Maintenance Practices in Cement Industry

Article

CITATIONS READS
5 7,216

1 author:

Hani Shafeek
King Abdulaziz University
27 PUBLICATIONS   187 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Engineering Laboratories Design, Construction, and Renovation: Participants, Process, and Product View project

ISO9001-2008 in Emerging Faculties View project

All content following this page was uploaded by Hani Shafeek on 27 December 2015.

The user has requested enhancement of the downloaded file.


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

Maintenance Practices in Cement Industry


Hani Shafeek
Faculty of Engineering ,Industrial Engineering Department
, King Abdulaziz University, Rabigh Branch, KSA
Faculty of Industrial Education, Suez Canal University, Egypt
Hanishafeek@yahoo.com

Abstract main ways: decreasing expenses and


increasing capacity. Maintenance costs consist
This paper analyzes an existing of two main divisions, labor and material. By
maintenance management system in a cement achieving maximum availability (minimum
factory in the Kingdom of Saudi Arabia using downtime) and efficiency from plant assets, a
a modified questionnaire. The analysis shows manager ensures that a company does not
that there are strong areas such as predictive need to invest in excess assets to produce its
maintenance and maintenance automation. products. Benchmarking is a continuous
Other areas are found weak such as training improvement tool; it should only be started if
programs and maintenance reporting. Some the company wants to make changes to
areas are found mix between strong and weak maintenance improvement.
such as maintenance documentation, and
maintenance planning and scheduling. This Khan and Darrab [1] reported that the
paper is an assessment initiative for purpose of maintenance is not only to upkeep
maintenance and productivity continuous the plant machinery and equipments
improvement and can be integrated as a part of preventing from failure and breakdowns,
a decision support system for maintenance increasing reliability, maintainability, and
management. availability of the operating system for
maximizing production, but also to improve
Scope quality and boost higher productivity through
improving capacity, faster and more
The performance measurement is aimed dependable throughput, reducing inventory,
to determine the missed practices in order to and lowering operating cost.Al-Sultan [2]
achieve further productivity improvement in investigated the there has been some research
cement industry. Furthermore, the research on maintenance management and practice in
push the management to adopt best practices Saudi Arabia, but it remains very limited
to remove the waste of the overall process. because most of it is written from a
practitioner’s prospective and very few
Keywords: Maintenance practices; Survey; articles focus on sound scientific solutions to
Questionnaire; Cement industry maintenance problems. Ikhwan et al. [3]
showed that a proper maintenance practice is
1. Introduction needed and more university-industry
interaction in the field of maintenance in
Because maintenance expenditures make up Saudi Arabia becomes necessary. Al-Saggaf
a percentage of production costs, attention is [4] investigated the case study of SCECO-
being turned to maintenance. Many companies EAST’s (Saudia Arabia) experts in
have tried to use standard production methods implementation of TQM to distribution
to control maintenance. This is not successful. substation (S/S) maintenance [5] and
The maintenance can increase profits in two investigated the developing training programs

Jan 2012 ATE-70115068©Asian-Transactions 10


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

for machine operation, thereby reduced the which the performance indicators can be
operational errors in Saudi Arabia. Bob [6] presented:
reported that wasted energy from poorly
maintained compressed air systems cost US 1. Economic ratios (as that in Table 1), which
industry up to $3.2 billion annually. Alsyouf allow the follow-up of the evolution of
[7] showed in a case study that at least 14% of internal results and certain comparisons
potential improvement in return on investment between maintenance services of similar
are directed to contribution of maintenance plants.
functions to lost profit, which is due to 2. Technical ratios, which give the
unplanned stoppages and bad quality caused maintenance manager the means of
by maintenance related problems. Blanchard following the technical performance of the
[8] demonstrated that a large percentage (e.g. installations.
70% for some systems) of total life cycle cost
for a given system is attributed to operating Some ratios are linked to maintenance
and maintenance activities. De Groote [9] costs. Among those are the economic ratios
investigated two categories of ratios under which seem to be the most representative and
have been chosen and customized hereafter.
Table 1. Surveys in Europe in cement industry.

