Вы находитесь на странице: 1из 108

Installation, Operations & Maintenance Manual

Benning Power Electronics


1220 Presidential Drive Suite 100
Richardson, TX 75081 USA
www.benning.us
800.910.3601
Tebevert III 25kVA
This manual contains important
-48VDC Inverter System safety instructions that should be
followed during installation and
028-0009-000 Rev. F
maintenance of the Power
System.
TEBEVERT III INVERTER SYSTEM

1 TABLE OF CONTENTS
1 TABLE OF CONTENTS...................................................................................................................... 2

2 SAFETY NOTES AND MARKINGS ................................................................................................... 3

3 GENERAL ........................................................................................................................................... 5

4 INVERTER SYSTEM OVERVIEW ...................................................................................................... 6

4.1 PSJ TYPE EQUIPMENT CABINET .................................................................................................6


4.2 INVERTER MODULE SHELF ....................................................................................................... 10
4.3 STATIC BYPASS SWITCH MODULE SHELF ................................................................................. 11
4.4 MAINTENANCE BYPASS SWITCH (MBS)..................................................................................... 12
4.5 INVERTER MODULES ............................................................................................................... 13
4.5.1 INVERTER MODULE FRONT PANEL .................................................................................. 16
4.5.2 INVERTER MODULE REAR PANEL .................................................................................... 19
4.6 STATIC BYPASS SWITCH (SBS) MODULE .................................................................................. 19
4.6.1 SBS MODULE FRONT PANEL ............................................................................................ 22
4.6.2 SBS MODULE REAR PANEL .............................................................................................. 25
4.7 AC DISTRIBUTION ................................................................................................................... 26
4.7.1 NA STYLE SNAP-IN BREAKER PANEL ................................................................................ 26
4.7.2 DIN RAIL MOUNT AC BREAKERS ..................................................................................... 27
4.8 INPUT & OUTPUT TRANSFORMERS ........................................................................................... 28
4.9 TECHNICAL DATA .................................................................................................................... 29

5 INSTALLATION & SITE ENGINEERING DETAIL ........................................................................... 30

5.1 PREPARATION FOR INSTALLATION .......................................................................................... 30


5.1.1 Unpacking the TEBEVERT III INVERTER SYSTEM ............................................................. 31
5.1.2 Inspecting the Equipment ............................................................................................... 31
5.1.3 Carrier Claims ................................................................................................................. 32
5.1.4 CHECKING PACKAGING CONTENTS ................................................................................. 32
5.1.5 SAFETY .......................................................................................................................... 32
5.1.6 INSTALLATION TOOLS .................................................................................................... 32
5.1.7 WIRING GUIDELINES...................................................................................................... 32
5.1.8 PACKAGING ................................................................................................................... 32
5.2 CABINET INSTALLATION .......................................................................................................... 33

02.06.2012 028-0009-000 Rev F


TEBEVERT III INVERTER SYSTEM

5.2.1 RECOMMENDED MINIMUM CABINET CLEARANCES ........................................................... 33


5.2.2 WEIGHTS AND DIMENSIONS........................................................................................... 33
5.2.3 CABINET FOOTPRINT ..................................................................................................... 34
5.3 CABINET WIRING .................................................................................................................... 36
5.3.1 DC CABLE REQUIREMENTS ............................................................................................. 37
5.3.2 AC CABLE REQUIREMENTS ............................................................................................. 40
5.3.3 ALARM OUTPUT CABLE REQUIREMENTS .......................................................................... 43
5.3.4 CABINET FRAME GROUNDING CABLE REQUIREMENTS ..................................................... 45
5.3.5 REMOTE MONITORING ................................................................................................... 45
5.3.6 TORQUE TABLES FOR ALL TERMINATIONS ...................................................................... 46

6 SYSTEM START-UP ........................................................................................................................ 47

6.1 MODULE INSTALLATION .......................................................................................................... 47


6.1.1 INVERTER MODULE SETTINGS ........................................................................................ 48
6.1.2 INSTALLATION OF INVERTER MODULES .......................................................................... 49
6.1.3 STATIC BYPASS SWITCH MODULE SETTINGS .................................................................. 50
6.1.4 INSTALLATION OF SBS MODULE ..................................................................................... 52
6.2 SWITCHING ON THE INVERTER SYSTEM .................................................................................. 53
6.2.1 PROCEDURE IF THE SYSTEM IS SET TO INVERTER PRIORITY .......................................... 53
6.2.2 PROCEDURE IF THE SYSTEM IS SET TO MAINS PRIORITY ................................................ 54

7 SYSTEM OPERATION ..................................................................................................................... 56

7.1 TOTAL SYSTEM........................................................................................................................ 56


7.2 INVERTER ............................................................................................................................... 57
7.2.1 MONITORING OF THE DC INPUT VOLTAGE ...................................................................... 57
7.2.2 MONITORING THE OUTPUT VOLTAGE ............................................................................. 58
7.2.3 MONITORING THE TEMPERATURE .................................................................................. 58
7.2.4 OVERLOAD BEHAVIOR .................................................................................................... 58
7.2.5 SHORT-CIRCUIT BEHAVIOR ............................................................................................ 59
7.3 STATIC BYPASS SWITCH MODULE (SBS) .................................................................................. 59
7.4 DISPLAY PANEL AND MCU ........................................................................................................ 62
7.4.1 INTRODUCTION TO THE DISPLAY PANEL ........................................................................ 62
7.4.2 STANDARD DISPLAY AND OPERATING ELEMENTS............................................................ 62
7.4.3 HELP FUNCTION ............................................................................................................. 64

02.06.2012 028-0009-000 Rev F


TEBEVERT III INVERTER SYSTEM

7.4.4 SELECT MENU ITEM ....................................................................................................... 64


7.4.5 MAIN MENU ................................................................................................................... 64
7.4.6 ERROR memory .............................................................................................................. 65
7.4.7 ERROR LEVEL AND CLASS ............................................................................................... 66
7.4.8 ERROR LOG ................................................................................................................... 67
7.4.9 THE INDIVIDUAL MENUS ................................................................................................ 68
7.5 ALARMS & INDICATORS ........................................................................................................... 78
7.6 REMOTE MONITORING ............................................................................................................ 79

8 MAINTENANCE ................................................................................................................................ 80

8.1 USE OF THE MANUAL BYPASS SWITCH (MBS) ........................................................................... 80


8.2 EXCHANGE OF MODULES ......................................................................................................... 82
8.3 INCREASING SYSTEM CAPACITY .............................................................................................. 84
8.4 SERVICE SOFTWARE ................................................................................................................ 84
8.5 SERVICE SUPPORT .................................................................................................................. 85

9 SPARE PARTS ................................................................................................................................. 85

APPENDIX A – PART NUMBERS ............................................................................................................. 86

APPENDIX B - PERFORMANCE TESTING ............................................................................................. 89

B.1 PRELIMINARIES TO PERFORMANCE TEST ................................................................................. 89


B.2 TEST EQUIPMENT REQUIRED .................................................................................................. 89
B.3 TEST OF THE INVERTER MODULES .......................................................................................... 89
B.3.1 INVERTER TEST ACTIVITIES ........................................................................................... 90
B.4 TEST OF THE SBS MODULE ...................................................................................................... 91
B.4.1 SBS TEST ACTIVITIES .................................................................................................... 92
B.5 FINAL STEPS ........................................................................................................................... 93

APPENDIX C - DRAWINGS ...................................................................................................................... 94

C.1 902-0106-306 sh 1 of 4 input output schematic ......................................................................... 94


C.2 902-0106-306 sh 2 of 4 sbs schematic ...................................................................................... 95
C.3 902-0106-306 sh 3 of 4 ac input & output options ..................................................................... 96
C.4 902-0106-306 sh 4 of 4 alarm and mcu wiring .......................................................................... 97

NOTES ........................................................................................................................................................ 98

02.06.2012 028-0009-000 Rev F


TEBEVERT III INVERTER SYSTEM

LIST OF FIGURES

Figure 1 Typical Design of Top Feed Cabinet without Modules ...................................... 7


Figure 2 Typical Cabinet with Inverter & Static Bypass Switch Modules Installed ........... 8
Figure 3 Typical System Input/Output Terminals with an Individual DC Feed/Module .... 9
Figure 4 Typical Remote Monitoring Adaptor Installation (SNMP) ................................... 9
Figure 5 Inverter Shelf Connector Locations ................................................................. 10
Figure 6 SBS Shelf Connector Locations ...................................................................... 11
Figure 7 Manual Maintenance Bypass Switch Q10 ....................................................... 13
Figure 8 Outline Drawing of the Modular Inverter unit ................................................... 15
Figure 9 Front View of the Inverter Module ................................................................... 16
Figure 10 Inverter Module Front Panel Controls & Indicators........................................ 17
Figure 11 Rear View of the Inverter Module .................................................................. 19
Figure 12 Outline Drawing of the Static Bypass Switch (SBS) Module ......................... 21
Figure 13 Front View of the Static Bypass Switch Module ............................................ 22
Figure 14 Partial View of Static Switch Display ............................................................. 23
Figure 15 SBS Single Line Mimic Diagram with LED Indicators .................................... 23
Figure 16 Rear View of the Static Bypass Switch Module ............................................. 25
Figure 17 Snap-in Style External Rack-mount AC Distribution Panel............................ 26
Figure 18 DIN-rail Style Internal AC Distribution ........................................................... 27
Figure 19 Optional Input & Output Transformers .......................................................... 28
Figure 20 TIP N TELL™ ................................................................................................ 30
Figure 21 SHOCKWATCH ............................................................................................ 30
Figure 22 Cabinet Mounting Hole Pattern ..................................................................... 34
Figure 23 Typical Non-Earthquake Zone Concrete Anchor ........................................... 35
Figure 24 Typical Earthquake Zone Concrete Anchor................................................... 35
Figure 25 Insulated DC Cable Support Detail ............................................................... 37
Figure 26 Stud Arrangement for Individual DC Input Feed / Module ............................. 38
Figure 27 Stud Arrangement for Bulk DC Input Feed .................................................... 39
Figure 28 AC Terminal Blocks for 208VAC In & 120/240VAC Out System ................... 40

02.06.2012 028-0009-000 Rev F


TEBEVERT III INVERTER SYSTEM

Figure 29 MCU2000 Alarm Terminal Block “X1” ........................................................... 43


Figure 30 Relay Box Alarm Terminal Blocks “X4” & “X5” .............................................. 44
Figure 31 Frame Ground Studs, Top of Bay ................................................................. 45
Figure 32 Remote Monitoring Network Connection ....................................................... 45
Figure 33 Inverter Module Rear Side Output Circuit Breaker ........................................ 49
Figure 34 Installation Positions of Locking Mechanism & Operating Element ............... 52
Figure 35 LED states of the SBS (Normal State Inverter Priority) ................................. 54
Figure 36 LED States of the Inverter (Normal State Inverter Priority)............................ 54
Figure 37 LED states of the SBS (Normal State Mains Priority) .................................... 55
Figure 38 LED States of the Inverter (Normal State Mains Priority) .............................. 56
Figure 39 Switching Thresholds for DC Over & Under voltage Monitoring .................... 57
Figure 40 Operator Panel .............................................................................................. 63
Figure 41 Main Menu Tree (password level in parenthesis) .......................................... 64
Figure 42 Error Log ....................................................................................................... 65
Figure 43 Control Menu Tree ........................................................................................ 68
Figure 44 Settings Menu Tree ....................................................................................... 69
Figure 45 Measuring Value Monitoring screen showing pale script .............................. 70
Figure 46 Measurement Values Menu Tree .................................................................. 71
Figure 47 Typical Actual Measurement screen ............................................................. 71
Figure 48 Example status screen .................................................................................. 72
Figure 49 Display Menu Tree ........................................................................................ 73
Figure 50 System setup Menu Tree .............................................................................. 75
Figure 51 MBS State: "Load on Bypass AC Input" ........................................................ 82
Figure 52 MBS State: "Load on Inverter Output" ........................................................... 82

02.06.2012 028-0009-000 Rev F


VERSION:
Revision Date Originator Approver
B 07.11.11 A.Waggott/J.Almond D. Almond
C 11.04.11 D. Anderson D. Almond
D 02.06.12 D. Bearrow D. Almond
E 03.11.12 D. Bearrow D. Almond
F 07.19.12 D. Bearrow D. Almond

Publication Document: Version 1.1


Copyright © 2011 Benning Power Electronics
Proprietary Information: This manual contains proprietary information which is protected
by copyright law. All rights are reserved. No part of this manual may be photocopied,
reproduced, or translated to another language without prior written consent of Benning
Power Electronics. Specifications in this manual are subject to change without notice.
TEBEVERT III INVERTER SYSTEM

PASSWORD:
Password Level 1: PW 1
Password Level 2: PW 2
Password Level 3: PW 3
Password Level 4: PW 4

NOTE: PUT A SPACE BETWEEN PW AND THE


NUMBER

02.06.2012 028-0009-000 Rev F

ii
PREFACE

Congratulations and thank you for purchasing a Benning TEBEVERT III Inverter
System!

We at Benning are committed to supporting the needs of our customers by supplying


the customer with the proper information and documentation needed to properly install
and operate the unit purchased.

Important:
It is imperative that all the information be observed.

This avoids:

 Danger during installation and operation.


 Danger to operating personnel.
 Downtime.
 Increases the reliability and lifespan of the system.

This manual explains all the necessary information to unpack, install, and operate the
Benning BLI Inverter System and related components. Refer questions outside the
scope of this manual to our Customer Service Department.

Customer Service:
We are committed to excellence in dependability and customer satisfaction. If you have
any questions or problems, please contact the Customer Service Department at:
1.800.910.3601 or 214.553.1444 for more information.

Please read all instructions before installing or operating the equipment and save these
manuals for future reference.

1
TEBEVERT III INVERTER SYSTEM

Switched-Mode Modular
TEBEVERT III
(HOT-PLUG-Version)
Inverter System

MODEL: 5.0kVA-25.0kVA
-48VDC Input, 120 VAC Modules

2
TEBEVERT III INVERTER SYSTEM

2 SAFETY NOTES AND MARKINGS


This operating manual contains important information for the installation,
operation, and maintenance of the inverter system. This manual must be retained
and observed at all times!
Explanation of the symbols used:

Indicates safety instructions which must be followed to avoid


danger to persons!

