Scope, Highlights and Challenges

2016 2017 2018 2019 Total


Rollout Planning
Scope Qty Qty Qty Qty Qty
• Starting P10 2016 until P6 2019 Physical Sites 300 2.000 2.000 984 5.284

Service Supplier – DEC Workshop


• TI – 5.284 sites considering New LTE installation and
modernization of 2G or 3G Technologies. LTE will be in AWS
and 700MHz bands (for SRAN and RAN Sharing) and
Amba
Interior
193
107
527
1.473
703
1.297
390
594
1.813
3.471

Modernization will be in 850 and 1900MHz. It is included 4th


Carrier of 3G sites.
• NPO Services for Site Implementation Highlights, Challenges & Current status:
• Replacement of 98 BSCs to17mcBSC incl. NPO+rehomings • Readiness process implemented since P8 with weekly follow up
• 1 new MME + 4 MME expansion • 147 TSSR delivered to Claro & 76 RFI available
• NetAct Upgrade (HW + SW upgrade + SRAN customization)
• Missing site CPO
• SQM new HW installation + SI + customization
• Target is 40 integrated sites per week linked to RFI volumen (160)
• SAFE Customizations
• PPP defined and under implementation to push profitability
• RG40 upgrade services
• GSM 16 upgrade services • 80 Crews needed, currently 30 aprox.
DEC – Digital Enablement Center • GPR is suporting negotiation site by site CoS
• Minimum management team in place
Financial Figures
2019-03-20
• Total GS: 59mEur
• Customer complaint about low integration per week since CW41
• Asignation by cluster / region to improve productivity
• Expected
Neimar Rosa /Revenue Q4 2016: 1.6mEur (160 Sites)
John Guerrero

1 FF-© 2018 Nokia


DEC E2E process
Interlock process:
- Information sharing and reporting in each quality control point - QCPx
- Weekly meeting practices to share information, identify challenges and define improvement actions

Initiate Prepare Delivery Site Work Quality Audit Customer


- Handover to Acceptance - MS15 & Self- Site
DEC - MS14 - Implementatio
- MS14 Assessment Acceptance
- Kick-off - Site call-off - MoS n starts
meeting - Supplier - Daily Tracking
- Implementatio (physical visit)
- Delivery n Ends
readiness - Site
Inspection - MS17 Acceptance
- Site Readiness
- MS17
- Supplier
QCP0 QCP1 Readiness QCP2 QCP3 QCP4 QCP5

Progress Reporting
Pre-check Delivery Acceptance & Self Assessment
- Site Design - H&S Technical Support - Quality & Acceptance check-list
- Inst. Std. - Security - Pictures & Video
- PPE Check - Delivery Acceptance - Site is clean
- LTW Check - Site Design - Excess material is collected
Phone
Video
- BoM - SMR / BoM
- Tools - Tools
- Site Access - Installation Standards
- MDI Customer Acceptance
- Site Documentation - Quality & Acceptance check-list
- Site Folder Requirement
Mobile WEB - LTW
- Project Induction Material
2 FF-© 2018 Nokia
QCPO
Handover FM a equipo DEC

3 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
QCP1
Caso aceptación DEC

4 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
QCP1
Caso rechazo DEC

5 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
DEC Tools

EXECUTION
(MOS TI START-TI FINISH INTEGRATION HW DOC.)

Geolocation
CARSO Remote Audit and Quality Funcional test Documentation
HW validation TALON VIEW PROBO IOM/CARSO
(pending)

Roll Out
WEB, MELIUS

6 FF-© 2018 Nokia


Documentos
Leadtimes

-14 0 17 19 24 27

RFE+RFD MOS Implementación Integración Desmonte ON Air

1 TSS Rep. Irradiante Pre % de avance Rep. Irradiante POS Site Folder de Baja
2 DataFill Logistica Baja (Acta Baja) Calidad Foto Apilamiento
3 Doc.Ing (Inventario/HW) Funcional TILT Acta Baja
4 TX Inventario SMR InventárioSMR
5 PO->SSI LSM LSM
6 Forecast MOS

WebTool IPM

7 FF-© 2018 Nokia Nokia internal use


Entregables
Documentación
DOCUMENTACION Actual_Normalizacion_Entregable_Nombre IPM (SITE FOLDER)

1.1 Instalación física (Check List Calidad) 0300_CheckList Calidad_PREPOST_WP_SiteName_ddmmaaaa Installation


1.2 Comisionamiento y Pruebas de Funcionalidad. (Check List Integración) 0100_CheckList OnAir_PREPOST_SiteName_ddmmaaaa Integration
1. Operativo
1.3 Videos Instalcion 0600_TI_Videos_SiteName_ddmmaaaa Installation
1.4 Reporte Radiante (PRE y POS) por tecnología (2G/3G/4G 0300_CheckList Calidad_PREPOST_WP_SiteName_ddmmaaaa Integration