Economic Ratio Value


Direct maintenance cost/Added value of production 12.90
Direct maintenance cost/Replacement value of assets 16.40
Cost of maintenance personnel/Direct maintenance cost 39.75
Cost of subcontracting/Direct maintenance cost 14.00
Cost of spare parts and current maintenance items/Direct maintenance cost 42.64
Average stock value/Replacement value of production equipment 09.80
Maintenance workforce/Total plant workforce 28.40
Downtime/Hours theoretically available for production on yearly basis 05.94
Number of stock-outs/Total items in stock 06.99

Salonen and Deleryd [10] reported that to rapid turnover of all jobs, reduces in-
companies often try to optimize their process inventory and decreases utilization of
maintenance using the ratio between resource. Alsyouf [12] investigated the case
preventive and corrective maintenance study the maintenance is no longer a cost
(PM/CM) as a key performance indicator. One centre, but it can be a profit generating
problem with this approach is that some function, especially in similar types of
companies increase the amount of PM industry where the downtime cost is high.
haphazardly, regardless of whether the PM has Mostafa [13] reported that although
the desired effect or not. Chen [11] reported maintenance is one of the oldest jobs in the
that once maintenance is performed, the job Egyptian industry, it has not progressed much
being processed must be stopped. This will through the years. In order to examine the
result in some jobs being late or tardy and a state of maintenance practice, we should
relatively larger flow time is generated. It is consider two main factors: the management
known that minimizing total flow time leads side of maintenance and the technology used.

Jan 2012 ATE-70115068©Asian-Transactions 11


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

Sharma et al. [14] investigated the optimal Mexican workforce and foreign investment
system maintenance policy that may be the and technology on the border region between
one which either minimizes system the United States and Mexico. Chang and
maintenance cost rate or maximizes the Wang [24] investigated the significant human
system reliability measures. Chen [15] risk factors in aircraft maintenance technicians
investigated a developed procedure to find the in the airline industry. Ahuja and Khamba [25]
sequence that minimizes the total setup time investigated the effectiveness and
and to minimize the completion time with implementation of the TPM program for a
maintenance schedule in a manufacturing steel manufacturing unit, and highlight the
system. Chinese and Ghirardo [16] contributions made by strategic TPM
investigated the maintenance performance. An initiatives in a typical Indian manufacturing
interesting finding is that no direct correlation organization.
between firms’ size and maintenance It is clear from the previous review and up
performance could be observed. Good results to the author knowledge that there is a
are equivalently reported by smaller and larger shortage in researches on continuous
firms and therefore seem not a matter of size. improvement of maintenance management and
Ahuja and Kumar [17] reported that one practice. A survey of maintenance practices is
approach to improve the performance of presented based on maintenance management
maintenance activities is to implement a total in cement factories in Saudi Arabia. The study
productive maintenance (TPM) system. TPM investigates the effect of different parameters
is considered to be an effective strategic on maintenance continuous improvement.
improvement initiative for improving quality
in maintenance engineering activities. Reis 2. Measurements and Methodology
[18] investigated the aims to promote
knowledge on issues related to maintenance, Industrial sector is growing and heavy
i.e. the behavior of manufacturing companies industry remains a driving force in Saudi
that consider maintenance as a source of Arabia. According to Ministry of Commerce
competitive advantage and maintenance & Industry recorded more than 4561
managers’ perception of planning when they Productive Factories Until 2009 Classified by
undertake certain practices in this area. Kans 22 Industrial Activity, employing about
[19] investigated the survey of computerized 519788 people and Finance by 399321 Million
maintenance support which reveals a focus on S.R. Ministry of Commerce & Industry data
maintenance management information show that manufacture of refined oil products,
technology. Vassilakis [20] reported that which involve 81firms employing about
maintenance is a process in its own right, thus 24595 people and finance by 153819 Million
it requires understanding, control and needs SR. Saudi Arabia faces a particular human
improvement. Aoudia et al. [21] investigated development challenge that involves a gradual
the recommended necessary improvements to shift away from dependence on expatriate
maintenance. They reported that it is not labor. The economy has gradually reduced
sufficient to demonstrate the negative impact dependence on oil revenues by diversifying
of ineffective maintenance management on a into export industries such as metals, plastics,
company, but it is also essential to identify its chemicals and cement.Saudi Arabia
causes. Lamptey et al. [22] investigated a case developmental policies and plans are outlined
study for optimizing decisions on the best in a five-year national plan that guides public
combination of preventive maintenance by investments. The eighth five-year
using the questionnaire survey. Dowlatshahi development plan (2005-2009) addresses
[23] investigated the role of industrial many of the challenges as: supporting private
maintenance in the maquiladora industry. sector investment as the driver of future
Maquiladora industry is a system utilizes growth and promoting further diversification

