Вы находитесь на странице: 1из 3

SEG - LIBAN SEG - LIBAN 1/3

Activity ID Activity Name Original Early Start Early Finish AREA LEVEL W/S ZONE
Duration 2014
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
MILESTONES
ALL AREAS
GENERAL WORKS
ALL LEVELS
CD-M-0005 COMMENCEMENT DAY 0 01-Apr-14 GEN ALL 01 GEN COMMENCEMENT DAY

PRELIMINARIES
ALL AREAS
GENERAL WORKS
ALL LEVELS
CD-M-0015 MOBILISATION 14 01-Apr-14 16-Apr-14 GEN ALL 02 GEN MOBILISATION
CD-M-0055 BACK PROPPING 14 17-Apr-14 02-May-14 GEN ALL 02 GEN BACK PROPPING
CD-M-0035 ERECTION OF TOWER CRANE 7 09-May-14 16-May-14 GEN ALL 02 GEN ERECTION OF TOWER CRANE

DESTRUCTION
AREA (A)
GENERAL WORKS
ALL LEVELS
CD-M-0025 TOWER CRANE OPENING 21 09-Apr-14 02-May-14 A ALL 03 GEN TOWER CRANE OPENING

RAFT FOUNDATION
CD-M-0045 TOWER CRANE FOUNDATION 5 03-May-14 08-May-14 A RAFT 03 GEN TOWER CRANE FOUNDATION
COREWALL 1
GROUND FLOOR
CD-M-0065 DEMOLITION OF GROUND FLOOR SLAB8 17-May-14 26-May-14 A GF 03 ZONE 1 DEMOLITION OF GROUND FLOOR SLAB
BASEMENT 1
CD-M-0145 REMOVING OF VERTICAL ELEMENTS 2 27-May-14 28-May-14 A BAS1 03 ZONE 1 REMOVING OF VERTICAL ELEMENTS
CD-M-0075 DEMOLITION OF BASEMENT 1 21 29-May-14 21-Jun-14 A BAS1 03 ZONE 1 DEMOLITION OF BASEMENT 1
BASEMENT 2
CD-M-0155 REMOVING OF VERTICAL ELEMENTS 4 23-Jun-14 26-Jun-14 A BAS2 03 ZONE 1 REMOVING OF VERTICAL ELEMENTS
CD-M-0085 DEMOLITION OF BASEMENT 2 4 27-Jun-14 01-Jul-14 A BAS2 03 ZONE 1 DEMOLITION OF BASEMENT 2
BASEMENT 3
CD-M-0165 REMOVING OF VERTICAL ELEMENTS 4 02-Jul-14 05-Jul-14 A BAS3 03 ZONE 1 REMOVING OF VERTICAL ELEMENTS
CD-M-0095 DEMOLITION OF BASEMENT 3 4 07-Jul-14 10-Jul-14 A BAS3 03 ZONE 1 DEMOLITION OF BASEMENT 3
BASEMENT 4
CD-M-0175 REMOVING OF VERTICAL ELEMENTS 4 11-Jul-14 15-Jul-14 A BAS4 03 ZONE 1 REMOVING OF VERTICAL ELEMENTS
CD-M-0105 DEMOLITION OF BASEMENT 4 4 16-Jul-14 19-Jul-14 A BAS4 03 ZONE 1 DEMOLITION OF BASEMENT 4
BASEMENT 5
CD-M-0195 REMOVING OF VERTICAL ELEMENTS 4 21-Jul-14 24-Jul-14 A BAS5 03 ZONE 1 REMOVING OF VERTICAL ELEMENTS
CD-M-0115 DEMOLITION OF BASEMENT 5 4 25-Jul-14 29-Jul-14 A BAS5 03 ZONE 1 DEMOLITION OF BASEMENT 5
BASEMENT 6
CD-M-0185 REMOVING OF VERTICAL ELEMENTS 4 30-Jul-14 02-Aug-14 A BAS6 03 ZONE 1 REMOVING OF VERTICAL ELEMENTS
CD-M-0125 DEMOLITION OF BASEMENT 6 4 04-Aug-14 07-Aug-14 A BAS6 03 ZONE 1 DEMOLITION OF BASEMENT 6
RAFT FOUNDATION
CD-M-0215 REMOVING OF AGGREGATES & CLEANING
5 08-Aug-14 13-Aug-14 A RAFT 03 ZONE 1 REMOVING OF AGGREGATES & CLEANING
CD-M-0205 REMOVING VERTICAL NECKS 6 14-Aug-14 20-Aug-14 A RAFT 03 ZONE 1 REMOVING VERTICAL NECKS
CD-M-0135 LIFT PITS ON RAFT FOUNDATION 14 21-Aug-14 05-Sep-14 A RAFT 03 ZONE 1 LIFT PITS ON RAFT FOUNDATION
COREWALL 2
GROUND FLOOR
CD-M-0235 DEMOLITION OF GROUND FLOOR SLAB8 17-May-14 26-May-14 A GF 03 ZONE 2 DEMOLITION OF GROUND FLOOR SLAB
BASEMENT 1
CD-M-0315 REMOVING OF VERTICAL ELEMENTS 2 27-May-14 28-May-14 A BAS1 03 ZONE 2 REMOVING OF VERTICAL ELEMENTS
CD-M-0245 DEMOLITION OF BASEMENT 1 21 29-May-14 21-Jun-14 A BAS1 03 ZONE 2 DEMOLITION OF BASEMENT 1
BASEMENT 2
CD-M-0325 REMOVING OF VERTICAL ELEMENTS 4 23-Jun-14 26-Jun-14 A BAS2 03 ZONE 2 REMOVING OF VERTICAL ELEMENTS
CD-M-0255 DEMOLITION OF BASEMENT 2 4 27-Jun-14 01-Jul-14 A BAS2 03 ZONE 2 DEMOLITION OF BASEMENT 2
BASEMENT 3

