Академический Документы
Профессиональный Документы
Культура Документы
OBJECTIVE
4) Preliminary survey was carried out in order to assess the various alternatives and
finalize the best alignment by collecting all necessary details either by
conventional approach or using modern approach. For pavement design, this
survey includes collecting of topographical features, leveling work, hydrological
data for CD work, soil survey etc.
5) Detailed survey of final location was conducted to establish centre line alignment
for the best route chosen and to collect detailed information for the preparation of
plans and drawings and finalization of the design and construction details for the
highway project. Soil and drainage studies also form apart of detailed survey.
Based on soil analysis and testing, pavement design was finalized.
1. Total station
2. Target
3. Measuring tape
Reduced level was computed from the total station with the help of the target for
all the observed levels of longitudinal sections, cross sections and block leveling.
Details of physical features, computed RL, observed bearing for the centre line etc.
were transferred to drawing as required in a standard format.
DRAWINGS PREPARED
1. INDEX MAP
This was drawn to a scale of 1cm=20m (as is usually specified). The plan shows
centre line alignment with bearings, RL along L/S and C/S, chainages, stream crossing
and all the other physical features surveyed. The details were symbolically represented
on a standard size drawing sheet. North line was represented for reference.
Finalized alignment details after the designs were plotted along with the initial
alignment plan only. Horizontal curves and transition curves designed were presented
with radius, length etc and were numbered.
4. ROAD PLAN
LONGITUDINAL PROFILE
This was drawn to a vertical scale of 1 in 100 and a horizontal scale of 1 in 1000.
The details presented include chainages, ground levels, formation levels, height of
bank, depth of cutting, datum, nature of ground, gradients and vertical curves along the
centre line of alignment. Height of banking and depth of cutting were shown after
finalizing the proposal of formation levels for the alignment. Vertical curves were
designed and incorporated based on formation gradients.
These were drawn to a scale of 1cm=2m on a drawing sheet. The cross sections
were shown on the drawing sheet for computing earth work quantities. Each cross
section contains the details of the ground profile, chainages, formation level and
standard cross sectional elements adopted for a village road like width of pavement
(3.8m), shoulders, formation width (8m), side slopes (1:1 to 1:2) and right of way (20m).
The road level and embankment slopes were indicated.
SURVEY OBJECTIVES
b) To obtain the longitudinal and cross sectional profile of existing ground for the
alignment.
c) To obtain details of drawing works, soil types, terrain and the other essential
features important for highway alignment and design.
GENERAL
Survey work was started with taking the RL from a specified reference B.M. to the
starting point from a local B.M. (as specified).
This was carried out by stretching one chain length (30m) fully in the direction of
survey as guided by gentle and flowing gradients of the terrain. Ruling gradient of 1 in
30 or a limiting gradient of 1 in 20 was provided for plain and rolling terrains. After
ensuring the direction and gradient, bearing (FB) was taken for the centre line thus fixed
by using compass. Frequent zigzags, sharp and reverse turns were avoided for centre
line alignment.
Physical features surrounding the centre line(up to 15m on either side) like buildings,
land(agricultural), ponds, wells, telephone lines etc were surveyed by target. Objects
surveyed were noted down in with chainages and measurement using proper symbols
and represented.
GRADIENT MEASUREMENTS
This was important especially for mountainous and steep terrains. Ghati tracer
was used to fix the ruling gradients for centre line. Ruling gradients were provided for
any terrain when unavoidable; limiting gradients for a short stretch (not exceeding 60
m/km) were allowed. However, exceptional gradients for short stretches were provided
when there was no other possibility (but usually it was avoided). IRC suggests a
maximum gradient of 1 in 15 for plain/rolling terrain and slight gradients not exceeding 1
in 12.5 for steep terrains. Generally, gradients of the terrains indicate the directions of
centre line.
LEVELLING WORK
To start with, fly levels were carried from a permanent B.M. to the starting point of
survey. To check errors in field work, fly levels were carried back from the terminal point
of survey to the permanent B.M. at the end of day’s work. Leveling work for highway
alignment includes:
1.Longitudinal sections L.S. taken at every 15m intervals along the centre line as the
survey proceeds.