Jan 2012 ATE-70115068©Asian-Transactions 12


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

away from heavy reliance on natural kiln, which is over half the length of a
resources, particularly oil and natural gas, football field and 4.2 meters in diameter. In
avoiding negative impacts on the environment, the kiln, the powder is heated to 1500
particularly water resources.By reviewing degrees Celsius. This creates a new
practicing maintenance as a continuous product, called clinker, which resembles
improvement tool for the companies those pellets about the size of marbles.
strive to achieve superior performance in their 4. The clinker is combined with small amounts
respective market. It is found that there are of gypsum and limestone and finely ground
limitations with heavy industry, especially the in a finishing mill. The mill is a large
cement industry. Therefore, the study focuses revolving cylinder containing 250 tons of
on cement industry. The main objective is the steel balls that is driven by a 4000 hp
descriptive application of a maintenance motor. The finished cement is ground so
questionnaire in order to continuously fine that it can pass through a sieve that
improve the cement factories. The link will hold water.
between maintenance practices and production 5. The cement manufacturing process consists
features of firms is very important. The survey of many simultaneous and continuous
was a result of cooperation with industrial operations using some of the largest
sector. The questionnaire was tested through moving machinery in manufacturing. Over
discussions with maintenance consultants. The 5000 sensors and 50 computers allow the
survey consists of 150 questions in 15 areas to entire operation to be controlled by a single
be answered by maintenance manager in the operator from a central control room.
cement company. A special check list was
used to test if the questionnaire covers all 2.2. Maintenance in cement industry
necessary maintenance areas in cement
industry. High productivity at the modern cement
plant is highly dependent on regular,
2.1. Cement manufacturing process scheduled maintenance. This requires
planning, to ensure that company staff always
Cement manufacturing industry is identified have the knowledge, manpower and parts on
by North American Industry Classification hand to give equipment the attention it needs
System (NAICS) code 32731 (formerly when it’s due for scheduled maintenance. The
identified as SIC code 3241). The procedure primary maintenance approach is to do what
of cement making follows: necessary to keep the equipment running with
maximum production. Maintenance include
1. The cement manufacturing process begins elements such as motor and bearing
when limestone, the basic raw material lubrication, motor belt replacement, fan blade
used to make cement, is transported by rail cleaning, fan wheel balancing, and
to the Edmonton plant from the Cadomin compressed air system maintenance.
limestone quarry 220 kilometers west of
Edmonton. 2.3. Data collection
2. The limestone is combined with clay,
ground in a crusher and fed into the Cement companies are the target of this
additive silos. Sand, iron and bottom ash study. The study included famous (large and
are then combined with the limestone and known) cement company in Saudi Arabia. To
clay in a carefully controlled mixture conduct the survey questionnaire was
which is ground into a fine powder in a delivered to these companies including field
2000 hp roller mill. visits, E-Mail and Fax. The purpose of data
3. Next, the fine powder is heated as it passes collection is to obtain information about
through the Pre-Heater Tower into a large maintenance in cement industry to keep on

