Академический Документы
Профессиональный Документы
Культура Документы
of Nigeria Limited
Operator for the NNPC/Shell/Agip/Elf Joint Venture
FOR
(FINAL REPORT)
November, 2006
TABLE OF CONTENTS
Page
CHAPTERS AND TITLES ii
LIST OF FIGURES ix
LIST OF TABLES xi
LIST OF APPENDICES viii
LIST OF PLATES AND BOXES xiv
GLOSSARY OF TERMS, ABBREVIATIONS AND ACRONYMS xv
EIA REPORT PREPARERS xix
ACKNOWLEDGEMENT xx
EXECUTIVE SUMMARY 1 of 20
3.3.2.10 Education 67 of 84
3.3.2.11 Occupation 68 of 84
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page iii
3.3.2.12 Cultural Environment 70 of 84
REFERENCES 1 of 4
APPENDICES 1 of 97
Fig. 2.0: Map of the Niger Delta Showing the Proposed Project
Location 3 of 11
Fig. 3.13 Household Size in Ahoada and other LGAs in Rivers State 64 of 84
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page vii
LIST OF TABLES
Table 3.17: Summary of the Nutrient Status of Soils from Project Area 41 of 84
Table 3.18: Summary of Alkaline Earth Metals of Soils from the Project Area 42 of 84
Table 3.19: Exchangeable Acidity and Cation Exchange Capacity
of Soil of the Project Area 43 of 84
Table 3.20: Heavy Metals of Soils in the Project Area 44 of 84
Table 3.21: Summary of Microbiological Characteristics of Soil
Samples from Project Area 45 of 84
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page viii
Table 3.22: Major Hydrological Features of Sombriero River at
Pipeline Crossing 46 of 84
Table 3.31: Fish Fauna and Fisheries in Waters around Project Location 61 of 84
Plate 3.6: Fresh Catch of Tilapia from the Sombriero River on the
Pipeline Crossing 60 of 84
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page xii
LIST OF ABBREVIATIONS AND ACRONYMS
Units
% - Percent
°C - degree Celsius
Cfu - Colony forming units
Cfu/ml - Colony forming units/milliliter
Cfu/g - Colony forming units/gramme
dB(A) - Decibel
g - Gramme
ha - hectare
°k - degree Kelvin
kg - Kilogram
km2 - Square Kilometre
L - Litre
µg - microgramme
µm - micrometer
mg - Milligramme
mg/kg - Milligramme per kilogramme
Meq - Milli-equivalent
mg/l - Milligrame per litre
mm - Milimetre
ml - Millilitre
m/s - Metres per second
NTU - Nephelometric Turbidity unit
nmi - Nautical Miles
ppm - Parts per million
psi - Pounds per square inch
psig - Pounds per square inch gauge
Abbreviations/Acronyms
AAS - Atomic Absorption Spectrophotometer
AGG - Associated Gas Gathering
ALARP - As Low As Reasonably Practicable
APHA - American Public Health Association
API - American Petroleum Insitute
BH - Borehole
BOD - Biochemical Oxygen Demand
Ca - Calcium
CASHES - Community Affairs, Safety, Health, Environment, and Security
CBO - Communiy Based Organisations
CDC - Community Development Committee
Cl- - Chloride ion
CLO - Community Liaison Officer
Cm - Centimetre
CO - Carbon monoxide (Carbon II Oxide)
Co - Cobalt
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page xiii
CO2 - Carbon Dioxide, Carbon iv oxide
COD - Chemical Oxygen Demand
Cr - Chromium
DO - Dissolved Oxygen
DPR - Department of Petroleum Resources
DS - Dissolved solids
DTE-GEM - Geomatic Services
E - East
EP - Extraction Procedure
E&P - Exploration and Production
EER - Environmental Evaluation Report
EIA - Environmental Impact Assessment
EPA - Environmental Protection Agency
ESP - Emergency Shut –Down Protection
Fe - Iron
FEPA - Federal Environmental Protection Agency
FMENV - Federal Ministry of Environment
F&G - Fire and Gas
GOR - Gas Oil Ratio
GPS - Global Positioning System
HC - Hydrocarbons
H2S - Hydrogen Sulphide
HAZID - Hazard identification
HEMP - Hazard and Effect Management Process
HET - Heterotrophic bacteria
HRA - Health Risk Assessment
HSE - Health, Safety and Environment
HSE-ENVE - Environmental Assessment Team of HSE Department
HSES - Health, Safety, Environment and Security
HSES-MS - Health, Safety, Environment and Security Management System
HUB - Hydrocarbon utilising bacteria
K - Potassium
LP - Low Pressure
LGAs - Local Government Areas
LNG - Liquified Natural Gas
N - North, Nitrogen
Na - Sodium
NA - Not applicable
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page xiv
NAG - Non Associated Gas
NAOC - Nigerian Agip Oil Company Limited
NE - North East
N-NH4 - Ammonium Nitrogen
N-NO2 - Nitrite Nitrogen
N-NO3 - Nitrate Nitrogen
N/D - Not Detected
NGC - Nigerian Gas Company
NGLs - Natural Gas Liquids
NGO - Non-Governmental Organisation
Ni - Nickel
NEGAS - National Environmental Guidelines and Standards
NAPIMS - National Petroleum Investment Management Services
NLNG - Nigerian Liquified Natural Gas Limited
NNPC - Nigeria National Petroleum Corporation
NOx - Nitrogen Oxides
NW - North West
QA - Quality Assurance
QC - Quality Control
QM - Quality Management
R - Correlation Coefficient
ROW - Right of Way
RPE - Respiratory Protection Equipment
RPI - Research Planning Institute
R/S - Rivers State
RSEPA - Rivers State Environmental Protection Agency
(now Rivers State Ministry of Environment)
RSMENV - Rivers State Ministry of Environment
S - South, Sulphur
SAFOP - Safety and Operability Study
W - West
WDG - Waste Disposal Guidelines
WHO - World Health Organisation
Zn - Zinc
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page xvi
EIA REPORT PREPARERS
CONSULTANTS
Professor A. Obi-Ekezie - Biophysical Consultant,
Institute of Oceanography,
University of Calabar,
Calabar,
Cross River State.
Mr. S. Ojo - Social Consultant,
30 Sobande Street,
Akoka,
Lagos State.
Dr. J. Amah - Health Consultant,
Amber Projects International,
Plot 104B Airport Road, Warri,
Delta State.
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page xvii
ACKNOWLEDGMENT
We appreciate the cordial working relationships we have with FMENV, DPR, Rivers State
Ministry of Environment, Local Government Authorities, Community Chiefs, Elders and
Youths of Ihuowo Community.
The efforts of the project team in putting this EIA together are also greatly commended.
Thank you.
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page xviii
EXECUTIVE SUMMARY
• Oil Pipelines Ordinances (CAP) 145, 1956 and Oil Pipelines Act, 1965.
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 1 of 113
EXECUTIVE SUMMARY
• Convention Concerning the Protection of the World Cultural and Natural Heritage
Sites (or World Heritage Convention).
International Guidelines
• World Bank Guidelines on Environmental Assessment {EA}.
E.S.1.2 Declaration
Shell Petroleum Development Company of Nigeria Limited (SPDC) hereby declares her
intention to abide by the existing international and local laws/regulations as well as
SPDC polices regarding environmental protection during the construction, operation and
decommissioning phases of the proposed project.
• Climatic Conditions
The project area is characterized by two seasons (rainy and dry seasons) on the basis of
the rainfall pattern, which peaks in June and September with drier periods between
November and February. The high mean annual rainfall (above 2200mm) and its pattern
of distribution influences other environmental parameters including ambient temperature
and relative humidity. Humidity is high during the rains (above 95%) dropping to about
86% in the dry season. The generally high temperatures of the area (up to 34 oC) are
typical of its tropical location. Wind speeds are moderate and calm periods occupy up to
42% of the time. Southwesterly winds prevail during the rainy season attaining speeds of
up to 0.3-3.2m/s around Ahoada.
• Air Quality
Ambient air quality parameters show that values for air pollutants (SPM, NO2, SO2, HC,
CO) are consistently within the permissible limits of the FMENV indicating fairly pristine
conditions in terms of air quality. Noise levels in and around the project location lie within
national regulatory limits.
• Vegetation
The vegetation types of the area include freshwater swamp/riparian forest, lowland forest
(mixed tropical rain forest), farmland / bush fallow mosaic and re-growth vegetation.
Floristic composition of the fresh water swamps is fairly diverse and dominated by the
raphia palm species, Raphia hookeri in terms of abundance. Open and un-stratified
secondary forest/fallow mosaic characterized by numerous stands of the oil palm, Elaeis
guineensis, dominate the landscape of the immediate project community. Isolated
patches of lowland rainforest randomly dispersed within this mosaic attest to a long and
sustained human-induced forest depletion. Within the homestead, traditional tree crops
(cola, pear, mango, plum) and cultivated plants provide subsistence and food. Plant
pathological conditions are mostly leaf spot diseases of fungal aetiology consistent with
the high humidity and typical for other areas of the Niger Delta.
• Wildlife
Civet cats (Viverra civetta), grey parrots (Psittacus erithacus) and bigger game
previously abundant in the area have reportedly become rare. The presence in large
numbers of rodents in particular, and the near absence of the bigger mammals which
make up a typical rainforest wildlife are indicative of the changes in land cover/vegetation
forms over the years. Typical high rainforest wildlife has become replaced over the years
by grassland-adapted species, mainly rodents such as grasscutters and the giant rats.
The Bates dwarf Antelope Neotragus batesi is fairly common in the area. Excessive
exploitation and habitat change has reduced the abundance, kill rate and size-at-capture
of traditional wildlife.
• Geology/Hydrogeology
Geologically, the area is underlain by quarternary sands belonging to the Sombreiro
deltaic plain of the Niger-Delta basin. Stratigraphy revealed that the site is covered by
loose light brown sand, underlain by about 4.5 m thick soft to firm brownish grey sands.
Static Water Levels (SWL) for the area vary from 0.75 – 1.35m allowing the communities
to extract water for domestic use from the relatively shallow aquifers Groundwater flow
direction is south eastwards in the area. The ground water exhibits freshwater
characteristics with values within recommended limits for drinking water (FEPA, WHO).
Faecal pollution indicators such as Escherichia coli, Streptococcus faecalis and
Clostridium perfringens were not detected nor were fungi isolated in borehole water
samples.
• Soil Characteristics
The soils of the location are predominantly loamy sand at top and mid-depth horizons
and sandy clay loam at bottom soil horizons. They are Entisols typical of the Ahoada –
Idu Ekpeye axis, greyish brown in the upper surface layers (10 YR 4/2) and tending to
grey in the deeper strata (5 YR 4/1). Porosity is moderate to high on the surface,
decreasing towards the bottom layers. The soils show moderate to high bulk densities
ranging from 1.24 – 1.32 gcm3 in the surface layers to only slightly lower values of 1.24 -
1.30 gcm3 in the bottom layers. Soil pH varied from extreme (3.98) to moderate acidity
(5.60) in the topsoil horizon. Proportion of organic carbon (approx. 14%) and levels of
nitrate-nitrogen, available phosphorus, and sulphate concentrations indicate a fairly
adequate nutrient base for soils of the area. The low oil and grease concentrations from
this area indicate that the soils are still relatively free of hydrocarbon contamination.
Heavy metal concentrations fell within the range of values reported for similar
ecosystems in the Niger Delta. Of significance is the low proportion of hydrocarbon
degraders among both fungi and bacteria in the soils of the area. These low values,
generally below 0.025%, indicate absence of hydrocarbon contamination of soils.
• Hydrobiology
Hydrobiological parameters were found to be conducive to aquatic life. Values of pH,
dissolved oxygen, and nutrients are at levels that should promote reasonable aquatic
productivity. Concentrations of phyto and zooplankton as indicators of aquatic production
are compatible with the lotic (flowing) nature of the river. Coliform loads indicate faecal
pollution of the river water incompatible with its use for drinking and domestic purposes.
Oil and grease contents exceed values permissible by national regulation. Sources of oil
and grease have not been determined but may not be unrelated to urban and industrial
activity in the area. Proportions of hydrocarbon-utilizing fungi and bacteria, however,
remained low (<0.1%) in spite of the relatively high oil and grease content. Levels of
alkaline earth metals in the sediment and nutrients are consistent with the freshwater
nature of the Sombreiro at the location and are considered adequate for the sustenance
of aquatic biota. Sediment microbial load is significantly higher than those of surface
waters consistent with microbial retaining character of detritus. The proportion of
hydrocarbon degraders in the sediment was low (<0.1%) in line with the low values
obtained for the surface water
• Fisheries
The project location with its freshwater swamps and grass/sedge-lined banks provide
suitable habitat for a wide variety of fish species. Twenty-nine fish species representing
thirteen families occur in the fish assemblage of the project area. Fishing is carried out
on an artisanal basis mainly for subsistence or as an occasional undertaking deploying
only traditional gears such as dug-out canoes, basket traps, cast nets, set nets and hook
and line. Species targeted include mainly mid-water species such as tilapias and swamp
dwellers such as the Clariidae. Catch-per-unit of effort is very low and does not exceed
an average of 4kg per person daily. Total average daily fish catch from the area is
estimated at not more than 20 kg of fish for most parts of the year.
The power structure of the community has the paramount ruler at the apex. The council
of chiefs, elders, CDC, youth leaders, women leaders and age grades assist in decision-
making and governance.
Christianity and traditional religion are the two major religions practiced. The Anglican
denomination is the most prominent church in Ihuowo. However, belief in deities and
“Juju” was found to be very strong, hence the existence of several shrines, sacred
forests and mystic water bodies.
• Demographic Characteristics
The current population estimate for Ihuowo is 5215 people. (Projections of 1991 census
figures, using 2.83% growth rate). Most households had 6-10 persons per household.
The population structure was bottom-heavy, as expected. Age bracket 0-14 made up
47.3%, almost half of the total population, while the 15-24-age bracket made up 24.3% of
the population. This age bracket (15-24) is considered very sensitive, being mostly
dependent students, dropouts and apprentices in their most volatile and venturing
phases of life, who commonly occupy the frontiers of youth restiveness.
About 55% of the respondents in the project area were married while 18.3% were single.
Among the remaining respondents 17.7% were divorced while 9% were widowed.
Polygamy is also practiced.
• Social conditions
The income of the respondents is generally low. More than 60% of the respondents
earned below N5,000 as monthly income. Most community members live in their own
houses. The majority of houses are of the modern type, built with cement blocks and
roofed with zinc plated corrugated iron sheets. However, several mud houses were
observed. Over 90% of the households in the community depend on hurricane lanterns
for lighting, while the rest rely on generators. Ihuowo is not connected to the national
electricity grid. Firewood is the major source of cooking fuel.
The major means of transportation is bicycles and commercial motorcycles. A very small
percentage of the respondents use motor vehicles. Canoes are also other means of
transportation to farms and fishing grounds. The community is accessible by road all
year round, although the main road linking Ahoada to Ihuowo was in a poor state of
disrepair.
The number of people with no form of formal education is exceptionally high, depicting a
low level of functional literacy. Ihuowo has a primary school but no secondary school.
Secondary school pupils walk daily to Edeoha, a neighbouring town about 9 km away.
There are enough classrooms in the primary school in Ihuowo.
Farming is the major occupation in the area. This is supplemented with fishing, palm
wine tapping and palm kernel processing. In addition, communities practice hunting,
logging and other traditional occupations commonly practiced in fresh water forest areas.
Other income generating activities found were contracting, welding, motor mechanics
and carpentry, civil service jobs in the Local or State government service, company
employees as well as teaching.
Cassava is the major crop cultivated in Ihuowo. Other crops are plantain, banana, okro,
vegetables, cocoyam, yam and maize cultivated mainly for subsistence. Local livestock
and fish rearing are practiced. The most popular livestock found in Ihuowo were local
fowls and goats. Females are as active as their male counterparts in farming activities.
Decreasing agricultural production was expressed as a major concern, which was
attributed to loss of soil fertility, gas flaring and oil pollution. Other reasons include
population pressure, pests and diseases, erosion, negative attitudes towards farming as
well as inadequate labour supply.
• Disease Pattern
Infectious diseases accounted for 80.24 % of the overall disease pattern in the
community. Major infectious diseases include malaria (46.16%), diarrhoea (20.5%), and
respiratory tract infections (13.58%). The leading causes of death among children under
five years of age were infectious diseases such as malaria, febrile convulsion, measles,
and diarrhoeal diseases, while in adults they were malaria, typhoid fever, tuberculosis,
hypertension and diabetes.
The prevalence of these infectious diseases could be due to the poor sources of
domestic water, unsanitary waste disposal and the abundance of disease vectors in the
area. The respiratory function tests using the peak flow meter revealed that in all the age
groups, there were compromised lung functions either due to smoking habits, contact
with smoke from cooking, fish processing or vehicular emissions.
The healthcare needs of the people are catered for by the NYSC Community Health
Centre and via trado-medical practices.
• Lifestyle / Habits
Starchy foods such as cassava, rice, yam and plantain are consumed in various forms.
The sources of animal proteins include seafood (fish, shrimps, crayfish) and snails etc.
Acute and chronic under-nutrition is prevalent in the area.
About 49% of adults drink alcohol, 10.1% smoke cigarettes while 4% snuffed tobacco.
No female among the respondents smoked cigarette.
About 20.5% and 9.1% of the community members were aware of the existence of
HIV/AIDS and gonorrhoea respectively. Most of the people had one sexual partner with a
few having two or more.
The immunization coverage of children under five years in the area were BCG 70%, oral
polio 80%, and DPT 65%. The coverage for yellow fever and hepatitis immunization was
very poor accounting for less than ten percent.
E.S.4.0 CONSULTATION
The identified stakeholders for this study were Government (Federal, State and Local),
Regulators (FMENV, DPR, Rivers State Ministry of Environment), Ihuowo community,
CBOs, NGOs, Government agencies, consultants, etc. The type of consultation
conducted was an interface meeting with the community and identified stakeholders to
obtain their issues and concerns on the proposed project.
• Pre-Construction Phase
Additional land take area of 80m2 could be required on a temporary basis for contractor
equipment lay down. Third party agitations may arise from land disputes, wrong
stakeholder (land owners) identification, leadership tussles within the community and
issues of compensation.
• Construction Phase
Clearing of vegetation in the ROW and the 80 m2 contractor lay down area may result in
potential negative impacts such as exposure of workers and community members to
attack by poisonous snakes, bees, scorpions, and other wildlife. Injuries from the sharp
objects used during manual vegetation clearing may also result. Opportunities for
business and employment due to vegetation clearing constitute positive impact.
It is envisaged that the project could create employment opportunities for about thirty-five
persons including Ihuowo community members. This is a positive impact of the project.
However, labour requirements could lead to increase in social vices such as violence,
drug/alcohol abuse, teenage pregnancies, prostitution and third party agitation over
employment issues.
Potential negative impacts from excavation and trenching include impairment of water
quality and interference with river-based traditional occupations such as fishing, cassava
and palm produce processing. Aquatic productivity and fisheries may also be disturbed
all of which will lead to third party agitation.
Site fabrication with generation of high intensity welding flash may lead to burns and
injuries from welding sparks. Radioactive emission during radiography (non-destructive
testing) may potentially cause genetic mutation in humans.
Cutting of the existing pipeline after flushing may potentially contaminate surface/ ground
water and soil from the residual water flow back. Pulling out of the pipeline section to be
replaced will temporarily impair the Sombreiro river quality through increased turbidity.
Third party agitation may arise over these issues and the inheritance of disused pipeline
sections. Pipeline laying, tie-in and backfilling have the potential to temporarily impair
water quality, block waterways increasing the possibility of maritime accidents.
• Operational Phase
The potential negative impacts during the pipeline operations/ maintenance include
contamination of soils, sediments, surface/ground water from oil spill incidents and wash
out from pigging operations as well as destruction of assets and properties from oil spill
fire outbreaks. These impacts were rated as moderate
• Decommissioning Phase
The decommissioning of the replaced pipeline section will be tied to the ultimate
decommissioning of the entire 33.4km Okordia – Rumuekpe pipeline.
To mitigate third party agitation that could arise from the temporary landtake, SPDC shall
ensure identification of the relevant stakeholders and legacy issues, regular consultation
with stakeholders (Government, Community, NGOs, CBOs etc.) and adequate/prompt
compensation to affected land owners/parties.
The potentials for exposure of workers and community members to attack by poisonous
snakes, bees, scorpions, other wildlife and contact with poisonous plants shall be
mitigated by providing workers with PPE (coveralls, jungle boots, hard hat and gloves).
Additionally, SPDC shall create awareness among workers and communities on the
likelihood of this exposure and provide first aid measures/ MEDEVAC.
Injuries from the use of sharp objects in clearing shall be mitigated by providing workers
with adequate PPE (coveralls, jungle boots, hard hat and gloves) and holding safety
briefing before commencing site-clearing activities.
The impairment of water quality by increased turbidity could interfere with river based
traditional occupations such as fishing, cassava/ palm produce processing and lead to
third party agitations. To mitigate this impact, SPDC shall provide potable water to
affected persons during water-impairing operations such as excavation, pulling off the
old pipeline section and backfilling. In addition, affected parties should be identified and
compensated.
SPDC shall activate her Emergency Response and Contingency Plan to mitigate the
impacts of any incidents such as oil spill and fire which may lead to loss of assets, etc.
The design of the project had incorporated mitigation measures against potential impacts
identified at the conceptual phase.
E.S.8.0 CONCLUSION
This environmental impact assessment has shown that the project could be executed
and operated with minimal negative impact on the environment by implementing
recommended mitigation measures, EMP and other provisions of this EIA.
1.0 BACKGROUND
The Shell Petroleum Development Company of Nigeria Limited (SPDC), in its capacity
as the technical operator of the NNPC/TotalFinaElf/NAOC Joint Venture and on behalf of
its partners plans a project for the replacement of the river crossing section of the 14”
Okordia – Rumuekpe Trunkline.
The 14” x 33.4 km Okordia - Rumuekpe pipeline evacuates fairly stabilised crude oil
production from the Adibawa and Ubie Flowstations into the Trans-Niger Pipeline (TNP)
network at Rumuekpe Manifold. Current production from both Adibawa and Ubie Flow-
stations is about 12,800 bpd. The pipeline was commissioned in 1981 and has a design
life of minimum 25 years. The pipeline traverses mainly land terrain and at Ihuowo, it
crosses the Sombriero River.
The environmental assessment covers the biophysical, social and health impacts of the
proposed project. This Environmental Impact Assessment (EIA) was done as a desktop
study (with approval from the Federal Ministry of Environment [FMENV]) using existing
baseline data from the following FMENV approved EIA reports:
1. Gbaran/Ubie IOGP (FMENv/CONF/EIA/123.423/Vol. 11/290 of 9/6/2005)
2. Rumuekpe Cuttings Re-injection, December 2002
3. Akri/Oguta Field Development
4. 20`` X 37 Km Kolo Creek – Rumuekpe Trunkline Replacement
(FMENv/CONF/EIA/123. 190/Vol. 1/1/164 of 3/5/2005).
The existing data was further updated through site visits and community engagement
(sensitization, Focus Group Discussion (FGD) and questionnaire administration).
• Use the existing baseline data to describe and characterise the study area;
This provides that the objective of solid and hazardous waste management shall be to:
• Identify solid, toxic and extremely hazardous wastes dangerous to public
health and environment,
• Provide for surveillance and monitoring of dangerous and extremely
hazardous wastes and substances until they are detoxified and safely
disposed,
• Provide guidelines necessary to establish a system of proper record keeping,
sampling and labelling of dangerous and extremely hazardous wastes,
• Establish suitable and provide necessary requirements to facilitate the
disposal of hazardous wastes;
• Research into possible re-use and recycling of hazardous wastes.
