Вы находитесь на странице: 1из 84

Layer of protection analysis (LOPA) for

determination of safety integrity level


(SIL)
stud. techn. Christopher A. Lassen
chrislas@stud.ntnu.no

The Norwegian University of Science and Technology


Department of Production and Quality Engineering
June 2008
Preface

This report is the result of the master project executed Spring 2008, and is the
final step in graduating as an Engineer with a Msc degree from The Norwegian
University of Science and Technology (NTNU). The master project is in collab-
oration with Aker Subsea AS, which is part of the Subsea Business Area within
Aker Solutions. Aker Subsea provides leading oil production systems and equip-
ment located sub-surface, and recent projects are Morvin (North Sea), Kristin
(Noth-Sea), Reliance KG-D6 (India) and Dalia (Angola). The work has been per-
formed partly in Trondheim at the facilities of the Department of Production and
Quality Engineering (IPK), and at Aker Solutions head quarters outside of Oslo.
A very special thanks to my supervisor and professor Marvin Rausand (NTNU)
who has been helpful with thorough guidance throughout the master project.
Another person that deserves attention is Linn Nordhagen (Aker Engineering
and Technology) who has provided helpful information on LOPA from a practi-
cal perspective, and given comments to the final product. Gratitude must be ex-
pressed toward Aker Subsea and Thor Kjetil Hallan for offering office space, and
providing information. Others that should be mentioned are: Katrine Harsem
Lund (Scandpower risk management. AS), Bjørn Solheim (BP) and Hanne Rolén
(Aker Subsea).

Particular gratitude must be expressed to my father, Petter O. Lassen, for advice


and support throughout my entire education.

Christopher A. Lassen

Snarøya, 19.06.2008

I
Contents

List of Tables IV

List of Figures V

1 Introduction 1
1.1 Introduction to LOPA . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.3 Limitations and structure . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.4 Relation to IEC 61508 and 61511 . . . . . . . . . . . . . . . . . . . . . 3

2 Methods in determining SIL 6


2.1 Quantitative method as described in IEC 61508 . . . . . . . . . . . . 6
2.2 Risk matrix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.3 Safety layer matrix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
2.4 The OLF 070 guideline . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.5 Risk graph . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2.6 Calibrated risk graph . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

3 LOPA 18
3.1 What is LOPA? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.2 Explanation of terms . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
3.3 The LOPA team . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
3.4 LOPA worksheet and the LOPA process . . . . . . . . . . . . . . . . . 25
3.5 Different approaches in literature . . . . . . . . . . . . . . . . . . . . 29
3.6 Aker E&T methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

4 Preferred approach 32
4.1 Flowchart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
4.2 Comments to the preferred LOPA approach . . . . . . . . . . . . . . 39

5 Interface with HAZOP 41


5.1 Introduction to HAZOP . . . . . . . . . . . . . . . . . . . . . . . . . . 41
5.2 HAZOP integration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
5.3 Adjustments and transformation of data . . . . . . . . . . . . . . . . 44
5.4 HAZOP / LOPA program specification . . . . . . . . . . . . . . . . . . 44

II
5.5 Illustration of software program . . . . . . . . . . . . . . . . . . . . . 46

6 Case study: Applicability of LOPA 49


6.1 Case text . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
6.2 Introduction to system . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
6.3 LOPA applied on the case study . . . . . . . . . . . . . . . . . . . . . . 52
6.4 Comments to the result . . . . . . . . . . . . . . . . . . . . . . . . . . 58
6.5 Implications during the case . . . . . . . . . . . . . . . . . . . . . . . 59

7 Conclusions and recommendations for further work 60

A Basic concepts 66

B Software schematic 67

C Case study: Worksheet 73

III
List of Tables

1.1 SIL for safety functions operating in low demand of operation adapted
from IEC 61511 (2003) . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

2.1 Risk classification of accidents adapted from IEC 61508 . . . . . . . 7


2.2 Frequency of hazardous event likelihood adopted from IEC 61511 . 10
2.3 SIL requirement table adopted from OLF 070 . . . . . . . . . . . . . 12
2.4 Classification of risk parameters adopted from IEC 61511 . . . . . . 13
2.5 Example calibration adapted from IEC 61511 . . . . . . . . . . . . . 16

3.1 Important columns in the LOPA report / worksheet adapted from


IEC 61511 (2003) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

4.1 Target mitigated event likelihood for safety hazards adapted from
Nordhagen (2007) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
4.2 Typical frequency values assigned to initiating causes adapted from
CCPS (2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
4.3 PFDs for IPLs adapted from CCPS (2001) and BP (2006) . . . . . . . 37

5.1 Process HAZOP worksheet adopted from Rausand (2005) . . . . . . 42

6.1 Initiating cause frequencies . . . . . . . . . . . . . . . . . . . . . . . . 53


6.2 IPL PFDs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55

IV
List of Figures

1.1 Safety lifecycle (IEC 61508, 2003) . . . . . . . . . . . . . . . . . . . . . 4

2.1 Typical risk matrix modified for SIL determination adapted from
(Marszal and Scharpf, 2002) . . . . . . . . . . . . . . . . . . . . . . . . 8
2.2 Safety layer matrix diagram adapted from IEC 61511 (2003) . . . . . 10
2.3 Typical risk graph . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

3.1 Risk analysis procedures adopted from Rausand and Høyland (2004) 18
3.2 The LOPA onion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
3.3 Relation between initiating causes, impact event, process devia-
tion and IPLs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.4 Extract of SIL determination methodology from Ellis and Wharton
(2006) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
3.5 Aker E&T methodology adapted from Nordhagen (2007) . . . . . . . 31

4.1 Preferred approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

5.1 Relationship between HAZOP and LOPA worksheets . . . . . . . . . 43

6.1 SPS and separator schematic . . . . . . . . . . . . . . . . . . . . . . . 50


6.2 Relation between initiating causes, impact event, process devia-
tion and PLs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56

B.1 Step 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
B.2 Step 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
B.3 Step 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
B.4 Step 4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
B.5 Step 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72

C.1 LOPA worksheet: Case study . . . . . . . . . . . . . . . . . . . . . . . 74

V
Abbreviations

AIChE American Institute of Chemical Engineers


Aker E&T Aker Engineering & Technology
AMV annulus master valve
BP British Petroleum
BPCS basic process control system
CCF common cause failures
CV control valve
DHSV downhole safety valve
ESD emergency shutdown
EUC equipment under control
FTA fault tree analysis
FMECA failure modes, effects, and criticality analysis
FPSO floating production, storage and offloading vessel
HAZID hazard identification study
HAZOP hazard and operability study
HCM HIPPS control module
HIPPS high integrity pressure protection system
HPU hydraulic pump unit
IEL intermediate event likelihood
IPL independent protection layer
LOPA layer of protection analysis
MEL mitigated event likelihood
MV master valve (PMV)
OREDA Offshore Reliability Data
PCV production choke valve
PFD probability of failure on demand
P&ID piping and instrumentation diagram
PIG pipeline inspection gauge
PL protection layer
PSD process shutdown
PSDV process shutdown valve
PST pressure safety transmitter

VI
PSV pressure safety valve
PT pressure transmitter
QRA quantitative risk analysis
ROV remotely operated vehicle
SCM susbea control module
SEM electronic control module
SIF safety instrumented function
SIL safety integrity level
SIS safety instrumented system
SPS subsea production system
TMEL target mitigated event likelihood
TT temperature transmitter
VB Visual Basic
WV wing valve (PWV)
XV cross-over valve (XOV)
XT X-mas tree (XMT)

VII
Summary

Layer of protection analysis (LOPA) and other safety integrity level (SIL) deter-
mination methods have been described, and the terms used in LOPA have been
thoroughly defined and clarified. Different views on LOPA found in literature
have been presented, and a preferred / recommended LOPA approach has been
developed and described. This preferred approach has also been applied on a
case study based on systems from Aker Engineering and Technology and Aker
Subsea. The interface between LOPA and hazard and operability study (HAZOP)
has been discussed, and it has been presented how an integrated software tool
could work.
The SIL is a measure of the availability of a protection layer or barrier. Pro-
tection layers include basic process control system (BPCS), critical alarms and
human intervention, safety instrumented functions (SIF), physical protection
and emergency response. All these mitigate the frequency of the occurrence
of the potential unwanted end-consequence or mitigate the impact the end-
consequence represents.
LOPA is a tool to determine the SIL of a SIF and evaluates the other pro-
tection layers individually by looking at the risk mitigation they lead to. Other
tools are the quantitative method described in IEC 61508, the OLF 070 guideline,
risk matrix, safety layer matrix, risk graph and the calibrated risk graph. Except
from the quantitative method in IEC 61508 and the OLF 070 guideline these are
graphical and qualitative methods which are simpler than LOPA. These SIL de-
termination methods do not differentiate between the individual risk mitigation
the protection layers lead to.
A clear understanding of the terms in LOPA is important, and a clear method-
ology essential to ensure a strong framework. The following relationship be-
tween terms are defined: The initiating causes lead to a process deviation, which
again may lead to an impact event that may result in an end-consequence. Pro-
tection layers are introduced previously and subsequently to the impact event.
An example is the initiating cause slippery road which lead to the impact event
car crash. The car crash has an end-consequence of three fatalities. In order
to prevent this fatal outcome, protection layers as rigid car body, air-bags, and
traction control may serve as protection layers.
The preferred LOPA approach developed during the master thesis is based
on the one in IEC 61511, taking the views from other methodologies in literature

VIII
into account. The impact event is the starting point of the analysis. The fre-
quency of the initiating events are multiplied with the probability of failure on
demand for all credited independent protection layers. In addition occupancy
and ignition probability (if applicable) is multiplied with the result. The final
value is denoted the intermediate event likelihood. This is the frequency of the
occurrence of the end-consequence with the existing protection layers in place.
By comparing this with a target frequency measure, the needed SIL is estimated.
HAZOP is a hazard identification method often applied previously or simul-
taneously to a LOPA. By integrating HAZOP and LOPA a high quality analysis,
requiring less resources, may be the result. HAZOP has information in common
with LOPA and some information have to be transformed. A software tool used
to combine and integrate the two methods is beneficial. Such a tool is advanced,
and must incorporate a complex issue like the implementation of expert judg-
ment, which is important in LOPA.
The definition of terms and the preferred approach have proved to be ben-
eficial when applying LOPA during the case study. An extensive issue during
this process has been which protection layers that are independent, and which
that are not. This requires understanding of basic reliability concepts, but also a
great amount of process and system understanding.
The concept of independent protection layers should be evaluated further,
and together with facilitating expert judgment during LOPA and in eventual soft-
ware tools, these are considered the main challenges.

IX
Chapter 1

Introduction

1.1 Introduction to LOPA


Offshore accidents may result in causalities and economic loss. Determining
specific safety requirements of safety systems is an important part in ensuring
that accidents are prevented. In the 1990s the standards IEC 61508 and IEC
61511 emerged, and the need for documenting compliance with these in a con-
sistent manner led to the introduction of the layer of protection analysis (LOPA).
In chemical processes several protection layers are used, and in LOPA the
number and the strength of these protection layers are analyzed. LOPA can be
considered as a simplified form of a quantitative risk assessment. It can be used
after a hazard and operability analysis (HAZOP), and before a quantitative risk
analysis (QRA). A difference between LOPA and other tools is that LOPA ana-
lyzes the different protection layers individually, and the mitigation they lead to.
LOPA is especially used to determine the safety integrity level (SIL) of safety in-
strumented functions in conjunction with IEC 61511, but also as a general risk
assessment tool to evaluate if the protection layers in a system are satisfactory.
In addition, several other applications as capital improvement planning, inci-
dent investigation and management of change can be found. The method is not
used to a large extent in Norway, but widely implemented internationally. In
gas / oil industry LOPA is more frequently applied on topside equipment than
subsea equipment
The concept of protection layers was first covered in the book Guidelines
for Safe Automation of Chemical Processes published by the Center of Chemi-
cal Process Safety (CCPS), a section of the American Institute of Chemical En-
gineers (AIChE), in 1993. These thoughts were developed further by the indus-
try resulting in internal procedures (Dowell, 1998). In 2001 the CCPS published
the book Layer of Protection Analysis, Simplified Risk Assessment describing the
LOPA method (Gowland, 2006). The method is also described in Part III Annex
F of IEC 61511. Extensive literature can be found on LOPA, and stepwise ap-
proaches are given both in IEC 61511 and CCPS (2001). The terms vary among

1
different authors, and definitions and interpretations of terms like scenario and
independent protection layers (IPL) may be confusing.

1.2 Objectives
The objective of the master project is to gain extensive knowledge of various
methods to allocate requirements to safety instrumented systems, with focus on
layer of protection analysis (LOPA). As a part of this the following aspects shall
be covered:

• Carry out a literature survey and compare and discuss the different ap-
proaches to LOPA found in the literature.

• Give a thorough presentation of a recommended LOPA approach. The ap-


proach shall be stepwise with a clear description of each step.

• Define and clarify all basic concepts of the recommended LOPA approach.

• Identify and describe interfaces between LOPA and other risk analysis meth-
ods (especially HAZOP)

• Discuss pros and cons related to LOPA - and especially the limitations of
LOPA.

• Define, exemplify, and discuss the independent protection layer (IPL) con-
cept and discuss the applicability of LOPA in cases where the indepen-
dence is violated.

• Compare the applicability of LOPA in determining SIL, and compare LOPA


with alternative approaches (incl. risk graphs). If possible, this evaluation
should be rooted in a practical case study.

1.3 Limitations and structure


A bayesian approach is used in this thesis, which is concerned with the ”degree
of belief” compared to a classical approach. The master project is executed in
a limited time frame, constraining the coverage of the topic. The reader should
have basic understanding of reliability concepts. In addition, knowledge of IEC
61508 and IEC 61511 is an advantage.
An introduction to LOPA and the project is given in Chapter 1. In addition,
the relation to IEC 61508 and 61511 is described to give the reader complemen-
tary background information. In Chapter 2 different methods in determining
SIL are presented, including the quantitative method in IEC 61508, the risk ma-
trix, the safety layer matrix, the OLF 070 guideline, the risk graph and the cal-
ibrated risk graph. Chapter 3 describes LOPA where important terms are de-
fined and clarified. Further different approaches to LOPA are compared and

2
discussed. A preferred approach is developed, and presented in Chapter 4, in-
cluding description of each step and the basic concepts that are employed. The
interface between HAZOP and LOPA is covered in Chapter 5. In addition the
functionality of a software tool integrating LOPA and HAZOP is described. In
Chapter 6 the applicability of the preferred LOPA approach suggested in Chap-
ter 4 is evaluated in a case study. Finally, conclusions and recommendations for
further work are given in Chapter 7.

