder coating 50 microns on aluminium
sections. kilogram 42.02 45.00 1890.90
9999 Carriage of material L.S. 52 1.00 52.00
LABOUR For fabrication of frame
116 Fitter Day 0.62 270 167.40
139 Beldar (Special) Day 0.54 180 97.20
114 Beldar Day 0.36 207.00 74.52
100 Bandhani Day 0.04 180.00 7.20
9999 Labour for drilling holes, hire charges of L.S. 52
drill, electricity charges, carriage of dash
hold fastners & sundries
1.00 52.00
TOTAL 10676.48
Add 1% for water charges 106.76
TOTAL 10783.24
Add for contractor’s profit and overheads
@15% 1617.49
Cost of 40.02 kg 12400.73
Cost of 1 kg 309.86
Say 309.86

21.1 Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded
built up standard tubular sections/ appropriate Z sections and other sections of approved make
conforming to IS: 733 and IS : 1285, fixed with rawl plugs and screws or with fixing clips, or with
expansion hold fasteners including necessary filling up of gaps at junctions, at top, bottom and sides
with required PVC/neoprene felt etc. Aluminium sections shall be smooth, rust free, straight, mitred and
jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing /
panelling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the
directions of Engineer-in-charge. (Glazing and panelling to be paid for separately):

21.1.1 For fixed portion.


21.1.1.3 Polyester powder coated aluminium (minimum thickness of polyester powder coating 50
micron)
Code Description Unit Quantity Rate Amount
Details of cost for 40.02 kg
MATERIAL :
7306 Aluminium T or L sections kilogram 42.02 195.00 8193.90
589 C.P. brass /stainless steel screws 20 mm 100 Nos. 72 63.00 45.36
7019 Dash hold fastners each 12 8.00 96.00
7393 Polyester powder coating 50 m icrons on
aluminium sections kilogram 42.02 50.00 2101.00
9999 Carriage of material L.S. 52 1.00 52.00
LABOUR For fabrication of frame
116 Fitter Day 0.62 270 167.40
139 Beldar (Special) Day 0.54 180 97.20
114 Beldar Day 0.36 207.00 74.52
100 Bandhani Day 0.04 180.00 7.20
9999 Labour for drilling holes, hire charges of L.S. 52
drill, electricity charges, carriage of dash
hold fastners & sundries
1.00 52.00
TOTAL 10886.58
Add 1% for water charges 108.87
TOTAL 10995.45
Add for contractor’s profit and overheads
@15% 1649.32
Cost of 40.02 kg 12644.76
Cost of 1 kg 315.96
Say 315.96

21.1 Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded
built up standard tubular sections/ appropriate Z sections and other sections of approved make
conforming to IS: 733 and IS : 1285, fixed with rawl plugs and screws or with fixing clips, or with
expansion hold fasteners including necessary filling up of gaps at junctions, at top, bottom and sides
with required PVC/neoprene felt etc. Aluminium sections shall be smooth, rust free, straight, mitred and
jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing /
panelling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the
directions of Engineer-in-charge. (Glazing and panelling to be paid for separately):

21.1.2 For shutters of doors, windows & ventilators including providing and fixing hinges/pivots and
making provision for fixing of fittings wherever required including the cost of PVC / neoprene gasket
required (Fittings shall be paid for separately).
21.1.2.1 Anodised aluminium (anodised transparent or dyed to required shade according
Code Description Unit Quantity Rate Amount
Details of cost for 20.212 kg
7306 Aluminium T or L sections kilogram 21.65 223.80 4845.27
689 Alum inium hinges 100x75x4 mm 10 Nos. 4 416.00 166.40
589 C.P. brass /stainless steel screws 20 mm 100 Nos. 92 63.00 57.96
7392 Powder coating 50 microns on aluminium
sections. kilogram 21.65 45.00 974.25
7390 Neoprene/ PVC gasket in groove of
meeting style metre 2.35 22.00 51.70
9999 Carriage of material L.S. 31.2 1.00 31.20
116 Fitter Day 0.32 168 53.76
139 Beldar (Special) Day 0.28 111 31.08
114 Beldar Day 0.18 92.00 16.56
100 Bandhani Day 0.20 111.00 22.20
111 Carpenter 1st class Day 0.06 168.00 10.08
114 Beldar Day 0.04 92.00 3.68
9999 Labour for making provision for fittings L.S. 26
and carriage of screws etc. including
sundries
1.00 26.00
TOTAL 6290.14
Add 1% for water charges 62.90
TOTAL 6353.04
Add for contractor’s profit and overheads
@15% 952.96
Cost of 20.21 kg 7306.00
Cost of 1 kg 361.50
Say 361.50

21.1 Providing and fixing aluminium work for doors, windows, ventilators and partitions with extruded
built up standard tubular sections/ appropriate Z sections and other sections of approved make
conforming to IS: 733 and IS : 1285, fixed with rawl plugs and screws or with fixing clips, or with
expansion hold fasteners including necessary filling up of gaps at junctions, at top, bottom and sides
with required PVC/neoprene felt etc. Aluminium sections shall be smooth, rust free, straight, mitred and
jointed mechanically wherever required including cleat angle, Aluminium snap beading for glazing /
panelling, C.P. brass / stainless steel screws, all complete as per architectural drawings and the
directions of Engineer-in-charge. (Glazing and panelling to be paid for separately):

21.1.2 For shutters of doors, windows & ventilators including providing and fixing hinges/pivots and
making provision for fixing of fittings wherever required including the cost of PVC / neoprene gasket
required (Fittings shall be paid for separately).
21.1.2.2 Powder coated aluminium (minimum thickness of powder coating 50 micron)
Code Description Unit Quantity Rate Amount
Details of cost for 20.212 kg
MATERIAL :
7306 Aluminium T or L sections kilogram 21.65 195.00 4221.75
689 Alum inium hinges 100x75x4 mm 10 Nos. 4 416.00 166.40
589 C.P. brass /stainless steel screws 20 mm 100 Nos. 92 63.00 57.96
7393 Polyester powder coating 50 m icrons on
aluminium sections kilogram 21.65 50.00 1082.50
7390 Neoprene/ PVC gasket in groove of
meeting style metre 2.35 22.00 51.70
9999 Carriage of material L.S. 31.2 1.00 31.20
LABOUR For fabrication of frame
116 Fitter Day 0.32 270 86.40
139 Beldar (Special) Day 0.28 180 50.40
114 Beldar Day 0.18 207.00 37.26
100 Bandhani Day 0.20 180.00 36.00
For fixing the shutter including hinges :
111 Carpenter 1st class Day 0.06 270.00 16.20
114 Beldar Day 0.04 207.00 8.28
9999 Labour for making provision for fittings L.S. 26
and carriage of screws etc. including
sundries
1.00 26.00
TOTAL 5872.05
Add 1% for water charges 58.72
TOTAL 5930.77
Add for contractor’s profit and overheads
@15% 889.62
Cost of 20.21 kg 6820.39
Cost of 1 kg 337.48
Say 337.48

21.2 Providing and fixing 12mm thick prelaminated particle board flat pressed three layer or graded
wood particle board conforming to IS: 12823 Grade 1 Type II in panelling fixed in aluminium doors,
windows shutters and partition frames with C.P. brass / stainless steel screws etc. complete as per
architectural drawings and directions of engineer-in-charge.
21.2.1 Pre-laminated particle board with decorative lamination on one side and balancing lamination on
other side.
Code Description Unit Quantity Rate Amount
Details of cost for 7 sqm
MATERIAL
7477 12 mm thick particle board sqm 7.35 595.00 4373.25
9999 Carriage of particle board L.S. 13.65 1.00 13.65
9999 Sundries & screws etc. L.S. 27.3 1.00 27.30
LABOUR:
112 Carpenter 2nd class Day 0.90 223.00 200.70
114 Beldar Day 1.00 207.00 207.00
TOTAL 4821.90
Add 1% for water charges 48.22
TOTAL 4870.12
Add for contractor’s profit and overheads
@15% 730.52
Cost of 7 sqm 5600.64
Cost of 1 sqm 800.09
Say 800.09

21.2 Providing and fixing 12mm thick prelaminated particle board flat pressed three layer or graded
wood particle board conforming to IS: 12823 Grade 1 Type II in panelling fixed in aluminium doors,
windows shutters and partition frames with C.P. brass / stainless steel screws etc. complete as per
architectural drawings and directions of engineer-in-charge.
21.2.2 Prelaminated particle board with decorative lamination on both sides.
Code Description Unit Quantity Rate Amount
Details of cost for 7 sqm
MATERIAL
7480 12 mm thick particle board sqm 7.35 625.00 4593.75
9999 Carriage of particle board L.S. 13.65 1.00 13.65
9999 Sundries & screws etc. L.S. 27.3 1.00 27.30
LABOUR
:
112 Carpenter 2nd class Day 0.90 223.00 200.70
114 Beldar Day 1.00 207.00 207.00
TOTAL 5042.40
Add 1% for water charges 50.42
TOTAL 5092.82
Add for contractor’s profit and overheads
@15% 763.92
Cost of 7 sqm 5856.75
Cost of 1 sqm 836.68
Say 836.68

21.3 Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc.
with PVC/neoprene gasket etc. complete as per the architectural drawings and the directions of
engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item):
21.3.1 With float glass panes of 4.0 mm thickness
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
MATERIAL
2406 FloatGlass panes 4.00 mm thick sqm 1.1 248.00 272.80
9999 Carriage of glass L.S. 2.42 1.00 2.42
7390 Neoprene/ PVC gasket in groove of
meeting style metre 6 22.00 132.00
9999 Sundries and carriage of gasket L.S. 6.89 1.00 6.89
LABOUR
:
119 Glazier Day 0.23 180.00 41.40
114 Beldar Day 0.23 207.00 47.61
TOTAL 503.12
Add 1% for water charges 5.03
TOTAL 508.15
Add for contractor’s profit and overheads
@15% 76.22
Cost of 1 sqm 584.37
Say 584.37

21.3 Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc.
with PVC/neoprene gasket etc. complete as per the architectural drawings and the directions of
engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item):
21.3.2 With float glass panes of 5.50 mm thickness
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
MATERIAL
2407 FloatGlass panes 5.50 mm thick sqm 1.1 340.00 374.00
9999 Carriage of glass L.S. 3.33 1.00 3.33
7390 Neoprene/ PVC gasket in groove of
meeting style metre 6 22.00 132.00
9999 Sundries and carriage of gasket L.S. 6.89 1.00 6.89
LABOUR
:
119 Glazier Day 0.23 180.00 41.40
114 Beldar Day 0.23 207.00 47.61
TOTAL 605.23
Add 1% for water charges 6.05
TOTAL 611.28
Add for contractor’s profit and overheads
@15% 91.69
Cost of 1 sqm 702.97
Say 702.97

21.3 Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc.
with PVC/neoprene gasket etc. complete as per the architectural drawings and the directions of
engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item):
21.3.3 With float glass panes of 8 mm thickness
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
MATERIAL
2408 FloatGlass panes 8.0 mm thick sqm 1.1 248.00 272.80
9999 Carriage of glass L.S. 3.33 1.00 3.33
7390 Neoprene/ PVC gasket in groove of
meeting style metre 6 22.00 132.00
9999 Sundries and carriage of gasket L.S. 6.89 1.00 6.89
LABOUR
:
119 Glazier Day 0.23 180.00 41.40
114 Beldar Day 0.23 207.00 47.61
TOTAL 504.03
Add 1% for water charges 5.04
TOTAL 509.07
Add for contractor’s profit and overheads
@15% 76.36
Cost of 1 sqm 585.43
Say 585.43
21.4 Providing and fixing double action hydraulic floor spring of approved brand and manufacture IS :
6315 marked, for doors including cost of cutting floors as required, embedding in floors and cover
plates with brass pivot and single piece M.S. sheet outer box with slide plate etc. complete as per the
direction of Engineer-in-charge.
21.4.1 With stainless steel cover plate
Code Description Unit Quantity Rate Amount
Details of cost for one number
MATERIAL
7394 Double action hydraulic floor spring with
stainless steel cover plate each 1 1400.00 1400.00
9999 Carriage L.S. 13 1.00 13.00
9999 Sundries and screws L.S. 26 1.00 26.00
Cement concrete 1:2:4 (Rate as per item no
A 4.1.3 SH : CC) cum 0.002 5,140.53 10.28
LABOUR: For cutting hole and making it good
123 Mason ist class Day 0.08 270 21.60
124 Mason 2nd class Day 0.08 223 17.84
112 Carpenter 2nd class Day 0.01 223.00 2.23
114 Beldar Day 0.17 207.00 35.19
TOTAL 1526.14
Add 1% for water charges execpt on A
15.16
TOTAL 1541.30
Add for contractor’s profit and overheads
@15% except on A 229.65
Cost of each 1770.95
Say 1770.95

21.4 Providing and fixing double action hydraulic floor spring of approved brand and manufacture IS :
6315 marked, for doors including cost of cutting floors as required, embedding in floors and cover
plates with brass pivot and single piece M.S. sheet outer box with slide plate etc. complete as per the
direction of Engineer-in-charge.
21.4.2 With brass cover plate
Code Description Unit Quantity Rate Amount
Details of cost for one number
MATERIAL
7396 Double action hydraulic floor spring with
brass steel cover plate each 1 1550.00 1550.00
9999 Carriage L.S. 13 1.00 13.00
9999 Sundries and screws L.S. 26 1.00 26.00
Cement concrete 1:2:4 (Rate as per item no
A 4.1.3 SH : CC) cum 0.002 5,140.53 10.28
LABOUR: For cutting hole and making it good
123 Mason ist class Day 0.08 270 21.60
124 Mason 2nd class Day 0.08 223 17.84
112 Carpenter 2nd class Day 0.01 223.00 2.23
114 Beldar Day 0.17 207.00 35.19
TOTAL 1676.14
Add 1% for water charges execpt on A
16.66
TOTAL 1692.80
Add for contractor’s profit and overheads
@15% except on A 252.38
Cost of each 1945.18
Say 1945.18

21.5 Providing and fixing powder coated aluminium work (minimum thickness of powder coating 50
micron) consisting of tee/ angle sections, of approved make conforming to IS : 733 in frames of false
ceiling including aluminium angle cleats with necessary C.P. brass/ stainless steel sunk screws,
aluminium perimeter angles fixed to wall with rawl plugs @ 450 mm centre to centre and fixing the
frame work to G.I. level adjusting hangers 6«mm dia. with necessary cadmium plated machine screws
all complete as per approved architectural drawings and direction of the Engineer-in-charge (level
adjusting hangers, ceiling cleats and expansion hold fasteners to be paid for separately).