Actual Work Critical Remaining Work Classic WBS Layout Date Revision Checked Approved
REV.0
Remaining Work Milestone
SEG - LIBAN SEG - LIBAN 2/3

Activity ID Activity Name Original Early Start Early Finish AREA LEVEL W/S ZONE
Duration 2014
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
CD-M-0335 REMOVING OF VERTICAL ELEMENTS 4 02-Jul-14 05-Jul-14 A BAS3 03 ZONE 2 REMOVING OF VERTICAL ELEMENTS
CD-M-0265 DEMOLITION OF BASEMENT 3 4 07-Jul-14 10-Jul-14 A BAS3 03 ZONE 2 DEMOLITION OF BASEMENT 3
BASEMENT 4
CD-M-0345 REMOVING OF VERTICAL ELEMENTS 4 11-Jul-14 15-Jul-14 A BAS4 03 ZONE 2 REMOVING OF VERTICAL ELEMENTS
CD-M-0275 DEMOLITION OF BASEMENT 4 4 16-Jul-14 19-Jul-14 A BAS4 03 ZONE 2 DEMOLITION OF BASEMENT 4
BASEMENT 5
CD-M-0365 REMOVING OF VERTICAL ELEMENTS 4 21-Jul-14 24-Jul-14 A BAS5 03 ZONE 2 REMOVING OF VERTICAL ELEMENTS
CD-M-0285 DEMOLITION OF BASEMENT 5 4 25-Jul-14 29-Jul-14 A BAS5 03 ZONE 2 DEMOLITION OF BASEMENT 5
BASEMENT 6
CD-M-0355 REMOVING OF VERTICAL ELEMENTS 4 30-Jul-14 02-Aug-14 A BAS6 03 ZONE 2 REMOVING OF VERTICAL ELEMENTS
CD-M-0295 DEMOLITION OF BASEMENT 6 4 04-Aug-14 07-Aug-14 A BAS6 03 ZONE 2 DEMOLITION OF BASEMENT 6
RAFT FOUNDATION
CD-M-0385 REMOVING OF AGGREGATES & CLEANING
5 08-Aug-14 13-Aug-14 A RAFT 03 ZONE 2 REMOVING OF AGGREGATES & CLEANING
CD-M-0375 REMOVING VERTICAL NECKS 6 14-Aug-14 20-Aug-14 A RAFT 03 ZONE 2 REMOVING VERTICAL NECKS
CD-M-0305 LIFT PITS ON RAFT FOUNDATION 14 21-Aug-14 05-Sep-14 A RAFT 03 ZONE 2 LIFT PITS ON RAFT FOUNDATION
AXIS (NK-NP) (N4-N5)
GROUND FLOOR
CD-M-0395 GROUND FLOOR SLAB 4 06-Sep-14 10-Sep-14 A GF 03 ZONE 3 GROUND FLOOR SLAB
BASEMENT 1
CD-M-0405 VERTICAL ELEMENTS 5 11-Sep-14 16-Sep-14 A BAS1 03 ZONE 3 VERTICAL ELEMENTS
AXIS (NN-NP) (N5-N8)
GROUND FLOOR
CD-M-0415 GROUND FLOOR SLAB 4 11-Sep-14 15-Sep-14 A GF 03 ZONE 4 GROUND FLOOR SLAB
BASEMENT 1
CD-M-0425 VERTICAL ELEMENTS 5 17-Sep-14 22-Sep-14 A BAS1 03 ZONE 4 VERTICAL ELEMENTS
AXIS (NA-NH) (N1-N4)
GROUND FLOOR
CD-M-0435 GROUND FLOOR SLAB 4 16-Sep-14 19-Sep-14 A GF 03 ZONE 5 GROUND FLOOR SLAB
BASEMENT 1
CD-M-0445 VERTICAL ELEMENTS 5 23-Sep-14 27-Sep-14 A BAS1 03 ZONE 5 VERTICAL ELEMEN TS
AXIS (NA-NE) (N4-N5)
GROUND FLOOR
CD-M-0455 GROUND FLOOR SLAB 15 29-Sep-14 15-Oct-14 A GF 03 ZONE 6 GROUND FLOOR SLAB
BASEMENT 1
CD-M-0465 VERTICAL ELEMENTS 5 16-Oct-14 21-Oct-14 A BAS1 03 ZONE 6 VERTICAL ELEMENTS
AXIS (NI-NO) (N5-N8)
GROUND FLOOR
CD-M-0475 GROUND FLOOR SLAB 4 20-Sep-14 24-Sep-14 A GF 03 ZONE 7 GROUND FLOOR SLAB
BASEMENT 1
CD-M-0485 VERTICAL ELEMENTS 10 22-Oct-14 01-Nov-14 A BAS1 03 ZONE 7 VERTICAL ELEMENTS
AREA (B)
RAMP AND COREWALL IN AREA (B)
ALL LEVELS
CD-M-0495 ANCHORING ON RAMP RET. WALLS 18 17-Apr-14 07-May-14 B ALL 03 RAMP ANCHORING ON RAMP RET. WALLS
BASEMENT 1
CD-M-0505 REMOVAL OF BAS1 SLAB 5 17-May-14 22-May-14 B BAS1 03 RAMP REMOVAL OF BAS1 SLAB
BASEMENT 2
CD-M-0515 REMOVAL OF RAMP FROM B1 TO B2 5 20-May-14 24-May-14 B BAS2 03 RAMP REMOVAL OF RAMP FROM B1 TO B2
CD-M-0545 REMOVAL OF BAS 2 VERTICALS 3 26-May-14 28-May-14 B BAS2 03 RAMP REMOVAL OF BAS 2 VERTICALS
CD-M-0525 REMOVAL OF BAS2 SLAB 4 29-May-14 02-Jun-14 B BAS2 03 RAMP REMOVAL OF BAS2 SLAB
BASEMENT 3
CD-M-0535 REMOVAL OF RAMP FROM B2 TO B3 5 31-May-14 05-Jun-14 B BAS3 03 RAMP REMOVAL OF RAMP FROM B2 TO B3
CD-M-0555 REMOVAL OF BAS 3 VERTICALS 3 06-Jun-14 09-Jun-14 B BAS3 03 RAMP REMOVAL OF BAS 3 VERTICALS
CD-M-0565 REMOVAL OF BAS3 SLAB 4 10-Jun-14 13-Jun-14 B BAS3 03 RAMP REMOVAL OF BAS3 SLAB
BASEMENT 4
CD-M-0575 REMOVAL OF RAMP FROM B3 TO B4 5 12-Jun-14 17-Jun-14 B BAS4 03 RAMP REMOVAL OF RAMP FROM B3 TO B4
CD-M-0585 REMOVAL OF BAS 4 VERTICALS 3 18-Jun-14 20-Jun-14 B BAS4 03 RAMP REMOVAL OF BAS 4 VERTICALS
CD-M-0595 REMOVAL OF BAS4 SLAB 4 21-Jun-14 25-Jun-14 B BAS4 03 RAMP REMOVAL OF BAS4 SLAB
SEG - LIBAN SEG - LIBAN 3/3