1.4 Relation to IEC 61508 and 61511


Requirements to safety instrumented systems (SIS) are given in IEC 61508 and
IEC 61511. Rausand and Høyland (2004) describe a SIS as a system comprising
sensors, logic solver(s), and actuating (final) items, and can be looked upon as
an independent protection shell for machinery or equipment. What the safety
systems shall protect is referred to as equipment under control (EUC) and is de-
fined as ”Equipment, machinery, apparatus, or plant used for manufacturing,
process, transport, medical, or other activities” (IEC 61508, 2003). A SIS imple-
ments the wanted safety function needed to maintain a safe state of the equip-
ment and has the function of achieving the essential risk reduction given by the
requirements (IEC 61508, 2003). Subsequently to the SIS-definition a safety in-
strumented function (SIF) can then be defined as a function implemented by
one or more SIS. However, usually a SIS realizes a number of SIFs (IEC 61508,
2003; Schönbeck, 2007).
Safety integrity is the probability of the safety related system performing the
required safety functions under all conditions, within a period of time. Safety
integrity level (SIL) is classified into four levels, and is defined by the proba-
bility of failure on demand (PFD). The PFD is the average safety unavailability
of an item, thus the mean proportion of time the item does not function as a
safety barrier. A protection layer is considered a safety barrier. When evaluating

Table 1.1: SIL for safety functions operating in low demand of operation adapted
from IEC 61511 (2003)
Safety integrity Average probability of fail-
level (SIL) ure to perform its design
function on demand
4 ≤ 10−5 to < 10−4
3 ≤ 10−4 to < 10−3
2 ≤ 10−3 to < 10−2
1 ≤ 10−2 to < 10−1

the SIL-requirements the system has to be classified either as high demand of


operation or low demand of operation. For subsea production equipment low
demand would be the most applicable because the systems are not used fre-

3
quently. The SIL-requirement is then verified by calculating the PFD (Rausand
and Høyland, 2004; Schönbeck, 2007). In Table 1.1 the PFD related to the four
SILs for low demand of operation is presented.
Standards do not require how the SIL should be determined to the SIFs, only
that they have to be determined. Figure 1.1 shows the safety lifecycle used as the
basic framework in IEC 61508 and IEC 61511. This framework makes it possible

Figure 1.1: Safety lifecycle (IEC 61508, 2003)

to deal with requirements and activities in a structured manner. After the two
initial phases, "concept" and "overall scope definition", the risk associated with
the EUC is analyzed in the "Hazard and risk analysis"- phase. Techniques as
checklists, failure modes and effects analysis (FMEA) and HAZOP may be used.
The next step, which has a red box in Figure 1.1, is to specify the overall safety
requirements in terms of safety functions and safety integrity which are needed
to achieve the necessary risk reduction. It is during this activity the SIL is deter-
mined, and this activity / phase is of greatest importance. LOPA may be applied

4
during this phase, but other methods like risk graph and safety layer matrix are
also applicable. In the next phase, "safety requirements allocation", the safety
functions are allocated to one or more SIS. Although phase four is the most in-
teresting in this case, phase three and five will come into play, as they give the
input and receive the output from phase four. All of these activities are carried
out in the design phase prior to final design and manufacturing (Rausand and
Høyland, 2004; IEC 61508, 2003; Schönbeck, 2007).

5
Chapter 2

Methods in determining SIL

As mentioned in the previous section various SIL determination methods and


tools exist. These may be applied during phase four in Figure 1.1, and in this
chapter the most common are presented briefly. Organizations have developed
these tools to help engineers to estimate the process risk and convert it to a re-
quired SIL (Marszal and Scharpf, 2002). Both qualitative and quantitative ap-
proaches may be applied. In qualitative methods the parameters used as deci-
sion basis are subjective and estimated by expert judgment. Quantitative meth-
ods describe the risk by calculations, and a numerical target value is compared
with the result. Which method to apply rely primarily on whether the necessary
risk reduction is specified in a numerical manner or qualitative manner. The
scope and extent of the analysis would also be an influencing factor. Even if the
assignment method is qualitative the SIL is always quantified by a numerical
number (IEC 61508, 2003; Marszal and Scharpf, 2002). The methods described
in this chapter include the quantitative method in IEC 61511, the risk matrix, the
safety layer matrix, the OLF 070 guideline, the risk graph and the calibrated risk
graph.

2.1 Quantitative method as described in IEC 61508


The approach starts off with establishing the tolerable risk target, which must
be in accordance with the company risk acceptance criteria. This is the accept-
able number of times the SIF is allowed to fail, i.e. the tolerable number of times
per year the specific unwanted consequence may occur. This can be determined
from a table where categories of consequences are assigned acceptable frequen-
cies. Such a classification is shown in Table 2.1. Assigning numerical values in
terms of frequencies, defining which classes that are tolerable and plotting the
consequence specific to the situation, makes it possible to determine the tolera-
ble risk target. If class III in Table 2.1 is tolerable, a catastrophic consequence has
a tolerable risk target of improbable which has an assigned numerical frequency
per year (IEC 61508, 2003).

6
Table 2.1: Risk classification of accidents adapted from IEC 61508
Frequency Consequence
Catastrophic Critical Marginal Neglible
Frequent I I I II
Probable I I II III
Occasional I II III III
Remote II III III IV
Improbable III III IV IV
Incredible IV IV IV IV

The next step is to determine the EUC-risk. Risk is a measure of probability


and consequence. The EUC-risk consists of the unwanted consequence, and the
demand rate on the system without protective features, i.e. number of times per
year the unwanted consequence occur without the SIF. This can be estimated
using quantitative risk assessment methods, e.g. fault tree analysis (FTA) or reli-
ability block diagram (RBD) (IEC 61508, 2003).
The final step is to calculate the necessary risk reduction to meet the tolera-
ble risk. This is obtained by dividing the number of times per year the SIF fail by
the number of demands per year. The result is ”the acceptable number of times
the SIF may fail per demand per year” thus the needed probability of failure per
demand, which is the PFD. The SIL requirement could be allocated further down
to subsystems, e.g. by expert judgment (IEC 61508, 2003).
A separator located topside on a platform or floating production, storage and
offloading vessel (FPSO), with a riser down to a subsea production system (SPS)
consisting of X-mas tree (XT) and reservoir, could be used as an example. The
EUC is in this case defined as the separator. The acceptable frequency of over-
pressure of the separator could be 10−6 /year, which could answer to category
class III with critical consequence. Note that this is the acceptable frequency of
a given unwanted consequence, which in this case is overpressure. The conse-
quence could in some cases also be directly related to human harm. From the
reservoir the demand rate on the system, without any protection systems, can
be found. If this is estimated to be 25 demands/year, the approach gives:

Acceptable no. of times the SIF may fail / year 10−6


PFD ≤ = = 4 · 10−7
No. of demands / year 25

This result is the acceptable frequency / demand, hence the probability of fail-
ure on demand. The protection system may consist of several sub-systems per-
forming several SIFs, and the PFD may be allocated further down. In this case
high integrity pipeline protection system (HIPPS), production shutdown (PSD),
emergency shut down (ESD) etc. are such systems or functions.

7
2.2 Risk matrix
Risk matrix, or often denoted hazard matrix, is one of the most popular SIL de-
termination methods due to it’s simplicity. The risk matrix takes frequency and
consequence into account qualitatively, based on a categorization of the risk pa-
rameters. Figure 2.1 shows a typical risk matrix diagram is modified for SIL de-
termination. The consequence and frequency (likelihood) make one axis each,
enabling the user to plot the situation under consideration in the diagram. If
each box in the diagram has an attached SIL level, the determination process is
simple. The consequence categories may be expressed in terms of economic,
human or environmental loss. The categories divide the consequences into mi-
nor, serious or extensive according to the level of severity. The likelihood cate-
gories are divided into low, moderate or high. The categories can be selected
either qualitatively, using expert judgment, but quantitative tools can in some
cases be utilized to make it easier to determine which category to use. Then the
categories may be attached to economic figures, number of fatalities, frequency
categories, etc. In Figure 2.1, different SILs are applied. Minor consequence -
low likelihood lead to no SIL required. This means that the risk is considered
tolerable. Minor consequence - moderate likelihood lead to a low SIL, while ex-
tensive consequence - high likelihood lead to a high SIL. If a SIL 3 is required,
further analysis should be done, as one SIF may not provide sufficient risk re-
duction (Marszal and Scharpf, 2002).

Figure 2.1: Typical risk matrix modified for SIL determination adapted from
(Marszal and Scharpf, 2002)

If the consequence is one that could cause any serious injury or fatality on

8
site or off site, it could be categorized as serious. If the frequency of this outcome
is expected to be > 10−2 , the assigned category is high. This consequence - like-
lihood pair would in Figure 2.1 give a SIL 3, but with further analysis required
(Marszal and Scharpf, 2002).
It is important to emphasize that the categorization and determination may
lead to an unrealistic result. Other tools and methods may be used in conjunc-
tion with this method to improve the quality of the categories and the accuracy
of the plotting (Marszal and Scharpf, 2002; IEC 61511, 2003).

2.3 Safety layer matrix


Safety layer matrix is a risk matrix which in addition to frequency and conse-
quence takes the number of protection layers (PL) into account. The resem-
blance between Figure 2.1 showing a typical risk matrix, and Figure 2.2 which
show a typical safety layer matrix, is as expected strong.
A PL is according to IEC 61511 a grouping of equipment and / or adminis-
trative controls which functioning together with other protection layers mitigate
the process risk. A PL must lead to a risk reduction factor of at least 10, and fulfill
the following criteria (IEC 61511, 2003):

• Specificity (one PL designed to prevent or mitigate the consequences of


one potential hazardous event. Multiple causes may initiate action by the
PL)

• Independence (PL must be independent of other protection layers, no


common cause failures (CCF))

• Dependability (PL must act as intended in design)

• Audibility (PL must be designed to facilitate validation of function)

A SIS is considered a safety instrumented PL (IEC 61511, 2003). Compared to


the term safety barrier as presented in Sklet (2006) a PL is a safety barrier with
additional requirements.
The classification of the consequence severity is almost identical as for the
risk matrix, with severity categories minor, serious and extensive. Table 2.2 shows
how to estimate the likelihood of the hazardous event which leads to the un-
wanted consequence or impact. The categorization of likelihood in the risk ma-
trix approach focus on frequency specifically, while the safety layer matrix cate-
gorization in IEC 61511 is based on type of events. Plant specific data should be
employed, if available, to establish the likelihood. The event classification in IEC
61511 makes it easy to distinguish between the frequency categories, as the fre-
quencies are related to specific events. Note that the categorization of likelihood
and consequence is done without considering the PLs (IEC 61511, 2003).

9
Table 2.2: Frequency of hazardous event likelihood adopted from IEC 61511
Type of events Likelihood
Qualitative ranking
Events such as multiple failures of diverse instru- Low
ments or valves, multiple human errors in a stress
free environment, or spontaneous failures of pro-
cess vessels
Events such as dual instrument, valve failures, or Medium
major releases in loading / unloading areas
Events such as process leaks, single instrument, High
valve failures or human errors that result in small
releases of hazardous materials
*The system should be in accordance with this standard when a claim that
a control function fail less frequently than 10−1 per year is made

Figure 2.2: Safety layer matrix diagram adapted from IEC 61511 (2003)

10
Figure 2.2 shows a typical safety layer matrix. The risk criteria are embedded
into the diagram, and the methodology and categorization is similar to the risk
matrix. The specific hazardous event likelihood and hazardous event severity
classification is plotted. This results in one of the 9 columns in the figure. In
order to determine the the final box in the figure that contain the necessary SIL
- the number of PLs must identified (IEC 61511, 2003). An example could be a
process leak resulting in catastrophic consequence to personnel (several causal-
ities). The hazardous event severity is categorized as serious. In Table 2.2 the
occurrence of a process leak is classified with high likelihood. Two mechanical
pressure relief devices were identified satisfying the PL criteria. In Figure 2.2 an
event with serious consequence - high likelihood rating with two PLs, would re-
quire a SIL 2. If the number of PLs had been one, a SIL 3 and additional analysis
would be required.

2.4 The OLF 070 guideline


OLF 070 was developed by operators and suppliers of services and equipment,
to facilitate the implementation of IEC 61508 and IEC 61511 in the Norwegian
petroleum industry. The guideline presents conservative minimum SIL require-
ments. A conservative requirement is a strict requirement which takes uncer-
tainty into consideration. It can be compared to oversizing a beam in order to
ensure the rigidity of the construction. The requirements in OLF 070 are given
in a set of tables in chapter seven of the guideline. Background information,
as definition of function including schematics and assumptions, for the various
SIL requirements is documented in appendix A OLF 070. If the tables are not
applicable, then a risk based methodology should be used. The guideline makes
it possible to skip many of the steps in the determination process, leading to
reduced engineering costs. But, the approach is not fully risk based and the re-
sults are not as appropriate as quantitative calculations (OLF 070, 2004). Table
2.3 show the table with SIL requirement to a subsea ESD function.

