PLANILLA DE METRADOS

DIMENCINES TOTAL
ITEM DESCRIPCION DE LA PRTIDA UND CANTIDAD PARCIAL
LARGO ANCHO ALTO
02 ESTRUCTURAS
02.01 OBRAS DE CONCRETO SIMPLE
02.02.01 SOBRECIMIENTO
02.02.03.01 CONCRETO EN SOBRECIMIENTO 1:8 C:H +25% P.M. M3 2.82
EJE 1-1 ENTRE A-B 1.00 4.95 0.15 0.40 0.30
EJE 1-1 ENTRE B-C 1.00 4.95 0.15 0.40 0.30
EJE 2-2 ENTRE A-B 1.00 4.95 0.15 0.40 0.30
EJE 2-2 ENTRE B-C 1.00 4.95 0.15 0.40 0.30
EJE A-A ENTRE 1-2 1.00 8.90 0.15 0.40 0.53
EJE B-B ENTRE 1-2 1.00 9.32 0.15 0.40 0.56
EJE C-C ENTRE 1-2 1.00 8.90 0.15 0.40 0.53
02.02.03.02 ENC. Y DES ENC. EN SOBRECIMIENTO M2 37.54
EJE 1-1 ENTRE A-B 2.00 4.95 0.40 3.96
EJE 1-1 ENTRE B-C 2.00 4.95 0.40 3.96
EJE 2-2 ENTRE A-B 2.00 4.95 0.40 3.96
EJE 2-2 ENTRE B-C 2.00 4.95 0.40 3.96
EJE A-A ENTRE 1-2 2.00 8.90 0.40 7.12
EJE B-B ENTRE 1-2 2.00 9.32 0.40 7.46
EJE C-C ENTRE 1-2 2.00 8.90 0.40 7.12
02.02 OBRAS DE CONCRETO ARMADO
02.02.01 ZAPATAS
02.02.01.01 CONCRETO EN ZAPATAS F'c = 175 kg/cm2 M3 5.89
ZAPATAS Z-1 4.00 1.45 1.45 0.70 5.89
02.02.01.02 ENCOFRADO Y DESNCOFRADO EN ZAPATAS M2 16.24
ZAPATAS Z-1 4.00 1.45 0.70 4.06
ZAPATAS Z-2 4.00 1.45 0.70 4.06
ZAPATAS Z-3 4.00 1.45 0.70 4.06
ZAPATAS Z-4 4.00 1.45 0.70 4.06
02.02.01.03 ARMADURA DE ACERO EN ZAPATAS FY':4200 KG 128.96
ZAPATAS Z-1 4.00 CATIDA TOTAL= 32.24 128.96
EN X-X EN Y-Y
DESCRIPCIÓ CANT.
N LONG. Y Nº VAR LONG. X

Z-1 4.00 1.45 8.00 1.45


ACERO EN ZAPATAS
EN Y-Y LONGITUD (ML) PESO PARCIAL (KG)
PARCIAL PARCIAL Diámetro 1/4 3/8
Nº VAR TOTAL
LONG X-X LONG Y-Y P. Unit. (Kg/Ml) 0.25 0.56
8.00 10.40 10.40 20.80
PESO PARCIAL (KG)
1/2 5/8 3/4 1 TOTAL
0.99 1.55 2.24 3.98
32.30 32.30
DATOS:
SLUMP 1.5
ELEMETO A DZAPATA REFORZADA
RESISTENCIA 175 KG/CM2
TAMAÑO MAX 1.1/2
CONDICIONESCONTROL DE OBRA MUY BUENO
DOSIFICACION POR PESO
condiciones SIN AIRE INCORPORADO
MATERIALES
-CEMENTO TIPO 1
-AGREGADO PESO UNITARIO COMPACTA 1600 KG
CONTENIDO DE HUMEDAD 2%
%ABSORCION 0.50% 1.50%
-AGREGADO MODULO DE FINEZA 2.5
CONTENIDO DE HUMEDAD 3%
%ABSORCION 2% 2.51%

RESOLUCION
1 ASENTAMIENT 1.5 PULGADAS
2 CONTENIDO DE AGUA EN 1M3 DE CONCRETO
SEGUN TABLA B 160 KG/CM
3 FACTOR DE INCREMENTO DE CONCRETO
SEGUN TABLA C 1.15

F´cr= 201.25 kg/cm2


4 RELACION AGUA/CEMENTO
SEGUN TABLA D
f´cr A/C
175 0.67
201.25 X= 0.6025
210 0.58

5 CONTENIDO 265.56

6 VOLUMEN DE AGREGADO GRUESO


SEGÚN TABLA E= 0.75 M3

7 CANTIDAD DE 1200 KG

8 PESO DEL CONCRETP POR 1M3


SEGÚN TABLA F= 2420 KG/CM3

9 PESO DEL AG 794.44 KG

10 PESO DEL A 24 KG

11 PESO DEL AG 23.83 KG

12 CANTIDAD D 6
PESO*(%HUMEDAD-%ABSORCION

13 CANTIDAD D 3.89
PESO*(%HUMEDAD-%ABSORCION

14 CANTIDAD DE 150.11

DOSIFICACION
-AGUA 0.150 M3 *DIVIDIMOS EL PESO DEL AGUA ENTRE EL PESO ESPESIFICO DEL AGUA
ᵞ AGUA 1000KG/M3
-CEMENTO 6.25 BLS
PESO DE 1 BLS DE CEMENTO 42.5 KG