Code Description Unit Quantity Rate Amount


Details of cost for 6.35 kg = 5.76 sqm
MATERIAL :
7306 Aluminium T or L sections kilogram 6.672 195.00 1301.04
589 C.P. brass /stainless steel screws 20 mm 100 Nos. 1.16 63.00 0.73
7048 Rawl plug for fixing perimeter angles each 24 7.00 168.00
7392 Powder coating 50 microns on aluminium
sections. kilogram 6.67 45.00 300.15
9999 Carriage of material L.S. 13 1.00 13.00
9999 C.P. brass screws for fixing frame with L.S. 13
suspenders 1.00 13.00
LABOUR For fabrication & erection
111 Carpenter 1st class Day 0.64 270 172.80
114 Beldar Day 0.64 207.00 132.48
9999 Scaffolding and sundries L.S. 13 1.00 13.00
TOTAL 2114.20
Add 1% for water charges 21.14
TOTAL 2135.34
Add for contractor’s profit and overheads
@15% 320.30
Cost of 6.35 kg 2455.64
Cost of 1 kg 386.72
Say 386.72
21.6 Providing and fixing 6 mm dia. G.I. level adjusting hangers (upto 1200mm length) fixed to roof
slabs by means of ceiling cleats made out of G.I. flat 40x3mm size 60mm long and expansion hold
fasteners 12.5 mm dia. 40mm long complete as per direction of Engineer -in-charge.
Code Description Unit Quantity Rate Amount
Details of cost for 23 nos (hangers in 2.40 mx 2.40 m = 5.76 sqm)one number
MATERIAL :
7395 6 mm dia G.I. adjustable hangers including
clips (upto 1.20 metre length)
each 23 25.00 575.00
992 Galvanised steel plain sheets quintal 0.014 3450.00 48.30
7388 Dash fastner 12.5 mm dia 40 mm long
with 6 mm dia bolts each 23 30.00 690.00
9999 Carriage of material L.S. 5.2 1.00 5.20
LABOUR For fabrication & erection
111 Carpenter 1st class Day 0.35 270 94.50
114 Beldar Day 0.27 207.00 55.89
TOTAL 1468.89
Add 1% for water charges 14.69
TOTAL 1483.58
Add for contractor’s profit and overheads
@15% 222.54
Cost of 23 hangers 1706.12
Cost of 1 hanger 74.18
Say 74.18

21.7 Providing and fixing machine moulded aluminium covering of approved pattern & design, made
out of machine cut aluminium sheet and machine holed for receiving screws, over expansion joints
on vertical surfaces/ceilings with full threaded, cadmium plated steel screws 4mm dia. stem, 30mm
long and aluminium washers 2mm thick, 15mm dia. at a staggered pitch of 200mm centre to centre
including drilling holes in the receiving surface and providing expandable plastic sleeves in holes etc.
complete.
21.7.1 Anodised aluminium sheet 2.5mm thick (anodised transparent or dyed to required shade
according to IS: 1868, Minimum anodic coating of grade AC 15)
Code Description Unit Quantity Rate Amount
Details of cost for 7 kg
MATERIAL :
2704 Anodised aluminium sheet 2.5 mm thick,
170mm wide kg 7.35 195.00 1433.25
7389 Anodising 15 microns on aluminium kilogram 7.35 32.00 235.20
sections
7347 Cadmium plated full threaded steel screws
30 mm x 4 mm dia 100 Nos 30 23.00 6.90
7348 Aluminium washers 2 mm 15 mm dia 100 Nos 30 7.00 2.10
7313 Expandable plastic sleeves each 30 7.00 210.00
9999 Carriage of material L.S. 6.5 1.00 6.50
LABOUR For fabrication & erection
112 Carpenter 2nd class Day 0.392 223 87.42
114 Beldar Day 0.392 207.00 81.14
9999 Sundries including machine work L.S. 21.45 1.00 21.45
TOTAL 2083.96
Add 1% for water charges 20.84
TOTAL 2104.80
Add for contractor’s profit and overheads
@15% 315.72
Cost of 7 kg 2420.52
Cost of 1 kg 345.79
Say 345.79

21.7 Providing and fixing machine moulded aluminium covering of approved pattern & design, made
out of machine cut aluminium sheet and machine holed for receiving screws, over expansion joints
on vertical surfaces/ceilings with full threaded, cadmium plated steel screws 4mm dia. stem, 30mm
long and aluminium washers 2mm thick, 15mm dia. at a staggered pitch of 200mm centre to centre
including drilling holes in the receiving surface and providing expandable plastic sleeves in holes etc.
complete.
21.7.2 Powder coated aluminium sheet 2.5mm thick (minimum thickness of powder coating 50 micron)
Code Description Unit Quantity Rate Amount
Details of cost for 7 kg
MATERIAL :
2704 Anodised aluminium sheet 2.5 mm thick,
170mm wide kg 7.35 195.00 1433.25
7392 Powder coating 50 microns on aluminium
sections. kilogram 7.35 45.00 330.75
7347 Cadmium plated full threaded steel screws
30 mm x 4 mm dia 100 Nos 30 23.00 6.90
7348 Aluminium washers 2 mm 15 mm dia 100 Nos 30 7.00 2.10
7313 Expandable plastic sleeves each 30 7.00 210.00
9999 Carriage of material L.S. 6.5 1.00 6.50
LABOUR For fabrication & erection
112 Carpenter 2nd class Day 0.392 223 87.42
114 Beldar Day 0.392 207.00 81.14
9999 Sundries including machine work L.S. 21.45 1.00 21.45
TOTAL 2179.51
Add 1% for water charges 21.80
TOTAL 2201.31
Add for contractor’s profit and overheads
@15% 330.20
Cost of 7 kg 2531.50
Cost of 1 kg 361.64
Say 361.64
21.8 Filling the gap in between aluminium frame & adjacent RCC/ Brick/ Stone work by providing
weather silicon sealant over backer rod of approved quality as per architectural drawings and direction
of Engineer-in-charge complete.
21.8.1 Upto 5mm depth and 5 mm width
Code Description Unit Quantity Rate Amount
Details of cost for 1 metre
MATERIAL
8646 Silicon sealant (i/c 5% wastage) Cartridge 0.087 281.00 24.45
8654 Masking tape. metre 2 1.40 2.80
9999 Sundries & profile L.S. 2.6 1.00 2.60
9999 Labour L.S. 20.8 1.00 20.80
TOTAL 50.65
Add 1% for water charges 0.51
TOTAL 51.15
Add for contractor’s profit and overheads
@15% 7.67
Cost of 1 metre 58.83
Say 58.83

21.9 Extra for applying additional anodic coating AC 25 instead of AC 15 to aluminium extruded
sections.
21.9.1 For fixed portion
Code Description Unit Quantity Rate Amount
Details of cost for 41.09 kg
7391 Anodising 25 microns on aluminium secti kilogram 41.09 40.00 1643.60
7389 Anodising 15 microns on aluminium kilogram 41.09 32.00 1314.88
sections
Difference 328.72
Add 1% for water charges 3.29
TOTAL 332.01
Add for contractor’s profit and overheads
@15% 49.80
Cost of 41.09 kg 381.81
Cost of 1 kg 9.29
Say 9.29

21.9 Extra for applying additional anodic coating AC 25 instead of AC 15 to aluminium extruded
sections.
21.9.2 For shutters of doors, windows & ventilators.
Code Description Unit Quantity Rate Amount
Details of cost for 21.65 kg
7391 Anodising 25 microns on aluminium secti kilogram 21.65 40.00 866.00
7389 Anodising 15 microns on aluminium
sections kilogram 21.65 32.00 692.80
Difference 173.20
Add 1% for water charges 1.73
TOTAL 174.93
Add for contractor’s profit and overheads
@15% 26.24
Cost of 21.65 kg 201.17
Cost of 1 kg 9.29
Say 9.29

21.10 Providing and fixing double glazed hermetically sealed glazing in aluminium windows,
ventilators and partition etc. with 6 mm thick clear float glass both side having 12 mm air gap
including providing EPDM gasket, perforated aluminium spacers, desiccants, silicon sealant (Both
primary and secondary sealant) etc. as per specifications, drawings and direction of Engineer-in-charge
complete.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 sqm
Materials
8648 Hermetically sealled double glazed unit
made with 6mm thick clear float glass
both side having 12 mm air gap.
sqm 1.1 1980.00 2178.00
9,999 Carriage of materials L.S. 6.66 1.00 6.66
7390 Neoprene/EPDM rubber gasket metre 6 22.00 132.00
Labour
112 Glazier Day 0.23 223 51.29
114 Beldar Day 0.46 207 95.22
9,999 Sundries & Carriage of gasket L.S. 6.89 1.00 6.89
TOTAL 2470.06
Add 1% for water charges 24.70
TOTAL 2494.76
Add for contractor’s profit and overheads
@15% 374.21
Cost of 1 sqm 2868.97
Say 2868.97

21.11 Providing and fixing stainless steel (SS-304 grade) adjustable friction windows stays of approved
quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-
in-charge complete.
21.11.1 205X19mm
Code Description Unit Quantity Rate Amount
Detail of cost for 1 nos.
Materials
8649 Stainless steel (SS 304 grade) adjustable
friction window stay. 205 x 19mm
each 10 145.60 1456.00
9,999 Carriage of materials L.S. 2.73 1.00 2.73
8647 Stainless steal screws 30mm x4mm. cent 0.4 25.00 10.00
Labour
112 Glazier Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 1528.93
Add 1% for water charges 15.29
TOTAL 1544.22
Add for contractor’s profit and overheads
@15% 231.63
Cost of 10 nos. 1775.85
Cost of 1 no. 177.59
Say 177.59

21.11 Providing and fixing stainless steel (SS-304 grade) adjustable friction windows stays of approved
quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-
in-charge complete.
21.11.2 255X19mm
Code Description Unit Quantity Rate Amount
Detail of cost for 1 nos.
Materials
8650 Stainless steel (SS 304 grade) adjustable
friction window stay 255 x19 mm
each 10 161.20 1612.00
9,999 Carriage of materials L.S. 2.73 1.00 2.73
8647 Stainless steal screws 30mm x4mm. cent 0.4 25.00 10.00
Labour
112 Glazier Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 1684.93
Add 1% for water charges 16.85
TOTAL 1701.78
Add for contractor’s profit and overheads
@15% 255.27
Cost of 10 nos. 1957.05
Cost of 1 no. 195.70
Say 195.70

21.11 Providing and fixing stainless steel (SS-304 grade) adjustable friction windows stays of approved
quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-
in-charge complete.
21.11.3 355X19 mm
Code Description Unit Quantity Rate Amount
Detail of cost for 1 nos.
Materials
8651 Stainless steel (SS 304 grade) adjustable
friction window stay 355 x19 mm
each 10 208.00 2080.00
9,999 Carriage of materials L.S. 2.73 1.00 2.73
8647 Stainless steal screws 30mm x4mm. cent 0.4 25.00 10.00
Labour
112 Glazier Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 2152.93
Add 1% for water charges 21.53
TOTAL 2174.46
Add for contractor’s profit and overheads
@15% 326.17
Cost of 10 nos. 2500.63
Cost of 1 no. 250.06
Say 250.06

21.11 Providing and fixing stainless steel (SS-304 grade) adjustable friction windows stays of approved
quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-
in-charge complete.
21.11.4 510X19mm
Code Description Unit Quantity Rate Amount
Detail of cost for 1 nos.
Materials
8652 Stainless steel (SS 304 grade) adjustable
friction window stay 510 x19 mm
each 10 390.00 3900.00
9,999 Carriage of materials L.S. 2.73 1.00 2.73
8647 Stainless steal screws 30mm x4mm. cent 0.4 25.00 10.00
Labour
112 Glazier Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 3972.93
Add 1% for water charges 39.73
TOTAL 4012.66
Add for contractor’s profit and overheads
@15% 601.90
Cost of 10 nos. 4614.56
Cost of 1 no. 461.46
Say 461.46

21.11 Providing and fixing stainless steel (SS-304 grade) adjustable friction windows stays of approved
quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-
in-charge complete.
21.11.5 710X19mm
Code Description Unit Quantity Rate Amount
Detail of cost for 1 nos.
Materials
8653 Stainless steel (SS 304 grade) adjustable
friction window stay 710 x19 mm
each 10 715.00 7150.00
9,999 Carriage of materials L.S. 2.73 1.00 2.73
8647 Stainless steal screws 30mm x4mm. cent 0.4 25.00 10.00
Labour
112 Glazier Day 0.14 223 31.22
114 Beldar Day 0.14 207 28.98
TOTAL 7222.93
Add 1% for water charges 72.23
TOTAL 7295.16
Add for contractor’s profit and overheads
@15% 1094.27
Cost of 10 nos. 8389.43
Cost of 1 no. 838.94
Say 838.94