2.5 Risk graph


The risk graphs are based on methods described in the German publication DIN
19250 published in 1994, and is a popular approach for determining SIL (Bay-
butt, 2007). Risk graphs are qualitative and category based. It considers the con-
sequence and frequency of the hazardous event, but also occupancy and the
probability of personnel avoiding the hazard (Marszal and Scharpf, 2002; Bay-
butt, 2007).
In Table 2.4 the classification of the risk parameters suggested in IEC 61511
is shown. The consequence parameter (C) describes the likely outcome of the
hazardous event, and four categories of consequences are suggested. C A is less
severe than C D , ranging from light injury to many fatalities. In this case conse-

11
Table 2.3: SIL requirement table adopted from OLF 070
Safety function SIL Functional boundaries for given SIL Ref.
requirement / comments
Subsea ESD 3 Shut-in of one subsea well A.13
Isolate one subsea well The SIL requirement applies to a con-
ventional system with flowline, riser
and riser ESD valve rated for shut-in
conditions. Isolation of one well by
activating or closing:

- ESD node
- Topside HPU and / or EPU
- WV and CIV including actuators and
solenoids
- MV
- DHSV including actuators and
solenoids

NOTE: If injection pressure through


utility line may exceed design capac-
ity of manifold or flow line, protection
against such scenarios must be evalu-
ated specifically

NOTE: If a PSD system is specified for


a conventional system for safety rea-
sons, the PSD functions shall be min-
imum SIL 1

12
Table 2.4: Classification of risk parameters adopted from IEC 61511
Risk parameter Category Classification
Consequence (C) CA Light injury to persons
CB Serious injury to one or more
persons. Death of one person
CC Death of several persons
CD Catastrophic effect, very many
people killed
Frequency of presence in the FA Rare to more frequent exposure
hazardous zone (F) (occu- in the hazardous zone
pancy)
FB Frequent to permanent expo-
sure in the hazardous zone
Possibility of avoiding the con- PA Possible under certain condi-
sequences of the hazardous tions
event (P)
PB Almost impossible
Frequency of the unwanted W1 A very slight probability that
consequence (W) the unwanted occurrences oc-
cur and only a few occurrences
are likely
W2 A slight probability that the un-
wanted occurrences occur and
few occurrences are likely
W3 A relatively high probability
that the unwanted occur-
rences occur and frequent
occurrences are likely

13
quences are measured in the extent of injury to people, but also environmen-
tal or financial target measures can be utilized (IEC 61511, 2003; Marszal and
Scharpf, 2002).
The occupancy parameter (F) indicates the fraction of time the hazardous
area is occupied by personnel. F B indicates higher risk than F A , as the area is
more frequently exposed. Usually, F A is selected if the hazardous area is occu-
pied less than approximately 10% of the time IEC 61511 (2003).
The possibility of personnel avoiding the hazard is incorporated in the pa-
rameter P . This parameter reflects what methods the personnel have to identify
and escape the hazard. In addition skill and supervision in process operation,
and the rate of development of the hazardous event are taken into account. Two
categories, P A and P B , are suggested and P B indicates the highest risk. A check-
list of statements that must be true in order to select P A , can be utilized in the
evaluation. Such statements are suggested in IEC 61511.
The final parameter is the demand rate parameter (W), which is the fre-
quency per year of the unwanted consequence without the concerning SIF but
with other safeguards operating. Also for this parameter higher parameter in-
dices indicate higher risk, as they take less credit for risk reduction by other safe-
guards. W1 indicates that only a few occurrences are likely, and a demand rate
less than 0.03 per year could fit such description. W2 and W3 indicate that few
occurrences or frequent occurrences are likely, and suitable demand rates per
year could be 0.03 - 0.3 and more than 3, respectively. The choice of this pa-
rameter will affect the result, and care should be taken when selecting category
(Baybutt, 2007; IEC 61511, 2003).
Figure 2.3 shows a typical risk graph diagram. The path from left to right is
decided by the selected risk parameters. The selected consequence, occupancy
and possibility of avoidance categories result in an output row X . Each output
row corresponds to three values of W . The selection of the demand rate W is
the last step in determining the SIL. Higher W -parameter lead to a higher SIL.
The tolerable level of risk is embedded in the boxes in the three columns at the
right hand side, and the choice of these must support the company risk criteria
(Marszal and Scharpf, 2002; IEC 61511, 2003).
If the separator example, as explained in section 2.1, is employed - the rea-
soning will be as follows: If the likely consequence is evaluated to be serious
injury to one or more persons, C B is selected. Then, F A is chosen because the
area could be rare to more frequent exposed to personnel. It is possible under
certain conditions to avoid the consequences, which indicates that parameter
P A should be used. The combination of these risk parameters result in output
row X 2 . It is a relative high probability that the unwanted occurrence takes place
and the demand rate category is set to W3 . In Figure 2.3 this results in a SIL 1 re-
quirement.

14
Figure 2.3: Typical risk graph

2.6 Calibrated risk graph


The calibrated risk graph method is a semi-qualitative method, similar to the
qualitative risk graph. The same risk parameters are used as for the conven-
tional risk graph approach, and Figure 2.3 is also applicable. Calibration means
that numerical values are assigned to the risk graph, and these are assigned to
the risk parameters. This allows a more precise determination of the SIL, and
making the decisions more objective. The calibration depends on individual
and societal risk, and these issues in addition to company criteria and authority
regulations, should be considered before assigning the parameter values. Cali-
bration does not need to be carried out every time a SIL need to be determined.
The organization only need to do it once for similar hazards(IEC 61511, 2003).
The consequence can be quantified by the number of fatalities. But in many
instances a failure does not cause immediate fatality, which leads to the intro-
duction of the vulnerability concept. Vulnerability (V) is a function of the con-
centration of the hazard and the duration of the exposure. In Table 2.5 a vul-
nerability range is given. By multiplying this measure with the number of peo-
ple present when the area exposed to hazard is occupied, the number of fatali-
ties is estimated. In the table a range is assigned to each consequence category,
making the categorization possible. Note that vulnerability (V) and possibility
of avoiding the hazard (P) are two different factors. V concerns the escalation,
while P concerns the prevention of the hazard by the operator (IEC 61511, 2003).

15
Table 2.5: Example calibration adapted from IEC 61511
Risk parameter Classification
Consequence (C)
C A Minor injury
Number of fatalities

Can be calculated as: ”No. of people present CB 0.01 < No. of fatalities <
when the area exposed to the hazard is 0.1
occupied” · ”vulnerability to the identified
hazard”

V = 0.01 (small release of flammable toxic CC 0.1 < No. of fatalities <
material) 1.0
V = 0.1 (large release of flammable or toxic
material)
V = 0.5 (As above but also a high probability CD No. of fatalities > 1.0
of catching a fire or highly toxic material)
V = 1 (Rupture or explosion)
Occupancy (F) FA Occupancy < 0.1
FB
Percentage of time the exposed area is occu-
pied during a normal working period
Possibility of avoidance (P) PA Hazard can be prevented
by operator taking ac-
tion, after he realizes
SIS has failed to operate.
Refer certain conditions
(given in IEC 61511-3)
PB Adopted if conditions do
not apply
Demand rate (W) W1 Demand rate <
0.1D per year
W2 0.1D < Demand rate <
10D
W3 For Demand rate> 10D,
higher safety integrity
shall be needed
D is the calibration factor

16
According to Marszal and Scharpf (2002) potential loss of life (PLL) ranges could
also be used as a measure of the consequence. PLL is the expected number of
fatalities within a population during a specified period of time (NORSOK Z-013,
2001). Note that care should be taken if PLL is chosen as a measure, because it
incorporates both probability and consequence. When assigning the other risk
parameters it is important to make sure that the consequence parameter is con-
sidered independent (Marszal and Scharpf, 2002).
The parameter F is often measured by the percentage of time the area, that
is exposed to hazard, is occupied. F A should be used if the parameter value is
less than 0.1 (IEC 61511, 2003; Marszal and Scharpf, 2002).
The avoidance factor P A is selected if all conditions stated in IEC 61511-3 are
satisfied. P B is selected if not (IEC 61511, 2003).
The demand rate (W) is the number of times per year that the hazardous
event would occur in the absence of the SIF under consideration. In Table 2.5
ranges to the different categories are assigned. D is a calibration factor that
should make the risk graph result in a level of residual risk that is tolerable. It
is important that issues not are accounted for several times, making the result
erroneous. Documentation of the calibration process with references is neces-
sary, and should be done with care (Marszal and Scharpf, 2002; IEC 61511, 2003).
When the calibration process is finished, and the parameters decided. The
risk graph is used to determine the SIL. The demand rate, occupancy and pos-
sibility of avoiding the consequence of the hazardous event, represents the fre-
quency of the unwanted consequence. In combination with the unwanted con-
sequence the frequency constitutes the risk without the SIF in place. The input
in each box in the risk graph must be in accordance with the tolerable risk (IEC
61511, 2003; Marszal and Scharpf, 2002).
The separator example as referred to in the previous section could again
serve as an illustration. In this case the vulnerability measure is estimated to be
equal to 0.5. Overpressure is severe and results in large release of flammable ma-
terial with a high probability of catching a fire. If the number of people present
when the area is occupied is 2, the resulting number of fatalities is 1 and class C C
is selected as the consequence severity. One operator does maintenance work or
supervision approximately 45 minutes per day, leading to that the exposed area
is occupied less than 10% of the time giving the occupancy class F A . The condi-
tions regarding the possibility of avoidance are satisfied and P A is selected. The
calibration factor D is set to 4. The demand rate is estimted to 20 demands per
year. This is less than 40 and greater than 0.4 which corresponds to W2 . The SIL
is determined as for the qualitative risk graph, and results in a SIL 2 requirement.

17
Chapter 3

LOPA

3.1 What is LOPA?


LOPA was introduced in the 1990s, and has recently gained international popu-
larity. LOPA is referred to in literature as both a simplified risk assessment tech-
nique and a risk analysis tool. Capital improvement planning, incident inves-
tigation, and management of change can be found as additional applications.
LOPA is a flexible tool which can be used in different contexts and applications
making it confusing to understand what it really is. The application under con-
sideration is LOPA as a SIL determination tool.

Figure 3.1: Risk analysis procedures adopted from Rausand and Høyland (2004)

18
According to Marszal and Scharpf (2002) LOPA can be viewed as a special
type of event tree analysis (ETA), which has the purpose of determining the fre-
quency of an unwanted consequence, that can be prevented by a set of protec-
tion layers. The approach evaluates a worst-case scenario, where all the protec-
tion layers must fail in order for the consequence to occur. The frequency of the
unwanted consequence is calculated by multiplying the PFDs of the protection
layers with the demand on the protection system (represented as a frequency).
Comparing the resulting frequency of the unwanted consequence with a toler-
able risk frequency, identifies the necessary risk reduction and an appropriate
SIL can be selected (Marszal and Scharpf, 2002; CCPS, 2001).
LOPA is a semi-quantitative method using numerical categories to estimate
the parameters needed to calculate the necessary risk reduction which corre-
sponds to the acceptance criteria (CCPS, 2001). In a quantitative risk assessment
(QRA) mathematical models and simulations are often used to estimate the ex-
tent or escalation of damage, e.g. toxic diffusion, explosion expansion or fire es-
calation. In addition, FTA or other methods are used to calculate the frequency
of the accidental event (Rausand and Høyland, 2004). In LOPA, simplifications,
expert judgment and tables are used to estimate the needed numbers (CCPS,
2001). LOPA usually receives output from a HAZOP or a hazard identification
study (HAZID) and often serve as input to a more thorough analysis as a QRA.
Figure 3.1 is often referred to as the bow-tie and is a common figure to describe
risk analysis. It shows the accidental event which is linked to the causes and the
consequences, and the methods which may be applied in the different phases.
An ETA focuses on the consequence spectrum not on the causal analysis, im-
plying that LOPA is placed in column (c) to the right in the figure. On the other
hand LOPA is not as in-depth as would be expected from a consequence anal-
ysis and does have a close interaction with HAZOP suggesting that it should be
positioned more to the middle (column b). The final ”position” is somewhere in
between.
Often, an "onion" as the one in Figure 3.2 is used as an illustration of the
protection layers in LOPA. The system or process design has protection layers
including basic process control system (BPCS), critical alarms and human inter-
vention, SIFs, physical protection and emergency response.
BPCS is the control system used during normal operation and sometimes
denoted as the process control system (PCS). Input signals from the process and
/ or from the operator are generated into output which make the process operate
in a desired manner. If the control system discovers that the process is out of
control (e.g. high pressure) it may initiate actions to stabilize the temperature
(e.g. choking the flow) (CCPS, 2001; IEC 61511, 2003).
Alarms monitoring certain parameters (e.g. pressure and temperature) are
considered another protection layer. When the alarm is tripped, the operator
may intervene to stop the hazardous development. Note that the alarm system
has to be wired to another loop than the BPCS in order to be independent (CCPS,
2001; IEC 61511, 2003).

19
Figure 3.2: The LOPA onion

20
Rausand (2004) describes a SIS as a system comprising sensors, logic solver(s),
and actuating (final) items, and can be looked upon as an independent pro-
tection shell for machinery or equipment. A SIS implements the wanted safety
function SIF. In LOPA, SIFs are considered as protection layers.
Physical protection include equipment like pressure relief devices. In a sep-
arator this may be a rupture disc which blows-off pressure if the pressure is
too high. Post release protection is physical protection as dikes, blast walls etc.
These have their function after the release or explosion has occurred. Both of
these types of physical protection are considered protection layers in LOPA (CCPS,
2001; The Dow chemical company, 2002; ACM Facility Safety, 2006).
If an accident occurs, procedures, evacuation plans, equipment and medical
treatment help the exposed personnel to escape, or to mitigate damage / injury.
Such measures are classified as plant and community emergency response, and
are considered the final protection layer (CCPS, 2001; The Dow chemical com-
pany, 2002; ACM Facility Safety, 2006).
LOPA incorporates the reliability of the existing barriers to determine the re-
liability of the needed SIF. Note that LOPA does not determine what protection
layers to implement, only the needed performance. In some cases, a SIF is al-
ready present, and the SIL of an additional SIF shall be determined. How many
and which protection layers that are required, depend on the situation at hand
(CCPS, 2001; The Dow chemical company, 2002).

21
3.2 Explanation of terms
Various authors use different terms in LOPA. Examples are terms like scenario,
impact event and initiating event. This makes it confusing to understand what
is meant by the different terms and how they are applied. What exactly is an
impact event? Does an impact event description include both causes and con-
sequences? What is an impact event compared to an accidental event? What is
a scenario? What is an independent protection layer? ”Where” do we start the
LOPA analysis? The objective of this section is to clarify these questions, and
build the foundation for the further evaluation of LOPA. The relation between
the terms is described by Figure 3.3.

Process deviation
According to NORSOK Z-013 (2001) an accidental event is defined as ”event or
chain of events that may cause loss of life, or damage to health, the environment
or assets”. Another definition is ”the first significant deviation from a normal sit-
uation that may lead to unwanted consequences” (Rausand and Høyland, 2004).
In IEC 60300-3-9 (1995) they use the term hazardous event instead of accidental
event. In the HAZOP study the accidental event is referred to as a process devi-
ation. The term process deviation is from now on used and the definition from
Rausand and Høyland (2004) is acknowledged as adequate.