Indicates instructions which must be followed to avoid


material damage!

All specifications in these operating instructions must be


observed at all times!

Index of abbreviations:

A Amps
AC Alternating Current
Commercial AC Mains voltage providing an alternative AC
Bypass source to the connected load equipment. The Bypass
input is used by either the Maintenance Bypass Switch or
Input
the SBS for back-up support in the event of an inverter
system failure. This source could also be a Gen Set.
DC Direct Current
DVA Digital Volt-Ammeter
I Current
CB, MCB Circuit Breaker, Magnetic Circuit Breaker
GND, PE Ground, Protective Earth
L Line
Mains Commercial AC Input Power Source
Management Information Base - an ASCII text file used to
MIB
describe SNMP network elements as a list of data objects
MBS Maintenance Bypass Switch
N Neutral

3
TEBEVERT III INVERTER SYSTEM

SNMP Simple Network Management Protocol


SBS Static Bypass Switch
V Volts
W Watts

The inverter system is an electrical unit with dangerous


voltage and current levels. For this reason, the following
safety instructions must be observed.

1. Installation, operation, maintenance, and repair should be carried out in


strict accordance with the instructions in this document.
2. Ensure that only fully trained and qualified personnel have access to the
system. Only qualified and authorized personnel should open the units.
3. Even when the unit is completely switched off, some of its interior
components remain live as long as they are connected to the mains supply or the
battery.
4. Installed capacitors may be charged even when the system is
disconnected. These must be correctly discharged by a qualified technician
before the connections or terminals are touched.
5. When working at the unit, use properly insulated tools at all times which
are suitable for the levels of voltage concerned.
6. All persons working with the unit must be familiar with the first-aid
techniques to be adopted in cases of accidents involving electricity.
7. The regulations of the local power supply companies and all other
applicable safety regulations must be observed at all times.

4
TEBEVERT III INVERTER SYSTEM

3 GENERAL
The Benning TEBEVERT III inverter system is a rugged, high reliability, field
proven inverter system intended for protection of critical AC loads in telecom,
cable and other related communication applications. It can be scaled in 5 kVA
increments up to 25 kVA. Unlike conventional standalone inverters, these parallel
operating modules can also be scaled to operate with N+1 redundancy. This
ensures optimal availability for your critical load applications. In this mode of
operation, a failure of one inverter module will not affect the operation of your
critical load. Since all units are designed for “hot plug” replacement, a faulty
module can easily be unplugged and replaced without disturbing critical loads.
The heart of the system operates at 120VAC and consists of hot-swappable
inverter modules, and an electronic Static Bypass Switch (SBS) module. All
electrical connections to the modules are automatically disconnected or
connected when the modules are removed or inserted into the system cabinet.
This may take place during normal operation without interruption in power to the
connected load equipment. This design provides an uninterrupted supply of AC
current and satisfies the highest requirements with respect to the expansion of
the system, ease of maintenance and operating safety. The system is made
flexible to accommodate various AC input and output voltage requirements by
the addition of optional transformers which are housed in the base section of the
cabinet.
The TEBEVERT III is available for DC voltages of -48VDC. Each inverter module
is rated 5.0kVA/4.0kW power output. Parallel operation of maximum of five (5)
inverter modules provides a maximum system rating of 25.0kVA/20kW. The
output voltage is 120VAC or 120/240VAC and can be adjusted to 50Hz or 60Hz
according to the application.
Warning!
Several inverter systems may not be operated in parallel.
This may lead to the destruction of the inverter systems.

5
TEBEVERT III INVERTER SYSTEM

In addition to UL and CE listings, this product is certified to Bellcore NEBS Level


3 standards and its elements have been issued CLEI codes for use in Tier 1 U.S.
Telcos.

4 INVERTER SYSTEM OVERVIEW


The standard components of the Tebevert III Inverter System are:
(1) PSJ type equipment cabinet
(5) carriers (module slots) for the Inverter modules
(1– 5) Inverter modules
(1) carrier (module slot) for the static by-pass switch (SBS)
(1) Static Bypass Switch module (SBS)
(1) manual Maintenance By-pass Switch (MBS)
Optional AC Input and/or Output Transformers as required
Optional Operator Panel supported by MCU2000 Master Communications Unit
and associated internal electronic I/O modules on Benning SATBus. It is located
on a swing out door in front of the I/O Terminal Blocks in the upper section of the
cabinet.
Optional Remote Monitoring capability supported by Remote Monitoring Adaptor
with HTML web-page and SNMP format capabilities.
4.1 PSJ TYPE EQUIPMENT CABINET
The Benning TEBEVERT III system is built and supplied into a 19”
Benning Model PSJ free standing NEMA1 equivalent / IP-20
cabinet with 23.6”(600mm) X 23.6”(600mm) X 7‟0” (2134mm)
outside overall dimensions. Cabinets are available for New
Equipment Building Standards (NEBS) and non-NEBS applications.
Deeper 31.5” deep (800mm) cabinets are available for special
applications i.e. raised floor, etc. Consult with Benning at time of
order. Cabinets may be supplied rated for Seismic Zone 0 or
(NEBS) Zone 4. Specify at time of order. See typical arrangement
for top cable feed in Figures 1 and 2 below. Bottom cable feed
configurations are also available.

6
TEBEVERT III INVERTER SYSTEM

Input & Output Terminals &


Distribution

Static By-Pass Switch (SBS)


shelf

Inverter module shelf 5


(A5)

Inverter module shelf 4


(A4)

Inverter module shelf 3


(A3)

Inverter module shelf 2


(A2)

Inverter module shelf 1


(A1)

Input/Output Transformers

Figure 1 Typical Design of Top Feed Cabinet without Modules

7
TEBEVERT III INVERTER SYSTEM

0 Manual Bypass Switch (Q10)


1 2

SBS module (A6)

Inverter Module 5 ( A5 )

Inverter Module 4 ( A4 )

Inverter Module 3 ( A3 )

Inverter Module 2 ( A2 )

Inverter Module 1 ( A1 )

Figure 2 Typical Cabinet with Inverter & Static Bypass Switch Modules Installed

8
TEBEVERT III INVERTER SYSTEM

Figure 3 Typical System Input/Output Terminals with an Individual DC


Feed/Module

Figure 4 Typical Remote Monitoring Adaptor Installation (SNMP)

9
TEBEVERT III INVERTER SYSTEM

4.2 INVERTER MODULE SHELF


1 2

7 6 5
4 3
Figure 5 Inverter Shelf Connector Locations
1. Data line factory connected to the next inverter slot or the SBS slot
(X1)

2. Data connector for the inverter connection (X3)

3. Load connector for the AC connection of the inverter output (X6) 3


poles (2.5kVA) 5 poles (5.0kVA)

4. Data line factory connected to the next inverter slot (X2)

5. Female connector for the DC connection of the inverter (+)

6. Female connector for the DC connection of the inverter (-)

7. Female connector for the protective earth of the inverter ( )

*Each inverter carrier is equipped with two guide rails ensuring the
inverter is accurately positioned and reliable contact is made.

10
TEBEVERT III INVERTER SYSTEM

4.3 STATIC BYPASS SWITCH MODULE SHELF

1 23 4 5 6 7 12 11 9

15 14 10 8 13

Figure 6 SBS Shelf Connector Locations


1. Terminal block for the connection of the auxiliary DC supply to
the SBS ( Connector X26)

2. Terminal block for the voltage-free collective fault messaging


system of the inverter system (Connector X25)

3. Terminal block for the connection of the auxiliary contact


signifying the by-pass switch is in the “manual bypass inverter”
position (Connector X27)

4. Terminal block for the connection of the auxiliary contact


signifying the by-pass switch is in the "manual bypass mains"
position (Connector X28)

5. D-SUB connector for the optional connection of the inverter


system to the MCU remote monitoring system (Connector X23)

6. DIP switches, without function (Switch S1)

7. Data line to the inverter slot (Connector X10) (This is used if


there are inverters arranged above the SBS. Not standard!

8. Female connector for the neutral contact mains input (N)

9. Female connector for the protective earth (PE) of the SBS ( )

11
TEBEVERT III INVERTER SYSTEM

10. Female connector for the mains input (L1)

11. Female connector for the SBS output and inverter output (N)

12. Female connector for the SBS output (L)

13. Female connector for the inverter input (1L)

14. Male connector for the data bus (Connector X20; X21)

15. Male connector for the auxiliary DC supply and the voltage-free
fault messaging system (Connector X22)

The SBS carrier is equipped with two guide rails ensuring the SBS module
is accurately positioned and that reliable contact is made.

4.4 MAINTENANCE BYPASS SWITCH (MBS)


The manual Maintenance Bypass Switch is pictured below. It is located in
the upper section of the system cabinet. It is a three position switch which
functions to manually switch the system output between UPS operation,
Inverter Output only, and AC Mains only for maintenance purposes. The
MBS is mechanically connected to both the SBS slot and the SBS module
itself, when inserted. The locking mechanism prevents the SBS module
from being pulled out of the inverter system when it is in Position 0 for
normal UPS type operation. The MBS must be in either Position 1 or
Position 2 to permit removal or insertion of the SBS module.

Significance of the MBS switch positions:

Position 0: UPS operation

Position 1: Load on Bypass Input (Commercial AC)

Position 2: Load on Inverter Output

12
TEBEVERT III INVERTER SYSTEM

Figure 7 Manual Maintenance Bypass Switch Q10

4.5 INVERTER MODULES


The inverter modules convert the incoming nominal DC voltage of -
48VDC into AC voltage of 120VAC, 50 or 60Hz. Refer to Section
5.3 for specific wiring details.

Important Note!
The 120/240VAC configuration utilizes input/output
transformers to convert the input and output voltages from
the nominal 120VAC. Therefore the 120/240VAC system
settings are configured the same as the standard 120VAC
system.

The functions of all inverter modules in the system are identical.


The applied DC voltage reaches an intermediate circuit via an input
filter. The voltage in this intermediate circuit is increased to
approximately 200V. A high-frequency transformer separates the
voltage between the input and the output of the inverter. In the
bridge of the inverter, the high DC voltage of the intermediate circuit
is transformed into the inverter output voltage of 120 VAC and a
frequency of 50Hz or 60Hz (selectable).

In order to obtain a constant sinusoidal output voltage under all


operating conditions, a series of monitoring functions and controls
are necessary.

13
TEBEVERT III INVERTER SYSTEM

The inverter module contains no serviceable components that must


be accessible by the user during normal operation. Located on the
front panel there are various LED´s used for the operational status
and fault diagnosis.

Warning!
The removal of the front panel, the alteration of switching
thresholds and the changing of the control fuse may only
be carried out by qualified personnel.

Shown below is the Outline Drawing of the inverter module. All


terminals and operating elements are located on the front or rear of
the inverter module.

14
TEBEVERT III INVERTER SYSTEM

7”

19.4”
”4”

18.4” 19”

17.1”

17.5” 6.7”

.2”

Figure 8 Outline Drawing of the Modular Inverter unit

15
TEBEVERT III INVERTER SYSTEM

4.5.1 INVERTER MODULE FRONT PANEL


The front panel of the inverter module is shown below. The bar
graph indicator shows the output current of the inverter in steps of
10% relative to its maximum output current (41.6 A at 120VAC).

1 2 3 4

kg

Figure 9 Front View of the Inverter Module


1 Weight notice of the individual plug-in unit

2 Model Type designation

3 ON/OFF switch (S1)

4 LED Indicators (See Figure 10 below)

16
TEBEVERT III INVERTER SYSTEM

Figure 10 Inverter Module Front Panel Controls & Indicators


Below is an explanation of the symbols on the front panel
indicators.

This symbol indicates that all the points in this operating


manual must be observed at all times.

Indicates the position of the inverter's power switch:

ON / 1 or OFF / O

Indicates AC output voltage is present.

Color Meaning when LED lights up


"OUTPUT VOLTAGE PRESENT" The output
voltage of the inverter is normal. (VN= 120 or
green 120/240V) See note See “Important Note” below.

"MAINS-SUPPLY SYNCHRONIZED" The output


voltage of the inverter is in phase and frequency
green
with the mains-supply voltage

17
TEBEVERT III INVERTER SYSTEM

"OVERLOAD" The output current of the inverter is


greater than 110% of the rated output current
red

"PARALLEL OPERATION" The inverter is in


parallel operation with other inverters. When this
LED flashes, the inverter is operating as the
green
MASTER.

"FAULT" The output voltage of the inverter is


outside the tolerance range
red

Important Note!
The Inverter and SBS Modules are 120VAC. An optional
transformer converts the output of the inverter system to
120/240VAC.

18
TEBEVERT III INVERTER SYSTEM

4.5.2 INVERTER MODULE REAR PANEL


1 2

X3 S2

X1

1 0

X2 F1 + -

7 6 5 4 3

Figure 11 Rear View of the Inverter Module

1 Data connector (X3)

2 DIP switch to set output frequency (S2)

3 Contact blade for the protective earth (X1: )

4 Contact blade for the DC input (X1: -)

5 Contact blade for the DC input (X1: +)

6 Inverter Output Circuit Breaker (F1)

(Placed above X2 for the 5kVA module)

7 Output connector (X2) - 5 poles for 5KVA module

4.6 STATIC BYPASS SWITCH (SBS) MODULE

The Static Bypass Switch (SBS) module monitors the AC bypass


input and DC input. The inverter system‟s default operation mode is
“Inverter Priority” which the output of the system is attached to the
parallel output of the inverter modules. If DC in to the inverter
modules is disrupted the SBS automatically switches the output to
the commercial AC input.

19
TEBEVERT III INVERTER SYSTEM

The inverter system can optionally be configured for “AC Mains


Priority”. In this configuration the output of the system is attached to
the commercial AC input. If commercial AC in to the inverter system
is disrupted the SBS automatically switches the output to the
inverter modules parallel output. The switching occurs in
milliseconds with no adverse effects to the load. The Maintenance
Bypass Switch (MBS) is set in Position “0” for normal UPS
operation. The SBS module can only be unplugged or inserted into
its shelf when the MBS is in Positions 1 (commercial AC out) or 2
(inverter AC out). Figure 12 on the next page is the SBS module
outline drawing.