1.4.5 FEPA National Guidelines for Spilled Oil Fingerprinting (Act 14 of 1999)
This provides Guidelines for spilled oil fingerprinting applicable throughout Nigeria, in
order to improve the quality of the environment and to free it from pollutants and other
environmental and health hazards.
1.4.9 Oil Pipelines Ordinances (CAP) 145, 1956 and Oil Pipelines Act, 1965
The oil pipelines ordinance (CAP 145), 1956, as amended by the Oil Pipelines Act 1965
provides under Section 4(2) for a permit to survey (PTS) a pipeline route to be issued to
the applicant by the Minister of Petroleum Resources, for the purpose of transporting
mineral oil, natural gas, or any product of oil or gas to any point of destination to which
such a person requires such oil, gas or product, thereof, for any purpose connected with
petroleum trade or operations. Such a survey should include the approximate route or
alternative routes proposed, in order to determine the suitability of the land for laying and
construction of the pipeline and ancillary installations. Section 15(1) of the Oil Pipelines
Ordinance (CAP) 145 prohibits the holder of an OPL to enter upon, take possession of or
use any of the following lands unless the occupiers or persons in charge thereof have
given their assent:
a) Any land occupied by a burial ground or cemetery,
b) Any land containing any grave, grotto, and trees or thing held to be sacred
or the object of veneration,
c) Any land under actual cultivation.
contractors. Section 21 - 24 address the issues of licensee interfering with protected and
productive trees, venerated objects, fishing rights and safety of navigation while Section
25 requires the licensee to ''adopt'' all practicable precautions, including provision of up-
to date technology approved by Director of Petroleum Resources, "to prevent the
pollution of inland waters, rivers, creeks, the territorial waters of Nigeria or the high seas
by oil, mud or other fluids or substances which might cause, harm or destruction to
freshwater marine life, and where such pollution occurs or has occurred, shall take
control and, if possible, end it...". Where the licensee is not able, for whatever reason, to
comply with the provisions of sections 21-24 of these regulations, he shall pay adequate
compensation of the contravention to those concerned.
In section 44, the licensee is required to comply with all existing safety regulations and
all such instructions as may from time to time be given in writing by the Director of
Petroleum Resources for securing the health and safety of persons engaged on or in
connection with operations under his license or lease. An offshoot of this Act was the
Environmental Guidelines and Standards for the Petroleum Industry in Nigeria
(EGASPIN) published by the Department of Petroleum Resources in 1992, which was
revised in 2002. The DPR Environmental Guidelines and Standards of 1992 stipulated in
Part VIII (A), the manner of preparing EIA for Exploration and Production operations. The
content of detailed EIA Report is outlined in Section 5 of Part VIII (A) of the guidelines.
Although the EIA decree No 86 of 1992 is the substantive law that regulates the sitting of
industrial projects that impinge on environmental elements in Nigeria, with part of the
project in Rivers State, this edict has a role to play in the overall EIA process as a matter
of law. The Edict setting up the Rivers State Environmental Protection Agency (RSEPA)
captioned as Edict No 2 of 1994 outlines the primary responsibilities of the agency,
which is to protect and develop the general environment of Rivers State.
(iii) Convention Concerning the Protection of the World Cultural and National
Heritage Sites (World Heritage Convention) and
The Bonn Convention concerns the promotion of measures for the conservation
(including habitat conservation especially for endangered species listed in Bonn’s
Appendix 1) and management of migratory species.
1.4.15.3 Convention Concerning the Protection of the World Cultural and Natural
Heritage Sites (or World Heritage Convention)
The convention sets aside areas of cultural and natural heritage for protection. The latter
is defined as areas with outstanding universal value from the aesthetic, scientific and
conservation points of view.
The convention focuses attention on the hazards of the generation and disposal of
hazardous wastes. The convention defines the wastes to be regulated and control their
trans-boundary movement to protect human and environmental health against their
adverse effects.
Book vols. I -III of 1991. Potential issues considered for EA in the upstream oil and gas
industry include the following:
• Biological Diversity
• Coastal and Marine Resources Management
• Cultural Properties
• Hazardous and Toxic Materials and
• International waterways.
The IUCN in conjunction with the Oil Industry International Exploration and production.
Forum presented a set of guidelines for oil and gas exploration and production in
mangrove areas. These guidelines are aimed at conservation of mangroves and
enhancing the protection of marine ecosystems during E & P activities. The document
also discusses the policy and principles for environmental management in mangrove
areas as well as EIA procedures, Environmental Audit and Monitoring.
SPDC operates under the guidelines of Shell International and complies strictly with
them. Where national standards and regulations are more stringent than Shell
guidelines, SPDC’s policy is to comply with the existing national legislation. It is SPDC's
policy that all activities are planned and executed in a manner that:
• Preserves the health, safety and security of its employees, the employees of
SPDC contractors, and all members of the public who may be affected by
SPDC operation.
• Identify any such interface for the complete life cycle of both new and existing
facilities and operations;
• Limit the nature and extent of any residual negative impacts, however
caused, such that they are as low as practicable;
• Leave the environment at the end of the useful life of any operation in a
condition suitable for future use;
• Track and maintain records of waste streams and provide an auditable trail as
to their management and disposal.
The Terms of reference for this EIA are based on standard EIA requirements and
stakeholder engagement (community representatives, Federal Ministry of Environment
(FMENV), Rivers State Ministry of Environment (RSMENV) and Department of
Petroleum Resources (DPR).
The summary of the scope of the EIA as contained in the Terms of Reference (TOR) is
as follows;
EIA Scope
• Baseline Data Collection
o Literature review.
o Site visits.
o Focused Group Discussions (FGDs) to update information on socio-
economics and health status.
• Questionnaire administration (semi-structured).
• Assessment and Prediction of Potential Impacts.
• Determination of Appropriate Mitigation Measures.
• Environmental Management Plan.
Biophysical
• Climate and meteorology.
• Air quality and noise.
• Vegetation.
• Land use/cover.
• Wildlife.
• Geology and hydrogeology.
• Soil/sediment quality.
• Aquatic studies.
• Groundwater quality.
• Hydrobiology and fisheries.
Social
• Demography,
• Social conditions of communities,
Health
• Socio-economics/vital health statistics.
• Individual/family/community health determinant.
• Environmental health determinants.
• Institutional health determinants.
• Knowledge, attitudes and practices.
2.0 INTRODUCTION
The Shell Petroleum Development Company of Nigeria Limited (SPDC), on behalf of the
Joint Venture Partners (Nigerian National Petroleum Corporation, Nigerian Agip Oil
Company, and TotalFinaElf), intends to embark on a river crossing pipeline replacement
project of the 14” Okordia – Rumuekpe Pipeline at the Sombriero River Crossing, in
order to comply with the statutory 5-yearly pipeline inspection requirement. The
proposed project will involve the replacement of 44 m Sombriero River Crossing faulty
section of the 14” x 33.4 km Okordia – Rumuekpe Pipeline.
(pigging), pre-IP runs are required to get the pipeline ready for the statutory 5-yearly IP
inspection. Previous pre-IP cleaning of this pipeline resulted in pigs getting stuck leading
to production deferments and costly operations to retrieve the pigs so as to restore the
pipeline transport capability. An analysis of the retrieved pig and the pipeline profile
shows a very steep gradient at the Sombriero River crossing, which could have
contributed to the difficulties in cleaning this pipeline. It has been resolved therefore that
the river crossing section at the Sombriero crossing be replaced with a less steep
gradient for improved sweep of debris through the crossing point during pigging
operations
Fig. 2.1: Location Map of the Proposed Okordia – Rumuekpe River Crossing
Pipeline Replacement Project
Movement of the 14” diameter line pipes and other construction equipment to site will be
by trucks from the Contractor’s Storage/transport facility. Movement of personnel (~25
persons) will be via a combination of trucks and buses to the site. Transportation of the
coated pipes shall be in accordance with 1API RP 5LW (recommended practice for
transportation of line-pipes). All racks, lifting and handling equipment shall be kept in
good condition, so as to prevent injury to the coating. The use of tongs, bare pinch bars,
chain slings, pipe hook without proper padding, ropes, chains or wire cables or any such
other handling equipment shall not be permitted.
1
API RP 5LW – A recommended practice issued by the American Petroleum Institute for
transportation of line pipes. API is one of the international standards used in Oil and Gas industry
worldwide.
Ground
+7m 30 m +7m level
Pipeline
Profile
SOMBRIERO RIVER
Land-take
There shall be no route survey of the pipeline since the proposed pipeline replacement
section is on an existing Right-of-Way (ROW). The existing 15 m corridor (width) of the
ROW should be adequate as laydown area for the pipeline replacement construction
equipment. In the event that this is not adequate, an additional 80 m2 land on any side of
the river may be acquired as part of the temporary laydown area for construction
equipment.
The excavation on the land sections shall be carried out with an excavator. The
excavated section shall be manually freed of roots, stones, or other hard objects that
may damage the pipe or its coatings. The maximum width of the excavated section shall
be 3 m with a minimum depth of 1 m.
The stringing and welding of the pipelines shall be done on the ROW. Visual inspection
and 100% radiography (non-destructive testing) of the welds shall be done as the
welding progresses. Weld repairs shall be carried out where necessary, prior to pipeline
pressure testing.
The installation of the newly constructed river crossing pipeline section (44 m) shall be
by surface pull technique using a crane. The pipe shall be pulled from the ROW and
carefully lowered into the trench such that it lies naturally along its entire length on the
bottom of the trench. Close observation of the lowered pipe shall be maintained to
ensure that the pipeline profile is as designed. The new section shall be tied-in (welded)
to the existing pipeline at both banks of the river (~ 7 m away from the river bank). All
field welds shall be coated using heat-shrinkable sleeves.
2.2.9 Backfilling
After the pipe has been inspected to confirm that it has been laid to the correct profile,
the pipeline trench will be backfilled using the previously excavated materials. Backfilling
on land shall be done manually, while the bucket dredger would be used for the river
trench.
The types of wastes generated during the construction activities shall be classified as:
solid wastes, liquid wastes, and gaseous wastes.
The solid wastes will include: excavated pipe, dredge spoil, food waste, papers, rags,
empty cans and bottles, pipe off-cuts, coating tapes, electrode butts and general
garbage. Liquid wastes will include: sewage, spent chemicals (adhesives, lubricants,
grease, detergent solutions etc). The gaseous waste will include dust particles and
smoke from heavy construction machinery. All these categories of wastes shall be
managed according to SPDC Waste Management (Appendix 2.1) and FEPA Guidelines.
2.2.13 Operations/Maintenance
After commissioning, the pipeline shall be hooked on to the cathodic protection system
for external corrosion protection. It shall also be placed on the SPDC bi-monthly routine
pigging for internal cleaning and debris removal. The five-yearly statutory internal
inspection by intelligent pigs for integrity checks shall be carried out. The pipeline will be
placed on the SPDC six-monthly cathodic protection and coating integrity survey
programme. The ROW shall be manually cleared of vegetation for maintenance and
emergency response purposes, as and when necessary.
The environmental baseline data in this report was culled from the following studies and
publications:
• Environmental Impact Assessment of the 20’’ X 37km Kolo Creek –
Rumuekpe Trunkline Replacement Project, Oct 2004
• Environmental Baseline Report (Wet Season) for the Ubie Node IOGP EIA,
December 2004.
The physico-chemical parameters measured and the analytical test methods employed
are summarised in Table 3.2.
Surface water/ Hydrodynamics Observations, Water Sampler, Current Meter, Secchi Disc,
pH Meter, DO Meter, Sediment Grab, TDS Meter, Turbidimeter and
Conductivity Meter.
Soil Quality Soil Sampling with an auger, and description of each sample with
British colour chart.
Microbiology Water Sampling with Hydrobios water sampler into sterile McCartney
bottles; Soil sampling with soil auger into aluminium foil; Sediments
sampling with van Veen grab sampler into aluminium foil.
Aquatic Studies
Sediment (Benthos) Collection with Van Veen grab
Phytoplankton Collection with plankton net
Zooplankton Collection with plankton net
Fisheries Observation, Collection, Interviews and Laboratory Analyses.
Social Status Reconnaissance Survey and Ground-truthing, Key Informant
Interviews, Focus Group Discussion (FGD), Direct Observation,
Administration of Structured Questionnaires and Literature Review.
Fig. 3.1: Sampling Locations for the Okordia – Rumuekpe Study Area
examination of the health records of the NYSC Community Health Centre at Ihuowo and
interviews with the resident NYSC health personnel of the centre.
b) Location within the tropical latitudes and the apparent movement of the sun which
determine ambient temperatures in the region
c) The relative stability of the Inter Tropical Convergence Zone (ITCZ) over the area
which controls the duration of the seasons [Federal Department of Meteorology,
Oshodi, Lagos – (Now Nigerian Meteorology Agency - NIMET)]
3.3.1.2 Rainfall
The mean annual rainfall in the region is high (above of 2200M) mainly due to the
moisture-bearing southwest trade winds blowing from the Atlantic Ocean. The rain falls
throughout the year peaks in June and September and lower amounts from November to
February (Fig. 3.2). Two seasons namely, wet and dry, characterize the area: the wet
season which extends from April to October and the dry season from November to
March.
800
700
600
Rainfall, mm
500
400
300
200
100
0
Jan. Feb. March. April. May June July Aug. Sept. Oct. Nov. Dec.
Months
Fig. 3.2: Rainfall Distribution in the Project Area
(Source: Federal Department of Meteorological Services, Oshodi, Lagos).
100
90
80
R elat ive humidit y( % )
70
60
50
40
30
20
10
0
1000
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
2100
2200
2300
2400
100
200
300
400
500
600
700
800
900
T ime ( h)
3.3.1.4 Temperature
The generally high temperatures of the area are typical of its tropical location. Air
temperatures range from 24.5 - 29.00C in the rainy season increasing to between 33.0
and 34oC in the dry season. Diurnal changes in air temperatures of the area are depicted
in Fig. 3.4 which shows fairly stable temperatures (24.5 – 280C) between 2100 and 0800
hrs increasing to (29 – 320C) between the hours of 0900 and 1700 hours.
40
Temperature
30
20
10
0
1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 100 200 300 400 500 600 700 800 900
Time
3.3.1.5 Wind
Southwesterly winds prevail during the rainy season in the general area ranging in speed
from 0.3 - 3.2 m/s around Ahoada. In the dry season, the predominant winds may attain
moderate speeds of between 3.4-5.4 m/s. Calm periods prevail for about 41.7% of the
time (Fig. 3.5)
Wind directions in the rainy season in the area are mainly Westerly (W), South Westerly
(SW), North Westerly (NW) and Southerly (S). In the dry season, they are more of
Southwesterly (SW), followed by Westerly (W), Northwesterly (NW) and Southeasterly
(SE) directions.
41.70
3 5
1 Wind
2 Speed
4
Fig. 3.5: Wind Distribution Pattern (Rose) for Proposed Project Area (Dry Season)
(Source: Baseline Studies Gbaran/Ubie IOGP, SPDC, 2003)
3.3.1.6.1 Gases
The low concentration of ammonia and carbon monoxide further highlight the pristine
nature of the area in terms of atmospheric pollutants. The high solubility of these gases
in water and the heavy precipitation over much of the year contribute to the effective
dispersal of whatever CO is generated from flares and fossil fuel combustion.
Floristic composition is fairly diverse and dominated by the raphia palm species, Raphia
hookeri in terms of abundance (Table 3.6). The forest physiognomy shows a
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project 13 of 84
CHAPTER 3 Description of the Environment
characteristic three-layer structure (Fig. 3.6). The emergent layer is approx 28-35m high,
dominated by Alstonia booneii, Piptaderiastrum africanum, Klainedoxa gabonensis. This
canopy is open and discontinuous. The second canopy layer is completely closed and
the close contact of the sclerophyllous leaves of species in this layer make penetration of
light into the ground floor of the forest difficult. Species in this layer are between 15 – 22
m tall and include Cleiostopholis patens, Raphia spp., Anthocleista vogelii, Uapaca
heudelotii, Pandanus sp.; Grasses, (Sporobolus pyramidalis, Cynodon dactylon,
Andropogon gayanus, Panicum maximum) ferns and sedges (Kyllinga nemoralis)
dominate the ground herbaceous layer.
Alstonia boonei
K. gaboensis
Raphia
hookeri
Pandanus sp
Plate 3.3: Closer View of Swamp Forest Vegetation at Pipeline Crossing on the
Sombreiro River (Note Dense Stands of Raphia) (Photo from site visit)
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project 15 of 84
CHAPTER 3 Description of the Environment
Of importance is the patchy and discontinuous nature of this forest type in the area.
Stages of re-growth and maturity differ at different places along both sides of the
pipeline. Human activity mostly logging and extensive agriculture has greatly depleted
and transformed the initial structure and probably species richness of this vegetation
type in the locality. This is evident in the expanses of farm lands and other intervention
which have been concluded at the expense of the original lowland forest. At the present
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project 16 of 84
CHAPTER 3 Description of the Environment
rate of exploitation tropical rain forest may disappear from the locality with the next two
decades except conscious conservation measures are put in place.
Antiaris africana
Triplochiton scleroxylon
Nauclea diderrichii
Alstonia boonei
Elaeis guineensis
Lophira alata
Manihot esculenta
Dioscorea sp.
and Fimbristylis spp.; Ferns: Diplazium sammantii, Pteridium aquilinum, Selaginella spp.,
and Pityrogramma calomelanus.
Plate 3.4: Stagnant Pool near Pipeline Crossing with Floating Aquatic Macrophytes
3.3.1.9 Phytopathology
Disease symptoms and their causative microorganisms isolated from diseased plants in
the project area are presented in Table 3.9. Visual and on-sight pathological
assessment showed that leaf spots were the most dominant disease symptoms affecting
several plants. Several organisms are associated with these symptoms which, on
account of the high humidity of the area, are mainly of fungal aetiology. Disease
prevalence in crops and plant species are comparable for the two seasons, both in their
nature and severity.
The state of health of the overall vegetation and the commonest species appeared quite
typical for the region. None of the diseases isolated were unusual to the plant species.
The area for the Sombriero River pipeline crossing project captured by satellite imagery
covers approximately 252.76km2 bounded by coordinates 457710E – 476635E and
102874.559N – 116230.484N. Seven main categories of land cover were identified
namely, Water, Forests I and II, Farmland, Sparse Vegetation, Bare Soil and
Urban/Industrial land covers. Fig. 3.8 shows the relative coverage ascribed to the
different land use forms in the area for the year 2002 as follows: Forest II (50%),
Farmland (4%), Forest I (9%), Urban/Industrial (5%), Sparse Vegetation (18%), Bare Soil
(13%) and Water (1%).
Table 3.9: Diseases of Crops and Plants within the Pipeline ROW, and Causative Agents
Table 3.10: Heavy Metals Content (mg/l) of Plant Species from the Study Area
Species V Ni Pb Cr Zn Cd Fe Mn Cu Hg
Alchornea cordifolia (Christmas bush) 0.04 0.37 0.03 BDL 29.65 BDL 2.7 34.45 6.82 BDL
Alchornea cordifolia (Christmas bush 0.01 0.14 BDL BDL 5 BDL 1.35 0.25 4.81 BDL
Raphia hookeri(Raffia palm) 0.02 0.16 0.03 0.008. 25.7 BDL 7.1 51 5.8 BDL
Pterocarpus santalinoides BDL 0.06 0.05 BDL 8.55 BDL 6.05 6.45 5.81 BDL
Antocleista vogelli (cabbage tree) 0.03 0.32 BDL 0.029 19.6 BDL 4.4 5.5 7.34 BDL
Diplazium sammanti 0.05 0.46 0.02 0.015 8.55 BDL 4.9 2.15 4.91 BDL
Costus afer (Ginger lily) BDL 0.24 BDL 0.002 2.1 BDL 5.15 3.7 5.61 BDL
Panicum maximum(Guinea Grass) 0.03 0.43 0.015 BDL 9.25 BDL 6.1 6.9 5.57 BDL
Panicum maximum (Guinea Grass) 0.07 0.1 BDL 0.021 11.8 BDL 4.6 7.4 6.03 BDL
Acroceras spp 0.04 0.3 BDL BDL 18.05 BDL 2.7 0.5 5.61 BDL
Manihot spp.(Cassava) 0.03 0.27 BDL 0.003 26.2 BDL 5.8 8.15 6.84 BDL
Manihot spp. .(Cassava) 0.02 0.11 BDL BDL 3.2 BDL 5.1 19.2 4.62 BDL
Harugana madagascariensis (Gum tree) 0.03 0.2 BDL BDL 34.35 BDL 1.9 8.6 5.59 BDL
Clappertonia ficifolia 0.04 0.16 BDL BDL 21.05 BDL 3.3 5.8 4.7 BDL
Cleistopholis patens (canoe wood) 0.03 0.25 0.01 BDL 20.55 BDL 5.85 14.2 5.65 BDL
Elaeis guineensis(Oil Palm) 0.17 BDL BDL BDL 12.9 BDL 16.3 19.1 2.6 BDL
Below Detection Limits of 0.01mg/l
(Source: Baseline Studies of Kolo Creek-Rumuekpe Trunkline Replacement Project, SPDC, 2004)
Vegetation
Forest II
Farmland 50%
4%
Water
Water body constitutes less that 1% of the landcover of the area ascribable mainly to the
Sombriero River. The trend indicates an increase in water cover of about 0.15% between
1986 to 2002 representing a land gain of 0.4 km2 during the period. This must have come
mainly from riverbank erosion which is a pervading problem in the Niger Delta.
Forests
Undisturbed forest (Forest I) has decreased in total land cover from 42.0 km2 or 16.61%
in 1986 to 23.47 km2 or 9.28% cover in 2002. Between 1986 and 2002, therefore, over
18.5 km2 or 44 % of this forest type has been converted representing an annual decline of
approx 1.2 km2. Continuing decrease in Forest I could be attributed to the continuing and
evident exploitation of this vegetation type for various purposes in the area. At this rate,
and projected over a 5-year period, much of the undisturbed forest would have been
converted by 2010.
Farmlands
Land under farming presently accounts for 11.32 km2 or 4.5% of the total land cover of
the area of interest. The trend shows that this represents an increase of over 2% from the
value of 2.13% in 1986. In effect, an additional 10 km2 of land has been converted to
agriculture over the period. Farming activities increase as a consequence of increasing
population and human habitation of the area. Projection to 2010 would indicate further
increase in acreage of land under agriculture. Farmlands consisting of cultivated crops
and plantations are widely distributed in the project area. The predominance of
subsistence agriculture with shifting cultivation as the dominant cultural land use
technique makes a huge demand on land.
Sparse Vegetation
Sparse vegetation also showed a sharp increase within the time period under
consideration. From a total land coverage of 27.3 km2 representing 10.79% in 1986, this
land cover type jumped to approx 44.76 km2 or 17.71% of the area in 2002. This
represents an annual increase of about 1.1 km2. At this rate of expansion and projected
over a 5-year period, sparse vegetation and disturbed forest would together account for
over 80% land coverage of the area of interest. The spread of sparse vegetation
indicates slow regeneration of the forests and the increased intensity of human
interference.
Bare Soil
Bare soil decreased from a coverage of approx 53.1km2 or 21.01% in 1986 to approx. 13
km2 or 32.9% in 2002. Decrease in bare soil is also attributable to human interference
which converts such land cover types to other uses.