2.1 Inventario LSM y/o SMR 0000_Inventario HW_SiteName_ddmmaaaa Production


2.1.1 Packing List 0000_Inventario HW_SiteName_ddmmaaaa On Site
2.1.2 Snap Shot Comisionamiento 0100_CheckList OnAir_PREPOST_SiteName_ddmmaaaa On Site
2.2 TSS 0200_TSS_SiteName_ddmmaaaa On Site
2. Administrativo
2.3 Acta Borrado de devolución equipos Funcionales 0500_Acta_SiteName_Banda_WP_FuncionalDesmontado_ddmmaaaa On Site
2.4 Acta Borrado de devolución equipos Funcionales 0700_Acta_SiteName_Banda_WP_FuncionalNoInstalado_ddmmaaa On Site
2.5 Pre Acta de devolución equipos de Baja y correo de Solicitud de Recolección a Claro 0800_SiteName_HWBaja_ddmmaaaa On Site
2.6 Formato de Culminación de actividades (sitio limpio + Material apilado) 1000_Formato Culminación de labores_ SiteName_ddmmaaaa Intallation

3.1 Marcacion en Web Web Tool


3.2 validacion de Ofensores Web Tool
3. seguimiento
3.3 Check list acorde a proceso Web Tool
3.4 Auditoria de Calidad KPI (On time, On Quality) Web Tool

8 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
Secuencia Entregable

9 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
Flujo Entregables

10 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
Carso Documentación: Reporte Radiante, Check List de Calidad

11 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
Talon View: Auditoria On line de Sitos
Videos

BOG.Sultana pendiente
BOY.Chiquinquira-7 PRE Video
COR.Cerete-1 PRE Video
VAD.5 de Noviembre-2 PRE Video
VAD.5 de Noviembre-2 POST Video
BGA.Centro PRE Video
VAL.Ansermanuevo-2 PRE Video
NEI.Sur Oriental PRE Video
SND.Landazuri-2 PRE Video

12 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
DOC Governance

13 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
DESCRIPCION MODELAMIENTO GENERAL DE ENTREGABLES

14 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
15 22/03/2019 © Nokia 2018 John Andres Guerrero
Confidential
DOC Examples

• SiteName_HWBaja.xlsx
• Acta_SiteName_Banda_WP_FuncionalDesmontado.xlsx
• Acta_SiteName_Banda_WP_FuncionalNoInstalado.xlsx
• InventarioHW_SND.Landazuri-2.xlsm
• SiteName_Formato Culminacion de labores.xlsm

16 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
EJEMPLO ENTREGABLES DOCUMENTACIÓN

1. GSM:
Carpeta OnSite Carpeta Instalación Carpeta Integración.

1. TSS 1. Formato culminación


1. PL (Probe of Delivery
2. Reporte fotográfico y de labores
"POD")
radiante Pre y Post (SS)
2. Inventario HW (Cierre 2. Pruebas V&D Post
3. Snapshot Pre.
SMR) 4. Borrador acta de 3. Borrador acta de
devolución equipos equipos de baja.
funcionales No instalados 4. Snapshot Post
(Si aplica). ( Final - Confirmación)

17 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
EJEMPLO ENTREGABLES DOCUMENTACIÓN
2. LTE
Carpeta OnSite Carpeta Instalación Carpeta Integración.

1. TSS 1. Formato culminación


1. PL (Probe of Delivery
2. Reporte fotográfico y de labores
"POD")
radiante Pre y Post (SS) 2. Pruebas V&D Post
2. Inventario HW (Cierre 3. Snapshot Pre. 3. Snapshot Post
SMR) 4. Borrador acta de ( Final - Confirmación)
devolución equipos
funcionales No instalados
(Si aplica).

18 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential
EJEMPLO NTREGABLES DOCUMENTACIÓN
3. UMTS
Carpeta OnSite Carpeta Instalación Carpeta Integración.

1. TSS 1. Formato culminación


1. PL (Probe of Delivery
2. Reporte fotográfico y de labores
"POD")
radiante Pre y Post (SS) 2. Pruebas V&D Post
2. Inventario HW (Cierre 3. Snapshot Pre. 3. Snapshot Post ( Final -
SMR) 4. Borrador acta de Confirmación)
devolución equipos 4. Borrador acta de
funcionales No devolución equipos
instalados (Si aplica). funcionales
desinstalados (si aplica)

19 22/03/2019 © Nokia 2018 John Andres Guerrero


Confidential