21.12 Providing and fixing aluminium tubular handle bar 32 mm outer dia, 3.0 mm thick & 2100 mm
long with SS screws etc .complete as per direction of Engineer-in-Charge.
21.12.1 Anodized (AC 15 ) aluminium tubular handle bar
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos handle bar.
MATERIAL :
7306 Aluminium T or L sections kilogram 16.34 195.00 3186.30
8647 Stainless steal screws 30mm x4mm. cent 0.08 25.00 2.00
7389 Anodising 15 microns on aluminium
sections kilogram 16.34 32.00 522.88
9999 Carriage of material L.S. 4.42 1.00 4.42
LABOUR For fabrication of frame
111 Carpenter 1st class Day 0.13 270.00 33.75
TOTAL 3749.35
Add 1% for water charges 37.49
TOTAL 3786.84
Add for contractor’s profit and overheads
@15% 568.03
Cost of 10 no.s 4354.87
Cost of 1 no 435.49
Say 435.49

21.12 Providing and fixing aluminium tubular handle bar 32 mm outer dia, 3.0 mm thick & 2100 mm
long with SS screws etc .complete as per direction of Engineer-in-Charge.
21.12.2 Powder coated minimum thickness 50 micron aluminium tubular handle bar.
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos handle bar.
MATERIAL :
7306 Aluminium T or L sections kilogram 16.34 195.00 3186.30
8647 Stainless steal screws 30mm x4mm. cent 0.08 25.00 2.00
7392 Powder coating 50 microns on aluminium
sections. kilogram 16.34 45.00 735.30
9999 Carriage of material L.S. 4.42 1.00 4.42
LABOUR For fabrication of frame
111 Carpenter 1st class Day 0.13 270.00 33.75
TOTAL 3961.77
Add 1% for water charges 39.62
TOTAL 4001.39
Add for contractor’s profit and overheads
@15% 600.21
Cost of 10 no.s 4601.60
Cost of 1 no 460.16
Say 460.16

21.12 Providing and fixing aluminium tubular handle bar 32 mm outer dia, 3.0 mm thick & 2100 mm
long with SS screws etc .complete as per direction of Engineer-in-Charge.
21.12.3 Polyester powder coated minimum thickness 50 micron aluminium tubular handle bar
Code Description Unit Quantity Rate Amount
Details of cost for 10 nos handle bar.
MATERIAL :
7306 Aluminium T or L sections kilogram 16.34 195.00 3186.30
8647 Stainless steal screws 30mm x4mm. cent 0.08 25.00 2.00
7393 Polyester powder coating 50 m icrons on
aluminium sections kilogram 16.34 50.00 817.00
9999 Carriage of material L.S. 4.42 1.00 4.42
LABOUR For fabrication of frame
111 Carpenter 1st class Day 0.13 270.00 33.75
TOTAL 4043.47
Add 1% for water charges 40.43
TOTAL 4083.90
Add for contractor’s profit and overheads
@15% 612.59
Cost of 10 no.s 4696.49
Cost of 1 no 469.65
Say 469.65

21.13 Providing and fixing 100mm brass locks (best make of approved quality) for aluminium
doors including necessary cutting and making good etc. complete.
Code Description Unit Quantity Rate Amount
Detail of cost for 1 nos.
Materials
Brass 100 mm mortice latch and lock
7001 with 6 levers without pair of handles each 1 150.00 150.00
Labour
111 Carpenter 1st class Day 0.17 270.00 45.90
9999 Sundry and screws L.S. 3.64 1.00 3.64
TOTAL 199.54
Add 1% for water charges 2.00
TOTAL 201.54
Add for contractor’s profit and overheads
@15% 30.23
Cost of 1 no 231.77
Say 231.77

21.14 Providing and fixing anodised aluminium (anodised transparent or dyed to required shade
according to IS : 1868. Minimum anodic coating of grade AC 15) sub frame work for windows and
ventilators with extruded built up standard tubular sections of approved make conforming to IS: 733
and IS : 1285 fixed with rawl plugs and stainless steel screws etc.
Code Description Unit Quantity Rate Amount
Details of cost for 4.082kg
MATERIAL :
7306 Aluminium T or L sections kilogram 4.286 195.00 835.77
589 C.P. brass /stainless steel screws 20 mm 100 Nos. 8 63.00 5.04
7019 Dash hold fastners each 8 8.00 64.00
7389 Anodising 15 microns on aluminium
sections kilogram 4.286 32.00 137.15
9999 Carriage of material L.S. 5.2 1.00 5.20
LABOUR For fabrication of frame
116 Fitter Day 0.04 270 10.80
139 Beldar (Special) Day 0.04 180 7.20
114 Beldar Day 0.02 207.00 4.14
101 Bandhani Day 0.01 180.00 1.80
9999 Labour for drilling holes, hire charges of L.S. 5.2
drill, electricity charges, carriage of dash
hold fastners & sundries
1.00 5.20
TOTAL 1076.30
Add 1% for water charges 10.76
TOTAL 1087.07
Add for contractor’s profit and overheads
@15% 163.06
Cost of 4.082 kg 1250.12
Cost of 1 kg 306.25
Say 306.25

21.15 Providing and fixing aluminium casement windows fastener of required length for aluminium
windows with necessary screws etc. complete.
21.15.1 Anodized(AC 15) aluminium
Code Description Unit Quantity Rate Amount
Detail of cost for 10 nos.
Materials
8660 Aluminium casement window fastener
(Anodised AC 15 ) each 10 30.00 300.00
8666 Stainless steel screws 25mm x4mm cent 0.4 21.00 8.40
Labour
0111 Carpenter 1st class Day 0.06 270 16.20
9,999 Carriage of materials L.S. 2.73 1.00 2.73
TOTAL 327.33
Add 1% for water charges 3.27
TOTAL 330.60
Add for contractor’s profit and overheads
@15% 49.59
Cost of 10 nos 380.19
Cost of 1 no 38.02
Say 38.02

21.15 Providing and fixing aluminium casement windows fastener of required length for aluminium
windows with necessary screws etc. complete.
21.15.2 Powder coated minimum thickness 50 micron aluminium.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 nos.
Materials
8661 Aluminium casement window fastener
(powder coated ). each 10 33.00 330.00
8666 Stainless steel screws 25mm x4mm cent 0.4 21.00 8.40
Labour
0111 Carpenter 1st class Day 0.06 270 16.20
9,999 Carriage of materials L.S. 2.73 1.00 2.73
TOTAL 357.33
Add 1% for water charges 3.57
TOTAL 360.90
Add for contractor’s profit and overheads
@15% 54.14
Cost of 10 nos 415.04
Cost of 1 no 41.50
Say 41.50

21.15 Providing and fixing aluminium casement windows fastener of required length for aluminium
windows with necessary screws etc. complete.
21.15.3 Polyester powder coated minimum thickness 50 micron aluminium .
Code Description Unit Quantity Rate Amount
Detail of cost for 10 nos.
Materials
8662 Aluminium casement w indow fastener
(polyester powder coated). each 10 35.00 350.00
8666 Stainless steel screws 25mm x4mm cent 0.4 21.00 8.40
Labour
0111 Carpenter 1st class Day 0.06 270 16.20
9,999 Carriage of materials L.S. 2.73 1.00 2.73
TOTAL 377.33
Add 1% for water charges 3.77
TOTAL 381.10
Add for contractor’s profit and overheads
@15% 57.17
Cost of 10 nos 438.27
Cost of 1 no 43.83
Say 43.83

21.16 Providing and fixing aluminium round shape handle of outer dia 100mm with SS screws etc.
Complete as per direction of Engineer-in-charge
21.16.1 Anodized (AC 15 ) aluminium
Code Description Unit Quantity Rate Amount
Detail of cost for 10 nos.
Materials
8663 Aluminium round shape handle (anodised A each 10 37.00 370.00
8666 Stainless steel screws 25mm x4mm cent 0.4 21.00 8.40
Labour
0111 Carpenter 1st class Day 0.06 270 16.20
9,999 Carriage of materials L.S. 2.73 1.00 2.73
TOTAL 397.33
Add 1% for water charges 3.97
TOTAL 401.30
Add for contractor’s profit and overheads
@15% 60.20
Cost of 10 nos 461.50
Cost of 1 no 46.15
Say 46.15

21.16 Providing and fixing aluminium round shape handle of outer dia 100mm with SS screws etc.
Complete as per direction of Engineer-in-charge
21.16.2 Powder coated minimum thickness 50 micron aluminium.
Code Description Unit Quantity Rate Amount
Detail of cost for 10 nos.
Materials
8664 Aluminium round shape handle (powder
coated) each 10 41.00 410.00
8666 Stainless steel screws 25mm x4mm cent 0.4 21.00 8.40
Labour
0111 Carpenter 1st class Day 0.06 270 16.20
9,999 Carriage of materials L.S. 2.73 1.00 2.73
TOTAL 437.33
Add 1% for water charges 4.37
TOTAL 441.70
Add for contractor’s profit and overheads
@15% 66.26
Cost of 10 nos 507.96
Cost of 1 no 50.80
Say 50.80

21.16 Providing and fixing aluminium round shape handle of outer dia 100mm with SS screws etc.
Complete as per direction of Engineer-in-charge
21.16.3 Polyester powder coated minimum thickness 50 micron aluminium .
Code Description Unit Quantity Rate Amount
Detail of cost for 10 nos.
Materials
8665 Aluminium round shape handle (polyester
powder coated). each 10 43.00 430.00
8666 Stainless steel screws 25mm x4mm cent 0.4 21.00 8.40
Labour
0111 Carpenter 1st class Day 0.06 270 16.20
9,999 Carriage of materials L.S. 2.73 1.00 2.73
TOTAL 457.33
Add 1% for water charges 4.57
TOTAL 461.90
Add for contractor’s profit and overheads
@15% 69.29
Cost of 10 nos 531.19
Cost of 1 no 53.12
Say 53.12
22.1 Providing and laying integral cement based treatm ent for water proofing on horizontal
surface at all depth below ground level for under ground structures as directed by Engineer-in-
Charge and consisting of : (i) 1st layer of 22mm to 25mm thick approved and specified rough stone
slab over a 25mm thick base of cement mortar 1:3 (1 cement : 3 coarse sand) mixed with
water proofing compound conforming to IS:2645 in the recommended proportion over the levelling
course (levelling course to be paid separately). Joints sealed and grouted with cement slurry mixed
with water proofing compound . ii) 2nd layer of 25mm thick cement mortar 1:3 (1 cement : 3 coarse
sand) mixed with water proofing compound in recommended proportions. iii) Finishing top with
stone aggregate of 10mm to 12mm nominal size spreading @ 8 cudm/sqm thoroughly embedded in
the 2nd layer.
22.1.1 Using rough kota stone.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIAL
Cement mortar 1:3 for fixing of cum 0.53 3262.33 1729.03
stone (Rate as per item no. 3.8)
1169 Kota stone slab sqm 11.00 175.00 1925.00
2216 Carriage of kota stone tonne 0.64 47.29 30.27
367 Cement for slurry tonne 0.07 5200.00 374.40
2209 Carriage of cem ent tunne 0.07 47.29 3.40
1213 Water proofing m aterial kilogra 6.86 20.00 137.20
m
0296 12 mm stone grit cum 0.08 1050.00 84.00
2202 Carriage cum 0.08 53.21 4.26
Labour for top layer & spreading stone grit and for base mortar & kota stone laying
114 Beldar Day 2.08 207.00 430.56
101 Bhishti Day 0.45 180.00 81.00
115 Coolie Day 1.00 207.00 207.00
125 Mason (for plain stone w ork) 2nd Day 2.28 223.00 508.44
class) 1.00 6.24
9,999 Sundries L.S. 6.24
TOTAL 5520.80
Add 1% for water charges 55.21
TOTAL 5576.01
Add for contractor’s profit and 836.40
overheads @15%
Cost of 10 sqm 6412.41
Cost of 1 sqm 641.24
Say 641.24

22.2 Providing and laying integral cement based treatment for water proofing on the vertical surface
by fixing specified stone slab 22 mm to 25mm thick with cement slurry mixed with water proofing
compound conforming to IS:2645 in recommended proportions with a gap of 20mm (minimum)
between stone slabs and the receiving surfaces and filling the gaps with neat cement slurry mixed
with water proofing compound and finishing the exjerior of stone slab with cement mortar 1:3 (1
cement : 3 coarse sand) 20mm thick with neat cement punning mixed with water proofing
compound in recommended proportion complete at all levels and as directed by Engineer-in-
charge :
22.2.1 Using rough Kota stone
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIAL
A Cem ent plaster 1:3 w ith neat cement sqm 10.00 179.02 1790.19
punning) (Rate as per item no. 13.9.2 )

1169 Kota stone slab sqm 11.00 175.00 1925.00


2216 Carriage of kota stone tonne 0.64 47.29 30.27
367 Cement for slurry tonne 0.31 5200.00 1612.00
2209 Carriage of cem ent tunne 0.31 47.29 14.66
1213 Water proofing m aterial kilogra 8.90 20.00 178.00
m
Labour for top layer & spreading stone grit and for base mortar & kota stone laying
114 Beldar Day 3.00 207.00 621.00
115 Coolie Day 1.00 207.00 207.00
125 Mason (for plain stone w ork) 2nd Day 3.00 223.00 669.00
class) 1.00 18.20
9,999 Sundries & scaffolding L.S. 18.20
TOTAL 7065.32
Add 1% for water charges except A 52.75

TOTAL 7118.07
Add for contractor’s profit and 799.18
overheads @15% except A
Cost of 10 sqm 7917.25
Cost of 1 sqm 791.73
Say 791.73

22.3 Providing and laying water proofing treatment to vertical and horizontal surfaces of
depressed portions of W.C., kitchen and the like consisting of : (i) 1st course of applying cement
slurry @ 4.4 Kg/sqm mixed with water proofing compound conforming to IS 2645 in
recommended proportions including rounding off junction of vertical and horizontal surface. (ii)
Ilnd course of 20mm cement plaster 1:3 (1 cement : 3 coarse sand) mixed with water proofing
compound in recommended proportion including rounding off junction of vertical and horizontal
surface. (iii) Illrd course of applying blown or residual bitumen applied hot at 1.7 Kg. per sqm of
area. (iv) IVth course of 400 micron thick PVC sheet. (Overlaps at joints of PVC sheet should be
100 mm wide and pasted to each other with bitumen @ 1.7 Kg/sqm.)