20
TEBEVERT III INVERTER SYSTEM

17.5” 18.4” 19”

5.2”

5”

11.8”

Figure 12 Outline Drawing of the Static Bypass Switch (SBS) Module

21
TEBEVERT III INVERTER SYSTEM

4.6.1 SBS MODULE FRONT PANEL


All terminals and operating elements are on the front panel or rear
of the SBS unit.
1 2 3 4 5

kg

Figure 13 Front View of the Static Bypass Switch Module

1 Single Line Display and Indicators

2 Model designation

3 Indicates the system output

4 Selector switch to display either the inverter output voltage


or inverter output current. According to the position of the
switch, the output voltage (V) or the output current (A) is
displayed.

5 Digital Volt/Ammeter (displays output voltage or output


current)

Important Note!
The 120/240VAC configuration utilizes input/output
transformers to convert the input and output voltages to/from
the nominal 120VAC as required. The Tebevert III is a
120VAC system and the voltage and current displayed on
the Digital Voltmeter is the 120VAC component only.

22
TEBEVERT III INVERTER SYSTEM

Figure 14 Partial View of Static Switch Display


In the “V” position, Inverter System Output Voltage is displayed.
This is the voltage feeding the output auto-transformer (120 VAC on
primary winding), if present. In the “A” position, the Inverter System
Output Current is displayed. This is the current feeding the output
auto-transformer primary, if present (208A maximum).

On the front panel of the SBS module there is a single line mimic
diagram with various LED´s, used to indicate the operating state of
the SBS unit.

Figure 15 SBS Single Line Mimic Diagram with LED Indicators

23
TEBEVERT III INVERTER SYSTEM

Below are the explanations of the various indicators on the SBS


module, when active.

LED Color Meaning when LED lights up

“LOAD ON BY-PASS OPERATION" The SBS supplies


Green
the load equipment via the mains.

"LOAD ON INVERTER OPERATION" The SBS


Green supplies the load equipment via the inverters modules.

"MAINS VOLTAGE NORMAL" The mains voltage is


within the limiting range.
Green

"INVERTER VOLTAGE NORMAL" The inverter output


voltage is within the limiting range.
Green

"NORMAL OPERATION" Mains voltage and inverter


voltage are within the specified range, the inverters are
Green operating synchronized to the mains.

"FAULT" The SBS or the inverters have a fault.


Red

"OVERLOAD" The inverter system is overloaded by


Red more than 5%.

24
TEBEVERT III INVERTER SYSTEM

4.6.2 SBS MODULE REAR PANEL

1 2 3 4 5

N 1L
S1
X1

N L1 L
S2 X5
X3 X4

10 9 8
7 6
Figure 16 Rear View of the Static Bypass Switch Module

1 Contact blade for the protective earth (Connector X1: )

2 Contact blade for the SBS output (Connector X1: N)

3 Contact blade for the inverter input (Connector X1: 1L)

4 Female connector for the data bus (Connectors X3 & X4)

5 Female connector for auxiliary DC supply and voltage-free


fault messaging system (alarm outputs) (Connector X5)

6 DIP switch S1 for system settings (Refer to Section 6.1.3


for details)

7 DIP switch S2 for system settings (Refer to Section 6.1.3


for details)

8 Contact blade SBS output (Connector X1: L)

9 Contact blade mains input (Connector X1: L1)

10 Contact blade neutral contact, mains input (Connector X1:


N) (not included on 25.0kVA unit, part no. 120416)

25
TEBEVERT III INVERTER SYSTEM

4.7 AC DISTRIBUTION
Two AC distribution options are available from Benning- one
utilizes a standard North American style snap-in breakers in
an external rack-mountable panel; the other utilizes standard
DIN style breakers which can be mounted on a DIN rail inside
the Inverter Cabinet.

4.7.1 NA STYLE SNAP-IN BREAKER PANEL


Note: This optional AC Distribution Panel, as shown below, cannot
be installed in the inverter cabinet, due to space constraints. It is a
UL Listed, externally mountable option. The panel is designed to
accommodate up to 20 breaker positions using standard
Eaton/Cutler Hammer CH style snap-in breakers (up to 50A /pole
max). The maximum allowable current per bus is 125A. The AC
Distribution Panel is designed to mount into a standard 19” relay
rack and occupy 5U (8.75”) of vertical space. Conduit knockouts,
sized for either ¾” or 1” conduits, are provided for conduit to enter
the back of the panel for the output wiring. The input wiring is
provided via a pigtail through a knockout also located at the rear of
the panel. This option can be wired as 120VAC and Neutral or
120/240VAC and Neutral.

CH Breaker
Ground Bar Neutral Bar Main Lugs
Positions
Figure 17 Snap-in Style External Rack-mount AC Distribution Panel

26
TEBEVERT III INVERTER SYSTEM

4.7.2 DIN RAIL MOUNT AC BREAKERS


This AC Distribution option is an internally mountable option. The
DIN rail accommodates up to 24 breakers using standard CBI type
QL, UL Listed, 1 or 2-pole, DIN Rail mounting circuit breakers. The
maximum allowable sized breaker is 25A per pole. The maximum
allowable current per bus is 125A. This AC Distribution is designed
to mount into the standard inverter cabinet and occupies 4U of
vertical space. Neutral and Ground connections are provided as
part of the distribution option. This option can be wired as 120VAC
and Neutral or 120/240VAC and Neutral depending on the output
voltage option selected.

Commercial AC
(By-pass) Input

Ground (PE) 1 or 2 pole


Neutral (N)
output breakers
Figure 18 DIN-rail Style Internal AC Distribution

27
TEBEVERT III INVERTER SYSTEM

4.8 INPUT & OUTPUT TRANSFORMERS


The heart of the Tebevert III system operates at 120VAC. Therefore, all
input transformer secondaries and output transformer primaries must be
120VAC. To accommodate diverse AC input and output voltages, optional
transformers can be supplied.

Input transformers can be supplied with the following primary windings:


240/120 (L1, L2, N) autotransformer; 208 (L1, L2); 220 (L1, L2); 230 (L1,
L2); 240 (L1, L2); 480 (L1, L2).

Output transformers can be supplied with the following secondary


windings: 120/240 (L1, L2, N) Autotransformer; 115/230 (L1, L2) Isolation
Transformer (system output adjusted down to 115V); and 115/230 (L1, N)
(system output adjusted down to 115V).

The transformers are mounted in the bottom section of the cabinet


typically as shown in Figure 19 below and factory-wired to AC
Input/Output Terminal Blocks at the top of the cabinet for customer
convenience.

Figure 19 Optional Input & Output Transformers

28
TEBEVERT III INVERTER SYSTEM

4.9 TECHNICAL DATA

Maximum System Capacity 5-25 kVA (4-20 kW)


Inverter Module Rating 5 kVA (4 kW)

Maximum Modules Per System 5

Inverter Overload Capability 200% for Approx. 1.25 Seconds (Inverter Output)

Static Bypass Switch Module Standard

SBS Priority Inverter or Commercial AC By-pass

SBS Transfer Time <2ms

SBS Overload Capability 500% for 100ms on bypass

Overload, Modules Over Temperature, Short Circuit On Output, Low DC Voltage,


SBS Transfer Criteria
Manual Initiation, and Output AC Voltage Out Of Range

(1) Form ―C‖‖ Summary Alarm; Optional Relay Card (8 Alarms); HTML and SNMP Alarms
Remote Alarming
Available

Metering Graphic Display, Power Flow diagram, and LED’s, Optional Digital Metering

On, Output Present, DC Input OK, Inverter Fault, Parallel Operation, Overload, and Bar
Indicators Graph for Output Power

AC Output Voltage 120 VAC Standard, Optional—120/240

AC Output Current (Max) @ 120 VAC 208 A (0.8 leading), 168 A (Unity pf)

AC Output Frequency 60Hz

Commercial AC By-pass Input Voltages Available 120 VAC Standard, Optional—208, 220, 240 or 480VAC

Load Power Factor Range 0.7 Lagging to 0.8 Leading

Output Voltage Regulation +/- 5% For All Combinations of Line, Load, and Temperature

Distortion < 3% @ 100% Rated Linear Load

DC Input Voltage -40.8 to -60VDC

93A at -54VDC (115 A max at -42VDC); DC Input Protection Recommended/Module or 700A DC


DC Input Full Load
Current/Module Input Protection for Bulk DC Systems Recommended

DC Inrush Current Soft Start, Current Limited

Efficiency >86.5% (on-line mode) / >97% (off-line mode)

Operating Temperature Range 32° to +131°F (0° to +55°C); derated by 2.5%/°C above 40° C

Operating Humidity Range 0-95% Non-Condensing

Heat Output Per Module < 2,040 BTUs Per Hour @ 100% Load

Cooling Temperature Controlled Fans

Elevation 6000’ (1800 m)

Cabinet Dimensions 84‖ x 23.6‖ x 23.6‖ (2134 mm x 600 mm x 600 mm)

Cabinet Weight 765 lbs. (347 Kg) without Modules

Inverter Module Weight 77.2 lbs. (35 Kg)

Module Mounting Hot Pluggable

Safety Standards UL60950

Design Standards Seismic Zone 0 (Standard), NEBS Level 3— Zone 4 Optional

EMI Emissions GR-1089, EN62040-2, FCC Class A

EMI Immunity GR-1089, EN61000-4-4, EN610004-5

Electrostatic Discharge Immunity EN61000-4-2

29
TEBEVERT III INVERTER SYSTEM

5 INSTALLATION & SITE ENGINEERING DETAIL


5.1 PREPARATION FOR INSTALLATION
This section describes how to prepare your Tebevert III system for installation,
once it has arrived at the site, including unpacking, inspection, and preparation
for installation. Read all sections carefully before installing the power system.

If the Tebevert III cabinet is crated for shipment, it should be equipped with TIP N
TELL™ indicator(s) and associated tag(s) to warn if the crate was (were)
mishandled or tipped during transportation. Verify that there are no blue beads in
the arrow of the indicator as shown in Figure 20 below. If blue beads are present
in the arrow, make note of it on the bill of lading and open the crate(s)
immediately to verify the equipment for damage (Claims for tipping will depend
on this notation). Report any damages to the freight carrier immediately.

Figure 20 TIP N TELL™


The Tebevert III crate may also be equipped with a shock watch. If Shock watch
is red, please note upon delivery on the shipping receipt .Follow instructions
located on the carton. Refer to Figure 21.

Figure 21 SHOCKWATCH

30
TEBEVERT III INVERTER SYSTEM

5.1.1 UNPACKING THE TEBEVERT III INVERTER SYSTEM


The cabinets and Inverter/SBS modules are shipped separately. Each module
has been factory tested and is ready to plug into the power shelves. The
following steps explain how to remove the cabinet from its packaging.
1. Cut the straps holding the cabinet to the pallet.
2. Remove the top cover section of cardboard and the foam inserts.
3. Carefully lift the exterior cardboard sleeve, lifting it completely off the
cabinet. (This may require two people)
4. Remove the remaining foam inserts and the plastic bag.

The Inverter Cabinet weighs up to 700lb (340kg) net and


up to approximately 850 lbs.(386kg) packed. It is
mandatory that necessary precautions be taken to lift,
move, set and position the cabinets.

5. Using an appropriate number of people or the proper lifting device lift the
cabinet off the shipping pallet. Should a forklift or other lifting device be
used you must first remove the front and rear lower cover plates. Be sure
to replace the cover plates once the cabinet has been positioned and
bolted in place. Once removed, lifting forks may be inserted into the frame
base allowing the cabinet to be lifted off the pallet. A secondary means of
moving the cabinets is to use a dolly truck. If this method is used, only lift
the cabinets from the right side of the cabinets as viewed from the front.
6. Ensure that the cabinet is installed on a level surface for proper operation
of the upper cabinet door.
7. Open the shipping cartons for each inverter/SBS module. Be sure to save
some of the packing materials in case the modules need to be returned to
the factory for some reason. The inverter modules weigh 77 lbs. (35kg)
each, net.

5.1.2 INSPECTING THE EQUIPMENT


Check the cabinet and the modules for external damage. If any damage
occurred during shipment, keep the shipping cartons and packing
materials so the carrier can inspect them.

It is your responsibility to file claim with the carrier for damages to the
equipment. Any and all damage noted upon receipt of the Tebevert III
Inverter System should be clearly identified in detail on the Bill of Lading.

31
5.1.3 CARRIER CLAIMS
Carrier‟s claim procedures should be initiated promptly. In the event damage is
found after delivery, it should be reported as soon as possible (normally 15 day
time limit on reporting damages incurred in shipment).

5.1.4 CHECKING PACKAGING CONTENTS

Verify the contents of the system against the packing list and the purchase order.
If the shipment does not contain the appropriate items, contact BENNING
Customer Service at 800-910-3601 (follow the prompts) or 214-553-1444.

5.1.5 SAFETY

Please review all safety warnings according to the GR1275 standards before
beginning the installation process. Observe all warnings and labels on the
equipment and in this manual as well.

5.1.6 INSTALLATION TOOLS


 Basic Hand Tools (i.e. wire cutters, wrenches, screw drivers, 8mm
Allen Key for AC Terminal Blocks)
 Insulated Rubber Mat
 Crimpers (match crimper and die to the lug manufacturer‟s
recommendation)
 Calibrated Digital Multi-meter
 Calibrated Torque Wrench

5.1.7 WIRING GUIDELINES


All electrical connections should be made using the proper crimping tools
and dies and should be torqued to the values specified. All building wiring
should comply with the NEC and other applicable local codes. The
temperature rating of the wire must be no greater than 195°F (90°C) and
may be sized using the ampacity table in the NEC handbook. Wiring
internal to enclosed equipment cabinets must be rated no less than 220°F
(105°C).

5.1.8 PACKAGING
All packages should be opened with a box cutter with the blade minimally
exposed so that only the sealing tape is cut. Save all packaging material
until the system has been powered up and all parts are operating within
specification. The shipping packaging may be used to return defective
parts.

32
TEBEVERT III INVERTER SYSTEM

5.2 CABINET INSTALLATION


The site chosen for the inverter system must have a solid and level floor.
The inverter system is designed for operation in a restricted access, dry
environment. The maximum ambient temperature permitted is 40°C. Each
inverter module at full load will emit 2,040 BTU‟s per hour (approximately
10,500 BTU‟s/hour for a fully loaded 25kVA system, including SBS module
and other electronics). Attention must be paid to the location of the
inverter system so that it is not exposed to air borne contaminants and the
flow of cooling air is not hampered.