2.Cross sections C.S. taken at 30m intervals and the cross levels taken at 3m intervals
extending up to 15m on either side of centre line.
3.Block leveling: At stream or nala, a block of 30x30m was constructed for leveling work
and the levels are observed at 5m intervals on either sides of and along the centre line
with reference to crossing point. Leveling work extends up to 15m on either side of
centre line.
Earth work quantities are computed with the help of details presented from LS &
CS data of final alignment.
This required the details of the area covering the valley position and 10m beyond
on the both sides of the valley. A grid was created of 5mx5m based on site condition.
Block leveling was carried out for the entire area covering the location of the proposed
culvert. Knowing the discharge Q (or assumed) the area was calculated by assuming
the velocity of flow. Non-pressure RCC pipes were chosen to take the flow. Abutment
and site wall (wing walls) were designed and necessary drawings were prepared
incorporating all the details.
8. Design speeds for village road=40 (Ruling) & 35(Minimum) for rolling terrain.
9. Minimum radii for village = 60m (ruling) & 45m (abs min).
Substituting,
V = 20kmph
Super elevation was calculated by taking the speed as 75% of the design
speed. e = [(0.75*V)^2/(127*R)]
e = 0.124
We = n x Le x e/(2 x R)+0.1 x V/
V=design speed=20kmph
Le=wheel of the
vehicle=6.1m
We=0.53m
C = (80/(75+V)) =0.842
Ls = 14.27m
Ls = (W+We) x e x 150/2
We=extra widening
e= 0.07 Ls = 22.73m
Ls = V^2/R
= 20^2/10
Ls =40m
Lc = (3.14 x R x ∆/180)
Lc = 20.93m
S = (Ls)^2/(24 x R)
= 22.372 / 24 x 14.32
S = 1.45m
Ts = (R+S) x tan(∆/2)+Ls/2
8. Tangent length
T = R x tan(∆/2)
= 10 x tan(120/2)
T = 17.32m
Curv ∆ Radi E We Ls Lc S Ts T V
e us
HC1 124 13.85 0.07 0.5 22.7 29.95 1.55 40.32 18.80 20
5 3
HC2 120 14.32 0.07 0.5 22.3 20.93 1.45 31.01 17.32 20
3 7
HC3 25 68.74 0.07 0.5 36.5 29.99 0.81 33.7 15.24 43
2 7
HC4 10 171.8 0.07 0.5 74.7 29.99 1.35 52.51 15.04 69
6 3 2
= - ((1/30) + (1/30))
N = 0.067 = 6.7%
= 30.34m
L = 0.38 x (N x V3)^0.5
L = 24.88m
L = 44.12m~ 45m
Q = C x M2/3
Where, C = 12
Considering 0.7km length of highway 4.5m width from the centre of highway we get
road side drainage area = 0.7 x 4.5/1000
M = 3.15 x 10-3km2
Q = 12 x
0.003152/3
Q = 0.25m3/sec
Therefore, A = 0.25/1.5
A = 0.17m2
Therefore,
. 17 = (0.5 +1.5d) x d
1.CUTTING
AVERAGE
AREA OF AREA OF VOL OF
SL NO CHAINAGE DISTANCE CUTTING IN M2 CUTTING IN CUTTING
IN M3
M2
1 0 0 1.48
2 30 30 0.67 1.075 32.25
3 60 30 0.08 0.375 11.25
4 90 30 0 0.04 1.2
5 120 30 0 0 0
6 150 30 0 0 0
7 180 30 0 0 0
8 210 30 0 0 0
9 240 30 0 0 0
10 270 30 1.01 0.505 15.15
11 300 30 0 0.505 15.15
12 330 30 0 0 0
13 360 30 6.02 3.01 90.3
14 390 30 0.015 3.0175 90.525
15 420 30 7.89 3.9525 118.575
16 450 30 19.59 13.74 412.2
17 459.42 9.42 28.53 24.06 226.645
2
Total volume of cutting 1013.24
5
Volume (m3 )
Total volume of cutting 1013.245
Total volume of filling 1393.110
Remaining filling 379.860