NOTIFICATION OF INSPECTION
ITP Ref No. LEX/P1/M/EAC-----F01/MP/020 Date 27/05/2019
Please be informed that the following item has been checked by us and are found to be conforming to the requirements These
Signature : RAO
Location : Stacking Conveyor 3B (SC 3B) & Transfer Station 2C (TS 2C)
Description of Work : To Conduct Final Walk Down for Package 4 – (SC 3B & TS 2C)
Purpose of Inspection : Punch List Clearance for conveyor SC3C & 3D prior Dry Commissioning
Attachments :
☒ AFC Drawing ☐ Method of Statement
Signature
BALAN HAZIME
Name
Thanabalan Mr HAZIME
Date
27/05/2019 27/05/2019
Inspection Results:
Date: Time:
Comments:
Inspected By:
Participant Sub - contractor Contractor Employer
Signature