5.2.1 RECOMMENDED MINIMUM CABINET CLEARANCES


Front: 24” (600mm); back: 12”(300mm); and above roof: 12”(600mm).

Cooling air flow is front to back with exhaust grills in back of cabinet
which must not be obstructed or the warranty will be void and the
operating life of the Inverter and SBS modules will be reduced.

Note, no clearance is required on the cabinet sides.

5.2.2 WEIGHTS AND DIMENSIONS


Cabinet Weight: Approximately 450lb/205kg without modules or
transformers (add 250lb/115kg if optional transformers present).

Cabinet Dimensions: 84”H (2100mm) x 23.6”W (600mm) x 23.6”D

Inverter Module Weight: 77lb. (35kg)

Static Bypass Switch Module Weight: 22lb. (10kg)

33
TEBEVERT III INVERTER SYSTEM

5.2.3 CABINET FOOTPRINT

Below is the mounting hole pattern for affixing the cabinet to the floor.
Dimensions are in inches. Using this pattern, mark the floor for anchor
positions and proceed with either standard floor anchoring means or
earthquake approved anchoring. Frame Isolation pads are available from
Benning if required. Non earthquake zone applications use four 0.42” dia.
floor mounting holes for each cabinet. Earthquake zone applications
require welded cabinets with eight 2” x 0.5” slots for mounting with
earthquake zone approved anchors (customer provides anchors).

Figure 22 Cabinet Mounting Hole Pattern

34
TEBEVERT III INVERTER SYSTEM

The cabinet should be shimmed to the floor to make sure it is level, and
then secured using washers in the mounting holes provided. Typical
standard concrete anchor mounting and earthquake zone concrete
applications are shown below in Figure 23 and Figure 24.

Figure 23 Typical Non-Earthquake Zone Concrete Anchor

Figure 24 Typical Earthquake Zone Concrete Anchor

35
TEBEVERT III INVERTER SYSTEM

5.3 CABINET WIRING

Cables may be fed into the inverter system from above or below,
according to the model. The size and location of the terminal blocks and
distribution assemblies are configuration dependant. For the cross-
sections and the recommended over-current protection the following
values must be observed. The recommended cable sizes shown below
meet National Electrical Code (NEC) Table 310-16 requirements.
However, larger size cables may be required in order to to reduce the
effects of voltage-drop, depending on the conditions at the installation site,
than would normally be necessary due to the current. It is recommended
that if a system can be expanded with additional inverters in the future, the
initial AC wiring should be sized for the maximum number of inverters.

Warning!

For the proper protection of loads, careful attention must


be paid to the selection of upstream mains protection.

The voltage-free external alarm contact outputs are


rated for a max of 230VAC/1A or 270VDC/0.2A (50W
max).

If a future inverter expansion is planned, the cable cross-


sections and the fuse protection must be used for the
maximum values of load power requirements.

If an external battery is connected to the inverter, then


instructions concerning the installation and maintenance
given by the battery manufacturer must be observed.

The supply circuits must be equipped with disconnecting


devices

The system has high leakage current potential. Frame


ground (Earth) connection is essential before connecting
the supply.

36
TEBEVERT III INVERTER SYSTEM

5.3.1 DC CABLE REQUIREMENTS


There are three options for DC power input to the Inverter system:

 1. Most Reliable: Individual DC input per inverter module accepting


two-hole lugs with 3/8-16 studs on 1”cc. These terminal blocks
accept up to one 4/0 stranded cable per pole.

 2. Individual DC input per inverter module using screw compression


type terminal blocks which accept up to one 4/0 stranded cable.
Even though the initial install may only require 2 or 3 plug-in inverter
modules, it is recommended that all five DC input feeds be wired
out.

 3. Bulk input accepting up to 750MCM two-hole lugs, two per pole


in a back-to-back configuration. The hole pattern is designed for
3/8” holes at 1” cc. EC-701 must be ordered for this.

Cable sizes should be calculated to meet National Electrical Code (NEC)


Table 310-16 requirements and applicable engineering standards. Please
remember that larger size cables may be required in order to meet site
voltage drop requirements.

An insulated DC input cable support bracket is provided. See Figure 25


below. It is attached to top of the inverter cabinet for support of cabling
between the cabinet and overhead cable racking.

Figure 25 Insulated DC Cable Support Detail

37
TEBEVERT III INVERTER SYSTEM

DC CABLE REQUIREMENTS FOR INDIVIDUAL DC INPUT PER MODULE


(DIN RAIL OR BUSBAR TERMINAL BLOCK)
Terminal Terminal/connection Suggested
Connection type
designation capacity protection
X1: 1L+/1L- DC input/inverter 1 4/0 Maximum* 150A
X1: 2L+/2L- DC input/inverter 2 4/0 Maximum* 150A
X1: 3L+/3L- DC input/inverter 3 4/0 Maximum* 150A
X1: 4L+/4L- DC input/inverter 4 4/0 Maximum* 150A
X1: 5L+/5L- DC input/inverter 5 4/0 Maximum* 150A
X4: NC/C/NO Alarm fault signal 28 - 10AWG 2A
Frame GND Bonding ground 3/8” stud, 1”cc two hole lug
*Wire should be sized by calculating for voltage drop, if calculated size exceeds the maximum size
then H-Tap the drop into the bay to the main run.

Figure 26 Stud Arrangement for Individual DC Input Feed / Module

38
TEBEVERT III INVERTER SYSTEM

DC CABLE REQUIREMENTS FOR BULK FEED DC INPUT SYSTEM


DC input bulk feed option allows all five inverters to be fed from one fuse/breaker
Maximum system
Supply conductor Suggested protection
capacity
DC Input 25kVA 5 Inverters 48VDC/600A-700A

Terminal Connection type Terminal/connection Suggested


designation capacity protection
Busbar
DC input
3/8” x 1”cc
X1: +/- Inverters 1-5 600A-700A
2 X 750MCM max.
Requires Part. No. EC-701
X4: NC/C/NO Alarm fault signal 28 - 10AWG 2A
Frame GND Bonding ground 3/8” single hole lug

Figure 27 Stud Arrangement for Bulk DC Input Feed

39
TEBEVERT III INVERTER SYSTEM

5.3.2 AC CABLE REQUIREMENTS


Figure 28 below identifies the AC Input and Output Terminal Blocks for a 208VAC
Input, 120/240VAC Split Phase Output system located near the top of the cabinet.
A removable filler plate is provided for the installer to punch conduit access holes.
An 8mm Allen key is required for securing the conductors. CAUTION: When
applying the cable size recommendations given below, derating allowances must
be made for high temperature environments and multiple conductor assemblies in
conduits, when applicable, in accordance with local codes.

Figure 28 AC Terminal Blocks for 208VAC In & 120/240VAC Out System


AC CABLE REQUIREMENTS FOR 120VAC INPUT

Maximum System
Supply Conductor Suggested protection
Capacity
AC Mains 5 inverters/25kVA 120VAC/300A

Terminal Connection Terminal Connection Suggested


Designation Type Capacity Protection
4/0 maximum
Mechanical
X2: L1/N/PE (90°C/194F cable 300A
Type

40
TEBEVERT III INVERTER SYSTEM

AC CABLE REQUIREMENTS FOR 120/240VAC AC INPUT

Maximum System
Supply Conductor Suggested protection
Capacity
AC Mains 5 inverters/25kVA 120/240VAC/150A

Terminal Connection Terminal Connection Suggested


Designation Type Capacity Protection
Mechanical 1/0 minimum
X2: L1/L2/PE 150A
Type 4/0 maximum

AC CABLE REQUIREMENTS FOR 208VAC AC INPUT

Maximum System
Supply Conductor Suggested protection
Capacity
AC Mains 5 inverters/25kVA 120/208VAC/150A

Terminal Connection Terminal Connection Suggested


designation Type capacity protection
Mechanical 1/0 minimum
X2:L1/L2/PE 4/0 maximum 150A
Type

AC CABLE REQUIREMENTS FOR 220VAC AC INPUT

Maximum System
Supply Conductor Suggested protection
Capacity
AC Mains 5 inverters/25kVA 220VAC /150A

Terminal Connection Terminal Connection Suggested


Designation Type Capacity Protection
Mechanical 1/0 minimum
X2:L1/L2/PE
Type 4/0 maximum 150A

41
TEBEVERT III INVERTER SYSTEM

AC CABLE REQUIREMENTS FOR 240VAC AC INPUT

Maximum System
Supply Conductor Suggested protection
Capacity
AC Mains 5 inverters/25kVA 120/240VAC /150A

Terminal Connection Terminal Connection Suggested


Designation Type Capacity Protection
Mechanical 1/0 minimum
X2:L1/L2/PE
Type 4/0 maximum 150A

AC CABLE REQUIREMENTS FOR 480VAC AC INPUT

Maximum System
Supply Conductor Suggested protection
Capacity
AC Mains 5 inverters/25kVA 480VAC /70A

Terminal Connection Terminal Connection Suggested


Designation Type Capacity Protection
Mechanical 4awg minimum
X2:L1/L2/PE 70A
Type 4/0 maximum

AC CABLE REQUIREMENTS FOR 120/240VAC AC OUTPUT

Terminal Connection Terminal Connection


Suggested Protection
Designation Type Terminal
Capacity Designation
125A Molded Case 2
Up to 4/0 Capacity; 1/0
CB1: L1, L2, Compression pole AC Output Circuit
AWG conductor
X3: N, G Type Breaker provided as an
recommended
option. See Figure 28

The system output current is 104A per leg at full load (25kVA) or 83A per leg at
20kVA (n+1 configuration). The maximum split phase imbalance recommended is
60/40%

42
TEBEVERT III INVERTER SYSTEM

5.3.3 ALARM OUTPUT CABLE REQUIREMENTS


The following information applies to the 120/240VAC output configuration.

The voltage-free external alarm contact outputs are rated for a maximum
of 230VAC/1A or 270VDC/0.2A (50W max).

Relay coils are activated in normal operation. There are a total of 11 alarm
outputs available, three from the MCU2000 and eight from the Relay Box,
located in the upper inside section of the cabinet. The outputs are
programmable, but are preassigned in the factory as shown below.

Alarms Available from MCU, Terminal Block “X1”

X3* X1
MINOR - COM
1 1
MINOR - NC K1
2 2
MINOR - NO
3 3
MAJOR - COM
4 4
MAJOR - NC K2
5 5
MAJOR - NO
6 6

OPERATING ON MAINS - COM


7 7
OPERATING ON MAINS - NC
8 8 K3
OPERATING ON MAINS - NO
9 9
10
*NOTE: X3 IS ONLY USED WHEN A 11
RELAY BOX IS NOT INSTALLED.
12

Figure 29 MCU2000 Alarm Terminal Block “X1”

43
TEBEVERT III INVERTER SYSTEM

Alarms Available from Alarm Relay Box, Terminal Blocks “X4” & “X5”
RELAY BOX

X5 X4
16 16
NO 15 15 NO
OUTPUT AC BRKR OPEN NC 14 K8 K4 14 NC MULTIPLE INVERTER FAIL MAJOR (REMOTE)
COM 13 13 COM
12 12
NO 11 11 NO
SYSTEM FAILURE - GROUP ALARM NC 10 K7 K3 10 NC INVERTER FAIL MINOR (REMOTE)
COM 9 9 COM
8 8
NO 7 7 NO
BYPASS UNAVAILABLE NC 6 K6 K2 6 NC MULTIPLE INVERTER FAIL MAJOR (LOCAL)
COM 5 5 COM
4 4
NO 3 3 NO
SYSTEM OVERLOAD - MAJOR NC 2 K5 K1 2 NC INVERTER FAIL MINOR (LOCAL)
COM 1 1 COM

TO MCU X4 A6 X300
48V RTN (+) TO X5
X1 + 1
- 3
48V (-) TO FUSE 8 (P/O GMT BOARD)

Figure 30 Relay Box Alarm Terminal Blocks “X4” & “X5”

44
TEBEVERT III INVERTER SYSTEM

5.3.4 CABINET FRAME GROUNDING CABLE REQUIREMENTS


Each cabinet must be grounded radially to the central office ground bus or
equivalent. Dual 3/8”dia. brass studs with 1” spacing have been provided
for this purpose on the roof of the cabinet. A 1/0 ground wire with double
hole lug is recommended

Figure 31 Frame Ground Studs, Top of Bay

5.3.5 REMOTE MONITORING


A CAT 5 or CAT 6 cable is required to be connected to the 10 Base T, RJ-45
connector on the base of the inverted remote monitoring adaptor shown below.

Figure 32 Remote Monitoring Network Connection

45
TEBEVERT III INVERTER SYSTEM

5.3.6 TORQUE TABLES FOR ALL TERMINATIONS

Terminal Block Torque Table

Terminal in-lb ft-lb


P/N#
UKH95 178 15

UKH150 266 23

Stud Terminal Torque Table

46
TEBEVERT III INVERTER SYSTEM

6 SYSTEM START-UP
6.1 MODULE INSTALLATION
It is recommended that the set up and installation of the Inverter and
SBS Modules be done as part of the start-up process by qualified
service personnel.

Prior to the set up and installation of the Static Bypass Switch and Inverter
modules in the system, the following points must be checked and
observed.

 Verify that the units are of the same type and model (48VDC in/
120VAC out, 5kVA). Since all inverters of the Tebevert III series have
a similar form factor, the exact model of the unit must be confirmed.

 Verify the Inverter and SBS module settings according to Sections


6.1.1 and 6.1.3 below. All inverter modules MUST have the same
settings.

 Verify that the ON/OFF Switch S1 on the front of each inverter module
is switched off. Note, the SBS does not have an ON/OFF switch, but is
ON after insertion as soon as Bypass AC is present or -48VDC is
applied to any inverter module position.

47
TEBEVERT III INVERTER SYSTEM

6.1.1 INVERTER MODULE SETTINGS


Each inverter is set to factory default values according to the required
operating conditions. An adjustment of these settings is not usually
necessary.

However, if the inverter must operate at 50 HZ, a simple adjustment can


be carried out.

Warning!
Alteration of the unit settings may only be carried out by
qualified personnel. The altered settings must be clearly
marked on the unit. Any alternations of these settings
must also be performed on all other inverters within the
system and on the SBS.