Code Description Unit Quantity Rate Amount


Details of cost for 10.00 sqm
MATERIAL
Cement mortar 1:3 (Rate as per item cum 0.22 3262.33 730.76
no. 3.8 )
313 Bitumen blown or/and residual bitumen tonne 0.02 35000.00 595.00
2211 Carriage of bitumen tonne 0.02 53.21 0.90
367 Cement for slurry tonne 0.04 5200.00 228.80
2209 Carriage of cem ent tunne 0.04 47.29 2.08
1213 Water proofing m aterial kilogra 3.60 20.00 72.00
m
3002 PVC 400 micron thick sheet sqm 10.00 26.00 260.00
9,999 Carriage L.S. 13.00 1.00 13.00
Labour for top layer & spreading stone grit and for base mortar & kota stone laying
114 Beldar Day 1.33 207.00 275.31
115 Coolie Day 1.02 207.00 211.14
155 Mason (average) Day 0.94 180.00 169.20
130 Mistry Day 0.06 270.00 16.20
131 Painter Day 0.20 180.00 36.00
101 Bhishti Day 1.10 180.00 198.00
9,999 Sundries & scaffolding L.S. 19.89 1.00 19.89
TOTAL 2828.29
Add 1% for water charges 28.28
TOTAL 2856.57
Add for contractor’s profit and 428.49
overheads @15%
Cost of 10 sqm 3285.06
Cost of 1 sqm 328.51
Say 328.51

22.4 Providing and Placing in position suitable PVC water stops conforming to IS: 12200 for
construction/expansion joints between two RCC members and fixed to the reinforcement with
binding wire before pouring concrete etc. complete :
22.4.1 Serrated with central bulb (225mm wide, 8-11mm thick).
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
MATERIAL
7427 Water stop serreted with bulb metre 100.00 330.00 33000.00
Labour
114 Beldar Day 2.00 207.00 414.00
9,999 Sundries L.S. 26.00 1.00 26.00
TOTAL 33440.00
Add 1% for water charges 334.40
TOTAL 33774.40
Add for contractor’s profit and 5066.16
overheads @15%
Cost of 100 metres 38840.56
Cost of 1 metre 388.41
Say 388.41

22.4 Providing and Placing in position suitable PVC water stops conforming to IS: 12200 for
construction/expansion joints between two RCC members and fixed to the reinforcement with
binding wire before pouring concrete etc. complete :
22.4.2 Dumb bell with central bulb (180 mm wide, 8 mm thick)
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
MATERIAL
7428 Dumb bell with central bulb (180 mm metre 100.00 306.00 30600.00
wide, 8mm thick)
Labour
114 Beldar Day 2.00 207.00 414.00
9,999 Sundries L.S. 26.00 1.00 26.00
TOTAL 31040.00
Add 1% for water charges 310.40
TOTAL 31350.40
Add for contractor’s profit and 4702.56
overheads @15%
Cost of 100 metres 36052.96
Cost of 1 metre 360.53
Say 360.53

22.4 Providing and Placing in position suitable PVC water stops conforming to IS: 12200 for
construction/expansion joints between two RCC members and fixed to the reinforcement with
binding wire before pouring concrete etc. complete :
22.4.3 Kickers (320mm wide, 5mm thick).
Code Description Unit Quantity Rate Amount
Details of cost for 100 metres
MATERIAL
7429 Kickers (320 mm wide, 5 mm thic k) metre 100.00 325.00 32500.00

Labour
114 Beldar Day 2.00 207.00 414.00
9,999 Sundries L.S. 26.00 1.00 26.00
TOTAL 32940.00
Add 1% for water charges 329.40
TOTAL 33269.40
Add for contractor’s profit and 4990.41
overheads @15%
Cost of 100 metres 38259.81
Cost of 1 metre 382.60
Say 382.60

22.5 Providing and laying water proofing treatment in sunken portion of WCs, bathroom etc., by
applying cement slurry mixed with water proofing cement compound consisting of applying :
(a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @
0.253 kg/sqm. This layer will be allowed to air cure for 4 hours (b) Second layer of slurry of cement
@ 0.242 kg/sqm mixed with water proofing cement compound @ 0.126 kg/sqm. This layer will be
allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes
preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry
with polymer mixed slurry.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIAL
367 Cement for slurry tonne 0.01 5200.00 62.40
2209 Carriage of cem ent tunne 0.01 47.29 0.57
8501 Polymer modified cementation kilogra 5.00 114.00 570.00
coating m
Labour for top layer & spreading stone grit and for base mortar & kota stone laying
114 Beldar Day 2.00 207.00 414.00
155 Mason (average) Day 2.00 180.00 360.00
101 Bhishti Day 0.25 180.00 45.00
9,999 Sundries , brushes etc. L.S. 15.60 1.00 15.60
TOTAL 1467.57
Add 1% for water charges 14.68
TOTAL 1482.24
Add for contractor’s profit and 222.34
overheads @15%
Cost of 10 sqm 1704.58
Cost of 1 sqm 170.46
Say 170.46

22.6 Providing and laying water proofing treatment on roofs of slabs by applying cement slurry
mixed with water proofing cement compound consisting of applying : (a) after surface preparation,
first layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @
0.253 kg/sqm. (b) laying second layer of Fibre glass cloth when the first layer is still green.
Overlaps of joints of fibre cloth should not be less than 10 cm. (c) third layer of 1.5 mm thickness
consisting of slurry of cement @ 1.289 kg/sqm mixed with water proofing cement compound @
0.670 kg/sqm and coarse sand @ 1.289 kg/sqm. This will be allowed to air cure for 4 hours
followed by water curing for 48 hours. The entire treatment will be taken upto 30cm on parapet
wall and tucked into groove in parapet all around. (d ) fourth and final layer of brick tiling
with cement mortar (which will be paid for separately For the purpose of m easurement
the entire treated surface will be measured.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIAL
367 Cement for slurry tonne 0.02 5200.00 104.00
2209 Carriage of cem ent tunne 0.02 47.29 0.95
8501 Polymer modified cementation kilogra 9.69 114.00 1104.66
coating m
8502 Fibre glass cloth sqm 11.00 33.00 363.00
Labour for top layer & spreading stone grit and for base mortar & kota stone laying
114 Beldar Day 1.00 207.00 207.00
155 Mason (average) Day 2.00 180.00 360.00
101 Bhishti Day 0.25 180.00 45.00
9,999 Sundries , brushes etc. L.S. 23.40 1.00 23.40
TOTAL 2208.01
Add 1% for water charges 22.08
TOTAL 2230.09
Add for contractor’s profit and 334.51
overheads @15%
Cost of 10 sqm 2564.60
Cost of 1 sqm 256.46
Say 256.46

22.7 Providing and laying integral cement based water proofing treatment including
preparation of surface as required for treatment of roofs, balconies, terraces etc consisting of
following operations:
(a) Applying a slurry coat of neat cement using 2.75 kg/sqm . of cement admixed with water
proofing compound conforming to IS. 2645 and approved by Engineer-in-charge over the RCC
slab including adjoining walls upto 300mm height including cleaning the surface before treatment.
(b) Laying brick bats with mortar using broken bricks/brick bats 25 mm to 115mm size with 50% of
cement mortar 1:5 (1 cement : 5 coarse sand) admixed with water proofing compound conforming
to IS : 2645 and approved by Engineer-in-charge over 20 mm thick layer of cement mortar of mix
1:5 (1 cement :5 coarse sand ) admixed with water proofing compound conforming to IS : 2645 and
approved by Engineer-in-charge to required slope and treating similarly the adjoining walls upto
300 mm height including rounding of junctions of walls and slabs
(c) After two days of proper curing applying a second coat of cement slurry using 2.75kg/ sqm of
cement admixed with water proofing compound conforming to IS : 2645 and approved by
Engineer-in-charge.
(d) Finishing the surface with 20 mm thick jointless cement mortar of mix 1:4 (1 cement :4 coarse
sand) admixed with water proofing compound conforming to IS : 2645 and approved by Engineer-
in-charge including
(e) The whole laying
terrace glass fibre
so finished shallcloth of approved
be flooded quality
with water forina top layer of
minimum plaster
period of and
two finally
weeks
finishing the surface with trowel with neat cement slurry and making pattern of 300x300 mm square
for curing and for final test. All above operations to be done in order and as directed and specified
3mm
by thedeep.
Engineer-in-Charge :
22.7.1 With average thickness of 120mm and minimum thickness at khurra as 65 mm.
Code Description Unit Quantity Rate Amount
Details of cost for 10.00 sqm
MATERIAL
367 Cement for slurry tonne 0.03 5200.00 143.00
Cement mortar 1:5 (1 cement: 5 coarse cum 0.724 2212.87 1602.12
sand) (Rate as per item no.3.10)

iii) Roof treatment with brick bats and cement mortar


Materials:

285 Brick bats/ brick aggregate cum 0.94 350.00 329.00


2260 Carriage cum 0.94 57.83 54.36
Labour
114 Beldar Day 1.75 207.00 362.25
101 Bhishti Day 0.28 180.00 50.40
123 (B) Mason 1st class Day 0.05 270 13.50
124 (B) Mason 2nd class Day 0.05 223 11.15
128 Mate Day 0.04 313 12.52
Extra labour for ramming
114 Beldar Day 0.25 207.00 51.75
9999 Sundries L.S 13.65 1.00 13.65
iv) Cement slury
367 Cement tonne 0.0275 5200.00 143.00
114 Beldar Day 0.20 207.00 41.40
v) 20 mm cement plaster 1:4(1 cement: 4 coarse sand)
(A) (Rate as per item no 13.6.1 of SH : sqm 10.00 135.77 1357.69
Finishing)
1213 Water proofing compound kilogram 5.00 20.00 100.00
Extra for making chequers for 10 sqm
7233 Fibre glass tissue reinforcement Type sqm 10.5 55.00 577.50
124 IIGrade I 2nd class
(B) Mason Day 0.36 223 80.28
114 Beldar Day 0.36 207.00 74.52
9999 Add labour for laying 20 mm bed L.S. 13.65 1.00 13.65
mortar
124 Mason 2nd class Day 0.54 223 120.42
114 Beldar Day 0.54 207.00 111.78
101 Bhishti Day 0.45 180.00 81.00
TOTAL 5344.94
Add 1% for water charges except on 39.87
A
TOTAL 5384.81
Add for contractor’s profit and 604.07
overheads @15% ecept on A
Cost of 10 sqm 5988.88
Cost of 1 sqm 598.89
Say 598.89

22.8 Providing and laying four courses water proofing treatment with bitumen felt over roofs
consisting of first and third courses of blown bitumen 85/25 or 90/15 conforming to IS : 702 applied
hot @ 1.45 Kg per square metre of area for each course, second course of roofing felt type 3 grade-I
(Hessian based self finished bitumen” felt) and fourth and final course of stone grit 6mm and down
size or pea-sized gravel spread at 6 cubic diameter per square metre including preparation of surface
but excluding grading complete with :

22.8.1 Bitumen felt (Hessian base) type 3 grade I conforming to IS : 1322.


Code Description Unit Quantity Rate Amount
Details of cost for 30 sqm
313 Blown type petroleum bitumen of tonne 0.09 35000.00 3045.00
penetration 85/25 of approved quality

322 Hession felt type 3 Grade I (hessian sqm 33.00 45.00 1485.00
base self finished bitumen felt)

1177 Stone grit 6mm and down size or pea cum 0.18 700.00 126.00
sized gravel. 30x6
2202 Carriage of stone grit cum 0.18 53.21 9.58
2211 Carriage of bitumen and felt tonne 0.16 53.21 8.62
370 Fuel (Steam coal) quintal 0.174 120.00 20.88
2200 Carriage of fuel tonne 0.0174 60.81 1.06
9999 Praparing roof surface, sutting groove L.S 134.55 1.00 134.55
and making good etc.
Labour:
131 Painter Day 2.16 180.00 388.80
114 Beldar Day 3.24 207.00 670.68
130 Mistries Day 0.18 270.00 48.60
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 5945.53
Add 1% for water charges 59.46
TOTAL 6004.98
Add for contractor’s profit and 900.75
overheads @15%
Cost of 30 sqm 6905.73
Cost of 1 sqm 230.19
Say 230.19

22.9 Providing and laying six courses water proofing treatment with bitumen felt over roofs
consisting of first, third and fifth course of blown bitumen 85/25 or 90/15 conforming to IS :
702 applied hot @ 1.45, 1.20 and 1.45 Kg per square metre of area respectively, second and fourth
courses of roofing felt type 3 grade I conforming to IS : 1322 (Hessian based self finished bitumen
felt) conforming to IS : 1322 and sixth and final course of stone grit 6 mm and down size or pea
sized gravel spread at 6 cubic dm per sqm including preparation of surface but excluding grading,
complete.
Code Description Unit Quantity Rate Amount
Details of cost for 30 sqm
313 Blown type petroleum bitumen of tonne 0.12 35000.00 4305.00
penetration 85/25 of approved quality
322 Hession felt type 3 Grade I (hessian sqm 66.00 45.00 2970.00
base self finished bitumen felt)