Activity ID Activity Name Original Early Start Early Finish AREA LEVEL W/S ZONE
Duration 2014
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
BASEMENT 5
CD-M-0615 REMOVAL OF RAMP FROM B4 TO B5 5 24-Jun-14 28-Jun-14 B BAS5 03 RAMP REMOVAL OF RAMP FROM B4 TO B5
CD-M-0625 REMOVAL OF BAS 5 VERTICALS 3 30-Jun-14 02-Jul-14 B BAS5 03 RAMP REMOVAL OF BAS 5 VERTICALS
CD-M-0635 REMOVAL OF BAS5 SLAB 4 03-Jul-14 07-Jul-14 B BAS5 03 RAMP REMOVAL OF BAS5 SLAB
BASEMENT 6
CD-M-0655 REMOVAL OF RAMP FROM B5 TO B6 5 05-Jul-14 10-Jul-14 B BAS6 03 RAMP REMOVAL OF RAMP FROM B5 TO B6
CD-M-0665 REMOVAL OF BAS 6 VERTICALS 3 11-Jul-14 14-Jul-14 B BAS6 03 RAMP REMOVAL OF BAS 6 VERTICALS
CD-M-0675 REMOVAL OF BAS6 SLAB 4 15-Jul-14 18-Jul-14 B BAS6 03 RAMP REMOVAL OF BAS6 SLAB
RAFT FOUNDATION
CD-M-0685 REMOVAL OF VERTICALS UNDERNEATH
4 BAS6
19-Jul-14 23-Jul-14 B RAFT 03 RAMP REMOVAL OF VERTICALS UNDERNEATH BAS6

Вам также может понравиться