The output frequency is changed with the DIP switch S2 located on the
rear side of the inverter unit (See Figure 11)

ON 4 3 2 1
50Hz
OFF 60Hz

NOTE: Only the setting of Switch 1 is changed. All the other switches must
always remain in the OFF position.

48
TEBEVERT III INVERTER SYSTEM

6.1.2 INSTALLATION OF INVERTER MODULES


Warning!
The weight of each inverter is approx. 77lbs (35kg). The
unit may only be lifted and transported using the carrying
handles built into each side of the unit. DO NOT carry or
lift the unit using the handles on the front panel!

Before the inverter unit is installed, any materials used to protect the unit
during transportation must be removed. Inspect connector pins on rear of
modules to ensure they are free of packing material. Ensure that the
output circuit breaker on the back of all modules is set to the 1=ON
position- see Figure 33 below.

Figure 33 Inverter Module Rear Side Output Circuit Breaker


The guiding rails on the base of the inverter shelf and under the inverters
ensure the exact positioning of the modular inverter unit. The unit should
be slowly pushed in past a slight resistance until its front panel is flush with
the frame of the cabinet. All electrical contacts have then been made. The
inverter is then fixed into the cabinet with four screws (supplied).

Any free slots reserved for future inverter capacity upgrades must be
covered with dummy coverplates supplied with the system at time of
shipment from the factory. These coverplates must be secured with four
screws (supplied).

49
TEBEVERT III INVERTER SYSTEM

6.1.3 STATIC BYPASS SWITCH MODULE SETTINGS


The Static Bypass Switch (SBS) is factory set to default values. It is not
usually necessary to change these settings. However, if the units are
exchanged or there are different operating conditions, the settings must be
checked or readjusted.

Warning! Only qualified personnel may carry out alteration


of the settings on the unit. Altered settings must be clearly
marked on the unit.

On the rear side of the SBS unit there are 2 sets of 8 DIP switches; S1 (on
is down) and S2 (on is up). Look closely at the switch to see the direction
of ON which is printed on the switch. See Figure 16 for location. The
settings are shown below.

10

01
ON DIP Switch S1 Settings

Adjustments Position 0 Position 1


Operating mode Inverter Priority Mains Priority
Nominal voltage 120 or 120/240 VAC 230 VAC
Nominal frequency 50 Hz 60Hz
Mains error signal No mains available Operation with
(no mains failure mains!
indicator) (Mains failure
indicator.)
Fault signal fault signal of Common fault signal
STATIC BYPASS from STATIC
BYPASS &
INVERTER
Maximum deviation Pos 1 Pos 0 Pos 1 Pos 0
of nominal frequency 3% 4%
Maximum deviation Pos 1 Pos 1 Pos 0 Pos 0
of nominal frequency
Reserved Reserved Reserved

50
TEBEVERT III INVERTER SYSTEM

Note: Highlighted areas correspond to factory default settings. The allowable


frequency deviation setting is defined by the binary combination of the two dip
switches designated, S1-2 and S1-3.

The settings of S2 provide the SBS with information on the output power of the
connected inverters. Depending on inverter system (25kVA or 12.5kVA) only one
highlighted switch may be in Position 1.

Important Note!
The setting of S2 shall be the same for both the 120 and
120/240VAC systems.

ON

51
TEBEVERT III INVERTER SYSTEM

6.1.4 INSTALLATION OF SBS MODULE


At the time the Static Bypass Switch (SBS) module is installed, the
operating handle of the manual Maintenance Bypass Switch (MBS) must
be attached to it. The handle is installed on top of the SBS unit using
supplied four (4) M4 x 8mm screws. Position the switch mechanism and
the operating element in the following position as shown in Figure 34.

Figure 34 Installation Positions of Locking Mechanism & Operating Element


Using the guide rails located on the base of the mounting shelf, slowly
push the SBS unit into the shelf until the front panel is flush with the frame
of the cabinet. This should require minimal effort. All electrical contacts
have been made and the operating element of the manual MBS is
connected to its rotation axle. The SBS is fixed into the cabinet with four
screws (supplied).

52
TEBEVERT III INVERTER SYSTEM

6.2 SWITCHING ON THE INVERTER SYSTEM


6.2.1 PROCEDURE IF THE SYSTEM IS SET TO INVERTER PRIORITY
Before the AC Bypass is connected and the inverters are switched on,
verify that the manual Maintenance Bypass Switch is in Position “0” (UPS
operation). In this position the Static Bypass Switch (SBS) is mechanically
locked and cannot be pulled out of the cabinet.

The load circuits should not yet be connected and all the inverters should
be switched off. The Static Bypass Switch (SBS) should be set to the
operation mode "inverter priority" (See Section 6.1.3).

Step 1: The DC supply should be switched on. All the LEDs on the SBS
module will light up for a short time during start-up. (Reset of the internal
processor!) Afterwards, only the LED "FAULT" is lit and the DVA indicates
the voltage or current to be "0".

Step 2: The AC Bypass source should be switched on. The LEDs "MAINS
VOLTAGE PRESENT" and "MAINS OPERATION" are then lit, as well as
the LED "FAULT". The AC Bypass source is connected to the output and
the DVA shows the AC Bypass voltage (e.g. 120), if the selector switch
underneath the DVA is set to position "V".

Step 3: The first inverter can now be switched on. After a start-up time of
approx. 20 seconds, the LEDs "INVERTER OUTPUT VOLTAGE
PRESENT"; "MAINS SYNCHRONOUS" are lit up and the LED
"PARALLEL OPERATION" starts to flash. The flashing of this LED
indicates that this inverter has been assigned the MASTER function. At the
same time, some of the LEDs on the SBS change their state. The LED
"FAULT" is extinguished and the LED "READY FOR OPERATION" is lit.
Assuming that the operation mode is "inverter priority", the inverter output
voltage is connected to the output. The LEDs "INVERTER OUTPUT
VOLTAGE PRESENT" and "INVERTER OPERATION" light up and the
LED "MAINS OPERATION" are extinguished. The voltage-free fault
indicator switches to the state "no fault".

Step 4: The remaining inverters are then switched on. The state of the
SBS LEDs on the SBS and the first inverter do not change. After the start-
up phase, the LEDs "INVERTER OUTPUT VOLTAGE PRESENT",
"MAINS SYNCHRONIZED" and "PARALLEL OPERATION" are lit on all
inverters.

53
TEBEVERT III INVERTER SYSTEM

Step 5: Finally, the load circuits may be switched on. When the load is
connected, the load current is divided equally between the individual
inverters and the bar graph indicators show the output current of the
individual inverter. The load voltage (inverter output voltage) or the total
load current can be read on the DVA display.

After all system components have been connected and switched on, the
states of the LEDs on the SBS and Inverter should be as follows.

Figure 35 LED states of the SBS (Normal State Inverter Priority)

When the inverter operates as


the master, this LED flashes.

Figure 36 LED States of the Inverter (Normal State Inverter Priority)

6.2.2 PROCEDURE IF THE SYSTEM IS SET TO MAINS PRIORITY


Before the AC Bypass is connected and the inverters are switched on,
verify that the manual Maintenance Bypass Switch is in Position “0” (UPS
operation). In this position the Static Bypass Switch (SBS) is mechanically
locked and cannot be pulled out of the cabinet.

The load circuits should not yet be connected and all the inverters should
be switched off. The Static Bypass Switch (SBS) should be set to the
operation mode "mains priority" (See Section 6.1.3).

Step 1: The DC supply should be switched on. All the LEDs on the SBS
module will light up for a short time during start-up. (Reset of the internal
processor!) Afterwards, only the LED "FAULT" is lit and the DVA indicates
the voltage or current to be "0".

54
TEBEVERT III INVERTER SYSTEM

Step 2: The AC Bypass source should be switched on. The front panel
LEDs "MAINS AVAILABLE", "OPERATING ON MAINS", and “INVERTER
OFF” are then lit. The AC Bypass source is connected to the output and
the DVA shows the AC Bypass voltage (e.g. 120), if the selector switch
underneath the DVA is set to position "V".

Step 3: The first inverter can now be switched on. After a start-up time of
approx. 20 seconds, the inverter module‟s LEDs "INVERTER OUTPUT
VOLTAGE PRESENT"; "MAINS SYNCHRONOUS" are lit up and the LED
"PARALLEL OPERATION" starts to flash. The flashing of this LED
indicates that this inverter has been assigned the MASTER function. At the
same time, some of the LEDs on the SBS change their state. The SBS
module‟s LED "FAULT" is extinguished and the LED "READY FOR
OPERATION" is lit. The LED "INVERTER OUTPUT VOLTAGE
PRESENT" lights up.

Step 4: The remaining inverters are then switched on. The state of the
SBS LEDs on the SBS and the first inverter do not change. After the start-
up phase, the inverter module‟s LEDs "INVERTER OUTPUT VOLTAGE
PRESENT", "MAINS SYNCHRONIZED" and "PARALLEL OPERATION"
are lit on all inverters. The front panel‟s LEDs “INVERTER OFF” and
“INVERTER FAULT” turn off.

Step 5: Finally, the load circuits may be switched on. The total load current
can be read on the DVA display.

After all system components have been connected and switched on, the
states of the LEDs on the SBS and Inverter should be as follows.

Figure 37 LED states of the SBS (Normal State Mains Priority)

55
TEBEVERT III INVERTER SYSTEM

When the inverter operates as


the master, this LED flashes.

Figure 38 LED States of the Inverter (Normal State Mains Priority)

7 SYSTEM OPERATION
It is not necessary to understand the exact function of all components in
this inverter system. However, basic knowledge of essential components
aids in the understanding of the whole system and helps to avoid errors in
the maintenance and operation.

7.1 TOTAL SYSTEM

The inverter system supplies a high availability AC current supply to load


equipment that must have an uninterrupted input power supply at all times.
According to the selected operating mode, the inverter output voltage
(inverter priority) or the AC mains voltage (mains priority) is switched
through to the load equipment by the SBS. In the event the priority system
(mains or inverters) should fail, the redundant system is switched with
minimal interruption to the alternate source (within a few milliseconds).
The use of the manual Maintenance Bypass Switch allows servicing and
maintenance work to be carried out on the inverter system or the
redundant AC mains without an interruption in the power supply to the load
equipment.

56
TEBEVERT III INVERTER SYSTEM

7.2 INVERTER
7.2.1 MONITORING OF THE DC INPUT VOLTAGE
The DC voltage applied to the inverter is monitored for under voltage or
over voltage conditions. The inverter supplies continuous, regulated output
voltage when operated within these limits.

1 2

ON

OFF

V1 V0 V3 V2
1 Under Voltage 2 Over Voltage
1 Under voltage range 2 Over voltage range

Figure 39 Switching Thresholds for DC Over & Under voltage Monitoring


Figure 39 shows the main principles of the system. If over voltage is
applied, the inverter switches off at V2. Once the voltage has dropped to a
value which is below V3, the inverter switches on again automatically.

After switching off as a result of under voltage V1, the inverter switches on
again only after the input voltage V0 is reached. This value, V0, must also
be available when the inverter is switched on at the main switch. This
ensures that the unit does not start up briefly when the battery is not
charged.

Because of component variances and setting tolerances, the following


voltage ranges apply for the switching thresholds.

Nominal V1 V0 V3 V2
Input
Voltage
VN = 48VDC 40.3V....41.3V 48.5V....49.5V 57.0V....58.2V 59.4V….60.6V

The unit cannot be switched on when input voltages are


below V0!

57
TEBEVERT III INVERTER SYSTEM

7.2.2 MONITORING THE OUTPUT VOLTAGE


The output voltage supplied by the inverter is also monitored. If the output
voltage is within the range 120
indicated by an LED on the front panel. If it is outside this range, an LED
indicates the fault. If the output voltage exceeds the upper limit, the
inverter is blocked and switches to a self-holding mode. The self-holding
mode can be cancelled by switching the unit on again at the main ON/OFF
switch.

7.2.3 MONITORING THE TEMPERATURE


The temperature is measured in two locations, in the air stream that the
cooling fan draws in near the fan (giving the ambient outside temperature)
and near the back of the housing (giving the interior temperature).

If the cooling air temperature reaches a value of approximately 113F


(45°C), the fan inside the inverter automatically switches on.

If the cooling air temperature exceeds a value of approximately 185F


(85°C), the inverter switches off because of over temperature.

The unit also switches off when the interior temperature reaches
approximately 158F (70°C). The most common causes of high interior
temperature are high ambient temperatures or obstruction of the air
supply. The shut-down of the inverter due to over temperature is indicated
by the LED "FAULT" on the front panel.

7.2.4 OVERLOAD BEHAVIOR


The inverter is designed to withstand short-term overloading. In cases of
overloading, an LED on the front panel lights up. 200% of the nominal
effective current can be supplied for a maximum of 1.2 seconds (i.e.
double the rated power). If the overload still exists after 1.2 seconds, the
current is reduced to 1.3 times the rated value with a resultant reduction in
the output voltage. If the overload situation still persists after another 41
seconds, the power unit of the inverter goes off. The inverter can only
restart if, after the inverter has been switched off with the main switch, all
LED´s on the front panel are extinguished and the inverter is switched on
again. When operating the inverter with an SBS (this is standard for this
inverter system), the SBS recognizes the overload. If the inverter output
voltage lies outside the tolerance range as described in section 7.2.2, the
SBS will switch the current mains supply through to the load equipment.

58
TEBEVERT III INVERTER SYSTEM

7.2.5 SHORT-CIRCUIT BEHAVIOR


The inverter is permanently short circuit proof. Short circuits are a special
type of overload. At the time of the short circuit, the current is limited for 5
seconds to 2.8 times the nominal effective current. During this period, the
short circuit current can trigger the AC load protection circuits in the
customer provided AC distribution. After approx. 5 seconds have elapsed,
the power unit of the inverter switches off. A restart of the inverter, after a
short-circuit, is only possible when the inverter has been switched off with
the ON/OFF switch, all LED´s on the front panel are extinguished, and the
inverter has then been switched on again.

If the short circuit persists, this procedure is repeated.

When the inverter is operated with a Static Bypass Switch (SBS) and is
configured for inverter priority the SBS immediately (in less than 2 ms)
switches to the AC bypass when a short circuit is detected. The connected
AC bypass supplies the short circuit current. Once the SBS detects the
circuit is no longer shorted the SBS switches the load back to the inverter
modules output.