1177 Stone grit 6mm and down size or pea cum 0.18 700.00 126.00
sized gravel. 30x6
2202 Carriage of stone grit cum 0.18 53.21 9.58
2211 Carriage of bitumen and felt tonne 0.27 53.21 14.53
370 Fuel (Steam coal) quintal 0.246 120.00 29.52
2200 Carriage of fuel tonne 0.0246 60.81 1.50
9999 Praparing roof surface, sutting groove L.S 134.55 1.00 134.55
and making good etc.
Labour:
131 Painter Day 3.24 180.00 583.20
114 Beldar Day 4.86 207.00 1006.02
130 Mistries Day 0.2 270.00 54.00
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 9240.65
Add 1% for water charges 92.41
TOTAL 9333.06
Add for contractor’s profit and 1399.96
overheads @15%
Cost of 30 sqm 10733.02
Cost of 1 sqm 357.77
Say 357.77

22.10 Providing and laying six courses water proofing treatment with bitumen felt over roofs
consisting of first, third and fifth courses of blown or / and residual bitumen applied hot at 1.45,
1.20 and 1.70 kg per square metre of area respectively, second and fourth courses of roofing felt
type 2 grade I (fibre base self finished bitufnen felt) six and final courses of stone grit 6mm and
down size or pea sized gravel spread at 6cu.dm per sqm including preparation of surface, excluding
grading compete.
Code Description Unit Quantity Rate Amount
Details of cost for 30 sqm
313 Blown type petroleum bitumen of tonne 0.13 35000.00 4567.50
penetration 85/25 of approved quality
318 Bitumen felt type 2 grade II (fibre base sqm 66.00 45.00 2970.00
self finished bitumen felt)
1177 Stone grit 6mm and down size or pea cum 0.18 700.00 126.00
sized gravel. 30x6
2202 Carriage of stone grit cum 0.18 53.21 9.58
2211 Carriage of bitumen and felt tonne 0.28 53.21 14.63
370 Fuel (Steam coal) quintal 0.246 120.00 29.52
2200 Carriage of fuel tonne 0.0246 60.81 1.50
9999 Praparing roof surface, sutting groove L.S 134.55 1.00 134.55
and making good etc.
Labour:
131 Painter Day 4.32 180.00 777.60
114 Beldar Day 6.48 207.00 1341.36
130 Mistries Day 0.36 270.00 97.20
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 10076.20
Add 1% for water charges 100.76
TOTAL 10176.96
Add for contractor’s profit and 1526.54
overheads @15%
Cost of 30 sqm 11703.50
Cost of 1 sqm 390.12
Say 390.12

22.11 Providing and laying six courses water proofing treatment with bitumen felt over roofs
consisting of first, third and fifth courses of blown or / and residual bitumen applied hot at 1.45,
1.20 and 1.70 kg per square metre of area respectively, second and fourth courses of roofing felt
type 2 grade II (glass fibre base self finished bitumen felt) and sixth and final course of stone grit
6mm and down size or pea sized gravel spread at 6 cubic dm per sqm including preparation of
surface but excluding grading, complete.
Code Description Unit Quantity Rate Amount
Details of cost for 30 sqm
313 Blown type petroleum bitumen of tonne 0.13 35000.00 4567.50
penetration 85/25 of approved quality
318 Bitumen felt type 2 grade II (fibre base sqm 66.00 45.00 2970.00
self finished bitumen felt)
1177 Stone grit 6mm and down size or pea cum 0.18 700.00 126.00
sized gravel. 30x6
2202 Carriage of stone grit cum 0.18 53.21 9.58
2211 Carriage of bitumen and felt tonne 0.33 53.21 17.77
370 Fuel (Steam coal) quintal 0.246 120.00 29.52
2200 Carriage of fuel tonne 0.0246 60.81 1.50
9999 Praparing roof surface, sutting groove L.S 134.55 1.00 134.55
and making good etc.
Labour:
131 Painter Day 4.32 180.00 777.60
114 Beldar Day 6.48 207.00 1341.36
130 Mistries Day 0.36 270.00 97.20
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 10079.34
Add 1% for water charges 100.79
TOTAL 10180.13
Add for contractor’s profit and 1527.02
overheads @15%
Cost of 30 sqm 11707.15
Cost of 1 sqm 390.24
Say 390.24

22.12 Supplying and applying bituminous solution primer on roof and or wall surface at 0.24 litre
per sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sq. metres
Materials
0316 Bitumenous solution primer litre 2.40 30.00 72.00
9999 Carriage L.S 1.43 1.00 1.43
Labour:
131 Painter Day 0.17 180.00 30.60
114 Beldar Day 0.17 207.00 35.19
9999 Sundries, brushes etc. L.S 13.52 1.00 13.52
TOTAL 152.74
Add 1% for water charges 1.53
TOTAL 154.27
Add for contractor’s profit and 23.14
overheads @15%
Cost of 10 sqm 177.41
Cost of 1 sqm 17.74
Say 17.74
22.13 Deduct for omitting in water proofing treatment final course of spreading stone grit 6mm or
down size or pea sized gravel:
22.13.1 At 6 cudm per sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:
1177 Stone grit 6mm or down size 6x10 cum 0.06 700.00 42.00
2202 Carriage of stone grit cum 0.06 53.21 3.19
9999 Labour for screening and spreading L.S 21.58 1.00 21.58
grit
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 73.53
Add 1% for water charges 0.74
TOTAL 74.27
Add for contractor’s profit and 11.14
overheads @15%
Cost of 10 sqm 85.41
Cost of 1 sqm 8.54
Say 8.54

22.13 Deduct for omitting in water proofing treatment final course of spreading stone grit 6mm or
down size or pea sized gravel:
22.13.2 At 8 cudm per sqm.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials:
1177 Stone grit 6mm or down size 6x10 cum 0.08 700.00 56.00
2202 Carriage of stone grit cum 0.08 53.21 4.26
9999 Labour for screening and spreading L.S 26.91 1.00 26.91
grit
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 93.93
Add 1% for water charges 0.94
TOTAL 94.87
Add for contractor’s profit and 14.23
overheads @15%
Cost of 10 sqm 109.10
Cost of 1 sqm 10.91
Say 10.91

22.14 Grading roof for water proofing treatment with


22.14.1 Cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal
C ode
size) Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
M aterials:
295 Stone aggregate 20mm cum 0.67 1100.00 737.00
297 Stone aggregate 10 mm cum 0.22 1100.00 242.00
2202 Carriage of aggregate cum 0.89 53.21 47.36
982 Coarse sand cum 0.45 300.00 135.00
2203 C arriage of c oarse sand cum 0.45 53.21 23.94
367 Cement (0.2833 cum) tonne 0.32 5200.00 1664.00
2209 Carriage of cement tonne 0.32 47.29 15.13
Labour:
123 Mason !st class Day 0.1 270 27.00
114 Beldar Day 1.63 207 337.41
101 Bhishti Day 0.7 180 126.00
2 M ixer Day 0.07 400 28.00
12 Vibrator Day 0.07 150 10.50
9999 Sundries, brushes etc. L.S. 14.3 1.00 14.30
9999 Sundries for laying on terrace L.S. 45.76 1.00 45.76
TOTAL 3453.40
Add 1% for water charges 34.53
TOTAL 3487.94
Add 15 % for contractor’s profit and overheads 523.19
Cost of 1 cum. 4011.13
Say 4,011.13

22.14 Grading roof for water proofing treatment with


22.14.2 Cement mortar 1:3(1 cement: 3 coarse sand)
C ode Discription Unit Quantity Rate Amount
Details of c ost for one cum.
Materials:
Cem ent mortar 1:3 (Rate as per item cum 1.00 3262.33 3262.33
no. 3.8)
Labour
155 M ason Day 1 180 180.00
114 Beldar Day 2 207 414.00
101 Bhishti Day 0.5 180 90.00
115 Coolie Day 5 207 1035.00
9999 Sundries L.S. 11.7 1.00 11.70
TOTAL 4993.03
Add 1% for water charges 49.93
TOTAL 5042.96
Add 15 % for contractor’s profit and overheads 756.44
Cost of 1 cum. 5799.40
Say 5,799.40

22.14 Grading roof for water proofing treatment with


22.14.3 Cement mortar 1:4 (lcement: 4 coarse sand)
C ode Discription Unit Quantity Rate Amount
Details of c ost for one cum.
Materials:
Cem ent mortar 1:4 (Rate as per item cum 1.00 2580.18 2580.18
no. 3.9)
Labour
155 M ason Day 1 180 180.00
114 Beldar Day 2 207 414.00
101 Bhishti Day 0.5 180 90.00
115 Coolie Day 5 207 1035.00
9999 Sundries L.S. 10.79 1.00 10.79
TOTAL 4309.97
Add 1% for water charges 43.10
TOTAL 4353.07
Add 15 % for contractor’s profit and overheads 652.96
Cost of 1 cum. 5006.03
Say 5,006.03

22.15 Providing and laying in situ seven course water proofing treatment with APP (Atactic poly-
propylene) modified Polymeric membrane over roof consisting of first coat of bitumen primer @
0.40Kg per sqm, 2nd, 4th & 6th courses of bonding material @1.20 Kg/sqm, which shall consist of
blown type bitumen of grade 85/25 conforming to IS : 702, 3rd and 5th layers of roofing
membrane APP modified Polymeric membrane 1.5mm thick of 2.25 Kg/sqm weight consisting of
five layers prefabricated with centre core as 20micron HMHDPE film sandwitched on both
sides with polymeric mix and the polymeric mix is protected on both side with 20micron
HMHDPE film. 7th, the top most layer shall be finished with brick tiles of class designation 100
grouted with cement mortar 1:3 (lcement:3 fine sand) mixed with 2% integral water proofing
compound by weight of cement over a 12mm layer of cement mortar 1:3 (1 cement: 3 fine sand)
and finished neat which shall be paid for separately as per D SR Item No. 12.19.

C ode Discription Unit Quantity Rate Amount


Details of cost for 30 sqm
MATERIAL
8200 APP modified polymeric felt (two sqm 66.00 50.00 3300.00
layers) 1.5 mm thick
0316 Bitumenous solution primer litre 12 30.00 360.00
313 Blown type petroleum bitumen of tonne 0.11 35000.00 3780.00
penetration 85/25 of approved quality

2211 Carriage of bitumen and felt tonne 0.12 53.21 6.39


9999 Carriage of polymeric felt L.S. 7.8 1.00 7.80
370 Fuel (Steam coal) quintal 0.174 120.00 20.88
2200 Carriage of fuel tonne 0.0174 60.81 1.06
9999 Preparing roof surface, cutting L.S. 134.55 1.00 134.55
grooves and making good the same

Labour:
131 Painter Day 2.16 180.00 388.80
114 Beldar Day 3.24 207.00 670.68
130 Mistries Day 0.18 270.00 48.60
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 8725.51
Add 1% for water charges 87.26
TOTAL 8812.77
Add for contractor’s profit and 1321.92
overheads @15%
Cost of 30 sqm 10134.68
Cost of 1 sqm 337.82
Say 337.82

22.16 Providing and laying in situ five course water proofing treatment with APP (Atactic
Polypropylene) modified Polymeric membrane over roof consisting of first coat of bitumen primer
@ 0.40K g per sqm, 2nd & 4th courses of bonding material @ 1.20Kg/sqm, which shall consist of
blown type bitumen of grade 85/25 conforming to IS: 702, 3rd layer of roofing membrane APP
modified Polymeric membrane 2.0mm thick of 3.00 Kg/sqm weight consisting of five layers
prefabricated with centre core as 100 micron HMHDPE film sandwitched on both sides with
polymeric mix and the polymeric mix is protected on both side with 20micron HMHD PE film .
5th, the top most layer shall be finished with brick tiles of class designation 100 grouted with
cement mortar 1:3 (1 cement: 3 fine (1 cement : 3 fine sand) and finished neat which shall be
paid for separately as persand) mixed with 2% integral water proofing compound by weight of
cement over a 12mm layer of cement mortar 1:3 DSR Item No. 12.19.
C ode Discription Unit Quantity Rate Amount
Details of cost for 30 sqm
MATERIAL
8201 APP modified polymeric felt (two sqm 33.00 85.00 2805.00
layers) 2.0 mm thick
0316 Bitumenous solution primer litre 12 30.00 360.00
313 Blown type petroleum bitumen of tonne 0.07 35000.00 2520.00
penetration 85/25 of approved quality

2211 Carriage of bitumen and felt tonne 0.08 53.21 4.47


9999 Carriage of polymeric felt L.S. 7.8 1.00 7.80
370 Fuel (Steam coal) quintal 0.174 120.00 20.88
2200 Carriage of fuel tonne 0.0174 60.81 1.06
9999 Preparing roof surface, cutting L.S. 134.55 1.00 134.55
grooves and making good the same

Labour:
131 Painter Day 1.58 180.00 284.40
114 Beldar Day 2.37 207.00 490.59
130 Mistries Day 0.13 270.00 35.10
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 6670.61
Add 1% for water charges 66.71
TOTAL 6737.31
Add for contractor’s profit and 1010.60
overheads @15%
Cost of 30 sqm 7747.91
Cost of 1 sqm 258.26
Say 258.26

22.17 Providing and laying in situ seven course water proofing treatment with APP (Atactic
Polypropylene) modified Polymeric membrane over roof consisting of first coat of bitumen primer
@ 0.40Kg per sqm, 2nd, 4th & 6th courses of bonding material @ 1.20 Kg/sqm, which shall consist
of blown type bitumen of grade 85/25 conforming to IS : 702, 3rd and 5th layers of roofing
membrane APP modified Polymeric membrane 2.0mm thick of 3.00 Kg/sqm weight consisting of
five layers prefabricated with centre core as 100 micron HMHDPE film sandwitched on both
sides with polymeric mix and the polymeric mix is protected on both side with 20micron
HMHDPE film. 7th, the top most layer shall be finished with brick tiles of class designation 100
grouted with cement mortar 1:3 (1 cement: 3 fine sand) mixed with 2% integral water proofing
compound by weight of cement over a 12 mm layer of cement mortar 1:3 ( 1 cement: 3 fine sand)
and finished neat which shall be paid for separately as per DSR Item No. 12.19.

