Академический Документы
Профессиональный Документы
Культура Документы
Owner’s Engineer
Contractor
Sub-Supplier
Project
Title
CONTENTS
1. INTRODUCTION ........................................................................................................................................... 3
1.1. Scope ................................................................................................................................................................. 3
1.2. Applicable Code& Standard ........................................................................................................................... 3
1.3. Project Reference Document .......................................................................................................................... 3
1.4. Abbreviations ................................................................................................................................................... 4
2. AIR CONDITIONING CALCULATION ..................................................................................................... 5
2.1. Design Input ..................................................................................................................................................... 5
2.2. Outdoor Design Condition .............................................................................................................................. 5
2.3. Indoor Design Condition ................................................................................................................................. 6
2.4. People and Occupancy .................................................................................................................................... 6
2.5 U-Value and Shading Coefficient ................................................................................................................... 6
2.6 Equipment Heat Dissipation ........................................................................................................................... 6
3. VENTILATION REQUIREMENT CALCULATION ................................................................................. 7
3.1 Exhaust Air for Chlorination Building .......................................................................................................... 7
4. SUMMARY OF AIR CONDITIONING SYSTEM ...................................................................................... 7
5. HVAC EQUIPMENT SELECTION .............................................................................................................. 7
5.1. AC Equipment Selection ................................................................................................................................. 7
5.2. Fan Equipment Selection ................................................................................................................................ 7
6. APPENDIX ...................................................................................................................................................... 7
6.1 Appendix A - Weather Data…………………………………………………………………………………….
6.2 Appendix B - Schedule Construction…………………………………………………………………………..
6.3 Appendix C - Schedule Input Data……………………………………………………………………………..
6.4 Appendix D - Space Input Data………………………………………………………………………………...
6.5 Appendix E - System Design Summary………………………………………………………………………..
6.6 Appendix F - ASHRAE STD 62.1 2017, ASHRAE Hanbook Fundamental (SI) 2009 and ASHRAE
Handbook Application (SI) 2013……………………………………………………………………………….
Rev. 0 2 of 7
HVAC CALCULATION FOR WATER TREATMENT PLANT
GRT-HM05-P0UGD-125452
1. INTRODUCTION
1.1. Scope
This report describes conceptually the proposed system and performance requirements for Heating,
Ventilating and Air Conditioning (HVAC) services for Grati Add On Block 2 Project With Minimum
Net Dependable Capacity of 150MW. This report is minimum cooling load and ventilation
requirement for sizing to HVAC equipment. The cooling load has been calculated in a accordance with
ASHRAE Fundamentals using the software/|Program E-20 System Design Load version 4.61.
Rev. 0 3 of 7
HVAC CALCULATION FOR WATER TREATMENT PLANT
GRT-HM05-P0UGD-125452
1.4. Abbreviations
Term Definition
ACH Air Change per Hour
American Society of Heating, Refrigerating and Air Conditioning
ASHRAE
Engineers
°C degrees Celsius
CMH Cubic meters per hour
H Enthalpy
hr hour
kg kilogram
kW kilowatt
L/s Liters per second
MAX Maximum
m meters
2
m Square meters
m3 Cubic meters
MIN Minimum
N/C Not Conditioned
Pa Pascal
RH Relative Humidity
TEMP Temperature
VENT Ventilation
W watt
% percent
∆ Delta
NE North East
NW North West
SE South East
SW South West
Rev. 0 4 of 7
HVAC CALCULATION FOR WATER TREATMENT PLANT
GRT-HM05-P0UGD-125452
m2 m NE NW SE SW
1. Panel Room 8.6 3.0 - 9.8 - 8.0
Reference:
• GRT-CA00-P0UGD-175345 Architectural Chlorination Building Plan, View, Section, &
Finishing Schedule
Min. 52.5
Max. 93.8
Ambient Temperature
Min. 19.0
Max. 35.0
Rev. 0 5 of 7
HVAC CALCULATION FOR WATER TREATMENT PLANT
GRT-HM05-P0UGD-125452
• Elevation : 5.0
• General : The climatic is tropical with along rainy season from October/November to
March/April
Min.
Temperature Humidity Min. Vent
Pressurized
No Room
Min. Max. Min. Max.