7.3 STATIC BYPASS SWITCH MODULE (SBS)


The Static Bypass Switch module accurately monitors all the relevant data
of the inverter system. This includes:

Inverter operational states


AC bypass voltage
Inverter voltage
AC bypass frequency
phase position between the inverter output and the mains
level of the load

This information is fed to an internal controller, which controls the SBS via
a logical trigger switching the AC bypass or the inverter output voltage
through to the load equipment. If the system is functioning correctly, the
voltage, which has been pre-selected by the setting of the operation mode,
is switched through the SBS, i.e. "mains priority" or "inverter priority".

In addition to the visual indicators (LEDs), the SBS also controls dry
contact alarm relays. A setting option is used to select whether this
messaging is a collective fault message from the SBS and the inverter, or
a single fault message of the SBS. This message follows the visual
indication with a delay of approximately 10seconds.
The cause of these faults may be:

59
TEBEVERT III INVERTER SYSTEM

Disturbance in the AC by-pass supply


Disturbance in the inverter / inverter system
Disturbance in the SBS

The reset of the dry contact alarm relay occurs without a delay. To permit
operation of the SBS via the remote monitoring system MCU, an additional
unit (satellite card) must be installed. Through this optional unit,
operational states and measurement values of the SBS and the
associated inverter system are transmitted to the remote monitoring
system via a serial interface to RS485 standard.

In the standard design, 6 different types of status information are


transmitted, resulting from the linkage of the various status data.

The transmitted status information comprises:

 Inverter operation
 SBS warning
 SBS fault
 Overload
 Faulty output voltage
 SBS blocked

In addition, 15 detected or calculated measuring values are transmitted.

 Heat sink temperature SBS


 Inverter output voltage
 AC by-pass voltage
 SBS output voltage
 SBS output current
 Output current Inverter 1 – Inverter 5
 Active power
 Apparent power
 Reactive power (calculated)
 Crest factor
 Output frequency

All indicated states and measuring values of the inverter system can be
further processed and evaluated using the service software of the remote
monitoring system.

Redundancy function for the SBS Satellite function (5 kVA and 2.5 kVA
inverters) - From Version 1.03 on we support a redundancy function
generating two events in the SBS satellite. This can be mapped to an input

60
TEBEVERT III INVERTER SYSTEM

of the optional MCU and used to control alarm relays in the optional relay
box.
The first alarm (Minor-non urgent) is activated, when one or more inverters
have a fault.

A fault is defined as:


- inverter module not working properly in any way (inverter error
message)
- inverter module turned off via its front panel switch
- inverter is removed from system (the total number of inverters is
logged, so, if the inverter module is plugged into a different slot, the
fault will be reset)

The second alarm (Major-urgent) is activated, when two or more inverters


have a fault. Fault conditions are defined above.
Note: If the alarm is triggered by removal of an inverter (e.g. for
service purposes) this can be reset by pushing the reset/led test
button on the LED-panel of the MCU.

61
TEBEVERT III INVERTER SYSTEM

7.4 DISPLAY PANEL AND MCU

This section applies to systems equipped with an MCU 2000 Monitor &
Control Unit and the optional Operator Panel shown in Figure 40 below.

7.4.1 INTRODUCTION TO THE DISPLAY PANEL

The Display Panel is a supplementary unit for the MCU 2000. It allows
monitoring and setting of the MCU and the entire power-supply system.
Its most important features are:

 Graphic illuminated LCD display


 Knob (jog-shuttle) for making quick settings
 freely selectable standard display of measured values
 menu-assisted input
 menu language freely selectable in four languages (three fixed and
one user-defined)
 user-defined signal and measurement-value text
 four password levels for access authorization.
 Error memory for the last 200 events (error log).
 Recording of values for 2000 measurement points.

7.4.2 STANDARD DISPLAY AND OPERATING ELEMENTS

This panel is located on the outside of the upper section swing-out door.
The MCU and associated I/O electronic modules are located inside that
section of the cabinet, mounted on DIN rail. The Operator Panel is used
for monitoring and set-up of the inverter system, with password levels for
access authorization as noted on Page ii at the front of this manual.

62
TEBEVERT III INVERTER SYSTEM

Figure 40 Operator Panel

The Operator Panel consists of:

 LCD Display – Displays Numeric Data: Factory default is set to


display Real Power (kW). Since the power factor of the load can
vary considerably, it is best to read the Real Power of the system
from MCU to determine actual AC loading. A fully equipped system
can provide 20kW of Load Power (16kW on fully equipped N+1
system). AC Volts, AC Amps, and Frequency are also available.
Displays logged data, e.g., alarm conditions, operator actions.
Control: allows system set-up and setting adjustments.

 LCD Display Controls – A thumbwheel is provided for scrolling


through displays. Three multi-purpose pushbuttons are as follows
with primary functions noted: E-Enter, S-Show alarms, & C-Clear

 System LED Indicators – Four LEDs are provided for major system
fault indication: from top to bottom – “System Running”, “System on
Battery Operation”, “Alarm Active”, “Urgent Alarm Active”

 Thirteen LED Indicator Strip with Reset/LED Test Pushbutton - see


section 7.5 for details

63
TEBEVERT III INVERTER SYSTEM

7.4.3 CLEAR FUNCTION

From any menu, it is possible to exit the menu system by pressing C


repeatedly until you reach the top screen.

7.4.4 SELECT MENU ITEM

The main menu is displayed by turning the knob. More sub menus can
then be displayed by pressing the E button.
To quit the menus, press the C button. You then return automatically to
the menu level above.
If no button is pressed for a period of time (user-defined) the unit returns
automatically to the standard display.

7.4.5 MAIN MENU

S button E button
Default Top Menu Show Error Log Clear Error Log

E button

*** Main Menu ***


Control (0)
Settings (0)
Measurement Values (0)
Status (0)
Display (0)
Menu Language (0)
System Setup (0)

Figure 41 Main Menu Tree (password level in parenthesis)


Entering text:
With some settings of the display (e.g. passwords) text has to be entered.
The cursors are as follows:
1. An underline „_‟:
The cursor position can be changed with the knob. Input mode is ac-
cessed by pressing the S button (see point 2). The entry is acknowledged
and concluded by pressing the E button. The entry procedure is cancelled
by pressing the C button.
2. A block „▓„:
All the possible input symbols can be scrolled through using the knob. The
shift mode is accessed by pressing the S button (see point 1). The entry is

64
TEBEVERT III INVERTER SYSTEM

acknowledged and concluded by pressing the E button. The entry


procedure is cancelled by pressing the C button.

A help function is also available for this procedure by means of pressing


the button combination of S then E.

7.4.6 ERROR LOG

Figure 42 Error Log


The display is fitted with a loop memory for the last 200 errors (referred to
hereafter as the error log). In the standard display mode, the log can be
displayed at any time with the Show error button S, and scrolled using the
knob. The most recent error recorded always appears first. All entries can
be deleted by pressing button E.

65
TEBEVERT III INVERTER SYSTEM

7.4.7 ERROR LEVEL AND CLASS

All the errors in the MCU, external monitoring devices, and SAT-Bus users
are assigned to certain error levels. These make it possible to generate a
selective error display and store it. The higher the error level, the more
serious the error.
The error levels are not programmable but are determined by the signal
filters set in the MCU.
Generally speaking, there are three classes of error:
1. Errors in the display and central signals
2. Errors in the external or internal monitoring logic
3. Errors in the SAT-Bus users.

7.4.7.1 ERROR LEVEL FOR DISPLAY AND CENTRAL FAULTS

ERROR
ERROR
LEVEL
Reception Error 02
Incorrect Command 02
Central Fault (SVC) 08
Defective MCU Connection 09
Central Fault (SVB) 09
Central Fault (SVA) 10

7.4.7.2 ERROR LEVEL FOR INTERNAL OR EXTERNAL MONITORING LOGIC

SIGNAL FILTER ERROR LEVEL


Input not free (/GEN) 00 (not error)
Release (GEN), otherwise nothing 01 (internal system status)
(GEN) and show signal (ME) 04 (e.g. service switch)
(GEN) and link with SVC 05
(GEN) and link with SVB 06
(GEN) and link with SVA 07

7.4.7.3 ERROR LEVEL FOR SAT-BUS USERS

SIGNAL FILTER ERROR LEVEL


Error Released 01 (internal system status)
(GEN) and link with SVB 06
(GEN) and link with SVA 07

66
TEBEVERT III INVERTER SYSTEM

7.4.8 ERROR LOG

The error log displays time, error level and status.

The lines of an error log:


1. +(07) 24.06.96 - 10:12 where:

"+" = "error occurred"

(07) = error level

"24..." = error time & date

2. Overvoltage unit 02 error-signal text

When an error is removed, a similar entry is generated with the time


updated and the symbol "-" to indicate "error corrected".

Example of an error log:


+(07)24.06.96 - 10:11
overvoltage unit 02
+(07)24.06.96 - 10:11
fault unit 02
+(10)24.06.96 - 10:11
***urgent error***
-(07)24.06.96 - 10:12
fault unit 02
+(01)24.06.96 - 10:12
unit 02 switched off
-(01)24.06.96 - 10:12
unit 02 switched off
-(10)24.06.96 - 10:12
***urgent error***
-(07)24.06.96 - 10:12
overvoltage unit 02

The causes of the errors are not always recorded to the exact second in
the order in which they occur, as the units, the modem board and the
display are not fully synchronized with the system statuses and some of
the fault signals in the system have delays. This explains why the "urgent
error" signal disappears first and then the overvoltage signal is cancelled
in the above example.

67
TEBEVERT III INVERTER SYSTEM

7.4.9 THE INDIVIDUAL MENUS


7.4.9.1 CONTROL MENU

Control (0)

E button

*System Control*
E button
Voltage level switchover (2) Boost Charge (2)
Float (2)
Direct (2)
battery test (2)
cancel battery test (0)
equalizing charge (2)
battery circuit test (2)
E button
Relay Test (2) Relay 1 (2)
Relay 2 (2)

Relay 10 (2)
Reset Hold Function (4)
E button
User Defined Commands (0) User Defined Command 1 (0)
User Defined Command 2 (0)
User Defined Command 3 (0)
User Defined Command 4 (0)

Figure 43 Control Menu Tree


Voltage level switchover
This menu tree is not used when the MCU is installed in an inverter.

Relay Test
The MCU can control up to 10 relays which can be tested via this menu
item. When the test is selected, the specified relay goes into the active
state for a pre-selected length of time and then returns to the inactive
state. Each relay test can be blocked separately in the MCU. In this case,
no test takes place.

Reset Hold Function


All the relays of the MCU and the LEDs on the LED board can be
configured to be self-holding (latching). This menu item causes all the
functions in self-hold to return to their initial (inactive) state, unless the
conditions for activation are still in effect. Without a display unit, the hold
functions can only be reset by special programming and an external
contact.

User Defined Commands


Four custom commands can be entered via the TEBE MCU service
software at this point, e.g. for controlling relays or setting or cancelling
signals in the MCU.

68
TEBEVERT III INVERTER SYSTEM

7.4.9.2 SETTINGS MENU

Settings (0)

E button

* Settings *
Date and time (1)
Interval Battery Test (2)
Duration Battery Test (2)
Threshold Voltage Battery Test (2) E button
Measuring Channel Battery Test (0) Voltage Battery 1 (3)
Current Battery 1 (3)
Voltage Battery 2 (3)
Current Battery 2 (3)
E button E button E button
Measuring Value Monitoring (0) Busbar Voltage (4) input measuring value * Choose Measurement *
Undefined Value 2 (3) lower threshold value inv output voltage
Undefined Value 3 (3) upper threshold value mains voltage
Undefined Value 4 (3) hysteresis static bypass outp. voltage
static bypass real power
static bypass 00 apparent po
static bypass 00 reactive power
busbar voltage
empty value
static bypass outp. curr
inverter current 01
inverter current 02
inverter current 03
inverter current 04
inverter current 05
static bypass 00 frequency
empty value
static bypass heat sink te
empty value
empty value
empty value

Figure 44 Settings Menu Tree

 Date and Time


Changes the setting of the real-time clock in the MCU 2000.

 Interval Battery Test


This menu tree is not used when the MCU is installed in an inverter.

 Duration Battery Test


This menu tree is not used when the MCU is installed in an inverter.

 Threshold Voltage Battery Test


This menu tree is not used when the MCU is installed in an inverter.

 Measuring Channel Battery Test


This menu tree is not used when the MCU is installed in an inverter.

69
TEBEVERT III INVERTER SYSTEM

 Measuring Value Monitoring


The MCU 2000 has five measurement-value monitoring features
whose parameters, lower limit value, upper limit value, hysteresis,
and the measurement value being monitored, can be altered.

In the menu you only receive access to authorized monitoring


systems which are listed with your password (e.g. "busbar voltage
< 43.2"). All the other limit-value monitoring systems are shown in
pale script, i.e. virtually invisible. Limit-value monitoring systems are
released only with a special configuration program.

Figure 45 Measuring Value Monitoring screen showing pale script

70
TEBEVERT III INVERTER SYSTEM

7.4.9.3 MEASUREMENT VALUES MENU

Contains menu items for indicating and recording the measurement values
available in the system

Measurement Values (0)

E button

* Measurement Values *
E button
Actual Measurements (0) inv output voltage
Measurement Recording (0) E button mains voltage
static bypass outp. voltage
static bypass real power
watch record (0) static bypass 00 apparent po
recording interval (2) static bypass 00 reactive power
E button E button busbar voltage
inv output voltage measurement value 1 measurements to record (2)
mains voltage E button measurement value 2 delete record (2) empty value
static bypass outp. voltage E button measurement value 3 static bypass outp. curr
static bypass real power E button measurement value 4 inverter current 01
static bypass 00 apparent po inverter current 02
static bypass 00 reactive power inverter current 03
busbar voltage inverter current 04
empty value inverter current 05
static bypass outp. curr static bypass 00 frequency
inverter current 01 empty value
inverter current 02 static bypass heat sink te
inverter current 03 empty value
inverter current 04 empty value
inverter current 05 empty value
static bypass 00 frequency
empty value
static bypass heat sink te
empty value
empty value
empty value

Figure 46 Measurement Values Menu Tree

 Actual Measurements
Indicates all the installed measurement values with their current
readings.