Jan 2012 ATE-70115068©Asian-Transactions 13


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

record, to make decisions about important companies. The companies use the preventive
issues in maintenance and to pass contusions maintenance program includes lubrication
improvement information on to analyses stage. checklists and inspection checklist. Some
Questionnaire design depends on keeping the diagnostic procedures such as heat, oil and
questionnaire as short as possible. Use simple vibration analysis are used. There is a specific
and clearly worded questions. Start with personnel execute preventive maintenance on
demographic questions to help respondents get each crew. The preventive maintenance results
started comfortably. Use dichotomous are checked annually for material cost and
(yes/no) and multiple choice questions. Use time. Corrective action work orders are
open-ended questions cautiously. Avoid using generate from the inspection plane. The
leading-questions. The questionnaire was inspections tasks include safety information,
designed with structured questions in which material requirements, time and number of
the respondent could choose an answer from a labors. The frequency of inspection task
set of list possibilities. Pretest a questionnaire interval in all equipment depends on fixed
(in Arabic) with maintenance manager in interval chart and equipment run time. More
cement, academics and consultant through than 90% from important equipments follow
many draft tests. All their comments were up by preventive maintenance. More than 90%
considered in a revised version. of PM program are completed within one
2.4. Data analysis week of the required date. More than 90% of
an equipment items are checked by PM
Statistical techniques were used to analysis program. Predictive maintenance program
collected data in order obtain answers to includes vibration analysis and thermograph
questions. Many questions of our survey are for criticality only and includes oil analysis for
based on five point Likert type scales all equipments. Predictive maintenance
.Achieving accurate data and understanding of program utilizes sonic techniques only for
maintenance processes and parameters that are criticality. The computer maintenance
being measured. The data analyses help the management systems (CMMS) is tied into
best practices which lead to superior predicative maintenance system. The data of
performance. The best practices are practices predictive maintenance is used to build work
are that enable a company to be become a orders for preventive corrective maintenance
leader in its marketplace. Benchmarking and to improve maintenance performance.
process in maintenance used the following And it assigns specific technicians to work in
steps. Conduct internal analysis, identify areas the predictive maintenance program. Weekly
for improvement, find partners, make contact, work schedule includes tasks for predictive
develop questionnaire, perform sit visits, maintenance.
compile results, develop and implement The percentage of all maintenance
improvements and do it again. The goal of operation utilizes CMMS is more than 80%.
internal analysis is to identify weaknesses and More than 75% of maintenance activity are
areas that need improvement in company. planned and scheduled through a CMMS.
Goals of maintenance organization are More than 75% of the maintenance inventory
maximum production at lowest cost, highest and purchasing include CMMS. The
quality, and within the optimum safety production scheduling system, the payroll,
standard. timekeeping system, financial, accounting
system and CMMS are integrated. The
3. Results and Discussion financial and accounting system and CMMS
are integrated. More than 90% of maintenance
Appropriate analysis for the data collection; personnel are using the system for their job
lead to obtain a general view or different functions with a high level of performance.
maintenance parameters in the cement CMMS data is used to make cost effective