C ode Discription Unit Quantity Rate Amount


Details of cost for 30 sqm
MATERIAL
8201 APP modified polymeric felt (two sqm 66.00 85.00 5610.00
layers) 2.0 mm thick
0316 Bitumenous solution primer litre 12 30.00 360.00
313 Blown type petroleum bitumen of tonne 0.11 35000.00 3780.00
penetration 85/25 of approved quality
2211 Carriage of bitumen and felt tonne 0.12 53.21 6.39
9999 Carriage of polymeric felt L.S. 7.8 1.00 7.80
370 Fuel (Steam coal) quintal 0.174 120.00 20.88
2200 Carriage of fuel tonne 0.0174 60.81 1.06
9999 Preparing roof surface, cutting L.S. 134.55 1.00 134.55
grooves and making good the same

Labour:
131 Painter Day 2.16 180.00 388.80
114 Beldar Day 3.24 207.00 670.68
130 Mistries Day 0.18 270.00 48.60
9999 Sundries, brushes etc. L.S 6.76 1.00 6.76
TOTAL 11035.51
Add 1% for water charges 110.36
TOTAL 11145.87
Add for contractor’s profit and 1671.88
overheads @15%
Cost of 30 sqm 12817.75
Cost of 1 sqm 427.26
Say 427.26
22.18 Providing and fixing APP (Atactic Polypropylene Polymer) modified prefabricated five layer
2mm thick water proofing membrance, black finished reinforced with glass fibre matt consisting of
a coat of bitumen primer for bitumen membrane @ 0.40 ltr/sq. mt. by the same membrane
manufacturer of density at 25°C, 0.87 - 0.89 kg/ ltr and viscosity 70 - 160 cps. Over the primer coat
the layer of membrane shall be laid using Butane torch and sealing all joints etc., and preparing the
surface complete. The vital physical and chemical parameters of the membrane shall be as under :
Joint strength in longitudinal and transverse direction at 23°C as 350/300 N/5cm. Tear strength in
longitudinal and transverse direction as 60/80N. Softening point of membrane not less than 150°C.
Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147. The laying of
membrane shall be got done through the authorised applicator of the manufacturer of membrane:

22.18.1 2mm (for corrugated roof sheets)


C ode Discription Unit Quantity Rate Amount
Details of cost for 30 sqm
MATERIAL
8203 A.P.P. modified 2 mm thick membrane sqm 33.00 147.00 4851.00
reinforced with glass fibre matt
8206 Bitumen primer for bitumen litre 12.00 54.00 648.00
membrane
2211 Carriage of bitumen and felt tonne 0.01 53.21 0.64
9999 Carriage of polymeric felt L.S. 7.8 1.00 7.80
1241 Com mercial LPG in cylinder. kg 7 35.00 245.00
9999 Preparing roof surface, cutting L.S. 49.53 1.00 49.53
grooves and making good the same

Labour:
159 Skilled torch operator for laying tack Day 2.16 180.00 388.80

114 Beldar Day 3.24 207.00 670.68


130 Mistries Day 0.18 270.00 48.60
9999 Sundries, brushes etc. L.S 23.4 1.00 23.40
TOTAL 6933.45
Add 1% for water charges 69.33
TOTAL 7002.78
Add for contractor’s profit and 1050.42
overheads @15%
Cost of 30 sqm 8053.20
Cost of 1 sqm 268.44
Say 268.44
22.19 Providing and laying APP (Atactic Polypropylene Polymer) modified prefabricated five layer,
3mm thick water proofing membrane, black finished reinforced with glass fibre matt consisting of a
coat of bitumen primer for bitumen membrane @ 0.40 ltr/sqm. by the same membrane
manufacturer of density at 25°C, 0.87 - 0.89 kg/ltr and viscosity 70 - 160 cps. Over the primer coat
the layer of membrane shall be laid using butane torch and sealing all joints etc., and preparing the
surface complete. The vital physical and chemical parameters of the membrane shall be as under :
Joint strength in longitudinal and transverse direction at 23°C as 350/300 N/5cm. Tear strength in
longitudinal and transverse direction as 60/80N. Softening point of membrane not less than 150°C.
Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147. The laying of
membrane shall be got done through the authorised applicator of the manufacturer of membrane:

22.19.1 3 mm thick
C ode Discription Unit Quantity Rate Amount
Details of cost for 30 sqm
MATERIAL
8204 A.P.P. modified 3 mm thick membrane sqm 33.00 185.00 6105.00
reinforced with glass fibre matt

8206 Bitumen primer for bitumen litre 12.00 54.00 648.00


membrane
2211 Carriage of bitumen and felt tonne 0.01 53.21 0.64
9999 Carriage of polymeric felt L.S. 7.8 1.00 7.80
1241 Com mercial LPG in cylinder. kg 7 35.00 245.00
9999 Preparing roof surface, cutting L.S. 49.53 1.00 49.53
grooves and making good the same

Labour:
159 Skilled torch operator for laying tack Day 2.16 180.00 388.80

114 Beldar Day 3.24 207.00 670.68


130 Mistries Day 0.18 270.00 48.60
9999 Sundries, brushes etc. L.S 23.4 1.00 23.40
TOTAL 8187.45
Add 1% for water charges 81.87
TOTAL 8269.32
Add for contractor’s profit and 1240.40
overheads @15%
Cost of 30 sqm 9509.72
Cost of 1 sqm 316.99
Say 316.99
22.20 Providing and laying APP (Atactic Polypropylene Polymer) modified prefabricated five layer
3mm thick water proofing membrane, black finished reinforced with non-woven polyester matt
consisting of a coat of bitumen primer for bitumen membrane @ 0.40 ltr/sqm. by the same
membrane manufacturer of density at 25°C, 0.87-0.89 kg/ltr and viscosity 70-160 cps. Over the
primer coat the layer of membrane shall be laid using Butane Torch and sealing all joints etc. , and
preparing the surface complete. The vital physical and chemical parameters of the membrane shall
be as under : Joint strength in longitudinal and transverse direction at 23°C as 650/450N/5cm. Tear
strength in longitudinal and transverse direction as 300/250N. Softening point of membrane not less
than 150°C. Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147.
The laying of membrane shall be got done through the authorised applicator of the manufacturer of
membrane.

22.20.1 3 mm thick
C ode Discription Unit Quantity Rate Amount
Details of cost for 30 sqm
MATERIAL
8205 A.P.P. modified 3 mm thick membrane sqm 33.00 221.00 7293.00
reinforced with polyester matt
8206 Bitumen primer for bitumen litre 12.00 54.00 648.00
membrane
2211 Carriage of bitumen and felt tonne 0.01 53.21 0.64
9999 Carriage of polymeric felt L.S. 7.8 1.00 7.80
1241 Com mercial LPG in cylinder. kg 7 35.00 245.00
9999 Preparing roof surface, cutting L.S. 49.53 1.00 49.53
grooves and making good the same

Labour:
159 Skilled torch operator for laying tack Day 2.16 180.00 388.80

114 Beldar Day 3.24 207.00 670.68


130 Mistries Day 0.18 270.00 48.60
9999 Sundries, brushes etc. L.S 23.4 1.00 23.40
TOTAL 9375.45
Add 1% for water charges 93.75
TOTAL 9469.20
Add for contractor’s profit and 1420.38
overheads @15%
Cost of 30 sqm 10889.58
Cost of 1 sqm 362.99
Say 362.99

22.21 Extra for covering top of membrane with Geotextile, 120gsm non woven, 100% polyester
of thickness 1 to 1.25mm bonded to the membrane with intermittent touch by heating the membrane
by Butane Torch as per m anufactures recommendation [for Item No. 25.18 to 25.20]
C ode Discription Unit Quantity Rate Amount
Details of cost for 30 sqm
MATERIAL
8207 Geotextile 120 gsm m embrane litre 31.50 25.00 787.50
9999 Carriage of geotextile L.S. 7.8 1.00 7.80
Labour:
159 Skilled torch operator for laying tack Day 0.43 180.00 77.40

114 Beldar Day 0.65 207.00 134.55


130 Mistries Day 0.04 270.00 10.80
9999 Sundries, brushes etc. L.S 46.8 1.00 46.80
TOTAL 1064.85
Add 1% for water charges 10.65
TOTAL 1075.50
Add for contractor’s profit and 161.32
overheads @15%
Cost of 30 sqm 1236.82
Cost of 1 sqm 41.23
Say 41.23
23.1 Trenching in ordinary soil upto a depth of 60cm including removal and stacking of
serviceable materials and then disposing of by spreading and neatly levelling with in a lead of
50m and making up the trenched area to proper levels by filling with earth or earth mixed with
sludge or/and manure before and after flooding trench with water (excluding cost of imported
earth, sludge or manure).
Code Description Unit Quantity Rate Amount
Details of cost for 10 cum.
Labour:
115 Coolie Day 0.35 207 72.45
114 Beldar Day 0.71 207 146.97
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 222.15
Add 1% for water charges 2.22
TOTAL 224.37
Add for contractor’s profit and 33.66
overheads @15%
Cost of 10 cum 258.03
Cost of 1 cum 25.80
Say 25.80

23.2 Supplying and stacking of good earth at site including royalty and carriage upto 1 km (earth
measured in stacks will be reduced by 20% for payment).
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Excavation:
Labour:
115 Coolie Day 0.167 207 34.57
114 Beldar Day 0.177 207 36.64
979 Roy alty for good earth cum 1 11.00 11.00
2241 Carriage of good earth by mechanical cum 1 66.51 66.51
transport upto 1 km lead
TOTAL 148.72
Add 1% for water charges 1.49
TOTAL 150.21
Add for contractor’s profit and 22.53
overheads @15%
Cost of 1 cum 172.74
Say 172.74

23.3 Supplying and stacking sludge at site including royalty and carriage upto 1 km (sludge
measured in stacks will be reduced by 8% for payment),
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
980 Royalty of sludge cum 1 60.00 60.00
2317 Carriage of good sludge mechanical cum 1 57.83 57.83
transport upto 1 km lead
TOTAL 117.83
Add 1% for water charges 1.18
TOTAL 119.01
Add for contractor’s profit and 17.85
overheads @15%
Cost of 1 cum 136.86
Say 136.86

23.4 Supplying and stacking at site dump manure from Badli or other approved source, including
carriage upto 1 km manure measured in stacks will be reduced by 8% for payment):
23.4.1 Screened through sieve of I.S. designation 20mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Labour:
114 Beldar Day 0.08 207 16.56
9,999 Sundries L.S. 2.73 1.00 2.73
2242 Carriage of dump manure by cum 1 57.83 57.83
mechanical transport upto 1 km lead
TOTAL 77.12
Add 1% for water charges 0.77
TOTAL 77.89
Add for contractor’s profit and 11.68
overheads @15%
Cost of 1 cum 89.57
Say 89.57

23.4 Supplying and stacking at site dump manure from Badli or other approved source, including
carriage upto 1 km manure measured in stacks will be reduced by 8% for payment):
23.4.2. Screened through sieve of I.S. designation 16 mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Labour:
114 Beldar Day 0.13 207 26.91
9,999 Sundries L.S. 2.73 1.00 2.73
2242 Carriage of dump manure by cum 1 57.83 57.83
mechanical transport upto 1 km lead
TOTAL 87.47
Add 1% for water charges 0.87
TOTAL 88.34
Add for contractor’s profit and 13.25
overheads @15%
Cost of 1 cum 101.60
Say 101.60
23.4 Supplying and stacking at site dump manure from Badli or other approved source, including
carriage upto 1 km manure measured in stacks will be reduced by 8% for payment):
23.4.3 Screened through sieve of I.S. designation 4.75mm
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Labour:
114 Beldar Day 0.17 207 35.19
9,999 Sundries L.S. 2.73 1.00 2.73
2242 Carriage of dump manure by cum 1 57.83 57.83
mechanical transport upto 1 km lead
TOTAL 95.75
Add 1% for water charges 0.96
TOTAL 96.71
Add for contractor’s profit and 14.51
overheads @15%
Cost of 1 cum 111.21
Say 111.21

23.5 Rough dressing the trenched ground including breaking clods.


Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.2 207 41.40
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 42.83
Add 1% for water charges 0.43
TOTAL 43.26
Add for contractor’s profit and 6.49
overheads @15%
Cost of 100 sqm 49.75
Say 49.75

23.6 Uprooting weeds from the trenched area after 10 to 15 days of its flooding with water
including disposal of uprooted vegetation.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.33 207 68.31
115 Coolie Day 0.33 207 68.31
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 139.35
Add 1% for water charges 1.39
TOTAL 140.74
Add for contractor’s profit and 21.11
overheads @15%
Cost of 100 sqm 161.86
Say 161.86

23.7 Fine dressing the ground.


Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.5 207 103.50
9,999 Sundries L.S. 1.43 1.00 1.43
TOTAL 104.93
Add 1% for water charges 1.05
TOTAL 105.98
Add for contractor’s profit and 15.90
overheads @15%
Cost of 100 sqm 121.88
Say 121.88

23.8 Spreading of sludge, dump manure or/and good earth in required thickness (Cost of sludge,
dump manure or/ and good earth to be paid separately).
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.07 207 14.49
9,999 Sundries L.S. 0.52 1.00 0.52
TOTAL 15.01
Add 1% for water charges 0.15
TOTAL 15.16
Add for contractor’s profit and 2.27
overheads @15%
Cost of 100 sqm 17.43
Say 17.43