Figure 47 Typical Actual Measurement screen

71
TEBEVERT III INVERTER SYSTEM

 Measurement recording
Sets the parameters for the recording of measurement values in the
display. A total of 2000 measurement points can be recorded which
can be divided into as many as four measurement quantities.

 Watch record
All the recorded curves are shown scaled in a graph. This produces
a purely qualitative representation. All the measurement values can
be marked by a cursor which is moved using the turning knob. First
the designation of the measurement value is shown and then the
exact value and the time at which it was recorded.
With button E, the cursor is then moved to the next measurement
curve at the same point in time and can be shifted there as
required.

 Recording interval
Scanning interval in hours and minutes.
One minute is the minimum interval.

 Measurements to record
Up to four measurement values can be selected (including no
measurement) for recording.

 Delete record
Once recording has started, the display scrolls the values on when
the memory overflows. This command deletes all the values
recorded up to that point. Changing the recording interval or the
values to be recorded also has the effect of cancelling all the
recorded values. A Warning appears before this happens.

7.4.9.4 STATUS

Figure 48 Example status screen


The statuses at the digital inputs and the internal monitoring logic can be displayed
using the knob. The (18) shows the logical index of the status in the configuration file.
Depending on the status (active, inactive) a smiling face is displayed to indicate signals
which could cause a central fault that are not causing a fault.

72
TEBEVERT III INVERTER SYSTEM

7.4.9.5 DISPLAY
Contains menus for configuring the Display and Operating Unit.
Display (0)

E button

* Display Configuration *
Set defaults (4)
E button E button
system info (1) address 25 -.- -.- -.- -.- -.-
E button -.- -.- -.- -.- -.-
address 26
E button -.- -.- -.- -.- -.-
address 27
-.- -.- -.- -.- -.-
-.- -.- -.- -.-

E button E button
measurements to display (1) measurement value 1 * Choose Measurement *
E button
text upload from MCU (3) measurement value 2 inv output voltage
E button
measurement value 3 mains voltage
E button
measurement value 4 static bypass outp. voltage
static bypass real power
E button E button static bypass 00 apparent po
configuration flags (1) type of clock analog
escape function (1) digital
busbar voltage
backlight function (1) E button
change displayed measurem yes empty value
lock display (0)
no static bypass outp. curr
E button inverter current 01
change passwords (1) password 1 (1)
password 2 (2) inverter current 02
password 3 (3) inverter current 03
password 4 (4) inverter current 04
inverter current 05
static bypass 00 frequency
empty value
static bypass heat sink te
empty value
empty value
empty value

Figure 49 Display Menu Tree

 Set Defaults
All programmable settings in the display are set to their default
values, e.g. Measurement value standard display, language,
waiting times and settings for the recording of measurement values,
passwords. All the programmed texts and passwords are retained.

 Systeminfo
All the addresses of system units which are in use are displayed
with a symbol for the unit in question. Using button E, a list of the
load distributions is shown under the rectifier units (in A). This
menu item is not used when MCU is installed in an inverter.

 Measurements to display
The top display shows 0 - 4 measurement values permanently.
This setting can be used to determine how many and which values
are dis-played. It is possible to display all the measurement values
in the system which are permanently accessible.

73
TEBEVERT III INVERTER SYSTEM

 Text upload from MCU


For all the measurement values and signals, identification codes
are stored in the MCU. These are transmitted with the signal
protocol. These can be loaded in the display. This cancels the texts
previously programmed in the display. A warning text informs the
user before this happens. Use this item with caution as system is
programmed with user friendly long text names. Default text
uploaded from MCU is highly abbreviated.

 Configuration flags
These are for configurations which require a choice between two
possibilities.
Type of clock
Possible settings: analogue 08.07.96
digital 19:00-08.07.96
If more than two measurement values appear in the basic display,
the digital form is always used for the time.

 Escape function
If no key is pressed, the display returns from any sub-menu to the
main menu after the time entered here in seconds (0-240). The
setting "0" prevents returning to the main display.

 Backlight function
The background lighting of the display is switched on automatically
when a key is pressed. The display lighting goes off after a certain
time if not key has been pressed. This time can be set here
between 10 and 240 seconds.

 Lock Display
The individual menu items are protected by four different password
levels. When the correct password is given, a certain level (1-4) is
released for the user. This menu item is used for setting the level to
0 again, thus blocking all the levels requiring a password. If the
display is locked, a small key symbol appears in the status line.
When a period of two hours has expired after the last operation, the
system locks itself automatically.
Four password levels are used by this MCU: "PW 1", "PW 2", PW
3", and "PW 4". (PW and the number are separated by a space).

 Change passwords
The four passwords can be changed here. The menu entry in each
case is protected with the appropriate password level.
Thus, the password for level 3 can only be changed when a
password for level 3 or 4 is entered beforehand.

74
TEBEVERT III INVERTER SYSTEM

7.4.9.6 MENU LANGUAGE

This item selects one of four languages for menu texts


 German
 English
 French
 user-defined language
The texts for the measurement values and signals are not shown in four
languages as these are user defined (and generally system-specific).

7.4.9.7 SYSTEM SETUP


Menus for editing the system parameters in the MCU 2000

Sytem Setup (0)

E button

* Select System Components *


MCU mainboard (0) E button * Settings Mainboard *
rectifier modules (0) Modem initialization (4)
Thysat (0) dial command (3)
first calling number (3)
second calling number (3)
passwords (0)
site identification (4)
delays (0) E button
duration of modem connect (2)
number of battery cells (3) wait at busy line (3)
delay urgent alarm (2)
delay non urgent alarm (2)
delay common alarm (2)
duration relays test (1)

options (0) E button


control modem (2)
time of last configuration (0) automatic battery test (2)
b-test for 2 batteries (3)

Figure 50 System setup Menu Tree


7.4.9.7.1 MCU MAINBOARD
 Modem Initialization
Edits the AT command string for initialising the telephone modem.
This text contains information on the communication between MCU
and modem as well as between modem and modem. The specified
command sequence should only be altered by persons with a
sound knowledge of remote data transmission. Incorrect entries
may impair the transmission of data or make it completely
impossible.

75
TEBEVERT III INVERTER SYSTEM

 Dial command
Determines the prefix AT command which is sent to the modem
before the actual dialing number.
Examples:
ATDT AT initiates every modem command.
D is for „dial‟.
T is for „tone‟. The modem dials using the tone-dialing process
(sometimes known as multi-frequency dialing process).

ATDP As above. P stands for pulse-dialing process (or impulse-


dialing process).

ATDT9W A zero is dialed before the number followed by a


delay of approximately 1 sec. This command is typical for a private
branch exchange where a "9" has to be dialed first to obtain an
external line.

 First calling number


States the complete telephone number of the central computer.
This number is dialed by the MCU in cases of fault or error or call-
back request. If this entry is left empty, the unit does not call.

 Second calling number


States the alternative telephone number for the central computer. If
no contact can be made with the first number (engaged or no
reply), the second number is dialed. From this point onwards it is
dialed first until it also fails to make contact.
If no entry is made here, the first number is always dialed.

 Passwords
Changes the four passwords stored in the MCU. One of these
controls access to the central computer and the other three the
access entitlement in the case of alternatively-routed calls (external
interrogation). The password for a central-computer interrogation is
transmitted with every interrogation from the PC and is generally
fixed there. If this password is changed in the MCU, no further
interrogation of the unit is possible.

76
TEBEVERT III INVERTER SYSTEM

 Site identification
The central location identifies the unit calling and its protocol by
means of this text.
The identification must fulfill two conditions:
1. It must be clearly attributable to each unit, i.e. different in
each case
2. The entry in the central computer must correspond to the
identification selected (even in choice of upper or lower-case
letters).

 Delays
In the MCU, several delays are used for the program sequence.
Some of these can be altered here to suit individual requirements.
Duration of modem connect - Determines the length of time the
MCU maintains contact to the PC after a protocol has been
transmitted without the user sending any further interrogation to the
MCU.
Wait at busy line - If the number is engaged when the MCU dials
the central computer, the call is repeated up to seven times. The
time interval is fixed here in seconds.
Delay urgent alarm – Time in seconds between when the MCU
senses an urgent alarm and when it is reported.
Delay non urgent alarm – Time in seconds between when the MCU
senses a non urgent alarm and when it is reported.
Delay common alarm – Time in seconds between when the MCU
senses a common alarm and when it is reported.
Duration relays test – Determines the length of time the relay
remains in the active state after a relay test is activated, before it is
set back to its normal function.

 No of battery cells
Some of the settings in the MCU relate to the number of battery
cells. The appropriate number is entered here. This menu item is
not used when the MCU is installed in an inverter.

 Options
Authorizes or blocks optional functions of the MCU.
Control modem - Authorizes or blocks remote data transmission by
the modem.
Automatic battery test - Authorizes or blocks the automatic battery
test.
B-test for two batteries - Authorizes or blocks the extended battery
test for two batteries.

77
TEBEVERT III INVERTER SYSTEM

 Time of last configuration


Records date and time the settings were last changed.

7.4.9.7.2 Rectifier Modules


This menu item is not used when MCU is installed in an inverter.

7.4.9.7.3 Thysat
This menu item is not used when MCU is installed in an inverter.

7.5 ALARMS & INDICATORS


There are 11 dry “C” Contact external alarm outputs. The contact ratings,
individual alarm definitions, and connection points are detailed in Section
5.3.3. The alarms which trigger the Major and Minor alarms and light the
System LEDs Alarm Active, Urgent Alarm Active respectively are:

Minor - Static Bypass Switch module warning, System Overload, Inverter


module turned off, Inverter module fail;

Major - AC Output MCB Open, Static Bypass Switch fault, Static Bypass
Switch output voltage alarm, Commercial AC Bypass not acceptable,
Operating on Commercial AC Bypass, DC Bus Voltage Low (<43.2V),
Multiple Inverter module failures.

The vertical LED strip with 13 programmable LED indicators is shown


below. A green pushbutton (PB) below the strip serves as a Reset/Test
LED PB for clearing indications and alarms where the LED is flashing to
indicate that the status has returned to normal. If the PB is held down for
a few seconds, all LEDs should light to indicate none have failed.

78
TEBEVERT III INVERTER SYSTEM

Figure 41 Operator Panel LED Indicator Strip

7.6 REMOTE MONITORING


The remote monitoring option requires the addition of a remote monitoring
adaptor, necessary interconnect cable from MCU to adaptor, and a MIB.
The kit can be installed at time of order of the system or for field retrofit.
See Figure 4. It is available optionally in two formats.

The first format consists of a web-based function using TCP/IP by


accessing the MCU with a LAN connection. A standard format of
parametric information and alarms is available as a web page. The
customer must assign his own IP address for the particular site and
system. This can be done remotely on the LAN. The default IP address for
initial access is 10.10.10.10. The password required to modify this
address is password “benning”. See TCP-IP Adaptor manual 4618 for
details. Once set up, an engineer at his desk can conveniently go on-line
and monitor the system.

The second format is SNMP and requires the MIB and central site
software for communicating remotely with the adaptor and decoding the
MIB data (central site software is not supplied by Benning).

79
TEBEVERT III INVERTER SYSTEM

8 MAINTENANCE
All the components of the inverter system have been developed for
continuous operation and are practically maintenance-free. To ensure
continuous operation, it is recommended that the flow of cooling air is
periodically checked and any dust is removed from the units.

Warning!
Do not use pressurized air to remove the dust since the
dust particles can be blown into the interior of the unit and
may cause malfunctions.

If servicing is required (exchange of units, work on the mains supply or the


DC supply etc.), the proper position of the manual Maintenance Bypass
Switch must be verified.

8.1 USE OF THE MANUAL BYPASS SWITCH (MBS)


The MBS is only required for servicing. This manual switch when operated
bypasses the SBS unit and connects, without interruption, the AC Back-up
source, AC Mains or Gen Set, (“Load on Bypass Input”) or the Inverter
Output (“Load on Inverter Output ") directly to the connected load
equipment, depending on the MBS switch position.

Warning!
The manual Maintenance Bypass Switch may only be
operated by qualified personnel.

0 Position 0: UPS operation

Position 1: Load on Back-up AC Input


1 2 Position 2: Load on Inverter Output

Prior to operating the MBS, verify that the SBS is operating in one of the
following modes. Failure to do so could result in an interruption in power to
the connected load equipment:

80
TEBEVERT III INVERTER SYSTEM

1) The SBS is operating correctly

This is signalled on the front panel of the SBS by:

LED "off" LED "on"

In this operating state, the MBS can be switched either into Position 1
(Load on Bypass AC Input) or Position 2 (Load on Inverter Output). After
the service work is complete, and, if the system is in proper working order,
the MBS can be turned back to Position 0 (UPS operation).

2) The SBS shows a fault

This is signalled on the front panel of the SBS by:

LED "on" LED "off"

In this operating state, two further cases must be differentiated.

a) The inverter system is operating in the inverter operation mode.

This is the case when the LED on the front panel of the
SBS is lit.

In this case only MBS switch Position 2 (Load on Inverter Output) is


permissible!

After the servicing work is complete (exchange of the SBS, work on the
AC supply mains) and if the system is in proper working order, the Manual
Bypass Switch can be turned back to Position 0 (UPS operation).

b) The inverter system is working in the mains operation mode. This is

the case if the LED on the front panel of the SBS is lit.

In this case only MBS switch Position 1 (Load on Bypass Input) is


permissible!

After the service work has been completed (e.g., exchange of SBS, work
on DC supply mains, or repair of Inverter) and if the system is in proper
working order, the MBS switch can be returned to Position 0 (UPS
operation).

81
TEBEVERT III INVERTER SYSTEM

The states of the MBS switch Positions 1 (Load on Bypass Input) or 2


(Load on Inverter Output) are indicated by two flashing LEDs on the SBS
front panel as shown below.

Figure 51 MBS State: "Load on Bypass AC Input"

Figure 52 MBS State: "Load on Inverter Output"

8.2 EXCHANGE OF MODULES


a) Exchange of an Inverter Module

In this case, the Manual Bypass Switch does not need to be used.
However, if this is desired for any reason, the MBS must be switched to
Position 1 (Load on Bypass Input).

Removal of an Inverter Module:

Switch the inverter off using the front panel ON/OFF switch (if the
remaining inverters in the system cannot take over the load, the
SBS will transfer the connected load to the mains supply).

Remove the four retaining screws.

Pull the unit out of the front of the cabinet.