Impact event
CCPS (2001) describe an impact as: ”The ultimate potential result of a hazardous
event. Impact may be expressed in numbers of injuries or fatalities, environmen-
tal or property damage, or business interruption.” According to IEC 61511 an
impact event is equivalent to the consequence in the HAZOP study. This im-
plies that the impact event is the unwanted consequence of the hazardous event
or accidental event which is referred to as a process deviation. Impact event is
closely related to the unwanted consequence, and the question which remains is
what degree of consequence an impact event represents, e.g. end-consequence
or intermediate consequence. From now on it is chosen to define impact event
as ”the first sign of harm to people, environment or assets”. Examples are a car
crash or an explosion due to overpressure of a separator. The impact event may
lead to an end-consequence which may include fatalities / injury, environmen-
tal damage or economic loss. For the impact event: car crash, the process devia-
tion could be: car starts to slide. The car is out of control and if not the situation
is brought back in control, the impact event occurs. For the impact event: ex-
plosion due to overpressure of separator, the process deviation could be high
pressure up-stream separator.

22
Initiating cause
The initiating causes are the reasons why the process deviation occur, not the
most basic underlying root-causes. The initiating causes are the results of the
root causes. CCPS presents three types of initiating causes: External events,
equipment failures and human failure. External events are earthquakes, hurri-
canes and other external shocks. Equipment failures are control system failures
or mechanical failures. Human failures are either error of commission (failure
to observe or respond appropriately) or error of omission (failure to execute the
task properly or not doing it at all) (CCPS, 2001). For the car crash example an
initiating cause could be slippery road.

Scenario
According to CCPS (2001) a scenario describes a single cause - consequence pair
from the HAZOP. In LOPA terminology this is a single initiating cause - impact
event pair. This implies that a scenario consists of more than just the impact
event. But should not a scenario comprise even more? A more appropriate defi-
nition of a scenario would include more than one cause. The scenario definition
is extended to describing ”the development from a process deviation to an impact
event, including the causes leading to the process deviation”.

Protection layers vs. independent protection layers


The term protection layer was defined by IEC 61511, and four important charac-
teristics were given in Section 2.3. What is the difference beetween a PL and an
IPL, and is the definition appropriate? According to IEC 61511 an IPL must have
the same inherent characteristics. In addition it must provide at least 100-fold
of risk reduction (not 10 as for a PL) and have functional availability of at least
0.9 (IEC 61511, 2003). These definitions seem confusing. From the point of view
of IEC 61511 an IPL is just a PL with stricter requirements to availability and de-
gree of risk reduction. A PL does have the same requirement to independence,
and the name is misleading. A more appropriate definition would be to call all
PLs as IPLs, and IPLs with high degree of availability and risk reduction as high
integrity IPLs. A definition of PL in CCPS (2001) is rewritten to: ”device, system
or action that is capable of preventing a process deviation from proceeding to the
end consequence”. Subsequently an IPL is defined as ”a PL that is capable of pre-
venting a process deviation from proceeding to the end consequence, regardless of
other PLs associated with the same impact event - initiating cause pair, and of the
initiating event”. An IPL should fulfill the characteristics presented in Section
2.3.
Another issue of interest is whether the PLs are designed to prevent the un-
wanted consequence from happening, or placed as barriers to mitigate the con-
sequences after the impact event has occurred. PLs mitigate the frequency of
the occurrence of the unwanted consequence, or mitigate the consequences.

23
An airbag-system is defined as a SIS. The airbag inflates when a set of sensors
send signals to a logic solver which initiates the inflation. If the impact event is
a car crash, this protection system will function subsequent to the occurrence
of the impact event. It limits the extent of damage rather than mitigating the
frequency of the impact event. In other cases SIFs may be placed previous to
the impact event. If the impact event is overpressure of separator, SIFs with the
intention of closing valves and shutting down the system, are vice. The SIF tries
to prevent the impact event from occurring, thus reducing the frequency.

Relation between terms

Figure 3.3: Relation between initiating causes, impact event, process deviation
and IPLs

Figure 3.3 shows the relation between the initiating causes, impact event,
process deviation and the PLs listed in IEC 61511. It shows how all the terms
fit together and the figure and the definitions given found the basis of the un-
derstanding of LOPA. Initiating causes may be the sources of a process devia-
tion which may lead to an impact event. The impact event may result in an
end-consequence. In order to prevent the end-consequence PLs are introduced.
Most of these have the objective of limiting the frequency of the impact event,
but PLs to minimize the extent of damage may also be put in place. Note that
the worst-case scenario is assumed. All the PLs have to fail in order for the end-
consequence to occur thus the analogy to a branch in an ETA. The symbol *
means that the PL may be credited as a IPL. The concept of IPL is discussed in
the case study in Chapter 6. Note that the starting point of the LOPA analysis is
the impact event. After this is identified, the causes are identified and the pro-
tection layers evaluated.

24
3.3 The LOPA team
LOPA is performed by a multi-disciplinary team, which at least should consist of
one:
• operator

• process engineer

• process control engineer

• manufacturing management representative

• instrument / electrical maintenance representative

• risk analysis specialist


One of the team members should be skilled in LOPA methodology, and it is im-
portant that the team has experience with the related process / system. One
of the team members should be a skilled meeting facilitator, and one secretary
of the team should also be elected. Persons with other expertise may take part
in the analysis at different points in the analysis when needed. The meetings
are usually run in several sessions, taking basis in process documentation and a
spreadsheet report to document the analysis (IEC 61511, 2003; Dowell, 1998; BP,
2006).

3.4 LOPA worksheet and the LOPA process


This section describes how LOPA works, and the LOPA process as described in
IEC 61511. The terms are adapted to the definitions presented earlier thus some-
what different from the ones in IEC 61511 Note that different approaches and
methodologies exists, and these are discussed in Section 3.5. The LOPA report
worksheet presented in IEC 61511 is shown in Table 3.1. Further the columns
will be explained briefly step by step.

Impact event
The potential impact event is described in the first column in the table. This is
the consequences determined in the HAZOP study.

Severity Level
In the next column the severity level of the impact event is entered, and levels
of Minor (M), Serious (S), or Extensive (E) are suggested, which is the same clas-
sification as in the risk matrix approach and safety layer matrix approach. Note
that in the risk graph approach the consequence levels are ranging from C A to
C D where C D is the most severe.

25
Table 3.1: Important columns in the LOPA report / worksheet adapted from IEC 61511 (2003)
Protection layers
1 2 3 4 5 6 7 8 9 10

Impact event descrip- Severity Initiating Initiation General BPCS Alarms Additional High integrity Intermediate SIF integrity Mitigated
tion level cause likeli- process etc. mitigation additional event likeli- level event
hood design (restricted mitigation hood likelihood
access) (dikes, pres-
sure relief)

26
Pressure above design E Pressure 0.1 1 1 1 0.21 0.08 1.7 · 10−3 3 · 10−5
pressure of separator. control fail-
Rupture of separator ure causing
and possible ignition. blocked outlet.
Leading to the end- E Spurious trip of 0.001 1 1 1 0.21 0.08 1.7 · 10−5 1.75 · 10−2 3 · 10−7
consequence: No. of the XV in addi-
fatalities between 1 to tion to PV con-
10. Assuming no slug trol failure
entering.
1.717 · 10−3 SIL 1 3.03 · 10−5
Initiating cause and initiation likelihood
All direct initiating causes of the impact event are listed in column 3. In column
4 the likelihood values of the initiating causes occurring, in events per year, are
entered. A table showing typical values is shown in IEC 61511, e.g. a failure with
a low probability of occurring within the lifetime of the plant (dual instrument
or valve failure) is categorized with a frequency between 10−4 and 10−2 per year.

Independent Protection layers


If protection layers satisfy the IPL criteria, they are given credit. The PFD value
is then added in the worksheet. Process design to reduce the likelihood of an
impact event from occurring, when an initiating cause occurs, are listed first in
column 5. Jacketed pipe or vessels serve as examples. BPCS is the next to be
listed in column 5. If the BPCS prevents the impact event from occurring, when
the initiating cause occurs, credit based on its PFD is claimed. The last item
in column 5 takes credit for alarms that alert the operator and utilize operator
intervention.
Additional mitigation layers with associated PFDs are listed in column 6.
Mitigation layers are normally mechanical, structural, or procedural and may
reduce the severity. However, not prevent the impact event from occurring. Ex-
amples of additional mitigation could be pressure relief devices, dikes, restricted
access and evacuation procedures.
IPLs may be credited as high integrity IPLs, if the functional availability is at
least 0.9 and if it provides at least 100-fold risk reduction. They are then listed in
column 7. A table in IEC 61511 presents typical PFD values for certain protection
layers.

Intermediate event likelihood


The intermediate event is the occurrence of the end-consequence with the ex-
isting / planned protection layers in place, but without the SIF under consid-
eration. The intermediate event likelihood is the frequency per year of the oc-
currence the this event. The intermediate event likelihood is entered in column
8. It is calculated by multiplying the initiating event likelihood (column 4) by
the PFDs of the protection layers and mitigating layers (column 5, 6 and 7). The
calculated number should be in events per year, and compared with the corpo-
rate criteria. If the intermediate event likelihood is greater than the corporate
criteria, additional mitigation is needed. Inherently safer design should be con-
sidered before new SIFs are introduced.

27
Safety integrity level (SIL)
If a new SIF is needed, the SIL is calculated by dividing the corporate criteria for
this severity level by the intermediate event likelihood. The result is entered in
column 9.

Mitigated event likelihood


The mitigated event is the occurrence of the end-consequence with all protec-
tion layers in place, including the proposed SIF. The mitigated event likelihood
is the frequency per year of the occurrence the this event. The mitigated event
likelihood is calculated by multiplying columns 8 and 9 and entering the result
in column 10. This is step is continued until the team has calculated a mitigated
event likelihood for each impact event.

Total risk
The last step could be to calculate the total risk with respect to each specific
impact event. The mitigated event likelihood for all the events rated as serious
or extensive, and that present the same hazard are added up. This step could
include additional probabilities, if not accounted for in the previous steps.

Example
In Table 3.1 some rows are filled in. The example is overpressure of a topside
separator taken from Harsem Lund (2007). The HAZOP identified that pressure
above design pressure of the separator could cause rupture and possible igni-
tion, leading to a number of fatalities between 1 and 10. Further, two initiating
causes with initiating likelihoods were identified. General process design, BPCS
and alarms are not given credit as PLs, thus given the value 1. Additional mitiga-
tion (restricted access) is estimated to 0.21, due to an assumed ignition probabil-
ity of 0.3 and occupancy of 70%. IPL additional mitigation is estimated to 0.08,
due to the assumption that 8 PSVs must be running to avoid pressure build-up
above test pressure. The intermediate event likelihood is now calculated for the
initiating events, and the corporate / company criteria for this severity level (E)
is 3 · 10−5 events per year. The sum of the intermediate event likelihoods are
1.717 · 10−3 events per year. Dividing 3 · 10−5 by 1.717 · 10−3 give a necessary risk
reduction of 1.75 · 10−2 , which is a SIL 1 requirement. The mitigated event likeli-
hood becomes 3·10−5 and 3·10−7 events per year, which give a total of 3.03·10−5
events per year.
Note that both in the table and in the calculations accurate numbers are
used with several decimals. This is done for illustration only. Usually, two deci-
mals are appropriate.

28
3.5 Different approaches in literature
Many similarities can be found among the approaches and methodologies pre-
sented in the literature. Summers (2003), Ellis and Wharton (2006) and Dowell
(1998) have presented flowcharts, while IEC 61511 use a worksheet as the basis
for their methodology. BP (2006) have their own procedure providing guidance
on LOPA which includes a flowchart. CCPS (2001) presents a diagram explain-
ing the LOPA steps, with a chapter explaining each step. But the approach in IEC
61511 is the most prevailing. The essential steps that seem common are:
• Documentation of the hazard analysis

• Development of scenario or impact event

• Identification of initiating causes

• Determination of the protection layers including the IPLs

• Quantification (cause frequency / likelihood and PFD)

• Target risk evaluation / SIL determination


As the list indicates the major steps in the SIL determination process are cov-
ered. Most approaches take information from previous studies to identify haz-
ards, and to found a basis for the next steps. The initiating causes are identified,
and the frequency determined. The most substantial differences between the
various approaches are the use of terms, the order of sequence and the intended
application. Another distinction is how the SIL is incorporated and evaluated.
Often the "as is" process design is evaluated. The existing protection layers are
identified and the intermediate event likelihood determined before assigning a
SIL level to the SIF. Sometimes the SIF under consideration, with the expected
PFD, is implemented implicit in the calculations. This result in a different crite-
rion for acceptability. The mitigated event likelihood is then the calculated fre-
quency that is compared to the acceptance criteria, not the intermediate event
likelihood.
Some authors use screening tools, and / or suggest LOPA as a part of a total
methodology. Ellis and Wharton (2006) suggest such a close interface between
LOPA and other methods. Figure 3.4 is an extract of the determination method-
ology presented in Ellis and Wharton (2006). The consequences of the impact
events are classified. A consequence level is chosen for the impact event under
consideration, and LOPA used if the most severe category C E is selected. If not
a risk graph approach is utilized. If the risk graph results in SIL 1 (or lower) this
is documented as the final SIL. The risk graph may result in a high SIL (SIL 2
- 4), and LOPA is suggested in those cases. The LOPA may conclude a SIL 3-4.
If this is the case, a fault tree analysis (FTA) is initiated. If the FTA result in SIL
3-4, redesign to eliminate hazard or reduce event severity or event likelihood is
needed. Harsem Lund (2007) supports the use of risk graph and QRA in addition
to LOPA, depending on the calculated SIL.

29
Figure 3.4: Extract of SIL determination methodology from Ellis and Wharton
(2006)

3.6 Aker E&T methodology


Aker E&T LOPA methodology is presented in Figure 3.5. The method is modified
in contrast to the one given in Nordhagen (2007). Compared to the approaches
discussed in Section 3.5, the Aker E&T approach is an overall methodology, not
taking the proposed SIF implicit into account. Often the customer methodology
(i.e. Statoil, BP) found basis for the analysis.
P&IDs are schematic diagrams describing piping, equipment and instru-
mentation connections within process plants. ISO 10418 (2003) is a technical
standard that provides objectives, functional requirements and guidelines for
techniques for analysis, design and testing of surface process safety systems.
This standard helps the design team to implement safety functions in the P&IDs
for the concerning system. A HAZID, HAZOP or WHAT-IF analysis helps to iden-
tify process deviations which require additional SIFs. After all information have
been gathered and documented in the P&IDs and additional documentation, a
LOPA is initiated. The report sheet in Table 3.1 is used, and the steps described
in Section 3.4 followed except from the steps where the mitigated event likeli-
hood and the total risk is calculated. An example of acceptance criteria is shown
in Table 4.1, and the accepted frequency denoted target mitigated event likeli-
hood (TMEL). The mitigated event likelihood is in the Aker E&T approach equal
to the TMEL (Nordhagen, 2007; ISO 10418, 2003).