23.9 Mixing earth and sludge or manure in proportion specified or directed.


Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.25 207 51.75
115 Coolie Day 0.25 207 51.75
TOTAL 103.50
Add 1% for water charges 1.04
TOTAL 104.54
Add for contractor’s profit and 15.68
overheads @15%
Cost of 100 sqm 120.22
Say 120.22
23.10 Grassing with ‘Doob’ grass including watering and maintenance of the lawn for 30 days or
more till the grass forms a thick lawn free from weeds and fit for mowing including supplying
good earth if needed (the good earth shall be paid for separately).
23.10.1 In rows 15 cm apart in either direction.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.25 207 51.75
115 Coolie Day 0.5 207 103.50
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 157.98
Add 1% for water charges 1.58
TOTAL 159.56
Add for contractor’s profit and 23.93
overheads @15%
Cost of 100 sqm 183.49
Say 183.49

23.10 Grassing with ‘Doob’ grass including watering and maintenance of the lawn for 30 days or
more till the grass forms a thick lawn free from weeds and fit for mowing including supplying
good earth if needed (the good earth shall be paid for separately).
23.10.2 In rows 7.5 cm apart in either direction.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.5 207 103.50
115 Coolie Day 1.06 207 219.42
9,999 Sundries L.S. 5.33 1.00 5.33
TOTAL 328.25
Add 1% for water charges 3.28
TOTAL 331.53
Add for contractor’s profit and 49.73
overheads @15%
Cost of 100 sqm 381.26
Say 381.26

23.10 Grassing with ‘Doob’ grass including watering and maintenance of the lawn for 30 days or
more till the grass forms a thick lawn free from weeds and fit for mowing including supplying
good earth if needed (the good earth shall be paid for separately).
23.10.3 In rows 5 cm apart in either direction.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.8 207 165.60
115 Coolie Day 1.6 207 331.20
9,999 Sundries L.S. 6.76 1.00 6.76
TOTAL 503.56
Add 1% for water charges 5.04
TOTAL 508.60
Add for contractor’s profit and 76.29
overheads @15%
Cost of 100 sqm 584.88
Say 584.88

23.11 Renovating lawns including weeding, cheeling the grass, forking the ground, top dressing
with sludge or manure, mixing the same with forked soil, watering and maintaining the lawn for
30 days or more till the grass forms a thick lawn free from weeds and fit for mowing and disposal
of rubbish as directed, including supplying good earth if needed but excluding the cost of sludge
or manure (the good earth shall be paid for separately).
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 2.7 207 558.90
115 Coolie Day 2 207 414.00
9,999 Sundries L.S. 2.73 1.00 2.73
TOTAL 975.63
Add 1% for water charges 9.76
TOTAL 985.39
Add for contractor’s profit and 147.81
overheads @15%
Cost of 100 sqm 1133.19
Say 1133.19

23.12 Uprooting rank vegetation and weeds by digging the area to a depth of 60cm removing all
weeds and other growth with roots by forking repeatedly, rough dressing, flooding with water,
uprooting fresh growths after 10 to 15 days breaking clods, and then fine dressing for planting
new grass, including disposal of all rubbish with all leads and lifts.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 5.66 207 1171.62
115 Coolie Day 2.64 207 546.48
9,999 Sundries L.S. 12.35 1.00 12.35
TOTAL 1730.45
Add 1% for water charges 17.30
TOTAL 1747.75
Add for contractor’s profit and 262.16
overheads @15%
Cost of 100 sqm 2009.92
Say 2009.92

23.13 Preparation of beds for hedging and shrubbery by excavating 60cm deep and trenching the
excavated base to a further depth of 30cm, refilling the excavated earth after breaking clods and
mixing with sludge or manure in the ratio of 8:1 (8 parts of stacked volume of earth after
reduction by 20% : one part of stacked volume of sludge or manure after reduction by 8%),
flooding with water, filling with earth if necessary, watering and finally fine dressing, levelling
etc. including stacking and disposal of materials declared unserviceable and surplus earth by
spreading and levelling as directed, within a lead of 50m lift upto 1.5 m complete (cost of sludge,
manure or extra earth to be paid for separately).
Code Description Unit Quantity Rate Amount
Details of cost for 10 cum.
Labour:
114 Beldar Day 1.8 207 372.60
115 Coolie Day 1.25 207 258.75
TOTAL 631.35
Add 1% for water charges 6.31
TOTAL 637.66
Add for contractor’s profit and 95.65
overheads @15%
Cost of 10 cum 733.31
Cost of 1 cum 73.33
Say 73.33

23.14 Digging holes in ordinary soil and refilling the same with the excavated earth mixed with
manure or sludge in the ratio of 2:1 by volume (2 parts of stacked volume of earth after reduction
by 20% : 1 part of stacked volume of manure after reduction by 8%) flooding with water, dressing
including removal of rubbish and surplus earth, if any with all leads and lifts (cost of manure,
sludge or extra good earth if needed to be paid for separately) ;-

23.14.1 Holes 1.2 m dia and 1.2 m deep.


Code Description Unit Quantity Rate Amount
Details of cost for one hole-
(A) Extra Excavation-Rate vide item No. cum 1.36 176.45
2.8.1 Earth work 129.74
9,999 Refilling mixture and flooding L.S. 5.2 1.00 5.20
TOTAL 181.65
Add 1% for water charges except on A
0.05
TOTAL 181.70
Add for contractor’s profit and
overheads @15% except on A 0.79
Cost of 1 no. 182.49
Say 182.49

23.14 Digging holes in ordinary soil and refilling the same with the excavated earth mixed with
manure or sludge in the ratio of 2:1 by volume (2 parts of stacked volume of earth after reduction
by 20% : 1 part of stacked volume of manure after reduction by 8%) flooding with water, dressing
including removal of rubbish and surplus earth, if any with all leads and lifts (cost of manure,
sludge or extra good earth if needed to be paid for separately) ;-

23.14.2 Holes 60 cm dia and 60 cm deep.


Code Description Unit Quantity Rate Amount
Details of cost for one hole-
(A) Extra Excavation-Rate vide item No. cum 0.17 22.06
2.8.1 Earth work 129.74
9,999 Refilling mixture and flooding L.S. 1.43 1.00 1.43
TOTAL 23.49
Add 1% for water charges except on A
0.01
TOTAL 23.50
Add for contractor’s profit and
overheads @15% except on A 0.22
Cost of 1 no. 23.72
Say 23.72

23.15 Half brick circular tree guard in 50 class designation bricks, internal diameter 1.25 metre
and height 1.2 metre above ground and 0.20 m below ground bottom two courses laid dry and top
three courses in lime mortar 1:2 (1 lime putty : 2 surkhi) or cement mortar 1:6 (1 cement : 6 fine
sand) and the intermediate courses being in dry honey comb masonry as per design complete:

23.15.1 With F.P.S. Bricks


Code Description Unit Quantity Rate Amount
Details of cost for one tree guard
Materials:
2603 Brick 3rd class 1000 230 368.00
Nos 1600.00
2201 Carriage of bricks 1000 230 32.63
Nos 141.88
9999 Lime or cement mortar top 3 courses L.S 15.86 15.86
1.00
Labour:
124 Mason 2nd class Day 0.25 223 55.75
114 Beldar Day 0.25 207 51.75
9,999 Sundries L.S. 4.16 1.00 4.16
TOTAL 528.15
Add 1% for water charges 5.28
TOTAL 533.43
Add for contractor’s profit and 80.02
overheads @15%
Cost of one tree guard 613.45
Say 613.45

23.16 Providing and fixing M.S. flat iron tree guard 60cm dia. and 2m height above ground level
formed of 4 nos. 25x6mm and 8 nos. 25x3mm vertical M.S. flats rivetted to 3 nos. 25x6mm M.S.
flat iron rings in two halves, bolted together with 8mm dia. And 30mm long bolts including
painting two coats with paint of approved brand and manufacture over a coat of priming,
complete in all respects.
Code Description Unit Quantity Rate Amount
Details of cost for one tree guard
Materials:
1008 M .S. Flats quintal 0.29 4600.00 1334.00
9999 Rivets 36 nos. L.S. 40.3 1.00 40.30
9999 G.I. Bolts and nuts L.S. 8.06 1.00 8.06
2205 Crriage of material tonne 0.029 47.29 1.37
Labour:
103 Blacksm ith 2nd class Day 2 223 446.00
114 Beldar Day 1 207 207.00
(A) Painting-(Rate as per item No. 13.50.4 sqm 1.77 15.39
of S.H. Finishing) 8.69
(A) Painting-(Rate as per item No. 13.61.1 sqm 1.77 87.94
of S.H. Finishing) 49.68
TOTAL 2140.06
Add 1% for water charges except A 20.37

TOTAL 2160.43
Add for contractor’s profit and 308.56
overheads @15% except A
cost for one tree guard 2468.99
Say 2468.99

23.17 Making tree guard 53 cm dia. and 1.3 m high as per design from empty coal tar drums
supplied free by the department including providing and fixing 2 nos. M.S. sheet rings 50 x 0.5
mm with rivets complete in all respects including painting inside and outside of tree guard with :
23.17.1 A coat of coal tar.
Code Description Unit Quantity Rate Amount
Details of cost for one tree guard
Materials:
9999 Cost of 2 putties L.S. 13.39 1.00 13.39
9999 Cost of 6mm dia x10 mm rivets 22 nos L.S. 26.91 26.91
1.00
9999 Fire wood L.S. 2.73 1.00 2.73
Labour:
103 Blacksm ith 2nd class Day 0.13 223 28.99
114 Beldar Day 0.07 207 14.49
9999 Sundries L.S. 1.43 1.00 1.43
(A) Coal tarring alround inside and outside sqm 2.16 40.10
(Rate as per item No. 13.59 of S.H.
Finishing) 18.56
TOTAL 128.04
Add 1% for water charges except A 0.88

TOTAL 128.92
Add for contractor’s profit and 13.32
overheads @15% except A
cost for one tree guard 142.24
Say 142.24

23.17 Making tree guard 53 cm dia. and 1.3 m high as per design from empty coal tar drums
supplied free by the department including providing and fixing 2 nos. M.S. sheet rings 50 x 0.5
mm with rivets complete in all respects including painting inside and outside of tree guard with :
23.17.2 Two or more coats of synthetic enamel paint of approved quality shade over a priming
coat
Code Description Unit Quantity Rate Amount
Details of cost for one tree guard
Materials:
(Rate as per item No. 23.17.1) sqm 1 142.24 142.24
Priming coat -(Rate as per item No. sqm 2.16 34.00
13.50.3 of S.H. Finishing) 15.74
Painting-(Rate as per item No. 13.61.1 sqm 2.16 107.32
of S.H. Finishing) 49.68
Less Coal tarring alround inside and outside sqm -2.16 -40.10
(Rate as per item No. 13.59 of S.H.
Finishing) 18.56
cost for one tree guard 243.46
Say 243.46

23.18 Making tree guard 53 cm dia. and 2 m high as per design from empty coal tar drums
supplied free by the department including providing and fixing four legs 40 cm long of 30 x 3 mm
M.S. flat riveted to tree guard and providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with
rivets complete in all respects including painting inside and outside of tree guard with :
23.18.1 A coat of coal tar.
Code Description Unit Quantity Rate Amount
Details of cost for one tree guard
Materials:
9999 Cost of two M.S. sheet rings L.S. 13.52 13.52
50x0.5mm 1.00
9999 Cost of 6mm dia. rivets 10mm long 50 L.S. 67.21 67.21
Nos. 1.00
9999 Fire wood L.S. 2.73 1.00 2.73
Labour:
103 Blacksm ith 2nd class Day 0.19 223 42.37
114 Beldar Day 0.1 207 20.70
9999 Sundries L.S. 1.43 1.00 1.43
1008 M .S. Flats quintal 0.013 4600.00 59.80
(A) Coal tarring alround inside and outside sqm 3.33 61.82
(Rate as per item No. 13.59 of S.H.
Finishing) 18.56
TOTAL 269.58
Add 1% for water charges except A 2.08

TOTAL 271.66
Add for contractor’s profit and 31.48
overheads @15% except A
cost for one tree guard 303.13
Say 303.13

23.18 Making tree guard 53 cm dia. and 2 m high as per design from empty coal tar drums
supplied free by the department including providing and fixing four legs 40 cm long of 30 x 3 mm
M.S. flat riveted to tree guard and providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with
rivets complete in all respects including painting inside and outside of tree guard with :
23.18.2 Two or more coats of synthetic enamel paint of approved quality and shade over a
Code
priming Description
coat. Unit Quantity Rate Amount
Details of cost for one tree guard
Materials:
(Rate as per item No. 23.18.1) sqm 1 303.13 303.13
Priming coat -(Rate as per item No. sqm 3.33 52.41
13.50.3 of S.H. Finishing) 15.74
Painting-(Rate as per item No. 13.61.1 sqm 3.33 165.45
of S.H. Finishing) 49.68
Less Coal tarring alround inside and outside sqm -3.33 -61.82
(Rate as per item No. 13.59 of S.H.
Finishing) 18.56
cost for one tree guard 459.17
Say 459.17

23.19 Edging with bricks laid dry length wise including excavation, refilling, consolidating with
hand packing and spreading neatly surplus earth within a lead of 50 m :
23.19.1 75 class designation.
23.19.1.1 F.P.S. Bricks
Code Description Unit Quantity Rate Amount
Details of cost for 10 m lenth-
Materials:
2602 F.P.S. bricks class designation75 1000 50 80.00
Nos 1600.00
2201 Carriage of bricks 1000 50 7.09
Nos 141.88
Labour:
124 Mason 2nd class Day 0.05 223 11.15
114 Beldar Day 0.05 207 10.35
9,999 Earth work in excavation and removal L.S. 13.52 13.52
of rubbish (or spereading and dressing
neatly of surplus earth) 1.00
TOTAL 122.11
Add 1% for water charges 1.22
TOTAL 123.34
Add for contractor’s profit and 18.50
overheads @15%
Cost of 10 metre 141.84
Cost of 1 metre 14.18
Say 14.18