(Attention! See warning statement in paragraph 4.4.2)

Insertion of the replacement Inverter Module:

The replacement inverter module must be switched off!

82
TEBEVERT III INVERTER SYSTEM

The circuit breaker (F1) on the rear of the module must be


switched on!

Slide the inverter module into the inverter shelf firmly until the
unit is flush with the frame of the cabinet.

Screw in the four retaining screws.

Switch the inverter on.

If necessary, turn the MBS to position 0 (UPS operation).

b) Exchange of the SBS module

Warning!
The Manual Bypass Switch must be used in this case
otherwise there will be an interruption in the power supply
to the load equipment. It must be established beforehand,
which of the scenarios described in Section 8.1 is valid
(check the state of the SBS and the operation mode!)

Removal of the SBS:

After the MBS has been turned to Position 1 or 2 record the position of the
switch. The 4 retaining screws are removed and the SBS is pulled out of
the front of the cabinet. This simultaneously removes the operating
element of the MBS from its mounting shaft. The MBS is mechanically
fastened to the SBS.

Insertion of the SBS:

If not already done, the bypass handle assembly must be mounted onto
the new SBS. Before the SBS is replaced into the cabinet, the operating
element of the Manual Bypass Switch must be turned to position 1 or 2,
according to the position of the switch before the SBS was removed. The
SBS is pushed into the free slot until the unit is flush with the frame of the
cabinet. The four retaining screws are screwed back in. Finally, the MBS
must be turned back to position 0 (UPS operation).

83
TEBEVERT III INVERTER SYSTEM

8.3 INCREASING SYSTEM CAPACITY


The inverter system can be equipped with a maximum of five inverter
modules. Additional modules can be added to the system if there are
unused inverter shelves. The system can be upgraded during running
operations without the need to switch off other components or the need to
put the system into Bypass Mode via the MBS. Following is the expansion
procedure. It is assumed that the DC input cable and upstream breaker or
fuse have been installed for the inverter shelf to be used.

1. Although these modules are hot-swappable, it is best to have the


upstream DC input breaker in the OFF position (or fuse removed) until
the module has been installed and secured.

2. Remove the module shelf coverplate(s) as required.

3. Refer to Figure 9. Ensure that the ON/OFF Switch S1 on the front


panel is in the OFF position.

4. Refer to Figure 11. Switch Circuit Breaker F1 located on the rear of the
new inverter module(s) to the ON (1) position.

5. Insert the new inverter module firmly into the shelf until it is flush with
the other module front panels, securing it with the four retaining screws
used for the coverplate. CAUTION: modules weigh 77lb (35kg).

6. Close the upstream breaker/fuse feeding the new module.

7. Set Switch S1 to the ON position.

After the module‟s internal start-up sequence is complete, the inverter is


brought into parallel operation automatically and the load current is then
evenly distributed between all inverter modules that are in operation.

8.4 SERVICE SOFTWARE


System management and troubleshooting can be carried out via the MCU
service software. TEBE MCU Service Software is available for field
service. It installs typically in a laptop computer which requires a null
modem cable to interconnect with the RS-232 service port on the MCU.
Only trained service staff should use this software as inadvertent changes
to settings can affect system operation. Contact factory for further
information. Reference TEBE MCU Service Manual 028-0008-030.

84
TEBEVERT III INVERTER SYSTEM

8.5 SERVICE SUPPORT

For technical support and information on Tebevert III Inverter Systems or


other products within our product range please contact:

Benning Power Electronics


1220 Presidential Drive, Suite 100
Richardson, TX 75081 USA
www.benning.us
1 800-910-3601 option 1

If you require a system check at regular intervals for safety reasons, e.g.
an annual inspection, please contact us. We will be pleased to submit a
quotation for an appropriate contract.

9 SPARE PARTS

Benning Part Description


Part
Number
5kVA Tebevert III inverter module, -48VDC
120325 input, 120VAC single phase output, CLEI:
PIIVM00GAA
25kVA 120VAC single phase Static Bypass
120416 Switch module, CLEI: PIIVN00GAA

85
TEBEVERT III INVERTER SYSTEM

APPENDIX A – PART NUMBERS


The high level part number beginning with BLI represents 11 variables A, V, B, X, C, D,
E, F, G, H, and J. The table below describes each variable.
BLI AVBXCDEFGHJ
Variable Description
A System Capacity (SBS Module)
2 25kVA System (SBS), 120 VAC
4 25kVA System (SBS), 230 VAC

V Cabinet Type
0 7ft Zone 0 Cabinet - Top Entry, 600mm deep
1 7ft Zone 0 Cabinet - Bottom Entry, 600mm deep
2 7ft Zone 0 Cabinet - Top Entry, 800mm deep
3 7ft Zone 4 Cabinet - Top Entry, 600mm deep
4 7ft Zone 4 Cabinet - Bottom Entry, 600mm deep
5 7ft Zone 4 Cabinet - Top Entry, 800mm deep
6 7ft NEBS L3, Zone 4 Cabinet - Top Entry
7 7ft NEBS L3, Zone 4 Cabinet -Bottom Entry

B Inverter Type
2 5kVA Inverter Shelf, 120 VAC
4 5kVA Inverter Shelf, 230 VAC

X Quantity of Inverter Shelves


1-5 # of Inverter Shelves (always 5)

C DC Input Options
1 Individual DIN Rail Terminal Blocks
2 Individual 2-Hole Busbars
3 Bulk DC Input
4 Bulk A/B Input with isolation diodes (non-UL)

86
TEBEVERT III INVERTER SYSTEM

BLI AVBXCDEFGHJ
D AC Bypass Voltage Options
0 120VAC (L/N)
1 120/240VAC (L1/N/L2)
2 208VAC (L1/L2)
3 220VAC (L1/L2)
4 230VAC (L/N) (25 kVA Versions ONLY)
5 240VAC (L1/L2)
6 480VAC (L1/L2)

E AC Output Voltage Options


0 120VAC (L/N)
1 120/240VAC (L1/N/L2)
2 115/230VAC (L1/N/L2)
3 230VAC (L/N) (25 kVA Versions ONLY)
4 110/220 VAC (L1/N/L2) non-UL

F AC Output Termination Options


0 Bulk DIN Rail Terminal Blocks
1 DIN Rail Mounted QL Type Breaker option, less breakers (24 Position)
2 125 A Output Circuit Breaker option, 120 VAC output, 12.5 kVA system
3 70 A Output Circuit Breaker option, 120/240 VAC output, 12.5 kVA system
4 250 A Output Circuit Breaker option, 120 VAC output, 25 kVA system
5 125 A Output Circuit Breaker option, 120/240 VAC output, 25 kVA system
6 North American Snap-In Breaker option, less breakers (20 Position)

87
TEBEVERT III INVERTER SYSTEM

BLI AVBXCDEFGHJ
G Communications Options
0 Standard Communications Option
1 Base MCU Monitoring Unit
2 Base MCU with TC/PIP
3 Base MCU with SNMP
4 Base MCU Monitoring Unit and MCU 2000 display
5 Base MCU, MCU 2000 display and TC/PIP
6 Base MCU, MCU 2000 display and SNMP (Preferred)
A Standard Communications Option - (120VDC High Voltage Option)
B Base MCU Monitoring Unit (120VDC High Voltage Option)
C Base MCU with TC/PIP (120VDC High Voltage Option)
D Base MCU with SNMP (120VDC High Voltage Option)
E Base MCU Monitoring Unit and MCU 2000 display (120VDC High Voltage
Option)
F Base MCU, MCU 2000 display and TC/PIP (120VDC High Voltage Option)
G Base MCU, MCU 2000 display and SNMP (120VDC High Voltage Option)

H Relay Box option


1 Relay Box
A Relay Box (120VDC High Voltage Option)

J Branded
0 Benning

88
TEBEVERT III INVERTER SYSTEM

APPENDIX B - PERFORMANCE TESTING


It is recommended that the following testing be performed by
Benning field service personnel. Doing so will add an additional year
of warranty on this system.

B.1 PRELIMINARIES TO PERFORMANCE TEST


The site manager must be informed of the test to be performed, and that
alarms will be sent (if connected) to the local Building Alarm Center and/or
Network Operations Center.

Warning!

During the performance test, pay attention to all safety


notes located in Section 1. In addition, these inverters may
be fed from multiple power sources, so additional
precautions must be taken.

Take off rings, wristwatches and similar objects that may cause short-
circuits.

Always use ESD-protection for any work to be carried out inside the
cabinet.

B.2 TEST EQUIPMENT REQUIRED


 A suitable voltmeter with measuring range 250 VAC, 100 mV and
60 VDC.

 A clamp-on ammeter capable of measuring 250Amps AC.

 A load bank capable of supplying 26,000 W load.

B.3 TEST OF THE INVERTER MODULES


Make sure the system is in the following state:

 Disconnect commercial AC from the AC by-pass input.

 Switch off all inverter modules.

 Disconnect the load from the inverter.

 Connect the load bank to the output of the inverter system.

 Apply an ammeter around the phase conductor to the load bank.

89
TEBEVERT III INVERTER SYSTEM

B.3.1 INVERTER TEST ACTIVITIES


Action Result

Switch on one of the inverter modules. The green LED “OUTPUT VOLTAGE
AVAILABLE” lights up. The green LED
“PARALLEL OPERATION” starts
flashing on the inverter. The red LED
“FAULT” on the by-pass lights up
indicating there is no mains voltage
present and that not all connected
inverters are not operating. Also an
outgoing alarm will be given.

Connect a load of approximately 2kW The reading of the voltmeter and of the
(2.5kVA modules) or 4kW (5.0kVA display shall read 120 or 120/240VAC,
modules). Switch the volt/ammeter  5%. (See Important Note below)
toggle switch on the by-pass module to
“V”. Connect a voltmeter to the output
of the inverter system.

Switch the volt/ammeter toggle switch The volt/ammeter and the clamp-on
on the by-pass module to “A” ammeter shall be the same ±5%.

Connect a load of approximately 3kW The red LEDs “OVERLOAD” light up on


(2.5kVA modules) or 6kW (5.0kVA inverter and SBS modules. The internal
modules) temperature will rise and the inverter
module will automatically switch off.

Disconnect the load bank and re-start The green LEDs “OUTPUT VOLTAGE
the inverter by means of the On/Off AVAILABLE” and PARALLEL
Switch. OPERATION” will light up.

1. WARNING! Verify the commercial The inverter system shall pass into
AC input to the AC by-pass is current limit and shall automatically
turned-off. switch off after approximately 40 to 50
seconds.
2. Switch off the inverter.

3. Short circuit the output of the


inverter system by connecting a cable
across the output terminals.The cable
shall be the same gauge as the normal
load cables.

4. Switch on the inverter.

Remove the short circuit and restart The inverter restarts


the inverter module by means of the
On/Off switch.

Switch off the inverter module The inverter shuts off.

90
TEBEVERT III INVERTER SYSTEM

Important Note!
The 120/240VAC configuration utilizes input/output
transformers to convert the input and output voltages from
the nominal 120VAC. Therefore the voltage displayed on
Digital Voltmeter shall display the 120VAC component only.

Repeat tests in Section 6.3.1 for each inverter module installed.

B.4 TEST OF THE SBS MODULE


Make sure the system is in the following state:

 Disconnect the load from the inverter system.

 Connect the load bank to the output of the inverter system.

 Connect the commercial AC mains to the AC bypass input.

 Switch on all inverter modules.

91
TEBEVERT III INVERTER SYSTEM

B.4.1 SBS TEST ACTIVITIES


Action Result

Switch off the mains from the by-pass. The green LED “MAIN VOLTAGE
AVAILABLE” and “READY FOR
OPERATION” go out and the red LED
“FAULT” lights up. Also an outgoing
alarm shall be given after approximately
10 seconds.

Connect a voltmeter to the output of The reading of the voltmeter and of the
the inverter system. display shall read 120VAC  5%. (See
Important Note below)

Switch on the mains for the bypass The green LED “MAINS AVAILABLE”,
“INVERTER OPERATION” light up and
the red LED “FAULT” goes out. The
reading of the by-pass volt/ammeter
shall be 120 or 120/240VAC  10%. The
alarm ceases.

Switch off all inverter modules. The green LEDs “INVERTER VOLTAGE
AVAILABLE” and “INVERTER
OPERATION go out, the green LED
“MAINS OPERATION” lights up and the
red LED “FAULT” lights up. Also and
outgoing alarm will be given.

Connect a voltmeter to the output of The reading of the voltmeter shall be 120
the inverter system. or 120/240VAC  5%.

Switch on all inverter modules. The green LEDs “INVERTER VOLTAGE


AVAILABLE”, “INVERTER OPERATION”
and “READY FOR OPERATION light up,
and the green LED “MAINS
OPERATION” and the red LED “FAULT”
go out. The alarm ceases.

Important Note!
The 120/240VAC configuration utilizes input/output
transformers to convert the input and output voltages from
the nominal 120VAC. Therefore the voltage displayed on
Digital Voltmeter shall display the 120VAC component only.

92
TEBEVERT III INVERTER SYSTEM

B.5 FINAL STEPS


 Disconnect any test equipment that has been connected to the
system and make sure that materials that do not belong in the
equipment have been removed.

 Restore the equipment to its original condition. Make sure the


cabinet is placed so that cooling air has free access.

 If a failure remains in the equipment, contact the responsible field


engineer.

93
TEBEVERT III INVERTER SYSTEM

APPENDIX C - DRAWINGS
The following drawings are provided for reference only.

C.1 902-0106-306 SH 1 OF 4 INPUT OUTPUT SCHEMATIC

94
TEBEVERT III INVERTER SYSTEM

C.2 902-0106-306 SH 2 OF 4 SBS SCHEMATIC

95
TEBEVERT III INVERTER SYSTEM

C.3 902-0106-306 SH 3 OF 4 AC INPUT & OUTPUT OPTIONS

96
TEBEVERT III INVERTER SYSTEM

C.4 902-0106-306 SH 4 OF 4 ALARM AND MCU WIRING

97
TEBEVERT III INVERTER SYSTEM

NOTES

98
TEBEVERT III INVERTER SYSTEM

NOTES

99
Benning Power Electronics
1220 Presidential Drive Suite 100
Richardson, TX 75081 USA
www.benning.us
800.910.3601

This manual contains important safety


instructions that should be followed
during installation and maintenance of
the Power System.

Вам также может понравиться