50
45
40
Pe r ce nt age Ar e a Co ve r age
35
30
25
20
15
10
0 2002
1999
Water
Forest 1
Forest II
Farmland
Sparse Vegetation
1986
Bare Soil
Urban/Industrial
L a n d C o v e r / L a n d U s e Fo r m s
Fig. 3.9: Trends in Land Cover/Land Use in Project Area (1986 - 2002)
(Derived from: Time Lapse mapping of the 14” Okordia-Rumuekpe Pipeline Crossing at
Sombriero River, SPDC, 2005)
Urban/Industrial
Human habitation and other infrastructure in the form of roads, public and private
establishments and industrial facilities accounted for 13.82 km2 or 5.47% of the total land
cover of the project area in 2002. This represents an increase of over 5 km2 from the
values of 1986. On the average, therefore, over 0.3 km2 additional land has been
converted to urban /industrial uses in the area on an annual basis. The generally upland
nature of the area and availability of relatively adequate communication networks
encourages human and industrial settlement, which should be expected to increase in the
near future.
plants, medicinal plants and animal life. Their rapidly declining land coverage as shown in
the analysis under land cover makes their preservation an environmental imperative.
3.3.1.13 Wildlife/Biodiversity
Information on wildlife was gathered from interviews, field observations and published
literature. Wildlife here will be considered in the restricted sense to refer to the larger
vertebrates. The other organisms, mostly invertebrates, can be considered under
biodiversity. Table 3.11 lists the various classes of terrestrial vertebrates (amphibians,
reptiles, birds and mammals) present in the project area. The Muridae dominated the
wildlife of the area in terms of species representatives. Sustained exploitation through
hunting, trapping and human–induced habitat alteration have combined to threaten or
endanger several species. Hunters claimed that civet cats (Viverra civetta) and grey
parrots (Psittacus erythacus) had become rare while leopards (Panthera pardus) were no
longer observed.
The presence in large numbers of rodents in particular, and the near absence of the
bigger mammals which make up the typical rainforest wildlife are indicative of the
changes in land cover/vegetation forms over the years. Among the avian species, the
most abundant were those commonly associated with farmlands and villages while those
typical of the rainforest environments were lacking. Amongst the Reptilia, the pythons,
monitor lizards etc typical of the dense rainforests were rare and/or absent in the area.
Generally, new and emergent colonizers of farmlands, swamps and the sparsely
distributed secondary forests have replaced the wildlife associated with the tall trees and
canopies of the dense tropical rainforests.
The freshwater swamp forest occurring around Rumuekpe Elele Alimini axis provide
habitat for numerous amphibians, fishes, snakes and piscivorous birds. The big games
visit the swamps at night according to hunters’ reports during which time they may be
trapped or shot. The cultivated farmlands as well as the bush fallow provide cover and
feeding ground for rabbits, cane rats, shrews, hedgehog, porcupine, birds and snakes.
Some wildlife constitutes a problem to cultivated farmlands.
The hunters interviewed attributed the low kill rate of wildlife and their average small size-
at-capture to excessive exploitation through hunting and trapping for food or sale. This is
typical for many tropical habitats where continuous exploitation severely endangers the
local wildlife (Happold, 1987).
1 MAMMALIA (i) Muridae Common rat Rattus rattus Forests ground and Very common
farmlands
2 Spotted grass mouse Lemniscomys striatus Forests ground and Common
farmlands
3 Giant rat Cricetomys gambianus Forests ground, soil Common
burrows
4 Jumping mouse Rattus morid Forests ground and Common
farmlands
5 (ii) Sciuromorpha West African ground Squirrel Xerus crythropus Forests, farmlands, Very common
arboreal
6 Giant forest Squirrel Protexerus strangeri Forests, farmlands, Common
arboreal
7 Pets flying Squirrel Anomalurus peli Forests, farmlands, Common
arboreal
8 Niger Flying Squirrel Anomalurus freseli Forests, farmlands, Common
arboreal
9 Sun Squirrel Heliasciurus gambianus Forests, farmlands, Uncommon
arboreal
10 Grass Cutter Thryonomys sunderianus Forests ground and Very common
farmlands
11 (iii) Thryonomidae Bush tailed Porcupine Anthemrus africanus Forests ground and Common
farmlands
12 West African hedgehog Erinaceus albiventris Forests ground and Very common
farmlands
Crested Porcupine Hystrix cristata Forests ground Common
13 (iv) Chiroptera Hammer heeded bat Hypsignatus monstrous Forest arboreal Less common
14 Pets pouched bat Taphozous peli Forest arboreal Less common
15 Common African least nosed Hipposideros caffer Forest arboreal Less common
bat
16 Free tailed bat Macrochiroptera spp. Forest arboreal Less common
17 (v) Manidae The black bellied pangolin Manis tetradachyta Forest ground Less common
farmlands
46 Green-backed heron Butroides striatus Forests and farmlands “
47 Little African bittero Ixobrychus minutes Forests and farmlands “
48 (ix) Alcedinmidae Blue crested king fisher Halycon malimbicicus Farmlands, swamps “
49 Senegal kingfisher Halycon senegalensis Swamps, river banks “
50 (xi) Columbidae Laughing dove Stigmatopelia Forests and farmlands “
senegalensis
51 (xii) Anatidae African pigmy goose Nettapus auritus Swamps and River banks “
52 Water duck Anser spp. Swamps “
53 (xiii) Phasianidae Bush fowl Francohanus Forests, farmlands “
bicedcaratus
54 Crested Guinea fowl Gultera pucherani Forests, farmlands “
55 Jungle fowl Gallus gallus Forests, farmlands “
56 (xiv) Nectarinidae Olive bellied sunbird Cinnyris Chloropyguis Forests, farmlands Common
57 Copper Sunbird Cinnyris cupreus Forests, farmlands Very common
58 (xv) Muscippidae Spotted flycatcher Muscicapa strata Forests, farmlands Common
59 Fagans paradise flycatcher Tehitrea spp. Forests, farmlands Common
60 (xvi) Picidae Cardinal woodpecker Dendpicus fuscescens Forests, farmlands Common
61C REPTILIA (i) Aganidae Rainbow lizard Agama agama Forests, farmlands Very common
62 (ii) Geckonidae Forest gecko Hemidactylus gasciatus ‘’ Common
63 (iii) Sincidae Blandings kink Mabura blandingii ‘’ Very common
64 (iv) Columbridae The Boomsland Disphodus typus ‘’ Common
65 (v) Elapidae Green mamba Dendroapsis viridis ‘’ ‘’
66 Yellow cobra Naja nivae ‘’ ‘’
67 Forest cobra Naja melanolenca ‘’ Rare
68 Black spitting cobra Naja nigricollis ‘’ ‘’
(vi) Varanidae Nile Monitor Lizard Varanus niloticus “” Common
67D AMPHIBIA (i) Bufonidae Bufo regularis Forest ground Common
70 (ii) Rhacophonidae Tree frogs Hyperlolius spp. Forest and Swamps ‘’
71 Chiromantus spp. Forest and Swamps ‘’
72 (iii) Ranidae Forest frog Rama spp. Forest ground ‘’
73 Goliath frog Gigantorrim goliath Forest ground, swamp ‘’
During the dry season, the black kite, Milvanus migrans is the most abundant bird
species. Other birds which may be found in the general area in fair numbers include the
allied hornbill, Lophorerus semifasciatus, the pied crow, Corvus albus, the cattle egret
Bulbulcus ibis, the fowl, Francohanus bicedacaratus, and the guinea fowl Guttera
pulcherari.
3.3.1.14 Geology/Hydrogeology
Geologically, the area is underlain by quaternary sands belonging to the Sombreiro
deltaic plain of the Niger-Delta basin. Stratigraphy showed that topsoils are sandy clay in
nature while lower depths consist of sandy clay and sand. The particle size analysis of
borehole cuttings showed that the soil strata are made up of silt and sand with medium
dense grey white fine to medium sand predominating (Fig. 3.10)
Water Levels
Static Water Levels (SWL) for the area varies from 0.75 – 1.35m allowing the
communities to extract water for domestic use from the relatively shallow aquifers. This,
however increases the liability to pollution because of the nearness to the soil surface and
the nature of the overlying soil.
BH BH BH
0 Sandy Clay
Sandy Clay
Sandy Clay
Loam
0.3
Sandy Clay
Loam
Static water
level
Sandy
0.9
Static water
1.2 level
Sandy
1.5
Static water level
Key
Sandy Clay
Sandy
Y axis is in metres
BH- Boreholes
BH2
BH 3
1.1 m 0.75 m
W E
Equipotential lines
join areas of equal
Hydraulic gradient
1.35 m
Direction of water flow (South-East wards)
BH1
_____________________________________________________________
*The Federal Ministry of Environment accepts WHO standards
Table 3.14: Microbial Contents of Borehole Waters from around the Project
Location
Sample Mean HF2, HDB3, HDF4, CC5 TS6 CF7 EC8
type HB1, cfu/ml cfu/ ml cfu/ml
cfu/ml
3.3.1.15 Soils
Rainforest soils constitute over 90% of soils in the project area. They are mineral soils
formed as a result of the weathering of siliceous sandstone fragments over varying
periods of time and range from the recently formed Entisols and Inceptisols, to the more
mature Alfisols and Oxisols.
Nature of Soil
The soils of the location are predominantly loamy sand at top and mid-depth horizons and
sandy clay loam at bottom soil horizons (Table 3.15). Percentage sand content varies
from a mean of 59.26% in the topsoil, 44.26% in mid-depth and 39.7% in the bottom soil
horizons. Similar textural classifications of the soils were obtained in the dry season.
Mean percentage clay contents also vary with depth: 12.48% in the topsoil, 26.16% at the
mid-depth and 30.90% in bottom soil horizons. As typical for tropical soils, no significant
textural changes were observed over the two seasons (Ogunkunle, 1983).
1
Heterotrophic bacteria
2
Heterotrophic fungi
3
Hydrocarbon utilising bacteria
4
Hydrocarbon degrading fungi
5
Coliform count (MPN/100 ml)
6
Total Streptococcus faecalis count (MPN/100 ml)
7
Clostridium perfringens count (MPN/100 ml)
8
Escherichia col count (MPN/100 ml)
Colour
The soils of the area show colour variations with depth. They are Entisols typical of the
Ahoada – Idu Ekpeye axis, greyish brown in the upper surface layers (10 YR 4/2) and
tending to grey in the deeper strata (5 YR 4/1).
Porosity
The soils are moderate to highly porous at the surface layers decreasing in porosity
towards the deeper soil strata. The highly porous soils around Ahoada contain many
macropores, which allowed easy passage of water and mineral salts that could be lost by
leaching through the profile. The porosity of tropical soils is directly related to their
percentage clay, sand and organic carbon contents (Babalola and Lal, 1977).
Bulk Density
The soils show moderate to high bulk densities ranging from 1.24 – 1.32 gcm3 in the
surface layers to only slightly lower values of 1.24 -1.30 gcm3 in the bottom layers (Table
3.16). These values are typical of the Entisols of the Ahoada – Idu Ekpeye axis to which
the present project area could be assigned.
Mean organic carbon content is about 14% for the area. Nitrate-nitrogen and available
phosphorus, and sulphate concentrations indicate a fairly acceptable nutrient base for
soils of the area Low concentrations of soil oil and grease were measured in locations
around the project area. Values of 2.68, 2.38 and 2.30 mg/kg soil obtained for the top,
mid-depth and bottom soils respectively during the rainy season did not significantly differ
from the dry season concentrations of 3.86, 3.55 and 3.60 mg/kg soil). The low oil and
grease concentrations from this area indicate that the soils are still relatively free of
hydrocarbon contamination.
Table 3.17: Summary of the Nutrient Status of Soils from Project Area
Table 3.18: Summary of Alkaline Earth Metals of Soils from the Project Area
Soil Level, meq/100g soil
Parameters horizon Range Mean SD (±
±)
Rainy Season
Top 12.60 - 37.95 25.89 9.45
Sodium Middle 6.20 - 36.10 21.48 8.01
Bottom 5.84 - 33.20 21.00 8.12
Top 3.90 - 44.35 34.44 12.13
Potassium Middle 4.10 - 40.38 26.16 10.14
Bottom 3.60 - 33.40 26.1 8.57
Top 18.40 - 56.16 41.63 11.07
Calcium Middle 20.60 - 44.24 31.34 7.65
Bottom 18.66 - 38.65 25.6 8.60
Top 7.10 - 40.26 27.78 8.57
Magnesium Middle 8.20 - 31.75 18.45 6.92
Bottom 9.20 - 32.60 18.5 6.02
Dry Season
Top 10.12 – 34.90 19.54 7.94
Sodium Middle 8.06 – 31.26 20.02 7.80
Bottom 8.02 – 28.14 18.14 6.80
Top 16.19 – 46.61 29.69 9.81
Potassium Middle 16.90 – 51.06 30.00 11.90
Bottom 16.14 – 54.36 31.41 13.60
Top 14.26 – 56.22 39.42 10.06
Calcium Middle 12.20 – 62.90 37.81 16.10
Bottom 10.04 – 56.36 33.88 16.94
Top 12.30 – 37.42 27.26 7.37
Magnesium Middle 10.64 – 41.69 25.15 11.68
Bottom 12.42 – 44.72 26.97 13.11
SD = Standard Deviation
(Source: Baseline Studies Gbaran/Ubie IOGP, SPDC, 2003)
Values of exchangeable acidity (Table 3.19) fell within ranges typical for similar
ecosystems in the Niger Delta. The dominance of non-expanding kaolinitic clay mineral
colloids in the soil aggregates of the region could enhance E.A. values. Cation Exchange
Capacity (C.E.C.) of the soils is quite high with values of 144.68, 113.30 and 107.0
meq/100g soil in the top, mid-depth and bottom soil horizons respectively in the rainy
season (Table 3.10a). Dry season values were not significantly different.
Heavy Metals
The concentrations of heavy metals in soils of the area measured in the two seasons are
shown in Table 3.20. Heavy metal concentrations fell within the range of values reported
for similar ecosystems in the Niger Delta. Seasonal alterations in metal concentrations
were not evident. The high concentrations of iron in all soil horizons during both the rainy
and dry seasons could be related to the dominance of red-coated oxides of iron and
aluminium in the Oxisols of Rumuekpe-Elele Alimini axis.
Heavy metal presence in the soil profile raise environmental concerns given the high
water table of the project area and the possibility of contamination.
Of significance is the low proportion of hydrocarbon degraders among both fungi and
bacteria in the soils of the area. These low values, generally below 0.025%, indicate
absence of hydrocarbon contamination of soils in the area.
Table 3.21: Summary of Microbiological Characteristics of Soil Samples from Project Area
Soil Statistics Total Total fungal Hydrocarbon Hydrocarbon % %
Horizon heterotrophic count utilising utilising fungi Hydrocarbon Hydrocarbon
count (cfux106/g) bacteria (cfux102/g) utilising utilizing fungi
(cfux106/g) (cfux102/g) bacteria
Rainy Season
Surface 2.4 – 3.6 2.0 – 3.0 4.2 – 8.3 3.2 – 6.7 0.014 – 0.031 0.013 – 0.028
Mid depth Range 0.7 – 1.4 0.5 – 1.1 0.8 – 2.3 0.5 – 1.0 0.006 – 0.030 0.003 – 0.018
Bottom 0.1 – 0.6 0.1 – 0.4 0.1 – 0.4 0.1 – 0.2 0.002 – 0.040 0.003 – 0.020
Surface 2.9 2.5 7.1 5.0 0.025 0.020
Mid depth Mean 1.1 0.8 1.4 0.6 0.01 0.0098
Bottom 0.3 0.2 1.2 0.1 0.009 0.0078
Surface 0.35 0.28 1.20 1.00 0.006 0.004
Mid depth ±S.D 0.34 0.2 0.45 0.24 0.006 0.004
Bottom 0.15 0.09 0.10 0.05 0.009 0.006
Dry Season
Surface 2.5 – 3.6 2.6 – 3.4 3.6 – 8.2 3.7 – 7.3 0.0108 – 0.0292 0.0029 – 0.0252
Mid depth Range 0.9 – 1.9 0.9 – 1.6 0.7 – 2.0 0.5 – 1.5 0.0037 – 0.0189 0.0006 – 0.0156
Bottom 0.3 – 0.7 0.2 – 0.8 0.1 – 0.6 0.1 – 0.4 0.0019 – 0.0200 0.0013 – 0.0067
Surface 3.07 2.85 7.03 5.48 0.022 0.017
Mid depth Mean 1.37 1.30 1.33 0.91 0.010 0.007
Bottom 0.52 0.57 0.30 0.20 0.006 0.004
Surface 0.33 0.31 1.14 1.07 0.005 0.006
Mid depth ±S.D 0.27 0.23 0.44 0.30 0.004 0.004
Bottom 0.14 0.16 0.15 0.10 0.005 0.002
(Source: Baseline Studies Gbaran/Ubie IOGP, SPDC, 2003)
The river is perennial around Ihuowo and navigable all the year round. Previous
observations show that the flood levels vary between the dry season and the rainy
season. Discharge is significant at the pipeline crossing point (approx. 30 m3/s) at a
reasonably fast flow rate of about 0.5 m/s. Consequently pollutant input in the river at
this point will speedily arrive at both upstream and downstream locations depending on
the tidal situation.
Data for physico-chemical parameters refer to those obtained for the general project
area and considered valid for the specific location. A summary of the data on physico-
chemical parameters for both the rainy and dry seasons is presented in Table 3.23.
Mean surface water temperatures of 27.6ºC in the rainy season were significantly lower
that 30.7ºC obtained during the dry season. This seasonal variation is understandable
on account of the ambient atmospheric temperatures during the respective seasons.
Dissolved oxygen has an inverse relationship with water temperature and this is
reflected in the equally significant variations in DO values measured during both periods.
Turbidity values, though expectedly higher during the rainy (13.2±7.09 NTU) that the dry
season (7.8±1.75 NTU) remained within values consistent with the sustenance of
aquatic productivity. The levels of mineral nutrients (PO4, N-NO3, SO42-) were
consistently low during both seasons indicating absence of eutrophication
The values for the bottom water samples for the different parameters were not
significantly different (P<0.05) from those of the corresponding surface water samples.
Physico-chemical parameters in both seasons lie within FMENV limits for surface waters
except for oil and grease contents which at a mean of 2.25mg/l was significantly higher
than FMENV limits of 0.01mg/l. There is a need for continuous monitoring of this
parameter to determine the sources of oil/grease input into the aquatic system of the
area.
Table 3.23: Summary of Physico-Chemical Parameters of Surface Water at the Pipeline Crossing (Rainy Season)
Parameters FMENV Levels of Parameters
9
Limits Surface Bottom
Range Mean SD Range Mean SD
Rainy Season
Temp.(°C) 25.0 - 29.2 27.6 ± 1.40 25.4 – 29.4 27.7 ± 1.40
PH 7.0-8.5 5.2 - 6.4 5.8 ± 0.47 5.4 - 6.4 6.1 ± 0.49
DO (mg/l) 4.1 - 6.3 5.6 ± 0.63 4.4 - 6.6 5.8 ± 0.65
BOD5 (mg/l) 0.5 - 1.8 1.1 ± 0.38 0.5 - 1.8 1.1 ± 0.38
COD (mg/l) 8.8 - 17.9 13.3 ± 2.73 8.8 - 18.2 13.2 ± 2.79
TSS (mg/l) 1.0 - 3.8 1.84 ± 0.94 1.0 - 2.2 1.5 ± 0.41
TDS (mg/l) 23.0 - 420.3 153.2 ± 188.39 25.9 – 680.1 160.5 ± 196.52
Turbidity (NTU) 5.0 4.8 - 29.8 13.2 ± 7.09 4.9 - 29.9 13.1 ± 7.46
Conductivity. (µS/cm) 42.2 - 683.3 221.0 ± 345.73 42.2– 1233.5 228.7 ± 360.39
Chloride (mg/l) 200.0 11.8 - 630.3 104.8 ± 195.06 11.8 – 635.5 105.6 ± 196.58
NO2 – N (mg/l) 0.005 - 0.018 0.009 ± 0.0054 0.005 – 0.018 0.009 ± 0.0052
NO3 – N (mg/l) 0.3 - 1.1 0.55 ± 0.27 0.3 - 0.8 0.54 ± 0.23
PO4 – P (mg/l) 0.005 - 0.42 0.05 ± 0.13 0.005 – 0.42 0.05 ± 0.13
NH4 – N (mg/l) 0.1 - 0.5 0.26 ± 0.12 0.1 - 0.5 0.25 ± 0.12
Oil and grease (mg/l) 0.01 1.0 - 3.9 2.25 ± 1.43 0.9 - 3.8 1.92 ± 1.03
(Source: Baseline Studies for the Gbaran/Ubie IOGP, SPDC, 2003)
9
Highest desirable level
Table 3.23b: Summary of Physico-Chemical Parameters of Surface Water at the Pipeline Crossing (Dry Season)
Parameters FMENV Levels of Parameters
10
Limits Surface Bottom
Range Mean SD Range Mean SD
Dry Season
0
Temp ( C) 28.7 – 31.6 30.7 1.4 29.1 – 31.8 30.9 1.3
pH 7.0-8.5 6.2 – 7.6 7.1 0.50 6.5 – 7.6 7.1 0.36
DO (mg/l) 2.1 – 4.8 3.8 0.84 2.5 – 4.9 3.8 0.78
COD (mg/l) 11.8 – 19.5 14.4 3.0 11.9 – 21.3 14.8 3.50
BOD5 (mg/l) 0.5 – 1.3 0.8 0.30 0.6 – 1.4 0.97 0.30
TSS (mg/l) 1.0 – 1.7 1.35 0.33 1.0 – 1.8 1.4 0.35
TDS (mg/l) 42.0 – 460.8 166.6 147.3 43.0 – 465.3 154.1 153.1
Turbidity (NTU) 5.0 4.9 – 10.2 7.8 1.75 4.9 – 10.2 7.8 1.75
-1
Conductivity (µScm ) 69.3 – 794.5 254.2 263.7 71.1 – 802.4 231.2 269.1
Chloride (mg/l) 200.0 12.4 – 780.3 125.6 288.7 12.5 – 782.2 125.9 289.3
NO2 – N (mg/l) 0.001 – 0.015 0.07 0.19 0.001 – 0.015 0.07 0.19
NO3 – N (mg/l) 0.3 – 0.83 0.51 0.21 0.3 – 0.85 0.51 0.24
NH4 – N (mg/l) 0.1 – 0.85 0.41 0.25 0.1 – 0.89 0.42 0.26
PO4 – P (mg/l) 0.004 – 0.014 0.026 0.05 0.004 – 0.015 0.026 0.05
2-
SO4 (mg/l) 200.0 17.2 – 62.8 27.8 16.11 17.5 – 63.7 28.4 16.25
(Source: Baseline Studies for the Gbaran/Ubie Nodes, SPDC, 2003)
10
Highest desirable level
Table 3.24: Heavy Metal Content of Surface and Bottom Water Samples from the
Project Location
Parameters FMENV Concentrations, mg/l
(mg/l)
Limits Bottom
(HDL) Surface
Range Mean SD Range Mean SD
Rainy Season
Vanadium 0.01 - 0.02 0.004 ± 0.004 0.01 - 0.02 0.02 ± 0.0
Nickel 0.01 - 0.02 0.01 ± 0.0 0.01 - 0.02 0.01 ± 0.006
Chromium 0.01 - 0.1 0.04 ± 0.05 0.01 - 0.05 0.025 ± 0.017
Lead 0.01 - 0.03 0.017 ±0.008 0.03 - 0.03 0.02 ±0.006
Zinc 5.0 0.5 - 2.4 0.88 ± 0.79 0.7 - 1.7 1.02 ± 0.67
Manganese 0.05 0.1 - 0.2 0.13 ± 0.048 0.1 - 0.2 0.15 ± 0.052
Copper 0.05 0.01 - 0.18 0.67 ± 0.075 0.01 - 0.2 0.06 ± 0.064
Iron 0.1 0.05 - 0.36 0.19 ± 0.11 0.05 - 0.3 0.18 ± 0.09
Cadmium 0.01 - 0.02 0.012 ± 0.004 0.01 - 0.2 0.015 ± 0.005
Dry Season
Vanadium 0.01 – 0.02 ND ND 0.01 – 0.02 ND ND
Nickel 0.01 ND ND 0.01 ND ND
Chromium 0.01 ND ND 0.01 ND ND
Table 3.24: Heavy Metal Content of Surface and Bottom Water Samples from the
Project Location Continues
The proportion of oil-degrading bacteria and fungi in surface waters of the area are low
(0.8 and 0.05% respectively). The values for bottom water samples were much lower
than 1% for both cases (Table 2.25). These values are within ranges for waters not
grossly polluted with oil (Atlas & Bartha, 1981). The river, however, showed high content
of coliforms incompatible with its current use as a source of drinking water.