30
Figure 3.5: Aker E&T methodology adapted from Nordhagen (2007)

The SIF under consideration is assumed not in place during the analysis, and
Acc. freq
the formula used in the evaluation of the LOPA results can be written: Total IEL .
If the fraction between the accepted frequency (Acc. freq.) and the calculated
total intermediate event likelihood (IEL) is greater or equal to 1, the team shall
evaluate whether the SIF shall be removed or not. This implies that the result-
ing frequency of the end-consequence, without the proposed SIF, is equal or less
than the accepted frequency. The analysis team can either remove the SIF, be-
cause the system is evaluated safe enough, or keep the SIF but without any re-
Acc. freq
quirements to the safety function. If 1 > Total IEL > 0.1, ”SIL 0” is selected. This
implies that the intermediate event likelihood is between 1 and ten times higher
than the acceptable value. No further evaluation is necessary, but the SIF is
Acc. freq
kept in order to achieve some risk reduction. If 0.1 > Total IEL > 0.01, which is
equivalent to SIL 1 in IEC 61511, SIL 1 is selected and no further evaluation is
Acc. freq
done. SIL 2 is selected if 0.01 > Total IEL > 0.001. If the analysis result is SIL 3
Acc. freq
(0.001 > Total IEL > 0.0001), a QRA is initiated to further evaluate the SIF (Nord-
hagen, 2007).

31
Chapter 4

Preferred approach

4.1 Flowchart
When performing LOPA, a clear methodology and approach is needed to make
the team focus on the analysis and not on how to do the analysis. The preferred
approach is a developed recommended approach based on the worksheet pre-
sented in IEC 61511, reproduced in Table 3.1. It is modified taking the views
presented in Sections 3.5 and 3.6 into consideration using the terms described
in Section 3.2. The steps in Figure 4.1 are described in the paragraphs below.

Step 1: Develop and document the risk acceptance criteria


It is of great importance that this step is done with care. The acceptance crite-
ria has to respond to the requirements from the company, authorities and cus-
tomers. Acceptance criteria should be established for different types of conse-
quences as safety, environmental and economical. In Table 4.1 an example of
acceptance criteria for safety hazards are presented. Note that the TMEL is a
frequency. For economical / commercial hazards the criteria could consist of
target mitigated likelihoods and monetary consequences. If acceptance criteria
do already exist, these should be verified before employed.

Step 2: Gather and document data


The results from HAZOP, HAZID and WHAT-IF analysis must be gathered and
documented. In addition, documentation like equipment data, maintenance
plans and operational conditions and procedures are important to obtain. If the
data material is not sufficient, further data must be collected. Especially, the
need for further hazard identification must be evaluated.

32
Figure 4.1: Preferred approach

33
Table 4.1: Target mitigated event likelihood for safety hazards adapted from
Nordhagen (2007)
Severity level Safety consequence Target mitigated
event likelihood
CA Single first aid injury 3 · 10−2 per year
CB Multiple first aid injuries 3 · 10−3 per year
CC Single disabling injury or mul- 3 · 10−4 per year
tiple serious injuries
CD Single on-site fatality 3 · 10−5 per year
CE More than one and up to three 1 · 10−5 per year
on-site fatalities

Step 3: Transform and integrate data


The data material have to be adapted to the input that LOPA requires. Accep-
tance criteria, frequencies and consequence / likelihood ratings may have to be
converted. The interface between HAZOP and LOPA is discussed in Chapter 5.

Step 4: Select impact event


The impact events should be evaluated separately, one at the time.

Step 5: Screen impact event


To each impact event a consequence severity level is determined, and the im-
pact event under consideration is screened by a criterion using these levels. This
could have been done already in the HAZOP study, and if applicable these re-
sults can be used. In Table 4.1 such severity levels are given. Let C be denoted
as the consequence severity level divided into five categories. If an impact event
is classified with consequence severity level C > C C (C D or C E ), a QRA has to
be performed. This implies that impact event consequences rated as C A , C B , or
C C are evaluated with LOPA. Note that the criterion for selecting either QRA or
LOPA should be adapted to how the acceptance criteria are expressed and the
situation under consideration.

Step 6: Identify initiating causes


The initiating causes are most likely identified in the HAZOP study, but these
may not include sub-causes. Sub-causes might be beneficial to identify to get
understanding of the situation at hand. But also to get an accurate result when
it comes to the calculations. Expert judgment and previous studies (as HAZOP)
is used in the identification process.

34
Step 7: Establish / determine initiating cause frequencies
The initiating cause frequencies must be determined. In Table 4.2 initiating
cause frequencies are presented. In addition expert judgment and plant specific
data / company data may be helpful in determining the frequencies.

Step 8: Select initiating cause - impact event pair


One pair of initiating cause and impact event should be evaluated at the time.

Step 9: Identify IPLs and determine PFDs


The IPLs must be identified, and the assumption of independence should be
evaluated with care and be thoroughly documented. If the IPL criteria are satis-
fied the PFDs are added in the LOPA worksheet in 3.1. Estimates of PFDs can be
found in tables in CCPS (2001) and OREDA. But company or plant specific data
can also be used. Table 4.3 shows some PFDs for different IPLs. If a protection
layer can not be given credit as an IPL the PFD value entered in the worksheet
is 1. The inherent process design and the reduction factor this gives should be
evaluated carefully. This protection layer is difficult to assess, and in most cases
no risk reduction is given credit.
In addition to the PFDs the following frequency modifiers may be included:

• Occupancy

• Ignition probability

• Time at risk (for systems not continuously in operation)

The additional mitigation (restricted access) column shall include ignition prob-
ability, in addition to occupancy. The occupancy factor is calculated as for the
risk graph (IEC 61511, 2003). For flammable hazards ignition probability shall
be considered. If there are many sources of ignition and the release is large, a
conservative value should be chosen. A conservative value is in this case a value
close to 1. The time at risk factor reflects the time the system is in the hazardous
mode, and is evaluated only for systems not in continuous operation. All of the
frequency modifiers are are a number between 0 and 1, and it should be taken
care in such a way that not too much risk reduction is given credit (BP, 2006;
CCPS, 2001; Harsem Lund, 2007). Note that the frequency modifiers are optional
and should be seen in relation to the impact event under consideration.

Step 10: Calculate intermediate event likelihood (IEL)


J
Y
f IEL,i = f i · P F D ij (4.1)
j =1

35
Table 4.2: Typical frequency values assigned to initiating causes adapted from
CCPS (2001)
Initiating event Frequency range from Example of a value
literature (per year) chosen by a company
Pressure vessel residual 10−5 to 10−7 1 · 10−6
failure
Piping residual failure- 10−5 to 10−6 1 · 10−5
100m-full breach
Piping leak (10 % section)- 10−3 to 10−4 1 · 10−3
100m
Atmospheric tank failure 10−3 to 10−5 1 · 10−3
Gasket / packing blowout 10−2 to 10−6 1 · 10−2
Turbine diesel engine 10−3 to 10−4 1 · 10−4
overspeed with casing
breech
Third party intervention 10−2 to 10−4 1 · 10−2
(external impact by back-
hoe, vehicle etc.)
Crane load drop 10−3 to 10−4 per lift 1 · 10−4 per lift
Lightning strike 10−3 to 10−4 1 · 10−3
Safety valve opens spuri- 10−2 to 10−4 1 · 10−2
ously
Cooling water failure 1 to 10−2 1 · 10−1
Pump seal failure 10−1 to 10−2 1 · 10−1
Unloading / loading hose 1 to 10−2 1 · 10−1
failure
BPCS instrument loop 1 to 10−2 1 · 10−1
failure
Regulator failure 1 to 10−1 1 · 10−1
Small external fire (aggre- 10−1 to 10−2 1 · 10−1
gate causes)
Large external fire (aggre- 10−2 to 10−3 1 · 10−2
gate causes)
LOTO (lock-out tag-out) 10−3 to 10−4 per oppor- 1 · 10−1 per opportu-
procedure failure tunity nity
Operator failure (to ex- 10−1 to 10−3 per oppor- 1 · 10−2 per opportu-
ecute routine procedure, tunity nity
assuming well trained, un-
stressed, not fatigued)

36
Table 4.3: PFDs for IPLs adapted from CCPS (2001) and BP (2006)
IPL PFD
BPCS, if not associated with the initiating 1 · 10−1
event being considered
Operator alarm with sufficient time avail- 1 · 10−1
able to respond
Relief valve 1 · 10−2
Rupture disc 1 · 10−2
Flame / detonation arrestors 1 · 10−2
Dike / bund 1 · 10−2
Underground drainage system 1 · 10−2
Open vent (no valve) 1 · 10−2
Fireproofing 1 · 10−2
Blast-wall / bunker 1 · 10−3
−1
Identical redundant equipment 1 · 10 (max credit)
Diverse redundant equipment 1 · 10−1 to 1 · 10−2
Other events Use experience of personnel
SIS that typically consist of single sensor, 1 · 10−1 to 1 · 10−2
logic and final element
SIL 1
SIS that typically consist of multiple sensors, 1 · 10 to 1 · 10−3
−2

multiple channel logic and multiple final el-


ements (for fault tolerance)
SIL 2
SIS that typically consist of multiple sensors, 1 · 10 to 1 · 10−4
−3

multiple channel logic and multiple final el-


ements. Requires careful design and fre-
quent proof tests
SIL 3

37
Equation 4.1 shows the formula to calculate the intermediate event likeli-
hood, f IEL,i , for a certain initiating event, i . Let the number of IPLs range from 1
to J, and each IPL have a PFD denoted P F D ij . The product of the PFDs is multi-
plied by the frequency of initiating event i , f i . The intermediate event likelihood
is the expected frequency of the consequence with the credited IPLs in place.

Next initiating cause - impact event pair


If there are more initiating event - impact event pairs, they should be evaluated.
As shown in Figure 5.1 the analysis team have to go back to the pair selection
phase. This process is iterative until all pairs have been evaluated

Step 11: Sum up the intermediate event likelihoods


The intermediate event likelihood of all the related initiating cause - consequence
pairs have to be summed, in order to identify the total rate of demands that are
not eliminated by the system (including planned / existing protection layers and
mitigation). Equation 4.2 shows the applied formula to determine the total mit-
igated event likelihood f IEL,total , for initiating events ranging from i = 1 to i = I .

I
X
f IEL,total = f IEL,i (4.2)
i =1

Target risk measurement


Column 3 in Table 4.1 shows the target mitigated event likelihood (TMEL) for
different consequence severity levels. The combination of the TMEL and con-
sequence category is in this case the risk acceptance criteria, which is the target
risk measure. For the concerning consequence severity level - the total interme-
diate event likelihood and target mitigated event likelihood are compared. If the
total intermediate event likelihood is less than the target mitigated event likeli-
hood, the target risk is acceptable. The next impact event can then be evaluated.
If not, a SIL should be determined. Note that even if the target risk is acceptable,
introducing a SIL may still be vice due to uncertainty in the calculations.
Modifications and changes to planned / existing system should be consid-
ered prior to introducing a SIF. Can the risk be reduced by enhancing the existing
protection layers, or by changing the design? If the answer is yes, such measures
should be evaluated, and the new intermediate event likelihood calculated and
compared with the acceptance criteria. If the answer is no, a SIF with an associ-
ated SIL have to be implemented.

Step 12: Determine SIL


The gap between the acceptable risk (the target mitigated event likelihood cor-
responding to a specific consequence category) and the current risk (interme-

38
diate event likelihood) must be eliminated by the SIF, hence the needed SIL. By
dividing the target mitigated event likelihood by the total intermediate event
likelihood, the PFD responding to the SIL is found. Equation 4.3 show how the
acceptable frequency, f Acc , is used to determine the necessary risk reduction.
The target mitigated event likelihood is denoted f TMEL .

f Acc f TMEL
SIL = neccesary risk reduction = = (4.3)
f IEL,total f IEL,total

Screen by SIL
If the resulting SIL > SIL 3, a QRA should be initiated. A high SIL requirement is
stricter demanding higher reliability and performance of the SIS. LOPA includes
uncertainty, and for SIL requiring high integrity a more thorough analysis is rec-
ommended. If SIL < SIL 4, the flowchart loop is finished. Note that the screening
criterion in this case is SIL > 3, and the criterion should be adapted to the situa-
tion at hand. In some cases SIL > SIL 2 is more applicable.

Step 13: Calculate mitigated event likelihood (MEL)


The last step is to calculate the mitigated event likelihood, f mit,i . This is the fre-
quency of the consequence in events per year, after the SIF has been imple-
mented. The selected SIL is multiplied with the intermediate event likelihood
to obtain the mitigated event likelihood, as Equation 4.4 shows.

f MEL,i = f IEL,i · SIL (4.4)


The calculation is done for all rows in the LOPA worksheet related to the
concerning impact event. Note that the mitigated event likelihood is the same as
the TMEL if the exact number of the calculated SIL is employed. It then serves as
a check whether the acceptable risk is satisfied or not with the current calculated
SIL.
This is the last step in the LOPA procedure. If there are more impact events,
these shall be evaluated. Then, the analysis team go back to the pick impact
event - phase. But, this is not implemented in the flowchart. The team usually
continue the analysis until all process deviations from the HAZOP are evaluated.

4.2 Comments to the preferred LOPA approach


The preferred approach is an overall approach considering the planned / exist-
ing system without the proposed SIF. As discussed previously several screening
tools exists, but it is chosen to screen by consequence and SIL only. Conducting
a risk graph-analysis for then to initiate a LOPA cause extra work and increased
engineering cost.

39
Only safety aspects have been considered. Usually economical and environ-
mental issues are also evaluated during a LOPA analysis. Such levels may be
determined to the SIF, and the integrity level giving the highest integrity level
chosen. Note that this requires additional acceptance criteria (BP, 2006; Nord-
hagen, 2007).
In the approach it is chosen to select an impact event before it is screened by
severity level. Another possibility is to do this the other way around.
Another issue is how to express and transmit the requirements to the ven-
dors or to the further allocation process. If the LOPA result in a required PFD
8 · 10−3 giving SIL 2, and the suppliers design their product with a designed PFD
of 1 · 10−2 the outcome may be that the system do not fulfill requirements. Im-
portant issues that must be covered in the interface work packages by the system
vendor are: What is the requirement? How is it expressed?