Jan 2012 ATE-70115068©Asian-Transactions 14


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

decisions and verify the progressive return of maintenance stores items are issued to a work
investment.The whole organization focused on order or account number upon leaving the
asset utilization and optimization. The store. Maximum and minimum levels for the
maintaining function is perceived as value maintenance stores items are specified for
added by management. The maintenance data more than 95% of the inventory. More than
collection system is utilized by management. 80% of critical maintenance material is stock
Operators are used for first line maintenance in the warehouse ore in a location readily
functions in some areas. More than 90% of accessible when the material is required. More
overall equipment availability is calculated on than 95% from maintenance stores inventory
key assets, processes and facilities. More than level are updated daily upon receipt of
90% of operational decisions are made taking materials. More than 90% from items are
into account equipment reliability and checked for at least one issue every year.
availability. More than 75% from the right soft Maintenance organization chart is current
skills training classes (such as leadership) and complete. The job descriptions are
have been conducted for maintenance available for all maintenance positions
supervisors. Less than 59% from the right including supervisors. The ratio between
technical training have been conducted for maintenance supervisors to hourly
appropriate personnel. The Financial effect of maintenance employee is between 1:13 to
equipment availability is not got by 1:16. The ratio between maintenance planners
everyone.From 75% to 89% of non- to hourly maintenance employee is between
emergency work orders are completed within 1:10 to 1:14. Maintenance organizational
four weeks of initial request. Work order assignments responsibility fully documented.
planning specific job instructions or job plan. Maintenance shop and work area from the
From 10% to 20% of planned work orders point of layout and locations is perfect.
experiencing delays due to poor or in Maintenance tools and equipment from the
complete plans. The maintenance planner is point of quality and quantity is perfect. The
responsible for planning the work orders. maintenance personnel are tied to pay
Maintenance job schedules are issued incentive plan based on output. From 75% to
biweekly. Maintenance and 89% of the time are the maintenance reports
production/facilities are scheduled for daily distributed on timely basis to the appropriate
meeting. The backlog of maintenance work is personnel. From 75% to 89% of time are the
available by date needed. After of the job is reports distributed within one day of the end
completed, the actual time, material, of the time period specified in the report.
downtime and other information is reported by Equipment reports include the equipment
the supervisor of the group. From 75% to 89% downtime in order of highest to lowest total
of time are actual measure compared to that hours weekly or monthly. Preventive
estimated for monitoring planning maintenance report include the PM hours
effectiveness. Bothe of planner and supervisor verses total maintenance hours per item
are report to same maintenance manager. expressed as a percentage. The personnel
From 80% to 95% of time are materials in reports include the time showing hours
stores when required by maintenance worked by employee divided by work order.
organization. From 75% to 80% of items in The planning reports include the backlog
inventory appears in maintenance stores report showing the total hours ready to
catalog. A person from maintenance staff schedule versus the craft capacity per week.
control stocked as maintenance inventory There is a strong support visible
items. The maintenance store catalog is management support for continuous
produced by alphabetic and numeric listing. improvement effort. The organization strong
More than 95% of aisle and bin location is support continuous improvement effort in
specified for the stores. More than 95% of maintenance. The spirit of cooperation

Jan 2012 ATE-70115068©Asian-Transactions 15


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

between plant management and labor is performance. Operators are trained and
excellent. On continuous improvement the certified to perform equipments inspections.
company focused on management, From 40% to 59% of time operators follow up
maintenance, stores and purchasing. and sign off on completed work order.
Management support training designed to Maintenance is included in production and
enhance employee skills purchasing. The process scheduling meetings.
continuous improvement efforts tied to Downtime duration is consistently tracked
reliability engineering. From 60% to 89%, for all assets. For key areas only the downtime
competitive forces affect improvement cost is clearly identified. For all assets
efforts.The site’s document management downtime causes are accurately and
system is electronic and interfaced with other consistently tracked. Maintenance costs are
systems. The ratio of maintenance drawings clearly and accurately tracked for key assets
included in the system is between 50 to 79 %. only. All other maintenance costs such as
The site’s timing for migration to fully energy, quality, and contractors are available.
functional and utilized document management Total operation costs are compared when
system is no plan. Document control making decisions for all cost factors.
procedures and associate work process exist Efficiency loss cost is available and accurate
for the system. The maintenance personnel are for 75% to 89% of time. Personnel are not
in process of being trained to use the dedicated to financial costs analysis. The
document management process. The majority is offered and attends supervisory
document management system has detailed training, which is offered on an infrequent or
indexing and search capabilities that make irregular basis. All maintenance planer receive
document simple and easy to find the quality one on the job training for at least one month.
and level of document version control is Maintenance planers received scheduling
excellent. A document management system is practices training program. General quality
used by managers and supervisors only. About and productivity training includes upper
75% of maintenance man-hours are reported management and line supervision. Formal job
to work order and 75% of maintenance experience for maintenance craft training is
materials are charged against a work order required before hire. Formal maintenance craft
number when issued. About 75% of total jobs employees training is provided in irregular
performed by maintenance are covered by intervals for some employee only. All training
work order. About 75% of total jobs program instructors is all on the job training
performed by maintenance are covered by only. Training program instructor is done only
work order. About 25% of the work orders are supervisors. Quality and skill level of
opened under a priority that would be maintenance work force group is good and
identified as emergency or urgent and 75% of need to some improvement. Quality and skill
work orders are available for historical data level of supervisory group still need some
analysis. About 50% of work orders are improvement.
checked by a qualified individual for work The organization has an attitude towards
quality and completeness. From 75% to 89% reliability centered maintenance (RCM)
from operations personnel generate work which is developed as a part of work culture.
order requests. From 60% to 74% from From 75% to 89% of complete and accurate
facilities generate work order requests. assets data is available for RCM analysis.
Operations work order priority is set for RCM is used to adjust and refine the
maintenance daily in a joint operation and preventive maintenance. From 75% to 89% of
maintenance meeting. Facility work order the work order history is accurate in tracking
priority is set for maintenance daily in a joint the causes of failures. From 75% to 89% of
facility and maintenance meeting. Operators the failures are clearly identified. Failure
are involved in the upkeep and asset analysis is conducted using analysis tools such