Table 3.25: Summary of Microbiological Characteristics of Surface and Bottom water Samples from Project Location
11 12
Sampl Para- Total Total fungal Hydrocarbo Hydrocarbon % HDB % HDF Coliforms*
e type meters heterotrophi count n utilising utilising fungi (MPN/
6 2
c count (cfux10 /ml) bacteria (cfux10 /ml) 100ml)
(cfux106/ml) 2
(cfux10 /ml)
Rainy Season
S Range 0.51 - 0.91 0.12 – 0.61 0.01 – 0.23 0.01 – 0.12 0.0003 – 0.0022 0.0002– 0.0050 3.2 – 15.3
(cfu/ml)
S Mean 0.74 0.40 0.08 0.05 1.29 1.42 9.1
(cfu/ml)
S S.D ± 0.12 0.13 0.07 0.04 0.00086 0.0015 4.2
B Range 7.21 – 11.40 4.21 – 7.21 0.03 – 1.19 0.04 – 0.21 0.0001 – 0.0014 0.0001– 0.0017 5.7 – 21.7
(cfu/ml)
B Mean 9.11 5.6 0.59 0.09 0.00055 0.0003 11.8
(cfu/ml)
B S.D± 1.21 0.93 0.49 0.04 0.00048 0.00047 5.29
Dry Season
Range 0.0001 – 0.0012 0.0003– 0.0054
S (cfu/ml) 0.33 – 0.83 0.08 – 0.47 0.01 – 0.07 0.01 – 0.13 6 – 14
Mean
S (cfu/ml) 0.63 0.31 0.04 0.05 0.0006 0.0020 9.57
S S.D± 0.19 0.13 0.03 0.04 0.0011 0.0022 3.15
Range 0.0001 – 0.0030 0.0001 – 0.0013
B (cfu/ml) 6.72 – 12.02 3.52 – 9.41 0.09 – 2.42 0.08 – 1.02 11 – 31
Mean
B (cfu/ml) 8.96 7.07 0.74 0.29 0.0009 0.00062 19.71
S.D±
B 1.88 1.88 0.90 0.25 0.0011 0.00044 7.99
S = Surface water samples
B = Bottom water samples
WHO/FMENV Most Probable Number (MPN) limit for coliforms is 10/100 ml of samples. Samples containing greater numbers are not potable.
(Source: Baseline Studies Gbaran/Ubie IOGP, SPDC, 2003)
11
Hydrocarbon utilizing bacteria
12
Hydrocarbon utilizing fungi
Table 3.27: Heavy Metal Content of Sediment from Locations on the Sombreiro River
the desmids dominated the phytoplankton community accounting for about 48% in terms
of relative abundance. This dominance was taken over in the dry season by the diatoms
(Bacillariophyceae) which accounted for 40.6% of phytoplankton at this time.
3.3.1.18.2 Zooplankton
The zooplankton community consisted of one protozoan, five rotifers, one cladoceran,
one ostracod, three copepod representatives (Table 3.30). The zooplankton also
included larval stages of insects and crustaceans such as nauplii and copepod larvae.
The density of the zooplankton increased from 14 organisms/l during the rainy season to
19 organisms/l in the dry season. This is consistent with the slower current speed,
decreased turbidity and consequent higher primary productivity of the river at this time.
During the rainy season, the zooplankton population was dominated by rotifers (35.7 %),
followed by larval forms (21.4 %). This situation was reversed during the dry season
when larval forms dominated the zooplankton (36.8%) as against the (26.3%) of the
Rotifera. Larval stages were important components of the zooplankton during both
seasons. Their abundance indicated that the zooplankton populations were in active
reproduction
Desmidaceae (Desmids)
Closterium sp 2 -
Cosmarium sp 3 5
Micrasterias sp 10 4
Sub total 15 (48%) 9 (8.5%)
Bacillariophyceae
Navicula sp 3 15
Synedra sp - 4
Amphora sp 2 -
Roya sp - 4
Melosira sp - 12
Tabellaria sp 2 2
Surirella sp 2 -
Campylodiscus sp - 2
Coscinodiscus sp - 2
Bidulphia sp - 2
Sub total 9 (29.0%) 43 (40.6%)
Protozoa
Phacus 2
Sub Total 2 (14.3%) 0 (0.0%)
Rotifera.
Brachionus sp 1 3
Keratella sp. 2
Filinia sp 2
Lecane sp. 2
Lepadella sp 1
Sub Total 5 (35.7%) 5 (26.3%)
Cladocera
Alona sp 1 2
Sub Total 1 (7.1%) 2 (10.5%)
Ostracoda
Bosminopsis sp 1
Sub Total 1 (7.1%)
Copepoda
Acartia sp 1
Diaptomus sp 1
Mesocyclops sp 1 4
Sub Total 2 (14.3%) 5 (26.3%)
Larval Forms
Nauplii 2 4
Insect larvae 1 3
Sub Total 3 (21.4%) 7 (36.8%)
Total 14 (100%) 19 (100%)
(Source: Baseline Studies Gbaran/Ubie IOGP, SPDC, 2003)
The Sombreiro River in its downstream sections may support significant fishing activities
which is, however, not the case in the more upstream locations including the proposed
project area. Fishing activities within 2 km stretch of the Sombriero on both sides of the
pipeline crossing is minimal, going by indicators of professional fisheries such as fishing
canoes and other gear. Reportedly, and by observation during the site visit, less than 10
professional fishermen operate within the relevant stretch of river, others are
occasional/part-time fishermen.
There is no mechanized fishing in any form within the vicinity of the proposed pipeline
crossing. Fishing activity is typical as for similar locations on the Niger Delta and is
conducted on an artisanal basis using mainly traditional fishing gear such as dug out
canoes, set nets and basket traps. Catch-per-unit of effort is low and the average total
daily catch per fisherman is below 4kg (Plate 3.5) comprising mainly Clariidae,
Gymnarchus niloticus and tilapines (Plate 3.6). Total daily fish production from the area
is probably below 20 kg for most parts of the year.
In other sections of the same river, however, fishermen operate different types of gears
such as cast nets, gill nets, beach seines, filter nets, long lines and encircling nets. Light
traps were used to exploit Pantodon sp and Pellonula leonensis. During the rainy
season, elaborate filtering devices are set across the width of small rivers (which were
less than 10 metres in width). Such devices trap large numbers of fishes including
juveniles. Basket traps are the gear of choice in the swamps. They are particularly
effective for exploiting Channa sp, Clarias sp, Synodontis spp and prawns.
Table 3.31: Fish Fauna and Fisheries in Waters around Project Location
Fish Family and Common A.I Gear Habitat
Species name
Family Cichlidae
Tilapia zillii Tilapia C 1,2,3,4,5 Shallow waters / brackish areas
Sarotherodon galilaeus “ C 1,2,3,4,5 Shallow waters/ brackish areas
Hemichromis fasciatus Dwarf Cichlid C 1,2,3,4 Shallow waters / brackish waters
Hemichromis Dwarf Cichlid C 4,6 Swamps
bimaculatus Tilapia R 3,6 Swamps
Chromidotilapia guentheri Tilapia C 1,2,3,4,5 Shallow waters and swamps
Oreochromis niloticus
Family Clariidae
Clarias albopunctatus African catfish C 1,2,3,4, Swamps
Clarias buthapogon “ C 1,2,3,4 Swamps
Clarias gariepinus “ C 1,2,3,4 Swamps and shallow waters
H. bidorsalis ‘ R 1,2,3,4,5 Swamps and shallow waters
Family Channidae
Channa obscura Snake fish C 3,4 Swamps
Channa africana C 3,4 Swamps
Family Pantodontidae
Pantodon sp Butterfly fish C 8 Swamps, shallow flood plains
Hepsetidae
Hepsetus odoe African pike C 1,2,4 Open waters,
Family Schilbeidae
Schilbe mystus C 1,2 Freshwater rives and lakes
Eutropius niloticus Glass catfish R 1,2 Freshwater rives and lakes
Family Mochochidae
Synodontis schall Three-spined C 1,2,4 Freshwater rivers and lakes
S. membranaceous catfish C 1,2,4 Freshwater rivers and lakes
Synodontis occelifer « R 1,2,4 Freshwater rivers and lakes
Synodontis sp « R 1,2,4 Freshwater rivers and lakes
Family Polypteridae
Polypterus bichir Bony tongue C 1,2,3 Swamps
Calamoichthys Lung fish C 3 Swamps
calabaricus
Family Lepidosirenidae
Protopterus annectens R 1,2,3,4 Swamps
Family Gymnarchidae
Gymnarchus niloticus C 1,2,3,4 Freshwater rivers and lakes
Family Characidae
Hydrocyon forskhali C 1,2,3,5 Open waters of rivers and lakes
Alestes baremose C 1,2,3,5,6 Open waters of rivers and lakes
Alestes macrolepidotus R 1,2,3,5,6 Open waters of rivers and lakes
Family Anabantidae
Ctenopoma kingsleyae Climbing perch R 3 Mainly in swamps
Family Notopteridae
Xenomystus nigri R 1,2,3 Swamps
Key
1 = Cast net 6 = Lift net AI = Abundance Index
2 = Gill net 7 = Filter net C = Common
3 = Basket trap 8 = Light trap R = Rare
4 = Long line/hooks
5 = Encircling nets/Beach seine
(Modified from: Baseline Studies Gbaran/Ubie IOGP, SPDC, 2003)
3.3.2.2 Population
The current population for Ihuowo was estimated at 5215 people, based on projections
from the 1991 census figures.
The linear extrapolation model utilized for the population projections is shown in Box 1
65 + (5%)
25-64(23%)
15-24(24.3%)
0-14 (47%)
The productive working age grade (24-64) accounted for 24.3% of the total population.
This category bears the burden of dependence of other age grades, including the
younger ones of 0-14, school goers of 15-24 and the old of 65-plus.
The 15-24-age bracket made up 24.3% of the population. This age bracket is considered
very sensitive, being students, dropouts and apprentices in their most volatile and
venturing phases of life, who commonly do not compromise their socioeconomic needs
without serious negative effects to family, society, oil companies and other important
stakeholders.
Bonny LGA had the lowest household size (3.3) amongst the LGAs in Rivers state, while
Obi Akpor had 3.6, Degema 4.2, Port Harcourt 4.1, Okrika 4.3, Ikwerre 5.1, Khana and
Oyigbo 4.6.
7
6
5
4
3 Household size
2
1
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Figure 3.13: Household Size in Ahoada and other LGAs in Rivers State
(Source: FOS 1994)
More recent studies in the study area came up with higher household sizes than the
findings shown above. Ihuowo and Rumuekpe were amongst the communities covered
in the EIA for the Gbaran-Ubie node IOGP. Findings from this study showed that about
48% of the households had between 6-10 persons, 21% had between 1-5 householders
and 31% had above ten people living in a household (Table 3.32).
The significantly larger households found in the more recent survey could be attributed
to the difference in perception of household in the two studies, with the previous survey
considering a household as a nuclear family comprising of a father, mother(s) and
children while the more recent survey considered other members of the extended family
living under the same roof
Widow ed
Single 9%
18%
Divorced
18%
Married
55%
These findings depict income poverty, which is commonly found in rural communities
that depend solely on low yielding returns on agrarian economic activities.
Within Ihuowo community, majority of houses are of the modern type, built with cement
block and roofed with zinc. However, several mud houses with either zinc or thatch roofs
were observed in the community.
3.3.2.10 Education
The level of literacy of a community depicts its level of development. High levels of
tertiary and secondary education are statements of development, while on the other
hand, high numbers of persons lacking primary education indicate poverty and
underdevelopment.
Ihuowo and Rumuekpe were amongst the communities covered in the EIA for the
Gbaran/Ubie IOGP. Figure 3.15 shows the educational attainment in this area. The
numbers of people with no form of formal education were exceptionally high, depicting a
low level of functional literacy.
Higher Degree
Tertiary Education
(NCE, OND, A/L
Degree/HND)
FEMALE
Secondary School
MALE
Primary School
No formal Education
Previous studies of the area established that the challenges of education were not so
much the availability of primary and secondary schools, as the poor infrastructure,
staffing and equipments in schools. There were enough classrooms in the primary
school in Ihuowo. In addition, the primary school has a staff quarter that was donated by
SPDC. However, there were complaints of lack of adequate tables and chairs (poor
furniture)
Ihuowo has a primary school but no secondary school. Secondary school pupils walk 9
km to and from school in Edoha daily.
3.3.2.11 Occupation
Farming is the major occupation in the area. This is supplemented with fishing, palm
wine tapping and palm kernel processing. In addition, communities practice hunting,
logging and other traditional occupations commonly practiced in fresh water forest areas.
Aside from the traditional occupations, the most popular income generating activity is
petty trading. Others include contracting, welding works, motor mechanics and
carpentry, civil servants in the Local or State government service, company employees
as well as teaching (Fig. 3.16).
FEMALE
MALE
1000
900
800
700
Frequency
600
500
400
300
200
100
0
*Electrician,
Trading
*Contractor
*Carpentry,
Fishing
Civil Servant
Farming
*Tailoring,
*Driving,
Others
Occupation
Cassava is the major crop cultivated in Ihuowo. Other crops cultivated are plantain,
banana, okra, vegetables, cocoyam, yam and maize. Crops were cultivated mainly for
subsistence, but some were grown in medium scale.
Local livestock and fish rearing are practiced. Local fowls and goats are the most
popular livestock found in Ihuowo. Females are as active as their male counterparts in
farming activities
Plate 3.7: Local Gin Distilling Shed on Banks of the Sombreiro at Ihuowo.
Farmers’ stocks for the previous year are the main source of planting materials. Planting
materials could also be sourced from other farmers and local markets. Fish fingerlings
are obtained mostly from the wild.
Farm labor was available but expensive. Farming operations requiring external labor
inputs include clearing, land preparation, staking, planting, weeding, harvesting,
processing, marketing and storage. The labor force used was family members, hired and
communal labor. Children, however, participated to some extent in the various activities.
Manual tools such as machetes and hoes are the major implements for agriculture.
There is no access to modern farm inputs and technologies. Some identified limitations
to agricultural productivity in Ihuowo include the lack of access to fertilizers, credit, agro-
chemicals (herbicides, pesticides etc) and tractors.
Social Groups
Several social groups exist in Ihuowo community. Their origin depends on their intended
mission and objectives for which they were conceived. Church-related groups have
existed for several years and are interested in the spiritual well-being of their members.
Some elders that were interviewed stated that some key community organisations had
existed since the beginning of their communities. These organisations were:
Women Associations
Youth Associations
Cooperatives
Social Clubs
Age Grades
Community Development Associations
Paramount Ruler:
(Onyenwe Ali)
Council of Chiefs
Community
Development
Committee (CDC)
Residents
Village Heads convene meetings monthly or when required to discuss the welfare of
their settlements and to settle disputes between residents. The Council of Chiefs,
Community Development Committee (CDC) and Youth Council all work with the village
head and play different roles in the day-to-day administration of each community.
The Council of Chiefs consists of traditional chiefs among whom a Chairman is elected.
The responsibility of the council is to ensure peace, progress and stability in the
community.
The CDC, which has representation from each section of the community, takes
responsibility for infrastructure and other aspects of community development. Its elected
chairman is usually an influential member of the community, who commonly serves as
the spokesman for the community in matters relating to community development.
The youth are most central for mobilizing for development. Both the youth and women
are key players in pushing home community advocacy agendas. For instance, it was the
Ihuowo women that were said to have denied Wilbros access to execute SPDC pipeline
construction/pigging activities in 1981 until commitments were made for community
development.
Church leaders, the local government councillor and other political office holders from
the community also assist in decision-making and governance. Table 3.34 shows the
different spheres of influence and lines of authority.
It is believed that the Ekpeye encountered strong mysterious forces and wars with other
human groups; hence they were “fortified” with mystic powers and weapons. Their belief
in deities and “Juju” is very strong among individual lineages. Hence, the existence of
several shrines, sacred forests, mystic lakes and totemic objects and masquerades.
For instance, a recent study established that Ihuowo has 1 sacred shrine, 4 sacred lakes
and 4 sacred forests (Table 3.35) (Gbaran-Ubie IOGP, 2003).
Ihuowo 1 4 4
However, discussions with the elders revealed that there are many more sacred places
than the numbers recorded, which includes the god of the Sombriero River that would
need to be appeased before the proposed construction can proceed.
Table 3.37: The Common Symptoms/ Signs and Diseases Detected During
Physical/Clinical Examination
Body Part Examined Physical Findings (Signs/ Percentage
Diseases) Incidence
Skin Pityriasis Vesicolor 20%
Tinia 10%
Scabies 30%
Ear Otitis Externa 2%
Eye Visual Problems 6%
Cataract (Senile / pathological) 5%
Mouth Poor oral hygiene 3%
Dental caries 6%
Cardiovascular system Anaemia 20%
Hypertension 12%
Crepitations 2%
Rubs 3%
3.3.3.2 Mortality
The leading causes of death (as given during the focus group discussions) among
children under five years of age were malaria, febrile convulsion, measles, and
diarrhoeal diseases, while in adults they were malaria, typhoid fever, rheumatism,
diabetes, hypertension and tuberculosis.
The services rendered include both preventive (immunisation) and curative. The average
daily clinic attendance is twenty. The pattern of diseases commonly seen at the centre
was infectious diseases (malaria, respiratory tract infections, measles, diarrhoea),
malnutrition, diabetes mellitus, hypertension, rheumatic diseases, complications of
pregnancy (early labour, spontaneous abortion,) etc.
The healthcare centre is easily accessible to members of the community. The needs of
the healthcare centre include generator for light, potable water, upgrading the doctor’s
residence, fence etc.
• Medicinal Plants
The Ihuowo community relies on some medicinal plants for their healthcare. These
include ogbuchuru for wound healing, ugbola for treating malaria, ukwoline for eye
problems and udo for treating hernia etc.
Observations on environmental health factors within the community shows that the
volume of domestic water available to individuals is less than ten litres per day and less
than 10% of the population have access to potable household water (Table 3.38). A
large proportion of houses (98%) have no modern toilet facilities. The number of
occupants per room is three to five as opposed to a maximum of two adults or one adult
plus a child as stipulated by WHO.
3.3.3.4.2 Wastes
Sources of Wastes
The types of wastes generated in these areas are from domestic, agricultural, fishing,
commercial and trading activities. Human/animal faecal deposits constitute further
sources of wastes
Waste Inventorisation
The inventory of wastes generated from various sources in the area are provided in
Table 3.39
Table 3.39: Wastes Inventorisation from the Identified Sources in the Communities
Waste Sources Waste Types
Domestic activities Ashes, cassava peels, yam peels, macerated food remains, rags,
kitchen waste water, vegetable, fish and meat waste parts, palm
kernel and coconut shells, coconut fruit barks, plates, polythene
bags, plastic containers, sticks, wire gauze, paper, foot wears,
deformed unidentifiable solid objects, detergent containers etc.
Wastes from agricultural Palm fronds, cassava tubers, sticks, leaves, fishing nets/hooks,
and fishing activities sticks, shells, and baskets etc.
Wastes from commercial Papers and cartons, nylon bags, jute bags, cans/tins, polythene
and trading activities bags, paper, crates, detergents packs bottles, wigs, plastic kegs etc
The prevalence of stunting was moderate in these communities, 24.4% (13.5% males
and 10.9% females) based on WHO classification. The moderate stunting rates reflects
long term or chronic nutritional inadequacy. The prevalence of underweight and wasting
were high (37.8% and 35.4% respectively), which indicates acute under-nutrition in
these communities.
The combination of moderate stunting and high/very high wasting as observed in this
area, is in keeping with the common pattern of malnutrition observed in many parts of
Nigeria; predominance of acute over chronic malnutrition.
These findings are in keeping with known patterns particularly in the developing
countries. Majority of the respondents in this study earned very poorly and probably,
were unable to afford balanced diet three (3) times a day. Repeated episodes of acute
infections from faeco-oral transmission might also have played an important role in this
picture of under-nutrition.
Table 3.40: Nutritional Status of children Under Five in the Area Using
Anthropometric Indices
(n2 = 82)
Anthropometric
Indicator Male Female Total
No % No % No %
Stunting A 11 13.5 9 10.9 20 24.4
Underweight B 8 22.0 13 15.8 31 37.8
Wasting C 16 19.5 13 15.8 29 35.4
A = Height-For-Age less than –2 standard deviations below WHO reference value
B = Weight-For-Age less than –2 standard deviations below WHO reference value
C = Weight-For-Height less than –2 standard deviations below WHO reference value
n2 = Total sample of under five.
1600
1400
1200
Frequency
1000
800
600
400 MALE
200 FEMALE
0
Alcohol Cigarette Tobacco
Other bodies such as the eight leading Industrialised Nations of the World (G8), WHO,
UNICEF, World Bank, USAID, major religious groups, the print/electronic media, local
and international NGOs, and professional groups etc. have also shown considerable
interest. This interest is not surprising because the national sero-prevalence rates for
HIV is 5.4% while Rivers States had 7.0% (State Ministry of Health 2003). These values
for Rivers States were in excess of the national figure. The high levels might have
contributed to the level of HIV awareness in the studied area.
800
700
600
Frequency
500
400
300
200
100
0
Sexual Behaviour
The highest number of multiple sexual partners kept by respondents was six (6) as
shown in Fig. 3.20. However, keeping of two (2) sexual partners were the most
commonly practised sexual behaviour. Negative social habits like the use of stimulants
such as drugs and alcohol (both found to be in use in these communities) are risk factors
in STIs and HIV/AIDS transmission. Drugs and alcohol are known to limit inhibitions and
increase sexual urge. These factors encourage unprotected sexual practice and having
multiple sexual partners. .
1400
1200
1000
Frequency
800
600
400
200
0
Single 2 3 4 5 6
No of Partners
Fig. 3.20: Frequency Distribution of Multiple Sexual Partners in the Study Area
90
80
70
60
Frequency
50
40
30
20
10
0
BCG Yellow fever Oral Polio Hepatitis DPT Measles
Vaccine
Immunization Type
700
600
500
400 P FR 1
Standard
300 P FR 2
Sample
200
100
0
20-24 25-29 30-34 35-39 40-44 45-49 50-55 55-59 60-64 65-69 70+
• Lifestyle and habits such as the use of alcohol and cigarette smoking.
These habits lead to organ damage, could encourage multiple sexual
partners and predispose individuals to the risk of STIs and HIV/AIDS.
4.0 CONSULTATIONS
In line with SPDC procedures for proactive engagement of stakeholders, the EIA
process for the Okordia-Rumuekpe Trunkline Replacement at the Sombriero River
included consultations with regulators and communities.
Establishing and maintaining communications with these important stakeholders met the
following additional objectives of the EIA:
• Ensuring that stakeholders are adequately, correctly and timely informed of
the proposed project.
• Encouraging meaningful participation of stakeholders in the EIA process.
• Building mutual trust between stakeholders and SPDC.