40
Chapter 5

Interface with HAZOP

5.1 Introduction to HAZOP


Table 5.1 presents a typical HAZOP worksheet. HAZOP is a structured way of
examining the planned or existing process operation. The objective of a HAZOP
study is to identify and evaluate problems that may represent risk to personnel
or equipment, or prevent efficient operation. The HAZOP is usually performed
early in the design stage, in a multidisciplinary team. The HAZOP meetings /
sessions are carried out with a leader, a secretary and team members with pro-
cess experience. The system is divided into nodes, and each node is evaluated by
a set of guidewords and parameters. The results are recorded in a report sheet
like the one in Table 5.1. A guideword + a parameter lead to a deviation. The
causes are the reasons why the deviation occurs, and the consequences are the
results of the deviations. Safeguards have the intention of reducing frequency of
occurrence and / or mitigate the consequences. During the meeting actions are
allocated to the participating parties. This can be technical improvements, but
also work tasks (Rausand, 2005). The briefly described HAZOP methodology is
close to how HAZOP is performed by Aker Solutions. Note that the experience
and knowledge of the participants are vital in getting a thorough examination.

5.2 HAZOP integration


Traditionally, HAZOP and SIL-determination have been two separate sessions.
They both require much of the same information and a common database is
beneficial, as it results in saved time and cost. Performing the analyzes in one
session give savings up to 30% and a significant improvement in data integrity
and manageability (Bingham and Goteti, 2004; ACM Facility safety, 2004). Soft-
ware tools to integrate LOPA and HAZOP exist, but Aker Solutions do not employ
such programs. Software programs can be used when HAZOP and LOPA are in-
tegrated in one session, but also when two sessions are performed. Further, the
relationship between the HAZOP output and LOPA input is discussed.

41
Table 5.1: Process HAZOP worksheet adopted from Rausand (2005)
Study title: Page:
Drawing no: Rev. no.: Date:
HAZOP team: Meeting date:
Part considered:
Design intent: Material: Activity:
Source: Destination:
No. Guideword Element Deviation Possible Consequences Safeguards Comments Actions Actions
/ process causes required allocated to
parame-

42
ter
Sep- High pressure Pressure Failure Release to envi- Alarm, oper- Evaluate Joe John-
arator above de- of BPCS, ronment ator, deluge new PLs. son (Aker
sign pres- high level, system Solutions)
sure external fire
Figure 5.1: Relationship between HAZOP and LOPA worksheets

Figure 5.1 shows the interaction between the HAZOP and LOPA worksheets.
LOPA is performed from the left to the right in the worksheet and receives input
from the HAZOP during the analysis. Note that the HAZOP worksheet in the fig-
ure is somewhat different from the one presented in Table 5.1, as it incorporates
severity level (S) and likelihood (L) of the HAZOP consequence (IEC 61511, 2003;
Dowell and Williams, 2005; CCPS, 2001).
If the (process) deviation in the HAZOP is high pressure, the HAZOP con-
sequence could be: release to environment. The impact event would then also
be release to environment because the consequence identified in the HAZOP
answers to the impact event in LOPA.
The possible causes from HAZOP are the initiating causes in LOPA (Dowell,
1998; IEC 61511, 2003). Further transformation or evaluation of causes and sub-
causes may be necessary and should be expected.
The safeguards identified in HAZOP are denoted PLs in LOPA. Note that all
IPLs are safeguards, but not all safeguards are IPLs (CCPS, 2001). What IPLs
to include and in which column in the LOPA worksheet they should be imple-
mented, requires evaluation. The actions required column in the HAZOP work-
sheet may include many things, e.g. new recommended safeguards and work
tasks. New recommended safeguards could either be modifications to existing
PLs and design or new protection layers, e.g. SIFs (CCPS, 2001). In Figure 5.1
the arrows are blue and dotted which indicates that the information from the

43
columns including safeguards and actions required can not be transformed di-
rectly.
The HAZOP consequence severity ranking (S), and the HAZOP consequence
likelihood (L) can be transformed to LOPA, and impact event severity level and
initiating cause frequency are the applicable terms in LOPA with associated columns
(Dowell and Williams, 2005). The HAZOP worksheet does not necessarily in-
clude these columns. There are several views of what columns are included in
the HAZOP according to what the organization or author prefer. The HAZOP
may either include severity ranking and likelihood of the HAZOP consequence,
or just the severity ranking. Another possibility is that HAZOP has none of these,
as in Table 5.1. This makes it difficult to know how this part of the interface will
be. If the HAZOP worksheet has both the severity and likelihood ranking it is not
certain that this categorization is used, adding another issue to the current prob-
lem. These issues must be evaluated prior to a LOPA and the blue dotted lines
in Figure 5.1 indicate that evaluation is needed when transferring data to LOPA.
It is suggested that the same risk matrix is used for HAZOP as for the LOPA with
related risk acceptance criteria. At least the severity ranking should be identi-
cal, because the initiating cause frequencies in LOPA usually are obtained from
tables and / or expert judgment. In BP (2006) such a common risk matrix in-
cluding risk acceptance criteria is presented.

5.3 Adjustments and transformation of data


It might be that only limited data are available to the analysis team. This requires
the analysis team to do adjustments. In Section 3.4 and Chapter 4 the initiating
cause frequency was represented as a number of occurrences per year. The fre-
quency from the data source may be expressed in occurrences per hour or per
minute. Sometimes the data is not even given as a frequency, but as a PFD. Ex-
amples are human error to execute a task or a crane load drop. If the frequency
is expressed in the wrong unit, the team has to multiply the data to get the cor-
rect frequency. When only a PFD is available, the PFD has to be multiplied with
the number of demands per year to get the wanted frequency (CCPS, 2001).
Another issue is when only general industry data are available. General data
should be adjusted to fit the local conditions. This requires understanding of
how the local conditions are compared to the general conditions.
In LOPA the numbers are often expressed in orders of magnitude. It is im-
portant that the team is consistent when rounding the numerical values (CCPS,
2001).

5.4 HAZOP / LOPA program specification


It is decided to assume that HAZOP and LOPA are divided into two sessions, but
that they are adapted to each other to enable a better interface. If HAZOP and

44
LOPA are performed by using an integrated software tool, several of the phases
in Figure 4.1 may be performed almost automatically, e.g. data gathering and
documentation and transformation of data. In addition, the calculation phases
are performed more efficiently. The objectives of a HAZOP / LOPA tool are:

• Reduce the time spent on the analysis (typing / rework, data collection,
meeting activity, calculations)

• Making it easier to quality check the results as the calculations/analysis


are conducted in real time

• Increased quality of the analyses

Specifications are vital in order to make a consistent and thorough software


program. These include what exactly the program has to do, and what character-
istics it needs. The basis for the specification is the objectives given above, and
the previous section. The specification of the proposed HAZOP / LOPA program
is as follows:

• HAZOP worksheet cells equal to cells in LOPA report, and automatic trans-
formation of data. This applies to:

– HAZOP consequence = LOPA impact event


– HAZOP possible causes = LOPA initiating causes
– HAZOP consequence likelihood = LOPA initiating cause frequency
(Note: may need adjustment)
– HAZOP consequence severity level = Severity level (Note: May need
adjustment)

• Calculate results based on data:

– Intermediate event likelihood


– Mitigated event likelihood
– SIL

• Provide database with risk acceptance criteria

• Interface with additional databases:

– Initiating cause frequency


– PFDs of IPLs

• Automatically include risk acceptance criteria in the calculations

• User interface quality assurance:

45
– Interactive SIL selection which allows the user to select a SIL by click-
ing and see the impact on the mitigated event likelihood on the screen
– Rectify erroneous input from user
– Modify input / help to specify the units
– Reminders / pop-up boxes

• Help function with guidelines describing how to implement LOPA. This


should include a flowchart, explanation of terms and examples. The help
function database should be searchable.

The planned software platform is a Microsoft Excel-workbook in combina-


tion with Visual Basic (VB) and macros.

5.5 Illustration of software program


To better illustrate how a program could work the execution is divided into 5
steps. It is important to emphasize that a real program has not been created,
only a model / illustration of how it could work. The illustration is showed in
Appendix B. Note that the suggested program is a simple program, with the pur-
pose of describing the underlying solutions. It is not put emphasis on sophisti-
cated coding.

Step 1 - HAZOP
The cells containing the HAZOP consequences are set equal to the ones that
shall contain the impact events. In excel this could be done by either creating
a VB macro which copies the information, or by defining the cell information
equal directly in Excel. The same applies to the possible causes in HAZOP. The
risk matrix sheet contains the classification of the HAZOP consequence and im-
pact event severity. The chosen severity level is transferred in the same man-
ner as the HAZOP consequence. To initiate the process of transferring the data,
a command button which is constantly visible is placed in the bottom of the
LOPA sheet. This is named ”Transfer HAZOP data”, and when clicked the rows
containing the data are transferred or copied.
After all the cause and impact event data are transferred, the impact events
are screened by severity level. Those impact events that are classified above a
certain severity level are colored red because the initiation of a QRA is suggested.
The encoding solution is VB in addition to macros.
Some impact events are similar, and combining several impact events is rel-
evant. This is not taken into account in this program illustration.

46
Step 2 - Retrieve initiating cause frequency
Next to the command button proposed in Step 1, a command button named
”implement initiating cause frequency” is placed. When this is clicked the user
may choose which cell to implement the value and which value to select in the
database sheet. The user may also adjust the numbers. This requires more ex-
tensive VB encoding.
The initiating cause frequency may be given as a PFD. A pop-up box, which
appears after the value has been implemented, asks the user to specify addi-
tional information if it is necessary. The number of demands / opportunities
per year is such information, this is done to make sure that the correct unit is
used. The program adjusts the numbers automatically.

Step 3 - Retrieve IPL PFDs


The same method and encoding applies to the IPL PFD selection. When all the
PFDs are filled in, the IPL cells that contains no numerical value are given the
value 1. This can be realized by a IF sentence checking if the cells have a value
or not, and employing the necessary values.

Step 4 - Calculation
The intermediate event likelihood is calculated directly in Excel by formulas, i.e.
’cell 10’ = product(’cell 4’;’cell 9’).
The TMEL is specified in the risk matrix sheet. Corresponding to which
severity level is selected the program implements the correct value of TMEL in
the mitigated event likelihood cell in the LOPA sheet. A simple IF sentence could
do this automatically. A command button called ”Calculate SIL” initiates the SIL
calculation. The IELs for each initiating cause related to the same impact event
is added. A set of IF sentences count how many rows that are related to the same
impact event and calculate the total IEL for the respective impact event. The
value of the total IEL for the impact event is divided by the TMEL value, and
the result is the needed SIL. IF sentences containing text strings evaluates the
results and prints a message to the user in the cell, i.e. ”SIL 2” or ”No SIS nec-
essary”. This part of the program requires extensive VB encoding. The program
has to remember parameters, and use these to calculate the correct columns
and implement the results in the correct cells.

Step 5 - SIL selection


It is not certain that the calculated SIL is the one the team wants to employ.
A command button named ”Change SIL”makes an input box appear if clicked.
The user may input the wanted SIL or specify the PFD of the SIS. The mitigated

47
event likelihood is again calculated, and a pop-up box notifies the user if this
PFD fulfill the TMEL requirement.
A screening process based on the calculated SIL is beneficial, as higher SILs
may require the initiation of a QRA. The program may color the entire row in a
certain color if the SIL is higher than a specified limit.

Comments to the illustrated software program


The illustrated program seems reasonable, as it helps the user to manage data,
and do the needed calculations. In addition it supports the user during the
analysis. The help function mentioned in the specification in section 5.4 is not
treated, but is expected to be a vital part in a program. The illustrated program
should be evaluated more in detail, and should be extended from a thought pro-
gram to a real prototype with more advanced coding and better user interface.
Expert judgment make an extensive amount of the analysis, which is difficult
to incorporate in a program. A software tool that ”learns by doing” is beneficial.
An example is a software program that saves and interprets the possible initi-
ating causes of an HAZOP or LOPA analysis. When a new analysis on a similar
system is performed the information from previous studies becomes available
to the user. This is an effective way of facilitating the transfer of experience.

48
Chapter 6

Case study: Applicability of LOPA

The objective of the study is to apply LOPA to a real system, to illustrate and eval-
uate the LOPA process described in Chapter 4. First the case and the concerning
system is described, before the LOPA approach and results are presented and
discussed. Finally, comments and remarks are given.

6.1 Case text


It is assumed that a new SIF may have to be implemented, and the LOPA is per-
formed to evaluate if this is necessary, and what SIL to assign. The evaluated
SIF is assumed not in place during the analysis. The topside oil/gas/water sep-
arator located in the FPSO is defined as the EUC. Overpressure of the topside
separator is evaluated in the case, and the source of the pressure build-up is the
reservoir. The case has a subsea and topside part combined together, and the
case schematic in Figure 6.1 describes a typical SPS and topside separator de-
sign. Skarv (BP / Aker E&T) and Morvin (Statoil / Aker Subsea) are two projects
that have P&IDs mounted on the same principles as the schematic.

6.2 Introduction to system


The production flows from the well through the X-mas tree (XT), the produc-
tion choke module and the manifold. From the manifold the flow is lead to the
riserbase and up to the FPSO and the separator in a production riser. The next
paragraphs explain the different parts of the system.

FPSO and topside equipment


The flow consists of water, oil and gas which are segregated in the separator lo-
cated on the FPSO. The separator has three outlets. Two for gas and produced
water, and one liquid outlet that goes to the second stage separation process.
The topside process control system control the inlet flow to the separator and

49
Figure 6.1: SPS and separator schematic

50
consist of a pressure transmitter (PT) and the control valve (CV). The process
shutdown valve (PSDV) and pressure safety transmitter (PST) is the only shut-
down possibility topside denoted PSDtopside . When the PST detects high pres-
sure the PSDV closes. The valve is hydraulically or air operated, and a logic solver
interprets the signal from the PST. Usually, additional barriers are located in the
turret, but for simplicity,these are neglected. A mechanical pressure relief device
is placed in the separator called production shutdown valve (PSV). This is either
a spring-loaded device or a pilot operated device that allows gas to go to flare if
the pressure exceeds a certain limit.
The subsea control unit (SCU) and the hydraulic pump unit (HPU) are lo-
cated topside in the FPSO. The HPU is basically a pump that supplies hydraulic
fluid to the subsea control module (SCM) and the HIPPS control module (HCM),
which again provides hydraulic pressure to the valve actuators. The SCU in-
cludes the logic solver which interprets the signals from the pressure and tem-
perature transmitters, and two surface power and communications units (SPCU)
or circuit breakers.
In the umbilical electronic signals (to and from the SCU), hydraulics (from
the HPU) and scale and hydrate (methanol) inhibitors are transported from the
FPSO to the production system on the seabed.