23.19 Edging with bricks laid dry length wise including excavation, refilling, consolidating with
hand packing and spreading neatly surplus earth within a lead of 50 m :
23. 19.2 50 designation.
23.19.2.1 F.P.S. bricks.
Code Description Unit Quantity Rate Amount
Details of cost for 10 m lenth-
Materials:
2603 F.P.S. bricks class designation 50 1000 50 80.00
Nos 1600.00
2201 Carriage of bricks 1000 50 7.09
Nos 141.88
Labour:
124 Mason 2nd class Day 0.05 11.15
223
114 Beldar Day 0.05 207 10.35
9,999 Earth work in excavation and removal L.S. 13.52 13.52
of rubbish (or spereading and dressing
neatly of surplus earth) 1.00
TOTAL 122.11
Add 1% for water charges 1.22
TOTAL 123.34
Add for contractor’s profit and 18.50
overheads @15%
Cost of 10 metre 141.84
Cost of 1 metre 14.18
Say 14.18
23.20 Filling mixture of earth and sludge or manure in the desired proportion in trenches, flooding
with water and levelling (cost of supplying earth and sludge or manure and mixing excluded).
Code Description Unit Quantity Rate Amount
Details of cost for 10 cum
Labour:
114 Beldar Day 0.17 207 35.19
115 Coolie Day 0.08 207 16.56
TOTAL 51.75
Add 1% for water charges 0.52
TOTAL 52.27
Add for contractor’s profit and 7.84
overheads @15%
Cost of 10 cum 60.11
Cost of 1 cum 6.01
Say 6.01

23.21 Excavation in dumped stones or malba including stacking of serviceable and


unserviceable material separately and disposal of unserviceable material lead upto 50 m and lift
upto 1.5 m disposed material to be neatly dressed.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Labour:
114 Beldar Day 0.35 207 72.45
115 Coolie Day 0.35 207 72.45
TOTAL 144.90
Add 1% for water charges 1.45
TOTAL 146.35
Add for contractor’s profit and 21.95
overheads @15%
Cost of 1 cum 168.30
Say 168.30

23.22 Excavation in bajri path including stacking of serviceable and unservicable material lead
upto 50m and lift upto 1.5m disposed material to be neatly dressed.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Labour:
114 Beldar Day 0.43 207 89.01
115 Coolie Day 0.35 207 72.45
TOTAL 161.46
Add 1% for water charges 1.61
TOTAL 163.07
Add for contractor’s profit and 24.46
overheads @15%
Cost of 1 cum 187.54
Say 187.54

23.23 Excation in water bound macadam road including stacking the srviceable and unserviceable
material separately and disposal of unservuceabke materil lead upto 50 m and lift upto 1.5 m
disposed material to be neatly dressed.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Labour:
114 Beldar Day 0.53 207 109.71
115 Coolie Day 0.43 207 89.01
TOTAL 198.72
Add 1% for water charges 1.99
TOTAL 200.71
Add for contractor’s profit and 30.11
overheads @15%
Cost of 1 cum 230.81
Say 230.81

23.24 Flodding the ground with water including making kiaries and dismantling the same.
Code Description Unit Quantity Rate Amount
Details of cost for 100 sqm
Labour:
114 Beldar Day 0.17 207 35.19
9,999 Sundries L.S. 35.88 1.00 35.88
TOTAL 71.07
Add 1% for water charges 0.71
TOTAL 71.78
Add for contractor’s profit and 10.77
overheads @15%
Cost of 100 sqm 82.55
Say 82.55
2.6 Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding
30cm in depth. 1.5m in width as well as 10 sqm on plan) including disposal of excavated earth, lead upto 50m and
2.6 lift upto 1.5m, disposed earth to be levelled and neatly dressed.
2.6.1 All kinds of soil
Code Description Unit Quantity Rate A mount
Details of cost for 10 cum.
Average output of Hydraulic Excavator per
hour = 30cum.
MACHINER Y
20 Hydraulic ExcaDay 0.04125 8000 330
18 Hire and runnDay 0.04125 8000 330
Labour-
128 Mate Day 0.32 543.83 174.0256
115 Beldar/Coolie Day 1.2 464.1 556.92
TOTAL 1390.946
Add I % for water charges 13.90946
TOTAL 1404.855
Add 15% for contractor’s profit and overheads 210.7283
Cost of 10 cum 1615.583
Cost of 1 cum 161.5583
Say 161.56

4.1 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering
-All work upto plinth level:
4.1.3 1:2:4 ( 1 Cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
C ode Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
M aterials:
295 Stone aggregate 20mm cum 0.67 1400 938
297 Stone aggregate 10 mm cum 0.22 1400 308
2202 Carriage of aggregate cum 0.89 138.63 123.3807
982 Coarse sand cum 0.445 800 356
2203 C arriage of c oarse sand cum 0.445 138.67 61.70815
367 Cement (0.2833 cum) tonne 0.32 3960 1267.2
2209 Carriage of cement tonne 0.32 123.25 39.44
Labour:
155 M ason Day 0.1 655.69 65.569
114 Beldar Day 1.63 464.1 756.483
101 Bhishti Day 0.7 543.83 380.681
2 M ixer Day 0.07 1000 70
12 Vibrator Day 0.07 500 35
9999 Sundries L.S. 14.3 1.7 24.31
TOTAL 4425.772
Add 1% for water charges 44.25772
TOTAL 4470.03
Add 15 % for contractor’s profit and overheads 670.5044
Cost of 1 cum. 5140.534
Say 5140.534

5.1 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring,
shuttering, finishing and reinforcement - All work upto plinth level:
5.1.2 1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum
MATER IALS
295 Stone aggregate 20mm cum 0.57 1400.00 798.00

297 Stone aggregate 10mm cum 0.28 1400.00 392.00

2202 Carriage of aggregate 20mm and 10 mm cum 0.85 138.63 117.84

982 Coarse sand cum 0.425 800.00 340.00


2203 Carriage of coarse sand cum 0.425 138.67 58.93
367 Cement (0.2833 cum) tonne 0.4 3960.00 1584.00
2209 Carriage of cem ent tunne 0.4 123.25 49.30
Labour;
155 Mason Day 0.17 655.69 111.47
114 Beldar Day 2 464.1 928.20
101 Bhishti Day 0.9 543.83 489.45
2 Mixer Day 0.07 1000 70.00
12 Vibrator Day 0.07 500 35.00
9999 Sundries L.S 14.3 1.70 24.31
TOTAL 4998.49
Add 1% for water charges 49.98
TOTAL 5048.48
Add 15 % for contractor’s profit and overheads 757.27
Cost of 1 cum. 5805.75
Say 5,805.75

5.2 Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string
courses, fillets, columns, pillars, piers, abutments, posts and struts etc. upto floor five level excluding cost of centring,
shuttering, finishing and reinforcement :
5.2.2 1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
Code Discription Unit Quantity Rate Amount
Details of cost for 9.18 cum
MATER IALS
295 Stone aggregate 20mm cum 5.2326 1400 7325.64
297 Stone aggregate 10mm cum 2.5704 1400 3598.56
2202 Carriage of aggregate 20mm and 10 mm cum 7.803 138 1076.814
982 Coarse sand cum 3.9015 800 3121.2
2203 Carriage of coarse sand cum 3.9015 138 538.407
367 Cement (0.2225 cum) tonne 3.672 3960 14541.12
2209 Carriage of cem ent tunne 3.672 123.25 452.574
Labour;
114 Beldar Day 11.29 464.1 5239.689
115 Coolie Day 7.53 464.1 3494.673
101 Bhishti Day 8.26 543.83 4492.036
123 Mason 1st class Day 0.92 655.69 603.2348
124 Mason 2nd class Day 0.92 543.83 500.3236
2 Mixer Day 0.64 1000 640
12 Vibrator Day 0.64 500 320
9999 Sundries L.S 131.82 1.7 224.094
9999 Scaffolding L.S 420.03 1.7 714.051
Extra labour for lifting of material upto floor V level: Coolie (0.75x9.18x2.5)
115 Coolie Day 17.2 464.1 7982.52
TOTAL 54864.94
Add 1% for water charges 548.6494
TOTAL 55413.59
Add 15 % for contractor’s profit and overheads 8312.038
Cost of 9.18 cum. 63725.62
cost of 1 cum. 6941.789
Say 6941.789

5.9 Centring and shuttering including strutting, propping etc. and removal of form for :

5.9.1 Foundations, footings, bases of columns, etc. for mass concrete.


Code Description Unit Quantity Rate Amount
Details of cost for footing size 2.7m x2.7mx 1.00m Contact area = 10.8 sqm.
Materials:–
Assuming shuttering material will become unserviceable after use of 40 times Adding for maintenance @ 10%
of cost Taking salvage value after full use of material @ 25% of cost
7319 Wall form panel 1250x500mm each 0.34 1050.00 357.00
7326 Corner angle (1.5m long) each 0.085 300.00 25.50
7327 100mm channel shoulders 2.5m long each 0.17 1160.00 197.20
7328 Double clip (bridge clip) each 0.34 97.00 32.98
7329 Single clip each 0.17 77.00 13.09
7330 MS tube 40mm - 4x2.7m = 10.8m metre 0.2295 280.00 64.26
9999 Assembly nuts & bolts L.S. 22.1 1.70 37.57
9999 Carriage L.S. 78 1.70 132.60
Labour:
0 116 Fitter Frade-I Day 0.75 655.69 491.77
0 114 Beldar Day 1.5 464.10 696.15
9999 Shuttering oil L.S. 52 1.70 88.40
9999 Sundries L.S. 26 1.70 44.20
TOTAL 2180.72
Add 1 % for water charges 21.81
TOTAL 2202.52
Add 15% for contractor’s profit and overheads 330.38
Cost for 10.8 sqm. 2532.90
Cost per sqm. 234.53
Say 234.53

5.9 Centring and shuttering including strutting, propping etc. and removal of form for :
5.9.2 Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc.
Code Description Unit Quantity Rate Amount
Details for 7.9m long and 1,00m high wall Area of contact 2x7.9x1.0 = 15.8 sqm.
Materials:–
Assuming shuttering material will become unserviceable after use of 40 times Adding for maintenance @ 10%
of cost Taking salvage value after full use of material @ 25% of cost
7319 Wall form panel 1250x500mm (1.25x0.5) each 0.51 1050.00 535.50
7327 100mm channel shoulders 2.5m long each 0.17 1160.00 197.20
7328 Double clip (bridge clip) each 0.51 97.00 49.47
7329 Single clip each 0.255 77.00 19.64
7330 MS tube 40mm - 4x2.7m = 10.8m metre 0.68 280.00 190.40
9999 Assembly nuts & bolts L.S. 27.62 1.70 46.95
9999 Carriage L.S. 78 1.70 132.60
Labour:
0 116 Fitter Frade-I Day 3.5 655.69 2294.92
0 114 Beldar Day 6 464.1 2784.60
9999 Shuttering oil L.S. 78 1.70 132.60
9999 Sundries L.S. 52 1.70 88.40
TOTAL 6472.27
Add 1 % for water charges 64.72
TOTAL 6537.00
Add 15% for contractor’s profit and overheads 980.55
Cost for 15.8 sqm. 7517.55
Cost per sqm. 475.79
Say 475.79

5.9 Centring and shuttering including strutting, propping etc. and removal of form for:
5.9.3 Suspended floors, roofs, landings, balconies and access platform.
Code Description Unit Quantity Rate Amount
Detail of cost for a room 4.50x3 = 13.50 sqm, height 3.5 m
Materials :
Assuming shuttering material will become unserviceable after use of 40 times Adding for maintenance @ 10%
of cost Taking
(X)salvage value
Rate as per itemafter
no full
10.1use of material @ 25% of cost kg 9.2055 62.42 574.61
7342 2. Adjustable span- ESOSI (2.35-3.40m) each 0.1063 480.00 51.02
7343 3. Adjustable telescopi prop 3m(2.02-3.75m) each 0.1275 300.00 38.25
9999 4. Assembly nut & bolts etc. L.S. 22.1 1.70 37.57
9999 Carriage L.S. 130 1.70 221.00
Labour:
0 116 Fitter Frade-I Day 3 655.69 1967.07
0 114 Beldar Day 6 464.1 2784.60
9999 Shuttering oil L.S. 78 1.70 132.60
9999 Sundries, paper tape etc L.S. 49.7 1.70 84.49
TOTAL 5891.21
Add 1 % for water charges except X 58.91
TOTAL 5950.12
Add 15% for contractor’s profit and overheads except
x 892.52
Cost for 13.5 sqm. 6842.64
Cost per sqm. 506.86
Say 506.86

5.22 : Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all
complete.
5.22.3 : Cold twisted bars
Code Description Unit Quantity Rate Amount
Details of cost for 1 quintal-
Materials:
1005 Cold twisted bars = 1.00 q Add 5% wastage =
0.05 quintal 1.05 4000.00 4200.00
2205 Carriage of steel 1.05/10 = 0.105t tonne 0.105 250 26.25
9999 Sundries L.S. 26 1.70 44.20
Labour: For straightening, cutting, bending, binding and placing in position-
102 Blacksmith 1st class Day 1 655.69 655.69
114 Beldar Day 1 464.1 464.10
9999 Sundries and binding wire L.S. 26.91 1.70 45.75
TOTAL 5435.99
Add 1 % for water charges 54.36
TOTAL 5490.35
Add 15% for contractor’s profit and overheads 823.55
Cost of one quintal 6313.90
Cost of 1 kg 63.14
Say 63.14

Вам также может понравиться