To
M/S. JINDAL SAW LTD.
OKLA-NEW DELHI
Kind Attn:
Sub: Proposal for 7.5 KL/Hr Multiple Effect Evaporation Plant – reg.
Dear Sir,
We thank you very much for the kind courtesy you had extended to the under signed recently
when he visited your office.
Based on the discussions and the data furnished by you, we are herewith enclosing our proposal
for multiple effect evaporation plant.
An appropriate process flow diagram is also enclosed for your ready reference.
Trust the same is line with your requirement and now we look forward for your favorable
decision.
With regards
B.SRIDHAR
DIRECTOR- BUSINESS DEVELOPMENT
Ph: 040-23759590/ 7702999590
CONTENTS
ANNEXURE CONTENTS
I DESIGN BASIS
V TERMINAL POINTS
1. DESIGN BASIS
Operating hours : 16
Initial concentration : 4%
Steam shall be made available with more than 0.96 dryness fraction
2. TECHNICAL SPECIFICATIONS
1 EVAPORATION
Feed rate : 7500 Kg/ Hr
Evaporation capacity : 6750 Kg / hr
Total solids in product feed : 4%( Estimated)
Total solids in product : 750Kg / Hr
2 ATFD
Feed rate : 750 Kg / Hr
Salt (10% moisture) : 334Kg/ Hr
Evaporation Capacity : 416Kg/ Hr
2 UTILITY REQUIREMENT
A Steam : 2800 Kg / Hr
Pressure : 3.5 Kg / sq cm (g)
Temperature : Saturated
Notes:
a) Final product outlet will depend on the nature of the solids / slurry. Concentration /
moisture contain in the evaporator will not be the part of performance criteria for
evaporation plant.
ANNEXURE-III
3. MATERIAL OF CONSTRUCTION
A. Evaporators
B. Pumps
Tubes : SS 304
F. ATFD
Shell : SS 316
Agitation : SS 316
Jacket : MS
G. ATFD Condenser
Main Shell : SS 304
End Cover : SS 304
Tube Sheet : SS 304
Tubes : SS 304
H. Process pipes & fittings : SS 316
ANNEXURE-IV
ANNEXURE-V
5. TERMINAL POINTS
a) Electrical power
b) Cooling water
c) Feed
d) Final product
e) Civil foundation
c) Local mountings