(Pa) (ACH)
(°C) (°C) % %
1. Panel Room 22.0 24.00 N/C N/C N/C 6
Water Treatment
2. N/C N/C N/C N/C Negative 12
Area
Rev. 0 6 of 7
HVAC CALCULATION FOR WATER TREATMENT PLANT
GRT-HM05-P0UGD-125452
Duct Heater
Total Heat Sensible Heat Supply Air Fresh Air
No Service Capacity
Rev. 0 7 of 7
HVAC CALCULATION FOR WATER TREATMENT PLANT
GRT-HM05-P0UGD-125452
Rev. 0
Design Weather Parameters & MSHGs
PT. REKAYASA ENGINEERING
Design Parameters:
Rev. 0
Roof Constructions
GRT-HM05-P0UGD-125452
PT. REKAYASA ENGINEERING
Roof
Roof Details
Outside Surface Color .......................................... Light
Absorptivity ............................................................ 0.450
Overall U-Value ..................................................... 0.722 W/(m²-°K)
Wall
Wall Details
Outside Surface Color .......................................... Light
Absorptivity ............................................................ 0.450
Overall U-Value ..................................................... 0.629 W/(m²-°K)
Rev. 0
Schedule Input Data
GRT-HM05-P0UGD-125452
PT. REKAYASA ENGINEERING
Hourly Profiles:
1:Profile One
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Value 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100
Assignments:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Design 1 1 1 1 1 1 1 1 1 1 1 1
Monday 1 1 1 1 1 1 1 1 1 1 1 1
Tuesday 1 1 1 1 1 1 1 1 1 1 1 1
Wednesday 1 1 1 1 1 1 1 1 1 1 1 1
Thursday 1 1 1 1 1 1 1 1 1 1 1 1
Friday 1 1 1 1 1 1 1 1 1 1 1 1
Saturday 1 1 1 1 1 1 1 1 1 1 1 1
Sunday 1 1 1 1 1 1 1 1 1 1 1 1
Holiday 1 1 1 1 1 1 1 1 1 1 1 1
Hourly Profiles:
1:Profile One
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Value O O O O O O O O O O O O O O O O O O O O O O O O
O = Occupied; U = Unoccupied
Assignments:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Design 1 1 1 1 1 1 1 1 1 1 1 1
Monday 1 1 1 1 1 1 1 1 1 1 1 1
Tuesday 1 1 1 1 1 1 1 1 1 1 1 1
Wednesday 1 1 1 1 1 1 1 1 1 1 1 1
Thursday 1 1 1 1 1 1 1 1 1 1 1 1
Friday 1 1 1 1 1 1 1 1 1 1 1 1
Saturday 1 1 1 1 1 1 1 1 1 1 1 1
Sunday 1 1 1 1 1 1 1 1 1 1 1 1
Holiday 1 1 1 1 1 1 1 1 1 1 1 1
Hourly Profiles:
1:Profile One
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Value O O O O O O O O O O O O O O O O O O O O O O O O
O = Occupied; U = Unoccupied
Assignments:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Design 1 1 1 1 1 1 1 1 1 1 1 1
Monday 1 1 1 1 1 1 1 1 1 1 1 1
Tuesday 1 1 1 1 1 1 1 1 1 1 1 1
Wednesday 1 1 1 1 1 1 1 1 1 1 1 1
Thursday 1 1 1 1 1 1 1 1 1 1 1 1
Friday 1 1 1 1 1 1 1 1 1 1 1 1
Saturday 1 1 1 1 1 1 1 1 1 1 1 1
Sunday 1 1 1 1 1 1 1 1 1 1 1 1
Holiday 1 1 1 1 1 1 1 1 1 1 1 1
Hourly Profiles:
1:24 hours
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Value 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100
Assignments:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Design 1 1 1 1 1 1 1 1 1 1 1 1
Monday 1 1 1 1 1 1 1 1 1 1 1 1
Tuesday 1 1 1 1 1 1 1 1 1 1 1 1
Wednesday 1 1 1 1 1 1 1 1 1 1 1 1
Thursday 1 1 1 1 1 1 1 1 1 1 1 1
Friday 1 1 1 1 1 1 1 1 1 1 1 1
Saturday 1 1 1 1 1 1 1 1 1 1 1 1
Sunday 1 1 1 1 1 1 1 1 1 1 1 1
Holiday 1 1 1 1 1 1 1 1 1 1 1 1
Hourly Profiles:
1:Office
Hour 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Value 0 0 0 0 0 0 0 30 50 100 100 100 100 100 100 100 100 80 50 30 30 0 0 0
Assignments:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Design 1 1 1 1 1 1 1 1 1 1 1 1
Monday 1 1 1 1 1 1 1 1 1 1 1 1
Tuesday 1 1 1 1 1 1 1 1 1 1 1 1
Wednesday 1 1 1 1 1 1 1 1 1 1 1 1
Thursday 1 1 1 1 1 1 1 1 1 1 1 1
Friday 1 1 1 1 1 1 1 1 1 1 1 1
Saturday 1 1 1 1 1 1 1 1 1 1 1 1
Sunday 1 1 1 1 1 1 1 1 1 1 1 1
Holiday 1 1 1 1 1 1 1 1 1 1 1 1
Rev. 0
Space Input Data
Grati Water Treatment Plant
PT. REKAYASA ENGINEERING
01 Panel Room
1. General Details:
Floor Area ............................................................. 8.6 m²
Avg. Ceiling Height ................................................ 3.0 m