Jan 2012 ATE-70115068©Asian-Transactions 16


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

as why tree, fishbone and Pareto diagram to maintenance organization chart is current and
assure accuracy and consistency of effort. complete. The job descriptions are available
Dedicated personnel are permanently assigned for all maintenance positions including
to maintain the RCM program. Management supervisors. The ratio between maintenance
view RCM as value added activity and supervisors to hourly maintenance employee
measure the reliability engineering is found between 1:13 to 1:16. The ratio
effectiveness. More than 90% from important between maintenance planners to hourly
equipments follow up by preventive maintenance employee is found between 1:10
maintenance. More than 90% of an equipment to 1:14. Maintenance personnel are tied to pay
items are checked by a preventive incentive plan based on output. Maintenance
maintenance program. More than 90% of PM inventory and purchasing show that from 80%
is completed within a week of date. Predictive to 95% of time are stored materials.
maintenance shows that CMMS tied into More than 95% of aisle and bin location is
predicative maintenance system. Data of specified for the stores. More than 95% of
predictive maintenance is used to build work maintenance stores items are issued to a work
orders for preventive and corrective order or account number upon leaving the
maintenance and to improve the maintenance store. Maximum and minimum levels for the
performance. maintenance stores items are specified for
Maintenance automation showed that the more than 95% of the inventory. More than
percentage of all maintenance operation 95% from maintenance stores inventory level
utilizes CMMS is more than 80%. More than are updated daily upon receipt of materials.
75% of maintenance activity are planned and More than 90% from items are checked for at
scheduled through a CMMS. More than 75% least one issue every year. Operations and
of the maintenance Inventory and purchasing facilities involvement showed that from 75%
include. More than 90% of maintenance to 89% from operations personnel generate
personnel are using the system for their job work order requests.
functions with a high level of performance. Fig 1. summarizes the score assigned to
Maintenance planning and scheduling each area based on the designed questionnaire.
showing that, more than 90% of overall It is evident that the maintenance work
equipment availability is calculated on key orders are the lowest level. Thus, total score
assets, processes and facilities. More than 90% of 17 points, indicates the need to improve
of operational decisions are made taking into the training and proposes appropriate
account equipment reliability and availability. solutions. Also it is clear that the work
From 75% to 89% of non-emergency work orders come in second level of weakness.
orders are completed within four weeks of Total score of 25 points confirms that there
initial request. From 75% to 89% of time is an are many activities can be improved in the
actual measure compared to the estimate for work orders.
monitoring planning effectiveness.
Maintenance organization showing that,

Jan 2012 ATE-70115068©Asian-Transactions 17


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

Organizations
Document 40 Training
35
Asset Care 30 Work Order
25
20
Financial 15 Plan & Sched
10
5
0
General PM

Reliability Inventory

PDM Automation
Operations - facilities
Reporting
Involvement

Fig.1. Scores of maintenance areas.