• Identifying, analysing and evaluating stakeholders’ issues and concerns early
(at the planning stage).
• Raising the comfort level of decision makers.
• Bringing forward different views on the project at the planning stage.
3. Site verification visit, which involved traveling to the proposed project area
with FMENV representatives on the 19th of August 2005.
The following interests were represented in the meeting held with community
representatives in Ihuowo.
o Paramount ruler of Ihuowo
o Council of Chiefs of Ihuowo
o Leadership of the Agolo family (owners of project land)
o The CDC
o Community Youth
o Opinion leaders in community and former SPDC staff
o Federal Ministry of Environment,
o Rivers State Ministry of Environment
o SPDC Project Management/Engineer
o SPDC, Health, Safety and Environment
o SPDC Consultants (Biophysical, Social and Health)
As an outcome, the stakeholder engagement session was able to deliver on its key
expectations. Community representatives were encouraged to make their views known
without restraint. The community participated actively and raised their concerns on the
project as follows:
• The god of the Sombriero River protects the community and would need to
be appeased before the proposed activity can proceed.
As follow up on the above, there has been regular consultation between SPDC
Community Relations Officer and the community on the project.
Picture clips of Stakeholders` Engagement Session at the Palace of Nye Nwe Ele
Ihuowo, Chief C.I Elebra. 28/09/05.
Plate 4b: HRH Chief Clinton Elebra, The Onyenwali of Ihuowo (sitting middle)
Plate 4f: SPDC SIA consultant in discussion with the Paramount Ruler
5.0 INTRODUCTION
The 44 m of the 14” x 33.4km Okordia – Rumuekpe Pipeline replacement project at
Sombreiro River Crossing is likely to have some environmental (biophysical, social and
health) impacts. The objectives of this assessment are to identify these potential
impacts associated with the proposed project activities, evaluate the likelihood of
occurrence, magnitude and significance of the identified impacts. Thereafter, mitigation
measures will be proffered for the anticipated negative impacts, while measures would
be provided for enhancing the positive (beneficial) effects.
STAGE 1: STAGE 2:
STAGE 3:
Description: Qualification: Likelihood
Qualification:
Five characteristics Five ratings:
Potential
Positive/negative High probability 80-
Consequence:
Direct/indirect 100% (very likely)
Five rating definitions,
Duration: Medium high
for environment,
Permanent (long probability 60-80%
social, health and
term)/temporary (likely)
reputation.
(short term) Medium probability
(see text)
Magnitude: local 40-60% (possible
Extreme
or widespread impact)
Great
Reversible or Medium low
Considerable
irreversible probability 20-40%
Little
(unlikely)
Hardly Any
Low probability 0-20%
(very unlikely)
STAGE 4: STAGE 5:
Degree of Impact Table STAGE 6:
Significance of Lists each Impact Text
Impact impact, its Describes each
Four degrees of source and its impact, its
significance: rating source and its
Major rating
Moderate
Minor
Negligible
The details of the procedures for the EIA process are as follows:
The potential consequence of an impact depends on two things: the magnitude of the
potential changes to the environment caused by a hazard and the level of sensitivity of
the receiving environment. This is depicted in Table 5.1.
The interaction between the magnitude of effect and receptor sensitivity will determine
the rating for potential consequence as shown in Table 5.2.
The definitions for the potential consequence of environmental, social and health
impacts are as follows:
Definitions for the potential consequence of environmental impacts
Hardly any: An effect on the biophysical environment such as physical (noise, light,
air), geochemical (water, soil), and biological (flora and fauna) that may cause temporary
and/or sub-lethal effects on individual plants and animals and does not cause any effect
on population structure or size; causes only temporary and/or minor disruption to
habitats and ecosystems.
Little: An effect on the biophysical environment that may cause small impacts with few
losses of individual plants/animals and some adverse effects on population structure and
size; may cause some degradation of habitat and ecosystem quality.
Considerable: An effect on the biophysical environment that may cause long term loss of
plant and/or animal species; local and temporary damage to habitats and dysfunction of
communities and ecosystems.
Great: An effect on the biophysical environment that may cause permanent loss of plant
and/or animal species, resulting in local extinctions of flora and fauna; permanent loss of
small areas of habitat and ecosystems.
Extreme: An effect on the biophysical environment that may cause permanent loss of
whole populations of plants and/or animals, with widespread extinctions; widespread and
permanent loss of habitats; and whole communities and ecosystems.
Hardly Any: A trivial effect on the social environment, which causes almost no
nuisance or damage in the community. The local culture and lifestyle as well as the
social infrastructure are somewhat negatively affected, but the effect is only temporary.
The impact could result in some disagreement with stakeholder groups, but relationships
are likely to remain strong.
Little: A slight effect on the social environment that causes temporary changes in the
way of life of the community. The local culture and societal structure is negatively
affected. There is disagreement with stakeholder groups but the relationship remains
fairly strong.
Considerable: A substantial effect on the social environment. The way of life in the
community is disrupted and fundamental disagreement with stakeholder groups has
arisen. There is a breakdown of trust between the company and its stakeholders
although relationships have remained stable. A single stakeholder group might have
started campaigning against the company.
Extreme: A massive effect on the social environment. There is sustained large disruption
of and changes to the lifestyle of a community leading to a reduction in quality of life.
Impacts have become a concern for all stakeholder groups, irreversible damage to social
structure, traditional culture, and infrastructure and total breakdown of stakeholder
relationships.
Hardly Any: These are mere nuisances, not affecting work performance or causing
disability, e.g. non-toxic dusts (as an acute hazard), short sleep disturbance. There is
no need to seek medical services or consult a doctor. These health effects will
disappear within a short time.
Little: Illnesses that will need the attention of medical services/doctor. They need only
a few days to fully recover and will not have led to chronic diseases, e.g., colds, chicken
pox, skin infections and irritants, or many food poisoning infections.
Ebola, SARS, parasitic diseases (malaria, sleeping sickness), alcoholism and drug
abuse, road traffic accidents, cancer caused by known human carcinogens (small
exposed population), malnutrition, heat stroke, severe psychological stress leading to
suicide.
Extreme: Multiple fatalities: diseases with the potential to cause multiple fatalities: highly
infectious diseases like tuberculosis, hepatitis B, HIV/AIDS, parasitic diseases as
malaria, diseases caused by acute toxins (hydrogen sulphide, carbon monoxide),
cancers caused by human carcinogens (large exposed population).
After the rating for each impact, the determination of mitigation measures follows. From
the table above, only moderate and major impacts were considered for impact mitigation.
Continuous improvement and standard practices will address low (minor and negligible)
impacts. The positive impacts shall be monitored and enhanced.
• Mitigation measures;
• Management plans.
The identified negative impacts were rated as minor, moderate and major. Beneficial
impacts arising from the project were rated as positive and were therefore not classified
further.
Type of
S/No Project Activities Sensitivities Impact Impact Description Likelihood Consequence Rating
.
4 Excavation/ 1, 4, 5, 6, 7, Change in E • Direct Medium Little Minor
Trenching 8, 9, 10, 11, topography of the • Negative
17, 18, 19, area • Long term
24, 25, 25, • Local
26, 27, 28, • Irreversible
29, 31, 45,
46, 47, 50,
52, 55, 73
Impairment of water E,S, H • Direct Medium Considerable Moderate
quality by increased • Negative high
turbidity • Short term
• Local
• Reversible
Interference with E, S, H • Direct Medium Considerable Moderate
river based • Negative
traditional • Short term
occupations • Local
(fishing, cassava/ • Reversible
palm produce
processing etc).
Increased erosion E • Direct Medium low Considerable Minor
of the riverbanks. • Negative
• Short term
• Local
• Reversible
Type of
S/No Project Activities Sensitivities Impact Impact Description Likelihood Consequence Rating
.
4 Excavation/ 1, 4, 5, 6, 7, Disturbance of E, H, S • Direct Medium Considerable Moderate
Trenching 8, 9, 10, 11, aquatic life • Negative
17, 18, 19, (zooplankton, • Short term
24, 25, 25, phytoplankton, • Local
26, 27, 28, benthic • Reversible
29, 31, 45, communities,
46, 47, 50, fisheries etc)
52, 55, 73 Third party agitation S, H • Direct Medium Considerable Moderate
due to impairment of • Negative
surface water • Short/Long
quality from term
increased turbidity • Local
• Reversible
Increased S, H • Direct Medium Positive Positive
opportunity for • Positive high
business and • Short term
employment. • Local
• Reversible
Type of
S/No Project Activities Sensitivities Impact Impact Description Likelihood Consequence Rating
.
5 Site Fabrication 1, 2, 3, 17, Burns/ injuries from H • Direct Medium Considerable Moderate
(Welding) and Non 26, 27, 28, welding sparks • Negative
Destructive 29, 45, 48, • Short term
Testing 52,73 • Local
(Radiography) • Reversible
Exposure to E, H • Direct Medium Considerable Moderate
radioactive emission • Negative
during radiography • Long term
with possibility of • Local
genetic mutation. • Irreversible
Type of
S/No Project Activities Sensitivities Impact Impact Description Likelihood Consequence Rating
.
6 Waste Generation 1, 4, 5, 6, 7, Impairment of the E, S, H • Direct Medium low Little Minor
(solids/liquid/gase 8, 9, 10, 17, health of aquatic • Negative
ous) 18, 19, 20, and terrestrial flora • Short term
21, 22, 25, and fauna • Local
26, 27, 28, • Reversible
29, 45, 48, Increase in disease S, H • Direct Medium low Considerable Minor
52, 73 conditions like • Negative
diarrhoea/ • Short term
respiratory tract • Local
diseases. • Reversible
Increased level of E,S,H • Direct Medium low Considerable Minor
disease vectors • Negative
(mosquitoes, rats, • Short term
cockroaches, flies, • Local
e.t.c) • Reversible
Type of
S/No Project Activities Sensitivities Impact Impact Description Likelihood Consequence Rating
.
8 Pulling out of the 1, 3, 4, 5, 6, Third party agitation S, H • Direct Medium Considerable Moderate
pipeline section to 7, 8, 9, 10, over inheritance of • Negative high
be replaced. 11, 16, 17, the disused pipeline. • Short/Long
18, 22, 25, term
26, 45, 46, • Local
52, 73 • Reversible
Nuisance (Noise, E, S, H • Direct Medium Little Minor
emission, Vibration • Negative
etc) from heavy • Short term
machinery • Local
• Reversible
Impairment of water E,S, H • Direct Medium Considerable Moderate
quality by increased • Negative high
turbidity • Short term
• Local
• Reversible
9 Pipeline Laying 3, 4, 7, 8, 9, Blockage of water S • Direct Medium Considerable Moderate
and Tie-in 10, 11, 12, ways and possibility • Negative
14, 17, 18, of maritime • Short term
24, 25, 26, accidents • Local
27, 28, 29, • Reversible
31, 39, 45,
49, 50, 52,
73
Type of
S/No Project Activities Sensitivities Impact Impact Description Likelihood Consequence Rating
.
10 Backfilling of the 1, 4, 5, 6, 7, Impairment of water E, S, H • Direct Medium Considerable Moderate
trenches. 8, 9, 10, 11, quality by increased • Negative high
16, 17, 18, turbidity • Short term
19, 25, 26, • Local
32, 45, 46, • Reversible
47, 50, 52, 73 Third party agitation S, H • Direct Medium Considerable Moderate
from increased • Negative high
turbidity • Short term
• Local
• Reversible
Pre-Construction Phase
• Third party agitations
• Attack of workers and community members by poisonous snakes, bees, scorpions, other
wildlife and contact with poisonous plants
• Opportunities for employment
Construction Phase
• Increased opportunity for employment and contracting resulting in increased income level
• Injuries from the use of sharp objects in clearing
• Increased social vices
• Third party agitation
• Impairment of water quality by increased turbidity
• Increased erosion of the riverbanks.
• Generation of high intensity welding flash and noise
• Emission of radioactive materials from radiography
• Burns (Injuries) from welding sparks
• Blockage of water ways/ possibility of maritime accidents
• Impairment of health of aquatic and terrestrial life.
Operation Phase
• Contamination of soil, sediments, surface and ground water from oil spill incidents and wash
out from pigging operations
• Destruction of assets and properties from any fire incident.
Decommissioning Phase
• Change in topography of the area.
• Contamination of surface and ground water from inhibited water used in mothballing
• Third party agitation due to employment issues and loss of benefits as pipeline host
communities.
5.4.2.2 Trenching/Excavation
The trenching/ excavation would be done on land and water using land excavators and Clamshell
(Bucket) dredger to a minimum depth of 1 m and maximum width of 3 m respectively. These could
have the following impacts:
the Sombreiro River showed that the water was relatively clear. The impact was described as direct,
negative, short-term, local, reversible and rated moderate.
• Interference with River based Traditional Occupations (Fishing, Cassava/ Palm Produce
Processing etc)
The increased water turbidity resulting from excavation/ trenching could interfere with the
community use of the river for fishing, and processing of cassava/ palm produce. The impact was
described as direct, negative, short term, local, reversible and rated moderate.
• Contamination of Soil, Sediments, Surface and Groundwater from Oil Spill Incidents and
Wash Out from Pigging Operations
A breakdown in the oil pipeline due to either mechanical failure or sabotage could lead to spillage.
The spilled oil as well as the wash out from pigging operations could contaminate the soil,
sediments or water bodies. The impact was described as direct, negative, long term,
local/widespread and reversible. It was rated moderate.
6.0 INTRODUCTION
Mitigation measures for the proposed replacement of the 44 m Sombriero River Crossing
section of the 14” x 33.4 km Okordia – Rumuekpe pipeline were proffered for the impacts
identified in chapter five.
There were no major negative impacts identified. Mitigation measures were provided for
the impacts rated as moderate, while recommendations were made for enhancing the
positive impacts. Continuous improvement and standard practices would address minor
and negligible impacts. The dual objectives of the mitigation measures were to reduce
the severity of the identified moderate negative impacts and enhance the positive
(beneficial) effects of the different phases of the project (Pre-construction, construction,
operations and decommissioning).
The residual impacts that could arise despite the mitigation measures were also
assessed. Information on these residual impacts as well as the plan for monitoring
compliance and effectiveness of mitigation measures are provided in the Environmental
Management Plan (Chapter Seven).
The mitigation measures proffered for the predicted environmental impacts from the
project took cognizance of:
• Environmental laws in Nigeria, with emphasis on permissible limits for waste
streams {FEPA (1991) now FMENV, DPR (1991, 2002)};
• Best Available Technology for sustainable development;
• Feasibility of application of the measures in Nigeria;
• Social well-being, etc.
The existing 15 m corridor of the ROW is expected to be adequate for the pipeline
replacement activities. However, there could be the need to acquire about 80 m2 of the
community land on any side of the river as temporary lay down area for construction
equipment.
Whereas this limited temporary land-take would not seriously reduce access to the
acquired land and its resources (minor impact), its potential to result in third party
agitation was rated moderate, thereby requiring mitigation measures
The mitigation measures proffered for reducing third party agitation are:
These mitigation measures should reduce the anticipated impact from moderate to
minor.
The potentials for attack of workers and community members by poisonous snakes,
bees, scorpions, other wildlife and contact with poisonous plants was rated moderate. To
mitigate these impacts:
• Workers shall be provided with PPE (coveralls, jungle boots, hard hat and
gloves) and their usage enforced.
These measures should reduce the potential impact from moderate to minor.
The potential for site preparation activities to create opportunities for business and
employment was identified as a positive impact. The positive effects of this anticipated
impact could be improved by the following measures:
Injuries from the use of sharp objects in clearing could occur during site preparation
activities. This impact was rated moderate. To reduce this potential impact from
moderate to minor:
• Workers shall be provided with PPE (coveralls, jungle boots, hard hat and
gloves) and their usage enforced.
• First aid /medical facilities shall be provided at site, with critical cases
transferred to SPDC clinic at Port Harcourt or other appropriate health
facilities (Medevac).
• Alcohol consumption and drug use shall be prohibited during working hours in
line with SPDC policy.
Third party agitation resulting from issues surrounding labour requirements at the
construction phase and implementation of MOU was anticipated. It was rated as a
moderate impact. Mitigation measures include;
• Identification and resolution of relevant stakeholders’ issues.
These mitigation measures are expected to reduce the impact rating from
moderate to minor
Impairment of water quality by increased turbidity was rated moderate. The following
mitigation measures were proffered for reducing the rating of this anticipated impact to
minor.
• Potable water shall be supplied to the affected communities during trenching
and excavation operations.
• The quality of surface/groundwater shall be monitored in line with regulatory
requirements.
Disturbance of aquatic life (zooplankton, phytoplankton, benthic communities,
fisheries etc) was rated as a moderate impact. The construction of a sedimentation
basin with effluent drains to allow water to gradually drain back into the river without
turbulence would mitigate this impact.
The excavation/trenching of the pipeline route could interfere directly and indirectly
with river based traditional occupations such as fishing, cassava/ palm produce
processing etc. This impact was rated moderate.
Third party agitation over impairment of surface water quality resulting from excavation
and trenching was rated moderate. Mitigation measures proffered to bring this
anticipated impact from moderate to minor include:
Generation of high intensity welding flash and noise was rated moderate. To
mitigate this impact:
These mitigation measures should reduce the impact rating from moderate to minor.
Burns/injuries from welding sparks was rated moderate. To mitigate this impact:
• Awareness sessions on health risks and safety precautions of welding
operations shall be carried out for workers.
• SPDC shall enforce the use of welder’s mask, earmuffs, jacket, gloves, boots
and cover alls, by welders during welding.
• Site/ first aid delivery service station clinic shall be provided.
These mitigation measures should reduce the impact rating from moderate to minor.
These mitigation measures should reduce the impact rating from moderate to
minor.
This was identified as a potential positive impact, which could be further enhanced by
the following measures:
• Engagement of indigenous contractors and qualified resource persons.
• Compliance with SPDC procedure/criteria for indigenous labour
sourcing/employment.
The two impacts listed above were rated moderate. The mitigation measures that were
proffered to reduce their adverse effects are provided below.
Third party agitation area could be reduced from moderate to minor by:
• Clear communication on the intended future use of the recovered pipeline
section.
These mitigation measures should reduce the impact rating from moderate to minor.
Mitigation measures recommended to reduce the rating of this anticipated impact from
moderate to minor include:
• Awareness building on the implications of pipe laying activities.
• Provision of traffic warning signs during pipe laying activities for waterway
users.
• Conclusion of the activity within the shortest possible time to minimize
inconveniences to users of the waterway.
• Engagement of trained and experienced pipe laying and tie-in crew.
These mitigation measures should reduce the impact rating from moderate to
minor.
6.2.8 Backfilling
The excavated pipeline trench will be backfilled using the previously excavated
materials. Backfilling operations shall be done manually, while the bucket dredger would
be used for the river trench.
These mitigation measures should reduce the impact rating from moderate to minor.
The operations phase of the pipeline project would require such activities as external
corrosion protection through hooking up to the cathodic protection system, bi-monthly
routine pigging for internal cleaning and debris removal, SPDC six-monthly cathodic
protection and coating integrity survey as well as manual clearing of the ROW.
The two impacts listed above were both rated moderate. The mitigation measures that
were proffered to reduce their adverse effects are provided below.
Contamination of soil, sediments, surface and groundwater from oil spill could be
reduced from moderate to minor by the following mitigation measures:
• Pipelines shall be made of carbon steel materials and coated with a three-
layer polyethylene anti-corrosion coating while the weld joints shall be
coated with anti-corrosion heat-shrinkable sleeves and buried.
• The pipeline shall be placed on routine pigging for internal cleaning and
debris removal.
• The site-specific contingency plan shall be in line with the existing SPDC
oil/chemical spill contingency plan to prevent spills/leaks impacting on
environment.
6.4 DECOMMISSIONING
The pipeline system and its ancillary installations have a design life of 25 years. A
decommissioning team shall be set up to plan and implement the laid down guidelines
on decommissioning. SPDC standard procedures for decommissioning shall be in
accordance with the pipeline Act of 1965. The identified impacts of the decommissioning
activities were:
1. Increased opportunity for business and employment
2. Change in topography of the area
3. Third party agitation due to employment issues and loss of benefits as
pipeline host communities
The first among the three identified impacts listed above was positive, while the other
two were adverse and rated as moderate. The mitigation measures that were proffered
to reduce the adverse and enhance the beneficial effects are provided below.
Change in topography of the area could be reduced from moderate to minor by the
following mitigation measures:
• Care shall be taken to backfill the pipeline trench with excavated materials, in
the order of excavation.
• Trenching shall be limited to the minimum size required.
Third party agitation due to employment issues and loss of benefits as pipeline
communities could be reduced from moderate to minor by the following mitigation
measures:
• Identification and resolution of relevant stakeholders and legacy issues
7.0 INTRODUCTION
An Environmental Management Plan (EMP) is incorporated for effective management of
the environmental concerns identified in an EIA. In specific terms, the EMP provides the
means for assessing the accuracy of the predicted project impacts and monitoring of the
effectiveness of the proposed mitigation measures contained in the EIA report.
Furthermore, it serves as an instrument for ensuring future compliance with legislation,
good environmental performance and integration of environmental issues into project
decisions
The detailed plan to monitor the effectiveness of the proffered mitigation measures are
provided in the EMP Tables (Tables 7.1a-d).
The above form the fundamental principles of the management and control of
environmental impacts and effects in the EIA process. The impacts are enumerated
based on hazard identification, risk assessment and application of preventive measures.
Figure 7.1 shows the details of the Hazard and Effect Management Process. This
process will be fully incorporated in the Environmental Management Plan of the project.
Evaluate Threats to
Control Techniques
Are they
significant?
Yes
Is Control
No Practicable?
Assess
Monitor Yes
Implement Control
Techniques No
Control
Develop Corrective
Action Systems
Recover
The Environmental Management Plans (EMP) for the four phases, pre-construction,
construction, operation and decommissioning are provided in Tables 7.1a-d
Table 7.1A: Mitigation Measures/Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Pre-Construction Phase)
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Tempora Temporary Moderate The relevant Minor SPDC Pipeline Pre- Documented Once Head
ry Land- Loss of stakeholders and team constru agreement. (during Pipeline
take for land legacy issues shall be -ction land-take) Maintenance.
lay down identified and
area. addressed. Records of
Regular consultation minutes of
with stakeholders meeting with
(Govt., Community, relevant
NGOs, CBOs etc.) parties.
shall be carried out.
Adequate and prompt
compensation shall be
paid to affected land
owners/parties.
Committee made up
of representatives of
government, Rivers
State Ministry of
Environment, State
Security agencies,
communities,
contractors and
SPDC, to guide land
acquisition process/
MOU implementation
shall be set up.
Table 7.1A: Mitigation Measures/Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Pre-Construction Phase).
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Site Exposure of Moderate Workers shall be Minor SPDC Pipeline Prior to and Site Weekly Head
Prepar communities provided with PPE team during inspection throughout Pipeline
at-ion and workers (coveralls, jungle pipeline report site Maintenance.
to attack by boots, hard hat and constru- preparation
poisonous gloves) and usage ction Incident activities
snakes, enforced. reports
bees, Awareness shall be
scorpions, created among site
other wildlife workers and nearby
and contact communities on the
with likelihood of
poisonous exposure to
plants. poisonous wildlife
and plants.
First aid measures
and Medevac shall
be in place.
Anti-venom shall be
provided on site.
Opportunities Positive Indigenous Positive SPDC Pipeline During Contract Weekly Head
for business contractors and team pipeline documents throughout Pipeline
and qualified resource constructio site Maintenance.
employment persons shall be n Register of preparation
used. community activities
SPDC shall members
develop employed
procedures/criteria
for indigenous
labour
sourcing/employme
nt.
Table 7.1A: Mitigation Measures/Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Pre-Construction Phase).