AGREGADO G 0.75 M3 *DIVIDIMIS EL PESO DEL AGREGADO ENTRE EL PESO ESPECIFICO DEL AGREGADO
ᵞ AGREGADO GRUESO= 1600 KG/M3
AGREGADO G 0.47 M3 *DIVIDIMIS EL PESO DEL AGREGADO ENTRE EL PESO ESPECIFICO DEL AGREGADO
ᵞ AGREGADO FINO= 1700 KG/M3

-AGUA 0.150
-CEMENTO 6.25
-AGREGADO 0.71
-AGREGADO 0.50
CONCRETO ARMADO
-AGUA 0.150
-CEMENTO 6.25
-AGREGADO GRUESO 0.75
-AGREGADO GRUESO 0.47

CONCRETO SIMPLE
-AGUA 0.130
-CEMENTO 3.7
-PIEDRA MEDIANA 0.4
-HORMIGON 0.85

4 SEGÚN LOS GRÁFICOS DE CAPECO, CALCULAR EL APORTE UNITARIO DE LOS ENCOFRADOS, TOMANDO EN CUENTA LOS SIGUIENTES DATOS
APORTE UNITARIO PARA ENCOFRADO DE CIMIENTOS

ENCOFRADO DE SOBRECIMIENTO 1.20

ELEMENTO DESCRIPCION SECCION (A) LONGITUD CANTIDAD DE CANTIDAD DE CON DESPERDICIOS N°DE USOS
MADERA EN
ELEMENTOS (MADERA 10%) (CAPECO)
PIES2 CANT/ N° USOS APORTE UNITARIO
M.L. PIES

TABLON 1.5"X12" 2 6.56 2 19.68 21.65 14 1.55 1.29


SOLERA 2"X3" 2 6.56 2 6.56 7.22 10 0.72 0.60
BARROTE 2"X4" 0.4 1.31 8 6.99 7.69 14 0.55 0.46
TORNAPUNTA 2"X3" 0.5 1.64 8 6.56 7.22 7 1.03 0.86
TORNAPUNTA 2"X3" 0.58 1.9 8 7.6 8.36 7 1.19 1.00
ESTACA 2"X3" 0.6 1.97 8 7.88 8.67 6 1.44 1.20
5.41
ALAMBRE N°8 3 0.32 0.37 1 0.37 0.31
CLAVO 3" 56 0.312 0.36 2 0.18 0.15

ENCOFRADO DE ZAPATAS 1.92

ELEMENTO DESCRIPCION SECCION (A) LONGITUD CANTIDAD DE


CANTIDAD DE CON DESPERDICIOS N°DE USOS CANT/ N° USOS APORTE UNITARIO
MADERA EN
M.L. PIES ELEMENTOS PIES2 (MADERA 10%) (CAPECO)

TABLON 1.5"X8" 1.2 3.94 8 31.52 34.67 6 5.78 3.01


SOLERA 2"X3" 1.2 3.94 4 7.88 8.67 6 1.44 0.75
ESTACA 2"X3" 0.85 2.79 12 16.74 18.41 6 3.07 1.60
ESTACA 2"X3" 0.6 1.97 12 11.82 13.00 6 2.17 1.13
TORNAPUNTA 2"X3" 0.56 1.84 12 11.04 12.14 6 2.02 1.05
7.54
CLAVOS 3" 88 0.49 0.56 2 0.28 0.15
REALIZAR EN ANÁLISIS DE PRECIOS UNITARIOS

02.02.03.01 CONCRETO EN SOBRECIMIENTO 1:8 C:H +25% P.M.


redimiento 10 M3/DIA P.U. POR 1M3: S/. 314.63
DESCRIPCION DEL INSUM UND CUADRILLA CANTIDAD PRECIO UNITARIO PARCIAL

MANO DE OBRA
CAPATAZ HH 0.10 0.08 S/. 23.00 S/. 1.84
OPERARIO HH 1.00 0.80 S/. 21.00 S/. 16.80
OFICIAL HH 2.00 1.60 S/. 19.00 S/. 30.40
PEON HH 8.00 6.40 S/. 17.00 S/. 108.80
OPERADOR HH 1.00 0.80 S/. 22.00 S/. 17.60
S/. 175.44
MATERIALES
CEMENTO BLS 3.70 S/. 21.50 S/. 79.55
HORMIGON M3 0.85 S/. 30.00 S/. 25.50
PIEDRA MEDIANA M3 0.40 S/. 28.00 S/. 11.20
AGUA M3 0.13 S/. 5.00 S/. 0.65
S/. 116.90
EQUIPOS Y/O MAQUINARIA
MEZCLADORA 9-11 P3 HE 1.00 0.80 S/. 18.00 S/. 14.40
HERRAMIENTAS MANUAL4.5%M.O. 0.045 S/. 175.44 S/. 7.89
S/. 22.29