4. Conclusions in order of highest to lower weekly or


monthly. The purchasing reports include price
The areas those need to improvement such performance, showing the quoted and actual
as training programs in maintenance show that prices, it preferably to include also buyer or
the majority is offered and attended purchasing agent performance report. Non
supervisory training on an irregular basis. All stock report showing all direct items not
instructors depend on the job training only. It carried in stock for a specified period.
is not a mix of classroom and lab exercises. Administrative maintenance reports including
Quality and skill level of maintenance work monthly maintenance costs versus monthly
force group is good but need to some maintenance budget with a year to date total.
improvement. Training is done by supervisors It is preferable to include also the comparison
while it must be by an outside contract expert of labor and material costs as a percentage of
staff. Quality and productivity training total maintenance cost and total costs of
includes upper management and line outside contractor usage. The finances of
supervision only without workers. Formal job maintenance showing that, downtime costs is
experience for maintenance craft training is clearly identified for key area only, it
required before hire but it is not tied to a pay preferably to include all area. Maintenance
and progression programs. Operations and costs are clearly and accurately tracked for
facilities involvement show that operators are key assets only, it preferably to include all
trained and certified to perform equipments assets. A dedicated individual or team is not
inspections. It must content lubrication, minor assigned to analyze financial costs.
maintenance task and assist in maintenance Maintenance documents show that
repair task. maintenance personnel are in process of being
Maintenance reporting shows that trained to use document management.
equipment reports include the equipment Although the application is conducted to
downtime in order of highest to lowest total one company, this application of this work
hours weekly or monthly. It is preferable to can be extended to more companies.
include also maintenance cost for equipment

Jan 2012 ATE-70115068©Asian-Transactions 18


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

5. The Sixth Five-year Development Plan.


Future Work Ministry of Planning, Kingdom of Saudi
Arabia, 1995.
The application will be extended to 6. Bob,V., “Experts layouts case for ROI of
different cement companies taking in maintenance,” Plant Engineering, 61: 12–
consideration the impact of maintenance 20, 2007.
practices on productivity. In addition, it will 7. Alsyouf, I., “Cost Effective Maintenance
consider establishing a reference guideline for Competitive Advantages,” Ph.D.
of a standard procedure based on the process Thesis, School of Industrial Engineering,
of maintenance protocol development for Vaxjo University press, Acta
cement companies. Wexionensia, Sweden, 2004.
8. Blanchard, B.S., Logistics Engineering
and Management, Sixth Ed., Prentice-
Acknowledgements Hall Pearson 2004.
9. De Groote, P., “Maintenance performance
The author is grateful to the cement analysis: A practical approach.” Journal
of Quality in Maintenance Engineering,
company that provides the information
2: 4–24, 1995.
required to finish this research and due to
10. Salonen, A. and Deleryd, M., “Cost of
their further cooperation. Also, the author
poor maintenance: A concept for
would like to thank Vice Dean for maintenance performance improvement,”
Development, Dr. Abdullah Al Shahri for Journal of Quality in Maintenance
supporting this project under the Industrial Engineering, 17: 63–73, 2011.
Relations Commission. 11. Chen, W.-J., “Minimizing total flow time
and maximum tardiness with periodic
maintenance,” Journal of Quality in
References Maintenance Engineering, 13: 293–303,
2007.
1. Khan, M.R.R. and Darrab, I.A., 12. Alsyouf, I., “Measuring maintenance
“Development of analytical relation performance using a balanced scorecard
between maintenance, quality and approach,” Journal of Quality in
productivity,” Journal of Quality in Maintenance Engineering, 12: 133–149,
Maintenance Engineering, 16: 341–353, 2006.
2010. 13. Mostafa, S.I., “Implementation of
2. Al-Sultan, K.S., “Maintenance in Saudi proactive maintenance in the Egyptian
Arabia: Needs and recommendations for glass company,” Journal of Quality in
improvement,” Journal of Quality in Maintenance Engineering, 10: 107–122,
Maintenance Engineering, 2: 5–16, 1996. 2004.
3. Ikhwan, M.H., Hague, A.A. and Burney, 14. Sharma, A., Yadava, G.S. and Deshmukh,
F.A., “Maintenance in Saudia Arabia,” S.G., “A literature review and future
Symposium on Maintenance Planning perspectives on maintenance
and Operations, Riyadh, 17-19 March: optimization,” Journal of Quality in
32–42, 1990. Maintenance Engineering, 17: 5–25,
4. Al-Saggaf, H.A., “Application of TQM at 2011.
SCECO-EAST: A case study,” Journal of 15. Chen, W.-J., “Minimizing completion
Quality in Maintenance Engineering, 3: time with maintenance schedule in a
341–353, 1997. manufacturing system,” Journal of