Project Impact Rating Description of Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Mitigation Impact for Monitoring Frequency Party
Mitigation Rating
Site Injuries Moderate Workers shall Minor SPDC Pipeline Pre and Site inspection Weekly Head
Preparat- during be provided team during report throughout Pipeline
ion vegetatio with PPE pipeline site Maintenance.
n (coveralls, constructi Incident reports preparation
clearing. jungle boots, on activities
hard hat and Minutes of tool
gloves) and box meeting
usage
enforced.
Toolbox
meeting will
be conducted
before
commencing
site clearing
activities
First aid
facilities shall
be provided
at site
Medevac
procedures
shall be put
in place
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase).
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Labour Increased Positive Indigenous contractors Positive SPDC Pipeline During Contract Weekly Head
Requir- employme and qualified resource team pipelin documents Pipeline
ement nt, services persons shall be used. e Register of Maintenance.
and SPDC shall develop constru community
income procedure/criteria for ction members
indigenous labour employed
sourcing/employment.
Increase in Moderate Awareness campaigns Minor SPDC Pipeline Pre Reports on Weekly Head
social shall be carried out to team and community throughout Pipeline
vices enlighten the during engagement constructio Maintenance.
(violence, communities/field constru sessions n activities
drug/alcoh workers on the ction
ol abuse, implications of drug and Site
teenage alcohol abuse, inspection
pregnancie unprotected sex, report
s, prostitution and the
Commerci need to sustain cultural Minutes of
al sex values. tool box
workers Condoms shall be meetings
(CSWs), made available at the
etc) site clinic.
Alcohol consumption
and drug use shall be
prohibited during
working hours in line
with SPDC policy.
Tie in to existing
government control
programs for HIV/AIDS
control
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase).
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Labour Third Moderate Relevant Minor SPDC Pipeline Pre- Records of Weekly Head
Requir- party stakeholders’ issues team constru minutes of Pipeline
ement agitation shall be identified and ction meeting with Maintenance.
over addressed. relevant
employm Regular consultation parties.
ent with stakeholders
issues (Govt, Community,
NGOs, CBOs etc.) Register of
shall be carried out to community
understand members
community employed.
perceptions, issues
and concerns
Effective liaison/
communication
channels (Community
interface
coordinators/
community relations
officers [CIC/CROs])
from the communities
to the project
execution team shall
be maintained.
The terms of
reference for the PAC
shall include
community
employment issues.
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) cont.,
Project Impact Rating Description of Residual Impact Responsibility Timing Parameters Monitoring Responsible
Activity Before Mitigation Rating for Monitoring Frequency Party
Mitigation
Excavation/ Impairm Moderate Potable water Minor SPDC Pipeline During Site Weekly Head
Trenching ent of shall be supplied team constructi inspection Pipeline
of pipeline water to the affected on report. Maintenance
route quality communities
by during trenching The quality of
increase and excavation surface/groun
d operations. dwater shall
turbidity be monitored
in line with
regulatory
requirements.
Compliance
monitoring
reports.
Disturba- Moderate Sedimentation Minor SPDC Pipeline Pre & Site Nil Head
nce of basin with team during inspection Pipeline
aquatic effluent drains constructi report Maintenance.
life shall be on
(zooplan- constructed to
kton, allow water to
phytopla- gradually drain
nkton, back into the river
benthic without
communi turbulence
t-ies,
fisheries
etc)
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) cont.
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters for Monitoring Responsible
Activity Before Impact Monitoring Frequency Party
Mitigation Rating
Excavati- Interfer-ence Moderate SPDC shall Minor SPDC Pipeline During Site inspection Weekly Head
on/ with river determine area of team constru report. Pipeline
Trenching based impact, Identify and -ction Maintenance.
of pipeline tradition-al compensate Documentation
route occupant-ions community on
(fishing, members directly compensation
cassava/ palm affected paid.
produce
processing
etc).
Excavati- Third party Moderate SPDC shall Minor SPDC Pipeline During Site inspection Weekly Head
on/ agitation from determine area of team constru and community Pipeline
Trenching impairment of impact, Identify and ct-ion engagement Maintenance
of pipeline surface water compensate reports
community members
route quality directly affected.
Consultation with
stakeholders (Govt., Status of
Community, NGOs, implementation
CBOs etc.) shall be of grievance
sustained. procedures.
Liaison/communicatio
n channels
(CICs/CROs)
between the
communities and the
project execution
team shall be
maintained.
Project Advisory
Committee (PAC)
shall be set up to
develop and ensure
implementation of
grievance
procedures.
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters for Monitoring Responsible
Activity Before Impact Monitoring Frequency Party
Mitigation Rating
Increased Positive Nigerian Positive SPDC Pipeline During Contract Weekly Head
opportunity for contractors and team constru documents Pipeline
employment resource (qualified) ction Maintenance
and business persons shall be Register of
used community
SPDC members
procedure/criteria employed
for indigenous
labour
sourcing/employme
nt shall apply.
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km
Okordia – Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) contin
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Site Genera Moderate Awareness Minor SPDC Pipeline Pre/ Medical Weekly Head
Fabrication tion of sessions on health team during- certificates of Pipeline
(Welding) high risks and safety constru fitness. Maintenance
and Non intensit precautions of ction
Destructive y welding operations Minutes of
Testing welding shall be carried out toolbox
(Radiograph flash for workers. meetings/saf
y) and Pre-employment ety briefings.
noise medical certification
shall be carried out Site
for the welders. inspection
SPDC shall enforce reports.
the use of welder’s
mask, earmuffs, Results of
jacket, gloves, radiation tag
boots and cover monitoring
alls, by welders
during welding.
A site clinic shall be
provided.
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Site Burns/i Moderate Awareness Minor SPDC Pipeline Pre/ Minutes of toolbox Head
Fabrication njuries sessions on health team during- meetings/safety briefings. Pipeline
(Welding) from risks and safety constru Maintenance
and Non welding precautions of ction Site inspection reports.
Destructive sparks welding operations
Testing shall be carried out
(Radiography for workers.
) SPDC shall enforce
the use of welder’s
mask, earmuffs,
jacket, gloves,
boots and cover
alls, by welders
during welding.
A site clinic shall be
provided.
SPDC MEDEVAC
procedure shall
apply.
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) cont.,
Project Impact Rating Description of Mitigation Residu Responsibility Timing Parameters Monitoring Responsible
Activity Before al for Monitoring Frequency Party
Mitigation Impact
Rating
Site Exposure Moderate Health awareness Minor SPDC During Minutes of Weekly Head
Fabrication to training shall be Pipeline team - toolbox Pipeline
(Welding) radiation conducted prior to constr meetings/safe Maintenance
and Non from commencement of uction ty briefings.
Destructive radiograp activities.
Testing hy with Staff shall undergo Site
(Radiograp possibiliti routine medical inspection
hy) es of check-ups for reports.
genetic radiation exposure.
mutation. Radiation monitors Records of
shall be provided to medical
monitor radiation checks.
levels above
threshold. Results of
The use of radiation tag
radiography aprons monitoring
to protect the body
from radiation shall
be enforced.
Warning signs shall
be provided during
actual activities.
The activity shall be
carried out in
accordance with
standard
construction
specifications.
Project Impact Rating Description of Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Mitigation Impact for Monitoring Frequency Party
Mitigation Rating
Waste Increased Positive Indigenous Positive SPDC Pipeline During Register of Weekly Head
Generatio opportunity contractors and team pipelin community throughout Pipeline
n for qualified e members site Maintenanc
(Solid/Liqu business resource constr employed preparation e
id/ and persons shall uction activities
Gaseous) employme be used.
nt. SPDC shall
develop
procedures/crite
ria for
indigenous
labour
sourcing/emplo
yment.
Cutting of Contaminat Moderate Emergency oil Minor SPDC Pipeline During Compliance Weekly Head Pipeline
existing ion of soil spill team pipelin monitoring Maintenance
pi-peline and water control/preventio e report.
after from n equipment constr
flushing residual shall be uction Site
flow back provided. Inspection
Surface water report.
quality 500 m
upstream and
downstream of
the site location
shall be analysed
in line with DPR
requirements.
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) cont.,
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Removal of Third party Moderate Clear communication Minor SPDC Pipeline During Site Nil Head
replaced agitation on the intended future team constru inspection/ Pipeline
(old) use of the recovered ction scrap Maintenance
pipeline pipeline section. consignment
section. notes.
Impairment Moderate Potable water shall be Minor SPDC Pipeline During Evidence of Weekly Head Pipeline
of water supplied to the affected team constru compliance Maintenance
quality by communities during ction
increased trenching and
turbidity excavation operations.
The quality of
surface/groundwater
shall be monitored in
line with regulatory
requirements.
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) cont.,
Project Impact Rating Description of Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Mitigation Impact for Frequency Party
Mitigation Rating Monitoring
Backfilling of Impairment Moderate Potable water Minor SPDC Pipeline Pre/Du Site Weekly Head
the trenches of water shall be supplied team ring inspection Pipeline
quality by to the affected constru report. Maintenance
increased communities ction
turbidity during trenching Documenta
and and excavation tion on
disruption operations. compensati
of fishing Affected on paid.
grounds fishermen shall be
adequately Complianc
compensated. e
monitoring
reports.
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) cont.,
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsibl
Activity Before Impact for Monitoring Frequency e
Mitigation Rating Party
Backfilling Third Moderate Determine area of Minor SPDC During Site Weekly Head
of the party impact, Identify/ Pipeline team construc inspection Pipeline
trenches agitation compensate tion report. Maintenan
from community members ce
increase directly affected. Community
d water Consultation with engagement
turbidity stakeholders (Govt., report.
and Community, NGOs,
disruptio CBOs etc.) shall be
n of sustained. Documentatio
fishing Liaison/communicatio n on
grounds n channels compensation
. (CICs/CROs) from paid.
the communities to
the project execution
team shall be
maintained.
Project Advisory
Committee (PAC) to
develop and ensure
implementation of
grievance procedures
Table 7.1B: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Construction Phase) cont.
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters for Monitoring Responsible
Activity Before Impact Monitoring Frequency Party
Mitigation Rating
Pipeline Blockage Moderate Awareness on the Minor SPDC Pipeline During Reports of Weekly Head
Laying of water implications of pipe team constru minutes of Pipeline
and Tie- ways/incre laying activities ction awareness Maintenance
in ase in shall be carried out. sessions
maritime Traffic warning
activities signs shall be Site inspection
resulting in provided for
increased waterway users.
accidents. Trained and
experienced pipe
laying and tie-in
crew shall be used.
Table 7.1C Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Operations/Maintenance Phase).
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Respons
Activity Before Impact for Monitoring Frequency ible
Mitigation Rating Party
Operations/ Contaminat Moderate Pipelines shall be made Minor SPDC Pipeline During Site inspection Six- Head
Maintenan- i-on of soil, of carbon steel team operation reports, monthly, Pipeline
ce sediments, materials and coated s/m- Compliance Five yearly Mainten
(cathodic surface and with a three layer aintenan monitoring ance
protection) groundwate polyethylene anti- ce reports,
r from oil corrosion coating while
spill the weld joints shall be Reports of
coated with anti- pipeline
corrosion heat- Integrity check
shrinkable sleeves and reports
provided with over-
pressurisation
protection system and
buried.
Pipelines in marshy
areas and at water
crossings shall have a
yard applied concrete
coating over the anti-
corrosion coating.
The pipeline shall be
placed on routine
pigging for internal
cleaning and debris
removal.
The five-yearly
statutory internal
inspection by intelligent
pig for integrity checks
shall be carried out.
Table 7.1C Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Operations/Maintenance Phase).
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Operations/ Conta Moderate The pipeline will be Minor SPDC Pipeline During Site Six- Head
Maintenan- minati- placed on the SPDC team operation inspection monthly, Pipeline
ce on of six-monthly cathodic s/m- reports, Five yearly Maintenance
(cathodic soil, protection and aintenan Compliance
protection) sedime coating integrity ce monitoring
nts, survey programme. reports,
surface The pipelines shall be
and designed to contain Reports of
ground at least the maximum pipeline
water discharge pressure of Integrity
from oil the flowstations/ check reports
spill manifolds, in order to
withstand pressure.
The Adibawa and
Ubie flowstations are
equipped with
automatic and
emergency
shutdown, pressure
relief, leak detection
and audible/ visible
alarm early warning
systems.
The site-specific
contingency plan
shall be in line with
the existing SPDC
oil/chemical spill
contingency plan to
prevent spills/leaks
impacting on
environment.
Table 7.1C Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Operations/Maintenance Phase).
Project Impact Rating Description of Residual Responsibility Timing Parameters for Monitoring Responsible
Activity Before Mitigation Impact Monitoring Frequency Party
Mitigation Rating
Operation Destructio Moderate Toolbox meetings Minor SPDC During Site After any Head
s/ n of assets shall be held prior Pipeline team operatio inspection incident Pipeline
Maintena- and to any operations ns/ reports. Maintenance
nce properties Fire protection Maintena
(cathodic from oil facilities nce Evidence of
protection) spill fire (detection, fighting periodic fire
incidents. and control) shall drills.
be provided at the
flowstation and Evidence of
inspected and compensation
drills carried out. .
SPDC emergency
response
procedures
(where assistance
could be quickly
sought from third
party
establishments, if
the fire cannot be
controlled by
SPDC) shall be
implemented.
Adequate
compensation
shall be paid to
affected parties.
Table 7.1D: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km Okordia –
Rumuekpe (Sombriero River) Pipeline Replacement Project (Final Decommissioning Phase)
Project Impact Rating Description of Mitigation Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Impact for Monitoring Frequency Party
Mitigation Rating
Decom Increased Positive Indigenous Positive SPDC During Contract Monthly Head
mi- opportunity contractors and Pipeline team decom documents. Pipeline
ssionin for resource (qualified) missio Maintenance
g employment persons shall be ning Register of
and used. community
contracting SPDC shall members
resulting in develop employed.
increased procedure/criteria
income for indigenous
labour
sourcing/employme
nt.
Change in Moderate Care shall be taken Minor SPDC During Site Weekly
topography of to backfill the Pipeline team decom inspection
the area pipeline trench with missio reports.
excavated ning
materials, in the
order of excavation.
Trenching shall be
limited to the
minimum size
required.
Table 7.1D: Mitigation Measures/ Management Plan Table for the 44m section of the 14” X 33.4 Km
Okordia – Rumuekpe (Sombriero River) Pipeline Replacement Project (Final Decommissioning Phase)
Project Impact Rating Description of Residual Responsibility Timing Parameters Monitoring Responsible
Activity Before Mitigation Impact for Monitoring Frequency Party
Mitigation Rating
Decom Third Moderate The relevant Minor SPDC Pipeline During Site inspection Weekly Head
mi- party stakeholders and team decom Pipeline
ssioning agitation legacy issues shall mission Community Maintenance
due to be identified and ing engagement
employ addressed. reports.
ment Regular consultation
issues with stakeholders
and loss (Govt., Community,
of NGOs, CBOs etc.)
benefits shall be carried out.
as Committee made up
pipeline of representatives of
commu government, Rivers
nities State Ministry of
Environment, State
Security agencies,
communities,
contractors and
SPDC, to guide land
acquisition process/
MOU implementation
shall be set up.
Note: SPDC Waste Management Plan shall apply to anticipated wastes from the proposed pipeline replacement project
8.0 CONCLUSION
The EIA of the Okordia – Rumuekpe Sombreiro River Crossing Project has been
carried out in accordance with the regulatory requirements established by the
Federal Republic of Nigeria, other statutory and international standards. The potential
impacts of the project on the existing environment have been identified and
evaluated, based on the interactions between the project activities and the various
environmental sensitivities (biophysical, social and health).
The magnitude of the anticipated impacts of the project activities on air, water, soils,
sediment, vegetation, fauna, fisheries, land use, waste management, socio-economic
and health issues were rated and mitigation measures proffered to reduce the
magnitude of identified negative impacts to a level as low as reasonably practicable
(ALARP) and further enhance the benefits of the positive impacts. These mitigation
measures are incorporated in the Environmental Management Plan (EMP) developed
specifically for this project and applicable to its entire life span (pre-construction
survey to decommissioning).
The approval of this EIA report for the execution of the project is hereby requested
for sustainable development.
APPENDICES
APPENDIX 2.1
SPDC 2003-
2003-065
Revision 0, Ver. 01 March 2003
STATUS PAGE
A g r e e d b y:
Approved by:
Distribution:
Distribution All SPDC staff via Intranet, Corporate HSE Website
To be revised before: March 2004
Change history:
history
Revision Date Pages Reason
0 March 2003 All Initial publication
Language:
In this document the recommendations for a course of action are made with varying degrees of
emphasis. As a rule:
The word ‘may’ indicates a possible course of action
The word ‘should’ indicates a preferred course of action
The word ‘shall’ indicates a mandatory course of action
Deviations:
Deviations:
This procedure supersedes all other earlier versions and the Document Custodian must agree to further
deviations in writing.
Document control
The only controlled and valid version of this procedure is the document on the SPDC HSE web page,
of which HSX-ENVW is the custodian.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 2 of 88
List of Appendices
_______________________________________________________________________________________________
Table of Contents
TABLE OF CONTENTS ......................................................................................................... 3
LI S T OF F I G UR E S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
LI S T OF A PP EN D I CE S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Er r or! B oo k m a r k n o t d ef in e d.
1 I N TR O D U C TI O N . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.1 BACKGROUND ........................................................................................................ 6
1.2 PURPOSE ............................................................................................................... 6
1.3 SCOPE ................................................................................................................. 6
1.4 RELATED DOCUMENTS ............................................................................................... 6
1.5 DEFINITIONS & ABBREVIATIONS .................................................................................. 10
2 L E A D ER S H I P A N D C O MM I T M E N T . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 1
3 P O L I C Y A ND S TR A T E G IC OB J E C TI V E . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 2
3.1 WASTE MANAGEMENT POLICY ................................................................................... 12
3.2 WASTE MANAGEMENT PLANNING .............................................................................. 12
3.3 ENVIRONMENTAL IMPACT ASSESSMENT ......................................................................... 12
3.4 REGULATORY AND LEGAL REQUIREMENTS ........................................................................ 13
4 . O R G AN I Z A T IO N, R E S PO N S IB I L I T IE S, R E S OUR C E S , S TA N D AR DS AN D
D O C U M EN T A T IO N . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 4
4.1 ORGANISATION AND RESPONSIBILITIES .......................................................................... 14
4.1.1 ORGANISATIONAL STRUCTURE .................................................................................... 14
4.1.2 ROLES AND RESPONSIBILITIES ..................................................................................... 15
4.1.2.1 HSX-ENVW RESPONSIBILITIES ................................................................................ 16
4.1.2.2 SSC-CLN RESPONSIBILITIES .................................................................................... 17
4.1.2.3 SSX-WST RESPONSIBILITIES .................................................................................... 18
4.1.2.4 DWR-EVX RESPONSIBILITIES.................................................................................... 18
4.1.2.5 LINE DEPARTMENTS’ RESPONSIBILITIES ......................................................................... 19
4.2 RESOURCES AND COMPETENCE .................................................................................. 19
4.2.1 COMPETENCE DEVELOPMENT .................................................................................... 19
4.2.2 TRAINING ............................................................................................................ 19
4.2.3 BUDGETING ......................................................................................................... 20
4.3 COMMUNICATIONS ............................................................................................... 20
4.4 CONTRACTOR MANAGEMENT ................................................................................... 20
4.5 STANDARDS ......................................................................................................... 20
4.5.1 REGULATORY STANDARDS AND COMPLIANCE ................................................................... 20
4.5.2 WORKSITE SAFETY .................................................................................................. 20
4.5.3 WASTE SEGREGATION ............................................................................................. 20
4.5.4 WASTE CATEGORISATION ......................................................................................... 20
4.5.5 WASTE MANAGEMENT PERFORMANCE INDICATORS .......................................................... 21
4.6 DOCUMENTATION AND RETENTION OF RECORDS ............................................................. 21
4.6.1 WASTE INVENTORY ................................................................................................ 21
4.6.2 DOCUMENT CONTROL ............................................................................................ 22
5 . H A Z A R D S A N D EFF E C TS M A N A GE M E N T . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 3
5.1 IDENTIFICATION ..................................................................................................... 23
5.1.1 WASTE IDENTIFICATION ........................................................................................... 23
5.1.2 WASTE CHARACTERIZATION ...................................................................................... 23
5.1 ASSESSMENT ........................................................................................................ 23
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 3 of 88
List of Appendices
_______________________________________________________________________________________________
6 . PL A NN I N G A N D PR O C E DU R E S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 4
6.1 PLANNING AND IMPLEMENTATION STRATEGIES................................................................. 24
6.2 PROGRESSIVE REDUCTION OF WASTES ........................................................................... 24
6.3 WASTE MANAGEMENT IN OPERATING PROCEDURES .......................................................... 24
6.4 DEVELOPMENT, REVIEW AND PUBLICATION OF PROCEDURES.................................................. 24
7 . I M P L E M E N TA T I O N, MO N I T OR IN G AN D C OR R E C T IV E A C T IO N . . . . . . . . . . . . . 2 5
7.1 REGULATORY COMPLIANCE MONITORING ...................................................................... 25
7.2 NON-COMPLIANCE MANAGEMENT ............................................................................. 25
7.3 PERFORMANCE MEASUREMENT AND REPORTING ............................................................... 25
7.4 WASTE TARGET SETTING AND MONITORING ................................................................... 25
7.5 WASTE TRACKING.................................................................................................. 25
7.6 ASSET INTEGRITY .................................................................................................... 25
7.7 INCIDENT MONITORING, REPORTING, INVESTIGATION AND FOLLOW-UP ................................. 25
8. AUDIT ................................................................................... 26
8.1 WASTE MANAGEMENT AUDIT .................................................................................... 26
8.2 AUDITORS’ COMPETENCIES ....................................................................................... 26
8.3 FOLLOW-UP .......................................................................................................... 26
9 . R E V IE W . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 7
9.1 QUARTERLY & ANNUAL PERFORMANCE REVIEW ................................................................. 27
9.2 WMS REVIEW ...................................................................................................... 27
9.3 ORGANIZATION CHANGES ....................................................................................... 27
R EF ER EN C E S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 8
A P P E ND I C E S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 9
APPENDIX 1: WASTE MANAGEMENT POLICY ................................................................ 29
APPENDIX 2: ROLES & TASKS IN WASTE MANAGEMENT PROCESS………………………..….28
AP P EN D IX 3 : W A ST E I NV EN T OR Y M AS T ER S H EE T .............................................. 30
AP P EN D IX 4 : W A ST E M AN A G E ME N T F A C IL I T IE S ................................................ 37
A p p e n d i x 5: W AS T E MA N A G E M E N T F O C AL PO I N T S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 9
List of Figures
Figure 1: WMS Manual With Group & SPDC Guidelines……………………………..……………6
Figure 2: Waste Management Planning Approach………………………………….………….…..10
Figure 3: Waste Management Organisational Chart…………………….…….………..………….12
Figure 4: Waste Management Roles & Responsibilities…………………..………………...……....13
Figure 5: Waste Management Classification Structure……………………………………..……….16
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 4 of 88
List of Appendices
_______________________________________________________________________________________________
List of Tables
L i s t Of S P D C R el a t e d Do c u m en ts … … …. …… …… … … .. …… … … …… ..… … … . 7
Definitions And Abbreviations In This Document……………………………………….…………8
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 5 of 88
List of Appendices
_______________________________________________________________________________________________
1 INTRODUCTION
1.1 Background
The deployment of a new Services Directorate in January 2003 prompted the review of the existing
waste management system. The re-organization, which gave rise to the setting up of an Integrated
Waste Management (SSX-WST) and Waste Management Technical Authority (SSC-CLN) teams in the
Logistics Department of the new directorate, has created changes in the existing waste management
process in SPDC.