Choke module
The production choke valve (PCV) has the objective of throttling the flow to con-
trol the temperature and the pressure. The choke module is the process control
system located subsea. It is important that the flow from different XTs have the
same pressure to prevent one well from producing into another.

X-mas tree
The XT is an assembly of valves, spools and fittings for the oil well. The down
hole safety valve (DHSV) is the valve closest to the reservoir, but not used as a
shutdown o ption in case of overpressure. The production master valve (PMV)
and the production wing valve (PWV) are the next two valves in the production
pipeline, and possible shutdown options. The crossover valve (XOV) is an annu-
lus service line. It can relief a potential pressure buildup in annulus, by injecting
the pressure in the production flow. In addition to the valves described above
the XT provides scale inhibitor and / or Methanol inhibitor injection lines. Note
that these are neglected in the schematic.
The XT valves are hydraulically held. The pressure from the fluid column
resist a spring force in the valve actuator to keep the valve open. In order to
shut the valve the hydraulics are bled off and the spring makes the valve go to
closed position. The valve is fail safe because it goes to a safe position (closed
position) in case of a failure (leakage in the hydraulic system, spring collapse
etc.). When closing the valve the hydraulics may either be bled off in the subsea

51
control module (SCM) or to sea. Another possibility is to turn down the pump
in the HPU in order to create a pressure drop.
The subsea control module (SCM) is together with the HPU / SCU the sus-
bea control system. Note that a process control system (like the choke module)
controls the flow, while the subsea control system is used to control the valve
operation on the XT. The subsea control system contains hydraulics and accom-
modates two subsea electronic modules (SEMs) which is the electronic part of
the control system. When the PTs used as reference detect high pressure, signals
are sent to the SEMs which transforms the signals into a rating. This rating (elec-
tronic pulse) is sent to the logic solver in the SCU. If the voting in the logic solver
(i.e. 2oo4) decides to initiate a shutdown, initiation signals are sent back to the
SEMs. The SEMs control change-over valves that are held electrically. When the
logic solver commands a shutdown the valves will switch, enabling hydraulics
from the actuator to bleed off in an internal loop in the SCM.
PSDsubsea is initiated automatically and either the PMV or the PWV and the
XOV must be closed. Figure 6.1 shows that the well is isolated by performing at
least one of the two shutdown options. Usually, both options are used during a
PSDsubsea shutdown. The PT / TT downstream the PCV are used as reference. If
high pressure is experienced at this point the PSD is initiated.

HIPPS
The HIPPS is located in the manifold. The manifold is an arrangement of piping
or valves designed to control, distribute and monitor the flow. Several XTs may
be mounted directly on the manifold, or be placed as satellite trees. The mani-
fold has inhibitor injection lines and pipeline inspection gauge (PIG) launch, to
prevent hydrate formation.
The objective of the HIPPS is to protect the pipeline from the manifold to
the FPSO. They have their own control system called the HIPPS control module
(HCM). This device is similar to the SCM. Note that the HCM is independent of
the SCM. HIPPS shutdown is initiated automatically. The 2 HIPPS valves on the
manifold are closed if high pressure is experienced by the PT / TT between the
valves or downstream the valves. Another possibility is that one set of transmit-
ter controls one HIPPS and the other the last HIPPS valve.

6.3 LOPA applied on the case study


In this section the LOPA procedure based on the system is described, where the
process in Figure 4.1 is used as the approach. In Appendix C the spreadsheet
used in the study is presented.
The acceptance criteria are as in Table 4.1. The severity level is categorized
as CC which is 1 to 3 fatalities suffered. The screening criteria give us that the
impact event is within the scope of LOPA and no QRA initiated at this stage in
the analysis.

52
Experts were involved in the hazard identification study, and all members
involved in the LOPA as well as in previous studies fulfill requirements regarding
competency. The HAZOP preformed previously to the LOPA is assumed well
documented and sufficient, and the data adjusted to fit with the LOPA analysis.

Initiating causes
Fluid slug congestion, choke control error due to human error, and choke col-
lapse are the initiating causes identified. Slug congestion is accumulation of
fluid / hydrates / scale leading to a blockage and pressure build-up upstream
the blockage point. When this substance yields, the fluid accelerates and creates
overpressure in the separator. Choke collapse is most likely a hardware valve
failure, e.g. fatigue. Choke control error is erroneous operation of the choke
control where the operator make the wrong response or fails to act at all. All
these initiating causes lead to potential overpressure of the separator. The ini-
tiating cause frequencies are found from tables, and the chosen values showed
in Table 6.1 The frequency of slug congestion differs from field to field, and de-

Table 6.1: Initiating cause frequencies


Initiating cause Data source Frequency
Fluid slug congestion Expert judgment / Ormen 5 times per year
Lange
Choke control, human error BP/CCPS 1·10−1 / per oppor-
tunity to act
Choke collapse / error OREDA 11.3 per 106 hours

pends on the composition of the fluid and the field construction. In the Ormen
Lange project 5 demands was identified by expert judgment, which is assumed
applicable. The human error (choke control) is assumed to be a routine task. In
order to estimate the frequency the value in the table has to be multiplied with
the number of opportunities / demands per year. The choke task is assumed to
be executed approximately 20 times per year giving a resulting frequency of 2
times per year for this initiating cause. The OREDA estimate is given in hours,
and assuming 8760 hours per year gives a frequency of 9.9 · 10−2 per year.

IPLs - general considerations


In the next section it is described and discussed what protections layers that
exist, and which of these that can be credited as IPLs.
The PL criteria are presented, and the definition of IPL clarified, in Section
3.2. The risk reduction and availability requirements are easy to assess. The four
characteristics, especially the independence characteristic, are more difficult to
prove. The key issue is to clarify what lies in the term independent. Can the
IPLs share components, or do they have to be totally redundant? CCPS (2001)

53
state that the independence requirement claims that the IPL must be indepen-
dent of the occurrence, consequence of the initiating event, and the failure of
any component of an IPL already credited. Two approaches (A and B) are sug-
gested, where B allows IPLs to physically share components and A restrains this
configuration. But it is assumed that the logic solver will not be the source of
failure, which imply detectors or final element to fail more frequently. If two
IPLs share the same sensor(s) or final element(s) neither of the approaches jus-
tify more than one IPL given credit. Note that approach A eliminates a larger
extent of CCFs.

IPLs in the system


The system has the following protection layers:

• Topside PSD (closing PSDV)

• PSV (mechanical relief device)

• HIPPS

• Subsea PSD (closing PMV and / or: PWV and XOV)

• BPCSsubsea (PCV)

• BPCStopside (CV)

BPCS is referred to as process control system in the introduction to system para-


graph. When and if these can be credited as IPLs must be evaluated. The BPCSsubsea
which has the PCV as the actuating item, is not independent when the initiating
cause is collapse of this valve. The PCV also share the same PT and TT as the
subsea PSD. These are not independent and both cannot be credited as IPL. A
question that arises is which system to credit. The most rational is to credit the
PSD, but should be evaluated for the different initiating causes.
The PSV is credited as an IPL. It is independent as it shares no other com-
ponents with any other protection layers. It is also independent of the initiating
causes, and of high reliability.
The requirement and credited risk reduction of the PSD functions may vary.
The equipment vendor (e.g. the valve manufacturer) must document the per-
formance of the valves in terms of SIL. This is documented in the safety anal-
ysis report (SAR), which is included in an overall document called safety anal-
ysis specification (SRS). The contractor (e.g. Aker E&T and Aker Subsea) often
present requirements to the equipment vendor which must be verified. In order
to save time on documentation the equipment vendor certify the equipment.
The equipment then becomes SIL-certified. Usually the PSD functions are given
credit within the interval of SIL 1, which is a PFD between 0.1 and 0.01. The con-
servative choice which is often used, is crediting the PSDs as SIL 1. Another
option is to use OLF 070 which requires minimum SIL 2 for PSD functions. It is

54
in the concerning case chosen to credit both PSD topside and subsea as a SIL 1
risk reduction.

Table 6.2: IPL PFDs


IPL Data source PFD
PSV CCPS table 1 · 10−2
Topside PSD (PSDV) BP / Aker Solutions 0.1 (SIL 1)
Subsea PSD BP / Aker Solutions 0.1 (SIL 1)
BPCSsubsea (PCV) CCPS table / BP 1 · 10−1
BPCStopside (CV) CCPS table / BP 1 · 10−1
HIPPS BP / Aker Solutions 5 · 10−4 (SIL 3)

The HIPPS and the PSD subsea do have different PTs and actuating items,
but they do share the same HPU / SCU. The XT and HIPPS valves will go to safe
state if the HPU / SCU fails to provide hydraulic pressure. The only way this
unit may cause an error is if the logic solver in the SCU fails in such way that the
system does not initiate shutdown when a shutdown is needed. The issue that
arise is how strict the independence requirement should be, and which of the
two approaches presented in the previous paragraph to use. Even if they share
logic solver both lead to risk reduction. With this basis approach B, which is
described in the previous section, seems fair to use.
It is important to emphasize that a PL can be an IPL for one initiating cause
- impact event pair, and not for another. The IPL PFDs are from different data
sources, and Table 6.2 show the selected values.

Occupancy factor and ignition probability


Occupancy and ignition probability is included in the IPL columns in the LOPA
worksheet. But they are not per definition considered as IPLs. It is assumed that
3 operators do rounds, and that the area is occupied 30 % of the time, leading
to an occupancy factor of 0.3. The ignition probability depends on the pressure
and the type of fluid. High pressure applied to a flammable fluid have a higher
ignition probability than a low inflammable fluid working under low pressure.
A common classification is: 1 if the fluid is self igniting, 0.3 if the fluid is easy
ignitable and 0.1 if it is a stable fluid. The fluid is a composition of oil, gas and
water. This is assumed to be easy ignitable, but not 100% self ignitable leading
to a chosen ignition probability of 0.5.

Analogy to Section 3.2: Relation between terms


Figure 6.3 is related to the figure in Section 3.2 and shows the initiating causes,
process deviation, impact event and PLs based on the case description.

55
Figure 6.2: Relation between initiating causes, impact event, process deviation
and PLs

Initiating cause - impact event pair 1: Choke control human error -


overpressure
The operator controlling the PCV has already failed and the PCV can not be cred-
ited. Another question is whether the BPCS topside can be credited if the oper-
ator and BPCSsubsea fails. The BPCS topside have sensors and actuating items
topside, which is far from the PCV located subsea. It is assumed that even if the
operator is involved in the failure of the PCV, the topside BPCS will still function.
The credited IPLs are:

• Topside PSD (PSDV)

• PSV (mechanical relief device)

• HIPPS

• Subsea PSD

• BPCStopside (CV)

The formula for calculating the intermediate event likelihood becomes:


Initiating cause frequency · PFDCV · PFDHIPPS · PFDPSDV · PFDsubseaPSD · PFDPSV ·
occupancy · ign. prob. = 2 · 10−1 · 5 · 10−4 · 0.1 · 0.1 · 1 · 10−2 · 0.3 · 0.5 = 1.5 · 10−9

Initiating cause - impact event pair 2: PCV collapse - overpressure


When the PCV fails, does this influence the performance of the subsea PSD? If
the PCV fails due to a SCU error it is expected that the subsea PSD will not func-
tion, as they have this component in common. But it is more likely that the PCV
fails due to a valve hardware failure. Another issue is the response time. It is

56
not certain that the PSD is able to prevent a pressure build-up due to the short
distance between the XT valves and the choke module. There are several ways
to interpret these issues. It is chosen to not give credit to the susbea PSD due to
the response time. The following IPLs given credit are:

• Topside PSD (PSDV)

• PSV (mechanical relief device)

• HIPPS

• BPCStopside (CV)

The formula for calculating the intermediate event likelihood becomes:


Initiating cause frequency·PFDCV ·PFDHIPPS ·PFDPSDV ·PFDPSV ·occupancy·ign. prob. =
9.9 · 10−2 · 10−1 · 5 · 10−4 · 0.1 · 10−2 · 0.3 · 0.5 = 7.42 · 10−10

Initiating cause - impact event pair 3: Slug congestion - overpressure


What PLs to give credit depends on where the slug congestion occurs. The PLs
having actuating items upstream the blockage point have no function. If the
blockage point is upstream the PSDV and downstream the riserbase the HIPPS,
PCV and PSD will not be able to eliminate the hazard. The fluid column be-
tween the blockage point and the valves will still provide pressure even if the
valves close. The only way to eliminate pressure would be to have some sort of
a bypass line in the system. Another issue is whether the other protection layers
downstream have time to act. In the situation described the BPCStopside (CV)
does probably not have time to act. The blockage point considered is upstream
the PSDV and downstream the riser base, and the only IPLs given credit are:

• Topside PSD (PSDV)

• PSV (mechanical relief device)

The formula for calculating the intermediate event likelihood becomes: Initiating cause frequency·
PFDPSDV · PFDPSV · occupancy · ign. prob. = 5 · 10−1 · 0.1 · 10−2 · 0.3 · 0.5 = 7.5 · 10−4

Sum up intermediate event likelihood for all pairs


The intermediate event likelihood for the three initiating cause - impact event
pairs is summed up. The total intermediate event likelihood is 7.5 · 10−4 . The
third initiating cause - impact event pair is the most contributing to the total in-
termediate event likelihood, and the frequencies associated with the two others
have little effect.

57
Target risk measurement, SIL determination and mitigated event like-
lihood
Compared to the TMEL the first two pairs are within the acceptable region be-
cause 1.5 · 10−9 and 7.42 · 10−10 is less than 3 · 10−5 . The total intermediate event
likelihood is greater than the total TMEL for the entire scenario leading to the
end-consequence (7.5 · 10−4 > 3 · 10−5 ). This implies that a SIL must be deter-
mined. By using Equation 4.3 the necessary risk reduction corresponding to the
needed SIL is calculated:

3 · 10−5
Necessary risk reduction = = 4 · 10−2
7.5 · 10−4
The question is now what SIL to set as the requirement. The necessary risk re-
duction is between 10−2 and 10−1 , and a SIL 2 is applicable. A conservative ap-
proach is chosen and a SIL 2 is set as the requirement.
The next question is what PFD value a SIL 2 requirement constitutes, i.e what
requirement to pass on to the SIS vendor. If the SIS vendor provides a system
fulfilling SIL 2, but which only gives a risk reduction of 5 · 10−2 the system is not
safe enough. To solve this potential issue an additional PFD requirement is set
to 1·10−2 . The final requirement is SIL 2, where the new safety system must have
a specific P F D ≤ 1 · 10−2 .
The chosen PFD requirement is implemented in worksheet, and the miti-
gated event likelihood is calculated. All values are within requirements, and the
analysis is finalized.