Jan 2012 ATE-70115068©Asian-Transactions 19


Asian Transactions on Engineering (ATE ISSN: 2221-4267) Volume 01 Issue 06

Quality in Maintenance Engineering, 16: in Maintenance Engineering, 15: 31–46,


382–394, 2010. 2009.
16. Chinese, D. and Ghirardo, G., 21. Aoudia, M., Belmokhtar, O. and
“Maintenance management in Italian Zwingelstein, G., “Economic impact of
manufacturing firms: Matters of size and maintenance management ineffectiveness
matters of strategy,” Journal of Quality in of an oil and gas company,” Journal of
Maintenance Engineering, 1: 156–180, Quality in Maintenance Engineering, 14:
2010. 223–261, 2008.
17. Ahuja, I.P.S. and Kumar, P., “A case 22. Lamptey, G., “Decision support for
study of total productive maintenance optimal scheduling of highway pavement
implementation at precision tube mills,” preventive maintenance within
Journal of Quality in Maintenance resurfacing cycle,” Journal of Decision
Engineering, 15: 241–258, 2009. Support Systems, 46: 376–387, 2008.
18. Reis, A.C.B., “Planning and 23. Dowlatshahi, S., “The role of industrial
competitiveness in maintenance maintenance in the maquiladora industry:
management: An exploratory study in An empirical analysis,” International
manufacturing Companies,” Journal of Journal of Production Economics, 114:
Quality in Maintenance Engineering, 15: 298–307, 2008.
259–270, 2009. 24. Chang, Y.-H. and Wang, Y.-C.,
19. Kans, M., “The advancement of “Significant human risk factors in aircraft
maintenance information technology: A maintenance technicians,” Safety Science,
literature review,” Journal of Quality in 48: 63–73, 2011.
Maintenance Engineering, 15: 5–16, 25. Ahuja, I.P.S. and Khamba, J.S., “An
2009. evaluation of TPM implementation
20. Vassilakis, E., “An application of TQM initiatives in an Indian manufacturing
tools at a maintenance division of a large enterprise,” Journal of Quality in
aerospace company,” Journal of Quality Maintenance Engineering, 13: 338–352,
2007.

‫ممارسات الصيانة في صناعة األسمنث‬

‫ُأً شفيق‬
‫كليح الٌِذسح جاهؼح الولك ػثذ الؼزيز فزع راتغ‬
‫كليح الرؼلين الصٌاػٔ جاهؼح قٌاج السْيس هصز‬
Hanishafeek@yahoo.com

‫خالصة‬
‫ُذٍ الوقالح ذحلل ًظام إدارج صياًح ألحذ هصاًغ األسوٌد الكائٌح في الوولكح الؼزتيح السؼْديح تئسرخذام‬
‫ ّقذ كشف ُذا الرحليل ػي ّجْد جْاًة قْج في الٌظام هثل الصياًح الرٌثؤيح‬.‫إسرثياى ذن إػذادٍ لِذا الغزض‬
ٔ‫ ّهي ًاحيح أخزٓ ذن الكشف ػي جْاًة الضؼف في الٌظام هثل تزاهج الرذرية ػل‬.‫ّهيكٌح الصياًح‬
ٓ‫ كوا ُّجذخ جْاًة ذجوغ تيي القْج في ػٌاصز هؼيٌح ّالضؼف في ػٌاصز أخز‬.‫الصياًح ّذقاريز الصياًح‬
‫ ّقام ُذا األسلْب تذّر الرقيين لجويغ جْاًة الٌظام ّلذلك‬.‫هثل سجالخ الصياًح ّذخطيط ّجذّلح الصياًح‬
‫يوكي إػرثارٍ هثادرج للرحسيي الوسروز للصياًح ّاإلًراجيح ّيوكي دهجَ كجزء هي ًظام لذػن القزار في إدارج‬
.‫الصياًح‬