As it were, Production Services, Utilities, Estate Services and General Services who were separate line
departments running waste management business in the old organisation, have come under the new
directorate, with all waste management activities being integrated and to be managed by SSX-WST
(Integrated Waste Management Team), with technical support from SSC-CLN.
1.2 Purpose
This Waste Management System Manual is developed to:
Document SPDC’s waste management system
Delineate the key roles and responsibilities for waste management delivery process
Provide direction on the interface between the line departments and corporate waste
management team.
1.3 Scope
This document provides the relevant steer to managing waste (any material to be disposed of, as
being of no further primary use, but excludes aqueous and gaseous effluents) in SPDC. It is structured
to be in conformity with relevant Group HSE and Waste Management Guides as well as SPDC HSE-
MS Manual.
It shall be applicable to waste management process in all SPDC locations. In other words, activities,
assets or organization in the waste management business shall be guided by this document.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 6 of 88
List of Appendices
_______________________________________________________________________________________________
Shell Group
Statement of
General Business
Policy Guidelines on
Health, Safety and
the Environment
Waste Management
Guide
SPDC
HSE-MS Manual
Other Guides
Waste Management
System Manual
Implementation Monitoring
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 7 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 8 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 9 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 10 of 88
List of Appendices
_______________________________________________________________________________________________
SPDC’s waste management is given top management attention. Waste Management leadership is
vested in the Corporate Waste Management Team and all Line Departments. In SPDC, commitment to
waste management is visible as in:
The allocation of resources for complying with the waste management policy.
The participation of top management in waste management reviews, workshops and inspections.
The approval of initiatives for waste management performance improvement.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 11 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 12 of 88
List of Appendices
_______________________________________________________________________________________________
The major regulatory guidelines and standards governing EP waste management business in Nigeria
include:
DPR Environmental Guidelines & Standards for the Petroleum Industry in Nigeria - 1991
FEPA Guidelines and Standards for Environmental Pollution Control in Nigeria - 1991
Compliance with waste management legislation is a line responsibility and is assured by compliance
verifications conducted by HSE-SYSA. Non-compliance is reported and followed up until they are
closed out.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 13 of 88
List of Appendices
_______________________________________________________________________________________________
SVD DMD
HSX-ENVW
DWR-EVX
DMP-HSE
PTX-HSE
PAX-HSE
PBX-HSE
PCX-HSE
VRL-ENV
PPX-HSE
POM-HSE
DTX-HSE
DEE-SVC
RPL
Waste management activities are undertaken in various forms in the different Directorates in the entire
company with locations in Abuja, Logos, Port Harcourt, Warri and Offshore. The directorates
include:
1. Human Resources (HRD)
2. New Business and Exploration (BDD)
3. External Relations (RXD)
4. Commercial and Finance (CFD)
5. Development (DVD)
6. Production (PDD)
7. Services (SVD)
The industrial and domestic activities of these directorates generate waste, which are managed in line
with relevant SPDC guidelines and procedures. Except waste from drilling, all wastes shall be
transported, treated and disposed by the Services Directorate.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 14 of 88
List of Appendices
_______________________________________________________________________________________________
WASTE
WASTEMANAGEMENT
MANAGEMENTGT IN CORPORATE HSE
IN CORPORATE
HSE WMS process
• WMS process driver
• Research
Research& &
driver development
• development
Guidelines & & Standards
HSE guidelines
• Regulatory
Regulatorycompliance
standards compliancemonitoring
monitoring
WASTE MGT.
WASTE MGT. TECHNICAL
TECHNICAL (SSC) -CLN)
AUTHORITY
AUTHORITY
(SSC • Corporate
Corporateperformance
performance reporting
•Technical
Technical
reportingguidelines & standards
• support
Standards
Procedures &
procedures
• Waste Mgt.Plan
LINE
L DEPARTMENTS
WASTE MGT. TECHNICAL AUTHORITY (SSC)
SSX -WST
WST DWR -EVE OTHER LINES
Report performance
via WMIS
Liase with SSX -WST to
Transport waste from transport, treat &
Drilling & other sites dispose waste
to WM facilities
Generate other waste
& segregate at source
Recycle, treat and
dispose waste
Inventorise and report
quantity via WMIS
Report performance
to SSC -CLN
Liase with SSX -WST to
transport, treat &
dispose waste
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 15 of 88
List of Appendices
_______________________________________________________________________________________________
The figure above shows waste management key roles and the relationship among the various waste
management teams namely HSX-ENVW, SSC-CLN, SSX-WST and other Line Departments. Details of
the specific roles in each waste management business activity and the overlaps within the various
teams are presented in Appendix 2. However high level responsibilities to be performed by HSX-
EVW, SSC-CLN, SSX-WST and the other Waste Management Line Departments are presented in
Sections 4.1.2.1 – 4.1.2.5 below.
4.1.2.1 HSX-
HSX-ENVW Responsibilities
The responsibilities of the Corporate Waste Management Team (HSX-ENVW) are as follows:
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 16 of 88
List of Appendices
_______________________________________________________________________________________________
4.1.2.2 SSC-
SSC-CLN Responsibilities
The responsibilities of the Corporate Waste Management Technical Authority team (SSC-CLN) are as
follows:
Be custodian of Waste Inventory Process, which includes management of WMIS & WCN
and training of users.
Carry out inspections and audits on waste management facilities in liaison with HSX-ENVW
Collate waste inventory data from drilling, SSX-WST and other line departments, using
WMIS.
Comply with MEE in all aspects of the waste management operations.
Conduct characterization and analysis of wastes in liaison with HSX-ENVW
Create awareness on standard waste management practice
Develop and maintain 5-year corporate waste management master plan.
Develop strategy and programme for waste minimisation based on waste forecast.
Develop strategy for deploying new waste management issues to the line departments.
Develop work procedures, instructions and technical standards of facilities, equipment and
systems for waste transportation, treatment and disposal.
Identify improvement opportunities to existing waste transportation, treatment and disposal in
liaison with HSX-ENVW.
Implement the Waste Management System requirements.
Maintain and review the corporate waste management master plan in liaison with HSX-
ENVW.
Plan and organize quarterly and annual waste management performance reviews.
Provide standards for setting up, operating and maintaining waste management facilities.
Participate in review of the waste management master plan and the waste management
manual.
Develop, and deploy HEMP to line on waste management functions.
Develop and maintain a database on waste management facilities capacities and
operational status vis-à-vis waste forecasts and reduction programmes.
Provide support to HSX-ENVW on waste petition management.
Quality-check waste inventory data from drilling and other line departments and report to
HSX-ENVW.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 17 of 88
List of Appendices
_______________________________________________________________________________________________
4.1.2.3 SSX-
SSX-WST Responsibilities
The responsibilities of the Integrated Waste Management Team (SSX-WST) are as follows:
4.1.2.4 DWR-
DWR-EVX Responsibilities
The responsibilities of the Drilling Waste Management Team (DWR-EVX) are as follows:
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 18 of 88
List of Appendices
_______________________________________________________________________________________________
4.2.2 Training
A wide range of HSE training including waste management is made available to all SPDC staff. This
training can be sourced through the HR function, through the corporate HSE function and via line
management approval from external sources. The Corporate Learning & Development (HRW-LD)
‘Learning Guide’ provides details of training courses available to Company staff and Contractor
personnel, and describes the nominations and course attendance process.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 19 of 88
List of Appendices
_______________________________________________________________________________________________
4.2.3 Budgeting
Every line department shall provide budget for the execution of its waste management work plan.
However a centralized budget for HSE training exists within the HR function.
4.3 Communications
Waste management work plans, standards, instructions, and performance are documented, discussed
in review meetings, shared via e-mails, published on the web, in newsletters or printed and distributed
to all responsible parties. Waste management process documents are available on the web @:
http://sww.phc.spdc.shell.ng/dir/pdd/hse/St3/environ/WMhome_page_1.htm
4.5 Standards
4.5.1 Regulatory Standards and Compliance
Relevant regulatory standards such as the Environmental Guidelines and Standards for the Petroleum
Industry in Nigeria (EGASPIN) 1991, and the FEPA (now FME) Environmental Guidelines and
Standards for Pollution Control in Nigeria, 1991 provide the basic regulations on waste management
in Nigeria. State EPAs, and other relevant international laws and conventions ratified by Nigeria are
also complied with. Detailed regulatory review is provided in Section Five of the SPDC Waste
Management Manual, 2001.
1. SIEP standard: which include wastes from core exploration and production activities but excludes
aqueous and gaseous effluents. This category does not include domestic and office wastes, and
are called EP Wastes.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 20 of 88
List of Appendices
_______________________________________________________________________________________________
2. SPDC standard: which include wastes from all forms of company activities, but excludes aqueous
and gaseous effluents. This category of wastes is called OU waste.
The figure below shows the waste classification structure. Detailed information is contained in the
Waste Classification Guide, 2002.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 21 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 22 of 88
List of Appendices
_______________________________________________________________________________________________
5.2 Assessment
5.2.1 Waste Disposal Screening Criteria
Waste screening criteria shall be used to assess a waste before discharge. This assessment shall
indicate whether or not a waste is qualified for discharge or requires further treatment. The guide for
this assessment shall be developed.
5.3 Control
5.3.1 Waste Handling, Treatment and Disposal
Methods for waste handling from generation to disposal are provided in the Procedure for handling,
transport and disposal of waste. Available and applicable treatment methods are presented in Section
6.9 of the Waste Management Manual.
5.4 Recovery
5.4.1 Emergency Response
Emergency response plan for waste related incident shall be developed.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 23 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 24 of 88
List of Appendices
_______________________________________________________________________________________________
7.2 Non-
Non-compliance Management
Non-compliance with HSE requirements and regulatory legislation shall be managed in line with the
Procedure for HSE MS Non Compliance and Corrective Action Reporting.
7.4 Waste
Waste Target Setting and Monitoring
Waste target setting and monitoring against actual performance is used for the development of a
realistic waste reduction programme. Currently, waste target setting (forecasting) is being developed
and shall be monitored until it is validated and suitable for the development of a waste reduction plan.
Line Departments and SSC-CLN shall agree to set the targets thereafter the former shall be the sole
owner of the targets. The performance against targets shall be published and communicated to all
responsible parties. Deviations greater or less than 20% from actual shall be reviewed and
documented. Details are presented in SPDC Waste Prediction Modelling, Deployment and Monitoring
Plan.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 25 of 88
List of Appendices
_______________________________________________________________________________________________
8. AUDIT
8.1 Waste Management Audit
Waste management audit is planned, driven and conducted by HSX-ENVW in liaison with the Line
Departments. The audit shall cover all the waste management system elements, as shown in Appendix
L of the Waste Management Manual.
8.3 Follow-
Follow-up
Waste management audits and inspections recommendations shall be tracked via an electronic
system. Recommendations shall be implemented and followed up by Action Parties until they are duly
closed out.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 26 of 88
List of Appendices
_______________________________________________________________________________________________
9. REVIEW
9.1 Quarterly & Annual Performance Review
SSC-CLN shall hold quarterly and annual waste management performance reviews, where plans &
performance, waste data reports & forecast, facilities operational status etc shall be communicated.
All line waste management focal points are expected to attend these reviews. Appendix 5 presents
the list of waste management focal points in SPDC. HSX-ENVW shall participate in these meetings.
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 27 of 88
List of Appendices
_______________________________________________________________________________________________
REFERENCES
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 28 of 88
List of Appendices
_______________________________________________________________________________________________
APPENDICES
It is SPDC’s policy
• to take all practical and reasonable measures to minimize the generation of solid
and liquid waste, as well as emissions from flares and otherwise
• not to use Mineral Oil-based muds in drilling
• to manage and dispose of such wastes in a statutory and environmentally
responsible manner
• to track and maintain records of the full life cycle of waste streams and provide
an auditable trail as to its management and disposal
__________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 29 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 30 of 88
List of Appendices
_______________________________________________________________________________________________
Provide
appropriate
equipment for waste
segregation
5. Waste Characterization & Support SSC-CLN in Conduct
Analysis matters of waste characterization and
characterization and analysis of wastes in
analysis liaison with HSX-
ENVW.
6. Waste Minimization Harmonize waste Develop strategy Implement waste Implement waste Implement waste
minimization strategies and programme for minimization minimization minimization strategies
waste minimization. strategies (recycle strategies (reduce, (reduce, reuse, recycle
and reuse) reuse, recycle and recovery)
recover)
7. Waste Transportation Provide technical Collect and Transport and Collect waste at
support to SSX-WST to transport waste from dispose drilling designated collection
effectively carry out designated collection waste from point of points
waste transportation. points to disposal generation to
facilities. disposal facilities.
__________________________________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 31 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 32 of 88
List of Appendices
_______________________________________________________________________________________________
Maintain and
review the hazardous
waste register.
__________________________________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 33 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 34 of 88
List of Appendices
_______________________________________________________________________________________________
__________________________________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 35 of 88
List of Appendices
_____________________________________________________________________________________________
__
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 36 of 88
List of Appendices
_____________________________________________________________________________________________
OU Waste
OU Non-hazardous wastes OU hazardous wastes
Air filters generated Tonne Asbestos generated Tonne
Aqueous effluents (e.g kitchen waste water) generated Tonne Batteries (wet and dry) generated Tonne
Ashes generated Tonne Clinical + medical waste generated Tonne
Ballast water generated Tonne Mercury waste/fluorescent tubes generated Tonne
Blasting grit generated Tonne Obsolete chemicals generated Tonne
BOP fluids generated Tonne Spent chemicals generated Tonne
Cans and tins generated Tonne
Cement water generated Tonne
Computer toner cartridges generated Tonne
Construction and delomition materials generated Tonne
Contaminated cement generated Tonne
Contaminated soil from fresh spill site generated Tonne
Contaminated soil from saver pits generated Tonne
Contaminated soil from surge vessels generated Tonne
Dredge spoil generated Tonne
Drilled cement generated Tonne
Food generated Tonne
Garbage generated Tonne
Garden waste generated Tonne
Glass generated Tonne
Oil & fuel filters generated Tonne
Oily rags generated Tonne
Oily sludge generated Tonne
Paper generated Tonne
Pigging waste generated Tonne
Plastics generated Tonne
SBM (whole mud generated) generated Tonne
SBM cuttings generated generated Tonne
Scrap metals (include drums) generated Tonne
Sewage generated Tonne
Spent lube oil generated Tonne
Tyres and tubes generated Tonne
Used absorbents generated Tonne
water filters generated Tonne
WBM (whole mud generated) generated Tonne
WBM cuttings generated generated Tonne
Workover/completion fluids generated Tonne
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 37 of 87
List of Appendices
_____________________________________________________________________________________________
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 38 of 87
List of Appendices
_____________________________________________________________________________________________
EAST WEST
Data Group Data Focal Point Activity Ref. Ind. Tel Data Focal Point Activity Ref. Ind. Tel Reportable Parameter
Activity Level Ejike, S. M Drilling Operations DWE-OPS 21488 Anighoro Sunny Drilling Operations DWW-OPS 42979 Hole length drilled with water-based mud (WBM
Hole length drilled with synthetic mud (SBM)
Total hole length drilled
Ayanruoh Henry Seismic DTW-GPH 42642 Seismic 3d Onshore/Offshore
Halons, CFCs, HCFCs and HFCs Nwosu, S.I AC Maintenance PSE-UAR 21393 Odeh Ben Utilities Maintenance PSW-UTL 47158 Halons and CFCs in stock and equipment
Ohwofasa Queen Utilities Maintenance PSW-UTL 46463 Halons and CFCs lost to atmosphere
Ezuma W.I Civil Maintenance PSW-CVL 47025 HCFCs and HFCs in stock and equipment
Imhoke Solomon Terminal Operations PTW-HSE 45030 HCFCs and HFCs lost to atmosphere
Oil-containing Effluents Adesina, T Production Data PIE-OGA 22773 Ofovwe Kevwe Production Data PIW-OGA 43469 Total produced water
Produced water discharged to fresh/brackish
water
Produced water discharged to sea
Produced water discharged to surface
environment
Oil discharged with produced water to
fresh/brackish water
Oil discharged with produced water to sea
Average oil concentration in produced water to
surface environment
Oil discharged with produced water to surface
environment
Oil discharged with other effluents to surface
Epidei, M.O Production Marine Services PTE-MAR 28514 environment
(Semi) Solid & Liquid Wastes Akpan, E.E Geomatics DTE-GEM 21601 Food, Plastic, Glass, Paper, Oil filters,
unsegregated waste, Carton, Battery
Onyeukwu, P.C Seismic DTE-HSE 21702 Ayanruoh Henry Seismic DTW-GPH 42642 Food, Plastic, Glass, Paper, Garbage, Garden,
Scrap metals, Sewage, Empty tins/cans, Oil filters,
Toner cartridges & Battery
Nnogo, C Office Services HGE-GEN 21798 Paper, Garbage, Restaurant water & Sewage
Ajiere, I Production Team A PAE-HSE 24607 Ehenemba Nicholas Production Operations PAW-HSE 42559 Food, Plastic, Glass, Paper, Garbage, Garden,
Scrap metals, Empty tins/cans, Oil filters, Oily
waste, Oil rags, Absorbents, Fan belt, Water filters
& Fluorescent tubes, Sewage
Amakiri, W.D Medical MDE-PUB 22442 Adeogun Kenny Medical MDW-OH 46854 Garbage, Medical/Clinical waste
Aigbotsua, P.P Production Team B PBE-HSE 20855 Adeyemi Adesoji Production Operations PBW-HSE 42534 Food, Plastic, Glass, Paper, Garbage, Garden,
Sewage, Scrap metals, Oily waste, Oil sludge,
Ashes, Contaminated soil, Medical/Clinical waste
& Fluorescent tubes, Oil & Fuel Filters
Nnokam, A.E Production Team C PCE-HSE 22261 Folashade Oladipo Production Operations PCW-HSE 42556 Food, Plastic, Glass, Paper, Garbage, Garden,
Sewage, Scrap metals, Oily waste, Oil sludge,
Ashes, Contaminated soil, Medical/Clinical waste
& Fluorescent tubes, Oil & Fuel filters
Aloba, P.O Pigging Operations PPE-OPS 21825 Neboh Candid Pipeline Operations PPW-HSE 43928 Pigging waste
Owowo, O.M Dredging PSE-CDR 24783 Alabi Sola Dredging Ioperation PSW-CDR 42978 Dredge Spoil
Nwosu, S.I AC Maintenance PSE-UAR 21393 HCFC Discharged
Anyanwu, O.C Estate Services PSE-CES 23120 Ezuma W.I Estate Servives PSW-CVL 47025 Food & Garden, Garbage, Glass, Plastic, Paper,
Sewage
Usiayo Samson Estate Servives PSW-CVL 44080
Odeh Ben/ Ohowafas
Eta, E.O Production Well Services PSE-WEL 24465 Queen Production Services Food, Paper
Odeh Ben/ Ohwofasa
Wachijem, I Production Workshop Serv. PSE-WKP 21817 Queen Production Services PSW-UTL 47158/46463 Scrap metals, Effluent water
Ufot Saviour, U Bonny Terminal Operations PTE-CAS 28727 Imhoke Solomon/ Dairo Terminal Operations PTW-HSE 45030 Food, Plastic, Glass, Paper, Scrap metals,
Vincent Sewage, Emty tins/cans, Oil/fuel filters, Oil rags,
Wood, Carton, Fluorescent tubes, Medical/Clinical
waste, Battery, Aerosol cans & Absorbents
Ejike, S.M Drilling Operations DWE-OPS 21488 Anighoro Sunny Drilling Operations DWW-OPS 42979 Food, Plastic, Glass, Paper, Garbage, Garden,
Cable, Sewage, Scrap metals, Empty tins/cans,
Spent lube, Oil/fuel filters, Drums, Construction
debris, Fluorescent tubes, Hole length drilled with
WBM, Hole length drilled with SBM, Oil in SBM
surface losses, WBM mud generated, SBM mud
generated, WBM mud recycled, WBM mud re-
injected, SBM mud recycled, SBM surface losses,
WBM surface losses, WBM cuttings generated,
SBM cuttings generated, WBM cuttings disposed,
SBM cuttings disposed, SBM on cuttings, Cement
water, Drilled cement & Workover completion fluid
produced
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 39 of 87
List of Appendices
_____________________________________________________________________________________________
APPENDIX 3.1
Land Use
Evaluation of the degree to which a project will affect the main land use
potentials is carried out using the land-use component in an EIA study.
Thus, the study’s success is dependant on the quality and reliability of
the data adopted. This land-use component assesses the existing
human activities relative to the human and natural elements of the
proposed 14” x 44 m Sombreiro River Crossing Pipeline Replacement
Project.
• The Landsat (TM) image of the area (1995) and the SPOT-4 image
(1999).
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 40 of 87
List of Appendices
_____________________________________________________________________________________________
of the gas was then read off. Standard Particulate Matter (SPM)
detection was done (UNEP/WHO, 1994) using a portable minimum
Aerosol Monitor Model PDM-3 (Lahman, 1992; Manahan, 1979; SKC,
2000).
Noise measurement was carried out at each sampling station using a digital sound
meter model 840029. To sample, the noise meter reading was allowed to
stabilize before results were recorded in decibel (dB) units.
Four (4) boreholes, (BH1 – BH4) were drilled (Fig 3.1). The boreholes
were drilled using percussion drilling method. The portable cable tool
used comprised of the tripod, the winch, the bailer, the drill line and
drilling accessories. Drilling was done by regularly lifting and dropping
the bailer in the borehole within a protective steel casing. The bailer
did the drilling and also bailed out soil samples for stratigraphic log
description.
After drilling, each borehole was properly cased, screened, and capped
with PVC materials. The borehole was then gravel packed, grouted and
provided with a concrete base. An Indian Mark II hand pump was used
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 42 of 87
List of Appendices
_____________________________________________________________________________________________
to manually flush each borehole until there was clean water before
collecting water samples.
Three water samples were collected per borehole. The samples for
heavy metals were acidified while the others were for physico-chemical
parameters and microbiological analysis.
Groundwater Flow
Hydraulic Conductivity
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 43 of 87
List of Appendices
_____________________________________________________________________________________________
K = Cd102
Vegetation
Ecologically and economically, the plant components of the ecosystem are of prime
importance. The intent of vegetation studies were to:
• Determine the floristic composition and species diversity around the
proposed project area; and
• Document the plant species of economic importance within the
project areas prior to commencement of site preparation;
Sample plots (10 m x 10 m) were established in each of the sampling
locations around the proposed pipeline route. In each plot, plant
species were identified, tree species were enumerated and the
vegetation structure described. The vegetation types in which the plot
was established were noted. Unidentified plant species were collected
for identification in a herbarium.
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 44 of 87
List of Appendices
_____________________________________________________________________________________________
Aquatic Studies
Several physical properties of water are significant in characterizing the
aquatic environment and the forms of life, which inhabit it. Any adverse
change in these physical and chemical properties due to industrial
activities can bring about a concomitant change in the biotic
components of the ecosystem. It is therefore necessary to catalogue
the existing water quality status prior to any environmental alteration.
Sediment
PHYSICO-CHEMISTRY OF SEDIMENT
Two grab samples were taken per station in order to obtain sufficient
quantity of sediment for determination of physico-chemical parameters.
Benthos
Benthos were ascertained at each sampling station after the modified
methods of Olaniyan (1975) and Isebor (1983). These organisms were
immediately identified to species level and the numbers of each
species in an area of approximately 5 m by 5 m were counted. Benthic
fauna were ascertained by examining the grab sediment and by using
pond or tow net along the river or creek bed.