6.4 Comments to the result


The LOPA identified that a SIS performing a new SIF had to be introduced, and
assigned a SIL to this function. It might be that improvements could have been
done to the existing system, e.g. improving the risk reduction provided by the
existing IPLs. Another approach could have been to make some of the PLs not
credited as IPLs more independent. Introducing a new SIF could have been
avoided. The PSDs were credited as SIL 1 risk reduction. If they had been cred-
ited as SIL 2, the final determined SIL of the new SIF would then have been SIL
1.
It is discussable whether the topside BPCS should have been included at all.
It is not included on the separator in the Skarv project. The contribution this
makes on the final LOPA result is neglectable because the specific intermediate
event likelihood is well below the TMEL where the topside BPCS is credited as
an IPL.

58
6.5 Implications during the case
In this section implications during the case is discussed. This throw light on the
shortfalls of the preferred approach presented in Chapter 4 illustrated in Figure
4.1, and on LOPA in general.
Most of the phases in Figure 4.1 were easy to apply, but there were some im-
plications encountered during the analysis. The initiating cause frequency of the
slug congestion was not possible to find from the tables. Expert judgment was
necessary which emphasize the need for database and exchange of experience
as discussed in Chapter 5.5.
Whether the IPLs were independent or not was a considerable issue dur-
ing the case. This touched deep into the valve control system, and an extensive
system understanding seems necessary. The independence requirement is also
hard to interpret, because it is difficult to know how strict these requirement
should be followed. Exchange of experience and more guidelines are needed in
order to make this part of the analysis easier.
What value to use as ignition probability was not intuitive, and a classifi-
cation and guideline in the approach in Chapter 4 should have been included.
LOPA requires knowledge, and the team composition is important in getting a
satisfying result. When the necessary risk reduction was calculated some ef-
fort was required to evaluate the result. This could have led to problems and
knowledge of the process, how LOPA works and laws of probability, are essential
aspects.
During the analysis it was made an error when converting failure data from
OREDA. This was corrected, but this incident underlines the importance of qual-
ity assurance and transformation process in an eventual software tool as men-
tioned in Chapter 5.5. The overall impression is that the preferred approach in
Chapter 4 is clear and applicable. Linking this together with a software tool as
described in Chapter 5.5, makes the LOPA procedure more efficient as well as
providing useful features.
Process experience, understanding of LOPA and knowledge of general relia-
bility and probability is success factors in making LOPA efficient and robust.

59
Chapter 7

Conclusions and
recommendations for further
work

Both qualitative and quantitative SIL determination methods and tools may be
applied during phase four in the IEC safety life cycle (Figure 1.1). The quantita-
tive method in IEC 61508, the OLF 070 guideline, the risk matrix, the safety layer
matrix, the risk graph and the calibrated risk graph are SIL determination meth-
ods that have been described in addition to LOPA. In qualitative methods the
parameters used as decision basis are subjective and estimated by expert judg-
ment. Quantitative methods describe the risk by calculations, and a numerical
target value is compared with the result. Which method to apply rely primarily
on whether the necessary risk reduction is specified in a numerical manner or
qualitative manner. The scope and extent of the analysis would also be an in-
fluencing factor. Even if the assignment method is qualitative the SIL is always
quantified by a numerical number.
The main objective of this thesis has been to gain knowledge of SIL deter-
mination tools, with LOPA as the the main focus. This is accomplished, and the
sub-objectives of the report is listed below, and the coverage and findings con-
cerning each objective discussed.

• Literature survey and different approaches to LOPA found in the literature.

A literature survey has been carried out and different methodologies and
approaches in literature has been presented and discussed. Especially, the IEC
61511 approach, Aker E&T and the approach in CCPS (2001) have been covered.
The guideline in BP (2006) seems reasonable and should have been covered to a
greater extent. Most methodologies and approaches have the similar basis, but
use different terms and have different sequence. Another distinction is how the
SIL is incorporated and evaluated. The process design can be evaluated ”as is”,
or with a new protection layer (e.g. SIF) implemented in the evaluation. Some

60
authors also use screening tools, i.e. risk graph, prior to, or embedded in the
LOPA-process.
Compared to the approaches discussed in Section 3.5, the Aker E&T LOPA
approach is an overall methodology, not taking the proposed SIF implicit into
account. Often the customer methodology also (e.g. Statoil or BP) found basis
for the analysis. ISO 10418 (2003) helps the design team to implement safety
functions in the P&IDs for the concerning system, and after all hazard identifi-
cation is finished the LOPA is initiated. The further approach is similar to the
approach presented in IEC 61511 (2003).

• Recommended LOPA approach

A stepwise preferred (recommended) approach has been developed and each


step described. The approach is clear, and all basic concepts clarified. In the
case study in Chapter 6 the need for more guidelines on how to credit IPLs has
been identified, and this part needs to be improved. The preferred approach
is an overall approach considering the planned / existing system without the
proposed SIF. Several screening tools exists, but it is chosen to screen by con-
sequence and SIL only. Conducting a risk graph-analysis for then to initiate a
LOPA cause extra work and increased engineering cost. The approach is shown
in Figure 4.1.

• Interfaces between LOPA and other risk analysis methods.

Interfaces between LOPA and HAZOP has been identified, but other risk
analysis methods have not been covered. Information in columns as conse-
quence and possible causes in the HAZOP worksheet can be directly transferred
to the LOPA worksheet. Information in the other columns may require transfor-
mation. This includes IPL PFD data and initiating cause frequency.
The thoughts behind a software tool transferring, facilitating, and adjusting
data have been presented. This includes a program specification and a sim-
ple illustration of a thought software program. The illustrated software program
takes basis in automatic data transformation from HAZOP, IPL PFD and initiat-
ing cause frequency databases, and a risk matrix including the acceptance crite-
ria. Linking all these aspects with a LOPA worksheet give the outline of the pro-
gram. The illustrated program showed in Annex B seems reasonable, but should
be evaluated more in detail. Expert judgment make an extensive amount of the
analysis, and a program that ”learns by doing” is beneficial. An example is a
program that has a database with previous analyzes, which provides previous
information when a new analysis is performed, e.g. possible initiating causes of
a specific type of valve.

• Discuss pros and cons related to LOPA

Advantages and disadvantages of LOPA and especially the limitations of LOPA,


have not been covered.

61
• Discussion of the IPL concept and the applicability of LOPA in cases where
the independence is violated

IPL has been defined, exemplified, and discussed. In the case study the IPL
concept has been applied to a practical system. CCFs have not been covered to
a great extent, which should have been the case.
IPL is defined as: Protection layer that is capable of preventing the process
deviation from proceeding to the end-consequence regardless of other protec-
tion layers associated with the same impact event - initiating cause pair, and of
the initiating event. It must lead to a risk reduction factor of at least 10, and fulfill
the specificity, independence, dependability and audibility criteria. The defini-
tion is clear, but it is still uncertain how to apply the concept of IPL in practice.

• Compare the applicability of LOPA in determining SIL, and compare LOPA


with alternative approaches (incl. risk graphs). If possible, this evaluation
should be rooted in a practical case study.

The preferred approach, based on the literature study, has been applied to
a combined system based on real systems by Aker Subsea and Aker E&T. The
preferred approach was easy to use, but as mentioned the IPL concept was diffi-
cult to apply. Where to draw the line where a component is independent or not
was the key issue throughout the case study. The case concluded that process
understanding and knowledge of basic reliability concepts are important.
This thesis may give some readers a more clear understanding of LOPA. The
sections explaining and clarifying terms and the IPL discussion in the case study,
may be a contribution to the LOPA discussion.
Still, many of the issues need to be clarified, and further work is recom-
mended. Specific recommendations for further work are:

• More in depth analyzes of CCFs and IPLs.

– What is the effect of not considering CCFs?

– Guideline describing concept of IPL for different systems, with ex-


tended definition of IPL.

• HAZOP integration software tool prototype that includes advanced func-


tions which incorporates expert judgment and previous analyzes.

• Combined framework of LOPA and HAZOP including a common termi-


nology and worksheet.

• Extend the development of the preferred approach.

– Include risk acceptance criteria development.


– Comparison with the approach in BP (2006).

62
Bibliography

ACM Facility safety (2004). HAZOP / SIL analysis item and cost compari-
son - Traditional way vs. integrated SILCore approach. Advertorial, Safety
Users Group. Retrieved on 03.04.08 from internet address: http://www.
safetyusersgroup.com/documents/AD040001/EN/AD040001.pdf.
ACM Facility Safety (2006). SIL Determination Techniques Report. "White Paper".
Retrieved on 30.02.08 from internet address: http://www.iceweb.com.au/
sis/ACMWhite-PaperSILDeterminationTechniquesReportA4.pdf.
Baybutt, P. (2007). An improved Risk Graph Approach for Determination of
Safety Integrity Levels (SILs). Process Safety Progress, 26:66–76.

Bingham, K. and Goteti, P. (2004). ISA (The Instrumentation, Systems, and Au-
tomation Society) 2004. In Integrating HAZOP and SIL / LOPA analysis: Best
practice recommendations.

BP (2006). Guidance on Practices for Layer of Protection Analysis (LOPA). British


Petroleum procedure: Engineering Technical Practice (ETP) GP 48-03, 1st edi-
tion.

CCPS (2001). Layer of protection analysis - simplified process risk assessment.


American Institute of Chemical Engineers (AIChE), Centre for Chemical Pro-
cess Safety (CCPS). 3 Park Avenue, New York.

Dowell, A. (1998). Layer of protection analysis for determining safety integrity


level. ISA Transactions, 37:155–165.

Dowell, A. and Williams, T. (2005). Layer of Protection Analysis: Generating Sce-


narios Automatically from HAZOP Data. Process Safety Progress, 24:38–44.

Ellis, G. and Wharton, M. (2006). Symposium Series No. 151, IChemE. In Prac-
tical experience in determining safety integrity levels for safety instrumented
systems.

Gowland, R. (2006). The accidental risk assessment methodology for industries


(ARAMIS) / layer of protection analysis (LOPA) methodology: A step forward
towards convergent practices in risk assessment? Journal of Hazardous Mate-
rials, 130:307–310.

63
Harsem Lund, K. (2007). Alternative måter for SIL fastsettelse - en sammen-
ligning (LOPA, Risk graf, OLF 070). In PDS forum, Trondheim. Scandpower,
Kjeller.

IEC 60300-3-9 (1995). Dependability management- Part 3: application guide -


section 9: Risk analysis of technological systems. International Electrotechni-
cal Commission, Geneva.

IEC 61508 (2003). Functional safety of electrical/electronic/programmable elec-


tronic safety-related systems. International Electrotechnical Commission,
Geneva.

IEC 61511 (1998-2003). Functional safety - safety instrumented systems for the
process industry sector. International Electrotechnical Commission, Geneva.

ISO 10418 (2003). Petroleum and natural gas industries - offshore installations -
Basic surface process safety systems. International Organization for Standard-
ization, Geneva.

Marszal, E. and Scharpf, E. (2002). Safety Integrity Level Selection - Systematic


Methods Including Layer of Protection Analysis. The Instrumentation, Systems
and Society (ISA). Research Triangle Park, NC.

Nordhagen, L. (2007). Bruk av LOPA ved fastsettelse av IL krav, Aker Kværner


Engineering &Technology. In PDS forum, Trondheim.

NORSOK Z-013 (2001). Risk and emergency preparedness analysis. Norwegian


Technology Centre, Oslo.

OLF 070 (2004). Application of IEC 61508 and IEC 61511 in the norwegian
petroleum industry. OLF.

Rausand, M. (2004). Reliability of safety systems (Slides). Retrieved


on 28.02.08 from internet address: http://frigg.ivt.ntnu.no/ross/
slides/chapt10.pdf.
Rausand, M. (2005). HAZOP - Hazard and Operability Study (Slides). Re-
trieved on 28.02.08 from internet address: http://frigg.ivt.ntnu.no/
ross/slides/hazop.pdf.
Rausand, M. and Høyland, A. (2004). System Reliability Theory. Models, Statisti-
cal Methods, and Applications. 2nd edition John Wiley & Sons. Hoboken, NJ.

Schönbeck, M. (2007). Introduction to reliability of safety systems, ROSS


(NTNU) report 200702, NTNU, Trondheim. Technical report, NTNU, ROSS.

Sklet, S. (2006). 2006:3, Safety Barriers on Oil and Gas Platforms. PhD thesis,
NTNU.

64
Summers, A. (2003). Introduction to layers of protection analysis. Journal of
Hazardous Materials, 104:163–168.

The Dow chemical company (2002). Introducing dow application of layer of pro-
tection analysis. In Introducing Dow Application of Layer of Protection Analy-
sis - LOPA.

65
Appendix A

Basic concepts

Impact event The first sign of harm to people, environment or


assets
Independent protection layer Protection layer that is capable of preventing a
process deviation from proceeding to the end-
consequence, regardless of other protection layers
associated with the same impact event - initiating
cause pair, and of the initiating event
Initiating cause Direct reasons why the process deviation occur,
not the most basic underlying root-causes
Intermediate event likelihood Intermediate event is the occurrence of the end-
consequence with the existing / planned protec-
tion layers in place, but without the SIF under con-
sideration. The intermediate event likelihood is
the frequency per year of the occurrence the this
event
Mitigated event likelihood Mitigated event is the occurrence of the end-
consequence with all protection layers in place, in-
cluding the proposed SIF. The mitigated event like-
lihood is the frequency per year of the occurrence
the this event
Process deviation The first significant deviation from a normal situa-
tion that may lead to unwanted consequences
Protection layer Device, system or action that is capable of prevent-
ing a process deviation from proceeding to the end
consequence
Scenario The development from a process deviation to an
impact event, including the causes leading to the
process deviation

66
Appendix B

Software schematic

Legend:
Black circles - User input
Blue Circles - Data cell
Red circles - Calculation cell (output cell)
Blue lines - Data path (blue or black circle to red circle)
Pale yellow box - Button
Yellow box - Clicked button

67
Figure B.1: Step 1

68
Figure B.2: Step 2

69
Figure B.3: Step 3

70
Figure B.4: Step 4

71
Figure B.5: Step 5

72
Appendix C

Case study: Worksheet

73
Figure C.1: LOPA worksheet: Case study

74

Вам также может понравиться