Building Weight .................................................. 341.8 kg/m²
1.1. OA Ventilation Requirements:
Space Usage ......................................... User-Defined
OA Requirement 1 ................................................. 0.0 L/s
OA Requirement 2 ................................................. 0.0 L/s
Space Usage Defaults ............. ASHRAE Std 62-2001
2. Internals:
2.1. Overhead Lighting: 2.4. People:
Fixture Type ............................ Recessed (Unvented) Occupancy ............................................................. 0.0 Person
Wattage .............................................................. 16.00 W/m² Activity Level .......................................... User defined
Ballast Multiplier ................................................... 1.00 Sensible ............................................................... 75.0 W/person
Schedule ...................................... Lighting Schedule Latent ................................................................... 55.0 W/person
Schedule ............................................................ None
Exp. Wall Gross Area (m²) Window 1 Qty. Window 2 Qty. Door 1 Qty.
NW 9.8 0 0 0
SW 8.0 0 0 0
4. Roofs, Skylights:
Exp. Roof Gross Area (m²) Roof Slope (deg.) Skylight Qty.
NW 8.0 15 0
5. Infiltration:
Design Cooling ..................................................... 0.00 L/(s-m²)
Design Heating ..................................................... 0.00 L/s
Energy Analysis .................................................... 0.00 L/s
Infiltration occurs at all hours.
6. Floors:
Type ......................................... Slab Floor On Grade
Floor Area ............................................................. 8.6 m²
Total Floor U-Value ............................................ 0.602 W/(m²-°K)
Exposed Perimeter ................................................ 0.0 m
Edge Insulation R-Value ....................................... 0.00 (m²-°K)/W
7. Partitions:
7.1. 1st Partition Details: Uncondit. Space Min Temp .................................. 20.0 °C
Partition Type ....................................... Wall Partition Ambient at Space Min Temp ................................ 28.0 °C
Area ..................................................................... 17.7 m²
U-Value .............................................................. 0.629 W/(m²-°K)
Uncondit. Space Max Temp .................................. 26.0 °C
Ambient at Space Max Temp ................................ 35.0 °C
7.2. 2nd Partition Details: Uncondit. Space Max Temp ................................. 26.0 °C
Partition Type ....................................... Wall Partition Ambient at Space Max Temp ............................... 35.0 °C
Area ...................................................................... 6.0 m² Uncondit. Space Min Temp .................................. 20.0 °C
U-Value .............................................................. 0.629 W/(m²-°K) Ambient at Space Min Temp ................................ 28.0 °C
Rev. 0
Zone Sizing Summary for 01 Panel room
Project Name: Grati Water Treatment Plant
Prepared by: PT. REKAYASA ENGINEERING
6.6 Appendix F – ASHRAE STD 62.1 2007, ASHRAE Handbook Fundamental (SI) 2009 and ASHRAE
Handbook Application (SI) 2003
Rev. 0
3.2 2003 ASHRAE Applications
Handbook (SI)
20 to 22°C 8 to 12
Libraries Average
below 0.13 m/s
and 40 to 55% rh
Museums
See Chapter 21, Museums, 8 to 12
Archival below 0.13 m/s
Libraries, and Archives
6.2.7 Dynamic Reset. The system may be designed to 6.2.8 Exhaust Ventilation. Exhaust airflow shall be pro-
reset the design outdoor air intake flow (Vot) and/or space or vided in accordance with the requirements in Table 6-4.
zone airflow as operating conditions change. These condi- Exhaust makeup air may be any combination of outdoor air,
tions include but are not limited to: recirculated air, and transfer air.