Plankton
A 55 µm mesh-size plankton net was used to collect plankton. The net
was either towed at a very slow speed or its open end was held at the
surface of the fast flowing water against the direction of water flow for 5
minutes. Collected plankton was preserved in 4% formalin. Each
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 45 of 87
List of Appendices
_____________________________________________________________________________________________
Fisheries
Fish and shellfish species and the indigenous fishing methods and gear
used were evaluated at the various sampling stations. During
interviews with the youths and some women in these human
settlements, coloured photographs of fish in the FAO Field Guide to the
Commercial Marine Resources of the Gulf of Guinea by Schneider
(1992) and in the West African Freshwater Fish by Holden and Reed
(1991) were shown to enable them identify the fish species present in
their waters. Fish and shellfish landed in canoes during the visits were
identified. Both dried and fresh fish in the town were observed and
identified. During the journeys to and from sampling locations, the
fishing methods and gears being employed in the various creeks and
rivers were noted. The fishing gears kept in and outside houses in the
settlements visited were also noted.
All other fisheries data such as spawning grounds, breeding habits and
migration pattern and routes were ascertained from literature reviews.
Water Quality
Using a map of the study area, twenty three (23) sampling points for
the aquatic studies were established along the Nun River water body. .
near the river bed). Five (5) samples were collected, 3 with glass-bottle
and 2 with plastic-bottles
Water Physico-Chemistry
Temperature
Dissolved Oxygen
Water samples were incubated for 5 days at 20oC in the dark before
titration for oxygen using the modified Winkler-azide method (APHA,
1980).
Transparency
Depth
Water depth was measured with a depth sounder, Horiba U-7 multi-
polmorgraphic meter.
Heavy Metals
Heavy metals in the water samples were analysed using Perkin Elmer
Model 3110 atomic absorption spectrophotometer.
• The taking and mixing of a series of core samples from each area
sampled.
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 48 of 87
List of Appendices
_____________________________________________________________________________________________
These salts were dissolved in 1.0 liter of distilled water and autoclaved
at 1.0 kg/cm2 for 13 minutes. The oil was mixed in equal volume of
carbon tetrachloride before being used to coat the dry surface of the
minimal salt agar plates. The inoculated plates of filter papers
moistened with the crude oil were inverted and were placed in the lid of
the Petri dishes. These filter papers supplied the hydrocarbon by vapor
phase transfer to the innoculum. The Petri dishes were taped round
with a masking tape so as to increase the vapor pressure within the
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 49 of 87
List of Appendices
_____________________________________________________________________________________________
Water samples were collected from points along the creeks and rivers.
Surface and bottom samples were collected by means of a Hydrobios
water sampler. Borehole water samples were also collected.
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 50 of 87
List of Appendices
_____________________________________________________________________________________________
Soil
Random soil samples were collected at each location by means of a
soil auger at the centre and four radial points at each location. Surface
soils (0-15 cm) and subsurface soils (15-30 cm) were collected into
plastic bags and transported within 48 hours to the laboratory for
analysis. Parameters analysed include organic carbon, total nitrogen,
available phosphorus, extractable micronutrients and soil mechanical
properties.
Quality Control/Assurance
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 51 of 87
List of Appendices
_____________________________________________________________________________________________
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 52 of 87
List of Appendices
_____________________________________________________________________________________________
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 53 of 87
List of Appendices
_____________________________________________________________________________________________
For statistical analysis, errors in field data included those resulting from
instruments and humans. With proper, sustained calibration of the
instrument and the use of standardised observational procedures,
equipment errors were brought to acceptable minimum. However, other
errors arise from the method of sampling. Errors often arise from two-
stage sampling or sub sampling, or even from the fact that the samples
collected are not representative samples of the medium. There are also
spatial variations of the same medium, e.g. soil and water. Thus, it is
necessary to determine the true mean and the estimated variance
among the number of samples taken, so as to establish a reasonable
level of confidence in the results obtained. A good result is obtained
when the variance is within 5% of the mean.
Data coding and manipulation in EIA studies, where reliable data banks
are non-existent, invariably involve acquisition of large amounts of
baseline data. To ensure preservation of the integrity of data collected,
data coding forms for use in the field, were designed in such a way that
field data could be directly entered into computer data sheets.
Samples were properly sealed and labelled. All samples collected were
labelled and the following information provided among others:
• Identification code or sample number
• Date and time of sampling
• Description of sample
• Methods of sampling.
Where samples were sent to another laboratory for examination, a duplicate copy of
this information was sent along with the sample to the laboratory, independent of the
sample. All movements of the samples were included on the samples’ record. Basic
information was recorded together with results of analysis, in a register.
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 54 of 87
List of Appendices
_____________________________________________________________________________________________
SIA QUESTIONNAIRE
1 NEIGHBOURHOOD/COMMUNITY/SETTLEMENT
1.1 Name of interviewer: ---------------------------------------------------------------------
1.2 Date of interview:--------------------------------------------------------------------------
1.3 Neighborhood /comm./settle:------ ----------------------------------------------------
1.4 Local Govt. Area:--------------------------------------------------------------------------
1.5 State:-----------------------------------------------------------------------------------------
3. DEMOGRAPHIC CHARACTERISTICS
3.1 Family size (Husband, wife/wives and children)
3.1.1 1-3
3.1.2 4-6
3.1.3 7-10
3.1.4 11-15
3.1.5 above 15
3.2 Sex: How many are:
3.2.1 Males------------------------------------------------------------------------------
-----
3.2.2 Females:-------------------------------------------------------------------------
------
3.3 How many births in your family in the last 12 months?
3.4.1 0
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 56 of 87
List of Appendices
_____________________________________________________________________________________________
3.4.2 1
3.4.3 2
3.4.4 3
3.4.5 4
4. ECONOMIC ENVIRONMENT
4.1 What is your occupation?
4.1.1 Farming
4.1.2 Fishing
4.1.3 Hunting
4.1.4 Civil servant
4.1.5 Trading
4.1.6 Business
4.1.7 Industrial worker
4.1.8 Other (specify):---------------------------------------------------------------------
-
4.2 If farmer, what crops do you grow?
………………………………………………
4.2.1 Yearly quality of farm produce in the last 5yrs
…………………………
4.3 If fisherman, name some fishes
…………………………………………………..
4.3.1 Yearly quality of fish caught in the last
5yrs…………………………..
4. 4 How long have you been in the occupation?
4.4.1 0-5 years
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 57 of 87
List of Appendices
_____________________________________________________________________________________________
4.8.2 -----------------------------------------------------------------------------------------
--
4.8.3 -----------------------------------------------------------------------------------------
--
4.8.4 -----------------------------------------------------------------------------------------
--
4.8.5 -----------------------------------------------------------------------------------------
--
4.9 How much do you realise from fishing in a week?
4.9.1 N0.0 - N250.00
4.9.2 N250.00 - N500.00
4.9.3 N501.00 - N750.00
4.9.4 N751.00 - N1000.00
4.9.5 N1001.00 - N1,500.00
4.9.6 N1,501.00 - N1,750.00
4.9.7 N1,751.00 - N2,000.00
4.9.8 Above N2,000.00
4.10 How much do you realise from other activities/sources in a week?
4.10.1 N0.00 - N500.00
4.10.2 N501.00 - N1000.00
4.10.3 N1001.00 - N1,500.00
4.10.4 N1,501.00 - N2,000.00
4.10.5 Others-----------------------------------------------------------------------------
-----
4.11 What is your annual income?
4.11.1 N11,000 - N20,000
4.11.2 N21,000 - N30,000
4.11.3 N31,000 - N40,000
4.11.4 N41,000 - N50,000
4.11.5 N51,000 - N60,000
4.11.6 N61,000 - N70,000
4.11.7 N71,000 - N80,000
4.11.8 81,000 - N90,000
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 59 of 87
List of Appendices
_____________________________________________________________________________________________
5.1.3 Traditional
5.1.4 Others (specify)--------------------------------------------------------------------
--
5.2 Which of the following do you have around this neighbourhood
/community: (Please show us the location)
5.2.1 Shrines
5.2.2 Sacred ground/forest
5.2.3 Historical / archaeological site
5.2.4 Religious houses
5.2.5 Others (Special)
5.3 What of these social problems do you have in your neighbourhood?
5.3.1 Youth /juvenile delinquency/unrest
5.3.2 Land dispute
5.3.3 Chieftancy problem
5.3.4 Inter-village problem
5.3.5 Inter-family problem
5.3.6 Unemployment
5.3.7 Others (specify)
5.3.8 None of the above
5.4 What is your source of water supply?
5.4.1 Pipe-borne water
5.4.2 Hand dug well
5.4.3 Streams
5.4.4 Rainfall
5.4.5 Others (please specify)
5.5 What are your sources of energy?
5.5.1 Wood
5.5.2 Kerosene
5.5.3 Gas
5.5.4 Petrol
5.5.5 Coal
5.5.6 Electricity
5.6 What are you fears about this proposed project?
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 62 of 87
List of Appendices
_____________________________________________________________________________________________
6 SOCIAL STATISTICS
(For interviewer only) Note and record the following:
6.1 School statistics
6.1.1 Primary school enrolment data Primary 1 to IV
6.1.2 Secondary school enrolment data JSS 1-3, SSS 1-3
6.1.3 Other educational institutions
6.2 What are the common illnesses in this community?
6.2.1 Malaria
6.2.2 Yellow fever
6.2.3 Dysentery/diarrhoea
6.2.4 Measles/any other contagious disease
6.2.5 Cough
6.2.6 Skin diseases
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 63 of 87
List of Appendices
_____________________________________________________________________________________________
7.2.7 -----------------------------------------------------------------------------------------
--
7.2.8 -----------------------------------------------------------------------------------------
--
7.2.9 -----------------------------------------------------------------------------------------
--
7.2.10 --------------------------------------------------------------------------------------
-----
7.3 In the last 5 years has your annual production of fish been:
7.3.1 Increasing
7.3.2 The same
7.3.3 Decreasing
7.4 If decreasing what do you think is responsible? (Record answer
verbatim).
7.4.1 -----------------------------------------------------------------------------------------
--
7.4.2 -----------------------------------------------------------------------------------------
--
7.4.3 -----------------------------------------------------------------------------------------
--
7.4.3.1.1.1.1 Please list the type of wild animal and birds you normally see or
catch in this area
7.4.4 -----------------------------------------------------------------------------------------
--
7.4.5 -----------------------------------------------------------------------------------------
--
7.4.6 -----------------------------------------------------------------------------------------
--
7.4.7 -----------------------------------------------------------------------------------------
--
7.4.8 -----------------------------------------------------------------------------------------
--
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 65 of 87
List of Appendices
_____________________________________________________________________________________________
7.5 In the last five years have you noticed any changes in the population of
animals and birds in the forest? What are the changes?
7.5.1 Increasing
7.5.2 The same
7.5.3 Decreasing
7.6 If decreasing what so you think is responsible (record answer verbatim)
7.7.1 -------------------------------------------------------------------------------------
-----
7.7 In the last 5 years have you noticed any changes in the types of animal
and birds in the forest?
7.7.1 Yes
7.7.2 No
7.8 If your answer to question 7.8 is yes, what are the changes (record
answer verbatim).
7.8.1 -----------------------------------------------------------------------------------------
--
7.8.2 -----------------------------------------------------------------------------------------
--
7.8.3 -----------------------------------------------------------------------------------------
--
7.8.4 -----------------------------------------------------------------------------------------
--
7.8.5 -----------------------------------------------------------------------------------------
--
7.9 In the last five years have you noticed any changes in the ways trees in
the forest and around the village have been growing? What are the
changes?
7.9.1 -----------------------------------------------------------------------------------------
--
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 66 of 87
List of Appendices
_____________________________________________________________________________________________
ADULTS
(5) How many babies have you had this year (For adult females
only)……………………………………………………………………
……
(8) In your work place, what health problems are you exposed
to:………………..……………………………………………………
…..………………………….…………………………………………
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 67 of 87
List of Appendices
_____________________________________________________________________________________________
…………………………………………………………………………
………………….
(10) How much does it cost you to take care of your family in a
month?…………………………………………………………………
……
(11) Religion…………………………………………………………………
…
(12) Ethnic
group………………………………………………………………
(iii) Occasional
……………………………………………
3. List all the illness episodes you had in the last 12 months.
…………………….……………………………………………………
……
(D) NOISE:
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 69 of 87
List of Appendices
_____________________________________________________________________________________________
Yes No
PHYSICAL EXAMINATION
1. Skin - Diseased
- Normal
- Wasted
- JaundiceYes / No
- Discharge Yes / No
- Cataract Yes / No
4. B/P Check…………………………………………………………………………..
TEST RESULTS:
(1) Urinalysis
TEST RESULT
Bilirubin
Urobilinogen
Ketones
Glucose
Protein
Blood
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 71 of 87
List of Appendices
_____________________________________________________________________________________________
Nitrite
pH
Specific density
Leucocytes
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 72 of 87
List of Appendices
_____________________________________________________________________________________________
1. Name of Town/Village
………………………………………………………
Lifestyle/habits
2. What are the common types of food eaten in the community?
……………….……………………………………………………………
……..
3. Are there any food taboos? Yes / No
4. What is the average life span (expectancy) in your community?
(a) Male ………………………. (b) Female …………………………
5. What are the common health problems in your
community?…………………..……………………………………………
………………………………………………………………………………
……
6. When are these health problems common during the year
S/NO DISEASE RAINY SEASON DRY
SEASON
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 73 of 87
List of Appendices
_____________________________________________________________________________________________
Thank you.
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 75 of 87
List of Appendices
_____________________________________________________________________________________________
SOCIO-DEMOGRAPHIC VARIABLES
1. Name of Town/Village
………………………………………………………
2. Age (last Birthday)
…………………………………………………………..
3. Sex
……………………………………………………………………………
4. Educational status:
(a) Primary School
(b) Secondary School
(c) None
5. Religion
…………………………………………………………………………
6. Ethnic group
…………………………………………………………………
9 IMMUNIZATION STATUS
Have you had any of the following vaccines doses?
DOSES
TYPE OF VACCINE 0 1 2 3
DPT
BCG
Oral Polio Vaccine (OPV)
Measles
Confirm with home-based immunization card if available.
PHYSICAL EXAMINATION
• Appearance of Individual
• Height:
• Weight:
• Mid upper Arm circumstance (for 2-4 years)
- Use shakir strip
• Hair
(a) Colour
(b) Quality - Normal
- Brittle and Pluckable
EYES
• Palor
• Jaundice
• Dischange (Purulent or tearing)
• Ulceration
• Others
………………………………………………………………………...
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 77 of 87
List of Appendices
_____________________________________________________________________________________________
SKIN
• Normal
• Wasted
• Diseased
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 78 of 87
List of Appendices
_____________________________________________________________________________________________
NOTE:
________________________________________________________
________________________________________________________
________________________________________________________
________________________________________________________
________________
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 79 of 87
List of Appendices
_____________________________________________________________________________________________
NOTE:
________________________________________________________
________________________________________________________
________________________________________________________
________________________________________________________
________________
(3) SEWAGE
• Defecate into rivers / stream
• Defecate in the bush
• Bucket
• Pit toilet
• Trench
• VIP
• Others (P/S specify)
NOTE:
____________________________________________________
____________________________________________________
____________________________________________________
____________________________________________________
________________
(5) WATER
• Sources of drinking water
o Tap
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 80 of 87
List of Appendices
_____________________________________________________________________________________________
o Well
o Stream
o Rain
Indicator Unity of Measurement Community Performance
Quantity of water No of litres per person per day
Quantity of water (access) No of users per point (of Tap or Well)
% of households without safe
drinking water supply
(6) HOUSING
(a) Type:
• Mud with thatched roof
• Mud with zinc roof
• Blockhouse with zinc roof.
(b) Number of persons living in a room
(c) Ventilation
• Cross ventilation
• No-cross ventilation
(d) Distance from high-tension cable/wire (Minimum 30m)
(7) TRAFFIC
• Means of transport
• Use of seat belts, helmets
• Status of vehicle (good motoring condition)
• Traffic regulations/sign boards
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 81 of 87
List of Appendices
_____________________________________________________________________________________________
A. Name of Community__________________________________________
• Name of Health
Institution____________________________________
• Outpatient and Inpatient (Delete not applicable)
B. Health professionals
S/No. Personnel Number Qualification Years of
Experience
1 Doctors
2 Nurses
3 Midwifes
4 Lab Scientists
5 Radiographers
6 Anesthetists
7 Record Clerk
8 Pharmacist
9 Others
C. Equipment
• Consulting table and chairs
• Examination couch
• Disposable needless and syringes
• Disposable suture kits
• Methods for sterilization
• Refrigerators
• Medical waste disposal methods
• X-ray facilities
• ECG
• Ultrasound
• Laboratory facilities
• Pharmacy (WHO Essential Drug List Available, List)
• No of beds
• Laundry facilities
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 82 of 87
List of Appendices
_____________________________________________________________________________________________
• Catering facilities
• Operating theatre.
E. Administration
FEATURES YES NO
• Appointment system
• Health records
• Security
• Confidentiality
• Scale of changes
• Cleaning and maintenance routine
Remarks
F. LOGISTICS
• Accessibility of the health Institution (average radial distance of the
centre from the members of the community)
• Communications Telephone/radio
• Hospital Ambulance
G.
• Average daily clinic attendance:
• Common diseases treated:
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 83 of 87
List of Appendices
_____________________________________________________________________________________________
APPENDIX 4.1
Objectives:
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 84 of 87
List of Appendices
_____________________________________________________________________________________________
Introduction:
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 86 of 87
List of Appendices
_____________________________________________________________________________________________
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 87 of 87
List of Appendices
_____________________________________________________________________________________________
___________________________________________________________________________________
Final EIA Report for Okordia-Rumuekpe Pipeline Replacement Project Page 88 of 87
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Site Preparation
Land Take (15x20 m2)/ Land Acquisition (8x10 m2)
Pre-Construction Phase
Construction Phase
1
1
1
1
1
Physico-chemical
52 Light/Solar radiation
2
2
environment
16, 17, 52, 64, 73. Level of Noise and Sounds
3
3
3
3
3
5, 6, 7, 8, 9, 10, 11, 16, 17, 18, 19, 20, 21, 22, 25, 26, 27,
Surface water quality
4
28, 29, 45, 46, 52, 58, 59, 60, 61, 73.
4
4
4
4
4
4
4
17, 45, 52, 58, 59, 60, 73. Groundwater table / Quality
5
5
5
5
5
4, 5, 7, 8, 9, 10, 11, 12, 14, 15, 16, 7, 18, 19, 20, 21, 23, 25,
Soil and sediment quality
6
67
26, 28, 45, 52, 58, 59, 73.
6
6
provision
4, 5, 6, 8, 9, 44, 45, 46, 52, 56, 58, 59, 73. Household water quality
7
89
House
water
7
7
7
7
7
8
10
8
8
8
8
8
9
11
9
9
9
9
9
fisheries
NATURAL ENVIRONMENT
10
9, 11, 16, 17, 25, 26, 46, 52, 58, 59, 73. Availability of breeding grounds and food for fish
10
10
10
10
10
10
10
10
11
25, 26, 27, 46, 52, 58, 59, 73. Access to fishing grounds
11
11
11
11
11
Forestry
12
13, 14, 15, 24, 25, 26, 27, 46, 47. Access to forests
12
12
12
12
13
25, 26, 27, 46, 60, 71. Availability of markets for forestry products
13
Biological Environment
14
farming
12, 13, 15, 24, 25, 26, 27, 46, 73. Access to farm lands
Mixed
14
14
14
14
15
7, 17, 21, 25, 26, 46, 60. Availability of markets for agricultural products
15
16
9, 17, 18, 19,20, 21, 22, 25, 26, 27, 44, 52, 58, 59, 73. Quality of habitat
Ecosys.
16
16
16
16
16
16
16
16
comp.
1, 2, 9, 10, 16, 18, 19, 20, 21, 23, 25, 26, 27, 45, 46, 52, 58,
17
Biodiversity/Genetic resource
17
17
17
17
17
17
17
17
17
17
17
17
59, 60, 73.
4, 5, 7, 8, 9, 10, 11, 16, 17, 19, 20, 21, 22, 24, 25, 26, 27,
Ecosystem function
18
Estuary/Freshwater complex (erosion)
18
18
18
18
18
18
18
18
18
18
18
45, 52, 58, 59.
Protecting Integrity
4, 5, 7, 8, 9, 10, 11, 16, 17, 19, 20, 21, 22, 24, 25, 26, 27,
19
Swamp forest complex
19
19
19
19
19
19
19
19
19
45, 52, 58, 59.
4, 5, 7, 8, 9, 10, 11, 16, 17, 19, 20, 21, 22, 24, 25, 26, 27,
20
Rainforest complex
20
20
20
20
20
20
45, 52, 58, 59.
21
6, 14, 15, 23, 25, 26, 27, 46, 52, 58, 59, 73. Farmland complex
21
21
21
21
21
21
22
53 Sense of Place / Wellbeing
22
22
22
ecosystem
function
Social
23
26, 27, 53, 73. Traditional value of land
23
23
24
22, 32, 41, 70, 71, 73. Access to ancestral and culturally significant sites
24
24
24
24
25
26, 27, 28, 59, 60, 73. Traditional occupations
Supporting economic
25
25
25
25
25
25
25
25
25
25
25
27, 30, 31, 33, 34, 35, 42, 44, 46, 49, 53, 54, 57, 58, 59, 60,
development
26
Level of income & financial flows
26
26
26
26
26
26
26
26
26
26
26
26
26
26
68, 73.
27
30, 31, 33, 34, 35, 42, 44, 46, 48, 58, 59, 69, 73. Cost of living / inflation
27
27
27
27
27
27
27
28
25, 26, 27, 29, 30, 31, 33, 34, 35, 42, 44, 46, 53, 59, 73. Opportunities for contracting and procurement
28
28
28
28
28
28
28
28
28
29
25, 26, 27, 29, 30, 31, 33, 34, 35, 42, 44, 46, 53, 69, 73. Opportunities for local and national employment
29
29
29
29
29
29
29
29
29
31
32
8, 11,12, 14, 15, 24, 25, 26, 27, 32, 33, 35, 36, 58, 59, 61. Access to roads and waterways
32
32
32
33
44, 53, 73. Access to electricity
34
53, 61, 73. Access to communication facilities
Protecting resources
35
53, 73. Access to learning and education facilities
36
1, 4, 5, 6, 7, 8, 16, 18, 19, 29, 21, 22, 23, 25, 26, 44, 45, 47,
37
infrastructure
22, 25, 71. Balance in gender
38
39
39
39
39
39
40
Socio-economic environment
41
22, 53, 69, 71. Functioning of family structure & trad. institutions
42
43
29, 31, 32, 33, 35, 58, 73. Functioning of Government services
44
22, 52, 58, 59. Healthy and clean housing and living conditions
44
45
45
45
45
45
45
45
45
45
SOCIAL ENVIRONMENT
46
22, 52, 58, 59, 73. Access to a nutritious and healthy diet
46
46
46
46
46
46
46
22, 52, 58, 59, 73. Exposure to nuisance (dust, noise etc.)
47
47
47
47
47
48
48
49
49
49
50
22, 51, 52, 58, 59, 61, 73. Exposure to Marine & Traffic Accidents
50
50
50
50
50
51
52
52
52
52
52
52
52
52
52
52
53
53
53
53
54
51, 52, 53, 58, 59, 61. Alcohol and drugs abuse/violence
54
54
54
54
55
55
55
55
55
55
56
57
57
57
58
58
58
59
59
59
59
60
61
61
61
61
62
63
63
63
63
64
64
64
64
Socio-cultural environment
65
65
66
69
69
69
69
integrity
70
70
70
70
71
73
73
73
73
73
73
73
73
73
73
73
NGOs,CBO etc).
sensitivities)