CONST.

CAMINO CHAQUILLA – TOMAVE


Id Modo de Nombre de tarea Comienzo Fin jun '19 jul '19 ago '19 sep '19 oct '19 nov '19 dic '19 ene '20 feb '20 mar '20 abr '20 may '20 jun '20 jul '20 ago '20 sep '20
tarea 16233007142128041118250108152229061320270310172401081522290512192602091623010815222905121926031017243107142128051219260209162330061320
1 <CRONOGRAMA DE mar 25-06-19 lun 17-08-20
MOVILIZACION DE EQUIPO>

2 CAMION mar 25-06-19 lun 20-01-20

3 CAMIONETA mar 25-06-19 lun 17-08-20

4 Cargador frontal sobre ruedas mar 25-06-19 vie 14-02-20

5 Cizalla lun 23-12-19 vie 07-02-20

6 Compactadora manual lun 11-11-19 vie 10-04-20

7 ESTACION TOTAL lun 01-07-19 jue 16-07-20

8 Mezcladora lun 02-12-19 jue 02-04-20

9 Motoniveladora lun 16-03-20 vie 14-08-20

10 Retroexcavadora lun 30-09-19 jue 14-05-20

11 TRACTOR A ORUGAS D7G lun 16-09-19 jue 27-02-20

12 Vibradora lun 16-12-19 vie 03-04-20

13 VIBROCOMPACTADORA lun 23-12-19 vie 24-07-20

14 Volqueta lun 24-06-19 jue 13-08-20

Tarea Tareas externas Tarea manual Sólo fin


División Hito externo Sólo duración Fecha límite
Proyecto: CRONOGRAMA DE EQU
Hito Tarea inactiva Informe de resumen manual Progreso
Fecha: mié 05-06-19
Resumen Hito inactivo Resumen manual
Resumen del proyecto Resumen inactivo Sólo el comienzo

INICIO DE PROYECTO: 25/06/2019


FIN DE PROYECTO: 17/08/2020
DURACION : 420 DIAS CALENDARIO