PROPOSAL NO.

REV 1
PROJECT : BPCL Kochi STATIC EQUIPMENT ERECTION BOQ DATE 28-Jan-201
CLIENT : BPCL PREP
CHKD
Erection Total
SI. Size Erection Total in
Rev. Unit No. Equipment No. Equipment Description Qty Position Support Type Elevation from Erection Unit Rate in USD Remarks
No. (mm / Item) Weight / Item USD
FGL Weight

Overall Height /
Length/ Height
nos. (V/H) skirt /saddle/ leg/ bracket Diameter length including (m) (MT) (MT) Goods Services Total Rate
(T/T)
support

(B) Drier Package


Debutanizer overhead dryer package (MR-LZ-02)
MR-LZ-02-V-01 A/B Adsorber vessel 2 V Skirt 924 3550 5152 4.582 9.164
MR-LZ-02-D-01 Feed coalescer 1 V Bracket 355.6 2500 2740 0.57 0.57
MR-LZ-02-F-02 A/B Product filter 2 V Bracket 355.6 2500 2740 0.514 1.028
MR-LZ-02-F-03 Moisture separator 1 V Bracket 508 2500 4097 0.535 0.535 Skid dimension 7.0 m x 4.0 m x 7.4 m
MR-LZ-02-E-01 Air cooled heat exchanger 1 H 475 1958 2575 2.651 2.651 adsorber weight 2500 kg
MR-LZ-02-H-01 Electric heater 1 H saddle 219 2350 2405 0.85 0.85 Skid weight 29.5 MT
MR-LZ-02-C-01 A/B Blower 2 skid 0.39 0.78
Instrumentation & interconnecting
13.93
piping
NET GAS DRYER PACKAGE (MP-LZ-02)
MP-LZ-02-V-01 A/B Adsorber vessel 2 V Skirt 1700 3700 6308 10.225 20.45
MP-LZ-02-D-01 Feed coalescer 1 V leg 508 2695 3936 1.05 1.05
MP-LZ-02-F-02 A/B Product filter 2 V leg 508 2695 3936 1 2
MP-LZ-02-F-03 Moisture separator 1 V leg 508 2500 4097 0.9 0.9 Skid dimension 10.0 m x 5.85 m x 8.204 m
MP-LZ-02-E-01 Shell & tube heat exchanger 1 H saddle 437.2 3057 4157 2.05 2.05 adsorber weight 8400 kg
MP-LZ-02-H-01 Electric heater 1 H saddle 355.6 3012 3215 1.39 1.39 Skid weight 52.5 MT
MP-LZ-02-C-01 A/B Blower 2 skid 0.79 1.58
Instrumentation & interconnecting
23.08
piping

Notes:
1 Touch-up painting shall be considered for the equipment at site for the damage to the surfaces which may occurred during transportation.
2 The Debutanizer overhead drier package shall be prefabricated and supplied as per details indicated below:
1 skid consisting of 2 After Filter & 1 Air cooler.
1 no. Electric Heater, 2 nos. columns with adsorbent,1 no. moisture separator, 1 no. Feed coalescer are supplied loose for erection at site.
Piping and structurals associtaed with the loose supplied equipment are supplied in prefabricated sections for erection at site.
Adsorbent of 2500 kgs for 2 Nos. of Columns is supplied loose. Adsorbent to be filled in 2 columns at site. All necessary accessories/equipment required for adsorbent filling will be provided by the site contractor.
All instrumentation including cables, cable trays,PSV's,JB's etc supplied loose for installation at site.
All these items will be assembled on skids at site.