02.02.03.02 ENC EN C. EN SOBRECIMIENTO


M2/DIA P.U. POR 1M3: S/. 63.56
DESCRIPCION DEL INSUM UND CUADRILLA CANTIDAD PRECIO UNITARIO PARCIAL
redimiento 14 40 28
MANO DE OBRA
CAPATAZ HH 0.1 0.057 S/. 23.00 S/. 1.31
OPERARIO HH 1 0.571 S/. 21.00 S/. 12.00
OFICIAL HH 1 1.00 0.486 S/. 19.00 S/. 9.23
PEON 2.00 0.571 S/. 17.00 S/. 9.71
S/. 32.26
MATERIALES
MADERA TORNILLO PIE2 5.41 S/. 5.30 S/. 28.67
ALAMBRE N° 8 KG 0.31 S/. 2.00 S/. 0.62
CLAVOS DE 3" KG 0.15 S/. 3.70 S/. 0.56
S/. 29.85
EQUIPOS Y/O MAQUINARIA
HERRAMIENTAS MANUAL4.5%M.O. 0.045 S/. 32.26 S/. 1.45
S/. 1.45

02.02.01.01 CONCRETO EN ZAPATAS F'c = 175 kg/cm2


redimiento 25 M3/DIA P.U. POR 1M3: S/. 257.11
DESCRIPCION DEL INSUM UND CUADRILLA CANTIDAD PRECIO UNITARIO PARCIAL

MANO DE OBRA
CAPATAZ HH 0.2000 0.064 S/. 23.00 S/. 1.47
OPERARIO HH 2.0000 0.64 S/. 21.00 S/. 13.44
OFICIAL HH 2.0000 0.64 S/. 19.00 S/. 12.16
PEON HH 8.0000 2.56 S/. 17.00 S/. 43.52
OPERADOR DE E. L. 1.0000 0.32 S/. 22.00 S/. 7.04
S/. 77.63
MATERIALES
CEMENTO PORTLAND I BLS 6.25 S/. 21.50 S/. 134.38
AGREGADO GRUESO M3 0.75 S/. 28.00 S/. 21.00
AGREGADO FINO M3 0.47 S/. 30.00 S/. 14.10
AGUA M3 0.15 S/. 5.00 S/. 0.75
S/. 170.23
EQUIPOS Y/O MAQUINARIA
MEZCLADORA HE 1.00 0.32 S/. 18.00 S/. 5.76
HERRAMIENTAS MANUAL4.5%M.O. 0.045 S/. 77.63 S/. 3.49
S/. 9.25

02.02.01.02 ENCOFRADO Y DESNCOFRADO EN ZAPATAS


M3/DIA P.U. POR 1M3: S/. 74.17
DESCRIPCION DEL INSUM UND CUADRILLA CANTIDAD PRECIO UNITARIO PARCIAL
redimiento 14 40 28
MANO DE OBRA
CAPATAZ HH 0.1 0.1 0.057 S/. 22.00 S/. 1.26
OPERARIO HH 1 1.0 0.571 S/. 21.00 S/. 12.00
OFICIAL HH 1 1.0 0.486 S/. 19.00 S/. 9.23
PEON HH 2.0 0.571 S/. 17.00 S/. 9.71
S/. 32.20
MATERIALES
MADERA TORNILLO PIE2 7.54 S/. 5.30 S/. 39.96
CLAVOS DE 3" KG 0.15 S/. 3.70 S/. 0.56
S/. 40.52
EQUIPOS Y/O MAQUINARIA
HERRAMIENTAS MANUAL4.5%M.O. 0.045 S/. 32.20 S/. 1.45
S/. 1.45

02.02.01.03 ARMADURA DE ACERO EN ZAPATAS FY':4200


redimiento 240 M3/DIA P.U. POR 1M3: S/. 5.07
DESCRIPCION DEL INSUM UND CUADRILLA CANTIDAD PRECIO UNITARIO PARCIAL

MANO DE OBRA
CAPATAZ HH 0.1000 0.003 S/. 23.00 S/. 0.08
OPERARIO HH 1.0000 0.033 S/. 21.00 S/. 0.70
OFICIAL HH 1.0000 0.033 S/. 19.00 S/. 0.63
S/. 1.41
MATERIALES
FIERRO CORRUGADO 5/ KG 1.00 S/. 3.50 S/. 3.50
ALAMBRE N° 16 KG 0.05 S/. 2.00 S/. 0.10
S/. 3.60
EQUIPOS Y/O MAQUINARIA
HERRAMIENTAS MANUAL 3%M.O. 0.045 S/. 1.41 S/. 0.06
S/. 0.06