6.2.9 Ventilation in Smoking Areas. Smoking areas
1. Variations in occupancy or ventilation airflow in one or
shall have more ventilation and/or air cleaning than compara-
more individual zones for which ventilation airflow
ble no-smoking areas. Specific ventilation rate requirements
requirements will be reset.
cannot be determined until cognizant authorities determine
Note: Examples of measures for estimating such varia-
the concentration of smoke that achieves an acceptable level
tions include: occupancy scheduled by time-of-day, a of risk. Air from smoking areas shall not be recirculated or
direct count of occupants, or an estimate of occupancy or
transferred to no-smoking areas.
ventilation rate per person using occupancy sensors such
as those based on indoor CO2 concentrations. 6.3 Indoor Air Quality (IAQ) Procedure. The Indoor Air
2. Variations in the efficiency with which outdoor air is Quality (IAQ) Procedure is a performance-based design
distributed to the occupants under different ventilation approach in which the building and its ventilation system are
system airflows and temperatures. designed to maintain the concentrations of specific contami-
3. A higher fraction of outdoor air in the air supply due to nants at or below certain limits identified during the building
intake of additional outdoor air for free cooling or exhaust design and to achieve the design target level of perceived
air makeup. indoor air quality acceptability by building occupants and/or
>0.55 Use Appendix A 6.3.2 Documentation. When the IAQ Procedure is used,
1. “Max Zp” refers to the largest value of Zp, calculated using Equation 6-5, among all the following information shall be included in the design doc-
the zones served by the system.
2. For values of Zp between 0.15 and 0.55, one may determine the corresponding value umentation: the contaminants of concern considered in the
of Ev by interpolating the values in the table. design process, the sources and source strengths of the con-
3. The values of Ev in this table are based on a 0.15 average outdoor air fraction for the
system (i.e., the ratio of the uncorrected outdoor air intake Vou to the total zone taminants of concern, the target concentration limits and
primary airflow for all the zones served by the air handler). For systems with higher exposure periods and the references for these limits, the
values of the average outdoor air fraction, this table may result in unrealistically low
values of Ev and the use of Appendix A may yield more practical results. design approach used to control the contaminants of concern,
and the background or justification for this design approach.
visitors. For the purposes of this procedure, acceptable per- If the design is based on an approach that has proved success-
ceived indoor air quality excludes dissatisfaction related to ful for similar buildings, the documentation shall include the
thermal comfort, noise and vibration, lighting, and psycho- basis for concluding that the design approach was successful
logical stressors. in the other buildings and the basis for concluding that the pre-
6.3.1 Designs employing the IAQ Procedure shall comply vious buildings are relevant to the new design. If contaminant
with the requirements in the following sections. monitoring and occupant evaluation are to be used to demon-
6.3.1.1 Contaminant Sources. Contaminants of con- strate compliance, then the monitoring and evaluation plans
cern for purposes of the design shall be identified. For each shall also be included in the documentation.
6.4 Design Documentation Procedures. Design criteria and rain and other sources of moisture by appropriate in-transit
assumptions shall be documented and should be made available and on-site procedures. Porous materials with visible micro-
for operation of the system within a reasonable time after instal- bial growth shall not be installed. Nonporous materials with
lation. See Sections 4.3, 5.2.3, 5.17.4, and 6.3.2 regarding visible microbial growth shall be decontaminated.
assumptions that should be detailed in the documentation. 7.1.4 Protection of Occupied Areas
7. CONSTRUCTION AND SYSTEM START-UP 7.1.4.1 Application. The requirements of Section 7.1.4
apply when construction requires a building permit and
7.1 Construction Phase entails sanding, cutting, grinding, or other activities that gen-
7.1.1 Application. The requirements of this section apply erate significant amounts of airborne particles or procedures
to ventilation systems and the spaces they serve in new build- that generate significant amounts of gaseous contaminants.
ings and additions to or alterations in existing buildings. 7.1.4.2 Protective Measures. Measures shall be
7.1.2 Filters. Systems designed with particle filters shall employed to reduce the migration of construction-generated
not be operated without filters in place. contaminants to occupied areas. Examples of acceptable mea-
7.1.3 Protection of Materials. When recommended by sures include, but are not limited to, sealing the construction
the manufacturer, building materials shall be protected from area using temporary walls or plastic sheathing, exhausting